ranger mine locked bag 1, jabiru nt 0886 …plant modifications reduced process water inputs by...
TRANSCRIPT
Head office Level 10, TIO Centre,
24 Mitchell St, Darwin NT 0800 GPO Box 2394, Darwin NT 0801, Australia
T +61 8 8924 3500 F +61 8 8924 3555
Ranger mine Locked Bag 1, Jabiru NT 0886 Australia
T +61 8 8938 1211 F +61 8 8938 1203
www.energyres.com.au ABN 71 008 550 865 A member of the Rio Tinto Group
31 May 2011 Company Announcements Office Australian Stock Exchange Limited Level 4, Stock Exchange Centre 20 Bridge Street SYDNEY NSW 2000 Dear Sir/Madam Attached is a handout provided during a meeting with analysts in Sydney and Melbourne by Rob Atkinson, Chief Executive and Steeve Thibeault, Chief Financial Officer, on Tuesday 31 May 2011 and Wednesday 1 June 2011. A copy of this handout can be found on the company’s website at www.energyres.com Yours faithfully
Robert O’Toole Company Secretary
For
per
sona
l use
onl
y
1
Los Angeles, USA.
Energy Resources of Australia LtdAustralian Financial CommunityMay 2011
For
per
sona
l use
onl
y
2
Forward-looking statementsThis presentation has been prepared by Energy Resources of Australia Ltd (“ERA”) and consists of the slides for a presentation concerning ERA.By reviewing/attending this presentation you agree to be bound by the following conditions.
Forward-looking statementsThis presentation includes forward-looking statements. All statements other than statements of historical facts included in this presentation,including, without limitation, those regarding ERA’s financial position, business strategy, plans and objectives of management for futureoperations (including development plans and subjectives relating to ERA’s products, production forecasts and reserve and resource positions),are forward-looking statements. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which maycause the actual results, performance or achievements of ERA, or industry results, to be materially different from any future results, performanceor achievements expressed or implied by such forward-looking statements.
Such forward-looking statements are based on numerous assumptions regarding ERA’s present and future business strategies and theenvironment in which ERA will operate in the future. Among the important factors that could cause ERA’s actual results, performance orachievements to differ materially from those in the forward looking statements include, among others, levels of actual production during anyperiod, levels of demand and market prices, the ability to produce and transport products profitably, the impact of foreign currency exchange rateson sales revenues, market prices and operating costs, operational problems, political uncertainty and economic conditions in relevant areas of theworld, the actions of competitors, activities by governmental authorities such as changes in taxation or regulation and such other risk factorsidentified in ERA’s most recent Annual Report. Forward-looking statements should, therefore, be construed in light of such risk factors and unduereliance should not be placed on forward-looking statements. These forward-looking statements speak only as of the date of this presentation.
Nothing in this presentation should be interpreted to mean that future earnings per share of ERA will necessarily match or exceed its historicalpublished earnings per share.
The information in this presentation relating to exploration results is based on information compiled by Greg Rogers, who is a member of theAustralasian Institute of Mining and Metallurgy. Greg Rogers is a full-time employee of the company and he has sufficient experience which isrelevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a CompetentPerson as defined in the 2004 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. GregRogers consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
For
per
sona
l use
onl
y
3
Acknowledge Traditional Owners
The mining operations of Energy Resources of Australia Ltd (ERA) are located on Aboriginal land and are surrounded by, but separate from, Kakadu National Park.
ERA respectfully acknowledges the Mirarr, Traditional Owners of the land on which the Ranger Mine is situated.
For
per
sona
l use
onl
y
4
• Continued strong safety performance;
• Suspension of production from late January to expected late July 2011;
• Successful management of third highest wet season on record;
• Significant maintenance work completed in plant;
• Strong mining fleet utilisation resulting in higher material mined;
• Announced significant investment in water management;
– Brine concentrator
– Tailings Storage Facility
– Pond water treatment
• Decisions for Heap Leach Project and Ranger 3 Deeps Project pending
Key Outcomes in YTD - May 2011F
or p
erso
nal u
se o
nly
5
SafetyContinued strong safety performance
0.00
1.00
2.00
3.00
4.00
5.00
2004 2005 2006 2007 2008 2009 2010 2011
AIFR LTIFR
Freq
uenc
y rat
e (pe
r 200
,000 h
rs w
orke
d)
LTIFR 0
For
per
sona
l use
onl
y
6
Indigenous Employment
9598
83
544646
25
83
0
20
40
60
80
100
120
2004
2005 2006
2007
2008
2009
2010201
1(YTD
)
Numb
er
0
2
4
6
8
10
12
14
16
18
20
Per c
ent o
f wor
k for
ce
Avg No. Ind. employees% Ind. employees
For
per
sona
l use
onl
y
7
2010/2011 Wet SeasonRainfall from 01 September 2010 to 23 May 2011 (2427mm Bureau of Meteorology Jabiru Airport)
1. 2006/07 2527mm2. 1975/76 2500mm3. 2010/11 2427mm4. 2005/06 2107mm5. 2000/01 2052mm
Prod
uctio
n su
spen
sion
For
per
sona
l use
onl
y
8
Tailings Storage Facility status as of 23 May 2011Free process water level (Relative Level 52.77m)
48
49
50
51
52
53
54
55
1/01
/201
0
1/02
/201
0
1/03
/201
0
1/04
/201
0
1/05
/201
0
1/06
/201
0
1/07
/201
0
1/08
/201
0
1/09
/201
0
1/10
/201
0
1/11
/201
0
1/12
/201
0
1/01
/201
1
1/02
/201
1
1/03
/201
1
1/04
/201
1
1/05
/201
1
1/06
/201
1
Leve
l (m
RL)
TSF Free Process Water Level
Level (mRL) Maximum Operating Limit TSF Clay Core
For
per
sona
l use
onl
y
9
Pit#1 status as of 23 May 2011Free process water level (Relative Level 14.25m)
*Temporary MOL
* Temporary maximum operating limit (MOL) as approved by the regulators
For
per
sona
l use
onl
y
10
Pit #3 status as of 23 May 2011Total pond water inventory at the end of the 2010/2011 wet season higher than 2006/2007 (Cyclone Monica)
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
Jan-
2009
Mar
-200
9
May
-200
9
Jul-2
009
Sep
-200
9
Nov
-200
9
Jan-
2010
Mar
-201
0
May
-201
0
Jul-2
010
Sep
-201
0
Nov
-201
0
Jan-
2011
Mar
-201
1
May
-201
1
Vol
ume
(ML)
Pond Water Inventory (RP2 and Pit#3)
Total Pond Inventory (ML) Dry Season Target (ML) RP2 Spillway Level
For
per
sona
l use
onl
y
11
Water Management Improvements• Significant catchment reduction works around Pit 1 to divert pond water from the process
water catchment
• Plant modifications reduced process water inputs by approx. 500 mega litres per year
• Enhanced treatment capacity of the current process water treatment plant by 26%,
• Raising the embankment of the Tailings Storage Facility (TSF) by 4 metres to provide additional storage during the 2011/12 and 2012/13 wet seasons and until the Brine Concentrator is commissioned
• Shut-down from 28 January to maintain the TSF level below the Maximum Operating Limit
• Installation of interception trenches around waste dumps to segregate clean run-off
• Obtained approval to temporarily increase the maximum operating level of Pit 1 to store process water
Using Pit 3 for emergency water storage remains the ultimate safeguard to protect the environment and preserve the structural integrity of the TSF. Trigger protocols have been prepared in consultation with StakeholdersF
or p
erso
nal u
se o
nly
12
Water Management Improvements
Interception trench
4m TSF wall raisePit 1 Catchment Work
Improved performanceof water treatment plant
Reduction of processwater inputs
For
per
sona
l use
onl
y
13
Additional Pond Water Treatment
• Addition of 11 mega litres /day of pond water treatment which doubles the current capacity
• Installation commenced April
• Foundations completed, tanks installed, pipelines installed, 5 containers installed
• To be commissioned by July 2011
• Pit 3 to be fully de-watered by Q4 2011F
or p
erso
nal u
se o
nly
14
Tailings Storage Facility LiftObjective• To provide process water storage through to Pit#3
availability to accept tailings and brine concentrator commissioning
• Increase embankment by four metres
Phase 1– Phase completed
– No new land disturbance
– Water management incorporated rainfall runoff to RP2
Phase 2– Commenced February 2011 with forecast completion
mid June 2011
Phase 3– Planned for June 2011 through October 2011
– Application to change Maximum Operating Limit being drafted;
– Final crest to be Relative Level 58m
For
per
sona
l use
onl
y
15
Brine Concentrator – Conceptual Flow Sheet• Approval of $80 million to conduct a feasibility
study and to secure long lead items. Total capex estimated at $220 million
• Target capacity 1.83Gigalitres of distillate per year
• Modular to allow for phased expansion
• 2 year procurement and construction lead time with commissioning scheduled for second half of 2013
• Further studies are being conducted on brine and salt disposal. Options being considered to remove/store residual salts include:
– Blending with tailings;
– Injection into the deposited tailings (Pit 3); and
– A cystalliser to produce a solid waste
• Pilot plant studies underway at Rio Tinto’s Research Facility
• No regret decision as water must be treated
STEAM
ELECTRICITY
MECHANICAL VAPOR
RECOMPRESSION SYSTEMS2 x Primary1 x Secondary
DISTILLATE TANK
TO WETLANDFILTER
POWERHOUSECONCENTRATED BRINE TANK
DILUTE BRINE TANK
FEED TANK
TAILINGS STORAGE FACILITY
P P S
For
per
sona
l use
onl
y
16
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Tonnes
PIT
3 MIN
ING
CESS
ATIO
N
MINI
NG &
PRO
CESS
ING
CEAS
ES IN
JA
NUAR
Y OF
2021
Pit 3 + Stockpiled ore through primary plant
Ranger Production RangeCurrent operations including Pit 3 (ending at the end 2012) and excludes major projects such as
Ranger 3 Deeps and Heap Leach
For
per
sona
l use
onl
y
17
Capital Expenditure – Water Management (2011-2014)
Total ($ million)
Brine concentrator ($80 million approved) 220
Tailings Storage Facility Embankment Lift (RL58m) 52
Pond Water – water treatment capacity 11ml/day 17
Pond Water Retention Ponds 30
Pit 3 tailings and process water pumping systems 48
Total 367For
per
sona
l use
onl
y
18
Rehabilitation ActivitiesCurrent operations (Pit 3 and stockpiles), excluding major projects
Description 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Facilities Demolition 1 1 1Pit #3 Backfill 1 1 1 1 1 1Relocate Residual Stockpiles 1 1Tails Reclamation to Pit #3 1 1 1 1 1 1Water Treatment 1 1 1 1 1 1 1 1 1 1 1 1 1
• Under the current lease obligation ERA is required to perform very significant rehabilitation work
• ERA must fully rehabilitate the Ranger site by 2026
• Most significant pieces of this work are:
– Water treatment (all water must be treated on site)
– Rehabilitation of Pit#1 (water extraction and >15Mt waste rock capping required)
– Relocation of tailings dam to Pit#3 (water, tailings wall and rehabilitation of site)
– Backfilling of Pit#3 (>100Mt of material needs to be moved back into pit)
• Significant capital and resources required
• The rehabilitation program is currently being reviewed including options and costs
• Rehabilitation is required under any strategic scenario
• Progressive rehabilitation will be carried out where possible
For
per
sona
l use
onl
y
19
Exploration ProgrammeZone 2 – Ranger Lease
300m Phase 1 (2011)
Phase 2 (2011)
2011 Drillholes
Proposed Soil Sampling
Ranger Lease boundary
Geophysical survey
Zone 1 – George Town Structure
• Ranger exploration program scheduled for 2011 – 2013
• Ranger 2011 Exploration program total $9 million
• Total estimated at approximately $20 million over 2011-2013
For
per
sona
l use
onl
y
20
Business Review• Internal team assisted by KPMG reviewing ERA’s near term strategic
priorities, business activities and operating model
• Two core objectives:
– Reduce near term cash costs to ensure the business is focussing on the most strategically appropriate and value creating activities, while ensuring our people remain safe and the environment is protected
– Define a path to restructure the business for the future after closure of Pit 3, when production will be significantly lower
• Immediate focus on reducing use of contractors, maintenance costs, improving procurement practices and limiting sustaining capital expenditure
• More detail to be provided with 2011 half year results announcement
For
per
sona
l use
onl
y
21
Ranger 3 Deeps Exploration DeclineF
or p
erso
nal u
se o
nly
22
Ranger 3 Deeps Exploration Decline – Critical Milestones
Milestone Target Date
Project approval June 2011
Award Site Preparation work August 2011
Commencement of Box Cut Excavation May 2012
Box Cut Excavation Completion Oct 2012
Commencement of Decline Construction Oct 2012
Commencement of Diamond Drilling Jun 2013
Decline Construction Completion Nov 2013
Diamond Drilling Completion May 2014
For
per
sona
l use
onl
y
23
Ranger 3 Deeps Exploration Decline – Potential Path to Production
• Exploration decline expected to be fully completed by 2014
• All drilling information studied and finalised
• Study completed on underground mine by early 2015
• Conversion of resources to reserves
• EIS submitted
• Mine Technical Committee approval sought for underground mine
For
per
sona
l use
onl
y
24
Proposed Heap Leach • ERA Board approval given for Feasibility Study (FS) in October 2009 ($36 million)
• Work continues on the Environmental Impact Statement (EIS) and it is expected to be ready for submission to the Northern Territory and Commonwealth Governments in H2 2011.
• Key dates:– Completion of the feasibility study Q4 2010
– Government approvals 2012
– ERA Board approval Pending FS and government approvals
– Project implementation 18-24 months
– Project completion and first production 2014 depending on all approvals
• Heap Leach approval requires wide range of stakeholders acceptance
• Approval pending
For
per
sona
l use
onl
y
25
Summary• Continued strong safety performance
• Severe rainfall season successfully managed by the suspension of production and significant water management strategies
• Expect to start up plant by end of July. Forecast production is 2400 tonnes for 2011
• Ranger 3 Deeps and Heap Leach – decision to be announced shortly
• Significant investment in water management to support ERA future
• Business review will examine strategic priorities, business activities and operational model
• Rehabilitation costs under review
• Exploration potential of Ranger Project AreaFor
per
sona
l use
onl
y