ransportation of 3 units of ship’s block · 2018-08-30 · c hung y ang shipping co., ltd. #2302,...

6
CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected] T RANSPORTATION OF 3 units of Ship’s block Name of project DSME Block transportation POL/POD Yantai, CHINA / Okpo, S. Korea TOS May 10, 2017 ~ May 20, 2017 Cargo 3 units of Ship’s block Vessel MV “CY INTEROCEAN Contractor DSME / Dongbang Transport Logistics Co., Ltd. Total steaming distance approx. 510 nm Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering - Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual Ballasting of vessel during loading & discharging Description Q’ty Dimensions(m) Weight (ton) Length Width Height 4307 20k 1 set 58.6 15.8 35.0 2010.9 4308 642 1 set 10.1 15.8 6.1 309.8 4308 652 1 set 10.1 15.8 6.1 309.8 C ARGO D ESCRIPTION K EY I NFORMATION

Upload: others

Post on 16-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RANSPORTATION OF 3 units of Ship’s block · 2018-08-30 · C HUNG Y ANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51

CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected]

TRANSPORTATION OF 3 units of Ship’s block

Name of project DSME Block transportation

POL/POD Yantai, CHINA / Okpo, S. Korea

TOS May 10, 2017 ~ May 20, 2017

Cargo 3 units of Ship’s block

Vessel MV “CY INTEROCEAN Ⅱ”

Contractor DSME / Dongbang Transport Logistics Co., Ltd.

Total steaming distance approx. 510 nm

Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering

- Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual

Ballasting of vessel during loading & discharging

Description Q’ty Dimensions(m) Weight (ton) Length Width Height

4307 20k 1 set 58.6 15.8 35.0 2010.9

4308 642 1 set 10.1 15.8 6.1 309.8

4308 652 1 set 10.1 15.8 6.1 309.8

CARGO DESCRIPTION

KEY INFORMATION

Page 2: RANSPORTATION OF 3 units of Ship’s block · 2018-08-30 · C HUNG Y ANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51

CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected]

TRANSPORTATION OF 4 units of RMGs

Name of project BMCT 4RMGs Transportation

POL/POD Zhangzhou, CHINA / Mumbai, India

TOS Aug 23, 2017 ~ Sep 30, 2017

Cargo 4 units of RMGs

Vessel MV “CY INTEROCEAN Ⅱ”

Contractor Konecranes / Dongbang Transport Logistics Co., Ltd.

Total steaming distance approx. 4,189 nm

Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering

- Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual

Ballasting of vessel during loading & discharging

Description Q’ty Dimensions(m) Weight (ton) Length Width Height

Rail Mounded Gantry 4 sets 64.7 27.3 33.4 441.2

CARGO DESCRIPTION

KEY INFORMATION

Page 3: RANSPORTATION OF 3 units of Ship’s block · 2018-08-30 · C HUNG Y ANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51

CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected]

TRANSPORTATION OF Offshore top side & Jacket structure

Name of project Daman development project – 1st shipment

POL/POD Vung Tau, Vietnam / Daman Offshore Field, India

TOS Nov 30, 2017 ~ Feb 10, 2018

Cargo 1 Unit of Deck and 1 Unit of Jacket with loose parts

Vessel MV “CY INTEROCEAN II”

Contractor L&T Hydrocarbon Engineering Ltd / Dongbang Transport Logistics Co., Ltd

Total steaming distance approx. 3,030 nm

Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering

- Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual

Ballasting of vessel during loading & discharging

Description Q’ty Dimensions(m) Weight (ton) Length Width Height

C24-P2 Deck 1 set 31.7 27.3 33.4 1524.1

C24-P2 Jacket 1 set 25.0 25.2 36.5 1695.3

Riser Protector 1 set 4.1 18.9 11.4 80.0

Boatlanding 1 set 6.7 21.4 13.4 120.0

CARGO DESCRIPTION

KEY INFORMATION

Page 4: RANSPORTATION OF 3 units of Ship’s block · 2018-08-30 · C HUNG Y ANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51

CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected]

TRANSPORTATION OF Offshore Windfarm Jackets

Name of project East Anglia ONE OWF – Voyage 5

POL/POD Hamriyah, UAE / Belfast, North Ireland

TOS Feb 15, 2018 ~ May 03, 2018

Cargo 7 packages containing structural elements of six Jackets

Vessel MV “CY INTEROCEAN II”

Contractor Lamprell Energy Services

Total steaming distance approx. 6,500 nm

Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering

- Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual

Ballasting of vessel during loading & discharging

Description Q’ty Dimensions(m) Weight (ton) Length Width Height

Package-1 1 unit 42.9 31.1 21.5 2235.7

Package-2 1 unit 18.9 21.8 17.3 755.6

Package-3 1 unit 42.6 10.6 8.5 787.6

Package-4 1 unit 19.0 8.6 7.7 269.3

Package-5 1 unit 17.9 23.9 20.1 623.4

Package-6 1 unit 14.4 19.8 15.9 329.2

Package-7 1 unit 13.9 16.3 15.8 269.4

CARGO DESCRIPTION

KEY INFORMATION

Page 5: RANSPORTATION OF 3 units of Ship’s block · 2018-08-30 · C HUNG Y ANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51

CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected]

TRANSPORTATION OF 2 units of Gas Slug catcher

Name of project FADHILI - Gas Slug Catcher transportation – 1st shipment

POL/POD Gijon, Spain / Jubail, Saudi Arabia

TOS Feb 15, 2018 ~ May 03, 2018

Cargo 2 units of Gas Slug catchers

Vessel MV “CY INTEROCEAN II”

Contractor Coordinadora

Total steaming distance approx. 6,068 nm

Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering

- Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual

Ballasting of vessel during loading & discharging

Description Q’ty Dimensions(m) Weight (ton) Length Width Height

Gas Slug Catcher 2 units 43.7 10.5 11.1 2008.0

CARGO DESCRIPTION

KEY INFORMATION

Page 6: RANSPORTATION OF 3 units of Ship’s block · 2018-08-30 · C HUNG Y ANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51

CHUNG YANG Shipping CO., LTD. #2302, Centum Leaders Mark Bldg., 17 Apec-ro, Haeundae-gu, Busan, Korea. Tel : +82 51 745 9100 Fax : +82 51 745 9101 e-mail : [email protected]

TRANSPORTATION OF 3 units of Gas Slug catcher

Name of project FADHILI - Gas Slug Catcher transportation – 2nd shipment

POL/POD Gijon, Spain / Jubail, Saudi Arabia

TOS Aug 04, 2018 ~

Cargo 3 units of Gas Slug catchers

Vessel MV “CY INTEROCEAN II”

Contractor Coordinadora

Total steaming distance approx. 6,068 nm

Scope of work Sea-transport of cargoes by deck ship Project Management including Load-out / In operations Engineering

- Calculation of dynamic forces during sea voyages - Stability & Long. strength Check - Ballast Calculation - Check of structural strength of vessel’s deck - Preparation of transportation manual

Ballasting of vessel during loading & discharging

Description Q’ty Dimensions(m) Weight (ton) Length Width Height

Gas Slug Catcher 3 units 43.7 10.5 11.1 2008.0

CARGO DESCRIPTION