replacement of berkeley bridge and martin street …
TRANSCRIPT
FINALSECTION 4(f) STATEMENT
ANDSECTION 106 PRELIMINARY
CASE REPORT
7
REPLACEMENT OF THE
BERKELEY BRIDGE
AND THE
MARTIN STREET CANAL BRIDGELINCOLN AND CUMBERLAND, RHODE ISLAND
STATE OF RHODE ISLANDDEPARTMENT OF TRANSPORTATION
DIVISION OF PUBLIC WORKS
FEDERAL AID PROJECT NO. BRM-J012(001)
GORDON R. ARCHIBALD INC.
PROFESSIONAL ENGINEERS
PAWTUCKET, R.I.
FEBRUARY. 1088
FINAT,
SECTION 4(f) STATEMENT
AND
SECTION 106 PRELIMINARY
CASE REPORT
REPLACEMENT OF THE. BERKELEY BRIDGE (NO. 769)
AND THE
MARTIN STREET CANAL BRIDGE (NO. 774)
IN
LINCOLN AND CUMBERLAND, RHODE ISLAND
FEDERAL HIGHWAY ADMINISTRATION
RHODE ISLAND DEPARTMENT OF TRANSPORTATION
FEDERAL- AID PROJECT NO. BRM-J012( 001 )
SUBMITTED PURSUANT TO
49 U.S.C. 303; 16 U.S.C. 470(f);
Date J. Gil Director RIDOTJ
- V- E7 Date Jordon G. 'Hoxie ' /
Div. Administrator FHWA
U.S. Department of Transportation Federal Highway Administration
Section 4(f) Determination
Replacement of Berkeley Bridge and Martin Street Bridge Over the
Blackstone River and Canal Lincoln-Cumberland, Rhode Island Federal-aid Project BRM-J012(001)
Pursuantto 49 USC 303
It has been determined that there 1s no feasible and prudent alternative to the use of land from the Paul Ronci Memorial Park for a proposed Federal-aid highway project. The proposed action Includes all possible planning to minimize harm to the Section 4(f) property resulting from the use of such land.
This determination follows consideration of all the Information contained in the "Final Section 4(f) Statement/Section 106 Preliminary Case Report" dated February 1988 for the subject project. The report provides detailed information about the project, the use of Section 4(f) lands, alternatives to avoid the use of such land, coordination with other involved agencies, and proposed plans to minimize harm. The information from the report is hereby incorporated Into this determination.
Approved:
Date: March 23, 1988
FINAL
SECTION 4(f) STATEMENT
AND
SECTION 106 PRELIMINARY CASE REPORT
REPLACEMENT OF THE BERKELEY BRIDGE AND THE
MARTIN STREET CANAL BRIDGE
LINCOLN AND CUMBERLAND, RHODE ISLAND
TABLE OF CONTENTS
PART NO. PAGE NO.
I. CLARIFICATION OF TERMS
A. Introduction 1 B. The Blackstone Canal 1 C. The Blackstone River Park 2 D. The Paul Ronci Memorial Park 3 E. Meaning of Terms 5
II. PURPOSE
A. Combined Document 6 B. Section 4(f) Statement 6 C. Section 106 Preliminary Case Report 7
III. DESCRIPTION OF PROPOSED ACTION
A. Location 9 B. Project History 9 C. The Public Highway 10 D. Alternative Solutions 16 E. Evaluation of Alternative Solutions 16 F. Comparison of Replacement Alternatives 26 G. Conclusion of "Supporting Documentation"
Report 28 H. Recommended Replacement Alternative 28
back and forth along the Canal. According to the R.I. Historical
Preservation Commission, this tow path forms the foundation of
the present utility maintenance road that runs along the canal
embankment.
The hydraulic drop between Worcester and Providence is
about 450 feet. Consequently, granite-walled lock structures
were constructed at critical points along the Canal to lift and
lower the barges.
It happens that the section of the Blackstone Canal that
still retains many of its original features is located between
Front Street in Lonsdale and the Ashton Dam, a distance of some
four miles. (See PLATE II.) The Ashton Dam is located just south
of the bridge that carries Interstate Route 1-295 over the Black
stone River. The bridge replacement project which is the subject
of this report is located one mile downstream of the Ashton Dam.
C. The Blackstone River Park. The Rhode Island Department
of Environmental Management is now in the planning stages of the
proposed Blackstone River Park. .The park will descend along the
Branch River in Slatersville to the Blackstone River. It will
pass through Woonsocket and then proceed downstream through
Manville and Albion to Ashton where the river and the watered
portion of the Blackstone Canal parallel each other as far as
the Lonsdale Mill complex in Lincoln. From this point the main
stream of the park will descend the Blackstone River to the falls
in downtown Pawtucket, just south of Slater's Mill. The park
will feature several small passive recreation areas at various
locations along the river, all connected by hiking trails,
bicycle paths, and bridal paths. "Put-in" and "take-out"
facilities for canoeing will be provided along with portages at
selected locations.
One such bikepath is presently in the planning stages
within the R.I. Department of Transportation. The Blackstone
River Bikeway [F.A.P. No. MBW-6666(005)] has been described in a
report entitled Blackstone River Bikeway Planning Study and Pre
liminary Design Final Report, December, 1987. The projected
route through the area of the Berkeley and Martin Street Bridges
project follows the existing utility maintenance road that runs
along the canal embankment.
D. The Paul Ronci Memorial Park is a term used repeatedly in
subsequent portions of this report. It is also a term that has
two connotations.
From an historical viewpoint, the Paul Ronci Memorial
Park is an existing riverfront park owned and operated by the
Rhode Island Department of Environmental Management. It consists
of the Blackstone Canal, itself, .and a fifteen foot wide, strip
along both banks of the Canal. It extends from Front Street in
Lonsdale north to the Ashton Dam, a distance of approximately
four miles. These limits are identical to those which describe
that portion of the old Blackstone .Canal that still retains many
of its original features. The area of the Paul Ronci Memorial
Park is approximately 40 acres. The boundary of the Paul Ronci
Memorial Park within the area of this project is highlighted in
"yellow" on PLATE III of this report.
The Paul Ronci Memorial Park is a passive recreational
area. In the words of a senior planning official, it is "a place
where people walk." At present there is no bicycle use, and
pedestrian use is light and sporadic. The proposed bridge
replacement project will in no way inhibit the park's present use
by occasional pedestrians. Additional discussion may be found on
pages 31 and 33 of this report. At some future date, however,
the existing Paul Ronci Memorial Park will be completely
incorporated into the much larger Blackstone River Park described
in Para. C, above.
The second connotation of the "Paul Ronci Memorial Park"
is that it constitutes the northern segment of the Blackstone
Canal Historic District. This archeological property was entered
in the National Register of Historic Places on December 18, 1970.
APPENDIX "A" contains the following information regarding the
status of the Paul Ronci Memorial Park as a National Register
property:
Exhibit 1
The Nomination Forms prepared by the R.I. Historical Preservation Commission on October 2, 1970.
Exhibit 2
The December 18, 1970 letter from the U.S. Department of the interior advising the State Historic Preservation Officer that the Paul Ronci Memorial Park had been entered in the National Register of Historic Places.
Exhibit 3
The actual entry for the Paul Ronci Memorial Park as it appears in the National Register of Historic Places publication.
There is also a southern segment of the Blackstone Canal
Historic District. It extends from Front Street in Lonsdale,
Lincoln, southerly to Promenade and Steeple Streets in
Providence. This section was nominated by the Rhode Island
Historical Preservation Commission for inclusion in the National
Register of Historic Places on July 28, 1970.
E. Meaning of Terms. Depending on the context in which it
appears the phrase "Paul Ronci Memorial Park" will mean either;
o An existing riverfront park located in the Town of Lincoln
or;
o The northern segment of the Blackstone Canal Historic District; an archeological property listed in the National Register of Historic Places.
II. PURPOSE
A. Combined Document. This report combines a Section 4(f)
Statement with a Section 106 Preliminary Case Report and
Memorandum of Agreement. The regulations for Section 106 of the
National Historic Preservation Act of 1966 and those for Section
4(f) of the Department of Transportation Act of 1966 overlap to
the extent that a joint presentation is warranted. The objec
tives of the Section 4(f) Evaluation and the Section 106 Case
Report are discussed separately below. The executed Memorandum
of Agreement appears in Appendix "C".
Both sets of regulations require a description of the pro
ject, a description of sites included on the National Register of
Historic Places, identification of mitigation measures and a
discussion of coordination activities. The two sets of regula
tions differ in the description and interpretation of use or
effects to the cultural resource under consideration.
B. Section 4(f) Statement. Section 4(f) of the Department
of Transportation Act of 1966 was enacted by Congress for the
purpose of preserving the Nation's natural beauty and cultural
heritage. Public Law 89-670 outlines Section 4(f) as follows:
The Secretary shall cooperate and consult with
the Secretaries of the Interior, Housing and
Urban Development, and Agriculture, and with
the States in developing transportation plans
and programs that include measures to maintain
or enhance the natural beauty of the lands
traversed. After the effective date of this
Act, the Secretary shall not approve any pro
gram or project which requires the use of any
land from a public park, recreation area,
wildlife and waterfowl refuge, or historic
site unless (1) there is no feasible or pru
dent alternative to the use of such land, and
(2) such program includes all possible plan
ning to minimize harm to such park,
recreational area, wildlife and waterfowl
refuge, or historic site resulting from such
use.
The proposed bridge replacement project will require lands
presently used as a riverfront park by the Rhode Island
Department of Environmental Management (RIDEM), i.e., the "Paul
Ronci Memorial Park." The project will also affect the northern
segment of the Blackstone Canal Historic District, again, the
"Paul Ronci Memorial Park." It is the purpose of this report to
present evidence and documentation that the Section 4(f)
requirements have been satisfied.
C. Section 106 Preliminary Case Report. Section 106 of the
National Historic Preservation Act requires that federal agencies
with direct or indirect jurisdiction over a federally funded
undertaking afford the Advisory Council on Historic Preservation
a reasonable opportunity for comment on those undertakings that
affect properties on, or eligible for inclusion on, the National
Register of Historic Places, and to take those comments into
account. This should occur prior to the agency's approval of any
such undertaking. This Preliminary Case Report and draft
Memorandum of Agreement will provide such opportunity pursuant to
Title 36 CFR Part 800.
The Federal Highway Administration (FHWA), in consultation
with the R.I. Department of Transportation (RIDOT) and the R.I.
Historical Preservation Commission (RIHPC), has determined that
the proposed undertaking will have an "adverse effect" on the
northern segment of the Blackstone Canal Historic District.
Accordingly, the Federal Highway Administration, the Rhode
Island Department of Transportation and the Rhode Island
Historical Preservation Commission, in consultation, have
determined that the project requires consideration under Section
106 of the National Historic Preservation Act.
III. DESCRIPTION OF PROPOSED ACTION.
A. Location. The Berkeley Bridge and the Martin Street
Canal Bridge are located on the Blackstone River in the northeast
corner of Rhode Island approximately seven miles north of
Providence. The bridges connect the Towns of Lincoln and
Cumberland. (PLATE I.) On the U.S.G.S. Topographic Maps, the
project is located on the Pawtucket, Rhode Island Quadrangle.
(PLATE II).
B. Project History. The Federal-Aid Highway Act of 1970
requires the systematic evaluation and subsequent replacement of
old, worn out, damaged and substandard highway bridges throughout
the United States. The Rhode Island Department of Transportation
has surveyed the highway bridges within its jurisdiction and has
prepared a priority list of those structures which should be
replaced in the near future. The two span Berkeley Bridge (No.
769) over the Blackstone River and the single span Martin Street
Canal Bridge (No. 774) have been determined to be both
functionally obsolete and structurally deficient. Accordingly,
they both have been designated for early replacement. The
determination of obsolescence and deficiency is addressed in
particular detail in Para. C, "The Public Highway", of this
chapter.
Categorical Exclusion. On March 27, 1986 the FHWA accepted
the Department's request that this project be designated as a
Categorical Exclusion. The basis for this action was the
determination that the effects of the feasible bridge replacement
options on the total environment were either insignificant or
non-existent. Paragraphs E, and F of Part III present a
complete discussion of this subject.
FAST Program. On September 18, 1986, the Department
requested that this project be incorporated into the FAST Program
in order to accelerate its design and implementation. The
Department stated that the project enjoyed a high level of public
support and a low level of controversy. Early coordination in
accordance with Section 106 of the National Historic Preservation
Act of 1966 with the R.I. Historic Preservation Commission
resulted in a project finding of adverse effect on the Blackstone
Canal Historic District. However, the Commission has agreed with
the Department on measures designed to mitigate the adverse
effect. With respect to archeological resources, a Phase I
Survey has been completed. That survey did not identify any
archeological resources other than the Blackstone Canal itself.
Given the above, the Department indicated in their request
that the project would be significantly expedited by placing it
in the FAST Program since the design of the project could proceed
concurrently with the processing of the appropriate Section 106
and 4(f) documentation. On October 15, 1986 the FHWA approved
the request that the project be placed on the FAST Program.
Final design is now proceeding.
C. The Public Highway.
Classification. The project area is contained within
the Providence-Warwick-Pawtucket Urbanized Area as defined in
Technical Page 100, Highway Functional Classification System for
10
the State of Rhode Island 1995-2005, published by the Rhode
Island Statewide Planning Program. In reference to that same
document, the project roadway is functionally classified as an
Urban Collector Street.
The Bridges. The Berkeley Bridge (No. 769) is a two-
span arrangement with a pier located at midstream of the
Blackstone River. Originally both spans were timber bow string
trusses, each approximately 80 feet in length. Several years ago
the Department replaced the easterly truss with a steel girder,
composite concrete deck highway bridge. The westerly timber
truss has remained in service to the present day. Visual
inspection and a review of the Department's Bridge Inspection
Reports revealed the following:
1. The eighteen foot roadway width is inadequate for two-way vehicular traffic according to current AASHTO standards.
2. The timber bridge rail fails to meet current structural and geometric standards of AASHTO.
3. The timber deck and curbing show evidence of rot.
4. The top timber truss chords (compression members) at the southeast and northwest portals are badly shaked. The bottom chord of the south truss is bent. The inspector noted that these "ITEMS INDICATE THAT THE BRIDGE IS IN A MODE OF FAILURE".
5. Minor damage to the substructure was noted due to concrete spalling, erosion and scour.
6. Load Rating: The bridge is posted for 3 tons. A sign nearby reads, "CLOSED TO TRUCK TRAFFIC".
The Martin Street Canal Bridge (No. 774) is a gerry
built arrangement of previously used steel plate girders with
precast concrete planks placed diagonally across the top flanges.
11
Timber curbing and light angle-iron bridge rail are provided.
Visual inspection and a review of the Department's Bridge
Inspection Report revealed the following:
1. The eighteen-foot roadway is inadequate.
2. The angle-iron bridge rail, together with its connection to the plate girders, fails to meet structural standards of AASHTO.
3. The wearing surface is severely cracked.
4. Bridge bearings show heavy rusting.
5. Plate girders show heavy rusting on bottom flanges and at bottom of webs at the bearings.
6. Both abutments exhibit severe spalling at bases; cavities are approximately 8-feet long; 6-inches deep; and 6-inches high.
7. Severe embankment erosion is evident at the abutments.
8. Load Rating: The bridge is posted for 3 tons.
The Roadways
Lincoln. The roadway approach in Lincoln, to the west
of the Canal, has some rather extreme horizontal and vertical
geometry. Martin Street descends from its intersection with
Lower River Road at grades ranging up to 6 percent. As it
approaches the canal, the alignment follows a horizontal curve
with approximately a 200-foot radius and no superelevation. The
pavement width averages about 20 feet. These roadways, and, more
specifically, the intersection of these roadways, are illustrated
on the following page. They may be described as the intersection
of two "S-curves". Lower River Road comprises the north-south leg
of the intersection and follows the less severe of the two com
pound reverse curves. Cullen Hill Road, and its extension to
the river, Martin Street, is the steeper and more severe of the
12
\ \
BLACKSTONE CANAL
^-EXISTING GRAVEL ROAD
BLACKSTONE RIVER
EXISTING ROADWAY APPROACHES
IN LINCOLN
13
S-curves. The tangent of Martin Street as it approaches the
intersection and the tangent of the southerly leg of Lower River
Road form an acute angle of approximately 9-degrees. More
over, the tangents of the southerly leg and the northerly leg of
Lower River Road are virtually parallel. This geometry, combined
with the indicated steep grades of three of the four legs of the
intersection, produce a highly irregular and potentially
dangerous configuration.
A review of the above-described approach roadways in Lincoln
with respect to both the American Association of State Highway &
Transportation Officials' (AASHTO) Policy on Geometric Design of
Highways and Streets and local subdivision standards indicates
the existence of the following problems:
1. Intersection Angle. The 9-degree acute angle between the tangent of Martin Street and the tangent of the southerly leg of Lower River Road clearly does not meet AASHTO's recommended minimum of 60-degrees.
2. Intersection Sight Distance. The stopping sight distance for westbound Martin Street/Cullen Hill Road with respect to northbound Lower River Road does not meet AASHTO's criteria.
3. Turning Radius. For the movement northbound Lower River Road to eastbound Martin Street, the turning radius is inadequate for any vehicle other than a passenger vehicle. Since Martin Street is classified as an Urban Collector Street, turning radii should accomodate at least a single unit vehicle.
4. Radius of Martin Street. The 200-foot radius of Martin Street does not meet AASHTO criteria for the 30 mph design speed.
5. Sharp Curve/Descending Grade. From the intersection with Lower River Road, Martin Street descends along its 200 foot radius, with no superelevation, at grades approaching 6%. This unsafe condition runs counter to AASHTO's caveat to avoid sharp horizontal curves on steep downgrades.
14
6. Pavement Width. As noted above, the average pavement width along Martin Street averages about 20 feet. This width is significantly less than the 30 feet recommended by local subdivision standards.
Across the River and Canal. The roadway alignment across
the Blackstone River and Canal consists of an unremarkable pair
of tangents that intersect at a deflection angle of approximately
9-degrees. The profile of Martin Street in this area is nearly
level, varying only four to five tenths of a foot (above Elev.
79.0) along the entire crossing.
On the bridges, the roadway width is 18 feet. Between the
bridges, the roadway crosses at-grade with the canal embankment.
The Blackstone Valley Electric Company (BVE) maintains a service
road which runs north/south along this embankment between the
canal and the river.
Cumberland. The roadway alignment along the Cumberland
approach consists of two tangents that intersect at a deflection
angle of approximately 10-degrees. There is one short section
(about 100 feet) adjacent to the river bridge where the grade is
about 6.6 percent. The remainder of this roadway approach has
good horizontal and vertical alignment. The roadway width in
Cumberland varies from 20 to 24 feet.
Summary of Condition. The preceeding paragraphs present
a detailed and explicit description of the present condition of
this river crossing and its highway approaches. Both the
Berkeley Bridge and the Martin Street Canal Bridge are shown to
have inadequate width, substandard bridge railing, and major
structural problems. Chief among the latter is the deteriorating
condition of the top and bottom chords of the westerly trusses of
15
the Berkeley Bridge. The most recent bridge inspection report
indicates that this deterioration has placed the bridge "IN A
MODE OF FAILURE". Both bridges are posted for a maximum load of
3 tons; which posting constitutes a severe restriction to
vehicular travel.
The highway approach in Lincoln from Lower River Road is shown
to possess severe and substantial constraints in terms of
geometry, grade, sight distance, turning radii and centerline
radius.
The above summary clearly demonstrates that the existing
Berkeley-Martin Street Bridge, along with its highway approach in
Lincoln, comprises a substandard, out-dated, and severely
deteriorating transportation facility. It represents, therefore,
a present and future hazard to safe vehicular transportation.
D. Alternative Solutions. The intent of this
Federally-assisted undertaking is to replace the existing two-
span Berkeley Bridge and the single span Martin Street Canal
Bridge with new structures. In this regard, the following three
alternatives have been considered:
1. No-Build Alternative
2. Existing Alignment Alternative
3. New Alignment Alternative
E. Evaluation of Alternative Solutions.
1. No-Build Alternative. This alternative implies
periodic routine maintenance for the two existing bridges and
approach roadways. No provision of improvements of a substantive
nature is contemplated.
16
However, routine maintenance cannot resolve the fact that
the two bridges are too narrow with respect to both pavement and
sidewalk width. Neither can routine maintenance remedy the
structural deficiency of the Martin Street Canal Bridge and the
old timber truss portion of the Berkeley Bridge. Both bridges
have substandard and, therefore, unsafe bridge rail details.
Routine maintenance cannot alter the fact that both bridges are
posted for the severly restrictive 3 ton load limitation. Con
sequently, adoption of this alternative would only allow the
existing problems with these bridges to perpetuate without
addressing in any meaningful way the solutions to these problems.
Likewise, with respect to the highway approach in Lincoln,
and including the intersection of Martin Street/Cullen Hill Road
with Lower River Road, routine maintenance could not address any
of the vexing problems noted above that are associated with
geometry, turning radius, sight distance, centerline radius and
steep grades. All these problems would remain indefinitely
unresolved. For the reasons noted above, the "no-build" alterna
tive is not considered to be a feasible approach for resolving
the multiple and serious problems associated with this crossing
of the Blackstone River.
2. Prior Evaluation of Replacement Alternatives. During
the winter of 1985-86 the Department conducted detailed evalu
ation of the two replacement alternatives with respect to social,
economic, engineering, and natural environmental considerations.
On March 11, 1986 the Department submitted a report to the FHWA
entitled, "Supporting Documentation for a Categorical Exclusion
Determination." This report addressed the following:
17
Social Impacts.
o Displacement of families or businesses.
o Effects on community cohesion.
o Accessibility of facilities and services.
Economic Impacts.
o Removal of property from municipal tax rolls.
o Employment, income and business activity.
o Residential activity.
o Effects on property taxes.
o Regional and community plans.
Natural Environment
o Vegetation,
o Fish and wildlife,
o Wetlands,
o Water quality.
Engineering Considerations.
o Cost estimates; construction and right-of-way,
o Traffic service.
Horizontal and vertical geometries,
o Bridge configurations.
The evaluation of each of the replacement alternatives with
respect to the above factors will be summarized in the following
paragraphs.
3. Existing Alignment Alternative. The concept of this
18
alternative is to replace the bridges in essentially their
existing location while improving the highway approaches to more
closely approach minimum AASHTO criteria. Existing at-grade
access to the BVE maintenance road will be maintained between the
two bridges.
Vertically, the design profile contains a 5.5 percent grade
as it descends from Lower River Road toward the canal, and a
short section of descending 5 percent grade to the east of the
river.
This alternative provides for two new bridges. The new
Berkeley Bridge would consist of two spans, each approximately 75
feet in length. The center pier of this arrangement would be
located in the middle of the Blackstone River. The new Martin
Street Bridge would be a single span of approximately 65 feet in
length. It would be located along a horizontal curve having a
280 foot radius. The thickness of the pavement surface would
vary to achieve transition into and out of superelevation.
Access to the canal embankment would be provided in the same
manner as presently exists.
Social Impacts. This alternative is not expected to have
any long-term effect. There will be no residential or commercial
property displacements. There will be no community cohe
sion impacts because the land within the project limits is
undeveloped and travel patterns will not be changed in any way.
Finally, there are no public facilities in the vicinity of the
project whose access will be affected.
The only negative, short-term social impact will be the
disruption of local traffic patterns during construction.
19
Traffic detours will be required. The detour route would utilize
the George Washington Highway (Route 116) river crossing located
approximately three-quarters of a mile north of the Berkeley
crossing. Since the river forms the Town line, this detour would
not affect municipal services such as school bus transportation
or fire and police protection.
Economic Impacts. With respect to economic impacts, the
improvement of the horizontal alignment in Lincoln will require
some right-of-way acquisition. However, the extent of this
acquisition is very limited, and it is not expected that property
taxes will be affected to any significant extent.
This alternative is not expected to have any significant
effect on any of the other economic factors listed on Page 18 of
this report. Region-wide impacts on employment, business
activity, residential activity, or property taxes are not
expected to occur because of both the relatively limited scope of
this project . and the fact that travel patterns will not be
affected in any way. Finally, since land within the project
limits consists of flood plain and is, therefore, undevelopable,
there will be no impacts to future local development.
Environmental Impacts. An environmental review was
conducted for this Existing Alignment Alternative by the consul
tant firm, Ecological Associates, Inc. Observations made during
that review are reported below.
Vegetation. The vegetation in the project area consists
of mixed hardwoods and is typical of the vegetation all along the
river. The Existing Alignment Alternative would remove approxi
20
mately 5/8ths of an acre of vegetation, primarily from the
forested area along the side of the existing roadway. Approxi
mately 90-percent of this area will be reseeded under this
option.
The field review revealed no unique or unusual plant
species that would be affected.
Fish and Wildlife. There is little concern regarding
potential effects on fish life because of the fact that the
Blackstone River is not a high quality fish habitat. This alter
native should not result in significant impacts in this category.
The wildlife habitat affected by the Existing Alignment
Alternative will be limited to side-of-road areas. Impacts are
expected to be negligible.
Wetlands. Technically, the river itself along with the
land within 200 feet on either side are considered wetlands and
are protected under the Rhode Island Freshwater Wetlands Act.
The field review revealed no other wetlands in the project area,
such as swamps, bogs, etc. A formal permit application will have
to be submitted to the Rhode Island Department of Environmental
Management (RIDEM) under this alternative. However, no unusual
or significant problems are anticipated in this regard. This
alternative would also require a Section 404 permit from the Army
Corps of Engineers since some filling within the 100-year flood
plain is required. The required flood plain compensation would
be provided.
Water Quality. This alternative should not have any
long-term effect on the water quality of the river when compared
to present conditions. This is due to the fact that there will
21
still be only one, 2-lane roadway crossing the river in either
case. The major water quality concern has to do with temporary
construction impacts. Proper erosion control techniques applied
prior to and during construction operations will prevent any
significant degradation of the river water quality.
Cultural Impact. The Existing Alignment Alternative uses a
total of 2,600 square feet (0.06th acre) of the Canal shoreline
within the Paul Ronci Memorial Park. This use is necessitated by
the increased width of the bridge cross section and the increase
in the centerline radius of Martin Street, west of the Canal, to
280 feet. This is 0.15% of the total park acreage.
Engineering Considerations.
Traffic Service. The typical cross section for the
Existing Alignment Alternative is adequate for the design year
(2005) traffic projection of 2500 vehicles per day. The main
problem with this alternative from the standpoint of traffic
service is the intersection of Martin Street/Cullen Hill Road
with Lower River Road on the Lincoln side of the river. On pages
12 and 14 of this report the problems associated with this
intersection are set forth in some detail. These problems
certainly suggest the potential for future accidents even though
statewide accident statistics for 1979-1983 indicate no recorded
accidents at this location for the five-year period studied.
Under this alternative only minor improvements can be
implemented at this difficult intersection. Thus, the existing
adverse and unsafe conditions will remain indefinitely.
Cost Estimates. Estimates for the Existing Alignment
22
Alternative were prepared for both construction and right-of-way
acquisition costs. The total area to be acquired from the Town
of Lincoln and private interests for this alternative is approxi
mately O.5 acre. The construction costs are based on the latest
RIDOT Weighted Average Prices. The ROW acquistion costs are
based on an average value of $15,000 per acre for the undeveloped
land in the industrial zone, and $1.00 per square foot for
residential properties. No structures are involved. The cost
estimate for the Existing Alignment Alternative follows:
Construction
o Highway: $ 165,000
o Bridge: 950,000
o Subtotal: 1,115,000
Right-of-Way
o Land Acquisition: 7,600
Total: $1,122,600
4. New Alignment Alternative. The intent of this alterna
tive is to replace the bridges on a new alignment that substan
tially improves its horizontal geometry and profile. A signifi
cant advantage of this alternative is that it permits the
improvement of the Martin Street, Lower River Road, Cullen Hill
Road intersection from its current difficult configuration to a
standard, four-way design.
Vertically, the terrain dictates that the new roadway
must pass over the Blackstone Canal to achieve acceptable grades.
Under that concept, the design profile includes a 0.6 percent
23
grade to the west of the canal and a 4.8 percent grade east of
the river.
This alternative would provide one bridge of approximately
360 feet in length. The bridge would consist of two equal
continuous spans, with a center pier located near the west bank
of the river, just off the embankment that forms the Blackstone
Canal.
Early coordination with the Blackstone Valley Electric
Company and the Town of Lincoln Department of Public Works
(DPW) indicated the necessity of maintaining access to the canal
embankment through the Martin Street Bridge. The BVE maintains
power lines along this area and the Town's DPW requires access
after periods of high river flow for maintenance and clean-up
purposes.
To accommodate these requirements for vehicular access to
the canal embankment, this alternative includes the retention and
modification of the existing Martin Street Bridge along with its
westerly approach from Lower River Road. The Berkeley Bridge
will be removed, and its easterly approach will be returned to a
natural setting.
In order to provide the necessary vertical clearance for
vehicles under the new bridge, this alternative includes the
construction of a short section of access road along the lower
elevations of the canal embankment.
Social Impacts. Like the Existing Alignment Alternative,
the New Alignment Alternative is not expected to have any long
term social effects. However, there is an advantage for this
option in that the existing bridges and approaches may continue
24
to serve local traffic during construction operations. Thus, the
short-terra negative impact of disruption of traffic would be
eliminated.
Economic Impact. The New Alignment Alternative would
require limited right-of-way acquistion. Thus, removal of a
small amount of property from the tax rolls would take place.
Three properties in Lincoln and one property in Cumberland are
affected. The tax loss to Cumberland has been estimated at $244.
The three properties in Lincoln are currently tax exempt so there
would be no loss of taxes in that town.
With respect to the other categories of economic impact
listed on Page 18 of this report, this alternative, like the
initial option, is not expected to have any significant effect.
Environmental Impact. Environmental concerns were reviewed
for the New Alignment Alternative on the same basis as that
discussed above for the Existing Alignment Alternative. The
results of this review were virtually the same, i.e., the impact
of this option on the natural environment is extremely limited to
the point where it may be considered insignificant.
Cultural Impact. The New Alignment Alternative uses a
total of 2,900 square feet (0.0.7th acre) of the Canal's westerly
shoreline within the Paul Ronci Memorial Park. This use is
necessitated by the presence of the new West Abutment and its
associated embankment. (See PLATE III). This is 0.17% of the
total park acreage.
Engineering Consideration.
Traffic Service. Like the first option considered, this
25
alternative provides a roadway cross section that is adequate for
the projected year 2005 traffic volumes. However, there is one
positive advantage to this option and it concerns the present
intersection of Lower River Road, Cullen Hill Road and Martin
Street. As indicated earlier in this discussion, this particular
intersection is highly unusual and difficult to negotiate. Under
this alternative it will be possible to re-align the local
roadways such that a conventional 4-way intersection may be
provided.
Cost Estimates. Estimates were prepared for the New
Alignment Alternative on the same basis as they were compiled for
the initial option. The total area to be acquired from the Town
of Lincoln and private interests is approximately 1.1 acres.
These estimates follow:
Construction.
o Highway: $ 195,000
o Bridge: 1,340,000
o Subtotal: 1,535,000
Right-of-Way.
o Land Acquisition: 16,500
Total: $1,551,500
F. Comparison of the Replacement Alternatives. The
following table presents a comparison of relevent factors for
each of the replacement alternatives.
26
Existing Alignment New Alignment Factors Alternative Alternative
Social Impact
Short Term Significant Insignificant Long Term None None
Economic Impact
Land Acquisition 0.5 Acre 1.1 Acre Tax Loss Negligible $ 224
Environmental Impact (Natural) Insignificant Insignificant
Cultural Impact
Archeological None None Use of 4(f) Land 0.06 Acre 0.07 Acre
Engineering
Traffic/Main Alignment Satisfactory Satisfactory Traffic/Lincoln Approach Problems remain Problems resolved
Cost Estimate $ 1,122,600. $ 1,551,500.
From the above comparisons it is clear that there is
virtually no difference between the replacement alternatives in
the areas of Economic, Environmental, and Cultural Impacts.
There is a single advantage associated with the Existing
Alignment Alternative and that is an indicated savings of
approximately $430,000 in estimated construction costs.
There are two advantages associated with the New Alignment
Alternative. The first is the absence of any disruption to local
traffic during construction operations. The second, and more
important advantage, is the complete resolution of the multiple
problems that exist at the intersection of Martin Street/Cullen
Hill Road with Lower River Road.
27
G. Conclusion of the "Supporting Documentation" Report.
Based upon the information developed in the "Supporting Documen
tation" report, together with the comparisons presented above, it
was concluded that the total environmental effect of either the
Existing Alignment Alternative or the New Alignment Alternative
was either insignificant or non-existent. Furthermore, it con
cluded that neither alternative warranted the filing of formal
environmental documents. Finally, based on the nature of the
alternative improvements, the "Supporting Documentation" report
recommended that this project be classified as a "Categorical
Exclusion" in accordance with FHPM 7-7-2.
H. Recommended Replacement Alternative. In their letter of
March 11, 1986 submitting the "Supporting Documentation" report
to the FHWA, the Department recommended that the New Alignment
Alternative be selected for the following reasons.
o It allows the maintenance of traffic during construction, thereby avoiding disruption of local traf.fic over a prolonged period of time.
o It permits a substantial improvement to the intersection of Martin Street, Cullen Hill Road and Lower River Road.
On March 27, 1986, in a letter to the Department, the FHWA
approved the selection of the New Alignment Alternative and
accepted the recommendation that this project be designated as a
Categorical Exclusion.
Both the letters referred to above are included in APPENDIX
"B" of this report as Exhibits 1 and 2, respectively.
For a complete graphic representation of the recommended New
Alignment Alternative, see PLATES III, IV, and V.
28
IV. IMPACT OF RECOMMENDED PLAN ON ARCHEOLOGICAL AND RECREATIONAL RESOURCES
A. The Section 106 Resource. As explained in Part I of this
report, the Paul Ronci Memorial Park constitutes the northern
segment of the Blackstone Canal Historic District. This district
contains the archeological remains of the old Blackstone Canal
and has been entered in the National Register of Historic Places.
In accordance with the Section 106 of the National Historic
Preservation Act of 1966 the proposed bridge replacement project
has been determined to adversely effect the Paul Ronci Memorial
Park. Therefore, mitigation measures must be examined.
B. The Section 4(f) Resource. The discussion in Part I
indicates that the Paul Ronci Memorial Park is a riverfront
park used as a passive recreational area. The proposed bridge
replacement project uses approximately 2,900 square feet, or
0.07th acre, of land contained in this park. This is 0.17% of the
total park land.
C. Section 106 Effects.
1. Blackstone Canal Historic District. On September 9,
1985 the RIHPC advised the Department that the proposed bridge
replacement project passes through the Blackstone Canal Historic
District and that said district is included in the National
Register of Historic Places. While noting that the existing
bridges, themselves, were not historically significant, RIHPC
advised that the replacement of the bridges with either of the
proposed alternatives would produce an adverse effect on the
29
District. The applicable criteria of adverse effect in this case
as set forth by the Advisory Council on Historic Preservation is
as follows:
"Introduction of visual, audible or atmospheric elements that are out of character with the property or alter its setting."
In this instance RIHPC believes that either;
The replacement of the bridges along their existing alignment with wider structures,
or; the replacement of the bridges with a wider structure along the proposed new alignment,
would produce a visual effect that was out of character with the
existing setting of the Blackstone Canal Historic District.
2. Archeological Considerations. A complete Phase I
archeological survey of the two alternative solutions for the
proposed replacement of the Berkeley Bridge and the Martin Street
Canal Bridge was conducted by Wilbur Smith and Associates during
the summer and autumn of 1986. Background research, walkover
survey, and subsurface investigations did not identify any pre
historic archeological sites in the project area. Background
research and walkover survey verified the existence of the Black
stone Canal, a National Register property, that runs north-south
through the project area. Background research indicated that no
locks or other canal-related structures are located within the
project area. Subsurface investigations did not identify any
archeological evidence of the former tow path associated with the
canal. Wilbur Smith and Associates concluded that based upon
their Phase I research, the Blackstone Canal is the only
archeological resource in the project area.
30
D. Section 4(f) Use. Following early coordination
efforts, it developed that RIDEM was not unduly concerned with
the very limited use of park land, or proposed park land, for
bridge replacement purposes. Their principal concerns were in
maintaining access to the canal embankment area through Martin
Street; in having sufficient vertical clearances under the new
bridge for bicycle traffic; and in having the embankment area,
itself, remain relatively undisturbed. These concerns were set
forth in detail by RIDEM in a September 17, 1985 memorandum to
the Department as follows:
o RIDEM recognizes the need for a new alignment for the new bridges to correct the problem at the intersection at Martin Street and Lower River Road.
o If the New Alignment Alternative is selected, the existing Martin Street Bridge should be retained to provide access to the embankment area for hikers., horseback riders, bicyclists and occasional emergency vehicles.
o Vertical clearance from the embankment area to the underside of the new bridge must be at least 10 feet to accomodate the uses enumberated above.
o There should be no permanent excavations or embankments along the banks of either the canal or the river.
o Abutments for the new bridge should not be located in either the river or the canal, but rather should be set back a suitable distance on the banks and should be essentially parallel to the banks.
o The center pier should not be located in the canal embankment area, but rather set just off shore and be oriented essentially parallel to that shore.
o The bridge abutments and center pier should be provided surface treatment such that
31
they are as compatible as possible with the existing ambiance and historical character of the area.
Mitigation measures are discussed in the following chapter,
32
V. MITIGATION MEASURES.
A. Section 4(f) Involvement.
1. Recommended Plan. On June 4, 1986 the Department's
consultant advised RIDEM that the New Alternative had been
recommended for adoption and that the FHWA had both approved of
that recommendation and had designated the project a Categorical
Exclusion under the appropriate NEPA criteria. On June 5, 1986
RIDEM responded to the Department's consultant and noted their
continued concern with the vertical clearance as it affected the
proposed Blackstone Bikepath. RIDEM is administering the bikepath
planning project for the R.I.D.O.T. (See Part I, Section C for
description of the proposed bikepath). RIDEM requested a set of
the revised plans for review. A print of the revised plan was
transmitted to RIDEM on September 26, 1986. (See PLATE III.)
2. Response to RIDEM's Concerns. The revised plan of
improvement submitted to RIDEM on September 26, 1986 responds to
their concerns as follows:
o Access to the Embankment Area; By retaining and modifying the existing Martin Street Bridge, along with its westerly approach from Lower River Road, access to the embankment area for Blackstone River Park purposes remains essentially as it does at the present time. The only difference is that access from Cumberland must now cross the new bridge to Lower River Road rather than cross the existing Berkeley Bridge which, of course, is to be removed. Access will generally be available to the embankment area from Martin Street during the construction period.
o Vertical Clearances; The minimum vertical clearance between the gravel road on the canal embankment and the underside of the
33
new bridge is 9.0 feet. This is more than sufficient for hikers. By construction of a 200 foot bypass to the existing gravel road--referred on the plans as the "Bicycle/Maintenance Vehicle Route"--just east of the gravel road, a minimum vertical clearance of 13.5 feet is provided. This bypass is 12.0 feet wide, unpaved, and is supported on each side by short, stone rubble retaining walls. The 13.5 foot clearance provided is more than adequate for bicyclists, horseback riders, and the occasional emergency vehicle. It is in this area that the recommended route for the Blackstone River Bikeway [(FAP No. MBW-6666 (005) ] is planned.
o Bridge Abutments: The two bridge abutments are set back on their respective shores as requested by RIDEM. The area in front of the West Abutment (canal) will be graded and finished with natural vegetation. The area in front of the East Abutment (river) will be finished with rock rip-rap to prevent erosion. Both abutments will be oriented essentially parallel to their respective shorelines. As indicated later under Section 106 mitigation, the abutments will be provided with appropriate surface treatments and landscaping materials to produce an appearance in keeping with the natural and historic setting.
o Center Pier; The pier is not located on the canal embankment area, itself, but just off its easterly shore. The pier is oriented parallel to that shore. Canoeing will not be permitted along the westerly side of the pier because of the necessity of providing scour protection in the form of rip rap. As with the abutments, appropriate surface treatment will be provided.
B. Section 106 Involvement.
1. Recommended Plan. On July 17, 1986 the Department's
consultant transmitted to RIHPC a revised set of plans for the
New Alignment Alternative. These plans incorporated elements
suggested during earlier coordination with RIHPC. RIHPC was
advised at that time that the Department had recommended the New
34
Alignment Alternative for the replacement of the existing
Berkeley-Martin Street Bridges. Furthermore, the RIHPC was
advised that the FHWA concurred with this recommendation and had
designated the project a Categorical Exclusion under the
appropriate NEPA criteria.
2. Mitigation. On August 25, 1986, RIHPC responded to
the Department's consultant. They noted that their basic
concerns had been addressed and suggested measures that might
satisfactorily mitigate the adverse effects on the Blackstone
Canal Historic District. (Exhibit 3, APPENDIX "B".)
Further coordination and discussions with RIHPC
resulted in the establishment of the following two measures which
will, in the judgment of the RIHPC, satisfactorily mitigate the
adverse visual effects of the bridge replacement on the
Blackstone Canal Historic District.
o Exposed surfaces of the new concrete pier and abutments shall be rusticated either by placing linear or area type inserts inside concrete forms or by other types of surface treatment to produce an appearance which is as compatible as possible with the existing setting.
o Appropriate landscaping at, or adjacent to, the new concrete pier and abutments will be provided to ameliorate the appearance of said substructure units in relation to the existing setting.
The executed Memorandum of Agreement which incorporates
the above mitigation is presented in APPENDIX "C" of this report.
35
VI. AGENCY COORDINATION.
A. Coordination with RIHPC and RIDEM. During the late
summer of 1985 the Department closely coordinated this project
with both RIHPC and RIDEM. Two working sessions were held, one
on August 28th and a second on September 19th. RIHPC was
represented at these workshops by Edward Sanderson and/or
Virginia Fitch; RIDEM was represented by Judith Benedict and/or
Patrick Gushue. RIDOT was represented by Richard Kalunian,
Richard Swanson, Anne Dowd and its consultant, Gordon R.
Archibald, Inc.
As a result of these meetings the following facts became
immediately clear:
o Both RIHPC and RIDEM recognized that both the Berkeley and Martin Street Bridges must be replaced as public transportation facilities.
o Neither RIHPC or RIDEM indicated any clear preference for either of the two replacement alternatives, i.e., existing alignment or new alignment, respectively.
o RIHPC indicated that the visual intrusion of the bridge replacement on the Blackstone Canal Historic District would be the same regardless of which alternative was selected.
o RIDEM's major concern was that access to the canal embankment must be provided regardless of which replacement alternative was selected. It was understood by all that if the New Alignment Alternative was selected, the existing Martin Street Bridge, together with its westerly approach, must be retained and modified to provide the desired access.
36
B. Document Distribution List. The Draft Section
4(f) Statement and Section 106 Preliminary Case Report was
distributed to the following individuals and agencies:
Mr. Bruce Blanchard Director, Office of Environmental Project Review U.S. Department of the Interior Interior Building-Room 4239 18th and C Streets, N.W. Washington, D.C. 20240
Mr. Edward F. Sanderson Executive Director Historical Preservation Commission Old State House - 150 Benefit Street Providence, RI 02903
Ms. Elizabeth Higgins Assistant Director Office of Environmental Project Review U.S. Environmental Protection Agency Region I John F. Kennedy Federal Building - Room 2203 Boston, MA 02203
Mr. Robert J. Klumpe State Conservationist U.S. Department of Agriculture Soil Conservation Service 46 Quaker Lane West Warwick, RI 02893
Mr. Daniel Varin Associate Director Office of State Planning 265 Melrose Street Providence, RI 02907
Mr. Robert Bendick Director Department of Environmental Management 83 Park Street Providence, RI 02903
Mr. Raymond Auclair Blackstone Valley Historic District 381 Blackstone Street Woonsocket, RI 02895
37
Mr. Samuel Cashman President Cumberland Preservation Society Newell Drive RFD #2 Cumberland, RI 02864
Mr. Albert Klyberg Director Rhode Island Historical Society 110 Benevolent Street Providence, RI 02903
C. Comments on the Draft Submission. The following
public agencies responded with written comments to the Draft
Section 4(f) Statement and Section 106 Preliminary Case Report
(Draft Document):
o U.S. Environmental Protection Agency; Region 1
o U.S. Department of the Interior; Office of Environmental Project Review
o R.I. Historical Preservation Commission.
o R.I. Department of Environmental Management; Environmental Coordination
A summary of each of the above responses, together with
an appropriate comment, follows:
Environmental Protection Agency. The EPA noted that the
Section 4(f) and Section 106 issues identified in the draft
document were outside of their jurisdiction. Accordingly, EPA
indicated they would have no comments on the draft report.
Comment: None required.
U.S. Department of the Interior. The Office of
Environmental Project Review concurs that there is no feasible
38
and prudent alternative to the proposed use of land within the
Paul Ronci Memorial Park for the planned bridge replacement;
agrees with the selection of the recommended plan; and concurs
that the proposed mitigation measures are appropriate. They
recommend, that the mitigation also include the conversion of the
existing right-of-way to park use.
Comment. The existing right-of-way of the Lincoln
approach has, in effect, already been designated for park use by
the decision to retain the Martin Street Bridge. The bridge and
its approach will allow access by bikers to the proposed Black
stone Bikeway while at the same time continuing to allow access
by public utility vehicles to the canal embankment.
R.I. Historical Preservation Commission. RIHPC offered
two clarifications of historical and geographical fact, both of
which have been incorporated into the final document. RIHPC
reiterated the fact that the proposed mitigation for adverse
visual impact is sufficient. They conclude by emphasizing the
importance that masonry and/or rusticated surfaces should
harmonize with the existing character of the site.
Comment. None required. Mitigation measures are
enumerated in the executed Memorandum of Agreement which appears
in Appendix "C".
R.I. Department of Environmental Management. RIDEM
restates their concerns regarding the location of abutments and
piers, maintenance of access to the towpath from Lincoln,
vertical clearance under the new bridge for hikers, bikers, and
39
equestrians, and the visual impact of the alterations to the
area. RIDEM acknowledges that RIDOT has responded to these major
concerns, but presents a list of six items on which it requests
additional information on design details. RIDEM also requests
clarification as to which side of the proposed center pier
canoeing will be permitted.
Comment. The R.I. Department of Transportation will
incorporate as many of the design details requested by RIDEM as
it can given applicable design and funding constraints. The
Department will also submit a set of the 30% complete design
plans to RIDEM for their review and comment. Finally, the
confusion as to which side of the center pier canoeing will be
permitted has been clarified on page 34 of this report.
Each of the above four responses are presented in
APPENDIX "D" of this report.
40
VII. CONCLUSION
This report presents three alternatives for replacing the
Berkeley and Martin Street Bridges and improving the safety and
quality of the approach roadways. Of the three alternatives
studied, the New Alignment Alternative (as opposed to the No-
Build or Existing Alignment Alternatives) is recommended for best
achieving the objectives of this project and addressing the
concerns of the local community. This report has identified the
Section 4(f) resource, the Paul Ronci Memorial Park, and has
discussed all possible measures to minimize harm to that
property. The avoidance alternatives investigated and the miti
gation measures proposed have been discussed in detail.
The New Alignment Alternative is the only prudent and
feasible alternative for replacing the existing bridges. All
other alternatives have unique problems of extraordinary
magnitude that render them imprudent and unfeasible. The No-
Build Alternative does not,accomplish the project objective to
replace the bridge structures. Furthermore, it would allow
seriously deficient structures to remain in service. This alter
native would also leave the unsafe geometry of the Lincoln
approach road and its intersection with Lower River Road
uncorrected. Ultimately, the bridges would have to be closed.
Both the Existing Alignment Alternative and the New Alignment
Alternative would replace the deficient bridge structures. The
impact of each of these alternatives on the Section 4(f) resource
is virtually the same (0.06 and 0.07 acre for the Existing Align
ment and New Alignment Alteratives, respectively) and is
41
negligible when compared to the 40-acre area of the Paul Ronci
Memorial Park. The Existing Alignment Alternative would, however,
allow the unsafe intersection and approach roadway in Lincoln to
remain indefinitely, whereas the New Alignment Alternative would
correct these conditions in line with current design standards.
42
PROJECT AREA
PROJECT LOCATION MAP BERKELEY & MARTIN STREET BRIDGES
LINCOLN & CUMBERLAND, R.I.
PLATE I
REPLACEMENT OF THE BERKELEY AND MARTIN ST. CANAL BRIDGES
BLACKSTONE RIVER LINCOLN & CUMBERLAND, R.I.
SHADED AREA PAUL RONCI MEMORIAL PARK VICINITY MAP
PLATEnr
APPENDIX "A"
MATERIALS RELATED TO THE NATIONAL REGISTER STATUS OF THE PAUL RONCI MEMORIAL PARK AS THE NORTHERN SEGMENT OF THE BLACKSTONE CANAL HISTORIC DISTRICT
S T A T Es/m 10-300 UNITED S T A T E S D E P A R T M E N T OF THE INTERIOR
,D»c. 1968) NATIONAL PARK SERVICE Rhode Island C O UN T V
NAT IONAL R E G I S T E R OF HISTORIC P L A C E S Providence I N V E N T O R Y - NOMINATION FORM FOR NFS USE ONLY
r N r n •> NuMtir
(Type all entries —complete applicable secfrons)
[V. NAME Mernorial
AND/OR M I S T O R I C :
Blackstone Canal [ 2 . LOCATION
S T R E E T A N C N U M B E R :
from Front Street north to the Ashton Dam C I T Y OR TOWN:
Lincoln COUNTY: CODE
Rhode Island Providence 007 (j. CLASSIFICATION
CATEGORY ACCESSIBLE \s\ OWNFRSHIP STATUS (Check One) TO THE PUBLIC
z Diitr lct [I] Building Public D Public Acquisit ion: Occupied I I Yes:
o Sit« J] Structure Privot* Zl In Proceis Unoccupied K] Reftricled [ |
Both D Being Conlldered Preservation work Unrestricted QQ In progrett I I No: D
u PRESENT USE fCheck One or More •• Appropriate)
Agricul tural | | Government Park Transportation Comments oe Commercial Q] Industrial Private Residence Other fspec/fyj
Educotionol | | Military Religious
Enlertoinment Q] Museum Scientific
[4. OWNER OF PROPERTY OWNERS N A M E
Frank Ronci Company, InCe UJ S T R E E T AND NUMBER:
UJ 2, Atlantic Boulevard w* C I T Y OR TOWN:
North Providence Rhode Island [5. LOCATION OF LEGAL DESCRIPTION
COURTHOUSE. R C G t S T R Y OF DEEDS. ETC:
Lincoln Town Hall STREET AND NUMBER:
Old River Road C I T Y OR TOWN: S T A T E '
Lincoln Rhode Island A P P R O X I M A T E A C H E A G T OF NOMINATrP P R O P E R T Y ; 3U
16. ftEPftESENTATION IN EXISTING SURVEYS T I T L E O F S U R V E Y :
Not known to be represented in any survey D A T E OF S U R V E Y : Federal (~) Stole Q County Local DEPOSITORY FOR SURVEY RECORDS: •n
O X 2
STREET AND NUMBER! •0
CITY OR TOWN:
Exhibit 1 Sheet 1 of 4
Ont<)COITION
Excel lent f l Good (J| Fair [J D»t«rlorcited Rulni LI (Jn«.«po««.d (J
(Check One) (Check One> I N T E G R I T Y
A l tered Q Unaltered Moved [ J O r i g i n a l Site
D E S C R I B E THE P R T S E N T AND ORIGINAL (II known) P H Y S I C A L A P P E A R A N C E
The stretch of the Blackstone Canal beginning at Front Street In Lincoln and extending four miles ncrth to the Ashton Dam sompriseg the Paul Ronci Memorial Park. It is the longest segment of the original forty-five mile canal still intact. Both the canal and the tow-path exist in pood condition. There are no locks or engineering structures along this stretch of the canal. The width of the canal varies between thirty-two and forty-five feet at the top. The bottom width is eighteen feet. Present water level averages between three and four feet in depth.
The land for use as a park includes the canal, tow-path, and fifteen feet on either side of the canal. The canal banks have a ground cover of brush and small-to-mediuro-size trees. The walls of the canal for the last two thousand feet at the northern end are lined with cut-stone blocks. The physical appearance to-day is, in short, m much the same as it was during the years 1828 to l8U8 when the canal m was in use, transporting goods between Providence, Rhode Island, and Worcester, Massachusetts.
TV
C
n H
O
z t/1
Exhibit 1
Sheet 2 of 4
.•./GNIFICANCE
n r n i O D (Cl'frk Onr nr Mnrf UK / tnprnprlnfr)
Pre-Columbian Q 16th Century Q] 18th Century Qj 20th Century
)5th Century Q 17th Century ( | 19lh Century (X)
D A T F K S I ( I I Applicable anilKnnnn)
A R E A S OF S I G N I F I C A N C E (Check One or More ••
Abor iglnol Education
Prehlttorlt [_J Engineering
Historic (71 , Industry
Agriculture [~] Invention . ,
Art [~] Landscape
Commerce Q Arch! tecture
Communications [̂ ] Literature
Conservat ion 1 ] Mil i tary
Music
Appropriate)
Q Political •• Urban Planning n f ~\ Religion/Phi- Other (Spicily) a
IT] losophy
[~] Science , 1 1
Sculpture f~)
[~| Soclal/Humon
[~~] itarlan f~~)
[~~] Theater
{"I Transportation
S T A T E M E N T OF S I G N I F I C A N C E (Include P«rtan»tte*, Dal**, Event., Etc.)
The canal was constructed between the years l82li and 1828. It linked the cities of Worcester, Massachusetts, and Providence. The forty-five-mile stretch, with a drop of U5l feet in altitude, employed granite locks. The canal was not built as one independent and continuous stretch for its entire length, as it utilized the parallel Blackstone River at various points, thus saving some con
•SI
T struction costs.
U Built at the height of the canal frenzy, the Blackstone had a T life df nearly twenty-five years—few of them orosperous. To begin
OH with, it was too late in coming. John Brown of Providence had seen the advantages of such a canal opening up country markets for Providence trade in the late 1700'sj but when his fellow-merchant, Edward Carrington, brought that vision to realization in the 1820's the coming of the railroad already heralded a faster and better way of moving goods and passengers. In addition, the canal project was underfinanced. Also, hasty planning had failed to provide a proper
UJ system of reservoirs to maintain a continuous water levelj droughts 111 and diversions of water by mill-owners resulted in frequent inter
ruptions of service.
To-day few sections of the canal remain. There are no known locks still to be seen, though some of their remains may exist. In several places in Massachusetts the canal has been filled in. The canal bed in Rhode Island, however, is largely intact.
Exhibit 1
f t l B L I O C R A P H I C A L R E F E R E N C E S
CarrinRbon, Edward t Papers (at Rhode Island Historical Society, Provi' donee).
Blactotono Canal Company: Account books (at Rhode Island Historical Society, Providence. )
Blackstone Canal, Trustees of: Minutes (in Thomas A. Jenckes Collection at Rhode Island Historical Society, Providence).
Map of the Blackstone Canal (based on the original survey, 1828-1830). (at Rhode Island Historical Society, Providence)
10 . G E O G R A P H I C A L D A T A **•*+.
_ L A T I T U D E A N D L O N G I T U D E C O O R D I N A T E S
0 D E F I N I N G THE C E N T E R P O I N T OF A P R O P E R T Y L A T I T U D E A N D L O N G I T U D E C O O R D I N A T E S
D E F I N I N G A R E C T A N G L E L O C A T I N G T H E P R O P E R T Y R O F LESS T H A N O N E A C R E
C O R N E R L A T I T U D E L O N G I T U D E L A T I T U D E L O N O I T U D E
Degrees M i n u t e s Seconds Degrees M i n u t e s Seconds Degrees Minutes Seconds Degrees J rilnutes Seconds NW hl° %• 1$ • 71° 26 • 02- o . . e
N E la° 56' 15 • 71° 2h • 02SE lil° !?b' 2U ' 71" 2li- 22 sw hl° 5b' 2h ' 71 ° 26 • 02 •
LIST ALL S T A T E S AND COUNTIES FOR P R O P E R T I E S O V E R L A P P I N G STATE OR COUNTY BOUNDARIES
S T A T E CODE C O U N T Y CODE
S T A T E CODE C O U N T Y - C O D E
S T A T E CODE C O U N T Y : CODE
S T A T E CODE C O U N T Y : CODE
•it. FORM PREPARED BY ' N A M E A N D T I T L E .
Albert T. Klyberg, Director O R G A N I Z A T I O N D A T E
Rhode Island Historical Society , , Pet.- 2, 1970 S T R E E T A N D N U M B E R
52, Power Street C I T Y O R T O W N - S T A T E CODE
Providence Rhode Island, 02906 Ui
12. STATE LIAISON OFFICER CERTIFICATION NATIONAL REGISTER VERIFICATION
, . r . As the designated State Liaison Officer for the Na-
I hereby certify that this property is included in the tional Historic Preservation Act of 1966 (Public Law National Register. 89-665). I hereby nominate this property for inclusion
in the Nat ional Register and certify that it has been
evaluated according to the criteria and procedures set
for th l>y (he National Park Service. The recommended Chief, Office of Archeology and Historic Preservation
level of Munificence of (his nomination Is:
National (Tj State Q Local Q
Date
Name ATTEST:
Title State Liaison Officer Keeper ol The National Register
Date Date
m
to
H
TO
n
o •z.
Exhibit 1
>-r A
C
»•**•*. . States Department of the
NATIONAL PARK SERVICE WASHINGTON, B.C. 20240
IN RFPLY REFER TO:
R30-HR DEC} R 1970
Mr. Frederick C. Williamson Director of Department of Community Affairs
C.I.C. Building 289 Promenade Street Providence, Rhode Island 02908
Dear Mr. Williamsons
We are pleased to inform you that the historic properties listed
on the enclosure have been placed on the National Register of
Historic Places. Senators John O. Pastore and Claiborne Pell
and Representative Fernand J. St Germain have also been notified.
A leaflet explaining the National Register is enclosed for each of
the property owners. Please withhold any publicity on this until
you have received a carbon copy of the Congressional correspondence,
Sincerely yours,
Crnest Allen Connally Chief, Office of Archeology and Historic Preservation
Enclosures
DEC 18 Entered in the National Register
Exhibit 2
Sheet 1 of 2
pcrrrca mrcrjr 01 fire
Properties added to the National Register of Historic Places
I i ' < ' RHODg ISLAND
Arnold (Israel) House Providonco County, Rhode Island Paul Ronci Mamorial Park Providence County, Rhode Island
Exhibit 2
2 of 2
The
National Registei •̂
of Historic Place:
19 7(
William J. Murtagh Keeper of the National Register
Ronald M. Greenberg Editor in Chief
Sarah A. Marusin Editor
Maricca J. Lutz Photo Editor
U.S. Department of the Interior National Park Service Washington, D.C. Exhibit 3
1 of
RHODE ISLAND 669
irking, 2 1/2 stories, rectangular, gabled 'ioof. 2 interior chimneys, main Doric entrance
portico and doorway with pilasters and fanl ight , fqooins. I 1/2 storv W wing Colonial elements
a r c M d c n c e . conver ted to a t a v e r n , 1102. local social center and stagecoach stop,
sbank, 1823-1853 Private
rCeorgiavilk vic ini ty SM.1TH-APPLEBY [ HOUSE, S t i l lwa te r Rd , SE of jet with Capron
1713 Frame, clapboarding, 2-2 1/2 stoL-shaped, gabled roof sections, original
ox structure enlarged, c 1750 and c 1780, •-19th C entrances including elaborate
ay with side lights and classical details, I N addi t ion, interior features 18th and
h C bui ld ing details Built by FJisha Smith, of John Smith, first gristmill owner in
ence. 1646 Private HABS
ster GLOCESTER TOWN POUND, I kd and Cnopmist Hil l Rd , 1748 Stone,
wall construction, 4-sided enclosure, 6' with large capstones, W stone jamb and entrance with simple iron bar gate
Irijinally used to keep stray animals; believed i be one of the oldest pounds in existence
al
on BROWN AVENUE HISTORIC DISF, Brown Ave , I8th-20lh C Rural dis-
of about 500 acres of farmland divided • 5 farms, features frame farmhouses, barns,
outbuildings in simple late-18th-20th C. s; focal point is Dame Farm with c. 1790 2
2-ctory farmhouse with I 1/2-story wing, now to the public Preserves grouping of ale-sized family farms typical of those
t provided food for state's urban areas dur [ I9tb-early-20th C Multiple public/private
CLEMENCE-IRONS HOUSE, 38 Waterman Rd , c 1680 Frame, clap
ng, I 1/2 stones, rectangular, gabled roof ng over rear lean-to; exterior stone
widened to create exterior lean-to restored, 1940's by Norman M. Isham;
reconstructed Typical Rhode Island nder " Home of Thomas Clemence,
I representative and treasurer One of earli 1 dwellings preserved in the state. Museum
E.-HABS
FARNUM EDWIN M., HOUSE 1ELL HOUSE), I' S. 44 at jet with Collins 1765. Frame, clapboarding, 2 1/2 stories,
lar, gabled roof, central chimney and with fan and side lights, front bay win
cornerboards, enlarged, early-19(h C and tavern built by Stephen Angell,
nt of,Thomas Angell who apprenticed Roger Williams and accompanied him to
vanishment from the Massachusetts Colony, 1636, and signed the charier lo
Providence, Aug 20, 1637. Municipal.
. ARNOLD, ELEAZER, HOUSE, Great 123) near jet. with Rl 126, c. 1687.
.clapboarding, 2 1/2 stories, rectangular, f pitched gabled roof, massive stone-end
; original l-room structure enlarged by
addition of rear lean-to with fireplace at tached to original fireplace, restored, 1951 I xcel lcnt example of state's "stone-end" dwel l ings Priialf Mil , IIABS
Lincoln ARNOLD, ISRAEL, HOUSE, Great Rd , c 1720 Frame, rlnphnarding, 2 1/2 sto ries, L-shaped, gabled and gambrel roof sec tions, central and end chimneys, center entrance with transom; original 1 1/2-story section expanded, 1760, original tr im and hard ware Intact example of 18th C New England farmhouse Private, not accessible to the public HABS, o
Lincoln BLACKSTONF ( ANAL, From Stee pie and Promenade Sts to the Ashlon Dam, 1824-1828 Portion of the remains of 4S m i l e -long canal and towpath 18 ' wide at bottom, 32-45' wide at top, some masonry retaining walls and wharfage areas remain Canal con structed to transport commercial goods and passengers between Worcester, MA, and Providence, Rl, granite locks accommodated 451'-drop between the cities, 4 mi segment from Front St to the Ashton Dam comprises Paul Ronci Memorial Park, largest segment of the original canal still intact Multiple public/private
Lincoln HEARTHSIDE (STEPHEN HOPKINS SMITH HOUSE), Great Rd ,c 1810 Ashlar, 2 1/2 stories with attic, rectangular, gabled roof with bell-cast end parapets, interior end chim neys, cornice with bead molding, front large bell-cast gublcd dormer wi th entrance, side lights, and convex oculus. front ful l -width 2 story tetrastyle portico with square posts, center entrance with fanlight and side lights, side entrance with fanlight, oculus in gable, original interior woodwork and mantels, early 19th C rear stone wing, I830's rear frame wing, side porch partially destroyed, portico parapetdestroyed. Federal house with unusual gable parapets. Private; not accessible to the public: HABS.
Lincoln. LIMEROCK VILLAGE HISTORIC DISTRICT, In irregular pattern along Smith, Wilbur, and Great Rds., and Old Louisquisset Pike, Late-17th-19th C Village center, includes 20 structures, 3 lime quarries, and the ruins of 3 lime kilns. Contains structures exhibiting characteristics typical of !7th and I 8th C. New England architecture as well as Greek Revival and later Victorian styles. Developed as slopping place on Great Road and as a l ime-manufacturing area unt i l construction of the Providence and Worcester RR in the I840's and the growing populanl) of Portland cement Retains curly New England qual i ty Multiple private H A H S
North Providence ALLEN DALE MILL, 494 Woonasquatucket Ave , 1822 Stone, 4 1/2 stories, rectangular, modified roof, side stair tower with low hipped roof, dormers, one end with 3tier corner buttresses; I I additions, 1844-1955, 5 outbuildings. Built for Zachariah Allen, Jr for manufacture of woolens; construction supervised by John Holden Greene, used "slow
burn ing" construction technique to increase fire rcsisl.mce, such concerns led to 1835 formal ion of fire insurance company Private IMPS
Nor th Scituate OLD CONGREGATIONAL CHURCH, Off U S 6 on Greenville Rd (Rl 1 1 6 ) 1 8 3 1 , Clark Sayles, builder-architect Frame, clapboarding, I story, rectangular, gabled roof, front square tower wi th octagonal belfry and spire, front center window flanked by 2 entrances, 3-aisled interior, simple woodwork, restored Federal and Greek Revival elements Buil t for North Smithvil le Society, regular services suspended, c 1897 Community house Municipal
P a w t u c k c l OLD SI ATER Mll.l , Roosevelt Ave . 1793 Frame, clapboarding. 2 1/2-3 sto ries, T-shaped, gabled roof, cupola, extensively enlarged. 19th C Fir" cotto" .nil! K. i: , America establishing cotton manufac tu r ing in the 0 S , built by Englishman Samuel Slater using British-inspired machinery and factory system of manufacturing Private NHL
Pawlucket TRINITY CHURCH, 50 Mam St , IR'iO-1854, Samuel J Ladd, architect Random ashlar, 1 story, modified rectangle, gabled roof, front pointed arched entrance through 3-story corner tower with upper-story louvered lancet openings and pyramidal roof interrupted by gables above lancets, side entrance in full-width shed roof extension to create side aisle, with gabled dormers above, corner and side buttresses, stained glass Innccl windows, enlarged 1865; parish house attached 1920; choir room added 1914 Good example of Gothic Revival parish church Private
Providence ALLEN, CANDACE, (HOUSE, 12 Benevolent St , 1818-1822, John Holden Greene, builder-architect Brick, 2 1/2 stories, L-shaped, monitor on hipped roof, tall interior end chimneys, modillion cornice with bead and tassel molding, front center entrance with fanl ight and side lights, small Corinthian portico, fron! center 2nd-story modified Palladian window with louvered fanlight, side ell with front entrance with partial portico abutting main block, marble sills and incised lintels, original interior woodwork, marble mantelpieces, and 19th C wallpapers, side ell enlarged, mid- 19th C . parapet removeu Drick carriage nouse Federal Built by John Holden Greene for Candace Allen, member of well-known textile-producing family (see also Allendale Mil l , R l ' typical of early 19th C tastes and lifestyle of ci ty 's wea l thy families Private, not accessible to tlir public HABS
Providence ARCADE, T1IK, I 30 Westminster St and 65 Weybosscl St . 1828, James C Uuiklin, Jr and Russell Warren, architects. Granite, 3 stories, rectangular with 2 side pavilions, gabled roof, monumental hexastyle Ionic portico on each front; skylighted interior arcade surrounded by 3 tiers of shops, cast iron gallery railings and stairs, monolithic granite columns Greek Revival Chief example of ear ly-19th C arcades in U S Private HABS.
Exhibit 3
Sheet 2 of 2
STATE OF RHODL IbLAND AND PROVIDENCE PLANTATIONS
Department of Transportation DIVISION OF PUBLIC WORKS State Office Building Providence, R.I. 02903
March 11, 1986
Mr. Gordon G. Hoxie, Division Administrator Federal Highway Administration 380 Westminster Mall
-, 1 ., _. . T , ,Providence, Rhode Island
mom 02903
Re: Berkeley Bridge and Martin St. Canal Brie _ . _/. „_, ,,-fnm\F.A. Project: HW-Jol2(001)
Dear Mr. Hoxie:
We are submitting a report prepared by our consultant that supports a decision that the subject project be classified as a Categorical Exclusion for each of the two alignments studied. Please note that the State Historical Preservation Officer considers either alternative to have an adverse effect on the Blackstone Canal Historic District. Accordingly, Section 4(f) and 106 Statement will have to be prepared.
With regard to the two final alignments studied we summarize below the advantages and disadvantages of each.
Existing Alignment
Advantages
Less impact on vegetation.
Less property acquisition and impact on abutting properties.
Lower construction cost.
Disadvantages
Requires a detour of traffic for about one construction season.
At grade access to the tow path between two structures results in discontinui't of the traffic railing system.
Horizontal alignment in Lincoln requires a design exception for substandard superelevation.
/
Does not significantly improve the intersection at Lower River Road and Cullen Hill Road.
New Alignment
Advantages
Smoother alignment which meets the adopted design criteria.
Exhibit 1 Sheet 1 of 2
Grade separation at the tow path results in greater safety for pedestrians and bicylists using the tow path.
Greatly improves the intersection at Lower River Road and Cullen Hill Road.
Allows traffic to be maintained on the existing alignment during construction
Disadvantages
Requires more property acquisition.
Higher construction cost.
Visual impact of the relatively low level separation at the tow path interrupts the open space of the proposed linear park between the canal and river.
A proposed bike route along the canal will have to dip and rise again to pass under the new bridge.
The existing canal bridge will have to be retained for Town access to the tow path.
At this time the Department does not have a strong preference for either alignment. Maintaining traffic during construction and the great improvements at the intersection at Lower River Road seem to indicate the new alignment to be better from a transportation improvement point of view. It is therefore our recommendation that final design be based on the New Alignment Alternative.
We request your concurrence that this project be classified as a Categorical Exclusion and for us to proceed with the Section 4(f) and 106 Statement based on the New Alignment.
-. Very truly yours,
Richard B. Kalunian Bridge Design Engineer
fmes R. Cap^ldi, P.E. lief of Design
RBK/fmv
cc: Mr. Kirby Mr. Carcieri Mr. Capaldi Mr. Parker
Exhibit 1 Sheet 2 of 2
380 Weetnlmter Mall 5th Floor
Providence. Bhode Island 02903
March 27, 1986
Mr. Janes R. Capaldi, Chief of Design Division of Public Works R. I. Department of Transportation State Office Building Providence, Rhode Island 02903
Dear Mr. Capaldi:
Subject: Project MW-J012(001), Berkeley Bridge and Martin Street Canal Bridge
This is in regard to your letter dated March 11, 1966 and the supporting docunantatlor fumLahed to establish a categorical racluslno detexoination for the subject project.
For the reasons stated in your letter and as docuamted in the attached report, we approve your request to proceed with design based on the new alignment, tfe assume you have considered the maintenance aspects required for retention of the canal bridge
proposing the recoonended alternative.
We accept your leouhinandatlon that this project be clasaified as a categorical eocclusi You oay proceed with fulfilling Section A(f) and 106 requirements.
Sincerely yours, cc: •» • • Mr. Carcieri
Gordon G. Hoodie Diviaion
Exhibit 2
STATE Or RHODE I S L A N D AND PROVIDENCE PLANTATIONS
(^o^J
HISTORICAL PRESERVATION COMMISSION Old State House 150 Benefit Street Providence, R.I. 02903 (401) 277-2678
August 25, 1986
Mr. Gordon R. Archibald Gordon R. Archibald, Inc. 200 Main Street Pawtuckct, R. I. 02860
Re: Berkeley Bridge Replacement Cumberland and Lincoln
Dear Mr. Archibald:
Thank you for submitting plans for review for the above referenced project which crosses the Blackstone Canal Historic District, a property listed in the National Register of Historic Places. In accordance with the Procedures of the Advisory Council on Historic Preservation (36 CFR 800) it is our opinion that introduction of a modern elevated bridge which clears the tow path berm by approximately 10 feet will have a effect on the rural quality of the district in that section also requiring construction of a new road section in the flood terrace below the tow path for vehicles and that the effect will be adverse, as previously stated in our letter of September 9, 1985. The plans show retention of the existing roadway and the canal bridge and a stone retaining wall along the new road below the tow path. These measures, along with bridge materials/color and landscaping may serve as mitigating factors.
Additional comments will be provided when the results of the Phase I Archaeological Survey are received.
Thank you.
Very truly yours,
Edward F. Sanderson Executive Director Deputy State Historic Preservation Officer
cc: A. Dowd R. Kalunian, Bridge Design RIDOT
Exhibit 3
M CF
WHEREAS, the Federal Highway Administration (FHVJA) has determined that the replacement of the Berkeley and Martin Street Bridges in Lincoln and Cumberland, Rhode Island, will have an effect upon the Paul Ronci Memorial Park/Elackstone Canal, nordnated to the National Register of Historic Places on May 6, 1971 and has consulted with the Rhode Island State Historic Preservation Officer (RISIIPO) pursuant to the regulations (36 CFR Part 80D) implementing Section 106 of the National Historic Preservation Act ( 16 U.S.C. 470f) ,
WHEREAS, the Rhode Island Department of Transportation (RIDOT) was invited and participated in the consultation process,
NOW, THEREFORE, FHV/A, RIDOT and the RISHPO agree that if the Advisory Council on Historic Preservation (Council) accepts this Memorandum of Agreement in accordance with 36 CFR Section 800.6 (a) (1) (i), the undertaking shall be implemented in accordance with the following stipulations in order to take into account the effect of the undertaking on historic properties.
STIPULATIONS
FHWA and RIDOT will ensure that the following measures are carried out:
1) Exposed surfaces of the new concrete bridge pier and abutments will be rusticated either by placing linear and/or area inserts inside the concrete forne or by using other means of surface treatment to produce an appearance which is as compatible as possible with the existing setting.
2) Landscaping adjacent to the new concrete pier and abutments will be provided.
3) The RISHPO will have thirty days to review and comment upon final plans for this project.
Execution of this Memorandum by the FHWA, RIDOT and the RISHPO and its subsequent acceptance by the Council and the FHWA's carrying out the terra of the Memorandum of Agreement evidences that the FHWA has afforded the Council an opportunity to commment on the replacement of the Berkeley and Martin Street Bridges in Lincoln and Cumberland and its effects on historic properties and that the
iws toKen ii.vAy account the effects of the project on historic properties.
Departiriefrc of Transportation
(date) 7-1$ ision Adninistrator eral Highv;ay Administration
land State Historic
AOC 5ry Council on
[stforic Preservation
1 r>—
£/&J UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION I
J. F KENNEDY FEDERAL BUILDING, BOSTON. MASSACHUSETTS 02203
July 29, 1987
James R. Capaldi, Chief of Design ^~/ Rhode Island Department of Transportation Dfpr nr rc,, State Office Building Providence, RI 02903
/\1<AW] 3 Dear Mr. Capaldi: 8
I *j
Thank you for sending us copy of your Draft Section 4(f) Statement and Section 106 Preliminary Case Report for the Replacement of the Berkeley Bridge and the Martin Street Canal Bridge in the Towns of Lincoln and Cumberland, Providence County, Rhode Island.
The report addresses the project's potential impacts to historic places and cultural resources in the Blackstone Canal Historic District, as well as potential impacts to the Paul Ronci Memorial Park. These issues are outside of EPA's areas of jurisdiction and expertise; hence, we have no comments on the Section 4(f) Evaluation or Section 106 Report. However, we note that the proposed bridge replacements will require a permit from the U.S. Army Corps of Engineers in accordance with Section 404 of the Clean Water Act. EPA will participate in reviewing the 404 permit application using EPA's 404(b)(l) Guidelines [40 CFR Part 230].
For your information Mr. Mark Kern is EPA's 404 permit coordinator for the State of Rhode Island. We recommend that you coordinate with Mr. Kern early in 404 permit process. He may be reached by telephone at (617) 565-4426. Thank you for informing us of the current status of this project. Should you have any questions, please contact Donald Cooke of my staff at (617) 565-3416.
Sincerely yours,
Elizabeth Higglers Congrajj, Assistant Director for Environmental Review
Office of Government Relations & Environmental Review
cc: Gordon Hoxie, FHWA - RI Anne S. Dowd, Planning Division, RI DOT Mark Kern, EPA WQP-1900 William Lawless, Chief Regulatory Branch, COE
TAXI'jAKt"
United States Department of the Interior Crooi^^•^ OFFICE OF ENVIRONMENTAL PROJECT REVIEW
WASHINGTON, D.C. 20240 AUG '2 '< 1987
18 1987
Mr. Gordon G. Hoxie Division Administrator AUG <Federal Highway Administration 380 Westminster Mall, Fifth Floor Providence, Rhode Island 02903
Dear Mr. Hoxie:
This is in response to a request for the Department of the Interior's comments on the draft Section 4(f) statement and Section 106 preliminary case report for Berkeley and Martin Street Bridges, Towns of Lincoln and Cumberland, Providence County, Rhode Island.
Section 4(f) Statement Comments
We concur that there is no feasible and prudent alternative to the proposed use of land within the Paul Ronci Memorial Park/Blackstone Canal Historic District for the planned bridge replacement. We are also in agreement with selection of the recommended plan. While we concur that mitigation measures are appropriate, we recommend the section on Mitigation include_the conversion of the existing bridge right-of-way to park use. Shouldf the park ranBPa^quired exceed that being replaced, we recommend the land taken be replaced with land of reasonable park and recreation utility and location.
Fish and Wildlife Cooordination Act Comments
Based solely on the information in this draft, it appears likely that the U.S. Fish and Wildlife Service will not comment further on this project at the permit application review stage, provided the application fully complies with the 404(b)(l) Guidelines (40 CFR 230).
Summary Comments
The Department of the Interior offers no objection to Section 4(f) approval of this project provided the measures mentioned above are included and documented in the final statement.
We appreciate the opportunity to provide these comments.
Sincerely,
Bruce Blancbyrd, Director
Mr. Gordon G. Hoxie
cc: Mathew J. Gill, Director RJ'Dept. of Transportation
. /State Office Building V Smith Street
Providence, Rhode Island 02903
Mr. Frederick C. Williamson Historical Preservation Commission 150 Benefit Street Providence, Rhode Island 02903
Robert L. Bendick, Jr., Director Dept. of Environmental Management 9 Hayes Street Providence, Rhode Island 02903
M \ 1 I 01 R H < > M ! 'M \.\1J \ \ [ ) | ' R ( ) \ | i ) i \( I I"; \ \ ! \ | |
.'Ml-R-OH 1C [ \1! Mo
!''
DLP!
IRON!
DEFT :
SUBJECT:
Victor R r l l , Ch--f nNM August 18, ]
DEM/Environmental Coordination •• / f
Judith Benedict, Chief .\\7 i
DEM/Planning and Development
MARTIN ST. BRIDGE REPLACEMENT: COMMENTS FROM THE DIVISION OF PLANNING AND DEVELOPMENT
The DEM Division of Planning and Development has several comments on the proposed DOT replacement of the Martin St. T'•idge across the Blackstone River and Canal.
As is noted in the draft 4(f) Statement and section 106 Preliminary Case Report, the new bridge will cross through state park land, formerly known as Paul Ronci Memorial Park, and now to be designated the Blackstone River State Park.
As is stated on pages 24 and 25 of the report, DEM Division of Planning and Development concerns include the location of the abutments, maintenance of access to the towpath from Lincoln, clearance under the bridge for hikers, cyclists, and equestrians, and the visual impact of alterations to the area.
In addition to the issues that have been addressed in the report and the plans, we have several further comments and questions:
1. Planting of side slopes
DEM would like side slopes, noted as areas A, B, C, D, and E, on the General Plans, to be planted with shrubs rather than seeded. Shrubs or small trees are more compatible with the existing vegetation than grass, and will require no maintenance. DEM would be happy to supply a list of appropriate plant material.
2. Center pier
We would like more design details on the center pier, including the abutment face material, proposed wing walls, and treatment of slope behind the abutment. We would prefer stone, or granite facing on concrete rather than scored concrete.
Victor Bell August 18, 1987 Page Two
Clarify the comment on page 28 that "Canoeing will not be permitted along the shore side of the pier." Does this mean to the east of the pier? We do not understand why canoeing would not be allowed here.
3. Treament of river edge
Since this is a park, riprap is not an appropriate river edge treatment. All banks should be graded to allow natural vegetation to secure the bank, as it does along this entire stretch of the Blackstone River.
4. Stone wall along towpath
Both stone walls should be continuous (see note on Recommended Plan).
5. Parking area between existing road to towpath and new bridge
DEM plans to use this area to provide parking for 10-15 cars, mostly for canoe access. We will provide DOT with plans of this area so that there is no conflict between DEM and DOT projects. Please advise as to the date by which such plans should be made available to DOT.
6. Other general comments
There are other notes on the plans to which we would like a response.
In conclusion, DOT has responded to our major concerns presented in an earlier meeting, but we would like more information about the design details. Another meeting is probably warranted.
Thank you for the opportunity to comment.
JB:as
cc Pat Gushue
Attachments
0140J
1,71987
August 14, 1987
James R. Capaldi Chief of Design Division of Public Works Rhode Island Dept. of Transportation State Office Building Providence, RI 02903
Re: Draft Section 4(f) Statement and Section 106 Preliminary Case Report, Berkeley and Martin Street Bridges, Lincoln & Cumberland, Rhode Island
Dear Mr. Capaldi:
The Rhode Island Historical Preservation Commission has reviewed the above-referenced document and offers the following comments.
Page 1 of ff. This combined statement and Case Report repeatedly refers to the Blackstone Canal as an archaeological feature. While in several locations in Rhode Island the canal survives only as an archaeological feature, the section contained in Paul Ronci Memorial Park is notable as a largely-intact engineering structure. It is not an archaeological feature, except in the more limited sense of an industrial archaeological feature. It consists of the water-filled trench, formed by both embankment and excavation, and the towpath bank on the eastern side. There was only one towpath built for the canal (not two), and this structure has become the basis of the present BVE maintenance road. The canal trench and towpath embankment are both integral components of the canal.
As a clarification of certain historical and geographical facts, the canal was constructed in the third decade of the 19th century (page l) and the section in Paul Ronci Memorial Park has its southern terminus at Front Street in Lonsdale, not Saylesville (pp. 2 and 3).
Mr. James R. Capaldi August 14, 1987 RI Dept. of Transportation Paqe -2
With regard to the proposed mitigation for the adverse visual impacts to the Blackstone Canal created by the bridge replacement, the Rhode Island Historical Preservation Commission concurs that appropriate treatment of the new pier and abutments surfaces and appropriate landscaping in the immediate area can be sufficient. We feel that it is important that these mitigation measures should harmonize with the existing character of the site. Masonry or rough surfaces and rustification to simulate masonry would be appropriate surface treatment for the bridge pier and abutments. The rubble stone retaining walls on the towpath embankment should employ stone similar in appearance to the local stone.
Thank you for the opportunity to comment.
Very- truly y-purs,
< _dward FA Sanderson Executive Director Deputy State Historic Preservation Officer
cc: Anne Dowd
TARGET SHEET
THE MATERIAL DESCRIBED BELOW WAS NOT SCANNED BECAUSE:
(X) OVERSIZED
() NON-PAPER MEDIA
() OTHER:
DESCRIPTION: DOC #17058 PLATE III (3), GENERAL PLAN.
THE OMITTED MATERIAL IS AVAILABLE FOR REVIEW BY APPOINTMENT
AT THE EPA NEW ENGLAND SUPERFUND RECORDS CENTER, BOSTON, MA
TARGET SHEET
THE MATERIAL DESCRIBED BELOW WAS NOT SCANNED BECAUSE:
(X) OVERSIZED
() NON-PAPER MEDIA
() OTHER:
DESCRIPTION: DOC #17058 PLATE IV (4), PROFILE, RELOCATED MARTIN STREET.
THE OMITTED MATERIAL IS AVAILABLE FOR REVIEW BY APPOINTMENT
AT THE EPA NEW ENGLAND SUPERFUND RECORDS CENTER, BOSTON, MA
TARGET SHEET
THE MATERIAL DESCRIBED BELOW WAS NOT SCANNED BECAUSE:
(X) OVERSIZED
() NON-PAPER MEDIA
() OTHER:
DESCRIPTION: DOC #17058 PLATE V (5), PLAN, SECTIONS AND ELEVATIONS, CANAL EMBANKMENT AREA.
THE OMITTED MATERIAL IS AVAILABLE FOR REVIEW BY APPOINTMENT
AT THE EPA NEW ENGLAND SUPERFUND RECORDS CENTER, BOSTON, MA