AMENDMENT No.1 Name of Work : Tender no. RITES/ CO/B&A/EE/PU/ VRF/E-3/2010 for the work of “Supply, installation, testing and commissioning of VRF (Variable Refrigerant Flow) Air Conditioning System work under 11th Plan Building Projects for U.G.C, School of Tamil, Humanities & Social Science, Centre for Electronic Media & Mass Communication, Examination Wing, Library and MISAARC Buildings at Pondicherry University, Puducherry. Tender No .:- Tender no. RITES/ CO/B&A/EE/PU/ VRF/E-3/2010. Table No- 1:- Pertaining to BOQ Part-II of Tender Documents S. No. Reference/ Page No./Clause No. As per tender Document Amended and to be read as:- 1 BOQ/ Page No -11 & 12 / Item 1 (a)/ (i) to (xii). Cooling & Heating Cooling only. 2 BOQ/ Page No -12 / Item 1 (b)/ (vi) & (vii). Hi Wall Type : 2.5 TR Hi Wall Type : 3.0 TR Ductable Type : 2.5 TR Ductable Type : 3.0 TR 3 BOQ/ Page No- 13 / Item 1 (c). Supply, Installation, testing & commissioning of TFA ( Fan Section ) units with high static 30 mm Minium Ceiling mounted Ductable unit capacity with Electrical Isolater switch below Supply, Installation, testing & commissioning of TFA ( Fan Section ) units with high static 30 mm Minimum Ceiling mounted Ductable unit capacity with Electrical Isolator switch below but without coil. 4 BOQ/ Page No-14 / Item 1 (d)/ Y-Joints/ Unit. Nos. LOT 5 BOQ/ Page No- 11 & 12 / Item 1 (a). Outdoor Units Bidder has to quote against the specific BOQ item only. The capacities mentioned are the minimum required capacity. However, the bidder can offer the next higher size unit (if the required capacity unit is not manufactured by them) against that particular item without any extra cost. 6 BOQ/ Page No- 11 & 12 / Item 1 (b). Indoor Units Bidder has to quote against the specific BOQ item only. The capacities mentioned are the minimum required capacity. However, the bidder can offer the next higher size unit (if the required capacity unit is not manufactured by them) against that particular item without any extra cost. 7 BOQ/ Page No- 14/ Item 1 (e). Remote Controller For each common hall area, only one group controller shall be required. Bidder has to quote against the specific BOQ item only. However, the exact requirements in this regard shall be finalized at

Upload: trinhliem

Post on 20-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

AMENDMENT No.1

Name of Work : Tender no. RITES/ CO/B&A/EE/PU/ VRF/E-3/2010 for the work of

“Supply, installation, testing and commissioning of VRF (Variable Refrigerant Flow) Air Conditioning System work under 11th Plan Building Projects for U.G.C, School of Tamil, Humanities & Social Science, Centre for Electronic Media & Mass Communication, Examination Wing, Library and MISAARC Buildings at Pondicherry University, Puducherry.

Tender No.:- Tender no. RITES/ CO/B&A/EE/PU/ VRF/E-3/2010. Table No- 1:- Pertaining to BOQ Part-II of Tender Documents S. No.

Reference/Page No./Clause No.

As per tender Document

Amended and to be read as:-

1 BOQ/ Page No -11 & 12 / Item 1 (a)/ (i) to (xii).

Cooling & Heating Cooling only.

2 BOQ/ Page No -12 / Item 1 (b)/ (vi) & (vii).

Hi Wall Type : 2.5 TR Hi Wall Type : 3.0 TR

Ductable Type : 2.5 TR Ductable Type : 3.0 TR

3 BOQ/ Page No- 13 / Item 1 (c).

Supply, Installation, testing & commissioning of TFA ( Fan Section ) units with high static 30 mm Minium Ceiling mounted Ductable unit capacity with Electrical Isolater switch below

Supply, Installation, testing & commissioning of TFA ( Fan Section ) units with high static 30 mm Minimum Ceiling mounted Ductable unit capacity with Electrical Isolator switch below but without coil.

4 BOQ/ Page No-14 / Item 1 (d)/ Y-Joints/ Unit.

Nos. LOT

5 BOQ/ Page No- 11 & 12 / Item 1 (a).

Outdoor Units Bidder has to quote against the specific BOQ item only. The capacities mentioned are the minimum required capacity. However, the bidder can offer the next higher size unit (if the required capacity unit is not manufactured by them) against that particular item without any extra cost.

6 BOQ/ Page No- 11 & 12 / Item 1 (b).

Indoor Units Bidder has to quote against the specific BOQ item only. The capacities mentioned are the minimum required capacity. However, the bidder can offer the next higher size unit (if the required capacity unit is not manufactured by them) against that particular item without any extra cost.

7 BOQ/ Page No- 14/ Item 1 (e).

Remote Controller For each common hall area, only one group controller shall be required. Bidder has to quote against the specific BOQ item only. However, the exact requirements in this regard shall be finalized at

Page 2: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

a later stage during execution of work. 8 BOQ Comprehensive

operation & maintenance of the VRF system.

During 1st year of defect liability period, AC agency is also required to provide the required man power for the operation of the VRF system without any extra cost. Bidders are also required to quote their per year rate separately (as a new BOQ item as per the attached annexure-“A”) towards comprehensive operation & maintenance of the VRF system for the next four years after completion of 1st one year of defect liability/maintenance period. In this regard the AC agency has to provide the bank guarantee of the equivalent per year quoted amount to be kept valid for the 4 years plus three months from the date of completion of 1st year of defect liability period. This BG is required to be submitted by the successful bidder before release of the final bill payments after the successful completion of the work. However a separate supplementary agreement shall be executed (after the successful completion of the work) between the PU and AC agency towards comprehensive operation & maintenance of the VRF system for the next 4 years after completion of 1st one year of defect liability period.

Table No- 2:- Pertaining to General Modifications

S. No.

Reference/Page No./Clause No.

Description Modifications:-

1 Technical Bid Part-I/ Page No 8 & 23 / 6 (a) & 2(a)

Work Experience: The VRF equipment manufacturers mentioned/ specified in the list of approved makes of this Tender shall be considered meeting the eligibility criteria of work experience given in Tender documents. However, any bidder other than approved VRF manufacturers shall have to full fill the stipulated tender criteria of work experience.

2 Technical Bid Part-I/Specs/Page No 69

Outdoor Unit Specification

Nos. of Inverter compressor in each ODU shall be as per manufactures standard meeting the technical requirements.

3 Technical Bid Part-I/ Page No 69

Color of Indoor Units Color of indoor units shall be as per manufacturers standard.

4 Technical Bid Part-I/Approved Makes/ Page No 86

Refrigerant & Drain Pipe Insulation (VRF System) at S. No. – 33.

Deleted

5 General Heat Load Calculation Bidders can give their confirmation on the heat Load calculations considered in the Tender or may submit their own heat Load calculations for achieving the inside design conditions. Heat Load calculations considered in the tender can be obtained from RITES Gurgaon office or same can also be downloaded from RITES website.

Page 3: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

BILL OF QUANTITIES 

Annexure-“A”

Comprehensive Operation & Maintenance

Note:- The AC agency has to provide the bank guarantee of the equivalent per year quoted amount to be kept valid for the 4 years plus three months from the date of completion of 1st year of defect liability period. This BG is required to be submitted by the successful bidder before release of the final bill payments after the successful completion of the work. However a separate supplementary agreement shall be executed (after the successful completion of the work) between the PU and AC agency towards comprehensive operation & maintenance of the VRF system for the next 4 years after completion of 1st one year of defect liability period.

S. No.

Description Unit Qty. RATE (Rs.) Amount ( Rs.)

In Figure In Words 24 Comprehensive Operation & Maintenance of

VRF System for the next four years after the completion of defect Liabilities period of one year. Note:- The per year rates to be quoted by the bidders as given below

i 1st Year

Per Job 01

ii 2nd Year

Per Job 01

iii 3rd Year

Per Job 01

iv 4th Year

Per Job 01

Total Amount in Rs.

Page 4: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

BASIS OF DESIGN

A. Outside Design Conditions DBT °C WBT °C

Summer / Monsoon / Winter 44.4/35/7.2 23.9/28.3/5 B. Inside Design Conditions DBT °C RH Summer / Monsoon 24.00± 1 Around 55% C. Exposed roof: All exposed roof / terraces shall be insulated with 50 mm thick expanded polystyrene or

equivalent material by client through their own agencies to get an overall heat transmission factor of 0.12 BTU/HR/SFT/°F.

D. POWER SUPPLY: Stabilised three phase four wire AC supply i.e. 415 Volts ± 10 % & 50 Hz ± 5 %

with double earthing shall be made available near each outdoor unit & Single-phase power supply with earthing near each indoor units.

Page 5: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

E. Parameters For Air-conditioning - VRF System

Building - UGC Academic Staff Building

Sl Floor & Area

Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load Pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Ground Floor

Machine - 1

1 Seminar Hall 120 120 20 105 5 10 1050 Gr. R-Sun 4745 16.69 14.482 x 8.0 TR Duct Type Unit

2 Classroom 72 72 20 60 NIL 10 600 Gr. R-Sun 2439 9.03 7.61 2 x 4.0 TR Duct Type Unit

3 Classroom 48 48 20 40 NIL 10 400 Gr. R-Sun 1631 6.03 5.05 3 x 2.0 TR Hi - Wall Unit

4 Classroom 48 48 20 40 NIL 10 400 Gr. R-Sun 1631 6.03 5.05 3 x 2.0 TR Hi - Wall Unit

Total 288 37.78 32.19 1 x 34 HP Out Door Unit

Ground Floor

Machine - 2

5 Office 25 25 20 4 NIL 10 40 Gr. R-Sun 866 1.91 1.45 2 x 1.6 TR Hi - Wall Unit

6 Director 32 32 20 4 NIL 10 40 Gr. R-Sun 888 1.95 1.49 2 x 1.6 TR Hi - Wall Unit

Page 6: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area

Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load Pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

7 Faculty - 2 No. 24 48 20 6 NIL 10 60 Gr. R-Sun 494 2.74 1.88 2 x 2.0 TR Hi - Wall Unit Each Each Each

8 Library 38 38 20 18 NIL 10 180 Gr. R-Sun 1007 3.22 2.63 2 x 2.0 TR Hi - Wall Unit

9 Computer Lab 48 48 20 32 5 10 320 Gr. R-Sun 2271 6.62 5.92 1 x 8.0 TR Duct Type Unit

10 Dinning Hall 70 70 20 50 5 10 500 Gr. NAC 2239 7.91 6.62 2 x 4.0 TR Duct Type Unit

1 x 3200 CFM TFA Unit 1 x 500 CFM TFA Unit - Ding

Total 261 24.35 19.99 1 x 28 HP Out Door Unit

Gross Total 549 62.13 52.18

Page 7: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Building - School of Tamil

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Ground Floor

Machine - 1

1 HOD Room 43 43 20 4 NIL 10 40 Gr. NAC 976 2.11 1.01 2 x 1.6 TR Hi Wall Unit

2 Prof Room - 4 No. 20 80 20 3 NIL 10 30 Gr. NAC 448 4.24 2.56 4 x 1.6 TR Hi Wall Unit Each Each

3 Seminar Room 120 120 20 120 5 10 1200 Gr. R-Sun 4969 18.24 16.13 2 x 8.0 TR Duct Type Unit

4 Dean Room 43 43 20 4 NIL 10 40 Gr. NAC 1136 2.41 1.19 2 x 1.6 TR Hi Wall Unit

5 Library 70 70 20 24 NIL 10 240 Gr. NAC 1851 5.24 3.49 1 x 8.0 TR Duct Type

1 x 1600 CFM TFA Unit

Total 356 32.24 24.38 1 x 34 HP out Door Unit

Page 8: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area

Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load Pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

First Floor

Machine - 2

6 Prof Room - 7 No. 20 140 20 3 NIL 10 30 Gr. R-

Sum 515 8.26 4.13 7 x 1.6 TR Hi Wall Unit Each Each

7 Reader Room - 2 No. 16 32 20 3 NIL 10 30 Gr.

R-Sum 368 1.82 116 2 x 1.3 TR Hi Wall Unit

Each Each 1 x 500 CFM TFA Unit

Total 172 10.08 5.29 1 x 14 HP out Door Unit

Gross Total 528 42.32 29.67

Page 9: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Building - Electronic Media & Communication

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Loador

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Ground Floor

Machine - 1

1 Reader Room - 2 No. 24 50 20 3 NIL 10 30 Gr. NAC 854 3.24 1.8 2 x 2.0 TR Hi Wall Unit

Each Each 2 Prof Room - 2 No. 17 34 20 3 NIL 10 30 Gr. NAC 727 2.84 1.6 2 x 1.6 TR Hi Wall Unit

Each Each 3 Board Room 68 68 20 20 NIL 10 200 Gr. NAC 1895 4.64 3.24 1 x 6.5 TR Duct Type Unit

4 Director Room 44 44 20 4 NIL 10 40 Gr. NAC 1257 2.36 1.24 2 x 1.6 TR Hi Wall Unit

5 Reception Room 41 41 20 8 NIL 10 80 Gr. NAC 1139 2.48 1.56 2 x 1.6 TR Hi Wall Unit

6 Multi Media Lab 83 83 20 60 3 10 600 Gr. R-Sun 4210 11.51 9.79 2 x 6.5 TR Duct Type Unit

1 x 1000 CFM TFA Unit

Total 320 27.07 19.23 1 x 30 HP Out Door Unit

Page 10: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Ground Floor

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Machine - 2

7 Hub Room / Server Room 41 41 20 4 4 10 40 Gr. NAC 1833 3.3 2.41 2 x 2.0 TR Hi Wall Unit

8 Audio Recording Room 43 43 20 12 4 10 120 Gr. NAC 1963 4.13 3.21 1 x 6.5 TR Duct Type

9 Video Recording Room 43 43 20 12 4 10 120 Gr. NAC 1852 4.13 3.21 1 x 6.5 TR Duct Type

10 Production Staff Room 33 33 20 10 NIL 10 100 Gr. NAC 1139 2.63 1.67 1 x 2.0 TR Hi Wall Unit

11 Video Production Home 182 182 20 20 8 10 200 Gr. R-Sun 6155 11.59 8.64 2 x 8.0 TR Duct Type

1 x 2000 CFM TFA Unit First Floor

13 Hub Room / Server Room 41 41 20 4 4 10 40 AC R-Sun 1833 3.3 2.41 2 x 2.0 TR Hi Wall Unit

14 Library 89 89 20 30 NIL 10 300 AC R-Sun 2648 6.64 4.87 1 x 8.0 TR Duct Type Unit

1 x 1000 CFM TFA Unit

Total 472 35.72 26.42 1 x 40 HP Out Door Unit

Page 11: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Ground Floor

Machine - 3

12 Auditorium 178 178 20 150 10 10 1500 Gr. R-Sun 9133 26.51 22.34 4 x 8.0 TR Duct Type Unit

Total 178 26.51 22.34 1 x 30 HP Out Door Unit

Gross Total 970 89.3 67.99

Page 12: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Building - Humanities and Social Science

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 5 ( Anthropology & Seminar Hall )

First Floor

1 Seminar Hall 185 185 20 185 10 10 1850 NAC R-Sun 10089 32.08 26.81 4 x 8.0 TR Duct Type

1 x 2000 CFM TFA

185 32.08 26.81 1 x 30 HP Out Door

Unit

Central Block

Ground Floor - LS

Machine - 1

1 Library Hall ( LS ) 132 132 20 80 NIL 10 800 Gr. NAC 4907 14.2 11.03 2 x 8.0 TR Duct Type Unit

2 Dean Room - ( LS ) 30 30 20 8 NIL 10 80 Gr. NAC 1084 2.39 1.51 2 x 1.6 TR Hi Wall Unit

3 Conference Hall - ( LS) 23 23 20 12 NIL 10 120 Gr. NAC 968 1.4 0.815 2 x 1.6 TR Hi Wall Unit

1 x 1000 CFM TFA

Page 13: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Second Floor - LS

4 Seminar Hall (LS) 132 132 20 112 NIL 10 1120 Gr. NAC 5500 17.64 14.32 2 x 8.0 TR Duct Type Unit

1 x 1000 CFM TFA

317 35.63 27.675 1 x 36 HP Out Door

Unit

First Floor - LS

Machine - 1

4 Seminar Hall (LS) 132 132 20 112 NIL 10 1120 Gr. NAC 5500 17.64 14.32 2 x 8.0 TR Duct Type Unit

5 Computer Room (LS) 92 92 20 65 8 10 650 Gr. NAC 5001 13.19 10.94 2 x 8.0 TR Duct Type Unit

6 Server Room (LS) 32 32 20 5 5 10 50 Gr. NAC 1283 1.24 1.03 2 x 2.0 TR Hi Wall Unit

1 x 2000 CFM TFA

256 32.07 26.29 1 x 36 HP Out Door

Unit

Page 14: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Ground Floor - RS

Machine - 1

1 Library Hall ( RS ) 132 132 20 80 NIL 10 800 Gr. NAC 4907 14.2 11.03 2 x 8.0 TR Duct Type Unit

2 Dean Room - ( RS ) 30 30 20 8 NIL 10 80 Gr. NAC 1084 2.39 1.51 2 x 1.6 TR Hi Wall Unit

3 Conference Hall - ( RS) 23 23 20 12 NIL 10 120 Gr. NAC 968 1.4 0.815 2 x 1.6 TR Hi Wall Unit

1 x 1000 CFM TFA Second Floor - RS

4 Seminar Hall (RS) 132 132 20 112 NIL 10 1120 Gr. NAC 5500 17.64 14.32 2 x 8.0 TR Duct Type Unit

1 x 1000 CFM TFA

317 35.63 27.675 1 x 36 HP Out Door

Unit

Cafeteria

First Floor

1 Cafeteria 224 224 20 120 NIL 10 1200 NAC NAC 9600 24.6 23.2 6 x 4.75 TR Duct Type 1 x 1200 CFM TFA Unit

224 24.6 23.2 1 x 28 HP Out Door

Page 15: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Unit F Parameters For Air-conditioning - Split Unit System

Building - UGC Academic Staff Building

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Ground Floor

1 Guest Room 1 To 4 - 4 No. 14 56 15 2 NIL 10 20 Gr. NAC 597 5.24 2.44 4 x 1.6 TR Hi - Wall Unit

Each Each

2 Guest Room 5 To 8 - 4 No. 14 56 15 2 NIL 10 20 Gr. NAC 570 4.32 2.44 4 x 1.6 TR Hi - Wall Unit

Each Each

3 Guest Room 9 To 11 - 3 No. 14 42 15 2 NIL 10 20 Gr. NAC 556 3.18 1.71

3 x 1.6 TR Hi - Wall Unit

Each Each

4 Guest Room 12 To 14 - 3 No. 14 42 15 2 NIL 10 20 Gr. NAC 572 3.27 1.86

3 x 1.6 TR Hi - Wall Unit

Each Each First Floor

14 Guest Room 1 To 4 - 4 No. 14 56 15 2 NIL 10 20 Gr. R-Sun 597 5.24 2.44 4 x 1.6 TR Hi - Wall Unit

Each Each

15 Guest Room 5 To 8 - 4 No. 14 56 15 2 NIL 10 20 Gr. R-Sun 570 4.32 2.44 4 x 1.6 TR Hi - Wall Unit

Each Each

16 Guest Room 9 To 11 - 4 No. 14 56 15 2 NIL 10 20 Gr. R-Sun 556 4.24 2.28

4 x 1.6 TR Hi - Wall Unit

Each Each 17 Guest Room 12 To 14 - 4 14 56 15 2 NIL 10 20 Gr. R-Sun 572 4.36 2.48 4 x 1.6 TR Hi - Wall

Page 16: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

No. Unit Each Each

420 34.17 18.09

Building - Humanities and Social Science

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UN

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 1 ( History )

Ground Floor

1 Prof Room - 2 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 2.2 1.22 2 x 1.5 TR Hi Wall UnEach Each

2 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

3 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

First Floor

1 Conservation & Museum 75 75 20 25 NIL 10 250 Gr. NAC 1944 4.95 3.46 4 x 2.0 TR Hi Wall Un

6 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

7 Arch Lab 23 23 20 8 NIL 10 80 AC R-

Sum 700 1.76 1.3 1 x 1.5 TR Hi Wall Un

8 Archival Room 31 31 20 10 NIL 10 100 AC R-

Sum 975 2.36 1.62 2 x 1.5 TR Hi Wall Un

259 16.72 10.65

Page 17: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 2 ( Sociology )

Ground Floor

1 Prof Room - 2 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 2.2 1.22 2 x 1.5 TR Hi Wall UnEach Each

2 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

3 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

First Floor

5 Prof Room - 2 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 2.2 1.22 2 x 1.5 TR Hi Wall UnEach Each

6 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

7 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

204 11.9 6.5

Page 18: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UN

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 3 ( Social Inclusion & Exclusion Studies)

Ground Floor

1 Prof Room - 1 No. 20 20 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall Un

2 Reader - 1 No. 14 14 20 3 NIL 10 30 Gr. NAC 376 0.85 0.51 1 x 1.5 TR Hi Wall Un

3 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

68 4 2.14

Block - 4 ( Politics & International Studies

Ground Floor

1 Prof Room - 2 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 2.2 1.22 2 x 1.5 TR Hi Wall UnEach Each

2 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

3 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

Page 19: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

First Floor

4 Reader - 2 No. 14 14 20 3 NIL 10 30 Gr. NAC 376 1.74 1.1 2 x 1.5 TR Hi Wall Un

5 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

150 9.74 5.36

Block - 5 ( Anthropology & Seminar Hall )

Ground Floor

1 Visual Anthro 50 50 20 15 2 10 150 Gr. NAC 1788 4.08 3.02 4 x 1.5 TR Hi Wall Un

2 Museum 41 41 20 15 NIL 10 150 AC R-

Sum 1317 3.31 2.46 2 x 1.5 TR Hi Wall Un

3 Prof Room - 1 No. 20 20 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall Un

4 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

5 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

173 12.24 8.13

Page 20: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UN

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 6 ( English )

Ground Floor

1 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

2 Prof Room - 3 No. 20 60 20 3 NIL 10 30 Gr. NAC 531 3.3 1.86 3 x 1.5 TR Hi Wall UnEach Each

3 Reader - 6 No. 14 84 20 3 NIL 10 30 Gr. NAC 376 5.1 3.06 6 x 1.5 TR Hi Wall UnEach Each

First Floor

4 ELT Lab 50 50 20 15 NIL 10 150 NAC R-Sun 2066 4.53 3.14 4 x 1.5 TR Hi Wall Un

5 Language Lab 50 50 20 15 NIL 10 150 NAC R-Sun 2066 4.53 3.14 4 x 1.5 TR Hi Wall Un

278 19.51 12.21 Block - 7 ( French)

Ground Floor

1 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

2 Prof Room - 1 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall UnEach Each

3 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall Un

Page 21: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Each Each

102 4.85 2.65

Block - 8 ( Applied Psychology)

Ground Floor

1 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

2 Prof Room - 1 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall UnEach Each

3 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

First Floor

4 Consulting Hall with 73 73 20 25 NIL 10 250 NAC R-Sun 2671 6.29 4.23 4 x 2.0 TR Hi Wall UnObservation Room

5 Lab With Object Space 73 73 20 25 NIL 10 250 NAC R-Sun 2671 6.29 4.23 4 x 2.0 TR Hi Wall Un

6 Lab With Object Space 73 73 20 25 NIL 10 250 NAC R-Sun 2671 6.29 4.23 4 x 2.0 TR Hi Wall Un

321 23.72 15.34

Page 22: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UN

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsson Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 9 ( Asian Christian Studies)

Ground Floor

1 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

2 Prof Room - 1 No. 20 20 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall UnEach Each

3 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

First Floor

4 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

5 Prof Room - 2 No. 20 40 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 2 x 1.5 TR Hi Wall UnEach Each

6 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

7 Computer Lab 31 31 20 18 NIL 10 180 Gr. R-Sun 1240 3.39 1.02 2 x 2.0 TR Hi Wall Un

8 Library 38 38 20 18 NIL 10 180 Gr. R-Sun 1206 3.36 2.74 2 x 2.0 TR Hi - Wall

253 16.45 9.06

Page 23: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

Sl Floor & Area Name Area Total Light Occu- Eqpt. ACPH Fresh Floor Floor Dehum. TR TR IN / OUT Door UNIT

No. SMT Area Load pancy Load or

CFM/ Air Below Above CFM Summer Monsoon Selection SMT W/SMT KW PER CFM Summer (Total) (Total)

Block - 10 ( Sanskrit)

Ground Floor

1 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

2 Prof Room - 1 No. 20 20 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall UnEach Each

3 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

First Floor

4 HOD 34 34 20 4 NIL 10 40 Gr. NAC 1067 2.05 1.01 2 x 1.5 TR Hi Wall Un

5 Prof Room - 1 No. 20 20 20 3 NIL 10 30 Gr. NAC 531 1.1 0.62 1 x 1.5 TR Hi Wall UnEach Each

6 Reader - 2 No. 14 28 20 3 NIL 10 30 Gr. NAC 376 1.7 1.02 2 x 1.5 TR Hi Wall UnEach Each

164 9.7 5.3

Gr. Total Huminaties 1972 128.83 77.34

Page 24: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

F. Refrigeration Load The total refrigeration load based on the parameters given below. Building Name Area Summer Monsoon SMT TR TR

Gr. Total Humanities 3308 390.72 283.92

UGC 804 88.66 65.32

Total Tamil 508 42.32 29.67

Total Elect Media 970 89.3 67.99

Gross Total ( Project ) 5585 611.05 446.9

Page 25: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

BASIS OF DESIGN FOR AIR CONDITIONING WORKS

EXAMINATION WING :  

SYSTEM‐1(44HP) 

No  DESCRIPTION  AREA HEIGH

T Occupancy 

Indoor Unit 

QTY TOTAL 

Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.   TR       

1  DDE Office  428  14.0 9.0  2.0  2.0  4.0  Concealed    Ground  

2  A.R Cabin  212  14.0 1.0  2.0  1.0  2.0  Concealed    Ground  

3  D.R. Secretary  50  14.0 1.0  1.0  1.0  1.0  Concealed    Ground  

4  D.R.Cabin‐2  102  14.0 3.0  1.0  1.0  1.0  Concealed    Ground  

5 Computer Section  317  14.0 9.0  2.5  1.0  2.5  Concealed    Ground  

6  Valuation Hall   3709  14.0 154.0  4.0  6.0  24.0  Ductable  Ground  

7  Finance Selection  228  14.0 5.0  2.0  1.0  2.0  Concealed    Ground  

8  A.R. Cabin  141  14.0 1.0  1.5  1.0  1.5  Concealed    Ground  

9  Cafteria  141  14.0 5.0  1.5  1.0  1.5  Concealed    Ground  

  TOTAL        15.0  39.5     

 

 

 

 

 

 

 

 

 

Page 26: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐2 (36 HP) 

No  DESCRIPTION  AREA HEIGH

TOccupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

      SFT  (FT) Nos  TR  Nos.   TR       

10  COMPUTER HALL  717  14.0 20.0  2.5  3.0  7.5  Concealed    Ground 

11  FUT SEC OFF  553  14.0 9.0  2.0  2.0  4.0  Concealed    Ground 

12 UG/PG Engg & Tech  432  14.0 9.0  2.0  2.0  4.0  Concealed    Ground 

13 Medical / Para Med/ Law  432  14.0 9.0  2.0  2.0  4.0  Concealed    Ground 

14 UG/PG Arts & Science 

432  14.0 9.0  2.0  2.0  4.0  Concealed    Ground 

15 Inquiry/ Certi room 

553  14.0 9.0  2.0  2.0  4.0  Concealed    Ground 

16  Waiting Hall 686  14.0 24.0  2.5  2.0  5.0  Concealed    Ground 

17  Reception 186  14.0 3.0  2.0  1.0  2.0  Concealed    Ground 

  TOTAL       16.0  34.5     

 

 

 

 

 

 

 

 

 

 

 

Page 27: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐3 (20 HP) 

No  DESCRIPTION  AREA HEIGH

T Occupancy 

Indoor Unit 

QTY TOTAL 

Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.   TR       

18  A.R ‐3 cabin 130  14.0 1.0  1.0  1.0  1.0  Concealed    Ground 

19  A.R ‐4 cabin 130  14.0 1.0  1.0  1.0  1.0  Concealed    Ground 

20  A.R ‐2 cabin 130  14.0 1.0  1.0  1.0  1.0  Concealed    Ground 

21  A.R ‐1 cabin 130  14.0 1.0  1.0  1.0  1.0  Concealed    Ground 

22  D.R. Secretary 55  14.0 1.0  1.0  1.0  1.0  Concealed    Ground 

23  D.R.Cabin‐1 102  14.0 3.0  1.0  1.0  1.0  Concealed    Ground 

24  Research section 318  14.0 3.0  2.5  1.0  2.5  Concealed  Ground 

25  Lobby 561  14.0 8.0  2.5  2.0  5.0  Concealed  Ground 

26 Security & Data room 

230  14.0 2.0  2.0  1.0  2.0  Concealed    Ground 

27  Staff Dinning 526  14.0 24.0  2.0  2.0  4.0  Concealed    Ground 

  TOTAL       12.0  19.5     

 

SYSTEM‐ 4 (50 HP) 

No  DESCRIPTION  AREA HEIGH

T Occupancy 

Indoor Unit 

QTY TOTAL 

Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.   TR       

1  Valuation Hall  5301  14.0  215.0  5.0  10.0  50.0  Ductable  First 

  TOTAL         10.0  50.0     

 

 

 

Page 28: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐ 5 (44 HP) 

No  DESCRIPTION  AREA HEIGH

T Occupancy 

Indoor Unit 

QTY TOTAL 

Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.   TR       

2 Mini Valuation hall 

867  14.0 35.0  4.0  3.0  12.0  Ductable  First 

3 Confidential room 

432  14.0 7.0  2.5  2.0  5.0  Concealed    First 

4  C.E.Room 432  14.0 10.0  2.5  2.0  5.0  Concealed    First 

5  C.E. Sec. cabin 288  14.0 6.0  3.0  1.0  3.0  Ductable  First 

6  Conference hall 686  14.0 21.0  3.0  3.0  9.0  Ductable  First 

7 Board meeting room 

720  14.0 24.0  3.0  3.0  9.0  Ductable  First 

8  D.R.Cabin‐3 97  14.0 3.0  1.0  1.0  1.0  Concealed    First 

9  D.R. Secretary 56  14.0 1.0  1.0  1.0  1.0  Concealed    First 

  TOTAL         16.0  45.0     

 

 

 

 

 

 

 

 

 

 

 

 

Page 29: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐ 6 

No  DESCRIPTION  AREA HEIGH

T Occupancy 

Indoor Unit 

QTY TOTAL 

Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.   TR       

10  Pre Valuation 330  14.0 10.0  3.0  1.0  3.0  Ductable  First 

11  Pre Valuation 289  14.0 10.0  3.0  1.0  3.0  Ductable  First 

12  Pre Valuation 289  14.0 10.0  3.0  1.0  3.0  Ductable  First 

13 Pre Val(M.ED & Law) 

710  14.0 10.0  3.0  3.0  9.0  Ductable  First 

14  Pre Val(Eng) 710  14.0 10.0  3.0  3.0  9.0  Ductable  First 

  TOTAL         9.0  27.0     

 

 

OUTSIDE DESIGN CONDITIONS : 39.44 DEG C DRY BULB / 27.77 DEC C WET BULB.

INSIDE DESIGN CONDITIONS : 24 +/- 1.1 DEG C DRY BULB AND 55 +/- 5 % RELATIVE HUMIDITY.

Page 30: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

BASIS OF DESIGN FOR AIR CONDITIONING WORKS

LIBRARY WING: 

SYSTEM‐1 (32 HP) 

No  DESCRIPTION  AREA HEIGHT 

Occupancy 

Indoor Unit 

QTY TOTAL 

Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.   TR       

1  Reading Hall 3543  12.0 30.0  5.0  6.0  30.0  Ductable  Ground  

2  Section In‐charge 180  12.0 2.0  1.5  1.0  1.5  Concealed    Ground 

3  Visually Challenged 1763  12.0 20.0  4.0  3.0  12.0  Ductable  Ground 

  TOTAL       10.0  43.5     

 

SYSTEM‐2 (32 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

4  Children Section  1146  12.0 20.0  4.0  2.0  8.0  Ductable  Ground  

5  Children Section  1432  12.0 20.0  4.0  3.0  12.0  Ductable  Ground 

  TOTAL       5.0  20.0     

 

 

 

 

 

 

 

Page 31: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐3 (32 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

6  Auditorium  2345  19.0 200.0  5.0  4.0  20.0  Ductable  Ground 

7  Lobby & Cafteria 919  12.0 20.0  4.0  2.0  8.0  Ductable  Ground 

  TOTAL       6.0  28.0     

 

 

SYSTEM‐4 (32 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

3  Readers Room 2495  12.0 30.0  4.0  5.0  20.0  Ductable  First 

4  Room‐1 133  12.0 2.0  1.0  1.0  1.0  Concealed    First 

5  Room‐2 133  12.0 2.0  1.0  1.0  1.0  Concealed    First 

6  Room‐3 133  12.0 2.0  1.0  1.0  1.0  Concealed    First 

  TOTAL       8.0  23.0     

 

 

 

 

 

 

 

 

Page 32: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐5 (16 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

1  Computer Section 1545  12.0 20.0  4.0  4.0  16.0  Ductable  First 

  TOTAL       4.0  16.0     

 

 

SYSTEM‐6 (16 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

2  Research Scholars 1587  12.0 10.0  4.0  4.0  16.0  Ductable  First 

  TOTAL       4.0  16.0     

 

 

 

 

 

 

 

 

 

 

 

 

Page 33: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐7 (26 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

6  Class Room‐2 1020  12.0 25.0  5.0  2.0  10.0  Ductable  Second 

7  Class Room‐3 1039  12.0 25.0  5.0  2.0  10.0  Ductable  Second 

8  Faculty Room‐1 111  12.0 2.0  1.0  1.0  1.0  Concealed    Second 

9  Faculty Room‐2 111  12.0 2.0  1.0  1.0  1.0  Concealed    Second 

10  Faculty Room‐3 111  12.0 2.0  1.0  1.0  1.0  Concealed    Second 

11  Faculty Room‐4 111  12.0 2.0  1.0  1.0  1.0  Concealed    Second 

12  Faculty Room‐5 111  12.0 2.0  1.0  1.0  1.0  Concealed    Second 

13  Faculty Room‐6 111  12.0 2.0  1.0  1.0  1.0  Concealed    Second 

  TOTAL       10.0  26.0     

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 34: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐8 (44 HP) 

No  DESCRIPTION AREA 

HEIGHT

Occupancy 

Indoor Unit  QTY 

TOTAL  Type of IDU  Floor 

     SFT  (FT) Nos  TR  Nos.   TR       

1  Rest Room 308  12.0 2.0  2.5  1.0  2.5  Concealed    Second 

   2  H.O.D Room 

252  12.0 2.0  2.5  1.0  2.5  Concealed    Second 

3  Office Room 762  12.0 10.0  4.0  2.0  8.0  Ductable  Second 

4  Lecturer Hall 1530  12.0 25.0  4.0  4.0  16.0  Ductable  Second 

5  Class Room‐1 1127  12.0 25.0  5.0  2.0  10.0  Ductable  Second 

14  Meeting 238  12.0 5.0  2.5  1.0  2.5  Concealed    Second 

  TOTAL       11.0  41.5     

 

 

 

OUTSIDE DESIGN CONDITIONS : 39.44 DEG C DRY BULB / 27.77 DEC C WET BULB.

INSIDE DESIGN CONDITIONS : 24 +/- 1.1 DEG C DRY BULB AND 55 +/- 5 % RELATIVE HUMIDITY.

Page 35: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

BASIS OF DESIGN FOR AIR CONDITIONING WORKS

MISAARC WING : 

SYSTEM‐1( 20 HP) 

No  DESCRIPTION  AREA  HEIGHTOccupancy 

Indoor Unit 

QTY  TOTAL  Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.  TR       

2  Rest Room 96  14.0 3.0  1.0  1.0  1.0  Concealed    Ground 

3  Office Room 222  14.0 4.0  2.0  1.0  2.0  Concealed    Ground 

4  Waiting Room 133  14.0 13.0  1.0  1.0  1.0  Concealed    Ground 

5  Faculty 201  14.0 6.0  2.0  1.0  2.0  Concealed    Ground 

6  Class Room‐1 426  14.0 30.0  2.0  2.0  4.0  Concealed    Ground 

7  Class Room‐2 604  14.0 40.0  4.0  2.0  8.0  Ductable  Ground 

8  Directors Room 320  8.0 8.0  2.5  1.0  2.5  Concealed    Ground 

  TOTAL       8.0  18.5     

 

 

 

 

 

 

 

 

 

 

 

Page 36: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐2(36 HP) 

No  DESCRIPTION  AREA HEIGH

T Occupancy 

Indoor Unit 

QTY  TOTAL  Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.  TR       

1 Waiting Lobby & Rece 

2388  14.0  31.0  5.0  3.0  15.0  Ductable  Ground 

9  Ladies Room 112  14.0  9.0  1.0  1.0  1.0  Concealed    Ground 

10  Class Room 315  14.0  20.0  2.5  1.0  2.5  Concealed    Ground 

11  Class Room 315  14.0  20.0  2.5  1.0  2.5  Concealed    Ground 

12  Computer Hall 604  14.0  28.0  3.0  3.0  9.0  Ductable  Ground 

13  Faculty‐1 160  14.0  6.0  1.5  1.0  1.5  Concealed    Ground 

14  Faculty‐2 160  14.0  6.0  1.5  1.0  1.5  Concealed    Ground 

15  Faculty‐3 160  14.0  6.0  1.5  1.0  1.5  Concealed    Ground 

  TOTAL         12.0  35.5     

 

 

 

 

 

 

 

 

 

 

 

 

Page 37: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐3( 20 HP) 

No  DESCRIPTION  AREA  HEIGHTOccupancy 

Indoor Unit 

QTY  TOTAL  Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.  TR       

2  Meeting Room‐2 361  14.0  12.0  3.0  1.0  3.0  Ductable  First 

3  VIP Guest Room 207  14.0  3.0  2.5  1.0  2.5  Concealed    First 

4  Faculty 207  14.0  6.0  2.5  1.0  2.5  Concealed    First 

5  Faculty 207  14.0  6.0  2.5  1.0  2.5  Concealed    First 

6  Meeting Room  320  14.0  14.0  3.0  1.0  3.0  Ductable  First 

7  Faculty 154  14.0  6.0  2.0  1.0  2.0  Concealed    First 

4 Visiting professor's room 

199  14.0 6.0  2.0  1.0  2.0  Concealed    Second 

5  Society Office 95  14.0 6.0  1.0  1.0  1.0  Concealed    Second 

6 Visiting professor's room 

199  14.0 6.0  2.0  1.0  2.0  Concealed    Second 

  TOTAL       9.0  20.5     

 

 

 

 

 

 

 

 

Page 38: Refrigerant Flow) Air Conditioning System work under 11th ... · a later stage during execution of work. 8 BOQ Comprehensive operation & maintenance of the VRF system. During 1st

 

SYSTEM‐4( 50 HP) 

No  DESCRIPTION  AREA  HEIGHTOccupancy 

Indoor Unit 

QTY  TOTAL  Type of IDU  Floor 

     SFT  (FT)  Nos  TR  Nos.  TR       

1  Auditorium 1922  28.0  104.0  6.0  4.0  24.0  Ductable  First 

8  Faculty‐1 207  14.0 6.0  2.5  1.0  2.5  Concealed    First 

9  Faculty‐2 207  14.0 6.0  2.5  1.0  2.5  Concealed    First 

10  Faculty‐3 207  14.0 6.0  2.5  1.0  2.5  Concealed    First 

11  Librarian 97  14.0 6.0  1.0  1.0  1.0  Concealed    First 

12 Library,Reading & Stack  

659  14.0 28.0  3.0  2.0  6.0  Ductable  First 

1 Library,Reading & Stack  

659  14.0 38.0  3.0  2.0  6.0  Ductable  Second 

2  Residential Scholars 403  14.0 8.0  2.5  1.0  2.5  Concealed    Second 

  TOTAL       13.0  47.0     

 

OUTSIDE DESIGN CONDITIONS : 39.44 DEG C DRY BULB / 27.77 DEC C WET BULB.

INSIDE DESIGN CONDITIONS : 24 +/- 1.1 DEG C DRY BULB AND 55 +/- 5 % RELATIVE HUMIDITY.