realizing successful transformation within politically charged environments
DESCRIPTION
TRANSCRIPT
Welcome Robin Cody
Chief Information OfficerSan Francisco Bay Area Rapid Transit District
(BART)
Session Title:Realizing Successful Transformation Within Politically Charged Environments: A Case
Study
2 April 21-23, 2008
Renaissance Washington, DC
Business Advancement Program
$40 Million
Obstacles
5 YearPayback
BusinessCase
New Technology
Old Culture Business Process
KeyStrategies
FinancialScorecard
ChangeExampleCultural
Change
Business Transformation
Topics / Overview
3 April 21-23, 2008
Renaissance Washington, DC
Service Map
4 April 21-23, 2008
Renaissance Washington, DC
BART’S SUCCESSBART’S SUCCESS
Established In 1957 By The California State Legislature
9-member Elected Board Of Directors
First Fully Automated Rapid Transit System In The World
Revenue Service Began In 1972
The 8th Wonder Of The World (Trans Bay Tube)
Top 10 Public Works Projects In The 20th Century
2004 Voted # 1 Transit System In North America
$1.6 Billion Original Investment Equals $15 Billion In Today’s Dollars
TRACK FACTSTRACK FACTS
$577 Million Operating Sources
$191 Million Capital Budget
66.5% Of The Operating Budget Is Labor ($323.5M)
Electric Bill = $40M / Year
60% Of Operating Expenses Comes From Farebox
3,265 Employees (90% unionized)
105 Miles Of Tracks / 43 Station
389,073 Average Daily Passenger Trips
46,392 Station Parking Spaces
1,398 Bicycle Lockers
Train Maximum Speed = 80 MPH
Maximum Train Length = 10 Cars
211 Police Officers
BART’S IMPACTBART’S IMPACT
4 Bay Area County Span
26 Cities Served
BART Carries 50% Of Peak Period, Peak Direction Transbay Traffic
Without BART, Another 75,000 Cars Would Be Added To A.M. Peak Direction Bridge Traffic
One-Third Of People Traveling Between Central Contra Costa And Oakland Use BART!
50% Of Downtown Oakland Workers Use BART
70% Of East Bay Travelers Are Destined For San Francisco And San Mateo Counties
1940’s, 1950’s, 1960’s, 1970’s, 1980’s, 1990’s, & 2000’s1940’s, 1950’s, 1960’s, 1970’s, 1980’s, 1990’s, & 2000’s1940’s, 1950’s, 1960’s, 1970’s, 1980’s, 1990’s, & 2000’s1940’s, 1950’s, 1960’s, 1970’s, 1980’s, 1990’s, & 2000’s
BART’s Evolution
5 April 21-23, 2008
Renaissance Washington, DC
Martinez
To EurekaSanta Rosaand Napa
Davis
Sacramento To Carson
City
Pittsburg/Bay
Point
To Stockton,Bakersfield
Dublin/Pleasanton
BART
Jack London Square
EmeryvilleBerkeley
Richmond
San Jose To Gilroy, Santa Cruz,
Salinas and Monterey
Santa Clara/Great America
Fremont
Warm SpringsExtension
Fremont/Centerville
Millbrae
ColmaSan Francisco
AirportExtension
OaklandAirport
Extension
Suisun/Fairfield
San Joaquin Route
Roseville
Regional Rail
6 April 21-23, 2008
Renaissance Washington, DC
ImplementOperational Standards &
Procedures
Change How We DoBusiness
Eliminate LegacyHardware & Software
EnhanceStaff Skills And Prepare
For Change
Achieve OurCommitments To Our
General Manager
“It’s Hard To Envision The FutureWhen You Haven’t Caught Up To The Past!”
BAP Objectives
7 April 21-23, 2008
Renaissance Washington, DC
Manage TransitDistrict
Manage TransitDistrict
Manage CustomerService
Manage CustomerService
Market & SellServices
Market & SellServices
Manage InformationTechnology
Manage InformationTechnology
Expand TheDistrict
Expand TheDistrict
Operate TrainsAnd Stations
Operate TrainsAnd Stations
Maintain FleetAnd FacilitiesMaintain FleetAnd Facilities
ManageHuman Resources
ManageHuman Resources
Manage Procurement
And InventoryManage Procurement
And Inventory
Manage Funding
And FinanceManage Funding
And Finance
Business Drivers
Business Drivers Old Environment
Inefficient With
Low Productivity!
Old Environment
Inefficient With
Low Productivity!
High CostOf Support
Old ManualProcesses
SystemIntegration
SystemExpansion
RemoteComputing
eBusiness
Lack OfInformation
OutdatedApplications
Lessons LearnedFrom Other’s
Couldn’tSupportDrivers
AdequateResources
CBA’s &Leadership
ProvenTechnology
NegotiatingH / S / M
DeterminingTrue Needs
Finding COTSolutions
Lack ExpertPersonnel
ChampionedFrom Top
ProcurementProcesses
Business Case (ROI)
True Costs& Benefits
Turfism-Silos Old Culture’s
NewObstacles
Facing Our Obstacles
8 April 21-23, 2008
Renaissance Washington, DC
Prepare Focus
BUSINESS ANALYSIS Current State Assessment Analysis of BAP Options Investment and Funding
Options Tactical Planning Software Select Planning 300 Employees – Readiness
Survey
Phase I 2001 - 2002
com
plet
edPhase III 2004 - 2009
Redesign
Design DeployConfigure
SYSTEMS INTEGRATION Change Management Business Process Reengineering Software Configuration And
Implementation Data Migration System Testing Technical Staff Training Post Production Support 10 Employees Helped Develop Problem
Statement 30 Employees Assisted Source
Selection Committee Union Leadership Assisted Source
Selection Committee
Business Transformation
Select /Validate
SOFTWARE SELECTION PeopleSoft – Timekeeping /
Payroll, Human Resources, General Ledger and Financials
MRO – Maintenance & Inventory Management
Optram – Linear Asset Tracking
200 Employees – 2600 Requirements Definitions
80 Employees Assisted Source Selection Committee by participating in Software Demonstrations
Phase II 2003
com
plet
ed
Phased Transformation
9 April 21-23, 2008
Renaissance Washington, DC
*Standish Group Survey - 1999
84%Fail
16%Finish
Why Implementations Fail:
42% Leadership
27% Organizational& Cultural Issues
23% People Issues
Source: Organization Dynamics, Jim Markowsky
4% Technology IssuesOther 4%
ERP / EAMImplementations
Success Rate
10 April 21-23, 2008
Renaissance Washington, DC
Risk of Failure
High
Low
Org
aniz
atio
nal
D
egre
e o
f C
han
ge
HighLow
INCREASED RISK OF FAILURE
Enterprise
Across Verticals
AcrossDepartments
Department Level
Unit Level “Sponsorship” & Good Management May Be Sufficient
Aligned Leadership & Collective Action Are
Required
Championed FromThe Top
11 April 21-23, 2008
Renaissance Washington, DC
Transit & Industry Administrative Best Practices Of“High Performance Organizations”
Reflects Those Functional Activities The Administrative Operations MustDo Well As Core Competencies
Moderate Importance -Can Be Deferred For A Brief Period.20 Criteria
Extreme Importance -Fundamental To Day To Day Administrative Operations.25 Criteria
Limited Importance -Impacts Can Be Delayed.4 Criteria
Document Control/RecordsManagementProject Management &CollaborationCentralized AccessNetwork StandardsEtc.
Marketing/Graphics
Integrated Timekeeping, PayrollAnd HR Mgmt.Integrated Maintenance,Materials, Inventory &Procurement Mgmt.Integrated Financial Mgmt.Etc.
IndustryAssessment
12 April 21-23, 2008
Renaissance Washington, DC
BART Current State Business Process And Applications
Most Of The Fundamental Day-to-day Business Processes And Corresponding Applications Do Not Meet Business Needs And Growth Expectations
Functionally Deficient,But Meets Most CurrentBusiness Needs8%
Does Not Address CurrentBusiness Practices4%
Functionally Deficient,Meets Limited BusinessNeeds88%
Integrated Timekeeping, PayrollAnd Human Resources Mgmt.Integrated Maintenance, Materials, Inventory And Procurement Mgmt.Integrated Financial Mgmt.
BART’sAssessment
13 April 21-23, 2008
Renaissance Washington, DC
INVESTMENT COSTS (out of pocket) 2003 2004 2005 2006 2007 2008 2009 Total
Hardware $2,000,000 $0 $0 $0 $0 $0 $0 $2,000,000Software $2,750,000 $0 $0 $0 $0 $0 $0 $2,750,000Implementation Costs - Includes Functional Implementation, Technical Services, Change Management And Project Management $7,186,000 $10,118,500 $608,000 $0 $0 $0 $0 $17,912,500Training $524,625 $1,704,625 $264,813 $0 $0 $0 $0 $2,494,063
TOTAL $12,460,625$11,823,125 $872,813 $25,156,563
Start Up Steady State
TOTAL COST OF OWNERSHIP
One Time:Hardware $2,000,000 $0 $0 $0 $0 $0 $0 $2,000,000Software $2,750,000 $0 $0 $0 $0 $0 $0 $2,750,000Implementation Services $7,186,000 $10,118,500 $608,000 $0 $0 $0 $0 $17,912,500Training $524,625 $1,704,625 $264,813 $0 $0 $0 $0 $2,494,063Internal Staffing (SOFT COSTS) $1,276,458 $1,629,279 $479,304 $0 $0 $0 $0 $3,385,041
Recurring: Hardware Maintenance $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $600,000
Software Maintenance $0 $495,000 $495,000 $495,000 $495,000 $495,000 $495,000 $2,970,000
Total $13,737,083 $14,047,404 $1,947,117 $595,000 $595,000 $595,000 $595,000 $32,111,604
ConsolidatedCost Statement
14 April 21-23, 2008
Renaissance Washington, DC
FY2003 FY2004 FY2005 FY2006 FY2007 FY2008 FY2009Integrated HR/Payroll/Timekeeping
Employee Self Service 150,280$ 150,280$ 150,280$ 150,280$ 150,280$
Improvement In Timekeeping & Payroll Payroll Run Processing -$ -$ 1,283,531$ 1,283,531$ 2,567,061$ 2,567,061$ 2,567,061$ Improvement In Check Adjustment Process & Accuracy Of Pay-Checks -$ -$ 177,837$ 177,837$ 355,674$ 355,674$ 355,674$
Integrated Financial ManagementInvoice Processing -$ -$ 234,123$ 326,967$ 458,129$ 630,312$ 646,070$
Report Writing -$ -$ 125,627$ 276,380$ 304,018$ 501,631$ 551,794$ Budget Analysis -$ -$ 133,455$ 350,320$ 514,971$ 772,456$ 811,079$
Savings In Cabinet Sq. Footage -$ -$ 57,951$ 91,454$ 128,392$ 169,115$ 214,012$
Integrated Maintenance MgtAverage Labor & Maintenance Cost Per Car Hour -$ -$ -$ 1,402,656$ 2,875,445$ 2,947,331$ 3,021,015$
Integrated Procurement & Inventory Mgt
Contract Processing -$ -$ 257,449$ 589,043$ 1,347,731$ 3,083,609$ 3,527,648$ Capital Allocation -$ -$ 2,424,000$ 2,515,000$ 2,590,000$ 2,670,000$ 2,803,000$
TOTAL BENEFIT -$ -$ 4,844,254$ 7,163,469$ 11,291,701$ 13,847,470 14,647,633$ CUMULATIVE TOTAL BENEFIT -$ -$ 4,844,254$ 12,007,723$ 23,299,424$ 37,146,894$ 51,794,527$
Start-up Steady-State
ConsolidatedBenefits Statement
15 April 21-23, 2008
Renaissance Washington, DC
Phase I
Base Agreement Option A
GL, Payroll,Timekeeping,
Enterprise PortalHuman Resources
Option B Option C
Maintenance &Materials
ManagementFinancials
Phase II
Payroll/Time & LaborTime and Labor
Payroll
Human ResourcesBase Benefits
Benefit AdministrationeProfile / ePay
Resume ProcessingeRecruit / eBenefits
e-DevelopmentPension Admin.
Financial ManagementGeneral Ledger
Enterprise Portal
BAP Program Scope
16 April 21-23, 2008
Renaissance Washington, DC
Phase 1Planning
Project Kickoff
Goals & Objectives
ManagementPlans
Team Structure
Orientation
Training Plans
Project Plan
Infrastructure Plans
Phase 2Design
BPR
Fit/GapAnalysis
Integration Interface Analysis
Functional &Technical
Specifications
PrototypeDevelopment
ChangeAssessment
Phase 3Development
Configuration
Customization
Interfaces
Security
Reports
Life-CycleDevelopment
Unit Testing
Phase 4Testing
FinalConfiguration
ProductionSetup
DataConversion
Testing
UserAcceptance
Training
Go-LiveReadiness
Phase 5Deployment
End UserTraining
MigrateProduction Data
Go-Live
PP SupportProcedures
Phase 6PP Support
ProductionSupport
SystemProcedures
SystemPerformance
PP Procedures
Acceptance Signoff
Program Management – Scope, Schedule, Budget & Quality
Change & Communications Management
WAKE-UPZONE
“Perceived”
“Influence”
Costs
Cost
“Reality”
DANGERZONE
The “Danger” Zone
17 April 21-23, 2008
Renaissance Washington, DC
Business Analysis BPR & To-Be Design Functional Specifications Testing & User Acceptance Training & Change Management Support
Customizations Interfaces / Integration Conversions Infrastructure Design & Development (desktops, applications, OS’, networks, security, etc.) Technical Cut-Over
Communications Change Management Organizational Impact Training Design & Development Training Rollout Labor Relations Strategies
Functional Teams Organizational ReadinessTechnology & Testing
Business ProcessReengineering and
CustomizationSubcommittee
Business ProcessReengineering and
CustomizationSubcommittee
JV / BART TeamsJV / BART TeamsBPRC Subcommittee
BPRC SubcommitteeExecutives
Executives
LegendSystem Integrator
System Integrator
GM / BAP Program ExecutiveDorothy Dugger
GM / BAP Program ExecutiveDorothy Dugger
Executive ManagersExecutive Managers
Program DirectorBeth Tripp
Program DirectorBeth Tripp
Deputy Program DirectorRobin Cody
Deputy Program DirectorRobin Cody
Program Management Team (PMT)Program Manager – Sreeni Malireddy
Program Management Team (PMT)Program Manager – Sreeni Malireddy
MAXIMUS Project ManagerPat Brown
MAXIMUS Project ManagerPat Brown
Nazgol Khamneipur /Bill Carrick / Scot t Wates
Maximus
Amit Kedia
Maximus
Kevin Scott
Maximus
Jane Wong / Michael Kilpatrick /
Ed Dutkowski
BART
Ravi Misra
BART
Randy Franklin
BART
Program Organization
18 April 21-23, 2008
Renaissance Washington, DC
ResultsResultsStrategicQuestionsStrategic
QuestionsElements
Of Change
BusinessProcess
Reengineer’g
What Processes Will Change?How Will They Change?Who’s Impacted?How Will The Transition Be
Accomplished?CommunicationManagement
What Are The Key Messages?When Should They Be
Communicated?What Are The Appropriate
Channels Of Communication?
ChangeManagement
Who’s Impacted By The Technology?
What’s Driving The Change?What’s The Extent Of The
Change?How Do We Change Behaviors?
WorkforcePlanning
How Will The Positions Change (Number, Type & Description)?
What Capabilities Are Required?
How Will The Workforce Be Re-Tasked?
Training
Who Should Be Trained?What’s The Content?
How Will Effectiveness Be Measured?What Are The Delivery Methods?
StakeholderManagement
How Will The Relationships Be Managed?When Should They Be Engaged?
Who Are The Stakeholders?How Do We Communicate With Them?
OrganizationalReadiness
19 April 21-23, 2008
Renaissance Washington, DC
What
As Is’As Is’
BPRBPR
Fit / GapFit / Gap
To Be’sTo Be’s
ContractRequirements
ContractRequirements
UpdateRequirements
UpdateRequirements
UpdateRequirements
UpdateRequirements
GapBPRC
Approved
Declined
Fit
1
2-1
2
4
4-1
5
UpdateRequirements
UpdateRequirements
How
6Change Impact
Assessment
Change ImpactAssessment Org Impact
Assessment
Org ImpactAssessment
Update JobDescriptions
Update JobDescriptions
Develop DeskProcedures
Develop DeskProcedures
Training MaterialDevelopment
Training MaterialDevelopment
7
8
9
8-1
Labor RelationsStrategy
Labor RelationsStrategy
7-1
ROIAnalysis
ROIAnalysis
Enterprise Perf.Metrics (EPM)
Enterprise Perf.Metrics (EPM)Performance
Metrics
PerformanceMetrics3
3-1
3-2
BPR & CMFramework
20 April 21-23, 2008
Renaissance Washington, DC
Technology
Strong Technical ArchitectureIntegrated SolutionOpen Source Standards
People
Change Management Organizational ReadinessTraining
Process
Business Process Re-engineeringLeverage Industry Best PracticesLeverage Software Best Practices
Structure
Improves Process / ConsistencyPromotes AccountabilityEliminates Duplication
Metrics
Qualitative Not SubjectivePlatform For CollaborationDescribes The “Cultures” Values
Programs
Explains The “What” and “Why”Not A “Spectator” SportAllow For Grieving
Process And TechnologyProcess And TechnologyEnable Capabilities!Enable Capabilities!
Technology And PeopleTechnology And PeopleImprove Effectiveness!Improve Effectiveness!
People And ProcessPeople And ProcessUnleash ROI!Unleash ROI!
Politics
Understanding Your BoardUnderstanding Your LeadershipUnderstanding Your Labor
People
Change Management Organizational ReadinessTraining
Policies
Strategic PlansManagement ProceduresOperating Rules
Cultural Change
21 April 21-23, 2008
Renaissance Washington, DC
Keep Bargaining Units Separate
Negotiate
Make Everything Transparent
Include Unions In Decision Making
Don’t Let The Unions Divide Your Board
Inform Your Board Often And Fully
Beneficial Practice
Establish Your End-Game
Involve Labor Relations Early & Fully
Identify Your Biggest Impacts
Mutual Consent Clause
Know When And What To Communicate
UnionUnionLeadershipLeadership
UnionUnionLeadershipLeadership
Don’t Play New Game By Old Rules
Beware Of Bureaucracy
Don’t Try To Control The Uncontrollable
Don’t Pick The Wrong Battles
Don’t Choose Your Own Pace Of Change
Don’t Expect Someone Else To Reduce Your Stress
Spend Your Energy On Solutions
Embrace The Future / Promote The Vision!
Understand The Rationale For Change
Try To Eliminate Uncertainty
Decide To Change / Commit
Expect Stress To Rise
ManagementManagementManagementManagement
The Sides OfResistance
22 April 21-23, 2008
Renaissance Washington, DC
100’s OfSpecial Pay
Rules
100’s OfSpecial Pay
Rules Paper TimeSheets
Paper TimeSheets
5 CollectiveBargaining
Agreements
5 CollectiveBargaining
Agreements
No ControlsNo Controls
ClericalData Entry
ClericalData Entry
No ManagementResponsibility /
Visibility
No ManagementResponsibility /
Visibility
Example: AutomatingTime & Labor Rules
23 April 21-23, 2008
Renaissance Washington, DC
Management Makes Big Ass Problems (BAP) for All
Several of the proposals that BART Management wants to implement through BAP, willresult in greater inefficiencies. In response, we have proposed several common sensesolutions to BART Management regarding such issues as pay stubs, job duties, timeclocks, etc.
Each time we present a possible solution to these issues, BART Managementsystematically ignores or minimizes our concerns. These continuous refusalsby BART Management to find common sense solutions will force us to takewhatever actions are necessary to resolve our concerns.
We, the undersigned SEIU 790 BART Chapter workers, demandthat BART Management agree to the following:1. No transfer of duties to inappropriate classifications2. Maintain paper paycheck stubs for all employees3. Do not expand use of time clock
AutomatingTime & Labor Rules
24 April 21-23, 2008
Renaissance Washington, DC
Payroll Reviews AndBatches For Data Entry
Payroll Reviews AndBatches For Data Entry
Supervisor VerifiesCard For Correctness
Supervisor VerifiesCard For Correctness
Tries To Resolve WithEmployee (Vacation, SickHoliday, OT, etc.)
Employee ReviewsCheck For Accuracy
Employee ReviewsCheck For Accuracy
If Over – Keeps; UnderRequests AdjustmentAnd Manual Check98% Underpaid
Timekeeper AddsTime Reporting Codes
Timekeeper AddsTime Reporting Codes
Prepares Total HoursBy Earning Code AndWrites On Back Of Card
Payroll Is Run,Direct Deposits / Checks
Payroll Is Run,Direct Deposits / Checks
Direct Deposits Sent,Checks PrintedAnd Distributed
Supervisor VerifiesTime Card
Supervisor VerifiesTime Card
Approves OrReturns To TimekeeperFor Correction
Timekeeper Signs-OffOn Timecard
Timekeeper Signs-OffOn Timecard
RLDS ChargesEntered Manually.Cards Batched, HeadersCreated
Data Entry ServiceCreates Tapes For Input
Data Entry ServiceCreates Tapes For Input
Cards CourieredTo / From IT For PayrollProcessing
EmployeePunches Manual
Time Clock
EmployeePunches Manual
Time ClockPayroll Adjusts
Checks (800 / month)
Payroll AdjustsChecks (800 / month)
If Manual CheckCreated, Start TheProcess Over Again
Original T&L / PayrollProcess Steps
25 April 21-23, 2008
Renaissance Washington, DC
Supervisor ApprovesPayable Hours
Supervisor ApprovesPayable Hours
Employee ReviewsCheck For Accuracy
Employee ReviewsCheck For Accuracy
Payroll Is Run,Direct Deposits / Checks
Payroll Is Run,Direct Deposits / Checks
Direct Deposits Sent,Checks PrintedAnd Distributed
Time AdministrationIs Processed
Time AdministrationIs Processed
System Check Exceptions;Wage / Time Types, RatesShift Differentials, etc
EmployeeSwipes Time Clock
EmployeeSwipes Time Clock
Payroll AdjustsChecks (100 / month)
Payroll AdjustsChecks (100 / month)
New T&L / PayrollProcess Steps
26 April 21-23, 2008
Renaissance Washington, DC
Better Accountability Of Absences And Reported Time
Better Data Going In / Out Of System
Integrated Time & Labor And Payroll System
Less Time Errors And Less Time Abuse
90% Less Payroll Errors And Adjustments
26 Payrolls Instead Of 54
Trained 3200 People Eliminated 52 Jobs with “No Layoffs” 50+ Grievances & No Lost Arbitrations
Checklist Of NewProcess Results
27 April 21-23, 2008
Renaissance Washington, DC
Phase IIPhase II
Finance / Supply ChainProjections
Phase IPhase I
Time & LaborPayroll / HRIS
ROIROI
Business Case$51,794,527
Projected CostProjected Cost
Business Case$25,156,563
Added CostsTo Improve
Success Rate
Added CostsTo Improve
Success Rate
Total ExpectedCost
$40 Million
District Added: $5M for PM
$5M for Training$5M Backfills
Goal: RealisticAnd Achievable
Goal: RealisticAnd Achievable
7 Year ROI2 Year Steady
5 Years OfImprovements
Conservative
Exec Workshop
GM Buy-In
Reduce LaborBy 1% ($3.2M)Equals: $8.1M
Reduce LaborBy 1% ($3.2M)Equals: $8.1M
Projected: 70%Received: 67%Equals: $4.9M
47 Positions
Ops: OT (18%)
Ops: (3%)
In Sum:Potential Of$12.4M/yr.
In Sum:Potential Of$12.4M/yr.
Inv. Turns: 30%AP: 25%
IT Budget: 25%
Inv: $2.8M
AP: $.7M
IT: $.8M
IntermediateFinancial Scorecard
28 April 21-23, 2008
Renaissance Washington, DC
Leadership Creates The VisionLeadership Aligns OrganizationLeadership Minimizes The Risk
Better Resource UtilizationAnticipates Risks & MitigationHigher Quality Product
Know Your End GameUnderstand the ROIEstablish Expectations
Inclusion Brings “Buy-In”Provides Needed ExpertiseGet Your Enemy In The Tent
Negotiated SW AgreementsDrafted SI RFPNegotiated SW Agreements
Defines The Playing FieldFreeze Vacant PositionsKeep Information Transparent
It Is NOT A Technology ProblemMust Change People’s BehaviorEstablish Accountability
The Steps Of Our“Key” Strategies
LeadershipLeadership
Business CaseBusiness Case
StakeholdersStakeholders
Get HelpGet Help
Understand LaborUnderstand Labor
Project ManagementProject Management
Change ManagementChange Management
29 April 21-23, 2008
Renaissance Washington, DC
Phase I
Base Agreement Option A
GL, Payroll,Timekeeping,
Enterprise PortalHuman Resources
Option B Option C
Maintenance &Materials
ManagementFinancials
Phase II
FinancialsReceivables / Payables
Asset ManagementPS EPM Analytics
BudgetingGrants / Projects
Purchasing eProcurement
MaintenanceWork Orders / RequestsPreventive Maintenance
Job Plans / LaborEquipment Tracking Project
ManagerMobile MAXIMO
Optram – Linear Assets
MaterialsPurchase Requisition’s
Purchase Order’sReceiving / Invoicing
Inventory ControlStorerooms / Items
IssuesTransfers
BAP Phase IIProgram Scope
30 April 21-23, 2008
Renaissance Washington, DC
Communications
Training
Change Management
Organizational Readiness
Better Project Outreach
Dedicated Labor Relations
Managers Involvement
Phase II Improvements
People – BART & SI
Heavy Staff Turnover
Contract Resources
Project Team Quality
Screened Leads
Minimize Turnover
SI Employees (Quality)
Phase II Improvements
Implementation Methodology
Project Plan Ownership
Late Deliverables
Implementation
Project Management Plan (PMP) Implementation
Phase II Improvements
Lessons LearnedTo Date
31 April 21-23, 2008
Renaissance Washington, DC
More Efficient Business Processes More Productive Workforce Integrated, Flexible and Expandable Systems Technology Investment Aligned With Business Objectives, Such
As: Labor Improvements Inventory Reductions Increased Fleet Availability Material Cost Reductions Purchasing Cost Reductions
Strategy
Process Organization
Exec
utio
n &
Perfo
rman
ce Metrics & G
oals
Rolls & AccountabilitySkills & Capability
ResultsResults
Leaner, Meaner Organization Work Smarter, Not Harder
What The Phase IIFuture Holds
32 April 21-23, 2008
Renaissance Washington, DC
“BAPtized” Union’s
33 April 21-23, 2008
Renaissance Washington, DC
Thank You!Robin CodyChief Information OfficerSan Francisco Bay Area Rapid Transit District (BART)