RECONSTRUCTION OF SAINTE MARIE BRIDGE ON B9 ROAD AT BAIE JACOTET

Upload: others

Post on 27-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

RECONSTRUCTION OF SAINTE

MARIE BRIDGE ON B9 ROAD AT

BAIE JACOTET

Page 2: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

1 | P a g e

Contents 1.0 Background ....................................................................................................................................... 2

2.0 PROJECT OBJECTIVES ........................................................................................................................ 2

3.0 PARTIES INVOLVED............................................................................................................................ 2

4.0 PROGRAMME SCHEDULE .................................................................................................................. 4

5.0 LIAISON WITH AUTHORITIES: ............................................................................................................ 4

ANNEX I ................................................................................................................................................... 5

PHOTOGRAPH BEFORE IMPLEMENTATION OF PROJECT ........................................................................ 5

ANNEX II- PHOTOS DURING CONSTRUCTION OF BRIDGE ....................................................................... 8

Page 3: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

2 | P a g e

ROAD DEVELOPMENT AUTHORITY

1.0 Background The project consists of the design and construction of Ste Marie Bridge at on B9 Road at Baie Jacotet, and upgrading/widening of existing road over an approximate length of 400m. The Rehabilitation of the Ste Marie is being undertaken by the Contractor; Rehm Grinaker Co. Ltd.

2.0 PROJECT OBJECTIVES • Improve the road geometry, • Improve level of service and • Enhance the safety for vehicles and pedestrians along the bridge. • Provide unrestricted flow of river into the sea.

The scope of works is as follows:

• Demolition of the existing structure and reconstruction of a reinforced concrete bridge/culvert of approximate length of 45 m to provide unrestricted flow of river into the sea.

• Upgrading and tie-in of approximately 250 m of B9 on both sides of the bridge. • Upgrading and extension of existing drains and retaining structures. • Construction of roadside footpaths, drains and masonry walls • Provision of handrails, street lighting, cat eyes, traffic signs … • A.O.B

Page 4: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

3 | P a g e

3.0 PARTIES INVOLVED

Employer: Road Development Authority (RDA)

REPRESENTATIVES:

Mr S.Jankee- Divisional Manager(Maintenance)

Mr A.Nubeebux- Ag Divisional Manager(Maintenance)

Mr Munoruth- Senior Manager (Maintenance)

Mr A.Kheejoo- Technical Officer

Mr M.Z.Darbarry- Trainee Engineer

Main Contractor: Rehm Grinaker Co Ltd

REPRESENTATIVES:

Mr A.Ramdin-Operations Executive

Mr S.Hosany-Contractor’s Representative/S.Site Manager

Mr R.Gopaul- Site Agent

Mr F.Rahimum- Topographical surveyor

Mr K.Ramdeehul- Health and Safety Officer

Mr B.Ellapah- Quantity Surveyor

Sub-Contractor: Numelec Ltd (Street Lighting)

Bridge Design Engineer: SJPCE Ltd

Page 5: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

4 | P a g e

4.0 PROGRAMME SCHEDULE Date of Award: 17TH July 2018 Project Starting Date: 31ST January 2019 Project Completion Date: 25TH April 2020 Project Duration: 450 days (15 months)

5.0 LIAISON WITH AUTHORITIES: Duration liaising with authorities: 9 Months

Page 6: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

5 | P a g e

ANNEX I

PHOTOGRAPH BEFORE IMPLEMENTATION OF PROJECT

Page 7: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

6 | P a g e

PROJECT LOCATION AND SITE PLAN

Photo of Bridge before implementation of project

Page 8: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

7 | P a g e

Existing and new bridge setting

Page 9: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

8 | P a g e

ANNEX II- PHOTOS DURING CONSTRUCTION OF BRIDGE

Page 10: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

9 | P a g e

PILING WORKS ON SITE

PLACING OF STEEL REINFORCEMENT FOR ABUTMENT WALL

Page 11: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

10 | P a g e

PILE CAPS BETWEEN ABUTMENTS

REINFORCEMENT FOR TRANSVERSE BEAMS

REINFORCEMENT FOR ABUTMENT WALL

REINFORCEMENT LINKING ABUTMENT TO PILE CAP AND TRANSVERSE BEAMS

Page 12: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

11 | P a g e

PLACING OF STEEL REINFORCEMENT FOR TRANSVERSE BEAMS

REINFORCEMENT FOR TRANSVERSE BEAMS

Page 13: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

12 | P a g e

LOWER PART OF TRANSVERSE BEAM CASTED FIRST

UPPER PART OF TRANSVERSE BEAM TO BE CASTED LATER WITH LONGITUDINAL BEAMS

Page 14: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

13 | P a g e

Laymen using vibrators for compaction of concrete in the casting of bridge decks

Page 15: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

14 | P a g e

Beam decks have been casted

Page 16: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

15 | P a g e

Pre cast slabs to be laid across beam decks

Page 17: RECONSTRUCTION OF Sainte MARIE BRIDGE ON B9 ROAD AT …rda.govmu.org › English › Projects › Documents › ste marie... · 8/13/2019  · The project consists of the design and

16 | P a g e