ratt ii summary - web viewsummary report – field visits. ratt ii team members tom pick, karin...

34
LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs) Summary Report – Field Visits RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell River affected by the 2011 flood. Field visits took place during the period September 23 thru 25, 2013 and September 30 and October 1, 2013 as directed under Agreement LMCD 2013-01 with the Lower Musselshell Conservation District: Development of Post-2011 Flood Best Management Practices (BMPs). The visits were coordinated by conservation district and Natural Resources Conservation Service (NRCS) staff. The purpose of the field visits was to interview a selection of landowners who had participated in the 2011 post-flood RATT process. Through discussion and observation it was the goal to determine what restoration practices have been completed; what practices have worked; what lessons have been learned; and how lessons can be shared with current and future river users. The team was accompanied by Doug Mann on September 23 and Scott Irvin on September 24, both from the DNRC- Regional Water Rights Office in Lewistown, Montana. This Summary Report provides a description of each field site visited, the nature of the flood-related resource issue(s) encountered, solutions discussed or implemented, and the current status of the situation. RATT priority ratings are provided for comparison. Sites were given treatment priority ratings in 2011 ranging from 1 (High) to 9 (Low) based on five criteria (see report for details). Information and observations obtained during the RATT and RATT II site visits will be used to develop draft BMPs for review by the LMCD. 1

Upload: nguyenhuong

Post on 30-Jan-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Summary Report – Field Visits

RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell River affected by the 2011 flood. Field visits took place during the period September 23 thru 25, 2013 and September 30 and October 1, 2013 as directed under Agreement LMCD 2013-01 with the Lower Musselshell Conservation District: Development of Post-2011 Flood Best Management Practices (BMPs). The visits were coordinated by conservation district and Natural Resources Conservation Service (NRCS) staff.

The purpose of the field visits was to interview a selection of landowners who had participated in the 2011 post-flood RATT process. Through discussion and observation it was the goal to determine what restoration practices have been completed; what practices have worked; what lessons have been learned; and how lessons can be shared with current and future river users. The team was accompanied by Doug Mann on September 23 and Scott Irvin on September 24, both from the DNRC-Regional Water Rights Office in Lewistown, Montana.

This Summary Report provides a description of each field site visited, the nature of the flood-related resource issue(s) encountered, solutions discussed or implemented, and the current status of the situation. RATT priority ratings are provided for comparison. Sites were given treatment priority ratings in 2011 ranging from 1 (High) to 9 (Low) based on five criteria (see report for details). Information and observations obtained during the RATT and RATT II site visits will be used to develop draft BMPs for review by the LMCD.

1

Page 2: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Monday, September 23, 2013

Jim Barrows: RATT Ref. # 41; 310 Permit No. 11-028: Bank Erosion, Overland Flow, and HQ flooding. Original visit on November 1, 2011. RATT priority ranking 2.

The Team met Mr. Barrows at his home near Ryegate. Mr. Barrows has not taken any action to date other than rebuilding his west property line fence and seeding grass over most of the flood affected area between his home and the river. Estimated construction costs of nearly $100,000 have prevented his proposed installation of bank riprap and an earthen berm. The river doesn’t appear to have changed much at this site since the post-flood visit in 2011. We again discussed removal of downed cottonwood trees on the downstream left bank (LB) to reduce the potential for accelerated bank erosion. We also suggested placement of a low elevation earth fill berm closer to his home to reduce impacts to the floodplain while meeting his objective of flood protection. The dike’s orientation should direct overland flow back into the wooded floodplain south of his property while minimizing the volume of excavation/fill material required. Materials and construction techniques were discussed as well as potential permits needed with these actions.

Figure 1. July 3, 2012 air photo of Barrows Site.

2

Page 3: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Jim Ballard (Egge Dam): RATT Ref. # 31; 310 Permit No. 11-046: Breached Diversion Dam. Original visit on October 18, 2011. RATT priority ranking 2. Also visited a damaged pump site on the Ballard Ranch RATT Ref. #32. RATT priority ranking 4.

Met Laura (representing Ballard), Steve Tyrell (neighbor and LMCD), and Steve Stoican (contractor) at the ranch and traveled to the sites. The pump site above the Egge Dam was left inoperable when the flooding damaged the pump and moved the active low-water channel away from the pump/sump. Flanking of the downstream Egge diversion dam also resulted in downcutting and loss of backwater for the pump. A side channel fill above the pump experienced some toe slope erosion. Recommendations in 2011 were to move the pump to a location upstream just below the fill. Protection of the toe fill would also provide protection for the pump. The pump should be equipped with a movable boom rather than a sump to provide more portability in case of future flooding. Estimated cost of reconstruction of the pump is in the $15 to $20K range. Factors surrounding reestablishment of the pump provide guidance for development of a BMP addressing this issue. Water right issues relative to moving the point of diversion (POD) upstream were also discussed by DNRC staff.

The Egge Diversion Dam has not been rebuilt or modified since the 2011 flood. The new bypass channel has not changed much although the right bank continues to erode along the field edge on the south side of the diversion. FWP has some interest in working with the owner of the dam to provide fish passage if it is restored. At present, it is no longer a barrier to fish passage. It is unknown if the owner will rebuild the facility or if anyone is responsible for removal if it is abandoned. Estimated costs of reconstruction are in the range of $75 to $100K so it may not be financially feasible. Use of pumps rather than a direct diversion was suggested but it is not known what the landowners will choose to do to restore irrigation. We discussed a number of ideas relative to fish passage, removal, and eroding bank protection using materials present at the site. Use of a transitional point of diversion was suggested if the POD is moved closer to the irrigated fields. A number of ideas were noted that are important in fish passage, structure/debris removal, and diversion dam BMPs. Several questions concerning 404 and 310 permits were raised and will be addressed in response.

3

Figure 2. July 3, 2012 air photo of Egge Dam.

Page 4: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Sylvan Anderson: RATT Ref. #5; 310 Permit No. 12-030-2. Bank Erosion/Threatened Irr. Field/Breached RR fill. Original visit September 21, 2011. RATT priority ranking 9. Also RATT Ref. #6; 310 Permit 12-030-2; Flanked Diversion Dam – put river back in old channel. Original visit on September 21, 2011. RATT priority ranking 5.

Met Sylvan Anderson and his son at the site accompanied by Steve Tyrell (LMCD representative). Donna Pedrazzi and Shirley Parrott of the LMCD met us at Andersons. No restoration actions have been taken other than the pump station has been re-built. We first looked at the eroding bank and RR fill upstream of the pump station. Sylvan has installed a center pivot irrigation system on the field adjacent to the eroding RR fill/bank. He is worried about future lateral channel movement into the field. It appears that the clay shelf that existed post-flood in 2011 has eroded out so the bank is now vertical. Sylvan planned to move the gravel bar on the LB across the channel to armor the eroding right bank (RB). Those present explained to Sylvan that to our knowledge he doesn’t have a 310 or 404 permit (and others) which are required to take such action. Mitigation would likely be required by USACE for this type and extent of fill. He does have a 310 permit to plant vegetation in this area. We suggested instead that he consider using rock barbs to protect key points on the RB. Two to three barbs would be likely needed as a phased and less costly approach to deflect water away from the actively eroding bank. We agreed to provide Sylvan with a plan view and sketch of a typical barb structure, although a formal site design will be needed to apply for needed construction permits. The costs of engineering and construction and uncertainty associated with tolerance for failure were discussed relative to developing a BMP for channel realignment and bank protection.

No work has been done on the flanked and buried diversion dam so we didn’t discuss this site in detail. Higher flows passively make it down the canal earlier in the summer, but low flows common during late season irrigation do not. Sylvan has thus far been unable to secure permits for restoring the channel and diversion dam.

A number of noxious weeds were observed in the flood affected areas which seems to argue the need for inclusion of a weed plan in the 310 permitting process.

4

Figure 3. July 2012 air photo of Anderson Site.

Page 5: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Brad Kinsey: RATT Reference No. 9; 310 Permit No. 11-009-11. Bank Erosion/Slope Bank for Pivot. Original visit on September 23, 2011. RATT priority rating 9.

Brad Kinsey met us at the site near the flanked Naderman Diversion Dam. Brad used a dozer to shape and slope the scarp cut by the avulsion to allow the pivot to run the original tower length. The project allowed recovery of about 12 to 13 acres of irrigated land. He has planted sudan /sorghum hybrid on the field. He estimates that a total of about $20K (equipment and operator time) was spent to restore the field which results in a salvage cost of a little over $1,500 per acre. A benefit of this practice is that the full use of the field was restored and the function and integrity of the floodplain was maintained without the cost and risk of using riprap to armor the bank.

Figure 4. July 2013 air photo of Kinsey site.

5

Page 6: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Naderman Diversion Dam: RATT Ref. #1; 310 Permit No. 11-015. Breached Diversion Dam and Move River Back to Original Channel. Original visit on September 22, 2011. RATT priority rating 4.

There are no plans to repair the Dam as the individual ditch members are now directly pumping from the river downstream. Joe Vescovi was present and expressed displeasure at the fact that the change (POD) process is taking too long. He is still not able to irrigate his entire property and feels like he is losing part of his water right as a result since the sprinklers will use less water. DNRC indicated that they are still several months out from completing the agency and public review/comment process on his change application. Reba Ahlgren, NRCS Soil Conservation Technician and Ken Mosdahl, NRCS engineer from the Roundup Field Office, gave an overview of the restoration efforts and accompanied us to a few of the individual irrigators’ operations.

Figure 5. Naderman Diversion Dam, July 2012.

6

Page 7: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Harper Ranch: (310 No. 11-024 – Stabilize Bank) a member of the Naderman Ditch, has installed a pump and now irrigates in part with a 43-acre center pivot. The new pump unit is an electric powered, trailer mounted unit anchored on a concrete pad on the upper terrace. Flexible lines connect to intake and discharge ports. The small remainder of the field is now dryland hay. Wilbur Harper showed us the pump station and pipeline and demonstrated the GPS-equipped pivot controller. The cost of the change was about $120K total with USDA-NRCS’s EQIP covering approximately 50% of the total excusive of running the power in. Power costs have been about $20 per acre per irrigation this year. They previously had diesel fuel costs of $350 per day to run their Crisafulli pumps (entire operation).Water use per irrigation was 24 ac-ft this summer compared to about 60 to 70 acre-feet under flood irrigation. They are pleased with the flexibility, labor savings, and independence that they now have although they also had some concerns with the time required for the water right change process and the financial expense of making the change. They have also seen some increase in productivity in the single season of operation. They are also pleased with the service they received from all those they worked with to get their irrigated hay production back after the flood.

Figure 6. Harper Pump Site, 2012.

7

Page 8: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Eliasson Ranch: No RATT visit in 2011 (310 No. 12-003 Replace Dike and Pump Site)

Gary Eliasson showed the Team his new pump station which utilizes rectangular precast concrete sections and a concrete pad to situate two pumps; one propane operated and one diesel powered. The propane motor runs a high volume pump that provides water for Gary’s flood and sprinkler system north of the highway. About 100 acres are flood irrigated. Another smaller pump down the system provides water for the sprinkler operation. The diesel fueled pump runs a wheel line sprinkler in the leased field adjacent to the pump. Total cost was about $153K. Cost-share helped to offset some of the cost for the pipeline and pumps (less so for the pumps). Irrigation operation costs have run about $10 per acre per irrigation this summer for the two irrigations made after completion. Savings through consolidation of the pump sites into one, along with the aforementioned independence from the ditch were noted as benefits of the change, although Gary was concerned about the total expense involved in making the conversion to sprinklers.

Figure 7. Eliasson Pump Site, 2013.

8

Page 9: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Tuesday, September 24, 2013

Willow/Soil Lift Demo Site at the County Fairgrounds: No RATT visit in 2011.

The Team visited this bioengineering demonstration site accompanied by Donna Pedrazzi, David Stout of the LMCD and Krist Walstad, Reba Ahlgren, and Jennifer Paddock with NRCS. The project was installed this spring through a DEQ Grant by David Stout to demonstrate the use of soil lifts in conjunction with willows and other plant materials to stabilize an eroding bank at the County Fairgrounds . Rock riprap had been used previously on the site with some rock still present up and downstream. The project location is on the RB on an outside bend in a deeply entrenched reach of river. A city well is located behind and above the project area. Length of slope treated is about 110 feet according to David. The toe was installed using pine fascines. Several 6 to 8 inch soil lifts using coconut jute mesh were layered above the pine fascine at the toe. Willow mattresses were incorporated in the lifts as the bank was sloped back. The approach seems to have merit where tolerance for the risk of failure is high and stream forces are low. Total cost was about $5,000. Some scouring has occurred at the toe. Growth of the willows along with plantings of other shrubs is progressing. The CD will continue to monitor vegetative growth and performance of the bioengineering project. Soils lifts and vegetative plantings may be a viable alternative, where appropriate, as a BMP in stabilizing excessively eroding banks on the Musselshell River.

Figure 8. Willow bank site, 2013.

9

Page 10: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Pedrazzi Ranch/Newton Diversion Dam: RATT Ref. #2/310 Permit No. 11-026. Compromised diversion dam and irrigation delivery canal. Original site visit on September 21, 2011. RATT priority rating 3.

Donna and Jim Pedrazzi accompanied the Team to the dam site located on their ranch. No work has been done on the dam since the irrigation water canal (Brown Ditch) the dam served was rendered inoperable due to breaching and sedimentation. Two of the three water users have now converted to direct pumping downstream. It is unknown what the absentee third owner will do since they have formally abandoned the ditch and dam. Erosion continues to occur on the upstream RB where several trees have hung up. This feature may cause issues over time as the river continues to try to flank the dam. Until the fate of the dam is decided, no action will likely be taken to address the erosion. FWP and other organizations may be interested in providing fish passage at this dam. Since the dam does serve as a control on channel grade, there may be a need to preserve the grade control function over time. A cost/benefit analysis will likely need to be made to evaluate alternatives to complete removal.

An irrigation pump (310 Permit No. 11-044) located upstream that was damaged by the flood has been rebuilt at the same location using rectangular, precast concrete sections at a cost of about $14K. No financial assistance was available for the replacement. The pump was redesigned to allow for less water depth in case the diversion dam below isn’t available or adequate to provide backwater to the pump. The system which serves 110 flood irrigated acres worked well the first year but wasn’t as effective this year in pumping an adequate rate of water. It was recommended to check out the pump and impellers to see if that may be the source of the problem or to redesign the pump lift rather than bear the expense and risk of creating an upper diversion (rock or otherwise) in the channel to provide backwater. However, a properly designed and implemented rock check may be the only viable alternative in providing the necessary water head to the pump, if the pump retrofit isn’t successful and/or the downstream diversion dam is removed.

10

Figure 9. Newton Dam, 2013.

Figure 10. Irrigation Pump Site, 2013 image.

Page 11: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

We viewed the new pump station (310 Permit No. 12-005) located below the Dam to serve the irrigated land that was formerly served by the Newton Dam and Brown Ditch. It was placed at the head of a bendway with good water depth and low velocity. Banks seem to be well vegetated and provide some protection to rapid channel movement although siltation could be a maintenance issue at this location. Precast concrete sections were used with minimal rock placed at the toe of the structure. Cost of the retrofitted pump and pipeline to serve the 30-acre flood irrigated field was about $16K of which NRCS cost-share contributed about $6K. Irrigation use is for about one week, two or three times a year. Flow rate is about 3K gallons per minute. The Pedrazzi’s are satisfied with the system now that it is in place because of the lack of ditch maintenance and freedom to draw water when needed. Use next year will give them a better idea of any adjustments needed to the new system. The abbreviated change in POD filing was not difficult and proceeded well in their experience as they didn’t change the method of application or place of use. They also allowed the Roundup Cemetery to co-locate a pump in the same structure which is beneficial in helping share the expense as well as reduce multiple maintenance and function issues associated with multiple pumping stations. The cemetery pump serves about 100 sprinkler heads.

We also viewed a previously unvisited site where the Pedrazzi’s had proposed to install a soil lift project to protect a field that had formerly been irrigated using a portable Crisafulli pump. Bank migration during the 2011 flood took out the ramp used to place the pump. We discussed various options for this small field, one of which was water leasing and another to transfer the water rights to their downstream fields. Scott will provide Donna with the appropriate statutes.

We also discussed inherent limitations and alternatives to using a purely bioengineered approach since costs will be high at this actively eroding site due to the bank’s height and high erosive forces at work on the outside bend. A third, least costly option is to just let the bank erode until any major adjustments in channel curvature and sediment transport have occurred over time.

11

Figure 11. Pedrazzi Pump Site downstream of Newton Dam, 2013.

Page 12: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Kilby Butte Colony: RATT Ref. # 3; 310 Permit No. 11-010-1 and 2; 11-035-10; and 11-036-3: Repair Diversion Dam, Repair Historical River Crossing, Harvest Gravel Bar, Divert River to Original Channel and Stabilize Bank. Original visit on September 21, 2011. RATT priority rating 5.

Met with Joe Stahl to visit various restoration sites. The concrete diversion dam (not visited in 2011) has had some minor repairs to rock riprap protection on the downstream abutments. Joe is concerned that future erosion to undermine the upstream, high vertical LB will result in a need for more bank protection to hold the dam. Team members pointed out that the only economic approach at this time to treatment would be to pull back the top of the high bank to reduce the weight and help to prolong any movement. The dam’s check boards are pulled in the fall so the structure doesn’t create a year-long barrier to fish passage.

We viewed the vehicle crossing project. Rather than install a crossing on a low height dike fill across the failed avulsion channel as planned, Joe used the upper clay shelf which has resisted downcutting to this point. He graded approaches on each end and so far the crossing has worked well. The benefit is low cost and less impact to the floodplain. Elevation of the crossing should allow high flows to pass and take pressure off the main channel. Edges of the avulsion will be shaped and seeded. The Team recommended that the downstream slope of the crossing be armored with rock to help reduce headcutting in the event of high flows. We also looked at the cut excavated to direct the flow back into the old channel. Sides of this cut could have been sloped back for more stability, but will likely erode and lay back with succeeding high flows.

We also visited a pumping site restoration project on the Colony which was not viewed in 2011. The pump station was rebuilt and the bank shaped. A limited amount of rock was mixed in with the soil fill material. They are to plant grass and trees at the site as part of the 310 permit. Approximately 300 feet of bank was treated at an estimated cost of $2 to 3K. The fill material appears to be pretty soft and the toe vulnerable, however the site is on a straight reach and so may have a chance to stabilize before it is tested.

12

Figure 12. Kilby Butte avulsion, July 2013.

Page 13: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

T7 Bar Ranch: RATT Ref. #4; 310 Permit No. 11-016. Original visit on September 21, 2011. RATT priority rating 7.

Met Curt Goffena at the ranch where we visited the failed avulsion which had cut off access and irrigation to a 10 acre field in 2011. Curt placed a large fill at the mouth of the 4-acre avulsion and has sloped the sides of the avulsion. The fill was pulled from the point bar across the channel to the south. The fill provides access to the remaining 6-acre crop field although it is still without irrigation. Rock was placed on the upstream face of the fill as well as on the LB above the fill. A cofferdam using the bed gravel was placed in the river to help dewater the construction site. Curt also placed a fill at the lower end of the avulsion. He said that the lower fill is retaining more water in the avulsion channel than he expected and he regrets doing so at this time. He spent about three weeks in construction of the fill and related rock work at an estimated cost of about $10K. Cottonwoods and willows not removed thru construction are still growing in the failed avulsion. Lessons experienced by Curt will be incorporated into an avulsion-related BMP.

Figure 13. T7Bar avulsion, 2013.

13

Page 14: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Kite Cattle: RATT Ref. #35; 310 Permit No. 11-037. Bank Erosion/Damaged Pump Site. Original site visit on October 19, 2011. RATT priority 1.

Ranch owner Henry Bedford and Rowdy took us to look at several locations with bank erosion and pump site issues. At the first site, they have reset a pump in the original, pre-flood location on an eroded outside bend using rectangular precast concrete sections with rock on the up and downstream faces. The alternative recommended by the RATT was to move the pump site upstream to a deep pool along a bedrock bluff. This alternative was not utilized as the power company dictated the location of power. Near the pump site, the flood affected 65-acre field was planted to “Yellowstone” winter wheat and hayed in preparation for re-leveling and planting alfalfa once irrigation was restored. A ~6-7 acre area damaged by overland flow and a potential avulsion is being left to grow cottonwoods and willows at this time. We also looked at another field in which the pump location was damaged. The estimated expense of moving the power poles, now located in the field to facilitate a better pump location and use of a sprinkler irrigation system on the field, is $47K which Kite Cattle is unwilling to pay. Henry was very vocal regarding the reimbursements provided through the Emergency Conservation Program. He did receive assistance through the NRCS’s EQIP.

Figure 14. Kite Cattle pump site, 2013 image.

14

Page 15: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Wednesday, September 25, 2013

Delphia-Melstone North Canal Siphon: RATT Ref. # 34; 310 Permit No. 11-041-1. Repair Damage to Siphon. Original site visit on October 11, 2011. RATT priority rating 5.

Lynn Rettig and Bill Bergin accompanied the Team to the North siphon location. The Delphia-Melstone Canal Users’ Association repaired the siphon at a cost of about $100,000. 2011 RATT recommendations, at least in part, were used in completing the repair work. Funding was obtained through a USDA Rural Development loan. Expenses were primarily to purchase and haul rock to cover the exposed and broken siphon pipe. About 10 to 12 feet of material had to be filled as well as the abutment aprons on each end. “Dirty” rock riprap was used as per the request of the DEQ and USACE. Apparently, the siphon was exposed and repaired in 1994 with assistance of the Federal Emergency Management Agency. Rock was also placed up and downstream on grade over the fill to create a protective barrier in the channel. An evaluation will be made annually to assess maintenance needs. The work demonstrates effective protection without encroachment on the active channel or floodplain. Fish should be able to easily navigate the rock fill placed over the pipe. Lynn said that one lesson learned was that it helps to have an emergency plan in place for infrastructure works such as the siphon as the emergency is a poor time for planning. Lynn experience good working relationships with all agencies and individuals involved. They were eligible for Emergency Watershed Protection Program funding but the construction expenses would have been much higher so they fixed the siphon on their own. They were not eligible for FEMA funding as the program no longer recognizes irrigation as a public benefit.

The Association may also plant woody vegetation on the banks as time permits. There is a stranded cottonwood tree near the RB above the siphon. It was suggested that it may be wise to move the tree away from the bank and out of the active channel to the exposed bar on the LB.

We also viewed the Bergin/North Canal Dam and the Davis Dam where we discussed flood repair work that was completed. Bill Bergin has decided that a floodplain dike above the Bergin Dam that was damaged will not be replaced. Both projects appear to be working and in good repair at this time. FWP is working with the irrigators to investigate fish passage at the Davis Dam.

15

Figure 15. Delphia-Melstone North Canal Siphon, 2013 image.

Page 16: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Harvey Road Bridge: RATT Ref. # 7; Avulsion/Road Washed Out. Original site visit on September 21, 2011. RATT priority rating 9.

Harvey Road was repaired with FEMA assistance to build a new bridge and approach over the avulsion channel. The concrete bridge span appears to constrict the active channel somewhat however several large culverts were installed in the new approach fill to provide floodplain relief during high flows. Depending on bedload deposition in the future, floodwater access to the overflow culverts is questionable. Some maintenance excavation and channel shaping may be needed for proper function of the culverts. Significant amounts of salt cedar plants are growing in the avulsion channel that again speak to the need for noxious weed control associated with flood restoration projects.

Figure 16. Harvey Road Bridge crossing, 2013.

16

Page 17: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Ty Checketts: RATT Ref. # 38; 310 Permit No. 11-039-2. Washed Out Crossing. Original site visit on November 1, 2011. RATT priority rating 5.

Checketts replaced a crossing several hundred yards above the original crossing using the recommended location at a existing riffle. Local, native gravel was used to build and shape the approaches to the shallow, right angle crossing. The tributary just above the crossing may help to contribute gravels to the crossing. This appears to be a good installation on a straight section that does not negatively affect stream or biologic functions (fish passage, sediment transport, and floodplain access) and will not require extreme maintenance actions. Again, weed control activities are sorely needed in most of the flood disturbed sites and especially following restoration activity. No information on the cost of construction was available.

Figure 17. Checketts river crossing site, 2013 image.

17

FL

Page 18: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Ty Checketts: RATT Ref. #37; 310 Permit No. 11-39-1. Bank Erosion, Threatened Buildings and Access Road. Original visit on November 1, 2011. RATT priority rating 4.

Active bank erosion threatening a farm shed and access road has been eliminated by breaching a very thin meander neck as recommended by the Team in 2011. The action completed a process which would have likely progressed in the next few years in any case. Approximately a 30’ by 50’ opening was excavated to allow the channel to bypass the actively widening meander adjacent to the building. The opening will be further widened as appropriate by flows in succeeding years. Emergent vegetation is beginning to fill the abandoned meander already. Succeeding high flows will bring additional sediment to further create an emergent wetland. No effort was made to close off the abandoned meander thus maintaining extra channel capacity during high water events and providing shallow wetland habitat. While this solution is rarely suggested, it appears that in this case, it solved the problem with minimal impacts to channel and riparian function at a relatively low cost compared to a bank stabilization alternative. No information about construction costs was available.

Figure 18. Checketts avulsion/erosion site, 2013image. Neck Breach Site

18

Page 19: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

September 30, 2013

Cat Creek Cattle: RATT Ref. # 12. Bank Erosion and Threat to HQ area on Upper Terrace. Original site visit on October 4, 2011. RATT priority rating 10.

B.G. FitzGerald (NRCS Soil Conservation Technician, Jordan F.O.) accompanied the Team to the CAT Creek HQ area. Cat Creek has not attempted any treatment of this site since the 2011 flood event. The lower river (below Flat Creek) experienced bankfull high water again this summer for a three week period, primarily coming from flows out of the Flat Willow Creek watershed. The USGS gaging station on Flatwillow Creek recorded 4,770 cubic feet per second discharge on June 4, 2012 prior to failing. It appears that portions of the high scarp on the LB upstream of the HQ area have experienced significant bank retreat and channel widening on the upper limb of the meander bend. Large, active slumps were noted. At this time, however, the erosion doesn’t appear to be threatening the buildings or corrals. Due to the expense and practicality to treat this site adequately, it is still not recommended to take any action.

Cat Creek Cattle: RATT Ref. # 13 and 14. Floodplain Scour and Dike Erosion. Original site visit on October 4, 2011. RATT priority rating 5.

Several fields were visited where floodplain scour and erosion has been treated. Sides of the scour holes have been sloped and filled to bring elevations to near field level. Repairs allowed irrigation and cropping to again be feasible on the fields. It also appears that the fields are being cropped to hay barley or other annual grain crops prior to replanting to alfalfa/grass hay. Infestations of bindweed are particularly heavy in the flood affected fields. Several years of chemical treatment may be needed to control this plant. Heavier sediment deposits were pushed off the end of fields prior to cultivation and shaping to re-level the border dikes.

A damaged pump station was restored and relocated using a portable, electric-powered pump tied into the newly reorganized flood irrigation system. Placement of the new pump station on an outside bend may experience problems in the future. A position located downstream of the bend may have been more sustainable. Most ditches on these fields have been eliminated with use of low pressure PVC underground delivery pipe and aboveground gated pipe. The power company provided new poles at no cost.

19

Figure 19. Cat Creek Cattle site, 2013 image.

Page 20: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

The floodplain dike that was overtopped in the 2011 flood has been rebuilt to the original dimensions. It is still recommended to provide some reduction in the dike elevation so as to allow more regular floodplain function at a lower elevation. This would possibly reduce scour and erosion in the future.

Tim and Travis Browning: RATT Ref. 19, 20, and 21. Abandoned/Damaged Pump Sites, Avulsion, Floodplain Scour and Sediment Deposition on Field. Original site visit on October 5, 2011. RATT priority rating 2 and 5, respectively.

The Brownings have replaced several pumps on the river that were damaged during the 2011 flooding. They continue to see significant changes to the channel and banks since flooding altered the length and grade so drastically in the lower river. Like most irrigators in this area, they now use portable pumps that are removed following the irrigation season. High water this spring again took out several of the new pumping stations that they had established, so they have learned to adapt to changes in the river. The use of diesel allows them to be somewhat flexible in their selection of pumping sites although access for fuel is a consideration. They purchased two identical, trailer mounted units each with a 4,500 gpm capacity. The purchase price was $18,000 each. They did get some technical and financial assistance from NRCS and the ECP in renovating their ranches after the flood. While thankful for the assistance, Travis Browning noted that the funding did not come quickly in some cases and the reimbursement rates for some practices such as re-leveling, were too low to be of much real help.

They have begun to restore the sediment affected fields beginning with those least affected. Those with less sediment have been simply worked by disking and cultivating prior to planting hay barley, sudan/sorghum hybrid, or millet for a year or two. Those with more sediment are graded or leveled with a laser level guided scraper according to a leveling plan. Several headcuts in the fields were filled in. Once they field has been re-leveled and has had a few annual crops grown, they plant back to alfalfa hay. Infestations of bindweed seem worse in some fields and this may be due the lack of active management for a year or two following the flooding. They noted that after several years of crop, the soil seems fine, growing good hay crops under irrigation. The flood cost them about 300 tons of hay per year in lost production each of the past three years. They are still having to buy hay as it will be a few more years before they will be back in full production.

20

Figure 20. Browning pump site, 2013 image.

Page 21: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

Figure 21. Rowton Brothers site, 2013 image.

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

October 1, 2013

Rowton Brothers: RATT Ref. # 11. Bank Erosion and Damaged Irrigation System. Original site visit on October 4, 2011. RATT priority rating 2.

Lloyd Rowton showed the Team his flood-related restoration projects. They have replaced buried mainline that was washed out by the 2011 flood. They also installed a portable electric motor and pump serving the mainline. The new pumping location was moved downstream as suggested by the Team in 2011. The pump is trailer mounted with a flexible intake and output hose. Irrigation on this field is made with gated pipe. To date, they have not yet located a good, solid crossing to access their fields across the river. According to Lloyd, it will take some time for the channel bottom to set up solid enough to allow equipment to cross.

A washed out domestic/stock water line from a well across the river was rebuilt. The new line was installed under the river bed using a two-inch flexible boring machine similar to that used for installing fiber optic cables along and under roads. The pipe was run 50 feet past the channel on each side. Installation cost was about $12 per foot. This cost (quite a bit below other bids) seems very reasonable compared to trenching expense along with the benefit of avoidance of the detrimental aspects of conventional trenching.

They are also participating in the three-year cottonwood conservation program. Riparian fencing and the water line described above was cost-shared under this program. Lloyd indicated that the program may have not been required since he is seeing a lot of trees with or without grazing, however, he is glad to have gotten the assistance and funding through the program to complete the fence and water line as well as the avoidance of grazing use payment. His neighbor across the river enrolled in the program and without adequate property fences in place, he felt that he might as well enroll since he couldn’t control livestock otherwise. Most of the weeds in the riparian conservation area are annual weeds such as kochia and cocklebur which will diminish in abundance as perennial plants cover the freshly deposited soil. They have spot sprayed saltcedar in this area which may have inadvertently also killed the tops of young cottonwood in their vicinity. With luck, some of the saplings may resprout next spring.

21

Page 22: RATT II Summary - Web viewSummary Report – Field Visits. RATT II team members Tom Pick, Karin Boyd, and Warren Kellogg revisited a selection of sites along the length of the Musselshell

LMCD 2013-01 Development of Post-2011 Flood Best Management Practices (BMPs)

Jay Woodford: RATT Ref. # 9. Multiple Avulsions, Loss of Access, and Pump Sites Abandoned. Original visit on October 4, 2011. RATT priority rating 5.

Mr. Woodford was not available so we observed several of his flood-related activities from a distance. He has not yet replaced an abandoned irrigation pump serving a large field which was rendered an island by the multiple avulsions in this reach. He appears to have hayed the field this summer using a new ford crossing site which was recommended during the earlier RATT visit. It doesn’t appear that much work was required to establish the crossing as there are some shale bedrock shelves present at the location. The channel below the mouth of Flat Willow Creek experienced significant change due to this year’s flush of high water coming out of Flat Willow Creek. The channel widened significantly as banks failed. Due to bank erosion and a shift in channel orientation the bridge crossing Flat Willow Creek may require some maintenance in the near future to protect the integrity of the structure.

Figure 22. Woodford crossing site below Flatwillow Cr confluence, 2013.

22