renewable natural gas long term application€¦ · bloom energy server –modular and scalable...
TRANSCRIPT
Renewable Natural GasLong Term Application
October 2016
Page 2 | Confidential
Agenda
How Bloom meets Sustainability Goals
Bloom’s Clientele Base
Blue Print to Long Term RNG Applications
Bloom Energy Server – Modular and
Scalable
Page 3 | Confidential
Fuel Cell25 W
Module50 kW
System200-250 kW
Solution200 kW to MW’s
Outputs
• AC or DC power
• Low/No CO2
• No NOx or SOx
Runs on
natural gas
or biogas
Converts fuel to electricity
• Without combustion
• At 60%+ electrical efficiency
• Highly reliable
Page 4 | Confidential
CO2 Emissions Compared (lbs/MWh) Water Usage
Compared
A 1MW installation will reduce at least 1.6 million pounds of CO2 emissions and millions of gallons of water consumption each year
*Excludes hydroelectric power, which has additional environmental impacts.
Generation Type Gallons per MWh
Bloom Energy Server 0
Combined Cycle Nat Gas Plant
Consumption (cooling tower)205
Coal Power Plant Withdrawal
(open loop cooling)36,350
Source CARB http://www.arb.ca.gov/cc/scopingplan/document/appendices_volume2.pdf EIA Average Heat Rates, 2012
http://www.eia.gov/electricity/annual/html/epa_08_02.html; Capstone Technical Reference http://www.multigen.com.au/wp-
content/themes/multigen/docs/410065B_Emissions_Tech_Ref.pdf
Source: Union of Concerned Scientists, Freshwater Use by U.S. Power Plants, 2011, Energy-Water Database,
http://www.ucsusa.org/clean_energy/our-energy-choices/energy-and-water-use/freshwater-use-by-us-power-plants.html
and NREL, Life cycle water use for electricity generation, 2013, http://iopscience.iop.org/1748-
9326/8/1/015031/pdf/1748-9326_8_1_015031.pdf
Sustainability Impact in California
1 MW Bloom 1 MW Solar
Footprint
Annual Generation Over 8 GWh Less than 2 GWh
Load Profile
Annual CO2
Reduction*~2.3 million lbs ~1.8 million lbs
How Does 1MW of Bloom Compare to
1MW of Solar?
Example: Manufacturing plant with 1.5 MW average load
Page 5 | Confidential
*Compared to non-baseload avg. of CA & Northeast
70% offset
13% offset
200 MW Deployed for Blue Chip
Customers
Page 6 | Confidential
100+ Customers, 14 Diverse Industries, 400+ Projects
RNG Long Term Application
Page 7 | Confidential
Decision Matrix: 1. Economic
2. Reliability
3. Sustainability
Delivered Supply $: $10.00 MMBtu
Term: 5 to 20 years
Volumes: 93% Load Factor
Commitment Level: Bilateral Firm Obligation
Contract Type: NAESB with Special Provisions
Contract Parties: RNG Developer with Fuel Cell Customer
Lead Time: 18 to 24 months prior to pipeline injection
Delivery Type: FERC Method - bundled Environmental Attributes with molecule
EPA Method - contractually transfer Environmental Attributes to Delivery Point
Developer Vetting EPC Ready/ Finance Secured/ Feedstock Contracts/ Permits
Page 8 | Confidential
Thank you!
Todd M. Little
Director, Gas Management
208-375-1483