january 23d 2009 P. Brugts
1
Rail freight corridor Rotterdam - Genoa
from sea to sea
together for success
january 23d 2009 P. Brugts
2
Agenda
Background and objectives
goals achieved so far
1
2
3
4
Organisation of programme
Work programme
january 23d 2009 P. Brugts
3
Agenda
Background and objectives1
january 23d 2009 P. Brugts
4
Corridor Rotterdam-Genoa
5 IM‘s
Transport volume in 2005: 28.5 bn tkm2020e: 56,6 bn tkm
Corridor lengthGeography: 1.400 kmTotal: 2.100 km
40 Intermodal terminals2 Sea ports6 Inland ports
1. Background, objectives
january 23d 2009 P. Brugts
5
Densely populatedHighly urbanised London,
Amsterdam, Brussels, Frankfurt,Basle, Zurich and Milan
Links the most active economic regions in Europe
Major industries
Freight Corridor links economic regions
Source: Wirtschaftsräume in Europa (Klett)Source: Gert-Jan Hospers 2002, 2003.
1. Background, objectives
january 23d 2009 P. Brugts
6
Strategic objectives
Develop European rail freight services
Meet market requirements
Shift traffic from road to rail
1. Background, objectives
Reliability+26%
Capacity+52% Time
-20%IM-Cost-10–15%
Expected Achievements
january 23d 2009 P. Brugts
7
Create interoperability
CP
BR
NS
SNCB/
NMBS
PKP
SNCF
MAVSBB/CFF/FFS ÖBB
CD
DSB
SNCFR
BDZ
FS
OSE
NSB SJ
VR
DB AG
CFL
JZ
HZSZ
RENFE
UZ
EVR
LDZ
LG
CFM
BZD
ZBH
ZSR
IE
HSH
EBICAB 700/L 10000
EBICAB 900
ZUB 123AWS
ATB/ATB-NG
TVM/KVB
ASFA/LZB
EBICAB 700
SIGNUMZUB
BACC/SCMT
EVM
SHP
IINDUSI / LZB
INDUSI/LZB
TBL
LS 90
Non electrified
Powerrail DC
1,5 kV DC3 kV DC
15 kV 16 2/3 Hz
25 kV 50 Hz3 kV DC/ 25 kV 50 Hz
ATC system
One locomotive
One CCS system
Harmonised operational procedures
Harmonised power systems
Enhanced cross borderprocedures
Simplified procedures for customers C
reat
eIn
tero
pera
bilit
y
1. Background, objectives
january 23d 2009 P. Brugts
8
Multicourante E-locs crossing borders
1. Background, objectives
january 23d 2009 P. Brugts
9
increase competitiveness of rail freight
Source : ERIM interim report, pp. 9, 13, based on TEN-STAC data
300-500 500-700 700-1000 >1000
2005
2020
17.0 15.1 19.5 22.217.3 16.1 22.6 27.1
[km]
[%]
Modal split railTraffic increase rail
Throughput sea ports
28.5 bn tkm in 200556.6 bn tkm in 2020e
19.6% in 200523.1% in 2020e
Rotterdam 376 Mio. t in 2005Genoa 50 Mio. t in 2005
1. Background, objectives
january 23d 2009 P. Brugts
10
Agenda
Organisation of programme 2
january 23d 2009 P. Brugts
11
Political commitments: LOI
A working group will improve the quality of railtraffic on the Corridor
Establish an EU deployment plan forERTMS
Implement ERTMS on the freightcorridor
+ +
EE
IG C
orrid
orR
otte
rdam
–G
enoa
Ministries ofNL, DE, CH, ITLugano 2003
EC, CER, UIC, EIM, UINIFE, Brussels 2005
Ministries ofNL, DE, CH, ITBregenz 2006
2. Organisation of programme
january 23d 2009 P. Brugts
12
Working Programme of EEIG
TAF TSI
- Process Gap Analysis- Monitoring of other TAF
projects- Value added services
ERTMS
- Technical Interoperability- Tendering & Rollout- Homologation & Cross Acc.
Operations
- Operational Rules- Traffic Management- Training of Personnel
Capacity
- Corridor Traffic Forecast - Elimination of Bottlenecks- Infrastructure Parameters
Traffic Quality
- OSS Optimization- Traffic Performance- Improving Quality- Int. Capacity Allocation
Terminal Studies
- Performance Parameters- Criteria of Terminals- Criteria of Ports- Improvement Options
2. Organisation of programme
january 23d 2009 P. Brugts
13
ProRail
DB RFISBB*BLS*
WGCsPIMs
Programme Management Office
Management Committee
Executive Board
CER & ERFAand
two designated RU’s from each
country
RUAdvisory Board
ProRail
DB RFISBB*BLS*
WGCsPIMs
Programme Management Office
Management Committee
Executive Board
ProRail DB RFISBB*BLS*
WGCs
Committee of IM
Executive Board of IM , MoT
Cooperation of Infra Managers & RU’s
2. Organisation of programme implementation and the EEIG
january 23d 2009 P. Brugts
14
Agenda
goals achieved so far3
january 23d 2009 P. Brugts
15
Organisational results
� Integrated working organisation set up
for the corridor
� Strategic business plan developed as the
starting point of all activities
� Corridor working groups established
� Implementation plan which contains all
actions and measures
� Monitoring and reporting process
3. goals achieved so far
january 23d 2009 P. Brugts
16
• April 2007 = 8.7 days
• May 2008 = 6.4 days
time for international ad hoc train pathtime for international ad hoc train path
Quality of services has been improved:
by reducing response time
3. goals achieved so far
january 23d 2009 P. Brugts
17
by streamlining train paths
2007 2009Annual time table process
3. Work programme and goals achieved so far
january 23d 2009 P. Brugts
18
by harmonising the timetable adjustments
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
200612 intermediate adjustm
20075 intermediate adjustments
AnnualTime table change
3. goals achieved so far
january 23d 2009 P. Brugts
19
Betuweline in NL: 2007
4.8 b €
january 23d 2009 P. Brugts
20
Lötchberg base tunnel in CH: 2007
4.7 b €
january 23d 2009 P. Brugts
21
Agenda
Work programme4
4. Work programme
january 23d 2009 P. Brugts
22
Debottleneck capacity to meet future demands
Rotterdam
Köln
Basel
BelDo
MilanoNo
Genova
EmmerichVenlo
Mainz/Wiesbaden
Mannheim
Rotterdam
Köln
Basel
BelDo
MilanoNo
Genova
EmmerichVenlo
Mainz/Wiesbaden
Mannheim
Rotterdam
Köln
Basel
BelDo
MilanoNo
Genova
Emmerich
Mainz/Wiesbaden
Mannheim
Rotterdam
Köln
Basel
BelDo
MilanoNo
Genova
2020
EmmerichVenlo
Mainz/Wiesbaden
Mannheim
ChiLi Li LiLi
ChiChiChi
Betuweroute16.06.2007 / 4580 M
Lötschberg15.06.2007 / 2800 M
Piattaf. Luino2007 / 445 M
Katzenberg
2012 / 340 M
3 tr. RütiCastione,
Giubiasco
Oberhausen2004
Osterpai2007
Ka-Offenbg4 track 2004
Blocksection2011 / 90 M
Gotthard 2017 / 5900 M
Ceneri 2019 / 1400 M
Ok – use < 80% Critical - use 80 – 100 %
Bottleneck - use > 100 %
2015 2010 2008
Venlo
Offbg.-Kenzgn. 2019
Rastatt Süd 2015
3. Track E-O
2013
4. Work programme
january 23d 2009 P. Brugts
23
Total future investments
0
1000
2000
3000
4000
5000
6000
7000
NL=213 DE=4558 CH=5742 IT=6781
20082009-2025
19221 166
4392
382
5360
16,5
6764
Total = 17.3 b €2008 = 0.586 b 2008 = 0.586 b €€
Figures in [Mio. €]
4. Work programme
january 23d 2009 P. Brugts
24
Capacity enlargements in near future
Gotthard base tunnel
Karlsruhe - Basel
4. workpgromme
january 23d 2009 P. Brugts
25
scope includes terminals and end-customers4. Work programme
january 23d 2009 P. Brugts
26
ETCS operations on the corridor in 2015
Train borneTrack side
2.3.0 d
3
3*
3
≥ 2.3.0 d
3
3
3
4. workprogramme
january 23d 2009 P. Brugts
27
Corridor: part of EU masterplan freight
january 23d 2009 P. Brugts
28
Thank you for your attention
EEIG Corridor
Rotterdam-GenoaStefan WendelManaging Director
Phone +49-(0)69-265-45440Fax +49-(0)69-265-45442Mobil +49-(0)[email protected]
EEIG CORRIDOR EEIG CORRIDOR
ROTTERDAMROTTERDAM--GENOAGENOA
Peter Brugts
Ministry of Transport Netherlands
+31(0)652596045