Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 April 5, 2018

Upload: others

Post on 27-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047

April 5, 2018

Page 2: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Presentation Agenda

PART A Bay of Quinte Skyway Bridge Rehabilitation (Site No. 11-245)

PART B Highway 49 and Old Highway 2/ York Road Intersection

Page 3: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Project Location

Highway 49 / Old Highway 2 Intersection

Airport Rd

Page 4: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

PART A: Bay of Quinte Skyway Project Location (Site 11-245)

BAY OF QUINTE SKYWAY (SITE #11-245)

BAY OF QUINTE

AIR

PO

RT R

OA

D

NO

RTH

PO

RT R

OA

D

COUNTY ROAD 49

Page 5: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Historical Photo - 1966

Page 6: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Existing Bridge Configuration

Page 7: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Background Bay of Quinte Skyway Bridge, Highway 49

Constructed 1964-1967 17 span high level bridge, 847 m long Carries 2 lanes on N-S oriented traffic Steel girders, concrete deck 5 continuous spans, 6 expansion joints 1992-dual columns replaced with single shaft at 3 piers

Page 8: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Existing Condition Deck: Extensively deteriorated (corrosion) Substandard barrier walls Substandard lane width Girders: Many fatigue prone details general coating failure Substructure: Generally sound except Pier 14 (beneath EJ) Minor scour at Pier 13 footing Abutments cannot accommodate widening

Page 9: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Bridge Rehabilitation Work

Replace superstructure

Reconstruct abutments, including new caissons, new wingwalls

Replace bridge bearings/alter bridge articulation

Eliminate expansion joints over piers

Rehabilitate and strengthen piers

New approach slabs

Reconstruct highway approaches to the bridge

Illumination

Page 10: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Rehabilitated Bridge Configuration

Continuous deck – no expansion joints over piers Road profile – same as existing

Page 11: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

New Superstructure

225 mm thick concrete slab TL-5 walls 4 steel girders 11.55 m wide deck Two 3.75 m traffic lanes Two 1.5 m wide side clearances 90 mm asphalt and waterproofing 2% crossfall

Page 12: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Construction Overview New superstructure with

4 steel girders

5 segments, replace 1 segment per year

‘Half-and-half’ staged construction with a single-lane of bi-directional traffic on the bridge controlled by temp. traffic signals for each Segment.

All lanes available during seasonal shutdown

Superstructure Replacement Scheme

Page 13: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Expansion Joint (EJ) Replacement

Eliminate existing EJ

Replace EJ and ramp over

Legend:

Temporary EJ required

Full closure required for modular expansion joint installation.

Page 14: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Construction Sequence Year Segment Major Work

1 - Advance work

2 C Replace segment

3 B Replace segment

4 D Replace segment

5 E Replace segment & Reconstruct abutment

6 A Replace segment & Reconstruct abutment

7 A Install EJ

Page 15: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Duration & Sequencing (1) 2018 (Year 1) Prepare site; procure structural steel for Segment C Structural steel repair (CIF) girders in west half of Segment C; Rehabilitate pier caps at Piers 8 and 11 Part B (Highway 49 / Old Highway 2 / York Rd. intersection) 2019 (Year 2) Replace Segment C superstructure Rehabilitate pier caps at Piers 5,6 and 7 to accommodate 2020 construction; Structural steel repair (CIF) girders in west half of Segment B Install traffic signals to accommodate 2020 construction 2020 (Year 3) Replace Segment B superstructure Rehabilitate pier cap at Pier 14 to accommodate 2021 construction; Structural steel repair (CIF) girders in west half of Segment D Install traffic signals to accommodate 2021 construction

Page 16: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Duration & Sequencing (2) 2021 (Year 4) Replace Segment D superstructure Structural steel repair (CIF) girders in west half of Segment E Install traffic signals to accommodate 2022 construction

2022 (Year 5) Replace Segment E superstructure Reconstruct south abutment and install modular type of expansion joint Rehabilitate pier caps at Piers 3 and 4 Structural steel repair (CIF) girders in west half of Segment A Install traffic signals for Segment A

2023 (Year 6) Replace Segment A superstructure and Reconstruct north abutment Install and maintain temporary ramp over expansion joint opening

2024 (Year 7) Install Modular Expansion Joint in Segment A Demolish Old Band Building

Page 17: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Construction Duration and Sequencing (3)

Page 18: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Construction Staging

2019

2020

2022

2023

Year 2 – 2019 – Segment C Year 3 – 2020 – Segment B Year 4 – 2021 – Segment D Year 5 – 2022 – Segment E Year 6 – 2023 – Segment A

2021

Page 19: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Seasonal Shutdown

Seasonal shutdown each year, all traffic lanes available

Work below the bridge deck is permitted; no traffic disruption

Work on Highway 49 affecting traffic or requiring lane closures not permitted

Page 20: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Traffic Management: Full Mainline Closures of Hwy 49 Type of Full Closure Description Short Duration Full Closures o 30 minutes during night hours (9 p.m. – 6 a.m.)

o Unlimited number Extended Duration Full Closures

o ½ - 2 hours during night hours (9 p.m. – 6 a.m.) o Maximum 52 occurrences

Full Night Closures o 9 p.m. – 6 a.m. o Police required o Maximum of 45 occurrences

No full closures permitted in 2018 Advance notification required Penalties for late opening

Page 21: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Traffic Management: Full Mainline Closures of County Rd 35

Passage for emergency vehicles shall be readily available at all times

Type of Full Closure

Description

Extended Duration o ½ - 2 hours during night (9 p.m. – 6 a.m.) o Police required o 5 occurrences

Page 22: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Restrictions on Crane Placement

No heavy equipment or cranes on any section of existing bridge in a 2 girder configuration

Page 23: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Snow Removal

Contractor responsible for snow and ice removal within work area

Remove within 3 hours of a snowfall event

Dispose at appropriate dump site

Snow removal plan each year

Snow removal against barrier by AMC, vacate work area

Page 24: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Utilities Bell and Hydro plant traverse Hwy 49 north of CR 35

Union Gas plant crosses beneath BOQ on west side of bridge

Portions of abandoned Union Gas main may be present within the

existing highway embankment near each end of BOQ Skyway Bridge

Page 25: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

MBQ Fishing Rights Area between piers 10 and 12 to remain accessible for MBQ to

exercise fishing rights during July and August each year Exception: only when construction work is performed between the

piers Advise intention to restrict access prior to May 15

Page 26: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Abutment Reconstruction Reconstruction of abutments & wingwalls Staged construction Four - 1200 mm diameter caissons with

steel liners at each abutment South abutment and caissons – Year 5 North abutment and caissons – Year 6

Page 27: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Navigation

Page 28: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Environmental Issues

Navigable waters permit Noise By Law exemption (must be renewed) Archaeological clearance Aeronautical lighting SARS Fisheries timing restrictions Spills Prevention

Page 29: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Environmental Constraints Environmental Specifics Species at Risk observed o Yes

o At least 9 species Blanding’s Turtle o Exclusionary Fencing to be installed prior to April 15 of 1st year of construction Barn Swallow o Netting required

o Breeding season timing window: March 31 - August 27 o Qualified Avian specialist required to screen for breeding migratory birds

Tree Removal o Prohibited between March 31 and August 27 o Within window – Qualified Avian Biologist to conduct a nesting survey

Timing window for Barge Operations

o For Segment C – No activity permitted between April 1 and May 20, 2019 o For Segment D – No activity permitted between April 1 and May 17, 2021 o No sediment plumes

Timing window for all other in water work

o July 1 to September 15

Page 30: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Existing Water Intakes

Page 31: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Spill Prevention and Response Contingency

Submit Plan for all activities within 30 m of watercourse

Barge, equipment and other operations shall be at least 50 m away from shore wells and municipal water intakes

Provide worker training

Review Plan annually

Page 32: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Police Jurisdictions

Area Police Service to be Contacted Tyendinaga Mohawk Territory Tyendinaga Police Service

Prince Edward County Ontario Provincial Police

Page 33: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

PART B Highway 49 and Old Highway 2/ York Road Intersection

Page 34: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Highway 49 and Old Highway 2 Location: Intersection of Highway 49 and Old

Highway 2/York Road Scope: Removal is existing NB channelized

right turn Adjustment to existing traffic signal

poles Ditching to ensure positive drainage

to existing ditch Benefit: Improves safety for

vehicles entering or leaving trading post, gas station

Page 35: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Highway 49 and Old Highway 2 Contract details: To be completed in Year one of Contract prior to October 31, 2018 Access to entrances to remain open Traffic permitted to travel on granular grade No open granular permitted on weekends

Page 36: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Summary Construction Start: Spring 2018

Late season work anticipated

All Traffic lanes restored during seasonal shutdowns.

Contract Completion: May 2024

Page 37: Rehabilitation of the Bay of Quinte Skyway Highway 49...Rehabilitation of the Bay of Quinte Skyway Highway 49 Pre-Bid Presentation Contract: 2017-4047 ... 2/ York Road Intersection

Thank you