rail baltica activities’ status in estonia...future timeline: technical solution fixing: q1 2019...
TRANSCRIPT
![Page 1: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/1.jpg)
Rail Baltica activities’ status in EstoniaRiia SillaveRail Baltic Estonia CEO
Press conference 23rd January 2019
![Page 2: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/2.jpg)
Rail Baltica route alignment in Estonia approved
▸ Preliminary design in Estonia completed
▸ New land aquisition law passed
▸ Spatial planning and route alignmentapproved
![Page 3: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/3.jpg)
Technical design and construction in 2019
▸ Ülemiste passenger terminal▸ Pärnu passenger terminal▸ Muuga multimodal freight terminal▸ Bridges/viaducts on the track
+▸ Environment and horizontal studies
Railwidth 1435mm
![Page 4: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/4.jpg)
Ülemistepassenger terminalStatus quo
▸ Detailed planning process is ongoing▸ Architectural contest is under preparation▸ Preliminarydesign of railway infrastructure
under preparation
Future timeline:▸ Architectural contest launch: Q1 2019▸ Preliminarydesign of railway infrastructure:Q1
2019▸ Detailed design of railway infrastructure and
terminal building: 2020▸ Constructionof the terminal: 2021-
2025
![Page 5: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/5.jpg)
Pärnupassenger terminal
Status quo▸ Architectural competition carried out in
2014▸ Detailed plan hasbeen approvedby the
local government▸ Detailed technical design tender for the
terminal and related facilities is ongoing
Future timeline:▸ Detailed design of terminal building and
related facilities: 2019-2020▸ Detailed technical designof railway
infrastructure: 2020-2021▸ Construction of the terminal: 2022-2025
![Page 6: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/6.jpg)
Muugamultimodal freight terminal
Status quo▸ Feasibility studywith study of technological and spatial needs carried out▸ Sketchdesign regarding possible technical
solutions is ongoing▸ Operational plan in harbor area in development
Future timeline:▸ Technical solution fixing: Q1 2019 ▸ Detailed planning: 2019-2020▸ Preliminary design of freight terminal: 2019▸ Detailed technical design of freight terminal
and related facilities: 2020-2021▸ Civil works:2021-2025
![Page 7: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/7.jpg)
Environment and horizontal studies
▸ Study on the habitat of capercaillies▸ Studies on plants and wildlife▸ Study on Rääma bog water regime▸ 3rd phase of archaelogical studies
▸ Availability of mineral resources▸ Implementation model for construction and
construction logistics
![Page 8: Rail Baltica activities’ status in Estonia...Future timeline: Technical solution fixing: Q1 2019 Detailedplanning: 2019 -2020 Preliminary design of freight terminal: 2019 D. etailedtechnical](https://reader035.vdocument.in/reader035/viewer/2022070100/600d51ea6e8843382824ccb0/html5/thumbnails/8.jpg)
Thank you!