real property institute of canada€¦ · • the egd is a federally owned, operated and maintained...
TRANSCRIPT
![Page 1: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/1.jpg)
Real Property Institute of Canada
2014 RPIC Federal Contaminated Sites National Workshop
April 2014
![Page 2: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/2.jpg)
Esquimalt Graving Dock Waterlot Remediation Project (Phase 1B)
Confirmatory Sampling, Analysis and Evaluation Plan (CSAEP) Implementation
and Dredging Residuals Management
Stream H: Contaminated Sites Management for Aquatic Environments and Sediment
Presenter: David McKeown (SLR Consulting) Collaborators: Jeff Nyman (SLR), Andrew Mylly (PWGSC), Rae Ann Sharp (PWGSC), Tom
Wang (Anchor QEA), Dan Berlin (Anchor QEA), Matt Woltman (Anchor QEA)
2 / 37
![Page 3: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/3.jpg)
Project Background • The EGD is a federally owned, operated and maintained
facility. • Ship repair and maintenance facility for military and
civilian vessels since 1927. • Industrial activities at the EGD have resulted in
contamination of the surrounding sediments. • PWGSC managed the remediation project through
FCSAP funding. • The Waterlot Remediation Program aimed to clean up
the site to meet federal and provincial environmental standards.
3 / 37
![Page 4: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/4.jpg)
Project Background (Cont’d) • Primary CoCs in sediment included Metals, PAH, and PCB. • Other contaminants included TBT, Dioxins/Furans, and
Pesticides. • Contaminant levels identified as IL+ for disposal
considerations. • Contaminated sediments were removed through remedial
dredging and off-site disposal. • Confirmatory sediment sampling program designed and
implemented to verify that remedial targets were met. • Decision criteria developed to determine potential re-
dredging and/or Remedial Management Cover (RMC) placement requirements.
4 / 37
![Page 5: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/5.jpg)
Project Location
Esquimalt Graving Dock
5 / 37
![Page 6: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/6.jpg)
Project Boundary
6 / 37
![Page 7: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/7.jpg)
Photo courtesy of Heath Moffa5
7 / 37
![Page 8: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/8.jpg)
Objectives • CSAEP developed to outline standardized procedures for
collection of post-dredge sediment samples. • Establish methods to characterize and assess post-dredge
sediment quality. • Provide an evaluation process to verify whether remedial
targets were met through dredging activities. • Provide project staff with a guidance tool to conduct
sampling, assess resulting information, and determine whether additional actions were required.
• Also used as a baseline planning tool for cost estimates to implement the sediment quality assessment program.
8 / 37
![Page 9: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/9.jpg)
Study Design • Waterlot divided into 11 dredge zones
based on pre-dredge contaminant profiles. – Zone 10 further broken into sub-zones
• Dredge zones sampled after completion of dredging activities using a 25 x 25 m grid spacing.
• Locations identified in field using sub-metre accuracy GPS
• Vibracore samples collected at each location with concurrent surface grab samples (petite ponar).
• Diver cores collected where unable to obtain vibracore samples.
• Test pit samples collected during low tide in intertidal area of Munroe Head. Photo courtesy of Heath Moffa5
9 / 37
![Page 10: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/10.jpg)
10 / 37
![Page 11: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/11.jpg)
• Sediment quality assessment conducted for each dredge zone and sub-zone individually.
• Confirmatory sediment cores and concurrent grab samples collected at each location for analytical testing. – Cores were sampled at 0.5 m intervals to identify missed inventory
contamination. – Surface grab samples were used to identify dredge residual
contamination.
• Slope samples also collected prior to slope armouring to aid in future risk assessment updates. – Not included in re-dredge decisions due to geotechnical considerations.
• Over 200 post-dredge locations sampled.
Study Design 11 / 37
![Page 12: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/12.jpg)
Remedial Objectives • Numeric Remedial Action Objectives:
– Based on most stringent and previously accepted applicable marine environmental quality guidelines, including:
• CCME Marine Sediment PEL • BC CSR Sediment Criteria for Typical Contaminated Sites • Puget Sound Dredge Disposal Analysis & Site-specific TBT
assessment (Golder) • NRAOs derived for:
– Metals – PAH – PCB – Dioxins & Furans – TBT – Select Pesticides
12 / 37
![Page 13: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/13.jpg)
Sample Collection, Handling and Processing
• Core samples collected by vibracoring vessel.
• Cores advanced in to sea floor 2 to 3 m or until refusal.
• Core tubes cut open to facilitate sample processing.
• Core compaction corrections applied based on penetration depth vs. recovery core length.
– Minimum recovery targets established for acceptance of cores.
13 / 37
![Page 14: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/14.jpg)
Sample Collection, Handling and Processing
• Samples collected at 0.5 m intervals along cores.
– Upper 1.0 m samples submitted for analysis.
– Remaining samples archived.
• Samples homogenized within each interval to ensure representative samples.
14 / 37
![Page 15: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/15.jpg)
Sample Collection, Handling and Processing
Concurrent grab samples collected using petite ponar sampler.
Diver assisted grabs/cores collected where vibracoring was not possible (e.g., dry dock sill area, hard substrate areas).
15 / 37
![Page 16: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/16.jpg)
Sample Collection, Handling and Processing
Munroe Head intertidal area (Zone 9) sampled by test-
pitting during low tides.
All grab, core, test pit samples homogenized to be representative.
16 / 37
![Page 17: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/17.jpg)
Laboratory Coordination and Submissions
• Prepared Laboratory Statement of Requirements to define: – Required detection limits to meet NRAO levels. – Turn-around-times for specific parameters. – Detailed schedule for samples and analysis requirements on a
daily, weekly and monthly basis. – Communication requirements. – Data management and QA/QC requirements.
• Electronic COC submissions. • Sample pick-up/delivery coordinated through laboratory.
17 / 37
![Page 18: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/18.jpg)
Data Management • Dedicated web-based Environmental
Management Tool (EMT) developed to provide accessible and up to date data repository.
• Remote access for project personnel. • Laboratory results loaded
automatically to the EMT. • Data manager included on project to
provide QA/QC review, data tabulation and management, and statistical analysis.
• Sediment quality compared to NRAOs
18 / 37
![Page 19: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/19.jpg)
Data Management (EMT) 19 / 37
![Page 20: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/20.jpg)
Confirmatory Sample Assessment • Post-dredge compliance decision framework generated
for assessment of sediment quality. • Post-dredge sediment quality was assessed using two
methods: – Overall dredge zone compliance with NRAOs based on
statistical approach (surface samples only). – Single point compliance assessment.
• Surficial samples compared to 4X NRAO threshold to assess dredge residual contamination. – Considered eventual mixing of upper sediment layers (up to 10
cm) with placed RMC layer (30 cm)
• Core samples compared to 1X NRAO to assess missed inventory contamination.
20 / 37
![Page 21: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/21.jpg)
Re-Dredge Decision Process • Initial re-dredge decision based on 3-day TAT parameters
(metals, PAH, PCB). – These parameters were drivers in most zones and other contaminants (i.e.,
pesticides, TBT, dioxins/furans) were generally shown to co-locate. – Pesticides, TBT, dioxins/furans analyzed on a 7-day TAT. – Where other parameters were drivers within a zone, results were re-
assessed once they became available. – Modifications to the re-dredge decision were then provided to the contractor.
• 10-day turn around requirement in specifications to provide re-dredge decision to contractor.
• Consultant design team and PWGSC personnel reviewed information from each zone in accordance with decision framework. – Re-dredge decisions formally relayed to contractor through PWGSC.
21 / 37
21 / 37
![Page 22: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/22.jpg)
Re-Dredge Decision Process • Contingency re-dredge depths
determined based on whether residual or missed inventory contamination was present within dredge zone and/or each sampling grid.
• Additional surface grab samples collected following re-dredging.
• Sediment quality from second sampling round was re-assessed in accordance with the post-dredge compliance decision framework. – Residuals assessment only.
Photo courtesy of Heath Moffa5
22 / 37
![Page 23: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/23.jpg)
Post-Dredge Compliance Decision Framework ZONE DREDGING
COMPLETED
CONFIRMATORY SAMPLING
(Vibracore and Surface Sampling)
SURFACE SAMPLING
(0 – 0.1 m)
Analytical Data Receipt, Tabulation and Review
Lab analysis (3-7 working days)
CORE SAMPLING (0 – 2.0 m with min 75% recovery)
Composite samples to lab (0-0.5 m and 0.5-1.0 m)
Archive Samples below 1.0 m
(in 0.5 m intervals)
23 / 37
![Page 24: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/24.jpg)
Post-Dredge Compliance Decision Framework COMPLIANCE UNIT ASSESSMENT
(based on surface samples only)
Method 1 – Single Sample Assessment Method 2 – Statistical Approach
Are the surface sample
concentrations less than NRAO?
Are there any surface sample concentrations >4X NRAO?
Is the 90th Percentile or 95% UCLM surface sample
concentrations below NRAO?
Is the 90th Percentile or 95% UCLM surface sample concentrations
below NRAO? If No, RMC thickness to be evaluated based on in-situ
concentrations
RESIDUAL RE-DREDGE (0-0.3 m)
PLACE RMC RESIDUAL RE-
DREDGE (0-0.3 m)
YES NO
YES NO: <4X NRAO NO: >4X NRAO
YES
If <NRAO
If <4X NRAO
2nd Round Surface Sampling 2nd Round Surface Sampling
YES
NO: <4X NRAO
NO FURTHER ACTION
REQUIRED
24 / 37
![Page 25: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/25.jpg)
Post-Dredge Compliance Decision Framework MISSED INVENTORY ASSESSMENT
(based on sediment cores)
Is the core sample concentration below NRAO?
Is the confirmatory surface sample concentration below the NRAO?
MISSED INVENTORY RE-DREDGE (0.5-0.8 m)
NO FURTHER ACTION
REQUIRED
PROCEED TO COMPLIANCE UNIT
ASSESSMENT METHOD
2nd Round Surface Sampling
NO
YES
YES
NO
25 / 37
![Page 26: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/26.jpg)
Surface Sample Results
<NRAO
1-‐4 X NRAO
>4X NRAO
Results Analysis - Example 26 / 37
![Page 27: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/27.jpg)
Core Sample Results
<NRAO
1-‐4 X NRAO
>4X NRAO
Results Analysis - Example 27 / 37
![Page 28: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/28.jpg)
Results Analysis - Example Re-Dredge Areas
28 / 37
Z03-12
![Page 29: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/29.jpg)
Contingency • In select cases, additional re-dredge passes were
conducted if concentrations in final surface grabs remained elevated above 4X NRAO.
• In other cases where additional re-dredging was not possible due to presence of hard substrates (e.g., till), diver surveys were conducted to document residual sediment layer thickness in order to adjust final predictions of COC concentrations after mixing.
• Assessment was conducted to determine whether increased RMC placement in these select areas would adequately reduce anticipated final concentrations.
29 / 37
![Page 30: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/30.jpg)
Final Surface Concentrations Before RMC
<NRAO
1-‐4 X NRAO
>4X NRAO
30 / 37
![Page 31: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/31.jpg)
RMC Placement Assessment • In areas where surface sediment contamination was
identified > 1X NRAO following required and/or contingency dredging, concentrations evaluated to determine if placement of RMC material (minimum 0.3 m thickness) would provide for sufficient mixing and attenuation to meet the NRAO target.
• In select cases where surface concentrations remained above 4X NRAO and additional re-dredging was not feasible or not considered to be effective, thicker RMC layers were applied.
• Areas identified for RMC placement reviewed by design team and requirements were relayed to the contractor.
31 / 37
![Page 32: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/32.jpg)
Post-Remediation Baseline Assessment
• Vibracore sampling at several locations within each dredge zone where RMC was placed. – Combined with RMC thickness assessment
• RMC thickness was verified within each core and compared to survey information.
• Baseline sediment quality within the upper 0.3 m was collected to provide baseline information for future studies to validate assumptions of post-remediation mixing.
32 / 37
![Page 33: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/33.jpg)
10 cm
33 / 37
![Page 34: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/34.jpg)
Surface Concentrations After RMC Placement
<NRAO
1-‐4 X NRAO
>4X NRAO
34 / 37
<NRAO
![Page 35: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/35.jpg)
Future Monitoring
• Long-term sediment quality assessments to be conducted to validate surface mixing assumptions and to determine trends over time.
• Sediment coring and analytical testing of upper 0.3 m in previously sampled locations.
• Comparison to baseline sediment quality established through RMC Assessment Sampling.
35 / 37
![Page 36: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/36.jpg)
Lessons Learned • Logistical considerations and staffing requirements/re-scheduling were
difficult and required appropriate budgeting and time allocation for proper planning.
• Areas where hard substrates were encountered proved to difficult to obtain adequate samples. – Diver cores required in some locations. – Very hard substrate areas only allowed for diver grabs. – Program modified in select areas to conduct diver video surveys to
document residual sediment layer thickness to re-adjust post-mixing assumptions where further re-dredging was not feasible or effective.
• RMC coring was difficult due to lower core retention. – Adjustments were needed in coring technique to provide adequate recovery.
• Overall challenges were realized with 10-day turn-around for response to contractor.
36 / 37
![Page 37: Real Property Institute of Canada€¦ · • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels](https://reader033.vdocument.in/reader033/viewer/2022052803/5f280d5f0c32767c420c6efd/html5/thumbnails/37.jpg)
Special Thanks to:
• Andrew Mylly (PWGSC) • Rae Ann Sharp (PWGSC) • Kristen Ritchot (PWGSC) • David Osguthorpe (PWGSC) • Chris Major (PWGSC) • Jeff Nyman (SLR) • Marci Martin (SLR) • Richard Plourde (SLR) • Hailey O’Neill (SLR) • Ingrid Sorensen (SLR) • Cheryl Nyman (SLR) • Heather Grant (SLR) • Coastline Technologies Inc.
• South Coast Diving Ltd. • Ben McKinnon (SLR) • David Grafton (SLR) • Ricki Sahota (SLR) • Drew Rice (SLR) • Vanya Jongkind (SLR) • David Pugh (SLR) • Aaron Haegele (SLR) • Chris Koziey (SLR) • Matt Woltman (Anchor QEA) • Dan Berlin (Anchor QEA) • Tom Wang (Anchor QEA) • Bud Whitaker (Anchor QEA) • Joe Persley (Anchor QEA) • Geoff Cooper (KCB) • Tervita • FRPD
37 / 37