ranieri - university of tulsa cese professional ... · paul ranieri, and alan weston...
TRANSCRIPT
Presenters' Contact Information
Paul Ranieri
Conestoga-Rovers & Associates
2055 Niagara Falls Blvd. Suite Three,
Niagara Falls, New York 14304Niagara Falls, New York 14304
Phone: 716-297-2160
Email: [email protected]
CHEMICAL OXIDATION AT
OPERATING GAS STATIONS
Sophia Dore, Christa Nunn, Donald Pope,
Paul Ranieri, and Alan Weston
Conestoga-Rovers & Associates
1. Introduction
2. Application System Design
3. Case Studies
Section
4. Conclusion
ISCO Treatment Review
� Involves complex processes
� Requires expertise and suitable site conditions
� Can save $$$ and accelerate cleanup
� Can be used as a pretreatment for MNA� Can be used as a pretreatment for MNA
In Situ Chemical Oxidation
� An oxidizing agent breaks carbon bonds in organic contaminants and converts them into nonhazardous compounds, primarily carbon dioxide and water
� Commonly used oxidizing reagents include potassium/sodium permanganate, Fenton’s Reagent, ozone, and sodium persulfateozone, and sodium persulfate
� A laboratory treatability study is required to select the most effective oxidant, and oxidant dose
� Successful ISCO treatment depends on the effectiveness of the delivery system
1. Introduction
2. Application System Design
3. Case Study
Section
4. Conclusion
Active Gas Stations
� Source of contamination can be spills
during filling of tanks or leaky fuel
storage tanks
� Flammable substances - Gasoline and � Flammable substances - Gasoline and
diesel range petroleum hydrocarbons
and BTEX compounds in soil and
groundwater
� Remedial activities must accommodate
day to day workings of the gas station
Steps for Safe ISCO Application at an
Operating Gas Station
� Treatability Study
� Determination of most
efficient oxidant
Calculation of dose and � Calculation of dose and
application rate
� Design of application
system
� Design of monitoring
system
Treatability Study
� Initial Characterization
� Microcosm Tests
� Natural Oxidant Demand � Natural Oxidant Demand
(NOD) determination
� Metals Leaching Tests
Delivery Methods
� Injection wells
� Direct push
� Mixing into open excavation
� Perforated pipe infiltration system� Perforated pipe infiltration system
Removal of LNAPL is recommended prior to ISCO Application
Design of Application System
� Use of Injection Wells for Injection
� Advantages
• Permanent wells can be used multiple times
• Screened through the relevant depth interval
� Disadvantages � Disadvantages
• Expensive to install
• All applications must be made in the same locations
• May required well permits
Design of Application System
� Use of Direct Push for Injection
� Advantages
• Can inject through the relevant depth interval
• Can offset injections during later events to cover
area more effectivelyarea more effectively
• Less costly than installing permanent wells
� Disadvantages
• Not appropriate for deep applications
• Not appropriate for bedrock applications
• Limited pumping rates
Design of Application System
� Mixing of Oxidant into Open Excavation
� Advantages
• A large amount of oxidant can be applied therefore
the entire dose can be applied at once
• Can get good distribution of oxidant in tight soils• Can get good distribution of oxidant in tight soils
� Disadvantages
• Not appropriate for Fenton’s Reagent (H&S);
recommended for sodium persulfate
• Mixing equipment required
• Depth limitations
Design of Application System
� Perforated Pipe Infiltration System In Excavation
� Advantages
• Multiple applications of oxidant can be made
• Inexpensive to install
• Gravity vs. pressure injection• Gravity vs. pressure injection
• Can be safer to apply oxidant after backfilling at an
active gas station
• Can locate injection ports away from traffic areas
� Disadvantages
• Difficult to get good distribution of oxidant in tight
soils
Design of Monitoring System
� Parameters to monitor:
� Chemicals of concern
• To determine whether reduction has taken place
� MetalsMetals
• To determine whether metals have been solubilized by the ISCO reagents; Fe and Mn levels show the oxidation state in the groundwater
Design of Monitoring System
� Parameters to monitor: (cont.)
� Sulfate
• If persulfate is used since sulfate can be a
breakdown productbreakdown product
� DO and ORP
• To verify that oxygen levels have been increased by
the oxidant
Design of Monitoring System
� Health and Safety Monitoring:
� Vapor monitoring for TPH and BTEX
• To determine whether chemistry has been volatilized
� Temperature
• To determine whether a vigorous reaction is taking • To determine whether a vigorous reaction is taking
place
� Pressure
• To determine whether the reaction is causing
pressure to rise
1. Introduction
2. Application System Design
3. Case Study
Section
4. Conclusion
Scenario
� Gasoline spill at an active gas station
� Gasoline has been detected in soil and groundwater samples
� No LNAPL is present
What to do?
� Consider In Situ Treatment
� Monitored natural attenuation (MNA)
� In situ chemical oxidation (ISCO)
� In situ enhanced biodegradation (ISEB)
� Permeable Reactive Barrier (PRB)
Treatment Assessment
� Permeable Reactive Barrier (PRB)
� Air Sparge Soil vapor extraction (AS/SVE)
Monitored Natural Attenuation
� Gasoline degrades readily under aerobic conditions however:
� Concentrations in soil and groundwater are high
� Site is paved therefore oxygen will be depleted quickly
� Potential for off-site migration if contamination is not addressed quickly
� Conclusion: This site is not a good candidate for MNA
Treatment Assessment
� Conclusion: This site is not a good candidate for MNA
ISCO
� ISCO is effective for treatment of gasoline in soil and groundwater
� ISCO using sodium persulfate is safe for application at active gas stations
� ISCO using sodium persulfate is safe for application around underground utilities and around an AST
Treatment Assessment
underground utilities and around an AST
� ISCO treatment would be complete in 1-2 years
� Conclusion: ISCO is retained for consideration
ISEB
� Gasoline biodegrades readily under aerobic conditions
� Oxygen injection would be safe at an active gas station
� Injection using a technology such as iSOC could be applied with most equipment below grade so the day to day activities of the gas station would not be affected
� ISEB treatment would be complete in 3-4 years
Treatment Assessment
� ISEB treatment would be complete in 3-4 years
� Conclusion: ISEB is retained for consideration
PRB
� Could intercept and treat contaminated groundwater before it migrates off-Site
� Would not treat soil
� Would not address on-Site contamination
� Without source treatment PRB would need to be maintained for a long time
Treatment Assessment
for a long time
� PRB alone not appropriate for this Site
� Could be considered in combination
with source treatment
AS/SVE
� Gasoline is volatile and could be removed by AS/SVE
� AS/SVE system would need to be installed
� May not be cost effective for such a small site
� Once concentrations are reduced to low levels AS/SVE is no longer efficient therefore another technology would be required for polishing
Treatment Assessment
required for polishing
� Conclusion: AS/SVE is not a good technology for this site
Technologies Retained for Consideration
� ISCO
� ISEB
Next Step
� Conceptual designs and cost estimates
Treatment Assessment
Conceptual Design
� 3 injection wells + MW-5 required for either ISCO or ISEB
� ISCO: reagent injection wells
� ISEB: air/nutrient injection wells
Treatment Assessment
Proposed injection well
Cost estimates
� ISCO
� Assuming 1 year of treatment estimated cost: $75,250
� ISEB
� Assuming 3 years of treatment estimated cost:
Treatment Assessment
� Assuming 3 years of treatment estimated cost: $96,550
� ISCO is more cost effective and faster
� Recommendation: ISCO
� A solution containing a mixture of 15 percent sodium persulfate solution and 25 percent sodium hydroxide solution was injected into MW-5 and each of the three newly installed injection wells
Oxidant Application
Well Volume Injected (gallons)
IW-1 650
MW-5 660
IW-2 1,330
IW-3 1,830
Post Injection Monitoring
� Monitoring was performed 1 month and 3 months after
the first ISCO injection
� Between 60 and 98 percent removal of petroleum
hydrocarbons was observed after treatment
� Concentrations in some areas remained above criteria� Concentrations in some areas remained above criteria
Post Injection Monitoring
Criteria not exceeded
Criteria exceeded
Second Injection Event
� A second injection event was performed focusing on the
area that still exceeded criteria
� After the second injection event, petroleum hydrocarbon
concentrations at all monitoring wells were below criteria
� No further treatment was required� No further treatment was required
Application of Sodium Persulfate at an
Operating Gas Station
� Soil and groundwater at an active gas station are impacted
by petroleum hydrocarbons
� GRO has been detected in Site groundwater at
concentrations of up to 100,000 µg/Lconcentrations of up to 100,000 µg/L
� Benzene has been detected at 2,000 µg/L
� An area 20 ft x 60 ft was excavated
� A perforated pipe infiltration system was installed into the
open excavation
Case Study Cont’d
� The injection consisted of 10% H2O2 mixed with 20%
sodium persulfate
� Mixing of the catalyst and oxidant occurred immediately
prior to injectionprior to injection
� The injection was performed by gravity
� A bromide tracer was included with the injection
Results
� Monitoring results showed that TPHg and BTEX
concentrations in groundwater were reduced below
criteria in all but one of the monitoring wells
� Mobilization of metals did not occur� Mobilization of metals did not occur
� Soil vapor monitoring did not show impacts to air quality
� A vigorous reaction did not occur
1. Introduction
2. Application System Design
3. Case Study
Section
4. Conclusion
CONCLUSIONS
� ISCO can be successfully implemented at
active gas station sites
� Correct dose, application rate, application � Correct dose, application rate, application
system design, and monitoring must be
carefully determined
Questions?Questions?