ravichandran a/l manoharan a project report submitted in...

30
SUBCONTRACTOR SELECTION METHOD USING ANALYTIC HIERARCHY PROCESS RAVICHANDRAN A/L MANOHARAN A project report submitted in partial fulfillment of the requirements for the award of the degree of Master of Sciences (Construction Management) Faculty of Civil Engineering Universiti Teknologi Malaysia APRIL 2005

Upload: others

Post on 25-Feb-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

SUBCONTRACTOR SELECTION METHOD USING ANALYTIC HIERARCHY PROCESS

RAVICHANDRAN A/L MANOHARAN

A project report submitted in partial fulfillment of the requirements for the award of

the degree of Master of Sciences (Construction Management)

Faculty of Civil Engineering

Universiti Teknologi Malaysia

APRIL 2005

Page 2: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

Especially dedicated

to my beloved family

Page 3: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

ACKNOWLEDGEMENT

Without the support and help of many people, this research would not have

been possible. First of all, the author wish to extent the greatest thanks to the project

supervisor, Dr Arham Bin Abdullah for his help, support, advise and corporation in

conducting the research, especially during the structuring the research model.

I also wish to acknowledge all the contractors and experts who have extended

their valuable times and resources in providing necessary information for the

research.

Acknowledgement is also due to anonymous panels for their valuable comments

during the presentation of the research.

I also owe a debt of gratitude to my family members and friends for their support

and encouragements throughout my master programme.

The author is extremely grateful to all who have contributed, either directly or

indirectly to the research.

Finally, but most important, express my thanks to Construction Technology

Management Centre (CMTC) and all lecturers in providing the knowledge and make

this master programme to reality.

Page 4: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

ABSTRACT

Sub-contractor selection is one of the most important aspects in construction

contract. The success level of construction is very depends on the quality of

subcontractor selection process. Majority of selection process are over emphasized

on the bid cost rather than trade-off between other parameter such as quality, safety

and environmental commitments. Instead these have contributes in project delays,

cost overruns, non-confirmation on quality, lost time accident, increase number of

claims, litigation and contractual issues and failure to comply with local authority

and construction specification. Concerning to this problems, the subcontractor pre-

qualification, evaluation and selection process needs to be reviewed to achieve the

project goals based on multi criteria decision making process. The main initial thrust

of this study was to identify the criteria used for selection process, which was

adopted by the various type of contractor working in Putrajaya. This exercise

involved “knowledge acquisition” phase to capture the expert knowledge including

collecting documents of current procurements practice, knowledge from the literature

review and interviews with experts from various construction companies. The data

collected are used to create a theoretical model for subcontractor selection that

represented by the Analytic Hierarchy Process. It is concludes that the choice of

subcontractor should be consider based on multi criteria decision rather than

automatically accepting the lowest bid. The finding from the research indicated that

the common criteria considered by the contractor during the selection are the cost,

past performance, financial soundness, technical expertise, management capability,

subcontractor workload, previous work experience, and track record. The study

recommended that procurers should no longer depends totally on their experience to

decide on their selection process but an effective decision support system (DSS) like

Analytic Hierarchy Process (AHP) is important to systematically evaluate the

selection process. The research also serves as sources of information for sub-

contractor to win the contract and act as platform for contractor to make an

appropriate decision on the choice of subcontractor.

Page 5: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

ABSTRAK

Pemilihan sub-kontractor adalah perkara paling penting dalam sektor

pembinaan. Tahap kejayaan sesuatu projek banyak bergantung kepada kualiti

pemilihan sub-kontraktor. Kebanyakkan kaedah pemilihan sub-kontraktor terlalu

memihak kepada faktor harga tanpa memikirkan faktor-faktor lain seperti kualiti,

keselamatan dan peranan alam persekitaran. Akibatnya banyak projek pembinaan

mengalami kelewatan, kerugian, tidak dapat memenuhi kualiti piawaian, peningkatan

kemalangan di tapak bina, peningkatan isu berkaitan dengan kontrak dan

pembayaran serta kegagalan memenuhi kehendak pihak berkuasa dan specifikasi

projek. Kajian ini adalah bertujuan untuk mengenal pasti kriteria dalam proses

pemilihan sub-kontraktor yang diamalkan oleh kontraktor-kontraktor di Putrajaya.

Untuk mencapai matlamat ini kepakaran pihak-pihak kontraktor dalam pemilihan

sub-kontraktor diambil kira melalui pengumpulan data, pengalaman mereka dan

menemubual kontraktor secara langsung. Analisis data kemudian digunakan untuk

membuat satu model theoretical yang digambarkan oleh “Analytic Hierarchy

Process”. Kesimpulannya, pemilihan sub-kontraktor mestilah berasaskan kepada

kepelbagaian kriteria dan bukan memilih secara langsung berdasarkan paras harga

yang terendah. Hasil kajian menunjukkan pemilihan sub-kontraktor dipengaruhi

faktor seperti harga, pencapaian masa lepas, keupayaan kewangan, kepakaran

teknikal, kemampuan pengurusan, pengalaman kerja lepas, beban kerja

subkontraktor dan rekod kerja. Kajian ini juga mencadangkan bahawa kontraktor

tidak seharusnya menggunakan hanya pengalaman mereka dalam pemilihan sub-

kontraktor tetapi mereka juga haruslah menggunakan sistem penyokong keputusan

seperti “Analythic Hierarchy Process” dalam membuat keputusan pemilihan. Kajian

ini juga dapat membantu sub-kontraktor untuk memenangi kontrak dan sebagai

landasan kepada kontraktor dalam pemilihan sub-kontraktor.

Page 6: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

vii

TABLE OF CONTENTS

CHAPTER TITLE PAGE

TITLE PAGE

DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENT iv

ABSTRACT v

ABSTRAK vi

TABLE OF CONTENTS vii

LIST OF TABLES xi

LIST OF FIGURES xii

LIST OF SYMBOL xiv

LIST OF APPENDICES xv

1 INTRODUCTION OF STUDY

1.1 Introduction 1

1.2 Problem statement 3

1.3 Background of the research 3

1.4 Justification of the research 4

1.5 Aim of the research 4

1.6 Objectives of the research 5

1.7 Scope and limitation of the research 5

1.8 Brief research methodology 6

1.9 Structure of dissertation 8

Page 7: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

xii

CHAPTER TITLE PAGE

2 LITERATURE REVIEW 10

2.1 Introduction 10

2.2 Construction project phases 11

2.2.1 Definition 11

2.2.2 Project life cycle 12

2.2.2.1 Conceptual and feasibility studies 14

2.2.2.2 Engineering and design stages 14

2.2.2.3 Procurement stage 16

2.2.2.4 Construction stage 16

2.2.2.5 Start up and Implementation 17

2.2.2.6 Operation and utilization 17

2.3 Tender and estimation process 18

2.3.1 Pre-qualification 18

2.3.2 The decision to tender 19

2.3.3 The estimating process 19

2.3.4 The tendering process 25

2.4 Bid evaluation 26

2.4.1 Criteria for bid evaluation 27

2.5 Sub-contractor selection model 35

2.5.1 Multicriteria decision making (MCDM) 38

2.5.1.1 Bespoke approaches (BA) 38

2.5.1.2 Multi attribute analysis (MAA) 41

2.5.1.3 Multi attribute utility theory (MAUT) 43

2.5.1.4 Multiple regression (MR) 47

2.5.1.5 Cluster analysis (CA) 48

2.5.1.6 Fuzzy set theory (FST) 50

2.6 Conclusion 50

Page 8: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

xiii

CHAPTER TITLE PAGE

3 RESEARCH METHODOLOGY 52

3.1 Introduction 52

3.2 The methodology adopted for the research 52

3.2.1 Literature review 53

3.2.2 Knowledge acquisition 54

3.2.2.1 Questionnaires survey 54

3.2.2.2 Interviews 56

3.2.3 Analytic hierarchy process (AHP) 58

3.2.3.1 Background of AHP 58

3.2.3.2 AHP principles 60

3.2.3.2.1 Decomposition 61

3.2.3.2.2 Prioritization procedure 63

3.2.3.2.3 Synthesis of results 65

3.2.3.2.4 Measuring Inconsistency 66

3.2.4 Decision support system 68

3.3 Summary 70

4 KNOWLEDGE ACQUISITION FOR MODEL DEVELOPMENT

4.1 Introduction 71

4.2 Knowledge acquisition 72

4.2.1 Survey sample 72

4.2.2 Questionnaire survey 74

4.2.2.1 Questionnaire design 74

4.2.3 Interview survey 76

4.3 Data Analysis 77

Page 9: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

xiv

CHAPTER TITLE PAGE

4.3.1 Analysis on questionnaire survey 78

4.3.1.1 Discussion and findings 88

4.3.2 Analysis on interview survey 89

4.3.2.1 Discussion on findings 93

4.4 Summary 97

5 DEVELOPMENT OF THEORETICAL MODEL 98

5.1 Introduction 98

5.2 Modeling 98

5.2.1 Expert Choice Software 99

5.3 Development of the AHP model 100

5.3.1 Developing the AHP hierarchy 100

5.3.2 The pairwise comparison 102

5.3.3 Synthesis of the AHP model 104

5.3.4 Sensitivity analysis 106

5.4 Operation of the theoretical model 106

5.4.1 User requirements 108

5.4.2 System requirements 108

5.4.3 Starting the system 109

5.4.4 Data input 110

5.4.5 Assigned judgment in pairwise comparison 110

5.4.6 Synthesize to get results 112

5.5 Summary 117

Page 10: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

xv

CHAPTER TITLE PAGE

6 CONCLUSION AND RECOMMENDATION 118

6.1 Introduction 118

6.2 Findings 118

6.3 Summary 120

6.4 Recommendation for further research 121

6.5 Conclusion 122

REFERENCES 123

APPENDICES A-B 129 - 146

Page 11: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

xvi

LIST OF TABLES

TABLE NO TITLE PAGE

2.1 Criteria for sub-contractor selection 28

2.2 Pre-qualification recommended by CID agency 31

2.3 Important of Pre-qualification criteria 35

2.4 Hypotthethical MAA example 42

2.5 MCDM method for single criterion synthesis approach 45

2.6 Matrix of methodology characteristic 51

3.1 AHP pairwise comparison scale 64

3.2 Random index RI 69

4.1 Response from the questionnaire survey 78

4.2 Response preference of selection criteria 85

4.3 Relative Index Value for each criteria 86

4.4 Application of DSS in selection process 88

4.5 Justification of the identified criteria 90

4.6 Sub criteria for the assessment of main criteria 92

Page 12: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

xvii

LIST OF FIGURES

FIGURE NO. TITLE PAGE

1.1 Research objective and methods 7

2.1 Project activity flow chart 13

2.2 The estimating and tendering process 20

2.3 Pre-qualification criteria used by MTRC, Hong Kong 30

2.4 RRC frame for contractor pre-qualification 33

2.5 Decision analysis paradigm 37

2.6 MCDM method of classification 39

2.7 Typical stepwise procedure for bespoke approach 40

2.8 Possible stepwise procedure for MR pre-qualification model 48

2.9 Jointing tree CA output 49

3.1 Hierarchy of the project example 62

4.1 The respondents acceptable to participate in the research 73

4.2 The composition of respondents by profession 79

4.3 The range of respondent’s experience in the selection process 80

4.4 Respondent’s roles in the selection process 80

4.5 Respondent’s involvement in the type of construction work 81

4.6 Procurement system applied by contractor 82

4.7 Tender arrangement method in the selection process 83

4.8 List applied in subcontractor pre-qualification 83

4.9 The source used in the selection criteria 84

4.10 Method of evaluating the selection criteria 87

Page 13: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

18

LIST OF FIGURES

FIGURE NO. TITLE PAGE

5.1 The functional architecture of theoretical model 99

5.2 Criteria and sub-criteria identified 101

5.3 Strong rating (5) in pairwise comparison between financial

soundness and managerial capability (level 1 with respect

to the goal) 102

5.4 Pairwise comparison level 2 element in respect to level 1 103

5.5 Pairwise comparison level 3 element in respect to level 2 103

5.6 Distribute synthesis mode 105

5.7 Ideal synthesis mode 105

5.8 The operational flowchart 107

5.9 Subcontractor selection model 109

5.10 The information data input 110

5.11 The verbal comparison window 112

5.12 Model view showing the synthesized with the respect to the goal 112

5.13 Synthesis window 113

5.14 Dynamic sensitivity graph 114

5.15 Performance sensitivity graph 114

5.16 Gradient sensitivity graph 115

5.17 Head to head graph 116

5.18 Two-dimensional plots sensitivity graph 117

Page 14: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

19

LIST OF SYMBOLS

A Crj - Score for contractor j Vij - Variable (attribute) i score respect of j

Wi - Maximum score

Σ - Total

n - Number of independent variables

Ui - Represents the attribute consider by decision maker

f(uxi) - Calculation based on considered parameter

Y* - Represents the dependent variable

Co - Permanent constant

Ci - Partials regression coefficients

∞ - Infinite

CI - Consistency index

Imax - Eigenvalue max

IR - Inconsistency ratio

Page 15: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

20

LIST OF APPENDICES

APPENDIX TITLE PAGE

A Sample of questionnaire survey 129 - 141

B Interview survey template 142 - 146

Page 16: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

21

CHAPTER 1

INTRODUCTION OF STUDY

1.1 Introduction

The construction industry in Malaysia has experience a wide range of

expansion during the past 20 years. Today, most of the construction project

undertaken are more complex in nature, demanding greater skill and technologies,

fast track and concurrent works practices, very competitive in term of price,

demanding for end-product quality and good decision making skill, capabilities in

utilizing knowledge management and very critical in dealing with contractual issue

than ever before. There are increasing number of research/ professional are being

conducted/engaged to confronted with the problems and challenges faced by the

modern construction industry. Since, many of these issues are of relatively new

concern to the industry and directly related to the sub-contractor performances, the

selection and evaluation process of sub-contractor needs to be reviewed to cope with

these challenges. There are many methods of tendering system applied in the

construction contract. However the open tender system seems be the most popular

for the client for awarding the contract. Normally, the client awarded the works to

the contractor, then the contractor will engaged a few companies called “sub-

contractor” to carry-out the works according to the work assigned. Therefore the

selection of the sub-contractor is consider the important aspects and critical issue in

any construction contract.

Page 17: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

10

The success level of any construction project may depend on the basis

philosophy of “the right person for the right job”. But, in many cases, the selection

of sub-contractor are over emphasize on the lowest bid acceptance. In reality, sub-

contractor with the lowest tender price is usually awarded a contract. This trend may

be valid when the client are very clear of the “likely cost” of the project and being

experience with similar type of project and working environment. However, it may

not works in most of the project, because the selection of sub-contractor based on the

lowest tender price alone may result in a “false economy” to the project.

Various research methodologies were adopted in several countries to achieve

the “Value procurement” to the procures in the selection of sub-contractor. The

“value procurement” is one that considers price and other factors in the bid greatest

“value for money” to the client. Finding from experts reveal that the tradition “lowest

price wins” in practice is being replaced by “multi criteria judges”. This indicates

increase awareness of procures in selecting sub-contractor attributes via a more multi

criteria selection methodologies. Certainly it is not a easy concept to identify the

universal criteria for bid selection, as it depends on certain factors consider such as

client demands, contractual issue, project viabilities, authority requirement and

construction methods.

Although, that is growing realization on the “value procurement” to the

client, but the basic fundamental problems is “ what constitutes a sound sub-

contractor selection methodology” for the bid selection. According to the previous

research by many experts, there are few types of selection methodologies can be

applied by the procures in the bid selection. These methodologies including Bespoke

approaches (BA), Multi-attribute analysis (MAA), multi attribute utility theory

(MAUT), Multi regression (MR), Cluster analysis (CA), Fuzzy set theory (FST) and

Discriminate analysis (MBA).

Page 18: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

11

1.2 Problem Statement

The correct choice of sub-contractor is a great concern for procurers during

the selection process, as it has a significant impact on the success of the project.

Although considerable effort has been focused on pre-qualification, but the majority

of selection are over emphasize on cost priority rather trade in between cost, time and

quality. In most circumstances, the lowest price bid is automatically win the tender.

Finding also suggest that contractor are not aware of all the options, methodologies

and decision support system that is available for sub-contractor selection and

evaluation. The human judgment and experience is used to select the most

appropriate sub-contractor during the evaluation process.

1.3 Background of The Research

This study begin with the identification the various criteria used by the

procures during the selection process. It will allows to address the issues of “which

decision criteria is most considerable in the selection process”. The background of

the research focused on the collection of data through “knowledge acquisition”. The

knowledge acquisition activities included extensive literature reviews, interviews,

questionnaires and correspondence with the experts in the construction company.

The purpose of the knowledge acquisition is to capture the nature of selection

process, potential criteria and ranking method applied by the construction experts

during the selection bid. It is also to reveal if any decision support system is applied

in the selection process.

Having set out the criteria, the research then consider to develop a theoretical

model that represents the appropriate sub-contractor selection by using Analytic

Hierarchy Process Model (AHP).

Page 19: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

12

1.4 Justification of The Research

The growing importance of sub-contractor selection criteria renews the

interest of both practitional and academia working in the construction industry.

Furthermore the current selection process is critized and typically emphasized on the

lowest tender price which eventually would lead to the false economy of the project.

There is a serious outcry in the construction industry demanding a revolution in the

tender awarding system for sub-contractor as it has significant impact on the project

success. This research is carry-out to justify that the selection of sub-contractor

should not based on lowest price alone but should consider other parameter such as

cost, quality and time.

In additional, the current selection process is performed in an un-structure

initiative manner with considerable reliance on the experience of procurers and his

judgment. The procurers can no longer depends totally on their past experience to

decide the appropriate sub-contractor, because the nature of selection process which

involves multi criteria decision skill has become more complex. In response to the

need for a robust sub-contractor selection system, this research is justify to develop

a theoretical model based on Analytic Hierarchy Process for the selection of sub-

contractor. In order to provide a better platform for subcontractor selection process,

it is essential to capture the knowledge of experts and to develop a more formalized

and accuracy process with the support of decisions making tools.

1.5 Aim of The Research

The specific aim of this research are to identify the criteria used in sub-

contractor selection and to help the procures in making decision on selecting the

Page 20: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

13

most appropriate sub-contractor based on the combination multi criteria and

application of Analytic Hierarchy Process.

1.6 Objective of The Research

The research is set-up to examine the criteria of subcontractor selection and

to support the procurers on the appropriate subcontractor selection using the decision

support system.

In order to satisfy these needs, it initiated with 3 objectives:

a) To understand the nature of subcontractor selection approaches

practiced by various contractor.

b) To explore and define the potential criteria which affect the selection

of sub-contractor.

c) o develop theoretical model that represents the appropriate sub-

contractor selection based on AHP process.

1.7 Scope and Limitation of The Research

The scope of the research is to identify the criteria for subcontractor selection

using knowledge acquisition phases and to assess the information which involves

multi criteria decision making ability using Analytic Hierarchy Process. Hence, the

research is limited to the following scope:

a) The knowledge acquisition phases only involved the main contractor

working in Putrajaya.

Page 21: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

14

b) Assessment of the information is used to develop the theoretical

model based on Analytic Hierarchy Process.

c) The study is not consider what is the best methodology for

subcontractor selection but it will focus on the application of AHP as

one of tool for decision support system.

1.8 Brief Research Methodology

The research methodology used to achieve the objectives of the research is

depicted in figure 1.1. A brief guideline of the research methods is explained in this

section and the details research methodology is represented in Chapter 3.

a) Literature Review :- The extensive literature review focused on two

major subjects . First, the overview understanding of the criteria used

for sub-contractor selection in various countries. Secondly, the review

of various methodologies for sub-contractor selection based on the

decision support system. This literature review provided a theoretical

idea and profound knowledge of the topics and to frameworks the

structure of the research. The literature review focused in obtaining

the information through a combination of several sources, which

includes, publication from several professional bodies, construction

magazines, experience, interaction with experts and the used of local

university library to assist books, journals, conference papers and

internet facilities.

b) Knowledge acquisition :- The process involved a capturing of

knowledge from the experts directly involved in the pre-qualification,

selection and evaluation process. The knowledge acquisition activities

Page 22: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

15

included interview, questionnaires survey and correspondence with

the contractors.

c) Theoretical model development :- The data collected in the knowledge

acquisition phases are use to develop a theoretical model based on the

Analytic Hierarchy Process as a propose decision support system for

this research.

Research Objectives Research Methodology

1. To understand the nature of sub-

contractor selection approaches

practiced by various contractor.

Literature Review

Chapter 2: Selection criteria and

methodology

2. To explore and define the

potential criteria which affect the

selection of sub-contractor.

Questionnaire Survey

Chapter 3 – Research Methodology

Chapter 4 - Knowledge acquisition for

model development

Interviews

Chapter 3 - Research Methodology

Chapter 4 - Knowledge acquisition for

model development

4. To develop theoretical model

that represents the appropriate sub-

contractor selection based on AHP

process.

Expert Choice 2000

Chapter 5 - Theoretical model

development

Figure 1.1 - Research objective and methods

Page 23: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

16

1.9 Structure of Dissertation.

The structure of the dissertation is frame into 6 major chapters and a brief

summary of each chapter’s contents is presented below:-

Chapter 1 : Introduction of study, discuss on the research project undertaken

and the important of the research. It then justifies the need for the research; aims,

scope, objective, limitation of research and brief research methodology adopted.

Chapter 2 : Literature review - more details literature review of sub-

contractor selection and construction practiced are considered. This including the

construction on project life cycle, sub-contractor tendering process, criteria of

evaluation & selection and methodology analysis for selection process.

Chapter 3 : Research methodology - give the overall view of research

methodology including the knowledge acquisition phases, basic concept of decision

making including its definition and phases, concept of model development and detail

information of Analytic Hierarchy Process – the theoretical aspect, justification of

using the model for the research and explanation of expert choice software as a

decision support system.

Chapter 4 : Knowledge acquisition for model development – presents the

method of data collection and the result obtained from the questionnaires survey,

semi-structured interviews and analysis.

Chapter 5 : Development of theoretical model– Described the development

process of theoretical model and the operation system.

Page 24: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

17

Chapter 6 : Conclusion and recommendation presents the summary and

conclusion of the dissertation. It discuss and concludes the key finding of the

research and recommendation for future works.

Page 25: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

42

LIST OF REFERENCES

REFERENCES

Abdullah. A. A Decision Model for the Selection of Demolition Techniques.

Doctoral Thesis.

Alhazmi, T. and McCaffer, R.(2000), Project Procurement System Selection

Model, Journal of Construction Engineering & Management Vol. 126 No. 3

PP176-184.

A. Mardtunga, D. Baldry, D. Sarsher, M. and Newton, R. (2000) Quantitative and

Qualitative Research in the Built Environment. Vol. 51, No1, pp 17-31.

Al. Khall. M. I. Selecting the Appropriate Project Delivery Method Using AHP.

International Journal of Project Management Vol. 20 (2002) 469, 474.

Bellman R. and Zadeh, L, A (1970), Decision Making in Fuzzy Environment, Vol.

17, No4, pp 141-164 Management Science, Vol. 17.

Belton v. (1990), Multi Criteria Decision Analysis: Department of Management

Science pp 1-49.

Page 26: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

42

Chau. C.K, Sing W.L, Leung T.M. An Analysis on the HUAS Maintenance

Contractor Selection Process. Journal Building and Environmental 38 (2003)

583-591.

Chan .D.W.M. and Kumaraswamy. M.M. (1997), A Comparative Study of Causes

of Time Over runs in Hong Kong Construction Projects. International Journal

of Project Management 15 (1). 55-63.

Dyer J. S (1990), Remarks on the Analytic Hierarchy Process. Management Science

Vol. 36 pp 249-258.

EFNI USLINDA BIN SHAMSURI, Subcontractor Selection Using Fuzzy Logic.

Theory. UTM. Master Programme.

EFNI USLINDA BIN SHAMSURI, Abd Majid, M.Z, Mohammad I.M and Bahrul

Anif (2004). A Pilot Study on Subcontractors Selection Using Fuzzy Logic

Algorithm. UTM

Fielding, N. and Schneier. M (2001), On the Compability Between Qualitative and

Quantitative Research Method Forum. Qualitative Social Research ConLine

Journal Vol. 2, No. 1.

Fong P. S. W. and Choi S.K.Y. (2000). Final contractor Selection Using the

Analytical Hierarchy Process Construction Management and Economics. Vol. 18.

Fox. R (1996), Contractor Selection http:// www.fotees.free.serve.co.uk/subjects/hnd

94/pia/pia 7.htm.1996.

Golden B. Wasil E and Harker. P (1989), The Analytic Hierarchy process

Applications and studies, Spinger- Verlog, Berlin.

Guitovni. A and Martel J.M (1998), Tentative guidelines to Help Choosing on

Appropriate MCDA Method European Journal of Operational Research. Vol. 109

No. 2, pp 510-521.

Page 27: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

43

Hatush. Z and Skitmore. M (1997), Criteria For Contractor Selection. Journal

Construction Management and Economics Vol. 15. 19-38.

Hatush. Z and Skitmore. M(1997b) Evaluating Contractor Pre-qualification Data.

Selecting Criteria and Project Success Factors. Journal Construction

Management and Economic Vol. 15, pp 129-147.

Hatush. Z and Skitmore R.M (1998), Contractor Selecting Using Multi-criteria

Utility Theory An Additive Model. Journal building and Environment Vol. 33,

105-115

Hold D.G Which, Contractor Selection Methodology. International Journal of

Project Management Vol. 16. No 3, pp 153-164 (1998)

Holt G.D (1998), Which contractor Selection Methodology International Journal of

Project Management 16. pp153-164.

Holt G.D, Dlmolaiye, P.D and Harris FC 1995, A Review of Contractor Selection

Practice in the UK. Journal Building and Environment Vol. 30 pp 553-561.

IVOR h. Seeley – Quantity Surveying Practice Macmillan Publication 1997.

Jack R. Meredith, Samual J. Mantel JR Project Management. Wiley John and Son

Publications 1989.

Jennings, P. and Holt G.D (1998), Pre-qualification and Multi-criteria Selection.

Construction Management and Economics Vol. 16 No. 6, pp 651-660.

John. M. Nicholas – Project Management for Business and Technology. Prentice

Hall Publication 2001

Page 28: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

44

Kamal, M, Al-subhi, Al-Harbi (2001), Application of the AHP in Project

Management 19 (2001) 19-27.

Keeney, R and Raiffa, H (1976), Decision with Multiple Objects : John Wiley &

Sons. New York.

Kumaraswamy. M.M Contractor Evaluation and Selection : A Hong Kong

Perspective. Journal of Building and Environmental Vol. 31, 273-282 1996.

Merna A. and Smith N.J (1990), Bid Evaluation for UK Public Sector Construction

Contracts. Proceeding of The Institute of Civil Engineers 1 pp 91-105.

Ng. S.T, Skitmore R.M, Client and Consultant Perspective of Pre-qualification

Criteria, Journal Building and Environment 34 (1999) 607-621.

Palaneswaran. E, Kumaraswamy M.M, Contractor Selection For Design/Build

Project. Journal of Construction Engineering and Management Sep/Oct 2000,

331-339.

Patrick SIK-WALT FONG and SONIA KIT YUNG (HO), Final Contractor

Selection in Using the Analytical Hierarchy Process. Construction Management

and Economics (2000) 18, 547-557.

Partovi, F.R (1994), Determining What to Benchmark; An Analytic Hierarchy

Process Approach. International Journal of Operation and productions and

production management, Vol 14 No. 6, pp 25-39.

Russell. J.S. (1992), Decision Models For Analysis and Evaluation of Construction

Contractors. Journal of Construction Management and Economics Vol. 10, pp.

185-202.

Russell J.S. and Skibriewski M.J. (1988), Decision Criteria in Contractor Pre-

qualification. Journal of Management in Engineering ASCE. Vol. 4, pp. 148-164.

Page 29: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

45

Saaty, T.L. (1994b), Highlights and Critical Points in the Theory and Application of

the Analytic Hierarchy Process, European Journal Of Operational Research,

Vol. 74, No. 3, pp. 426-447.

Saaty, T.L. and Vargas, L.G. (2001), Models, Methods, Concepts & Applications of

the Analytic Hierarchy Process, International series in operations Research &

Management Science, Kluwer Academic, Boston.

Saaty, T.L. (1977), a Scaling Method for Priorities in Hierarchy Structure, Journal

of Mathematical Psychology, Vol. 15.

Saaty T.L. (1980), The Analytic Hierarchy Process, McGraw-Hill International,

New York.

Saaty T.L. (1983), Axiomatic Foundations of the Analytic Hierarchy Process,

Management Science, Vol. 32.

Saaty T.L. (1987), Decision Making , New Information , Ranking and Structure,

Mathematical Modeling, Vol. 8.

Saaty T.L.(1987), The Analytic Hierarchy Process : Planning, Priority Setting,

Resources Allocation, Rws Publication, Pittsburg, PA.

Saaty, T.L. (1994a), Fundamentals of Decision Making and Priority Theory with the

Analytic Hierarchy Process, Rws Publications, Pittsburgh, PA.

Triontaphyyllou, E. and Mann S.H. (1995), Using the Analytic Hierarchy Process

for Decision Making in Engineering Application. International Journal of

Industrial Engineering Application and Practice. Vol. 12 No. 1, pp. 35-44.

Turban E. and Aroson J.E (1988), Decision support system and Intelligent System

5th

Edition, Prentice-Hall, Jersey.

Page 30: RAVICHANDRAN A/L MANOHARAN A project report submitted in ...eprints.utm.my/id/eprint/3489/1/RavichandranManoharanMFKA2005.pdf · keselamatan dan peranan alam persekitaran. Akibatnya

46

Zeleny, M. (1982), Multiple Criteria Decision Making, McGraw-Hill Series in

Quantitative Methods for Management, McGraw-Hill New York