relocation and shielding activities status and roadmap
DESCRIPTION
Relocation and shielding activities Status and roadmap. R2E project meeting, 7 th April 2011 A. L. Perrot. R2E shielding activities. Integration - all shielding walls = integrated; agreed by LHC integration team - official approval process to be launched through ICL Deadlines: - PowerPoint PPT PresentationTRANSCRIPT
Relocation and shielding activitiesStatus and roadmap
R2E project meeting, 7th April 2011A. L. Perrot
R2E shielding activities
Integration- all shielding walls = integrated; agreed by LHC integration team- official approval process to be launched through ICLDeadlines:Points 8: 13 AprilPoint 1: 20 AprilPoint 5: 4 May- simplified models still needed afterwards for implementation in CATIA models
Ordersall blocks are now ordered- Point 1 RBs special shape ‘frites’: 18th/19th April technical reception in Austria of the first 2 blocks by M. Lazzaroni and C. Saint Jal -pre-series of blocks 4x4 x2, 6x3x3: check by June in Bulgary by M. Lazzaroni and C. Saint Jal
LogisticsCleaning and painting of the ‘old’ blocks = finished yesterdayStorage place: blg 157 implementation storage area under progress
1
R2E shielding activitiesplanning
Blocks deliveryall @ CERN in November 2011- 4x4x2 & 6x3x3 : all delivered @cern in November 2011;- ‘frites’: all delivered @cern in June 2011- bricks: order sent yesterday - all delivered @cern end of June 2011
2011-2012 Xmas activities goals- Point 1:UJs & RBs,- be ready for Point US85
Courtesy M. Lazzaroni
LHC tunnel
IP1
Courtesy A. Tursun, J.- M. Bianco, F. Delsaux
US85
2
UJ17/16 - RB 16UJ13/14 - RB 14
R2E relocation activitiesIntegration studies- Point 8: finished- Point 5: see the end of the tunnel; finished by the end of April- Point 1: new proposal under check; need to know the exact position of the area
to empty -> CE input.- Point 7: need the ‘Safe room’ study conclusions to go ahead
Approval through ICL- deadlines- Point 8: 20th April;- Point 5: 4th May;- Point 1: 8th June;- Point 7: ?
2011-2012 Xmas shutdown goalsanticipate possible relocations – list of activities by Junemark on floor all the future equipment locations;- Point 8: valves positionners(t.b.c), cooling cabinet in UJ87-> UA87;- Point 1: fire detectors; - Point 5: survey GGPSO installation in by-pass 3
TODAY
UJ16
UL16Courtesy A. Tursun, Y. Muttoni
R2E relocation study in Point 1
A. L. Perrot, 2nd March 2011
Point 1- Relocation
4
“LHC Performance Workshop”, 25 January 2011, A. L. Perrot
2 Power Converters
RYCA 01RYCA 02
RYMCB 01-04
RYLB 01
RYLC 01
DYPG 02
DYPG 01CYCIP 01
QYC 02QYC 01
(additional rack)
TYCFL 01
DYXA 01
Fire detectors
Situation in UL14/16 after relocation(present study)
area to be reconsidered
additional rack
RYSC 01
Courtesy A. Tursun, Y. Muttoni
2 Power Converters
RYCA 01RYCA 02RYMCB 01-04
RYLB 01
RYLC 01
DYPG 02
DYPG 01CYCIP 01
QYC 02QYC 01
(additional rack)
TYCFL 01 to be relocated in US15 level 2 close to TYCCR01 rackDYXA 01Fire detectors
Situation in UL14/16 after relocation(new proposal)
area to be reconsidered
RYSC 01
A
B
C
distance A-B= 18.5mdistance A-C= 25m