Eng. David M. Mwangi
Independent Energy Consultant
Kenya
RegionalInterconnectivity & Cross Border Trade Networks:An EAPP Update
Outline of the Presentation
• EAPP member countries• Existing power interconnections in the region• Road map for regional power market• Planned interconnections• Ongoing institutional capacity building
programmes• Critical pending issues• Summary
EAPP MEMBER COUNTRIES
Member Countries (9):
Libya, Egypt, Sudan,Ethiopia, Kenya, Tanzania, Rwanda, Burundi, DRC,
Potential Members (3):Djibouti, Eritrea, Uganda.
Existing Interconnections
• Existing Interconnections as at August 2012�DRC-Burundi, DRC-Rwanda and Burundi-
Rwanda associated to Ruzizi II (45 MW), 110kV and 70kV Single Circuit
�Kenya-Uganda Interconnection, 132kV Double Circuit
�Ethiopia-Sudan, 230 kV Double Circuit�Ethiopia-Djibouti, 230 kV Double Circuit
Existing SINELAC Interconnector
• DRC, Burundi and Rwanda associated to Ruzizi II (45 MW)
G45MW
70kV
110kV
Existing Kenya -Uganda Interconnector
• Kenya Uganda Interconnection– In Operation since 1958
132kVDouble Cct
Existing Ethiopia-Sudan Interconnector
– Ethiopia - Sudan (Completed 2012)
230kV, 290MWDouble Cct
Currently only 100MW is Contracted from Ethiopia
Existing Ethiopia -Djibouti Interconnector
• Ethiopia-Djibouti– Completed and tested 2012
230kV, 950 kmDouble Cct
Regional Power Market: The Road MapRegional Power Market: The Road Map
Preliminary
Stage
Stage #1
Transitional
2013
Stage #2
Transitional
2016/7
Stage #3
Final
2021
MarketCurrent.
Country to country
Mostly between neighbouring
countries
Between any pair of countries
Fully trading environment
Previous arrangements
• Previous arrangements • Bilateral Market [BTA]• Balancing Mechanism
(TSOs)
• Previous arrangements • Bilateral Market [BTA]• Spot Market• Balancing Market
Liquid MarketTransactions
Market Participants
Single buyer in each country
• Single buyers• IPPs & eventually
Multiple sellers- buyers (in unbundled countries)
• Multiple sellers-buyers& eventually
• Single buyers
• Single buyers& eventually
• Multiple sellers- buyers
RRC with few functions but empowered
RRC evolves as Market . Full staff by the end of Stage #1
RRC fully established
regarding staff
Same asStage #2
Regional Regulator
By the countries taking into account
future regional developments
• Regional Indicative Planning
• Countries encouraged to take into account in their MPs the regional planning
Same asStage #1
• Regional Indicative Planning
• Private Investors & utilities more interested in identified projects
Regional Planning
� EAPP plans to attain full fledged power market in four stages
� Interconnection and generation projects in progress
� Institutionaldevelopment also progressing
Planned Interconnectors - EAPP Trade Zone 1
Uganda-Rwanda, 220KV, 2014
DRC-Uganda,220KV, 2015
DRC-Rwanda, 220KV, 2014
Rwanda-Burundi 220KV, 2020
DRC-Burundi,220KV, 2020
DR CONGO
UGANDA
RWANDA
BURUNDI
220KV TX/RW/BRD/DRC- Rusumo Falls, Ruzizi III and IV Interconnector Expected
Planned Interconnectors• EAPP Trade ZONE 1
Interconnector Capacity(MW) KV TechnologyYear expected to be
in Operation
UG-RW 300 220 AC 2014
RW-DRC 400 220 AC 2014
UG-DRC 300 220 AC 2015
DRC-BRD 300 220 AC 2020-2030
BRD-RW 300 220 AC 2020
TZ,RW,BRD,DRC 220 AC Rusumo Falls Interconnection
Planned Interconnectors - EAPP Trade Zone 2
Trade Zone 2Uganda-Tanzania, 220KV, 2016
Uganda-SouthSudan,400KV,2020
Kenya –Uganda,220KV,2014
Kenya-Tanzania,400KV, 2015
Kenya-Uganda,400KV,2036
SOUTH SUDAN
TANZANIA
KENYAUGANDA
Planned Interconnectors• EAPP Trade ZONE 2
Interconnector Capacity(MW) KV TechnologyYear expected to be in Operation
UG-South Sudan 1000 400 AC 2020*
UG-KE 300 220 AC 2014
TZ-KE 1500 400 AC 2015
TZ-UG 400 220 AC 2016*
UG-KE 800 400 AC 2036*
Planned Interconnectors - EAPP Trade Zone 3
• EAPP Trade Zone 3Sudan-Ethiopia,500KV,2022
Ethiopia-Kenya, 500KV,2015
Sudan-Egypt.600KV,2025
Kenya-Ethiopia,500KV,2020
Ethiopia –Eriteria, 220KV,2024
Ethiopia-Somaliland,200KV,?
Planned Interconnectors• EAPP Trade ZONE 3
Interconnector Capacity(MW) KV TechnologyYear expected to be
in Operation
ETH-KE 2000 500 DC 2016 (1000MW)
ETH-KE 2000 500 DC 2020
ETH-SUDAN 1200 500 AC 2022
ETH-Eriteria 400 220 AC 2024
Sudan-Egypt 2000 600 DC 2025
ETH-Somaliland ? 220 AC ?
CountryCountryCountryCountry Plant NamePlant NamePlant NamePlant Name Type Type Type Type Inst. Cap (MW)Inst. Cap (MW)Inst. Cap (MW)Inst. Cap (MW)
Eastern DRC Ruzizi III Hydro 145
Ruzizi IV Hydro 287
Ethiopia
Mandaya Hydro 2000
Gibe III Hydro 1870
Border Hydro 1200
Gibe IV Hydro 1468
Karadobi Hydro 1600
Rwanda KivuI Methane 100
Kivu II Methane 200
Tanzania Stieglers Gorge (I, II, III) Hydro 1200
Uganda
Karuma Hydro 700
Ayago Hydro 550
Murchison Falls Hydro 750
Identified Regional Generation Projects –NGP_RIP
INSTITUTIONAL CAPACITY BUILDING PROJECTS - 1
EC Technical Assistance & Capacity Building Project - EUROS 2.7m
�Objective is to strengthen the capability of Objective is to strengthen the capability of Objective is to strengthen the capability of Objective is to strengthen the capability of the EAPP Permanent Secretariatthe EAPP Permanent Secretariatthe EAPP Permanent Secretariatthe EAPP Permanent Secretariat
�Project constitutes the following componentsProject constitutes the following componentsProject constitutes the following componentsProject constitutes the following components
� Preparation of the Eastern Africa Power Preparation of the Eastern Africa Power Preparation of the Eastern Africa Power Preparation of the Eastern Africa Power Market DevelopmentMarket DevelopmentMarket DevelopmentMarket Development
� Preparation of a strategic plan and a 5 year Preparation of a strategic plan and a 5 year Preparation of a strategic plan and a 5 year Preparation of a strategic plan and a 5 year business planbusiness planbusiness planbusiness plan
� Preparation of Preparation of Preparation of Preparation of power market rules and power market rules and power market rules and power market rules and agreements for crossagreements for crossagreements for crossagreements for cross----border tradeborder tradeborder tradeborder trade
INSTITUTIONAL CAPACITY BUILDING PROJECTS - 2
Regional Master Plan & Grid Code Study Regional Master Plan & Grid Code Study
(AfDB/NEPAD IPPF) (AfDB/NEPAD IPPF) -- US$11.7m
�Objective was to develop EAPP/EAC Power Master Objective was to develop EAPP/EAC Power Master Objective was to develop EAPP/EAC Power Master Objective was to develop EAPP/EAC Power Master Plan & common Grid Code and train staff to enable Plan & common Grid Code and train staff to enable Plan & common Grid Code and train staff to enable Plan & common Grid Code and train staff to enable them update the master plan in futurethem update the master plan in futurethem update the master plan in futurethem update the master plan in future
�The project is completed and the Power Master The project is completed and the Power Master The project is completed and the Power Master The project is completed and the Power Master Plan and Grid Code final report submitted in May Plan and Grid Code final report submitted in May Plan and Grid Code final report submitted in May Plan and Grid Code final report submitted in May 2011201120112011
ONGOING INSTITUTIONAL CAPACITY BUILDING PROJECTS - 3
� Recruitment of staff for the CC and IRB Recruitment of staff for the CC and IRB Recruitment of staff for the CC and IRB Recruitment of staff for the CC and IRB ---- completedcompletedcompletedcompleted
� Installation and operationalization of the data base in Installation and operationalization of the data base in Installation and operationalization of the data base in Installation and operationalization of the data base in progressprogressprogressprogress
� Installation and operationalization of the Communications Installation and operationalization of the Communications Installation and operationalization of the Communications Installation and operationalization of the Communications Infrastructure Infrastructure Infrastructure Infrastructure ---- postponedpostponedpostponedpostponed
� Facilitation of Institutional set up of the CC and the IRBFacilitation of Institutional set up of the CC and the IRBFacilitation of Institutional set up of the CC and the IRBFacilitation of Institutional set up of the CC and the IRB
� Recruitment of Data Base Consultant Recruitment of Data Base Consultant Recruitment of Data Base Consultant Recruitment of Data Base Consultant ---- completedcompletedcompletedcompleted
� Recruitment of Training Consultant Recruitment of Training Consultant Recruitment of Training Consultant Recruitment of Training Consultant ---- completedcompletedcompletedcompleted
� Recruitment of Management Consultant Recruitment of Management Consultant Recruitment of Management Consultant Recruitment of Management Consultant –––– completedcompletedcompletedcompleted
� Training of 0ver 60 experts (Secretariat Staff and utility representatives) on issues of regional power trade
Ministry of Foreign Affairs Norway Project Ministry of Foreign Affairs Norway Project --
USD 2.2MUSD 2.2M
ONGOING INSTITUTIONAL CAPACITY BUILDING PROJECTS - 4
�Market development workshop held on 1-5 February 2009
�Renewable and Energy Efficiency Workshop held in March 2010
�Additional support to EAPP and EAC to prepare for Power Market and Power Trade.
�To ensure at least 3 PPAs are concluded
�Draft Transmission Interconnection Standards being considered by the Technical Committees and REC;
�Gap Analysis
USAID : Powering Progress PROJECT USAID : Powering Progress PROJECT -- 2.4m 2.4m
US$US$
INSTITUTIONAL CAPACITY BUILDING PROJECTS - 5
� Approval and implementation of Harmonized Approval and implementation of Harmonized Approval and implementation of Harmonized Approval and implementation of Harmonized Transmission Standards as identified by the Grid Transmission Standards as identified by the Grid Transmission Standards as identified by the Grid Transmission Standards as identified by the Grid CodeCodeCodeCode
� Study tours to PJM and WAPPStudy tours to PJM and WAPPStudy tours to PJM and WAPPStudy tours to PJM and WAPP
� Implementation of Regulatory Regime in line Implementation of Regulatory Regime in line Implementation of Regulatory Regime in line Implementation of Regulatory Regime in line with MFA, AfDB and EC Projects. with MFA, AfDB and EC Projects. with MFA, AfDB and EC Projects. with MFA, AfDB and EC Projects.
� Development of IDSDevelopment of IDSDevelopment of IDSDevelopment of IDS
USAID 2.4mUSD : Powering Progress USAID 2.4mUSD : Powering Progress
Project contd.Project contd.
CRUCIAL PENDING TASKS 1
�Harmonization of transmission standards is required to expand trade
�Implementation of the Regional Grid Code
�Cooperation from development partners, and participation of private and public utilities required to realize master plan (Through PPP, IPP?).
�Progressing capacity building until commencement of power market
�Supporting EAPP Secretariat until it is self sustaining
CRUCIAL PENDING TASKS 2
� Gap Analysis and filling the Gaps on ability to
trade in each Countries
� Full Establishment of the Coordination Centre (Regional Market Operations Centre)
� Full Establishment of an Independent Regulatory board (IRB)
� Staff attraction and retention (after the current training by EC & MFA)
� Full commitment by Regional Players
CONCLUSIONS
� Several power interconnections projects in
EAPP region are at various stages of implementation
�Most projects’ implementation has slipped -originally expected to be completed by 2012
� EAPP region now expected to be substantially interconnected by 2016/17 to facilitate regional power trade
�Various projects for institutional and human capacity building are either completed or are ongoing
� Some crucial tasks are pending and need to be addressed
Presenter’s Contact Details
• For any additional information, please do not hesitate to contact:
Eng. David M. MwangiEnergy ConsultantEmail: [email protected]: [email protected]: +254 20 8085287Mobile: +254 714 610026 / +254 722 741601Skype name: dmmwangi55
Thank You
for your attention