radionet fp7
DESCRIPTION
RadioNet FP7. Advanced Radio Astronomy in Europe Contract no.: 227290. 26 beneficiaries. Overview of project Project Organisation Project reporting Uniboard Plan/Budget Questions?. Overview. Three types of activities: Networking Activities Trans National Access - PowerPoint PPT PresentationTRANSCRIPT
Uniboard Kick OffFebruary 26th 2009
RadioNet FP7
Advanced Radio Astronomy in Europe
Contract no.: 227290
Uniboard Kick OffFebruary 26th 2009
26 beneficiaries
Uniboard Kick OffFebruary 26th 2009
• Overview of project• Project Organisation• Project reporting• Uniboard Plan/Budget• Questions?
Uniboard Kick OffFebruary 26th 2009
Overview
Three types of activities:
- Networking Activities- Trans National Access- Joint Research Activities
Uniboard Kick OffFebruary 26th 2009
RadioNetCoordinator
Garrett
EuropeanCommission
Project Scientist(0.6FTE)
Project Manager (0.6 FTE)Van Es
Admin (0.4 FTE)Public Outreach
Joint Research Activities Networking Activities Transnational Access
J1: ALBiUS van Langevelde (JIVE)
J2: AMSTAR+Guelin (IRAM)
J3: APRICOTWilkinson (UMAN)
J4: UniBoardSzomoru (JIVE)
Spectrum Management Ambrosini (INAF)
Training for Radio Astronomers Richards (UMAN)
Engineering Forum:Keller (MPIfR)
Science workshop working group:Venturi (IRA)
EVN Campbell (JIVE)
LOFAR Vermeulen (ASTRON)
APEX Olofsson (OSO)
Effelsberg Krauss (MPIfR)
IRAM Cox (IRAM)
JCMT Davis (STFC)
WSRT Vermeulen (ASTRON)
MERLIN Garrington
(UMAN)
SRT Mack (IRA)
RadioNet Management Team (RMT): Project Coordinator, Project Manager, Project Scientist, JRA Work Package Leaders
Uniboard Kick OffFebruary 26th 2009
Networking Activities
• Management• Science Working Group• Engineering Forum• Training• Spectrum Management
Uniboard Kick OffFebruary 26th 2009
Trans National Access
• A program with support for astronomers to observe using a range of world leading radio telescopes
• 10 infrastructures: EVN, LOFAR, e-Merlin, Effelsberg, SRT, JCMT, APEX, PdBI, PV, WSRT
Uniboard Kick OffFebruary 26th 2009
Joint Research Activities
AMSTAR+APRICOT (kick off March 12th)ALBiUS (kick off 2 -3 March)UniBoard (kick off 26 -27 February)
Uniboard Kick OffFebruary 26th 2009
Total RNFP7 Budget 13,6M€
7%4%
33%56%
Management
NA
TNA
JRA
Uniboard Kick OffFebruary 26th 2009
EC Contribution per Activitytotal 10 M€
9%6%
45%
40%
Management
NA
TNA
JRA
Uniboard Kick OffFebruary 26th 2009
0
500.000
1.000.000
1.500.000
2.000.000
2.500.000
JRA Budget and EC Contribution
Budget
Requested EC
Budget 1.757.860 1.954.107 2.027.235 1.851.715
Requested EC 799.900 1.199.998 1.237.412 803.484
ALBiUS AMSTAR+ APRICOT UniBoard
Uniboard Kick OffFebruary 26th 2009
ID WBS Task Name
305 WP.9 WP9 UniBoard306 WP.9.3 Hardware307 WP.9.3.1 System design
308 WP.9.3.2 Board design
309 WP.9.3.3 Completed board design
310 WP.9.3.4 Board implementation
311 WP.9.3.5 Production run
312 WP.9.3.6 Basic hardw are test
313 WP.9.3.7 Test & Integration
314 WP.9.3.8 Completed test
315 WP.9.3.9 Preparation for 2nd phase
316 WP.9.4 Software317 WP.9.4.1 Correlator318 WP.9.4.1.1 VHDL design
319 WP.9.4.1.2 Completed VHDL design
320 WP.9.4.1.3 VHDL implementation
321 WP.9.4.1.4 Test & Integration
322 WP.9.4.1.5 VHDL implementation 2nd phase
323 WP.9.4.2 Pulsar Binning Machine324 WP.9.4.2.1 VHDL design
325 WP.9.4.2.2 Completed VHDL design
326 WP.9.4.2.3 VHDL implementation
327 WP.9.4.2.4 Test & Integration
328 WP.9.4.2.5 VHDL implementation 2nd phase
329 WP.9.4.3 Digital Receiver330 WP.9.4.3.1 VHDL design
331 WP.9.4.3.2 Completed VHDL design
332 WP.9.4.3.3 VHDL implementation
333 WP.9.4.3.4 Test & Integration
334 WP.9.4.3.5 VHDL implementation 2nd phase
335 WP.9.4.4 Generic control softw are
30-10
4-2
30-10
30-10
30-10
Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
Uniboard Kick OffFebruary 26th 2009
Project Organisation
Governance Structure:
- The Governing Board- The Executive Committee- The Coordinator- The Management Team
Uniboard Kick OffFebruary 26th 2009
Governing Board
• Has representative of each beneficiary• The decision making body• Meets once a year
This year: 31st of March connected to project kick off
Uniboard Kick OffFebruary 26th 2009
Executive CommitteeRadioNet
CoordinatorMike Garrett
Project ScientistCorina Vogt
(0.6FTE)
Project Manager (0.6 FTE)André van Es
Admin (0.4 FTE)Emmy Boerma
Aukelien v/d PollPublic Outreach
Joint Research Activities
J1: ALBiUS van Langevelde (JIVE)
J2: AMSTAR+Guelin (IRAM)
J3: APRICOTWilkinson (UMAN)
J4: UniBoardSzomoru (JIVE)
RadioNet Management Team (RMT): Project Coordinator, Project Manager, Project Scientist, JRA Work Package Leaders
Chair of the BoardVice Chair of the Board
Meets 4 times a year
Supervises the execution of the project
Implement decisions of the board
Report on project progress
(so JRA’s report each quarter to management)
Guards Intellectual Property
Uniboard Kick OffFebruary 26th 2009
Project Management
• Assists the coordinator• Consists of:
– Coordinator– Project Manager– Project Scientist– Project Administration
Uniboard Kick OffFebruary 26th 2009
Contact Details:Project Manager: André van Es
Email: [email protected]: + 31 521 595 248Mobile: + 31 651 433 473
Contact for all questions related to DoW, Budget, EC-financing, project reporting etc..Project Scientist: Corina VogtEmail: [email protected]: + 31 521 595 771Contact for Outreach, Coordinates NAAdministration: Aukelien van den PollEmail: [email protected]: + 31 521 595 511Contact for TNA and NA Travel Claims, Website and WikiAdministration: Emmy BoermaEmail: [email protected]: + 31 521 595 259Contact for Overall RadioNet Budget, JRA Budget Question, Financial Reporting to EC
(C-forms etc..)
Uniboard Kick OffFebruary 26th 2009
Website+WikiNew website will be launched: www.radionet-eu.orgWill have CM system, each activity can update
own contentEven more important Wiki www.radionet-eu.org/fp7wikiUse wiki for: exchanging documents, announcing
meetings, minutes of meetings, list of everyone involved in RadioNet.
Wiki will also be used for project reportingContact: Aukelien
Uniboard Kick OffFebruary 26th 2009
Project Reporting
• RadioNet FP7 has only 2 reports to EC !!(midterm + final)
• Internal RNFP7 Reporting for JRA– Quarterly – Extensive Reporting each 6 months incl.
budget estimates – (advance payment each 6 months is based on
work performed and work planned)
Uniboard Kick OffFebruary 26th 2009
UniBoard Budget
WP9 UniBoard Personell Costs
Total mpower (month)
EC funded manpower
(month)
Direct Costs
Incirect Costs Total EC
Contribution
JIVE 249.900 51 28 108.500 215.040 573.440 294.840ASTRON 285.600 48 23 2.875 192.000 480.475 173.794UMAN 165.000 36 23 2.875 100.725 268.600 129.950INAF 88.000 24 19 2.375 54.225 144.600 86.450KASI 200.000 48 0 200.000BORD 62.500 15 13 1.625 38.475 102.600 66.950UORL 50.000 12 10 1.250 30.750 82.000 51.500
1.101.000 234 116 119.500 631.215 1.851.715 803.484
Uniboard Kick OffFebruary 26th 2009
Questions??