rail method of measurement 2 detailed measurement
TRANSCRIPT
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
1/106
Rail Method of Measurement
Detailed Measurement
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
2/106
This Page is Intentionally Blank
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
3/106
Acknowledgements
This document has been developed in association with rail industry partners andprofessional bodies.
Further consultation with other industry bodies including the ICE, RICS, CECA, RIA willfollow as part of the ongoing industry consultation
© 2014 Network Rail Infrastructure Ltd
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
4/106
This Page is Intentionally Blank
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
5/106
Contents
Table of Figures................................................................................................................................4
PREFACE.........................................................................................................................................5
Foreword to Rail Method of Measurement – Volume 2 – Detailed Measurement ...........................6
1 Principles of Application ......................................................................................................7
1.01 Introduction..........................................................................................................................7
1.02 Purpose ...............................................................................................................................7
1.03 Structure of the RMM Suite of Documents..........................................................................7
1.04 Use of the RMM Suite of Documents ..................................................................................8
1.05 Format and Layout ..............................................................................................................8
1.06 Alignment with CESMM 4....................................................................................................9
1.07 Form of Contract..................................................................................................................9
1.08
Cost Analysis, Benchmark Analysis and Cost Models......................................................10
1.09 Details of works .................................................................................................................11
2 Use of the Work Classifications.........................................................................................12
2.01 Descriptions.......................................................................................................................12
2.02 Coding for Cost Analysis...................................................................................................12
3 Definitions..........................................................................................................................13
3.01 Reference Terms...............................................................................................................13
3.02 Measurement Terms .........................................................................................................18
3.03
Units of Measurement and Abbreviations .........................................................................18
4 RMM 2 – Work Classifications...........................................................................................19
5 Glossary of Terms .............................................................................................................20
APPENDIX A – Group Element Cost Summary.............................................................................22
APPENDIX B – Element Cost Summary........................................................................................23
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
6/106
This Page is Intentionally Blank
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
7/106
Table of Figures
Figure 1 Rail Method of Measurement application across Project Lifecycle
Figure 2 How RMM 1 and RMM 2 work together
Figure 3 Cost Model example
Figure 4 The ‘Railway Corridor’
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
4
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
8/106
PREFACE
The Rail Method of Measurement has been written to provide a basis for the elemental costanalysis, measurement and valuation of all costs of a project, whether they are incurred by theinfrastructure owner or the contractor thus providing, if so desired, Total Cost Management ofProjects.
In order to efficiently and effectively manage their assets, Asset owners require certainty of costfor their capital investment and maintenance programmes through the project lifecycle toenable sound decisions to be made on where, when and how to invest.
Increased accuracy at the early stages of the project lifecycle achieves this, but also minimisesabortive cost/spend on non-viable investments thereby improving overall capital efficiency.
The Rail Method of Measurement (RMM) has been written to provide a progressive integratedmeasurement and valuation process in context with project development and deliveryprocesses used by railway infrastructure owners, network operators and suppliers in the UK.
The RMM provides a structure for the consistent preparation of budgets for capital andmaintenance works to a railway asset such that there is understanding between all involvedparties as to where cost items are covered, how they should be measured, what they include,and if relevant what cost items are not included.
Volume 1 – Cost Planning
Volume 2 – Detailed Measurement
Volume 3 – Operational Maintenance
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
5
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
9/106
Foreword to Rail Method of Measurement – Volume 2 –Detailed Measurement
Mature construction sectors have well established cost planning and modelling frameworks thatallow funders, clients and stakeholders to make clear assessments of the value for money and
cost drivers associated with their schemes. These frameworks of rules and definitions areusually developed and published by the professional institutions and well honed examplesinclude the New Rules of Measurement suite (NRM 1-3) published by the Royal Institution ofChartered Surveyors and the Civil Engineering Standard Method of Measurement (CESMM4),published by Institution of Civil Engineers.
Commercial practitioners from estimators and procurement professionals through to postcontract managers and Quantity Surveyors are well versed in the application and benefits thatthese frameworks bring.
The establishment of such a framework for the rail industry is fundamental to our ability toillustrate what rail infrastructure schemes ‘should’, ‘will’ and ‘did’ cost and perhaps asimportantly, ‘why’. Illustrating what rail investment schemes should cost is a perennial challengeand in order to provide a coherent answer, a common language is needed to instil cross-
industry consistency and support improved domestic and international analysis andbenchmarking.
Such a language must be based on a standard hierarchy of definitions and nomenclature forthe description, measurement, pricing and modelling of rail infrastructure works. That language,developed in collaboration with an Industry Development Group is a suite of documentscollectively referred to as the Rail Method of Measurement (RMM).
It comprises three volumes:
Volume 1: Cost Planning - Standard Cost Planning for Rail Infrastructure WorksVolume 2: Detailed Measurement - Standard Descriptions of Works ActivitiesVolume 3: Operational Maintenance - Standard Descriptions of Operational Maintenance Activities
Volumes 1 and 2 have been released as part of a broadened industry consultation. Volume 3will follow.
Volume 2 provides guidance on the quantification and description of rail infrastructure works forthe purpose of quantification in support of schedules of works, estimates, pricing documents,final accounts and the constituent elements of cost models. Direction and definition on how toaddress ‘non physical’ items such as preliminaries, overheads and profit, design costs and risksis also given. Adoption by practitioners will provide a uniform basis for measuring anddescribing rail infrastructure works and embodies the essentials of best practice.
The work of the Industry Development Group will continue with the refinement of volumes 1 and2 in light of industry feedback, and the validation and first release of volume 3. Comments,proposed revisions and amendments to the documents are welcome and should be sent [email protected] Requests to formally contribute to the IndustryDevelopment Group’s ongoing activities are also welcome.
The successful introduction of the Rail Method of Measurement and associated unit costmodelling is an important element in driving industry change and leaving a lasting legacy in therail sector. In time it will support the industry’s ability to better demonstrate value for money, thecapital cost dynamics of rail infrastructure schemes, enable whole life costing and facilitateimproved transparency and consistency. This will only happen with the overt support fromindustry stakeholders and adoption by client and supply chain practitioners.
It has been a privilege to facilitate this work from concept through to industry deployment and Iwould like to thank members of the IDG and other stakeholders for their active collaboration inbringing a fit for purpose product to industry.
Stephen Blakey, FRICS
Commercial Projects Director, Infrastructure Projects, Network Rail
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
6
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
10/106
1 Principles of Application
1.01 Introduction
The Rail Method of Measurement (RMM) Suite of Documents provides the guidance forconsistent measurement and cost analysis of works to railway infrastructure.
1.02 Purpose
The Rail Method of Measurement provides a consistent basis for description, measurement andallocation of cost for railway works, and embodies the knowledge of current industry bestpractice.
It enshrines the common language within which the works required and the costs planned andeventually incurred for the complete development and delivery of capital and operationalinvestment projects can be described and understood. It covers all aspects of client andcontractor involvement within the project lifecycle.
Volume 1 provides the framework to create a cost plan for the required outcome using a ‘topdown’ methodology. As the solution develops through its lifecycle into pre-construction stages,greater certainty of cost is provided by more specific and detailed itemisation of tasks requiredto complete the outcome.
In addition, Volume 1 provides the standard hierarchy and framework through which all costs atany development or delivery stage can be analysed and reconciled for comparison.
Volume 2 provides the required level of detail to produce ‘bottom up’ cost plans, estimates, anddetailed pricing schedules in a manner consistent with other construction sectors.
Volume 3 provides the required level of detail to produce estimates and pricing schedules forworks required to keep the railway operational between capital investment stages, throughclassification of major groupings of maintenance activities, including inspections, servicing and
maintenance works items
Concept Construction UseDesignFeasibility
MEASUREMENT: Cost Plans, CBS, Estimates, Pricing Schedules, Resources
ANALYSIS: Project Analysis, Cost Metrics, Unit Rates Benchmarking
RMM 1 – Cost Planning
RMM 2 – Detailed Measurement
RMM 3 – Operational Maintenance
Asset Lifecycle – Increased Knowledge
Figure 1 : Rail Method of Measurement application across asset lifecycle
Through the use of Volumes 1, 2 and 3 of the RMM all costs incurred from the inception of aproject to the ultimate disposal of the asset can be consistently measured, priced and recordedto complete the circle of cost knowledge.
1.03 Structure of the RMM Suite of Documents
RMM Volume 1 (Cost Planning) provides a standardised list of Cost Categories and GroupElements within a hierarchical cost breakdown grouped principally by railway asset groups,
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
7
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
11/106
then element assets or systems, sub-elements and components (e.g. Permanent Way; Plainline; Running rails; Modular track)
RMM Volume 2 (Detailed Measurement) provides a standardised list of railway specific workclassifications (e.g. Rail Track, Railway Control Systems, Electric Power Installations)incorporating railway asset specific sections for M&E type works, using the principle of “oneitem, one place”, such that each item appears only once but can be used and allocated once ormultiple times within the estimate or pricing schedule and against the RMM 1 structure.
RMM Volume 3 (Operational Maintenance) provides the same principle as RMM 2, but re-usesthe railway asset groups to classify the work items more in line with the order of work activitytaking place (patrol, inspection, repair, etc).
1.04 Use of the RMM Suite of Documents
The figure below gives an example of how RMM 1 and RMM 2 work together and complimenteach other. RMM 1 provides the Cost Categories, Group Elements and Element structurewhich shall apply for all Cost Planning, Detailed Estimates and the Valuations of all ProjectCosts through the Project Lifecycle. RMM 1 is used for Cost Planning purposes however whenmore design information is available the RMM 2 can be introduced to provide a more granularlevel of Measurement yet still correlating back to RMM 1 and the Cost Categories, GroupElement and Element structure.
Figure 2 – How RMM 1 and RMM 2 work together
1.05 Format and Layout
All RMM Volumes are set out in tabular form to provide the method of measurement andvaluation; each section includes rules relating to measurement, definition, coverage andadditional information or additional description required to be given.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
8
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
12/106
RMM 1 divides the costs of works generally encountered within the Railway Corridor into sixcost categories:
1. Direct Construction Works
2. Indirect Construction Works
3. Employer’s Indirect Costs
4. Risk
5. Inflation
6. Taxation
Each Cost Category comprises one or more Group Elements, which provide a breakdown ofcost in increasing detail: Elements, Sub-elements, and Components. It is intended that as thelevel of maturity of the project increases, so a greater level of breakdown of cost items can bemeasured.
1.06 Alignment with CESMM 4
RMM 2 provides supplemental information to the Civil Engineering Standard Method ofMeasurement, 4th Edition (CESMM4) rules and principles to amplify and encompass specific
works to railway infrastructure and systems. This document should be read in conjunction withCESMM4 to enable a full and complete breakdown of work items to be provided for railwayinfrastructure projects.
1.07 Form of Contract
RMM is “contract agnostic” - it makes no reference to any particular form of contract as it isintended for application to any project, irrespective of the form of contract between the parties.The term “contract” is used, generically, to make reference to the requirements of the contractbeing used for the project, where those requirements affect the method of construction or thecost of the works.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
9
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
13/106
1.08 Cost Analysis, Benchmark Analysis and Cost Models
The RMM can be used as the basis for capturing current and historical data in a commonformat. This allows for consistent Cost Analysis, Benchmark Analysis and Cost Modelling. Both
the Cost Analysis and Benchmark Analysis techniques will be based on the Group Element andElement Cost Summaries as shown in Appendix A and B.
An example of a Cost Model based on the RMM format is shown in Figure 3. As well as theRMM format it is important to note that Cost Models will also be determined by their ‘CostDrivers’ and ‘Technical Parameters’ with examples shown.
Figure 3 – Cost Model example
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
10
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
14/106
1.09 Details of works
Unless otherwise specifically stated in the cost plan, estimate or pricing schedule, all worksdescribed and measured in accordance with this document shall be deemed to includeprovision of goods, materials and services necessary to carry out the described items.
Items measured using the rules contained in this document shall fully describe the quantity andquality of the required works.
Where a specific area of project works requires a greater level of detail than the ‘Component’level, RMM Volume 2 – Detailed Measurement, or RMM Volume 3 – Operational Maintenanceshall be utilised to define the precise extent, nature and specification of the required works.
Items of works or groups of items shall be classified to define the type of work activity beingcarried out, in accordance with the definitions listed below:
New Build New installation on greenfield / brownfield site workswhere no similar type of asset exists.
Replace – Full Replacement / reconstruction of all life-expired structural
components with equivalent or lesser specificationcomponents.
Replace – Partial Replacement / reconstruction of targeted life-expiredstructural components with equivalent or lesserspecification components.
Refurbish Renovation or overhauls of existing asset orcomponents / elements, including e.g. redecoration,cleaning, remove graffiti / vegetation, etc. Also includesminor remodelling & upgrades.
Upgrade (Enhance) Improvement of existing asset to provide additionalbenefit or functionality over that it currently exhibits.
Remodel / Alter Modifications in layout or location but with functionalityof elements unchanged.
Extend Increasing the functionality of existing elements throughextension of length, area, volume, or coverage.
Repair Restoration to good condition of defective elements orcomponents, including inspection, spot/patch repairs,etc.
Strengthen Addition to existing or replacement with higherspecification components to increase strength of assetor components, make safe or prolong life prior to repair.
Preventative Maintenance Treatments or maintenance to prevent or slow the rate
of deterioration of assets or components.
Hazard Management Planned programme of work to reduce risk; works ortreatments to remove or make safe existing hazardswithin assets or components, other than strengthening.
Abandon / Demolish / Remove Removal of an asset, the functionality or liability of anasset without replacement. Where this entails worksother than demolition (e.g. Infilling) to removefunctionality, this shall be classed as replacement.
Asset Protection Infrastructure owner supervision only of works to assetswhich impinge on railway land but are owned andconstructed by outside parties.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
11
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
15/106
2 Use of the Work Classi fications
NOTE: Information contained within this section is to be read in conjunction with the relevantsections of CESMM4 to obtain full understanding and compliance with the guidance contained
herein.
2.01 Descriptions
If it is necessary for the Detailed Estimate / Pricing Schedule / Bills of Quantities to bestructured by a Work Breakdown Structure or other means of organisation, this structure shouldeither form the high level headings or be attached to each item, so as to preserve the alignmentof the current estimate/schedule/BoQ with that structure.
2.02 Coding for Cost AnalysisIn order to provide a means for consistent analysis of cost and to compare to previous budgets,documents produced using Volume 2 of RMM shall be referenced and coded to thecorresponding Cost Category and Group Element as set out in RMM Volume 1.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
12
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
16/106
3 Definitions
3.01 Reference Terms
The following reference terms shall be found within this document, and the meanings assignedto them are detailed below:
“ Anticipated Final Cost (AFC)” – means the estimated final cost of a project at completion,i.e. a forecast of the total expenditure for development and delivery of the entire project atclose-out. This may or may not be equal to the Cost Limit. – see Cost Limit.
“Bill(s) of Quantities” – means a list of items giving brief identifying descriptions and quantitiesof the work.
“ Component” – means a measured item which forms part of an element or sub-element. Thequantity of one or more items is measured and the rates and prices entered to calculate thecost target for an element or sub-element.
“ Consolidated Unit” – means an item of work described from a combination of components
within a sub-element.
“ Contract” – means the Conditions of Contract, the Specification, the Employer’sRequirements, the Contractor’s tender or proposals and the written acceptance thereof,together with such other documents as may be expressly agreed between the employer andthe contractor and referred to in the Contract Agreement(where completed).
“Contractor ” – means the individual or incorporated body responsible for the total constructionand completion process of the works. Where the works are let in defined packages, the term“contractor” may apply to the legal entity constructing each of the packages.
“ Contractor’s equipment” – means all appliances or things of whatever nature required in orabout the construction and completion of the works but do not include materials or other thingsintended to form or forming part of the permanent works.
“ Contractor’s overheads and profit” – means the contractor’s costs associated with headoffice administration proportioned to each works contract plus the contractor’s return on capitalinvestment. Contractor’s overheads and profit exclude costs associated with sub-contractor’soverheads and profit, which are to be included with the rates for the sub-contractor’s work.
“ Contractor’s preliminaries” – Contractor’s preliminaries include the costs associated withsuch items as management and staff, site establishment and maintenance, site supervision,requirements under the contract, temporary works and temporary services. Contractor’spreliminaries exclude costs associated with sub-contractor’s preliminaries, which are to beincluded with the rates for sub-contractor’s work.
“ Contractor’s risk” – means the allowance added to the tender calculation for the commercialrisk associated with competitive tendering.
“Construction Cost” – means the total cost of the Direct and Indirect Construction Works cost(i.e. the total cost for the works including the Contractor’s preliminaries, overheads and profit).
“Construction and Development Cost” – means the total cost of the Construction works andthe Employer’s Indirect Costs.
“ Construction inflation” – See “Inflation”.
“ Construction package” – means a part of the programme or project form part of the workswhich let to one or more contractors.
“Cost Category” – the term used to differentiate at the highest level types of costs incurred ona project, distinguishing between cost of physical works and other cost areas.
“ Cost control” – means the process of planning and controlling the costs of the programme and projects throughout the complete programme or project.
“Cost estimate” – means a report determining the possible cost of a project early in the designprocess in relation to the Employer’s fundamental requirements. This is prepared prior to thepreparation of a full set of working drawings or specification or Pricing Document and forms theinitial stage in the cost planning process.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
13
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
17/106
“ Cost limit” (or authorised budget or approved budget) – means the maximum expenditurethat the employer is prepared to make in relation to the completed programme or project.
“ Cost plan” – see elemental cost plan.
“ Cost target” – means the recommended total expenditure for a group element, element orsub-element. The total cost for an element is likely to be derived from a number of sub-
elements and components; a cost target may be set for a sub-element as the designdevelopment progress, the aggregate of cost targets for each of the sub-elements within anelement form the target cost of the element and the aggregate of the cost targets for eachelement form the cost target for the group element and so on.
“ Design and build cont ract” – means a contract by which the design and construction of theworks are the responsibility of the contractor.
“ Design team” – means project managers, engineers, cost managers and specialistconsultants responsible for the conceptual design and its development into drawings,specifications, instruction and schedules required for the construction of the works. The designteam is part of the project team.
“ Direct Construction Works Cost” – means the labour, plant, material, and subcontract costs
for the provision and installation of the permanent works. Direct Construction Works Costsexclude ‘Contractor Preliminaries’, ‘Contractor Overhead & Profit’ and ‘Design’.
“ Element” – means the principal division of a group element. Elements provide the standardlevel of cost planning or analysis. A separate cost target can be established for each elementfrom the sum of the underlying sub-elements.
“ Element Unit Quantity” (EUQ) – means the unit of measurement that relates solely to thequantity of the element or sub-element (e.g. the length of track, the number of switches orcrossings and the length of drainage).
“ Element Unit Rate” (EUR) – means the rate derived from the total cost of the elementdivided by the element unit quantity (EUQ). For example, the EUR for permanent way is thetotal cost of track, turnouts and crossings, ancillaries, track drainage, treatment of existing trackabandonment and recovery of old materials, survey and recovery of old materials, testing and
commissioning, contractor’s design and contractor’s overheads and profit, divided by the EUQfor permanent way. EURs include the cost of all labour, materials and plant, sub-contractor’sdesign fees, sub-contractor preliminaries and sub-contractor’s overheads and profit. EURsexclude contractor’s preliminaries, contractor’s overheads and profit and other costs such asproject team fees, other development/project costs, risk allowances and inflation. These itemsare assessed separately.
“ Elemental cost analysis” (or cost analysis) – means a schedule of detailed costs ofpreviously constructed works and is intended to provide information to assist the accurateestimate of cost of similar future works. Based on completed projects, it contains data on whichinitial elemental estimates and elemental cost plans can be based.
“ Elemental cost plan” (or cost plan) – is the critical breakdown of the cost limit for the projectinto cost categories and group elements for each element of the project. It provides a statement
of how the design and delivery team proposes to distribute the available budget among theelements of the project and a frame of reference from which to develop the design and maintaincost control. It also provides both a work breakdown structure (WBS) and a cost breakdownstructure (CBS) which, by codifying, can be used to redistribute work in elements toconstruction packages for the purpose of procurement.
“ Employer ” – means the promoter or owner of the works. The terms “Project Sponsor” or“Supervising Officer ” (SO) are used to define representatives of the Employer empowered tomanage the works project and, unless otherwise provided in the contract, issue instructions ornotices on behalf of the Employer. For the purposes of RMM, the term “Employer” shall besynonymous with the terms “Project Sponsor ” or “Supervising Officer ” (SO).
“ Employer’s Indirect Costs” – means the total costs incurred by the Employer in thedevelopment, design and delivery of the project, excluding the Construction Cost.
“ Enabling Works” – means the works required to be completed prior to the commencement ofthe principal works within the “railway corridor”.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
14
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
18/106
“ Engineering hours” – (for the London Underground network), means the period of timebetween (a) the published time or actual time, if later, traction current is switched off and (b) thepublished time or amended time, if earlier, traction current is switched on.
“ Estimate” – see Cost estimate.
“ Estimate base date” – means the date on which the cost limit (excluding inflation – i.e. the
sum of the works cost estimate, project/design team fees estimate, other development/projectcosts estimate and risk allowance estimate) is established as a basis for calculating inflation,changes or other related variances.
“ Estimate of Prime Cost [EPC] – means the estimate prepared to calculate the probable“target cost” for a cost reimbursable contract; the EPC is used to exercise size cost control.
“ Expressly required” – means shown on the drawings, described in the specification orordered by the Employer pursuant to the contract(s) in use.
“Four-foot” – means the space between two running rails of standard gauge track.
“ Four-foot walkway” – means a track asset walkway which runs along the four-foot of a track,to give access to, or egress from, a stabled train or rail-mounted vehicle.
“ Free issue services, materials or plant” – means items that are supplied to the Contractorthrough Employer facilitated contracts. These items should not incur ‘Contractor Overhead &Profit’.
“Group Element” – means the principal headings used to describe the cost groups in anelemental cost plan. Group elements are the principal division of cost categories and providethe highest level of elemental cost planning or analysis. A separate cost target can beestablished for each group element from the sum of the underlying elements.
“ Indirect Construct ion Works Cost” – means the Contractor’s preliminaries, overheads,profit, and any other costs associated with the execution of the works excluding the directconstruction works costs.
“Inflation” – an allowance made for the rate of change of prices (as indicated by a price index)calculated on a monthly or annual basis. Refer to definitions for tender inflation and
construction inflation as follows:
“ Construction inflation” – means an allowance included in the Cost Estimate or Costplan for the rate of change of prices for labour, plant and materials during the periodfrom date of the tender return to the completion of construction work.
“ Tender inflation” – means an allowance included in the Cost Estimate or Cost Plan for the rate of change of prices from the estimate base date to the tender return date.The allowance may include for inflation brought about by changes in market conditionsor for the rate of change in the prices of labour, materials and plant and equipmentduring the period from the estimate base date to the date for tender return.
“Isolation” – means:
(a) the formal procedure for de-energizing a section of traction current supplyequipment, earthing, verifying its lack of potential and issuing certification tothat effect, or
(b) the severance of any electrical supply to electrically operated devices, linesidecabinets and the like.
“ Overheads and Profit” – See Contractor’s overheads and profit.
“ OGC Gateway Process” – means the Government process in the United Kingdom, whichexamines projects at all stages of their delivery from inception to completion. The processrequires a business case to be prepared for the project, which is progressively reviewed until adecision to invest is taken. Following the investment decision, the project is monitored to ensurethe business case is maintained and the project delivers its intended benefits to the Employer.
“ OGC Gateways” (or OGC Gateway) – are the milestone decisions taken in the process.“ Other development/project costs” – means costs that are not necessarily directlyassociated with costs of constructing the works but form part of the total cost of the project tothe Employer (e.g. land acquisition costs, funding costs, fees to local authorities for statutoryconsents, decanting and relocation costs).
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
15
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
19/106
“Package” – means a self-contained section or discrete sections of works brought together fordelivery under one contract or sub-contract.
“ Period” – means the time calculated from the date of the order of cost estimate (OCE) or thedate of the contract to the time for completion of the programme or project.
“ Permanent works” – means the permanent works to be constructed and completed in
accordance with the contract.
“Possession” – means the circumstances obtaining when arrangements have been made toblock the line to normal passage of trains and the only movements allowed are those of on-track plant or engineering trains and the limits of demarcation of possessions are shown bypossession board limits.
“ Preliminaries” – See “Contractor’s preliminaries”.
“ Pricing document” – means a set of requirements included in a contract to calculate thecontract price and forming part of the contract to exercise cost control and to value change.
“ Pricing schedule” – means a list of items, prepared in accordance with this document, givingbrief identifying descriptions and indicative quantities of the work comprised in the project. Seealso Bill(s) of Quantities.
“ Principal works” – means the works covered by group elements 1.01 to 1.08 inclusive, whenthe enabling works have been completed.
“ Procurement Strategy” – means the forms and methods for the programme and the works stated in reports prepared in accordance with this document.
“ Project” – means the works executed in the railway corridor and all associated buildingsrequired to be constructed forming part of the permanent works.
“ Project team” – means Employer, Project Sponsor, Supervising Officer and all otherconsultants responsible for the delivery of the project to the required performance (design andquality) and cost criteria. The project team will include the contractor and sub-contractors wherethey have been engaged to provide pre-construction services.
“ Project/design team fee(s)” – means project and design teams consultants fees for pre-construction, construction and post construction related services, other consultants fees, feesand charges for intrusive site investigations, specialist support consultant’s fees andcontractor’s fees for pre-construction services.
“ Programme” – means a series of projects co-ordinated within an overall plan to develop therailway corridor in whole or in part.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
16
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
20/106
“ Railway Corridor” – means the area bounded by the external limits of the operational railwayas shown on the diagram below, containing all of the works including structures and theirsupports spanning the corridor.
Figure 4 - the “Railway Corridor ”
“ Railway infrastructure wor k (or works to the railway infrastructure)” – means all of thecomponents measured and incorporated into elements 1.01 to 1.09 (i.e. permanent way,railway control systems and equipment, level crossings, operational telecommunicationinstallations, electric power and plant, electric contact systems, and off track (building andproperty) works; civil engineering works and enabling works).
“ Risk allowance” – means the allowance added to the base cost estimate for items thatcannot be precisely predicted or calculated to arrive at the cost limit.
“ Risk register ” (or risk log) – means a schedule of identified risks.
“ Risk value” – means the estimated cost of the individual risk.
“Site area” – means the total area of the site within the site title boundaries (or the total areawithin the site title boundaries defined by the Employer as the site for the works), measured ona horizontal plane.
“Sub-contractor ” – means an individual or incorporated body who undertakes specific workonly within the project under the supervision of the Contractor.
“ Sub-element” – means the principal division of an Element. Sub-elements provide a moredetailed level of cost planning or analysis. A separate cost target can be established for eachsub-element from the sum of the underlying components or measured items.
“ Target cost” – see “Estimate of Prime Cost”.
“ Temporary work” – means all temporary works of every kind required in or about theconstruction and completion in accordance with the contract.
“ Tender inflation” – See Inflation.
“ Works” – means the permanent and temporary works and their design.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
17
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
21/106
3.02 Measurement Terms
The following measurement terms shall be found within this document, and the meaningsassigned to them are detailed below:
“ Gross Internal Floor Area (GIFA)” – means the area of a building measured within its
external walls and over all internal walls and partitions in accordance with the rules contained inthe Standard Form of Cost Analysis (SFCA) published by the RICS.
“ Gross Surface Area (GSA)” – for external floors, decking and structures means the area ofthe uppermost level of the structure measured within its external perimeter or between thefurthermost supporting structures for a bridge of viaduct
“ Internal cube” – means all enclosed spaces within a bridge, viaduct or tunnel. The cubeshould be measured as the Gross Surface for floors and structures multiplied by the height tothe underside of the bridge or structure.
“ Line of railway” – means a single track of gauge stated measured over its entire length.
“ Single track metre” (STM)” – means the length of all track in a project measured gross overall switches and crossings, expressed as a single track length.
“Signalling Equivalent Unit” – see Appendix A.
“Level Crossing Equivalent Unit” – see Appendix B.
3.03 Units of Measurement and Abbreviations
The unit of measurement for each group element, element, sub-element, or component itemshall be that stated in the measurement rules. The following symbols and abbreviations areused in this method of measurement:
Cubic metre m3
Day Day
Degree º
Equal to or greater than ≥
Greater than >
Hectare ha
Hour Hr
Kilogramme kg
Less than <
Less than or equal to ≤
Level Crossing Equivalent Unit LXEU
Linear metre m
Litre L
Number Nr
Percentage %
Signalling Equivalent Unit SEU
Single Track Metre STM
Square metre m2
Sum Sum
Tonne t
Week Wk
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
18
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
22/106
4 RMM 2 – Work Classif ications
NOTE: These Work Classifications should be read in conjunction with CESMM4 WorkClassifications which are not reproduced herein.
Class A1: PROJECT AND DEVELOPMENT COSTS
Class A2: DESIGN DEVELOPMENT AND MANAGEMENT
Class A3: CONTRACTOR'S PRELIMINARIES
Class A4: CONTRACTOR'S OVERHEADS AND PROFIT
Class A5: RISK
Class I2: CABLES, DUCTS AND CONTAINMENT
Class S1: RAIL TRACK
Class S2: RAILWAY CONTROL SYSTEMS
Class S3: ELECTRIC POWER INSTALLATIONS
Class S4: OPERATIONAL TELECOMMUNICATION INSTALLATIONS
Class S5: ELECTRIFICATION CONTACT SYSTEMS
Class S6: FIXED PLANT
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
19
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
23/106
5 Glossary of Terms
ABCL Automatic barrier crossing
AHB Automatic half barrier
AOCL Automatic open crossing locally monitored
ARS Automatic Route Setting
ATC Automatic train control
ATP Automatic train protection
AWS Automatic warning system
CBI Computer based interlocking
CCTV Closed Circuit television
CD Close Doors
CET Chemical Effluent Toilet
CLS Coloured light signal
DNO Distribution Network Operator
ERTCS European rail traffic control system
ETD Emergency telephone device
ETPWS European Train Protection Warning Systems
FDM Frequency division multiplex
FSP (Power) Supply points : functional
FTN Fixed Telecomms Network
GPL Ground position light (signal)
GSM-R Global Satellite Mobile - Radio
HABD Hot Axle Box Detectors
IBJ Insulated block joint
IDF Internal distribution frame (internal concentrator cabling)
IECC Integrated electronic control centres
LED Light emitting diode
MCB Manually controlled barrier
MCB-CCTV Manually controlled barrier with CCTV
MCB-OD Manually controlled barrier with object detector
MDF Main distribution frame (external cables to concentrator)
MSL Miniature stop light crossing
MWL Miniature warning light crossing
OFF Signal OFF indicator
PA Public Address
PCM Printed Circuit Module
PLJI Position light junction indicators
PLOD Patrolman's lookout device
PLS Position Light Signals
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
20
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
24/106
PSP (Power) Supply points : permanent
RA Right Away
REB Relocatable equipment buildings
RETB Radio Electronic Token Block
RRI Relay Electro - mechanical interlocking
SMS Short Message Service (modem)
SPAD Signal passed At Danger
SSI Solid state interlocking
SSP (Power) Supply points : signal
TASS Tilt activation and suspension system
TDM Time division multiplex
TFM Trackside function module
TMO Train crew operated crossingTPWS Train protection and warning system
TRTS Train Ready To Start
TTMS Timetable management system
UWC User worked crossing
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
21
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
25/106
This Page is Intentionally Blank
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
22
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
26/106
RMM Volume 2
Class A1- Man & Other Proj Cost
RMM Volume 2
Class A1- Man & Other Proj Cost
CLASS A1 : MANAGEMENT AND OTHER PROJECT COSTS
Includes:
Land acquisition costs
Employer's Staff costs
Employer-owned plantOther employer's costs
Employer's finance costs
01 Land acquisition costs 01 01 Acquisition of land : leasehold Sum
02 Acquisition of land : freehold Sum
03 Acquisition of property : freehold Sum
04 Acquisition of property : leasehold Sum
02 01 Licences Sum
02 Easements Sum
03 Wayleaves Sum
02 Fees : facilitation 01 Inauguration works 01 Site investigation Sum
02 Intrusive investigation Sum
03 Other site investigation Sum
02 Statutory charges 01 Planning fees Sum
02 Building control fees Sum
03 Discharge consents Sum
03 Other Project Requirements 01 Employer's staff costs 01 Employer's management personnel Wk
02 Other third parties' management and
monitoring staff
Wk
02 Employer's main office costs 01 Additional staff costs Wk
03 Employer's project office costs 02 Outsourced staff services Wk
04 Employer's site office costs 03 Relocation and living costs Wk
04 Business travel : rail Wk
05 Business travel : road and air Wk
06 Management and possession costs Wk
07 Communications : mobile phones and
pagers
Wk
08 Office supplies Wk
09 Office equipment and furniture Wk
10 IT equipment and services Wk
11 Office rentals or licence fees Wk
12 Utilities : water, gas, electricity and
telecommunications
Wk
13 Office catering services Wk
14 Office cleaning services Wk
Management and Other Project Costs incurred by the employer (or the contractor on behalf of the employer) in the delivery of a project, including
execution of contracts
FIRST DIVISION SECOND DIVISION THIRD DIVISION
Project specific costs : inauguration
Fees paid to neighbouring land owners
and users
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
23
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
27/106
RMM Volume 2
Class A1- Man & Other Proj Cost
RMM Volume 2
Class A1- Man & Other Proj Cost
Excludes: Refer to :
Site investigation after commencement of the design works Class B
Design development and management costs Class A2
M1 D1 C1 A1
M2
D2
M3
M4 Items shall be given for
management personnel engaged
by the employer or by other
parties appointed by the
employer to manage the project
D3 C2 A2
M5 Items for staff costs shall identify
each type of personnel
separately
M6 D4 C3
M7
The cost of administrative or
supervisory staff required by the
employer, expressly for the
project, shall be classed as
employer's main office costs or
employer's project office costs or
employer's site office costs as
appropriate
MEASUREMENT RULES
Employer's main office costs,
employer's project costs or
employer's site costs shall cover
the costs of all staff expressly
required by the project who are
not engaged in the design or
management of the project
Items shall be given for the cost
of management of possession
and isolation costs, whichcannot be apportioned to any
particular item of work
Investigative works prior to the
preparation of the design of the
project shall be classed as
Inauguration works
Items shall be given for
payments for consents required
from statutory bodies to
commence or to complete the
project
Personnel or advisors engaged
by the employer other than for
the design and management of
the project shall be classed as
employer's staff costs
Employer's staff costs shall be
deemed to include the costs of
all personnel or advisors who
are expressly required to monitor
or represent third party interests
Items for employer's staff costs
and other third parties'
management costs shall state
the period for which the staff are
required
Items shall be given for the costs
of additional staff required by the
employer expressly by the
project to supplement the
employer's normal staff
The costs associated with the
acquisition of land that is
expressly required for the
execution of the project shall be
classed as land acquisition
costs
Items for land acquisition costs
shall be deemed to include the
costs of the land and associated
legal fees and, where
appropriate any land taxes
Legal and other fees associated
with acquisition of land and
property are included elsewhere
DEFINITION RULES COVERAGE RULES ADDITIONAL RULES
Items for licenses, easements
and wayleaves shall describe
the purpose and duration
Items for land acquisition costs
shall identify the cost of land and
associated legal fees separately
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
24
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
28/106
RMM Volume 2
Class A1- Man & Other Proj Cost
RMM Volume 2
Class A1- Man & Other Proj Cost
FIRST DIVISION SECOND DIVISION THIRD DIVISION
04 Employer owned plant 01 Plant only 01 Plant : establishment and removal Sum
02 Plant with operating staff 02 Plant : maintain and operate Wk
05 Research for Innovative products 01 Research and development 01 Research : details stated Sum
02 Development : details stated Sum
06 Other Employer's costs 01 Facilitation costs 01 Insurances Sum
02 Fitt ings, furnishings and equipment Sum
03 Marketing costs Sum
04 Archaeological works Sum
02 Decanting and relocation costs 01 Temporary relocation costs Sum
02 Rents and other running costs Wk
03 Compensation costs Wk
03 Interruption of asset use 01 Payments to asset users : planned Wk
02 Payments to asset users : unplanned or
emergency
Wk
03 Costs associated with temporary speed
restrictions
Wk
04 Costs of diversionary routes or
alternative lines of supply
Wk
04 Payments to public or statutory bodies 01 Adoption charges in connection with
highways and bridges
Sum
02 Maintenance charges for highways and
bridges
Sum
03 Planning contributions Sum
04 Transport & Work Act charges Sum
05 Street Works Act Sum
06 Parliamentary fees Sum
05 Legal and other fees 01 Fees : acquisition of land Sum
02 Fees : planning enquiries Sum
06 Employer's finance costs 01 Commitment fees Sum
02 Interest Sum
03 Credit charges Sum
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
25
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
29/106
RMM Volume 2
Class A1- Man & Other Proj Cost
RMM Volume 2
Class A1- Man & Other Proj Cost
MEASUREMENT RULES DEFINITION RULES COVERAGE RULES ADDITIONAL RULES
M8 Items shall be given for the use
by the contractor of employer-
owned plant
D5 Plant that is the property of the
employer or hired by the
employer shall be classed as
employer owned plant
C4 Plant : establishment and
removal shall be deemed to
include the provision of plant,
replacement of defective plant
and the return after use
A3 Items for employer-owned plant
shall state the work for which it
is to be used and the period and
terms of its use
M9 Items shall identify separately
plant that is supplied by theemployer for operation by the
contractor, and plant which is
supplied and operated by the
employer for use by the
contractor
D6 The time for the use of employer
operated plant shall be deemedto include the time from leaving
its stabling or storage point to
time of its return after use
C5 Maintenance of plant shall be
deemed to include the insuranceof the plant, all servicing and
repair, replacement of defective
parts, the provision of fuels,
lubricants and water
A4
M10 Items for plant with operatives
shall identify the number of
operatives
D7 Operatives expressly required to
operate and maintain employer-
owned plant shall be classed as
operating staff supply
M11 Items for research shall describe
the extent of the research and
the manner in which the resultsshall be monitored and
published
D8 Work to investigate or establish
the behaviour of materials or
systems under workingconditions shall be classed as
research
C6 Items for research shall be
deemed to include the cost of
preparing the researchprogramme, monitoring, testing
and publishing the results
M12 Items for development shall
describe the extent of the work,
its purpose and function
D9 Work to improve performance of
materials, goods or systems
under working conditions shall
be classed as development
C7 Items for development shall be
deemed to include everything
necessary to reach the aims of
the improvement
M13
M14
D10
M15
Payments or consideration given
pursuant to planning approvals
shall be classed as statutorypayments
Items for employer's finance
costs shall state the sum which
is being financed, the period of
finance and the percentage
interest
Items shall be given for
insurances which the employer
puts in place prior to the
commencement of works but
which cannot be allocated to any
class of the works
Items shall be given for
decanting and relocation costs
arising from requirements
expressly necessary for the
works, the extent of each
requirement and the period of
the requirement shall be given
The cost of periodic
maintenance and servicing ofemployer-owned plant expressly
required for the project shall be
identified separately
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
26
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
30/106
RMM Volume 2
Class A2 - Design
RMM Volume 2
Class A2 - Design
CLASS A2 : DESIGN
Includes:
01 Fees for design : employer 01 Railway Control System Design 01 Pre-design : inception and feasibility Wk
02 Train Power Syste=ms Design 02 Design : outline proposals Wk
02 Fees for design : contractor 03 Electric Power and Plant Design 03 Design : scheme design Wk
04 Permanent Way Design 04 Design : detail design Wk
05 Operational Telecomms System Design 05 Design : production information Wk
06 Buildings and Property Design 06 Construction : procurement and tender
action
Wk
07 Civil Engineering Design 07 Construction project planning Wk
08 Enabling Works Design 08 Construction : operations off site Wk
09 Construction : operations on site Wk
10 Cost control and commercial
management
Wk
03 Fees for design management 01 Design management 01 Coordination Sum
02 Submission and approval Sum
04 Correlation of documentation of existing
installations
01 Survey 01 Desk top Sum
02 On site Sum
02 Provision of drawings 01 Hard format : number of copies stated Sum
02 Electronic format Sum
05 Fees for design & construction
monitoring
01 Planning Supervision : CDM regulations 01 Health and safety plan Sum
02 Health and safety file Sum
All design development and management costs incurred in the delivery of a project
Design costs - pre-contract
Design costs - post contract
Fees payable for CDM supervision and monitoring
Design management
FIRST DIVISION THIRD DIVISIONSECOND DIVISION
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
27
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
31/106
RMM Volume 2
Class A2 - Design
RMM Volume 2
Class A2 - Design
Excludes: Refer to:
Statutory fees paid for planning & construction approvals Class A1
Statutory fees paid for building regulations Class A1
M1 D1 C1 A1
M2
C2
M3
M4
M5 Items shall be given for the
management of the co-
ordination and the submission
and approvals of design
D2 Work to co-ordinate the
preparation and development of
the design with the construction
programme will be classed as
design management : co-ordination
C3 Design management shall
include the submission of all
elements of the design at each
stage, to receive comments for
the relevant bodies and tocollate all amendments and to
submit the design for approval
A2 Fees for the design
management paid by the
employer shall be separately
identified from those paid by the
contractor
D3 Work to co-ordinate the
submission of design approvals
and to receive and to obtain
approvals will be classed as
design management :
submission and approvals
C4 Fees for design management
includes those paid by the
employer and those paid by the
contractor
M6
The scope of work in each stage
of design shall be that defined in
the ACE Agreement 4A
Where a "design and build"
contract strategy is used, the
fees for design in this section
shall cover the fee costs prior tothe transfer of the design
responsibility to the contractor
Where fees for the design of the
works are paid for by the
employer for the whole project,
they shall be included in this
section
Where a framework contract
strategy is used and there are
major sections of work that are
designed by contractors other
than the principal contractor, the
design fees shall be grouped by
the work sections or
contractor(s)
Items for design that are
expressly paid for by the
employer shall be identified by
discipline and the various design
stages
Items for design fees shall state
the format in which drawings and
schedules are to be prepared
and the number of copies
required to be issued
Items shall be given for the
correlation of documentation of
existing installations where no
records of the installationsinvolved exist and where the
records are expressly required
Fees for design shall identify
separately those fees incurred
by the employer and those
incurred by the contractor
For each stage or function of
fees for design the classes of
personnel used shall be
separately identified
COVERAGE RULES ADDITIONAL RUL ESMEASUREMENT RULES DEFINITION RULES
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
28
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
32/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
CLASS A3 : CONTRACTOR'S PRELIMINARIES
Includes:
General obligations, site services and facilities, temporary works, testing of materials and work
Contractor's risk
01 Contractual requirements 01 Bonds 01 Performance bond Sum
02 Advance payment bond Sum
02 Insurances 01 Insurance of the works Sum
02 Third party insurance Sum
03 Other insurance : details stated Sum
03 Parent company and joint ventureguarantees
01 Parent company contract guarantee Sum
02 Joint ventures Sum
04 Commencement and completion 01 Period of the works Wk
05 Payments and cash flow 01 Programme and payments : neutral cash
flow
Sum
02 Specified requirements 01 01 Offices Sum
02 Laboratories Sum
03 Meeting rooms Sum
04 Storage cabins Sum
05 Welfare facilities Sum
06Sanitary accommodation Sum
02 01 Transport vehicles Sum
02 Telecommunication services Sum
03 IT services Sum
03 01 Office equipment Sum
02 Laboratory equipment Sum
03 Surveying equipment Sum
04 Management of the works 01 Programme and progress reports Sum
Accommodation for the contract
administrator's staff
Services for the contract administrator's
staff
Equipment for the contract
administrator's staff
Contract execution and management costs incurred by the contractor in the delivery of contracted project works
Items to cover works which are not to be considered as proportional to the quantities of the permanent works
FIRST DIVISION SECOND DIVISION THIRD DIVISION
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
29
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
33/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
Excludes: Refer to:
Risks that are shared by employer and the contractor Class A5
M1 D1 C1 A1
M3 A2
M4 Items shall be given where the
period of the works is expressly
determined by the employer
D2 Where access to the works or
parts of the works is within times
or times expressly determined
by the employer and affects the
period during which the works
may be completed, the times
shall be detailed and defined in
the period of the works.
C2 Times in which restricted access
to the infrastructure and/or
isolation of services is expressly
defined by the employer shall be
deemed to be included in period
of the works
A3 Where the works or parts of the
works may only be executed at
times expressly determined by
the employer, bank holidays,
national holidays or in hours of
darkness, items shall so state
M5 Items for neutral cash flow shall
be given where the employer
requires interim payments to be
calculated by earned value or
other techniques.
D3 Milestone payments shall be
classed as neutral cash flow.
A4 Separate items shall be given
under management of the works
for possessions of infrastructure
and isolations of services
M6 D4 C3 A5
A6
M7 A quantity shall be given against
all items, which shall unless
otherwise stated cover the
length of the contract period
including the period for making
good defects..
D5 All work that is expressly
required by the employer shall
be classed as employer's
specified requirements
A7 Item descriptions for work
classed as employer's specified
requirements shall distinguish
between the establishment and
removal of services or facilities
and their continuing operation
and maintenance.
M2 Items for other insurance shall
describe the type of insurance,
the level of indemnity and the
period of the insurance cover.
Where the contractor is asubsidiary of a larger company
or a joint venture of several
companies, an item for parent
company guarantee shall be
given
Items for contractual
requirements shall describe the
requirement of each item by
reference to the specification or
other contract documents.
Where the contractor is a jointventure of more than one
subsidiary company, the item
description for parent company
guarantee shall include all
companies
Item descriptions for work
classed as specified
requirements which is to be
completed after the employer
has taken the works shall so
state.
MEASUREMENT RULES DEFINITION RULES ADDITIONAL RULESCOVERAGE RULES
Services for the contract
administrator's staff, services for
the contract administrator's staff,
equipment and attendance for
the contract administrator's staff
shall be measured only where
they are expressly required.
Facilities that are expressly
required for the use of the
employer's staff, shall be
classed as Accommodation for
the contract administrator's staff
Accommodation for the contract
administrator's staff shall be
deemed to include all costs of
establishment and maintenance
including furniture and fittings
Description for accommodation
for the contract administrator's
staff shall describe the furniture
and fittings required
Item descriptions for
performance bonds shall be
included only where they are
expressly required by the
employer. The purpose of the
performance bond , e.g.
advance payment provision,
shall be identified.
Items for insurance classed as
contractual requirements shall
be deemed to include only the
provision of insurance of the
works and plant and third party
insurance.
All work other than the
permanent works which is
expressly required to be carried
out which the nature and extent
is stated in the description of the
works shall be classed as
specified requirements.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
30
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
34/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
FIRST DIVISION SECOND DIVISION THIRD DIVISION
02 Specified requirements cont'd 04 Management of the works cont'd 02 Cost reporting and control Sum
03 Records for labour and plant Sum
04 Value engineering Sum
05 Access to the site Sum
06 Possession of working infrastructure :
establishment of possession
Sum
07 Possession of working infrastructure :
management of possession
Wk
08 Isolation of live services: type stated Sum
05 Testing 01 Materials Sum
02 The works :during the progress of the
works
Sum
03 The works : during the progress of the
works : completed in sections
Sum
04 Co-ordination of sectional works
05 The works : on completion Sum
06 Special testing : test trains Sum
07 Special testing : details stated Sum
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
31
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
35/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
MEASUREMENT RULES DEFINITION RULES ADDITIONAL RULESCOVERAGE RULES
M8 A8 Item descriptions for work
classed as employer's specified
requirements which is to be
carried out after the completion
of the works as defined in the
contract shall so state.
M9 Items for value engineering
shall state the frequency of
periodic examinations and the
form in which the results of the
procedure are to be published
C4 Items for value engineering shall
be deemed to include the cost of
creating and maintaining the
procedure and publishing the
results
M10 Items for access to the site shall
identify the locations of access
to the site and any limitation in
respect of time for access.
A9 Item descriptions for access to
the site shall identify separately
access for pedestrians, vehicles
and plant.
M11 Items for establishment of
possession of working
infrastructure shall describe their
frequency and times when the
contractor may take possession
D5 Where the contractor requires
continuous access to
infrastructure which is in use,
such as roads, railways,
pipelines, waterways, sewers or
power lines, the work shall be
classed as possession of
working infrastructure
C5 Items for establishing
possession shall include only the
cost of managing the application
for and the hand back of
possessions or electrical
isolations.
A10 The details and number of
possessions and electrical
isolations required shall be
included in descriptions where
the possessions or electrical
isolations are granted by the
employer
M12 Items shall be given for the
management of possession of
working infrastructure shall state
the period of the possession.
C6 Items for management of
possession shall be deemed to
include complying with all
legislation, provision of safety
management personnel and
maintaining safety for those
working in the possession
A11 Separate items shall be given for
each possession of working
infrastructure
M13 Items for isolation of live
services shall describe the
frequency and times when the
contractor isolates them.
D6 Where the contractor requires
continuous isolation of live
services such as pipelines,
sewers or power lines, including
traction power supply for
railways, the work shall be
classed as isolation of live
services
M14 D7 A12 Special testing required by the
employer shall be described in
detail
D8 Testing during progress of the
works is testing carried out to
individual equipment or discrete
sections of systems such as
continuity testing
M15 Separate items shall be given for
testing of telecommunications,
electric power supplies and train
power systems
D9 Testing on completion of the
works is testing carried out to
complete sytems and for
systems integration
Items for programme and
progress reports, cost control
reports and records of labour
and plant shall describe the type,
frequency and number of reports
required by the employer and
the method of their preparation
and publication.
Where the works are to be
completed in sections, the
sections shall be described and
separate items measured for
each section
Testing shall cover the works:
commissioning and handover to
the employer is measured
separately
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
32
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
36/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
FIRST DIVISION SECOND DIVISION THIRD DIVISION
02 Specified requirements cont'd 06 Decommissioning of redundant assets 01 Permanent way; details stated Sum
02 Railway control system equipment:
details stated
Sum
03
04 Electric power installation equipmnt :
details stated
Sum
05 Operational Telecommunication
Installation equipment: details stated
Sum
06 Electric Contact systems equipment;
details stated
Sum
07 Fixed plant equipment: details stated Sum
07 Commissioning and handover 01 The works :during the progress of the
works
Sum
02 The works : during the progress of the
works completed in sections
Sum
03 The works : on completion Sum
04 Signal sighting Sum
05 Operating manuals Sum
06 Training : employer's signalling staff and
other operatives
Sum
07 Training : maintenance staff Sum
08 Strategic spares : details stated Sum
03 Method-related charges 01 Accommodation and buildings 01 Offices Wk
02 Laboratories Wk
03 Cabins Wk
04 Stores Wk
05 Canteens and mess rooms Wk
02 Services 01 Electricity Wk
02 Water Wk
03 Security Wk
04 Hoardings Wk
05 Signs and notices Wk
06 Site transport Wk
07 Personnel transport Wk
08 Welfare Wk
03 Plant : mechanical 01 Cranes and hoists Wk
02 Pipe laying Wk
03 Concrete mixing Wk
04 Piling Wk
05 Crushing and screening Wk
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
33
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
37/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
MEASUREMENT RULES DEFINITION RULES ADDITIONAL RULESCOVERAGE RULES
M16 C7 A14
M17 Separate items shall be provided
for the commissioning of the
operational signalling systemand for the sighting of signals
A13 For signal sighting, full
descriptions by reference to the
signalling specification of theemployer's requirements in
respect of the approval of the
signalling systems by the signal
sighting committee; these
requirements shall include any
approvals to be sought and
obtained in the design of the
system
M18 Where post commissioning
handover is expressly required,
details of the handover shall be
included in item descriptions
D10 A14 Item descriptions for post
commissioning handover shall
include the location of the
process and the number of
handover events.
M19
C8
Items for decommissioning of
redundant asset shall be
deemed to include isolating all
control systems and power
supplies before and after
removal
Items for taking down and
disposal or recovery to store of
assets are included in Class D
Separate items shall be given for
the lump sum costs of method-
related charges and for the
maintenance of these charges
M20 Items for electricity shall
describe heating, power and
lighting separately
Items for services shall be
deemed to inlude all necessary
connection, disconnection and
consumables
Items shall be given for
decommissioning assets which
are taken down or removed
Post commissioning handover is
defined as the processes
required, after testing and
commissioning have been
completed to induct the
employer's staff to the use of the
equipment and systems.
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
34
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
38/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
FIRST DIVISION SECOND DIVISION THIRD DIVISION
03 Method related charges cont'd 04 Plant : mobile 01 Cranes and hoists Wk
02 Transport : people or materials Wk
03 Concrete transport Wk
04 Earthmoving Wk
05 Compaction Wk
06 Paving Wk
07 Tunnelling Wk
08 Boring and drilling Wk
05 Plant : rail-mounted 01 Cranes Wk
02 Transport : people or materials Wk
03 Concrete transport Wk
04 Railway : track laying Wk
05 Maintenance : tamping Wk
06 Maintenance : ballast cleaning Wk
07 Overhead wiring train Wk
06 Temporary Works: site access 01 Access roads Wk
02 Bridges Wk
03 Coffer dams Wk
04 Pumping Wk
05 De-watering Wk
06 Compressed air for tunnelling Wk
07 Temporary works ; construction 01 Access scaffolding Wk
02 Support scaffolding and propping Wk
03 Piling Wk
04 Formwork Wk
05 Shafts and pits Wk
06 Hard standings Wk
08 Project specific management and staff 01 Project and construction management Wk
02 Trade supervision Wk
03 Health and safety management Wk
04 Commercial and procurement
management
Wk
05 Design management Wk
06 Project engineering Wk
07 Environmental management Wk
08 Other project specific management :function stated
Wk
09 01 Directors Wk
02 Quality Assurance management Wk
03 Contract management Wk
04 Health and safety management Wk
05 Environmental management Wk
06 Other visiting management; function
stated
Wk
Visiting management and staff
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
35
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
39/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
MEASUREMENT RULES DEFINITION RULES ADDITIONAL RULESCOVERAGE RULES
M21
M22 D11 C9
D12
Items for project specific
management and staff shall
identify different grades
separately
Management and staff that are
dedicated to the project shall be
classed as project specific
management and staff
Items for management and staff
shall be deemed to include all
administrative and clerical staff
Management and staff that is not
dedicated to the project shall be
classed as visiting management
and staff
Item descriptions for temporary
works shall provide such detail
as is required to describe the
complexity of the works; the
details shall be provided in
accordance with the rules of the
appropriate work Class
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
36
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
40/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
FIRST DIVISION SECOND DIVISION THIRD DIVISION
05 Temporary works 01 Traffic regulation 01 Traffic regulation : road Wk
02 Temporary speed restrict ions : road Wk
02 Traffic diversion 01 Traffic diversion ; road Wk
03 Services 01 Service interruption ; type stated Wk
02 Service suspension : type stated Wk
03 Service diversion : type stated Wk
04 Service protection : type stated Wk
Rail Method of Measurement - 2 - Detailed Measurement
July 2014
Industry Consultation Issue - Not for Reproduction or Sale
37
-
8/17/2019 Rail Method of Measurement 2 Detailed Measurement
41/106
RMM Volume 2
Class A3 - Contractor's Prelims
RMM Volume 2
Class A3 - Contractor's Prelims
MEASUREMENT RULES DEFINITION RULES ADDITIONAL RULESCOVERAGE RULES
M23 Items for temporary works that
are required by the employer
shall be identified; the scope and
period of the temporary works
shall be described.
D13 All temporary works expressly
required by the employer shall
be classed as temporary works
and included in this Class
C10 Items for traffic regulation shall
be deemed to include
possession or live infrastructure
A15 Where possessions of road
infrastructure is required, details
of the dates, time, lengths and
types of possession shall be
identified
M24 Items for traffic regulation shall
describe the location, the periodand the times of the regulation
D14 Where partial closures to public
or private thoroughfares, orroads are required for the
execution and completion of the
Works, they shall be classed as
traffic regulation
C11 Items for temporary works shall
be deemed to include the cost ofestablishment, maintenance and
removal.
M25 Items shall be given for
temporary speed restrictions
expressly required to allow the
works to proceed
D15 Where speed restrictions are
expressly required to allow the
works to be executed safely,
they shall be classed as
temporary speed restrictions
C12
D16 Where complete closure of
public or private thoroughfares,or road, are required for the
execution and completion of the
Works, they shall be classed as
traffic diversion.
C13 Items for traffic regulation and
traffic diversion shall be deemedto include the provision,
maintenance and removal of all
warning, lights, barriers and
traffic signals
M26 Items for service interruption
shall describe the type of service
to be interrupted, the period of
the interruption and the provision
of any temporary service.
D17 Where partial interruptions of
services , water, gas, electricity
or telecommunications, are
required for the completion of
the Works, they shall be classed
as service interruptions
C14 Items for service interruptions
shall be deemed to include the
provision, maintenance and
removal of all temporary
services
A16 Where isolations of power or
other services to rail
infrastructure is expressly
required by the employer,
details, the dates, time, length
and types of isolation shall be
stated
M28 Items for service protection shall
describe the type of service and
the period of protection
D19 Where services, water, gas,
electricity and
telecommunications, are
required to remain insitu, live,
and protected from disturbance
or pollution during the execution
and completion of the Works,
they shall be classed as service
protections
C16 Items for service protection shall
be deemed to include the
provision, maintenance and
removal of all protection
measures
Items for temporary speed
restrictions shall be deemed to
include obtaining permits for the
restriction, serving al