radioactive waste management system and effluent control ... · steam generator feed pump turbine...

54
VEGP-FSAR-1 boron, in the form of burnable poison rods, is employed in the first core to establish the desired initial reactivity. 'The fuel rods consist of slightly enriched uranium dioxide cylindrical pellets contained in slightly cold-worked, Zircaloy-4 tubing which is plugged and seal welded at the ends to encapsulate the fuel. All fuel rods are pressurized with helium during fabrication to reduce stresses and strains and to increase fatigue life. Additional reactivity control is provided by control rod assemblies which consist of a group of individual absorber rods fastened at the top end to a common hub or spider assembly. The control rod drive mechanisms for the control rod assemblies are of the magnetic latch type. The latches are controlled by three magnetic coils. They are so designed that upon a loss of power to the coils, the control rod assembly is released and falls by gravity to shut down the reactor. The components of the reactor internals are divided into three structures consisting of the lower core support structure (including the entire core barrel and neutron shield pad assembly), the upper core support structure, and the incore instrumentation support structure. The reactor internals'support the core, maintain fuel alignment, limit fuel assembly movement, maintain alignment between fuel assemblies and control rod drive mechanisms, direct coolant flow past the fuel elements and to the pressure vessel head, provide gamma and neutron shielding, and (provide guides for the incore instrumentation. Instrumentation is provided in and out of the core to monitor the nuclear, thermal-hydraulic, and mechanical performance of the reactor and to provide inputs to automatic control functions. The reactor core design together with corrective actions of the reactor control, protection, and emergency core cooling systems ensure that attained peak local power densities do not: * Lead to fuel damage during normal operation or faults of moderate frequency. " Cause failure of more than a small fraction of fuel rods due to infrequent fault. * 'Prevent acceptable heat transfer during transients associated with limiting faults. 1.2.3.2 Reactor Coolant System The RCS is arranged as four closed loops connected in parallel to the reactor vessel. Each loop consists of one 29-in. inside diameter (ID) outlet pipe (hot leg), one steam generator, and one 27.5-in. ID inlet pipe (cold leg), with one reactor coolant pump in each cold leg. The piping between the steam generator and the reactor coolant pump suction has an inside diameter of 31 in. to reduce pressure drop and improve flow conditions to the pump suction. An electrically heated pressurizer is connected to one of the loops. A safety injection line is connected to each of the four cold legs;- The RCS operates at a nominal pressure of 2235 psig. The reactor coolant enters the reactor vessel through four inlet nozzles, turns and flows downward between the reactor vessel shell and the core support barrel, and enters the lower plenum through the flow skirt. The coolant then turns and flows upward through the core barrel lower supportstructure, through the core support plate flow holes, and continues parallel to the axis of the fuel assemblies to remove the heat generated within the fuel. The coolant continues its upward flow through the upper guide structure, then turns and leaves the reactor vessel through the four outlet nozzles and the hot leg pipes, which lead to the steam generators..Thb coolant flows through the tube side of the four steam generators, where heat is transferred to the secondary system! Reactor coolant pumps return the reactor coolant to the reactor vessel. 1.2-9 REV 13 4/06

Upload: others

Post on 23-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

boron, in the form of burnable poison rods, is employed in the first core to establish the desiredinitial reactivity.

'The fuel rods consist of slightly enriched uranium dioxide cylindrical pellets contained in slightlycold-worked, Zircaloy-4 tubing which is plugged and seal welded at the ends to encapsulate thefuel. All fuel rods are pressurized with helium during fabrication to reduce stresses and strainsand to increase fatigue life.

Additional reactivity control is provided by control rod assemblies which consist of a group ofindividual absorber rods fastened at the top end to a common hub or spider assembly. Thecontrol rod drive mechanisms for the control rod assemblies are of the magnetic latch type.The latches are controlled by three magnetic coils. They are so designed that upon a loss ofpower to the coils, the control rod assembly is released and falls by gravity to shut down thereactor.

The components of the reactor internals are divided into three structures consisting of the lowercore support structure (including the entire core barrel and neutron shield pad assembly), theupper core support structure, and the incore instrumentation support structure. The reactorinternals'support the core, maintain fuel alignment, limit fuel assembly movement, maintainalignment between fuel assemblies and control rod drive mechanisms, direct coolant flow pastthe fuel elements and to the pressure vessel head, provide gamma and neutron shielding, and

(provide guides for the incore instrumentation.

Instrumentation is provided in and out of the core to monitor the nuclear, thermal-hydraulic, andmechanical performance of the reactor and to provide inputs to automatic control functions.

The reactor core design together with corrective actions of the reactor control, protection, andemergency core cooling systems ensure that attained peak local power densities do not:

* Lead to fuel damage during normal operation or faults of moderate frequency.

" Cause failure of more than a small fraction of fuel rods due to infrequent fault.

* 'Prevent acceptable heat transfer during transients associated with limiting faults.

1.2.3.2 Reactor Coolant System

The RCS is arranged as four closed loops connected in parallel to the reactor vessel. Eachloop consists of one 29-in. inside diameter (ID) outlet pipe (hot leg), one steam generator, andone 27.5-in. ID inlet pipe (cold leg), with one reactor coolant pump in each cold leg. The pipingbetween the steam generator and the reactor coolant pump suction has an inside diameter of31 in. to reduce pressure drop and improve flow conditions to the pump suction. An electricallyheated pressurizer is connected to one of the loops. A safety injection line is connected to eachof the four cold legs;- The RCS operates at a nominal pressure of 2235 psig.

The reactor coolant enters the reactor vessel through four inlet nozzles, turns and flowsdownward between the reactor vessel shell and the core support barrel, and enters the lowerplenum through the flow skirt. The coolant then turns and flows upward through the core barrellower supportstructure, through the core support plate flow holes, and continues parallel to theaxis of the fuel assemblies to remove the heat generated within the fuel. The coolant continuesits upward flow through the upper guide structure, then turns and leaves the reactor vesselthrough the four outlet nozzles and the hot leg pipes, which lead to the steam generators..Thbcoolant flows through the tube side of the four steam generators, where heat is transferred tothe secondary system! Reactor coolant pumps return the reactor coolant to the reactor vessel.

1.2-9 REV 13 4/06

Page 2: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

The pressure in the RCS is controlled by regulating the temperature of the coolant in'thepressurizer, where steam and water are held in thermal equilibrium. Steam is formed by thepressurizer heaters or condensed by the pressurizer spray to reduce pressure variationscaused by expansion and contraction of the reactor coolant due to system temperaturechanges. The pressurizer limits pressure variations during plant load transients and keepssystem pressure within design limits during abnormal conditions.

1.2.4 STEAM AND POWER CONVERSION SYSTEM

The turbine-generator is furnished by the General Electric Company. The gross generatoroutput at turbine guaranteed rating is 1,156,622 kW output at 1800 rpm, using a tandemcompound 6-stage flow machine with 38-in. last-stage buckets. The throttle steam conditionsare 940 psia, 1191.4 Btu/Ib, with one stage of reheat. The exhaust pressure is 3.5-in. Hg abs;the makeup is 0.0 percent. Extraction steam is used for normal feedwater heating and forsteam generator feed pump turbine operation.

General features of the generator include a 1,350,000-kVA output at 1800 rpm, four polesdirect connected, 3-phase, 60-Hz, 25,000-V conductor cooled synchronous generator rated at0.90 power factor, 0.5 short circuit ratio at maximum hydrogen pressure of 75 psig.

The auxiliary feedwater system contains two motor-driven pumps and one turbine-driven pump.This system is designed to provide emergency heat removal capacity.

1.2.5 CONTAINMENT

The containment completely encloses the reactor and reactor coolant system. It is a vertical,right-cylindrical, prestressed, post-tensioned concrete structure with a dome and flat base witha depressed center for a reactor cavity and instrumentation tunnel. The interior is lined withcarbon steel plate for leaktightness. Approximate dimensions of the containment are asfollows: inside diameter, 140 ft; inside height, 228 ft; vertical wall thickness, 3 ft 9 in.; domethickness, 3 ft 9 in.; foundation thickness, 10 ft 6 in., with a minimum thickness of the concretebasemat of 8 ft 3 in.; and the minimum thickness of the concrete instrumentation cavity of 8 ft.

Inside the containment, the reactor and other nuclear steam supply system components areshielded with concrete. A vent stack is attached to the outside of the containment and extendsa short distance above the top of the containment dome. Access to portions of the containmentduring power operation is permissible.

The containment, along with the safety features, is designed to withstand the internal pressureand coincident temperature resulting from the energy release of the high energy line breakaccident. The containment design internal pressure is based upon the design basis loss-of-coolant accident, and the internal temperature is based upon design basis main steam linebreak.

1.2.6 SAFETY FEATURES

The safety features limit the potential radiation exposure to the public and to plant personnelfollowing an accidental release of radioactive fission products from the reactor system,particularly as the result of a loss-of-coolant accident (LOCA). These safety features functionto localize, control, mitigate, and terminate such accidents, ensuring that 10 CFR 100guidelines are not exceeded. The safety features include the following systems:

1.2-10 REV 13 4/06

Page 3: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

* Emergency core cooling system (ECCS).

" Containment spray system.

* Containment cooling system.

" Penetration room filtration systems.

* Hydrogen recombiners.

1.2.6.1 Emergency Core Cooling System

The ECCS injects borated water into the reactor coolant system following a LOCA. Thisprovides cooling to limit core damage, metal-water reactions, and fission product release andensures adequate shutdown margin regardless of temperature. The ECCS also providescontinuous long term, post-accident cooling of the core by recirculating borated water betweenthe containment sump and the reactor core.

1.2.6.2 Containment Spray System

The containment spray system is composed of two redundant, full-capacity trains which aredesigned to reduce the post-accident containment building iodine concentrations so that offsitedoses are less than 10 CFR 100 guidelines.

The containment spray system supplies borated water during injection and borated water mixedwith trisodium phosphate during recirculation to the containment atmosphere. The spraysystem in combination with four of the eight containment air coolers (operating at reducedspeed) is sized to provide adequate cooling with either or both of the two containment spraypumps in service. These pumps take suction from the refueling water storage tank. When theRWST empty alarm is received, suction of'the containment spray pumps is aligned to pumpwater from the containment sump directly into the containment during the recirculation mode ofoperation.

1.2.6.3 Containment Cooling System

The containment cooling system consists of two independent, redundant, full-capacity trainscontaining the equipment necessary for safe shutdown of the plant following an accident. Thesystem is designed to reduce the post-accident containment pressure to 50 percent or less ofthe peak containment pressure within 24 h or less following the accident.

1.2.6.4 Penetration Room Filtration Systems

The penetration room filtration systems for each unit collect and process potential airbornecontamination due to leakage from process components during the recirculation mode of ECCSoperation. This filtration limits the environmental activity levels following an accident.

1.2-11 REV 13 4/06

Page 4: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

1.2.6.5 Hydrogen Recombiners

Fully redundant electrical hydrogen recombiners inside the containment reduce the percentageof hydrogen in the post- accident containment atmosphere to below combustible levels.

1.2.7 UNIT CONTROL

The reactor is controlled by control rod movement and regulation of the boric acid concentrationin the reactor coolant. During steady-state operation, the reactor control system maintains aprogrammed average reactor coolant temperature that rises in proportion to the load.

The solid state protection logic system automatically initiates appropriate action whenever theparameters monitored by this system reach preestablished setpoints. This system acts to tripthe reactor, actuate emergency core cooling, close containment isolation valves, and .initiate theoperation of other safety feature systems.

1.2.8 PLANT ELECTRICAL POWER

The two main turbine-generators are each rated at 1350 MVA, 0.90 power factor, 25,000 V;they are 3-phase, 60-Hz, 1800 rpm hydrogen- and water-cooled units. The power from theseunits is delivered to the Georgia Power Company 230-kV and 500-kV transmission lines.Termination points of these lines are described in section 8.2.

Each unit has three separate sources of power for its auxiliaries. The three sources of powerand associated electrical equipment ensure the functioning of both units without undue risk tothe health and safety of the public and provide reliable power sources for startup, normaloperation, safe shutdown, and emergency situations.

The three sources for each unit are:

A. The main turbine-generator supplies normal auxiliary loads during plant operation.

B. The two reserve auxiliary transformers supply the two safety feature buses fromthe 230-kv switchyard. The standby auxiliary transformer (SAT) may supplyeither of the two safety feature buses from Plant Wilson.

C. The two standby diesel generators provide emergency power to two safetyfeature buses. Upon loss of all offsite power, either diesel generator and itsassociated bus has the capacity to power the equipment required to safelyshutdown the reactor and mitigate the consequences of the design basesaccidents.

Plant batteries ensure a constant supply of power to vital instruments and controls.

Plant power is distributed through buses at 13,800 V, 4160 V, and 480 V, and 120 V ac. Thesafety-related dc loads in each unit are powered from four 125-V dc buses.

1.2.9 PLANT INSTRUMENTATION AND CONTROL SYSTEM

To avoid undue risk to the health and safety of the public, instrumentation and controls monitorand maintain neutron flux, primary coolant pressure, temperature, and control rod positionswithin prescribed operating ranges.

1.2-12 REV 13 4/06

Page 5: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

The regulating, process, and containment instrumentation measure temperatures, pressures,flows, and levels in the reactor coolant system, steam systems, containment, and auxiliarysystems. Process variables required on a continuous basis for startup, operation, andshutdown of the unit are indicated, recorded, and controlled from the control room. The qualityand types of process instrumentation provided ensure safe and orderly operation of all systemsand processes over the full operating range of the plant.

Startup and shutdown of the reactor and adjustment of reactor power in response to turbineload demand are provided by the reactor control system. The reactor is controlled by controlrod motion for startup, shutdown, and load-follow transients; it is also controlled by a solubleneutron absorber (boron, injected as boric acid into the primary coolant) which is insertedduring cold shutdown and refueling, partially removed during reactor startup, and adjusted inconcentration during core lifetime to compensate for such effects as fuel consumption andaccumulation of fission products which reduce the levels of desirable nuclear reactions. Thecdntrol system permits each unit to accept step load increases or decreases of 10 percent andramp load increases or decreases of 5 percent/min over the load range from 15 percent to, butnot exceeding, 100-percent power under normal operating conditions, subject to xenonlimitations.

Under normal conditions both the reactor and the turbine-generator are controlled from thecontrol room by Nuclear Regulatory Commission-licensed personnel.

1.2.10 AUXILIARY SYSTEMS

Nuclear auxiliary systems perform the following functions:

• Supply reactor coolant system (RCS) water requirements.

" Purify reactor coolant water.

" Introduce chemicals for corrosion inhibition.

" Introduce and remove chemicals for reactivity control.

* Cool system components.

" Remove residual heat during a portion of the reactor cooling period and when thereactor is shut down.

* Cool the spent fuel pool water.

* Permit sampling of reactor coolant water.

* Provide for safety injection.

" Vent and drain the RCS and the auxiliary systems.

* Provide containment ventilation and cooling.

" Process liquid and gaseous wastes and dispose of solid wastes.

These functions are performed by the systems discussed below.

1.2-13 REV 13 4/06

Page 6: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

1.2.10.1 Chemical and Volume Control System (CVCS)

The CVCS performs the following functions:

* Reactivity control.

" Regulation of reactor coolant inventory.

" Reactor coolant purification.

* Chemical additions for corrosion control.

" Seal water injection to reactor coolant pump seals.

The purity level in the RCS is controlled by continuous purification of a bypass stream of reactorcoolant. Water removed from the RCS is cooled in the regenerative heat exchanger. Fromthere, the coolant flows to a letdown heat exchanger and through a demineralizer wherecorrosion and fission products are removed. The coolant then passes through a filter and issprayed into the volume control tank.

The CVCS automatically adjusts the amount of reactor coolant to compensate for changes inspecific volume due to coolant temperature changes and reactor coolant pump shaft sealleakage in order to maintain a constant level in the pressurizer.

1.2.10.2 Residual Heat Removal (RHR) System

The RHR system is used to reduce the temperature of the reactor coolant at a controlled ratefrom 3500F to 140°F and to maintain the proper reactor coolant temperature during refueling.

The RHR pumps are used to circulate the reactor coolant through two RHR heat exchangers,returning it to the RCS through the low-pressure injection header.

1.2.10.3 Auxiliary Feedwater (AFW) System

The AFW system provides feedwater to the steam generators for removal of reactor core decayheat following a loss of main feedwater. The AFW system is also used to cool down the reactorto the temperature and pressure conditions required for initiation of the RHR system.

1.2.10.4 Component Cooling Water (CCW) System

The CCW system consists of two independent trains of pumps and heat exchangers to removeheat from the various auxiliary systems handling the reactor coolant. Corrosion-inhibiteddemineralized water is circulated by the system through the spent fuel pool heat exchangers,the residual heat exchangers, and the RHR pump seal coolers.

The CCW system provides an intermediate barrier between the RCS and the nuclear servicecooling water (NSCW) system described in paragraph 1.2.10.8.

1.2-14 REV 13 4/06

Page 7: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

1.2.10.5 Auxiliary Component Cooling Water (ACCW) System

The ACCW system consists of pumps and heat exchangers to remove heat from variousauxiliary systems handling reactor coolant. Corrosion-inhibited demineralized water iscirculated by the system through the letdown heat exchanger, the reactor coolant pump coolers,sample heat exchangers, waste gas compressors, and other nonsafety-related heat loads.

The ACCW system provides an intermediate barrier between the RCS and the NSCW systemdescribed in paragraph 1.2.10.8.

1.2.10.6 Fuel Handling and Storage System

The reactor is refueled with equipment designed to handle spent fuel underwater from the timeit leaves the reactor vessel until it is placed in a cask for shipment offsite.' Transfer of spent fuelunderwater enables the use of an optically transparent radiation shield and provides a reliablesource of coolant for removal of residual heat.

The fuel handling system also provides for the safe handling of rod cluster control assembliesunder all foreseeable conditions and for the required assembly, disassembly, and storage ofreactor internals. This system includes a manipulator crane located inside the containmentabove the refueling pool, fuel transfer carriage, upending devices, fuel transfer tube, spent fuelcask bridge crane in the spent fuel pool area, and various devices used for handling the reactorvessel head and internals.

The new fuel storage area is shared by both units and is sized to accommodate storage of 162fuel assemblies and control rods. The new fuel assemblies are stored in racks in parallel rowshaving a center-to-center distance of approximately 21 in. to preclude criticality.

Together, the two stainless steel-lined, reinforced concrete spent fuel pools provide storagecapacity for 3574 fuel assemblies. Spent fuel assemblies are stored in vertical racks spaced topreclude criticality with no credit taken for the borated pool water. See drawings 1X6AN1OB-66and AX6AN1OA-6 for the layout of the pools. The layout of the pools is also shown in figures9.1.2-3 and 9.1.2-5.

Purification and redundant cooling equipment is provided for each spent fuel pool. Thisequipment may also be used for cleanup of refueling water after each fuel change in thereactor.

1.2.10.7 Sampling Systems

Three sampling systems are provided: nuclear sampling system - liquid, nuclear samplingsystem - gaseous, and turbine plant sampling system. These systems are used for determiningboth chemical and radiochemical conditions of the various fluids used in the plant.

1.2.10.8 Cooling.Water Systems

The turbine-generator condenser is cooled by the circulating water system, which rejects heatto a cooling tower.

The cooling water requirements for various nuclear components, CCW system, ACCW system,and diesel generators are supplied by pumps taking suction from the NSCW tower basins.Water makeup to the storage basins is supplied by the normal plant makeup wells or the

1.2-15 REV 13 4/06

Page 8: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

Savannah River. In addition, a standby nuclear service makeup well can supply makeup flow tothe NSCW system as a backup source of water.

1.2.10.9 Plant Ventilation Systems

Separate ventilation systems are provided for the containment, penetration rooms, auxiliarybuilding, fuel handling building, control room, control building, turbine building, and emergencydiesel generator building. In addition, a purge system, mini- purge system, post-loss-of-coolantaccident purge system, and containment preaccess filtration system are provided for thecontainment.

The auxiliary building, fuel handling building, and control building penetration rooms areventilated by the penetration room filtration systems, which include filters for control of anyleakage from process components during the recirculation mode of emergency core coolingsystem operation.

1.2.10.10 Plant Fire Protection System

The major fire protection system contains both diesel- and electric-driven fire pumps whichsupply the various hydrants, hose stations, sprinklers, and deluge systems. Hydrants and hosestations are manually operated; the sprinkler and deluge systems are a combination ofautomatic and manually actuated systems. Supplementary to these facilities, chemical fire-extinguishing equipment is provided to accommodate special requirements for various classesof hazards. Noncombustible and fire-resistant materials are selected for use wherever practicalthroughout the facility, particularly in critical portions of the plant such as the containment,control room, and components of the safety features system.

1.2.10.11 Compressed Air Systems

One reciprocating and two rotary air compressors, with separate aftercoolers and separators,discharge compressed air to two separate headers. These headers provide a continuoussupply of filtered, dried, oil-free, compressed air for pneumatic instrument operation and controlof pneumatic actuations. The system also provides service air at outlets throughout the plant.An additional reciprocating compressor train can be aligned to either unit.

1.2.10.12 Radioactive Waste Disposal System

The waste disposal system provides controlled handling and disposal of liquid, gaseous, andsolid wastes. The waste processing system provides all equipment necessary for controlledtreatment and preparation for retention or disposal of all liquid, gaseous, and solid wastesproduced as a result of reactor operation.

The liquid waste processing system collects, processes, and recycles reactor grade water;removes or concentrates radioactive constituents; and processes them until suitable for releaseor shipment offsite. Liquid wastes are sampled and activity levels verified and recorded prior torelease. Processed liquid effluent from the RCS will have been subjected to the CVCSpurification ion exchanger and the components of the waste processing system and will bewithin the limits established by the Offsite Dose Calculation Manual.

1.2-16 REV 13 4/06

Page 9: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

The gaseous waste processing system functions to remove fission product gases from thereactor coolant and to contain these gases during normal plant operation. Waste gases arecollected in the vent header. These gases are withdrawn from the vent header by one of twocompressors and discharged to a waste gas decay tank. The tank contents will be released tothe environment in accordance with the program requirements of Technical Specifications, andreleases will be within the limits set forth in the Offsite Dose Calculation Manual. Seven wastegas decay tanks and two shared waste gas decay shutdown tanks are provided. Gaseouswastes are discharged through an absolute particle filter to the vent stack.

Solid wastes are stored in suitable containers for eventual disposal.

1.2.11 SHARED FACILITIES AND EQUIPMENT

An integrated, twin-unit station enables certain components, systems, and facilities to bedesigned and arranged so that they are common to both units without impairing the safety orreliability of either unit.

Separate and similar systems and equipment are provided for each unit except as noted inparagraphs 1.2.2.1 and 1.2.2.2.

1.2.12 PRINCIPAL DESIGN CRITERIA

The VEGP is designed to comply with the intent of the General Design Criteria for NuclearPower Plants contained in Appendix A to 10 CFR 50. The details of compliance to the generaldesign criteria are provided in section 3.1.

The principal design criteria are presented in two ways--power generation function or safetyfunction--and grouped according to system. Although the distinctions between powergeneration or safety functions are not always clear and occasionally overlap, the functionalclassification facilitates safety analyses, while the grouping by system facilitates theunderstanding of both the system function and design.

1.2.12.1 General Design Criteria

1.2.12.1.1 Power Generation Design Criteria

A. The plant is designed to produce steam for direct use in a turbine-generator unit.

B. Heat removal systems are provided with sufficient capacity and operationaladequacy to remove heat generated in the reactor core for the full range ofnormal operational conditions and abnormal operational transients.

C. Backup heat removal systems are provided to remove decay heat generated inthe core under circumstances wherein the normally operational heat removalsystems become inoperative. The capacity of such systems is adequate toprevent fuel cladding damage.

D. The fuel cladding, in conjunction with other plant systems, is designed to retainintegrity through the range of normal operational conditions and abnormaloperational transients.

1.2-17 REV 13 4/06

Page 10: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

E. The fuel cladding accommodates, without loss of integrity, the pressuresgenerated by fission gases released from fuel material throughout the design lifeof the fuel.

F. Control equipment is provided to allow the reactor to respond automatically tominor load changes, major load changes, and abnormal operational transients.

G. Reactor power level is manually controllable.

H. Control of the reactor is possible from a single location.

I. Reactor controls and related indicators and alarms are arranged to allow theoperator to rapidly assess the condition of the reactor system and locate systemmalfunctions.

J. Interlocks, or other automatic equipment, are provided as backup to proceduralcontrols to avoid conditions requiring the functioning of nuclear safety systems orengineered safety features (ESF).

1.2.12.1.2 Safety Design Criteria

A. The plant design conforms to applicable regulations as discussed in sections 1.9and 3.1.

B. The plant is designed, fabricated, erected, and operated in such a way that therelease of radioactive materials to the environment does not exceed the limits andguideline values of applicable government regulations pertaining to the release ofradioactive materials for normal operations and for abnormal transients andaccidents.

C. The reactor core is designed so its nuclear characteristics do not contribute to adivergent power transient.

D. The reactor is designed so that there is no tendency for divergent oscillation ofany operating characteristic, considering the interaction of the reactor with otherappropriate plant systems.

E. Gaseous, liquid, and solid waste disposal facilities are designed so that thedischarge of radioactive effluents and offsite shipment of radioactive materialscan be made in accordance with applicable regulations.

F. The design provides means by which plant operators are alerted when limits onthe release of radioactive material are approached.

G. Sufficient indications are provided to allow determination that the reactor isoperating within the envelope of conditions considered by plant safety analysis.

H. Radiation shielding is provided and access control patterns are established toallow a properly trained operating staff to control radiation doses within the limitsof applicable regulations in any mode of normal plant operations.

1. Those portions of the nuclear steam supply system (NSSS) that form part of thereactor coolant pressure boundary (RCPB) are designed to retain integrity as aradioactive material containing barrier following abnormal operational transientsand accidents.

1.2-18 REV 13 4/06

Page 11: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

J. Nuclear safety systems and ESF function to ensure that no damage to the RCPBresults from internal pressures caused by abnormal operational transients andaccidents.

K. Where positive, precise action is immediately required in response to abnormaloperational transients and accidents, such action is automatic and requires nodecision or manipulation of controls by plant operations personnel.

L. Essential safety actions are provided by equipment of sufficient redundance andindependence so that no single failure of active components can prevent therequired actions. For systems or components to which Institute of Electrical andElectronics Engineers (IEEE) 279-1971, Criteria for Protection Systems forNuclear Power Generating Stations, applies, single failures of both active andpassive electrical components are considered in recognition of the higheranticipated failure rates of passive electrical components relative to passivemechanical components.

M. Provisions are made for control of active components of nuclear safety systemsand ESF from the control room.

N. Nuclear safety systems and ESF are designed to permit demonstration of theirfunctional performance requirements.

0. The design of nuclear safety systems and ESF includes allowances for naturalenvironmental disturbances such as earthquakes, floods, and storms at thestation site.

P. Standby electrical power sources have sufficient capacity to power all nuclearsafety systems and ESF requiring electrical power.

Q. Standby electrical power sources are provided to allow prompt reactor shutdownand removal of decay heat under circumstances where normal auxiliary power isnot available.

R. A containment is provided which completely encloses the reactor system.

S. The containment is designed to allow periodic integrity and leaktightness testing.

T. The containment, in conjunction with other ESF, limits to less than the prescribedacceptable limits-the radiological effects of accidents resulting in the release ofradioactive material to the containment volume.

U. Provisions are made for removing energy from the containment as necessary tomaintain the integrity of the containment system following accidents that releaseenergy to the containment.

V. Piping that penetrates the containment and could serve as a path for theuncontrolled release of radioactive material to the environs is automaticallyisolated whenever such uncontrolled radioactive material release is threatened.Such isolation is effected in time to limit radiological effects to less than thespecified acceptable limits.

W. Emergency core cooling systems (ECCS) are provided to limit fuel claddingtemperature to less than the limits established by 10 CFR 50.46 in the event of aloss-of-coolant accident (LOCA).

X. The ECCS provides for continuity of core cooling over the complete range ofpostulated break sizes in RCPB.

1.2-19 REV 13 4/06

Page 12: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

Y. Actuation of the ECCS occurs automatically when required, regardless of theavailability of offsite power supplies and the normal generating system of thestation.

Z. The control room is shielded against radiation so that continued occupancy underaccident conditions is possible.

AA. In the event that the control room becomes uninhabitable, it is possible to bringthe reactor from power range operation to cold shutdown conditions by utilizingthe shutdown panels and other equipment available outside the control room.

BB. Backup reactor shutdown capability is provided independent of normal reactivitycontrol provisions. This backup system has the capability to shut down thereactor from any normal operating condition and subsequently to maintain theshutdown condition.

CC. The fuel handling and storage facility is designed to prevent inadvertent criticalityand to maintain shielding and cooling of spent fuel.

1.2.12.2 System Criteria

The principal design criteria for particular systems are discussed below.

1.2.12.2.1 Nuclear System Criteria

A. The fuel cladding is designed to retain integrity as a radioactive material barrierthroughout the design power range. The fuel cladding is designed toaccommodate, without loss of integrity, the pressures generated by the fissiongases released from the fuel material throughout the design life of the fuel.

B. The fuel cladding, in conjunction with other plant systems, is designed to retainintegrity throughout any abnormal operational transient.

C. Those portions of the nuclear system that form part of the RCPB are designed toretain integrity as a radioactive material barrier during normal operation andfollowing abnormal operational transients and accidents.

D. Heat removal systems are provided in sufficient capacity and operationaladequacy to remove heat generated in the reactor core for the full range ofnormal operational transients. The capacity of these systems is adequate toprevent fuel cladding damage.

E. Heat removal systems are provided to remove decay heat generated in the coreunder circumstances wherein the normal operational heat removal systemsbecome inoperative. The capacity of these systems is adequate to prevent fuelcladding damage. The reactor is capable of being shut down automatically insufficient time to permit decay heat removal systems to become effectivefollowing loss of normal heat removal systems.

F. The reactor core and reactivity control system is designed so that control rodaction is capable of bringing the core to subcriticality and maintaining it subcriticaleven with the rod of highest reactivity worth fully withdrawn and unavailable forinsertion into the core.

1.2-20 REV 13 4/06

Page 13: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1

G. The reactor core is designed so that its nuclear characteristics do not contributeto a divergent power transient.

H. The nuclear system is designed so there is no tendency for divergent oscillationof any operating characteristic, considering the interaction of the nuclear systemwith other appropriate plant systems.

1.2.12.2.2 Power Conversion Systems Criteria

Components of the power conversion systems are designed to produce electrical power fromthe steam coming from the steam generator, condense the steam into water, and return thewater to the steam generator as heated feedwater.

1.2.12.2.3 Electrical Power System Criteria

Sufficient normal and standby auxiliary sources of electrical power are provided to facilitateprompt shutdown and continued maintenance of the plant in a safe condition under all crediblecircumstances. The power sources are adequate to accomplish all required essential safetyactions under postulated design bases accident conditions.

1.2.12.2.4 Radwaste System Criteria

A. The gaseous and liquid radwaste systems are designed to minimize the releaseof radioactive effluents from the station to the environs. Such releases as may benecessary during normal operations are limited to values that meet therequirements of applicable regulations.

B. The solid radwaste disposal systems are designed so that in plant processing andoffsite shipments are in accordance with applicable regulations.

C. The system design provides means by which station operations personnel arealerted whenever specified limits on the release of radioactive material areapproached.

1.2.12.2.5 Auxiliary Systems Criteria

A. Fuel handling and storage facilities are designed to prevent criticality and tomaintain adequate shielding and cooling for spent fuel. Provisions are made formaintaining the cleanliness of. spent fuel cooling and shielding water.

B. Other auxiliary systems or portions of these systems, such as service water,cooling water, fire protection, heating and ventilating, communications; andlighting, are designed to function during normal and/or accident conditions.

C. Auxiliary systems which are not required to effect safe shutdown of the reactor ormaintain it in a safe condition are designed so that a failure of these systemsdoes not prevent the essential auxiliary systems from performing their designfunctions.

1.2-21 2 REV 13 4/06

Page 14: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR- 11

11.2.1.3 Equipment Design

The LWPS equipment design parameters are provided in table 11.2.1-2.

The seismic design classification and safety classification for the LWPS components andstructures are listed in table 3.2.2-1. Safety class designations are also indicated on the LWPSpiping and instrumentation diagram, drawings 1X4DB124, 1X4DB125, 1X4DB126, 1X4DB127,AX4DB124-2, AX4DB124-3, "AX4DB124-4, and AX4DB124-5.

11.2.1.4 Reference

1. U.S. Nuclear Regulatory Commission, "Calculation of Releases from Pressurized WaterReactors," NUREG-0017, April 1976.

11.2.2 SYSTEM DESCRIPTIONS

The liquid waste processing system (LWPS) collects and processes potentially radioactivewastes for recycling or release to the environment. Provisions are made to sample and analyzefluids before discharge. Based-onthe-laboratory-analysiS-theer eitl-erretained-f6rfurther-p~rocessing, or rel~aýR-s-n-dbulr cont"ro l-d'-c-ondititons-th ugh-the-cooing-wate-r-syste-m,-

which-dilutes-the-discharge-flowt A permanent record of liquid releases is provided by analysesof- k5nvolume s of effluent.

The radioactive liquid discharged from the reactor coolant system (RCS) is processed by theradwaste processing facility systems and may be discharged or recycled.

The LWPS is arranged to recycle reactor grade water if desired. This is implemented by thesegregation of equipment drains and waste streams to prevent intermixing of liquid wastes.The LWPS can be divided into the following subsystems:

A. Reactor Coolant Drain Tank (RCDT) Subsystem

This portion of the LWPS collects nonaerated, reactor grade effluent fromsources inside the containment.

B. Drain Channel A

This portion of the LWPS collects aerated, reactor grade effluent that can berecycled.

C. Drain Channel B

This portion of the LWPS processes all effluent that is not suitable for recycling.

D. Radwaste Processing Facility Demineralizers

The radwaste processing facility demineralizer systems consist of portabledemineralizers installed in subterranean enclosures inside the radwasteprocessing facility. The radwaste processing facility is described in paragraph11.4.2.4. The radwaste processing facility demineralizers can be aligned toprocess any of the three waste drain streams.

E. The radwaste processing facility filtration system consists of a portable, vendorsupplied system located within a shielded area inside the radwaste processingfacility. The filtration system associated tanks, pumps, accumulator, piping,valves, and controls located within a shielded area inside the radwaste

11.2-4 REV 13 4/06

Page 15: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

processing facility. The peripheral equipment is located adjacent to the filterassembly. The filter system can be aligned to process any of the three wastedrain streams. Details of this equipment are shown on drawing AX4DB124-1.

In addition, the LWPS provides capability for handling and storage of spent ion exchangeresins.

The LWPS does not include provisions for processing secondary system wastes. Secondarysystem effluent is handled by the steam generator blowdown processing system (SGBPS), asdescribed in subsection 10.4.8, and by the turbine building drain system. Estimated releasesfrom these systems are discussed in subsection 11.2.3. The LWPS design, which segregatesprimary and secondary wastes, minimizes the amount of water that must be processed bydischarging low activity wastes directly, where permissible, with no treatment.

Instrumentation and controls necessary for the operation of the LWPS are located on a controlboard in the auxiliary building. Any alarm on this control board (except for the waste processingholdup control panel) is relayed to the main control board in the control room.

The LWPS piping and instrumentation diagrams are shown in drawings 1X4DB124, 1X4DB125,1X4DB126, 1X4DB127, AX4DB124-1, AX4DB124-2, AX4DB124-3, AX4DB124-4, andAX4DB124-5 and process flow diagram for the LWPS is shown on figure 11.2.2-1. Table11.2.1-1 lists the assumptions regarding flows and activity levels that were used in preparationof table 11.2.1-3, which gives nuclide concentrations for key locations within the LWPS asshown on figure 11.2.2-1. The process flow data is calculated using the data in table 11.2.1-1,the flow paths indicated on figure 11.2.2-1, realistic primary coolant activity levels from section11.1, and decontamination factors as given in reference 1 of subsection 11.2.1.

11.2.2.1 Reactor Coolant Drain Tank Subsystem

Recyclable reactor grade effluents enter this subsystem from valve leakoffs, reactor coolantpump No. 2 seal leakoffs, reactor vessel flange leakoff, and other deaerated, tritiated watersources inside the containment. Connections are provided for draining the RCS loops and thesafety injection system (SIS) accumulators and for cooling the pressurizer relief tank. Inaddition, refueling canal drains can be routed to the refueling water storage tank using theRCDT pumps.

The RCDT contents are continuously recirculated through the RCDT heat exchanger tomaintain the desired temperature. Level is prevented from varying significantly by a controlvalve which automatically opens a path from the recirculation line to the BRS when normal tanklevel is exceeded. The RCDT is also connected to the gaseous waste processing system(GWPS) vent header. Hydrogen gas bottles connected to the RCDT ensure a hydrogenblanket. Maintaining a constant level minimizes the amount of gas sent to the GWPS andminimizes the amount of hydrogen used. Provisions for sampling the gas are provided.

Details of the RCDT subsystem are shown on drawing 1X4DB127. A separate RCDTsubsystem is provided for each of the two units.

11.2.2.2' Drain Channel A Subsystem

Aereated, tritiated liquid enters drain channel A through lines connected to the waste holdup

tank. Sources of this aerated liquid are as follows:

A. Accumulator drainage (via RCDT pump suction).

11.2-5 REV 13 4/06

Page 16: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

B. Sample room sink drains (excess primary sample volume only).

C. Ion exchanger, filter, pump, and other equipment drains.

The containment sump or auxiliary building sump may be directed to the waste holdup tank orthe floor drain tank for processing as necessary.

The collected aerated drainage is pumped or flows to the waste holdup tank prior to processingthrough the radwaste processing facility filtration system and/or the radwaste processing facilitydemineralizers before reuse or discharge. Details of this equipment are shown on drawingsAX4DB124-2, AX4DB124-3, AX4DB124-4, and AX4DB124-5.

The basic composition of the liquid collected in the waste holdup tank is boric acid and waterwith some -radioactivity.

A separate drain channel A subsystem is provided for each of the two units. Details are shownon drawings 1X4DB124 and 1X4DB127. Table 11.2.1-1 lists the estimated flows entering thewaste holdup tank.

11.2.2.3 Drain Channel B Subsystem

Drain channel B is provided to collect and process nonreactor grade liquid wastes. Theseinclude:

* Wastes from floor drains.

• Equipment drains containing nonreactor grade water.

" Laundry and hot shower drains.

" Other nonreactor grade sources.

Drain channel B is comprised of three drain subchannels, each associated with one of thefollowing tanks.

A. Laundry and Hot Shower Tank

The laundry and hot shower tank is provided to collect and process wasteeffluents from the plant laundry and personnel decontamination showers andhand sinks.

Laundry and hot shower drains normally need no treatment for removal ofradioactivity. This water is transferred to a waste monitor tank through thelaundry and hot shower tank filter for eventual discharge. If sample analysisindicates that decontamination is necessary, the water can be directed throughthe Unit 1 or Unit 2 waste monitor tank demineralizer or the radwaste processingfacility for cleanup.

The laundry and hot shower tank and filter are shared by the two units. Detailsof this portion of the LWPS are shown on drawing 1X4DB126. Table 11.2.1-1lists estimated flows entering the laundry and hot shower tank.

B. Floor Drain Tank

Water may enter the floor drain tank from system leaks inside the containmentthrough the containment sump, from system leaks in the auxiliary buildingthrough auxiliary building sumps and the floor drains, and floor drains in the

11.2-6 REV 13 4/06

Page 17: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

radwaste facilities. Sources of water to the containment sump and auxiliarybuilding sumps and floor drains are the following:

1. Fan cooler leaks.

2. Secondary side steam and feedwater leaks.

3. Primary side process leaks.

4. Decontamination water.

The containment sump or auxiliary building sumps may be directed to the wasteholdup tank.

Another source of water to the floor drain tank is the chemical laboratory drains.Excess nonreactor grade samples that are not chemically contaminated andlaboratory equipment rinse water are drained to the floor drain tank.

The contents of the floor drain tank are processed through the radwasteprocessing facility demineralizers and/or the radwaste processing facility filtrationsystem and then pumped to a waste monitor tank for ultimate discharge.

If the activity in the floor drain tank liquid is such that the discharge limits cannotbe met without cleanup, the liquid can be processed by the waste monitor tankdemineralizer, the radwaste processing facility demineralizers, or the radwasteprocessing facility filtration system.

A separate floor drain tank and associated equipment are provided for each ofthe two units. Details of this portion of the LWPS are shown on drawing1X4DB126. Table 11.2.1-1 lists the estimated flows entering the floor drain tank.

C. Chemical Drain Tank

Laboratory samples which contain reagent chemicals (and possibly tritiatedliquid) are discarded through a sample room sink which drains to the chemicaldrain tank. Chemical drains requiring radwaste processing are sent to the solidwaste management system or may be processed through the radwasteprocessing facility demineralizers and/or the radwaste processing facility filtrationsystem.

The chemical drain tank and associated equipment are shared by Units 1 and 2.Details of this portion of the LWPS are shown on drawing 1X4DB125. Table

11.2.1-1 lists the estimated flow directed to the chemical drain tank.

Annyliq uids-released-to-the-environment-byt he-L-W PS-a-re-first-directed-to-a-waste-mnriitortank?Btef.e releasi ng-the-contents-of-a-waste-monitor-tankl,_-_asample _is-tak:eWf67an-a r Ds Tihef i dihgs--a r~e-l o~g ed ,-a n d,_-I f.te- a---ti~it-lv eli-iti _a ct--'•tbel rris-ee-ank-~ 0-•-

releeased-to-the-dischargecan-lThe discharge valve is interlocked with a process radiationmonitor -and-lo-sesautomatically when the radioactivity concentration in the liquid dischargeexceeds a preset limit. The radiation element is located upstream of the discharge valve at adistance sufficient to close the valve before passing the fluid that activated the detector tripsignal. The isolation valve also blocks-flow if sufficient dilution water is not available. Theradiation monitor is described in section 11.5. A permanent record of the radioactive releasesis provided by a sample analysis of the known volumes of waste effluent released. Liquidwaste discharge flow and volume are also recorded.

If the monitor tank contents are not acceptable for discharge, the fluid can beheld for a time toallow activity to decay to acceptable levels, or it can be further processed by the waste monitor

11.2-7 REV 13 4/06

Page 18: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

tank demineralizer, the radwaste processing facility filtration system, or radwaste processingfacility demineralizers.

11.2.2.4 Spent Resin Handling Subsystem

This subsystem collects, handles, and processes spent resins from the primary fluid systemsprior to their disposal.

Spent resin from the primary system demineralizers is transported to and stored in the spentresin storage tank prior to being drummed. The spent resin sluice portion of the LWPS consistsof a spent resin sluice filter, spent resin sluice pump, and the spent resin storage tank. Theresin sluice water, after being directed to an ion exchange vessel by the sluice pump, returns tothe spent resin storage tank for reuse.

Thus, sluicing of spent resin from primary plant demineralizers is accomplished withoutgenerating a large volume of liquid waste.

Reactor makeup water storage tank system pressure may also be used as a motive force forsluicing demineralizers to the spent resin storage tank.

Resin from the SGBPS demineralizers is handled in a similar manner to that described for theprimary system demineralizers. The SGBPS resin handling is discussed in subsection 10.4.8.The primary system resins and the SGBPS resins are segregated during all phases of handlingso that no cross-contamination occurs.

Resin slurry from both spent resin storage tanks is sent to the radwaste processing facility bypressurizing the tank with nitrogen.

A separate resin handling subsystem is provided for each of the two units. Details of thisportion of the LWPS are shown on drawing 1X4DB125.

11.2.2.5 Liquids From Sources Other Than the Liquid Waste Processing System

11.2.2.5.1 Steam Generator Blowdown Processing System

Blowdown from the steam generators of each unit is cooled, filtered, and demineralized.Normally it is then returned to the condensers for reuse as condensate makeup, but it may bedischarged to the environment. The SGBPS is described in subsection 10.4.8.

11.2.2.5.2 Turbine Building Drain System

The function of the turbine building drain system is:

A. To collect the floor drains and sampling wastes in the turbine building and othermiscellaneous drains.

B. To treat these wastes, if necessary, to meet the requirements of the State ofGeorgia Environmental Protection Agency (EPA) regulations and NuclearRegulatory Commission regulations prior to discharge to the Savannah River.

11.2-8 REV 13 4/06

Page 19: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

All the wastes generated in the turbine building including drains, leakages, and the samplingwastes are collected in the sumps in the turbine building. The sump pump discharge,combining with the auxiliary building clean water sump discharge, auxiliary feedwaterpumphouse drain, maintenance building drain, and the treated turbine building drain, normallypasses through a radiation monitor before entering into an oil water separator to meet the EPAoil discharge limit. If the radioactivity level of this combined waste stream exceeds the setpointof the radiation monitor, a signal is sent to stop the flow to the nonradioactive oil waterseparator. This stream is then sent to one of the turbine building drain tanks before processing.The amount of waste delivered to the turbine building drain tanks is kept minimal by promptlylocating the specific contaminated (radioactive) stream(s) and pumping the remaining(nonradioactive) streams via their normal route. The turbine building drain system andassociated components are discussed in detail in subsection 9.3.3.

11.2.2.6 Equipment Description

Principal design parameters for the LWPS equipment are given in table 11.2.1-2. All parts orcomponents in contact with borated water are fabricated from or clad with austenitic stainlesssteel. Pumps are provided With vent and drain connections.

Since this system performs no function related to the safe shutdown of the plant, manycomponents of the system are classified as nonnuclear safety. Component safety classes,seismic design, and principal codes are shown in table 3.2.2-1.

11.2.2.6.1 Pumps

Pumps in the LWPS have been standardized wherever possible. Where operation is not criticaland surge capacity is available, a single pump has been provided. Spare pumps can be keptonsite in case any pump should fail. Quick replacement is possible because:

" The pumps are flanged, not welded.

* The system has surge capacity.

" Adequate vent, flush, and drain capabilities are provided.

* The pumps are standardized.

Three types of standard pumps are required, as described below.

Canned rotor pumps are used wherever possible to minimize fluid leakage and to minimize therelease of entrained radioactive gases in the leaking fluid to the atmosphere.

Canned rotor pumps with similar head-flow characteristics are used for the followingapplications:

" Spent resin sluice pumps.

" RCDT pumps.

Another canned rotor pump design is used for the following applications:

* Waste evaporator feed pumps.

11.2-9 REV 13 4/06

Page 20: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

" Waste evaporator condensate tank pumps.

* Chemical drain tank pump.

* Waste monitor tank pumps.

Mechanical seal pumps are also used in some applications because these pumps, have anopen impeller, which will not be damaged by large particles in the water. Mechanical sealpumps with similar head-flow characteristics are used for the following applications:

" Floor drain tank pump.

" Laundry and hot shower tank pump.

Globe valves are installed in pump discharge lines where necessary to prevent pump runout.Pump miniflow lines have locked-in-position globe valves to ensure that the minimum pump flowrequirements are met.

A. RCDT Pump

The design basis for this pump is that, in its function of RCS drain, the coolantlevel reaches the midplane of the reactor vessel nozzles within an 8-h period.Two pumps are furnished because of the relative inaccessibility of thecontainment during plant operation. Both pumps are operated to meet thedraining time requirement. One pump provides sufficient flow for normaloperation of the RCDT portion of the LWPS. The liquid is sent to the recycleholdup tanks.

B. Waste Evaporator Feed Pump

This pump supplies feed to the radwaste processing facility for processing fromthe waste holdup tank, and it can be used to transfer waste holdup tank contentsto the floor drain tank, if desired.

C. Waste Evaporator Condensate Pump

The waste evaporator condensate tank pump is used to transfer the contents ofthe waste evaporator condensate tank.

D. Chemical Drain Tank Pump

This pump may be used to transfer the contents of the chemical drain tank.

E. Spent Resin Sluice Pump

One pump is provided to sluice resins from primary side demineralizers to thespent resin storage tank. Its delivery flow is based on the velocity required tosluice resin in a 3-in. pipe.

F. Laundry and Hot Shower Tank Pump

This pump is used to transfer the water from the laundry and hot shower tank toa waste monitor tank.

G. Floor Drain Tank Pump

This pump is used to transfer water from the floor drain tank to the radwasteprocessing facility. From the radwaste processing facility, processed waste istransferred to the waste monitor tank.

11.2-10 REV 13 4/06

Page 21: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

H. Waste Monitor Tank Pumps

Two pumps are provided for each unit. One pump is used for each monitor tankto discharge water from the LWPS or for recycling if further processing isrequired.

The pump may also be used for circulating the water in the waste monitor tank toobtain uniform tank contents, and therefore a representative sample, beforedischarge. These pumps can be throttled to achieve the desired discharge rate.

Auxiliary Waste Monitor Tank Pumps

Two pumps are provided. They are installed in Unit 2 but serve both units. Onepump is used for each auxiliary waste monitor tank to discharge water fromLWPS or for recycling if further processing is required. A mixer may be used forcirculating the water in the auxiliary waste monitor tank to obtain uniform tankcontents, thereby assuring a representative sample is acquired prior to dischargeof the tank contents. The pumps can be throttled to achieve the desireddischarge rate.

11.2.2.6.2 Tanks

A. Reactor Coolant Drain Tank

One tank is provided for each unit. The purpose of the RCDT is to collectleakoff-type drains inside the containment at a central collection point for furtherdisposition through a single penetration via the RCDT pumps. The tank providessurge volume and net positive suction head (NPSH) to the pumps.

Only water which can be directed to the boron recycle holdup tanks enters theRCDT. The water is compatible with reactor coolant and does not containdissolved air during normal plant operation, by engineering design.

A constant level is maintained in the tank to minimize the amount of gas sent tothe GWPS and also to minimize the amount of hydrogen cover gas required.The level is maintained by one continuously running pump and by a control valvein the discharge line. This valve operates on a signal from a level controller tolimit the flow out of the system. The remainder of the flow is recirculated to thetank.

Continuous flow is maintained through the heat exchanger in order to preventloss of pump NPSH resulting from a sudden inflow of hot liquid into the RCDT.

B. Waste Holdup Tank

One atmospheric pressure tank is provided for each unit to collect:

1. Equipment drains.

2. Valve and pump seal leakoffs (outside the containment).

3. Boron recycle holdup tank overflows.

4. Other water from tritiated, aerated sources.

The tank size is adequate to accommodate 11 days of expected influent duringnormal operation.

C. Waste Evaporator Condensate Tank

11.2-11 REV 13 4/06

Page 22: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

One tank with a diaphragm to exclude air is provided for each unit to collectwater from processing systems.

D. Chemical Drain Tank

One tank is provided to collect chemically contaminated, tritiated water from thelaboratories. This tank is shared by the two units and has sufficient capacity toaccept a month's laboratory waste during normal operation of both units.

E. Spent Resin Storage Tank

The purpose of the spent resin storage tank is to-provide a collection point forspent resin and to allow for decay of short-lived radionuclides before disposal.The tank also serves as a head tank for the spent resin sluice pump.

One vertical, cylindrical tank with sufficient capacity to handle the spent resinstorage needs is provided. A vertical, cylindrical tank is used because thesymmetrical bottom facilitates the removal of resin. The tank is designed so thatsufficient pressure can be applied in the gas space of the tank to move the resinslurry to the radwaste processing facility.The spent resin storage tank and associated equipment, which can containradioactive material, are shielded to limit the dose to personnel.

The level indicating system in the spent resin storage tank shows only total leveland not the amount of resin and water separately. However, since the resinvolumes flushed from demineralizers and the resin volumes transferred to theradwaste processing facility are known, the resin level in the tank is also known.

F. Laundry and Hot Shower Tank

One atmospheric pressure tank is provided to collect laundry and liot showerdrains for the two units. The tank size is sufficient to furnish a 10-day surgecapacity for the two units during normal operation of both units and a 2-daysurge capacity during refueling of a single unit.

G. Floor Drain Tank

One atmospheric pressure tank is used to collect floor drains from the controlledareas of each unit's primary system. The tank provides sufficient surge capacityfor the floor drains within the collection area and, in connection with the wasteholdup tank, provides surge capacity for abnormal primary system leaks. Thetank size is adequate to accommodate 3.5 days of expected influent duringnormal operation or 1.8 days of expected influent during shutdown operation.

H. Waste Monitor Tanks

Two atmospheric pressure waste monitor tanks are provided for each unit tomonitor liquid discharged from the plant site. Each tank is sized to hold avolume large enough that sampling requirements are minimized, therebyminimizing laboratory effluent.

Two additional atmospheric pressure tanks have been provided to augment theplant capacity to handle large surges of water or to accommodate conditions inwhich release of the processed water is not feasible. These 20,000 gallon tanksare installed on level D of the Unit 2 auxiliary building. They are shared by bothunits, with one tank normally aligned to each unit.

11.2-12 REV 13 4/06

Page 23: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

11.2.2.6.3 Reactor Coolant Drain Tank Heat Exchanger

This heat exchanger is located in the discharge line of the RCDT pumps and is in constantservice as part of the RCDT recirculation path. Continuous auxiliary component cooling waterflow is maintained to the heat exchanger to accommodate, without operator action, sudden flowof hot liquid to the RCDT. The heat exchanger can also be used to cool the contents of thepressurizer relief tank in the RCS.

The heat exchanger is sized for several modes of operation:

A. It can maintainthe RCDT liquid below 1700 F, assuming a 10-gal/min input of600°F reactor coolant.

B. It can cool the contents of the pressurizer relief tank from 200OF to 120OF in lessthan 8 h.

C. It can maintain the contents of the RCDT at less than 1700 F, assuming a 25-gal/min input from the excess letdown heat exchanger (chemical and volumecontrol system).

One RCDT heat exchanger is provided per unit.

11.2.2.6.4 Demineralizers

.As part of a program of continuous pressurized water reactor operating plant followup,Westinghouse has obtained operational data on demineralizer decontamination factors forselected isotopes. The measured range of decontamination factors for these isotopes is givenin table 11.2.2-1.

These values were observed across mixed bed demineralizers containing cation resin in thelithium-7form and anion resin in the borated form. The minimum values in table 11.2.2-1 weregenerally observed just before resin flushing and recharging; during the operating life of thedemineralizer, decontamination factors were consistently closer to the maximum values.

Although specific operating decontamination factors have not yet been measured for otherisotopes, their behavior in a mixed bed demineralizer may be inferred from this data.

The process decontamination factor used for the demineralizers in the analysis of systemperformance is taken from reference 1, subsection 11.2.1. These decontamination factors aregiven 'in table 11.2.2-1.

A. Waste Monitor Tank Demineralizer

One mixed bed demineralizer is provided upstream of the waste monitor tanks toremove, if desired, trace ionic contaminants. The laundry and hot shower tankcontents can also be processed through the demineralizer if such processing isnecessary.

B. Radwaste Processing Facility Demineralizers

The radwaste processing facility houses a series of demineralizers which can beoperated in various configurations. The type and loadings of resins or other filtermedia utilized in these vessels can be changed as necessary to optimize theperformance of the system.

11.2-13 REV 13 4/06

Page 24: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

11.2.2.6.5 Filters

The following filters are provided in the LWPS:

0 Laundry and hot shower tank filter.

* Floor drain tank filter.

* Spent resin sluice filter.

e Waste evaporator condensate filter.

* Waste monitor tank filter.

The laundry and hot shower tank filter element is normally removed since installation of thefiltration system in the radwaste processing facility.

11.2.2.6.6 Strainers

Basket-type strainers of mesh construction are provided to prevent clogging of filters and linesdownstream because of large particles being sluiced through the lines during liquid transferoperations.

The following strainers are provided in the LWPS:

0 Laundry and hot shower tank strainer.

0 Floor drain tank strainer. (This strainer may be removed to enhance systemoperability.)

11.2.2.7 Instrumentation Design

The system instrumentation is shown on the LWPS drawings 1X4DB124, 1X4DB125,1X4DB126, 1X4DB127, AX4DB124-2, AX4DB124-3, and AX4DB124-4.

Instrumentation readout is located mainly on the waste processing system panel in the auxiliarybuilding. Some instruments are read at the equipment location.

All alarms are shown separately on the waste processing system panel and are further relayedto one common waste processing system annunciator on the main control board in the controlroom. The waste processing holdup control panel does not relay signals to the control roomannunciator.

All pumps are protected against loss of suction pressure by a control setpoint on the levelinstrumentation for the respective vessels feeding the pumps. In addition, the RCDT pumpsand the spent resin sluice pump are interlocked with flowrate instrumentation to stop the pumpswhen the delivery flows reach minimum setpoints. The RCDT pumps have a keyswitch allowingthe bypass of the flowrate instrumentation control logic. During certain intermittent outageflowpaths, flowrates less than those recommended by the pump vendor may be established.Administrative controls require continuous monitoring of pump performance during suchflowpaths to ensure the pumps' availability.

11.2-14 REV 13 4/06

Page 25: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

Pressure indicators are provided to give local indication of pressure drops acrossdemineralizers, filters, and strainers.

All releases to the environment are monitored for radioactivity. This instrumentation isdescribed in section 11.5.

Each tank is provided with level indication instrumentation that actuates an alarm on high liquidlevel in thejtank, thus warning of potential tank overflow.

11.2.2.8 Operating Procedures

The LWPS is manually operated except for some functions of the RCDT circuit. The system.includes adequate control equipment to protect components and adequate instrumentation andalarm functions to provide operator information to ensure proper system operation.

Operation of the LWPS is essentially the same during all phases of normal and defined off-normal reactor plant operation; the only differences are in the load on the system. The term"normal operation," as used here, means all phases of plant operation except operation underemergency or accident conditions. The LWPS is not regarded as an engineered safetyfeatures system.

11.2.2.8.1 Reactor Coolant Drain Tank Subsystem Operation

A. Reactor Coolant Drain Tank Recirculation

Reactor coolant is continuously circulated through the RCDT heat exchanger tomaintain _<170 0 F in the event of a hot reactor coolant leak. Level is maintainedby a control valve which automatically opens a path from the recirculation line tothe recycle holdup tanks. Normal operation of this mode is automatic andrequires no operator action. The system can be put into the manual mode, ifdesired.

Leakage into the RCDT can be estimated by putting the system in the manualmode, stopping the pump, and monitoring the level change. A venting system isprovided to prevent wide pressure variations in the RCDT. A hydrogen blanket isautomatically maintained between 2 and 6 psig. Hydrogen is supplied frombottles which must be replaced when the pressure drops to -100 psig.

During all other operations, the recirculation mode is stopped and the RCDT isisolated.

B. Pressurizer Relief Tank Cooling

The pressurizer relief tank may be cooled by a feed- and-bleed method, byspraying cold makeup water and pumping the water to the recycle holdup tankswith an RCDT pump through the RCDT heat exchanger. This is a rapidcooldown and can be used even if the heat exchanger is out of service.However, to minimize the addition of water to the system when a rapid cooldownis not necessary, the pressurizer relief tank may be cooled from 200OF to 120OFin less than 8 h by using the RCDT heat exchanger and one pump in arecirculation mode without adding makeup water.

C. Loop Draining

11.2-15 REV 13 4/06

Page 26: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

Four RCS loops may'be drained simultaneously to the midpoint of the reactorvessel nozzles in less than 8 h when both RCDT pumps are running. The loopsare vented to 100 psig, then a spectacle flange is positioned to the pumps'suction. The water may be sent to the recycle holdup tanks, refueling waterstorage tank, waste holdup tank, or the spent fuel pool. Since the RCDT heatexchanger is not needed for cooling, it may be bypassed or used in parallel withthe bypass.

D. Refueling Canal Draining and Cleanup

Refueling canal water is transferred, using the RCDT pumps, to the refuelingwater storage tank (draining), to the canal via the spent fuel pool cooling system(cleanup), or to the waste holdup tank (disposal).

Since the RCDT heat exchanger is not needed for cooling, it may be bypassedor used in parallel with the bypass.

E. Accumulator Draining

This mode is available for accumulator maintenance. After the accumulator isvented to 90 psig, the spool piece is connected to the RCDT pump suction fortransfer of accumulator water to the reactor water storage tank or recycle holduptank.

F. Excess Letdown Header

During normal plant heatup operations, excess letdown to the RCDT will permitfaster heatup rate. Excess letdown flow is directed from the RCDT to the recycleholdup tanks.

11.2.2.8.2 Drain Channel A Subsystem Operation

Water is accumulated in the waste holdup tank until sufficient quantity exists to warrant startingthe processing systems for a batch process.

If it is not desired to recycle the water in the waste holdup tank and analysis indicates thatdecontamination is not necessary, the water may be sent to the floor drain tank for eventualdischarge.TLhe-w~aste-hiold u p-ta nk-conte nts-ma~y.be-processe~d-b.y-th e-ad~waste-p rocessing-facilitT}-filtr-tib nsystem-and/or-the-a ig-facility-deniiff-e-alizerst

11.2.2.8.3 Drain Channel B Subsystem Operation

Drain channel B of the LWPS consists of the laundry and hot shower system, the floor draintank system, and the chemical drain tank system.

Laundry and hot shower water enters the laundry and hot shower tank for holdup; it is sampled,filtered, and transferred to the monitor tank for discharge, or processed through the radwasteprocessing facility filtration system or the radwaste processing facility demineralizer. Ifdemineralization is required, the resin must be replaced with clean resin thereafter.

The floor drain tank contents are recirculated, and then samples are taken and analyzed. If thefloor drain tank is overloaded or the water is recyclable, the water can be transferred to thewaste holdup tank.

11.2-16 REV 13 4/06

Page 27: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

Water leaving this system to the discharge canal is monitored for radiation. This radiationmonitor is described in section 11.5. If the radiation monitor closes the discharge valve, it mustbe cleared before the valve can be reopened. The monitor element can be cleared by flushingit with demineralized water from the temporary connection back to the waste monitor tank.During refueling, the load on this portion of the LWPS is increased, but there is no change inoperation.

Spent samples with high chemical concentrations are held up in the chemical drain tank, thensampled. The contents are drained to the auxiliary building sumps or the radioactive drainsumps.

11.2.2.8.4 Spent Resin Handling Subsystem

A. Resin Fluffing

The demineralizer is valved out of service, and the flow path is aligned from thespent resin sluice pump (or the reactor makeup water system header) throughthe process line of the demineralizer, through theJohnson screen at the top ofthe demineralizer, and back to the spent resin storage tank. The resin bed isbackflushed for about 10 min to loosen it for sluicing. This operation may alsobe used to recover pressure drop caused by bed fouling by backwashingparticulates from the top layer of the resin into the spent resin storage tank.Such a recovery is useful when the resin is not ionically depleted.

B. Resin Sluicing

The sluice pump is shut off after fluffing. The valves in the backflush circuit areclosed, the sluice line to the bed screen is opened, and the sluice pump isstarted. The resin flows to the spent resin storage tank, initially at a slow rate; itcontinues for about 10 min until sluicing is completed. Finally, the pump isstopped, and the sluice inlet and outlet valves are closed. If the pump suctionline screen in the tank becomes resin plugged at any time, it can be cleared witha blast of nitrogen.

C. Resin Fill

After sluicing is completed, fresh resin must be added. The path to the drainheader from the demineralizer is opened to allow overflow. The resin fill line isopened and resin added. After fresh resin is added, the fill line valve is closedand the flow path is realigned for normal demineralizer operation.

D. Resin Disposal

The resin in the spent resin storage tank is loosened before disposal by sendingpressurized nitrogen or sluice water through the six sparging nozzles in the tank.The valves in the resin transfer line are opened to direct the spent resin to theradwaste processing facility.

The tank is then pressurized with nitrogen to force the resin up through the resintransfer line to the disposal area. A single nozzle in the spent resin storage tankis provided to allow local fluidization with sluice water at the opening of thedischarge pipe. During resin transfer, this nozzle is used to ease the flow of theresin slurry. After resin transfer is complete, the tank is vented to the plant ventand returned to atmospheric pressure. The resin transfer line is thenbackflushed to the spent resin storage tank to clear it of resin.

11.2-17 REV 13 4/06

Page 28: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

Since a certain amount of resin remains in the tank after a disposal operation, itmay hinder the backflush operation. Therefore, the fluidizing nozzle is againused to facilitate the backwash operation.

11.2.3 RADIOACTIVE RELEASES

11.2.3.1 Criteria for Discharge, Recycle, or Further Treatment of Liquid Waste

Processed liquids are recycled for reuse within the plant whenever possible, provided that thefollowing criteria are satisfied:

0 The plant water inventory requires makeup.

0 The water to be reused satisfies system water quality requirements.

* Tritium buildup is less thanplant operating limits.

Processed liquids are discharged under the following conditions:

" The processed water does not satisfy plant operating requirements for water qualityand tritium buildup.

" The effluent concentrations are within the limits specified by the Offsite DoseCalculation Manual.

* The discharge does not cause the limits of 10 CFR 50, Appendix I, to be exceeded.

Processed liquids are recycled within their respective treatment systems for additionalprocessing when system water quality requirements are not satisfied and reuse within the plantis desirable, or when discharge of the processed liquid is planned but the discharge wouldresult in exceeding limits in the Offsite Dose Calculation Manual.

11.2.3.2 Estimated Releases

The equipment utilized during liquid waste processing is at the discretion of the operator;therefore, the calculated releases conservatively do not address all possible treatmentprocesses but only the expected process. Liquid releases from VEGP are calculated using thePWR-GALE computer code~1 ) and parameters listed in'table 11.1-8, which are discussed inmore detail below. Releases calculated assuming operation with expected levels of fuelcladding defects of 0.12 percent are presented in table 11.2.3-1. Primary and secondarycoolant activity levels are given in section 11.1 for the realistic case. In agreement withreference 1, the-total releases include an adjustment factor of 0.15 Ci/year, using the sameisotopic distribution as the calculated release, to account for anticipated operationaloccurrences.

The tables list the calculated annual release from each of the process paths discussed belowas well as, the total annual release. A comparison of annual average effluent concentrationswith Appendix B, Table II, column 2 values of 10 CFR 20.1 -20.601 is provided in table 11.2.3-2for operation with expected fuel leakage.

11.2-18 REV 13 4/06

Page 29: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

The releases are calculated for one unit, assuming that both units are operating. This is doneto reflect the impact of the second unit's operation on the operation of systems and componentsshared between the two units. To obtain the combined releases of the two units, simply doublethe values listed in table 11.2.3-1.

A survey has been performed of liquid discharges from different Westinghouse pressurizedwater reactor plants, with results presented in table 11.2.3-3. The data includes radionuclidesreleased on an unidentified basis and are all within the permissible concentration for release ofliquid containing an unidentified radionuclide mixture. The data in table 11.2.3-4 clearly indicatethat actual releases are highly dependent upon the actual operation of the plant and can varysignificantly from year to year for a given plant as well as from plant to plant.

11.2.3.2.1 Boron Recycle System (BRS)

Primary coolant is withdrawn from the reactor coolant system (RCS) and processed through thechemical and volume control system (CVCS). A side stream of 1700 gal/day of the letdownstream is assumed to be diverted to the BRS as shim bleed. The shim bleed is combined witha conservatively estimated 300 gal/day of other reactor grade wastes that are collected by thereactor coolant drain tank (equipment drain wastes). Since the BRS is shared by both units, thetotal process flow is 4000 gal/day. The equipment drains and shim bleed flows have an activitylevel equivalent to primary coolant activity (PCA).

The combined shim bleed and equipment drain wastes streams are routed to one of the recycleholdup tanks. The contents of the recycle holdup tank are then processed through theradwaste processing facility filtration system and the radwaste processing facilitydemineralizers. The water is either pumped to the reactor makeup water storage tank for reusein the plant or to a waste monitor tank for monitoring and discharge. The BRS has sufficientcapacity to allow total reuse of the combined shim bleed and equipment drain wastes.

Radioactive decay during collection in the recycle holdup tanks is calculated using a collectiontime of 22.4 days. This value is based upon filling one of the recycle holdup tanks to 80 percentof capacity using the combined shim bleedand reactor coolant drain tank flows. Radioactivedecay during processing and discharge is calculated using a process time of 0.31 days. Thisvalue is based upon processing the combined shim bleed and reactor coolant drain tank flowsat the design flowrate of the recycle evaporator.

The decontamination factors used in calculating radionuclide removal for iodine, cesium,rubidium, and other nuclides, are determined by applying the methodology and parameters ofreference 1 to the processing capabilities of the BRS and CVCS as shown in figure 11.2.3-1.No credit is taken for the recycle evaporation condensate demineralizer since its main functionis to remove boron carryover.

11.2.3.2.2 Liquid Waste Processing System (LWPS)

A. Clean Wastes (Drain Channel A - Miscellaneous Wastes)

Clean wastes are collected in the waste holdup tank for processing. Based onsample analysis, the water in the monitor tank would either be discharged orprocessed further by recirculation through the waste monitor tank demineralizeruntil sample analysis indicated that it was acceptable for discharge. The flow tothe waste holdup tank is 713 gal/day at 0.051 times PCA. The LWPS hassufficient capacity to allow total reuse of the processed clean wastes. However,

11.2-19 REV 13 4/06

Page 30: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1.1

in the release calculations a discharge fraction of 1.0 is used as specified byreference 1.

Radioactive decay during collection in the waste holdup tank is calculated usinga collection time of 5.6 days. This value is based upon filling the waste holduptank to 40 percent of capacity. Radioactive decay during processing anddischarge is calculated using a process time of 0.028 days. This value is basedupon processing 40 percent of the waste holdup tank capacity at the designflowrate of the waste evaporator (no longer in system) and the time required topump this volume of water out of the monitor tank at the maximum pumping rate.

The decontamination factors used in calculating radionuclide removal are basedupon demineralization as shown in figure 11.2.3-1.

B. Dirty Wastes (Drain Channel B - Miscellaneous Wastes)

Dirty wastes are collected in the floor drain tank. A sample is analyzed todetermine whether the water can be discharged without processing. If cleanup isrequired,'the liquid is processed by the radwaste processing facility filtrationsystem and/or the radwaste processing facility demineralizer and the effluentdirected to a waste monitor tank. Based on sample analysis, the monitor tankcontents are either discharged or processed further by recirculation through the -monitor tank demineralizer until sample analysis indicates that the water isacceptable for discharge. The flow to the floor drain tank is 2047 gal/day at 0.02times PCA. Since all of the di'rty wastes are normally discharged, a dischargefraction of 1.0 is used in the release calculations.

Radioactive decay during collection in the floor drain tank is calculated using acollection time of 1.43 days. This value is based upon filling the floor drain tankto 40 percent of capacity. Radioactive decay during processing is calculatedusing process time of 0.03 days. This value is based upon processing 40percent of the floor drain tank capacity at the design flowrate of the wasteevaporator (no longer in service) and the time required to pump this volume ofwater out of the monitor tank at the maximum pumping rate.

The decontamination factors used in calculating radionuclide removal are basedupon the decontamination factors given in reference 1 for demineralizers asshown in figure 11.2.3-1.

C. Detergent Wastes (Laundry and Hot Shower Tank)

Detergent wastes are normally released without treatment. The releasesthrough this path are assumed to be the same as listed in reference 1, table 2-20.

11.2.3.2.3 Steam Generator Blowdown Processing System (SGBPS)

Blowdown from the steam generators is normally processed by the two generator blowdowndemineralizers (in series) and recycled back to the main condenser. If discharge of blowdownis desired, the demineralizers can be bypassed. A valve in the discharge line automaticallystops discharge on a high radioactivity signal. In the event of a primary to secondary side leak,the demineralizers would be in use. For the release calculation, a 100 lb/day primary tosecondary side leakage is assumed. Also, a design basis total blowdown rate of 180,096 lb/h isassumed with 100 percent of the flow being discharged.

11.2-20 REV 13 4/06

Page 31: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

No credit is taken for radioactive decay of the isotopes in the blowdown stream since theSGBPS design utilizes a through-flow process with no significant decay.

The decontamination factors used in calculating radionuclide removal are shown in figure11.2.3-1. Thesevalues are based upon the decontamination factors given in reference 1 fortwo steam generator blowdown mixed bed demineralizers (in series).

11.2.3.2.4 Turbine Building Floor Drains

The processing of the low level radioactive water in the turbine building dirty drain tank ismanually initiated by the operator based on the predetermined water level in the tank. Thisprocessing system, located in the auxiliary building, consists of an oil water separator, anactivated charcoal filter, two demineralizers in series, and a discharge filter. The treated wateris returned to the clean drain tank in the turbine building. After monitoring it is combined withother waste streams for disposal.

11.2.3.3 Release Points

The natural draft cooling towers are not radioactive release points. However, the followinginformation regarding location is offered.

Blowdown from both cooling towers and flow from the waste water retention basin is collected ina common blowdown sump and is discharged to the river via the waste water effluent pipe. Theradioactive release line discharges into the waste water effluent pipe at a point downstream ofthe blowdown sump and is then discharged into the Savannah River downstream of the riverintake structure.

11.2.3.4 Dilution Factors

At 100-percent capacity factor and design basis conditions for cooling tower operation,blowdown from the cooling tower to the blowdown sump is approximately 5000 gal/min per unit.Furthermore, 10,000gal/min per unit river water can be provided to the sump through a dilutionflow transfer line takeoff on the river water makeup line to the natural draft cooling towers.Thus, a total of 15,000 gal/min per unit dilution flow is available during the liquid radwastedischarge operation. Minimum dilution flow is as specified in the release permit which isprepared in accordance with the ODCM.

There will be some additional dilution following discharge due to the effect of the near fieldmixing zone in the Savannah River. For 15,000 gal/min (33.4 ft3/s) effluent discharge into theSavannah River with 5800 ft3/s minimum flow, the VEGP thermal plume analysis utilizes adilution factor of 10 for summer discharge conditions and 20 for winter conditions.(2)

For conservatism, the lower dilution factor of 10 was chosen for the LADTAP II analysis.

11.2.3.5 Estimated Doses

Release of radioactive effluents to the Savannah River during normal plant operation andanticipated operational occurrences will result in a minimal radiological exposure to individualsas noted in table 11.2.3-4. The estimated annual average doses to the maximum exposedindividual were calculated using the LADTAP II computer code.(3)

11.2-21 REV 13 4/06

Page 32: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-1 1

The location of maximum exposure is in that area of the river allowing for initial near fielddilution of the discharge with essentially zero travel time. Since crop irrigation from theSavannah River has not been observed in the vicinity of the plant site, this pathway has notbeen considered in the evaluation of doses. The anticipated dose due to drinking water couldbe considered insignificant because the nearest location of potable use of river water is inBeaufort County, South Carolina, approximately 103 river miles downstream of the plant site.However, for conservatism, this pathway was evaluated assuming the maximum exposedindividual obtains drinking water in the immediate area of the discharge plume. Shoreline usein the vicinity of the plant is very limited, with essentially no fishing from the bank, swimming, orsunbathing, and, consequently, is expected to be an insignificant pathway in comparison withthe pathway of aquatic foods. Nevertheless, for purposes of conservatism, this pathway hasbeen included in the evaluation of doses for the maximum exposed individual.

Furthermore, a single dilution factor (10.0) for the initial near field dilution of the discharge witha travel time of zero was used for the pathway's consideration. In lieu of site specific data, thepathway usage factors and shorewidth factor (0.2) outlined in Regulatory Guide 1.109, Revision1, October 1977, were utilized in this evaluation. As noted in table 11.2.3-4, based on thecriteria as outlined above, the maximum exposed individual annual doses from the discharge ofradioactive materials in liquid effluent from each of the VEGP units meet the guideline ofAppendix 1, 10 CFR 50, and Docket RM-50-2, Annex to Appendix I.

11.2.3.6 References

1. U.S. Nuclear RegulatoryCommission, "Calculation of Releases from Pressurized WaterReactors," PWR-GALE Computer Code, NUREG-0017, April 1976.

2. Georgia Power Company, "Waste Water Effluenit Discharge Structure Thermal PlumeAnalysis," Vogtle Electric Generating Plant Units 1 and 2, Revised March 1981.

3. U.S. Nuclear Regulatory Commission, "Calculation of Radiation Exposure to Man fromRoutine Release of Nuclear Reactor Liquid Effluents," LADTAP II Computer Code,NUREG/CR-1276, March 1980.

11.2-22 REV 13 4/06

Page 33: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.3.2 SYSTEM DESCRIPTION

This section describes the design, operating features, andperformance of the gaseous waste processing system (GWPS) andother plant gaseous waste management systems with respect to thecollection and control of radioactive gases. Detailed.descriptions of the plant ventilation systems and condenservacuum system are presented in sections 9.4 and 10.4,respectively.

The GWPS is provided with two main process loops. Eachprocesses gaseous wastes from one of the two plant units.Interconnections are provided to allow either process loop toprocess waste gas from either or both units.

All equipment in the GWPS is controlled from the wasteprocessing panel. The GWPS consists mainly of two closed loopscomprised of a waste gas compressor, a catalytic hydrogenrecombiner, and seven waste gas decay tanks (GDTs) to accumulatethe fission product gases. All pipes containing radioactivegases are shielded as necessary, and no piping is run throughnormally occupied areas.

Each main process loop also includes a GDT drain pump, six gastraps, and a waste gas drain filter. All of the equipment islocated in the auxiliary building.

The piping and instrumentation diagram for the system is shownin drawings 1X4DB128 and 1X4DB129. This diagram indicatessafety classes for all components and piping.

The GWPS reduces the fission gas concentration in the reactorcoolant system (RCS), which in turn reduces the escape offission gases from the RCS during maintenance or throughequipment leakage.

Tprimar-yvsour ce of radioac.ti-ve---gas-to-_Dh- GWPS-i-s-t-he-volumet-o l--t-ak--(•-T-)-pu-rge/. Smaller quantities-of-7ýdT•diothfive gasare received-via the vent connections from the reactor coolantdrain tank (RCDT), the pressurizer relief tank, and the recycleholdup tanks.

Although the GWPS functions to contain radioactive gases, at notime do the radioactive gases constitute more than a smallfraction of the gases stored in the GDTs.

REV 5 9/9511.3.2-1 REV 4 4/94

Page 34: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

Since hydrogen is continuously removed in the hydrogenrecombiner, this gas does not build up in the GWPS. The largestcontributor to the nonradioactive gas accumulation is heliumgenerated by a B10 (n,x)Li 7 reaction in the reactor core. Thesecond largest contributors are the impurities in the bulkhydrogen and oxygen supplies.

The expected accumulation rate is 575 sf 3/year per unit(1150 sf 3/year total), assuming the following:

* Two-unit operation.

* A 0.7-sf 3/min hydrogen purge for the VCT of each unit.

* An 80-percent plant load factor for each unit.

* 99.95-percent pure hydrogen.

* 99.5-percent pure oxygen.

At this rate of accumulation and assuming zero leakage from theGWPS, the 14 GDTs have sufficient combined capacity to hold allthe gaseous wastes produced during 4 years of plant operationswithout any releases to the environment. This assumes that thewaste gas holdup tanks are operated with an initial charge of 5psig of nitrogen and the pressure in the tanks is allowed toaccumulate to 100 psig.

Operation of the system is such that fission gases from one unitare distributed throughout seven normal operation GDTs.Separation of the gaseous inventory into several tanks ensuresthat the allowable site boundary dose will not be exceeded inthe event any one of the .GDTs ruptures. Radiologicalconsequences of such a postulated rupture are discussed inchapter 15.

The GWPS also provides sufficient capacity to hold indefinitelythe gases generated during reactor shutdown. Nitrogen gas fromprevious shutdowns is contained in one of the shutdown GDTs.This is used to strip hydrogen from the RCS during subsequentshutdowns. The second shutdown tank is normally at low pressureand is used to accept relief valve discharges from the normaloperation GDTs, the hydrogen recombiners, and the waste gascompressors.

Table 11.3.2-1, based on the RCS activities given in table11.1-2, shows the maximum fission product inventory in the

11.3.2-2 REV 4 4/94

Page 35: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

GWPS over the 40-year plant life. Table 11.3.2-2, based on theRCS activities given in table 11.1-7, shows the expected fissionproduct inventory in the GWPS over the 40-year life assuming noreleases from the system.

Figures 11.3-.2-1 and 11.3.2-2 are based on the RCS activitiesgiven inr tables 11.1-2 and 11.1-7, respectively; the figuresshow that the quantity of fission gas activity accumulated after40 continuous years of operation is about twice the activityaccumulated after 30 days of operation. Most of the accumulatedactivity arises from short-lived isotopes reaching equilibriumin 1 month or less.

The difference between the 30-day and 40-year accumulations ispredominantly krypton-85. This accumulation of krypton-85 isnot a hazard to the plant operator because:

A. Krypton-85 is principally a beta emitter, for which thetanks themselves provide adequate shielding.

B. The activity of the system's inventory is distributedamong seven normal operation GDTs, minimizing inventoryin any single tank.

The removal of fission gas from the reactor coolant by the GWPSduring normal operation reduces the plant activity levels causedby a leakage of reactor coolant. Operation of the GWPS allowsthe collection of virtually all the krypton-85 released to thereactor coolant and can reduce the fission product gas inventoryin the RCS, as shown in table 11.3.2-3. Table 11.3.2-3 is basedon the RCS activities given in table 11.1-2. Provisions aremade to collect any gases from the RCDT and gases from therecycle holdup tanks.

Process flow diagrams are shown in figures 11.3.2-3 and11.3.2-4. Table 11.3.2-4 gives process parameters for keylocations in the GWPS for the normal operating mode with thenormal operation GDTs at low pressure (less than 25 psig). Thisoperating mode is used early in plant life and is shown infigure 11.3.2-3. Table I1.3.2-6 gives process parameters forkey locations in the system for the normal operating mode at theend of plant life, when the waste GDTs are at high pressure.This operating mode, shown in figure 11.3.2-4, is used from thetime the normal operation GDT pressure reaches 25 psig until theend of plant life.

Table 11.3.2-5 gives the process parameters for key locations inthe GWPS based on a 90-day holdup of the waste gases.

REV 5 9/9511.3.2-3 REV 4 4/94

Page 36: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.3.2.1 Component Design

The gaseous waste processing equipment design parameters aregiven in table 11.3.2-7. Since the GWPS performs no functionrelated to the safe shutdown of the plant, some components areclassified as nonnuclear safety. Component safety classes andthe corresponding code and code class are shown in section 3.2.

11.3.2.1.1 Waste Gas Compressor Packages

Two waste gas compressor packages are provided to circulategases around each GWPS system loop. One is normally in use andthe other on a standby basis.

The compressor packages are water-sealed centrifugaldisplacement machines which are skid mounted in a self-containedpackage. The waste gas compressor packages are primarilyconstructed of carbon steel. Mechanical seals are provided tominimize seal water leakage.

11.3.2.1.2 Catalytic Hydrogen Recombiner Packages

Three catalytic hydrogen recombiners are provided for the twounits. One recombiner per. unit is used in each main processloop to remove hydrogen from the hydrogen-nitrogen fission gasmixtures by oxidation to water vapor, which is removed bycondensation. The third recombiner is available on a standbybasis. The units are self-contained and are designed forcontinuous operation.

11.3.2.1.3 Waste Gas Decay Tanks

The tanks are vertical cylindrical type constructed of carbonsteel. There are a total of 16 waste decay tanks. Seven areused by each unit during-normal operation; the remaining two areshared between the two units and are used for shutdown andstartup.

11.3.2.1.4 Gas Decay Tank Drain Pump

The waste GDTs may contain water from condensation from theprocess gas or from maintenance operations. This pump is usedto drain water from the waste GDTs when there is insufficientpressure in the GWPS to transfer the fluid. Two canned motorpumps are provided, one for each set of seven normal operationGDTs.

11.3.2-4

Page 37: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.3.2.1.5 Waste Gas Drain Filter

Two waste gas drain filters are provided, one to filter thedrain water from each of the two process loops.

11.3.2.1.6 Waste Gas Traps

The gas traps serve to prevent undissolved gases from leavingthe GWPS via the liquid drains. For each of the two processloops there are four gas traps - one in the compressors drainline, one in the recombiner drain line, and two mounted in thewaste GDT drain line. There are also gas traps on each lowpoint of the gaseous portion of the system to avoid condensateaccumulation in the piping that may block the flow path.

11.3.2.1.7 Valves and Piping

Each valve in the hydrogen recombiner packages is designed tomeet the temperature, pressure, and code requirements for thespecific application in which it is used. The recombinercircuits contain manual valves provided with a metal diaphragmto prevent stem leakage and control valves provided with gaseousleakoffs returned to the GWPS. Other parts of the GWPS useelastomer diaphragm valves and control valves with bellowsseals. Relief valves have soft seats and operate at pressureswhich are normally less than two-thirds of the relief valve setpressure. The relief valves of the major components dischargeto one of the shutdown GDTs. This allows the discharge to bemonitored before being released. It also provides a means ofcontaining and detecting seal leakage across the relief valves.

All piping from the waste GDTs, up to and including theisolation valves, is designed to Seismic Category 1 requirementsto preclude any accidental release of gas to the environment.

11.3.2.2 Instrumentation and Control Design

The GWPS instrumentation is shown on the piping andinstrumentation diagram, drawings 1X4DB128 and 1X4DB129.

The instrumentation readout is located mainly on the wasteprocessing system (WPS) panel, while some instruments are readlocally.

All alarms are shown separately on the WPS panel and furtherrelayed to one common WPS annunciator on the main control board.

REV 6 4/9711.3.2-5 REV 5 9/95

Page 38: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

Where suitable, instrument lines are provided with diaphragmseals to prevent fission gas leakage through the instrument.

11.3.2.2.1 Waste Gas Compressor Package Instrumentation andControl

Figure 11.3.2-5 shows the location of the instruments on thewaste gas compressor package.

The compressors are interlocked with the seal, water inventory inthe moisture separators; they trip off on either high or lowmoisture separator level.

During normal operation the proper seal water inventory ismaintained automatically.

11.3.2.2.2 Hydrogen Recombiner Package Instrumentation andControl

The catalytic hydrogen recombiner packages are designed forautomatic operation with a minimum of operator attention.

Figure 11.3.2-6 shows the location of the instruments on thehydrogen recombiner. A multipoint temperature recorder monitorstemperatures at several locations in the packages. Process gasflowrate is measured by an orifice located upstream of thehydrogen recombiner preheater. Local pressure gauges indicatethe hydrogen recombiner process inlet pressure and the oxygensupply pressure.

The oxygen concentration. is monitored and controlled to ensurethat a flammable hydrogen-oxygen mixture does not occur. TheGWPS is provided with two analyzers to monitor oxygenconcentrations. One is between the oxygen supply and thehydrogen recombiner package, and one is downstream of thehydrogen recombiner. When the hydrogen concentration is abovethe lower flammability limit of 4 percent, the minimumconcentration of oxygen necessary for deflagration is 5percent.. The control function assigned to these analyzers is toautomatically terminate the oxygen supply before reaching GWPSoxygen concentrations favorable for hydrogen flammability. Eachhydrogen recombiner package also includes two hydrogenanalyzers. One monitors the process stream entering thehydrogen recombiner, and one monitors the discharge stream.

The controls and alarms incorporated to maintain the gascomposition outside the range of flammable and explosivemixtures are described below.

11.3.2-6 REV 5 9/95

Page 39: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

A. The maximum concentration of hydrogen that the hydrogenrecombiner can process in a single pass is 6-percenthydrogen by volume.

B. If the hydrogen recombiner feed concentration exceeds6-percent hydrogen by volume, a high-hydrogen alarmsounds to warn that all hydrogen entering the hydrogenrecombiner is not reacted. This alarm will be followedby a second alarm indicating high hydrogen in thehydrogen recombiner discharge. These alarms warn of apossible hydrogen accumulation in the GWPS.

C. If the hydrogen concentration in the hydrogenrecombiner feed reaches 9 percent by volume, ahigh-high hydrogen alarm sounds; the oxygen feed isterminated; and the VCT hydrogen purge flow isterminated. These controls limit the possibleaccumulation of hydrogen in the system to 3 percent byvolume.

D. If the oxygen concentration in the hydrogen recombinerfeed reaches 3 percent by volume, an alarm sounds andoxygen feed flow is limited so that no further Afncreasein flow is possible. This control maintains the systemoxygen concentration at 3 percent or less, which isbelow the flammable limit for hydrogen-oxygen mixtures.

E. If hydrogen in the hydrogen recombiner dischargeexceeds 1.5 percent by volume, an alarm sounds. Thisalarm warns of high hydrogen feed, possible reactormalfunction, or loss of oxygen feed.

F. If oxygen in the hydrogen recombiner discharge exceeds15 ppm, a high alarm sounds. If it exceeds 60 ppm, ahigh-high alarm sounds and oxygen feed is terminated.This control prevents any accumulation of oxygen in thesystem in case of reactor malfunction.

G. On low flow through the hydrogen recombiner, oxygenfeed is terminated. This control prevents anaccumulation of oxygen following system malfunction.

H. On high discharge temperature from the cooler-condenser(downstream from the catalytic reactor) oxygen feed isterminated. This protects against loss of coolingwater flow in the cooler-condenser.

REV 9 5/00REV 8 10/98

11.3.2-7 REV 5 9/95

Page 40: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

I. On high temperature indication by any one of sixthermocouples in the catalyst bed, the oxygen feed isterminated, and the VCT hydrogen purge flow isterminated.

J. On high temperature indication at the recombinercatalytic reactor discharge, oxygen feed to therecombiner is terminated.

11.3.2.2.3 Volume Control Tank Purge Flow Control

Each VCT purge line into the GWPS is equipped with a trip valve,a pressure-reducing valve and a hand-operated flow controlvalve. This arrangement will maintain a constant purge flow asselected by the operator.

Pressure fluctuations caused-by changes in the VCT water levelare absorbed by the pressure-regiulating valve, which maintains aconstant downstream pressure. This provides a constant headloss across the hand-operated control valve. Design flow is 0.7sf 3/min hydrogen, with a range of 0.3 sf 3/min to1.2 sf 3/min. When mixed with the 40 sf 3/min nitrogenstream, the maximum hydrogen content (both units operating) inthe recombiner feed is 6.0 volume percent.

The purge line trip valve closes as a result of:

A. A low-pressure signal from the VCT pressureinstrumentation. This prevents depressurization of theVCT if the hydrogen supply is lost.

B. A low-pressure signal from the gas compressor suctionline. Thissignal also stops the gas compressor.

C. Closure of the oxygen supply valve to the hydrogenrecombiner.- The purge line trip valve is closed onlyif the oxygen supply valves for both the normallyoperating recombiner and the standby recombiner areclosed.

11.3.2.3 System Operation

11.3.2.3.1 Startup Operation

The GWPS is initially purged with nitrogen to remove all air.During startup operation, one waste gas compressor, one hydrogenrecombiner, and one shutdown GDT are in service in the processloop serving that plant unit. The reactor is at cold

REV 9 5/0011.3.2-8 REV 5 9/95

Page 41: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

shutdown and the VCT contains nitrogen in the gas space. Reactorcoolant contains neither hydrogen nor fission gases, but it maybe saturated with air. While one unit is being started up, theVCT purge for the other unit is unaffected since each unit isserved by a separate process loop of the GWPS.

When the reactor startup procedure requires that a hydrogenblanket be established in the VCT gas space, fresh hydrogen ischarged into the VCT. The hydrogen-nitrogen mixture vented fromthe VCT enters the GWPS circulating nitrogen stream at the wastegas compressor suction. Nitrogen added to the GWPS accumulatesin the shutdown GDT, causing the tank's pressure to rise.

Initially, the VCT vent gas will be very lean in hydrogen, andalmost all the gas entering the GWPS will accumulate in theshutdown GDT. As the operation continues, however, the vent gashydrogen content will gradually increase until it is almosttotally hydrogen at t'he point when all of the nitrogen has beenremoved from the reactor coolant. At that time, hydrogen gas ispassing through the VCT and mixing with the circulating nitrogenstream to give a mixture of hydrogen in nitrogen at the hydrogenrecombiner inlet. A sufficient amount of oxygen is added in thehydrogen recombiner to react with the hydrogen to yield adischarge stream with a low residual concentration of hydrogenin nitrogen. After the water vapor is condensed and removed,the gas flow is directed to a shutdown GDT and from there to thewaste gas compressor and back to the hydrogen recombiner.

When the reactor coolant hydrogen concentration is withinoperating specifications, the shutdown GDT is isolated, and flowis routed to one of the normal operation GDTs provided fornormal power service. Gas accumulated in the shutdown GDT willbe retained for use during operations to strip hydrogen from thereactor coolant when a plant unit is shut down.

11.3.2.3.2 Normal Operations

During normal power operation, nitrogen gas with entrainedfission gases is continuously circulated around each GWPSprocess loop by one of the two waste gas compressors in theloop. Fresh hydrogen gas is charged to the VCT, where it ismixed with fission gases which have been stripped from thereactor coolant into the VCT gas space. The contaminatedhydrogen gas is continuously vented from the VCT into thecirculating nitrogen stream to transport the fission gases intothe GWPS. The resulting mixture of nitrogen-hydrogen fissiongas is pumped by the waste gas compressor to the hydrogen

11.3.2-9

Page 42: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

recombiner, where enough oxygen is added to reduce the hydrogento a low residual concentration by oxidation to water vapor on acatalytic surface. After the water vapor is removed, theresulting gas stream is circulated to a normal operation GDT andback to the waste gas compressor suction to complete thecircuit.

Each normal operation GDT is capable of being isolated, and onlyone tank is valved into operation in each process loop at anytime. This minimizes the amount of radioactive gases that couldbe released as a consequence of any single failure, such as therupture of any single tank or connected piping. A normaloperation GDT is valved into the GWPS recirculation loop untilthe pressure or curie content of the inservice GDT reaches avalue determined by approved plant procedure(s), after which itis isolated and another tank is placed in service. This processis illustrated in figure 11.3.2-3 for GDT pressure • 20 psig andas illustrated in figure 11.3.2-4 when .GDT pressure will exceed20 psig. By alternating the use of these tanks, the accumulatedactivity from one unit is distributed among all seven normaloperation GDTs in the process loop.

With continued plant operation, pressure in the normal operationwill gradually increase as nonremovable gases accumulate in thesystem. The initial system equipment lineup, as describedabove, will be from the waste gas compressor to the hydrogenrecombiner and, then to the normal operation GDT. As the normaloperation GDT'pressure builds up, compensation must be made byperiodic adjustment of the hydrogen recombiner backpressurecontrol valve. When the normal operation GDT pressure reachesapproximately 20 psig, the backpressure control valve will befully open, so that no more adjustment can be made. At thistime, the appropriate bypass lines are opened to line up theequipment for flow from the waste gas, compressor to the normaloperation GDTs and then to the hydrogen recombiner, as shown infigure 11.3.2-4. The hydrogen recombiner backpressure controlvalve is reset as required for the new arrangement, and thenormal operation GDT pressure indicators are switched to readhigh range. This arrangement is suitable for operation up to100 psig. Note that this high-pressure mode of operation willalso normally be utilized during shutdown/startup operations.

11.3.2.3.3 Shutdown and Degassing of the Reactor CoolantSystem

Plant shutdown operations are essentially startup operations inreverse sequence. The VCT hydrogen blanket is maintained untilafter the reactor is shut down and reactor coolant fission gasconcentrations have been reduced to desired level. During this

REV 6 4/9711.3.2-10 REV 5 9/95

Page 43: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

operation hydrogen purge flow may be increased to speed upreactor coolant degassing. At this time, the VCT hydrogen purgeis stopped for the plant unit being shut down. The normaloperation GDT in service for that unit is then valved out and anitrogen purge from a shutdown GDT to the VCT is begun for theunit being shut down. This shutdown GDT is placed in the GWPSprocess loop at the waste gas compressor discharge so that thegas mixture from the VCT vents to the waste gas compressorsuction, passes through the shutdown GDT and to the hydrogenrecombiner, where hydrogen is removed, and remaining gases arereturned to the waste gas compressor suction. The nitrogenpurge continues until reactor coolant hydrogen concentrationreaches the required level or chemical degassing may be used bythe operator to reduce RCS hydrogen concentrations during coldshutdown operations. Degassing is then complete, and the RCSmay be opened for maintenance or refueling. At this point theshutdown GDT may be isolated.

During the first plant cold shutdown, fresh nitrogen is chargedto the VCT to strip hydrogen from the reactor coolant. Theresulting accumulation of nitrogen in the shutdown GDT isaccommodated by allowing the tank pressure to increase. Duringsubsequent shutdowns, however, there is no additionalaccumulation since the gas from the first shutdown will bereused.

11.3.2.3.,4 System Drains

During operation, water may accumulate in the waste gascompressor moisture separator, in the hydrogen recombiner phaseseparator, and in the GDTs. Normally, the waste gas compressorand hydrogen recombiner drains will discharge to the VCT undermotive head provided by internal component pressure. Duringmaintenance, the. drains-are directed either to the recycleholdup tanks (if the drains contain dissolved fission gases) orto the waste holdup tank through the drain header (if the drainscontain no fission gases). A gas trap is provided in the drainlines from the waste gas compressors and hydrogen recombiners toprevent undissolved gases from leaving the GWPS.

All drains from the waste GDTs are manually operated. Dependingon the internal tank pressure on the drain routing, the wasteGDT drain pump is used or bypassed. As necessary, the tank isdrained by pumping the accumulated condensate to the VCT.However, during tank maintenance, waste GDT drains are routed tothe recycle holdup tank because the volume of water in a wasteGDT may be large enough to cause a noticeable dilution ofreactor coolant boron concentration. Gas traps are provided inthe waste GDT drain line to prevent the discharge of gases intoother parts of the plant. All drains from the GWPS are filteredbefore entering either the VCT or the recycle holdup tank.

REV 8 10/9811.3.2-11 REV 6 4/97

Page 44: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.3.2.3.5 Atmospheric Releases

Although the GWPS is designed to accommodate continuousoperation without atmospheric releases, the system designpermits controlled discharge of gas from the system. Before atank is emptied to the atmosphere via the plant vent, a gassample must be analyzed to determine and record the activity tobe removed. While the contents of a tank are being released tothe atmosphere, a trip valve in the discharge line will closeautomatically if a high activity level is detected in the plantvent effluent.

11.3.2-12

Page 45: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-ll

11.4 SOLID WASTE MANAGEMENT SYSTEM

The solid waste management system is designed to collect,process, and package all solid radioactive wastes generated as aresult of normal plant operation, including anticipatedoperational occurrences. The packaged waste is stored until itis shipped offsite to a licensed volume reduction facility orburial site. This system does not normally handle large wastematerials such as activated core components.

11.4.1 DESIGN BASES

The solid waste management system is designed to meet thefollowing objectives:

A. Provide packaging capability for spent radioactiveresins from the liquid waste processing and steamgenerator blowdown systems.

B. Provide a means to package crud from backflushablefilters.

C. Provide a means to package combustible dry solid wastes,such as paper, rags, and contaminated clothing.

D. Provide a means to transfer the spent filter cartridgesfrom filter vessels to shielded disposal containers in amanner which minimizes radiation exposure to operatingpersonnel and the spread of contamination.

E. Provide a means for compacting and packagingmiscellaneous dry radioactive materials, such as paper,rags, and contaminated clothing.

F. Provide temporary onsite storage of packaged wastes inthe event of delay or disruption of offsite shippingschedules.

G. Package radioactive solid wastes for offsite shipmentand disposal in accordance with applicable Department ofTransportation (DOT) and Nuclear Regulatory Commission(NRC) regulations, including 49 Code of FederalRegulations (CFR) 170-178 and 10 CFR 71.

REV 6 4/9711.4.1-1 REV 2 3/92

Page 46: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

The solid waste management system is designed and constructed inaccordance with Regulatory Guide 1.143, as described in section1.9, to meet the requirements of General Design Criterion (GDC)60 of 10 CFR 50, Appendix A. The seismic design classificationof the alternate radwaste, radwaste processing facility, andradwaste transfer bui.ldingsis-provoided in section 3.2. jTh-eradwaste-proces.ing faci ltio.t-- proai.de• t ollow useof op6rtabie

_ssems,(Aemineral, rs frtion systemde e~rin7iying.,-sol~iditicatioAlied by contractors forhandling solid wastes from plant operations duringallplantcond-i-tions-(-paragraph 11.4.2.A). D__-y=c.tive~wase_(.DAW.)f.ce-i-l-i-t--i-es-a-re-pprovided toprocess anfd stforeDAW(paragraph 11.4.2.5).

The solid waste management system design parameters are based onthe radionuclide concentrations and volumes consistent withoperating experience for similar reactor designs and with thesource terms of section 11.1.

he-e eil-dwefstte-ma-nagemesnt-system--•±;bo6rn~e-pr.cess Ients-areyre-l-ea'sedIt-ihr-ddgh the oýadV-a •t e=p-5•sn-g f-a~c-i]t y-ve nt-t-he

latmcfs45here-as4p5rt of the"I 0 CFR So; AppendikIk nalysis=-j

T~he _sol-idw_--s-te -managment-s ystem--s-des-gned-to--cZlet-7

[s o-l-id-i-f y7-pack}ageý-, ad t- 3ý-tmation-6- =Yotd"ndi:at:ro-,e r_. tcý pl ah£ i operati on or, maintenancepersnnel as low as , sreas~onab.uy_ailfievaJe £!ý±ý inacco-dance wi.t h-GDDC 0 CFR 50,,ppendix A•WandýRegu-latoryGu•8T8-n-- o orde rt-t-oT- Thatiain pe rsonne-l--expo suros--•re s--o-w'----

l 1 -~~qi~emets. C 6r1,0-6-CER-ý2:_ --ý6 uu@ f m• ] -Acce!E Ss- --t •the_'p roc(ýss I pfmm nt--an d-7,

s 'o :l d =w a E f6,-ý- Eoria g e -a-r-e a s-1- s -c Jen- ttre-1-e ýd -to i-nimrze-personne47expos--reb7y-sil---tabl "bartiers such a's locked doorfsor-gat-es--orj7control cardst--See paragrap-H-27.3.1.2and sect-onnd25)- -Thesocrr-waste management system has been designed to conform withthe design criteria of NRC Branch Technical Position ETSB 11-3.

11.4.1.1 Safety Design Bases

The solid waste management system performs no function related tothe safe shutdown of the plant, and its failure does notadversely affect any safety-related system or component;therefore, the solid waste management system has no safety designbasis.

REV 11 5/0311.4.1-2 REV 2 3/92

Page 47: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.4.1.2 Power Generation Design Bases

The solid waste management system is designed to minimize thevolume of solidified wastes and provide temporary onsite storagefor the packaged wastes. 'The system is designed for a 40-yearservice life, maximum reliability, minimum maintenance, andminimum exposure to operating and maintenance personnel. Thesystem is designed to have sufficient capacity based on normalwaste generation rates to ensure that maintenance or repair ofthe solid waste management system equipment does not impact powergeneration.

.. \vegpfsar\Chapll\11-4-1

11.4.1-3 REV 2 3/92

Page 48: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.4.2 SYSTEM DESCRIPTION

11.4.2.1 General Description

The solid waste management system consists of the following whichare shown in drawings AX4DBI05-1, AX4DBI05-2, AX4DBI05-5, lX4DBI48,IX4DB148-1, IX4DB148-2, lX4DBI48-3, IX4DB148-4, AX4DBI48-5,AX4DBI48-6, AX4DBI48-7, lX4DBI48-8, IX4DB148-9, lX4DBl48-10,IX4DB148-11, lX4DBI48-12, and IX4DB148-13.

* Resin transfer.

* Backflushable filter system.

* Crud transfer.

The activity of the influents to the solid waste managementsystem is dependent on the activities of various fluid systems,such as the boron recycle system, liquid waste processingsystem, chemical and volume control system, spent fuel poolcooling and cleanup system, steam generator blowdown system, andcondensate polishing demineralizer system. Reactor coolantsystem activities and the decontamination factors for thesystems given above also determine the influent activities tothe solid waste management system.

Table 11.4.2-1 lists the parameters used in calculation of theestimated activity fed to the solid waste management system.Table 11.4.2-2 lists the estimated expected activities of wastesto be processed on an annual basis, their physical form andsource, and their isotopic makeup and curie content. Table11.4.2-3 provides the same information based on the maximumexpected activities of the input wastes. The estimated annualquantities of radwaste input to the solid waste managementsystem and the estimated quantities of radwaste to be shippedoffsite are presented in table 11.4.2-4. The estimated expectedcurie and isotopic content of wastes to be shipped offsite foreach waste category is presented in table 11.4.2-5. Table11.4.2-6 presents the same'information based on expected maximumactivities.,

Section 11.1 provides the bases for determination of liquidsource terms which are used to calculate the solid waste sourceterms. The data presented in tables 11.4.2-2, 11.4.2-3,11.4.2-5, and 11.4.2-6 are conservatively based on section 11.1and the following additional information:

REV 8 10/98REV 6 4/97REV 5 9/95

11.4.2-1 REV 2 3/92

Page 49: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

A. As a basis for the shipped-from-site activities givenin tables 11.4.2-5 and 11.4.2-6, 30 days of decay priorto shipping is assumed. The major contributors to theactivity levels in the system are radionuclides havinglong half-lives; therefore, further onsite decay ofradionuclides provides limited benefit.

B. The miscellaneous dry and compacted waste volume isbased on reference 1.

C. Shipping volumes from the cartridge filter handlingsystem are based on packaging (per 55-gal drum):

1. One spent filter cartridge.

2. The drum is prelined with cement with an integralcavity to accept a filter.

Section 11.1 provides the bases for the quantity of primary andsecondary resins. Section 11.2 provides the basis for thequantity of chemical drain wastes, while reference 1 provides thebasis for the remaining quantities presented in table 11.4.2-4.

11.4.2.2 Component Description

Codes and'standards applicable to the solid waste managementsystem are listed in table 3.2.2-1. The solid waste managementsystem is housed within buildings designed to meet the seismicrequirements of Regulatory Guide (RG) 1.143. Conformance withRG 1.143 is to the extent specified in section 1.9.

11.4.2.3 System Operation

11.4.2.3.1 Resin Transfer System

The resin transfer system provides the capability for remotetransfer of spent radioactive resin from the auxiliary buildingto the radwaste processing facility.

11.4.2.3.2 Backflushable Filter System

The backflushable filter system provides the means to remove anddeliver radioactive crud from certain process streams to thecrud transfer system. The system consists of the filterssummarized in table 11.4.2-7, a backflushable filter crud tank,and a centrifugal pump. Each backflushable filter is operated

REV 11 5/03REV 8 10/98REV 4 4/94

11.4.2-2 REV 2 3/92

Page 50: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

in a similar manner. A sufficient buildup of crud on the filtersignals an annunciator and the operator then initiates theautomatic filter backflush sequence (Unit 1 only). The operatorcan manually carry out the backflush sequence if it is desired.The backflush sequence isolates the filter, opens a line to thebackflushable crud tank, and introduces approximately 8 ft3 ofhigh-pressure (350 psig) nitrogen from a nitrogen accumulatorthrough the filter. The nitrogen accumulator is supplied by theauxiliary gas system. The crud removed from-the filterscollects in the backflushable crud tank. After each backflushoperation the lines and tank are water flushed. The contents ofthe backflushable crud tank may be slurried to the radwasteprocessing facility at operator discretion or upon high tanklevel annunciation.

11.4.2.3.3 Filter Handling System

The filter handling system is a semiremote system which providesthe capability to remove spent radioactive cartridge filters fromtheir filter housings and place them in drums with externalshielding or use of a transfer cask for transport to the radwasteprocessing facility. The techniques used in the filter handlingsystem included the consideration of the following:

* Operator exposure.

* Time and manpower requirements.

* Potential for the spread of contamination.

* Potential for mechanical difficulties.

Logistics for filter handling.

The semiremote system, as the name implies, requires the operatorto be in the proximity of the filters; however, operator exposureis minimized by distance and shielding.

The filter handling system consists of a working plug, abell-shaped shielded transfer cask, a mobile cask-to-drumtransfer station, and drum capper. The working plug is designedto fit in a hatch above the filter housing and has provisions forviewing the top of the filter housing and penetrations to allowlong handled tools to be used for the removal of the filterhousing top. The bell-shaped shielded transfer cask is used toretract the spent filter cartridge from its housing and transportit to the filter transfer station where the filter is placed in ashielded drum and capped. The filters in the shielded drums aretransported to the radwaste processing facility for packaging.The filters may also be transported using the transfer caskdirectly to the radwaste processing facility for packaging.

REV 11 5/03REV 6 4/97

11.4.2-3 REV 2 3/92

Page 51: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

11.4.2.4 Portable Radwaste System

VEGP will utilize vendor-supplied portable radwaste equipment toprovide for disposal of spent resins, radioactive cartridgefilters, backflushable filter crud, and chemical wastes viadewatering or solidification. Details of this equipment areshown on drawings AX4DBl24-2, AX4DBI24-3, and AX4DBI24-4. Inaddition, a portable demineralizer system and a filtration systemare available as alternate means of processing the contents ofthe waste holdup tank, chemical drain tank, floor drain tank, andboron recycle holdup tank. Details of this equipment are shownon drawings AX4DBI24-2, AX4DBI24-3, AX4DBI24-4, and AX4DBI24-5.These systems are housed in the radwaste processing facilitywhich is shown on drawing AX4DE357.

Isolation valves are provided to allow processing of wastestreams at the radwaste processing facility. The valves aremanually and remotely operated to achieve the desiredconfiguration. Delivery of waste streams to the radwasteprocessing facility is controlled from local panels near thewaste stream source. Flanged connections are provided at theradwaste processing facility to interface with the vendor-supplied systems. Major components for portable radwaste systemstypically include process liners, process skids, and controlpanels. A separate radwaste processing facility control room anddressout area is provided to facilitate system operation.

Radioactive condensate polishing demineralizer resins,backflushable filter crud, and spent resins from the liquidwaste processing system and the steam generator blowdown systemwill be dewatered. The dewatering system supplied by vendorallows the water to be-removed from the spent resins in theshipping containers. A vendor-supplied container vent isprovided for the shipping containers thereby minimizing leakageinto the building. A vent line to a monitored HVAC exhaust ductin the radwaste processing facility is provided. In addition,demineralizer resins from the portable demineralizers (asdiscussed in section 11.2) can be sluiced to the container fillskid for dewatering and disposal.

An NRC approved process control program (PCP) will be required ofthe vendor and appropriately referenced in the VEGP PCP prior toany actual operation. If the burial site does not acceptdewatered resins or the waste form criteria cannot be met, VEGPwill have the ability to solidify resins utilizing a portablesolidification system. Cartridge filters will be loaded intoliners for shipment offsite.

Solidification/dewatered liners will normally be shipped afterfilling and proper cure time, provided the proper shielding isavailable, without exceeding DOT radiation limits. If

REV 11 5/03REV 6 4/97REV 5 9/95

11.4.2-4 REV 2 3/92

Page 52: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

49 CFR 173 dose limitations cannot be met with the availableshielding, the liners are stored ard allowed to decay until theappropriate shielding is available. Onsite storage for decay ofshort-lived radionuclides is accomplished both prior tosolidification in holdup tanks and in appropriate onsite storageareas.

Short-term storage of solid radwaste for the purpose of activityreduction by radioactive decay is provided by shieldedenvironmental containers located on a concrete pad adjacent tothe southeast corner of the abandoned radwaste solidificationbuilding. High-integrity containers, containing the solidradwaste, are inserted into the shielded environmental containerswhich are right circular cylinders of reinforced concrete ofsufficient thickness to provide appropriate shielding and normalenvironmental protection.

11.4.2.5 Dry Active Waste Facilities

Low level dry wastes are collected in drums, plastic bags, andother methods as approved by the health physics department, atappropriate locations throughout the plant, as dictated by thevolume of these wastes generated during operation or maintenance.

Large components and equipment which have been activated duringreactor operation and which are not amenable to solidification,compaction, or volume reduction are handled either by qualifiedplant personnel or by outside contractors specializing inradioactive materials handling and are packaged in boxes orshipping casks of appropriate size.

Two buildings have been designed for handling dry active wastes(DAW) from plant operations:

A. The DAW processing building was designed to be used forsorting and compacting DAW. This building-may also beused to store radioactively contaminated outage materialand other radioactively contaminated items as needed.

B. The DAW storage building is used to store DAW. Thisbuilding may also be used to store radioactivelycontaminated .outage material and other radioactivelycontaminated items as needed.

11.4.2.5.1 Dry Active Waste Processing Building

uAWota-gee equipment --- and-other--ra'di-oa-c-t-i-•iiv -- contýa minated7'j--_- tot-hep - asr - -° (deto thai "i----n

c-t-•-iners or( contained-in some manner which will prevent anyleakage of radioactive material during conditions incident to

REV 9 5/00REV 6 4/97

11.4.2-5 REV 2 3/92

Page 53: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR- 11

normal transportation; The radioactive material is packaged suchthat contamination on the outer container/containment surface isbelow administrative limits. The transport path remains withinthe owner-controlled area.

The DAW processing building has separate areas for incomingradwaste containers, sorting and compaction of radioactive waste,handling of nonradioactive dry waste, and storage of emptycontainers. The DAW is sorted to separate usable material,radioactive waste, and nonradioactive waste. Radioactive wasteis compacted into packaging that will comply with the criteria of10 CFR part 71 to minimize the need for repackaging for shipment.

A sorting table and dry waste compactor are provided. Thesorting table and trash compactor have designs that direct anyairborne dusts created by the sorting or compaction operationthrough an exhaust fan and filter and then to the buildingventilation system.

T-Fi -i--Z----i-n-g-h-a-s--ockab-l-e-door-s-a.nd-is-enc-l-osed-by-a-f-ence-wi-t-h.•1-07.• k-a15 l _-•gates- - e p urp S • f•-t-•- =•f e-n-•e,ýf -t o-pre •eln-t -- ,/

czErtypatr-'svri y-bu-ild-i-ng~s ecu-rity--_ý

The building is provided with automatic wet-pipe sprinklersystems designed for an Ordinary Group II Hazard. Ionization andphotoelectric smoke detectors are provided. Smoke detectorsactuation or sprinkler head water flow initiates localaudible/visual alarms external to the building. A fire hosestation with portable extinguisher is provided. The wastecontainer materials used do not support combustion.

11.4.2.5.2 Dry Active Waste Storage BuildingDAW--ou-t-age-equi-pment--nd-7ohern

radi-a-tve--arial--aretransported to the storage facility inpackaging that will comply with the criteria of 10 CFR Part 71 orin containers that will prevent leakage of any radioactivematerial incident to normal transportation. The waste-i.sstored,in the interior of the building. L:]k-a-l-e--deor-s-and---a-fence-withaock abcl--are e-p-rov-i-de d.

The building is provided with automatic wet-pipe sprinkler systemand smoke detectors. Fire alarms external to the building areprovided. The waste container materials used do not supportcombustion.

REV 9 5/00REV 6 4/97

11.4.2-6 REV 2 3/92

Page 54: Radioactive Waste Management System and Effluent Control ... · steam generator feed pump turbine operation. General features of the generator include a 1,350,000-kVA output at 1800

VEGP-FSAR-11

REFERENCES

1. "A Waste Inventory Report for Reactor and Fuel-FabricationFacility Wastes," ONWI-20, NUS-3314, March 1979.

11.4.2-7 REV 2 3/92