rain-wind vibration: different approaches ... - ravenel bridge
TRANSCRIPT
Rain-Wind Vibration: Different Approaches at
Different Locations
Rain-Wind Vibration: Different Approaches at
Different Locations
Michael J. Abrahams, P.E.Vijay Chandra, P.E.
Ruchu Hsu, P.E.
Michael J. Abrahams, P.E.Vijay Chandra, P.E.
Ruchu Hsu, P.E.
Parsons BrinckerhoffParsons Brinckerhoff
Workshop on Wind Induced Vibration of Cable Stayed Bridges, St. Louis, MO. April 27, 2006
Replacement of theCooper River BridgesCharleston, South Carolina
Replacement of theCooper River BridgesCharleston, South Carolina
Michael J. AbrahamsMichael J. AbrahamsMichael J. Abrahams
Cable Stay SpanCable Stay Span
Diamond Towers
Roadway – 200 Feet Above Water
1546 Foot Long Span
Tower Height – 570 Feet
Longest Span in North and South America
140 Feet Wide Section – 8 Traffic Lanes Plus Pedestrian/bicycle Lane
Diamond Towers
Roadway – 200 Feet Above Water
1546 Foot Long Span
Tower Height – 570 Feet
Longest Span in North and South America
140 Feet Wide Section – 8 Traffic Lanes Plus Pedestrian/bicycle Lane
Wind Tunnel TestingWind Tunnel Testing
M2 M2 –– Turbulent FlowTurbulent Flow
Stay Cable System FeaturesStay Cable System Features
Freyssinet Monostrand, Isotension System
Extensive System Testing Program (PTI)
Freyssinet on Design – Build Subcontract
Joint effort PB- Freyssinet - PBC
Early Stage Parametric Exitation Study
Early Integration of Damping System
Provisions for Cross-ties
Freyssinet Monostrand, Isotension System
Extensive System Testing Program (PTI)
Freyssinet on Design – Build Subcontract
Joint effort PB- Freyssinet - PBC
Early Stage Parametric Exitation Study
Early Integration of Damping System
Provisions for Cross-ties
Strand ErectionStrand Erection
Welding of Stay PipesWelding of Stay Pipes
Lifting of Stay PipeLifting of Stay Pipe
Initial Length and TensionInitial Length and Tension
Upper Anchorage Inside TowerUpper Anchorage Inside Tower
Vibration Suppression DevicesVibration Suppression Devices
External Hydraulic DampersExternal Hydraulic Dampers
Internal Hydraulic DampersInternal Hydraulic Dampers
Lateral Lateral SupportsSupports
Concrete Concrete Blocks for Blocks for StiffnessStiffness
Cooper River BridgesCooper River Bridges
Vijay Chandra P.E.Vijay Chandra P.E.Senior VP / Service Center managerSenior VP / Service Center manager
Parsons BrinckerhoffParsons Brinckerhoff
Leonard P. Zakim Bunker Hill BridgeCentral Artery /Tunnel Project
Boston, Massachusetts
Leonard P. Leonard P. ZakimZakim Bunker Hill BridgeBunker Hill BridgeCentral Artery /Tunnel ProjectCentral Artery /Tunnel Project
Boston, MassachusettsBoston, Massachusetts
Bridge ElevationBridge Elevation
Bridge PlanBridge Plan
Main Span SuperstructureMain Span Superstructure
Back Span SuperstructureBack Span Superstructure
Stay CableStay Cable
Old Concept Old Concept New ConceptNew Concept
Internal DamperInternal Damper
Wind TieWind Tie
Required Damping (with Cross-ties)South Tower Main StaysRequired Damping (with Cross-ties)South Tower Main Stays
Required Damping (with Cross-ties)North Tower Main StaysRequired Damping (with Cross-ties)North Tower Main Stays
ViscoVisco--Elastic DampersElastic Dampers
Cross Tie Connection OverviewCross Tie Connection Overview
Cross Tie DetailCross Tie Detail
Cross Tie Connection DetailCross Tie Connection Detail
Section A-ASection A-A
Load TestingLoad Testing
Holiday Lighting Scheme
William H. Natcher BridgeOwensboro, KY
William H. William H. NatcherNatcher BridgeBridgeOwensboro, KYOwensboro, KY
Ruchu Hsu, P.E.Project Engineer
Parsons Brinckerhoff (PB)
Ruchu Hsu, P.E.Project Engineer
Parsons Brinckerhoff (PB)
Bridge Site
Elevation of Cable-Stayed SpansElevation of Cable-Stayed Spans
Steel Composite SuperstructureSteel Composite Superstructure
Cable ConnectionCable Connection
Tower Head and Cable ConnectionsTower Head and Cable Connections
Access Inside Tower HeadAccess Inside Tower Head
The Goal of Longevity and Minimum Maintenance Have
Been Achieved In Design.
The Goal of Longevity and The Goal of Longevity and Minimum Maintenance Have Minimum Maintenance Have
Been Achieved In Design.Been Achieved In Design.
ChaoChao PhrayaPhraya River BridgeRiver BridgeSouthern Outer Bangkok Southern Outer Bangkok
Ring Road ProjectRing Road ProjectDesigner: Designer: RuchuRuchu HsuHsu
Chao Phraya River Bridge
SOBRR
ELEVATIONELEVATION
PLAN
ELEVATION
500m Main Span941m Total Length
36.7m Width (4 Lanes Each Way)
Result of Engineer & Result of Engineer & Architect CooperationArchitect Cooperation
Tower & Anchor Pier ConstructionTower & Anchor Pier Construction
Stay Cable Stay Cable
Wind Tie Layout and DetailsWind Tie Layout and Details
Human EngineeringHuman Engineering
A User Friendly Bridge for ThailandA User Friendly Bridge for Thailand