Raven Installation Plan Part 2 Transportation and Safety Célia Blain and the Raven team Nov 26th, 2013 - Raven Readiness Review 1

Upload: vuongtuyen

Post on 06-Mar-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Raven Installation Plan Part 2 Transportation and Safety

Célia Blain and the Raven team

Nov 26th, 2013 - Raven Readiness Review 1

Page 2: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Summary

• Shipping plan overview

• Personal Protective Equipment

• Unloading Raven in Hilo

• Loading Raven to the BSIT truck

• Transportation to the NIR platform

• Lifting point

• List of hazards

• Work area

• Storage plan

Nov 26th, 2013 - Raven Readiness Review 2

Page 3: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Shipping Plan Overview

Nov 26th, 2013 - Raven Readiness Review 3

• Raven will be shipped by sea in a 20-foot container.

The bench structure will be reinforced.

• Bench crate and computer crate will be set on top of a vibration damping base.

• All content will be sealed, blocked and strapped.

Should be able to handle: - 25 cm drop - 30° pitch and roll

Page 4: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Shipping Plan Overview

Nov 26th, 2013 - Raven Readiness Review 4

• Container will be picked up at UVic on Dec 16th ( 3 days loading )

• Transporter: Carson (Matson) port of departure: Seattle. • Window delivery at Subaru:

January 6th-10th

Container will be in standby at Subaru for 4 days.

Page 5: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Shipping Plan Overview

Nov 26th, 2013 - Raven Readiness Review 5

Page 6: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Shipping Plan Overview

Nov 26th, 2013 - Raven Readiness Review 6

Page 7: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Shipping Plan Overview

Nov 26th, 2013 - Raven Readiness Review 7

Kaiju

Jaeger

Raven

Page 8: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Personal Protective Equipment

• Raven team members and Subaru staff involved in the loading/unloading of Raven must be wearing appropriate PPE:

hard helmet

steel-toed shoes

gloves

Nov 26th, 2013 - Raven Readiness Review 8

Page 9: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Unloading Raven in Hilo

• Container left on a 4-feet high trailer in Hilo for 4 days

• Container content will be all on pallets

• Pallets will be moved within the container using a palette jack then unloaded from the container using a forklift.

• Once the crates are removed, the clean room must be lifted up using the crane and Raven will be rolled in position.

• The computer rack will be rolled in the clean room.

• Other small equipment will be handled manually.

Nov 26th, 2013 - Raven Readiness Review 9

Page 10: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Loading Raven on the BSIT truck

• Clean room lifted using crate – Raven rolled out.

• A custom frame has been designed to attach Raven to the BUSF.

• Raven will be craned to the BSIT truck and BSIT cover craned on top and secured.

• Computer rack must be repacked into its original transportation crate - transportation to summit using a regular truck.

• Other Raven’s equipment to be transported using Subaru’s SUVs.

Nov 26th, 2013 - Raven Readiness Review 10

Page 11: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Loading Raven on the BSIT truck

Nov 26th, 2013 - Raven Readiness Review 11

Page 12: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Transportation to NIR platform

• Raven will be unloaded from BSIT truck using 80T crane.

• Two options are available to bring it to Cassegrain floor:

the bench is equipped with caster and can be rolled to the elevator

the bench can be lifted up using the 80T crane

• The computer rack will be brought to the Cassegrain floor using the elevator.

• Once at the Cassegrain floor, both the bench and computer rack will be lifted up to the NIR platform using the crane.

Nov 26th, 2013 - Raven Readiness Review 12

Page 13: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Lifting points

• The Raven bench is equipped with 4 lifting points.

Nov 26th, 2013 - Raven Readiness Review 13

• Lifting point = Lifting eye + Bracket + High-strength bolt

• Raven lifting slings will be provided by the Raven team

• Spreader will be provided by Subaru All lifting equipment are well below their respective WLL

Page 14: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Lifting points

Nov 26th, 2013 - Raven Readiness Review 14

List of purchased hardware:

Page 15: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

List of hazards

Nov 26th, 2013 - Raven Readiness Review 15

• High voltage cables have been listed and labeled • Camera cooling system = water – propylene-glycol mix MSDS was provided • No powered industrial truck • Raven does not used compressed gas

Page 16: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Work area (Hilo)

Nov 26th, 2013 - Raven Readiness Review 16

Page 17: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Storage plan

Nov 26th, 2013 - Raven Readiness Review 17

Raven bench crate: 2.0 m L x 1.75 m W x 2.0 m H Computer crate:

1.75 m L x 1.4 m W x 1.5 m H

Page 18: Raven Safety Plan - University of Victoriaweb.uvic.ca/~ravenmoa/Docs/AccRev_Celia_pres.pdf · • Container content will be all on pallets ... • Raven will be craned to the BSIT

Thank you…

Nov 26th, 2013 - Raven Readiness Review 18