renelle gronert masters thesis (2012)

203
SUSTAINABLE THERMAL RETROFIT OF THE NEW ZEALAND 1930’s – 1950’s LABOUR PARTY STATE HOUSE Renelle Gronert A thesis submitted in fulfilment of the requirements for the degree of Master of Architecture Sustainable, The University of Auckland, 2011. (Edited version)

Upload: renelle-gronert

Post on 11-Jan-2017

55 views

Category:

Documents


6 download

TRANSCRIPT

SUSTAINABLE THERMAL RETROFIT

OF THE NEW ZEALAND

1930’s – 1950’s LABOUR PARTY STATE HOUSE

Renelle Gronert

A thesis submitted in fulfilment of the requirements for the degree of

Master of Architecture – Sustainable, The University of Auckland, 2011.

(Edited version)

ii

ABSTRACT

Labour Party State Housing (LPSH) was introduced by New Zealand’s first Labour

Government, during a period in New Zealand history from 1937 - when the first house was

built - until 1949. It was the first and biggest scale of mass housing in New Zealand’s history,

which set the precedent for housing models that followed. After the demise of Labours

fourteen year term in government, the methodology of LPSH was adopted by private building

companies who continued to build suburbs of ‘group housing’ that had slight aesthetic

modification, but were built in the same way and of the same materials.

Most New Zealanders are familiar with the LPSH typology, as throughout the country there

are large neighbourhoods, and suburbs of these houses, standardised similarly enough to be

recognisable (although this was not the intention at their concept.) The various house

typologies that have evolved since, have added to their categorisation.

Up until 1978, New Zealand housing had no legislation for the provision of insulation, which

has left thousands of New Zealand houses suffering from cold temperatures, large amounts

of energy being wasted in heat loss; and contaminated indoor air quality (IAQ) causing ill

health of many occupants. A third of these are LPSH, which have unresolved problems since

they were built – they are cold, damp and mouldy.

The implications are that energy is being wasted due to heat loss that is transmitted through

the uninsulated building envelope, air gaps, passive ventilation and electrical heating, which is

wasteful of energy resources. These houses are problematic to occupant health, which

places a hefty burden on government funds for hospitalisation, and financial loss through lost

days at work and school.

Although improvements of insulation and ventilation have sometimes occurred, they are often

inadequate as they only address insulation to the ceiling and floor, omitting the walls and

windows. These building elements need to be adequately insulated to complete a thermal

envelope capable of retaining heat, maintaining indoor temperatures, as for the World Health

Organisation recommendation and healthy living conditions. Alternative technologies can

further improve comfort levels and indoor air quality of these houses, to the benefit of

occupant health, government expenditure, and carbon emissions to assist New Zealand in

meeting its commitments to the Kyoto Protocol.

As a holistic approach to energy retrofit of LPSH seem to be still lacking in New Zealand, this

thesis aims to identify correct and comprehensive intervention packages for this house type

and to verify their feasibility in the national building market, considering both, their affordability

and constructability.

iii

Practicing architects were interviewed to determine New Zealand common energy retrofitting

practice for LPSH. The interviews identified how budget constraints, or lack of consideration

limited the amount of intervention addressing higher levels of IAQ. Heat loss through air

movement and lacking thermal insulation had not been addressed, to ensure adequate

temperatures could be met, and maintained to the best possibility.

To rectify the problem of heat loss – i.e. energy efficiency and comfort - the use of a

continuous and airtight thermal envelope has been proposed in this thesis. The improved

thermal performance of the proposed solution has been then verified using Risk Matrix

evaluation and Homestar™ residential rating tool assessments.

In conclusion this research found that LPSH philosophy originally used in its establishment of

communities - sustainable neighbourhoods, blended communities, and houses that owners

are proud of - provided sustainable living by current definition. This confirmed that LPSH has

the potential to provide sustainable living in sustainable environments, thus substantiating the

case for its retrofitting.

iv

Dedicated to my daughters Jade and Georgia,

and to their children –

the future generation of New Zealand

v

I would like to acknowledge and thank

Professor Paola Leardini, who been my supervisor,

for her academic knowledge, and guidance;

My professional colleagues who kindly gave of their time to be interviewed,

and shared their knowledge and experiences;

And to my family and friends for their help and support.

vi

Table of Contents

CHAPTER 1: INTRODUCTION ...................................................................... 2

1.1 METHODOLOGY .................................................................................. 7 CHAPTER 2: THE NEED FOR ENERGY CONSERVATION ......................... 9

2.1 NEW ZEALAND AND THE KYOTO PROTOCOL.................................. 9

2.2 CARBON EMISSIONS AND BUILDING .............................................. 14

2.3 THE NEED FOR ENERGY REDUCTION ........................................... 14

2.4 ENERGY CONSUMPTION IN NEW ZEALAND .................................. 16

2.4.1 FUEL POVERTY .......................................................................... 19

2.4.2 POPULATION GROWTH IN NEW ZEALAND .............................. 19

2.4.3 THE GROWTH OF THE AGING POPULATION IN NEW ZEALAND .............................................................................................................. 20

CHAPTER 3: HOUSING IN NEW ZEALAND ............................................... 21

3.1 NEW ZEALAND’S CLIMATE ............................................................... 21

3.2 NEW ZEALAND HOUSING ................................................................. 23

3.2.1 HOUSING QUALITY ..................................................................... 24

3.2.2 BRANZ HOUSING SURVEYS ...................................................... 25 CHAPTER 4: HOUSING AND HEALTH....................................................... 29

4.1 HEALTH COSTS ................................................................................. 32

4.3 INDOOR AIR QUALITY AND HEALTH IN LABOUR PARTY STATE HOUSING ................................................................................................. 33

4.3.1 PENTACHLOROPHENOL: SOLUTION TO THE FIRST MOULD DISCOVERY IN LPSH........................................................................... 34

4.3.2 THE EXPERIMENTAL COTTAGE: TEST OF INSULATION, VENTILATION AND DAMPNESS .......................................................... 36

4.4 MOULD IN STATE HOUSES, POST 1990 .......................................... 39

4.5 THE HEALTHY HOUSING PROGRAMME ......................................... 40

4.6 INDOOR AIR QUALITY ....................................................................... 42

IAQ AND HEALTH ................................................................................. 42

4.6.1 CONTAMINANTS ......................................................................... 43

4.6.2 HEALTH RISKS RELATED TO MOULDS .................................... 46

4.6.3 MOISTURE AND DAMPNESS ..................................................... 47

4.7 THERMAL COMFORT ........................................................................ 50

4.8 AIRTIGHTNESS .................................................................................. 53

4.8.1 AIR TIGHTNESS TESTING – WUFI AND BLOWER DOOR ......... 55

4.9 VENTILATION..................................................................................... 57

4.9.1 PASSIVE VENTILATION .............................................................. 59

4.9.2 MECHANICAL VENTILATION SYSTEMS .................................... 60

4.10 IAQ GUIDELINES FOR NEW ZEALAND HOUSING ......................... 63

4.11 INSULATION .................................................................................... 64

4.11.1 THE HISTORY OF INSULATION IN NEW ZEALAND ................ 64

4.11.2 UNINSULATED NEW ZEALAND HOUSING .............................. 68

4.12 HEAT LOSS ...................................................................................... 71

4.13 INCENTIVES AND EDUCATION ...................................................... 74

4.14 THE NEED TO INSULATE ................................................................ 76

4.14.1 RESEARCH INTO THE BENEFITS OF INSULATION ................ 77

4.14.2 INSULATION IN NEW ZEALAND ............................................... 80

4.15 THE IMPORTANCE OF CORRECT INSULATION INSTALLATION .. 81

4.16 INSULATION PRODUCTS: ............................................................... 82

vii

4.17 WINDOWS ........................................................................................ 88 CHAPTER 5: THE HISTORY OF LABOUR PARTY STATE HOUSING ...... 89

5.1 THE POLITICAL HISTORY OF STATE HOUSING ............................. 89

5.1.1 PRE-LABOUR GOVERNMENT FUNDED HOUSING ................... 89

5.1.2 THE FIRST LABOUR PARTY ....................................................... 92

5.2 THE COMMENCEMENT OF LABOUR PARTY STATE HOUSING ..... 95

5.3 LPSH: SOLAR DESIGN .................................................................... 109

5.4 THE CONSTRUCTION OF LABOUR PARTY STATE HOUSING ..... 111

5.4.1 LABOUR ..................................................................................... 111

5.4.2 THE IMPACT OF WORLD WAR 2 .............................................. 112

5.4.3 PREFABRICATION .................................................................... 113

5.4.4 CONSTRUCTION MATERIALS OF LABOUR PARTY STATE HOUSING............................................................................................ 113

5.4.5 THE STRUCTURE AND EXTERIOR MATERIALS ..................... 115

5.4.6 THE INTERIOR MATERIALS ..................................................... 117

5.4.7 SERVICES ................................................................................. 118

5.5 THE END OF LABOUR PARTY STATE HOUSING .......................... 118

5.5.1 STATE HOUSING AND THE NATIONAL PARTY....................... 118

5.5.2 GROUP BUILDING SCHEME .................................................... 120

5.5.3 A REFLECTION ON LABOUR PARTY HOUSING ..................... 121 CHAPTER 6: THE FUTURE OF LABOUR PARTY STATE HOUSING ...... 122

6.1 ARCHITECT INTERVIEWS............................................................... 122

6.1.1 THE SELECTION OF ARCHITECTS .......................................... 122

6.1.2 THE INTERVIEWS ..................................................................... 124

6.1.3 SUMMARY ................................................................................. 133

6.2 LABOUR PARTY STATE HOUSING IN ITS CURRENT CONTEXT.. 138

6.3 SOCIETAL CHANGE IN OCCUPANT BEHAVIOUR ......................... 139

6.4 THE FUTURE OF LABOUR PARTY STATE HOUSING ................... 140

6.5 SUSTAINABLE ENVIRONMENTS .................................................... 141 CHAPTER 7: PROPOSED RETROFIT PACKAGE .................................... 143

7.1 THE HOMESTAR RESIDENTIAL RATING TOOL ANALYSIS .......... 143

7.1.1 HOMESTAR™ RATINGS ........................................................... 145

7.1.2 OUTCOMES FROM THE HOMESTAR™ RATINGS .................. 149

7.1.3 CONCLUSION BASED ON THE HOMESTAR RATING ............. 150

7.2 RISK MATRIX APPLIED TO A LABOUR PARTY STATE HOUSE .... 152

7.3 PROPOSED THERMAL INTERVENTION......................................... 155

7.3.1 REPLACING THE WALL LININGS ............................................. 156

7.3.2 INSULATION LEVELS ................................................................ 157

7.3.3 R-VALUES PROVIDED: ............................................................. 158

7.3.4 DRAWINGS OF THE PROPOSED SOLUTION .......................... 158 CHAPTER 8: CONCLUSION ..................................................................... 162

APPENDIX: ................................................................................................ 165

APPENDIX A – Participant Information Sheet For Architect Interviews ... 165

APPENDIX B - Consent Forms For Participating Architects .................... 168

APPENDIX C - The Questionnaire - Guideline For Interviews ................ 169

APPENDIX D - Homestar Ratings .......................................................... 171

APPENDIX D - Design Navigator - R-Value Calculation Sheets ............. 177

BIBLIOGRAPHY ..................................................................................... 190

1

“It is our collective and individual responsibility

to protect and nurture the global family,

to support its weaker members

and to preserve and tend to

the environment

in which

we all live.”

– Dalai Lama

2

CHAPTER 1: INTRODUCTION

Sustainability is about the capacity to endure; for humans it is the potential for long term

maintenance of well being, and responsibility for the use of natural resources (Oxford English

Dictionary, 2011).

The fuel crisis that has arisen as a result of the technological demands of increased human

development in the last century has prompted global awareness that recognises

improvements are needed to conserve energy. Respecting this, New Zealand has committed

to reduce carbon emissions in becoming a signatory to the Kyoto Protocol, which came into

force in 2005. The Kyoto Protocol was established to address global warming by committing

developed countries to reduce their green house gas emissions. As New Zealand is a

signatory to the Kyoto Protocol, it is required to reduce the carbon emissions, including those

caused by solid fuel used in energy generation.

Building construction, heating and transportation are all fuel intensive. As there is a need to

reduce the energy required for building and heating, this thesis investigates the sustainable

regeneration of an existing mass-built house typology commonly known as Labour Party

State Housing (LPSH) in New Zealand. Thousands of LPSH are in sound condition, located

in neighbourhoods that were designed to be lived in sustainably, but they are wasting energy

through their thermal inefficiency. Collectively, there is significant potential for energy savings

by thermally retrofitting existing LPSH. Their reuse regenerates already committed energy,

minimises the energy and product required for new build, and provides warm and healthy,

energy efficient homes for future generations.

New Zealand’s first Labour government had a long term goal for New Zealand people and

housing, that provided thousands well built houses that have endured, and have the capacity

to continue to provide for the nation. Walter Nash, Finance minister for the Labour Party at

the commencement of LPSH stated:

“Planning for housing on any national scale means in effect, planning for the future of

the Nation”.

The vision Nash had of long term provision for future generations by providing durable and

well built housing, was an investment in sustainable resource that is worthy of preservation,

although there is a need for intervention of modern technology to improve their energy

consumption.

3

LPSH was built from the late 1930’s with a unique and identifiable style that created the early

suburbs of New Zealand’s main cities and satellite towns. It was a historic venture for New

Zealand when the Labour Government committed to provide five thousand State owned

houses to provide affordable homes at fair rents to New Zealanders (Schrader 2005), and

many more were built throughout Labours governance. The mass dominance of LPSH in the

urban landscape is still recognisable more than eighty years later. They were of a simple

design, suited to the New Zealand climate and were built of quality materials intended to last

at least sixty years (Schrader, 2005).

The town planning for LPSH was designed to function ‘sustainably’. As privately owned

transport (cars) were not common at the time these neighbourhoods were planned, bicycles

and walking were the common modes of transport, with public transport linking home life to

employment in the city. They worked as sustainable communities, planned to function without

reliance on private vehicles by incorporating public amenities close by to service domestic

needs. Their heating does not fare as well sustainably. Electricity was a new, clean, easy to

use and inexpensive source of energy that was introduced into housing at the start of the

LPSH era. Although solid fuel burning open fire (and later fireboxes) was the primary heat

source designed into the living area of LPSH, electricity became more commonly used for

heating from the 1950’s.

Regrettably, LPSH had no insulation, and within two years of being built, they developed

mould as a result of them being cold and damp (District Inspector for Medical Officer of Health

1947). Mould has been recognised as one of the contaminants that are connected to poor

health, particularly asthma which is currently an expensive health problem for New Zealand.

The lack of insulation legislation in New Zealand prior to 1978 has left almost one million

houses in New Zealand with poor thermal performance, of which 45% have evidence of

mould, causing ill health of the occupants, and deterioration of the structure. Uninsulated

houses are cold, damp, draughty and mouldy, with poor indoor air quality that is detrimental to

the health and well being of its inhabitants. Their heating requirement is wasteful of valuable

fuel resources, and with increasing energy costs, will potentially become unaffordable for the

occupiers, who are often low-income earners. Improved environmental awareness and

education highlights the need to reduce the high heating requirements of these houses.

A third of these houses are LPSH, which are now averaging sixty years of age, having been

built through almost two decades that followed the opening of the first LPSH in 1937. This

house typology has endured time in its contextual situation. This thesis investigates the origin

of LPSH to understand its construction features improve indoor air quality and thermal

comfort of such houses, in a way that meets current international standards. This is done with

research to provide evidence for the need of a full thermally insulated envelope, and to

4

introduce technologies that successfully address the three factors required for a warm and

damp-free healthy indoor environment - adequate ventilation, heating and insulation (British

Medical Association 2003). Collectively, this has the ability to assist in improving air quality

and occupants’ health, and in the reduction of wasted energy consumption - therefore

lowering New Zealand’s carbon emissions in accordance with national objectives.

Affordable and appropriate housing should protect people from hazards, and promote good

health and wellbeing (World Health Organisation 1989). Inadequate or poor housing has a

documented impact on the health of occupants, with older housing being known to increase

the risk of deaths in winter (Wilkinson et al. 2001). The most common environmental hazards

that are associated with poor housing are dampness and low indoor temperatures (Howden-

Chapman, Signal et al. 1999). Scientific evidence linking warm homes and good health was

recently established by University of Otago researchers, who investigated houses occupied

by low income earners, demonstrating that properly insulated homes lead to significant health

gains (Howden-Chapman 2007). This is substantiated in the research report ‘National value

case for sustainable housing innovations making the case for the national benefit to be gained

by transforming the New Zealand housing stock – both new and existing - to improve

sustainability’. In this report, prepared by one of New Zealand’s researchers established for

the betterment of energy consumption, Beacon Pathway, it is agreed that when upgrading

existing housing stock, anything less than a complete thermal upgrade is inadequate and will

not provide an adequate solution to improve thermal comfort and energy efficiency (Beacon

Pathway Ltd 2007).

Uninsulated house construction looses heat through the floors, ceilings, walls and windows,

and through draughts within the house. Demand for heating is high, and attempting to obtain,

and maintain comfortable temperature levels is wasteful of energy, which is now an expensive

commodity that is expected to further increase as fuel resources become scarce. A

standalone timber framed house looses 39 - 48% of heat through the uninsulated walls and

windows, and 6-9% through air leakage, which means 45 - 51%, which is close to half of the

heat, is unnecessarily lost through poor building performance. Ceilings and floors of LPSH are

elements that are typically positioned in a secondary position to the external climate, as they

are protected by a roof, or foundation walls. By comparison walls and windows are a direct

barrier between the interior and exterior environments of the house structure. In not

addressing the walls and windows, cold temperatures, consequential condensation and

mould, and drafts into the house interior, require considerable heat to improve the indoor air

temperature. Walls and windows are elements of the structure that require more effort and

expenditure to retrofit, but the savings made in energy and health costs make such

consideration and implementation worthy. The ability to reduce energy consumption has not

been adequately resolved by insulating floors and ceilings alone.

5

In New Zealand, various organisations have been established to collect and process

information to provide solutions in which government and house owners / tenants can

ultimately reduce fuel consumption. Solutions that have evolved into practice focus on the

application of minimum levels of insulation to the ceiling and the floor of uninsulated older

houses, which government partially fund. Although ceilings and floors are easily accessed for

the installation of product, this solution merely addresses half of the heat leakage problem.

This is an inadequate solution as it does not reduce moisture, or create a thermal envelope

capable of sufficient heat retention to meet the World Health Organisation (WHO) minimum

recommended temperature of 18°C. A study on the efficacy of the energy efficient upgrade

programme in New Zealand undertaken by the University of Otago verifies that the simple

insulation upgrade involving only one aspect of the building envelope provides a low level of

thermal comfort. It comments that “if improving indoor thermal comfort, and at the same time

making energy efficiency of these homes was the goal, then more intensive housing

insulation measures, or better home energy efficiency technologies would need to be applied

to reach satisfactory health goals and promote energy efficiency in the residential area.’

(Lloyd, 2006).

To become familiar with, and to understand LPSH, the history of New Zealand politics that led

to the introduction of the State Housing scheme, established by the Labour Party of 1935 –

1949 is researched, enlightening on the political ideology that shaped the scheme. This

presents the political structure, philosophies and developmental departments that introduced

the new style of town planning and house design, construction methods and materials used.

The Labour Party philosophy encouraged the development and manufacture of New Zealand

made materials to be used for the construction of State Housing, leading to the establishment

of many companies that are still in existence today. The materials and construction

technology used to build the houses is researched as described in the methodology section of

this chapter. Research into the archival history of the LPSH discovered that moulds were

evident within two years of the houses being built. Issues related to insulation, ventilation and

moisture were recognised and investigated, but not implemented to the long term detriment of

thousands of houses, the health of their occupants and government expenditure in health

related costs.

A standalone Labour Party State House located in Auckland has been selected as a case

study to verify feasibility of identified retrofit solutions and application for some assessments.

This is because this type of house is very common in Auckland and is usually occupied by

lower income earners, typically the elderly, sick or young families who are vulnerable to poor

health, and have less available income to adequately heat the homes the State allocates to

them. By selecting this typology that is architecturally familiar, there is hope for their

preservation and heritage value, by sustainably recycling these well-built houses that embody

quality products. It is sustainably preferable to preserve, rather than discard, existing houses

6

of a good standard. The preservation of older houses minimises energy and product waste,

meanwhile providing for homes future generations. Improving the quality of the internal

environment maintains the health and well being of the occupants, and adds value to the

houses. In retaining existing LPSH, their neighbourhoods that were designed to function

sustainably can also be preserved, with their missing elements of infrastructure assessed for

worthwhile reinstatement.

To investigate the approach of New Zealand architects that have designed renovations for

state houses (of the era studied in this thesis), interviews of ten selected practicing architects

were conducted to research how they addressed State housing. A list of interview questions

enquired of the priorities set by the house owner and of the architect, and how they were

resolved. In particular the research was to understand the importance of thermal and indoor

air quality, if at all.

LPSH of the 1930’s through to the 1950’s are an important part of New Zealand’s history that

still remain as sturdy, existing housing stock of varying condition. The condition of some

interiors has deteriorated largely due to neglect, but refurbishment is uncomplicated. Their

native timber framing structure endures, although it is apparent that their neglect has changed

the way these houses are valued, evident in this comment by the well-known historian Ben

Schrader:

'In the 1930's securing a State House was viewed as a "step up", but by the 1970's it

had come to be seen as a step down' (Schrader 2005).

Research and investigation undertaken on LPSH for this thesis, finds them worthy of

preservation to provide warm comfortable homes that sit within communities that are worthy

of reactivation. The mass ownership of LPSH by the Government offers quantum, their quality

of construction is typically sound, and their size renders them easy to work on. The repetitive

design of State Housing uses standardised details, materials, components and size which

simplifies retrofit on mass, and has added potential for economy.

This thesis supports retrofitting existing uninsulated and inadequately insulated New Zealand

LPSH for thermal comfort, to preserve energy consumption and to assist in meeting New

Zealand’s commitment to the Kyoto Protocol. An effective retrofit strategy includes insulating

the entire envelope of the house and improving air-tightness and ventilation, to create warm

healthy home capable of retaining heat, with consequential health improvements and reduced

heating expenditure for the occupants of the house.

7

1.1 METHODOLOGY

The documentation and data for this thesis has been collected from two main sources.

A literature review was undertaken of relevant publications on the history of LPSH. Books

and thesis provided historical records that included some interviews of State house tenants.

Research of many agencies engaged by, or provided by government to establish the direction

of sustainability; building codes; statistical and climatic records; housing related health

problems, and housing conditions provided information that related to New Zealand.

International research of reports and studies provided information that was for international

comparison. These sources of information were used in Chapter two in which commitments

and the need for energy consumption is presented; and Chapter four in which indoor air

quality (IAQ), is presented. In Chapter four, issues that effect IAQ and the associated health

problems are discussed. The technologies for improved IAQ are presented, which includes a

history of insulation in New Zealand, which has influenced the condition of housing and

impacted on occupant health for one and a half centuries.

The information presented in Chapter six on LPSH was researched through historical record

books, archived historical information and an interview with a historian.

New Zealand Archives in Auckland and Wellington (the information at Christchurch archives

was not accessible as a result of earthquake damage) were researched to find photographs

and records from the time they were built. Information found was in the form of original plans,

elevations, sections and a few details of hundreds of houses, which provided information on

how they were constructed. Photographs taken during construction also provided a visual

record of what was built in the structure. Archived Government memos and instruction for

tests that were applied to a model State house, and the conclusion to potentially resolve the

problems encountered provided valuable insight into the awareness of factors that impact on

IAQ. A historic researcher for a recent publication on Fletcher Construction was informative

on many aspects of the origins on LPSH as Fletcher’s were its largest builder. She also

provided clarification of some previously published inaccuracies, verified through historical

records.

Chapter three presents information on the climate of New Zealand, and its housing. This

includes information from the recent BRANZ surveys of 2005 and 2010, to include visual

record in the form of photographs that shows the poor condition of many New Zealand

houses.

8

The second source of information was personal interviews with a number of practicing

architects, and the information from these is presented in Chapter six. The interviews were

based on a series of prepared questions to extract information on each architects’

experience/s with working on LPSH. Information sought involved age of the house, the extent

and dates of the works undertaken, a summary of the requirements, the brief and budget to

meet, the resultant design, what interventions were adopted and applied, how they found the

structure to work with and a summary of post-construction follow-up where possible.

Practicing architects that have been involved in designing or altering LPSH were invited to

participate by being interviewed on their knowledge and experience relevant to the works they

had completed. The invitation was made through a website for architects (NZIA chat). The

interviews were conducted either in person by meeting at the architects offices where

possible, or by telephone conversation. The interviews were done to determine what

common practice was, and what thermal interventions were introduced into renovation design

of LPSH. From these interviews, it was apparent that budget constraints or lack of

consideration had limited the amount of intervention used to address higher levels of IAQ.

Although improvements were made to the insulation and ventilation levels, these could be

advanced further to improve comfort levels, IAQ and heat retention. The improvements

identified provide an eco-retrofit package for LPSH, which has been applied to a case study in

Auckland. A housing risk matrix (E2/AS1) used to assess how appropriate the weather

tightness of LPSH is, Design Navigator thermal calculations were used to evaluate thermal

performances, and the outcomes of the interventions selected in this thesis were verified

using Homestar™, the New Zealand residential rating tool for the assessment of comfort,

health and energy-efficiency. The outcome is presented within Chapter seven.

The final Chapter eight concludes that the research of this thesis finds LPSH worthy of

investment into their sustainable thermal retrofit.

9

CHAPTER 2: THE NEED FOR ENERGY CONSERVATION

2.1 NEW ZEALAND AND THE KYOTO PROTOCOL

A fuel crisis has arisen as a result of the technological demands of human development in the

last century; affecting climate change, resource availability, and population change (New

Zealand Ahead 2010). As building construction, heating, and transportation are all fuel

intensive, improvements to existing housing stock offers some resilience to these global

challenges.

The Kyoto Protocol, an international agreement that was established by the United Nations

aims to address global warming and delay climate change. The Kyoto Protocol treaty was

negotiated on December 11, 1997 in the city of Kyoto, Japan and came into force February

16, 2005. It legally binds thirty-seven industrialised countries and the European Community

to reduce collective emissions of greenhouse gases (GHG) by 5% compared to the levels

they were in the year 1990. The emissions from six greenhouse gases are to be reduced,

being carbon dioxide, methane, nitrous oxide, sulphur hexafluoride, HFCs and PFCs.

As a signatory to the Kyoto Protocol, New Zealand has made a commitment to reduce its

greenhouse gas emissions to the levels that were produced in 1990. In 1990 our gas

emissions were 61,912,947 tonnes CO² equivalent and since then average annual emissions

have grown by 1.3% per year (Ministry for the Environment 2010). Where the Kyoto Protocol

is a committed agreement between countries, the United Nations Framework Convention on

Climate Change (UNFCCC) differs in that it is an international agreement for the

encouragement of industrialised countries, such as New Zealand, to stabilise GHG emissions.

For a country deemed to be clean and green, New Zealand in fact has one of the worst

carbon footprints in the world, as seen in its greenhouse gas emissions recorded by

UNFCCC.

10

Figure 2. 1 Total aggregate gas emissions of individual Annex I parties, 1990 – 2008

(Source: UNFCCC)

11

New Zealand gas emission performance is very poor by comparison to other countries of

similar population and GDP. Countries such as Denmark, Finland and Sweden have had a

similar economic growth to New Zealand over the Kyoto period, with emissions decreased by

3 – 7%, whereas New Zealand’s grew by 25% (Buckwell 2010).

Figure 2. 2 Greenhouse gas emissions for New Zealand

(Buckwell 2010)

GHG are a collection of carbon dioxide (CO²), methane and nitrous oxide, with CO² having

the highest volume emitted by human activity. These gases have increased with global

development, and continue to accumulate causing a warming effect once released into the

atmosphere. A 2°C increase in the average global temperature would impact on climate

change dangerously. For a 50% chance of preventing this, significant emission reductions are

needed. The average global emissions rate of 7 tonne per person in 2010, would need to

reduce to 4 tonne by 2030 to be effective (New Zealand Ahead 2010).

A warming trend is evident in New Zealand over the last few decades. Record collecting of

temperatures between 1930 and 2008 from the eleven climatic stations around the country

has shown an increase of 1°C in the average annual mean temperatures.

12

Figure 2. 3 1930 – 2008 Temperatures’ recoded for New Zealand

(National Institute of Water and Atmospheric Research 2010)

The targeted rate to match 1990 GHG emissions of 61.9Mt, would equate to a distribution per

capita of 14.8 tonnes for the targeted period between 2008 and 2012 (New Zealand Ahead

2010). In September 2010, New Zealands CO² emissions per capita were 17.9kt, maintaining

a poor ranking amongst the other twenty eight OECD countries. Being twenty-fourth rated

New Zealand as maintaining ‘high emissions’ and ‘making little progress’ (New Zealand

Ahead 2010). New Zealand’s energy emissions have increased by 23% between 1990 and

2008, placing us with the fifth highest emissions rate per capita in the OECD (New Zealand

Ahead 2010). A reduction of between 10 and 20% is necessary to progress with meeting our

Kyoto Protocol commitments, therefore significant savings in energy need to be made to

avoid significant government expenditure. Although New Zealand has the ability to gain

emission credit transfers through carbon sinks, such as forestry, it is still probable that there

will be a cost of $820 million for the Kyoto period (to 2012) that will ultimately met by the

taxpayer (New Zealand Ahead 2010).

Figure 2. 4 New Zealand’s position by international comparison for greenhouse gas emissions for

2008. (New Zealand Ahead 2010)

13

Figure 2. 5 Performance vs. Kyoto targets based on 2008 emissions

(New Zealand Ahead 2010)

New Zealand is a high user of energy with consequent high levels of GHG emissions. The

country’s energy is supplied by imported oil, gas and coal, being fossil fuels; and renewable

energy sources used are hydro, wind and geothermal generated.

The generation of electricity, heat production and transportation are the main factors that

have increased GHG emissions, and it is clear this needs to reduce rather than increase. In

New Zealand, in 2008 the energy sector produced 34,017.77Gg carbon dioxide equivalent

(CO2-e), which is 69% of the country’s total GHG emissions (United Nations Framework

Convention on Climate Change 2008). Of this, a contribution of 10% (3.4 Mt) was from

energy used in housing (Energy Efficiency and Conservation Authority, 2008). It is estimated

that a typical new Zealand house emits over three thousand kilograms of carbon monoxide

annually (Level). As energy related emissions in 1990 were 23,1974Gg (United Nations

Framework Convention on Climate Change 2008), there has been an increase of 43.8%, so

rather than decreasing to meet international commitments, New Zealand's energy

requirements increase by over 2% a year (Beacon Pathway Ltd 2005).

Transportation contributes to 40% of New Zealand's CO² emissions. Private car use

consumed 42% of energy consumption in 2003, and car use has increased since then at a

rate of 13,000 per year. Auckland has over 260,000 cars on its roads each day, costing an

average of about 18% of household expenditure (Beacon Pathway Ltd 2005).

As global energy resources become scarce, efficiency of the use of all energy is imperative.

14

Figure 2. 6 New Zealand’s energy emissions by category from 1990 to 2008

Note: Emissions from electricity generation are included in energy industries.

(Environment, 2010)

2.2 CARBON EMISSIONS AND BUILDING

Building construction emits a number of GHG, with CO² being the largest contributor.

Manufacturing and building contribute 17.7% of New Zealand’s carbon emissions created

through construction and its related processes of material manufacture, processing and

transportation (Level). Once occupied, a house emits more carbon, and at the end of its life,

demolition involves further carbon emissions.

Available technology has the ability to reduce energy consumption considerably by simple

changes to the building envelope, including solar heating, and other that could reduce carbon

emissions.

2.3 THE NEED FOR ENERGY REDUCTION

As the worlds population has grown, particularly in the last few decades urbanisation and

industrialisation has increased. The global population living in urban areas has expanded

from being 30% of the population in 1950, to 50% now (Wilkinson, Smith et al. 2007), and this

is forecast to grow over the coming decades. With such growth there is an increase in the

built environment which absorbs increasing quantity of materials and energy to meet human

demand. A challenge for the future is in providing the population with the provision of energy,

without increasing GHG emissions, reflecting the need for global energy efficiency.

Internationally, many houses are of an age that predated energy use and thermal comfort as

we know it. By comparison, New Zealand is a relatively new developed country and its

15

houses, although predominantly lacking thermally were designed within the era of available

energy sources.

The Energy Efficiency and Conservation Authority (EECA) is a government agency working

for the betterment of energy efficiency. The Energy Efficiency and Conservation Act was

established in 2000 binding government to promote energy efficiency, energy conservation,

and renewable energy. Under this act strategies have been prepared outlining the required

objectives, and how they can be achieved. The New Zealand Energy Efficiency and

Conservation Strategy (NZEECS) was written in 2007 as part of governments response, with

a plan of action for meeting its energy, climate change, sustainability and economic

transformation goals (Energy Efficiency and Conservation Authority 2007). EECA consults

with a number of researchers, universities, government research institutes, private

consultants and the energy industry both nationally and internationally (Europe, North

America and Australasia), seeking expertise on energy efficiency, energy conservation and

renewable energy. National research agencies it engages with include the National Energy

Research Institute (NERI); the Ministry of Research, Science and Technology; the Ministry of

Economic Development; and the Foundation for Research, Science and Technology Energy

Efficiency and Conservation Authority, 2011).

In attempting to kerb our increasing reliance on energy consumption, Beacon Pathway was

established in New Zealand in 2004, as a collaborative research consortium to find affordable

ways to make New Zealand homes more sustainable by researching building technologies;

construction industry practices; urban planning, policy and regulation; and also meeting and

understanding consumer needs. The consortium is comprised of members with residential

connections, being Fletcher Building, (the largest building company of Labour Party State

Housing), Waitakere Council, (known for their progressive sustainability initiative), NZ Steel,

Building Research, and Scion (New Zealand Forest Research Institute).

Their goal was to revise the standard of sustainability of houses throughout the country by

2012, and to ensure new and redeveloped subdivisions or neighbourhoods from 2008

onwards are created with reference to a nationally recognised sustainability framework that

acknowledges the importance of communal and infrastructure facilities that service

neighbourhoods (Beacon Pathway Ltd 2005). The goals were set to use diminishing

resources wisely to reduce fuel requirements for energy, addressing heating and

transportation fuels, as well as water conservation.

Government started campaigning to educate New Zealanders on climate change, and

measures that can be undertaken personally to assist in reducing our consumption, thereby

minimising our GHG emissions. The government established the Sustainable Development

Programme of Action in 2003, ensuring government lead by example on moves towards

becoming carbon neutral, and that government decision making ensured the ‘well-being of

16

current and future generations (Ministry for the Environment 2008). ‘Towards a Sustainable

New Zealand’ is directed at householders and businesses with the intention of making

enduring changes in behaviour that are favourable to rectifying the global climate change that

is currently active.

Targeting the residential market, government established the ‘Household Sustainability

Campaign’, which commenced in 2007, to increase sustainability into the everyday life of New

Zealanders, particularly relating to energy efficiency, water use, transportation, waste and

house construction. This campaign targeted and intertwined sustainably minded people,

regional and local government, and house owners seeking improvements in energy efficiency

both in homes and transportation. Guidance is given through this by way of practical tips, and

direction towards relevant home improvements.

2.4 ENERGY CONSUMPTION IN NEW ZEALAND

Historically in New Zealand, solid fuel heating has predominated. Until the mid 1900’s coal

ranges were commonly used as space heaters that also heated water and provided for

cooking. New energy technology was introduced about the same time as LPSH commenced,

which was clean, convenient, readily available, and able to be turned on with the flick of a

switch. Gas became available in the early 1900’s, and New Zealand’s hydro-electric

schemes and supply networks made electricity available as of the 1930’s. In the 1960’s the

supply of gas and electricity became more plentiful, reliable and affordable. There was

increased hydro-electric generation in NZ, and natural gas which was discovered in Taranaki

was reticulated through the North Island. Electricity prices fell over the 1950s and 1960s,

which encouraged its use (Ministry for the Environment 1998-2010).

Latterly there has been a change in the source of heating from other fuels to electricity

(Efficiency and Energy Conservation Authority 2009) as proven by the recent increased use

of heat pumps for space heating – from 16,000 in 1999 to 111,000 in 2007. Although

recognised as having ample ability to increase the room temperature, they work to cool as

well. This has introduced an additional load into New Zealand energy consumption,

extending the demand on energy to peak in summer and winter, as experienced in USA &

Australia (Mc Chesney, Cox-Smith et al. 2008). The growing use of heat pumps may have

influenced a 3% increase in electricity consumption between 2001 and 2007, as there is a

related decline in the use of gas and solid fuels (Efficiency and Energy Conservation Authority

2009).

Although prices have increased (Efficiency and Energy Conservation Authority 2009), New

Zealand residential electricity is still one of the lowest in the industrialised world, being

approximately 60% of the price paid by European consumers (Ministry for the Environment

17

1998-2010). Although technology is available to reduce energy consumption, while prices of

energy are low it will continue to be used. Regulatory requirements are necessary to ensure

corrective measures are implemented for energy conservation in new and existing buildings

(Lowe, 2000).

Figure 2. 7 International comparison of residential energy prices

Source: HEEP

Figure 2. 8 NZ residential energy consumption

Source: NZ Home Energy Web 2008

Residential energy use accounts for 12% of New Zealand’s energy consumption per year,

and 33% of the electricity consumed (Energy Efficiency and Conservation Authority, 2009).

Although renewable sources such as hydro-generation provide about two-thirds of the

electricity consumed in New Zealand, the balance is generated using coal and gas. Coal and

18

gas, being fossil fuels, emit CO² which is one of the GHG targeted for global reduction

(Ministry for the Environment 1998-2010).

Beacon Pathway, estimates that to heat a home to temperatures that meet the minimum

WHO standards the average New Zealand household requires 12,300kw/h of energy per year

(Beacon Pathway Ltd 2007). That the average use recorded is 10,500kw/h, substantiates

that in New Zealand, we under heat our houses. This recorded level of consumption is

comparably less than other developed countries of a similar climate, (Isaacs, Camilleria et al.

2006) being 30% less than used in Australia, 50% less than used in the UK and 70% less

than is used in Canada (Efficiency and Energy Conservation Authority 2009). Residential

energy consumption in New Zealand is growing. Since 1995, New Zealand’s residential

energy use has increased by 19.4%, from 54PJ to 64.5 PJ in 2007. A growth of rate of 1.5%

annually between 2001 and 2007 increased consumption from 59PJ to 64.5PJ (Efficiency and

Energy Conservation Authority 2009).

The magnitude of energy committed to use for space heating depends on size of house and

external climate, and as house sizes have increased, so has the demand on energy. Space

heating uses 35% of the energy consumed in homes, which is estimated as being 23 PJ

(TE210 Beacon). This is 4% of New Zealand's energy. Currently, $1.1 billion is spent by

New Zealand households each year on space heating, water heating and appliances (Energy

Efficiency and Conservation Authority 2009). The most important fuel source for heating is

electricity, and solid fuel for space heating, (solid fuel being coal or wood) (Isaacs, Camilleria

et al. 2006), with solid fuel providing the better source of heat. Energy consumed in homes

for space heating, of which electricity accounts for 69% and solid fuel for 20%, are two areas

identified for finding energy efficiency savings within (Isaacs, Camilleria et al. 2006).

Figure 2. 9 Total energy use by fuel type - Total energy use by end-use

Source: Household Energy End-use Study (HEEP).

19

2.4.1 FUEL POVERTY

Low temperatures are found in housing of various income levels, but ‘fuel poverty’ is defined

as ‘the requirement of spending more than 10% of income on energy’. The inaffordability of

fuel for heating impacts more severely on low income households and this is common in New

Zealand. The Household Energy End-use Study (HEEP) was a long term study undertaken

by BRANZ to collect data on energy use in New Zealand. The study conducted between

1995 and 2005; found that 28% of New Zealanders were in fuel poverty, with the inability to

adequately heat homes to create healthy living temperatures due to financial constraints

(Isaacs, Camilleri et al. 2005). This socio-economic group includes young families, those

already suffering from ill-health and the elderly, who as well as being on limited incomes, are

also the more vulnerable groups of the population. Heating is often unaffordable for

occupants, and certainly is not retainable without adequate thermal insulation. Fuel poverty

compels occupant confinement to a single heated room ‘zone’. ‘Zoned’ heating leaves the

remaining areas of the house cold and damp, which is a particular problem for bedrooms in

which occupants sleep in an unhealthy environment for almost a third of their 24 hour day

(WHO, 2009).

The elderly often live on their own, and typically have a very limited income (being in the

category that typifies fuel poverty), inaffordability of fuel for heating means they are forced to

endure very cold living conditions. Future increases in the cost of energy for heating,

antagonises this situation, with the likelihood that these houses will continue to be cold and

damp, potentially effecting the health and mortality of the vulnerable elderly, and adding to

national health expenditure.

With the predicted increases in energy costs, inaffordability will restrict adequate heating of

houses in winter, and puts lower income earners in a vulnerable position, that requires stable

and economical means to maintain warmth and health within their homes.

2.4.2 POPULATION GROWTH IN NEW ZEALAND

Population growth influences levels of consumerism and resource efficiency unsustainably, so

global population growth is of great concern, particularly as it is forecast to reach seven billion

by 2012, and over nine billion humans on the earth in 2050. This has a drastic impact on the

planet and its limited resources. The population growth of the developed world with its

expectation of high living standards is not sustainable. The growing population is not living

within the means of what the planet can provide forever, and typically it is the developed

countries higher standard of living that expends resources.

20

2.4.3 THE GROWTH OF THE AGING POPULATION IN NEW ZEALAND

New Zealand is one of the developed countries of the world, with an expected population

growth of the current population of 4.37 million, to increase to 5.09 million by 2031.

Population growth impacts on housing requirements expected to increase to 2.09 million

dwellings, which will also increase energy consumption.

The age of the population is also increasing, and by 2031 the estimated average age

expectancy is 82.5 years for males and 86.2 years for females. The growth rate of those over

50 years of age is expected to increase by 63% between 2006 and 2031, reflecting a global

trend of an increased aging population in the OECD. The current portion of New Zealand’s

population that is aged between 65 and 79 has grown by an average 2% per annum over the

last decade, and the older age group of eighty years and over grew by 3.4% in the same

period. Within the next decade, New Zealand’s post-war ‘baby-boom’ generation will start to

reach the retirement age of sixty-five, with an expected increase from 550,000 in 2009, to

about a million, over the next two decades (NZ, 2009). This is an anticipated growth rate from

the current approximately twelve percent of the population that are aged over sixty-five, to a

potion of twenty percent by 2031. Demographically, it is evident that the over sixty–five year

old age group has the most rapid population growth. The aged require higher temperature

levels, and without management, this will add to the energy demands for heating unless

adequate provision is made.

Figure 2. 10 New Zealand Population and projected growth 1951-2061

Source: Statistics New Zealand

21

CHAPTER 3: HOUSING IN NEW ZEALAND

3.1 NEW ZEALAND’S CLIMATE

New Zealand is a long thin country located between latitudes 34 deg and 48 deg south

(NIWA). The country’s length has coastal exposure, and the topography of the land varies

from mountainous ranges to flat plains. Located relatively remotely from other land masses in

the southern hemisphere, New Zealand is positioned between the tropics and the sub-polar

south, which exposes the country to atmospheric circulation that is affected by warm winds

and tropical storms from the north, and sub-polar westerly winds form the south (Ummenhofer

and England 2007). Consequently there is a wide range of temperatures and conditions that

housing needs to address, with regional differences influencing the regulatory insulation

requirements for housing into three zones. The map in figure 3.1 shows the average

temperatures of the colder areas of the South Island, and the mountainous central North

Island. The top of the North Island, where Auckland is situated, has warmer temperatures.

Figure 3. 1 New Zealand’s average daily temperatures 1971 - 2000.

(National Institute of Water and Atmospheric Research)

22

The climatic conditions for the northern region of New Zealand is sub-tropic with maximum

summer temperatures that range between 22°C to 26°C, occasionally reaching temperatures

that are over 30°C, and winter maximum temperatures that range from 12°C to 17°C. The

prevailing wind is from the south-west, with coastal breezes through summer. It often rains

through winter, and tropical storms can cause high winds and heavy rainfall during summer

and autumn (National Institute of Water and Atmospheric Research). As New Zealand’s

landscape comprises many coastal areas and river valleys, it can be expected that with the

predicted climate change (global warming) the increased storms, rain and flooding it brings

will mean such areas will be more exposed to dampness than the inland areas (WHO, 2009).

Auckland is within the northern region, and it is the largest city in New Zealand with over a

third of the population living there. National Institute of Water and Atmospheric Research

(NIWA) records from between 1971 to 2000 for Auckland, show winter temperatures that

range from 7.1°C to 15.8°C, and in summer from 14.5°C to a maximum of 23.7°C. Mean

temperatures for Auckland range between 19.8 °C in February and 10.8 °C in July (National

Institute of Water and Atmospheric Research).

MEAN MONTHLY AIR TEMPERATURE FOR AUCKLAND (°C)

Data are mean monthly values for the 1971-2000 period for locations having at least 5 complete years of data

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC YEAR

19.3 19.8 18.5 16.2 13.7 11.6 10.8 11.3 12.6 14.1 15.8 17.8 15.1

Mean monthly air temperature for Auckland (National Institute of Water and Atmospheric Research)

Rainfall ranges from a summer minimum of 70 mm in February to a winter maximum of 130

mm in July. Winds are predominantly southwest, with the north east being secondary.

Auckland is known for being humid, with an average RH level of over eighty percent.

MEAN RELATIVE HUMIDITY FOR AUCKLAND (%)

Data are mean monthly values of 9am relative humidity for the 1971-2000 period

for locations having at least 5 complete years of data

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC YEAR

77.1 78.3 79.0 82.2 85.2 89.0 88.5 85.7 80.2 76.8 76.3 75.9 81.1

Mean relative humidity for Auckland (National Institute of Water and Atmospheric Research)

23

3.2 NEW ZEALAND HOUSING

Housing represents the most significant single item owned for most New Zealanders.

Housing stock is estimated to consist of between 1.5 and 1.6 million dwellings, with a value of

about $178 billion (Clark, Jones et al. 2005), making it the largest portion of the New Zealand

built environment. Approximately 80% of dwellings are standalone houses, most of which

were built from the 1950's through to the 1970's as single storey buildings (Bengtsson,

Hargreaves et al. 2007).

There are currently between 700,000 and 900,000 homes that are not insulated to 1977

standards (Amitrano, Page et al. 2006), have poor thermal performance and consequently are

cold and damp. Of these houses, 45% of them have evidence of mould, which contributes to

the ill health of the occupants, and deterioration of the structure (Clark, Jones et al. 2005).

A third of these houses are Labour Party State Houses. Although many houses have been

upgraded, the inadequacy of the level of insulation product and fitment does not meet current

standards, and will be unable to meet the recommend temperatures aimed for to meet WHO

recommendations. Such housing requires copious amounts of energy to raise and maintain

temperatures to an adequate comfort level. As occupants spend up to 90% of their lives at

home, thermal comfort and a healthy indoor environment is important, largely for health

reasons, but there are additional benefits of having warm and healthy housing.

Almost a third of New Zealand homes fall below the World Health Organisation recommended

indoor temperature of 18°C. More than a quarter have unflued gas heaters, which result in

high levels of condensation inside houses. On average, New Zealand housing is 6°C below

the World Health Organization recommended minimum temperatures in winter. Almost half of

them are mouldy. They are cold, damp, draughty and hard to heat in winter, and

improvement of the indoor air environment is required to meet current international standards.

Little has been done in New Zealand to improve the situation with regards to old, thermally

inefficient houses, until recently. There are a number of organisations established in New

Zealand to educate, encourage and incentivise heating and thermal improvements to homes.

But, these focus on retrofitted insulation to the ceilings and under-floor, which accounts for

about half of the amount of heat loss, leaving the balance of the heat to escape from the

house interior through the walls, windows and air gaps. This is wastage of global energy

resources, and an unnecessary financial expense for the occupant. It also lacks in the

provision of adequate indoor air quality.

Improving the energy efficiency of existing houses has the potential to reduce the impact on

the environment by reducing fuel consumption and operational CO² emissions, while also

improving thermal comfort conditions. With peak oil predicted this decade, fuel costs are

24

expected to rise due to the scarcity of resources (Lloyd 2010); therefore it is practical to

explore retrofit options urgently. If 900,000 uninsulated, or insufficiently insulated houses

were insulated with complete thermal envelopes, substantial amounts of wasted energy could

be conserved that are currently consumed attempting to maintain interior temperatures

required for human comfort.

In thermally upgrading and increasing the sustainability of New Zealand’s housing stock,

improvements can be made in the quality of life for occupants, reduced demand from homes

on reticulated energy, with a consequential reduction of total energy requirements and related

costs. This can assist in reducing carbon dioxide emissions and assist New Zealand in

meeting our commitments to the Kyoto Protocol.

3.2.1 HOUSING QUALITY

‘Everyone has the right to a standard of living adequate for the health and well being

of himself and his family, including food, clothing, housing and medical care and

necessary social services and the right to security in the event of unemployment,

sickness, disability, widowhood, old age or other lack of livelihood in circumstances

beyond his control’ (Universal Declaration of Human Rights, Article 25).

New Zealand law has no provision for a right to housing, but in its ratification to International

Covenant on Economic, Social and Cultural Rights (ICESCR), Government has accepted an

undertaking to comply with these international human rights standards.

In April 2009, the New Zealand Government in its Universal Periodic Review report (Clause

3.2.8) outlines the rights to an adequate standard of living but, acknowledges that affordability

to provide adequate housing was a challenge. It did report that over $100 million was

planned to be spent on upgrading existing State houses to improve the habitability of over

18,000 homes. A large number of these houses are inhabited in crowded rental housing by

Maori and Pacific islanders and it was recognised that there are connections linking to “low

income, poor health and lower educational achievement in young people” (New Zealand

Ministry of Foriegn Affairs and Trade 2009).

HNZC’s energy efficiency retrofit programme has upgraded 17,300 of its less well-insulated

houses. Funding in the 2008 Budget has been allocated to retrofit the remaining 21,000 State

houses requiring insulation, by 2013 (Human Rights Commission 2010).

In June 2010 there were 10,434 people on HNZC’s waiting list, 27 per cent of whom were

current State tenants awaiting a transfer, arguably to seek warmer and typically newer house

option (Human Rights Commission 2010).

25

Government funding for insulation is being provided, albeit at low levels. Between 1996 and

2009, 57,000 people received government funding for insulation. The $323 million of ‘Wake

Up NZ Heat Smart’ funding introduced on 1 July 2009, extended insulation to all home

owners regardless of their income level. The aim was to insulate more than 188,500 New

Zealand homes built prior to 2000. In November 2009, it was announced that an additional

$24 million was being provided to insulate the homes of low-income households and some

iwi-specific initiatives.

A higher level of thermal protection and technology to best address future energy demands

improves this investment of national funds.

3.2.2 BRANZ HOUSING SURVEYS

BRANZ undertakes surveys of New Zealand housing to collect information on the type,

structure and condition of New Zealand’s housing stock. The data collected is used to

analyse connection between housing quality, condition and sustainability; as well as

dampness, insulation and heating which effect energy use, comfort and health of the

occupants. These surveys have been undertaken in 1994, 1999, 2005 and 2010.

The most recent survey has shown that the condition of housing has regressed from the 2005

survey, possibly influenced by fewer new houses, and an increased number of rental

properties. Whereas in 2005, fifty percent of housing was reported as being well maintained,

there was a ten percent decline in the 2010 results. Only forty percent of New Zealand

houses are in a good or excellent condition (Buckett, Marston et al. 2011).

The 2005, BRANZ survey of existing housing built between 1930 and 1959 found that only

fifteen percent of the houses would meet the 1996 standard for ceiling insulation of R1.9

(Clark, Jones et al. 2005). The most commonly used ceiling insulation was fibreglass wool,

and where insulation had been installed, there was evidence of it being poorly installed with

gaps, damaged and improper fitting product (e.g. removal of batts by tradespeople without

replacement). Where macerated paper had been used for ceiling insulation, it had settled

reducing its effectiveness to trap air and insulate properly. Typically, walls are left uninsulated

as the removal of the wall linings or claddings make it more difficult and disruptive to retrofit

wall insulation. Foil sisalation was the commonly used under-floor insulation.

Most houses suffered from inadequate interior ventilation, causing physical problems to

develop such as mildew, and damage to materials, linings and finishes. Bathrooms usually

had inadequate ventilation relying on opening windows which are not always opened. The

survey reported that a third of bathrooms surveyed were vented to the exterior, with 15%

venting moisture directly into the roof space.

Of the kitchens, which also contribute large amounts of vapour from cooking and hot water,

26

50% vented cooking fumes to the exterior and 20% either exhausted the fumes into the roof

space, or recirculate the air back into the interior, extracting odours rather than moisture. The

remaining 30% had no form of air extract, internalising moisture into the volume of air as

vapour (Clark, Jones et al. 2005).

Their condition shows deterioration caused by dampness; inadequate insulation; moulds and

rot, which are all recorded in this survey. From this survey a visual representation of the

condition of New Zealand Housing follows:

Figure 3. 2 - Ceiling insulation damage to a 1960s Auckland house

The Fibreglass batts are damaged and not put back correctly

after the installation of a fan in ceiling space.

Figure 3. 3 Insulation damage to a 1940’s Auckland house

The Fibreglass batts are damaged and not put back after

The installation of fan in ceiling space

27

Figure 3. 4 - Bathroom ceiling mildew and finish deterioration in a 1950s Auckland house

Figure 3. 5 - Bathroom mildew in a 1950s Auckland house

Figure 3. 6 - Water damage in a 1950s Auckland house

28

Figure 3. 7 - Bedroom mildew in a 1950s Auckland house

This photo of is of a bedroom showing extensive black mould found throughout the

house, moisture damage to linings and no insulation in walls or ceilings.

Figure 3. 8 - Wall finishes in a 1950s Auckland house

This photo of is of a bedroom in a house which has extensive mould in the bedrooms,

some in living areas, an open fire and LPG heater, and no insulation in the walls or

ceilings (Clark, Jones et al. 2005).

29

CHAPTER 4: HOUSING AND HEALTH

A connection between health and housing has long been recognised. Florence Nightingale

(1820 – 1910) quoted that, “the connection between health and the dwellings of the

population is one of the most important that exists” (Lowry 1991; Lynch 1999). Lowry linked a

dwellings structure with physical health seen in the Victorian era in Britain, and similarly in

New Zealand. To avoid epidemics sanitation became a requirement, which became of more

importance than the condition of the house (Lowry 1989; Lynch 1999). Franklin Roosevelt

proposed to the nation in his annual speech of 1944, a second Bill of Rights to the existing

USA Constitution: “that every family had the right to a decent home” (Roosevelt, Samuel

1938[50).

In New Zealand the Public Health Commission in 1993 commented that “Housing should

provide shelter and warmth” with further reference to low quality housing as meaning either or

both of the following: poor ventilation and lacking basic insulation (Public Health Commission

1993). As New Zealand is a party to both the Universal Declaration of Rights in 1948, and its

reaffirmation in 1993, government is bound to work towards meeting these rights, which

incorporates the provision of a standard of living that includes housing for the health and well

being of everyone.

Everyone has the right to a standard of living adequate for the health and well being

of himself and his family, including food, clothing, housing and medical care and

necessary social services and the right to security in the event of unemployment,

sickness, disability, widowhood, old age or other lack of livelihood in circumstances

beyond his control. (Universal Declaration of Human Rights, Article 25)

New Zealand law has no provision for a right to housing, but its ratification to International

Covenant on Economic, Social and Cultural Rights (ICESCR), Government has accepted an

undertaking to comply with these international human rights standards.

And yet almost a third of New Zealand homes fall below the World Health Organisation

recommended indoor temperature of 18°C. More than a quarter have unflued gas heaters,

which result in high levels of condensation inside houses. Issues that affect the habitability of

both State and privately owned housing are dampness, coldness and crowding. That these

houses are cold and undesirable is reflected in the large numbers of HNZC tenants’ awaiting

a transfer, arguably to seek warmer and typically newer house options. In June 2010 there

were 10,434 people on HNZC’s waiting list, 27 per cent of whom were current State tenants

(Human Rights Commission 2010).

30

In recognition that New Zealand’s housing is in need of improvement, government funded

insulation for fifty-seven thousand people between 1996 and 2009. This was followed with a

commitment of $323 million under the ‘Wake Up NZ Heat Smart’ funding which was

introduced on 1 July 2009, to extend insulation to all home owners regardless of their income

level. Its aim being to insulate over 188,500 New Zealand homes built prior to 2000, which

equates to approximately a fifth of the 900,000 homes estimated to have inadequate

insulation. In November 2009, an additional $24 million was announced to insulate the

homes of low-income households and some iwi-specific initiatives.

Housing New Zealand Corporation (HNZC) provides affordable housing, also recognised as

Social Housing. They mange over 69,000 properties valued at approximately $15 billion, to

provide homes for those in need (Housing New Zealand Corporation). HNZC’s energy

efficiency retrofit programme has upgraded 17,300 of its less well-insulated houses. Funding

in their 2008 budget was allocated to retrofit the remaining 21,000 state houses requiring

insulation, by 201. (Human Rights Commission 2010). A level of thermal protection and

technology that best addresses future energy demands needs to be included in this

investment of national funds.

World Health Organisation (WHO) recognises and defines the term ‘exposure’ as ‘an event

during which people come into contact with a pollutant at a certain concentration during a

certain length of time’ (World Health Organisation 2009). Occupants of unhealthy housing are

exposed to cold temperatures and pollutants for a large percentage of their day, and

regardless of income or nation, unhealthy housing is a global epidemic.

During the cold season, when temperatures are below comfort conditions, houses are cold

due to lack of insulation, air leakage, and inadequate heating sources – often unaffordable for

low income groups. They are difficult to heat, and have a tendency to grow mould. Cold

houses are known to cause discomfort and ill health, mortality affecting the occupants,

confinement to a heated room, condensation on cold surfaces, and consequent mould growth

causing physical, emotional and psychological illnesses. This is evident by the high level of

seasonal mortality in NZ and possibly by other epidemiological evidence e.g. high asthma

rates (Howden-Chapman 2003; Isaacs, N., et al. 1993). Dampness and mould in buildings

has contributed to increasing cases of asthma and allergies throughout various climates of

many countries (WHO, 2009). To prevent walls from dampness they need maintain warm

surfaces to the interior of the house. This is achieved by insulating the complete building

envelope of the house, with as few minimal thermal bridges as is physically possible.

New Zealand has the second highest rate of asthma in the world effecting over 800,000 New

Zealanders of which 25% are children (The Asthma Foundation 2010). The economic cost of

asthma in New Zealand is conservatively estimated to be around $825 million per year, which

31

represents a large health and financial burden to New Zealand’s society. These costs consist

of about $125 million in direct medical costs and $700 million in indirect medical costs (which

includes days off work, premature disability and death from asthma) (Holt and Beasley 2001).

Asthma is the most common cause of hospital admission among New Zealand children. It

also causes 1 in 200 deaths of whom most are elderly, rating New Zealand highly in winter

mortality comparative to other OECD countries (Bierre, Howden-Chapman et al. 2007).

Studies conducted between the University of Auckland and the Auckland District Health

Board investigated the effects climate has on health in the Auckland area, with a focus on

respiratory infections. Over a six-year period, comparison was made between climate and

weather data, and hospital admission figures for the Auckland area. It was found that low

temperatures and high rainfall / humidity corresponded with increased hospital admissions for

respiratory, cardiovascular, and meningococcal diseases, worst effecting the children and

elderly. There was an approximate 40% increase of hospital admissions for respiratory

infections and inflammations during winter when temperatures are low (Gosai and Salinger

2006).

Figure 4. 1 Graph of minimum temperatures: number of admissions to Auckland hospitals

(Gosai and Salinger 2006)

32

4.1 HEALTH COSTS

Uninsulated housing affects New Zealand in health, energy and environmental costs. This

was demonstrated in an analysis of the reduced number of visits to GPs, hospitalisations,

days off school, days off work, energy savings and CO² savings found in a New Zealand

study undertaken in 2001 and 2002 called ‘The Housing, Insulation and Health Study’

(Chapman, Howden-Chapman et al. 2009). To achieve environmental, energy and health

benefits, the value for money of improving housing quality by retrofitting insulation is

convincing.

Philippa Howden-Chapman, a social scientist based in Wellington (NZ) has helped to inform

policy development in health, housing and energy policy. Her knowledge contributes to many

studies that involve housing, insulation, heating and health. From the ‘The Housing,

Insulation and Health Study’, Howden’s analysis ‘Retrofitting houses with insulation: a cost–

benefit analysis of a randomised community trial’, found that insulating housing was very cost

effective. The study found that the health benefits exceed the actual cost of fixing houses by

a ratio of almost 2:1 (Chapman, Howden-Chapman et al. 2009).

The cost of installing insulation above the ceiling, fixing foil beneath the floor, applying some

draught stopping and in some cases a polythene barrier over the exposed ground beneath

the house to prevent rising dampness, was twice as cost effective as the amount of health

related savings to be made. This study involved 1350 houses that were retrofitted with

insulation of levels meeting EECA standards of almost a decade ago. Insulation levels have

since improved, and heating costs have increased, which further substantiated that the cost of

retrofitting uninsulated housing is recoverable from current health related expenditure.

Current expenditure on housing related heath problems incurs costs for hospital stays for 50

people suffering from respiratory illness per day ($3,000 per night for hospitalisation), which

amounts to $54 million; $17 million in 180,000 lost workdays taken for illness; and $475

million in wasted residential energy consumption (NZBCSB, 2008). To correctly address

adequate insulation, by making improvements to provide a complete thermal envelope has

the potential to save an estimated $546 million per annum.

It was concluded in ‘Housing, Insulation and Health Study’ that energy and environmental

savings such as carbon emission savings, were modest but significant, with larger savings

being achieved from health benefits. Although Local Authorities are required by the Health

Act 1956 and the Building Act 1991 to monitor housing conditions and building standards

(Rankine 2004), this does not appear evident when observing clear link between poor

housing and health.

33

4.3 INDOOR AIR QUALITY AND HEALTH IN LABOUR PARTY STATE HOUSING The link between cold, uninsulated houses with mould and ill health is not new to New

Zealand. Mould has been discovered in State housing since soon after they were first built.

Within the first two years – post construction, problems developed with the condition of

Labour Party State Housing (LPSH) that affected fifty-seven percent of the houses (Brien and

D.R. 1944). Discolorations were discovered, caused by black, blue-green and yellow moulds.

The black mould that resembled splattered soot was found on the distempered ceilings, and

the other moulds were found on the top areas of the wall-papered walls. The moulds

reappeared after the surfaces were repainted and re-wallpapered.

A test house was built and accommodated by staff members during a testing period in which

these moulds were investigated, and reported on in 1944 by the Department of Scientific and

Industrial research to Government (DSIR). The DSIR report ‘Investigations into causes and

controls of moulds in State Houses’, indentified the moulds as being Cladosporium herbarum,

Penescillium commune, Penescillium chrysogenum and Aspergillus versicolor (Brien and

D.R. 1944).

Cladosporium herbarum is the dark brown fungi found formed in colonies on the ceiling, which

when established forms a vegative body composed of thick-walled hyphae which penetrates

the distemper applied to the ceiling, rendering it unable to be cleaned off. Penescillium

commune, P.chrysogenum and Aspergillus versicolor grew on wallpapers, but not un-

wallpapered wallboard. They commonly occur on other hygroscopic items such as books,

papers, shoes and clothes stored with limited ventilation. These moulds grow superficially

without penetrating the surfaces so are easily cleaned off without staining.

Tests were done on sample pieces of plasterboard that were half coated with glue-size (the

common surface sealer prior to distemper or wallpaper application), casein (used as the

binding agent for distemper) and flour paste (used to glue the wallpaper to the plasterboard).

The remaining half of each sample was left untreated for comparison. The samples were

lightly sprayed with moisture containing Cladosporium herbarum spores, and then stored for

30 days in a warm humid environment of 22.8 °C with a relative humidity of 95%. The same

test was done replacing the plasterboard substrate with glass.

Mould grew on all samples that had the glue size, casein and flour-paste identifying that the

plasterboard was not causing the problem. As mould resistant substitutes for the glue-size,

casein and flour-paste were not available potential additives known to be toxic to fungi were

tested to prevent mould growth.

34

Commercial formalin, Zinc sulphate, Copper-sulphate, Borax (sodium borate), Sodium

salicilanylide (“Shirlan W.S.”), Sodium penta-chlor-phenate (“Santobrite”), Phenol and

Potassium alum were all chemical additives applied to water in varying concentrations and

applied to the new samples of plasterboard prior to application of the glue-size, casein and

flour-paste, and the same test conditions were applied, extended up to 45 days. The samples

using 1% concentration each of Sodium salicilanylide and Sodium penta-chlor-phenate

inhibited growth on the distemper.

4.3.1 PENTACHLOROPHENOL: SOLUTION TO THE FIRST MOULD DISCOVERY IN LPSH

The DSIR conducted tests to find a solution to prevent the mould growth. It was established

the mould was caused by the glue-size, casein and flour paste. To solve the problem, a

chemical was introduced. A two percent concentration of Sodium penta-chlor-phenate (PCP)

was added into the distempers, and the glues that adhered the wallpapers to the plaster

board walls, was concluded as a ‘treatment’ to deter the moulds. This solution was

recommended to government with a caution given as to the care required in the handling of

the chemical as “it was liable to cause skin injury if brought continuously in contact with the

hands or face” (Brien, 1944).

For reasons of practicality of the decorating procedure, PCP applied to a bucket of wallpaper

paste could have been applied to all walls of a room, not just the exterior walls that would be

the most affected by mould growth. State House plans typically were designed with small

bedrooms that often placed a bed along an exterior wall up against cold uninsulated

wallpapered walls. Therefore, should PCP have been used as an additive to wall paper

pastes and applied to the walls of LPSH, it implies there was toxicity within very close

proximity to sleeping occupants. A thickness of absorbent paper separated a sleeping child

from possible PCP contamination at close range, for a minimum period of eight to ten hours

daily.

Diluted as it was, PCP is known to be toxic, and if this practice was administered, tests of the

existing wall lining could advise that its removal should be considered for health reasons.

PCP was introduced in 1936 as a timber preservative fungicide and pesticide treatment to

prevent the growth of fungi, algae, mosses, and other micro-organisms. It was economical

and insoluble with water, so was used extensively in house construction and paper (Jorens

and Schepens 1993).

PCP in houses is an environmental pollutant that presents an unacceptable risk to human

health. In an enclosed space such as a closed bedroom, PCP can be transported through the

35

air. This is confirmed by findings of PCP contamination in house dust and absorbed within

untreated materials in close proximity of PCP (Jorens and Schepens 1993). In Germany,

PCP was banned for indoor use in 1978 and outdoor use in 1989. (Schulz, Conrad et al.

2007)

The use of PCP inside housing exposes occupants to the vapours it releases, which is

absorbed into the lungs, gastrointestinal tract and skin. High exposure to PCP has the ability

to affect the skin, metabolism (fever), the haematopoietic tissue, the respiratory and nervous

system, the kidney and the gastrointestinal tract. Although PCP is not classified as a human

carcinogen, research has suggested that it may contribute risk for some malignancies such as

nasal carcinoma and soft tissue sarcoma (Jorens and Schepens 1993). PCP has caused

acute poisoning of children exposed to its use as an additive to laundering wash powders

(Jorens and Schepens 1993; Schulz, Conrad et al. 2007).

It is not known if the solution of PCP was introduced on the DSIR recommendation, as

records could not be found confirming either way. Tests on the effected houses may provide

confirmation if residue is possible after more than 50 years having passed since its potential

application.

Figure 4. 2 Recommendation for the use of Pentachlorophenol to treat mould in LPSH

(Brien and D.R. 1944)

36

4.3.2 THE EXPERIMENTAL COTTAGE: TEST OF INSULATION, VENTILATION AND DAMPNESS

In 1946 an experimental cottage was set up to provide a vehicle for tests to address the

“trouble with certain State houses”, which recognised the relevance of dampness and

inadequate thermal insulation (Marsden 1946). The house was lived in through the tests.

Different methods of insulation were to be tested with various temperatures, ventilation and

humidity being recorded to provide observations for the future improvements of LPSH

construction (Cooper 1948). Heating ranges were also tested to find an option that improved

comfort, was more economical, and that required less coal and effort to light (Furkert 1946;

Cooper 1948).

In 1948 the DSIR made a written recommendation to Walter Nash (Labour Party Finance

Minister) to investigate the moisture content of timber framed walls; the thermal transmittance

of walls and windows; the heating costs comparing the efficiency of open fires and heat

pumps; ventilation of rooms, and the interior climate and comfort measurements of the

experimental cottage (Cooper 1948). Heat loss was assumed as being a third through the

wall, a third through the windows and a third through air leakage around the doors and

windows. Various insulating materials were tested such as ‘Vermiculite’, (vermiculite),

‘Perlite’ and ‘Rock wool’, all natural mineral-based products.

The suggested programme of investigations for the ‘experimental cottage’ is transcribed as

follows:

Moisture content of stud timbers

(a) Insert prongs into stud timbers and wire to a central point: check resistance

between prongs at least once weekly.

(b) Insert test samples of stud timbers loosely in cavities behind removable

panels. Weight samples regularly.

Arrange for one room (say Bedroom No.2) to have a minimum of stud ventilation, and

another room (say Living Room), to have a maximum of stud ventilation. Measure

rates of ventilation in these cavities under varying outdoor conditions.

Thermal transmittance of walls, etc.

Measure transmittance values of various wall sections, external and internal,

ventilated and unventilated, insulated and uninsulated.

Measure transmittance values of ceiling and floor, before and after insulating in

various ways.

Try effect of various types of insulation: building paper on rafters; insulwool;

vermiculite; thermax; ardor, etc.

37

Thermal transmittance of windows

Determine heat losses through casement and sash windows, open and closed, bare

and curtained, and with blinds

Heating Costs

Determine overall heating costs by continuous heating, under various insulation

conditions and with ventilators open and closed.

Ventilation of rooms

Measure ventilation rates in all rooms under various outside conditions.

Comfort Measurements

Make eupatheoscope and katathermometer measurements in all rooms under

various conditions.

Efficiency of open hearth fires

Certain aspects of this problem may be capable of investigation in the living room of

the cottage.

Heat pump

Utilise the cottage to investigate the efficiency of the heat pump as a possible means

of domestic heating.

Interior climate

Investigate changes in R.H. (room heat) and temperature throughout the year when

the cottage is inhabited. (Cooper 1948)

It is regrettable that although there was knowledge of temperature, moisture and ventilation,

which are important factors that contribute towards good indoor air quality and create a

healthy and thermally comfortable environment to live in, these houses were left un-insulated.

The lack of insulation being installed during construction has incurred significant long-term

costs in wasted energy and poor health for New Zealand.

38

Figure 4. 3 Government memorandum regarding the investigation of insulation and air movement

(Furkert 1946)

Common complaints developed regarding the dampness and mildew that became part of

LPSH. A comment frequently made in a survey of State house tenants undertaken prior to

1944 was that the houses had “dampness caused by faults in construction”. “Although the

houses were constructed well, they were indeed cold and damp. Mildew was found on walls,

ceilings and in cupboards.” These defects were reported to authorities and “remedies were to

be undertaken”. There were also complaints of draughty windows, where ‘unseasoned’

timber joinery had shrunk as it fully dried, leaving gaps. Rooms were cold and draughty due

to fireplaces, vents that were in some ceilings, and “lack of sarking” or other preventative

device under the draughty tiled roofs (Wells 1944).

39

4.4 MOULD IN STATE HOUSES, POST 1990

In the mid 1990’s research was undertaken by Kate Lynch for her thesis ‘Healthful Housing’.

She investigated State rental housing and related health issues interviewing a number of

tenants from nine households. Damp and mouldy rooms were still common complaints of the

families interviewed, with mould present in their Housing New Zealand houses.

Overcrowding was a major problem, often caused by cold temperatures, and lack of

affordability to heat the uninsulated house. It was suggested in Lynch’s thesis that the

“primary causes or risk factors of the current meningococcal epidemic may relate to over

crowding and high household size”. In addition there are many diseases, especially

respiratory, that are droplet-borne. The added volume of moisture caused by human

breathing intensifies with overcrowding, which increases the chance of disease spreading

(Lynch 1999). International studies show overcrowding to be a risk factor in the developing of

meningitis. Indeed Stuart et al. (1989) states that “the carriage rates are high in young adults,

in people who live in conditions of severe overcrowding”

Interview extracts from ‘Healthful Houses’ depict the damp conditions experienced:

“Damp mouldy houses are common. Condensation can be seen visibly running down

walls. Three or more adults sleep in the same room without adequate ventilation.

The windows are kept shut because of the cold and the inability to afford heating”.

(Tui)

“It wasn’t that clean when we moved in. They, (Housing New Zealand), were

supposed to do the cleaning but they never. I had it all done myself. Like the

mould’s black marks on the wall, in the bedrooms and that, cos it smells. That’s what

normally makes my children sick cos the air’s not fresh in the house. Me and my

husband cleaned everything out, the walls, the bedrooms ... Mould all over the walls,

bedrooms, smelly too. So I spent everyday cleaning it bit by bit until it was all done,

and the ceiling too. I finally had it all done “(Ani).

“It was a three bedroomed house and there were two bedrooms that got the sun, and

then there was the spare bedroom. That bedroom was just so damp that it was

actually mouldy. And the other lady, she didn’t use her . . . that same bedroom

either” (Bob)

Heating is one thing you really notice in winter. But if they have the luxury of

one family living in a house, often they will all be living in one room of the

house, just cos it’s the only way they can afford to heat the house (Carol).

40

“I’d just had Charlotte at the time. I was going back and forward to the doctor’s

because of her bronchitis, and it was the coldness that caused that.”

The cold and damp conditions caused many to sleep in the same room to conserve electricity

and warmth in the house. The heating required to raise indoor temperature to 18°C

throughout the winter months would require a level of finance beyond the means of families in

serious housing need. Market level rents contribute further health risks as households cannot

afford the cost of heating from their post-rent residual incomes (Lynch 1999).

The reported comments are from a decade ago. Since then fuel costs for heating have

risen, and will continue to increase.

4.5 THE HEALTHY HOUSING PROGRAMME

Auckland Regional Public Health Service commissioned a report with an interest in housing

and health issues in Auckland. It was established that the cost of affordable housing was

beyond the financial means of over a quarter of Auckland households, in meeting the defined

percentage of housing cost based at 25% of income. In 2001, 23% of Auckland households

were paying upwards of 40% of their net income on housing (Rankine 2005). Issues of

concern were that unaffordable housing costs cause overcrowding (to share the cost),

substandard quality of housing, houses that are cold, damp and mouldy which create

unhealthy living environments for its residents who are exposed to both mental and physical

stresses.

Diseases such as asthma and meningococcal meningitis, which are strongly linked with

substandard or overcrowded housing, are those to which children are also highly susceptible.

Inadequate housing may affect the life chances of another generation through poor health,

missed schooling and the lack of formal educational qualifications. (Lynch 1999)

Between 1991 and 1998, there was an epidemic of meningococcal disease that reached its

peak in 1997. The highest rates were found in Auckland, with Maori and Pacific communities

being the worst affected. Seventy percent of the 1097 notifications were made in winter and

spring when temperatures were low and humidity levels were high (Lindsay, Hope et al.

2002). Rates of incidence increased with high humidity levels and cooler temperatures

(Lindsay, Hope et al. 2002). Overcrowding of housing drastically increases dampness in

housing, which spreads infection, and increases contaminants such as mould and dust mites

known to cause and antagonise respiratory health problems. Health issues recognised were

meningococcal disease, tuberculosis, rheumatic fever, cellulitis and respiratory diseases

41

In response, the Government activated the Healthy Housing Programme (HHP), which was

established in 2001 as a response to the outbreak of meningococcal disease that was found

to be connected to tenants in overcrowded HNZC State housing. Most State housing had

been built for ‘nuclear families’, and therefore was not meeting the needs of larger families,

extended and multi-family use (Housing New Zealand Corporation 2000). Housing New

Zealand Corporation (HNZC) recognised that there was a need for healthier housing to

reduce the ill health of its tenants, particularly children. The programme was co-jointly

managed between HNZC and District Health Boards (DHB), who engaged the architectural

services of the New Zealand Institute of Architects (NZIA) for housing renovation design input.

The Department of Building and Housing (DBH) and the New Zealand Institute of Architects

(NZIA) teamed together to address the problem with the ‘Healthy Housing scheme’. A

number of architects in conjunction with NZIA created designs to improve State housing

under the Healthy Housing Programme. A number of architects were engaged to improve the

houses by alterations that upgraded bathrooms and kitchens, and increased the size of the

homes to better accommodate large families. Insulation, ventilation and heating systems

were to be included.

At the commencement of the Healthy Homes programme, HNZC owned 19% of the New

Zealand’s rental properties at the time, which accommodated between 160,000 and 170,000

tenants. Two thirds of the 59,000 properties owned are standalone houses, and 74% of these

are located in Auckland. In Auckland, Glen Innes and the southern suburbs of Otara and

Mangere, and in Wellington Hutt Valley were recognised as being deprived areas that had a

high incidence of infectious disease, therefore were selected for this programme. A survey

undertaken in Glen Innes for the HHP found that 90% of the dwellings had excess

condensation, mould, dampness and cold draughts (Housing New Zealand Corporation

2000).

By the middle of 2009, this programme had completed 11,979 interventions with an outcome

that showed the retrofits did improve the health and wellbeing of the occupants. The risk and

rate of house related disease, specifically meningitis, rheumatic fever, cellulitis, and

respiratory diseases that include asthma had minimised, which effectively reduced the need

for doctor and hospital visitations, as well as increased school attendance. Even with minimal

interventions that included heating, ventilation and insulation – the three essentials for quality

indoor air – the occupants found their homes to be more comfortable and pleasant to be in,

and found that asthma and respiratory problems improved. The final evaluation provided

evidence of a wider social impact that was enriched by improved housing. Families were

happier and healthier (Housing New Zealand Corporation 2007).

42

From interviewing one of the architects involved in the HHP, post intervention observation

was “that people were now living in and around them [houses] in a different way. Gardens

were around where previously they had not been. These families are taking pride in their

homes” (Cook 2010).

4.6 INDOOR AIR QUALITY

IAQ AND HEALTH

The enclosed indoor environment directly affects the health, quality of life, and productivity of

its occupants. Deteriorating health problems impact on a large sector of the global

population, which has raised the concern of the World Health Organisation (WHO), who have

recognised that poor indoor air quality (IAQ) caused by microbial pollution is indeed a global

problem. International research has provided epidemiological evidence that demonstrates the

connection between damp and mouldy homes, with the increased risk of respiratory problems

that include asthma, hypersensitivity, pneumonitus, allergic alveolitus, chronic rhinosinitus,

and allergic fungal sinitus (WHO, 2009). House related health problems are common to all

countries where people spend a lot of time within their homes.

Consequently, in 2009 WHO published 'Guidelines for IAQ' based on a comprehensive review

and evaluation of the scientific evidence that pertained to health related problems, and

contributing factors of microbial growth indoors.

Having identified the health risks and probable causation, WHO developed guidelines for

world wide use to improve IAQ and occupant health, which are summarised as follows:

1. Persistent dampness and microbial growth on interior surfaces and in building

structures should be avoided or minimised as they lead to adverse health effects.

2. Condensation on or in structures, visible mould, and mouldy odour are indicators of

dampness and microbial growth.

3. Dampness and mould related problems are recommended to be prevented, and when

they occur, they should be remedied because of the increased risk of hazardous

exposure to microbes and chemicals.

4. Well-designed, well-constructed, well maintained building envelopes are critical to the

prevention and control of excess moisture and microbial growth, as they prevent

thermal bridges and entry of liquid or vapour-phase water. Moisture management

requires the proper control of temperatures and ventilation to avoid excess humidity,

43

condensation on surfaces and excess moisture in materials. Effective distribution of

ventilation and avoidance of stagnant air spaces is required.

5. Proper building construction and maintenance for a healthy house is the responsibility

of the building owner, and the occupants are responsible for heating and ventilation

adequate to avoid dampness and mould growth.

6. Remediation of poorly maintained houses with mould and damp that accommodates

low income earners should be prioritised to prevent increased poor health to those

already suffering from ill health.

In New Zealand, housing and national health has deteriorated as the result of the moulds and

dustmites that thrive in home climates we cohabitate. Given a situation with a high level of

relative humidity, mould growth and dust mites thrive, both of which produce allergens. The

moist, damp environment found in homes provides the ideal environment for biological

microbes to propagate, as there is water, dust and dirt - all of which feed such contaminants.

By following the WHO guidelines, and with the help of government strategies that act

appropriately and encourage implementation, effective health objectives can be gained by

using a holistic design that is inclusive of adequate ventilation, insulation to create a complete

thermal envelope, and a source of heating and cooling. Combined with the correct selection

of appropriate healthy building materials and technologies, along with appropriate occupant

use, quality indoor air can be achieved and maintained. This has consequential health

benefits of value to both the occupant, and health related government expenditure.

As humans breathe approximately 11,000 litres of air each day, with 50-90% of this being in

homes, it is important for health reasons to create healthy air to live within. To achieve quality

indoor air, technologies that address internal sources of humidity, thermal comfort and

controlled air infiltration rates are necessary. Ventilation, heating and insulation are the three

critical elements that are all required for a successful outcome that will provide quality indoor

air (Lloyd and Callau 2006).

4.6.1 CONTAMINANTS

A wide range of contaminants found in the indoor air of housing can arise from pollutants

within the house, or they can be transported into the indoor confines from the outdoor

environment through the air. Biological and chemical contaminants pollute indoor air, which

deteriorates IAQ and contributes to, or causes ill health of the occupant/s by affecting the

mucous membranes, eyes and breathing of the occupants, and can cause a number of other

health problems to include headaches, depression and anxiety, respiratory difficulty, asthma

and allergies. There are a few more serious disorders that involve damage to cellular growth,

44

which can be linked to cancer growth (Greig). Without adequate ventilation to release the

contaminants, they accumulate in the air, intensifying indoor air pollution.

CHEMICAL CONTAMINANTS

Chemical contaminants are commonly found in building materials, and are also introduced

though occupant use. Ten percent of the New Zealand population have a heightened

chemical sensitivity, Multiple Chemical Sensitive, meaning they cannot handle the same

exposure limits that others can.

Of the range of pollutants that can be introduced into the indoor air, outdoor pollution such as

traffic gas emissions, or other chemicals in the area can be transferred in the natural air used

for ventilation. Within the house, indoor air can be contaminated by airborne particles from

open fireplaces and wood stoves; noxious gases such as carbon monoxide and nitrogen

monoxide that is emitted from unflued gas heaters; building materials that emit volatile

organic compounds (VOC’s) and occupant used chemical such as household cleaners and

sprays . VOC’s chemicals are commonly found in composite materials such as plywood,

fibreboards, laminates, glues and timber treatments. A common toxic example is

formaldehyde which can be released from all of these products. Some chemicals reduce with

time, but others can continuously off-gas.

Human breathing creates increased levels of carbon dioxide that accumulate which can

cause headaches and lethargy without adequate ventilation. Fresh air contains 20.9%

oxygen and 0.2% Carbon dioxide (CO²), whereas expired air changes these rates to 16% and

4% respectively. CO² levels of 0.1% compromise the comfort of occupants, at 0.35% there

can be long term health implications and levels higher than 5% acutely affect human health

Lead is a common contaminant found particularly in older houses as it was commonly used

as a pigment and drying agent in "alkyd" oil based paint prior to 1979 (when white lead was

banned from use) in New Zealand (Level 2010). Lead toxicity released from old lead based

paints as paint flakes or dust is a problem that can arise from paint deterioration and during

the renovation of older houses. Ingress into the body can occur upon swallowing the residues

from lead paint or by inhaling its fumes. Exposure to lead is cumulative if left untreated and

can cause human poisoning. It is known medically to cause haematological, gastrointestinal,

and neurological dysfunction (Lockitch 1993), causing high blood pressure and hypertension;

nerve disorders; lowered levels of memory and concentration; infertility; and joint and

muscular pain in adults. Children are the more vulnerable to whom the effect of lead can

cause damage to the brain and nervous system; hyperactivity and learning problems; growth

limitations; hearing problems and headaches (EPA, 2010).

45

There are many other chemicals that have the ability to contaminate indoor air, one of which

is Pentachlorophenol that may have impacted on LPSH.

BIOLOGICAL CONTAMINANTS

Dampness and inadequate ventilation cause the growth of biological contaminants. Moulds,

fungi, and bacteria, release spores, cells, fragments and volatile organic compounds into the

air, and combined with other biological contaminants such as dust mites and their faeces;

contribute to the high rates of asthma, perennial allergic rhinitis and eczema, that affects over

800,000 people in New Zealand (The Asthma Foundation 2010).

DUST MITES

Dust mites are part of the arachnid family of insects having a spider-like appearance. As they

are light in colour and blend well amongst dust particles, and are minuscule, about 200μm in

length as an adult, they are difficult to see (Leardini and Van Raamsdonk 2010), and yet are

very common in New Zealand housing.

Dust mites survive on water absorbed from the air and feed on human skin scales. Clearly, a

damp house in a mild and temperate climate is ideal to encourage the presence and

procreation of dust mites (WHO, 2009; Leardini, 2010). For their survival, dust mites require

a level of relative humidity (RH) which is higher than 45% (WHO, 2009), and they will multiply

rapidly as the humidity levels increase. The ideal environment for dust mites has humidity

levels of between 52% and 75% RH, and an indoor temperature within the range of between

15°C to 30°C (Leardini and Van Raamsdonk 2010).

MOULDS

Mould spores arise as a result of dampness and inadequate ventilation and contribute to the

contamination the indoor air environment. Indoor fungi have similar requirements to dust

mites in that they also require moisture, nutrients and a temperature of 10-35°C to survive

and grow. Mould fungi are ubiquitous in damp housing as these elements are found in

materials such as wall paper and textiles, as well as household dust to provide sufficient

nutrition for sustenance and growth. Provided with a high relative indoor humidity, the growth

of mould and fungi on damp surfaces of building interiors is evident, and where there is a

humidity level achieved of 70% or more, mould will grow on a surface of many substrates

within seven days (WHO, 2009). Along with the many negative health implications, mould

has the ability to deteriorate the building fabric, furnishings, interior decorations, clothes, toys

and household equipment. It causes irritation and discomfort, and its pungent and unpleasant

smell, and visual unattractiveness can cause social deprivation (Hunt, 1994). Visually mould

fungi have a woolly or powdery appearance in colours of green, blue, black, pink and orange

(Hedley and Wakeling 2002).

46

Moulds can be caused in buildings arising from two different situations:

1. Poor internal moisture management caused by insufficient heating, poor insulation, poor

use of vapour barriers and inadequate ventilation that leads to damp surfaces conducive

to mould growth.

2. Weather tightness failure which leads to the ingress of external moisture that causes wall

sheathing and associated materials and fittings to become wet, which leads to mould

growth. (Hedley and Wakeling 2002)

4.6.2 HEALTH RISKS RELATED TO MOULDS

New Zealand housing is known to accommodate at least 60 varieties of moulds that can

cause serious health problems (Leardini and Van Raamsdonk 2010). Asthma has historically

been the dominant mould-related health issue in New Zealand, but more recently, health risks

related to toxigenic moulds connected to the ‘leaky house’ syndrome, have been prevalent

(Hedley and Wakeling 2002).

Asthma symptoms are linked to inhalation of mould spores and mycelium fragments, which

can affect those individuals prone to asthma and other respiratory health complications, but

anyone can be put at risk if they are exposed to high spore concentrations over a prolonged

period (several days or weeks). Mycotoxicosis, is poisoning caused by prolonged inhalation,

ingestion or absorption of Mycotoxins produced by toxigenic fungi (mainly moulds but other

fungi and actinomycetes or filamentous bacteria also). The seriousness of a mycotoxicosis

relates to the dose or concentration of mycotoxin to which an individual is exposed.

Mycotoxins (fungal toxins) produced by fungi have been known to interfere with DNA

synthesis and may cause DNA damage, although it is not clear whether the levels of airborne

Mycotoxins found in damp buildings is high enough to cause health effects.

Penicillium, Aspergillus and Cladosporium are all moulds that are strongly related to allergic

respiratory disease, especially asthma. Penicillium and Aspergillus are commonly found in

most houses. Cladosporium herbarum has been known to produce various allergens, often

linked epidemiologically to asthma as a main aeroallergen in many health studies.

Aspergillus versicolor is an internationally recognised fungus commonly found in temperate

and colder areas, and is frequently found in buildings with humidity and ventilation problems.

Aspergillus versicolor and Cladosporium herbarum both require intermediate levels of

moisture to grow, (ERH 80-90%), while Penicillium chrysogenum and Penicillium commune

will grow with low levels of moisture (<80%). Aspergillus versicolor is a mycotoxin that along

with Stachybotrys Chartarum are producers of macrocyclic trichothecenes, trichodermin,

sterigmatocystin and satratoxin G, which could be present in most materials and dusts in

buildings with current or historical water damage. Stachybotrys chartarum is a toxigenic

47

mould commonly known as ‘black mould’ (Leardini and Van Raamsdonk 2010), which is

found in New Zealand houses. It prefers materials that contain wood fibres, building paper;

fibre cement boards and paper coated gypsum plasterboard (Hedley and Wakeling 2002) and

grows in a wide range of temperatures, (between 2°C and 40°C with its ideal situation being

where the RH is higher than 70% (Zhang 2009). With its ability to grow in such low

temperatures, it is often found in cold and damp housing, most commonly in moist bathrooms.

The two significant categories of housing in New Zealand that are highly conducive to the

growth of Stachybotrys are pre-1978 uninsulated houses, which have an average RH of

between 65% and 85% (Zhang 2009); and the recent crisis in New Zealand of ‘leaky’ housing

that been built over the last two decades (Hedley and Wakeling 2002).

The moulds discovered in LPSH within the first two years post-construction, were indentified

as being Cladosporium herbarum, Penescillium commune, P.chrysogenum and Aspergillus

versicolor (Brien and D.R. 1944).

An evaluation could be surmised that houses built in the period from post- 1978, up until the

early 1990’s when the leaking house crisis commenced, may provide adequate, mould-free,

healthy housing. This suggests that there are thousands of houses with problems that

continue to affect the health and comfort levels of millions of New Zealanders. The ‘leaky

house’ crisis is being addressed litigiously, to rectify the problematic design, construction and

technology of these houses, leaving uninsulated housing to find alternative drivers to instigate

and encourage intervention for their improvement.

4.6.3 MOISTURE AND DAMPNESS

As well as a range of contaminants that are contained in the air, water vapour is another

pollutant (Clark, Jones et al. 2005; Pollard and McNeil 2010). Indoor dampness seems to be

the key. Indoor dampness is estimated by WHO to affect 10 to 50% of buildings that include

homes, schools, and offices, with the highest incidence of dampness found in deprived

communities. As New Zealand’s relative indoor RH is usually above 65% in winter this

provides ideal conditions for mould growth. In New Zealand, dampness in housing

contributes to approximately 15% of the population being affected by allergies such as

asthma, headaches, eczema and sneezing related to the moulds, spores and household

toxicity (SmarterHomes 2008). The 2010 BRANZ House Survey found that dampness affects

over a third in New Zealand’s houses (Buckett, Marston et al. 2011), and according to the

Energy Efficiency and Conservation Authority (EECA), about 45% of our homes suffer from

moisture related problems. In Auckland, where the climate is more humid, the rate of

dampness in homes increases to 72% (Easton 2010). An ideal RH is between 40 and 60%.

A lower level of RH is too dry for the human mucus system and a higher RH presents the risk

of mould developing.

To stabilise humidity levels, the use of technology and correct material selection can assist.

48

Despite being a nationally and internationally recognised problem, building standards and

regulations typically do not regulate or set minimum requirements for preventing and

controlling excessive moisture and dampness.

There are a number of reasons that cause high moisture levels as well as condensation.

Dampness that enters the house from the outside, which has the potential to increase due to

changing climatic conditions altering weather patterns that bring increased storms, heavy

rainfall and flooding (World Health Organisation 2009). Water vapour caused within the

house interior and water vapour from unflued gas heating. In new construction, moisture can

be introduced through damp building materials that are used. Dampness in old and new

housing is also affected by high levels of indoor humidity, lacking insulation causing cold

surfaces and inadequate ventilation. The quantum of moisture that is gathered in homes is

from a number of sources created by human behaviour are outlined in the chart below:

MOISTURE CREATED BY COMMON HOUSEHOLD ACTIVITIES

Activity Litres

Cooking 3.0 per day

Clothes washing 0.5 per day

Showers and baths 1.5 per day (per person)

Dishes 1.0 per day

Clothes drying (unvented) 5.0 per load

Gas heater (unflued) Up to 1.0 per hour

Breathing, active 0.2 per hour (per person)

Breathing, asleep 0.02 per hour (per person)

Perspiration 0.03 per hour

Pot plants as much as you give them

Moisture created by human activity within housing

(Consumerbuild)

The ability of warm air to hold moisture increases as temperatures rise, with the level of

moisture held yielding the level of relative humidity. Condensation appears when the indoor

air in a room cannot hold the level of moisture in relation to its temperature, therefore when

temperatures are low the moisture (vapour) in the air liquefies to form condensation wherever

the temperature change occurs. This is known as dew point. Such condensation causes

dampness on porous surfaces, such as walls, and will grow mould within seven days. (WHO,

2009). Without adequate ventilation the moisture re-circulates into the air, continually adding

to the moisture content within the enclosed environment.

49

Forces that are exerted on material surfaces attract water vapour molecules to stick to their

surface. The thickness of film they form and the amount of water held in equilibrium with the

surrounding atmosphere is roughly proportional to the relative humidity of the atmosphere.

Therefore where humidity is low, a water film thickness of one molecule occurs. As the

humidity rises, so does the vapour thickness until at 100% relative humidity, it reaches

saturation point and condensation occurs. The effect of moisture on building materials

increases the risk of attack by moulds, fungi or insects, which leads to the deterioration of the

material.

Glass is a great collector of condensed air vapour as it represents a thin layer that separates

temperature differential between a house interior and exterior. In most single glazed

buildings, the window glazing has the lowest interior surface temperature, which leads to

condensation. The condensate increases in the form of tiny water droplets that collect into

drips, giving the term 'crying windows'.

INTERSTITIAL CONDENSATION

Interstitial condensation is concealed, as it occurs within the building fabric. It happens when

warm, moist air is sucked by diffusion or air leakage, within the layers of the building envelope

where lower temperatures can cause condensation to occur. Where the air temperature of

the interior is higher than the exterior, the pressure differential will cause the heat and vapour

within the air to migrate from the interior through the building envelope, attempting to escape

to the cold ambient external temperature. Where there is no insulation to provide thermal

retention, heat flows out of the interior envelope with resultant heat loss, requiring a constant

additional heat source to maintain a comfortable room temperature. Vapour and

condensation flow with the air movement to settle on cold materials, either hygroscopic or

non-permeable. If the dew- point is found within the wall, this is where the condensation will

occur. Moisture absorbed into insulation or any hygroscopic material will be detrimental and

will affect the thermal conductivity of insulation material.

HYGROSCOPIC WALLS

Transfusive walls made of vapour permeable and highly hygroscopic materials, can enhance

IAQ when used in conjunction with other strategies, to eliminate fungal growth by moderating

humidity variations. Hygroscopic materials have an ability to react quickly, absorbing

moisture in humid situations or releasing it in dry conditions, therefore stabilising the humidity

level of the air. Materials such as timber, plaster, aerated concrete, lime render, clay, wood-

fibre boards, wood-fibre cement, earth and textiles have good hygroscopic properties. They

50

have an ability to hold moisture without risk of biological activity or degradation. Impervious

coating such as paint or varnish negates the hygroscopicity and should be avoided.

4.7 THERMAL COMFORT

Due to long exposure to indoor thermal environment (people spend 90% of their time

indoors), indoor temperatures are very important as they can affect human comfort and thus

health. World Health Organisation (WHO) recommendations for indoor temperatures have

minimum standards of 16°C for bedrooms and 18°C for living areas. Temperatures of 20°C

for living areas and 18°C for bedrooms are the optimums. The minimum temperatures of 16 -

18°C is extended to increase up to 24°C for living spaces that are inhabited by the weaker

members of the population, which is usually the sick, immobile or elderly (World Health

Organisation 2009). Temperatures that are less than the minimum 18°C introduce health

problems. Room temperatures that are lower than 16°C can impair the respiratory system

(which can be further exasperated by high or low humidity). Temperatures below 12°C place

stress on the cardiovascular system, and there is a risk of hypothermia if temperatures are

below 6°C (Collins 1986).

By international comparison, New Zealand’s indoor temperatures are low; approximately 6°C

lower than international recommendation. A study carried out by the Building Research

Association of New Zealand (BRANZ) confirmed very low indoor temperatures in winter, as

New Zealand houses were found having an average temperature in the living rooms of

15.8°C, and 14.1°C in the bedrooms (Isaacs, Camilleria et al. 2006).

BRANZ established a project to collect and update data on the residential use of energy for

heating in New Zealand. The Household Energy End-Use Project (HEEP) collected energy

and temperature data from 400 randomly selected houses that represented typical housing

throughout New Zealand. The project ran for a ten year period, which commenced in 1995.

HEEP found that in non-insulated houses during the winter months of June, July and August,

the typically warmest room was the living room which had an average temperature of 17.8°C

(French, Camilleria et al. 2007). The mean temperatures recorded between 5pm and 11pm

ranged from 10°C to 23.8°C, with temperatures below WHO's optimum of 20ºC for 83% of the

time. Bedroom median temperatures ranged from 13.42°C to 15.38°C, which do not meet the

WHO and even not Beacon’s High Standard of Sustainability (HSS™), New Zealand’s IAQ

optimum guideline minimum temperature of 16°C. The lower temperatures in the range could

be attributed to older, non-insulated houses. HEEP records that the summer months of

December, January and February had a stable range of internal temperatures between

20.5°C and 21.5°C (Isaacs, Camilleri et al. 2005). Indeed it was found that large eaves that

were common in pre-1978 houses protected the house interior from the solar heat gain from

the summer sun.

51

WINTER LIVING ROOM TEMPERATURES

Period Minimum Mean Median

Morning 8.78°C 13.98°C 13.88°C

Day 9.85°C 15.91°C 15.87°C

Evening 11.86°C 17.79°C 17.85°C

Night 10.63°C 16.01°C 16.07°C

Internal house temperature national averages for New Zealand living rooms

(French, Camilleri et al. 2006)

WINTER BEDROOM TEMPERATURES

Period Minimum Mean Median

Morning 7.98°C 13.1°C 13.42°C

Day 8.13°C 14.57°C 14.64°C

Evening 8.45°C 15.18°C 15.38°C

Night 8.24°C 14.43°C 14.61°C

Internal house temperature national averages for New Zealand bedrooms

(French, Camilleri et al. 2006)

ROOM Mean winter temperatures (°C)

Morning

7 – 9 a.m.

Day

9 a.m. – 5 p.m.

Evening

5 – 11p.m

Night

11 p.m. – 7 a.m.

Living room 13.5 15.8 17.8 14.8

Bedroom 12.6 14.2 15.0 13.6

Ambient

(Outside)

7.8 12.0 9.4 7.6

Table of national average temperatures for a New Zealand house.

(French, Camilleria et al. 2007)

Comparing the mean winter temperatures for the four different periods during the day for the

living room, bedroom and outside ambient temperature, it was found that during the day the

bedroom was only 2.2 C warmer than outside. The living room was not much better, being an

average 3.8 C warmer. The mean temperature of the living room increases from the morning

to the evening, which indicates the use of heating in the morning, solar benefits during the

day, and heating in the evening. New Zealand homes are known to have a tendency to zone

heat one room, which is usually the living room, rather than the whole house. This is reflected

in the higher temperatures found in the living rooms. It was found that 18% of houses

52

maintain a heating source through the night, and this is reflected in the lowered temperatures

of the living areas overnight. (11 p.m. – 7 a.m.) (French, Camilleria et al. 2007).

In Auckland, 87.5% of living rooms and 90.6% of bedrooms were below the WHO

recommended temperatures. Bedrooms that aren’t used in the day become subject to a

sudden increase in moisture load when people go to bed. The impact of this moisture is

problematic as typically the bedroom is unheated, poorly ventilated and uninsulated, leading

to condensation, which is then followed by mould growth.

The problem of cold housing has been a long term problem for New Zealand housing, as

historical evidence shows. Prior to HEEP research in 1994/5, national data had not been

recorded since the 1971 Household Electrical survey. Mean temperatures recorded in this

survey show the temperatures of houses were approximately 1°C lower than houses that

were insulated to meet the requirements of the first level of mandatory insulation in New

Zealand. In 1971 temperatures averaged at 15°C in Living areas and 14.4°C in bedrooms.

Average Living room temperatures in 2000 for Hamilton recorded 16.7°C, and in 2001/2

Auckland recorded 16.5°C. In the northern area of New Zealand, pre and post 1978

insulation demonstrated a variance of 1°C (Household Energy End-use Project 2003),

confirming that mandatory insulation at low levels, applicable to the floors and ceiling only,

provided insignificant thermal improvement.

Figure 4. 4

HEEP and 1971 historical Living Room temperatures

(Household Energy End-use Project 2003)

Auckland, which has a mixed climate, typically has house interiors that are warmer than the

external temperatures, although minimally when insulation isn’t installed. Evidence recorded

from non-insulated houses demonstrates interior temperatures are 1-2 degrees higher than

the ambient temperature (Lloyd, Bishop et al. 2007). Auckland houses with solar

considerations such as eaves have reduced solar gain in summer, therefore interior and

ambient temperatures are closely matched.

53

Uninsulated New Zealand homes are known for having cold, damp and uncomfortable

interiors and that consequently, they are wasteful of energy contributing almost a third of New

Zealand’s total energy use, which is consumed by 20% of households (NZBCSB, 2008).

EECA have found that a major cause of wasted energy and health issues is the lack of

insulation in New Zealand homes (Energy Efficiency and Conservation Authority 2009).

Clearly, New Zealand housing is drastically lacking in warmth. Unfortunately for the

occupants of almost two thirds of New Zealand’s homes, a warm and comfortable indoor

temperature is not achievable due to heat escaping through the draughty and uninsulated

building envelope.

4.8 AIRTIGHTNESS

Air tightness or air permeability, is the effectiveness of a building to restrict uncontrolled

leakage of air through the building envelope. Air leakage through uncontrolled air movement

within a building envelope causes damage and reduced performance of insulation materials,

transports air pollutants, is detrimental to human health, causes unnecessary waste of energy

and reduces thermal comfort. Air leakage, can occur through gaps in the building envelope

typically found around window sashes, doors, and through the building structure and linings,

and open fireplaces.

Internationally, air leakage has become recognised as one of the major causes of energy

consumption and discomfort in the buildings of many European countries. WHO has

commented affirming that for the conservation of energy, adequate measures need to be

undertaken to tighten building envelopes as well as to rectify ventilation deficits and

inadequate or improper insulation (WHO, 2009). The importance of airtightness for energy

efficiency and IAQ is seen in the recent implementation of many national and international

standards, in particular the European Directive on Energy Performance of Buildings (EPBD).

There is a variety of International performance levels for airtightness, but countries such as

Czech Republic, Germany, Denmark, Spain, The Netherland, and Norway define the

minimum requirements on airtightness in their regulations (Leardini and Van Raamsdonk

2010).

New Zealand has no national regulation for the provision of airtightness in residential

buildings, and yet it is evident that uncontrolled moisture can be transported into the structural

components of a building, at the risk of building degeneration. Consequently a number of risk

factors for mould and indoor pollutant levels can be found in different housing types, both old

and new, of the New Zealand building stock.

54

Airtightness is important for the effectiveness of thermal insulation and ventilation, and even

more particularly in exposed coastal areas in high wind zones, as air infiltration is normally

driven by wind, and air pressure differences between the indoor and outdoor air.

Air pressure within a building is affected by differential air temperatures on the inside and

outside faces of the building envelope, which is impacted on by climatic seasonal change.

Temperature differential between a house interior and exterior changes the pressures around

and within a building structure, so as that with an exterior temperature that is lower that the

interior temperature, the air flows from the inside of a structure towards the outside,

transporting heat with it. Not only does this incur heat loss that increases the demand on

heating, differential pressure that causes the airflow that transports heat also transports water

vapour and contaminants causing migration from the interior through the building envelope,

attempting to escape to the cold, external environment.

Evidence of New Zealand’s cold housing history can be seen in figure 4.4, which shows little

difference between the indoor and outdoor temperatures. As these temperatures are so

similar, there hasn’t been a problem with condensation in housing. The introduction of higher

insulation levels to meet the requirements of NZS4218:2007 will lead to higher indoor

temperatures that will increase the temperature differential between indoor and outdoor

environments. Consequently the outside face of the insulation material can have a

temperature that is close to the dew point, therefore without the correct technology, warm air

that transmits through the wall condensates when it reaches cold exterior material. Within

timber framed cavities such as walls, air-transported moisture that permeates the building

fabric causes dampness, mould and degradation of the timbers, metals, insulation and linings

within.

Strategies can be implemented to minimise the risk of moisture damage by controlling

moisture entry into the building envelope. Impermeable ‘vapour barriers’ such as polyethylene

vapour barriers, foil-faced fibreglass-wool insulation and reflective radiant barrier foil

insulation on the interior of air-conditioned assemblies were used in the past but were soon

linked with mouldy buildings. Such a solution is clearly unsuitable as in preventing moisture

from entering the building envelope it can also prevent moisture from leaving it, and

conversely a system that is successful at eliminating moisture may also allow moisture to

enter. A balance between entry and removal is required.

Airtightness is required to prevent the leakage of humid indoor air to the colder side of the

thermal insulation layer, therefore a permeable vapour membrane installed on the higher

pressured side of the building, retards vapour movement without preventing vapour

transmission. Where vapour barriers and vapour permeable membranes differ is that a

vapour barrier prevents water, whereas a vapour permeable (check) membrane allows water

55

to penetrate through, in a controlled manner. Vapour permeable membranes need to be able

to breathe, and require the following properties: vapour permeance, mechanical strength in

tension, shear, impact and flexure, adhesion, elasticity, thermal stability, ease of fabrication,

application and sealing (WHO, 2009). The vapour permeance characteristic is defined by the

effective ‘wet cup’ permeance of both the cladding and vapour check combined, which is

categorised as follows:

• Vapour impermeable is less than or equal to 0.1 perm

• Vapour semi-impermeable is less than, or equal to 1 perm and greater than 0.1

perm

• Vapour permeable is greater than 1 perm (Lstiburek 2004)

The New Zealand climate has moderate seasonal change over most of the country. The

northern region, is often wet, particularly Auckland which has high levels of relative humidity

(RH). The temperature differences between summer and winter have opposing effects on the

envelope of a structure. In summer the inside face of the external layer (e.g. weatherboards

on a wall) is cold, but in winter with heat from the house interior, it becomes the warm surface.

To correctly accommodate moisture transmission, a breathable membrane is needed on both

faces of an element (e.g. a wall) to provide low diffusion permeability in winter and high

diffusion permeability in summer (Goldau and Roth 2007). Vapour checks are humidity-

variable, diffusion permeable membranes that provide airtightness to prevent air movement

from reducing the thermal capacity of insulation material. They allow moisture to escape

according to the humidity level the vapour check is exposed to, ensuring that interstitial

condensation does not occur. Low diffusion permeability protects the building structure from

dampness, mould and rot; and high diffusive permeability allows moisture to dry out of the

structure (Goldau and Roth 2007). Therefore the integrity of the building element is protected,

and the thermal insulant is able to perform to its best ability.

4.8.1 AIR TIGHTNESS TESTING – WUFI AND BLOWER DOOR

To evaluate a building for airtightness an air pressure test is applied to check for air leakage.

A blower door test (as described in the European Standard EN 13829:2000) can be used to

diagnose the amount of air leakage a building has. A Blower-Door test consists of a

calibrated fan for measuring an airflow rate, and a pressure-sensing device to measure the air

pressure created by the fan flow. The combination of pressure and fan-flow measurements is

used to determine the building airtightness. Measurements performed in pressurised or

depressurised buildings, where climatic or other external influences are minimized due to high

pressure difference created by means of a fan, allow a reliable prediction of ventilation rates

in buildings (Leardini and Van Raamsdonk 2010).

56

Typical results relevant to New Zealand housing typology testing airtightness ac/h at 50 Pa

are as follows:

Airtight 5 ac/h Post 1960 houses with a simple rectangular single story floor plan of

less than 120m2 and airtight joinery (windows with airtight seals)

Average 10 ac/h Post 1960 houses of larger simple designs with airtight joinery

Leaky 15 ac/h Post 1960 houses of more complex building shapes and with

unsealed windows

Draughty 20 ac/h All pre 1960’s houses with strip flooring and timber windows

(Bassett 2001)

The BRANZ database of over 100 residential building airtightness measurements (Basset,

2001) was used to develop the above mentioned classification of New Zealand house

airtightness in four type categories, each characterized by a “base level infiltration rate”.

One of these categories was LPSH, built before 1960 without insulation or building paper

within the building envelope which were described as leaky and draughty buildings. With an

airtightness level of 20ac/h LPSH perform very poorly. This is four times New Zealand’s

required rate of air exchange of 5 ac/h (New Zealand Government 2007), which falls short of

international comparison. The rate of ventilation in Germany for passively ventilated houses

is 3 ac/h at n50 (Leardini and Van Raamsdonk 2010). The updated version of NZBC H1 is

somewhat lackadaisical in addressing airtightness as it is ‘a requirement to consider’, but it

does not provide limitations to be met. However airtightness is extremely important in NZ due

to high RH and risk of condensation as explained before. Moisture control is necessary when

designing construction solution.

There are new tools for predicting hygrothermal performance of building components such as

WUFI (Wärme und Feuchte instationär). WUFI is a software programme that calculates the

hygrothermal performance of the layers of a building envelope that is exposed to natural

climatic conditions. WUFI calculations that have been done on standard timber framed

housing with and without intelligent vapour checks indicated that the greater the temperature

differential between the internal and external temperatures of a building, the more important

the internal moisture control became in winter time as well as in summer time. New

Zealand’s unique climate of cold winter temperatures and warm summer temperatures

provide a challenge for the performance of vapour barriers. Vapour barriers are required on

the outside face, beneath the cladding, in summer; and on the inside face beneath the wall

lining in winter to prevent air exfiltration.

57

Using WUFI simulation, DeGroot (DeGroot 2009) assessed State Housing that had been

specifically retrofitted with insulation to meet the requirements of NZS 4218:2004 (to achieve

a minimum level of thermal ;performance of the envelope), which requires insulation levels of

R2.9 for the ceiling, R1.9 for the walls and R1.3 for the floor. For the simulation WHO

recommended air temperature and humidity levels for the house interior were used and the

ambient temperature was that of Auckland’s climate. Results showed that ‘interstitial

condensation occurred and the moisture content of the insulation layer remains always very

high, with relative humidity over 80%’ (DeGroot 2009; Leardini and Van Raamsdonk 2010).

When WUFI testing was applied to standard timber framed construction that had vapour

checks (vapour transmission resistance: 1.275 MNs/g – 53 MNs/g, humidity variable) it was

found that the vapour check was important to control moisture dissipation through the building

envelope, most particularly as the temperature differential increased between the inside and

outside of the building envelope, applicable to both summer and winter climates (DeGroot

2009; Leardini and Van Raamsdonk 2010).

4.9 VENTILATION

Fresh air is not only important to an occupants perception of a space and their productivity, it

is essential for their health & well-being. For healthy human respiration, occupied buildings

require adequate ventilation to remove contaminants that exist in the air, as well as moisture

& odours that can be unpleasant or hazardous. To be protected from the adverse effects of

allergens produced from mould growth and dust mites, adequate ventilation rates are

essential. Without ventilation, moisture accumulates and leads to increased condensation,

and where low ventilation meets cold surfaces, such as external walls, and in low ventilated

areas, the risk of mould growth increases, as cold surfaces without air movement will grow

mould (WHO, 2009). Wardrobes and cupboards, especially when they adjoin external walls,

will often have mould due to their lacking ventilation. Easily detected by human senses,

indicators of inadequate ventilation are condensation, stale air, musty odour, mildew and

moulds.

The New Zealand Building Code (NZBC) requires that houses are ventilated with outdoor air

to maintain air purity. The New Zealand Department of Building and Housing (NZDBH)

requirements for ventilation and moisture management is the provision of good ventilation, a

warm and dry house, heating, extraction fans to areas exposed to excess steam i.e. the

kitchen and bathroom, and good insulation to keep the home warm and to reduce

condensation and mould growth. As with heating, the magnitude of ventilation required

depends on the building size and the external climate. International ventilation rates of an air

change every two or three hours, which is 0.35 – 0.5 air changes per hour (ac/h) is commonly

accepted to provide fresh air and remove contaminants.

58

Clause G4 of the NZBC relates to ventilation, providing the requirements for ventilation to

supply and remove air to a space by either natural or mechanical means, to ensure that

adequate fresh air is supplied to ‘safeguard people from illness or loss of amenity due to lack

of fresh air’. Ideally the air in a home should be ‘renewed’ every two hours, even when the

house is unoccupied, either by using passive air vents by leaving windows secured in an ajar

position, or by a mechanical ventilation system such as heat recovery ventilation (New

Zealand Government 2008). NZS4303:1990 ‘Ventilation for Acceptable Indoor Air Quality’,

stipulates an air change with fresh out door air to be distributed throughout the home every 3

hours, which is 0.35 ac/h (Mc Chesney 2009).

In a UK typical dwelling the graph below shows the effect of ventilation rates on the internal

relative humidity and the energy consumed to maintain heating levels. It can be seen that the

fuel rich households are more capable of maintaining ventilation to reduce the RH, but the

energy consumption for space heating is high (Wilkinson, Smith et al. 2007).

Figure 4. 5 Hypothetical relation between ventilation rates and indoor relative humidity for fuel-

poor and fuel-rich households and energy to heat ventilation air. (Wilkinson, Smith et al. 2007)

Ventilation can be provided passively, by opening windows, or actively by mechanically

provided ventilation to maintain a constant comfortable and healthy interior climate throughout

the year. The challenge with ventilation is to maintain room temperatures without heat loss.

That there can be considerable heat loss could be argued as a reason for occupants’ to not

ventilate housing.

It was recognised in New England that uncomfortable homes can make people take action

that makes a home unhealthy. A lack of comfort can lead to a lack of ventilation and over-

humidification. If people are cold, they won’t ventilate their home. If people can’t afford to

heat their home they will not ventilate their home (Lstiburek and Brennan 2001).

59

It is apparent that to avoid the loss of valuable heat to cold exterior temperatures, windows

remain closed for human comfort. A solution to this is heat recovery ventilation systems

which require airtightness, but are the most reliable technology available for cost effective

heat retention as well as providing adequate, controllable ventilation. It is necessary to have

controlled air movement to avoid unnecessary heat loss.

4.9.1 PASSIVE VENTILATION

Passive (natural) ventilation is the most common form of ventilation used in New Zealand,

provided by manually using windows, doors and vents. Passive ventilation relies on wind

pressure and stack effect. Stack ventilation relies upon the pressure difference between the

indoor and outdoor environments. As warm air rises it is replaced with cold air. The problem

with passive ventilation is that ventilation rates are uncontrolled causing draughts, and the air

intake brings with it pollutants from outdoors. Natural ventilation can be used in combination

with mechanical ventilation to increase cooling.

Ventilation rates for occupied spaces of New Zealand household units is given in Clause G4

of the NZBC, in which clause 1.2.1 states that ‘an area of at least 5% of the floor area is to

have windows that open to the outside air’ (New Zealand Government 2008).

Natural ventilation can be used in combination with mechanical ventilation to increase cooling.

Opening windows for natural ventilation in summer provides effective passive cooling, but in

winter it causes heat to escape from the warm house interior. As the capacity of ventilation

within a building is affected by the climate, and prevailing wind the building is located within.

Wind is affected by topography, house location, the built form, vegetation and surface

pressures around the house. Therefore the amount of opening windows needs to be a design

consideration to correctly size and locate opening windows. Window placement and

ventilation openings positioned to activate through-ventilation allows cross ventilation to assist

in drawing air through the room / area interior. Ventilation can be taken from different aspects

to introduce cool or warm breezes. Larger windows that open to the breeze and smaller,

higher windows on the walls on the opposite side of the house will encourage air flow through

the building. The New Zealand breezes from the south or east will provide a cool breeze from

the start of the day, which is advantageous in summer but will undesirably cool the house in

winter. Ventilation from the north and west, positioned higher up on the wall encourages air

movement. LPSH positioned the larger windows to the north, lesser windows to the east and

west, and smaller utility windows to the south; therefore they have good passive cooling

ability through ventilation.

60

4.9.2 MECHANICAL VENTILATION SYSTEMS

New Zealand is not amongst the countries that have a mandate to provide mechanical

ventilation, but NZS4303 does set a requirement for air changes when natural ventilation

requirements can not be met, which therefore requires mechanical assistance.

The most well used mechanical ventilation in New Zealand has been mechanical extraction

such as fans, extracts, rangehoods. Positive pressure and heat recovery ventilation systems

rely on electricity of varying capacity to extract or supply air, and rates of air removal is

dependant on correct sizing of the extract and motor capability. Mechanical extraction is

beneficial to housing as it removes excess moisture from rooms that are heavily exposed,

typically steam in bathrooms, laundries and kitchens. As isolated extractor fans remove the

moist air by extraction only, there remains a requirement for the provision an air intake, which

is usually provided by an opening window. Opening a window causes heat loss, which in a

cold climate is undesirable to human comfort levels for warmth.

Mechanical ventilation systems that are used to provide controlled ventilation and heat in

housing are either positive pressure roof cavity ventilation (heat transfer), or balanced

pressure heat recovery ventilation systems (HRV).

Figure 4. 6 Positive pressure roof cavity ventilation system (forced) and

Balanced air heat recovery ventilation systems.

(Image from Heatpumps NZ)

61

POSITIVE PRESSURE / ROOF CAVITY HEAT TRANSFER VENTILATION

New Zealand appears to have welcomed the use of mechanical ventilation systems in

housing, with an increased use from 1% in 1999, to 6% of houses surveyed in 2005 (Clark,

Jones et al. 2005). They have been used successfully in the UK since the 1970’s to rectify

condensation problems (Stephen, 1998). They have also been beneficial to many of New

Zealand’s damp houses (Smith et al., 2008). New Zealand preference has been for the

heavily marketed, positive pressure roof cavity ventilation systems (Clark, Jones et al. 2005).

Such systems rely on using warm air found in the roof cavity between the ceiling and roofing,

to fan supply ducted warm air into the house interior, on an assumption that the roof space air

is warmer than the exterior. The air from the roof enters the house through ceiling vents,

relying on pressure to force the air out through air gaps. Along with the air that is forced out

through gaps, heat is lost.

Positive pressure roof cavity systems rely on assumed solar collected heat from the roof

space being gathered and transmitted through ducts into the house interior. Given that

heating of the house interior is needed in winter, when sun hours are reduced, this is an

ineffective system, as verified by studies undertaken by the University of Otago. The

University of Otago and BRANZ studied an older style typical New Zealand weather board

house with a metal roof, and ceiling insulation, to predict the heat transfer from the roof space

to the living area. The model was located in Dunedin, with National Institute of Water and

Atmospheric Research, (NIWA) data applied for other cities that include Auckland. Tests

applied to the roof space in all four seasons found the highest heating potential was 0.52kW,

which is comparable to five 100W light bulbs. It concluded that the roof space would not

reach a sufficiently high temperature to be able to increase the living area temperature during

the cold external temperatures experienced in winter (Fitzgerald, Smith et al. 2011).

To prevent the transfer of contaminants from vermin mould and dust that are commonly found

in roof spaces being transferred to the house interior with the air supply, filters are relied

upon. Human intervention is required for their regular replacement. EECA recommendation

is that supply air for home ventilation systems should be sourced from the outside, not from

the roof cavity. Forced air systems do not comply with NZS4303:1990.

BALANCED PRESSURE HEAT RECOVERY VENTILATION SYSTEMS (HRV)

Heat Recovery Ventilation (HRV) ventilates the entire house with pre-warmed fresh air. The

heat exchange transfers the heat reclaimed from the already heated air it has extracted, and

transfers this to the fresh air intake. Heat is added to maintain the temperature required, but

the additional energy required is minimal. With adequate air intake, balanced pressure air

systems comply with NZS4303:1990.

62

HRV is a balanced pressure mechanical system that allows filtered air to be introduced at

controlled ventilation rates to supply an adequate amount of fresh air required for occupant

health, with minimum heat loss. They require a heat exchange unit, as defined by the

American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE), which

enables heat to be transferred from one air flow into another air flow, retaining and re-using

the recovered heat. HRV systems provide constant and secure ventilation and fresh air

supply. Of the two types of mechanical ventilation systems available, HRV is better suited to

providing IAQ as it can control relative humidity and remove airborne irritants by stale air

extraction, as well as providing a reliable, and less contaminated ventilation at a controllable

rate to suit the requirements of the space it services.

In an airtight house, with a suitable source of heat, a HRV system allows the heat to be

retained and circulated throughout the entire house. A HRV system balances the air pressure

between the house interior and exterior, which reduces pressure related air flow, and allows

ventilation to be controlled. As seasonal change requires, additional ventilation and cooling

can be provided by manually opening windows. The air intake vents that are typically located

in a dry situation such as beneath the protection of an eave enable continuous air movement

in all weather conditions. By controlling ventilation, the heat loss associated with ventilation is

minimised, which reduces the demand on energy consumption to maintain room

temperatures. This system of maintained heat and continuous ventilation is particularly

suitable for cold climates. Where heat is to be retained for warmth, HRV provides efficient

energy use by using a heat exchanger that requires minimal equipment to retain existing heat,

introduce warm fresh air and to extract moisture. Up to 90% of the heat energy that would

otherwise be wasted through passive ventilation can be reclaimed for reuse within the entire

house interior, to be reticulated through ducts back to all areas of the house.

HRV systems operate using two fans for two separate air streams and a heater unit, which is

usually located in the roof cavity. One fan supplies fresh outdoor air into the house through

several ceiling vents supplying each room, while the exhaust fan extracts an equal volume of

air from inside the house and discharges it to the outside. The exhaust air stream transfers

some of its heat energy into the incoming air in a heat exchange unit for redistribution into the

house interior. HRV extracts air from areas of greatest contamination within a house, filters,

and replaces it with an equivalent volume of pre-warmed fresh air. An airtight house is

required to control ventilation losses through air movement, and to ensure all air is transferred

through the heat exchanger (Energy Efficiency and Conservation Authority 2010).

63

Figure 4. 7 Heat Recovery Ventilation heat exchanger

Source: mikegigi.com

In Canada, Inuit housing is known to be lacking in ventilation, with consequential respiratory

disease, more dominantly caused by mould than dust mites. A Canadian study over six

months, in which Inuit houses equipped with heat exchange ventilation units were compared

with placebo houses. This study found a significant decrease of CO² level and relative

humidity (RH), of 33% and 17% respectively (Kovesi, Zaloum et al. 2009). The indoor air

quality of those houses with HRV improved, with reduced respiratory symptoms for the

occupants.

4.10 IAQ GUIDELINES FOR NEW ZEALAND HOUSING

In New Zealand, guidelines to improve the quality of indoor air have been established by

Beacon Pathway, but they are not mandatory. Beacon Pathway was founded to work with

government agencies to research areas where residential energy savings could be found.

Their aim was that 90% of New Zealand housing would be sustainable by 2012. In setting

gaols for housing to meet, Beacon Pathway established high standard of sustainability

(HSS™) benchmarks for New Zealand housing. The temperatures are as per WHO

recommendations, with the additional criteria that house interiors have adequate ventilation

without excessive draughts; a mean relative humidity of 40-70%; mechanical ventilation to

extract moisture from the kitchen, bathroom and laundry; and that there are no unflued gas

heaters or air conditioning. The benchmarks to be met to achieve energy savings, and also

improve indoor environment quality (IEQ, referred to in this thesis as IAQ), has the following

criteria:

64

Temperature Living room evening in winter mean minimum temperature of 18°C;

Bedroom overnight in winter minimum mean temperature of 16°C.

Relative Humidity Living room evening in winter 40 – 70%; preferably 40 - 60%

Bedroom overnight in winter 40 – 70%; preferably 40 - 60%

Surface relative humidity < 80% all year.

Ventilation rate 0.0 – 0.75 ac/h for existing houses.

0.4 – 0.6 ac/h for new houses.

Biological Visible mould or mould odour to be less than 0.5m² in entire house.

Check list Mechanical extractor ventilation of kitchen, bathroom and laundry;

Means to passively ventilate dwelling;

No unflued gas heaters;

No indoor clothes drying.

HSS™ Indoor environment quality key criteria for IES

4.11 INSULATION

4.11.1 THE HISTORY OF INSULATION IN NEW ZEALAND

New Zealand’s first houses were made of available natural materials, such as Raupo reeds

walls and Nikau roofs which had good thermal performance (estimated as an R-value of 2.1

(Household Energy End-use Project 2003), and earth construction which gave protection from

the rain and wind. The insulation values these houses had were not again matched in New

Zealand until 2000, to meet the energy efficiency requirements of the new building code

(Household Energy End-use Project 2003). The colonisation of European immigrants that

arrived in New Zealand in the mid 1800’s introduced houses that were constructed using

lightweight timber framed construction. An estimated ninety percent of houses built between

1890 and 1910 were well built with enclosed air cavities formed by 4” x 2” dry timber

framework, externally clad with timber weatherboards, and internally lined with thin horizontal

boards of timber covered with scrim and paper. Roofs and ceilings were also timber framed,

with corrugated iron roofing over. Open fires that heated the house interior, also provided

ventilation. The English styled double hung windows used, leaked air which provided air flow

(draughts). The houses kept the rain and wind out and were dry, warm and well ventilated.

(Isaacs 2007) As New Zealand’s climate would have been mildly temperate to the new

immigrants who had arrived from the colder European climate, this poor thermal protection,

estimated to be R0.6 (Household Energy End-use Project 2003), may have been acceptable.

In the 1930s, green (wet) timber was used for house framing which needed ventilated wall

cavities for drying. Poor quality workmanship and tiled roofs allowed air infiltration to the roof

space. Casement windows were designed and made with weather-grooves for weather

protection, such grooves being sizeable enough to prevent capillarity water transmission from

65

the house exterior to the house interior (i.e. rain) (NZCIDE, 1965). An open fire in the living

room only, left other areas of the house cold, and air infiltration from the fire place, leaking

windows and roof, caused draughts. The R-value of these houses dropped even further to an

estimated R0.3 (Bastings and Benseman 1950; Household Energy End-use Project 2003).

By the 1940’s it was reported that fifty percent of all new houses had evidence of mould

growth. This impacted on a number of the newly built State Houses. In 1944, State Advance

Corporation commissioned DSIR to investigate the sudden increase in moulds found on

ceilings and walls. It took three years to investigate, and Lyndon Bastings, a scientist for the

Dominion Physical laboratory of DSIR, concluded the solution was to increase thermal

insulation and ventilation, and look into more efficient home heating (Isaacs, 2007; NZCIDE,

1965; McLintock, 1966). Government investigated insulation options, although they were not

implemented, possibly as a result of its high cost as insulation was an imported building

product at the time.

The first set of recommended R-values was published in 1950 by Bastings and Benseman. It

showed a range of forty-two wall types who’s R-values ranged from a low value of R 0.27 for

a concrete veneer with a 50mm ventilated cavity and plaster and pumice sandwich board, up

to R1.35 for lightweight timber framing with 100mm mineral wool insulation and asbestos

cement sheet cladding. A following publication on how to keep warm in winter and reduce

mould problems was written by Bastings in 1954, called ‘Handbook on the insulation and

heating of buildings with special reference to dwellings’. The book demonstrated a fifty

percent drop in thermal performance between traditional 1920’s weatherboard walls with

cavities, compared to 1950’s walls of brick veneer with lath and plaster. It found that R values

were less for the newer construction having a value of R 0.3, as opposed to the older

construction being R 0.6, concluding that “it was changes to the houses, not to the occupants

behaviour which were causing mould growth” (Isaacs 2007)

Local manufacture of glass fibre began in New Zealand in the 1960’s, making it more

affordable to use, but it wasn’t until 1971 that it was first introduced as a bylaw requirement

for house construction. Waimairi County, near Christchurch in the South Island, was the first

local authority to introduce a thermal insulation bylaw as a response to clean its air and ban

fires as a means of home heating. This was followed by the Christchurch City council in 1972

(Greenaway 2004). Air pollution was a problem as wood and coal fires were commonly used

for residential heating, and by introducing thermal insulation, houses would be kept warmer.

In 1972 Christchurch City Council introduce R-values based on the proportion of windows in a

wall area, which was the first time this was factored into thermal design in New Zealand

(Isaacs 2007). Also in 1972, BRANZ presented a proposal for minimum levels of house

insulation which was based on the calculation of optimum expenditure on thermal insulation

66

(H.Trethowen and E.Hubbard 1972). Their analysis supported the first NZS insulation

regulation introduced in 1977.

Following the world oil crisis and low hydro lake storage in New Zealand of 1973 to 1974,

government introduced an interest-free loan scheme in 1975 for insulating houses to

minimum levels to conserve energy. At the same time requirements were also established for

all new houses built by or for HNZC.

It wasn’t until 1977 that New Zealand had its first building legislation that made insulation a

compulsory part of New Zealand housing, with the introduction of NZS 4218P:1977 (minimum

thermal insulation requirements for residential buildings) All new housing built from 1978

when the code was activated were insulated. This code was used as an acceptable solution

under the current Building Code (H1/AS1). In 1992, the Verification Method (H1/VM1) was

added to the NZBC based on the Building Performance Index , and in 1996 thermal standards

were further updated to NZS 4218:1996 Energy Efficiency – housing and small building

envelope. In 2000 the mandatory New Zealand Building Code was implemented which

included Clause H1/AS1 that specifically relates to provision for energy efficiency used for

modifying temperature and or humidity, and water heating (Building Industry Authority 2000).

In 2004, NZS 4218 was updated in to include limitations for window areas and introduced a

higher thermal requirement for that increased the use of double glazing. The third edition of

the NZ Building Code Clause H1 came into effect in October 2007, setting even higher

thermal performance requirements for housing.

The latest revisions to the building code is NZS 4218:2009 (Thermal Insulation Housing and

small buildings), which replaces the 2004 edition of this code. It clarifies the use of the three

options of determining R-values, which are Schedule method, Calculation method and

Modelling method). The intention of the revision is to reduce energy consumption by 30%

meanwhile still achieving comfortable temperatures within new homes. This code, as with its

predecessors, does not address compulsory insulation to the existing structure when a house

is being altered.

The table below shows the gradual improvements of insulation into New Zealand housing with

very low R-values for most of the country’s housing.

67

Historical Development of Insulation Levels’ in New Zealand Housing

Table 1: Schedule method component R-values (mandatory levels in bold).

Year Source and date Roof

M²˚C/W

Wall

M² ˚C/W

Floor

M² ˚C/W

Glazing

M² ˚C/W

1950 Bastings and Benseman 0.6 0.7 0.7 –

1964 Bastings 0.6 0.7 0.7 –

1971 Waimairi County 1.2 0.7 0.9 –

1972 Christchurch City 1.0 1.0 1.1 –

1972 BRANZ 1.6 1.1 0.9 –

1975 Government loan scheme min. 1.6 1.6 – –

1975 NZ Housing Corporation 1.6 0.9 0.8 –

1978 NZS 4218P: 1977 1.9 1.5 0.9 –

1987 DZ4218 (review draft) 2.6 2.0 0.9 –

1990 DZ4218 (draft) 3.0 2.0 0.9 –

1989 Ministry of Energy (recom-

mended)

3.2 2.0 1.3 –

1991 ECNZ Medallion Award 3.0 1.5 2.0 –

1992 NZBC Clause H1/AS1 1.9 1.5 0.9 –

1996 NZS 4218: 1996 * 1.9 1.5 1.3 –

2000 NZBC Clause H1/AS1 1.9 1.5 1.3 –

2003 PAS 4244: 2003 (Best) 3.3 2.6 3.1 0.43

2004 NZS 4218: 2004 1.9 1.5 1.3 0.15

2007 NZBC Clause H1/AS1 2.9 1.9 1.3 0.26

BUILDING CODE THERMAL PERFORMANCE REQUIREMENTS - 1978 TO CURRENT

YEAR

STANDARD

COVERAGE

R-VALUES (m² °C/W)

CEILING WALL FLOOR WINDOW

GLAZING

1978 NZS4218P:1978 New Zealand 1.9 1.5 0.9 -

1996 NZS4218:1996 Zones 1 and 2

Zone 3

1.9

2.5

1.5

1.9

1.3

1.3

-

-

2009 NZS4218:2009 Zone 1 and 2

Zone 3

2.9

3.3

1.9

2.0

1.3

1.3

0.26

0.26

Changes in the R-values required by New Zealand building regulations

68

4.11.2 UNINSULATED NEW ZEALAND HOUSING

Up until 1978 in New Zealand, insulation was an option used by either the wealthy or the well-

informed. Prior to this insulation was an option usually not afforded. In the era of that time,

electricity was cheap, supplied on demand, and was used to heat with little consequence of

the environmental consequence.

Uninsulated houses had problems that grew like the moulds within them. The New Zealand

public was not well informed of health issues related to the well utilised homes generations

were growing up in. New Zealand was a hardened outdoor type of nation who toughed up to

our climate, both indoors and out! Rather than thermally address the building, we thermally

addressed ourselves, wrapping up in hand knitted woollen garments as typical of that era as

insulation wasn’t. That the cold air breathed was well below what was internationally

recognised as healthy, was not common knowledge. What became discovered were

increased health problems such as allergies and asthma, to reach a current scenario where

New Zealand now has the second highest incidence of asthma in the world. The wonderful

clean, green image and the outdoor climate and environment New Zealand is internationally

recognised for, is veiled beyond the exterior of most of our homes.

The majority of New Zealand housing does not perform well in providing comfortable internal

environment in either air quality or energy efficiency, falling well short of what has been

established as a global guide established by WHO. New Zealand is no exception to current

global housing problems, and currently is exposed to many consequential health problems

that are related to cold and damp housing. Houses are cold due to physical conditions which

include cold external temperatures, lacking insulation, uncontrolled air leakage, and

inadequate heating sources.

New Zealand housing is relatively poor in terms of thermal comfort, particularly houses built

before 1978 due to the lacking legislation for compulsory insulation in new houses. Even with

the introduction of NZS 4218P:1977 – ‘Minimum thermal insulation requirements for

residential buildings’ insulation was inadequate by comparison to current requirements.

Consequently most houses, particularly those built prior to 1978, are difficult and unaffordable

to maintain at a comfortable temperature as they do not retain heat.

Since 1978, levels of insulation have gradually improved, particularly with the most recently

introduced legislation, NZS4218:2009 in which there are upgrades of R-values, and

importantly, it includes thermal glazing requirements for the first time in New Zealand.

Unfortunately though, this code is applicable only to new housing and to areas of house

alteration work, but it is not applied to the entire existing house where alterations are being

undertaken. As there is no requirement for retrofitted insulation, areas of altered houses will

69

remain cold and wasteful of the energy that is required to maintain a comfortable indoor

temperature. New Zealand research has confirmed that insulation is associated to reduced

energy use, as report in by HEEP (Isaacs, Camilleria et al. 2006). To have made insulation

mandatory to all building works encompassing the entire house provides an opportunity

beneficial to energy efficiency. Given that housing is affected by the climate it is built in,

climate can and should influence the design requirements accordingly.

In addition to legislation that specifies the quantum of insulation requirement, to assist in

improving the quality of insulation installation, NZS4218 was introduced to provide better

performance levels for insulation in providing guidance for the correct installation of insulation.

The historical and current levels of insulation applicable to new NZ housing is identified in the

following chart, and map of the designated climatic zones 1, 2 and 3:

Figure 4. 8 Map of climate zones

Source: Department of Building and Housing

New Zealand’s total housing stock of 1.6 million has about 1.04 million houses that were built

prior to 1978 when mandatory insulation regulations for housing were introduction in New

Zealand. This is about 65% of the current housing stock, and in is estimated that 900,000

houses are still inadequately insulated (Amitrano, 2006). Some have partial insulation. Aged

insulation has slumped or been blown about ceiling spaces to sit at variable depths, which

reduces the thermal properties to become inefficient. Of the existing houses that have

insulation it was found that 64% have no underfloor insulation, 29% have inadequate or no

ceiling insulation and 71% have no wall insulation. Unfortunately for the occupants of almost

two thirds of New Zealand’s homes, a warm and comfortable indoor temperature is not

achievable due to heat escaping through the draughty and uninsulated building envelope.

EECA has found that a major cause of energy and health issues is the lack of insulation in

New Zealand homes.

70

Figure 4. 9

Ceiling standards in existing New Zealand housing

(NZHCS, 2005)

Beacon Pathway estimated that New Zealand will have 1.7 million homes in 2012, of which

ninety percent are existing houses (Easton 2010). The level of insulation in at least half a

million houses was either non-existent, partial or sub-standard, with higher numbers lacking

wall and floor insulation (Ministry for the Environment 1998-2010). Of the two-thirds of the

existing housing stock that was built before 1978, an estimated forty percent of houses have

had some retrofitted insulation installed. Insulation was most commonly found in the ceiling

where there is easy access for installation through the roof space. The 2005 BRANZ house

survey verifies the inadequacy of insulation levels. Since this survey, insulation R values

levels have been raised, therefore more houses than are represented require thermal

improvement.

Beacon Pathway has a goal to meet before 2012, that 90% of New Zealand homes will reach

a higher level of sustainability, which includes a high standard of insulation capable of

maintaining a minimum temperature of 18ºC. To achieve this, insulation is required for

housing built prior to 1978. Although the BRANZ house survey shows that 69% of houses

have ceiling insulation, in reality the level provided is insufficient as aged insulation poorly

installed or movement of insulation compromises its thermal ability.

It has become critical to upgrade not only the condition of New Zealand existing housing

stock, but to improve their performance to higher levels of sustainability, for social, economic

and environmental reasons (Easton 2010).

71

Figure 4. 10 Representation of the amount of New Zealand housing that requires renovation work

(Easton 2010)

4.12 HEAT LOSS

Heat loss is determined by the sum of accumulated heat loss from each element of a building

structure (Mc Chesney, Cox-Smith et al. 2008). Without insulation to resist heat loss in light

weight timber housing, there is a significant amount of heat lost through the building

envelope. The rates of heat loss are variable between houses, but approximately 21-31% of

heat escapes through the walls, 18-25% through the windows, 12 -14% through floors, 30-

35% through ceilings / roofs and 6-9% through air gaps.

For houses to retain heat a complete envelope is needed, therefore ceilings, walls, windows

and floors all require thermal protection. Heat loss through any element of building structure

is proportionate to the area of such an element, therefore to increase the resistance value of

one element of a structure (e.g. ceilings), does not adequately compensate for heat loss

though other elements (e.g. walls). Uninsulated walls are common in pre 1979 housing and it

is estimated that this affect 700,000 New Zealand houses (Mc Chesney and Amitrano 2006).

72

Figure 4. 11 Heat losses through uninsulated and insulated housing.

73

The heat loss through walls is dramatically reduced by even a simple level of insulation

application. R1.0 Insulation applied to an uninsulated wall assumed to have a value of R 0.4

restricts the amount of heat loss to 700W, which is a reduction of 70% (with an assumed heat

flow of 1000W). Upgrading the level of insulation to R2.0 further reduces heat flow by an

additional 12% (Mc Chesney, Cox-Smith et al. 2008). R-values beyond this level provide

minimal reductions of 3%; therefore it can be assumed that the optimum R-value for insulated

timber framed walls is R2.4.

Figure 4. 12

Diminishing returns effects by adding increments of insulation to walls (Mc Chesney, Cox-Smith et al. 2008)

Insulating homes to the minimum level in the NZBC, it is estimated that annual savings in

home energy usage of approximately 30% can be expected. This equates to about a $760

annual saving for the energy expenditure for a home in Auckland, and up to $1,800 for a

home in Dunedin (Department of Building Construction 2008). Greater savings can be

achieved by upgrading the thermal performance level beyond what is required by the NZBC.

74

A better and best practice for R-values that are beyond the building code requirements for

timber framed housing in the warmer two zones of New Zealand are portrayed in the following

chart:

R VALUES FOR LIGHT TIMBER FRAMED HOUSING

Zones 1 and 2

(North Island excluding the

Central Plateau)

Building code

minimum

Better practice Best practice

Roof R2.9 (Outdated) R3.3

Walls R1.9 R2.1 R2.6

Floor R1.3 R1.9 R3.1

Preferred insulation levels for timber framed housing

(Source NZS 4218:2009 and 4244:2003) (Department of Building and Housing, Ministry for

the Environment et al. 2007)

4.13 INCENTIVES AND EDUCATION A number of agencies have been established in New Zealand to encourage house owners to

improve the energy efficiency of their houses, for the benefit of energy conservation, and to

reduce energy related greenhouse gas emissions.

The Energy Efficiency and Conservation Authority (EECA) is a government agency

established under the Energy Conservation and Efficiency Act of 2000. It recognised that the

energy conservation in the residential arena can make a difference to energy consumption.

With the expert assistance of Building Research Association (BRANZ) and the Centre for

Building Performance Research (CBPR), research has been undertaken with the intention of

educating New Zealand residential dwellers in how to use energy efficiently. EECA works to

promote practices and technologies to further energy efficiency, energy conservation, and the

use of renewable sources of energy by raising the public awareness of New Zealanders its

importance. The established a goal for 2008 through to 2011, is to create warmer and drier

housing that is healthier to live in, with improved air quality and lower energy costs (Energy

Efficiency and Conservation Authority, 2008). EECA has used information campaigns

providing information via media outlets that include television, radio, and print advertising,

events, websites, sponsorship and speaking opportunities, and proactive media

communications (Energy Efficiency and Conservation Authority, 2008).

Energywise is associated with EECA to provide the subsidies and grants to help low and

modest income homeowners insulate and heat their homes where they have been built prior

to 2000 (Energy Efficiency and Conservation Authority, 2008). The amount of the subsidy

varies, but generally a $1300 grant is available if both the ceiling and floor is insulated to

75

NZBC standards. The government meets the full cost of insulation those with community

services cards – typically low income earners such as the elderly (pensioners), sickness

beneficiaries and young families. There is also is funding of $500 available for an approved

source of heat. Under the umbrella of EECA, the Energywise Home Grant programme has

insulated more than 300,000 houses by 2007, and this programme still continues. The

'whole-house' retrofitting under this programme included ceiling and underfloor insulation,

draught-proofing, underfloor ground sheets, hot water cylinder wraps and pipe insulation, low-

flow shower heads and low energy light bulbs (Beacon Pathway Ltd). Although the intention

is valid, the retrofits were often inadequately done. The intended scope of works to achieve

the 'whole-house' solution was not always complete, and workmanship skills in the installation

were found to be inadequate in many situations. The level of insulation provided was low.

The Ministry for the Environment established the Warm Homes project to find ways to

encourage New Zealand households to use cleaner heating sources and increase household

energy efficiency to achieve warmer and healthier homes. With energy conservation the goal,

an investigation was done to find the social drivers that would influence home owner’s

decisions on insulation and heating, and what financial or other incentives were necessary for

their home, to achieve behaviour change (Ministry for the Environment 1998-2010).

New Zealand Business Council for Sustainable Development (NZBCSD) recently undertook a

two year research project that sought improvements for the 433,000 homes that were causing

occupants illness. The study discovered that 59% of owners could not afford to improve the

warmth and energy efficiency of their homes (New Zealand Business Council for Sustainable

Development 2009). Current government subsidies of $1,300 for insulation, and $500

towards a heat source are a small potion of the actual costs. There is a need for home

improvement packages whereby grants or loans are made available from local councils,

power providers and banks, to provide the stimulus and affordability for many to activate

retrofit options.

The NZBCSD study also found that most people surveyed wanted a performance rating on

houses to demonstrate the value of its upgrade. Overseas evidence shows that there is a

perceived increase in the property value of between 5 and 10%, with an added advantage

being such properties rent out quicker and with a higher rental return to the owner (Murdoch

2008). Performance rating for housing is now available in New Zealand, called Homestar™.

Funding for insulation provides for the ceilings and floors only. Although almost half of a

houses heat is lost through walls and windows, there is no incentive to encourage or assist

insulating this large area of the building envelope. That these areas are more difficult to

access costly of retrofitting insulation means that a large amount of New Zealand’s energy is

76

lost, and wasted. This costs the owner in increased energy expenditure, and health risk; and

it cost the country in health expenditure and carbon credits.

4.14 THE NEED TO INSULATE

The greater the temperature differential between outdoors and indoors, the more beneficial

insulation becomes for human comfort. Now, there is also a need for energy conservation.

Insulation works by trapping air, limiting heat loss from passing through it. Heat is transferred

by conduction, convection or radiation, or by a combination of all three, and it moves from

warmer to colder areas. If the exterior is colder than the inside air, heat is drawn the outside.

The greater the temperature difference, the faster the heat will flows to the colder

temperature. Insulation is an effective way of improving the energy performance of a building,

by reducing heat losses in winter and minimises heat gains in summer. Bulk insulation traps

air, and as air is a poor conductor of heat, it slows heat transfer. The ability of an insulating

material to resist heat transfer gives an R-value, with a higher number indicating a higher

performance level of the insulator. Connectors in the building fabric often create thermal

bridges such as timber framing that connects the exterior to the interior, which influence the

overall R value of the building fabric.

The installation of product with high R - values, avoidance of thermal bridges in the envelope

and correct detailing is required to achieve sustainable buildings with excellent energy

efficiency. Insulation also needs to be kept dry to avoid it loosing its thermal properties and to

avoid mould growth.

Figure 4. 13 Heat transfer

Source: Image from Saint-Gobain Isover

An insulating product is measured by its thermal conductivity in watts per kelvin per meter

(W/mK), with the other elements of the built fabric of the structure being factored in to

establish the R value of an element. Multiplied by a temperature difference (in kelvins, K) and

an area (in square metres, m2), and divided by a thickness (in metres, m) the thermal

77

conductivity predicts the rate of energy loss (in watts, W) through a piece of material

(Wikipedia, 2010). The R-value is the reciprocal of this.

The interior surface of an insulated element of structure is warm to touch. Although the

element of a building that the majority of heat dissipates through is the ceiling, the human

body is in physical contact with the floor surface, and passes by or rests against walls and

windows, which if left uninsulated are uncomfortable for humans to touch or be near.

Therefore, along with the fact that walls are usually the largest areas in the building fabric,

insulating the walls will provide human comfort as well as have a major impact in reducing

energy requirements. Walls and windows are also a single element between the inside and

outside, as opposed to ceilings and floors which are often secondary to the external element,

being sheltered by roofing and foundation walls.

4.14.1 RESEARCH INTO THE BENEFITS OF INSULATION

PAPAKOWHAI STUDY

Beacon Pathway undertook a three year study investigating the performance of nine, pre-

1978 houses on the perimeter of Wellington, in Papakowhai. This study demonstrated that as

well as ceiling and floor insulation, wall and window insulation needs to be included to retain

heat to be able to achieve adequate comfort levels in winter.

For the Papakowhai study, a range of simple interventions were examined to demonstrate the

significant difference that can be made to the sustainability of the housing stock, particularly

when implemented in combination. Houses had nine retrofit alternatives applied to them,

which involved practical application which was regarded as being ‘straightforward for a

competent and suitably qualified tradesman’. The installations into the existing structures

were to fit insulation into the ceiling cavities and underfloor, and to replace the internal wall

linings to allow for the fitment of wall insulation. A specialised installer was required for the

more difficult task of replacing the windows with double glazed IGUs and frames.

The retrofit interventions at Papakowhai were of three different thermal insulation levels:

1). Increased ceiling insulation and installation of underfloor insulation, providing

a basic intervention.

2). Heavy ceiling and underfloor insulation was fitted to achieve a standard level

of intervention.

3). A high level was applied by fitting ceiling, floor and wall insulation, double

glazing and an efficient space heater.

78

All levels were higher than the minimum New Zealand standards require, as these minimum

R-values have been proven to not provide adequate improved indoor air temperatures, or

energy savings.

The houses in which windows, walls, ceiling and floors were insulated and efficient heating

installed saved the most electricity and had the biggest temperature gains. Energy costs were

reduced, with savings of 23-33% (2,480kwh - 930kwh), meanwhile achieving temperature

increases that ranged from 2.5°C to 5.5°C.

Partial insulation upgrades did not make significant improvements to the indoor air

temperatures and comfort, or provide reduced heating costs. Confirming “it is important

therefore to insulate the full thermal envelope if good reticulated energy savings and

temperature improvements to HSS® -2006 standards are to be made’ (Easton 2009).

MONITORING EFFICIENCY UPGRADES IN STATE HOUSES IN SOUTHERN NEW ZEALAND A research project was undertaken by the University of Otago on the effectiveness of

upgrading uninsulated or partially insulated houses. The study included 1940-50’s

weatherboard State houses in the southern South Island investigating how to make them

warmer by reducing heat loss through improved thermal insulation. Physical improvements

were made to provide warmer indoor temperatures, lower energy usage, drier living

conditions, more air tight building envelopes, and non-energy benefits such as occupant

health benefits, subjective improvements (such as more contented householders) and other

societal benefits.’

Minimal increases to the indoor temperature were found. Temperatures required for

comfortable or healthy living were unable to be met due to inadequate heating and heat

losses through the uninsulated light timber-framed walls, leaky windows, single glazing and

large gaps in the external building fabric, in particular the suspended timber floor. The report

established that insulation is a cost effective way to retain heat, suggesting that upgraded

insulation needs to extend beyond the basic ceiling and floor upgrades. The entire building

envelope needs to be insulated as well as reducing air movement to achieve a minimum of

0.75 ACH. Additional comments for improvements were that insulating the underfloor with

fibreglass batts would be of greater benefit than the under floor foil insulation used.

RETROFITTING HOUSES WITH INSULATION TO REDUCE HEALTH INEQUALITIES: A COMMUNITY-BASED RANDOMISED TRIAL

This was a research study undertaken on 1350 mixed types of housing, although largely

single-storey, standalone, pre-1978 uninsulated houses across a range of areas throughout

New Zealand in which at least one person had symptoms of respiratory disease. These

79

houses were selected to be retrofitted with insulation. Although It was not possible to install

all of the package into all of the houses due to access limitations, the model insulation

package installed for this study was the standard New Zealand Energy Efficiency and

Conservation Authority package, which consisted of ceiling insulation, draught-stopping

around the windows and doors, sisalation (insulated foil) strapped to the underside of the floor

joists and a polyethylene covering was laid over the ground (Howden-Chapman 2005). The

study was done through the three winter months of 2001. It needs to be noted that recent

legislation has improved the levels of insulation since this study, arguably providing higher

energy savings than was discovered (Chapman, Howden-Chapman et al. 2009).

Having expended an average $1800 per dwelling on the retrofit installation, total savings

shown in the study (monetary value of benefits discounted back to the point at which the

costs are incurred) amount to NZ$3374 per household, netting benefits of $1574 per

household. More than half the total benefits (61%) were health sector gains related to

hospitalisation, but this is an achievable national cost saving. The health gains and energy

savings that will arise from the investment will accumulate over time as costs increase

(Chapman, Howden-Chapman et al. 2009). The overall result of a benefit–cost ratio

approaching two (and an NPV of around NZ$1570 at a discount rate of 5%) means that the

benefits accruing over time, in terms of health gains and energy savings, are a comfortable

margin in excess of the costs of installing insulation in the houses in the study (Chapman,

Howden-Chapman et al. 2009).

This study found that the costs of installing insulation suggested beneficial health gains, and

energy and CO² emissions savings one and a half to two times the cost of retrofitting

insulation. The benefits of insulating homes able to have an ‘actual’ value assigned were

improved health, savings in energy and associated greenhouse emissions. Additional

benefits were the everyday improvement of physical and emotional wellbeing from living in a

warmer and more comfortable home, and avoidance of premature mortality (Chapman,

Howden-Chapman et al. 2009).

Indeed the most effective way of retaining heat is by applying adequate insulation, and as the

London Economist reports, house insulation improvements represent the lowest cost way of

achieving carbon emission reductions (London Economist, 2007).

80

Figure 4. 14 Comparison of costs for different ways of cutting carbon emissions’

A national priority on sustainable development, and the national-scale benefits that would

accrue from an improved housing stock, provides strong reason to be made for incentivising

retrofitting existing uninsulated housing. This is needed to achieve the Government’s vision

of being a sustainable nation, carbon neutral, and to meet our commitments to the Kyoto

Protocol.

4.14.2 INSULATION IN NEW ZEALAND

Historically insulation in New Zealand has been minimal and poorly fitted. There are many

products that settle, and their initial performance factor is reduced accordingly. The New

Zealand Standard, NZS 4246:2006, Energy Efficiency –Installing Insulation in Residential

Buildings provides installation guidance to ensure insulation is correctly installed to achieve

the best thermal performance and thermal durability of the building element. This code

recognises a number of important factors that are applicable to all new buildings, and parts of

new construction in renovations .It states that although vapour barriers are not methods of

insulation, they are included as a means of protecting and enhancing the performance of

insulation materials.

The acceptable solution to NZBC Clause E3 Internal Moisture requires that the exterior walls

and ceilings of habitable spaces, and the exterior walls and ceilings of wet area rooms of

housing are insulated. It is explained that this is to ensure internal surface temperatures can

be maintained at levels that reduce the likelihood of condensation and consequent fungal

growth on building elements.

81

NZBC Clause B2 Durability requires that building materials continue to provide compliance

with the other clauses of the NZBC for lengths of time, varied depending on their function,

accessibility, ease of replacement and detection of failure. The ingress of moisture,

settlement, air movement, and slight movement of materials encasing the insulation are some

of the causes of deterioration of insulation materials or their installation. As insulation is a

product hidden within the building envelope it is difficult to measure its failure, therefore it is

required to have a durability of not less than 50 years.

There is a large range of international product available for installation in light timber framed

construction. These include: Aerogel, cellulose fibre flakes, flax, hemp, lambs wool,

strawbales, wood shavings, glass wool, rock wool and polystyrene. These products can be in

various forms to suit different locations - Rigid panel, mat blankets, roll blankets and blown to

name a few. Their performance is limited by the thickness available .i.e. strawbales need

great thickness to achieve adequate thermal performance, and would not be suited to LPSH.

Breathing walls, using timber frames, wood fibre boards and natural insulations are quite

common overseas. Hygroscopic insulation absorbs and releases moisture in its vapour form,

allowing it to pass through the wall without affecting the insulating properties of products

used. Natural hygroscopic insulates such as cellulose, sheepswool, hemp, and flax are

preferable to synthetic insulation such as glass and mineral fibres, and polystyrene foams

which do not perform hygroscopically. Natural insulation products are a preferred sustainable

option having lower embodied energy than mineral fibre options, and along with wood fibre,

they are biodegradable helping to achieve a zero waste building solution (Morgan 2008).

4.15 THE IMPORTANCE OF CORRECT INSULATION INSTALLATION

The total resistance-value (R-value) of a building element is the sum of the surface

resistances on each side of a building element and the thermal resistances of each

component of the building. This includes any cavities and the representative structure of the

building element, less the effects of any thermal bridging. Poor installation of insulation

allows air movement around the product, which has the ability to halve the insulation value of

the building element. Incorrect installation that causes folds, tucking in, and gaps as small as

2mm will be detrimental to the performance of the insulation. Also, if insulation becomes wet,

the thermal resistance and the durability of insulation will be reduced.

The correct conditions for insulation need to be evaluated prior to installation to ensure it is

dry. Adequate space needs to be available to prevent compaction, with product selected to

suit the thickness and performance of the situation the insulation is being retrofitted into. It is

important to ensure that the insulation has room to remain at its designed thickness as

82

compression of the insulation into a cavity smaller than the design thickness will reduce its

actual delivered R-value, e.g. compressing a material that delivers R2.0 at 100mm down to

80mm will result in an R-value of approximately 80% of R2.0, or R1.6 (Standards Council

2006).

When retrofitting wall insulation that has no vapour barrier (building paper), a new vapour

barrier needs to be provided to the exterior before the insulation is fitted to help protect

insulation from being damaged by condensation. The figure below shows how to retrofit into

existing cavities within the timber framing, wrapping and fixing the membrane to the existing

framing.

Figure 4. 15 Retrofitting building paper into an existing wall cavity

Source: NZS 4246:2006

4.16 INSULATION PRODUCTS:

Insulation products are produced from a range of products, and in a number of forms to suit

differing requirements. Typically blanket and segment products are used, although blown

products are useful for existing situations that can be difficult to access for manual installation.

The following is a summary of the various forms of insulation, which is followed by a range of

products available, or that have been available in New Zealand.

83

WOOL AND WOOL BLENDS

Approximately R1.8 for 100 mm thickness.

Figure 4. 16 - Wool insulation

Wool is an ecological natural product. It often has a small percentage (aprox 5%) of polyester

added as a support and bonding fibre and is treated to discourage mould and pests. Being

hygroscopic, wool insulation allows the structure to breathe, balancing the moisture content in

the air by absorbing moisture and releasing it later. It is a comfortable product to use, and is

easy to install. Wool products have lower R-values than fibreglass of the same thickness, and

are more expensive. Wool will burn if it comes into direct contact with a flame, but will not

ignite through heat or help a fire to spread. Wool products can be sprayed with a resin to bind

the fibres and provide strength, or blended with polyester for binding to hold its structure.

Wool will re-loft should it become wet.

WOOD FIBRE BOARD

35mm board: W/mK = .049

Figure 4. 17 - Wood fibre board insulation

Tongue and grooved wood fibre board provides insulation properties and has the ability to

form an airtightness layer. It is hygroscopic, ecological, environmentally-friendly and

recyclable. It is flexible for installing, fixes over the framing, and one of its benefits is that it

avoids thermal bridging.

84

WOOD FIBRE FLEXIBLE INSULATION BOARD

Figure 4. 18 – Wood fibre insulation

Wood fibre is a non-irritant, hygroscopic, flexible insulation that fits into cavities within timber

framing. It is semi rigid for ease of installation and can be installed to reduce thermal

bridging. It is ecologically and environmentally certified and recyclable.

MACERATED PAPER

Approximately R2.0 for 100mm loose fill

Figure 4. 19 – Macerated paper insulation

Recycled paper treated with a fire retardant can be used as loose fill insulation in ceilings. It

uses PVA glue to reduce settlement. Its performance depends on the quality of the

installation, ensuring that all levels are even. This product is commonly used internationally,

particularly in the UK, but is not used in New Zealand.

85

FIBRE GLASS WOOL

Approximately R2.0 for 100mm thickness.

Figure 4. 20 - Fibreglass wool insulation

This is the most commonly used insulation material in New Zealand, and it tends to be

cheaper than alternative options. Its technical performance is well proven and it outperforms

most other materials of the same thickness in R-value, but it has many detriments. Most

fibreglass insulation is made from recycled glass with formaldehyde resins. Glass fibres can

break away easily to become airborne, raising concerns about health impacts on installers

and occupants from the small fibres invading breathing passages. Fibreglass is not

comfortable to handle and can cause irritation of the skin and respiratory tract. It can

compress, becomes brittle with age and is susceptible to sag. It does not perform when it is

wet, and once wet it will not reloft. Fibreglass does not burn, but it can melt in the intense heat

of a house fire. The International Agency for Research on Cancer (IARC), part of the World

Health Organisation, lists glass wool insulation as “not classifiable as to its carcinogenicity to

humans”.

POLYESTER

Approximately R2.0 for 100mm blanket or segment.

Figure 4. 21 – Polyester insulation

86

Polyester insulation is a non-renewable resource made from petroleum that has good thermal

performance. The performance of polyester is similar to wool in that it is non-irritant and

retains its loft, and is effective even if wet, but it is not hygroscopic. The health concerns

raised about fibreglass do not apply to polyester. Polyester will not burn easily, but it will give

off dense smoke.

POLYSTYRENE

Approximately R1.4 for a 50mm thick sheet

Figure 4. 22 - Rigid polystyrene board

Closed or open cell polystyrene is a product of the petrochemical industry and therefore a

non-renewable resource, but it is recyclable. Its insulation properties are excellent. It must

not be in contact with electrical cables insulated with plasticised PVC. It is waterproof, but is

not hygroscopic. It can provide airtightness, but it is difficult to get a tight fit into existing

framing. Most commonly it is used beneath timber floors being inserted between floor joists.

BLOWN FOAM

R value varies

Figure 4. 23 – Blown polystyrene foam insulation

87

Polyurethane foams have higher R-values than most other materials. They are non

hygroscopic, and condensation can form as a result of dewpoint on the product. The foam

product is injected into cavities as a liquid which then expands and sets, leaving considerable

moisture within the structure as it dries. Installation requires an expert applicator. Foams

such as urea formaldehyde and polyurethane can release harmful gases such as

formaldehyde (a known carcinogen) over a long period, contributing to indoor air pollution.

FOIL SISALATION

R value dependent on air gap

Figure 4. 24 – Foil sisalation

Foil sisalation consists of paper coated in bitumen and aluminium foil. Rather than being bulk

insulation, foil works on its reflective quality to reflect heat back to its source, and that it traps

air within a cavity. Sisalation needs airtightness to function, therefore it needs to be well

installed. It does not provide a satisfactory level of insulation. Sisalation and polythene

ground sheets laid to prevent ground dampness rising beneath housing, in combination with

heated house interiors have caused floor boards to dry out. The air gaps release the trapped

air beneath the flooring, which negates the effect of the sisalation. Corrosion or dust that

disrupts its reflective ability can reduce its effectiveness over time. Typically it is staple fixed,

so extreme care is required when stapling around electrical wiring. It is easily damaged and

its conductive ability with electricity has seen this product banned from many markets,

including New Zealand’s. Foil by itself is no longer accepted as complying with the Building

Code for underfloor insulation.

88

4.17 WINDOWS

Windows are the coldest portion of a building envelope as a pane of glass provides a very

thin layer between differential temperatures. Single–glazed windows conduct heat at ten

times the rate of insulated walls (Department of Building and Housing, Ministry for the

Environment et al. 2007), allowing heat to escape at ten times the rate that it will through an

insulated wall. External cold temperatures are transferred directly through the glass, making

them an uncomfortable element of a house structure for humans to be near. Windows are

often a large component area of a wall, so require solar control to prevent overheating of a

space.

Single glazing has an R value of approx. 0.19, which is very low. The Housing Insulation

Standard (NZS4218:2S04) recommends double glazing, which has an R-value of 2.6, where

the window area is greater than 30% of the wall it is within. Double glazing traps air between

layers of glass, providing an insulation layer that separates the air temperatures between the

exterior and interior, which keeps the internal layer of glass at a temperature that is

comfortable to be near. It also prevents condensation from forming on the glass surface.

In situations where windows are single glazed, heavy weight curtains can minimise the cold

from entering, but this option is effective only at night. Unless the curtains have containment

by e.g. pelmets and the floor, cold air is able to circulate from behind the curtain to cause cold

draughts. A common occurrence in New Zealand is to find black mould spots on the back of

curtains where they sit against condensated glazing. It is indeed a preferable option to

double glaze, and in the case of LPSH this requires retrofitted double glazing into the timber

window frame.

89

CHAPTER 5: THE HISTORY OF LABOUR PARTY STATE HOUSING

Labour Party State Housing (LPSH) is a significant part of New Zealand’s architectural and

social history. Established by New Zealand’s first Labour Party in 1935, LPSH became the

country's largest, government funded, mass housing scheme. LPSH was socially motivated

to give hope, and the opportunity for many New Zealanders to live comfortably (Oliver). They

linked many New Zealanders who have lived in, and made a LPSH their home at some stage

during their lives, some of whom have resided in their State home for their entire lives.

LPSH was built throughout the fourteen year term that Labour governed, a period that

spanned from the end of the Great depression, through six years of World War 2 as well as

New Zealand’s post-war recovery. Labour lost the 1949 election to the National party, and

from then there was a redirection of the philosophy of LPSH. The provision of housing

continued for a number of years under both National and Labour governments.

LPSH provided homes for nearly 280,000 people (15% of the New Zealand population). By

August 1959, over 620,000 dwellings had been built (which included 822 flats) which, on

average, accommodated 4.5 people per dwelling (Weston and Jones 1959). This was a

unique housing programme and social undertaking initiated by the political Labour Party and

funded by the Governments of New Zealand, never seen before or since in the history of New

Zealand.

The LPSH typology that evolved set a pattern for ensuing private development housing

schemes (Group Housing). These mass-produced, privately developed housing schemes

followed the construction methodology and planning philosophy that was used for LPSH,

often replicating the same plans. Minor aesthetic changes were made; the obvious

differences being the inclusion of lower pitched corrugated iron roofs, and modified window

elevations simplified by the deletion of glazing bars.

5.1 THE POLITICAL HISTORY OF STATE HOUSING

5.1.1 PRE-LABOUR GOVERNMENT FUNDED HOUSING

Governments (Reform and Nationalist) prior to the Labour Party being elected into power had

been interested in, and provided lesser versions of State house building schemes.

In 1894 the Government Advance to Settlers Act 1984 was introduced to accelerate the

development of New Zealand, by lending money at affordable rates for urban and rural land

90

development. It was modified by following governments, however the policy of government

funding for resources benefited the productive and social development of New Zealand. This

was the basis of what later became the State Advances Corporation (SAC), an important

factor in LPSH.

In the early 1900’s, Workers Dwelling Houses were established under the Liberal

administration of Richard Seddon and his 1905 Workers Dwelling Act. This, and the

Advances to Workers Act 1906, provided the mechanism for the construction of several

hundred of the first State house rental properties. The intention of the Liberal Party was to

provide inner city workers with a higher standard of living than what was available at the time.

Throughout the life of this scheme, the production of houses was on average about 77

houses a year (Wells 1944). High rents set under the scheme led to the end of the

programme in 1919.

The Reform government then introduced The Housing Act 1919, with an intention to supply

funds for low income workers to buy homes. Lending was easily obtained, providing low

equity mortgages (funding up to 95% of the costs). Mortgages were capped at £1250. The

onset of the Depression years that followed in the 1920’s – 1930’s caused defaults of

payments on loans, bringing about the collapse of the scheme and leaving the Government

as the largest mortgagee. The 1919 Housing Act was later used for LPSH. State Advances

was replaced by ‘The Mortgage Corporation’. Where State Advances had been known as the

‘financial bulwark and friend of the people’, the Mortgage Corporation was by contrast known

as ‘a soul-less business concern, and an instrument of private finance’ (Oliver).

Neither of the housing schemes of the first part of the century provided enough houses to

meet the required demand. Building activity declined in New Zealand as a result of the

1930’s Depression, which added to the shortage of housing already caused by the increased

populations that had developed in Auckland and Wellington in search of employment.

THE EARLY 1900 HOUSING

The standard of housing was not good. Houses at the time were poorly built, as the average

builder knew little about sound building practice. House ownership at this time became

increasingly unaffordable due to the lack of money, confidence, and unemployment that the

Depression had brought, and rental property became the favoured housing option. Typically

working class families lived in overcrowded and sub-standard conditions, often forced for

reasons of affordability to share rental accommodation, sometimes two or three families to a

house. Collectively, the deterioration of housing developed inner city slums.

The acute shortage of housing was recognised by the governing Coalition (Reform and

United Parties), and the new Labour Party, a political rival in the upcoming election in 1935.

91

In 1934 the New Zealand Prime Minister, Joseph Gordon Coates, travelled to the UK where

he was inspired by the housing schemes, slum removal and rebuilding that he saw there. His

preference was to improve the existing housing by upgrading the unsatisfactory houses.

Secondary to this was his intention to initiate the building of new houses to provide for future

needs. Immediately prior to the 1935 government elections, and possibly for political gain, he

published a pamphlet titled ‘Housing in New Zealand: an outline of Policy’ explaining the

objectives of the Reform Party. They intended to conduct a national survey of building

conditions, and then to address New Zealand’s housing problems, subject to the findings of

survey. The Housing Survey Act 1935 was placed before Parliament in October 1935.

THE HOUSING SURVEY ACT 1935

Coates directed his Housing Committee to conduct a survey under the Housing Survey Act

1935, extracting data on the existing houses on which to base a housing rectification

programme. He also set up the Mortgage Corporation to provide low interest loans for

funding the proposed works.

The housing survey was undertaken in 119 New Zealand towns that had a population greater

than 1,000 inhabitants. It obtained information on houses to establish the number of rooms;

the physical condition of the dwelling; age, sex and number of occupants; owners and

occupiers; rental costs; extent of overcrowding; population densities of residential areas;

construction; facilities (food storage, cooking, washing, sanitary); light and ventilation; outdoor

yard and air space (1936). Occupancy per dwelling and per room was sought to confirm the

extent of overcrowding.

The survey investigated 225,363 houses, populated by 901,353 occupants. Of these, 27,214

houses were found to be sub-standard, and 9,835 overcrowded. This confirmed there was a

shortage of adequate housing, estimated as being about 20,000 (Firth 1949).

Labour had also recognised the need for housing, but addressed it with a different approach.

The problem of affordable housing had been recognised and needed to be solved. When

they were elected, they took the data and quickly progressed with their plans for building new

houses away from the slum areas of the inner city.

The Survey Act became a common link between the outgoing and incoming political parties,

as it was passed on to be administered by the newly elected Labour Party.

92

5.1.2 THE FIRST LABOUR PARTY

At the 1934 Labour Party pre-election conference, a goal had been set to provide reasonable

housing for all classes, with fixed rents relative to earnings, thus reducing the existing high

rents (Oliver).

Labour was first elected into power in 1935, with Michael Joseph Savage as Prime Minister.

Other politicians that were influential in LPSH were Walter Nash, John A. Lee and Peter

Fraser. Nash had a ministerial portfolio that included Finance, State Advances, and Land and

Income tax. Lee was Parliamentary Under Secretary to the Minister of Finance (for Housing).

Following the death of Savage in 1940, Peter Fraser was promoted to Prime Minister.

Once elected, Savage commenced the LPSH programme, which set a pattern for the future of

New Zealand housing. Suburbs of State Houses of similar design were built during this

programme, to become an iconic vernacular throughout the country. The Labour Party used

government funding to provide quality homes for New Zealanders that they would be proud to

live within, as is reflected in the following comment Savage made in 1936:

“I think we can have smiling homes in New Zealand; that we can use the public credit

for the purpose of building homes worth living in” (Metge 1972).

In 1937, Savage, in Mirimar Wellington, ceremoniously opened New Zealand's first Labour

State House. This was followed later in the same year, when he also opened Auckland’s first

State House in Orakei, with similar ceremony. From then, an average of 2,198 ‘bright and

attractive’ houses were built per year, a vast amount more than what the two preceding

government housing schemes had achieved (Wells 1944).

THE HOUSING AIM OF THE LABOUR PARTY

The newly elected Labour Party wanted to provide new suburban homes for working-class

people who were living in rundown inner-city districts. Savage had intended that there would

be no more slums, and that “only the best houses are good enough for New Zealand” (Metge

1972). The inherited problem of acute overcrowding was too urgent to wait for the outcome of

the Housing Survey commissioned by the previous government. A manually computed

estimation of the housing shortage established that between 12,000 and 20,000 houses were

needed. 16,000 houses was the average set as a goal to be achieved.

As part of the 1936 Budget, Labour Finance Minister Walter Nash announced that 5,000 State

rental houses would be erected under the Housing Act of 1919, at a cost of £3 million

(Schrader 2005). These houses were to be owned by the State and let to New Zealanders at

93

‘fair rents’ which were aimed at being less than 20% of the tenant’s income (Metge 1972). In

Walter Nash’s vision, ‘planning for housing on any national scale meant in effect, planning for

the future of the Nation’ (Wells 1944).

THE ESTABLISHMENT OF THE FIRST LABOUR PARTY STATE HOUSE SUBURBS

Government purchased hundreds of hectares of suburban land throughout the country, upon

which private builders, engaged by government, erected thousands of high-quality, modern,

State houses to provide homes for New Zealanders. This revitalised the building industry and

helped restore a deflated economy that was still recovering from the Great Depression.

The Ministry of Housing Department was set up in 1936, headed by John A. Lee. It was

administered and financed by State Advanced Corporation (SAC), for the purpose of building

new State houses, with SAC also responsible for letting the completed houses.

Lee travelled overseas to research international examples of large scale, low-cost housing

schemes and related legislation, to prepare a report that directed a scheme for mass housing

in New Zealand (Oliver). The Row housing and Tenement blocks seen overseas were not

suited or desirable for use in New Zealand. He was eager to follow a Swedish scheme used

to rebuild Stockholm, using factory-built, pre-fabricated, mass-produced housing, but this did

not eventuate as time demanded that housing construction get underway promptly Although

many aspects of his report were rendered redundant (1936), Lee’s determination that houses

were varied visually, so no two houses in one street looked the same was adopted. He also

considered it necessary to have a balanced cross-section of people in every street, mixing

old-age pensioners with young families, avoiding streets of equal income earners.

Figure 5. 1 A street of mixed aesthetics used to individualise LPSH

Photo taken by the Author in 2010

94

Figure 5. 2 Street view of new LPSH

Photo from NZ National Archives – Wellington (AALF 6112 Box 1)

Government needed to address the urgency and physical practicality of constructing

hundreds of new houses. The Railways Department registered their interest, suggesting they

be involved in the building of the proposed house building scheme as they had built 1,595

five-roomed, standardised cottages between 1923 and 1928. Savage had little confidence in

the existing Public Works Department’s ability to achieve the £3 million housing scheme. He

chose to respond to written correspondence he had received prior to Labour being elected,

from James Fletcher, head of the Fletcher Construction Company.

Fletcher was a prominent self-made industrialist and builder who was skilled in dealing with

politicians. His company, Fletcher Construction, had been established since 1917 and had

expanded into manufacture and distribution of New Zealand made materials. Fletcher

favoured Labour’s policy of stimulating business and industry over the Coates led (Reform)

government focus on farming. His recognition of the post-depression need for employment

for nearly 80,000 men had prompted him to write to the current Coalition Government Minister

of Employment in 1934. The letter expressed a suggestion that provided employment, and

new housing to replace the existing slum areas in the cities of Auckland and Wellington. He

had also copied the letter to the opposition party, being the Labour Party. As well as practical

measures for recovery from the depression, Fletcher’s proposal was to a degree self

interested, needing to generate work for his construction related companies.

Following the election, Fletcher again wrote to parliament offering his Construction company’s

expertise and services to assist with the proposed building scheme which led to meetings

between Fletcher, Savage and Nash. Fletcher was recognised as having a reputable

company, being reliable, of good reputation and having a wealth of experience. Savage

accepted his offer to get the project underway with an early start (Metge 1972).

95

5.2 THE COMMENCEMENT OF LABOUR PARTY STATE HOUSING

Fletcher’s enthusiasm was an important part of the physical realism of State House building.

As well as being an established building company, Fletcher had a plentiful supply of local

materials, owning timber mills and forests, and companies Consolidated Brick and Pipe, and

less well known was ownership of 50% of Certified Concrete. Prior to Labour being elected

Fletcher had planned his own development of a group housing scheme, and had paid ₤1,500

to have 400 plans prepared by a number of architects, each with two or thee options of

elevations for the same plan, to suit the position of the sun (Cheer, 2010). James Fletcher

prepared a State Housing scheme for the government, based on the latest planning and

manufacturing techniques, that started with land in Orakei (Auckland) and Mirimar

(Wellington). Subdivisions and new houses needed to be planned. By 1936, private

architects throughout New Zealand had designed and drawn nearly 400 sets of plans.

Fletcher Construction became the major contractor meeting the governments’ needs (Metge

1972). Between 1937 and 1942, 5,149 standalone houses were erected in Auckland, of

which 44% were built by Fletchers. Fletchers Construction Company was the largest of 78

building companies involved constructing LPS houses.

THE FINANCIAL STRUCTURE

In 1936, Labour returned the semi-privately owned Mortgage Corporation of New Zealand

that had been established in 1934-35, to become fully Government owned, renaming it State

Advances Corporation (SAC) (Branch, 1940). SAC had two branches, one of which was to

provide funding for rental LPSH, and the other was to finance private housing. Private

lending was more conservative than it was at the beginning of the century, financing the

lesser amount of up to two-thirds of the cost. This was capped at £1250, with an interest rate

of 3% (Oliver).

The function of SAC for LPSH was to purchase land and construct houses. Land purchase,

design and contracts were run by the State who owned the houses and let them to approved

tenants under The Housing Act of 1919. The houses were erected under the Ministry of

Housing department, and upon completion the houses were handed to the State Advance

Corporation who effectively was the landlord. The rentals for State Housing were intended to

generate enough revenue to provide adequate reserves for depreciation, maintenance,

insurance, losses, vacant tenancies, interest and management expenses, with a surplus kept

in reserve.

96

The houses were rented out to moderate income earners. A requirement for eligibility to rent

a State house was that the tenants were to have a stable job and income. It is often

misconceived that these houses were for needy or low-income earners (Weston and Jones

1959). Rental varied depending on the number of bedrooms the house had, with an

additional cost if there was a porch.

The LPSH Conditions of Tenancy had a clause under the Maintenance and Repairs section of

the contract that encouraged tidiness of the property and street appearance. If rents were

paid up to date, there was a concession of two shillings and six pence from the weekly rents if

the tenant maintained the section, the verge between the section and the street kerb, and any

adjacent pedestrian right-of-way. In addition, all gates and fences were to be kept in good

repair. The sum was adequate enough that most houses were well maintained.

THE BRIEF

LPSH were to meet a number of criteria:

Primarily, they were built for rental, not for sale. Contributing reasons the State wanted to

retain ownership was that the Housing Survey had shown that that those most in need were

either unable or unwilling to finance the purchase of the house, and New Zealanders were a

mobile population. New Zealanders occupied several houses in a lifetime. Civil servants of

the State were transferred about the country, so State rental houses simplified the process by

removing the need to sell before moving, and provided accommodation at the destination.

They were to be built of high quality construction that where possible, used New Zealand

produced or manufactured materials to revitalise and build New Zealand resources and to

generate employment opportunity. At the initiation of the LPS housing, potential industries

were consulted for the selection of materials that could be produced in New Zealand that

could be used profitably to create an ‘all New Zealand’ house.

Brick veneer, roof tiles and concrete foundations were preferred as they could be locally

provided, and required little maintenance.

They were to have individual designs with differing elevations when viewed from the street.

97

THE DEPARTMENT OF HOUSING

The Housing Construction Branch (HCB) was established under Walter Nash, with Arthur

Tyndall as its director, R.B. Hammond as town planner, and Gordon Wilson as Chief Architect

(Ferguson 1994). HCB was set up within the SAC in 1936, and was separated to become a

division of the Ministry of Works (MOW) with its own planners, engineers and architects in

1940 (Oliver).

F. Gordon Wilson, then aged 36, had trained as an architect at Auckland University College.

Previously he had worked for Gummer and Ford, architects who had some significant

commissions, amongst them being Auckland’s monumental Railway Station (Alington and

Knight 1966). He had a long-term role as government architect, being responsible for the

architectural organisation and development of LPSH.

Cedric Firth was another architect, employed by the HCB in 1939. He had been an

apprenticed builder and later trained as an architect at Auckland University College. He then

travelled Europe, visiting new housing schemes built through the depression. His knowledge

of social housing contributed to the design of the town planning and social housing of LPSH.

In 1949, Firth published a book ‘State Housing in New Zealand’ which is an informative record

of State Housing.

Other young architects to undertake designs were R.C. Muston, F. Steward and l. Walker.

(Firth 1949) whose early rendered drawings of the proposed LPSH were reminiscent of an

English street.

Figure 5. 3 An image of the English Street aesthetic presentation for LPSH –

published in Building Today, April / June, 1957

(Smith 2009)

98

When material selections for use in LPSH were confirmed, the information was forwarded to

the NZ Institute of Architects, who for a very reasonable cost assisted in preparing the initial

plans. The architectural documentation for construction was done by the HCB. Wilson and

his staff compiled a document titled ‘Designs for Houses: Particulars as to Accommodation,

Design, Construction and Equipment’ to assist with the production of the large number of

houses required (Smith 2009). Standardisation of the design and detailing, and a repetitious

system of documentation was required to be able to advance the mass building programme

speedily and economically.

A Master Specification and Master Schedule of Materials for the materials and construction

were implemented, applicable to all houses. Individual house schedules of materials were

provided specific to each individual house. These documents could be revised for reasons of

economy of floor space or construction, or for further standardisation of units and fittings,

without varying the house design. Also as LPSH were built through an era of advancing

scientific and technological advancement, new materials were being developed. As materials

became available locally, the documents could be extended to accommodate them.

The simplified and standard detailing created the familiarity of LPSH, recognised for its

rectangular box shape, with a regularly pitched tiled roof and its identifiable timber window

configuration.

PLANNING THE COMMUNITY

The goal for the living environment to be created by LPSH was:

“To provide suburban homes for families, a place where children could grow up in

safe and spacious surroundings, away from the dangers of the inner city” (Schrader

2008).

LPSH wanted to create housing of a high standard for every New Zealand family, to provide

homes that they would be proud of, within wholesome suburban communities in which

neighbours would become friends and look out for each other. Living out in the suburbs was

recognised as a healthy way to live, and in LPSH it was important that housing, health and

happiness were connected. “We had a marvellous life for the kids” was a comment made by

a LPSH resident of 1940 (Schrader, 2008) which reflects the Labour Party’s success in this

area.

To meet Labours aim of creating new healthy suburbs away from the slums of the inner city,

large areas of land were bought. Areas close to the city such as Orakei and Mt Roskill in

Auckland, and Mirimar in Wellington were the first LPSH suburbs, and these were

progressively extended to outer suburbs.

99

The new ‘Garden suburb’ urban planning seen overseas in Britain and America had an

influence on the New Zealand planners of LPSH. ‘Garden City’ town planning was founded in

Britain by Ebenezer Howard in 1898. Its philosophy was to create self-contained

communities that could effectively be defined as a ‘cluster’ also recognised as a suburb.

When a set population for that ‘cluster’ was met, another was set up with the ‘clusters’ being

connected to the city by roads and rail.

The “Garden City’ also had an influence in America, where a smaller scale ‘Garden suburb’

was used by town planners Clarence Stein and Henry Wright in the early 1900’s. In response

to the introduction of motor vehicles, ‘a town for the motor age’ was designed where

pedestrian and vehicle pathways were separated, and cul-de-sacs were introduced. Radburn

in New Jersey (USA) is an example of their design that uses the garden suburb philosophy.

A typical subdivision plan for State housing was well planned, using the overseas research to

provide safe, self-sufficient communities that were well connected to outer services by public

transport and roads to the city. LPSH was to relate well to neighbours, industry, transport,

community buildings and park space (Firth 1949).

The typical grid formation of road networks wasn’t adopted in the new subdivisions. Planners

introduced loop-roads and curving streets, which created a more interesting view of the

unfolding streetscape. Roads were stratified into three levels, with separate routes for

pedestrians. Primary roads were the main routes that were utilised for traffic commuting

between suburbs or cities. Existing roads were used for this if they were in existence;

otherwise new roads were built to suit. Secondary roads were used as circulating routes for

localised traffic. The third level of road was cul-de-sacs or recessed courts for destination

users, minimising through traffic on residential streets.

This methodology reduced the traffic to local users and kept those roads safer, minimised

traffic noise and traffic-related grime. It also provided economy, as the roads could be

narrower, and their construction was to suit the capacity of use, i.e. heavier duty road

construction was used for the main roads, and a lighter road construction could be used on

the cul-de-sac roads. Maintenance was more economical due to reduced wear and tear of

the lesser used roads.

Pedestrian’s safety was accommodated. As well the way traffic reduction was managed, the

pedestrian routes provided safety by using walkways that minimised the need for pedestrians

to cross roads.

All subdivisions, even smaller ones of a few acres, had provision of approximately 10 to 15%

of the land area developed to be assigned for recreational use. This land was used to provide

100

public amenities that included reserves, local shops, community centres, schools, sports

grounds and churches that were within walking distance of home. These were vested to local

authorities to control, and the State owned shops were leased out to proprietors. A group of

shops provided for the everyday needs of families, and typically comprised of a green grocer,

butcher, grocer, dairy and often a chemist.

The reserves incorporated existing trees where possible, and provided safe and child-friendly

access to local amenities. In addition to the reserves, right-of-ways were used to make

efficient pedestrian connections to public amenities.

Figure 5.4

Walkway connection through reserves linking streets for pedestrian access.

Figure 5.5

Walkway connection through pathways Photos by the Author

101

A transcript of a news report of 1946 that describes the planning of a LPSH community (used

in Trentham) is as follows:

“Self-contained communities are being built on the outskirts of our cities. This project

at Trentham is designed so that the houses will surround a park in which will be

sports grounds and schools and shops and theatres. Paths will link them altogether –

where the path meets the road there will be an overbridge. When the children go to

school or we go shopping we won't be dodging cars and in our shopping areas we

will find a series of courts free of traffic, planned to group shops and offices and

recreation. Our quiet streets will be close to the city through fast transport systems,

but we will live with space about us and order and room for the sun to get in.”

(Unknown, 1946)

(Source: Archives New Zealand - Housing in New Zealand-(1946)

The following plan is of a community showing the pedestrian and road linkages, reserves,

recreational areas, and amenities:

Figure 5.6 Pureora Village Plan

(Illustration from National Archives, Mangere)

102

Figure 5. 7 A typical plan showing the subdivision layout for about 600 sites.

(Firth 1949)

103

THE STREET

In a street, houses were symmetrically set back from the road grouped around a feature or in

a staggered saw-tooth arrangement to avoid a monotonous streetscape (Firth 1949).

Cul-de-sacs created a full stop to the street, with a fan of houses about them and ‘contained’

neighbours. The street verges were designed to be wide enough to accommodate tree

planting to add to the attractiveness of the development.

The streets were visually impaired by rows of power poles supporting cables that were slung

through the air between them to supply electricity and telephone cables to each house. This

resulted as the consequence of avoiding the expense of underground reticulation.

A few streets escaped this visual blight by either having underground servicing, or that the

over-ground servicing was slung above back yards, still visual, but in a less obvious location.

Decades of age and irregular repair added to the unsightliness of this mode of wired service

provision.

THE SITE - A QUARTER ACRE SECTION

For the first time in New Zealand, the houses were positioned on the site to allow maximum

sun penetration into the living areas of the house (solar design). Space was allowed around

the houses accordingly and trees were removed if they restricted sun to access the house.

Large blocks of land were subdivided to provide a density of four houses per acre,

accommodating a mixture of single housing and combined housing.

The front boundary width of the site was commonly fifty-five feet. The house was positioned

on the site twenty-five to sixty feet from the street boundary, in a staggered formation. On flat

sites they were symmetrically set back from the street. Where the land was hilly, they were

positioned to suit the land contour running along the contour so minimal excavation was

required. Side yards were created between the house and side boundaries of five on one

side, with a greater width of nine feet from the other side boundary to allow for car access to

future garaging which was preferred to be located behind the house.

Private car ownership was not common at the start of LPSH, and for reasons of economy and

building material shortages, garages was not provided for on the site. Occasional communal

garages were built in the earlier period of LPSH. In 1944 it is recorded that only 19% of the

households owned a private vehicle, (Wells 1944) which made community amenities within

walking distance valuable to most families.

The garden and house were to work together harmoniously (Firth 1949). The large section

each house was built on provided plenty of space for gardens and landscaping. Health and

cost benefits of vegetable gardening were encouraged as part of the idealised healthy living

lifestyle. Boundaries of the site were defined by using trees and gardens in preference to

104

fencing, to create a feeling of community garden. Chain mesh fencing was used to create

secluded and safe play areas for children (Firth 1949). Windows and porches that over-

looked another property were avoided, to provide privacy between houses.

A reduced rental cost for maintaining the grounds and gardens to the standards required by

the Housing Inspectors was an effective way to maintain a tidy streetscape (Wells 1944).

THE STATE HOUSE

The design of the typical stand-alone State house was based on the English Cottage,

possibly an adaptation of the English Arts and Crafts concept seen in Architect Binney’s

cottages, or the Californian bungalow. There was also a public preference for the Georgian

style which may have also been influential (Oliver). The houses of the late 1930’s were like

miniature versions of the brick mansions built for the rich. Their design progressively evolved

to become more standardised for economy and speed of construction. Consequently many of

the details seen in the first LPSH were lost to the process of simplification.

The house plan was rectangular, conservative and standardised, easily recognised by its

external aesthetics of tiled roofs of a constant pitch and unique windows divided into

simplified regular pane sizes with timber beading. Their typology of weatherboard or common

brick, with tiled hip roofs dominated the populated areas of the New Zealand landscape for

over two decades. The repetitive pitch or the roofs was criticised for creating a sense of

sameness between houses. The use of New Zealand made concrete roof tiles promoted

local industry and saved overseas funds (Taylor 1986), and Labour accordingly deemed such

criticism an acceptable price to pay (History online, 2010).

Each house had a living room, kitchen, two to four bedrooms, bathroom, laundry and usually

a dining alcove off the kitchen. Typically, a hallway separated the lounge, kitchen and dining

recess from the bedrooms. Two or three bedroom configurations were the most common,

with each bedroom designed to accommodate two single beds (Firth 1949).

By comparison to earlier housing, these modern new houses had many changes. Windows

were larger, and let in more sunlight and ventilation. The era of LPSH followed an outbreak of

Tuberculosis and Diphtheria, and ventilation was recognised as being important for health

reasons. Window areas were sized to be 15% of the floor area of the room it serviced, with

half of the windows being able to be opened for ventilation (Firth 1949).

The living room was larger than in the past and was a warm and well lit social space, with an

open fire that was the main heating source for the house.. Utilities such as the bathroom,

toilet, and often the laundry were brought into the house. Fitted joinery and wardrobes were

incorporated. ‘Modern’ services were introduced into State housing. Electricity was a new,

clean and easy to use service that was used for cooking and water heating.

105

HOUSE SIZE

There was a variety of house plans to accommodate a range of house requirements.

The Standardisation of LPSH produced the following guidelines for house and room areas:

TYPICAL HOUSE SIZES:

Number of bedrooms Area in square feet Aprox. Area in square meters

2 882 82

3 1055 98

TYPICAL ROOM SIZES

Room Area in square feet Aprox. Area in square meters

Lounge minimum 180 16.7

Main Bedroom 120 11.1

Other Bedrooms 100 9.3

Single Bedroom 63 5.8

Kitchen and Meals 143 13.3

Kitchen (single space) 94 8.7

Bathroom 36 3.3

Laundry 40 3.7

The first LPSH displayed English influences in their detailing. The brick arches, colonial

timber window beading and panelled timber doors can be seen in some of the early LPSH in

Orakei. This detailing was discontinued with the process of standardisation.

Figure 5. 8 Brick archway entry to a LPSH in Orakei

Photo by the Author

106

Figure 5. 9 Timber panelled doors of the early English influence in Orakei State Housing

Photo by the Author

107

Figure 5. 10 Early English cottage style LPSH Plan and elevations

Source: NZ National Archives, Wellington

108

The following drawings show differing elevations for the same plan. (Quality limited by the

condition of the document.) The difference is in the roof shape, being a hipped roof or a

gable end roof:

Figure 5. 11 LPSH 6H/1180 - Hip-roof, two-bedroom standalone house

Source: National Archives, Wellington

Figure 5. 12 LPSH 6H/1206 – gable-end roof, two-bedroom standalone house

(Drawing from National Archives, Wellington)

109

5.3 LPSH: SOLAR DESIGN

In LPSH, New Zealand saw its first solar design considerations adopted. They were designed

for sun, light and air as the result of a growing awareness of the health and heating benefits

that could be obtained from sunlight. The previously designed Villa and Bungalow houses

were dark and cold, having been designed with their front to the street regardless of any

connection between the plan and sun orientation. By comparison, LPSH were filled with light

and sun.

Figure 5.13 Sun penetration diagrams based on Cedric Firths sunlight analysis

(The number represents the number of hours the floor has sunlight on it.) (Firth 1949)

110

These houses were designed for maximum sun penetration into the interior in mid winter, with

adequate protection from the summer heat. The sunlight analysis illustrated shows the

amount of sun that enters the room during the day. The penetration of sunlight is controlled

by the eave, which shadows the higher angle of the summer sun from entering the room. In

winter, when the angle of the sun is lower, the sun can penetrate deep into the room. (The

number represents the number of hours the floor has sunlight on it.)

LPSH were orientated to the north to maximise the use of the sun. The plan positioned the

most commonly used Living areas to the north to receive all day sun, with the kitchen

positioned to the east of the house plan to receive the morning sun, and to avoid the evening

heat of the westerly sun. Bedrooms were positioned on the east and west of the house plan

to receive morning or evening sun leaving the utility rooms such as the bathroom and laundry

to be positioned along the cold south wall.

Solar sensitivity is demonstrated by the allocations of glazing, being 15% of the floor area.

Larger windows were positioned on the north wall, with smaller windows on the east and

west. Windows with minimal areas of glazing serviced the utility rooms on the south wall.

The lesser amount of window area on the south wall reduced the amount of cold glass, and

cold southerly draughts.

111

5.4 THE CONSTRUCTION OF LABOUR PARTY STATE HOUSING

Figure 5.14 Building LPSH

Source: NZ Archives

5.4.1 LABOUR

LPSH were built to a high standard by artisans, using quality materials for an intended life of

60 years, double the expectation for houses at the time. Thousands of LPSH were built by

private building contractors under contract to the Housing Division. These houses were built

under 669 contracts, which were awarded in groups of between one and twenty houses, to

economise and speed up the construction process. Auckland had seventy-eight different

contractors (Squires, 2010), one of which was Fletcher Construction who built 44% of the

5,149 standalone houses in Auckland during the period from 1937 – 42.

Not long after LPSH started there was shortage of builders. The building trade

apprenticeships that trained boys and youth had dwindled through the depression, to leave an

estimated shortage of 500 craftsmen by the time the war started, which the war further

reduced. To meet the demand of the huge increase in building, Labour repealed the previous

restrictions that had limited the growth of apprenticeships and imported building related

workers from Australia and England.

112

Following the war, the gross shortage of labour was addressed by the introduction of a new

training scheme for mature men returning from war, which differed from apprentice training.

Returning ex-servicemen were offered rehabilitation training in carpentry, joinery, painting,

plastering and bricklaying, which was established by the Rehabilitation Department. The

training period was up to two years, most of which was spent building LPSH, with much of the

labour cost being met by the Rehabilitation Department, which effectively reduced the labour

costs of building. By 1948 about 2,670 men were trained per year and the result was that

30% of the trained men were building houses on-site, while the others were engaged in

building related industry and manufacture (Firth 1949). Reducing numbers caused the

eventual closure of the training centres in 1953.

5.4.2 THE IMPACT OF WORLD WAR 2

War prioritisation absorbed enormous amounts of timber, metal and labour. Steel, copper,

zinc, electric cable and conduit and some paint ingredients imported from overseas were

committed to the requirements of war and consequently become unavailable for building use

in New Zealand. The effect of lacking materials meant houses could not be completed. In

1941 LPSH construction ground to a halt and houses under construction were boarded up

until the end of the war when the housing needs of returning soldiers reactivated construction.

Auckland’s population grew with the migration of factory workers supporting the war, and

wives moving to be nearer their husbands who were based in the city. In addition, soldiers

returning from war coincided with an influx of Maori post-war urbanisation. This placed

demand on all housing, particularly State housing, which was expected by and required for

the returning servicemen. The resultant shortage of housing increased rents and initiated a

building boom that started in 1941. As there was a shortage of artisans due to the war, there

was work beyond what the available building labour could meet. Consequently, building

contractors inflated their prices, and continued to do so for government work as the building

market and confidence improved.

The restart of State house building after the war was slower than needed due to a lack of

skilled labour and diminished material supplies drained by the war. The amount of timber

consumed by the requirements of war equated to 20,450 houses, which closely matched the

number of houses needed at the end of the war. By 1944 there were over 30,000 applicants

waiting for a LPSH, many of whom were already well accommodated, but sought the cheaper

rental. The low rents charged for new and quality housing made LPSH very attractive by

comparison to private rental. By 1947, there were 52,759 names of which 15,278 were ex-

servicemen, on the waiting list for a LPSH. This created a problem for the Labour

government.

113

5.4.3 PREFABRICATION

Pre-fabrication had been used for farm buildings and in the war to erect buildings for the army

and airforce. Prefabrication was beneficial as productivity could be increased by using less

skilled labour, and in conditions that were unaffected by weather. To assist with the housing

shortage and to speed up the construction process, pre-fabricated timber framed wall panels

were introduced for use on-site. Also, to meet the post-war housing shortage, the

Department of Housing designed a smaller and cheaper timber framed house that, that could

be built using pre-fabrication at a cost of ₤800 (Taylor 1986). The first pre-fabricated example

was built in Mt Albert (Auckland) in 1944, and pre-fabricated, portable housing started

production in 1946.

5.4.4 CONSTRUCTION MATERIALS OF LABOUR PARTY STATE HOUSING

LOCAL MATERIALS

The standalone LPSH were built on-site, using native timber framed floors, wall and roofs,

with various claddings. Most commonly used was rimu bevel-back weatherboard, finished

with oil paint to protect the timber from the weather. Prefabrication was later developed and

introduced into LPSH. Doors, windows, timber, sheet materials and detailing throughout were

standardised, and used New Zealand products such as timber, clay and cement roof tiles,

and fibrous plaster ceilings and plasterboard wall linings. New Zealand made gas and electric

stoves, electric lights and light shades were also used. Many New Zealand manufacturing

companies were established and expanded by LPSH.

At times when material shortages were encountered, government did need to import some

materials, such as timber, fibrous plaster and roof tiles to continue the building programme.

TIMBER:

LPSH preferred to use native timbers for quality and durability. Timbers used were to be

graded according to The Dominion Federated Association standard grading rules

(Department of Housing Construction Pre 1941), and only those timbers listed on the NZSI

grading rules were allowed to be used (Timber Association, 1951).

Rimu was the most common timber for framing and weatherboards, using 188,500,000 lineal

feet of board in 1938. From the late 1930’s, supplies of quality durable native timber became

more scarce and expensive. The war's impact on timber supply was significant from the need

for war related buildings to the demand for war related shipping crates that were typically built

out of Radiata Pine. The great demand for these crates exhausted the available Radiata

114

Pine, so the Rimu and Matai used for housing became its substitute. As access to native

forests became more remote and difficult due to the heavy demand for supply, alternatives

needed to be found. This introduced a variety of native timbers such as Tawa (which was kiln

dried, treated with pentachlorophenol (PCP) and used for interior fitments); Beech, Totara and

later Radiata Pine. Kiln dried and treated (PCP) Radiata pine had grown in use in New

Zealand construction from 1938, as it was a cheaper and more available source of timber. It

became the most readily available timber by 1947, but it wasn’t introduced into LPSH until

1946. Untreated Radiata pine was allowed to be used for internal walls, ceiling joists, nogs

and trimmers, but it was not allowed for use in the external framing walls, or for roof framing

(Department of Housing 1947). From 1951, the use of pine was extended. Both treated and

untreated pine were able be used, but only above the floor level and not for the bottom plates.

Untreated pine was not to be used adjacent to brick veneer walls, exterior banks or other

damp positions. Where asbestos cement sheet cladding was used, it was to be installed over

‘Malthoid’, a bitumen impregnated felt damp-proofing membrane. As roof spaces were

deemed to be dry and well ventilated, untreated pine was approved for use there, but the

battens directly supporting the roofing were to be treated (Timber Association, 1951). To

accommodate the recognised softness of pine, nails were required to be 25% longer than

used for native timbers, or coated or to have a mechanism to provided additional grip.

The quantities of timbers (board length measured in lineal feet) that were used on LPSH in its

intense building period of 1945 -46 are represented as follows:

Rimu: 175,000,000 (a decrease from 1938)

Matai: 19,000,000

Beech: 12,000,000

Totara: 11,000,000

Tawa: 5,327,046

(Taylor 1986)

0

20,000,000

40,000,000

60,000,000

80,000,000

100,000,000

120,000,000

140,000,000

160,000,000

180,000,000

lineal foot of board used for

LPSH

Rimu

Matai

Beech

Totara

Tawa

Figure 5. 15 Footage of native timbers used in LPSH

115

Of New Zealand’s native timbers, Rimu and Matai are classified as being native softwoods

and Tawa and the southern Beeches (red, hard, silver, mountain) are commercial hardwoods

(Hedley 2010).

TIMBER PRESERVATION

In the late thirties, SAC became concerned about the amount of borer-susceptible sapwood of

native timbers and Radiata Pine being used for building use. As SAC was the principal

financier and owner of LPSH and mortgagor for privately owned properties, it wanted to

ensure the houses were adequately protected. This led to the Timber Protection Research

Committee being established in 1938 by the Department of Industrial and Scientific Research

(DSIR) for the purpose of testing and approving wood preservatives. A simple dip treatment

based on dilute zinc naphthenate was developed to become the only insecticide treatment for

building timber that was approved by SAC. It is understood that its effectiveness was not

known at the time. After the war, further timber treatment was developed to become known as

Tanalith® U, a fluor-chrome-arsenate-phenol formulation which SAC accepted to become its

only approved preservative treatment (Hedley 1996).

Borates were developed to protect timber against insect borer attack. The DSIR tested and

confirmed that a dip/diffusion treatment effectively protected native timber and Radiata pine

from borer attack. They were approved for use in New Zealand in the mid-1950s. Typically

the green diffusion process was used in which newly sawn timber was immersed momentarily

in strong solutions of boric acid/borax and was then stored under tarpaulins for six to eight

weeks to allow the preservative to diffuse deeply into the timber. As well as protecting timber

from insect attack, boron-based preservatives also work as a fungicide (Hedley 1996).

5.4.5 THE STRUCTURE AND EXTERIOR MATERIALS

LPSH were framed using native timbers, most commonly Rimu. Prior to the introduction of

Radiata pine, all of the framing above floor level was BA Rimu or medium Kauri. The timber

used for the framing below floor level was dressing A rimu (Timber Association, 1951).

Typical framing was rough sawn 4” x 2” (102mm x 51mm), with larger sized framing used as

necessary for the suspended timber floor and subfloor. Hip and gable-end roofs were built

using 4” x 2” (102mm x 51mm) rafters and ceiling joists. Diagonal struts transferred the

heavy roof load of the tiles back to an internal load-bearing wall. Ceiling runners and

underpurlins spread loads to minimise the spans, and consequent size of the timber framing

member required. External timber was dressed A-grade heart Rimu, Matai or Totara. (Timber

Association, 1951).

Foundations were comprised of poured concrete (insitu) foundation walls at the house

corners, with pre-cast concrete piles for the mid-floor area. Horizontal timber boards ran

116

between the foundation walls, which were adequately spaced to provide ventilation to the

subfloor. Where the house was built of brick veneer, the brick would be supported on a

continuous concrete footing with ventilation grilles installed in the brick wall, subfloor. A crawl

space of ideally 3’ (910mm) was provided between the ground and the floor framing. The

chimney foundation, flue and hearth were formed of insitu concrete.

Building paper was not always used. The New Zealand building code of 1949 (Clause 945b)

had a requirement for building paper or other approved weatherproof material to be fixed to

the outer face of timber framed exterior walls of buildings for human inhabitation. From then,

building paper was introduced into most LPSH, although not always in the upper North Island,

as the DBH didn’t specify it’s use, deeming it unnecessary because of the higher

temperatures in that area (Hammond 1949). The many houses built without building paper

relied on construction detail, roof and cladding materials and enamel paint to deter water

ingress. Insulation was not used, although there was an awareness of its benefits.

Roofs were constructed using timber framing and later, timber trusses. The roofs were

battened and covered with clay or concrete tiles in the 1930’s and Marseille style concrete

tiles in the 1940’s and 50’s. The roof was pitched at 32° to support the tiles, and to provide

water run-off.

Corrugated asbestos cement sheet and 24 gauge corrugated iron were lesser used roof

coverings and from the 1950’s a new Malthoid product was used for flat roofs (Cheer, 2010).

By 1951, pitches of the roofs lowered for timber economy, which raised the concern of a

waterproofing risk for some Councils (Clist, 1951).

Soffits were timber lined initially, but later this was replaced by the more economical asbestos

cement sheet when it became available.

Claddings were varied, with over half of the houses receiving timber bevel-back weather

board, which was economical. As native timber used for weatherboarding became in short

supply, the manufacture of a new product - asbestos cement sheet or tiles - provided an

economical option.that along with concrete, eventually replaced weatherboard in almost

three-quarters of the houses built in 1946-7. Brick was also used, favoured for its longevity,

performance and low maintenance, Rendered pumice was another occasionally used

cladding.

The timber window joinery was constructed using standard details, out of native timbers,

being heart Rimu, Matai or Totara. Windows were of a standard height, with the window head

positioned beneath the soffit. Craftsmanship and detail provided good waterproofing,

although technology for airtightness was not available.

117

The desire to recreate the English Cottage, by use of leadlight glazing bars as seen in the

windows of the Arts and Crafts style proved too expensive, and the constraints of using

timber meant the complexity of similar window glazing detailing be simplified. The solution

adopted was a very simplified use of timber glazing bars. Horizontal timber glazing bars of

the same elevation heights divided the sashes into three panes of glass. Casement windows

were used, being either fixed, side-hung or top-hung for ventilation. Top-hung fan lights

provided a more secure form of ventilation as it was accessed at a higher level. Side-hung

sash sizes were standardised as being four feet, six inches high (1.37m) by two feet wide

(610mm) or three feet high (990mm) x two feet (610mm) wide (Firth 1949).

Windows were detailed with anti-capillary weather-grooves around the edges of the sashes,

and the frames they sat within to prevent the ingress of external rain. These gaps were often

increased with timber shrinkage.

Exterior doors were made of Heart Totara, Matai or Kauri, and were protected from wind and

rain by outdoor porches.

5.4.6 THE INTERIOR MATERIALS

Room ceiling heights (stud heights) were nine feet high (2.74m) until 1943, when they were

reduced to eight feet high (2.44m) to economise on materials.

The floors throughout the house were made of four inch by one inch (102mm x 25mm) tongue

and groove, heart native timber boards laid directly over, and perpendicular to the timber floor

framing. They were usually Rimu or Matai, finished with a coating of a mixture of linseed oil

and turpentine (the turpentine aided absorption). Floors closer than four feet (1.2m) to the

ground in the North Island were to be Dressing A heart Rimu, or Dressing A heart Matai,

pressure treated, kiln dried and dipped (Clist 1951; Rogers 1951; Timber Association 1951).

The living area, halls and bedrooms were lined with plasterboard that had wallpaper applied

as a finish. Walls to the utility areas were lined with hardboard, with half-round timber beads

applied over the sheet joins. Utility rooms were finished with enamel paint. Ceilings were

lined with either Pinex softboard with battens over the sheet joins, or fibrous plaster. Sheet

linings were fixed to the timber framing with tolerance gaps of approximately a quarter of an

inch (6mm) at the top and bottom of the sheets. These gaps were covered by a ventilating

cornice or native timber shirting boards. One inch (25mm) quarter-round moulds or one and a

half inch (32mm) scotia moulds were used where required.

Internal doors were panelled native timber in the first LPSH’s, but for economical reasons

they became a flush finish, dressed A-grade heart Rimu or Kauri veneer. All interior finishing

timber was Dressing A Rimu.

118

5.4.7 SERVICES

Hot water was stored in thirty gallon (113.5 litres) cylinders that were electrically heated.

They were low-pressured systems that were fed via a header watertank in the ceiling space.

Quality copper piping was used in preference to standard metal for the plumbing throughout

the house.

Each room was electrically lit with a centrally placed, ceiling-mounted lamp-holder light fitting

using 60 watt or 100 watt incandescent light bulbs (Department of Housing Construction).

Electric power outlets were scheduled frugally to provide two outlets in the lounge and one in

each of the main bedroom, kitchen, dining recess, laundry and kitchen (Department of

Housing Construction). Often the lounge had a radio aerial outlet. The electrical wiring was

fed through metal conduits.

Although the houses were better designed for solar heat gain, there was less heating

provided in LPSH than previous housing, with only one open fire located in the living room.

The open fire was later revised to be replaced by the use of fire-boxes.

5.5 THE END OF LABOUR PARTY STATE HOUSING

There is little doubt that the LPSH of the 1930’s and 1940’s raised the standard of housing in

New Zealand. Unfortunately following the war price increases raised the costs of the two

greatest commodities of LPSH building - timber and labour. The ‘yard’ cost (excluding

cartage to sites) of timber increased by 13.52% between 1945 and 1946, and increased a

further 20.52% by 1949 which had a significant impact. By 1949, the demand for State

housing grew to require the production of 12,000 houses annually (Firth 1949), which the

Labour Party struggled to cope with leaving a lot of people frustrated and disappointed with

Labours’ lack of performance.

Problems that developed at the end of the 1940’s with the LPSH programme, and its

economic losses, led to the demise of Labour. The National party, with a new and more

credible leader, Sid Holland, attacked the Labour Party, pointing to its failings. National

promised to provide a new era of freedom and prosperity, while retaining Labours social

welfare policies. This turned opinions enough for National to be voted into government in the

1949 elections, which saw the end of the immense era of LPSH. During their fourteen year

period of leadership, the Labour Party had constructed 61,000 houses.

5.5.1 STATE HOUSING AND THE NATIONAL PARTY

The National Party had no intention of continuing the rate of building of State housing, or to

continue the LPSH building policy (Minister of Industries and Commerce 1953). National

modified the direction and structure of State housing by initiating privatisation to allow tenants

119

to buy their State house. Generous lending terms offered 95% of the purchase price, at 3%

interest over a period of up to forty years. There was a high number of sales when the option

was first introduced in 1950, which settled through the mid 1950’s, and declined when Labour

was re-elected in 1957. Sales increased once again with the re-election of National in 1960.

National introduced capitalisation of the family benefit (a government subsidy paid to families

per child under the age of sixteen), which was used as a vehicle to provide families with their

own first home, either private or State built. It provided funding to the value of ₤1,000 for use

as a deposit, with the balance mortgaged at 3% interest. Funding was provided by SAC.

From 1939 through to 1952, the cost of timber for a standard three bedroom house had

increased by over a hundred percent. International demand on metals such as copper, brass,

steel, tin and lead used for house building had increased costs. Using lead (used for

flashings) as an example, costs increased from ₤55 per ton in 1945 to ₤232 per ton by 1953.

In the 1950s, the demand for State housing grew, but the capability of the government to build

at a rate to meet demand couldn’t be achieved. The escalating building costs experienced in

the 1950’s eventually lowered the standard of housing.

Figure 5.16 Document requesting revised design proposals to reduce costs for State Housing

(Wilson 1953)

The repetitively designed, poor quality and underserviced rows of housing built to provide for

the poor, created ghetto communities which was the opposite of the Labour Party philosophy

for LPSH. Since the 1960s State housing has targeted the poor, and those who face

discrimination in the private rental market, including Maori, Pacific Islanders and solo mothers

(Schrader).

120

5.5.2 GROUP BUILDING SCHEME

Group housing was a privatised extension of the State house model. It was introduced by

National to accelerate house building to meet the housing demand, but with reduced

government expenditure or ownership. Crown land that Labour had previously purchased for

LPSH was made available to substantially established builders for development under

contract with the Housing Construction Division of the Ministry of Works. Government still

had some control, as there were requirements of SAC and Rehabilitation lending that needed

to be met. The expenditure involved in the land subdivision, site and house plans,

specifications and buy-back costs were to be approved by SAC in writing. The houses were

to be sold at prices reflecting ‘fair value’, with a maximum price for a 3-bedroom house in

metropolitan Auckland or Wellington being ₤2,900, (reduced in lower cost areas). Sections

were not to cost more than ₤750.

Private builders funded and constructed groups of houses, with the security of a government

guaranteed buy-back of any houses unsold within two months of completion. This ensured

the continuity of building without the financial burden of holding costs, allowing the builder to

meet his costs of staff, sub-contractors’ and materials. It also provided houses for the New

Zealanders in need.

LPSH helped establish many Group housing construction companies in New Zealand, some

of which are still in existence today. The house picture below has used the same design and

construction methodology of LPSH. It was built in 1965, and is built using the same materials:

concrete tiled 32° pitch roof, weatherboard, brick base, native timber framing and no building

paper.

Figure 5.17 An example of a Group house following LPSH methodology

Photo by the Author

121

5.5.3 A REFLECTION ON LABOUR PARTY HOUSING

The following quote from a Thesis written in 1944, almost halfway through the Labour House

scheme, portrays the high regard in which State Housing was held:

“‘In any case, the faults of the scheme are insignificant when compared with the

comfort and happiness that it has bestowed on thousands of people. Let the

doubters and detractors inspect the closely packed tumble-down shacks of a slum

area where rusting iron roofs , leaking spouting, rotting wooden fences and piles of

rubbish form a fitting background to the sordid drama that such conditions inevitably

produce.

Let them then by way of contrast walk along a street made up entirely of state

Houses where closely cut lawns, neat frontages, trim pathways and modern buildings

create an environment that can not help improving the lives of the people morally and

spiritually, as well as materially.” (Wells 1944)

122

CHAPTER 6: THE FUTURE OF LABOUR PARTY STATE HOUSING

6.1 ARCHITECT INTERVIEWS

6.1.1 THE SELECTION OF ARCHITECTS

Practicing architects that met the criteria of having designed alterations to existing State

housing were sought to be interviewed on their experience and solutions that were

implemented. Those that responded were interviewed either by telephone if they were

located outside of Auckland, (or was more convenient for them), or in person. When

interviews were undertaken in the offices of local architects, some files on various projects

were made available for viewing. Otherwise graphic material was provided form architects by

email or post.

A questionnaire for the purpose of interviewing was developed to obtain information about the

practice and the overall experience with retrofitting. Information was gathered on each house

as it was prior to the renovation works, such as its location and the age of the house/s were

obtained to establish that they were of the typology studied in this thesis. An understanding

of the driver for the renovation was sought to understand what priorities were placed on the

various requirements that contributed to the brief. Health issues of the occupants were

checked, and if present, their influence on requirements was identified. Information was

obtained on the existing structure, construction and materials, to determine whether the

original composition was matched, or were alternatives introduced e.g. thermal mass or

increased solar gain.

Ownership was verified to understand different approaches that may occur between privately

owned, rented, or State owned housing. Information was sought on the priorities of retrofit

requirements such as the levels of thermal comfort, insulation, ventilation, air tightness,

moisture and thermal gain. During construction with the house structure exposed, contingent

problems with the condition of the structure such as rotting timber, unstable structure,

moulds, water ingress and other unknown problems could be identified. Such problems

impact on the budget, and information is sought to assess how realistic and affordable these

houses are to work on.

Where post-construction monitoring was available, this would enable an evaluation of the

building performance to assess if an adequate level of IAQ had been achieved. In conclusion

it was asked if the architect was satisfied with the outcome and, where it was possible to

know what the occupant’s comments were, to reflect the success of the interventions. The

questionnaire is available in the appendix to this document.

123

Figure 6. 1 Healthy Housing Programme sketch proposal

Image courtesy of Marshall Cook

The sketch above shows the existing house on the left and a new addition to the right with

indoor to out door connection and new decking for outdoor living.

Figure 6. 2 Map of State housing in central Auckland

Source: HNZC

124

6.1.2 THE INTERVIEWS

The interviews presented that typically the condition of the State housing worked upon was of

a similar condition, with a couple having had some prior improvements made. Overcrowding

and excessive moisture in the indoor air had contributed to ill health, and this needed

rectification.

HNZC established written generic briefs outlining the minimum requirements for the various

types of housing to be upgraded, which were issued to the involved architects. A number of

items in the brief are the same as they were when the houses were built, although many

improvements were made. Improvements to the brief for a stand alone house that address

IAQ better addressed ventilation by installing passive vents into the new and existing exterior

joinery. The living area, where possible was to be cross-ventilated by providing windows into

two external walls. Bedrooms were to have adequate natural light and ventilation. The

kitchen and bathroom was to have ‘adequate’ passive or mechanical ventilation, with the

bathroom preferably having an external window.

Exterior joinery was to have condensation channels and was to be ‘robust’, without reference

to specification of the materials to be used.

Items that addressed heating was that an adequate, fixed heat source was to be installed in

the living space; window coverings were to be provided in the lounge, dining bedrooms and

kitchen areas and it was preferable that an airlock be designed into the plan where the house

was located in cold or exposed situations.

There was nothing specific to insulation other than compliance with the New Zealand Building

Code, and the HNZC Housing Specification. The extent of the latter document relative to

insulation is as follows:

“MATERIALS

THERMAL BLANKET – WOOL FIBRE: Long fine wool fibres bonded with a polymer

fibre to form a 600mm blanket.”

INSTALLATION – Install as per manufacturers’ instructions.”

(HNZC, 2004-2005)

125

INTERVIEWS ON GOVERNMENT OWNED STATE HOUSING

ARCHITECT 01

The first architect interviewed is Auckland architect who directed the establishment of the

Healthy Housing Programme (HHP) to modernise and upgrade State homes, and was one of

the two architects that ‘mentored’ the many architectural practices that were involved in the

scheme. His practice upgraded a large number of houses in Auckland between 2001 and

2005. The budget given per house, within a range of $40,000 and $140,000, was tight for all

that was required to be achieved. Where an investment beyond $150,000 was needed, this

was committed to rebuilding for reasons of economy.

EXISTING CONDITION

Many of the large families that were crammed into smaller houses than was suitable were

from the more affectionate cultures where human contact, particularly cuddling and nursing

babies is common. This exacerbated the spread of Meningococcal disease. In overcrowded

situations it was not uncommon for bedrooms to have four teenagers sharing one bedroom in

an observed situation. An unsanitary situation that arose from too many people sharing

minimal facilities was recognised in absence of hand washing facilities in the toilet rooms.

Basins were located in a separate bathroom, often occupied by other family members.

Massive amounts of cooking were done by boiling, which produced copious amounts of

steam.

INTERVENTIONS

Interventions undertaken were to increase the size of the houses by enlarging living areas,

adding bedrooms and improving the connection between indoors and outdoors by adding

decks. Bathrooms were added, and basins put into the existing toilet rooms. Kitchens and

existing bathrooms were upgraded to include mechanical extract fans, with permanent

passive vents in the glazing. If windows were in need of refurbishment, they were replaced

with single glazed timber joinery. Otherwise they remained as they were, passively ventilating.

Insulation was fitted into the ceilings and beneath the floor throughout, but due to cost

limitations, the walls were only insulated if there was renovation work that involved relining

them. Typically the existing walls remained uninsulated, and the timber windows with single

glazing were left without seals. Adjustable passive vents were fitted into most windows, and

permanent passive vents were fitted into the windows of the kitchens and bathrooms. The air

leakage was seen to provide balanced pressure between the house interior and exterior.

Electric panel heaters were installed for heating.

POST EVALUATION

A post evaluation showed that the windows were not always opened, and boiling food was

still supplying the air with copious amounts of steam, often as the extract was not activated.

126

However the programme had managed to create a feeling of worth, and connection within the

community.

ARCHITECT 02

The second Auckland architect interviewed was engaged within the HHP to work on

individually targeted houses and the larger ‘Star’ flats. His company upgraded eighteen triple

units, fifteen blocks of twelve units ‘Star’ flats, an atrium block of 36 units and twenty

standalone houses, in Onehunga, Mangere and Otara, in the southern area of Auckland. His

philosophy was to meet the expectation of a clean dry house to live in, without middle class

aspirations that added unnecessary expense.

EXISTING CONDITION

State housing did not have good building performance, and tenants were not happy. The way

many occupants lived varied with differing cultures, which affected sleeping patterns and

cooking. Cooking was done by boiling in large pots, which produced huge quantities of steam

and created problems as the windows were not opened for ventilation due to security issues.

(At the time of this programme, there had been a number of rapes in south Auckland.)

INTERVENTIONS

Interventions used to improve the housing were to add pods to the existing houses, which

were designed to improve the connection between indoor and outdoor living. New aluminium

sliding doors were used to facilitate the connection. Insulation was used in the floors, walls

and ceilings throughout the new areas, but only the floors and ceilings in the existing parts of

the house. Polyester ‘Greenstuf’ insulation was used in the walls and ceilings. Drawings were

provided of retrofitted solutions to insulate the existing walls by installing polyester insulation

pads, with either new grooved plywood, or prefinished ‘Climateline’. ‘Climateline’ is a

propriety product that is a plasterboard sheet lining product which is prefinished with a

powder-coated surface that is finished with jointers therefore eliminating the need for plaster,

sanding dust and paint that standard plasterboard requires. Although detailed in the drawn

documentation, these details were not implemented by HNZC. The original walls were left

uninsulated.

Hard wired smoke alarms were required to comply with NZBC.

Mechanical fan extracts were used in the kitchen and bathroom/s, and permanent passive

vents were installed into the glazing at the top of the bedroom windows. Air tightness was not

considered. Although there was some water damage from failed plumbing, the timber used

was in good condition. Clothes' drying typically was not done outdoors due to theft.

This architect felt that durability and sustainability was challenged by the HNZC brief as the

solid timber kitchen joinery (which had often endured fifty years of use) required melamine

replacements which by comparison, had a life of approximately ten years. The formaldehyde

127

and VOC’s emitted from such product would add to the contaminants in the air. This architect

was not in favour of this decision, as part of the character architectural heritage of these

building was being discarded for a lesser replacement. He also commented unfavourably at

the use of formaldehyde glues, when low emission VOC adhesives were available.

Operation manuals were supplied to HNZC at practical completion, although these weren’t

passed on to the tenants. HNZC had people to assist tenants but some basic things like the

operation of passive ventilation devices in windows were not explained.

POST EVALUATION

Post evaluation it was found that a lack of knowledge as to how the vent worked meant the

passive vents were not used. The programme was effective as the tenants who had

previously spoken negatively about their housing, had raised self esteem post renovation

which impacted in that the properties were cared for and image became important.

He commented that the HHP ended for architects as they were deemed to add expense

beyond what could be achieved using a design and build methodology.

ARCHITECT 03

The third Auckland architect interviewed had worked on the HHP in 2003, and privately

owned State housing. HHP houses he worked on were built during the 1960’s.

EXISTING CONDITION

His experience confirmed the overcrowding, having worked on three bedroom housing that

accommodated 8 -10 people.

INTERVENTIONS

The houses he worked on were completely renovated with additional space added. Ceilings,

walls and floors were insulated in the additional built spaces, and to the ceilings and floors of

the existing house. Existing walls were insulated of they were affected by the additions.

Bathrooms and kitchens were refitted with new fixtures, joinery, wall linings and mechanical

extraction fans. Heated towel rails were fitted to the bathrooms to dry towels.

Typically, tenants did not open windows, so permanent passive vents were installed in the

existing window glazing to ensure the house was ventilated without relying on windows being

opened.

ARCHITECT 04

The fourth Auckland architect interviewed had worked on contract to a larger company to

upgrade twenty-six houses in 2005 under the HHP. These were 1950’s State housing located

in Bayswater on Auckland's North Shore.

128

EXISTING CONDITION

The condition of many of these houses was adequate, with some of them having had very

long term tenants. Overcrowding was not such problem in this area. Some mechanical

extract fans had been installed in a previous upgrade, and many houses had existing floor

and ceiling insulation, and yet the ceiling linings were mouldy.

INTERVENTIONS

Emphasis for the upgrade was to open up the living and kitchen areas (open plan) with

connection to the back yards and new decks. He commented that the decks were over

designed, being for a floor load of 3KPa when 2Kpa was required under the building code of

the time. This involved additional and wasted expenditure that could have been dedicated

elsewhere. Kitchens and bathrooms were upgraded with new bathroom linings, fittings and

joinery. The bathroom walls were lined with ‘Aqualine’ (a water resistant plasterboard sheet

lining), with ‘Hardiglaze’ (a water resistant, prefinished, polyurethane-coated fibrous cement

sheet) fixed over plasterboard to replace the ceiling linings. Some houses already had

mechanical extractor fans, but those that didn’t had new ones installed to the bathroom and

kitchens. Passive vents (‘Easy air’) were installed into new and existing windows, with the

adjustable slides removed for permanent ventilation to the laundry and bathroom. Hot water

cylinders were replaced. The new additions had aluminium window joinery installed. If walls

were affected by the renovation works, they were fitted with R1.8 insulation (polyester or wool

being specified) before relining. The subfloors of the new extensions were insulated with

double-sided perforated foil draped 100mm between the floor joists. R2.2 insulation (polyester

or wool being specified) was fitted to the new ceilings in the bathrooms, toilet and other

selected areas designated on individual plans.

Open fires had been closed off, and the houses had no fixed source of heating.

INTERVIEWS ON PRIVATELY OWNED LPSH

ARCHITECT 05

The fifth Auckland architect interviewed worked on privately owned State housing and HHP.

Privately owned houses he has designed renovations for are typically in Onehunga and the

affluent eastern suburbs of Auckland. His clients include young families and professional

young couples who can manage to afford a simple State house, and work towards improving

them by updating the layout and fixtures.

INTERVENTIONS

Renovation has involved adding an upper storey, extensions, opening up the plan and

improving indoor-outdoor connections with provision for decks for outdoor living.

One of his projects included interventions that were client driven as the owner had specific

requirements having an asthmatic child. Their house was brick veneer. They specifically

129

requested that a polythene membrane be applied across the natural ground beneath the

house, that the ceilings and floor be insulated, and that they had a good heat source, being

an efficient solid burner inserted into the existing fireplace. There was also to be a heat

transfer system from the heated living area to transfer heat to the bedrooms. The windows

remained as existing, so the R-value of ceiling insulation was substantially increased.

POST EVALUATION

The polythene membrane was noted for making quite a difference, and it was considered this

was possibly due to the subfloor of a State brick house not being as well-ventilated as that of

a weatherboard State house. Although the outcome was not monitored, the client was

satisfied.

In his experience with State housing, other than this client, he has never had a request for

polythene on the ground, heat transfer systems, double glazing or sealing around windows.

He has specified single pane low-e glazing in a recent renovation.

ARCHITECT 06

The sixth Auckland architect interviewed lives and works from his State house. He has

worked on many State houses in the more affluent areas of Auckland - St Heliers, Parnell,

Remuera as well as Sandringham and his own neighbourhood of Orakei. His neighbour has

been a government owned State house tenant in the same house for over 30 years.

EXISTING CONDITION

His experience of State housing is that they are well built solid houses that breathe and

benefit by having large suburban sites. In some of the affluent areas, the houses are often

demolished, or transported away for relocation, and replaced with large modern housing.

He has never encountered any mould within the structure, although he has found an

occasional bit of borer.

INTERVENTION

Renovation work he has undertaken typically involves improving the indoor outdoor

connections, with the addition of decks for outdoor living. Old kitchens, bathrooms and

laundries are stripped out and replaced to suit twenty-first century living. Living areas are

increased in size, and in his own home he added an upper storey with a preference to visually

match materials. The renovations to his home started twenty years ago. The new areas have

been insulated with polystyrene beneath the floor, and R2.2 fibreglass to the ceiling and walls.

Windows remained as is, and new windows and French doors were single glazed timber

joinery.

130

He designed a renovation for a client who owns one of the early LPSH in Orakei. The house

has the same footprint, but the fireplace has been removed which enabled the living areas to

be opened up. This client’s brief was that she liked the house cold, so although he did install

an electric heat pump, it may not be used. He relied on increasing the insulation levels

beyond the legal requirement of the time. R3.2 ceiling insulation was used and R1.3

polystyrene was inserted between the floor joists. The external walls were not altered and

were not insulated. The house relies on natural passive ventilation, by opening windows.

Mechanical extract fans were installed in the kitchen and bathroom. He was not a fan of heat

recovery systems, as if the house was designed properly they were not needed, although he

had used heat transfer systems to move heat from living areas to bedrooms.

The renovation of this house recognised the charm and fenestration of its style which

reflected the English cottage influence of the very early LPSH, which could also be seen

internally in the panelled doors, hardware, high skirting’s and a higher stud height.

POST EVALUATION

The architect was satisfied with the outcome and the owner was very happy with her home,

and its performance.

ARCHITECT 07

The seventh Auckland architect interviewed has worked with his father, and in over twenty-

four years of architectural practice has worked on at least one State house renovation a year,

in locations all over Auckland. These houses have all been privately owned.

INTERVENTIONS

Renovations undertaken have involved a range of alteration work to include opening up the

existing plan, adding rooms or extending living space, an upper storey, garaging, new

kitchens, laundries and bathrooms.

Health was never an issue discussed; the alterations were singularly for space requirement.

Old is kept as old and new is insulated according to the current building code. Ceilings and

floors may be insulated, and walls are only if they are opened up as part of the renovation. If

the renovation is separate from the existing external walls, they are left uninsulated.

POST EVALUATION

He has found the houses to be well built, with no contingent items and has happy clients at

the end of the project.

ARCHITECT 08

The eighth Architect interviewed lives in Wellington. He has completed a number of houses

over a forty year period, for a variety of clients that include a Judge, Head of Treasury, and

other high level earners. The value of the soundness of State housing outdoes any stigma

131

that may be attached to them. The houses he has worked on are located in various socio-

economic areas, from the high value suburbs with views in the northern and eastern suburbs

of Wellington such as Wilton, to the lower valued suburbs of Wainuiamata, NaeNae and Taita.

He comments that State houses are favoured for the size of the site they are located on, with

generous set backs from the boundaries. The advantage of being located close to public

transport, schools, shops, amenities and reserves is recognised too. Their structure, size and

simple plan makes them straightforward to work with, being easily extendible.

EXISTING CONDITION

State housing he has worked on have been well built on solid foundations and are made of

excellent raw materials, usually rimu. On occasion he has found borer damage, but never

mould other than on some deteriorated linings to wet areas. They have had well installed

weatherboards and timber joinery, good drainage but typically they need the electrical wiring

and plumbing upgraded. Contingent items are extremely rare. Insulation, when it has been

found, is typically in the ceiling, usually collapsed or displaced as a result of wind driven air

movement in the roof space.

INTERVENTIONS

Ceiling insulation is replaced during the renovation work to the level required by the current

building regulation of the time (usually 100mm thick fibreglass). The floor is insulated to

Building Code standards. Existing walls are not insulated unless they are part of the alteration

work, and timber window joinery remains single glazed. Where sashes have moved (often as

a result of being twisted in the winds) or badly eased to rectify layers of old paint, they are

refitted if possible or replaced, but done properly which may require staging for budgetary

reasons. He comments favourably on the construction of the original window joinery used as

it is well detailed with a decent slope to the sill to prevent water ingress, has good head

flashings and decent facing boards to the jambs. If rust is found in the flashings, these are

replaced in the alteration process. The windows provide passive ventilation, and he

encourages this be done regularly, and if it gets cool ‘wear a warm jersey!’

POST EVALUATION

He thinks State housing is wonderful, is satisfied with the homes they become and has never

had an unhappy client, which reflects they are happy with the outcome.

ARCHITECT 09

The ninth architect interviewed lives in a State house in Christchurch that she has renovated

in two stages. It is timber framed, with a hip and gable concrete tiled roof with walls clad in

painted timber weatherboard. The location of the house is in Bryndwr, a mixed area of almost

fifty percent privately owned and fifty percent government owned State housing that has had

132

some intensification by subdivision of lots (typically into two). The house was built in 1952,

and was altered in 1994 and 2000, being staged for budgetary reasons.

EXISTING CONDITION

Her house was cold, but in sound condition. The native timber wall framing was in good

condition, although the bathroom hardboard wall linings were rotten.

She commented that the house was good value and sound as, by comparison, a privately

built (as opposed to State built) house of the same age in the area is smaller, less well fitted

out with joinery, and has rotting windows.

INTERVENTIONS

The first stage addressed the requirement for improved heating, to open up the living area

and to reline the bathrooms. By removing the fireplace and chimney, the size of living room

was increased and was better connected to the kitchen and dining spaces. Air lost up the

chimney ceased, and electric heating was used as a replacement for the open solid fuel fire.

A heat pump was installed in the lounge, and oil heaters were used at times in secondary

areas, which were found to provide adequate heat to meet their requirements. The heat pump

was not found to be intrusive, and its noise level was similar to that of a fridge. New linings

replaced the existing hardboard wall linings around the shower-bath area, which had rotted as

a result of water damage from use. Although an occupant had asthmatic symptoms, this was

not a driver for the renovation works. The second stage addressed the poor indoor to outdoor

connection, by adding single- glazed French doors and a new covered deck to the north. This

improved sunlight into the house, and the layout and flow of the adjacent indoor areas.

Insulation was not added to the walls, unless they required lining as part of the alteration

work. The ceilings were insulated with fibreglass batts of an unknown R-value, and the floor

framing received ‘Cosy floor’ insulation in which an R-value of 1.8 is achieved. “Cosy floor’ is

a product that has perforated foil attached to fibreglass batts. It is a product that is no longer

available. 80/20 wool blend carpet was laid on the timber floor boards for additional warmth.

The windows remained as single glazed timber joinery, and these were used for passive

ventilation to remove condensation. Heavy weight floor to ceiling curtains were fitted to

separate the cold air from the glazing and the warm interior air. An attempt was made to fit

foam tape to seal the air gaps around the opening ashes of the windows, but this proved too

difficult to be practical as the gap sizes varied.

POST EVALUATION

Temperatures achieved were unconfirmed, but found to be adequate. She was satisfied with

the outcome for her home.

133

ARCHITECT 10

The tenth Architect interviewed is lives in Christchurch. He grew up in a new State house his

parents had lived in since 1953, for twenty-one years, and now owns a State house in which

he has lived for the last ten years. His house was built in 1950 for Sid Holland (National Party

Prime Minister 1949 – 1956) in Fendalton. It was later used as a manse for the Presbyterian

Church.

EXISTING CONDITION

The house is weatherboard clad and has a concrete tiled roof, with two-storeys that

accommodate living downstairs and bedrooms upstairs. Living areas and bedrooms are

orientated to the north, which makes the house very warm from solar gain. There was no

insulation or building paper in the house when he bought it. The structure was sound with no

rot, although a small amount of borer damage. (It faired well in the recent earthquakes, with

some cracks to the plaster board linings being the only apparent damage.)

INTERVENTIONS

He has renovated his house, removing walls to open up the living areas. Indoor to outdoor

connection has been made with French doors and decking for outdoor living. Insulation was

added insulation to the ceilings, floor and walls, with building paper being fitted into each

cavity against the weatherboard, with edges fitted to the studs and nogs that form the cavity

to be filled within the wall framing. Heat is provided by an electric heat pump in the living area

and electric panel heaters in the hall downstairs. This provides heat that rises to heat the

upstairs level of the house. Mechanical extract fans have been installed in the bathrooms and

kitchen.

POST EVALUATION

The house is a sound, well built house that is warm and well connected to outdoor living

areas. Temperatures are unmonitored, but the heat pump is set between 16°C and 21°C.

He does not find the house to be draughty, other than what is caused by the heat pump.

As an Architect and occupant, he is satisfied and happy with his home.

6.1.3 SUMMARY

The interviews exposed that either budget constraints or lack of consideration restricted the

amount of intervention available to address higher levels of IAQ. Insulation was improved,

but not always in areas that were not effected by the new building works. Existing windows

and walls were commonly left devoid of thermal improvement. The timber windows remained

single glazed, whether replaced or existing, and provided passive ventilation. Some

permanent ventilation was retrofitted, which combined with the opening windows left the

ventilation being uncontrolled, causing heat loss and allowing cold draughts to infiltrate the

indoor air. Mechanical ventilation was only used for extract fans to remove moisture from

134

areas exposed to heavy loads of steam. Heat recovery ventilation systems were not used.

Heating sources, when provided typically relied on electricity as its energy source. Heat loss

through air movement and lacking thermal intervention had not been addressed, to ensure

adequate temperatures could be met, and retained as best possible.

The implications are that energy is wasted through heat loss transmission through air gaps,

passive ventilation and electrical heating. Although the improvements of insulation and

ventilation levels are apparent, consideration of alternative technologies provides for further

improvement of the comfort levels and IAQ of such houses.

There were minor differences of thermal and IAQ intervention between privately and

government owned housing. It would be fair to say that there was additional expenditure

dedicated to the quality of fixtures and finish applied to the privately owned houses. The

houses in the private sector were less densely occupied as they tended to accommodate

smaller families, whereas the rental properties tended to be occupied by more people,

housing larger families.

The renovation work of both government and privately owned State housing, presented

similar briefs. Spatially, the houses were improved in all cases by the removal of walls to

open up the plan to create larger areas, often with an addition built to extend the floor area.

Improved connection between indoors and outdoors was typically accommodated via new

door joinery to new deck areas. Bathrooms and kitchens were upgraded to provide modern

fittings and fixtures. Commonly the bathroom linings were replaced, often required as the

hardboard originally used had suffered from mould and water damage.

Indoor air quality and thermal comfort is not particularly well addressed. Insulation was

commonly retrofitted to ceilings and floors, at levels that met legal requirements of the time.

Walls and windows were typically left uninsulated. Existing opening windows theoretically

provided adequate provision for passive ventilation, but relied on occupant activation, which in

many cases was not effective. Opening windows presented security problems, evident more

so in low socio-economic areas, e.g. the Mangere rapist. Permanently opened passive vents

were installed into most government-owned rental properties to address continuous

ventilation. Where adjustable passive vent units were installed they were not used due to lack

of knowledge of how they operated. Fitted passive vents were not used in privately owned

housing. Background ventilation caused by draughts through air gaps was seldom

addressed, as either it was not seen to be necessary, it allowed balanced air pressure or it

was too difficult to apply (e.g. seals around window sashes.) The provision of mechanical

extract fans installed into the bathrooms and kitchens of all houses assisted in reducing

moisture. Heat transfer to move heat from the heated living areas through ducting connected

to bedrooms was not common. Alternative mechanical ventilation systems such as positive

135

pressure with roof cavity heat transfer or balanced pressure heat recovery ventilation were

not considered. It would appear in some cases, that there was a lack of knowledge of their

theory, advantages, and functionality. Heating was not well addressed with few permanent

heat sources being provided. Commonly used electrical or portable gas heating appliances

could be assumed to heat where affordable.

136

SUMMARY OF DISCOVERY AND INTERVENTIONS APPLIED TO EXISTING STATE HOUSES RENOVATED BY TEN SELECTED PRACTICING ARCHITECTS

INTERVENTIONS ARCHITECT

1 2 3 4 5 6 7 8 9 10

House ownership: Government Y Y Y Y

Private Y Y Y Y Y Y

Known occupant health problems Y Y Y Y Y N U N Y N

Existing windows

(single-glazed timber

joinery):

Remains as is Y Y Y Y Y Y Y Y Y Y

Retrofit double glaze N N N N N N N N N N

Air seals applied N N N N N N N N N N

New window joinery:

* new aluminium

joinery installed

Single glazed Y Y* Y Y* Y Y Y Y Y Y

Double glazed N N N N N N N N N N

Air seals fitted N N N N N N N N N N

Airtightness was considered N N N N N N N N N N

Permanent passive vents to windows Y Y Y Y N N N N N

Mechanical extract

fan installed to:

Bathroom/s Y Y Y Y Y Y Y Y Y Y

Kitchen Y Y Y Y Y Y Y Y Y Y

Positive pressure roof heat transfer system N N N N N N N N N N

Balanced pressure HRV system N N N N N N N N N N

Ducted heat transfer between rooms N N Y N Y N N N N N

Existing insulation (found in ceilings only) N N N Y N N N Y N N

Insulation to new

build:

Ceiling Y Y Y Y Y Y Y Y Y Y

Walls Y Y Y Y Y Y Y Y Y Y

Floor Y Y Y Y Y Y Y Y Y Y

Retrofitted insulation

applied to the

existing:

Ceiling Y Y Y Y Y Y Y Y Y Y

Walls N N N N N N N N N N

Floor Y Y Y Y Y Y Y Y Y Y

Heat source

provided:

Existing open fire

New elec. heat pump Y Y Y

New efficient solid

fuel burner

Y

Electric heater Y

Other Y

Thermal mass added N N N N N N N N N N

Solar gain added Y Y N N N N N Y Y Y

Mould in the existing house Y Y Y Y Y Y Y Y Y Y

Significant mould or rot in existing structure N N N N N N N N N N

Significant structural degradation N N N N N N N N N N

137

0

10

20

30

40

50

60

70

80

90

100

Existing To new additions To existing

during

renovations

Ceiling Walls Floor

Figure 6. 3

INSULATION INTERVENTIONS IN RENOVATED STATE HOUSING

(From architect interviews)

10

20

30

40

50

60

70

80

90

100

Single glazed Double glazed Passive vents

Existing windows New windows

Figure 6. 4 WINDOW INTERVENTIONS IN RENOVATED STATE HOUSING

(From Architect Interviews)

138

0

10

20

30

40

50

60

70

80

90

100

Exis

ting

passiv

e

ventila

tion

(openin

g

win

dow

s)

Perm

anently

ventila

tiin

g

passiv

e v

ents

Positiv

e

pre

ssure

roof

heat tr

ansfe

r

syste

m

Bala

nced

pre

ssure

HR

V

Mechanic

al

extr

act fa

ns to

bath

room

s

and k

itchens

In existing house Retrofitted into existing house Installed into new additions

Figure 6. 5

VENTILATION INTERVENTIONS

(From Architect Interviews)

6.2 LABOUR PARTY STATE HOUSING IN ITS CURRENT CONTEXT

Observation of renovations to State housing show that improvements are made to alter living

configurations to provide improved connection between indoor and outdoor living, to suit New

Zealand’s lifestyle. Often walls are removed to enlarge living spaces. Many houses have

minor insulation improvements to prevent heat loss, and some propriety type, standard

mechanical extraction from bathrooms. There are some houses that have replaced timber

window joinery with aluminium joinery, which requires less maintenance and has improved

airtightness. Open fires are often removed as part of the process in enlarging living areas.

Space heating in recent times has commonly become heat pumps installed on the walls of

living areas, with its mechanical extract box located in an adjacent position on the house

exterior.

Renovation work varies between privately owned and government owned housing, quite

possibly due to financial investment. As HNZC owns approximately sixty-nine thousand

houses, their maintenance demands large financial investment. Balanced against health

expenditure, the financial investment for betterment of the house IAQ also improves the

health of tenants, which reduces personal and national government expenditure on health

care. It appears that some improvements are being made to insulation, ventilation and

139

heating evident in some insulation having been retrofitted, permanent passive vents to

provide regular ventilation, and heat pumps are being installed to provide an economical

source of heat, albeit to the living areas only.

6.3 SOCIETAL CHANGE IN OCCUPANT BEHAVIOUR

Societal change over the last few decades has altered how we live in houses, and occupant

behaviour affects and influences the quality of indoor air in housing. As time has progressed,

many household ‘skills’ have changed, possibly through modifications that absorb time in

alternative ways. In the era LPSH commenced, the house was typically occupied throughout

the day by women / mothers. This gave opportunity for the house to be well ventilated as

windows were opened daily. Household chores were a routinely undertaken that included

dusting (removal of dust accumulation); laundering bed linen and clothing that and hung

outside to dry. Consequently, dust and mould were minimised by the thoroughness of

cleaning and ventilating.

A standard house size was an average of one thousand square feet (approximately one

hundred square metres), which is about half the size of new houses today. As houses were

small, so were the rooms' sizes. Children often shared bedrooms, with beds often placed up

against external walls to fit into the room. As these houses were cold, bedding and the

clothing stored in bedrooms, and any other absorbent materials, were vulnerable to mould. A

bed placed up against an external wall lacks ventilation between the wall and bed, and allows

condensation from the cold wall to be absorbed into the bedding, causing dampness.

Clothing, bags and shoes stored in small wardrobes, an enclosed space without ventilation,

were also exposed to mould growth.

During winter a warm bath or shower is a great way to heat up. The considerable amount of

steam produced requires adequate ventilation for its removal, but the steam is warm, and

ventilation by window opening allows the heat to escape and cold air enter. This would cause

human discomfort, and steam from the bathroom would be more likely to escape through the

door when it is opened into the house interior (passage), than to escape to the house exterior

via the window.

Although many factors that cause mould growth were evident, the vigorous cleaning and

ventilating which was part of the routine of home life, quite likely minimised its invasion.

By comparison to that era, houses now are left unoccupied for long periods of time. Vacant

houses lack ventilation due to the security problems that restrict windows being left open.

Laundry is more likely to be dried indoors using mechanical dryers, some of which are not

externally ventilated. Bedding is still cold, wardrobes and their contents still grow mould,

140

showers and baths are still regular daily events. Electricity is dearer, and possibly restricts a

healthy level of heating.

6.4 THE FUTURE OF LABOUR PARTY STATE HOUSING

It is regrettable that although there was an awareness of the need insulation, ventilation and

heating these important requirements for healthy IAQ were not implemented into the

construction of LPSH (and similar housing), to the detriment of the houses and the health of

many generations of occupants that resided within such homes.

There are many reasons to consider LPSH for thermal retrofit capable of transforming existing

cold, damp, mouldy, internal environments into healthy, comfortable, warm homes that are

capable of retaining heat.

1. They were not insulated, and are difficult to heat;

2. Their cold, damp and mouldy interiors have been associated with health problems;

3. Mass production means there are a lot of them that collectively could make a

significant difference to energy consumption;

4. Sustainable retention for future provision of homes;

5. Sustainable value in preserving the dedicated materials and energy already

committed;

6. Their neighbourhoods designed are designed for sustainable community living;

7. They are built of quality materials, using sound construction practices that have

endured.

Existing LPSH remain as sturdy housing stock of varying condition, despite being almost

three-quarters of a century old. They are designed for, and suited to the New Zealand climate

with the benefits of solar design to provide shade in summer and sun penetration in winter.

Where once LPSH were homes that residents were proud of, decades of neglect and lacking

maintenance has rendered many LPSH houses as being no longer desirable. Their structure

of native timber framing has endured, and although the condition of some interiors has

deteriorated largely due to neglect, their refurbishment is uncomplicated. They suffer from

superficial problems typically affecting the interior linings, and yet are structurally sound and

constructed in a well built manner made of stable, dry, and relatively chemical free materials

such as VOC’s and MVOC’s. That the houses are as small as they are, usually single storey

and being built of simple construction methodology, renovation is not onerous.

LPSH are existing buildings that have significant dedicated national resources committed to

use. To remove them, either as a whole or dismantled, requires the commitment of additional

141

energy. Sustainability infers reuse, and these houses and the communities are sustainably

valuable recourses the country has in its housing stock. There is a need to ensure they

function well, to provide the requirements for an “adequate standard of living’, as well as

respecting the requirement for energy efficiency.

6.5 SUSTAINABLE ENVIRONMENTS

Part of LPSH was the design of the neighbourhoods they sat within, which meets the criteria

sought now for sustainable living communities. At the sustainable building conference SB10

in 2010, Nils Larson (International Initiative for a Sustainable Built Environment) commended

minimising taxation on energy-efficient renovation, undertaking redevelopment of existing

urban areas and launching major training programmes to increase the pool of skilled

renovators, which would offer great incentive and affordability to energy efficiently restore

LPSH. Part of his suggested triage programme evaluates existing building stock in urban

areas for redevelopment. The functions of a neighbourhood as described by Duany and

Plater-Zybork is a combination of dwelling, shopping, working, schools worshipping and

recreating (Duany and Plater-Zybork 1994; Hargreaves, Howell et al. 2004).

Beacon Pathway has presented ten principles’ that a sustainable neighbourhood requires of

which LPSH planning and infrastructure provides a significant number of (Hargreaves, Howell

et al. 2004).

1 Walkability – that most things are within a ten minute walk from home, with a pedestrian

friendly street design.

2 Connectivity – an interconnected street network that disperses traffic and eases walking,

with a hierarchy of narrow streets and alleys with high quality pedestrian networks. There are

existing walkways and reserves that provide connectivity for pedestrians away from vehicular

traffic.

3 Mixed use and diversity – mixed use within neighbourhoods exists, and can be extended.

4 Mixed housing – a range of types, sizes and prices can be provided by including some infill

development.

5 Quality architecture and urban design – aesthetics’, beauty comfort and creating a sense of

place with special places for civic uses and site within the community, is all provided but the

housing in many cases need upgrading. Well restored LPSH make beautiful homes, it is

when they are neglected that they become less desirable.

142

6 Traditional neighbourhood structure – LPSH is as traditional as you would find in New

Zealand. They provide the public spaces, and can provide for a range of density with

additional urban planning.

7 Increased density – to provide for more housing, shops, and services close together for

easy pedestrian access for efficient use of services and resources is required. Most of this

exists in areas of LPSH, and there is room to facilitate further provision.

8 Smart transportation – a network of trains to connect neighbourhoods, towns the city, with

pedestrian friendly design that encourages alternative modes of transportation such as

cycles, scooters and rollerblades. The LPSH suburbs and neighbourhoods were designed to

be serviced by trains to connect housing to the city. Bicycles and pedestrian were common

forms of transportation when these areas were designed.

9 Sustainability – Minimal environmental impact on development and its operations, local

production, eco-friendly technology, are all possible by retaining LPSH in their current

environments.

10 Sustainability where it requires energy efficiency is a factor that is not currently met.

These houses require adequate thermal intervention.

The outcome of Beacon Pathway research on neighbourhoods found that people like living in

neighbourhoods that have good quality housing with little dilapidation, safe streets, low noise

disturbance and offer opportunity for social interaction. Minimised travel costs were also

favoured. (Beacon Pathway Ltd 2008). The communities that State houses are built in have

an existing structure that can be restored to provide sustainable living and reduced

transportation fuel costs, to the benefit of the occupant, neighbourhood, country and the

world.

By applying the Homestar™ residential rating tool to LPSH, it can be seen that it has the

potential to provide for sustainable living.

143

CHAPTER 7: PROPOSED RETROFIT PACKAGE

7.1 THE HOMESTAR RESIDENTIAL RATING TOOL ANALYSIS

Following international developments used in countries such as the UK, US and Australia,

New Zealand now has its own residential rating tool, ‘Homestar™’, which has been developed

for local conditions. Homestar™, launched in 2010, has been developed in a partnership that

joins BRANZ, Beacon Pathway and the New Zealand Green Building Council to improve the

performance of housing energy efficiently. It provides house owners with an awareness of

the quality, health, comfort and energy efficiency of their houses. The ten-star rated tool

informs both the current house owner, and future owners, of the sustainable improvements

made to a property and it is hoped this is recognised as adding value to house. (New Zealand

Green Building Council, Beacon Pathway et al. 2010)

The Homestar™ evaluation appraises the house, site and location for its sustainability and

energy conservation, which is divided into six areas: energy, health and comfort, water,

waste, home management and site.

To complete the appraisals some assumptions been made and which were based on

research of the State house history, literary and visual research, or the interviews.

The Homestar™ reports can be viewed in the appendix of this document.

SITE, ENERGY WATER AND WASTE

Transportation is rated in this component, affected by its proximity to public transport and

local amenities. Locality reveals how well connected the house is to public transport, as this

effects privately owned, vehicular related fuel consumption. How rainwater collection and

recycled water options are managed impacts on the water component, as do water

consumables within the home, such as the shower (flow rate) and appliances. Waste

addresses how recyclable materials and compost are managed. Home management impacts

on indoor air contamination caused by condensation, mould, LPG heating and toxicity. Areas

of waste such as leaking taps and downlights are part of this component, as is accessibility,

safety, security and knowledge of how things operate. On-site stormwater management,

areas of native and fruit producing planting and vegetable gardening are all factored into the

site appraisal.

HOME DETAILS

The analysis starts with a collection of information on the house typology, floor plan area, the

number of stories and bedrooms. The house typology impacts on the ease of applying

insulation, whether it is suited to solar heating and the materials used effect the VOC’s

144

emissions within the house as well as the environmental impact of their production. The

details entered are common to all of the six assessments presented.

ENERGY, HEALTH AND COMFORT

The energy component of the assessment considers what is used to provide space heating

(solid burners, gas heaters, electric heaters and solar); water heating, insulation and lighting.

Appliance age and energy ratings are assessed and what, if any onsite energy generation is

provided.

Health and comfort investigates the windows, walls, floors, ceilings and dampness.

Information required covers the following:

The levels of insulation to the walls, floors and ceilings, the standard of fitment, and

whether there are penetrations that risk heat loss, such as downlights;

If there are any changes within an element (e.g. changes in a wall or ceiling).

Wall and floor materials such as their material composition, and if they receive any

sun;

Window to wall ratios, window orientation to the sun, materials used for the window

frame and the type of glazing, and curtain treatment;

Causes of draughts in the house such as floor boards, doors, windows and fireplaces;

Items that affect dampness such as whether polythene has been laid across the

ground beneath the house to prevent rising damp; fan extraction to the bathroom/s

and kitchen; and if there is a clothesline to dry clothing outside.

THE HOME STAR RATING APPLIED TO VARIOUS STATE HOUSE INTERVENTIONS

The Homestar™ rating tool has been applied to an original LPSH to presenting six different

scenarios. The first of these is the original house as it functioned when it was built. The

second application is of the same house, but in its current condition without having had any

intervention. The third application for the house adds the previously used standard,

government subsidised insulation improvements and the fourth applies the HHP interventions.

The fifth application retrofits the house with a full thermal envelope and minor recycling

improvements, the house being in its current environment. The sixth option uses all of the

interventions applied to the fifth scenario, with the addition of as many available energy

efficient applications as are realistically possible for the site.

The LPSH used as the example to be applied to the Homestar™ rating tool is a single storey,

stand-alone house, built between 1930 and 1949. It is of timber framed construction with a

hip shaped concrete tiled roof, clad with weatherboard and has a suspended timber floor.

The window area is 15% of the wall area, located with the largest areas of window facing

north. The windows allow the sun to penetrate into the rooms in winter. Eaves provide solar

145

shade in summer. The house is of a rectangular plan shape that is 7.3 meters wide and 10

meters long, giving a plan area of seventy-three square meters.

Figure 7. 1 - Plan 6H/1180: The house example applied to the Homestar™ rating tool and the Risk Matrix

(Picture courtesy of NZ Archives)

7.1.1 HOMESTAR™ RATINGS

RATING 01: THE STATE HOUSE IN THE ERA IT WAS BUILT

SITE, ENERGY WATER AND WASTE

Part of the LPSH philosophy was that the houses were built on large sites (sections) that

could be gardened and grow fruit trees. Therefore it is assumed that these were in place on

well maintained sites. In the era these were built, domestic recycling was managed by either

exchange of bottles when purchase was made (i.e. milk and beer bottles) or by returning

glass bottles to a retailer (i.e. soft drink bottles), a small monetary refund was paid. Paper

packaging was used more commonly than plastic. Therefore it is assumed that recycling (as

such) was possible on site. Reticulated services were very ‘modern’ at this time, (having

recently replaced water storage tanks and septic tanks) and so stormwater was piped directly

into the council system. There was neither grey water nor stormwater collection on site.

Facilities in the area within a ten minute walk include the following:

146

Public transport; takeaway; chemist or medical centre; dairy; an educational institute (school);

a supermarket (known then as a Grocer); a place of worship (local church) and a sports field.

A fitness centre, library or marae are variables, therefore have not been included in this

assessment.

ENERGY HEALTH AND COMFORT

Being solar designed; the house was sited to the sun. The house was clearly identifiable and

able to be viewed from the road. The front entrance had secure locks. Automated security

lighting and smoke detectors were not available at the time these houses were built, so a

manually switched outdoor light was the only light available and not considered to be ‘security

lighting’ in the assessment. Internal doors were less than 810mm wide.

The primary space heating source for the house was an open fire in the living area. The

structure had no insulation, unsealed window and door joinery, and draughty floor boards.

The timber floor boards were left uncarpeted, and there was some curtaining in the house,

25% has been assumed (as it was more common at this time to have metal slat venetian

blinds, and sheer privacy netting.)

The ground beneath the house was natural damp earth. It would be assumed there was

moisture in the form of condensation on the inside of the bedroom windows in winter, and

there would be black mould on the walls or ceilings. There were no mechanical extract fans to

the bathroom or kitchen. The taps did not leak as they were new and as the HWC was low

pressure, the flow from the shower was less than nine litres per minute. Washing was dried

on an outdoor clothes line. There was neither a clothes drier nor dishwasher. It is assumed

that there was no home operation maintenance manual.

RATING 02: THE STATE HOUSE IN ITS CURRENT CONDITION

SITE, ENERGY WATER AND WASTE

This assessment was based on the existing State house, but in its current, aged condition.

It is assumed that it is in its original form, still uninsulated with deterioration that has caused

taps to leak, and neglect of the garden. Therefore trees, vegetable gardens and compost

facilities have not been included. Increased availability and use of motor vehicles modified

the distribution of amenities, with local suppliers being replaced by larger facilities such as

supermarkets (that replaced grocers, butchers, stationers and greengrocers) now located

further from ‘home’. It has been assumed that the public transport; a café / restaurant /

takeaway; dairy / service station; an educational institute (school); a place of worship (local

church) and a sports field still remain in use.

RATING 03: THE STATE HOUSE WITH GOVERNMENT SUBSIDISED INSULATION

147

The criteria as described for Rating 02 are applicable to this rating, but the previous

government insulation intervention has been included. Previous government subsidised

insulation installations to the ceiling and floor of houses provided R1.8 insulation into the

ceilings and R1.3 insulation beneath the floor.

RATING 04: THE STATE HOUSE WITH THE HHP UPGRADE

Some of the criteria used in Rating 02 also apply to Rating 04, but there have been many

improvements introduced through the HHP brief.

SITE, ENERGY WATER AND WASTE

Visual connection and recognition from the street was reinstated, two fruit trees were planted,

and a clothesline was provided. On-site stormwater disposal was mentioned in the HNZC

brief for the HHP, but it didn’t appear to have been implemented (from Architect interviews),

so the stormwater remained reticulated into the existing public stormwater drain.

ENERGY HEALTH AND COMFORT

These houses had new additions built; bathrooms and kitchens upgraded; and insulation with

higher R-values applied to the ceilings, walls and floors. (Insulation was only applied to the

new areas of built structure.) Mechanical extract fans were fitted to the bathroom and kitchen.

Smoke alarms were installed. There appears to have been no operation manual issued to the

tenants. Although permanent passive vents were fitted to all rooms this is not a rated item in

Homestar™.

RATING 05:

THE STATE HOUSE THERMALLY RETROFITTED IN ITS CURRENT ENVIRONMENT

This is the first of two proposals that provide the house with a full thermal envelope. The

house is in the same external environment as the previous three examples, but the thermal

interventions have been improved to meet the current building regulation for insulation, (that

would be used for a new house) have been applied to the entire house.

SITE, ENERGY WATER AND WASTE

Waste recycling and composting are possible on site, and have been included in the

assessment. The stormwater remains piped into the council system. So, there is no storm

water or grey water collection applied to this study, but there is opportunity for its provision.

Improved water conservation has not been applied in this assessment with the exception of

appliances that would have been upgraded.

148

The native planting remains the same as used in the first assessment, being less than 50% of

the site area. There are no pest plants on the property and at least two food producing trees

or vines, and a vegetable garden are on the property.

The same facilities within a ten minute walking distance are applicable as with the previous

existing analysis.

ENERGY, HEALTH AND COMFORT

To improve the thermal performance of the house, new double glazing has been retrofitted

into the existing windows improving the r-value from R0.19 to R0.36. (Design Navigator Ltd)

The Living Room and Bedrooms have thick curtains assumed as being to three-quarters of

the house. A double layer of wool insulation that is 190mm thick with an R-value of 4.34

(Terralana TLDBL3.8 wool) (Terra Lana Products Ltd 2011) is fitted between the ceiling joists,

with a second layer across the entire ceiling area, laid over the top of the ceiling joists. The

existing timber framed walls have been insulated with 90mm thick R2.2 wool insulation slabs

fitted into the wall cavities, with a vapour permeable (vapour check) airtight barrier and

battens that create a 20mm air cavity to the inside face of the wall. This is deemed to provide

‘extra thick insulation’ for rating purposes. New 10mm plasterboard wall lining is tightly fitted

with taped edges. The timber sub-floor is insulated with 100mm R1.8 wool insulation

between the joists, with a 4.5mm layer of fibrous cement sheet lining with sealed joints is

fitted to the underside of the floor joists for airtightness.

Polythene has been laid over the ground to prevent rising dampness entering the house. The

kitchen and bathroom have mechanical extract fans and clothes are dried on an outdoor

clothesline, or in a drier that is externally vented.

Air movement around the doors and windows is eliminated by the use of silicone compression

air-seals. The fireplace is sealed and replaced with a pellet burner as its main source of heat,

with a wet back to supplement the hot water heating. The sun shines on a third of the

exposed timber floor boards.

The existing hot water cylinder has been replaced with an insulated low pressure HWC that is

‘newer than 2004’, with insulated pipes and a wet back connected from the pellet burner. The

shower flow rate is less than 9L/sec, and the WC has been replaced with a new dual flush

cistern. The dishwasher and washing machine are assumed to be the most efficient 5 or 6

Star WELS (Water Efficient Labelling Scheme) rated, and there is one fridge that is less than

ten years old.

Surface mounted compact fluorescent lights that to not penetrate the ceiling lining have

replaced the existing incandescent light bulbs.

149

The house and entrance door is clearly viewed from the street. Outdoor security lighting,

secure locks, smoke detection, a fire extinguisher and secure medicine storage are all

included for safety. A home operation maintenance manual is provided. The doors remain,

and are less than 810mm wide.

Environmental choice products were selected for the insulation, replacement wall linings and

paints.

RATING 06:

THE STATE HOUSE, THERMALLY RETROFITTED, IN ITS ORIGINAL ENVIRONMENT

ENERGY, HEALTH AND COMFORT

In this proposal, all of the interventions used in the previous rating are duplicated, but the

house is located in an environment that replicates the original neighbourhood amenities (as

noted in Rating 01). As many of the sustainable options available on its site have been

introduced, such as the installation of photovoltaic’s onto the 32° pitched roof, to convert

solar energy into electricity to provide between 25% and 50% of the electricity demanded by

the house.

SITE, ENERGY WATER AND WASTE

The added improvements for energy efficient living include on-site stormwater management.

A small (1000 - 2000 litre) rainwater collecting tank is installed to provide water for the laundry

and the garden. A greywater system has been introduced to service the WC and to

supplement summer water usage for the garden.

Facilities in the area that were historically within a ten minute walk have been reinstated.

(Refer to rating 01).

7.1.2 OUTCOMES FROM THE HOMESTAR™ RATINGS

RATINGS 01, 02, 03 AND 04 Out of a rating of ten stars (ten being the most sustainable) the outcomes allocate two-star

ratings for the first four options. Ratings 01 and 02 received the same outcome with values of

8% for energy and 16% for health and comfort.

Two-star ratings are assessed by Homestar™ as not having reached a minimum core

performance level in warmth and comfort, and that winter temperatures are not achievable

without expending excessive energy. (New Zealand Green Building Council, Beacon Pathway

et al. 2010)

150

RATINGS 05 AND 06

When the house was fully thermally retrofitted, Ratings 05 showed improvement to seven

stars and 06 improved further to an eight star rating. Rating 06 increased its values to 46%

for energy, and 84% for health and comfort. This is an increase of 38% and 68%

respectively.

The outcome for components that were required to complete the assessment, but are not

relevant to this thesis gave values of 68% for water, 100% for waste, 67% for home

management and 62% for the site.

7.1.3 CONCLUSION BASED ON THE HOMESTAR RATING

This assessment verifies that with adequate thermal intervention to LPSH to create a full

thermal envelope, there is considerable improvement possible for the levels of health and

comfort, and energy efficiency.

Figure 6.6 presents the outcome for the Homestar™ ratings, representing the various

outcomes applied to LPSH comparing its original built situation to what it has become, either

being left without intervention or with previous and proposed interventions applied. Figure 6.7

clearly demonstrates the potential sustainable opportunity achievable by introducing energy

efficient interventions that are practically applicable. These houses are capable of achieving

high levels of sustainability.

LPSH houses can be restored to rectify current problems so as to provide good IAQ and

thermal comfort. Their neighbourhoods have the ability to function without the need for

vehicles for everyday needs. The sites (sections) provide enough land for sustainable living,

and even with possible housing intensification, there can be provision included for communal

green areas that can be utilised for food producing planting.

151

0

10

20

30

40

50

60

70

80

90

100

Rati

ng

01

Rati

ng

02

Rati

ng

03

Rati

ng

04

Rati

ng

05

Rati

ng

06

Energy Health and Comfort Water Waste Home management Site

Figure 7. 2 BAR CHART PRESENTATION OF SUSTAINABILITY RATING OPTIONS

0

20

40

60

80

100

Rati

ng

01:

Ho

use in

era

bu

ilt

Rati

ng

02:

Ori

gin

al h

ou

se in

cu

rren

t co

nd

itio

n

Rati

ng

03:

Pre

vio

us g

ovt.

su

bsid

ised

in

su

lati

on

Rati

ng

04:

HH

P U

pg

rad

e

Rati

ng

05:

Th

erm

al

Retr

ofi

tted

Rati

ng

06:

Th

erm

al re

tro

fit

in

ori

gin

al en

vir

on

men

t

Energy Health and Comfort Water Waste Home management Site

Figure 7. 3 POTENTIAL IMPROVEMENTS IN THE SUSTAINABILITY OF LPSH

152

7.2 RISK MATRIX APPLIED TO A LABOUR PARTY STATE HOUSE

A primary function of a building is to provide shelter from the weather, and yet the last two

decades have seen increased complexity of building design, systems and construction

practices in New Zealand, with resultant problems of inadequate watertightness due to

lacking and misused technology. From early 2000 there was recognition of problematic

design features such as flat roofs, complex building shapes and junctions, parapets, narrow

or no eaves, monolithic claddings, untreated framing, sealed decks, built-in balconies and

inadequate flashings around windows and doors.

Acceptable Solution E2/AS1 provides an assessment tool to assess potential external

weathertightness risks and ways to manage them. The design of this tool was based on a

simple concept developed by two Canadians, Don Hazelden and Paul Morris called ‘the 4Ds’,

to describe the basic principles of water management in buildings DBH, 2010).

Figure 7. 4 Weathertightness - Deflection, Drying Drainage and Durability

Image from the Department of Building and housing

The risk matrix assesses the weathertightness and durability of various nominated cladding

types, either directly fixed, or fixed over a cavity system. As the building complexity develops,

the risk assessment increases and leads to permissible cladding options that will suit the

house design.

Applying the a typical LPSH, using example 6H/1180 for assessment using this tool produced

a result that the design and materials are of low risk to water penetration from the exterior

design. There is a variable factor applicable to the house being the wind zone the house

could be located in. Both Low and Very high wind zones have been applied, presenting the

best and worst scenarios. The lower the number on the scale, the less risk there is

associated with the building.

153

Figure 7. 5 Risk assessment of a LPSH in a low wind zone

154

Figure 7. 6 Risk assessment of a LPSH in a very high wind zone

155

The risk assessment rates LPSH as having a very low risk of water penetration. The house is

not complex in its form or material use, it does not have complex junctions, it has a generous

eaves width to deflect water and shelter the window heads. With the current New Zealand

housing crisis of monolithic clad ‘leaking’ housing, these reliable and durable houses that

have performed well in terms of weather tightness are of value.

7.3 PROPOSED THERMAL INTERVENTION

New Zealand research has confirmed that insulation improves the quality of the indoor air,

and thermal environment, with the best results found being when insulation is applied at

higher resistant values than the minimum levels required by the building code, and insulation

is applied to the entire building envelope.

An adequate heat source that will provide temperatures throughout the house to achieve

temperatures of 18 – 20°C, with controlled ventilation rates of between 0.35 and 0.5ac/h can

be achieved by installing a balanced pressure heat recovery ventilation system that extracts

moisture loads, and reuses heat recovered from the house interior. This provides adequate

ventilation without compromising home security when the house is vacated. Balanced

pressure systems require airtightness that can be addressed by sealing air movement.

Airtightness cane be provided beneath the floor to prevent draughts from being transmitted

through the floor boards, air tightness can be installed into the walls and ceiling also. Air gaps

around the windows and doors can be rectified with proprietary silicone seals.

Bulk insulation is easily applied over the ceiling by access through the roof space, and bulk

insulation can be applied beneath the flooring as typically there is a 600mm minimum space

beneath these houses.

It is more difficult to rectify the thermal properties of the walls and windows. These involve

more mess, higher expenditure to retrofit (largely due to the amount of labour required), and

there is no government subsidy for their thermal rectification. It could be argued that as

government contributed to the problem with knowledge of there being ‘a problem’ that they

have an obligation to rectify the situation, or contribute to its rectification. Should there have

been PCP introduced into the wallboard, there may be an environmental safety obligation to

for its remediation.

But, the aim of this thesis is to present a solution to thermally retrofit uninsulated LPSH to

create a complete thermal envelope.

156

7.3.1 REPLACING THE WALL LININGS

Aged interior wall linings suffer damage over time. Bathroom and kitchen linings typically

have mould damage, as seen in the BRANZ House surveys. Plasterboard wall linings are

often physically damaged, and as they are absorbent, they are great collectors of

contaminants. Investigation may need to be undertaken should there be residual PCP

absorbed into the linings, but regardless, they have the potential to harbour mould growth on

the cavity side of the linings, as well as possibly on the interior faces as was exposed in the

DSIR investigations of 1944 and evident from the occupant surveys.

To fit insulation into walls access is required, either from the exterior or the interior. The

removal of the interior linings is preferred in this proposal for the following reasons:

The exterior skin of the house is left in place; therefore flashings and weather board do not

need to be replaced. Aged weatherboard can become brittle, and may suffer damage in its

removal. Timber is also an expensive product that is also a valuable dedicated resource.

Practically, it is easier, and more economical to install insulation from the inside of a house.

This provides all weather climatic control, allowing work to progress without interruption,

ensuring that all materials remain dry, and easy access is possible without the need for

scaffolding. It also allows for the provision of internal moisture control by application of a

vapour permeable (vapour check) airtight barrier; and at the end of the refurbishment, the

interior walls have a superior condition.

When retrofitting insulation, if building paper is either non-existent, or of poor quality, new

building paper can be applied within each cavity as per the diagram provided in NZS4246,

and as shown in Chapter 4 of this thesis.

The timber framing will provide thermal bridging that can be rectified by the application of

horizontal battens to the inner face of the framing, positioned not to coincide with nogs. The

application of a vapour check between the existing wall framing and the new battens which is

sealed to the floor, cornice, window reveals and any penetrations, will seal the exterior air

movement from entering thus providing air tightness to the interior.

Plasterboard is an inexpensive product that is relatively quick to install (particularly when

compared to fixing weatherboard). Plasterboard is made of gypsum plaster and paper, so

redundant product is recyclable.

The Design Navigator insulation selection tool has been used to make selections for the

insulation materials that are suitable and meet the of HSS™ guidelines, as best possible

157

given the constraints of space i.e. the wall cavity, and construction. These were entered into

the Homestar™ ratings.

7.3.2 INSULATION LEVELS

New Zealand made products have been selected to minimise transportation related carbon

emissions. Supporting locally manufactured product also supports the original philosophy

LPSH was built from.

CEILING:

Wool bulk insulation has been selected for its resilience and hygroscopic capacity.

The product is applied between the timber framed ceiling joists, to fit firmly without any gaps.

The blanket is 90mm thick, which matches the typical depth of the timber framed ceiling joists

that were used. In its blanket form, the insulation is able to be laid with even coverage. Run

in a perpendicular direction across the top of the first layer of insulation and across the top of

the joists a second layer of wool insulation is laid. This top layer prevents the transfer of the

roof space temperature and moisture through thermal bridging through the ceiling joists into

the house interior. The double layer of wool insulation is 190mm thick and has an R-value of

3.8m²/K/W (Terra Lana Products Ltd 2011). When it is installed in the timber framed and

plasterboard lined ceiling, it provides an R-value of 3.95m²/K/W.

WALLS:

The existing timber framed walls have a cavity depth of about 95mm, which allows 90mm

thick wool insulation slabs with an R-value of 2.2m²/K/W to be fitted into the building paper

lined wall cavities. The vapour permeable (vapour check) airtight barrier is applied over the

inside face of the wall framing, with joins in its sheets sealed with tape. Air seal tape is

required to seal the edges of the membrane along the junction between the wall and the

ceiling; the walls to the floor; and around any openings such as windows and doors; and

service outlets that penetrate the membrane. Over the top of this membrane horizontal

battens are installed to suit the wall lining being applied. The plasterboard, or other selected

wall board can then be applied. In this case, 10mm plasterboard with taped joins is being

applied, finished with breathable paint or wall paper.

WINDOWS:

Retrofitted double glazing has the ability to increase the R-value of the window to 3.6m²/K/W.

Silicone compression air seals applied to the reveal of the opening window sash, or rebated

into the frame to close the air gap will prevent air infiltration through the window joinery.

158

FLOORS:

The timber sub-floor is insulated with 75mm R1.8 wool insulation installed between the floor

joists. It is preferable to run battens in a perpendicular direction to the floor joists, prior to the

installation of the fibrous cement sheet lining to minimise thermal bridging. A 4.5mm layer of

fibrous cement sheet lining with sealed joints is fitted to the underside of the floor joists.

Which combined with the insulation provides an R-value of 2.13 - 2.28m²/K/W, dependant on

whether the site is sheltered or exposed. It is assumed that the floor is 600mm above ground

level, and polythene is laid over the ground to prevent rising dampness entering the house.

7.3.3 R-VALUES PROVIDED:

The following table identifies the R-values for the original, uninsulated house; the previous

government provided insulation to the ceiling and sisalation to the subfloor; the HHP

insulation and the proposed intervention to insulate the entire building envelope.

COMPARISON OF LPSH R-VALUES THROUGH VARIOUS INTERVENTIONS (M²K/W)

EXISTING PREVIOUS

GOVT.

SUBSIDISED

HHP PROPOSED

ROOF 0.28 1.87 2.14 3.95

WALLS 0.3 0.3 1.69 - new walls

0.3 - existing

2.23

WINDOWS 0.2 0.2 0.2 2.6

FLOOR 0.4 * & 0.55** 1.23 * & 1.38** 1.23 * & 1.38** 2.28* - 3.15**

* Exposed site

** Sheltered site

7.3.4 DRAWINGS OF THE PROPOSED SOLUTION

Drawings follow showing isometric views of the intersections between the walls and the floor

and ceiling. Cross-sections show detail of the junctions where the wall meets the ceiling, floor

window head and sill. The head detail is similarly applicable to the jamb of the window.

In all situations the airtightness layer must be securely taped to any surface in the building

envelope it adjoins e.g. windows, doors, floor and ceiling.

The airtightness layer is marked in red.

159

Figure 7. 7 Isometric sketch of ceiling to wall and wall to floor junctions

160

Figure 7. 8 Cross-section through wall to ceiling and wall to floor junctions

161

Figure 7. 9 Cross-section through wall at the window head and sill

162

CHAPTER 8: CONCLUSION

Climate change is a recent concern and there is still little confidence in climate change

implication by the general public (Bengtsson, Hargreaves et al. 2007). Concern is minor

suggesting a slow and inconsistent response to a problem of considerable magnitude, as

stated by the American economist Milton Friedman:

"Only a crisis, actual or perceived, produces real change when crisis occurs. The

actions that are taken depend on the ideas that are lying around"

Clearly there has been evidence of a looming energy problem that has lacked recognition by

the Global populous. New Zealand’s reliance on fossil fuels has increased, and with peak oil,

climate change and related increased costs, as well as commitments to the Kyoto Protocol to

be met, New Zealand needs to address its preservation of fossil fuels. Although progress has

been made with the various government organisations established to encourage energy

efficiency, stronger and speedier measures are needed to meet to the urgency the global

energy crisis has presented.

Milton Friedman also made this comment, decades ago:

"Preparation and action is required attempting to combat superfluous energy wasted

in heating and non-insulated or poorly insulated homes."

In New Zealand the majority of the current housing stock is made up of poorly performing

homes. Retrofit represents an efficient approach to provide comfortable and healthy living

conditions as well preserving our architectural heritage where structurally sound, older

housing is retained. As there are thousands of existing houses that require thermal

improvement, and as these houses have existing embodied energy retainable in existing

neighbourhoods, this current situation presents a current plethora of opportunity to make

improvements to reduce energy consumption without the added greenhouse gas emissions

that new building creates. As well as reducing unnecessary landfill, wasted energy in

dismantling the structure is avoided, and probable transportation to land fill or recycling

depots. Improvements to existing housing stock offers some resilience to global challenges

faced such as climate change, resource availability, and population change (Specialists,

2007).

It is regrettable that important requirements for healthy IAQ were recognised and investigated

by government in the 1940’s, but not implemented, to the detriment of the houses and the

health of many generations of occupants that resided within such homes. Had ventilation

163

rates, insulation and improved heating sources been implemented while LPSH were being

built, national expenditure could have been reduced in health, energy consumption and post-

construction retrofitting.

Decades of lacking maintenance has rendered LPSH undesirable, and their neglect en mass

has created many unsavoury ghetto neighbourhoods. It is known that poor quality housing is

often the only affordable option for low-income earners and beneficiaries, and yet it seems

unethical to accommodate those suffering from ill health, in unhealthy homes.

Prior to the introduction of legislation setting a reasonable degree of thermal insulation in

1978, thousands of New Zealanders grew up in these cold, damp and draughty houses.

There are many who may develop health problems as a result of living within such unhealthy

homes, and as health deteriorates, earning ability has the possibility to diminish. By

comparison, creating warm, healthy homes raises the self-esteem of its occupants, who then

take pride in their homes. Privately owned LPSH's have often been restored, reinstating them

to homes owners can be proud of.

Records show that over the last thirty years New Zealand houses change ownership on

average every 7.2 years, with almost 25% of these being owned for between two and five

years (Quotable Value 2010). This high turnover may reflect a dissatisfaction of comfort

within the home, and on selling is a solution in seeking an improvement, but as there is such

a high number of inadequate housing in New Zealand, the same problem is recurrent.

The newly released Homestar™ residential rating tool for energy efficiency is an asset to the

future value of any housing, and as seen in its application to the existing LPSH, demonstrates

LPSH as being a sustainable resource when thermally retrofitted to a level that provides a

complete thermal envelope, particularly in their original environment. The initial LPSH

philosophy of provision for community living with amenities and close link to public transport

provides for long term energy savings in transportation fuels. This tool offers an operating

cost savings analysis for invested costs related to sustainable interventions dedicated to

existing housing stock (Donn, 2008).

Surely this represents sustainability as a capacity to endure, enabling these houses to be

productive over time, meanwhile providing long-term maintenance of occupant well being,

looking after the world situation and acting responsibly with natural resources. In this

scenario the natural resources are the material already used, as well as preservation of future

fossil fuels consumed in energy generation.

The sustainable retrofit of LPS housing (and other uninsulated housing), has the ability to

retain and rejuvenate existing housing stock. This will reduce energy consumption and

164

improve the health of its occupants, which is collectively beneficial to the nation, as well as

the global benefits of green house gas emission savings. The typology of housing commonly

built in the 1940 – 1960’s, either by the State, or the private builders who followed the same

methodology during that time, are the largest mass-housing group in the country (Page and

Verney 2010). Their plan is simple and energy efficient in shape, having the minimum

amount of wall area possible. Their characteristics, favourable for retrofitted energy efficient

interventions of retrofitting are determined by BRANZ and Beacon Pathway as being

beneficial to fiscal and private expenditure, efficiency of resource use, and providing

environmental benefits.

Acting on the reuse of existing neighbourhoods as units of action, using energy efficient

building systems to achieve retrofits that decrease demand on energy needs to become a

national priority for sustainable development. The national-scale benefits that would accrue

from an improved housing stock, provides strong reason for incentivising retrofitting existing

uninsulated housing. This is needed to achieve the Government’s vision of being a

sustainable nation, carbon neutral, and to meet our commitments to the Kyoto Protocol.

Sustainable neighbourhoods, blended communities, and houses that owners are proud of

reflects the origin of LPSH housing and philosophy. The theory that established the

communities of our past has the ability to provide sustainable living for our future.

165

APPENDIX:

APPENDIX A – Participant Information Sheet For Architect Interviews

166

167

168

APPENDIX B - Consent Forms For Participating Architects

169

APPENDIX C - The Questionnaire - Guideline For Interviews

INTERVIEW QUESTIONS:

1. Name of Architectural practice:

2. Project Architect:

3. Architects profile and experience with retrofitting

4. The address of project (suburb only if address is confidential):

5. What year (approximately) was the house built?

6. What year were the alterations done?

7. Ownership by: private / HNZC, owner occupied / tenant.

8. Was there a set budget?

9. Was this met?

10. Is their an awareness of health problems of the occupants e.g. asthma, allergy?

11. Could you give a summary of the ‘brief’

12. What were the problems to be rectified?

13. What were the requirements to be achieved?

14. What was rated highly in the brief?

15. Was there a budget priority list when retrofitting?

16. What were the claddings, roofing, linings, and windows?

17. What materials were reused?

18. What materials were introduced as replacements / additions?

linings, claddings, finishes (carpet), etc

19. How were the windows addressed :

replacement and if so what with or

Were air seals added?

What if any change to the glazing?

What insulation was used and to what extent i.e. walls / ceilings / floor?

What requirement was aimed for - temperature to be met / R-values

specified?

20. What ventilation does the house have?

21. Was air-tightness considered?

22. What methods of removing moisture / vapour were used?

23. What benchmark was set addressing Thermal comfort and no condensation

24. Was solar gain improved?

25. Was thermal mass added?

26. Was the Client receptive to improvement of thermal comfort and the costs involved?

170

27. Were their many / any contingent items discovered?

28. Were there any contingent problems identified when house was “opened” (e.g. mould

in walls, no insulation, insulation settled....)

29. As the Architect, were you happy with the outcome, and that all possible

improvements were achieved?

30. Was there any post-renovation monitoring?

31. Have you received any feedback from the Owner / Occupier following the

renovations

171

APPENDIX D - Homestar Ratings

Rating 01 – The existing LPSH in its original condition in the era it was built

172

Rating 02 - LPSH in its current condition without intervention

173

Rating 02 – LPSH with the previous government-subsidised insulation intervention

174

Rating 04 – LPSH with the Healthy Housing Programme insulation intervention

175

Rating 05 – LPSH with proposed thermal envelope

176

LPSH with the proposed thermal envelope, located in its original sustainable

environment

177

APPENDIX D - Design Navigator - R-Value Calculation Sheets

R-value of the original uninsulated roof

178

R-value for the original uninsulated walls; previous level of government insulation

intervention and Healthy Housing Programme walls not affected by new construction works.

179

R-value for the original uninsulated floor (Exposed situation)

180

R-value for the original uninsulated floor (Sheltered situation)

181

R-value for the ceiling insulation used by the previous government insulation

intervention

182

R-value for the floor insulation used by the previous government insulation

intervention, and Healthy Housing Programme floors of the new areas of construction (exposed situation).

183

R-value for the floor insulation used by the previous government insulation

intervention, and Healthy Housing Programme floors of the new areas of construction (sheltered situation).

184

R-value for the ceiling insulation to the new areas of construction under the Healthy

Housing Programme

185

R-values for the new walls built under the Healthy Housing Programme

186

R-values for ceiling as proposed in this thesis

187

R-values for the walls as proposed in this thesis

188

R-values for floor (exposed situation) as proposed in this thesis

189

R-values for floor (sheltered situation) as proposed in this thesis

190

BIBLIOGRAPHY

(1936). New Zealand official year book: 493. (1950). The Public Papers and Addresses of Franklin D. Roosevelt New York, Harper. (2007). Irrational Incandescence. The Economist. London, Economist Newspaper Ltd. (2011). Sustainablity. Oxford English Dictionary. McCracken. J., Oxford University Press. Alington, W. H. and C. R. Knight (1966 ). Wilson N, Francis Gordon. A. H. McLintock. Wellington, Encyclopaedia of New Zealand. Amitrano, L., I. Page, et al. (2006). Market Segmentation of New Zealand’s Housing Stock. Auckland, Beacon Pathway Ltd. Bassett, M. R. (2001). Naturally Ventilated Houses In New Zealand − Simplified Air Infiltration Prediction. 2001CIB World Building Congress Wellington. Bastings, L. and R. F. Benseman (1950). "Transmition of heat through walls, ceilings and floors." New Zealand Journal of Science and Technology 31(4): 21-42. Beacon Pathway Ltd (2005). Together creating tomorrows homes. Auckland, Beacon Pathway. Beacon Pathway Ltd (2007). National Value Case for Sustainable Housing Innovations. Making the case for the national benefit to be gained by transforming the New Zealand housing stock – both new and existing - to improve sustainability., Beacon Pathway Ltd. Beacon Pathway Ltd (2008). "Neighbourhoods." from http://beaconpathway.co.nz/neighbourhoods/article/neighbourhood_survey_data_available. Bengtsson, J., R. Hargreaves, et al. (2007). Assessment of the need to adapt buildings in New Zealand to the impacts of climate change. Wellington, BRANZ. Bierre, S., P. Howden-Chapman, et al. (2007). "Institutional challenges in addressing healthy low-cost housing for all: learning from past policy." Social policy journal of NZ(30). Brien, R. M. and W. D.R. (1944). Investigation into causes and control of moulds in State houses. D. o. S. a. I. R. (DSIR). Wellington: 175-181.

Buckett, N. R. e., N. J. e. Marston, et al. (2011). Preliminary BRANZ 2010 House Condition Survey Report - Second Edition. Wellington, BRANZ. Buckwell, J. (2010). Insulation. N. e. group. Auckland. Building Industry Authority (2000). New Zealand Building Code Clause H1 Energy Efficiency. Wellington. Chapman, R., P. Howden-Chapman, et al. (2009). "Retrofitting houses with insulation: a cost–benefit analysis of a randomised community trial." Epidemiol Community Health 63(4): 271-277. Chapman, R., P. Howden-Chapman, et al. (2009). "Retrofitting houses with insulation: a cost–benefit analysis of a randomised community trial." Epidemiol Community Health 2009 63(4):

271-277.

191

Clark, S. J., M. Jones, et al. (2005). New Zealand 2005 House Condition Survey. . BRANZ. Wellington. Clist, E. L. G. (1951). Letter to Housing Construction Division. M. C. Council. Auckland. Collins, K. J. (1986). "Low indoor temperatures and morbidity in the elderly." Age and Ageing 15(4): 212-220. . Consumerbuild. "Where can moisture come from?". from http://www.consumerbuild.org.nz/publish/maintenance/interior-dampness.php#gen6. Cook, M. (2010). Healthy Housing. R. Gronert. Auckland. Cooper, E. R. (1948). Experimental Cottage - Suggested programme of investigations. DSIR. Wellington. DeGroot, H. (2009). Indoor Air Quality and Health. An Analysis of the Indoor Air Quality and Health in New Zealand’s Homes. School of Architecture and Planning. Auckland, University of

Auckland. Masters. Department of Building and Housing, Ministry for the Environment, et al. (2007). "Smarter Homes - Insulation." 2011, from http://www.smarterhomes.org.nz/design/insulation/. Department of Building Construction (2008). "Your Guide to Smarter Insulation.". Department of Housing (1947). Memo. Housing. Department of Housing Construction (Pre 1941). Schedule. Wellington. Department of Housing Construction (Pre 1941). Specification. Housing. Wellington. Design Navigator Ltd. "Home The New Zealand Window Efficiency Rating System." 2011, from http://www.design-navigator.co.nz/WERS2.html. District Inspector for Medical Officer of Health (1947). Mould in state houses. D. o. Health. Christchurch. Duany, A. and E. Plater-Zybork (1994). The Neigbourhood the District and the Corridor. The New Urbanism: Toward an Architecture of Community. P. Katz. New York. Easton, L. (2009). Papakowhai Renovations: Project Summary and Case Studies, Beacon Pathway Ltd. Easton, L. (2010). Sustainable Renovations from Auckland to Invercargill, Beacon Pathway Ltd. Efficiency and Energy Conservation Authority (2009). Energy Efficiency and Renewable Energy in New Zealand Year Six Report: March 2001 to 2007. Wellington. Energy Efficiency and Conservation Authority (2007). The New Zealand Energy Efficiency and Conservation Strategy: Making it happen. Wellington, New Zealand Government. Energy Efficiency and Conservation Authority (2009). Annual Report 2008/2009 The Energy Efficiency and Conservation Authority. Wellington. Energy Efficiency and Conservation Authority (2010). "Energywise." Ferguson, G. (1994). Building the New Zealand Dream. Palmerston North.

192

Firth, C. (1949). State Housing in New Zealand. Wellington, Ministry of Works. Fitzgerald, W., I. D. Smith, et al. (2011). Heating and cooling potential of roof space air: implications for ventilation systems. Dunedin, EECA. French, L., M. Camilleri, et al. (2006). Winter temperatures in New Zealand houses. Comfort and energy use in buildings - getting them right. Windsor, U.K., BRANZ. French, L. J., M. J. Camilleria, et al. (2007). Temperatures and heating energy in New Zealand houses from a nationally representative study—HEEP Porirua BRANZ. Furkert, F. W. (1946). Memo to E.R Cooper D. P. Laboratory. Lower Hutt. Goldau, O. and B. Roth (2007). "Proclima." Gosai, A. and J. Salinger (2006). "How is climate linked to respiratory infections in Auckland?" Water & Atmosphere 14(4). Greenaway, R. L. N. (2004). Rich Man, Poor Man, Envoronmentalist, Thief. Christchurch. Greig, A. "Indoor Air Quality and Health." Hammond, R. B. (1949). Letter in reply to J.V Jebson, District supervisor. Wellington. Hargreaves, R., M. Howell, et al. (2004). Neighbourhoods NBH1: Neighbourhood research baseline - Hedley, M. (1996). Steps towards the realisation of durability expectations for preservative-treated wood - A New Zealand perspective. 17th annual meeting of the Canadian Preservation Association in Montreal, Quebec, New Zealand Forest Research Institute, Rotorua. Hedley, M. (2010). Timber classifications. R. Gronert. Auckland. Hedley, M. and R. Wakeling (2002). Understanding the Science Behind Decay and Mould-Related Property Damage. Weathertight Construction Conference Lexis. Holt, S. and R. P. Beasley (2001). The burden of asthma in New Zealand. Wellington, Asthma and Respiratory Foundation of New Zealand (Inc.). Household Energy End-use Project (2003). Energy Use in New Zealand Households. Porirua. Housing New Zealand Corporation (2000). Background information prepared for New Zealand Institute of Architects. Housing. Housing New Zealand Corporation (2007). The Healthy Housing Outcomes Evaluation, NZ Government. Housing New Zealand Corporation (2009-2010 ). "Chairs Foreward." Retrieved May 8, 2011, 2011, from http://www.hnzc.co.nz/hnzc/web/about-us/statement-of-intent/online-version---statement-of-intent/2009-2010-statement-of-intent/chairs-foreword/chairs-foreword_home.htm. Howden-Chapman, P. (2005). "Retrofitting houses with insulation to reduce health inequalities: Aims and methods of a clustered, randomised community-based trial." Social Science & Medicine 61(12): 600-2610. Howden-Chapman, P. (2007). New Zealand research shows insulating houses results in better health. New Zealand Herald. Auckland, APN.

193

Howden-Chapman, P., L. Signal, et al. (1999). Housing and health in older people: Aging in place. Wellington, Wellington School of Medicine, University of Otago. Human Rights Commission (2010). The right to an adequate standard of living: focus on the right to housingTe tikanga whaiora rawaka: Arotahi ki te tika whai whare - Draft for discussion. Auckland. Isaacs, N. (2007). "Thermal Insulation." BUILD October/ November. Isaacs, N., M. Camilleri, et al. (2005). Energy Use in New Zealand Households: Report on the Year 9 Analysis for the Household Energy End-use Project (HEEP). Wellington. Isaacs, N., M. J. Camilleria, et al. (2006). HEEP: Study Report No. SR 155(2006) Report on the year 10 analysis for the Householod Energy End-use Project Wellington, BRANZ. Isaacs, N., A. Pollard, et al. (2002). Energy use in New Zealand households - SR115. Wellington, BRANZ. Jackson, J. (2006/2007). "In-home ventilation systems." Build. Jorens, P. G. and P. J. C. Schepens (1993). "Human Pentachlorophenol Poisoning." Human & Experimental Toxicology 12(6): 479-495. Kovesi, T., C. Zaloum, et al. (2009). "Heat recovery ventilators prevent respiratory disorderss in Inuit children." EBSCOhost Academic Search Premier 19(6): 489-499. Leardini, P. M. and T. Van Raamsdonk (2010). Design for airtightness and moisture control in New Zealand housing. SB10. Wellington, School of Architecture and Planning, University of Auckland and Pro Clima NZ Limited. Level (2010). "Designing for Climate Change." from http://www.level.org.nz/passive-design/climate-change/designing-for-climate-change/. Level (2010). "Lead Paint." from http://www.level.org.nz/health-and-safety/airborne-and-other-pollutants/lead-paint/. Lindsay, A. P., V. Hope, et al. (2002). "Meningococcal disease and meteorological conditions in Auckland, New Zealand " Australian and New Zealand Journal of Public Health 26(3): 212-

218. Lloyd, B. (2010). Peak oil in New Zealand - are we ready. Peak oil in New Zealand - are we ready. University of Auckland. Lloyd, B., T. Bishop, et al. (2007). Retrofit alternatives for State Houses in Cold Regions of New Zealand -REPORT Nº 2. Dunedin Physics Department - University of Otago. Lloyd, B. and M. Callau (2006). Monitoring Efficiency Upgrades in State Houses in southern New Zealand - A research project by the Energy Management Group. Dunedin, Physics Department - University of Otago. Lockitch, G. (1993). "Perspectives on lead toxicity." Clinical Biochemistry 26(5): 371-381. Lowe, R. (2000). "Defining and meeting the carbon constraints of the 21st century." Building Research & Information 28(3): 159-175. Lowry, S. (1989). "Housing and Health: An Introduction to Housing and Health." British Medical Journal 229: 1261-1262. Lowry, S. (1991). "Florence Nightingale." British Medical Journal 303: 838-840.

194

Lstiburek, J. (2004). Vapor Barriers and Wall Design. Westford, Massachusetts Building Science Corporation. Lstiburek, J. and T. Brennan (2001). Read this before you design, build or renovate., Asthma Regional council of New England Lynch, K. (1999). Healthful Housing. Sociology. Auckland, Massey. Master of Arts. Marsden, E. (1946). Memo - State House - Erection at Dominion Physical Laboratory. DSIR. Wellington. Mc Chesney, I. (2009). Home Ventilation Systems Assessment. Christchurch, Report to EECA. Mc Chesney, I. and L. Amitrano (2006). Sustainability options for retrofitting New Zealand houses - Energy. Auckland, Beacon Pathway Ltd. Mc Chesney, I., I. Cox-Smith, et al. (2008). Thermal Insulation in New Zealand Homes: A Status Report. Auckland, Beacon Pathway Ltd,. Metge, R. T. (1972). The House that Jack Built. Auckland, University of Auckland. Minister of Industries and Commerce (1953). Memorandum for The Prime Minister. Wellington. Ministry for the Environment (1998-2010). "Warm Homes Technical Report: Social Drivers: Phase 1: Interim Progress Report." from http://www.mfe.govt.nz/publications/energy/warm-homes-social-drivers-phase1-nov05/html/index.html. Ministry for the Environment (2007, 2011). "Greenhouse gas inventry 1990-2007." 2011, from http://www.mfe.govt.nz/publications/climate/nz-fifth-national-communication/page4.html. Ministry for the Environment (2008, 12 March, 2008). "New Zealand Sustainable Development Programme of Action." 2011, from http://www.mfe.govt.nz/issues/sustainability/programme.html. Ministry for the Environment (2010). "New Zealands greenhouse gas inventory 1990-2008." Retrieved 30 October, 2010, 2010, from http://www.mfe.govt.nz/publications/climate/greenhouse-gas-inventory-2010/page5.html. Morgan, C. (2008). "Breathing Buildings." Self Build - Extend & Renovate Ireland(Winter). Murdoch, G. (2008). "The Home Energy Rating Scheme and Home Energy Efficiency in New Zealand." National Institute of Water and Atmospheric Research. "Climate Data and Activities." 2011, from http://www.niwa.co.nz/education-and-training/schools/resources/climate. National Institute of Water and Atmospheric Research (2010). Overview of NZ Climate. New Zealand Ahead (2010). "New Zealand Ahead." from http://www.nzinstitute.org/index.php/nzahead/measures/co2e_emissions_per_capita1/. New Zealand Business Council for Sustainable Development (2009, 28 May 2009). "Extra loans key to achieving 1 million home upgrade." Retrieved April 23, 2011., from http://www.nzbcsd.org.nz/story.asp?id=998. New Zealand Government (2007). New Zealand Building Code: Clause H1 Energy Efficiency. D. o. B. a. Housing. Wellington.

195

New Zealand Government (2008). New Zealand Building Code: Clause G4 Ventilation. B. a. Housing. Wellington. New Zealand Green Building Council, Beacon Pathway, et al. (2010). "Homestar Home Performance." from http://www.homestar.org.nz/home-performance. New Zealand Ministry of Foriegn Affairs and Trade (2009). "New Zealand National Universal Periodic Review report." 2010, from http://www.mfat.govt.nz/Foreign-Relations/1-Global-Issues/Human-Rights/Universal-Periodic-Review/Final-Report/promotion-and-protection2.php#social. Oliver, W. H. (1943). The Origins and growth of the Welfare State. Page, I. and R. Verney (2010). It takes all sorts: a typology of New Zealand housing stock, BRANZ Beacon Pathway. Pollard, A. and S. McNeil (2010). Forced Air ventilation Systems. Auckland. Public Health Commission (1993). Our Health, Our Future, the State of Public Health in New Zealand. PHC. wellington. Quotable Value (2010, 5 March, 2010). "How long are houses owned before they are sold." Retrieved 26 September, 2010, 2010, from http://www.qv.co.nz/propertyinformation/KnowledgeCentre/howlongarehousesownedbeforetheyaresold05032010.htm. Rankine, J. (2004). Housing and Health in Auckland. Human Rights in New Zealand Today. Auckland, Huuman Rights Commission. Rankine, J. (2005). Housing and Health in Auckland, A Summary of Selected Research. Auckland. Rogers, T. S. (1951). Design of Insulated Buildings for Various Climates. Toledo. Franklin, D. R. and I. R. Samuel (1938-[50.). The public papers and addresses of Franklin D. Roosevelt, with a special introduction and explanatory notes by President Roosevelt. . New York, Random House. Schrader, B. (2005). We call it Home - A history of State Housing in New Zealand, Reed. Schrader, B. (2007, 31Aug,2007). "Designing communities - State housing in New Zealand." Retrieved 18August, 2010, from http://www.nzhistory.net.nz/culture/we-call-it-home/designing-communities,. Schrader, B. (2008, 31Aug, 2007). "Building families - State housing in New Zealand ". Retrieved 19 Aug, 2010, from http://www.nzhistory.net.nz/culture/we-call-it-home/building-families. Schulz, C., A. Conrad, et al. (2007). "Twenty years of the German Environmental Survey (GerES): Human biomonitoring - Temporal and spatial (West Germany/East Germany) differences in population exposure." International Journal of Hygiene and Environmental Health 210(3-4): 271-297. SmarterHomes (2008, 11 March, 2008 ). "Ventilation." Retrieved numerous, 2010, from www.smarterhomes.org.nz Smith, J. (2009). No job too big: A history of Fletcher Construction. Vol 1, 1909-40. Wellington.

196

Specialists, A. C. P. a. R., Infometrics, et al. (2007). National Value Case for Sustainable Housing Innovations. Auckland. Squires, K. (2010). History of State Houses and Fletchers involvement. R. Jordan. Auckland. Standards Council (2006). NZS 4246:2006 - New Zealand Standard Energy Efficiency – Installing Insulation in Residential Buildings. NZS 4246:2006. S. Council. Taylor, N. M. (1986). The Home Front Volume II. Official History of NZ - In The Second World War 1939-1945 - The Home Front. Wellington, Historical Publications Branch. Terra Lana Products Ltd (2011). "Terra Lana Building Insulation Products." from www.terralana.co.nz. The Asthma Foundation (2010). "Asthma." Retrieved 27 July, 2010. Timber Association (1951). Memo. Wellington. Ummenhofer, C. C. and M. H. England (2007). " Interannual Extremes in New Zealand Precipitation Linked to Modes of Southern Hemisphere Climate Variability. ." Climate 20:

5418–5440. United Nations Framework Convention on Climate Change (2008). "Annual greenhouse gas (GHG) emissions for New Zealand, in Gg CO2 equivalent ". 2011, from http://unfccc.int/di/DetailedByParty/Event.do?event=go. Wells, J. L. (1944). The history of State House construction in New Zealand. School of Architecture. Auckland, University of Auckland. Weston, D. W. and S. W. P. Jones (1959). Brochure - The Housing Division of the Ministry of Works. Wellington. Wilkinson, P., K. R. Smith, et al. (2007). "Energy, energy efficiency, and the built environment." The Lancet 370(9593): 1175-1187. Wilson, F. G. (1953). House Design - Revised Type. M. o. Works. Wellington. World Health Organisation (1989). Health principles of housing. Geneva. World Health Organisation (2009). Guidelines for Indoor Air Quality: Dampness and Mould. Copenhagen, World Health Organization Regional Office for Europe. Zhang, D. (2009). Energy Efficiency Upgrade of Existing Homes in Auckland – A Housing Typology Analysis and Mapping. School of Architecture and Planning. Auckland, University of Auckland. Masters