ref guide loans construction

Upload: kphillipsbiz8996

Post on 14-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Ref Guide Loans Construction

    1/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Introduction This reference guide provides information and step-by-step instructions forhow to submit construction loan applications and what happens after the

    application has been approved.

    Responsibility The Business Banker / Small Business Banker is responsible for submittingclients applications for constructional loans, and for certain steps in the

    closing process. In addition, the Banker should understand the entire process

    to enable him/her to answer clients questions.

    1

  • 7/30/2019 Ref Guide Loans Construction

    2/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Terminology The table below defines terms you should know to assist your client insubmitting an application for a construction loan.

    Term Definition

    AIA DrawRequest

    An AIA draw request is submitted on an AIA DocumentG702 form and summarizes the original contract sum (+/-)

    any change orders and the total completed to date. Thisform is extremely useful when monitoring a constructionproject and should be required for all constructionprojects.

    AIA Schedule

    of Values

    AIA stands for the American Institute of Architects, of

    which they drafted a set of uniform documents to be used

    by general contractors for construction projects. An AIA

    Schedule of Values is the detailed contractor budget that

    is included in the construction contract. This term can be

    used synonymously with detailed Budget.

    As-Built (Final)

    Survey

    Useful to identify sidewalks, parking lots, and other

    completed improvements. This survey is conducted at the

    end of the project.

    Contractor &

    Borrower

    Signed

    Inspection

    To avoid disputes on work performed, both parties should

    certify they are ready for inspection by signing the draw

    request. We will then fund into the borrowers

    construction DDA account and borrower will write a check

    to the contractor.

    Fund on Work

    in Place

    Inspections by a 3rd party inspector are used to ensure

    that the bank is only funding on work actually completed.

    The 3rd party inspector will use the original AIA schedule of

    values to confirm the status of completion for individual

    items and recommend funding if completed. Note that the

    AIA form is amended throughout the project to reflect all

    change orders and their associated cost.

    General Insurance coverage usually with $1MM in coverage for

    2

  • 7/30/2019 Ref Guide Loans Construction

    3/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Liability

    Insurance

    loans of $2MM and less. Coverage of $2MM per

    occurrence and $5MM aggregate for jobs between $2MM -

    $5MM. Insurance company providing coverage must have

    a minimum rating of A

    Investor Real

    Estate

    A real estate project that is built and leased by investors

    to generate a stream of lease/rental income. Typically

    includes multi-family, multi-tenant office, or leased retailprojects.

    Lien Period The period in which to file a lien on a job where they were

    not paid. The retainage period is never shorter than the

    lien period in case someone files a claim. State law allows

    that if the construction contract is recorded at the

    beginning of the job and if at the conclusion of the job a

    certificate of completion is then filed as well, the lien

    period can be reduced from 72 days to 30 days.

    Owner

    Occupied

    Real-Estate loans which are underwritten based on

    the operating revenue of the owner-occupied

    business that occupies the banks collateral.

    Slab Survey Useful to ensure the building is not built in the wrong

    place and shows the position of the slab in relation to

    property boundary, easements, etc.

    Workers

    Compensation

    Coverage

    Insurance coverage provided by the contractor with

    amount set by state statute. Insurance company providing

    coverage must have a minimum rating of A

    3

  • 7/30/2019 Ref Guide Loans Construction

    4/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    ConstructionLoans vs.ConventionalLoans

    Construction loans are Non-Revolving Lines of Credit that allowfor interest-only payments during construction. Typical termsare 24 months and are co-terminus with the duration of theconstruction/renovation timeframe.

    Conventional loans specifically deal with residential financing.

    4

  • 7/30/2019 Ref Guide Loans Construction

    5/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Characteristicsof aConstructionLoan

    The following are the characteristics of typical construction loans:

    Available for owner-occupied and investor real estate projectsincluding all projects where the take-out is SBA 504 or 7A.

    Common types of construction loans are for (i) expansion ofowner-occupied business with the construction of a new

    building; (ii) renovations to existing owner-occupied businesses;and (iii) leasehold improvements for tenant space.Construction of an IRE property is less common in the currenteconomic climate and is handled on a case by case basis.

    Loan amounts follow the Maximum Credit Exposure guidelinesfor Business Banking Relationships and are typically $3,000M. Regional MCE approval is required for any loanamounts >$3,000M.

    Construction loans are Non-Revolving Lines of Credit that allowfor interest-only payments during construction. Typical terms

    are 24 months and are co-terminus with the duration of theconstruction/renovation timeframe.

    All construction loans must convert to a term loan uponconstruction completion. Terms offered are 5, 7, or 10 yearswith amortizations up to 20 yrs. In special cases, higheramortizations are available. Please consult with your MCE fordetails on available loan structures.

    Relationship based pricing is driven by deposits and ancillarybusiness.

    Note: The primary repayment source on the loan drives theclassification of a construction loan as either owner-occupied orinvestor. Owner-occupied real estate loans are underwritten basedon the operating revenue of the owner-occupied business thatoccupies the banks collateral. Investor real estate loans areunderwritten based on the 3rd party lease income of the property thatis the banks collateral. As such, each has their own set ofunderwriting guidelines. Please consult with your MCE when youreceive a construction loan request to ensure proper classification forunderwriting and loan structure purposes.

    5

  • 7/30/2019 Ref Guide Loans Construction

    6/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    6

  • 7/30/2019 Ref Guide Loans Construction

    7/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Factors toconsider whendevelopingTarget Zonefor potentialloancustomers

    Higher overhead cost compared to what we earn and higher inrisk.

    Only profitable to the bank if we obtain; a) the relationship ofthe owner and all of their business, b) the permanent loan, c)more in fees; and d) a satisfactory interest rate.

    Deposits and ancillary business (i.e. Treasury Management&Merchant Services) factor into pricing the loan, but do notmitigate the construction risk.

    An MCE approved Loan Pricing Model (LPM) will factor in: a) theconstruction risk; and b) the overall banking relationship toensure that an acceptable Risk Adjusted Return on Capital(RAROC) is generated from the fees and interest rate charged.

    7

  • 7/30/2019 Ref Guide Loans Construction

    8/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    FactsRegardingConstructionLoans

    Underwriting LTV (Loan to Value) & LTC (Loan to Cost)

    o Owner-Occupied loans, where the primary repayment

    source is the operating income of the owner-occupiedbusiness, allow for loan amounts up to the lesser of 80%of cost or 80% of appraised value subject to supportableloan amount derived from cash flow

    o

    IRE property types where the source of repayment is the3rd party lease income of the property are subject to IREand CRE underwriting guidelines which are morerestrictive than owner-occupied guidelines with LTV/LTCof 75%. Please consult with your IRE RelationshipManager for details on IRE loan structures.

    Equity

    o Explain to borrower that their equity can be in land value

    or cash, and equity is used first. This delays the need toborrow during the project, saving the borrower interestexpense.

    o The land value is determined by the original cost if the

    property has been owned 3 years or less.

    Note: Any cash equity not used for the project at the loan closingmust be deposited into a Capital One bank account with a hard hold.Capital One does not allow staged equity. The final equityrequirement cannot be determined until receipt of the final budgetand appraisal.

    8

  • 7/30/2019 Ref Guide Loans Construction

    9/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    ApplicationRequirements

    In addition to the standard application requirements for a loanrequest, the following items are useful if they can be obtained duringthe initial meeting with the borrower:

    o Description of Proposed Improvements

    o Detailed Budget

    o Status of Building Permits, Plans and Specs

    o Name of the Contractoro Current Debt on Property (if any)

    o Expected Equity Contribution, Requested Loan Amount

    and Terms

    The IRE construction monitoring team will provide a detailed list of allitems that will be needed to close the loan. Please consult with themaccordingly.

    Note: You must submit a request for the construction and thepermanent loan as you would for any other standard loan approval.For owner-occupied real estate construction loans, a TIP Form, IRE

    preliminary budget review, and MCE approval is required prior tosubmitting to the BBC for underwriting. If the loan is an IREconstruction loan, then an IRE underwriting memo will be required aswell. The banker, in conjunction with MCE should engage IRE asneeded. Approval of the permanent loan is required to approve theconstruction loan.

    9

  • 7/30/2019 Ref Guide Loans Construction

    10/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Stages in theOverallProcess

    Once the Banker submits the application package on behalf of the client, the

    following is a high level overview of the process:

    Stage Description

    Underwriting The underwriting team reviews the submitted package,

    requests any necessary additional documents orinformation and underwrites the project.

    Pre-Closing Once the credit is approved, it moves to the Construction

    Team who prepares the commitment letter and

    coordinates surveys and other necessary pre-closing

    work.

    Closing Appraisals, environmental report, and all other necessary

    reports, contracts, and inspections are coordinated and

    conducted. Documentation is prepared and the loan isclosed with the client.

    Post Closing The Construction Team monitors the construction,

    requests inspections and coordinates draws.

    Term Out The construction loan is converted to a permanent loan.

    10

  • 7/30/2019 Ref Guide Loans Construction

    11/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    TheUnderwritingProcess

    During the Underwriting Process, the following steps are completed:

    11

    Step Action

    1 The Underwriter reviews the application package and

    contacts the banker and / or the client to obtain any

    missing documentation.

    2 The Underwriter determines if the project is Owner Occupied or

    Investment Real Estate (IRE).

    If Then

    Owner

    Occupied

    Loan capacity is determined by the cash

    flow of the operating entity and guarantor

    support. The Underwriter continues to

    underwrite and makes a credit decision.

    IRE The Underwriter will ask the borrower for

    additional information to determine the loan

    capacity. The Underwriter will share the

    information with the IRE Team, who reviews

    the project information and generates an IRE

    memo to assist with the credit decision.

    3 The Underwriter completes the underwriting process and

    makes a credit decision (decline, approve, counter-offer)

    which is communicated to the Market Credit Executive

    (MCE) and the Banker.

    4 The Banker communicates the decision to the client.

    If Then

    Approved Once the client accepts, the Banker will work

    with the CSS to prepare a commitment letter

  • 7/30/2019 Ref Guide Loans Construction

    12/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    The Pre-ClosingProcess

    During the Pre-Closing Process, the following steps are completed:

    IREs construction team: Receives the approval Assists with preparing the commitment letter Works with Credit Support Specialist to gather/review all required

    docs for closing Engages 3rd party inspector for upfront plan and cost review Engages appraiser for appraisal report based on as complete

    value.

    Assists with obtaining environmental review (i.e. Phase I or

    Environmental Checklist.

    The ClosingProcess

    During the Closing Process, the following steps are completed:

    Banker engages legal counsel and obtains closing checklist from LAD.All documentation that is provided in the closing checklist needs to bereviewed and approved by LAD and banks legal counsel prior toclosing.

    All construction documentation is submitted to IRE for review andapproval by 3rd party inspector.

    Once all documentation is reviewed and approved, the loan is ready

    to close.

    The PostClosing &Draw Process

    During the Post-Closing & Draw Process, the following steps are

    completed:

    IRE Construction Team monitors the construction project to

    completion to ensure that it is on time and within budget.

    The Term-OutProcess

    During the Term-out Process, the following steps are completed:

    IRE in conjunction with LAD & the Banker close the Construction Loaninto Permanent Loan.

    Roles andResponsibilities

    The following are the roles and responsibilities of all parties who are needed

    to close a construction loan:

    12

  • 7/30/2019 Ref Guide Loans Construction

    13/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Role Responsibility

    IREs

    Construction

    Monitoring

    Team

    is to guide the Business Banker and Borrower

    throughout the construction process to ensure

    a complete project that is on time and within

    budget. Prior to approval, IREs construction

    monitoring team should be engaged as soon

    as a request for construction financing isreceived so they can assist with the

    preliminary budget review needed for

    underwriting. Post closing, the IRE

    construction monitoring team is responsible

    for administering all construction advances

    and assists in getting required documentation

    for the Term Out (Permanent Loan).

    IRE

    Relationship

    Manager

    is required to provide an IRE underwritingmemo to the BBC for all investor real estate

    construction loans where the primaryrepayment source is 3rd party lease income ofthe property. An IRE underwriting memo isnot needed for owner-occupied constructionloans where the primary repayment source isthe operating revenue of the owner-occupiedbusiness.

    LAD (Post

    Approval)

    is to provide the Banker & CSS a closingchecklist of items needed. LAD is then

    responsible for reviewing all of the requireddocumentation and letting the Banker / CSSknow if additional information is needed.LADs approval of all documentation is neededprior to closing. Post closing, LAD worksclosely with the IRE construction monitoringteam to advance funds in accordance withbank policy until substantial completion andclose the Term Out..

    Business is to act as the quarterback on the

    13

  • 7/30/2019 Ref Guide Loans Construction

    14/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Banker transaction to keep the borrower informed on

    the status of the request and gather the

    needed information. Business Banker is also

    responsible for engaging the attorney,

    ordering appraisals & environmental reports,

    tracking closing costs, and closing.

    Client/Borrower

    is to provide the information needed tosuccessfully underwrite and close the

    transaction. Open lines of communication are

    key to getting the loan closed in a timely

    manner.

    Attorney Attorneys Role is as follows:

    a) Review all due diligence items;b) Prepare the loan documents for thebank (as required);c) Revise and review any in-house

    prepared documents;d) Review and negotiate the titlepolicy;e) Review the survey and allcertificates of public records that wereordered to check for priorencumbrances on the property to bemortgaged, and;f) Assist in the coordination of the

    closing process.

    Credit

    Support

    Specialist

    (CSS)

    is to draft the commitment letter (IRE canassist as needed) from the Credit ApprovalMemo (CAM), gather all required closingdocumentation per LADs closing checklist,and coordinate loan closing between LAD,funding department, and attorney.

    14

  • 7/30/2019 Ref Guide Loans Construction

    15/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Construction

    Document

    Checklist

    The following items are standard construction documents that willneed to be reviewed and approved by the banks 3rd party inspectorprior to closing:

    A fixed price contract to include a schedule of values, outline of thedraw schedule, progress payments, duration of the project andretainage

    A final loan budget that determines borrowers final equityrequirement at closing

    Building plans and specifications All appropriate licenses and necessary permits Zoning Certificates and Utility Letters (as applicable) Proof (Certificates) of Insurance (builders risk [during construction],

    workers compensation, multi-peril hazard, general liability, and flood[if applicable])

    Geotechnical Soils Report (as applicable) Other items as required for each project.

    Note: The above list is not comprehensive in nature and is presentedas an overview of the types of construction documents that will beneeded. Each construction project is different and additionaldocumentation may be needed depending on the specifics of the

    project.

    15

  • 7/30/2019 Ref Guide Loans Construction

    16/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    AppraiserRequirements

    The CSS in conjunction with the banker will order the appraisalrequest through RETECHS to obtain an appraisal report that providesan as complete value. The appraiser will need the followingdocuments:

    A full set of plans and specifications, a legal description of theproperty, a copy of the construction contract, and the final budget

    to begin the appraisal process.o Plans and Specs (a legible 11 X 17 copy or pdf file from the

    engineer/architect will usually work for the appraiser)o Draft or Final Contract (prefer to use the final contract)

    o AIA Schedule of Values (i.e. Detailed Budget).

    The appraiser will provide us with a turnaround time, which beginsfrom the date the appraiser receives all of the necessary documents.

    DrawChecklistsPost closing, IRE will work with the borrower, the contractor, and LADto make sure that the bank is in receipt of all required documentationneeded for each draw advance. Please consult with your IREconstruction monitoring team for the complete draw checklist whichincludes, but is not limited to the following items:

    o AIA draw request signed and approved by borrower

    o 3rd party inspection report approving the amount to fund

    o Proof of builders risk and general liability insurance(s)

    16

  • 7/30/2019 Ref Guide Loans Construction

    17/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    FAQs Frequently asked questions and their respective answers follow.

    Question Answer

    What is the primary

    risk for all

    construction loans?

    The primary risk of all construction loans is the

    non-completion of construction. To mitigate that

    risk, the Banks Investor Real Estate Groupmonitors all construction projects for owner-

    occupied and investor real estate projects. IRE

    provides a monthly report on the status of the

    construction portfolio to Bank Risk Management,

    the SBB credit officers and the MCEs.

    What does prepaid

    equity include?

    Prepaid equity often includes the land purchase,

    site improvements (like clearing and fill), A&E,

    permitting fees, etc. When calculating the

    borrowers cash requirement at closing,

    verifiable prepaid items can be deducted from

    the borrowers cash injection since these are sunk

    costs.

    Why does the bank

    require equity on

    construction loans?

    Equity is required to ensure that there is enoughcash available to complete the project. Equity isalways funded first before any loan proceeds areadvanced. The amount of equity required isalways based on the total project cost. Totalproject costs include land, hard costs(improvements), and soft costs.

    Total Project Costs Equity = Loan Amount

    Equity + Loan Amount = Total Project Costs

    What are change

    orders?

    Change orders occur in most construction projectsas the borrower may add (increase costs) ordeduct (decrease costs) items from the originalplans. Also, unforeseen costs related toconstruction delays or other extraordinary events,can increase costs. All change orders must beapproved by the bank.

    17

  • 7/30/2019 Ref Guide Loans Construction

    18/19

    Reference Guide for Submitting & ClosingConstruction Loans

    For Business Banking & Small Business Banking

    Who can be the

    inspector in the

    construction process?

    IRE will engage a licensed, 3rd party real estate

    inspector to perform an initial plan/cost review,

    and to monitor the construction progress. All

    inspectors need to be a neutral, 3rd party to the

    project to ensure that there is no bias. The bank

    will not allow the borrower or an agent of theborrower to monitor the project. IRE has a list of

    bank approved inspectors.

    The construction

    phase seems

    complicated; how

    can I get this done

    efficiently?

    The Investor Real Estate construction monitoring

    team will guide you through the entire process.

    The IRE construction monitoring team will answer

    questions that your or your borrower may have to

    ensure that the project is completed on time and

    within budget. Leave it to the experts.

    18

  • 7/30/2019 Ref Guide Loans Construction

    19/19

    This is the header title

    This is a subsequent page

    Subsequent pages have a different header and top page margin. It is vitally important to retain the

    hard Section Break (Next Page) between the first page and subsequent pages of this document.