    RBIRISK BASED INSPECTION

    Presented by:

    Mohammad Javad Ranjbar

    5 May 2014

    Introduction to RBI

    what is RBI

    what are the key elements of RBI

    how to implement an RBI program

    how to sustain an RBI program

    RBI Softwares

    TWI - RISKWISE

    ReliaSoftRBI

    Outline

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    2/29

    5/30/20

    What is RBI?

    Risk-based Inspection (RBI) is a methodology foridentification of high-risk equipment by review ofactive/potential damage mechanisms and the suitability ofmitigation methods

    RBI allows inspection/maintenance RBI systematicalevaluated both the probability of failure and theassociated consequence of failure.

    Risk is the combination of the probability of some eventoccurring during a time period of interest and theconsequences,(generally negative) associated with theevent. In mathematical terms, risk can be calculated bythe equation:

    Risk = Probability Consequence

    RBI vs. Other Inspection Methods

    Fixed Interval

    STANDARDInspection

    Service Interval

    ConditionBased

    TREND Analysis

    Consequencesnot considered

    Backward Looking

    Risk Based

    RISK Analysis

    Probability &Consequences

    Proactive

    Forward Looking

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    3/29

    5/30/20

    Increase Availability

    (reducing unplanned outages )

    Improve Safety

    )Ensure Safe Operation)

    Optimise InspectionCosts

    Objectives of RBI

    CATASROPHIC

    FAILURE OF

    STEAMLINE

    (JAPAN 2004)

    1

    2

    3

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    4/29

    5/30/20

    RBI Benefits and Limitations

    a) an overall reduction in risk for the facilities and

    equipment assessed,

    b) an acceptance/understanding of the current risk.

    RBI will not compensate:

    c) inaccurate or missing information,

    d) Design errors or faulty equipment installation,

    e) External events (e.g. Collisions or falling object)

    f) not effectively executing the plans,

    g) Secondary effects from nearby units

    h) lack of qualified personnel or teamwork,

    Outcome of an RBI?

    Hotspotlocations

    InspectionFrequency

    AppropriateInspectionTechnique

    Types ofdamageexpected

    What? How?

    Where?When?

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    5/29

    5/30/20

    International Standards

    API 580 / API 581 ASME PCC-3

    CWA 15740 DNV-RP-G101(Offshore topsides)

    Type of RBI Assessment

    Qualitative: Provides a broad-based risk assessment of

    an operating unit or a part of an operating unit, required

    less detail information about the facility. In this

    assessment using engineering judgement and experience

    for the analysis of probability and consequences of failure.

    Quantitative: Provides risk values for each equipment

    item and pipe segment in a operating unit, requiredcomprehensive detail information about the facility and

    equipment. In this assessment using logic models,

    likelihood and probability data to calculate the risk of

    failure.

    Semi-quantitative: Some were between either approach.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    6/29

    5/30/20

    RBI planning process overview

    1. Data Collection

    design and construction records/drawings:P&IDs, process flow diagrams, material selection diagrams (MSDs), etc.,

    piping isometric drawings,

    engineering specification sheets,

    materials of construction records,

    construction QA/QC records,

    codes and standards used,

    protective instrument systems,leak detection and monitoring systems,

    isolation systems,

    inventory records

    emergency depressurizing and relief systems,

    safety systems,

    fire-proofing and fire-fighting systems,

    layout;

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    7/29

    5/30/20

    1. Data Collection

    inspection recordsschedules and frequency,

    amount and types of inspection,

    repairs and alterations

    inspection results

    process datafluid composition analysis including contaminants or tracecomponents,

    distributed control system data,

    operating procedures,

    start-up and shutdown procedures,emergency procedures,

    operating logs and process records,

    1. Data Collection

    Off-site data and information

    ifconsequence may affect off-site areas;

    Failure datageneric failure frequency data

    industry specific failure data,

    plant and equipment specific failure data,

    reliability and condition monitoring records,

    leak data;Site conditionsclimate/weather records,

    seismic activity records;

    Equipment replacement costsproject cost reports,

    industry databases;

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    8/29

    5/30/20

    1. Identification of Damage Mechanisms

    2. Probability of Failure

    6. Material of construction: steel,

    stainless steel, cast steel, aluminium

    etc, any coatings

    7. Damage mechanisms: what damage

    mechanisms are known to occur or

    have the potential to occur in theplant. eg stress corrosion, brittle

    failure, temper embrittlement, fatigue,

    localised or general corrosion, creep,

    others,

    8. Inspection: dates, type (visual,

    thickness, MPI, UT etc) and extent of

    inspection, inspectability, inspection

    results, corrosion allowance.

    Effectiveness and management of the

    inspection programme.

    1. Number of units and type of plant:

    pressure vessel, tank, column,

    pipework, heat exchanger etc.

    2. Plant function: distillation unit, cat

    cracker, storage etc

    3. Plant processes: gas, hydrocarbon,steam etc, number of planned and

    unplanned interruptions per year

    4. Process stability: rate stability from

    a) very stable no known upset

    conditions known to exist to b) loss of

    control is inherent in process

    5. Plant maintenance history: repairs,

    modifications, quality of maintenance,

    painting & insulation maintenance

    Probability Information

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    9/29

    5/30/20

    2. Consequence of Failure

    3. Chemical data: relates to the

    chemicals tendency to ignite. What is

    the flash point of the material, rate its

    stability when unconfined.

    4. Quantity: how much material could

    be released in a single event

    5. Chemical state: what is the process

    temperature,what is the boiling point?

    6. Commercial damage potential: what

    is the value of plant within a 30m

    radius, within 150m?7. Toxicity: rate the toxicity from: a) no

    hazard to b) death or major injury on

    very short exposure

    8. Population: number of people, on site

    and off site, within 500m of releasepoint

    1. Fire: are external fire fighting

    resources required for the most

    serious event

    2. Incident mitigation: which one:

    i) gas detection systems,

    ii) plant operated under inert atmosphere,

    iii) secure fire fighting system,

    iv) automatic or manual isolation systems

    v) blast walls around high pressure

    equipment,

    vi) drain, dump or blowdown systems thatwill deinventory plant

    vii) fire proofing of plant strct. and cables

    viii) available supply of fire water, hour?

    ix) foam system or water curtain

    Consequence Information

    3. Risk Analysis

    RISK MATRIX: The LoF value is plotted on the

    vertical axis, and the CoF value is plotted on

    the horizontal axis, of the dimensionless 55

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    10/29

    5/30/20

    4. Inspection Planning

    When or before the risk target is reached, an inspection of the

    equipment is recommended based on a ranking of the

    component damage mechanisms that have the highest

    calculated damage factors.

    An inspection program is the combination of NDE methods

    (i.e. visual, ultrasonic, radiographic etc.), frequency of

    inspection, and the location and coverage of an inspection.

    Inspection programs vary in their effectiveness for locating

    and sizing damage, and thus for determining damage rates.

    4. Inspection Effectiveness

    Lack of coverage of an area subject to deterioration,

    Inherent limitations of some inspection methods to detect and

    quantify certain types of deterioration,

    Selection of inappropriate inspection methods and tools,

    Application of methods and tools by inadequately trained

    inspection personnel,

    Inadequate inspection procedures,

    The damage rate under some conditions (e.g. start-up, shut-down, or process upsets) may increase the likelihood or

    probability that failure may occur within a very short time.

    Inaccurate analysis of results leading to inaccurate trending of

    individual components, and Probability of detection of the applied

    NDE technique for a given component type, metallurgy,

    temperature and geometry .

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    11/29

    5/30/20

    5. Mitigation

    Reducing the POF, Primary source of consequence,

    magnitude of consequence:

    Equipment Replacement and Repair

    Evaluating Flaws for Fitness-For-Service

    Equipment Modification, Redesign, and Rerating

    Emergency Isolation

    Emergency Depressurizing/Deinventorying

    Modify Process

    Water Spray/Deluge

    Blast-resistant Construction

    spill detector

    Fireproofing

    .;

    6. Reassessment and

    Updating RBI Assessments

    Why Conduct an RBI Reassessment?

    Damage Mechanisms and Inspection Activities

    Process and Hardware Changes

    RBI Assessment Premise Change

    The Effect of Mitigation StrategiesWhen to Conduct an RBI Reassessment?

    After Significant Changes

    After a Set Time Period

    After Implementation of Risk Mitigation Strategies

    Before and After Maintenance Turnarounds

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    12/29

    5/30/20

    RBI Softwares

    RiskWISE

    ORBITRBI

    Credo RDMIP

    RB.Eye

    RB.QEye

    FAME+

    S.RBI

    RBI

    RISKWISERisk Based Inspection / Risk Based

    Maintenance software

    http://www.google.com/url?q=http://wildeanalysis.co.uk/news/2013/reliability-hotwire-151&sa=U&ei=OlVUU8zOEsmWyAT8sYGgBQ&ved=0CFAQ9QEwEA&sig2=FNFjGEGPoqhGOuz7MCERWw&usg=AFQjCNHCSGCZgnPcU3947Ex5O5iY2SYVjghttp://www.google.com/url?q=http://blog.offecct.se/index.php/2011/03/25/iso-9000-and-iso-14000-periodic-visit-by-bureau-veritas/&sa=U&ei=9VNUU_S3IYGMyATeroDADQ&ved=0CDIQ9QEwAg&sig2=CjkIenp9DyGvFDFma1grHA&usg=AFQjCNFFd5DehCj6oFe5DeFx9U6o62qSHAhttp://www.google.com/url?q=http://www.wkrb13.com/markets/287605/royal-dutch-shell-rating-reiterated-by-cowen-company-rds-a/&sa=U&ei=N1JUU-2mAdeyyATx5YIw&ved=0CFIQ9QEwEg&sig2=evA1Vi0Zi6DlJMOtcO0m9w&usg=AFQjCNGrQ_j4ilrgi9LVm_wP06YvNjyYtghttp://www.google.com/url?q=http://158.132.155.107/posh97/private/Full_text_reference/Risk_management/rbmi.html&sa=U&ei=ulBUU7ioD82GyATuiIGADw&ved=0CC4Q9QEwAA&sig2=jdRi2UUjJvzZAbTpWXfGYg&usg=AFQjCNGHzPIGIMcf84wLhnmgeZMoRudK_Ahttp://fuelmarketernews.com/wp-content/uploads/2013/08/api-logo1.jpg
  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    13/29

    5/30/20

    Demonstrator Contents

    System Overview

    Introduction Ease of Use

    Access Controls

    Knowledge-base

    Options and Settings

    Fluid Properties

    Nameplate Information

    Inspection History

    Damage Mechanisms

    Risk Factors

    Risk Summary

    Risk Profile

    Record Data Tables

    Record Properties

    Risk Mitigation

    Risk Comparison

    Inspection Plans

    Management Reporting

    Contact TWI

    TWI Ltd is the sole owner of this software

    demonstration show and may change this

    demonstration without issuing notice. Noperson or entity may reproduce or transmit

    any part of the demonstration without written

    permission from TWI Ltd.

    RISKWISE has a friendly Microsoft style graphical user interface )GUI,

    developed in Visual Basic using object-oriented design tools.

    Graphical

    Navigation

    Microsoft

    Toolbar

    Folder

    Tree

    Intuitive

    Interface

    Drag n Drop

    Table Sorting

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    14/29

    5/30/20

    RISKWISE is an API RP580 compliant risk-

    based inspection (RBI) planning tool for use with

    pressure equipment, pipelines, power boilersand storage tanks. The risk model is semi-

    quantitative, so it can be easily learned and is

    convenient to use.

    RBI management systems are applied to:

    Improve the safety of critical plant

    Reduce the duration of inspection outages

    Extend the interval between major

    inspections

    Reduce direct inspection and maintenance

    costs

    FeaturesIntegrationRISKWISE is a second

    generation client-server

    product, using the ODBC

    (Open DataBase

    Connectivity) protocol for

    SQL databases (eg

    FoxPro, SQL Server,

    Oracle and Access).

    Multi-lingualRISKWISE is designed

    to provide complete

    multi-lingual capability

    for rapid native language

    implementation.

    RISKWISE enables the system administrator

    to control user access, tailoring it to the specific

    needs of the inspection and maintenance

    organisation. This allows simple control and

    auditability of previous assessment records.

    FeaturesAccess ControlThree main levels:

    Read-Only

    Proposal Write

    Item Write Access

    AuditabilityThe name of the

    assessor undertaking the

    RBI evaluations for each

    item of equipment is

    recorded, in compliance

    with best practice

    auditing principles.Record HierarchyProposed inspectionplans

    RBI assessment results

    which cannot be

    changed or deleted

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    15/29

    5/30/20

    RISKWISE stores equipment nameplate

    information in the Item Properties and Materials

    screens. This information can be easilyintegrated with asset information in other

    applications, via the in-built RISKWISE Import

    Wizard.

    FeaturesItem PropertiesCaptures general

    information about the

    equipment including

    drawings, design and

    operating parameters.

    MaterialsCaptures information

    about the materials of

    construction

    components within

    equipment or pressure

    system.

    RISKWISE contains an inspection knowledge-

    base covering non-destructive testing (NDT)

    methods and comprehensive descriptions of

    over 30 damage mechanisms (DM), including 20

    corrosive species leading to general and

    localised corrosion and 10 species leading to

    stress corrosion cracking.

    FeaturesNDTThe knowledge-base

    covers visual, magnetic,

    ultrasonic, eddy current,

    metallurgical,

    radiographic,

    thermographic, acoustic

    emission and other non-

    intrusive methods.

    Damage MechanismsThe common

    mechanisms are

    categorised in terms of

    leading to Metal loss,

    Environmental or

    Metallurgical and

    mechanical damage.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    16/29

    5/30/20

    RISKWISE allows users complete freedom to

    undertake assessments in European, US

    Customary units or User-defined units. Systemadministrators have the ability to define safety

    factors based on assessment consequence

    categories, for direct use in the derivation of

    equipment inspection intervals.

    FeaturesUnitsDefine system wide

    defaults for assessment,

    such as engineering

    units of measure.

    Factors of SafetyModify configuration of

    safety factors, that are

    linked to the

    consequence categories,

    in the calculation of

    remaining life indicators

    for all damage

    mechanisms.

    RISKWISE assesses consequence of failure

    generally in accordance with guidance provided

    in API BRD581 based on the fluid property

    classifications presented by National Fire

    Protection Association (NFPA).

    FeaturesChemical FactorA Flammability Factor is

    used by RISKWISE, in

    combination with a

    Reactivity Factor, to derive

    a Chemical Factor,

    representing a fluids

    inherent tendency to ignite.

    Explosion and FireRISKWISE assesses a

    State Factor and the

    Chemical Factor, in

    accordance with theprocedure in publication

    API BRD581.

    ToxicityRISKWISE employs the

    NFPA ranking of the

    probable severity of the

    effects of a fluid on

    exposure to personnel, in

    the event of a release and a

    fire.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    17/29

    5/30/20

    RISKWISE captures all relevant historical

    inspection and maintenance history in the

    Inspection Methods screen for subsequent use

    in the identification of equipment damage

    mechanism prior to the risk assessment.

    FeaturesInspection MethodsCaptures relevant

    historical information

    including coverage and

    findings, that will be

    regularly updated

    following future

    inspections.

    Inspection PlansRISKWISE transfers

    historical findings as well

    as the proposedinspection activities, to

    the Written Scheme of

    Examination.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    18/29

    5/30/20

    RISKWISE captures the location of all active

    and potentially active damage mechanisms

    within each item of pressure equipment.

    FeaturesChecklistRISKWISE deals with

    damage mechanisms

    relevant to oil, gas and

    petrochemical process

    equipment, storage

    tanks, pipelines, and

    fossil fuel power boilers.

    Remaining Life

    IndicatorsThe estimated remaining

    life of each damage

    mechanism is assessed

    within RISKWISE, to

    establish equipment

    inspection intervals.

    RISKWISE assesses seven likelihood

    (probability) of failure factors and nine

    consequence of failure factors, for each item of

    equipment.

    FeaturesTime-based Risk

    AnalysisRISKWISE assesses

    failure probability over

    three forward periods of

    time, for each active or

    potentially active damage

    mechanism.

    Inspection

    EffectivenessRISKWISE assesses

    the effectiveness of thecurrent inspection

    program for each

    damage mechanism

    separately.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    19/29

    5/30/20

    RISKWISE presents the results of the risk

    analysis for each of the damage mechanisms,

    over the three forward time intervals, as well asthe resulting remaining life indicator (RLI) which

    defines a safe inspection interval.

    FeaturesRisk Matrix

    RISKWISE plots eachassessment point on an

    API RP580 five-by-five

    risk matrix for risk

    regions ranging from

    Favourable to Critical.

    Limiting Damage

    MechanismsThe lowest RLI out of all

    damage mechanisms

    equates to the maximum

    allowable inspection

    interval for the

    equipment.

    RISKWISE provides a risk profile of all

    equipment within the facility for the identification

    of critical and non-critical equipment.

    FeaturesSummaryThe distribution of risk

    can be presented using a

    risk matrix, pie charts or

    bar charts as well as

    comparatively, ie for

    subsequent post-

    assessment cost-benefit

    analysis.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    20/29

    5/30/20

    RISKWISE simply identifies critical equipment

    as those items where the RLI is less than

    current inspection period, and non-criticalequipment as those items where the RLI is

    greater than the current inspection period!

    FeaturesTable SortingThe results of the RBI

    assessment are

    presented in the

    RISKWISE data tables,

    which can be easily

    sorted using the drag n

    drop column titles.

    RISKWISE ensures that the individual authors

    of each equipment RBI assessment are fully

    traceable.

    FeaturesAuditabilityRISKWISE enables

    comprehensive tracking

    of assessment results

    and input assumptions,

    in accordance with the

    requirements of API

    RP580.

    Record NotesRISKWISE includes a

    simple catch-all free

    text field for any other

    information relevant to

    the likelihood of

    consequence of failure of

    the equipment under

    consideration.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    21/29

    5/30/20

    RISKWISE presents RBI assessors with a risk

    action plan from which the most suitable risk

    mitigation options, for critical equipment, can beevaluated.

    FeaturesAction GroupingRISKWISE assigns the

    most frequently used risk

    mitigating actions to six

    groups, for ease of

    evaluation during the

    final inspection planning

    and optimisation phase

    of the RBI assessment.

    RISKWISE allows the RBI assessor to

    evaluate the impact of the proposed actions or

    inspection changes on risk and the remaining

    life indicator (RLI).

    FeaturesInspection OptimisationThe process of risk

    comparison within

    RISKWISE enables users to

    systematically evaluate the

    effect of actions on the risk of

    failure, while considering the

    constraints.

    RBI

    Inspection

    Savings

    Production

    CostSavings

    $100k

    $300k

    $500k

    $700k

    $900k

    Total Savings = $1.1MB/C Ratio = 11:1

    RBI

    Inspection

    Savings

    Production

    CostSavings

    $100k

    $300k

    $500k

    $700k

    $900k

    Total Savings = $1.1MB/C Ratio = 11:1

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    22/29

    5/30/20

    The final output of a RISKWISE assessment is

    an optimised inspection plan )Written Scheme

    of Examination which focuses on each damagemechanism.

    FeaturesReportingRISKWISE presents a

    detailed report of the RBI

    assessment for use by

    field inspection

    engineers, or in other

    reports application as

    necessary.

    RISKWISE provides a post-assessment

    analysis capability to evaluate the impact of

    actions on the risk distribution for all equipment.

    FeaturesTime TrackingRISKWISE enables the

    user to assess the value of

    RBI following successive

    major inspections and

    subsequent RBI updating,

    eg. between Revision 0 and

    Revision 1.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    23/29

    5/30/20

    RISKWISE 2014

    NEW

    Released

    Feature

    RBI EXAMPLEQuantitative Assessment of a Boiler

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    24/29

    5/30/20

    Application

    Selection

    Chosse boilers as

    Oil,Gas and

    Process Plant

    Suite

    Current Table

    A table of current

    revision records or a

    table of all proposal

    records can be

    displayed by

    navigating to these

    screens via theshortcut bar.

    These lengthy tables

    can be organised

    and sorted by

    dragging the column

    titles to the top of the

    screen, into any

    ordered display

    hierarchy:

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    25/29

    5/30/20

    Item Proposal

    Once you have

    specified the

    equipment class,

    (for example,

    specify that a

    particular pipe is a

    Hot Reheat Pipe),

    the list of expected

    damage

    mechanisms is

    shortenedautomatically to

    display the types of

    damage that might

    be expected.

    Item Properties

    The entries on the

    unit properties

    screen determine

    the risk associated

    with various items

    in boilers.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    26/29

    5/30/20

    Item Properties

    Enlarge the picture

    to see the detailes

    you have to enter.

    Risk Factors

    All of the items on

    the Risk Factors

    screen will be read-

    only if the item

    properties, damage

    mechanisms and

    inspection methodsscreens are fully

    completed. If you

    need to change any

    of these values you

    will need to change

    back to manual

    mode

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    27/29

    5/30/20

    RISK Analysis

    The assessment

    points for each of the

    three risk analysis

    periods can be

    toggled on or hidden

    via the buttons on the

    toolbar. For example,

    if you wish to display

    the assessment

    points for the first

    analysis period (1AP)

    only, select thebuttons to HIDE 2AP

    and HIDE 3AP. The

    risk plot will then only

    display 1AP ( )

    assessments points.

    Level 1

    Assessment

    The level 1

    assessment is a

    unit level

    assessment to

    assess a boiler as a

    whole. To switch to

    the level 1 view,click on the

    assessment level

    toggle at the top of

    the main screen.

    When switching to

    the level 1

    assessment, the list

    of items now only

    shows units.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    28/29

    5/30/20

    Home

    You can right-click

    on an existing unit

    to create a

    proposal, or create

    a new unit or

    proposal

    from the links on

    the home screen.

    Unit

    Proposal

    Each unit has a set

    of properties

    associated with it

    in a similar way

    that other (level 2)

    components have

    an item propertieslist. The proposal

    record can be

    viewed by double

    clicking on it in the

    items list.

  • 7/23/2019 rbi-150531182513-lva1-app6892.pdf

    29/29

    5/30/20

    Unit

    Analysis

    The analysis

    screen shows the

    business

    consequence of

    the major

    components of the

    boiler failure.

    THANK YOU FOR YOUR ATTENTION