region 4 - mobility presentation 7-12-2018 document...2018/06/07  · region 4 - mobility...

38
REGION 4 - MOBILITY PRESENTATION 7-12-2018

Upload: others

Post on 19-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

REGION 4 - MOBILITY PRESENTATION

7-12-2018

Page 2: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

PROJECTS TO DISCUSS

1. OR140: Brett Way Extension (KFalls – K18731)

• OR140/Homedale Rd Roundabout – ROS

2. 2019 Construction Work Zone Impacts

• I-84: Swanson Canyon – Arlington (K20274)

• Region 4 ITS (K20551)

3. ORS 366.215 Impacts

• Warm Springs Safety Corridor (K19640)

2

Page 3: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

OR140/Homedale Road Roundabout

GOAL: Improve safety for all users, including freight at the

intersection and provide access to industrial land south of OR140.

Update from May 2017 MCTD Stakeholder Meeting:

• Conceptual Drawing of Proposed Single Lane Roundabout

• Proposed Single Lane Roundabout compared to

US20/Barclay and OR126/Tom McCall Roundabouts

• Design and Accommodation Vehicles

Over-dimension Load Routes: US97/OR39/Cross Rd

• Concept Drawings with WB-67 Truck Turning Movements

3

Source: Sisters TSP Refinement (KAI)

Page 4: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

4

Source: Sisters TSP Refinement (KAI)

Page 5: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

5

Proposed Single Lane Roundabout compared to

US20/Barclay and OR126/Tom McCall Roundabouts

Page 6: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

6

Source: Sisters TSP Refinement (KAI)

DESIGN VEHICLE: WB-67

DESIGN INCLUDES: Splitter islands and truck apron

ACCOMODATE: Can accommodate the following trucks without

hitting the curb for the east/west OR140 thru movement.

Over-dimension Load Routes: US97/OR39/Cross Rd

Vehicle Name # Parts Length Trailer Length

WB67-D 3 (Double trailer) 72 29

STAA 2 72 48

Long Timber Transport 2 98 84

Page 7: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

7

Source: Sisters TSP Refinement (KAI)

Over-dimension Load Routes: US97/OR39/Cross Rd

Rail Crossing

16’ 2” unbuffered

Page 8: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

8

Source: Sisters TSP Refinement (KAI)

Page 9: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

9

Source: Sisters TSP Refinement (KAI)

Page 10: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

10

Source: Sisters TSP Refinement (KAI)

Page 11: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

11

Source: Sisters TSP Refinement (KAI)

Page 12: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

12

Source: Sisters TSP Refinement (KAI)

Page 13: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

13

Source: Sisters TSP Refinement (KAI)

Page 14: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

14

Source: Sisters TSP Refinement (KAI)

Page 15: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

OR140: Brett Way Extension (Kfalls) (K18731)

15

Source: Sisters TSP Refinement (KAI)

Questions?

Next Steps in Obtaining a Record of Support?

• Confirm Roundabout Rodeo not needed?

• Additional Accommodation Vehicles/movements?

Page 16: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Scope - pavement preservation between MP 125-138.

Construction in 2019

MP 125.50 – 132.00 (6.5 miles)

- 3” grind, 5” inlay/overlay

MP 132.00 – 137.78 (5.8 miles)

- Left (“A”) Lane - 5” grind, 8” inlay/overlay

- Right (“B”) Lane – 3” grind, 5” inlay/overlay

Traffic Analysis – single lane conditions remain below

delay thresholds except during Memorial Day and Labor

Day weekends.

16

Page 17: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Single Lane Closure vs Temporary Crossover

• Separation of work zone and live traffic – Safety

• Estimated Paving Production

• Anticipate a 16-20% cost savings over traditional

traffic control of single lane closures option.

• Estimated $2.1M savings based on programmed

construction funding.

17

Paving Days Paving Rate (Tons/Day)EB WB

Single Lane Closures – 12 hr shift (DAYS)

63 66 1320

Crossover – 12 hr shift (DAYS) 42 44 1980Crossover – 24 hr shift or double pavers (DAYS)

21 22 4000

Page 18: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Stages 1 & 2: Temporary Crossover

18.5’ horizontal clearance, 24-hour restriction

Surface mounted tubular markers

19’ horizontal clearance at start/end, 24-hour

Concrete barriers

Speed Reduction to 45mph

Restrict duration to 4 weeks for each crossover

Require 2 weeks between crossover stages

18

Page 19: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

19

Page 20: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

20

Page 21: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Temporary Crossover Cont.

Arlington Interchange (Exit 137) – Open during crossover

Closure during paving of ramps and when paving outside

(slow) lanes on I-84 mainline as paver passes ramps.

Friday night - Sunday morning 10pm-5am

Message boards used to direct traffic to use Heppner

Highway Interchange (Exit 147)

Arlington Viewpoint parking lot (MP136.6) closed and

paved during westbound crossover.

Blalock Interchange (Exit 129) and Woelpern

Interchange (Exit 131) closures.

Message boards used to direct traffic to nearest I-84

Interchange to east/west.

21

Page 22: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Stage 3: Median Work

Traffic in outside (slow) lanes

22’ horizontal clearance w/soft barriers

One lane, one-way traffic considered no

impact

Allowed Daily Anytime

22

Page 23: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Stage 4: Paving of Crossover Returns

Single lane closures

14.5’ horizontal clearance w/soft barriers

• Nighttime Sunday night – Friday morning 7pm-7am

19’ horizontal clearance w/soft barriers

• Allowed daily anytime

23

Page 24: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

I-84: Swanson Canyon – Arlington (K20274)

Documents

Work Zone Decision Tree Attached

Transportation Management Plan Attached

Mobility Checklist Attached

Questions?

24

Page 25: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

Region 4 ITS Project (K20551)

Scope – Improve communication

infrastructure on the state highway

system through Region 4 by

replacing and rehabilitating aging

infrastructure and incorporating

electronic and information

technologies with Intelligent

Transportation Systems (ITS).

Incident Response Cameras

Illumination

Road Weather Information

System (RWIS) & Cameras

25

Page 26: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

Region 4 ITS Project (K20551)

Incident Response Cameras

26

US97/Bend Parkway, US20/Bend Parkway, and US97/Lava Butte

MP Site Description

Type of

Work Zone

Closures

Allowable Work Hours

(any day of week)

Mobility Impact/

Horizontal

Clearance

Maintained

US97 (Hwy 004: The Dalles - California) MP 134.09 – 146.55

134.09 Site 1: Cooley Rd – Northbound Single lane 8pm-7am (nighttime) no impact

137.12 Site 3: Revere Ave – Southbound Single lane 8pm-7am (nighttime) 14ft; ramp delays

139.02 Site 4: Reed Market Rd – NorthboundSingle lane 9am-3pm (daytime) and

7pm-7am (nighttime)

no impact

139.98 Site 5: Powers Rd – Southbound Single lane 7pm-7am (nighttime) 19ft

141.09Site 6: Murphy Rd – Northbound

(US97/3rd St. Interchange Conn. No. 2)

Single lane/

shoulder

7pm-7am (nighttime)/

anytime

no impact

142.68 Site 7: Rocking Horse VMS – Southbound shoulder anytime no impact

142.75 Site 8: China Hat VMS – Northbound shoulder anytime no impact

146.55 Site 9: Lava Butte Scales – Northbound shoulder anytime no impact

US20 (Hwy 017: McKenzie - Bend) MP 19.91

19.91Site 2: Hwy 017 – Northbound

(Existing Cantilever)

Single lane 7pm-7am (nighttime) 19ft

Page 27: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

Region 4 ITS Project (K20551)

Illumination, RWIS, & Camera

Replace existing illumination with LEDs on Brewery Grade

Install RWIS and Camera @ I-84 The Dalles

27

I-84 Brewery Grade Interchange(Hwy 002: Columbia River) MP 85 – 86

MP Site Description

Type of Work

Zone Closures

Allowable Work Hours

(any day of week)

Mobility Impact/

Horizontal Clearance

Maintained

85-86 I-84 Exit 85 Ramps Ramp Closures 7pm-7am (nighttime) 22ft

85.5Site 10: The Dalles – Northbound

(Brewery Grade Connection No. 2 - Interchange) Flagger Controlled 7pm-7am (nighttime) Ramp Closures

85-86 I-84 Mainline Single lane 7pm-7am (nighttime) 15ft

Page 28: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

Region 4 ITS Project (K20551)

RWIS & Cameras

28

US20/Buck Creek and US97/Shaniko

MP Site Description

Type of Work

Zone Closures

Allowable Work Hours

(any day of week)

Mobility Impact/

Horizontal Clearance

Maintained

US20 (Hwy 007: Central Oregon) MP 82.92

82.92 Site 12: Buck Creek – Eastbound Shoulder Any Time No Impact

US97 (Hwy 042: Sherman) MP 56.36

56.36 Site 11: Shaniko – Northbound Shoulder Any Time No Impact

Shaniko RWISUS20/Buck Creek RWIS

Page 29: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

Region 4 ITS Project (K20551)

29

Documents

Work Zone Decision Tree Attached

Transportation Management Plan Attached

Mobility Checklist Attached

Questions?

Page 30: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Scope - Repaving the roadway, culvert replacements,

improve roadside cut, implementing safety and traffic

calming improvements, and constructing a 10ft multi-use

path along US26 as part of the 2017 Warm Springs

Commercial Corridor Safety Plan from US26/Kahneeta

Junction (MP103)to Gumwood Lane near Madras (MP112).

30

Page 31: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

ORS366.215 Impacts MP103 to MP105 – Installation of

raised medians/pedestrian refuge islands proposed at

several locations will impact horizontal clearances.

Existing widths = 32ft to 52ft

Proposing 20ft horizontal clearances(curb to curb/edge of pavement)

Seeking Record of Support

31

Page 32: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

32

Page 33: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

33

Page 34: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

34

Page 35: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

35

Page 36: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

36

Page 37: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

37

Page 38: REGION 4 - MOBILITY PRESENTATION 7-12-2018 Document...2018/06/07  · REGION 4 - MOBILITY PRESENTATION 7-12-2018 PROJECTS TO DISCUSS 1. OR140: Brett Way Extension (KFalls –K18731)

US26: Warm Springs Safety Corridor (K19640)

Draft Plans with Approximate Median/Island Locations

May be slight adjustments, but will maintain minimum of 20ft

horizontal clearance

38