reach solar project 2006 east blair housing co-op eugene, or
TRANSCRIPT
REACH Solar Project2006
REACH Solar Project2006
East Blair
Housing Co-op
Eugene, OR
East Blair Housing Co-opEast Blair Housing Co-op
Established June 30, 1981 Located in the historic Whiteaker
neighborhood 22 households (only 5 in solar project) Townhouse apartments, SF and large
conversions Garden space and safe play areas
Project PartnersProject Partners
OHCS
Lane County HSC
EWEB
HACSA
EBHC
Time linesTime lines
July 2006 Request for proposal August Submittal deadline September 2nd solicitation October Review committee selection November Award of Contract and roof
replacement December Installation, inspections,
progress payments. Dec. 29th Solar Heated water “on-line”
Selection CriteriaSelection Criteria
Cost Design Effectiveness Completion time line Maintenance Reliability EWEB approved “Brightway specs”
Proposal Cost RangeProposal Cost Range
Solar Assist $23, 332 to $25,832
Mr. Sun $35,750 to $38,230
Cascade ~ no quote ~
BudgetBudget
DOE $5,082
LIEAP $9,605
REACH $7,500
EWEB $1,145
Solar System ComponentsSolar System Components
Drain-back Solar Water Heater (3) 4’ X 10’ SunEarth “black chrome” collectors (2) 120 gallon Rheem/Ruud Solar storage tanks (1) SunEarth “Steca) Differential Temperature
Control (1) Grundfos Pump (1) 10 gallon drain back tank (1) 1 ¼ Tempering valve
Scope of WorkScope of Work
Build storage shed for solar tanks and equipment Replace roofing on south slope (by EBHC) Install collectors, tanks, valves, differential
temperature control, and pump Connect all components and plumbing to serve 5
townhouse units. Instruct Co-op residents regarding recommended
system maintenance and operation