rate analysis of orr with present rates most
TRANSCRIPT
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
1/343
This softawre is based on Standard Data book for analysis of Rates for Road and Bridge Works
This Software runs on Microsoft Excel
INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
SUMMARY - In this sheet summary of all the rates analysized is presented
ANALYSIS- The analysis has been presented in 16 nos. of spread sheetsWorksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCE
Worksheet- 9 : CHAPTER-9 PIPE CULVERTSWorksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
2/343
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
3/343
(A) Usage Rates of Plant and Machinery
Sl. No. Description of Machine Activity Output Unit
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour
P&M-002 Concrete Mixing cum/hour 20 hour
P&M-003 Concrete Mixing cum/hour 13 hour
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour
P&M-006 Paving of concrete surface cum / hour 20 hour
P&M-007 Pumping of concrete cum / hour 33 / 22 hour
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour
P&M-017 cum/hour 60 /25 hour
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour
P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour 60 /60 /60 1175
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour
P&M-034 cum/hour 40 hour
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour
P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour
P&M-041 Ripper Scarifying cum/hour 60 hour
P&M-042 Rotavator Scarifying cum/hour 25 hour
P&M-043 Road marking machine Road marking Sqm/hour 100 hour
P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour
Output ofMachine
Batching and Mixing Plant (a) 30 cumcapacity
Batching and Mixing Plant (b) 15 - 20cum capacity
Concrete Paver Finisher with 40 HPMotorConcrete Pump of 45 & 30 cumcapacity
Front End loader 1 cum bucketcapacity
Soil loading / Aggregateloading
Soil Ordinary/Soil Marshy / SoilUnsuitable
Paver Finisher Hydrostatic with sensorcontrol 100 TPH
Paving of DBM/ BM/SDC/Premix
0.75 m dia to 1.2 m dia Boringattachment
Soil Compaction /BMCompaction
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
4/343
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour
P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km
P&M-053 Tractor Pulling capacity in HP 50 hour
P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour
P&M-060 Water Tanker Water Transport capacity in KL 6 hour
P&M-061 Water Tanker Water Transport capacity in KL 6 km
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour
Sl. No. Description of Machine Unit
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour
P&M-065 Belt conveyor system hour
P&M-066 Boat to carry atleast 20 persons hour
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour
P&M-069 Cold milling machine @ 20 cum per hour hour
P&M-070 Crane 5 tonne capacity hour
P&M-071 Crane 10 tonne capacity hour
P&M-072 Crane 15 tonne capacity hour
P&M-073 Crane 20 tonne capacity hour
P&M-074 Crane 40 T capacity hour
P&M-075 Crane with grab 0.75 cum capacity hour
P&M-076 Compressor with guniting equipment along with accessories hour
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour
P&M-078 Epoxy Injection gun hour
P&M-079 Generator 33 KVA hour
P&M-080 Generator 100 KVA hour
P&M-081 Generator 250 KVA hour
P&M-082 hour
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour
P&M-084 Jack for Lifting 40 tonne lifting capacity. day
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs
P&M-086 Plate compactor hour
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour
P&M-088 Texturing machine (for rigid pavement) hour
P&M-089 Truck Trailor 30 tonne capacity hour
P&M-090 Truck Trailor 30 tonne capacity t.km
P&M-091 Tunnel Boring machine hour
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour
P&M-093 Wet Mix Plant 100 TPH hour
P&M-094 Wet Mix Plant 75 TPH hour
Transportation of Concrete Mixto site
Transportation of Concrete Mixto site
Transportation of Concrete Mixto site
Transportation of Concrete Mixto site
Induction, deinduction and erection of plant and equipment including all components and accessories forpneumatic method of well sinking.
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
5/343
(B) Labour
Sl. No. Description of Labour Unit
L-01 Blacksmith (IInd class) day
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day
L-03 Blaster (Stone cutter) day
L-04 Carpenter I Class day
L-05 Chiseller (Head Mazdoor) day
L-06 Driller (Jumper) day
L-07 Diver day
L-08 Fitter day
L-09 Mali day
L-10 Mason (IInd class) day
L-11 Mason (Ist class) day
L-12 Mate / Supervisor day
L-13 Mazdoor day
L-14 Mazdoor/Dresser (Semi Skilled) day
L-15 Mazdoor/Dresser/Sinker (Skilled) day
L-16 Medical Officer day
L-17 Operator(grouting) day
L-18 Painter I class day
L-19 Para medical personnel day
(C) Materials
Sl. No. Description Unit
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum
M-004 Coarse sand at Mixing Plant cum
M-005 Coarse sand at Site cum
M-006 Fine sand at Site cum
M-007 Moorum at Site cum
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
6/343
Page 4 of 344
Sr No Description Unit QuantityRate Rs Cost Rs
1.1
Unit : cum
Taking output = 5.5 cum
Time required for
1 Min
13 Min
2 Min
4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 200.00 66.00
hour 0.330 520.00 171.60
b) Overheads @ 8 % on (a) 19.01
c) Contractors profit @ 10 % on (a+b) 25.66
Cost for 5.5 cum = a+b+c 282.27
Rate per cum = (a+b+c)/ 5.5 51.32
Note Unloading will be by tipping. say 51.00
1.4
Unit : t.km
1.4(I) Case I Surfaced Road
Speed with load : 25 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
hour 0.400 200.00 80.00
Time taken for empty return trip. hour 0.290 200.00 58.00
b) Overheads @ 8 % on (a) 11.04
c) Contractors profit @ 10 % on (a+b) 14.90
cost for 100 t km = a+b+c 163.94
Rate per t.km = (a+b+c)/100 1.64
say 1.60
1.4(II) Case II Unsurfaced Gravelled RoadSpeed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity
hour 0.500 200.00 100.00
Time taken for empty return trip hour 0.330 200.00 66.00
b) Overheads @ 8 % on (a) 13.28
c) Contractors profit @ 10 % on (a+b) 17.93
Ref. toMoRTHSpec.
Remarks/ Input
ref.
Loading and unloading of stoneboulder / stone aggregates / sand /kanker / moorum.Placing tipper at loading point, loading withfront end loader, dumping, turning for
return trip, excluding time for haulage andreturn trip
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cumbucket capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumpingand turning for return
iv) Waiting time, unforeseen
P&M-
Front end-loader 1 cum bucket capacity@ 25 cum/hour
P&M-017
Cost of Haulage Excluding Loadingand Unloading
Haulage of materials by tipper excludingcost of loading, unloading and stacking.
Taking output 10 tonnes load and lead10 km = 100 t.km
Speed while Returning empty : 35 km /
Time taken for onward haulage with P&M-
P&M-
Time taken for onward hanlage with P&M-
P&M-
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
7/343
Page 5 of 344
Cost for 100 t .km = a+b+c 197.21
Rate per t.Km = (a+b+c)/100 1.97
say 2.00
1.4(III) Case III
Speed with load : 10 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 200.00 200.00
Time taken for empty return trip hour 0.670 200.00 134.00
b) Overheads @ 8 % on (a) 26.72
c) Contractors profit @ 10 % on (a+b) 36.07
Cost for 100 t .km = a+b+c 396.79
Rate per t.Km = (a+b+c)/100 3.97
say 4.00
1.5
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 100.00 6.00 L-12
Mazdoor day 1.500 85.00 127.50 L-13
b) Material
cum 1.100 115.00 126.50 M-002
c) Overheads @ 8 % on (a+b) 20.80
28.08
Rate per cum = a+b+c+d 308.88
say 309.00
1.6
Unit : cum
a) Labour
Mate day 0.760 100.00 76.00 L-12
Mazdoor Skilled day 2.000 150.00 300.00 L-14
day 17.000 85.00 1445.00 L-13b) Material
cum 800.000 115.00 92000.00 M-001
c) Machinery
Hour 6.000 ### 70560.00
Front end loader 1 cum bucket capacity Hour 20.000 520.00 10400.00
Tipper 5.5 cum capacity Hour 20.000 200.00 4000.00
d) Overheads @ 8 % on (a+b+c) 14302.48
19308.35
Katcha Track and Track in river bed /nallah bed and choe bed.
Speed while returning empty : 15 km /
P&M-
P&M-
Hand Broken Stone Aggregates 63 mmnominal sizeSupply of quarried stone, hand breakinginto coarse aggregate 63 mm nominal size
(passing 80 mm and retained on 50 mmsieve) and stacking as directed
Supply of quarried stone 150 - 200 mmsize
d) Contractors profit @ 10 % on(a+b+c)
Crushing of stone aggregates 13.2 mmnominal size.
Crushing of stone boulders of 150 mm sizein an integrated stone crushing unit of 200tonnes per hour capacity comprising ofprimary and secondary crushing units, beltconveyor and vibrating screens to obtainstone aggregates of 13 mm nominal size.
Taking Output = 600 cum at crusher
Mazdoor including breaking of any
Stone Boulder of size 150 mm and
Integrated stone crusher of 200 TPHincluding belt conveyor and vibratingscreens
P&M-028
P&M-
P&M-
e) Contractors profit @ 10 % on
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
8/343
Page 6 of 344
Cost for 600 cum = a+b+c+d+e 212391.83
Rate per cum = (a+b+c+d+e)*0.95/600 336.29
say 336.00
Note
1.7
Unit : cum
a) LabourMate day 0.760 100.00 76.00 L-12
Mazdoor Skilled day 2.000 150.00 300.00 L-14
day 17.000 85.00 1445.00 L-13
b) Material
cum 800.000 115.00 92000.00 M-001
c) Machinery
Hour 6.000 ### 70560.00
Front end loader 1 cum bucket capacity Hour 20.000 520.00 10400.00
Tipper 5.5 cum capacity Hour 20.000 200.00 4000.00
d) Overheads @ 8 % on (a+b+c) 14302.48
19308.35
Cost for 670 cum = a+b+c+d+e 212391.83Rate per cum = (a+b+c+d+e)*0.90/670 285.30
say 285.00
Note
1.8
Unit : cum
a) Labour
Mate day 0.760 100.00 76.00 L-12
1. 800 cum of stone boulders are needed toget 600 cum of stone chips of size 13.2mm.2. 95% of above cost will be attributed tothe production of 600 cum of stone chips of
13.2 mm size and balance 5% to theproduction of stone dust which comes outas a by-product.3. The integrated stone crusher includesprimary and secondary crushing units.
Crushing of stone aggregates 20 mm
Crushing of stone boulders of 150 mm sizein an integrated stone crushing unit of 200tonnes per hour capacity comprising ofprimary and secondary crushing units, beltconveyor and vibrating screens to obtainstone aggregates of 20 mm nominal size.
Taking Output = 670 cum at crusher
Mazdoor including breaking of any size
Stone Boulder of size 150 mm and
Integrated stone crusher of 200 TPHincluding belt conveyor and vibratingscreens
P&M-028
P&M-
P&M-
e) Contractors profit @ 10 % on
1. 800 cum of stone boulders are needed toget 600 cum of stone chips of size 20 and40 mm.2. 90% of above cost will be attributed tothe production of 670 cum of stoneaggregates of 20mm size and balance 10%will be for smaller size aggregates andstone dust which comes out as a by-3. The integrated stone crusher includesprimary and secondary crushing units.
Crushing of stone aggregates 40 mm
Crushing of stone boulders of 150 mm sizein an integrated stone crushing unit of 200tonnes per hour capacity comprising ofprimary and secondary crushing units, beltconveyor and vibrating screens to obtainstone aggregates of 40 mm nominal size.
Taking Output = 750 cum at crusher
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
9/343
Page 7 of 344
Mazdoor Skilled day 2.000 150.00 300.00 L-14
Mazdoor day 17.000 85.00 1445.00 L-13
b) Material
cum 800.000 115.00 92000.00 M-001
c) Machinery
Hour 6.000 ### 70560.00
Front end loader 1 cum bucket capacity Hour 20.000 520.00 10400.00
Tipper 5.5 cum capacity Hour 20.000 200.00 4000.00
d) Overheads @ 8 % on (a+b+c) 14302.48
19308.35
Cost for 750 cum = (a+b+c+d+e)x0.85 180533.05
Rate per cum = (a+b+c+d+e)x0.85/750 240.71
say 241.00
Note
5.9 510 Surface Dressing
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 100.00 44.00 L-12Mazdoor day 9.000 85.00 765.00 L-13
Mazdoor skilled day 2.000 200.00 400.00 L-15
b) Machinery
hour 7.200 230.00 1656.00
Air compressor 250 cfm hour 7.200 196.00 1411.20
hour 6.000 1700.00 10200.00
hour 6.000 200.00 1200.00
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
Bitumen pressure distributor hour 6.000 692.00 4152.00
hour 6.000 297.00 1782.00
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 ### 174196.66 M-074
cum 135.000 244.00 32940.00 M-053
d) Overheads @ 8 % on (a+b+c) 18549.35
25041.62
Cost for 9000 sqm= a+b+c+d+e 275457.82
Stone Boulder of size 150 mm and
Integrated stone crusher of 200 TPHincluding belt conveyor and vibrating
screens
P&M-028
P&M-
P&M-
e) Contractors profit @ 10 % on
1. 800 cum of stone boulders are needed toget 600 cum of stone chips of size 13.2mm.2. 85% of above cost will be attributed tothe production of 750 cum of stoneaggregates of 40mm size and balance 15%will be for smaller size aggregates and
stone dust which comes out as a by-3. The integrated stone crusher includesprimary and secondary crushing units.
Providing and laying surface dressing aswearing course in single coat using crushedstone aggregates of specified size on alayer of bituminous binder laid on preparedsurface and rolling with 8-10 tonne smoothwheeled steel roller
Mechanical broom @ 1250 sqm perhour
P&M-031P&M-001Hydraulic self propelled chip spreader
@ 1500 sqm per hourP&M-025
Tipper 10 tonne capacity for carriage ofstone chips from stockpile on road sideto chip spreader
P&M-048
P&M-017P&M-
004Smooth wheeled roller 8-10 tonneweight
P&M-044
Crushed stone chipping,19 mm nominalsize @ 0.015 cum per sqm
e) Contractors profit @ 10 % on(a+b+c+d)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
10/343
Page 8 of 344
Rate per sqm = (a+b+c+d+e)/9000 30.61
say 31.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 100.00 44.00 L-12
Mazdoor day 9.000 85.00 765.00 L-13
Mazdoor skilled day 2.000 200.00 400.00 L-15
b) Machinery
hour 7.200 230.00 1656.00
Air compressor 250 cfm hour 7.200 196.00 1411.20
hour 6.000 1700.00 10200.00
hour 6.000 200.00 1200.00
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
hour 6.000 692.00 4152.00
Vibratory roller 8-10 tonne weight hour 6.000 994.00 5964.00
c) MaterialBitumen@ 1.00 kg per sqm tonne 9.000 ### 145163.88 M-074
cum 90.000 244.00 21960.00 M-052
d) Overheads @ 8 % on (a+b+c) 15682.89
21171.90
Cost for 9000 sqm= a+b+c+d+e 232890.86
Rate per sqm = (a+b+c+d+e)/9000 25.88
say 26.00
Note
5.15 516 Slurry Seal
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 100.00 24.00 L-12
Mazdoor day 6.000 85.00 510.00 L-13
b) Machinery
Mechanical broom hour 6.000 230.00 1380.00
Mechanical broom @ 1250 sqm perhour
P&M-031P&M-001Hydraulic self propelled chip spreader
@ 1500 sqm per hourP&M-025
Tipper 10 tonne capacity for carriage ofstone chips from stockpile on road sideto chip spreader
P&M-048
P&M-017Bitumen pressure distributor @ 1750
sqm per hourP&M-004P&M-
059
Crushed stone chipping,13 mm nominalsize @ 0.01 cum per sqm
e) Contractors profit @ 10 % on(a+b+c+d)
1.Where the proposed aggregate fails topass the stripping test, an approvedadhesion agent may be added to the binder
as per clause 510.2.4. Alternatively, chipsmay be pre-coated as per clause 510.2.52.Input for the second coat, whererequired, will be the same as per the Istcoat mentioned above
Providing andlaying slurry seal consisting ofa mixture of fine aggregates, portlandcement filler, bituminous emulsion andwater on a road surface including cleaningof surface, mixing of slurry seal in asuitable mobile plant, laying and
Taking density of 2.2 tonnes per cum,weight of mix = 264 tonnes
P&M-031
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
11/343
Page 9 of 344
Air compressor 250 cfm hour 6.000 196.00 1176.00
Mobile slurry seal equipment hour 6.000 650.00 3900.00
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
hour 6.000 200.00 1200.00
hour 6.000 740.00 4440.00
Water tanker6 KL capacity hour 2.000 237.50 475.00
c) Material
tonne 19.360 ### 297599.98 M-077
cum 102.080 425.00 43384.00 M-005
tonne 3.520 input #VALUE! M-188
Cost of water KL 12.000 250.00 3000.00 M-189
d) Overheads @ 8 % on (a+b+c) #VALUE!
#VALUE!
Cost for 16000 sqm= a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/16000 #VALUE!
say #VALUE!
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 100.00 20.00 L-12
Mazdoor day 5.000 85.00 425.00 L-13
b) Machinery
Mechanical broom hour 6.000 230.00 1380.00
Air compressor 250 cfm hour 6.000 196.00 1176.00
Mobile slurry seal equipment hour 6.000 650.00 3900.00
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
hour 6.000 200.00 1200.00
Water tanker6 KL capacity hour 2.000 237.50 475.00
c) Material
tonne 17.160 ### 263781.80 M-077
cum 74.800 425.00 31790.00 M-005
tonne 2.640 input #VALUE! M-188Cost of water KL 12.000 250.00 3000.00 M-189
d) Overheads @ 8 % on (a+b+c) #VALUE!
#VALUE!
Cost for 30000 sqm= a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/20000 #VALUE!
say #VALUE!
Case III 1.5 mm thickness
P&M-001P&M-033P&M-017Tipper 5.5 cum capacity for carriage of
aggregate from stockpile on road sideto slurry equipment,bitumen emulsion
and filler.
P&M-048
Pneumatic tyred roller with individualwheel load not exceeding 1.5 tonnes
P&M-037
P&M-060
Residual Binder @ 11 % of mix 80 x 2.2x 0.11Fine aggregate 4.75 mm and below 87% of total mix,80 x 2.2 x 0.87 = 153.12tonnes. Taking density1.5,= 153.12/1.5= 102.08 cumFiller @ 2 % of total mix = 80 x 2.2 x0.02
e) Contractors profit @ 10 % on
(a+b+c+d)
P&M-
031P&M-001P&M-033P&M-017Tipper 5.5 cum capacity for carriage of
aggregate from stockpile on road sideto slurry equipment,bitumen emulsionand filler
P&M-048
P&M-060
Residual Binder @ 13 % of mix = 60 x2.2 x 0.13Fine aggregate 3 mm and below 85 %of total mix, 60x 2.2 x 0.85 = 112.2tonnes. Taking density 1.5,Filler @ 2 % of total mix =60x 2.2 x0.02
e) Contractors profit @ 10 % on(a+b+c+d)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
12/343
Page 10 of 344
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 100.00 20.00 L-12
Mazdoor day 5.000 85.00 425.00 L-13
b) Machinery
Mechanical broom hour 6.000 230.00 1380.00
Air compressor 250 cfm hour 6.000 196.00 1176.00
Mobile slurry seal equipment hour 6.000 650.00 3900.00
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
hour 6.000 200.00 1200.00
Water tanker6 KL capacity hour 2.000 237.50 475.00
c) Material
tonne 12.670 ### 194761.97 M-077
cum 43.300 406.00 17579.80 M-022
tonne 1.580 input #VALUE! M-188
Cost of water KL 12.000 250.00 3000.00 M-189
d) Overheads @ 8 % on (a+b+c) #VALUE!
#VALUE!
Cost for 24000 sqm= a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/24000 #VALUE!
say #VALUE!
Note
5.17 518 Fog Spray
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 100.00 12.00 L-12
Mazdoor day 3.000 85.00 255.00 L-13
b) Machinery
hour 6.000 230.00 1380.00
Air compressor 250 cfm hour 6.000 196.00 1176.00tonne 6.000 692.00 4152.00
c) Material
Bitumenemulsion @ 0.75 kg per sqm tonne 7.880 ### 121130.57 M-077
d) Overheads @ 8 % on (a+b+c) 10248.45
13835.40
Cost for 10500 sqm= a+b+c+d+e 152189.42
P&M-031P&M-001P&M-033P&M-017Tipper 5.5 cum capacity for carriage of
aggregate from stockpile on road sideto slurry equipment,bitumen emulsionand filler.
P&M-048
P&M-060
Residual Binder @ 16 % of mix, 36 x 2.2x 0.16Fine aggregate 2.36 mm and below,82
% of total mix,36x 2.2 x 0.82 = 64.94tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x0.02
e) Contractors profit @ 10 % on(a+b+c+d)
1.Tack coat, if required to be provided,before laying slurry seal may be measuredand paid separately
Providing and applying low viscositybitumen emulsion for sealing cracks lessthan 3 mm wide or incipient fretting ordisintegration in an existing bituminous
Mechanical broom @ 1250 sqm perhour
P&M-031
P&M-001Bitumen emulsion pressure distributor@ 1750 sqm per hour
P&M-004
e) Contractors profit @ 10 % on(a+b+c+d)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
13/343
Page 11 of 344
Rate per sqm = (a+b+c+d+e)/10500 14.49
say 14.00
a) Labour
Mate day 0.160 100.00 16.00 L-12
Mazdoor for precoating of grit day 4.000 85.00 340.00 L-13
c) Material
cum 26.250 406.00 10657.50 M-024
tonne 0.790 ### 12143.80 M-077
23157.30
2.21
say 2.00
5.21 522 Crack Prevention Courses
Case - I
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 100.00 24.00 L-12Mazdoor day 6.000 85.00 510.00 L-13
b) Machinery
hour 6.000 230.00 1380.00
Air compressor 250 cfm hour 6.000 196.00 1176.00
hour 6.000 692.00 4152.00
Hydraulic Chip spreader hour 6.000 1700.00 10200.00
Smooth wheeled road roller 8-10 tonne hour 6.000 297.00 1782.00
c) Material
Modified binder tonne 9.450 ### 170027.24 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 244.00 25620.00 M-050
d) Overheads @ 8 % on (a+b+c) 17189.70
23206.09
Cost for 10500 sqm= a+b+c+d+e 255267.03
Rate per sqm = (a+b+c+d+e)/10500 24.31
say 24.00
1.In case it is decided by the engineer toblind the fog spray, the following may beadded
Crushed stone grit 3 mm size @ 3.75 kgper sqmBitumenemulsion for precoating grit @2 % of grit,39.38 x 0.02
Stress Absorbing Membrane (SAM)crack width less than 6 mm
Providing and laying of a stress absorbingmembrane over a cracked road surface,with crack width below 6 mm after cleaningwith a mechanical broom, using modifiedbinder complying with clause 521, sprayedat the rate of 9 kg per 10 sqm andspreading 5.6 mm crushed stoneaggregates @ 0.11 cum per 10 sqm withhydraulic chip spreader, sweeping thesurface for uniform spread of aggregates
Mechanical broom @ 1250 sqm perhour
P&M-031P&M-001Bitumen pressure distributor @ 1750
sqm per hourP&M-004P&M-025P&M-044
e) Contractors profit @ 10 % on(a+b+c+d)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
14/343
Page 12 of 344
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 100.00 24.00 L-12
Mazdoor day 6.000 85.00 510.00 L-13
b) Machinery
hour 6.000 230.00 1380.00
Air compressor 250 cfem capacity hour 6.000 196.00 1176.00
hour 6.000 692.00 4152.00Hydraulic Chip spreader hour 6.000 1700.00 10200.00
Smooth wheeled road roller 8-10 tonne hour 6.000 297.00 1782.00
c) Material
Modified binder tonne 11.550 ### 207811.07 M-078
Crushed stone chipping 11.2 mm size cum105.000 244.00 25620.00 M-051
d) Overheads @ 8 % on (a+b+c) 20212.41
27286.75
Cost for 10500 sqm= a+b+c+d+e 300154.22
Rate per sqm = (a+b+c+d+e)/10500 28.59
say 29.00
Case III
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 100.00 24.00 L-12
Mazdoor day 6.000 85.00 510.00 L-13
Mazdoor skilled day 2.000 200.00 400.00 L-15
b) Machinery
hour 6.000 230.00 1380.00
Air compressor 250 cfem capacity hour 6.000 196.00 1176.00
hour 6.000 692.00 4152.00
Case -II
Stress Absorbing Membrane (SAM)with crack width 6 mm to 9 mm
Providing and laying of a stress absorbingmembrane over a cracked road surface,with crack width 6 to 9 mm after cleaningwith a mechanical broom, using modifiedbinder complying with clause 521, sprayed
at the rate of 11 kg per 10 sqm andspreading 11.2 mm crushed stoneaggregates @ 0.12 cum per 10 sqm,sweeping the surface for uniform spread of
Mechanical broom @ 1250 sqm perhour
P&M-031P&M-001
Bitumen pressure distributor @ 1750sqm per hour
P&M-004P&M-025P&M-044
e) Contractors profit @ 10 % on(a+b+c+d)
Stress Absorbing Membrane (SAM)crack width above 9 mm and crackedarea above 50 %Providing and laying a single coatn of astress absorbing membrane over a crackedroad surface, with crack width above 9 mmand cracked area above 50 % after cleaningwith a mechanical broom, using modifiedbinder complying with clause 521, sprayedat the rate of 15 kg per 10 sqm andspreading 11.2 mm crushed stoneaggregates @ 0.12 cum per 10 sqm,sweeping the surface for uniform spread of
Mechanical broom @ 1250 sqm perhour
P&M-031P&M-001Bitumen pressure distributor @ 1750
sqm per hourP&M-004
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
15/343
Page 13 of 344
Hydraulic Chip spreader hour 6.000 1700.00 10200.00
Smooth wheeled road roller 8-10 tonne hour 6.000 297.00 1782.00
c) Material
Modified binder tonne 15.750 ### 283378.73 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 244.00 30744.00 M-051
d) Overheads @ 8 % on (a+b+c) 26699.74
36044.65
Cost for 10500 sqm= a+b+c+d+e 396491.11
Rate per sqm = (a+b+c+d+e)/10500 37.76
say 38.00
Case IV
Unit = sqmTaking output = 3500 sqm
a) Labour
Mate day 0.560 100.00 56.00 L-12
Mazdoor day 12.000 85.00 1020.00 L-13
Mazdoor skilled day 2.000 200.00 400.00 L-15
b) Machinery
hour 2.800 230.00 644.00
Air compressor 250 cfem capacity hour 2.800 196.00 548.80
tonne 2.000 692.00 1384.00
Pneumatic roller hour 2.000 740.00 1480.00
c) Materialtonne 3.680 ### 55616.36 M-075
Geotextile including 10 % for overlaps sqm ### 400.00 1540000.00 M-108
d) Overheads @ 8 % on (a+b+c) 128091.93
172924.11
Cost for 10500 sqm= a+b+c+d+e 1902165.20
Rate per sqm = (a+b+c+d+e)/3500 543.48
say 543.00
NOTE
8.3 801
ii) English and Roman
P&M-025P&M-044
e) Contractors profit @ 10 % on(a+b+c+d)
Case - IV : Bitumen ImpregnatedGeotextileProviding and laying a bitumenimpregnated geotextile layer after cleaningthe road surface, geotextile conforming torequirements of clause 704.3, laid over atack coat with 1.05 kg per sqm of pavinggrade bitumen 80 - 100 penetration andconstructed to the requirement of clause
Mechanical broom @ 1250 sqm perhour
P&M-031P&M-001Bitumen pressure distributor @ 1750
sqm per hourP&M-004P&M-037
Paving grade bitumen of 80 - 100penetration @ 1.05 kg per sqm
e) Contractors profit @ 10 % on(a+b+c+d)
As bitumen overlay construction shallfollowclosely the fabric placement on the sameday, an output of 3500 sqm only has been
considered for the analysis which will covera length of 500 m, of 7 m widecarriagway. This can be conveniently overlaid by abitumenious course in a dayPrinting new letter and figures of anyshadePrinting new letter and figures of any shadewith synthetic enamel paint black or anyother approved colour to give an evenshade
Hyphens and the like not to be measuredand paid for
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
16/343
Page 14 of 344
Unit = per cm height per letter
a) Labour
Mate day 0.07 100 7.00
Painter Ist class day 1.25 200 250.00
Mazdoor day 0.5085 42.50
b) Material
Paint Litre 0.50 90 45.00
c) Overheads @ 8 % on (a+b) 27.56
d) Contractors profit @ 10 % on (a+b+c) 37.21
Cost for 1600 cm = a+b+c+d 409.27
0.26
say 0.30
8.8 803
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 100 12.00
Painter day 2.00 200 400.00
Mazdoor day 1.00 85 85.00
b) Material
Litre 6.00 150 900.00
9.00
c) Overheads @ 8 % on (a+b) 112.48
d) Contractors profit @ 10 % on (a+b+c) 151.85Cost for 40 sqm = a+b+c+d 1670.33
Rate per sqm = (a+b+c+d)/40 41.76
say 42.00
8.9 803 Painting on Steel Surfaces
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.03100 3.00
Painter day 0.45 200 90.00
Mazdoor day 0.25 85 21.25
b) Material
Paint ready mixed approved brand. Litre 1.25 90 112.50
1.13
c) Overheads @ 8 % on (a+b) 18.23
d) Contractors profit @ 10 % on (a+b+c) 24.61
Detail for 100 letters of 16 cm height.i.e.1600 cm
Rate per cm height per letter =(a+b+c +d)/1600
Painting Two Coats on New ConcreteSurfacesPainting two coats after filling the surfacewith synthetic enamel paint in all shades onnew plastered concrete surfaces
Paint conforming to requirement ofclause 803.3.Add for scaffolding @ 1% of labour costwhere required
Providing and applying two coats of readymix paint of approved brand on steelsurface after through cleaning of surface togive an even shade
Add @ 1% on cost of material forscaffolding
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
17/343
Page 15 of 344
Cost for 10 sqm = a+b+c+d 270.72
Rate per sqm = (a+b+c+d)/10 27.07
say 27.00
12.6 Cement mortar1:3 (1cement :3 sand)
Unit = 1 cumTaking output = 1 cum
a) Materials
Cement MT 0.51 3500.00 1785.00
Sand cum 1.05 425.00 446.25
b) Labour
Mate day 0.04 100.00 4.00
Mazdoor day 0.90 85.00 76.50
Total Material and Labour = (a+b) 2312.00
Cement mortar1:2 (1cement :2 sand)
Unit = 1 cumTaking output = 1 cum
a) Materials
Cement MT 0.67 3500.00 2352.00
Sand cum 0.93 425.00 396.67
b) Labour
Mate day 0.04 100.00 4.00
Mazdoor day 0.90 85.00 76.50
Total Material and Labour = (a+b) 2829.00
Cement mortar1:6 (1cement :6 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.29 3500.00 1008.00
Sand cum 1.20 425.00 510.00
b) Labour
Mate day 0.04 100.00 4.00
Mazdoor day 0.90 85.00 76.50
Total Material and Labour = (a+b) 1599.00
12.7 1400
Unit = cum
Taking output = 5 cum
(A)
a) Material
Stone cum 5.50 input #VALUE! M-169
Through and bond stone each 35.00 16.00 560.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
cum 1.50 2312.00 3468.00
b) Labour
Mate day 0.66 100.00 66.00 L-12
Sub-analysis (A)
Sub-analysis (B)
Sub-analysis (D)
Stone masonry work in cement mortar1:3 in foundation complete as drawingand Technical Specification
Square Rubble Coursed RubbleMasonry (first sort)
Cement mortar 1:3 (Rate as in Item12.6 A sub-analysis)
Item12.6 (A)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
18/343
Page 16 of 344
Mason day 7.50 200.00 1500.00 L-11
Mazdoor day 9.00 85.00 765.00 L-13
#VALUE!
#VALUE!
Cost for 5 cum = a+b+c+d #VALUE!
Rate per cum (a+b+c+d)/5 #VALUE!
say #VALUE!
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 92.50 508.75
Through and bond stone Nos 35.00 16.00 560.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 cum 1.55 2312.00 3583.60
b) Labour
Mate day 0.62 100.00 62.00
Mason day 6.00 200.00 1200.00
Mazdoor day 9.00 85.00 765.00
c) Overheads @ 8 % on (a+b) 534.35d) Contractors profit @ 10 % on (a+b+c) 721.37
Cost for 5 cum = a+b+c+d 7935.07
Rate per cum (a+b+c+d)/5 1587.01
say 1587.00
@
1400
Unit = cum
Taking output = 5 cum
1405.3 B) Random Rubble Masonry( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 92.50 508.75
Through and bond stone Nos 35.00 16.00 560.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 cum 1.55 1599.00 2478.45
b) Labour
Mate day 0.62 100.00 62.00
Mason day 6.00 200.00 1200.00
Mazdoor day 9.00 85.00 765.00
c) Overheads @ 8 % on (a+b) 445.94
d) Contractors profit @ 10 % on (a+b+c) 602.01Cost for 5 cum = a+b+c+d 6622.15
Rate per cum (a+b+c+d)/5 1324.43
say 1324.00
@
c) Overhead charges @ 8 % on
d) Contractor's profit @ 10 % on
The labour already considered in cementmortar has been taken into account whileproposing labour for masonry works.
12.7(Add)
Stone masonry work in cement mortar1:6 in foundation complete as drawingand Technical Specification
The labour already considered in cementmortar has been taken into account whileproposing labour for masonry works.
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
19/343
Page 17 of 344
12.8
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 4.13 3500.00 14455.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 8.10 244.00 1976.40
20 mm Aggregate cum 4.05 244.00 988.20
10 mm Aggregate cum 1.35 244.00 329.40
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 63 KVA hour 6.00 250.00 1500.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
1004.15
e) Overheads @ 8 % on (a+b+c+d) 2088.63
f) Contractors profit @ 10 % on (a+b+c+d+e) 2819.65
Cost for 15 cum = a+b+c+d+e+f 31016.19
Rate per cum (a+b+c+d+e+f)/15 2067.75
say 2068.00
Note
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) MaterialCement MT 5.16 3500.00 18060.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.60
10 mm Aggregate cum 2.70 244.00 658.80
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 C RCC Grade M20Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement MT 5.21 3500.00 18235.00
Coarse sand cum 6.75 425.00 2868.75
20 mm Aggregate cum 8.10 244.00 1976.40
10 mm Aggregate cum 5.40 244.00 1317.60
1500,1700 &2100
Plain/Reinforced cement concrete inopen foundation complete as perdrawing and technical specifications
d) Formwork @ 4% on cost of concretei.e.cost of material, labour and machinery
Nedle Vibrator is an item of minor T & Pwhich is already included in overheadcharges. Hence not added in rate analysisof cement concrete works.
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
20/343
Page 18 of 344
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 3500.00 145810.00
Coarse Sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
Lead beyond 1 km, L-lead in km T-km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
9786.76
e) Overheads @ 8 % on (a+b+c+d) 20356.46
f) Contractors profit @ 10 % on (a+b+c+d+e) 27481.22
Cost for 120 cum = a+b+c+d+e+f 302293.44Rate per cum = ( a+b+c+d+e+f )/120 2519.11
say 2519.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 3500.00 20965.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.60
10 mm Aggregate cum 2.70 244.00 658.80
b) Labour
Mate day 0.86 100.00 86.00Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
With Batching Plant, Transit Mixer andConrete Pump
d) Formwork @ 4% on cost of concretei.e.cost of material, labour and machinery
With Batching Plant, Transit Mixer andConrete Pump
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
21/343
Page 19 of 344
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 3500.00 167825.00
Coarse sand cum 54.00 230.00 12420.00
40 mm Aggregate cum 43.20 230.00 9936.00
20 mm Aggregate cum 43.20 230.00 9936.00
10 mm Aggregate cum 21.60 230.00 4968.00
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###10000.65
e) Overheads @ 8 % on (a+b+c+d) 22134.77
f) Contractors profit @ 10 % on (a+b+c+d+e) 29881.94
cost of 120 cum = a+b+c+d+e+f 328701.36
Rate per cum (a+b+c+d+e+f)/120 2739.18
say 2739.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 3500.00 21175.00Coarse sand cum 6.75 425.00 2868.75
20 mm Aggregate cum 8.10 244.00 1976.40
10 mm Aggregate cum 5.40 244.00 1317.60
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit : cumTaking Output = 120 cum
a) Material
Cement MT 48.38 3500.00 169330.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixer Kg 193.52 17.90 3464.01
b) Labour
Transit Mixer 4 cum capacity leadbeyond 1 Km, L - lead inKilometer
d) Formwork @ 3.75% of cost of concretei.e.cost of material, labour and machinery
With Batching Plant, Transit Mixer andConrete Pump
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
22/343
Page 20 of 344
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity 1 cum hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 3500.00 21280.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.6010 mm Aggregate cum 2.70 244.00 658.80
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit : cum
Taking Output = 120 cuma) Material
Cement MT 48.60 3500.00 170100.00
Coarse sand cum 54.00 230.00 12420.00
40 mm Aggregate cum 43.20 230.00 9936.00
20 mm Aggregate cum 43.20 230.00 9936.00
10 mm Aggregate cum 21.60 230.00 4968.00
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00 Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Transit Mixer 4 cum capacity leadbeyond 1 Km, L - lead inKilometer
Using Batching Plant, Transit Mixerand Conrete Pump
Transit Mixer 4 cum capacity leadbeyond 1 Km, L - lead inKilometer
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
23/343
Page 21 of 344
Taking output = 15 cum
a) Material
Cement MT 6.10 3500.00 21350.00
Coarse sand cum 6.75 425.00 2868.75
20 mm Aggregate cum 8.10 244.00 1976.40
10 mm Aggregate cum 5.40 244.00 1317.60
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 3500.00 170800.00
Coarse sand cum 54.00 230.00 12420.0020 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 3500.00 22155.00
Coarse sand cum 6.75 425.00 2868.75
20 mm Aggregate cum 8.10 244.00 1976.40
10 mm Aggregate cum 5.40 244.00 1317.60
b) Labour
Mate day 0.86 100.00 86.00
Mason day 1.50 200.00 300.00Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit ; cum
Case II Using Batching Plant, Transit Mixerand Conrete Pump
Transit Mixer 4 cum capacity leadbeyond 1 Km, L - lead inKilometer
Using Batching Plant, Transit Mixerand Conrete Pump
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
24/343
Page 22 of 344
Taking Output = 120 cum
a) Material
Cement MT 50.64 3500.00 177240.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixer Kg 202.56 17.90 3625.82
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
8391.74
e) Overheads @ 8 % on (a+b+c+d) 23049.33
f) Contractors profit @ 10 % on (a+b+c+d+e) 31116.59
cost of 120 cum = a+b+c+d+e+f 342282.48
Rate per cum (a+b+c+d+e+f)/120 2852.35
say 2852.00
2401.00
Note:
12.11
C Bottom Plug
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 3500.00 19425.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.6010 mm Aggregate cum 2.70 244.00 658.80
Admixer Kg 18.60 17.90 332.94
b) Labour
Mate day 0.90 100.00 90.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Transit Mixer 4 cum capacity leadbeyond 1 Km, L - leadin Kilometer
d) Formwork @ 3% on cost of concretei.e.cost of material, labour and machinery
Rate per cum (a+b+c+d)/120
Where ever concrete is carried out usingbatching plant, transit mixer, concretepump, admixers @ 0.4% of weight ofcement may be added for achieving desiredslump of concrete.
1200,1500 &1700
Plain/Reinforced cement concrete, inwell foundation complete as perdrawing and technical specification
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
25/343
Page 23 of 344
Generator 33 KVA hour 6.00 240.00 1440.00
hour 6.00 230.00 1380.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Note
Case II
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 3500.00 155400.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixer Kg 148.80 17.90 2663.52
b) Labour
Mate day 0.88 100.00 88.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) MachineryBatching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
(ii) PCC Grade M25
Case I Using Concrete Mixer
Unit = cumTaking output = 15 cum
a) Material
Cement MT 5.99 3500.00 20965.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.60
10 mm Aggregate cum 2.70 244.00 658.80
Admixer Kg 21.60 17.90 386.64
b) Labour
Mate day 0.90 100.00 90.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00Generator 33 KVA hour 6.00 240.00 1440.00
hour 6.00 230.00 1380.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit = cum
Taking output = 120 cum
Light Crane 3 tonnes capacity forhandling tremie pipe
10% extra cement may be added whereunder water concreting is involved.
Using Batching Plant, Transit Mixerand Crane/concrete pump
Transit Mixer 4 cum capacity, leadbeyond 1 Km, L - lead in Kilometer
Light Crane of 3 tonnes capacity forhandling tremie pipe
Using Batching Plant, Transit Mixerand Crane/concrete pump
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
26/343
Page 24 of 344
a) Material
Cement MT 47.88 3500.00 167580.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixer Kg 172.80 17.90 3093.12
b) Labour
Mate day 0.88 100.00 88.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
(iii) PCC Grade M30Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.08 3500.00 21280.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.60
10 mm Aggregate cum 2.70 244.00 658.80
Admixer Kg 21.60 17.90 386.64
b) Labour
Mate day 0.90 100.00 90.00
Mason day 1.50 200.00 300.00Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
hour 6.00 230.00 1380.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.64 3500.00 170240.00
Coarse sand cum 54.00 230.00 12420.0020 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixer Kg 172.80 17.90 3093.12
b) Labour
Mate day 0.88 100.00 88.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Transit Mixer 4 cum capacity, leadbeyond 1 Km, L - lead in Kilometer
Light Crane of 3 tonnes capacity forhandling tremie pipe
Using Batching Plant, Transit Mixerand Crane/concrete pump
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
27/343
Page 25 of 344
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
(iv) PCC Grade M35
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.29 3500.00 22015.00
Coarse sand cum 6.75 425.00 2868.75
40 mm Aggregate cum 5.40 244.00 1317.60
20 mm Aggregate cum 5.40 244.00 1317.60
10 mm Aggregate cum 2.70 244.00 658.80
Admixer Kg 21.60 17.90 386.64
b) LabourMate day 0.90 100.00 90.00
Mason day 1.50 200.00 300.00
Mazdoor day 20.00 85.00 1700.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
hour 6.00 230.00 1380.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II
Unit = cum
Taking output = 120 cuma) Material
Cement MT 50.28 3500.00 175980.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixer Kg 172.80 17.90 3093.12
b) Labour
Mate day 0.88 100.00 88.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00 Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Transit Mixer 4 cum capacity, leadbeyond 1 Km, L - lead in Kilometer
Light Crane of 3 tonnes capacity forhandling tremie pipe
Using Batching Plant, Transit Mixerand Crane/concrete pump
Transit Mixer 4 cum capacity, leadbeyond 1 Km, L - lead in Kilometer
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
28/343
Page 26 of 344
10927.56
d) Overheads @ 8 % on (a+b+c) 23109.09
e) Contractors profit @ 10 % on (a+b+c+d) 31197.28
cost of 120 cum = a+b+c+d+e 343170.05
Rate per cum (a+b+c+d+e)/120 2859.75
Say 2860.00
F Well cap
iv) RCC Grade M35
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 3500.00 177240.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
b) LabourMate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader(capacity 1 cum) hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upt hour 15.00 625.00 9375.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
Formwork @ 3% of (a+b+c) 8282.97
d) Overheads @ 8 % on (a+b+c) 22750.56e) Contractors profit @ 10 % on (a+b+c+d) 30713.25
cost of 120 cum = a+b+c+d+e 337845.78
Rate per cum (a+b+c+d+e)/120 2815.38
Say 2815.00
Note
3.13 304 Excavation for Structures
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
Add 5% of cost of material and labourtowards cost of forming sump, protectivebunds, chiselling and making arrangementsfor under water concreteing with tremiepipe..
Using Batching Plant, Transit Mixerand Conrete Pump
Where ever concrete is carried out usingbatching plant, transit mixer, concretepump, admixers @ 0.4% of weight ofcement may be added for achieving desired
Earth work in excavation of foundation ofstructures as per drawing and technicalspecification, including setting out,
construction of shoring and bracing,removal of stumps and other deleteriousmatter, dressing of sides and bottom,backfilling the excavation earth to the
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
29/343
Page 27 of 344
a) Labour
Mate day 0.320 100.00 32.00 L-12
Mazdoor day 8.000 85.00 680.00 L-13
b) Overheads @ 8 % on (a) 56.96
c) Contractors profit @ 10 % on (a+b) 76.90
Cost for 10 cum = a+b+c 845.86
Rate per cum = (a+b+c)/10 84.59
say 85.00
Note
B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 100 32.00
Mazdoor day 8.00 85 680.00
b) Machinery
Hydraulic excavator 1.0 cum bucket cap hour 6.00 1175 7050.00
c) Overheads @ 8 % on (a+b) 620.96
d) Contractors profit @ 10 % on (a+b+c) 838.30
Cost for 300 cum = a+b+c+d 9221.26
Rate per cum = (a+b+c+d)/300 30.74
say 31.00
Note
13.6
Output : MT
Taking output = 1 MT
a) Material
MT 1.05 ### 30187.50
Binding wire kg 6.00 34.00 204.00
Mate day 0.34 100.00 34.00
Blacksmith day 2.00 200.00 400.00Mazdoor day 6.50 85.00 552.50
c) Overheads @ 8 % on (a+b) 2510.24
d) Contractors profit @ 10 % on (a+b+c) 3388.82
Rate for per MT (a+b+c+d) 37277.06
say 37277.00
14.1
A RCC Grade M20
Cost of dewatering may be added whererequired upto 10 % of labour costAssessment for dewatering shall be madeas per site conditions..
Cost of dewatering upto 5% of (a+b) maybe added, where required. Assessment for
dewatering shall be made as per siteconditions..
Section1600 &2200
Supplying, fitting and placing HYSDbar reinforcement in sub-structurecomplete as per drawing and technicalspecifications
HYSD bars including 5% overlaps and
b) Labour for cutting, bending, shiftingto site, tying and placing in position
1500&16001700
Furnishing and PlacingReinforced/Prestressed cementconcrete in super-structure as perdrawing and Technical Specification
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
30/343
Page 28 of 344
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 3500.00 143220.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto hour 15.00 625.00 9375.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00t of Labour, Material & Mechinery (a+b+c) for 120 cum ###
(i)
(p) Height upto 5m
242079.00
d) Formwork and staging 20 % of (a+b+c) 20.00 48415.80
e) Overheads @ 8 % on (a+b+c+d) 23239.58
f) Contractors profit @ 10 % on (a+b+c+d+e) 31373.44
Cost for 15 cum = a+b+c+d+e+f 345107.82
Rate per cum (a+b+c+d+e+f)/120 2875.90
say 2876.00
B RCC Grade M25
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 3500.00 167825.00
Coarse sand cum 54.20 230.00 12466.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
b) Labour
Mate day 0.84 100.00 84.00
Mason day 3.00 200.00 600.00
Mazdoor day 18.00 85.00 1530.00c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto hour 15.00 625.00 9375.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
Using Batching Plant, Transit Mixerand Concrete Pump
For solid slab super-structure, 20-30%
Basic Cost of Labour, Material & Mechinery(a+b+c) for 120 cum
Using Batching Plant, Transit Mixerand Concrete Pump
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
31/343
Page 29 of 344
t of Labour, Material & Mechinery (a+b+c) for 120 cum ###
(i)
(p) Height upto 5m
266730.00
20.00 53346.00e) Overheads @ 8 % on (a+b+c+d) 25606.08
34568.21
Cost for 15 cum= a+b+c+d+e+f 380250.29
Rate per cum (a+b+c+d+e+f)/120 3168.75
say 3169.00
C RCC Grade M 30
Case II
Unit = cum
Taking output = 120 cuma) Material
Cement MT 48.79 3500.00 170765.00
Coarse sand cum 54.60 230.00 12558.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
b) Labour
Mate day 0.88 100.00 88.00
Mason day 3.00 200.00 600.00
Mazdoor day 19.00 85.00 1615.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto hour 15.00 625.00 9375.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
t of Labour, Material & Mechinery (a+b+c) for 120 cum ###
(i)
(p) Height upto 5m
269851.00
d) Formwork and staging 20 % of (a+b+c) 20.00 53970.20
e) Overheads @ 8 % on (a+b+c+d) 25905.70
f) Contractors profit @ 10 % on (a+b+c+d+e) 34972.69
Cost for 15 cum = a+b+c+d+e+f 384699.59
Rate per cum (a+b+c+d+e+f)/120 3205.83
say 3206.00
Rate per cum (a+b+c+d)/120 ( including formwork and excludin 2699.00
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excludin 2249.00
For formwork and staging add thefollowing:For solid slab super-structure, 20-30%of (a+b+c)
Basic Cost of Labour, Material & Mechinery(a+b+c) for 120 cum
d) Formwork and staging 20 % of(a+b+c)
f) Contractors profit @ 10 % on(a+b+c+d+e)
Using Batching Plant, Transit Mixerand Concrete Pump.
For formwork and staging add the
For solid slab super-structure, 20-30%
Basic Cost of Labour, Material & Mechinery(a+b+c) for 120 cum
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
32/343
Page 30 of 344
E PSC Grade M-40
Case 1 Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.45 3500.00 22575.00
Coarse sand cum 6.75 425.00 2868.75
20 mm Aggregate cum 8.10 244.00 1976.40
10 mm Aggregate cum 5.40 244.00 1317.60
Admixture @ 0.4% of cement kg 25.80 17.90 461.82
b) Labour
Mate day 0.96 100.00 96.00
Mason day 2.00 200.00 400.00
Mazdoor day 22.00 85.00 1870.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 33 KVA hour 6.00 240.00 1440.00
ost of Labour, Material & Mechinery (a+b+c) for 15 cum ###
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 51.60 3500.00 180600.00
Coarse sand cum 54.00 230.00 12420.00
20 mm Aggregate cum 64.80 230.00 14904.00
10 mm Aggregate cum 43.20 230.00 9936.00
Admixture @ 0.4% of cement kg 206.40 17.90 3694.56
Admixer Kg 216.00 17.90 3866.40
b) Labour
Mate day 0.94 100.00 94.00
Mason day 3.50 200.00 700.00
Mazdoor day 20.00 85.00 1700.00c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto hour 15.00 625.00 9375.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 19.00 34200.00 L= 6
Concrete Pump hour 6.00 165.00 990.00
st of Labour, Material & Mechinery (a+b+c) for 120 cum ###
(i)
(p) Height upto 5m
287300.00
18.00 51714.00
e) Overheads @ 8 % on (a+b+c+d) 27121.12
36613.51
Cost for 15 cum= a+b+c+d+e+f 402748.63
Rate per cum (a+b+c+d+e+f)/120 3356.24
say 3356.00
Using Batching Plant, Transit Mixer
and Concrete Pump
For formwork and staging add thefollowing:For solid slab super-structure, 18-28%of (a+b+c)
Basic Cost of Labour, Material & Mechinery(a+b+c) for 120 cum
d) Formwork and staging 18 % of(a+b+c)
f) Contractors profit @ 10 % on(a+b+c+d+e)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
33/343
Page 31 of 344
Note
14.2 1600
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and was MT 1.05 ### 30187.50Binding wire Kg 8.00 34.00 272.00
Mate day 0.44 100.00 44.00
Blacksmith day 3.00 200.00 600.00
Mazdoor day 8.00 85.00 680.00
um Basic Cost of Labour, Material & Mechinery (a+b+c) ###
1.Where ever concrete is carried out usingbatching plant, transit mixer, concretepump, admixers conforming IS: 9103 @0.4% of weight of cement may be added forachieving desired slump of concrete.2. Cement provided for various componentsof the super structure is for estimatingpurpose only. Actual quantity of cement
will be as per approved mix design.Similarly, the provision for coarse and fineaggregates is for estimating purpose andthe exact quantity shall be as per the mix3. The items like needle and surfacevibrators are part of minor T & P which isalready covered under the overheadcharges. As such these items have notbeen added seperately in the rate analysis.A) Supplying ,fitting and placing HYSDbar reinforcement in super-structurecomplete as per drawing and technicalspecifications
b) Labour for cutting, bending, tying andplacing in position
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
34/343
Page 32 of 344
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-1
CARRIAGE OF MATERIALS
1.1 cum 51.00
1.2 Loading and Unloading of Boulders by Manual Means cum 49.00
1.3 Loading and Unloading of Cement or Steel by Manual Means and stacking. tonne 69.001.4 Cost of Haulage Excluding Loading and Unloading
(i) Surfaced Road tonne.km 1.60
(ii) Unsurfaced Gravelled Road tonne.km 2.00
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. tonne.km 4.00
1.5 cum 309.00
1.6 cum 336.00
1.7 cum 285.00
1.8 cum 241.00
CHAPTER-2
SITE CLEARANCE
2.1
(i) Girth from 300 mm to 600 mm each 89.00
(ii) Girth from 600 mm to 900 mm each 175.00
(iii) Girth from 900 mm to 1800 mm each 317.00
(iv) Girth above 1800 mm each 582.00
2.2 Clearing Grass and Removal of Rubbish hectare 5287.00
2.3
(i) By Manual Means:-
A In area of light jungle hectare 16125.00
B In area of thorny jungle hectare 21676.00
(ii) By Mechanical Means
A In area of light jungle hectare 9598.00
B In area of thorny jungle hectare 11724.00
2.4
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below cum 142.00
B Cement Concrete Grade M-15 & M-20 cum 163.00
C Prestressed / Reinforced cement concrete grade M-20 & above cum 402.00
II By Mechanical Means for items No. 202( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 240.00
B Prestressed / Reinforced cement concrete grade M-20 & above cum 410.00
(ii) Dismantling Brick / Tile work
A In lime mortar cum 100.00
B In cement mortar cum 121.00
C In mud mortar cum 91.00
D Dry brick pitching or brick soling cum 87.00
(iii) Dismantling Stone Masonry
Loading and unloading of stone boulder / stone aggregates / sand / kanker /moorum. (Placing tipper at loading point, loading with front end loader, dumping,turning for return trip, excluding time for haulage and return trip)
Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone,hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retainedon 50 mm sieve) and stacking as directed)Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone bouldersof 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacitycomprising of primary and secondary crushing units, belt conveyor and vibrating screensto obtain stone aggregates of 13 mm nominal size.)Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacitycomprising of primary and secondary crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of 20 mm nominal size.)Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacitycomprising of primary and secondary crushing units, belt conveyor and vibrating screensto obtain stone aggregates of 40 mm nominal size.)
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting oftrees, including cutting of trunks, branches and removal of stumps, roots, stacking ofserviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in thedepression/pit.)
Clearing and Grubbing Road Land .(Clearing and grubbing road land includinguprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm,removal of stumps of trees cut earlier and disposal of unserviceable materials andstacking of serviceable material to be used or auctioned up to a lead of 1000 metresincluding removal and disposal of top organic soil not exceeding 150 mm in thickness.)
Dismantling of Structures (Dismantling of existing structures like culverts, bridges,retaining walls and other structure comprising of masonry, cement concrete, wood work,steel work, including T&P and scaffolding wherever necessary, sorting the dismantledmaterial, disposal of unserviceable material and stacking the serviceable material with alllifts and lead of 1000 metres)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
35/343
Page 33 of 344
Summary of Rate Analysis
Item No. Descriptions Unit Rate
A Rubble stone masonry in lime mortar cum 108.00
B Rubble stone masonry in cement mortar. cum 121.00
C Rubble Stone Masonry in mud mortar. cum 100.00
D Dry rubble masonry cum 95.00
E Dismantling stone pitching/ dry stone spalls. cum 91.00
F cum 100.00(iv) cum 239.00
(v)
A Including dismembering tonne 564.00
B Excluding dismembering. tonne 401.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 5.00
(vi) Scraping of bricks dismantled from brick work including stacking.
AIn lime/Cement mortar
370.00
BIn mud mortar
132.00
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 149.00
B In Mud mortar cum 31.00(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 5.00
(ix)
A Up to 600 mm dia metre 55.00
B Above 600 mm to 900 mm dia metre 74.00
C Above 900 mm metre 127.00
2.5
I By Manual Means
A Bituminous courses cum 259.00
B Granular courses cum 193.00
II By Mechanical Means
A Bituminous course cum 137.00
2.6 cum 1593.00
2.7 metre 29.00
2.8 metre 7.00
2.9 metre 10.00
2.10
A 5th KM stone each 131.00
B Ordinary KM Stone each 79.00
C Hectometre Stone each 16.00
2.11 metre 18.00
2.12 metre 47.00
2.13 metre 77.00
2.14 each 65.00
Dismantling boulders laid in wire crates including opening of crates andstacking dismantled materials.Wood work wrought framed and fixed in frames of trusses upto a height of 5 mabove plinth levelSteel work in all types of sections upto a height of 5 m above plinth levelexcluding cutting of rivet.
1000numbers
1000numbers
Removing all type of hume pipes and stacking within a lead of 1000 metresincluding earthwork and dismantling of masonry works.
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposalof dismantled materials up to a lead of 1000 metres, stacking serviceable andunserviceable materials separately)
Dismantling of Cement Concrete Pavement (Dismantling of cement concretepavement by mechanical means using pneumatic tools, breaking to pieces not exceeding0.02 cum in volume and stock piling at designated locations and disposal of dismantledmaterials up to a lead of 1000 metres, stacking serviceable and unserviceable materialsseparately)
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal ofdismantled material with all lifts and up to a lead of 1000 metres, stacking serviceablematerials and unserviceable materials separately.)Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal ofdismantled material with all lifts and up to a lead of 1000 metre)
Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual meansand disposal of dismantled material with all lifts and up to a lead of 1000 metre)
Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of
earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 mand back filling of pit.)
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencingincluding posts, foundation concrete, back filling of pit by manual means includingdisposal of dismantled material with all lifts and up to a lead of 1000 metres, stackingserviceable material and unserviceable material separately. )Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm diaincluding disposal with all lifts and lead upto 1000 metres and stacking of serviceablematerial and unserviceable material separately under supervision of concerneddepartment)Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concretepipe of sewer gutter 1500 mm dia under the supervision of concerned departmentincluding disposal with all lifts and up to a lead of 1000 metres and stacking of
serviceable and unserviceable material separately but excluding earth excavation anddismantling of masonry works.)
Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electricpoles including excavation and dismantling of foundation concrete and lines under thesupervision of concerned department, disposal with all lifts and up to a lead of 1000metres and stacking the serviceable and unserviceable material separately)
-
8/6/2019 Rate Analysis of ORR With Present Rates MOST
36/343
Page 34 of 344
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
3.1 cum 60.00
3.2 cum 82.00
3.3 cum 31.00
3.4 cum 52.00
3.5 cum 76.00
3.6 cum 34.00
3.7 cum 47.00
3.8
A Mechanised cum 272.00
B Manual Method cum 327.00
3.9 cum 130.00
3.10 cum 39.00
3.11 cum 35.00
3.12 sqm 55.00
3.13
(i) Ordinary soil
A Manual Means (Depth upto 3 m) cum 85.00
B Mechanical Means (Depth upto 3 m) cum 31.00
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 106.00
B Mechanical Means cum 42.00
(iii) Hard rock ( requiring blasting )
A Manual Means cum 198.00(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 286.00
(v) Marshy soil
A Manual means ( upto 3 m depth) cum 199.00
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manualmeans including loading in truck for carrying of cut earth to embankment site with all liftsand lead upto1000 metres.)Excavation in ordinary rock by manual means (Excavation in ordinary rock using
manual means including loading in a truck and carrying of excavated material toembankment site with in all lifts and leads upto 1000 metres )Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road wayin soil by mechanical means including cutting and pushing the earth to site ofembankment upto a distance of 100 metres (average lead50 metres), including trimmingbottom and side slopes in accordance with requirements of lines, grades and crossExcavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavationfor roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushingthe cut earth to site of embankment upto a distance of 100 metres ( average lead 50metres ), trimming bottom and side slopes in accordance with the requirements of lines,grades and cross sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres(Excavation for roadway in hard rock (requiring blasting) by drilling, blasting andbreaking, trimming of bottom and side slopes in accordance with requirements of lines,grades and cross sections, loading and disposal of cut road with in all lifts and leads upto1000 metres )
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposalupto 1000 metres. (Excavation for roadwork in soil with hydraulic excavator of0.9 cumbucket capacity including cutting and loading in tippers, trimming bottom and sideslopes, in accordance with requirements of lines, grades and cross sections, andtransporting to the embankment location within all lifts and lead upto 1000m)
Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers withdisposal upto 1000 metres. (Excavation for roadway in ordinary rock with hydraulicexcavator of 0.9 cum bucket capacity including cutting and loading in tippers,transporting to embankment site within all lifts and lead upto 1000 m, trimming bottomand side slopes in accordance with requirements of lines, grades and cross sections.)
Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock(blasting prohibited) with rock breakers including breaking rock, loading in tippers anddisposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes inaccordance with requirements of lines, grades and cross sections.)
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres(Excavation for roadway in hard rock with controlled blasting by drilling, blasting andbreaking, trimming of bottom and side slopes in accordance with requirements of lines,grades and cross sections, loading and disposal of cut road with in all lifts and leads upto1000 metres )
Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulicexcavator 0.9 cum bucket capacity including cutting and loading in tippers and disposalwith in all lifts and lead upto 1000 metres, trimming of bottom and side slopes inaccordance with requirements of lines, grades and cross sections.)Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal ofunserviceable soil including excavation, loading and disposal upto 1000 metres lead butexcluding replacement by suitable soil which shall be paid separately as per clause 305.)
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock toachieve a specified slope of the rock face by controlled use of explosives and blastingaccessories in properly aligned and spaced drill holes, collection of the excavated rock by
a 80 HP dozer, loading in tipper by a front end loader and disposing of the material withall lifts and lead upto 1000 m, all as specified in clause No. 303)
Excavation for Structures (Earth work in excavation of foundation of structures as perdrawing and technical specification, including setting out, construction of shoring andbracing, removal of stumps and other deleterious matter, dressing of sides and bottom,backfilling the excavation earth to