re-futures study

Upload: tita-cholifah-rahayu

Post on 02-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 re-futures study

    1/20

  • 8/10/2019 re-futures study

    2/20

    A. POWER SYSTEM OPERATIONS

  • 8/10/2019 re-futures study

    3/20

    This section discusses several elements of power system operations, including

    forecasting and the day-ahead schedule or unit commitment, within-a-day

    economic dispatch, frequency response and control , and operating reserves.

  • 8/10/2019 re-futures study

    4/20

    A1. SECURITY-CONSTRAINED UNIT

    COMMITMENT

  • 8/10/2019 re-futures study

    5/20

    If a large thermal generator is suddenly lost, the instantaneous impact of

    such a loss to the surrounding power system and system operatingreserves requirements is depicted in Figure above. Turbine speed

    governors and the systems automatic generation control (AGC) sense a

    drop in system frequency and initiate corrective action to increase

    power from generators that are still operating.

  • 8/10/2019 re-futures study

    6/20

    Unit commitment is a process of determining which generating units that

    will be needed for the next day, and ensuring that any large thermalunits started and synchronized to the grid. This process is based on the

    day-ahead load forecast, an estimated 2-3% of the peak load. The aim

    of this process is for the solution of every economic problem.

    in this process, many of the risks faced, either too much or too little

    capacity is committed. operating reserves appeared to be the solution

    of these problem.

  • 8/10/2019 re-futures study

    7/20

    A2. ECONOMIC DISPATCH AND LOAD

    FOLLOWING

  • 8/10/2019 re-futures study

    8/20

    Economic dispatch is the short-term determination of the optimal output

    of a number of electricity generation facilities, to meet the system load,at the lowest possible cost, subject to transmission and operational

    constraints. In order to serve load at minimum total cost, the set of

    generators with the lowest marginal costs must be used first, with the

    marginal cost of the final generator needed to meet load setting the

    system marginal cost.

  • 8/10/2019 re-futures study

    9/20

    A3. FREQUENCY RESPONSE AND

    CONTROL

  • 8/10/2019 re-futures study

    10/20

    The value of Frequency Control is 60 Hz. If there is deviation from 60 Hz,

    its indicates that there is a problem in the power system, the larger thedeviation, the bigger the problem. Abnormal frequency will damage the

    power system, especially large steam turbines. While Frequency

    response from generators actually helps protect the turbines from

    abnormal frequencies by limiting the magnitude of the frequency

    change during events.

  • 8/10/2019 re-futures study

    11/20

    B. TRANSMISSION TECHNOLOGY AND

    INSTITUTIONAL ISSUES

  • 8/10/2019 re-futures study

    12/20

    This chapter provides a brief overview of transmission technology and then

    an introduction to the basic institutional issues.

  • 8/10/2019 re-futures study

    13/20

  • 8/10/2019 re-futures study

    14/20

    Worldwide, the transmission technologies in use and functioning today,

    either broadly or in initial installations, for transmitting bulk electricalpower are high, extra-high, and ultra-high-voltage AC transmission

    systems up to 1,000 kV (Global Transmission 2009); high and ultra-

    high-voltage DC transmission systems; and underground cables. The

    current motivation for pursuing new higher capacity transmission

    technology is the growth of large regional markets and the opportunity

    for greater economic exchange.

  • 8/10/2019 re-futures study

    15/20

    AC&HVDC TRANSMISSION SYSTEMS

  • 8/10/2019 re-futures study

    16/20

  • 8/10/2019 re-futures study

    17/20

    HIGHER VOLTAGES

    AND SUPERCONDUCTING CABLES

  • 8/10/2019 re-futures study

    18/20

    3. Higher Voltages

    The advantage of using higher voltages is the decline in per unitcosts; the disadvantage is the risk of losing a larger portion oftransmission capacity in a single contingency failure.

    4. Superconducting Cables

    These cables use high-temperature superconductor materialsinstead of copper or aluminum and have substantially higherpower handling capabilities at lower voltages than conventionalcables. however, there are parasitic refrigeration losses. Thecommercial competitiveness remains to be fully demonstrated inthe market. As this technology is not commercial, it was notincluded in RE Futures transmission modeling.

  • 8/10/2019 re-futures study

    19/20

    B.2 TRANSMISSION AND INSTITUTIONAL

    ISSUES

  • 8/10/2019 re-futures study

    20/20

    1. State and Federal Jurisdictions

    the regulatory and economic drivers affecting transmission planning aresplit among the federal government and the states.

    2. Siting, Permitting, and Right-of-Way Acquisition

    Currently, the siting and permitting of transmission lines is the

    responsibility of individual states.

    3. Transmission Cost Allocation

    Transmission cost allocation is controversial and one of the most important

    issues to resolve if significant transmission system expansion is to be

    realized.