report by the comminee assessing fuel storage part 2 ... · appendix j retrievability j-1 1...
TRANSCRIPT
![Page 1: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/1.jpg)
AECL-5959/2
ATOMIC ENERGY W É F & L'ÉNERGIE ATOMIQUEOF CANADA UMITED E f i j F DU CANADA LIMITÉE
REPORT BY THECOMMinEE ASSESSING FUEL STORAGE
PART 2: APPENDICES
| Edited by W. W. Morgan
Whiteshell Nuclear Research Establishment
Pinawa, Manitoba, ROE 1LO
November, 1977
(work completed 1972-1974 )
![Page 2: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/2.jpg)
ATOMIC ENERGY OF CANADA LIMITED
REPORT BY THECOMMITTEE ASSESSING FUEL STORAGE
PART 2: APPENDICES
Edited by W.W. Morgan
Whiteshsll Nuclear Research Establishment
Pinawa, Manitoba, ROE 1LO
November, 1977 AECL-5959/2
(Work completed 1972-1974)
![Page 3: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/3.jpg)
Rapport du Comité d'évaluation du stockage du combustible
2ieme P a r t i e : Appendices
édité par W.W. Morgan
Résumé
On a envisagé divers concepts de stockage intérimaire pour
le combustible nucléaire irradié. Des études préliminaires ont été faites
et des devis estimatifs ont été préparés pour les concepts suivants: deux
à refroidissement par eau - stockage prolongé en bassin près d'une centrale
nucléaire et stockage en bassin dans un établissement central; trois à
refroidissement par air dans un établissement central - "cartouche en béton",
"cavité à convection" et "cavité à conduction" - et un projet de stockage
souterrain dans du sel gemme. Les coûts estimés en dollars de 1972 compren-
nent les frais de transport et un fonds destiné à l'entretien perpétuel et
au renouvellement périodique des installations de stockage. La 1 Partie
de ce rapport est le sommaire des résultats obtenus. La Partie 2 donne des
précisions au sujet des concepts et des méthodes employés pour évaluer les
coûts. Les coûts de tous les concepts étudiés se sont révélés modestes
puisqu'ils ne s'élèvent qu'à environ 0.1 m$/kWh dans le coût unitaire de
l'énergie. Les avantages et les inconvénients des différents concepts sont
comparés entre eux.
L'Energie Atomique du Canada, Limitée
Etablissement de Recherches Nucléaires de Whiteshell
Pinawa, Manitoba, ROE 1L0
Novembre 1977
AECL-5959/2(Travaux effectués de 1972 à 1974)
![Page 4: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/4.jpg)
REPORT BY THE COMMITTEE ASSESSING
FUEL STORAGE. PART 2: APPENDICES
Edited by W.W. Morgan
ABSTRACT
Various concepts for interim storage of spent nuclear fuel have
been considered. Preliminary design studies and cost estimates have been
prepared for the following concepts: two with water cooling - prolonged
pool storage at a generating station and pool storage at a central site - ,
three with air cooling at a central site - "canister", "convection vault",
and "conduction vault" - and one underground storage scheme in rock salt.
Costs (1972 dollars) were estimated including transportation and a perpetual
care fund for maintenance and periodical renewal of the storage facility.
Part 1 of this report summarises the findings. Part 2 provides details of
the concepts and costing methods. All concepts gave moderate costs providing
a contribution of about 0.1 m$/kWh to the total unit energy cost. Advantages
and disadvantages of the respective schemes are compared.
Atomic Energy of Canada Limited
Whiteshell Nuclear Research Establishment
Pinawa, Manitoba ROE 1L0
November, 1977 AECL-5959/2
(Work completed 1972-1974)
![Page 5: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/5.jpg)
FOREWORD
by
M. Tomlinson
This report covers certain aspects of an early phase in the
formulation of the program for long-term management of nuclear waste.
Since the material was of an exploratory and preliminary character, the
report was prepared with a view to internal use only and was initially
issued as an internal report. Since then, we have reported our findings
in various publications. Because of recent widespread interest in interim
fuel storage, the entire report is being published so that the full details
of the work may be generally available. It should be noted that consider-
able further evolution has occurred in concepts and strategies of spent
fuel management so that those depicted here do not necessarily correspond
with those of the present. The hereditary influence is nevertheless
powerful.
Individual authors are indicated in those sections which were
primarily the work of the one or two individuals named. Other sections
were the work of many people or of the committee as a whole.
![Page 6: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/6.jpg)
MEMBERSHIP OF CAFS
S.R. Hatcher
W.W. Morgan
J.A. Morrison
W.R. Taylor
J.C. Tremblay
A. Duchesne
R.W. Barnes
I. Lauchlan
ff.M. Campbell
D. Radojkovic
D.R. McLean
J.R. Coady
M.M. Ohta
R.V. Baker
WNRE, Chairman (-1)
WNRE, Chairman
CRNL
CRNL
Hydro Quebec
Hydro Quebec
Ontario Hydro
Ontario Hydro
PPSP
PPSP
WNRE
WNRE
WNRE
WNRE, Secretary
Many others made significant technical contributions. The
work of E.W. Fee, PPSP, R. MacFarlane, WNRE, C. Purdy, CRNL, S.C. Bhatia,
a CIDA fellow from the Bhabha Laboratories, and R. Wilson, Ontario Hydro,
was particularly helpful.
01) S.R. Hatcher was the original chairman of CAFS, but resigned in June
1973 to carry out a special assignment at Bruce Heavy Water Plant.
![Page 7: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/7.jpg)
CONTENTS
Page
APPENDIX A GROUND RULES AND DATA REQUIRED FOR THE A-lCAFS STUDY
1 GROUND RULES A-l1.1 General Conditions for the
Storage of Spent Fuel A-l1.2 Scope of the Present Investigation A-21.3 The Fuel A-21.4 Financial Aspects A-21.5 Siting A-3
APPENDIX B TECHNIQUES USED IN ESTIMATING STORAGE COSTS B-l
1 ESTIMATION OF STORAGE CHARGES, $/kg U B"l1.1 Derivation.of Storage Cost Equation B-l1.2 Comments on the Use of the Storage B-5
Cost Equation2 ESTIMATION OF INVESTMENT REQUIRED IN B-6
PERPETUAL CARE FUNDS2.1 Derivation of Sinking Fund Equation B-62.2 Form of Equation for Future B-7
Operating Costs2.3 Form of Equation for Withdrawals at B-8
50 Year Intervals2.4 "F" Values for 100 Year Care and B-9
Perpetual Care2.5 General Comments on the Use of B-9
Perpetual Care Funds
APPENDIX C THE TOXIC LIFE OF SPENT CANDU FUEL C-l
APPENDIX D STORAGE OF SPENT FUEL IN WATER-FILLED BASINS D- 1AT A CENTRAL SITE
1 GENERAL DESCRIPTION D- 12 COST SUMMARY D-3
2.1 Summary of Capital Costs D- 32.2 Storage Baskets D-42.3 Summary of General Operating Costs D" 42.4 Perpetual Care Costs D" 52.5 Levelized Costs, $/*kg U for Capital, D~ 6
Operating and Perpetual Care2.6 Shipping D- 6
![Page 8: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/8.jpg)
2.7 Public Relations and Site Selection D-62.8 Total Costs for Management of Spent D-6
Fuel in Basins3 GENERAL COMMENTS ON POOL STORAGE D-6
APPENDIX E STORAGE OF SPENT FUEL IN WATER POOLS AT E-lREACTOR SITES
SUMMARY OF STUDY1.1 Introduction1.2 Design Basis1.3 Long-Term Facility1.4 Short-Term Facility1.5 Possible Design Improvements
SUMMARY OF COST2.1 Cost Estimate for Long-Term
Facility2.2 Cost Estimate for Short-Term
FacilitySAFETY ASSESSMENT3.1 Activity in Spent Fuel3.2 Containment of Activity3,3 Activity Release Paths
CONCLUSIONS AND RECOMMENDATIONS4.1 Conclusions4.2 Recommendations
SUPPLEMENTARY DATA5.1 Special Ground Rules for this
Project5.2 Design Criteria for Short-Term
Facilities
E-lE-lE-3E-6E-8E-9E^IOE-10
E-13
E-13E-13E-14E-14E-15E-15E-15E-16E-16
E-18
APPENDIX F STORAGE OF SPENT CANDU FUEL IN CONCRETE F-lCANISTERS
12
INTRODUCTIONGENERAL DESCRIPTION2.12.22.3
2.42.5
CanistersFuel Handling at the Reactor SiteFlask and Canister Handling at theCentral Storage SitePersonnel RequirementsOverall Schedule
COST SUMMARY3.13.23.33.4
3.5
Capital CostsAnnual Operating CostsPerpetual Care CostsLevelized Storage Price at CentralSite - $/kg UPenalty for Storage for Four ExtraYears
F-lF-lF-1F-2F-3
F-5F-5F-6F-6F-7F-7F-8
F-8
![Page 9: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/9.jpg)
3.6 Shipping3.7 Development Costs3.8 Total Cost for Management of Spent
Fuel in Concrete CanistersGENERAL COMMENTS ON CANISTER STORAGE
F-9F-9F-9
F-9
APPENDIX G STORAGE OF SPENT FUEL IN LARGE AIR-COOLED VAULTS G-l
1 INTRODUCTION G-l2 REACTOR SITE OPERATIONS G-23 CENTRAL STORAGE FACILITIES G-34 CONVECTION SCHEME VAULT G-45 CONDUCTION SCHEME VAULT G-46 GENERAL STORAGE CONSIDERATIONS G-57 DEVELOPMENT REQUIRED G-68 ESTIMATED COSTS G-79 CONCLUSIONS G-8
APPENDIX H THE STORAGE OF SPENT CANDU FUELS IN SALT MINES
INTRODUCTIONGENERAL CONCEPTS2.1 Mine Layout
Mining OperationsWaste HandlingPersonnel RequirementsOverall Schedule
2.22.32.42.5
COSTS3.13.23.33.43.5
Initial InvestmentSalt Mining and Salt Disposal CostsSpent Fuel Handling CostsPerpetual Care CostsLevelized Costs, $/kg U for Capital,Operating and Perpetual Care
3.6 Penalty for Four Extra Years ofStorage
3.7 Shipping3.8 Development Costs3.9 Total Cost for Mangement of Spent
Fuel in Salt MinesGENERAL COMMENTS ON SALT STORAGEREFERENCES
H-l
H-1H-2H-2H-3H-3H-4H-5H-5H-6H-6H-6H-711-7
H-8
H-8H-8H-8
H-9H-12
APPENDIX I TRANSPORTATION1 INTRODUCTION2 DISTRIBUTION OF CANADIAN SPENT FUEL
ARXSINGS IN THE YEAR 20003 SHIPPING SYSTEM
3.1 General Assumptions3.2 Flask and Unit Train Requirements
1-11-11-1
1-11-21-2
![Page 10: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/10.jpg)
COSTS1.4.1 Capital Costs1.4.2 Unit Shipping Costs1.4.3 Weighted Average Shipping Costs
for More Than One SiteSUMMARYRECOMMENDATIONS
1-21-21-21-3
1-41-4
APPENDIX J RETRIEVABILITY J-1
1 INTRODUCTION J-12 PROJECTED ARISINGS OF SPENT CANDU FUEL J- 23 STORAGE REQUIREMENTS J-34 CONSEQUENCES OF REHANDLING J- 45 EMERGENCY RETRIEVAL J-4
J.5.1 Standby Storage J-5J.5.2 Relocation Time J- 5
6 OBSERVATIONS J-6
![Page 11: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/11.jpg)
A-l
APPENDIX A
GROUND RULES AMD DATA REQUIRED FOR THE CAFS STUDY
1. GROUND RULES
A great deal of attention was given to arriving at an
acceptable set of ground rules for the project.
The main aim was to tie all the separate studies together,
giving them a common set of guidelines. Some of these were derived
directly from the report of the Radioactive Waste Management Committee
while others were arrived at during the meetings.
The ground rules are summarized below:
It was recognized that special sub-sets of rules might have to be
introduced for specific design studies, for example, a stipulation with
regard to water table could not be made that would satisfy engineered
storage both on the surface and in a salt bed.
1.1 GENERAL CONDITIONS FOR THE STORAGE OF SPENT FUEL
1. In all studies, safety will be the prime concern.À full safety analysis is not required for the initialstudies but obvious accident occurrences should be bornein mind. These should be documented in order to assistthe later safety analyses.
2. The fuel will not be reprocessed.
3. The stored fuel must be retrievable.
4. Release of active solids, liquids, and gases to theenvironment must be as small as possible.
![Page 12: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/12.jpg)
A-2
5. Ownership and operation of the storage facility will beassumed to be under control of the Federal Government.
6. Ownership of the fuel will be transferred from the utilityto the government at the reactor site.
1.2 SCOPE OF THE PRESENT INVESTIGATION
1. Only fuel discharged up to the year 2000 will be consi-dered.
2. All the fuel will be stored at one central site.
3. All known defected bundles will be canned before storage.
4. It must be possible to locate and can bundles which defectduring storage.
5. Adequate and sufficient supervision of the facility willbe provided at all times.
1.3 THE FUEL
X. Standard Pickering type fuel will be used.
2. Burnup will be taken as 9000 MW.d/Mg U.
3. All fuel will be cooled for one year at the reactor site.The cost of any extra cooling required by a particularmethod will be included in the price of that method.
4. The quantities of fuel involved will be as shown in Table 1.
5. The heat characteristics of the fuel will be as shown inFigure 1.
1.4 FINANCIAL ASPECTS
1. A perpetual fund must be set up to allow for maintenancesurveillance and replacement of the facility as necessaryin perpetuity.
See the note on perpetual care funds in Appendix B.
2. The cost will be expressed as a levelized price so as tobe independent of the date of storage.
![Page 13: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/13.jpg)
A-3
3. All money used for capital will be borrowed at 7%.
4. Money invested up to the year 2000 will be at a 7% return.
5. Escalation during construction will be 4% per annum.
6. Interest on the perpetual fund beyond 2000 will be 7% perannum.
7. Escalation beyond 2000 will be at 4% per annum.
8. All values will be expressed in 1972 Canadian dollars.
1.5 SITING
1. The location of the central storage site will be definedby taking a fixed shipping charge FOB the storage site.
2. Access by road and rail and availability of power can beassumed.
3. Optimistic conditions can be assumed for items such aswater table, excavation, and foundations.
REFERENCE
CO H.B. Merlin, Energy Consumption its Growth and Pattern, Atomic Energy
of Canada Limited Report, AECL-3293, March 1969.
![Page 14: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/14.jpg)
A-4
TABLE 1
ACCUMULATION OF SPENT CANDU FUEL TO THE YEAR 2 0 0 0 ^
Date
1971
1972197319741975
197619771978(ii)19791980
19811982198319841985
19861987198819891990
19911992199319941995
19961997199819992000
Quantity of 1-Year-Cooled
Fuel to be Stored at Central Site (Mg)
Annual
23
5496
154239
324401471556648
741895
104912341466
16981975226925772917
32413627401243214706
50155324563259416327
Cumulative
23
77173327566
8901291176223182966
37074602565168858351
1004912024142931687019787
2302826655306673498839694
4470950033556656160667933
Note: (i) Based on nuclear power forecasts by Merlin in 1969 .
(ii) The first shipments of spent fuel are to be received at thecentral site in 1978. Spent fuel produced prior to that datewill be stored temporarily at reactor sites. The backlog willbe shipped to the central site over a 5 year period beginningin 1978.
![Page 15: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/15.jpg)
DECAY HEAT (watts/ Mg U)
omo
S70(A
m §_ o
c
nCm
toooo
c
![Page 16: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/16.jpg)
B-l
APPENDIX B
TECHNIQUES USED IN ESTIMATING STORAGE COSTS
1. ESTIMATION OF STORAGE CHARGES, $/kg U
1.1 DERIVATION OF STORAGE COST EQUATION
1.1.1. PRESENT WORTH CONCEPT
The present worth concept was used to calculate the storage
charges for spent fuel from basic capital, operating and perpetual care
cost data. It is a concept frequently used in economic evaluations and
provides the basis for a simple algebraic relation between income and
cost. The basis is the time value of money.
Consider for example, a $1 million expenditure to be made 10
years hence. Assume an investment is to be made at time zero, earning
interest at 7% compounded annually, to cover this cost. The size of the
investment required is:
$1 million x = $0.5 million
C1.O7)10
The $0,5 million is the net cost expressed at time zero or the "present
worth" of the future expenditure.
If expenditures are to be made at different dates in the
future, the present worth of each one can be determined in a similar
manner. The results may then be summed to get the combined present
value of these future expenditures.
![Page 17: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/17.jpg)
B-2
In a similar way, the present value of future incomes may be
calculated. If these incomes are to be used to pay future costs, the sum
of their present worths should equal the present worth of the future
expenditures. This may be expressed algebraically as:
EPWIncomes= ZPWCosts ^
This is the basic relationship used to calculate storage charges for spent
fuel.
1.1.2 PRESENT WORTH OF INCOME FROM FUEL ARISINGS
At a fuel storage site, the income in any year "n" taay be
expressed as follows:
I = S x F 1.2n z n
where I = income in year "n", S = storage price, $/kg U, in time zeron zdollars and F = fuel arisings, kg U, in year n.
The present worth of all the future incomes then becomes:
ZPWT = PW(S F ) + PW (S F ) + (S F ) + PW (S F ) 1.3Incomes z o z i z z z t
where t = year in which the site is filled with fuel and hence is the
final year in which there is income from fuel arisings.
Equation 1.3 can be rearranged:
EPWIncomes = Sz[PW(Fo) + P W ( V + PW(F2>+---+ P W < V ] 1.4
= Sz(£PWF) 1.5
1.1.3 PRESENT WORTH OF STORAGE SITE COSTS
The basic costs incurred at the storage site are capital,
operating and perpetual care. Capital and operating expenditures occur
![Page 18: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/18.jpg)
B-3
over the site filling period. Perpetual care costs are treated as a lump
sum expenditure required in the final year of the filling period to set
up a sinking fund to take care of all future costs. The method used in
calculating the size of fund required is described in Section 2 of this
appendix. The equation for the present worth of the costs is:
PW = ZPW + ZPW + PW n ,
costs c o p 1.6
where the subscripts c, o and p refer to capital, operating and perpetual
care respectively.
Substituting equations 1.7 and 1.6 in equation 1.1 and solving
for S yields
ZPW + ZPW + PWS =z F
The denominator is the sum of the present worth of the fuel arisings
which has no meaning in an economic sense but is valid in an algebraic sense.
1.1.4 ALLOWANCE FOR ESCALATION IN PRESENT WORTH ANALYSES
Normally in present worth analyses, escalation of costs is
ignored because of the difficulty in forecasting escalation trends. It is
assumed that all costs and incomes will escalate at the same rate, and
therefore the effects of escalation cancel out. This assumption however
is not always valid.
If, in the example of the $1 million expenditure discussed
earlier, costs escalate at the rate of 4% per year, the investment required
at time zero to cover the escalated cost would be
(1 04^10
$1 million x KX'W ' = $0.74 million
(1.07)ao
Thus, an additional $0.24 million is required in the initial investment.
![Page 19: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/19.jpg)
It should be noted in this calculation that the escalation and
interest factors appear as a ratio, 1.04/1.07. The value of this ratio is
primarily dependent on the net difference between the two rates rather than
on absolute values. This is illustrated in Table 1.
Thus in spite of substantial variations in i and e, for a fixed
net difference, the value of the ratio (TZT)11 i s essentially a constant.
This is further illustrated in Table 2 when the net difference is fixed
at 2%.
This observation eases one of the difficulties in making economic
evaluations, which is choosing suitable escalation and interest rates. The
task becomes one of estimating a reasonable value for the net difference,
or determining the sensitivity to different values of the net difference.
The change in the value of the ratio (TTT) 1 0 is illustrated in
Table 3 for a difference of 2%, 3% and 4%. Even here the effect is not large.
1.1.5 FINAL FORM OF STORAGE COST EQUATION
After analyzing the cost data for one of the storage schemes,
it became evident that an allowance should be included for escalation.
Including escalation effects, the final detailed form of equation 1.8 for
calculating the storage price is:
n=t .. n n=t£ C (4rf) + S Czn 1+i
s _ n=o n^o 1.8z
where S = storage price, $/ kg U, in time-zero dollars that will escalateat the same rate as costs,
Z • indicates time-zero dollars,
n = number of years from time zero. Time zero is the date used forestimating costs in fixed-time dollars. It may or may not bethe same date that the first shipments of spent fuel are shippedto the site. (For CAFS studies it was assumed that the firstfuel is shipped in ,1978, six years beyond time-zero).
![Page 20: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/20.jpg)
B-5
t = number of years elapsed from time zero until all the storagefacilities at the site are filled (i.e., 28 years from 1972 toyear 2000 or from 1982 to 2004 for CAFS studies).
C = capital costs in time-zero dollars spent in year n.
0 = operating costs in time-zero dollars spent in year n.
P = size of perpetual care fund expressed in time-zero dollars thatz will be required in year t (year 2000 or 2004 for CAFS studies)
to cover all future costs including future escalation. Themethod used for estimating F is described in Section 2 ofthis appendix. z
F = fuel, kg U, placed in storage in year n.
e = annual escalation rate, % (used in equation as a decimal fraction).
1 = annual interest rate, %, for both borrowed and invested money(used in equation as a decimal fraction).
1.2 COMMENTS ON THE USE OF THE STORAGE COST EQUATION
( 1. To utilize equation 1.8, a schedule of spending expressed in! time-zero dollars is required. The use of time-zero dollars: in the schedule provides an indication or measure at any time. of the quantity of goods and services being purchased. However,: for borrowing or investment purposes, it is necessary to usej real dollars since interest charges or earnings in actualI practice are based on the flow of the actual number of real' dollars. Time-zero dollars are automatically converted to real
dollars in the equation assuming escalation at e% per year.
2. Capital expenditures for any phase of site development must beshown on an annual basis and not as a Jump sum at the end ofeach construction period. The costs must be expressed in time-zero dollars without any allowance for escalation or interestcharges during construction. These charges are automaticallyincluded in the equation.
3. The expenditure required for perpetual care is shown as a singleitem, P , in year t (i.e., the year in which all the storagefacilities are completely filled). The equation is based onthe premise that surplus funds (i.e., excess of income overexpenses) are invested each year at interest rate i and thatthe total surplus funds plus interest earnings will equal therequired amount of real dollars in year t for perpetual care.
![Page 21: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/21.jpg)
B-6
4. The net difference between interest and escalation rates chosenfor CAFS was 3%. This was arrived at from a comparison of thecorporate borrowing rates and inflation rates in the CanadianGross National Product over a period extending from 1926 to 1969.The average net difference over this 43 year period was 3%.The absolute values of interest and escalation rates used inCAFS as specified in the ground rules is 7% and 4% respectively.These values are low compared with current rates, but we assumedthey would be more realistic for the long term than the currenthigh rates. In any case it is the net difference between theinterest and escalation rates that really matters. Our mainconcern was to adopt a standard approach for estimating thestorage price for all the storage schemes for comparisonpurposes.
5. A breakdown of the storage price, S , to determine the relativecharges for capital, operating and perpetual care can be obtainedby dividing the present worth of each of these main cost itemsby the total present worth of all the costs.
6. A computer program was prepared by the Systems Analysis Branchat WRNE utilizing this type of equation for the calculation oftotal unit energy costs for power produced by nuclear reactors.This program can also be used to calculate tne storage price forspent fuel by adjusting the inputs.
2. ESTIMATION OF INVESTMENT REQUIRED IN PERPETUAL CARE FUNDS
The present worth technique discussed in Section 1 of this
appendix is also utilized here. A general equation is derived for a
sinking fund from which withdrawals may be made at regular intervals.
2.1 DERIVATION OF SINKING FUND EQUATION
Once a storage site hafc beefc filled with spent fuel, there is
no longer any new income. One way of paying for future costs of surveillance,
maintenance and other costs is through the establishment of sinking funds
which will generate sufficient interest earnings to cover these costs as
they escalate with time. Assuming that future costs can be estimated in
fixed-time dollars and occur at regular intervals, the sum of the present
worth of these costs is the size of investment required to meet them.
![Page 22: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/22.jpg)
B-7
Let P = present worth of future costs = principal to be invested initially,
C = cost, in fixed-time dollars,, to be paid out in intervals,
H = interval in years between payments,
n = number of payments to be made,
e = annual escalation rate - % (use in equation as decimal fraction),
i = annual interest - % earned by fund (use in equation as a decimal
fraction),
R = ratio of escalation and interest = TTT, e.g. y Tyr»
F = ratio of P to C i.e. F = P/C.
Then
or P = C(RA + Rz£ + R3* +...-Rnl) 2.1
The R terms in this equation form a geometric progression with
an initial term of R and a multiplier of R for which the sum is
1-R*
Thusi-r-
This is the general form of the equation and it may be observed
tnat the size of the fund P, is a function of the ratio of ~T+t' A s shown
in section 1, the value of this ratio is primarily dependent on the net
difference between the interest and escalation rates and not on the absolute
values. Thus the size of the initial investment is essentially a function
of the net Interest rate (i-e).
2.2 FORM OF EQUATION FOR FUTURE OPERATING COSTS
Assuming annual withdrawals are made from a sinking fund, P ,
to cover annual operating costs, C , then
![Page 23: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/23.jpg)
B-8
and P = C U\~l } 2.3o o 1-R
or P = P F (Note P and C are expressed in time-zero dollars).o o o o
The sensitivity of F and hence P to the length of time in the
future over which operating costs must be paid and their sensitivity to
different values of i-e are shown in Table 4.
For a given value of n as i-e increases, F and therefore P
decrease. This effect is expected. Larger values of i-e mean larger net
interest rates and as a result the size of the initial investment required
is reduced. For conservative estimating purposes it is better to pick a
value of i-e that is on the low side to ensure that sufficient funds are
invested initially.
For a given value of i-e, the F value increases as n, the life
of the fund, increases up to 200 years. Leyond that time F is essentially
constant. Thus the size of sinking fund required for perpetual care is
nearly the same as that required for 200 years of care.
reduces to
For the case of perpetual care(n=»), R — K ) , and equation 2.3
C R o .
„ = _g . 2.4o 1-1R
2.3 FORM OF EQUATION FOR WITHDRAWALS AT 50 YEAR INTERVALS
In the surface storage schemes studied by CAFS, a vault service
life of 50 years was assumed. Therefore a sinking fund is required that
will pay the cost of replacing site facilities at 50 year intervals. For
this case, £«50 and equation 2.2 becomes
![Page 24: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/24.jpg)
B-9
or P r = C r x F 5 0
where C = replacement cost in time-zero dollars for replacingr facilities at each 50 year interval.
For use of a particular scheme in perpetuity, n*°° and R K),
and equation 2.5 becomes
R 5 0
P = C -S-^TT 2.6r r 1-R50
2.4 "F" VALUES FOR 100 YEAR CARE AND PERPETUAL CARE
In the CAFS study, sinking funds for all future costs were
calculated assuming a 3% net difference between escalation and interest.
The corresponding F values for funds set up to care for wastes for a
period of 100 years, and for perpetual care are shown in Table 5.
2.5 GENERAL COMMENTS ON THE USE OF PERPETUAL CARE FUNDS
1. It is important to recognize that perpetual care costs derivedin the manner described above are theoretical costs based on aset of assumptions about future costs, interest rates andescalation rates. They provide one means of determining thecost of managing wastes for their hazardous life. This techniquealso provides a basis for comparing the future costs of differentstorage schemes.
2. Establishment of perpetual care funds provides a method wherebycharges for waste management could be placed against the cost ofproducing electrical power at the time it is produced.
3. The use of sinking funds to pay for future costs is not withoutprecedent. Two common examples are life insurance and pensionfunds. However, the time scales involved are drastically different.It is not credible to assume that perpetual care funds could bemanaged successfully over the hazardous life of spent fuel. Inview of this factor, geologic storage schemes are very attractivesince it appears that operating and surveillance costs may benegligible once mines have been backfilled and sealed.
![Page 25: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/25.jpg)
B-10
TABLE 1
3% NET DIFFERENCE BETWEEN ESCALATION AND INTEREST
e %
i %
Comparison:
0.
0.
2
5
7484
995
0.
1.
4
7
7525
00
0.
1.
6
9
7565
005
0.
1.
8
11
7603
01
TABLE 2
2% NET DIFFERENCE BETWEEN ESCALATION AND INTEREST
e %
i %
1+e 1 0
Comparison:
0
0
2
4
.8235
.996
0
1
4
6
.8265
.00
0.
1.
6
8
8295
003
0
1
8
10
.8323
.007
TABLE 3
COMPARISON
e %
i %
(~\"
Comparison
OF
0.
1.
2%, 3%
4
6
8265
1
AND
0
1
4% NET
4
7
.7525
.0
DIFFERENCE
4
8
0.6856
.91
![Page 26: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/26.jpg)
B-ll
TABLE 4
"F" VALUES FOR ANNUAL OPERATING COST FUND
Life of FundCYears)
n
50100200
Values of "F"
i-e=0.02
32.67 '"45.3952.2753.49
i-e=0.03
27.0633.5935.5435.66
i-e-0.04
22.7626.1626.7326.74
TABLE 5
"F" VALUES FOR 3% NET DIFFERENCE BETWEEN INTEREST AND ESCALATION
Time Interval BetweenWithdrawals from Fund
Of ears)
125102050
100
F Factor
100 YearCare
32.715.96.142.871.230.300.058
PerpetualCare
35.716.96.523.051.310.3180.062
![Page 27: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/27.jpg)
C-l
APPENDIX C
THE TOXIC LIFE OF SPENT CANDU FUEL
The activity of spent fuel diminishes with time and therefore,
in general, so does the toxicity. This raises the possibility that at
some time in the future the fuel may no longer be considered a potential
hazard.
The period of time for which spent fuel is considered a potential
hazard has been defined as the "toxic life" of the fuel. It is necessary to
have an appreciation of how long this might be in order to determine the kind
of precautions that must be taken to ensure its containment.
One method of assessing the toxic life is to compare the toxicity
of spent fuel, at various times to the toxicity of other similar materials
such as natural uranium and uranium mill tailings. Such comparisons take no
account of the consequences of a release of spent fuel to the biosphere nor
do they consider the pathways by which a release might take place. They can,
however, provide a useful perspective for assessing, on a weight for weight
basis, the toxicity of spent fuel in relation to materials which are more
familiar and for which the need for special precautions is well recognized.
The toxicity of radioactive materials is usually measured in
terms of the volume of water or air that would be required to dilute a given
amount of the material to the maximum concentration allowed for the general
public. Graphs of this toxicity index versus time for CANDU fuel are shown
in Figures 1 and 2. Both graphs show that fission product decay is
essentially complete In less than 1000 years. This is because the principal
components, strontium-90 and cesium-137, have half-Jives of t>30 years.
Actinide activity, however, is of much longer duration;, due to the plutonium
and americium present, and reaches a minimum in about 250,000 years. This
![Page 28: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/28.jpg)
\
C-2
level is then maintained for many millions of years; in the case of air
toxicity, for over a thousand million years.
As indicated in Figures 1 and 2, and Table 1, the toxicity of
irradiated fuel eventually reaches the same level as that attained by un-
irradiated fuel. This occurs after approximately a quarter of a million
years when the toxicity of both materials is essentially that of uranium-238
in equilibrium vith its daughter products. At this level they are as much
as 100 times more toxic than freshly separated uranium and up to 2000
times higher in toxicity than uranium ore. Perhaps the most significant
comparison that can be made, however, is with respect to the tailings produced
from uranium mining operations. The lowest level of toxicity ever reached
by Irradiated fuel is still as high as 2000 times the toxicity of the tailings
pile created at the mine when the uranium was first produced. The problems
associated with the containment of these piles are well known.
The materials used in these comparisons are all potentially
dangerous in their own right and there are regulations covering their handling
and storage. The significance of the comparisons, therefore, is that at no
time is the toxicity of spent fuel lower than the toxicity of the other materials.
It is also significant that the lowest toxicity of spent fuel occurs only
after approximately a quarter of a million years.
There are other substances having chronic toxicity to which
spent fuel can also be compared. Examples of these, as shown in Figures
3 and 4, are the heavy metal poisons, lead and mercury. Both are well
known and both are widely distributed in the environment as pollutants.
These graphs should not be used to draw firm conclusions as to the relative
hazards of radioactive and non-radioactive materials. They do demonstrate,
however, that when these different materials are compared, using the same
units, they appear to be similar in potential hazard. This is in contrast
to the popularly held belief that radioactivity demands far greater attention
than any other form of toxicity.
^Average values obtained from the ratios given in Table 1.
![Page 29: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/29.jpg)
C-3
The graphs also clearly show that while some amelioration of
the total potential hazard present in radioactive materials can be expected
with the passing of time, no such change occurs with elemental poisons.
Their toxicity, with which society seems to have come to terms, remains
the same forever.
Although spent fuel undergoes a significant reduction in
toxicity, eventually reaching a level which in the case of water is well
below that of both mercury and lead, it is obvious that it never really
reaches a level that could be considered non-hazardous. As shown in Figure
1, even when the long lived uranium has all decayed, stable lead isotopes
produced from the uranium still represent a significant potential hazard.
It is clear, however, that after about 250,000 years there is no longer
any decrease in toxicity. Therefore, with these considerations in mind,
the toxic life of spent CANDU fuel can be said to be at least a quarter
of a million years.
![Page 30: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/30.jpg)
C-4
TABLE 1
COMPARISON OF TOXICITIES*
SPENT FUEL; UNIRRADIATED FUEL; ORE; TAILINGS
a)
b)
c)
d)
e)
F u e l ( 2 1 6 M W h / k g )( 0 2 5 0 , 0 0 0 a )
S e p a r a t e d U r a n i u m( @ t i m e z e r o )
S e p a r a t e d U r a n i u m( < 3 2 5 0 , 0 0 0 a )
U r a n i u m O r e( @ 2 5 0 , 0 0 0 a )
T a i l i n g s ( 9 5 % E x t r a c -t i o n ( @ t i m e z e r o ) )
R A T I O S
a/b
a/c
a/d
a/e
W A T E R
SOLUBLE(mVkg)
3.2
6.4
3.4
4.4
4.3
50
0.9
730
740
x 1 0 "
x 1 0 z
x 1 0 1 *
x 1 0 1
x 101
T O X I C I T Y I N D E X
INSOLUBLE(mVkg)
1.2
2.0
8.0
6.0
6.0
6.0
1.5
20
20
x 1 0 2
x 1 0 2
x 1 0 1
S O L U B L E(mVkg)
1 . 2 . x 1 0 1 0
1 . 3 x I f , 8
4 . 8 x 1 0 9
5 . 6 x 1 0 6
5 . 4 x 1 0 6
96
2»6
2 1 0 0
2 2 0 0
AIR
I N S O L U B L E( m 3 / k g )
1 . 6 x 1 0 9
1 . 5 x 1 0 8
1 . 3 x 1 0 9
1 . 7 x 1 0 6
1 . 5 x 1 0 6
11
1.3
940
1 1 0 0
* C A N I G E N , J u n e 1 9 7 4
** D i l u t i o n r e q u i r e d t o r e d u c e 1 k g o f m a t e r i a l t o m a x i m u m p e r m i s s i b l ec o n c e n t r a t i o n i n w a t e r o r a i r a s r e c o m m e n d e d b y t h e I n t e r n a t i o n a lC o m m i s s i o n o n R a d i o l o g i c a l P r o t e c t i o n ( I C R P ) f o r t h e g e n e r a l p u b l i c .
*** " T y p i c a l " u r a n i u m o r e i s a s s u m e d t o c o n t a i n 0 . 1 % u r a n i u m a n d 0 . 0 3 % l e a d .
![Page 31: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/31.jpg)
103 - r
102 - r
101
10"2
T| I"mTTTT| ' ' ' Mill)
•TOTAL (ACTINIDES + FISSION PRODUCTS)
i ii in>| r-rr f Mill I I I TTTTa
SPENT FUEL - ACTINIDES
SPENT FUEL - FISSION PRODUCTS
FRESHLY SEPARATEDNATURAL URANIUM
r URANIUM ORE
103
TIME (years)
FIGURE 1. RELATIVE TOXICITY OF SPENT CANDU FUEL IN WATER
![Page 32: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/32.jpg)
<o
1011 - r
1e9
) J nui) 1 ) i i)iii| i i r IIIIT] r i i riinj 1—i i iinrj 1—i mm) 1 i 11 ini[
TOTAL (ACTINIDES + FISSION PRODUCTS)
SPENT FUEL - ACTINIDES
SPENT FUEL - FISSIONPRODUCTS
: FRESHLY SEPARATEDNATURAL URANIUM
: URANIUM ORE
i i i j t u i l i ' ' ' i i f i f * ' l i t 1 1 1 ! * 1 1 i f i n lj — *»% •*• •103
11lira
108
TIME (years)FIGURE 2. RELATIVE TOXICITY OF SPENT CANDU FUEL IN AIR
![Page 33: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/33.jpg)
IB3
«
BHU
I
i I I i 1 1 * 1 1 l \ IITTÏT —miTïïj 1 i ) rrrrrj f—i t u HTJ—i—rmrnrj 1—rnrmj—
,,TOTAL (ACTINIDES + FISSION PRODUCTS)
1 G T 1
10-2
SPENT FUEL - FISSION PRODUCTS
1J Ji.1 U 1 t 1 I M U.
MERCURY
LEAD
PENT FUEL - ACTINIDES
' i i i nul 1—I.IIHI,1 I L-LJJ
o
TIME (years)
FIGURE 3. RELATIVE TOXICITY OF SPENT CANDU FUEL IN WATER
![Page 34: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/34.jpg)
>11 T T iTrriTj ;—rnrm—r~rrrrr.Ti—TT-rr T~T l~ !i l!j--
10 1 J -v-,TOTAL (ACTINIDES + FISSION PRODUCTS)
.SPENT FUEL - ACTINIDES
10,10
10s - j
10 s
SPENT FUEL - FISSION PRODUCTS
105
TIME ( y e a r s )
FIGURE 4 . RELATIVE TOXICITY OF SPENT CANDU FUEL IN AIR
![Page 35: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/35.jpg)
D-l
APPENDIX D
STORAGE OF SPENT FUEL IN WATER-FILLED BASINS AT A CENTRAL SITE
by
D.R. McLEAN
1. GENERAL DESCRIPTION
The purpose of this study was to look at the application of
storage pools, as they are currently used at reactor sites, for use at a
central site. One variation adopted was the use of cooling towers rather
than lake or river water since it was believed this would give more
flexibility in the choice of a central site.
Since pool storage is generally a very familiar concept, only
a brief description of site facilities is provided. Costs are dealt with
at length since storage costs at a location apart from reactors are not
widely known.
An overall site plan and a detailed site plan for the storage
basin area are shown in Figure 1. The entire site, including a buffer zone
around the site proper and waste disposal grounds, covers an area 1.6
kilometres (1 mile) square. Eight storage basins are required. They are
arranged in two banks each of which contains one flask handling center with
two basins on each side. A water-filled transfer canal links each basin in
the bank with the others and with, the flask-handling center. Each basin
will hold 8,500 Mg of spent fuel and is designed to handle fuel that has
been cooled for one year at reactor sites.
![Page 36: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/36.jpg)
D-2
It is assumed that the spent fuel is shipped by rail in 50 Mg
flasks containing a total of 3,840 kg U stacked in six Pickering-type
baskets C32 Pickering-type bundles per basket). A schematic drawing of
this basket is shown in Figure 2. The rail cars are moved into the flask
handling center where the flasks are monitored and then moved by crane into
a dry hot cell for unloading. The baskets are removed with a light crane
and placed on a trolley car which carries them underwater along the transfer
canal to the storage basin. At the storage basin the baskets are removed
by crane from the trolley car and placed in storage. The stacked baskets
are stored under a minimum of 4.3 m 0 3 ft.) of water to provide radiation
shielding for workmen handling the spent fuel. A flask-handling center
and a storage basin are shown in Figures 3,4, and 5.
Each basin is equipped with a primary cooling system to remove
radioactive decay heat from the spent fuel and a purification system to
remove activity from the water and to keep it clear for viewing purposes.
The flowsheets are shown in Figures 6 and 7.
The superstructure above each basin is continually purged with
ventilation air for humidity control and to remove hydrogen generated from
radiolytic degradation of the basin water. The ventilation air is heated
in winter to prevent condensation and/or frost buildup on the walls of the
superstructure and to maintain suitable temperatures in the area for workmen.
Normally, the exhausted air is not filtered but the basins are equipped
to filter all the air if necessary.
The main auxiliary systems at the site include:
1. A bank of cooling towers to supply secondary cooling water tothe primary basin cooling systems. The towers will handle amaximum flow rate of 190 m3/min, (50,000 gpm*) cooling it from29.4°C to 23.9°C. A flowsheet Is shown in Figure 8.
2. An oil-fired steam heating plant for heating the basin ventilationair and the other buildings on the site. Total steam raisingcapacity is 77 Mg/h at a gauge pressure of 590 kPa.
3. A water supply and treatment system to provide démineraiizedwater for the basins, to provide make-up to the cooling towers,and water for general usage. The flowsheet is shown on Figure 9.
*Gallons in this report refer to U.S. gallons
![Page 37: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/37.jpg)
D-3
Emergency reservoirs located on the site will supply water forregular site operation for about two weeks or emergency coolingwater on a recirculation basis if the cooling towers fail.Total capacity of the water treatment plant is about 5.5 m3/min(approximately 1,500 gpm) .
4. An electrical distribution system and emergency dieselgenerators to ensure continued operation of the basin coolingand ventilation systems in the event of a power failure. Thetransformers at the main station on the site are sized tohandle a maximum load of 21,000 kVA. The total emergencypower generating capacity is 12,000 kVA.
5. Waste management facilities for domestic wastes, storm runoff,non-active chemical wastes, active liquid waste treatment, andactive solid and liquid waste disposal. When all basins arefilled, for example, approximately 700 m3 of active solidwaste will be generated per year.
Other site facilities include a maintenance shop, a warehouse,
a garage, a firehall, a gatehouse, fuel oil storage tanks, roads, railroads,
and mobile equipment (trucks, cranes, tractors, rail car puller, etc.).
The number of personnel required for regular site operation
ranges from 34 when the first basin is being filled to 70 when the last
two basins are being filled. A breakdown for the latter period is shown
in Table 1. These totals do not include manpower for major maintenance
work since this work is assumed to be handled by outside contractors. ji
A schedule for development of the site is shown in Figure 10.
The systems installed in each of the five phases are listed in the capital
cost summary.
2. COST SUMMARY
2.1 SUMMARY OF CAPITAL COSTS
These costs are summarized in Table 2. The construction costs
for all five phases of site development total $76 million and include
equipment, materials, labour for installation of equipment and materials,
and all contractor overheads and indirect costs including contractors'
![Page 38: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/38.jpg)
D-4
profit. Costs for design and engineering, startup, owner costs, and the
contingency allowance raised the total fixed investment required to $100
million.
The capital expenditure for each phase of site development
averages about $20 - 25 million with the exception of phase II where the
total cost is about $11 million.
2.2 STORAGE BASKETS
The Pickering-type storage baskets cost about $200 each, or
$0.31/kg U. The total expenditure for baskets amounts to $21 million.
2.3 SUMMARY OF GENERAL OPERATING COSTS
Total annual general operating costs for the final year of
Phases I, III, and V are shown in Table 3. They include the costs for
manpower, utilities (electrical power, fuel oil, water treatment), fresh
resin (for basin purification systems), waste storage (for spent resin,
filter cake, etc.), maintenance labour and material, operating supplies,
taxes, insurance and storage fees. Costs were estimated at the end of
each phase and the general operating costs in the intervening years were
determined by interpolation. Manpower costs were determined from the
estimate of the personnel requirements at the end of Phase I and at the
end of Phase V. Utility and fresh resin costs were based on estimated
consumptions for each phase. Waste storage costs were based on the
estimated volumes of spent resin and filter cake discharged annually in
each phase. The material and labour costs for major maintenance were
estimated at 1% of the total fixed investment for each phase of the site
development period. Operating supplies were estimated at 15% of the
maintenance cost. Taxes and insurance were estimated at 1.5% of the fixed
investment for each phase and storage contract fees at $10 per Mg. These
fees are for contractual agreements for placing spent fuel in storage and
![Page 39: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/39.jpg)
D-5
transferring the title for ownership of the fuel to the owner of the
storage site. The total general operating costs amount to $1.4 million
in 1985 and to $6.2 million in the year 2000.
A percentage breakdown of the total annual operating costs is
also shown in Table 3 to indicate the relative influence of each of the
operating cost items.
Total annual operating costs during the site filling period
amount to $68 million.
2.4 PERPETUAL CARE COSTS
The costs beyond the year 2000 must be paid for from accrued
interest in perpetual care sinking funds. These costs Include annual
general operating costs, costs for equipment replacement every 25 years,
cost for site replacement and new buildings and facilities every 50 years,
and costs for transferring spent fuel from the eld site to the new site
and decommissioning the old site. These costs, along with the size of the
investments required in the various sinking funds in the year 2000, are
found in Table 4.
The investment required in the sinking funds at the end of the
year 2000 totals $247 million, of which nearly $200 million is required
to cover the annual general operating expense. The manner in which the
size of perpetual funds is calculated is described in Appendix 8. It was
assumed that future costs would escalate at the rate of 4% per year and
that interest would accumulate at the rate of 7% per year. The sinking
funds are to be established by placing a charge against the spent fuel as
it is received year by year and investing the resultant income at an
interest rate of 7% per year until the year 2000.
![Page 40: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/40.jpg)
û-6
2.5 LEVELIZED COSTS, $/kg U FOR CAPITAL, OPERATING AND PERPETUAL CARE
A breakdown of the levelized costs for capital operating and
perpetual care is given in Table 5.
2.6 SHIPPING
The cost for shipping fuel from the reactor site to a central
storage site has been calculated in Appendix I. It amounts to $2.20/kg U.
2.7 PUBLIC INFORMATION AND SITE SELECTION
Costs for development of pool storage should be small. An
expenditure of $1.0 x 106 for public relations and $1.0 x 106 for site
selection have been allowed. This amounts to a levelized cost of = $0.05/kg U.
2.8 TOTAL COSTS FOR MANAGEMENT OF SPENT FUEL IN BASINS
A breakdown of the total levelized costs for the management
of spent fuel in basins is given in Table 6.
3. GENERAL COMMENTS ON POOL STORAGE
1. Since water is used as a shielding material and as a coolant,a basin design providing high integrity containment of thewater is required. This requirement will probably restrictthe service life of the basin to about 50 years.
2. The free space in the basin superstructure above the basinwater must be ventilated continuously for the following reasons:
a) To ensure habitable working conditions.
b) For humidity control to avoid frost buildup on the super-structure walls in the winter and to prevent condensation
![Page 41: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/41.jpg)
D-7
of moisture on equipment such as storage basin cranes.
c) To purge the radiolytic hydrogen released from the basinwater.
The ventilation requirements for humidity control are substantial.The intake air must be filtered to remove dust that mightsettle on the basin water and require removal in the basinpurification system. In winter, this air must be heated.The design heat transfer load for heating the ventilationair in basin No.l is 25% of the design heat transfer required forcooling the spent fuel in that basin immediately after it isfilled with spent fuel. Provision is also required forfiltration of the exhaust air if it becomes contaminated withradioactive particulates.
3. Since continuous purification of the basin water is required,active wastes in the form of spent ion-exchange resin andfilter cake are continually being produced and must be stored.
4. The use of forced convection cooling requires extensive use ofmechanical equipment. Strict surveillance is required and aheavy maintenance program is essential to keep the equipmentin operation.
5. A distinct advantage of the pool storage is ready retrievabilityof the spent fuel.
6. Because of the high operating costs, perpetual care costs forpool storage are high. However, a large perpetual care fundhas the advantage of allowing more flexibility in switchingto other storage schemes in the future. In this case thefunds with cunmulative interest earnings reach their maximumvalue in the 50 year cycle just prior to the expenditure forreplacement of site facilities. This is equivalent to $5.45/kg U.
![Page 42: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/42.jpg)
D-8
TABLE 1
MANPOWER REQUIREMENTS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Site Superintendent
Manager of Operations
Fuel HandlingDriver - Rail Car PullerFlask UnloadersBasket Stacker in BasinTotal
I/shift2/shiftI/shift ,..4/shift x 5 shifts W
Utility and Basin Operators (powerhouse, watertreatment plant, cooling tower, basin cooling,purification and ventilation systems) ,...
3 men/shift x 4 shifts111'
Laboratory StaffChemistTechnicianTotal
Traffic and Records ClerkOne man per day shift onlyby health surveyors)
1 (day shift only)I (day shift only)
'he is to be assisted
Health and SafetyHealth and Safety Head 1 (day shift)Technician ' 1 (day shift)Shift Surveyors (fuel handling)
1/shift x 4/shifts 4Total
Changing Spent Resins - day shift
Minor Maintenance - day shift
Other ServicesJanitorial ServiceGrounds KeepersMiscellaneous DutyGuard Duty
I/shift x 4/shiftsTotal
Engineering Services
Business AdministrationAccountantPayroll ClerkEmployee ServicesStenograhersTotal
TOTAL for Phase V Operations
3 (day shift)2 (day shift)3 (day shift)
4.
1 (day shift)1 (day shift)1 (day shift)3 (day shift)
Number of PeopleRequired
during Phase V
1
1
20
12
2
1
6
4
4
12
1
_6
70
(i) Actually require 4.7 nen to provide full coverage for 3 shifts perday including weekends, holidays, vacation and sick leave. Duringslack periods, men are to be used for minor maintenance.
(11) To ensure full coverage of all shifts, minor maintenance staff willbe used as operators when required.
![Page 43: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/43.jpg)
D-9
TABLE 2
SUMMARY OF CAPITAL EXPENDITURES
Construction Costs
LandYard DevelopmentFlask Handling CentresStorage BasinsStorage BasinsCooling Towers and C.W. Distribution
Steam Supply andDistribution
Power HouseFuel Oil Storage TanksWater Supply Systems
& Emergency CoolingWater
Waste ManagementSystems
Ph.I
0.031.941.686.52
1.17
0.230.190.08
1.64
0.97Miscellaneous Buildings
& Equipment(Maintenance Shop etc.]Plant and Instrument
Air Supply
0.63
0.10Electrical Supply - main
& sec. transformer stationsprimary distributionemergency generators
Rolling StockSpare PartsEngineering, Design,
Inspection, Adminis-tration, SafetyAnalyses
StartupOwner CostsContingency
Total Fixed
and0.690.110.08
2.760.080.752.94
Investment 22.59
Ph
6
0
000
0
1.0.01.
11.
Costs,
.11
.75
.81
.08
.14
.04
58
02032445
14
Ph
0166
0
0
0
1
0
0
00.0.
2.0.0.3.
25.
Million
.III
.12
.68
.81
.86
.84
15
09
49
03
07
911308
33085133
51
Ph
66
0
000
0
1002
20
$ (1972)
.IV
_
--.91.97
.83
.15
.22
.07
.80
28083565
31
Ph.V
_
--
7.007.06
0.86
0.15
-0.07
-
-
-
-
0.97
--
1.290.080.352.67
20.50
Total
0.032.063.36
QA OOJt. OO
4.51
0.760.550.35
3.13
1.00
0.63
0.17
3.950.240.16
8.68(i)0.352.20(11)
13.04(iii)
100.05(iv)
(i) This cost varied as a percentage of the construction costs,depending on the phase of the building program. The overallcost amounts to 11% of the total construction costs or 8.7%of the total fixed investment.
(ii) Includes site selection, property taxes and insurance, generaland administrative expense and public relations.
(ill) Estimated to be 15% of each of the main cost items.
(Iv) No allowance is included here for cost escalation or Interestcharges during construction. These items are included, however,in the determination of the price to be charged for storing the
![Page 44: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/44.jpg)
D-10
TABLE 3
BREAKDOWN OF ANNUAL OPERATING COSTS
IN THE FINAL YEAR OF PHASES I, III, AND V
Total Annual Cost $106
Manpower, %
Utilities, Resin, WasteStorage, %
Maintenance (M & C) andOperating Supplies, %
Taxes and Insurance, %
Storage Contract Fees, %
1985
1.42
24
27
21
27
1
100
1994
3.61
14
36
21
28
1
100
2000
6.21
11
41
21
26
1
100
![Page 45: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/45.jpg)
D-ll
TABLE 4
SUMMARY OF FUTURE COSTS AND INITIAL INVESTMENT REQUIRED IN
THE PERPETUAL CARE FUNDS
(All costs are given in 1972 dollars)
General Operating Costs
Costs for Replacement ofEquipment Every 25 Years
Net Cost For Site ReplacementEvery 50 Years
Costs For Transferring Fuel ToNew Site & Decommissioning OldSite
Future CostsAfter
Year 2000
Investment RequiredIn Sinking Fund atEnd of Year 2000
CIO6 dollars)
5.7Ci>
15
67
til)
(ill)
,Civ)
(106 dollars)
198
14
21
14
Total Initial Investment RequiredIn The Sinking Funds 247
Ci) Estimate of operating costs per year for the first 50 years ofsite operation after the year 2000. This cost is not expectedto decrease significantly beyond that time.
(ii) Total installed cost for replacement of equipment, piping,instrumentation, etc. in the basins, flask handling centresand auxiliary systems.
Ciii) Net Cost • total cost for site replacement every 50 years(estimated to be $82 million) less the allowance for equipmentreplacement spent every 25 years. Site replacement includes thecost of a new site, yard development costs, and all new buildingsand equipment.
(iv) Estimate includes decanning defective bundles, loading andunloading flasks, transport costs, an allowance for operatingcosts while both sites are being operated and the cost ofdecommissioning old basins.
![Page 46: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/46.jpg)
D-12
TABLE 5
LEVELIZED COSTS FOR CAPITAL, OPERATING
AND PERPETUAL CARE
Cost,
CAPITALGeneral Capital Expenditures
Interest Charges for BorrowedMoney
Basket Costs
GENERAL OPERATING
TOTAL FOR CAPITAL AND GENERAL OPERATING
PERPETUAL CARETotal Value of Sinking Fund inYear 2000
Interest Earned to Year 2000
Deposits to Sinking FundDuring Filling
TOTAL COSTS FOR CAPITAL, OPERATING AND
PERPETUAL CARE
106
100.
13.
21.
68.
247.
-47.
Dollars
1
6
1
0
202.8
0
8
199.2
402.0
Levelized
Costs,
1.
0.
0.
1.
$/kg U
47
20
31
00
2.98
2.93
5.91
![Page 47: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/47.jpg)
D-13
TABLE 6
TOTAL COSTS FOR MANAGEMENT OF SPENT FUEL IN BASINS
1.
2.
3.
4.
5.
Site Selection and Public Relations
Capital and Operating Costs DuringSite Filling Period
Petpetual Care
Shipping
Total
Levelized Costs$/kg U
0.05
2.98
2.93
2.20
8.16
![Page 48: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/48.jpg)
POOLS
7C2 m
< Î > STORAGE I A 9 N «RE*
<§> WASTE STORAGEAREA FOR STORAGEVAULTS • TANKS
WRIAL omuNos AREA
SITE SUFFER ZONE
— OVERALL SITE PLAN —
{ I , STORAGE BASINS
{Zj FLASK HANDLING CENTRES
(lj COOLING TOWERS
.4; COOLING WATER PIPEWAY
(5 POWER HOUSE
^6 ACTIVE WASTE TREATMENT PLANT
* \7. WATER TREATMENT PLANT0»
3 l'a GARAGE a Fl REHALL
(9 MAINTENANCE SHOP
'!§> WAREHOUSE
fît) GATEHOUSE
( ^ STORM SEWER DELAY PONOS
@ EMERGENCY WATER SUPPLY RESERVOIRS
'Ï4 FUEL OIL STORAGE TANKS
f5 MAIN ELECTRICAL TRANSFORMER STATION
(j PARKING LOT
@ SEPTIC TANKS
FIGURE 1.
SITE PLAN FOR STORAGE BASIN AkEA
![Page 49: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/49.jpg)
PLAN
1.02 m
.17
NOTES
1. BASKETS ARE FABRICATED FROMSTAINLESS STEEL.
2. BASKETS HOLDS A TOTAL OF 3 2PICKERING FUEL BUNDLES (640 kg U)
. 55 mm
2 FUEL BUNDLES aPER ROW I
FRONT ELEVATION SIDE ELEVATION
FIGURE 2.
SCHEMATIC DRAWING OF PICKERING STORAGE
BASKET
![Page 50: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/50.jpg)
TGRADE
(DL5-1 !l EL - iOS I
.5 Mi
EL = 108.8 m
GRADE EL -100.0 m
f * M ^ REINFORCED CONCRETE
• • • • • » : CRANE RAIL SUPPORTS
0 CELL FDR MONITORING, OPENING AND DECONTAMINATING FLASKS(2) FLASK UNLOADING CELLiS) CELL FOR CANNING DEFECTIVE BUNDLES4) FLASK ON TROLLEY CAR WITH COVER REMOVED® FLASK COVER(6) CABLE DRIVEN UNDERWATER TROLLEY CARf) RAILWAY FLAT CAR
,6)
EL • 92.4 m
ELEVATION
FIGURE 3
LAYOUT OF FLASK HANDLING CENTRE
![Page 51: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/51.jpg)
D-I7
STORAGE BASKETS
6 PER STACK-^
4 ROWS OFSTACKS PERSECTION, 8 ROWSPER STORAGECANAL.
7 ROWS CONTAIN4 6 STACKS ANDI ROW CONTAINS
4 7 STACKS
L
51.2 m
EQUIPMENT BAY
h- 159 m -Ih- 15.9 m.92 m
15.9 m -H
LOCATIONOF CANALDOORWHILEC/>NAL IFBe NGTILLED
EQUIPMENT BAY
( LAYOUT OF OTHEREQUIPMENT BAYIS SIMILAR EXCEPTFOR GANTRYMAINTENAMCE AREAWHICH IS USEDINSTEAD FORTRANSFER CANALPURIFICATIONEQUIPMENT )
_£_:
STORAGE CANALS
STORAGE CANALS
STAINLESSSTEELSTORAGECANALDIVIDER
d
MAINTENANCEAREA FORSTORAGECANALGANTRY
{COOLING EQUIP FOR 3 IPURIF" EQUIPI ADJACENT STORAGEI CANALS
FOR 3ADJACENTSTORAGECANALS
1E
in
t-
o
•JFIGURE 4.
STORAGE BASINPLAN VIEW
![Page 52: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/52.jpg)
EL» 108.8 m
BASIN FLOOR E L - 9 2 . 4 m
.92 m
SECTION A-A
SEE FIGURE A. 2.1.1
I
00
EQUIPMENTBAY
EL • 105.1 mEQUIPMENT
BAY
GRADE
(VENT •»EQUIP)
(COOLING 8|PURF"BQUIPj
PIT FOR CANALWATER PURF"EQUIPMENT
WATER LEVELS
E L - 108.8 m
EL- 104.4 m
GRADE EL- 100.0 m
\»-.e\ m EL- 96 . 3 m
- 9 2 mFLOOR EL • 92.4 m
SECTION B-BSEE FIGURE A . 2 . I . I
STORAGE BASIN ELEVATIONS
FIGURE 5
![Page 53: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/53.jpg)
LEGEND
£Y PRIMARY CIRCUIT PUMP
_?£.PRIMARY CIRCUIT HEAT EXCHANGER
—— PRIMARY CIRCUIT COOLING WATER (CANAL WATER)
SECONDARY CIRCUIT COOLING WATER(FROM COOLING TOWERS)
SECONDARY COOLING, WATER RETURN
29.4 °C
t»
SECONDARY COOLINGWATER SUPPLY7S°F (23.9°OMAX. FLOW BO m 3 /min. (25 ,000 qpm)- FOR BASINFILLED IN 13 ytora.
FIGURE 6
BASIN PRIMARY COOLING SYSTEM
![Page 54: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/54.jpg)
TRANSFER CANAL PURIFICATION EQUIPMENTPUMP
FILTER ( WIRE WOUND PERFORATED TUBE TYPE)
MIXED BED ION EXCHANGE COLUMN
.379 m3/m
379
.379 m3/m
STORAGE CANAL PURIFICATION EQUIPMENT STORAGE CANALS . I . STORAGE CANALS STORAGE CANAL PURIFICATION EQUIP.
• 379 m 3 / m
f STANDBY EQUIPMENT
STORAGE _CANALHMVJDER
£M i t 1
.379 m 3 / m
O
STANDBY EQUIPMENT
NOTE
1. EACH ION EXCHANGE COLUMN CONTAINS ABOUT I m 3 OF MIXEDRESIN THE COLUMNS FOR THE STORAGE CANALS CAN BE RUN FORABOUT I MONTH BEFORE REPLACEMENT OF THE RESIN IS REQUIRED
2. THE STORAGE CANAL FILTERS ARE EXPECTED TO PICK UP ABOUT O . I 5 m 3
OF CAKE PER MONTH AND WILL REQUIRE BACKWASH ING ONCEEVERY 6 MONTHS.
FIGURE 7.
BASIN PURIFICATION SYSTEM
![Page 55: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/55.jpg)
EMERGENCY COOLING WATER
RETURNED TO EMERGENCY SUPPLYRESEVOIR
AMBIENT DESIGN CONDITION
0. B. 294 °C ( 8 5 ° F )
W.B. 21.1 °C ( 70°F)
MAKE-UP WATER
LOSSES
(EVAPORATION, ENTRAINMENT)
•LOWDOWN(TO STORM SEWER)
STORAGE BASINS
29,4
(85 °F)RETURN
233 °CH EADER
INDUCED DRAFTCOOLING TOWER
) {75°F ) SUPPLY£ HEADER
EMERGENCY COOLING WATER
—
FROM EMERGENCY WATER SUPPLYRESEVOIR
NOTES
1. IT IS ASSUMED THAT CONNECTIONS FROM EACH BASIN TO EACH SET OF MAIN HEADERS IS REQUIRED TO ENSURE
ADEQUATE FLEXIBILITY IN DISTRIBUTING COOLING WATER.
FIGURE 8.
SECONDARY COOLING WATER SUPPLY SYSTEM
(Typical of installation required for one phase )
![Page 56: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/56.jpg)
EFFLUENT FROM FILTER. .9m3/iT
. 4 m3 / m i n .
BACKWASH TO STORM SEWER
SEEPAGE AND
EVAPORATION LOSSES*4nVmin.
D 3.1 m3/min. ..
* ,44,000 m 3
Q 3. a n>3/min. - ,
SEEPAGE ANDEVAPORATION LOSSES . I n
RAW WATER INTAKE
SYSTEMS
EMERGENCY
WATER SUPPLY
RESERVOIRS
LEGEND
INSTALLED IN PHASE I FOR PHASES I a H
« _ ^ _ » INSTALLED IN PHASE n FOR PHASES HI , IZ ;
— - - ^ F O R EMERGENCY
- — 4 U S E ONLY
3. 79 m 3 / m i n .
.3 m 3 /m in .
FILTER .4m3/mW
BACKWASH
TO FIRE LOOP ( FROM SPECIAL
"RESEVOIR OF FILTERED WATER)
. LAWN WATERING
.01 m^/nin.->-MAKE-UP TO STEAM SYSTEM
I.9m3/min.
2.9 m3/min.• MAKE-UP TO COOLING TOWERS
• I m3/mjg.1
FILTER 5n?/
BACKWASH
WATER
TREATMENT
PLANT
• 3 m ymm.
DEMINERALIZED MAKE-UP4 m ./minwftTER TO STORAGE CANALS
FOR EVAPORATION LOSSES
OEMINERALIZER PLANT O
. 4 ff|3/mln. SUPPLY TO STORAGE CANAL £*"DEMINERAUZERS TO INCREASE
SUPPLY OF DEMINERALIZED WATERDURING INITIAL FILLING OF
BASINS
.2 m 3 / m i n .
.2 m 3 / in in .
.GENERAL USAGE
47 m V m i n .1 94 m/min.
47 n> / min.
EMERGENCY COOLING WATER
»• TO SECONDARY COOLING
WATER DISTRIBUTION SYSTEM
FIGURE 9.
WATER SUPPLY SYSTEMS
![Page 57: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/57.jpg)
DATE_
PHASE III1 D 1
K N O . 3/iSNo It
PHASE IVIn 1 „ .
lNo5WIobl
LEGENDD
C
Design
Construction
Filling Basin with
1Spent
Start-up
Fuel
FIGURE 10.
SCHEDULE FOR SITE DEVELOPEMENT
![Page 58: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/58.jpg)
E-l
APPENDIX E
STORAGE OF SPENT FUEL IN WATER POOLS AT REACTOR SITES
by
R.W. Barnes
Ontario Hydro
1. SUMMARY OF STUDY
1.1 INTRODUCTION
This section is a summary of work carried out by Ontario
Hydro as a member of CAFS. It contains a summary design description and
an assessment of cost to store spent fuel for long periods of time in
pools at a reactor site.
The accumulated production of spent fuel from the Ontario
Hydro nuclear power stations planned up to and including the station
designated E20 (see Figure 1) has been plotted against time in Figure 2.
By 1989 about 1 million bundles will have been discharged from
the reactors at these stations. The present storage capacity of the spent
fuel bay at Pickering G.S. A is just over 80,000 bundles while the bay
capacity at Bruce G.S. A is about 32,000. It is planned to build auxiliary
bays for Pickering G.S. A and Bruce G.S. A. The auxiliary spent fuel bay
at Pickering G.S. A will be capable of holding approximately 9 station
years of spent fuel and the one at Bruce G.S. A at least 10 station years
and probably more.
![Page 59: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/59.jpg)
E-2
Ontario Hydro regards spent fuel as a resource because of its
fissile plutonium content and until recently, it was the policy of Ontario
Hydro that the spent fuel would be sold for plutonium recovery. The
market for spent fuel however is not likely to materialize in significant
quantities until towards the end of this century at the earliest. Therefore,
spent fuel will have to be stored for an interim period of at least 30 years.
The auxiliary bays provide temporary storage and allow time for a carefully
planned approach to interim storage. The CAFS study will provide a basis
for Ontario Hydro to act in the future.
As a member of the CAFS study group, Ontario Hydro agreed to
provide the following:
1. A conceptual design and cost information for perpetual (approx.106 years) storage of the total spent fuel produced at areactor site. The spent fuel would be stored in water pools.Since the pools would deteriorate, it was assumed that newpools would be built and the spent fuel stored in them. Thiscycle of events would continue until the hazardous radiationlevel from the spent fuel was very small.
2. The incremental capital and operating cost, for extendingspent fuel storage in the reactor station spent fuel bayfrom one year up to three years and from one year up to fiveyears.
This report refers to the perpetual storage scheme as the long-
term facility and refers to the spent fuel bay which is part of the
generating station, as the short-term facility.
The design of the long-term facility is considered in enough
detail to demonstrate the feasibility of the concept. The cost analysis
is sufficiently detailed to identify major cost areas. No provision has
been made for costs resulting from requirements of international commitments
for safeguarding the spent fuel.
For the short-term facility, although only incremental costs
were required, a review was made of existing bay designs and fuel handling
systems. The review was carried out in the conceptual design stage and
some of the recommendations became part of the ground rules. A modified
![Page 60: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/60.jpg)
E-3
Bruce G.S. A spent fuel bay was used as a basis for the study. Cost
assessments were made for the incremental storage times.
1.2 DESIGN BASIS
1.2.1 GROUND RULES FOR STORAGE OF SPENT FUEL IN POOLS AT REACTOR SITES
A set of ground rules for all the studies was prepared by the
CAFS group at the start. However, for this study additional ground rules
were required. The CAFS ground rules are set out in Appendix A. The
additional ground rules are given in Section 5 of this Appendix.
1.2.2 SITE
For the purposes of the study, Bruce Nuclear Power Development
(Bruce NPD) was used as the reactor site because basic costs of engineering,
construction and supplies are well known. A location for the facility on
the Bruce NPD site is shown in Figure 3 to give some idea of how distance
affects the transfer of spent fuel between the station spent fuel bays
and the long-term spent fuel storage facility located on-site.
1.2.3 SPENT FUEL BUNDLE PRODUCTION
The average bundle production rate for the existing and proposed
stations at Bruce NPD is given in Table 1. The figures in this table
assume an 80% capacity factor and the bundle production rate is averaged
over the year. For the purposes of this study it is assumed that an
additional 6000 MWe will be built and that this additional 6000 MWe
would be in-service in 1984. This was assumed since that is the largest
quantity of electric generation (12,000 MWe, see Appendix A, Al.l) likely
at any one energy centre and therefore is a maximum design condition. The
total number of spent fuel bundles discharged assuming each unit has a
lifetime of 30 years is 2.3 x 106 bundles.
![Page 61: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/61.jpg)
E-4
1.2.4 DECAY HEAT GENERATION
The decay heat generation rate used for the design is shown
in Figure 4. This curve was produced using a modified version of the
program ISOGEN. The program was originally written at Hanford and has
been modified to fit the decay properties of spent CANDU fuel. The
modifications that have been made to the program are:
1. extensions to the nuclide library,2. addition of new isotope properties,3. incorporation of new options into the program,4. variations in the manipulation of basic output data.
Although the nuclide library has been expanded, the total
number of isotopes in the library has been reduced. This reduction in
fission products was achieved by dropping all the short-lived species,
which in the context of the study means those products having negligible
activity after one year's cooling. The addition of stable fission products
and their significant capture products has yet to be completed.
1.2.5 MAN-REM
One of the basic design objectives adhered to was that
occupational.doses should not dictate labour costs. A man-rem audit
was carried out and this indicated that this objective had been met.
1.2.6 RADIOACTIVE RELEASE TO THE ENVIRONMENT
1.2.6.1 General Activity Control
It is postulated that a certain percentage of the fuel will
fail in storage, even though the storage environment is less severe on
the bundles than in the reactor. Normally, there will be no attempt to
retrieve and can these defective bundles. This means that the cooling
«rater circulating through the vaults will be contaminated. The volume
of water in the vault is very large and it is expected that the dilution
factor alone will be adequate to keep radiation levels to very low values.
![Page 62: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/62.jpg)
E-5
If there was a massive failure of bundles, an attempt would be made to
retrieve and process these bundles.
Flow through the chemical control circuit is dictated by
chemical needs and net purification requirements. The chemical control
circuit will be used basically for pH control and not for purification,
although purification of the water will result from its passage through
the ion-exchange columns. It is possible to put the whole cooling flow
through the ion-exchange columns for purification of the water if that
ever becomes necessary.
An attempt to keep the cooling water very clean would almost
certainly result in very large quantities of low-level contaminated
resin. The resin would then have to be disposed of in some storage
system. There appears to be no gain from transferring the low-level
activity in the water to the resin except that on the resin it is fixed.
Spent fuel bundles that are known to be defective in the short-term
facility will not be stored in the long-term facility.
1.2.6.2 Radioactive Liquid Release
The design was carried out with the objective of keeping to a
minimum the risk of a radioactive liquid release to the environment. Any
loss of radioactive fluid will be directed to a leakage collection tank
by way of the leakage collection system.
1.2.6.3 Radioactive Gas Release
The Health Physics Department suggests limits on releases of85Kr, 3H and 1 2 9I to the environment. It is expected that these isotopes
would be the main contributors of radiation dose in any radioactive gas
release. They would be the major gaseous isotopes remaining because of
their long half-lives. It may be necessary to limit releases of these
nuclides on a world-wide dose commitment basis rather than a local dose
basis. Any gaseous release would be by way of the ventilation system.
This system is required to prevent the collection of explosive quantities
![Page 63: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/63.jpg)
E-6
of hydrogen and oxygen caused by the radiolytic decomposition of water,
through the gamma ray activity from the fuel. The system is kept under
negative air pressure thus preventing uncontrolled leakage to the
environment. A once-through ventilation system was chosen for this
design. If the release of airborne activity proves to be a problem, a
filtering system could be connected into the exhaust.
There is a monitoring system for control and an extraction
system through which the ventilation exhaust air can be diverted in the
event of a large, sustained release of radioactive gas. It is not
expected that the release of radioactive gas will be a problem. Should
it prove to be one, the system could be converted to a closed system and
an extraction system placed on the exhaust. The exhaust would be required
to keep the system at a negative pressure. A catalytic recombiner would
be used to control the concentrations of hydrogen and oxygen.
1.3 LONG-TERM FACILITY
1.3.1 GENERAL DESCRIPTION
The storage facility consists of four concrete vaults partially
above ground, with each vault consisting of a row of eight bays separated
by expansion joints (Figure 5). A bay is an integral, reinforced concrete
structure partially subdivided into six sections by cover support beams
(Figure 6). The capacity of each storage bay with baskets stacked six
high is 82,150 (approximately) fuel bundles. In addition, floor space
is allocated for flask setdown during unloading. When filled, each bay
is covered by stainless steel plate and reinforced concrete covers are
then placed over each bay section for protection of the stainless steel
covers (Figure 7).
During and after filling, each bay is connected to process
equipment to provide air space ventilation (Figure 8), water cooling,
water chemistry control and purification (Figure 9). Most of the process
and monitoring equipment is located in the Service and Control Centre
Building at the southeast corner of the site.
![Page 64: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/64.jpg)
E-7
Fuel handling is performed within a single loading cell
facility (Figure 10) which is moved from vault to vault on a transfer
vehicle and along each vault to any bay on its own wheels. The cell is
designed to reside over and be sealed around a single bay section where
it will remain until the bay is filled. Connection points are provided
at regular intervals to the pipe chase alongside each vault. These
connections provide the loading cell with electric power, domestic water,
sewage and liquid radioactive waste return lines directed through the
Service and Control Centre.
1.3.2 CONSTRUCTION OF THE SPENT FUEL STORAGE FACILITY
1.3.2.1 Method of Construction
As the first step in construction, the chosen area is fenced
off and the site cleared for the whole project. Excavation for the first
concrete vault consisting of eight water bays is carried out and the
concrete poured. The stainless steel liner for the first bay in that
vault is then installed. The preliminary cost estimate indicated that
the stainless steel liner was a major cost factor and that the liners
should be installed only when needed, allowing suitable cushion time
(approximately one full year before filling is due to start) for labour
and supply problems.
The Loading Cell, the Service and Control Centre and part of
the retaining walls for the Loading Cell transfer vehicle track will be
constructed during this first stage. The transfer vehicle track is
extended as new vaults are built. The main headers and leakage collection
system for the first vault are also installed at this stage. The
connecting piping to each bay is not installed until the stainless steel
liner for that particular bay is in place.
Figure 11 shows the project life cycle for the spent fuel
storage facility including the main milestones leading up to the operation
of the first bay. The time requirements for regulatory licensing and for
![Page 65: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/65.jpg)
E-8
public approval have not been included at this stage. These may add an
additional twelve months from start of project to commencement of filling.
1.3.2.2 Construction Schedules
Figure 12 gives the construction schedule for this facility.
The schedule shows the relative timing of the engineering, construction,
liner installation and filling of the bays with spent fuel. Note that
only seven of the eight bays are used in any one vault. The eighth bay
is kept as a standby to be used if a major leak develops in a liner of
one of the filled bays requiring the fuel in that bay to be transferred
to a new bay. The construction order used on the first vault is repeated
for each of the other three vaults.
1.4 SHORT-TERM FACILITY
1.4.1 DESIGN CRITERIA
The basic intent of this study was to determine the incremental
cost for holding spent fuel at the generating station for an extra two
Cl-3) years and an extra four (1-5) years assuming the normal holding
time to be one year. This study was done because some of the proposed
long-term schemes were unable to remove the decay heat produced by spent
fuel that had only been one year out of the reactor. The extra cost to
hold the spent fuel at the reactor station for the longer period is added
to the overall cost of the scheme.
To do a realistic cost study, a certain amount of redesign
was required. It was decided to use this opportunity to collect information
on the operation of present systems as well as any suggestions for
improvement. Much of this work was done during the conceptual stage of
the study. Discussions were held with:
1. operations personnel on spent fuel bay operation,
2. members of the Spent Fuel Bay Working Parties about theirfindings, and
3. designers about problems encountered.
![Page 66: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/66.jpg)
E-9
The basic findings are discussed in Section 5 of this Appendix.
1.4.2 SUMMARY OF DESIGN CHANGES
The review of the existing spent fuel handling and storage
systems showed that the systems at Bruce G.S. A complied with some of the
suggested improvements. It was decided to use the spent fuel bay at Bruce
G.S. A as the basic design, incorporating most of the accepted suggestions.
Since the costs for Bruce G.S. A are well established, reasonable reliance
can be placed on the incremental cost estimates.
The hypothetical modifications were carried out by Generation
Mechanical Department. Figure 13 is a layout of the existing spent fuel
bay at Bruce G.S. A and acts- as a base to compare the overall changes.
The modifications (Figures 14, 15 and 16) do not affect the station
arrangement and foundations. Two major changes included in the design
were the relocation of the spent fuel ports above water, necessitating
additional shielding, and an increase in the water depth to suit the fuel
handling system employed. This would rais the building roof line in the
central fuelling area.
The reference basket for holding fuel in the storage bay is
based on the Pickering G.S. A version which holds four rows of four end-
to-end fuel bundle pairs (32 bundles per basket). This design of basket
was used to benefit from simplified loading while maintaining good
support of the fuel bundle. The major drawback of the design is poor
storage density which has been improved to some degree for this study.
Further improvement is possible. The general pool construction is
similar to that at Bruce G.S. A.
The water and air space is partitioned into a receiving bay area
(Figure 17) and a holding bay area. The spent fuel passes from the
fuelling machine into the receiving bay. The bundles are placed in baskets
and stacked. It is here that any defective fuel bundles are canned. From
here the stacked baskets move to the holding bay. Each area is served by
![Page 67: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/67.jpg)
E-1Q
a two-ton manbridge/gantry with a basket-handling mechanism. Transfer of
baskets between bays is accomplished by a short conveyor.
The receiving bay has the potential of being highly contaminated
with fission products. It is provided with a high blow purification
circuit for the water. The turn-over of the ventilation air can also be
increased to assist in the removal of airborne activity and fission gases.
The bay floor space utilization is very similar to Bruce G.S.
A. In each case the main basket storage area is in the large holding
area adjacent to the receiving bay. Five metres (16 feet) at the north
end of the holding bay is largely reserved for booster fuel storage and
flask operation. The latter area is served by a 100-ton overhead crane.
1.5 POSSIBLE DESIGN IMPROVEMENTS
1.5.1 STAINLESS STEEL USAGE
The stainless steel liner is a large factor in the capital
cost. Optimization of the design with respect to stainless steel would
lead to a lower cost. The following actions can be taken:
1. Use a 4.76 mm thick stainless steel liner instead of theproposed 6.35 mm thick liner. At Douglas Point G.S. 3.18 mmthick stainless steel plate was used for the liner.Difficulty was experienced in construction with the thinplate so it was decided to use 4.76 mm thick stainless steelplate for the Bruce G.S. A spent fuel bay liner. For thisstudy the 4.76 mm could be considered as proven from aconstruetability point of view.
The corrosion of the liner is expected to be very smallalthough with thinner liners the chances of getting a leakare probably increased. However, with the provision of oneemergency bay for each vault, sufficient flexibility has beenprovided for the situation where a liner develops a severe leak.
2. Replace the stainless steel bay cover with a less expensivematerial. The cover acts as a barrier to dust and forms anenvelope for the ventilation system which operates at anegative pressure.
The reinforced concrete beams that span each bay are wrapped
![Page 68: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/68.jpg)
E-ll
in stainless steel plate. The beams are used by the Loading Cell to seal
off an area of the bay whi}.e it is loaded with spent fuel and for
supporting the concrete covers. Redesign of these functions would eliminate
a substantial quantity of stainless steel plate.
1.5.2 BAY FLOOR SPACE
It was intended in the original design that there would be
no empty space on the bay floor except for the setdown area for the flask.
However, the space under each of the beams spanning the bay was not
utilized and this space is capable of stacking an extra row of baskets.
1.5.3 FUEL BUNDLE STACKING DENSITY
Recent work has indicated that the fuel bundles can be stacked
mechnically about 60% closer than with the Pickering style baskets.
2. SUMMARY OF COST
2.1 COST ESTIMATE FOR LONG-TERM FACILITY
2.1.1 GENERAL
One of the ground rules of this study was that all cost
estimates would be expressed in 1972 dollars. However, the basic cost
estimate was prepared in the fall of 1973. Therefore, 1973 dollars were
used and the capital and operating costs have been expressed in 1973
dollars in the tables. For the unit storage cost the figures were
converted into 1972 dollars assuming an overall escalation rate of 5%.
The cost estimate was prepared using the present worth method
of analysis as outlined in Appendix B. The calculation assumed an annual
interest rate of 8% on borrowed or invested money and an escalation rate
![Page 69: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/69.jpg)
E-12
of 5%. The cost estimates are based on the schedule for construction
(Figure 12).
2.1.2 CAPITAL COST ESTIMATE
The cash flows for capital and operating expenditure together
with the annual fuel arisings at the spent fuel storage facility are
given in Table 2. A summary of the estimate showing a breakdown of
expenditure into the areas where the money is spent is given in Table 3.
The largest capital expenditure occurs in the building and structures
area. The stainless steel liner accounts for approximately 75% of the
69 x 106 M$ (1973$).
2.1.3 OPERATING COST ESTIMATE
The summary of operating cost is given in Table 3. In this
table, building maintenance and major equipment maintenance have been I
separated. An annual cost of 0.1% of building capital costs has been '
allowed for major equipment maintenance. It is assumed that from the
year 2014 onwards the operating costs will be constant. The last bay
is filled in the year 2013. The estimate for taxes and insurance has
been allowed at 1-1/2% of capital costs. The storage contract costs have
also been added into the total overall operating costs although not
included in Table 4. The cost assumed was the same as for the other
schemes i.e., $10/ Mg U.
2.1.4. PERPETUAL CARE COST ESTIMATE
The vault will be filled by the year 2013. From the year 2014
onwards the annual operating costs, retrieval of spent fuel from a leaking
bay and the storing of it in an emergency bay <Cevery 25 years), equipment
replacement (every 33-1/3 years), facility replacement (every 100 years)
transfer of the fuel to a new facility and de-commissioning of the old
facility (every 100 years) must be paid for from the sinking fund. The
total investment required by the year 2013 is 99M$ Q.973 $). Table 5
shows the breakdown of the total investment.
![Page 70: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/70.jpg)
E-13
2.1.5 COST OF SPENT FUEL MANAGEMENT IN POOLS
Combining the costs (Capital, Operating and Perpetual Care)
on a present worth basis Csee Table 6) expresses the total unit cost of
management of spent fuel (1972 $/fcg TJ). The storage basket cost included
in the operating cost has been taken at $0.31/kg U (.1972 $), a figure
given at the start of the study. The total unit cost of spent fuel
management at a reactor site in pools is $5.33/kg U (1972 $).
2.1.6 COST SAVINGS THROOGH DESIGN IMPROVEMENTS
In this section it is assumed that the design has been optimized
as described in Sections 1.5.1 and 1.5.2 and the new capital cost evaluated.
The assumptions are:
1. The thickness of the stainless steel liner has been reducedto 4.76 mm C3/16 inch).
2. The stainless steel covers have been replaced by a lessexpensive material such as fibre-glass.
3. Spent fuel is stacked in the space under the beams. Thisresults in a reduction of the number of bays required (4 less).
The new costs are expressed in Table 7. There is a significant
reduction in the capital cost ($0.58/kg U) and a slight change in the
perpetual storage cost.
2.1.7 COST SAVINGS THROUGH HIGHER BUNDLE STACKING DENSITY
In this section the cost of management is calculated assuming
that the fuel has been stacked closer as proposed in Section 1.5.3 and
include the design improvements suggested in Sections 1.5.1 and 1.5.2.
The fuel stacking density will be increased by about 60%. This results
in substantially fewer bays (12 less than the 28 originally required),
and thus lower capital cost. The results are set out in Table 8. The
storage basket cost is increased (from $0.31/kg U to $0.43/kg U 1972 $)
causing an increase in the operating costs but an overall decrease in
total cost. Once again there is a slight decrease in the perpetual care cost.
![Page 71: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/71.jpg)
E-14
2.2 COST ESTIMATE FOR SHORT-TERM FACILITY
The incremental cost for the short-term facility was calculated
using the present worth, analysis (Appendix B).
The breakdown of incremental capital expenditure is given in
Table 9. The capital expenditure estimates are based on Bruce G.S. A costs.
The breakdown of the incremental operation and maintenance
cost is given in Table 10. There is probably no increase in the labour
cost due to the extension. The main increase in cost results from the
extra power, equipment, materials (e.g. resin), and storage baskets
required and management of the extra radioactive wastes produced.
Combining the costs, the estimate for storing spent fuel for
an extra two (1-3) years is $0.27/kg U and for an extra four (1-5) years
is $0.47/kg U. These figures are expressed in 1972 dollars (Table 11).
3. SAFETY ASSESSMENT
3.1 ACTIVITY IN SPENT FUEL
The radioactivity associated with spent fuel can be categorized
into two groups, fission products and actinides. While gamma radiation
is the main hazard earlier in the life of the spent fuel, this decays
relatively quickly and beta and alpha radiation become the main hazards.
Broadly stated,the beta activity is associated with the fission products
and the alpha activity with the actinides. The fission products and the
actinides emit gamma radiation but mostly of low energy, so that the hazard
is relatively low.
Beta and alpha radiation are not very dangerous from an external
radiation dose aspect because of their low penetrability. They are
dangerous if located in body tissues because of their high rate of damage
![Page 72: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/72.jpg)
E-15
per unit distance. The fission products and the actinides have to be
isolated from the biosphere to prevent their being ingested by man
through the food chains and/or through inhalation.
3.2 CONTAINMENT OF ACTIVITY
Since the primary safety objective is to keep the spent fuel
isolated from the biosphere, any safety assessment must evaluate the
possibility of release to the biosphere. This involves an examination
of the possible barriers and what accidents could occur that would lead
to their failure. The primary containment barrier for the spent fuel is
the fuel sheath. To maintain its integrity, the fuel sheath requires
the support of auxiliary systems, for example, a cooling system to
remove the decay heat produced. Part of the safety assessment is to
evaluate the reliability of such supporting systems.
.1i
For water pools, the cooling system is a circulating water '
system with water as a transport agent. The water takes the heat from
the fuel and passes it to the heat sink through heat exchangers. The
water system itself has to be contained and this containment acts as a
secondary barrier against escape of activity to the environment. The
gaseous products of the activity pass through the ventilation exhaust
system to the atmosphere while the solid active material circulates with
the water. A tertiary containment is provided by the leakage collection
system. This however provides only partial containment since it can
handle only small to moderate water leaks.
3.3 ACTIVITY RELEASE PATHS
The possible escape paths of activity from the spent fuel
bundles have been charted in Figure 18. Identified on the chart are the
boundary failures and possible causes together with activity collection
points. An accident analysis would be the next step to determine the
extent of the activity release as well as the probability of the release
occurring along this path.
![Page 73: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/73.jpg)
E-16
4. CONCLUSIONS AND RECOMMENDATIONS
4.1 CONCLUSIONS
1. Previous experience has shown that spent fuel can be storedsafely in pools. This experience is of the order of tens ofyears. Development work would be required to project thisconclusion into the 100 years and longer time range.
2. This study demonstrated that water pools can be engineeredon a large scale.
3. The technology is simple, reliable, well developed and tested.
4. Previous design, construction and operational experiencedemonstrates that a high quality storage facility could bebuilt and operated.
5. The cost estimates are based on actual experience and showthat this method of storage is competitive with other lessproven schemes.
4.2 RECOMMENDATIONS
The following development work should be undertaken if it is
decided to store spent fuel in water pools for a long period of time.
1. Determine the extent of the electrochemical action that takesplace between zircaloy and stainless steel in view of thelong periods of time that these metals will be together.
2. Determine the effects, if any, of the contact of stainlesssteel with concrete over long periods of time.
3. Determine the best methods for controlling the corrosion thatwill take place between the stainless steel liners and thewater in the bays.
4. Determine the corrosion rate of zircaloy in the bay water overthe long term.
5. Evaluate the effects of extended irradiation on the propertiesof zircaloy Ceg. strength, corrosion resistance etc).
![Page 74: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/74.jpg)
E-17
5. SUPPLEMENTARY DATA
5.1 SPECIAL GROUND RULES FOR THIS PROJECT
5.1.1 GENERAL
1. The study used the nuclear power development at Bruce. Atpresent there are 4 x 750 MWe units under construction (1974)and a second station consisting of 4 x 750 MWe units will beadded. In long-term planning, it has been assumed that12,000 MWe would be a limit to work to for electricalgeneration at one location. For the study it was assumedthat another 6000 MWe will be added to complete the nuclearcomplex.
2. It is assumed that a nuclear power plant will operate for30 years.
3. The storage of spent fuel is divided into two areas.
(a) Short-term storage at the reactor site, i.e., up to oneyear of storage although the study will consider storageat the plant up to three and five years.
(b) Long -term storage at the nuclear complex, i.e., fromone year up.
4. Release of gaseous radionuclides to the environment from thelong-term storage facility will be kept to an absolute minimum.The intent of the design is to achieve an essentially zerorelease of radioactive gases. This also applies to the releaseof radioactive liquids.
5. Handling and movement of fuel is to be kept to a minimum.
6. The general ground rules of the study are set down inAppendix &. (Some exceptions have been made especially inthe financial area and the actual values used are noted inthe text.)
![Page 75: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/75.jpg)
E-18
5.1.2 SHORT-TERM STORAGE FACILITY
1. This facility is divided into two bays.
(a) A receiving bay, where fuel bundles received from thefuel transfer mechanism are loaded into baskets priorto being moved to the holding bay. Any canning of fuelin the short-term storage is done in the receiving bay.
(b) A holding bay, which is used to store the spent fuelfrom the reactor up to one year (or three or five years)including the full inventory of one reactor should thatbe necessary.
2. Separate storage and shipping baskets are to be used forcanned fuel and uncanned fuel.
3. The design intention is to keep the spread of contaminationbetween the receiving bay and holding bay to a minimum. Theventilation system in the receiving bay is to be capable ofkeeping the level of gaseous fission products in the atmosphereto a minimum. The release of gaseous and liquid radionuclidesfrom the short-term facility is to be included in the allowablerelease for the station.
IJ. 1.3 LONG-TERM STORAGE FACILITY
1. This facility is to be capable of safe storage from one yearupwards.
2. The storage facility is to be designed to store fuel for 100years after filling.
3. The storage facility is to be designed so as to requireminimum upkeep and operation.
4. The stored fuel, after 100 years, must be capable of beingretrieved and stored in a similar or another facility to bechosen.
5.1.4 FUEL
1. All fuel bundles must be retrievable.
2. Fuel bundles will be stored in baskets capable of being placedin a flask, and used in the long-term storage facility.Pickering fuel storage baskets will be assumed since theWhiteshell Study has used Pickering storage baskets.
![Page 76: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/76.jpg)
E-19
5.2 DESIGN CRITERIA FOR SHORT-TERM FACILITIES
5.2.1 CONCLUSIONS
It was concluded that the major problem In spent fuel bay
operation would be defected fuel. The escaping fission products would
contaminate both the bay atmosphere and the bay water. From there they
would spread throughout the station causing low level contamination - a
constant source of man-rem consumption. When the spent fuel bay water is
contaminated, flasks and other equipment lowered into it have to be
decontaminated causing further expenditure of man-rem.
Experience has demonstrated that on certain occasions the
concentration of fission products (mainly gaseous) in the bay water reaches
the point where the bay itself is a significant source. The fuel handling
equipment often lacks simplicity and accessibility. Thus maintenance on
this equipment usually results in a sizable expenditure of man-rem.
5.2.2 RECOMMENDATIONS
The basic recoimnendations resulting from the study are:
1. Divide the spent fuel bay into two basic areas, a receivingbay and a holding bay.
2. Separate the atmospheres and water of the two basic areas.
3. Design simple and accessible fuel handling equipment.
5.2.3 RECEIVING BAY AND HOLDING BAY
The first bay, the receiving bay, would receive the fuel directly
from the fuelling machine. This bay would be designed to handle high
levels of fission products both in the bay water and the bay atmosphere.
Since the bay would be effectively isolated from the rest of the station,
the spread of contamination would be minimal. Defected fuel would be
canned in this bay and then transported to the holding bay. Any inspection
![Page 77: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/77.jpg)
E-20
or experimentation would be done here as well.
To handle large releases of fission products effectively, the
bay would be kept as small as possible and the ventilation and bay water
purification system would be capable of high clean-up rates. The receiving
bay should be located as close to the reactor as possible. This will
ensure that the defected fuel will be quickly transferred to the receiving
bay for canning, reducing the time available for fission product release.
The second bay, a holding bay, should be separated from the
receiving bay by a water lock, and an atmospheric partition. Pressure
differences between the two bays should be sufficient to ensure that the
air flow between bays would result in flow from the holding bay to the
receiving bay. It is expected that there will be an occasional fuel
defect in the holding bay. The frequency of this occurrence is expected
to be small. The concentration of fission products in the bay should be s,
at a low level and the purification and ventilation systems would be |
designed accordingly. \
![Page 78: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/78.jpg)
E-21
TABLE 1
AVERAGE PRODUCTION RATE OF SPENT FUEL
PLANT
Douglas Pt. G.S.220 MWe
Bruce G.S. A4 x 750 MWe
Bruce G.S. B4 x 750 MWe
Bruce6000 MWe
TOTALBUlwJLÎSS/DAY
1973-1975
6
0
0
0
6
1976
6
13
0
0
19
1977
6
26
0
0
32
1978
6
39
0
0
45
1979
6
52
0
0
58
1980
6
52
0
0
58
1981
6
52
13
0
71
1982
6
52
26
0
84
1983
6
52
52
0
110
1984
6
52
52
100
210
Average bundle discharge rate assumes a capacity factor of 80%.
Each reactor assumed to have 30 years life.
Assumed that 6000 MWe In-service at the beginning of 1984 and finishservice at the end of 2013.
![Page 79: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/79.jpg)
TABLE 2
CAPITAL, OPERATION AN0 MAINTENANCE CASH FLOWS AND FUELARISINGS AT THE SPENT FUEL STORAGE FACILITY
DESCRIPTION
Capital Cash Flow
(less Interest)
1973 MS
Operation and Mtce.
Cash Flow
1973 H$
Fiid ArUings *kgU x 10»
DESCRIPTION
Capital Cash Flow
(less Interest
1973 M$
Operation and Mtce.
Cash Flow
1973 M$
Fuel Arisings
kgU x 10'
1975
0.971
-
0.305
1995
1.975
1.701
1.525
1976
0.886
-
0.138
1996
1.975
1.897
1.525
1977
22.347
-
0.232
1997
-
2.093
1.525
1978
-
0.961
0.327
1998
1.975
2.093
1.52S
1979
1.975
0.955
0.421
1999
1.975
2.092
1.482
1980
-
0.955
0.421
2000
1.975
2.092
1.482
1981
1.003
0.956
0.516
2001
2.078
2.092
1.482
1982
1.004
0.956
0.610
2002
10.920
2.092
1.482
1983
1.975
0.959
0.799
2003
1.975
2.092
1.482
1984
1.975
0.967
1.525
2004
1.975
2.386
1.482
1985
1.975
0.967
1.S25
2005
1.975
2.386
1.482
1986
2.078
0.967
1.525
2006
-
2.385
1.387
1987
11.325
0.967
1.525
2007
1.975
2.384
1.293
1988
1.975
0.968
1.525
2008
1.975
2.383
1.198
1989
1.975
1.701
1.525
2009
-
2.382
1.104
1990
1.975
1.701
1.525
2010
1.975
2.382
1.104
1991
1.975
1.701
1.525
2011
-
2.381
1.010
1992
1.975
1.701
1.525
2012
-
2.380
0.915
1993
2.078
1.701
1.525
2013
-
2.378
0.726
1994
10.641
1.701
1.525
2014
-
2.256
-
to
Fuel arising* In 1975 Is the sum of all Douglas Fc. G.S. spent fuel from in-service date to end of 1975.
![Page 80: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/80.jpg)
E-23
TABLE 3
SUMMARY OF CAPITAL COST
COST SOURCE
DIRECTSCommissioningSite Improvements and WorkBuilding and StructuresElectricsInstrumentation and ControlCommon Processes and Services
TOTAL DIRECTSConstruction IndirectsEngineering
TOTAL CONSTRUCTION COSTAdministration OverheadsInterest During Construction
TOTAL ALLOCATED COSTContingencies
TOTAL PROJECT COST
1973 k$
2,260.0879.0
69,193.0388.0220.0
9,868.0
82,808.0
14,264.01,300.0
98,372.0
2,215.04,136.0
104,723.0
4,250.0
108,973.0
Ï
TABLE 4
SUMMARY OF OPERATING COST
SOURCE
Labour
Transport andWork Equipment
Resin Replacement
Demineralized Water
Power
Radiation Waste
Building Maintenance(0.1% of Bldg Capital)
Major Equip Mtce(1% of Equip Capital)
Taxes and Insurance(1 1/22 of Capital Inv)
TOTAL (1973 k$)
1978-1988
295
30
32
1
27
15
100
65
386
951
1989-1996
402
66
32
2
31
15
100
80
957
1685
1996-2003
402
66
32
2
35
16
100
95
1329
2077
2004-2013
402
66
32
2
46
16
100
105
1602
2371
2014 +
287
5
16
-
41
11
100
105
1691
2256
![Page 81: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/81.jpg)
E-24
TABLE 5
INVESTMENT IN THE PERPETUAL CARE FUND AT THE YEAR 2014
COST SOURCE
General Operating Costs(Annual)
Leaking Bay Recoveryand Restorage(Every 25 years)
Equipment Replacement(Every 33 1/3 years)
Facility Replacement(Every 100 years)
Fuel Transfer AndDecommission(Every 100 years)
AMOUNT1973 M$
2.256
3.2
15.0
84
31
F
34.7
0.98
0.66
0.062
0.062
TOTAL INVESTMENT IN FUNDAT START OF YEAR 2014
INVESTMENT INFUND AT 2014
1973 M$
78.3
3.1
9.9
5.2
1.9
98.4
(Investment at 2014 = Amount x F)
TABLE 6
PRESENT WORTH ESTIMATE OF COSTFOR MANAGEMENT OF SPENT FUEL
COST SOURCE
A. STORAGE COSTCapital CostOperating Cost(includes storage basket)
B. PERPETUAL CARE COSTTOTAL UNIT COST OF
MANAGEMENT OF SPENT FUEL
1972 $/kgU
2.57
1.53
1.23
5.33
![Page 82: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/82.jpg)
E-25
TABLE 7
PRESENT WORTH ESTIMATE OF COST FORMANAGEMENT OF SPENT FUEL WITH DESIGN IMPROVEMENTS
COST SOURCEA. STORAGE COST
Capital CostOperating Cost(includes storage basket)
B. PERPETUAL CARE COSTTOTAL UNIT COST OF
MANAGEMENT OF SPENT FUEL
1972 $/kgU
2.02
1.53
1.22
4.77
TABLE 8
PRESENT WORTH ESTIMATE OF COST FOR MANAGEMENT OF SPENT FUELWITH DESIGN IMPROVEMENTS AND INCREASED STACKING DENSITY
COST SOURCEA. STORAGE COST
Capital CostOperating Cost(includes storage baskets
B. PERPETUAL CARE COSTTOTAL UNIT COST OF
MANAGEMENT OF SPENT FUEL
1972 $/kgU
1.69
1.65
1.21
4.55
![Page 83: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/83.jpg)
E-26
TABLE 9
PRESENT WORTH ESTIMATE OF INCREMENTAL CAPITAL COST
COST SOURCEDIRECTSCivil and StructuralElectricalInstrumentation and ControlCommon Services
TOTAL DIRECTSConstruction IndirectsEngineering
SUBTOTALAdministration OverheadsC2 1/4% of Subtotal)Interest During ConstructionC8% per annum)
TOTAL ALLOCATED COSTContingencies
TOTAL ADDITIONAL COST
1-3 Years1972 $
610,00057,000
230,000
897,000
243,000
1,-140,000
26,000
48,000
1,214,000
127,000
1,341,000
1-5 Years1972 $
1,026,000113,000
418,000
1,557,000
448,000
2,005,000
46,000
83,000
2,134,000
214,000
2,348,000
TABLE 70
PRESENT WORTH ESTIMATE OF INCREMENTALOPERATION AND MAINTENANCE COST
COST SOURCELabour (approx)
Power, Materialsand Waste Storage
Extra Storage Baskets
TOTAL
1-3 Years1972 $
405,000
281,000
686,000
1-5 Years1972 $
688,000
550,000
1,238,000
![Page 84: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/84.jpg)
E-27
TABLE 11
PRESENT WORTH ESTIMATE Of TOTALINCREMENTAL COST FOR A SHORT-TERM FACILITY
No. of BundlesProcessed ThroughSpent Fuel Bay
Weight of Spent FuelProcessed
569,400
11.4x106kgU
COST SOURCEIncremental CapitalExpenditure
Incremental Operation
TOTALUnit Cost
1-3 Years1972 $1,341,000
686,000
2,027,000
$0.27/kgU
1-5 Years1972 $
2,348,000
1,238,000
3,586,000
$0.47/kgU
![Page 85: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/85.jpg)
PROJECTS
BRUCE 1—4
E12 PICKERING 5—6
El 3 BRUCE 5—8
El4 BOMMANVILLE
El5 FOSSIL OR NUCLEAR
4—750 MW
El 6 NUCLEAR 4—750 MW
El 7 NUCLEAR 4—1200 MW
El 9 NUCLEAR 4—1200 MW
E20 NUCLEAR 4—1200 MW
1976
•
1977
•
1978
•
1979
•
1980
•
1981
• «
•
1982
» •
1983 1984
. . . |
• + '• <
(
1985
> •
1986
•
1987
1 (
1988
}
•
•
1989
•
•
^
FIGURE 1
FUTURE PROGRAM
IN SERVICE DATE
![Page 86: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/86.jpg)
E-29
20x106
J5JOD6
„_ 10M06
o
0.5 x106
BGS B - BRUCE GS B
PGS B - PICKERING GS B
BGS A - BRUCE GS A
PGS A - PICKERING GS A
1970 1975 1980 1990 1395 2000
YEAR
FIGURE 2: ACCUMULATED SPENT FUEL
![Page 87: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/87.jpg)
E-30
BAIK DU DORE
STUDY LOCATION OF , - -.SPfHITFUEl \ S"^ \
PROPOSED BRUCE STORAGE FACILITYHEAVY WATER PLANT
MCTftI*
FIGURE 3: STUDY LOCATION OF SPENT FUEL STORAGE FACILITY
![Page 88: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/88.jpg)
E-31
S
I
5o
10'
10 -
IOC 10 '
FISSION PRODUCTS
J L J L
I 0 3 10' 10s 10 '
TIME (YEARS)
10' 10 ' 10!
FIGURE 4: DECAY HEAT PRODUCTION FROM SPENT CANDU FUEL(9000 MWd/Mg U)
![Page 89: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/89.jpg)
mwto
FIGURE 5: SPENT FUEL STORAGE FACILITY
![Page 90: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/90.jpg)
"i-
L
iv
= r5?
PLAN WITH CONCRETE SLABS ANDSTAINLESS STEEL LINERS REMOVED
PLAN
1.37m .76mW-6") 6.55m (21--6") <2'-6")
i i6.25m |20'-6") | | 6.25m (2O'-6") |1.07m
PLAN
WATER LEVEL
6.2Sm (20'-6"> (5'V
SECTION WITH CONCRETE SLABS ANDSTAINLESS STEEL LINERS REMOVED
FIGURE 6: STORAGE BAY
![Page 91: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/91.jpg)
SECTION
PLAN
!
si
STAINLESS STEEL COVbRiilII!
. ! i !Hl! J.
iJJÀ.
-WEATHER PROOF AIR INTAKE
WATER, SEWAGE LEAKAGECOLLECTION RETURNRAD WASTE
PLAN
AGE I1 •
SCALE IN METRES
FIGURE 7: SECTION OF STORAGE BAY
![Page 92: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/92.jpg)
E-35
DISCHARGE STACK
SPENT FUEL BAYS (TYPI—»-j
I J.II t
WEATHER RESISTANT HOUSING-»}"?- ""
INTAKE jFILTER
FIGURE 8: FLOW DIAGRAM - VENTILATION SYSTEM
![Page 93: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/93.jpg)
2 2275 rr.3 1500.000 IMPERIAL GALLON!-DEMINERALIZED WATER
STORAGE TANKS ' I
-SERVICE & CONTROL CENTRE
FIGURE 9: FLOW DIAGRAM — COOLING SYSTEM
![Page 94: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/94.jpg)
J
LOADING CELL
24 GAUGE STEEL FACEDI 7.62mm iZ") THICK POLYURETHANE
FOAMED CORE PANELSOBSERVATIONWINDOW
RETRACTABLE LADDER-THAVEL RAIL i ~
7sTEEL ROOF DECK fI AND SIDING PANELS »
10.2 mm (4") FIBERGLASSINSULATION STEEL PLATEINTERIOR PANELS
SCALE IN MCTNES
FIGURE 10: LOADING CELL
![Page 95: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/95.jpg)
CONCEPT DEFINITION
0
AQUISITION
COWMISSIOIIIHC
7OPERATION
__ - . .E FIUHW »SIIUNG VIUIT H* 1 IAVST0TA1 OF 11 TEARS TD COMttlH.Stf DWG 5CHGS I I I I I - I 1 S I
ISIIIHIESS StlElLIHtR IHSIAUED
. VAUU H* 1I COICflETI' COMPIEK
FIGURE 11: PROJECT LIFE CYCLE — SPENT FUEL STORAGE FACILITY
![Page 96: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/96.jpg)
T—i—i—i—i—i—i—i—i—i—r—i—i—r—I—i—r—i—i—i—i—i—i—i—r—i—i—i0 1 2 3 « 3 « 7 • • 10 I I 1 13 14 IS 1» 17 » 1* 20 21 22 23 24 25 26 2
1 1 1 1 1 1 1— I 1 1 1 1 1—" 21 2» 30 31 32 33 34 39 1 * 37 3» 3*
CALENDAR ITEMS
LONG TERM SPENT FUELFACILITY
PRELIMINARY ENGINEERING
SITE IMPROVEMENTSPROCUREMENTCONSTRUCTION
a"1VAULT Nt 1FILLEO tSEALED
VAULT N91
FIUWS « 0 SEALING IAYS
INSTALLATION OF STAINLESS STEEl LINERS a i BLUE aVAULT N?2FILLED ï SEALED
VAULT N? 2
FILLING AND SEALING MVS
ENGINEERING
CONSTRUCTION
INSTALLATION OF STAINLESS STEEL LINERS
mma LU H msa
I i
TTVAULT NI 3FILLED «SEALED
w
VAULT N° 3
FILLING AND SEALING IAVS
ENGINEERING
CONSTRUCTION
INSTALLATION OF STAINLESS STEEL LINERS
BE
mm E. H
i
VAULT N MFILLED «SEALED
VAULT NP 4
FILLING AN» SEALING H V S
ENGINEERING
CONSTRUCTION
INSTALLATION OF STAINLESS STEEl LINERS
H• 1 * 1 * 1 * 1 » 1 «
SHi LUiSi IB!
FIGURE 12: CONSTRUCTION SCHEDULE - SPENT FUEL STORAGE FACILITY
![Page 97: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/97.jpg)
E-40
L
PLAN
FUELLING MACHINE DUCT
FIGURE 13: EXISTING SPENT FUEL BAY AT BRUCE GS A
![Page 98: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/98.jpg)
E-41
LSECTION SECTION
34.93m,. (114--6"). .
, • 7 7 . T
SPENT FUELPORTS
PLAN
NEW FUEL ROOM
WINDOW
\ WL 636.0
J^^W^W1
,-r1
PLAN
1FUELLING MACHINE OUCT
MALE IN MCTRES
FIGURE 14: ONE YEAR SPENT FUEL BAY
![Page 99: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/99.jpg)
E-42
L
PLAN
CN
JSECTION
SPENT FUELPORTS
r—NEW FUEL ROOM |
II \ || WINDOW |
I 615.0
______ *v--'*.2 k|'
FUELLING MACHINE DUCT-
WWWK^T****»
PLAN
FIGURE 15: THREE YEAR SPENT FUEL BAYSCALE IN METRES
![Page 100: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/100.jpg)
E-43
L
PLAN
FUELLING MACHINE DUCT- 0 10 «0
SCALE IN METRES
FIGURE 16: FIVE YEAR SPENT FUEL BAY
![Page 101: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/101.jpg)
, , ~ ~ _ _ ~ ~ J_, _A]CONCRETEL 1 J EMERGENCY BASKET STORAGE ^SHIELDING
FUEL STORAGEBASKET ONINDEX TABLE
MAN-BRIDGE-GANTRY & HANDRAILING| NOT SHOWN ON THIS VIEW FOR CLARITYJ
J
EQUIPV -NT IS SYMMETRICAL ABOUTNORTH/SOUTH WITH THE EXCEPTIONOP THE PERISCOPE
FUEL STORAGEBASKET POSITIONED *ON INDEX TABLE
PLAN
-SPENT FUEL PORT
— FUEL TROUGH
HYDRAULIC RAM
HANDRAILING & EMERGENCYSTORAGE BASKETS OMITTEDFOR CLARITY IN THIS VIEW
O I 8 3 4 5
SCALE IN METRES
FIGURE 17: RECEIVING BAY LAYOUT AND FUEL HANDLING EQUIPMENT
![Page 102: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/102.jpg)
Fuel Sheaih Failu
'n-.nmn Fiom tmliMii len.^'nonnit.it D.im.itu; IDroppinq.» Fl.isk)
Failure
Activity collection point
®J Mattim Structural Boundaryà FaHura (Concrtt* Bay and
SS L i w l Resulting in Lossof Coolant
AcB. y Wai PI
k ®XF \ Boundary Failute / Z \ o.erflowof
1 Circul.ting Coolin9 < F > Waicr Bays
erfili.Tiq Bays 1ikp tip Wjteo I
Acnviiv in HayAimosphere
©1/v\f
\ Bound/ Ventila
CiuseEjrthnMissileCorrnsAccideMech.i
ry Failure /tian System \
on1t.il O.lltld()BIC.ll We.lr
• Scrubber and/orMomtoniq
FIGURE 18 ACTIVITY RELEASE PATHS
![Page 103: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/103.jpg)
F-l
APPENDIX F
STORAGE OF SPENT CANDU FUEL IN CONCRETE CANISTERS
by
S.C. Bhatia and D.R. McLean
1. INTRODUCTION
Concrete canisters are potentially useful for interim storage
of spent fuel. In the concrete canister method, the fuel is stored in
small units which are self-shielding and self-cooling. Once placed in
storage, they do not require any elahorate mechanism for operation,
surveillance, or maintenance. The canisters are easily handled and can
be replaced easily. In an act of war, sabotage or natural catastrophe,
the damage may be limited to only a small number of the canisters.
2. GENERAL DESCRIPTION
2.1 CANISTERS
A concrete canister is a reinforced hollow concrete cylinder
2.29 m (7.5 ft) in diameter and 4.88 m C16 ft) high (see Figure 1). The
all-welded mild steel can within the canister contains 4.4 Mg of spent
![Page 104: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/104.jpg)
F-2
fuel arranged in 37-hundle clusters, the 2.54 cm (1 in) layer of lead
between the fuel-can and the thick concrete walls provides additional
radiation shielding, reducing the surface dose to 15 mR/h.
The canister is stored outdoors. Decay heat from the fuel
flows by radiation and conduction through the air spaces within the fuel-
can and then by conduction through the can wall, the lead, and the concrete;
the outside surface is cooled by natural convection. Heat absorbed from
the sun must also be dissipated from this surface. This additional source
of heat limits the amount: of decay heat that can be handled in the canister
and makes it necessary to pre-cool the fuel at the reactor site for five
years. The use of lead which is a much better shielding material than
concrete, reduces the thickness of concrete required. The temperature
gradient across the canister is shown graphically below the canister in
Figure 1.
Approximately 15,000 canisters are required to handle the
68,000 Mg of fuel being considered for this study. This requires a storage
area of about 0.809 km2 (200 acres). Each canister weighs about 50 Mg
and for most soil conditions only a gravel base is required to carry the
load.
The canisters are fabricated indoors, on-site, in re-usable
metal forms and are cured for approximately 30 days before being given a
final inspection. It is assumed that concrete is supplied from an off-
site batching plant. (If this is not possible, a small batching plant
can be built at the site.) At least 30 canisters will always be in process
in the fabrication building. It was assumed for costing purposes that
5% of the canisters will be rejected because of defects.
2.2 FUEL HANDLING AT THE REACTOR SITE
To minimize handling at the reactor site, the fuel bundles
are stored in baskets. Each basket holds 2.2 Mg of fuel (111 bundles
![Page 105: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/105.jpg)
F-3
stacked in 37-bundle clusters) and is fabricated from stainless steel to
permit storage in the reactor pools. The baskets are filled as the fuel
emerges from the reactor and, after five years of cooling, are placed in
the mild steel storage cans Ctwo baskets per can) for shipment to the
central site. The design of the basket and the fuel-can are shown in
Figure 2.
The cans are filled in a hot cell (not shown). The baskets are
lifted from the pool and allowed to dry in the hot cell before they are
placed in the fuel-can. After the cover has been welded in place (by a
remote welder), the can is inspected and monitored. It is then air-cooled
in a temporary storage cell until ît can be loaded into a shipping flask.
A device for lifting the fuel baskets and the fuel-can is also
shown in Figure 2. It has a circular ring in which three spring-loaded
retractable pins are fixed. When this ring is placed in the top of the
basket or fuel-can, the retractable pins are released and fit into the
three holes in the basket or the can frame which can then be lifted by
eye bolts attached to the ring.
An allowance for the cost of the hot cell and extra handling
for the canning operation is included in the cost of the fuel storage can.
2.3 FLASK AND CANISTER HANDLING AT THE CENTRAL STORAGE SITE
The operations involved in transferring fuel from shipping
flasks to the canisters and moving the canisters out to storage are shown
in Figure 3. The hot cell where the unloading takes place is shown in
Figures 4, 5, 6, and 7. The design permits the fuel to be transferred
without taking either the flask or the canister into the hot cells. This
is achieved by parking the flask (on rail cars or trucks)and the canister
(on a flat bed truck) under the hot cell, where shielding collars are
lowered to their top surfaces (see Figure 6). After the shielding plugs
have been removed, the fuel cans are transferred with, an overhead crane.
Two flask unloading ports are provided to speed up operations. If a
![Page 106: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/106.jpg)
F-4
canister is not ayailable, the fuel cans are stored temporarily in an
air-cooled storage cell Cspace for 16 cans).
In the first few years of operation, the frequency of shipments
to the site will be low. To reduce -manpower requirements in this period,
the flask unloading crew will simply transfer all the fuel to the temporary
storage cell. This same crew can then transfer the fuel to the canisters
between flask shipments.
The hot cell is equipped to handle fuel cans that fail during
shipment. If the monitoring operations reveal that a newly arrived flask
is badly contaminated within, it is removed from the transport vehicle
and unloaded in the isolation cell. The fuel cans are repaired or replaced
in the repair cell.
When a canister has been loaded, lead shot is poured into the
space around the fuel can and the shielding plug is inserted. The shielding
collar is raised and the canister is moved forward below a ring-shaped
gamma scanner. This scanner is slightly larger in diameter than the
canister and is lowered automatically over the canister to check the
radiation field from top to bottom. If the canister passes inspection,
it is moved forward again and an automatically operated welder is lowered
to weld the shield plug in place. The canister is then hauled on the
flat bed truck to the outdoor storage area.
The canisters are placed outdoors in a storage area on gravel
beds suitable for withstanding the load of the canisters. Gravel roads
are provided around each bed for trucks and the canister handling crane.
Each bed is 7.62 m (25 ft) wide by 464.8 m (1525 ft) long and provides
space for 200 canisters placed in a square pitch arrangement. A layout
of the storage site and the area around the main buildings is shown in
Figure 8.
The truck carrying the canister is brought near the storage
spot over which a canister handling crane (Figure 9) is positioned. The
![Page 107: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/107.jpg)
F-5
canister is lifted from the truck by the crane and placed in position on
the gravel hed.
The cabins of the truck and the crane are lined with lead to
ensure that under normal operating conditions workmen will not received
more than 2 R/a.
The storage area is to be monitored as follows:
1. Runoff flowing from the storm sewers will be sampled andmonitored.
2. Zone monitors will monitor the air and the radiation fieldsfrom the canisters.
3. A portable truck-mounted monitor will be used on a routinebasis to check the site for the presence of abnormalradiation fields which might indicate that a serious crackhas developed in a canister.
2.4 PERSONNEL REQUIREMENTS
The canister handling load will increase from three per week
in 1982 to 27 per week in 2004. The canister arisings and the canister
handling capability are plotted against calendar years in Figure 10.
In 1982, 15 persons will be employed. They will be able to
handle a nominal throughput of 7 canisters per week initially but this
will gradually improve to 10 per week by the year 1992 through experience
and by standardization of the handling procedures. The personnel required
will increase to 29 by 1993 and to 59 by 2001. A breakdown is shown in
Table 1 for the last period. Beyond the year 2004, only routine surveil-
lance will be required for the storage area and this will require 10 people.
2.5 OVERALL SCHEDULE
As a result of the four additional years of cooling required
at the reactor site for fuel stored in canisters, the first arisings are
not sent to the central site until 1982 and the last shipment of fuel is
made in 2004. (In schemes where one-year-cooled fuel can be stored, the
![Page 108: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/108.jpg)
first shipments are sent in 1978 and the last in 2000.)
The hot cells and some of the auxiliary facilities must be
ready before the first shipment arrives. Construction should be completed
between 1981 - J.982. The canister storage area will be prepared as
required. Three rows of storage plots (i.e. 9. plots) will be prepared
at a time.
The life of the canister handling facility and the canisters
is expected to be about 50 years. Then a new canister handling facility
will be built and the canisters will be replaced gradually.
3. COST SUMMARY
3.1 CAPITAL COSTS
3.1.1 GENERAL CAPITAL EXPENDITURES
Approximately $9 million must be spent on design and construc-
tion of facilities between 1979 and 1981 to prepare the site for the first
fuel shipments. A breakdown of this cost is shown in Table 2. "Land and
Yard Development" includes roads, railroads, parking lots, fencing,
lighting, perimeter roads required at the canister storage area, a portion
of the low-level waste burial grounds, and the first three rows of canister
storage plots (nine plots in total) with adjoining roads. "Buildings
and Building Equipment" includes all buildings shown in Figure 8 except
the canister fabrication plant and the administration, cafeteria, and
stores buildings.
The cost of the canister fabrication plant is included in the
unit costs for the canisters which will be described subsequently.
The administration building, cafeteria, and stores will be
built in 1992 to coincide with an increase in personnel required to
![Page 109: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/109.jpg)
F-7
handle the growth in fuel shipments to the central site. The entire
expenditure in 1992 amounts to $1.5 million. It includes expansion of
the low-level waste burial grounds, completion of the storm sewers and
monitoring systems required at the canister storage area, replacement of
some worn-out rolling stock, and some additional mobile equipment (see
Table 3).
This brings the total general capital expenditures to about
$10.5 million. An additional $3.3 million will be spent in stages between
1982 and 2004 for new storage plots to handle the new canister arisings.
The spending schedule for these plots is shown in Table 7.
3.1.2 CAPITAL EXPENDITURES FOR FUEL CAMS AND CANISTERS
Two baskets are required per fuel-can at a cost of $777 per
basket. The unit cost per fuel-can (4440 kg U), including filling charges,
amounts to $3600 per can; canisters including the lead shot cost about
$4500 each (see Table 4). The total capital expenditure for baskets, cans,
canisters, and lead during the site filling period is $147 million.
3.2 ANNUAL OPERATING COSTS
To illustrate the cost of the various items that make up the
annual operating cost, a breakdown for the year 2004 is given in Table 5.
The total expenditure for that year is $1.2 million. The total values
for each year are shown in Table 7.
3.3 PERPETUAL CARE COSTS
Annual operating costs beyond the year 2004 were estimated to
be $0.6 million (see Table 6). To provide this sum in perpetuity, a
sinking fund of $21 million must be established by 2004.
It was assumed that the site facilities, the canisters, the
lead shot, and 5% of the fuel-cans would be replaced at 50 year intervals.
![Page 110: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/110.jpg)
F-8
The replacement costs in 1972 dollars were assumed to be the same as the
initial costs with the following adjustments;
1. The old lead shot could be sold for 50% of its initial valueand the resultant income applied to the cost of the new lead.
2. Operating costs for the replacements would be 1.5 times greaterthan the total operating expenditures in the first site fillingperiod (1982 - 2009).
3. The old canisters would be disposed of at a cost of $1000/canister.
The total expenditure for replacements at the end of each 50
years was estimated to be $111 million. This cost can be covered in
perpetuity with a sinking fund valued at $35.0 million in 2004.
The total investment in perpetual care is $56 million.
It can be shown that if canister storage is used for 100 years
rather than in perpetuity the investment required is $54 million. If, after
100 years the fuel is shipped to a salt mine for final disposal an
additional investment of $17.73 million is required.
3.4 LEVELIZED STORAGE PRICE AT CENTRAL SITE - $/kq U
The capital, operating, and perpetual care cost data that are
required to estimate the levelized storage price are shown in Table 7.
The levelized price amounts to $2.7I/kg U for capital and
operating expenses. Perpetual care costs are $0.67/kg U. If canister
storage is used for 100 years the sinking fund costs are $0.65/kg U. The
additional amount required to switch to salt storage at the end of the
100 year period is $0.21/kg U. A breakdown of the levelized price is
shown in Table 8.
3.5 PENALTY FOR STORAGE FOR FOUR EXTRA YEARS
As mentioned previously, this scheme requires five year cooled
fuel. Ontario Hydro has calculated that the cost of storing fuel for an
extra four years at a reactor site is $0.47/kg U.
![Page 111: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/111.jpg)
F-9
3.6 SHIPPING
WIRE has calculated that the cost for shipping fuel from the
reactor site to a central storage site amounts to $2.20/kg U (see
Appendix I).
3.7 DEVELOPMENT COSTS
A development program for a surface storage facility has been
considered to cover a 10 year period prior to the emplacement of fuel on
a routine basis at a selected site. It includes funds for development
work, site selection, public, information, and capital and operating
expenditures for pilot work. The total cost is $4.0 x 106. If the
development costs are charged against the fuel arisings to the year 2004,
the additional cost to the total scheme is $0.10 kg U.
3.8 TOTAL COST FOR MANAGEMENT OF SPENT FUEL IN CONCRETE CANISTERS
A breakdown for the total levelized cost of the management
of spent fuel in concrete canisters is given in Table 9.
4. GENERAL COMMENTS ON CANISTER STORAGE
1. A canister is an independent, self-contained unit for thestorage of spent fuel. Canisters are easy to handle, transport,repair or replace. They mav be safer with respect to acts ofwar, sabotage, or natural catastrophes than large vaults.They should require very little care during their entireservice life except for minor routine surveillance. Thisadvantage is offset somewhat by the large number of canistersrequired.
2. Since the canister offers dry storage in a sealed container,there is little chance that a major leak may occur causinglarge scale spread of contamination, because it is not likelythat all the canisters will leak at the same time.
3. The design of the fuel-can, and the concrete canisters maybe improved even during the filling period without causingmajor changes in the project.
![Page 112: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/112.jpg)
F-10
4. Loss of cooling by natural or artificial means is unlikely.
5. The spent fuel can be retrieved easily.
6. Defective canisters vjill be rejected by quality controlprocedures at the manufacturing stage. A rejection rate ofabout 5% is included in the cost of the canisters.
7. Development work is essential to confirm the temperaturegradients and the dose rates estimated in this report and toexamine the thermal stresses in the concrete.
In this phase of the study, only relatively simple and basic
concepts were examined. Suggestions for further study which might improve
the concept are as follows:
1. The emissivity of the canister surface could be improved and,therefore, its heat load from the sun could be reduced, bypainting the surface of the canister with metallic paint.This may allow the decay heat load to be increased, eitherby storing younger fuel or by increasing the cluster size from37 bundles to 61. To ensure that the centerline temperatureof the fuel-can does not exceed 300°C, the temperature dropacross the cluster can be reduced by filling the air spacesin the can with fine sand. Because of the self-shieldingeffect of the bundles, the required increase in shieldingthickness of the canister will be small. If 61-bundle clusterscan be used, the storage price per kg U will be loweredsignificantly.
2. The life of the canister may be greatly increased if theconcrete surface is waterproofed and covered with an aluminumskin to slow down weathering.
3. Monitoring would be facilitated by putting a roof over eachstorage bed occupied by canisters. This would cost about$0.20/kg I). If the roof is peaked and an opening is providednear the peak, warm air rising from the canisters could bemonitored for activity as it leaves the roof opening. Afurther advantage would be a reduced sun heat load.
4. A canister made from steel and concrete would have a longerservice life than an all concrete canister. If steel aloneis used a 33 cm thickness would be required for a 37-bundlecluster at five years cooling and 25 cm after 50 years cooling.Thus a canister with 25 cm thick steel walls plus additionalconcrete shielding could handle five year cooled fuel. Thishas the advantage that after 50 years when the integrity ofthe concrete is in doubt, the all steel shielding will provideservice for a further period, which may extend to a few hundredyears. Also, the steel canister may serve as a shipping flaskat the end of the first 50 years, thereby providing some savingin shipping costs. This type of canister might be useful forstoring fuel at the reactor site for 50 years before shippingit to a central surface or geologic storage site.
![Page 113: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/113.jpg)
F-ll
TABLE 1
MANPOWER REQUIREMENTS FOR THE PERIOD 2001 TO 2004
CATEGORY OF PERSONNEL
Site Superintendent
Hot Cell Fuel Handling Operations(12 persons per shift x 2 shifts)
Hot Cell Services(2 persons per shift x 2 shifts)
General Maintenance
Health and Safety: Head
Health and Safety Surveyor
Traffic and Records Clerk
Accountant
Accounts Clerk
Stenographer
Janitors
Miscellaneous Duties
Guards
TOTAL PERSONS REQUIRED
SHIFTALLOCATION
Day Shift
2 Shifts
2 Shifts
Day Shift
Day Shift
Day Shift
Day Shift
Day Shift
Day Shift
Day Shift
Day Shift
Day Shift
2 Shifts
NUMBERREQUIRED
1
27
5
3
1
1
1
1
1
2
2
2
_9
59
![Page 114: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/114.jpg)
V-12
TABLE 2
SUMMARY OF GENERAL CAPITAL EXPENDITURES - 1979 - 1981(All Costs tn 1972 dollars)
CONSTRUCTION COSTS
Land and Tard DevelopmentBuildings and Building EquipmentOther Services: Storm Sewer, Electrical
Substation and Distribution, StorageArea Monitors
Rolling Stock
TOTAL
ENGINEERING SERVICES
Canister DesignSite Facilities: 12% of Construction
Costs dhown Above
TOTAL
OWNERS1 EXPENSE: 2.5% of Construction Costs
CONTINGENCIES: 15% of Construction Costs,Engineering and Owners' Expense
TOTAL CAPITAL EXPENDITURES - 1979 - 1981
MILLIONS
2.373.30
0.570.48
0.03
0.81
OF DOLLARS
6.72
0.84
0.17
1.16
8.89
![Page 115: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/115.jpg)
F-13
TABLE 3
SUMMARY OF GENERAL CAPITAL EXPENDITURES IN 1992CA11 costs tn 1972 dollars)
MILLIONS OF DOLLARS
CONSTRUCTION COSTS
Buildings and Building Equtpment -Administration, Cafeteria, Stores 0.25
Expansion of Services at Storage Area;Roads to Low-Level Vaste Burial Grounds,Storm Sewers, Monitor for Canister Storage 0.63
TOTAL 0.88
ENGINEERING: 12% of Construction Costs 0.11
OWNER'S EXPENSE: 2.5% of Construction Costs 0.02
CONTINGENCIES: 15% of Above Costs 0.15
TOTAL FOR FACILITIES BUILT AT SITE 1.16
ROLLING STOCK: Replacements and SomeAdditional Equipment 0.39
TOTAL GENERAL CAPITAL EXPENDITURES 1992 1.55
![Page 116: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/116.jpg)
F-14
TABLE 4
UNIT COST FOR BASKETS, FUEL-CANS AND CANISTERS
BASKETS C2 per fuel-can)
FUEL CANS
Material, Fabrication Labour, Inspectionand Overheads
Capital Charges for Hot Cell at ReactorSite and Hot Cell Services
TOTAL FOR FUEL-CAN
CANISTERS
Materials, Labour, Inspection andOverhead in Canister ManufacturingPlant Plus 5% for Defects
Lead Shot
UNIT
1400
2200
25701900
TOTAL FOR ONE FUEL-CAN AND ONE CANISTER
COST, $
1554
3600
4470
9624
$/kg U
0.35
0.81^
1.01
2.17
If stainless steel rather than mild steel cans are used thecost may be about 20-30ç/kg U higher. (Assumed a thinnerwalled can if fabricated from stainless steel)
TABLE 5
SUMMARY OF ANNUAL GENERAL OPERATING COSTS IN 2004
MILLIONS OF DOLLARS
MANPOWER - 50 People @ $10,000/a 0.50
UTILITIES - Fuel Oil, Electrical Power andWater Supply 0.03
OPERATING SUPPLIES, 25% of Manpower Costs 0.13
MAINTENANCE, 1.0% of General Capital InvestmentPlus 0.25% of Cost of Filled Canisters 0.35
TAXES AND INSURANCE, 1.5% of General CapitalInvestment 0.20
TOTAL GENERAL OPERATING COSTS IN 2004 1.21
![Page 117: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/117.jpg)
F-15
TABLE 6
PERPETUAL CARE COSTS
ANNUAL OPERATING EXPENSES
Manpower, 10 Men @ $10,000/aUtilities, $1000/monthOperating Supplies, 15% of Manpower
CostsMaintenance, 0.5% of General Capital
Investment Plus 0.25% of Cost ofCanisters
Taxes and Insurance, 1.5% of GeneralCapital Investment
TOTAL ANNUAL OPERATING COST
INVESTMENT IN PERPETUAL CARE FUND IN YEAR2004 TO COVER ANNUAL OPERATING EXPENSE
REPLACEMENT OF SITE FACILITIES^ CANISTERSAND FUEL CANS AT 50 YEAR INTERVALS
Replacement Cost: Site FacilitiesReplacement Cost: Canisters
$100$ 12
$ 15
$220
$200
$613
$14 x$97 x
TOTAL REPLACEMENT COSTS $111 X
INVESTMENT REQUIRED IN PERPETUAL CAREFUND IN YEAR 2004 TO COVER REPLACEMENTS
TOTAL INVESTMENT REQUIRED IN PERPETUALCARE FUNDS IN YEAR 2004
000000
000
000
000
000
$21.3 x 106
106
106
106
$34.7 x 106
$56.0 x 106
![Page 118: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/118.jpg)
TABLE 7
SUMMARY OF EXPENDITURES FOR CAPITAL, OPERATING AND PERPETUAL CARE
NUMBER OFCANISTERS
164
182
205
225
259
236
277
331
383
446
511
581
658
730
818
903
973
1060
1131
1198
1263
1333
1426
15302
DATE
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
GENERAL
0.40
4.85
3.64
1.55
10.41
CAPITAL, MILLIONS
EXPAND STORAGEPLOTS AND ROADS
0.43
0.43
0.43
0.43
0.43
0.43
0.43
0.29
3 . 3 0
OF DOLLARSFUEL CANSCANISTERS
AND BASKETS
1.59
1 . 7 5
2.00
2.17
2.49
1.42
2.67
3.18
3.68
4.29
4.92
5.59
6.33
7.02
7.87
8.69
9.36
10.19
10.87
11.88
12.20
12.88
13.71
147.25
TOTALCAPITAL
OPERATING,MILLIONS OF
DOLLARSGENERAL
PERPETUAL CARE, MILLIONS OF DOLLARSANNUAL OPERATING AND REPLACEMENT
CAPITAL FACILITIES
0.421
0.421
0.431
0.431
0.448
0.448
0.458
0.458
0.468
0.474
0.696
0.706
0.723
0.733
0.744
0.759
1.05
1.06
1.08
1.11
1.15
1.19
1.21 56
160.99 16.67 56.0
i
![Page 119: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/119.jpg)
F-17
TABLE 8
LEVELIZED COSTS FOR CAPITAL, OPERATING AND PERPETUAL CARE
COSTS,MILLIONS OF DOLLARS
CAPITAL
Expenditure for GeneralFacilities and StoragePlots 13.74
Interest Charges forBorrowed Money ^5.96
TOTAL 19.7
Expenditures for Baskets,Cans and Canisters 147.3
GENERAL OPERATING 16.7
TOTAL fpR CAPITAL AND GENERALOPERATING 183.7
PERPETUAL CARE (Use of Canisters inPerpetuity)
Total Value of Sinking Fund inYear 2004 56.0
Interest Earned to Year 2004 -10.5
Deposits to Sinking FundDuring Filling 45.5
TOTAL COST FOR CAPITAL, OPERATING 229.2AND PERPETUAL CARE
LEVELIZED COST,$/kg U
0.29
2.17
0.25
2.71
0.67^
3.38
If canister storage is used for 100 years, future care costswould be $0.65/kg U. The additional investment required tocover the cost of switching to salt storage at the end of this100 year period Vould be $0.21/kg U.
![Page 120: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/120.jpg)
F-18
TABLE
SUMMARY OF
Development
Penalty for
Shipping
Capital and
COSTS FOR MANAGEMENT OF SPENT FUEL IN CONCRETE CANISTERS
LEVEHZEDCOSTS, $/kg U
, Site Selection and Public Information
4 Extra Years of Storage at Reactor
Operating Costs During Site Filling
Perpetual Care
TOTAL
Sites
Period
0.10
0.47
2.20
2.71
0.67
6.15
![Page 121: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/121.jpg)
F-19
2.32 m.
JêL
4.87 m
«W »•••: ft* V 4I>/
lf>. . . . J»
-PLUG-
FUEL CAN2.54 cm SPACE (filled with lead shot)
3.35 m
76 cm
REINFORCING STEEL
TEMP. °C
TEMPERATUREPROFILE
"ADIAL DISTANCE
CANISTER SEALINGMETHOD-
FIGURE 1: CONCRETE CANISTER
![Page 122: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/122.jpg)
FUEL BASKETS15.24 m 18 cm I.D.
!S< 5.08 x 5.08 xR>0.95 cm
cm O.D.73.7 cm O.D.LIFTING DEVICE(with retractable pins)
1.56 m
. 3.28m
10.1 cm
I1 ,|
1 »
1
|
HI|U—- typ.1 \ .?5 cm
70.5 cm dia.
iTMTnT37 FUEL BUNDLE
CLUSTER(3 per basket)
49.5 cm
2,54 c m — sq. pitch grating7.62 cm
SECTIONAL ELEV. "?';
-STORAGE POOL-(at Reactor Site)
FUEL BASKETS
-FUEL CAN-
-FUEL BASKET-
FIGURE Z-FUEL BASKET ANDSTORAGE CONTAINER-
![Page 123: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/123.jpg)
FLASK RECEIVING AND DESPATCH
1. Check Flasks Physically2. Prepare to Locate Under
Hot Cells3. Despatch to Empty Flasks
back to Reactor Stations
Flaskson Cars
Canisterson Trucks
Unit Train Engine
1. Reverse Unit TrainEngine on a Turn-table and Park
2. Assemble Empty FlaskRail Cars into UnitTrains
CANISTER CONSTRUCTION PLANT
1. Construct ConcreteCanisters
2. Cure Canisters3. Quality Control4. Load Canisters on
Trucks
HOT CELLS OPERATIONS
1. Pre-Monitor Flasks2. Transfer Contaminated Flasks/Fuel Cans to
Isolation/Repair Cells3. Liquid Wastes go to Treatment Cells4. Locate Flasks/Canisters under Shield Collars5. Transfer Fuel Cans from Flasks to Concrete
Canisters or Can Storage6. Post Monitor Flasks/Canisters7. Transport Canisters to Storage Area
CANISTER STORAGE
1. Lift Canisters from Trucks and Place Themon Storage Beds with a Crane
AUXILIARY SERVICES
1.2.3.4.
5.6.7.8.9.10.
Boiler HouseElectrical SubstationWater Treatment PlantMaintenance Shop/GarageStoresAdministrationCafeteriaFire StationGate HouseParking
FIGURE 3: CANISTER HANDLING OPERATIONS
![Page 124: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/124.jpg)
kRAILWAY TRACK
30.48 m AL.
1-SERVICES
91 cm
A
OPERATINGAREA
CHANGEROOM
1REPAIRHOT-CELL
J,ISOVATION
HATCHÏ2.44 m
» • •
HOT CELLSERVICE
> AREA
BU -FLOOR PLAN-ELEV. 30.48 m
76 cm PIPE(30" SCH 10 S PIPE)
MAIN ENTRANCE
OVERHEAD DOOR
FIGURE 4-CONCRETE CANISTER STORAGE-
HOT CELL DETAILS
![Page 125: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/125.jpg)
34.7m
25.9m
STAIRS'
VENTILATIONAND OTHERSERVICES
HOT CELLSERVICEAREA
f \ ( '••-'• i \ 1 •' i \ !
7.9m
l
FIGURE 5 FLOOR PLAN OF HOT CELLSELEV. 37.2m
![Page 126: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/126.jpg)
34.7 m-
HOISTROOM
VENTILATIONANDOTHERSERVICES
15.9 m
OPERATINGAREA
'yyyyyyT,
7.5 m
WASTEOPERATINGAREA
•••'•»•:•»••»*•••' «•:*••
SHIELDINGCOLLAR
TRAVELLINGCRANE
SHIELD PLUG
ELEV. 37.2 m
RAIL CARS
ELEV. 22.6 in
ELEV. 52.4 m
0.61 m
ELEV. 46.3
0.91 m
TEMPORARY STORAGEFUEL HANDLING SHAFT
yyyyyyyy//yFIGURE 6
-CROSS SECTIONAL ELEVATION A-A -OFHOT CELLS
![Page 127: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/127.jpg)
POT.ACTIVE HOLD-UPTANKS & PUMPS
OPERATINGAREA
fi*
1 « y ••»••*•.
IEVAPORATp
ROOM
MED. ACTIVEHOLD-UP TANKS& PUMPS
-FLOOR PLAN-ELEV. 22.6 m
ELEV. 46.3 m
ELEV. 37.2 m
S/ST. COVERS/ST. LINER
ELEV. 30.5 m
EQUIPMENTREMOVAL HATCHES
S/ST. LINERELEV. 22.6 m
tn
FIGURE 7
-CROSS SECTIONAL ELEVATION B-BOF HOT CELLS
![Page 128: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/128.jpg)
RADIO-ACTIVE HASTE
STORAGE TRENCHES 30 m GRAVEL(CANISTERSTORAGE BED)
U— 610 m J
-SITE PLAN- -SECTIONAL ELEV. A-A-
PERIHETER FEXCE
TURNTABLE
300'
1
la
2
2b
3
4
S
6
7
8
9
10
11
12
13
HOT CELLFUTURE EXTENSIONCONCRETE CANISTER CONSTRUCTIONCONCRETE BATCHING PLANT (if required)MAINTENANCE & GARAGEPARKINGGATE HOUSEADMINISTRATION BLDG.CAFETERIABOILER HOUSEFIRE STATIONELECTRICAL SUB-STATIONSTORES SHEDWATER TREATMENT PLANTCANISTER CRANE GARAGE
168 m
MAIN ENTRANCE
-DETAIL A-
EHERGENCVEXIT
FIGURE 8
- CENTRAL STORAGESITE LAYOUT -
![Page 129: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/129.jpg)
CANISTERUNLOADINGFACILITYFIGURE 9
•Tito
![Page 130: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/130.jpg)
F-28
HI
Q.
QUJ
ena:UJ
Q:UJm
t u
3D
20
10
0
OA
-
—
CANISTER
CANISTER
IMPROVED
HANDLING
HANDLING
CANISTFRCAPABILITY
M» ^ ^
1
-
1
1
LOAD
CAPABILITY
HANDLING
•A f I*S PFO PI F
1
Sà
59 PEOPLEEMPLOYED J >
/ # -
i 29 PEOPLEEMPLOYED
—
cMpi nvcn»
I
1982 85 90 95 2000 2004
DATE
CANISTER HANDLING CAPABILITY
FIGURE 10
![Page 131: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/131.jpg)
G-l
APPENDIX G
STORAGE OF SPENT FUEL IN LARGE AIR-COOLEC VAULTS
by
W.M. Campbell and D. Radojkovic
1. INTRODUCTION
At AECI,Power Projects, two closely related schemes for storing
spent fuel, - the Convection and Conduction schemes - have been studied
in sufficient depth to be able to compare them with the schemes being
studied elsewhere. An essential feature of both schemes is the removal
of heat by natural air circulation with the chimney effect of the hot air
rising from the fuel providing the circulation. With this system, fans,
pumps, etc. are eliminated, which reduces the operating costs to a minimum,
and at the same time eliminates the potential hazard due to failure of
mechanical or electrical equipment.
A basic assumption was made that all the fuel produced in
Canada up to the year 2000 would be stored at one central site. A 1969
estimate of spent fuel production, which is about half that of recent
estimates, was used. The difference does not change the cost per kilogram
![Page 132: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/132.jpg)
of uranium significantly, Tut the capital costs are about half those using
the latest estimates.
Secondary containment is required for all storage schemes. In
these it is provided by casting zinc around the fuel bundles in an
aluminum mold, the solidified zinc and, to a certain extent, the aluminum
acting as the secondary containment (Figure 1). If the fuel is reprocessed
at a later date, the casting process can be reversed by heating the
assembly and pouring out the zinc. The process uses zinc which is not one
of the most plentiful metals, but the quantities required will be small
compared with production at least in the short term. Aluminum is plentiful,
however, and may be an acceptable substitute.
The operations can be divided into two parts:
1. Preparation of spent fuel at the reactor site which is commonto both schemes, and
2. Storage at the central site where the facilities are somewhatdifferent.
These are discussed below.
One essential step in the whole process is shipping the fuel
between the reactor and the storage site. This has not been considered
in detail, but there does not appear to bp any significant cost difference
for this step in any of the schemes being considered; with the two schemes
discussed here, there may be a slight safety advantage since the fuel
bundles are cast in metal blocks and will have considerably better
resistance to mechanical damage than bare bundles.
2. REACTOR SITE OPERATIONS
In the spent fuel receiving bay at the reactor, an empty
aluminum extrusion with a perforated bottom welded on is located in front
of the spent fuel discharge mechanism and six bundles are loaded into it.
The loaded extrusion is then raised into the zinc casting position just
![Page 133: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/133.jpg)
G-3
above the water level in the bay. The water drains out, the fuel and its
aluminum container are heated to about 300°C by self heating or by an
external induction heater, and then the molten zinc is poured in (Figure 2).
The extrusion or module is then lowered into the water at a rate of about
5 cm/s (1.95 in/s), which promotes solidification from the bottom up
and avoids shrinkage cracks in the zinc. At this pnint, an extra operation
may be required if the conduction scheme is to be used. This involves
sawing off the top of each module to give a flat contact surface for uniform
heat conductivity. Development work will be required to prove whether
this is lecessary. Finally, the module is lowered into the bay and placed
in a six-module basket (Figure 3). These are stored in the bay until they
are shipped to the storage site (l-r> years) .
In preparation for shipping, the baskets are moved back under
the casting - loading cell (Figure 2), raised up and placed in the decon-
tamination area, washed down, dried and then loaded into the shipping
flask. As indicated in Figure 2, the shipping flask is not removed from
the railway car or truck, and in order to prevent radiation beams during
loading, a shielding collar is lowered to connect the flask and the
casting - loading cell.
3. CENTRAL STORAGE FACILITIES
The storage building at the central site is similar for the
Convection and Conduction schemes as shown in Figure 4. It consists of
two storage vaults, 48.2 m (158 ft) long x 20.7 m (68 ft) wide, connected
by a 15.2 m (50 ft) long unloading bay. The shipping flask on its rail-
way car or truck is positioned in the unloading bay, the cover is unbolted
and remotely removed, and the fuel basket lifted out into the bottom-loaded
transfer flask. This is then moved over the storage site being loaded,
the flask door is opened, and the basket is lowered into the storage site
(Figure 5). Since there may be some residual activity on the outside of
the modules, and there is the possibility of dropping a basket (with fuel
![Page 134: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/134.jpg)
G-4
rupture) during loading, a temporary ventilation and filter system is
provided as shown in Figure 5. Once a site is loaded, the possibility
of activity release is thought to be negligible, so the temporary ventilation
facility is removed and used for the next site to be loaded.
4. CONVECTION SCHEME VAULT
1'igure 6 shows a cross section of the vault. The air inlets
are along both sides of the building just above ground level, and are
provided with screens to keep out coarse, airborne particles. The air
passes into the lrwer distribution plenum and up past each fuel stack.
The stacks are ten baskets (11.2 m (36.6 ft)) high, and are kept vertical
by three 5 cm (1.9 in) diameter pipes which act as supports. The exit
air at about 63°C (1.5 year-cooled fuel with an air inlet temperature of
21°C) then passes out the exits located along both sides of the vault.
With the ten-basket stack, there is sufficient'chimney effect to provide
adequate cooling without any mechanical assistance. Air flow patterns
are likely to dictate the spacing of the buildings and the location of
air inlets and outlets to prevent air recirculation, but these have not
been studied.
Each two-vault building holds 478 000 spent fuel bundles or
9576 Mg of uranium. By the year 2000 seven such buildings will be required.
5. CONDUCTION SCHEME VAULT
Figure 7 shows a cross-section of the vault. The primary
difference between this and the previous scheme is the way the heat is
removed from the fuel. Here the baskets are stacked into concrete cubicles,
each closed at the top by a finned aluminum shield plug. The cubicles
are packed tightly into the vault as shown. Heat is conducted from
![Page 135: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/135.jpg)
G-5
module to module up through the stack, through the shield plug, and into
the air stream above. Again the air inlets with their screens are along
the sides of the building and the exits are along the top centreline.
Airflow, as before, is by natural draft. To keep the maximum fuel
temperature below the specified 300°C, the fuel stacks are only five
baskets (5.6 m (18.3 ft)) high and the fuel is cooled in the reactor bay
for five years before storage. The air outlet temperature is somewhat
lower (35 C) than in the previous scheme.
One two-vault building will hold 335 160 bundles or 6650 Mg
of uranium, so by the year 2000 ten such buildings will be required.
6. GENERAL STORAGE CONSIDERATIONS
The temperatures of the concrete in the vault are higher than
recommended by conventional civil engineering practice. This situation
has not been studied in detail, but it is thought that any problem can
be overcome by the use of appropriate insulation and by modifying the
vault layouts.
Retrievability of the spent fuel is a basic requirement for
all storage schemes. In the above designs, the site loading procedures
can be reversed - the baskets can be removed, and can be restored in
another facility, or reprocessed to recover the plutonium.
Fuel failure during storage is an unknown factor but it is
clear that the evolution of radioactive gases such as krypton-85 and
tritium will not be a problem. Under extreme conditions, the oxidation
of VOz to U3O6 and the formation of a fine radioactive dust is a possibility.
For these reasons, the main purpose of monitoring the fuel storage facility
is to detect the release of solid radioactive particles. A periodic
scanning of the exit air is considered sufficient with a more detailed
check to pinpoint the failure if a release is detected. The development
![Page 136: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/136.jpg)
G-6
program will show more clearly just how failures might occur and how they
can best be detected.
The greatest potential hazards from stored fuel are the release
of radioactivity due to missile impact, or overheating and barrier failure
due to loss of coolant. These have not been evaluated in detail, but it
is difficult to see how loss of coolant can be complete enough to allow
the fuel to overheat to a dangerous level, i.e., there will always be
some cooling and a higher fuel temperature can be tolerated for a
considerable tine.
7. DEVELOPMENT REQUIRED
Host of the uncertainty in the two schemes centres around the
casting step and the behaviour of the fuel during and subsequent to it.
The following are the main questions that would have to be answered.
1. What casting conditions will give a satisfactory productCspent fuel bundles would have to be used for development)?
2. What inspection is required to ensure a satisfactory product?
3. Hot; much loose or fixed activity is left on the surface ofthe castings?
4. Are ruptures in the fuel sheathing likely to occur during thecasting step?
5. How are the Zircaloy properties changed during casting?
6. Is there any interaction between the zinc and Zircaloy duringcasting or later in storage?
7. Can the zinc be melted easily to allow recovery of the bundles?
8. Will the castings withstand stacking, 10 bundles high, atstorage temperatures and for long periods? Present predictionsare that creep and bundle strength are quite adequate butthese need to be checked experimentally.
9. Are the heat transfer calculations for both schemes correct?
10. How much reduction in air flow for both schemes can be tolerated?
11. Is the corrosion of zinc and aluminum acceptable under all theoperating conditions that they will have to withstand?
![Page 137: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/137.jpg)
G-7
12. What type of concrete must be used and how must it be designedto give the maximum facility life?
13. What types of fuel failures might occur and what would theconsequences of such failures Be?
The above development is estimated to require 3 engineers
with supporting staff for 2 years. This means about $300 000 for salaries
with about $500 000 for equipment giving a total development cost of
$800 000. This does not cover the cost of a pilot project - an essential
final requirement.
8. ESTIMATED COSTS
Except where noted, the costs are in 1972 dollars.
The Cominco Product Research Centre at Sheridan Park worked
out the zinc casting process (on paper) and provided a cost estimate for
the capital and the operation.
AECL Power Projects (Peterborough) did a preliminary design
of the handling equipment required for both the reactor sites and the
central storage site and provided a cost estimate.
Assistance was obtained from Ontario Hydro on the design of
the storage buildings and the costs were estimated by AECL-Power Projects.
Table 1 gives the capital costs of facilities required to
handle all Canadian spent fuel production up to the year 2000 by the two
schemes.
Table 2 gives the operating costs both at the reactor and
storage sites during the loading period, i.e., up to the year 2000.
![Page 138: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/138.jpg)
G-8
Table 3 gives the annual costs of spent fuel storage once
the facility is full and includes replacement of the facility at two
time intervals, 50 and 100 years. As far as capital is concerned, the
calculation method is only approximate since a straight-line apportionment
of cost over the life of the facility was used.
Table A shows the perpetual care fund that would be required
at the year 2000 to cover annual operating costs and facility replacement
for an indefinite period beyond the year 2000.
Table 5 summarizes the cost on the basis of dollars per kilogram
of uranium using the perpetual care fund principle. This means that when
the deposit Is made to the perpetual care fund at the year 2000, there
would be no further charges against the uranium.
Table 6 summarizes the cost where the perpetual care fund
system is not used. This shows the costs from the year 2000 to 2050, a
period when facility replacement will not be required, i.e., this is the
period of minimum storage cost. Beyond the year 2050, facility replacement
will be required, assumed here to be at 50 and 100 year intervals. Table 6
gives the costs in dollars per kilogram ->.-r year for an indefinite period
beyond the year 2050.
9. CONCLUSIONS
1. The two schemes are very simple and since they depend onnatural air circulation for cooling there is no mechanical orelectrical equipment. This gives a very low labour cost andwith no equipment to fail, the safety is high.
2. Neither scheme has been proven out but there do not seem tobe any insurmountable problems that cannot be resolved bydetailed design and a development program.
3. Removal of fuel bundles from the cast modules has not beendone, but it should be feasible to do this by inverting themodule and heating it in a furnace to a temperature where thezinc would melt and run out.
![Page 139: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/139.jpg)
G-9
4. Either scheme might be used for storage of solidified, high-level, fission product wastes from a reprocessing plant, althoughthe primary containment would have to be developed.
5. The storage costs as summarized in Tables 5 and 6 are low evenwith a 50-year life for the storage facility - and it is to be hopedit would last much longer. Thus, storage until year 2050would only add about 0.05 U$/kWh to the power cost.
6. As shown in Table 6, taxes and insurance amount to almost 90%of the cost during the 2000 - 2050 period and 40-50% afterthat. At this point it is not clear that these are coststhat would be incurred with a publicly owned facility.
7. The difference in cost between the two schemes is not enoughto outweigh other factors such as development required, safety,etc. The hotter exit air from the convection scheme alighteven be used profitably.
8. Dry storage of spent fuel as proposed is not attractive forshort-term storage where there is a prospect of reprocessing,say up to 20 years, but it has a real attraction for interimstorage due to its simplicity and low operating cost.
![Page 140: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/140.jpg)
G-10
TABLE 1
CAPITAL COSTS(1972 Dollars)
Reactor Site Equipment
Storage Building and Handling Equipment
Miscellaneous Buildings
Electrical Supply
Site Layout and Yard Development
Rolling Stock
Sewers and Water Supply
TOTAL CONSTRUCTION COST
Engineering, Design, Administration,Safety Analysis
Start-up
Owner Costs
Financial Expense
Contingency
TOTAL FIXED INVESTMENT
MILLIONSCONVECTIONSCHEME
6.80
26.00
0.20
0.20
2.00
0.10
0.50
35.80
3.22
0.10
1.87
4.78
7.21
52.98
OF DOLLARSCONDUCTIONSCHEME
6.80
32.20
0.20
0.20
2.00
0.10
0.50
42.00
3.76
0.10
1.92
5.59
8.40
61.77
![Page 141: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/141.jpg)
G-ll
TABLE 2
OPERATING COSTS (1972 $) DURING LOADING PERIOD (TO YEAR 2000)(Except as noted they are the same for both Conduction and Convection Schemes)
Reactor Site Labour
Reactor Site Maintenance Labour
Storage Site Labour
Storage Site Maintenance Labour
Storage Site Overheads
Taxes and Insurance- Convection Scheme
- .Conduction Scheme
Zinc and Aluminum
Storage Baskets
Reactor Site .Equipment Replacement
Conduction Scheme 5 year Storage at Reactor Site
TOTAL COSTS
- Convection Scheme
- Conduction Scheme
$/kg U
0.090
0.027
0.029
0.009
0.325
0.070
0.082
0.784
0.374
0.022
0.50
1.730
2.206
![Page 142: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/142.jpg)
G-12
TABLE 3
COSTS AFTER LOADING PERIOD (AFTER YEAR 2000)(1972 $)
Labour
Taxes and Insurance >
Storage Site Capital Replacement
(a) 50-year vault life
Cb) 100-year vault life
Total (a) 50-year life
(b) 100-year life
(DOLLARS PER kg
ConvectionScheme
0.00177
0.0117
0.0167
0.0090
0.0302
0.0225
U PER YEAR)
ConductionScheme
0.00177
0.0136
0.0194
0.0105
0.0348
0.0259
TABLE 4
PERPETUAL CARE FUND REQUIRED AT YEAR 2000 (1972 $)
Operations
Taxes and Insurance
Facilities Replacement
50-year life
100-year life
Total - 50-year replacement
100-year replacement
MILLIONSCONVECTION
4.11
27.2
17.6
3.7
48.9
35.0
OF DOLLARSCONDUCTION
4.11
31.6
20.5
4.3
56.2
40.0
![Page 143: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/143.jpg)
G-13
TABLE 5
OVERALL FUEL STORAGE COSTS (1972 $)
Loading Period - to Year 2000
Capital
Reactor Site Equipment'Replacement
Operating Labour
Maintenance Labour
Storage Site Overheads
Taxes and Insurance
Zinc and Aluminum
Storage Baskets
Reactor Site Storage, 1 - 5 years
TOTAL to year 2000
STORAGE BEYOND YEAR 2000
Perpetual Care Fund
- 50-year facility life
- 100-year facility life
Total Storage Cost
- 50-year facility life
- 100-year facility life
CONVECTIONSCHEMEC$/kg U)
0.780*
0.022
0.119
0.036
0.325
0.070
0.784
0.374
0
2.510
0.455
0.326
2.97
2.84
CONVECTIONSCHEME($/kg U)
0.908*
0.022
0.119
0.036
0.325
0.082
0.784
0.374
0.32
2.970
0.522
0.372
3.49
3.34
* These values are somewhat high since the reactor site equipmentwill have many years of useful life after year 2000.
![Page 144: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/144.jpg)
G-U
TABLE 6
COST FOR STORAGE BEYOND YEAR 2000
;.."V
Storage From Years 2000 - 2050
Labour
Taxes and Insurance
TOTAL for period
Storage Beyond Year 2050
Labour
Taxes and Insurance
Facility Replacement
- 50-year life
- 100-year life
Total annual cost
- 50-year facility life
- 100-year facility life
CONVECTION$/kg U
0.089
0.585
0.674
$/kg U*
0.00177
0.0117
0.0167
0.009
0.030
0.022
CONDUCTION$/kg U
0.089
0.680
0.769
$/kg U*
0.00177
0.0136
0.0194
0.0105
0.035
0.026
Annual Costs
![Page 145: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/145.jpg)
G-15
•ALUMINUM EXTRUSION
LIFTING LUG
• FUEL BUNDLE•
B
• PLUG •
B
22,8 cm (9.0")
FIGURE 1 CASTING MODULE«7.00000 - M
1*73
![Page 146: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/146.jpg)
G-16
![Page 147: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/147.jpg)
G-17
LIFTING PIN CASTING MODULE
DIVIDER BAR
CENTRAL PIPE
TUBULAR RING
VERTICAL TUBE
FIGURE 3 STORAGE BASKET97.00000 • 38
1973
![Page 148: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/148.jpg)
M'(26.2i»
CONVECTIONBUILDING VAULT
>- -^ j l> •^••^r
S | — CONTHOL DOOM
LAYDOWNAREA
UNLOADING CONDUCTIONBUILDING VAULT
58(17.4i»|
FIGURE 4 FUEL STORAGE BUILDINGS
![Page 149: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/149.jpg)
G-19
BUILDINGCRANE
BASKET LOWERINGMECHANISM
TRANSPORTING
FLASK CLOSURE
TEMPORARYSHIELDING
SLEEVE
TEMPORARY VENTILATION SLEEVE
LOADEDCHANNEL
EXHAUST AIR
INACTIVITY MONITOR
SHIELD PLUG
NORMAL AIR FLOW
„ GUIDE Pli 1;
EMPTY CHANNEL
FIGURE 5STORAGE SITE LOADING WITH
TEMPORARY VENTILATION97 . 00000 . 33
«IV.2.1974
![Page 150: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/150.jpg)
G-20
AIR OUTLET
AIR INLET
CHARGING PLUG
UPPER SHIELD
10 BASKETSSTACKED FUEL
FIGURE 6 DRY STORAGE FACILITY - CONVECTION COOLINGt r ooooo.it
lt?3
![Page 151: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/151.jpg)
G-2J
EXHAUST
COOLING AIR
CONCRETE
FUELSTACK
COOLING FINS
CONDUCTING METALSHIELD CAP
CONCRETE
FUEL STACK
INSULATION 4' • 6" (137 cm) THICK CONCRETE
FIGURE 7 DRY STORAGE FACILITY - CONDUCTION COOLING97 00000 25RfcV. 4 1974
![Page 152: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/152.jpg)
H-l
APPENDIX H
THE STORAGE OF SPENT CANDU FUELS IN SALT MINES
by
D.R. McLean and R. MacFarlane
1. INTRODUCTION
If the reprocessing option is not exercised for CANDU fuel,
two waste management possibilities are open: storage in surface facilities
or burial in geologic formations. Salt was chosen as the geologic option
since it is the only disposal scheme advanced to date which has been
examined in any detail. Active salt disposal programs exist in the U.S.A.
and Germany.
Disposal of radioactive wastes in salt was suggested first by
the U.S. National Academy of Sciences - National Research Council (USNAC)
in 1957 . Since that time, considerable experimental work has been done
and a demonstration of the concept has been completed . Cost estimates
have also been made . Recently (1970), all pertinent work on salt
disposal was re-examined by the USNAC and it has been concluded that bedded
salt is a satisfactory disposal medium for radioactive wastes . As the
USNAC points out, all questions regarding salt disposal have not been
answered. Nevertheless, they judged it to be a sound concept for the
disposal of wastes.
No experience exists in Canada with respect to disposal of
wastes or fuel in salt. It was necessary for this work to rely heavily
![Page 153: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/153.jpg)
H-2
on published reports, mainly from the U.S. Thus the work contained in
this Appendix is mainly the adaptation of American work to CANDU fuel, plus
an independent audit and -up-dating of costs. It should reflect the cost
of disposal of CANDU fuel in salt formations within the limits of accuracy
required for this study.
2. GENERAL CONCEPTS
2.1 MINE LAYOUT
The study is based on a simple mine layout and conventional
mining techniques.
The mine is assumed to be 300 m below the surface in suitable
salt strata and to cover 2.6 km2 (one square mile). This area is divided
into four quadrants, each surrounded by a set of double peripheral tunnels.
The inner peripheral tunnels are used exclusively for mining and mining
ventilation, and the outer tunnels for spent fuel handling and spent fuel
ventilation.
All services and access to the surface are provided by three
shafts:
1. A 4.87 m diameter mining and mining-ventilation shaft (venti-lation supply for mining and spent fuel handling, and miningexhaust air).
2. A 2.44 m diameter shaft for exhausting air from spent fuelhandling tunnels (also used for initial mine development).
3. A 76 cm diameter shaft for lowering spent fuel from the surface.
Storage rooms, each holding 564 Mg of fuel, extend across each
quadrant. There are 32 rooms/quadrant. A typical quadrant is shown in
Figure 1. Mine specifications are listed in Table 1. Container spacings
were estimated from data in reference 4.
![Page 154: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/154.jpg)
H-3
2.2 MINING OPERATIONS
The development sequence for a quadrant is as follows: Starting
at the central region, peripheral tunnels and cross-over tunnels are
excavated around the quadrant. Two storage rooms are then excavated and
fuel insertion begins. Mining of storage rooms continues on an as-required
basis. Mining of peripheral tunnels for an adjoining quadrant is scheduled
such that they are completed when two rooms remain in the previous quadrant.
The techniques used for mining and disposal of salt are described in detail
in Figure 2.* The manner in which the mined salt is disposed of on the
surface is shown in Figure 3.
2.3 WASTE HANDLING
The assumed movement of spent fuel from a reactor site to a
storage hole in a salt mine is discussed in the following paragraphs.
At the reactor site, fuel is packaged in carbon steel pipe
3 m long (9.9 ft.) x 30 cm diameter (11.9 in) (42 bundles/containers)
with plates welded on the ends. These containers are loaded into flasks
and shipped on railway flat cars to the central storage site.
This site has the facilities to unload fuel, check its integrity,
lower it to mine level, transport it to its storage location and store it
in a safe state. Equipment is available to check for contamination and
handle it adequately if the need arises. When flat cars arrive at the
site, they are shunted under the shielding collars of the surface hot cell.
These shields are lowered to form a seal between the hot cell and the
flask top. This allows the flask covers and spent fuel containers to be
removed without taking the flasks inside the hot cell. Facilities are
available in the hot cell to check containers for contamination,
* The drill and blast mining technique was described in ORNL-3358, reference4. An alternative method would be the use of the large boring machinesused in potash mining. This would avoid potential damage to the geologicstructure, that may be caused by blasting.
![Page 155: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/155.jpg)
H-4
decontaminate, handle residue from decontamination, stdre fuel (65
containers), and/or lower fuel to mine level. Sketches illustrating
these features are given in Figures 4, 5, 6, and 7.
Assuming the fuel is being moved to storage at mine level, it
is lowered 304.8 m with a hoist to a hot cell. This mine level hot cell
serves as a distribution centre for fuel containers and an isolation area
in the event of an accident in the waste handling shaft. Details of this
hot cell are shown in Figure 8.
Transportation of fuel to its storage location is done with a
specially designed transporter shown in Figure 9 (schematic view of trans-om
porter used in USAEC Project Salt Vaultv ' ) . It is backed under the front end
of the mine level cell, the transporter shield raised, the shielding plug in
the hot cell removed, and the transporter loaded from a travelling crane.
Once loaded, the transporter drives down an outer peripheral
tunnel (spent fuel handling tunnel) to a prepared storage hole (see
Figure 10). The prepared hole includes an asbestos cement liner which
protects the fuel bundle container from contact with the salt.* The
transporter discharges its fuel through the bottom of its shield, places
a shielding plug in the hole, and drives away. A more detailed description
of fuel handling operations is given in Figure 11.
In addition to the mining and waste handling facilities
mentioned above, some auxiliary surface facilities are required. They
are listed in Table 2 along with the main surface facilities.
2.4 PERSONNEL REQUIREMENTS
During the fuel insertion period (year 1982-2004), salt mining
and waste handling operations require varying numbers of people. Require-
It has been pointed out that asbestos - cement materials are hazardousto handle. This factor must be taken into consideration when materialsfor liners are being selected in any development work.
![Page 156: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/156.jpg)
H-5
ments grow from 87 people in the year 1982 to 120 in the year 2004. An
indication of the numbers and types of personnel required in the year
2004 is given in Table 3.
2.5 OVERALL SCHEDULE
To put the scheme into perspective, it is necessary to look
at the various phases involved and the time scale of each phase.
1. Fuel Arisings Phase (1978-2004)
Arisings for one-year-cooled fuel would normally begin in theyear 1978.
Our scheme requires five-year-cooled fuel (an additional fouryears cooling at the reactor site), so that the first fueldoes not reach the site until 1982.
2. Initial Construction Phase (1980-1981)
Hot cells, shafts, peripheral tunnels, and surface buildingsare constructed prior to first fuel insertion.
3. Fuel Insertion Phase (1982-2004)
During this phase, the mine is gradually being filled with fuel.
4. Mine Surveillance Phase (2004-2054)
The mine (filled with fuel) is left open as a final check onthe integrity of the salt containment. Surveillance of thefuel continues throughout this period.
5. Site Surveillance (2054-indefinlte future)
In the year 2054, the mine is backfilled with salt, shaftssealed, surface facilities dismantled, and the site cleaned.Surveillance continues indefinitely.
A chart showing the above phases is given in Figure 12.
3. COSTS
An economic study of the salt mine scheme is presented to
allow comparison with other schemes. Costs are grouped into four main
divisions :
1. initial investment coat,
![Page 157: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/157.jpg)
K-6
2. salt mining and disposal cost during fuel insertion period,3. spent fuel handling costs,4. perpetual care costs.
A breakdown of the major Items in each category is given
below.
3.1 INITIAL INVESTMENT
These costs are mainly due to site preparation, initial
construction, and machinery purchases in the first two years before fuel
insertion. Table 4 gives a cost breakdown of the items involved.
3.2 SALT MINING AND SALT DISPOSAL COSTS
Costs were divided into mining costs and disposal cost.
Neither one includes machinery which shows as a capital expenditure. A
breakdown is given In Table 5.
Yearly salt handling costs are calculated by multiplying the
total cost for salt handling ($2.955/Mg) by the amount of salt mined in
that year. Yearly and cumulative salt mining quantities are given in
Figure 13.
3.3 SPENT FUEL HANDLING COSTS
A major item in the spent fuel handling costs is that of spent
fuel containers. This cost includes:
1. two baskets,2. mild steel can,3. packaging,4. asbestos cement liner,5. base plug,6. shield plug.
The above costs are detailed in Table 6.
![Page 158: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/158.jpg)
H-7
3.4 PERPETUAL CARE COSTS
Beyond the last year of active mine life (year 2004), three
operations require funding:
1. fifty-year surveillance (year 2004-2054),2. backfilling, etc. of mine (year 2054),3. indefinite surveillance (year 2054 - ?).
To cover these costs, three funds were set up with the initial
investment made in the year 2004. The size of each fund is described
below.
1. 50-Year Surveillance Fund
Annual costs of operation during this phase were calculated(see Table 7).
The amount of money invested in the year 2004 to meet thesecosts over the period was calculated to be $9.1 x 106.
2. Backfilling and Dismantling Fund
After 50 years, extensive repairs might be required for themine and its equipment to permit backfilling. The costs forrepairs, backfilling and other items were assumed to be thesame as the costs for the entire mining operation ($40.0 x 106).To generate this amount, an investment of $9.7 x 106 in theyear 2004 is required.
3. Indefinite Surveillance Fund
An annual expense of $50 000 is assumed for the final phase,beginning in 2054. An investment of $0.4 x 106 in the year2004 will provide this amount in perpetuity.
4. Total Investment for Perpetual Care Required in Year 2004
50-year surveillance $9.1 x 106
Backfilling, etc. $9,7 x 106
Indefinite surveillance $0.4 x 10s
TOTAL $19.2 x 106
3.5 LEVELIZED COSTS, $/kg U FOR CAPITAL, OPERATING AND PERPETUAL CARE
Annual cash flows for capital, operating, and perpetual care
during the initial and fuel emplacement stages are shown in Table 8. An
explanation is given in the footnotes which follow.
![Page 159: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/159.jpg)
H-8
A levelized cost in $/kg U is given in Table 9. These values
were determined using present worth, techniques and 1972 dollars.
3.6 PENALTY FOR FOUR EXTRA YEARS OF STORAGE
As mentioned previously, this scheme requires five-year-cooled
fuel. The cost of storing fuel for an extra four years at a reactor site
has been calculated by Ontario Hydro. This cost amounts to $0.47/kg U.
3.7 SHIPPING
Cost for shipping fuel from the reactor site to a central storage
site has been calculated by WNRE in Appendix I. This cost amounts to $2.20/kg U.
3.8 DEVELOPMENT COSTS
A development program for storage in salt has been advance by
WNRE. The plan covers a 15-year period at a carefully chosen site prior
to the emplacement of fuel on a routine basis. It includes money for site
selection, public information, and capital expenditures. The program involves
general salt research as well as a 5-year program. The total cost is
^$25 x 106. Of this money, $13 x 106 is required for mine shafts, hot
cells, land, etc. These facilities can be used again during the routine
emplacement period so that net costs for development are reduced. If the '
development costs are charged off against the fuel arisings to the year
2004, the additional cost to the total scheme is $0.38/kg U.
3.9 TOTAL COST FOR MANAGEMENT OF SPENT FUEL IN SALT MINES
Total salt mine costs are summarized in Table 10. These values
were arrived at using present worth techniques and 1972 dollars, (see
Appendix B).
![Page 160: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/160.jpg)
H-9
4. GENERAL COMMENTS ON SALT STORAGE
One of our objectives in this series of studies was to examine
each scheme from engineering, safety, and cost points of view.
We were not in a position to assess fully the engineering
aspects of salt mining and relied extensively upon the work done by the
United States Atomic Energy Commission. It is evident from their work
that the concept of storing highly active wastes in bedded salt is
feasible. However, the use of this concept is strongly dependent upon
the geology, hydrology, etc., of the site. Therefore, we have been able
to look at the concept of storage only in broad generalities. A more
detailed examination cannot be carried on until one or more possible sites
have been selected.
From a safety point of view, there are a number of advantages
to this type of storage.
1. It appears that loss of cooling is highly improbable.
2. The spent fuel is shielded beneath 300 m of overburden andtherefore prospects for complete loss of shielding are veryremote. Thus this mode of storage appears to be much lessvulnerable to earthquakes, acts of war, or sabotage thansurface storage concepts.
3. We are not able to predict, at the present time, the lifetimeof the primary containment (fuel container and sleeve) in thesalt. However, in view of the plastic qualities of the saltand because of the thickness of the overlying strata, extremelygood secondary containment is provided. Since the age of thesalt bed could be of the order of hundreds of millions ofyears, the 250 000 years required for the decay of the spentfuel is only a small extension of the age of the bed.
A further containment advantage of salt storage lies in the
fact that planned retrievals of the fuel are not required every 50-100
years as in the case of man-made vaults on the surface. Thus, there is
less chance of activity being released to the environment.
![Page 161: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/161.jpg)
Although having advantages not present in surface storage,
this scheme puts new stresses on the geology of the area. These stresses
are due to mining operations, decay heat production, and radioactivity,
and may create some difficulties.
Mining involves penetrating (within mining shafts) the
protective layers of shale and overburden which isolate the salt from
water. Once the mine is filled with fuel, can these shafts be plugged
in such a way that the exclusion of water is guaranteed? Mining also
involves removing large volumes of salt. It is realized that even after
backfilling, the remaining salt will flow to fill the void, But what is the
effect of this flow? Could this flow cause a break of the overburden or
protective shales? If the mined salt is left on the surface over the
mined-out area, will this cause a stability problen?
The integrity of the containment may also be affected by old
drillings or boreholes in the storage area. Careful investigation of the
site is required to be sure that such holes do not exist, or if they do
exist, that they can be safely sealed.
Decay heat produced by the spent fuel will cause an increase
in the temperature of the salt and overburden resulting in some degree of
thermal expansion. Will the increase in temperature change the physical
properties of the salt to such an extent that mine stability is threatened?
Will the higher temperatures cause accelerated deterioration of the mild
steel can? Is it possible that the thermal expansion of the salt could
cause a breach in the protective shales and overburden? Will thermal
expansion cause mine stability problems? How will the heat affect the
small amount of water trapped in the salt?
The rock salt and any water present may undergo some radiolytic
degradation in the vicinity of the stored fuel. Products formed may lead
to increased corrosion of the fuel containers; hydrogen produced from
radiolysis of the water could, during the mining process, create a minor
explosion hazard. The question of stored radiation energy in the salt
![Page 162: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/162.jpg)
H-ll
crystals has been raised, with some concern about the effects caused by-
sudden release of the energy.
From a general point of view of environmental impact, it
would appear that one of the important concerns is the disposal of the
mined salt. A technique illustrating what might be done is given in
this report, primarily as a means of estimating the cost of salt disposal.
Depending on the quality of the salt, it may be possible to sell it,
dispose of it in the ocean, inject it as a brine into deep strata, or
store it in other abandoned mines.
These and other difficulties were examined by the United
States Atomic Energy Commission in Project Salt Vault. Although some
difficulties at the Kansas site arose, it was concluded that the use of
salt mines per se was a safe method of storage.
From an economic point of view, the cost of storing fuel in
salt is of the same order of magnitude as surface storage.
![Page 163: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/163.jpg)
H-12
5. REFERENCES
(1) "Disposal of Solid Radioactive Wastes in Bedded Salt Deposits",Report by the Committee on Radioactive Waste Management,National Academy of Sciences - National Research Council,November, 1970.
(2) R.L. Bradshaw et al, "Results of a Demonstration and ccherStudies of the Disposal of High Level Solidified, RadioactiveWastes in a Salt Mine", Health Physics, Volume 18, pp 63-67, 1970.
(3) R.L. Bradshaw, W.C. McLean (editors), "Project Salt Vault: ADemonstration of the Disposal of High-Activity SolidifiedWastes in Underground Salt Mines", Oak Ridge National Laboratory,OFNL - 4555, April, 1971.
(4) R.L. Bradshaw et al, "Evaluation of Ultimate Disposal Methodsfor Liquid and Solid Radioactive Wastes: VI Disposal of SolidWastes in Salt Formations", Oak Ridge National Laboratory,ORNL - 3358, March, 1969.
![Page 164: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/164.jpg)
H-13
TABLE 1
SALT MINE SPECIFICATIONS
Depth
Overall area underground
Overall area on the surface
storage room width
305 m (1000 ft.)
2.6 km2 (1 mi2) (divided into0.65 km2 (1/4 mi2)quadrants)
4.9 km2 (1.9 mi2)(includes 305 m(1000 ft.)buffer zone)
31% (ORNL = 50%)Mining ratio = . , , ,,storage room width + pillar
Pillar width to height ratio 16.9 m/4.6 m (55ft/15ft) 3.7
Storage rooms/quadrant
Buried fuel bundle containers/room
Bundles/container
(ORNL
32
3.3)
671 (5 year cooled)arranged on a triangularpitch, 3.1 m (10 ft.)center to center spacing)
42(0.84 Mg U)
![Page 165: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/165.jpg)
H-14
TABLE 2
SURFACE FACILITIES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Main hot cell
Mining head frame
Electrical substation
Gate house
1.2 km road
1.2 km railroad spur
Garage
Maintenance shop
0.64 km2 salt disposal area
Parking lot
TABLE 3
PERSONNEL REQUIRED IN YEAR 2004
Mining
Surface salt handling
Waste handling
Maintenance
Miscellaneous
Administration
TOTAL
28
12
35
25
7
13
120
![Page 166: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/166.jpg)
H-15
TABLE 4
INITIAL INVESTMENT COSTS(1972 Dollars)
YEAR Z98O
Land (1>
Site DevelopmentSite clearingWater systemSewer systemElectricalParking lotFenceLightingRailroadRoadHeating plantGate house
TOTAL
Mining shafts and equipment16 ft. shaft8 ft. shaft2.5 ft. shaftShaft equipmentMiscellaneous
TOTAL
Ventilation
Surface hot cellHot cell properS tack (*•)
Office areaEquipment and instrumentation
.TOTAL
Taxes and Insurance
TOTAL
YEAR 1981
Mine level hot cell
1
1
3
1
3
Miscellaneous mine level equipmentMining Machinery*1)Initial mining <*)Surface salt handling machinery
TaxesInsuranceMine heat
TOTAL
2569765260581802626339013025
750
62597925641594
369
73293633643
101
(i)
DOLLARS
000000000000000000000000000000000
000
000000000000000
000
000000000000
000
1
3
3
9
DOLLAR!
1
3
710
750
369
41
101
180
151
i
41024399556242513013044
939
000
000
000
000
000
000000(ii)(iii)
000000000000000000000000
ooo(ii>
(1) Cost extracted from reference 4.
(ii) The costs shown above for constructed facilities include costsfor overhead, engineering, and contingencies.
(ill) The cost of some of the above items is shown to occur in asingle year, whereas the costs may actually be distributed overmore than one year. This approach was taken to simplify thepreparation of the cash flow chart in Table 7. The resultanteffect on interest and/or escalation charges for the constructionperiod is negligible compared with total expenditures involvedfor the entire construction and mine filling period.
![Page 167: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/167.jpg)
H-16
TABLE 5
SALT MINING AND SALT DISPOSAL C O S T S ^
SALT DISPOSAL (SURFACE HANDLING) COSTS
Fuel
Wages
Maintenance
Liner
Oil (waterproofing)
Overheads and contingencies
TOTAL
SALT MINING COSTS (1972 Dollars)
Fuel
Wages
Power
Explosives
Maintenance
Overheads and contingencies
TOTAL
Total Salt Handling Cost
C1972 Dollars)/Mg
0.048
0.196
0.114
0.425
0.245
0.196
1.225
0.048
0.604
0.082
0.114
0.278
0.604
1.731
2.956
Ci) Extracted from reference 4 with the exception of linerand waterproofing costs.
![Page 168: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/168.jpg)
K-17
TABLE 6
SPENT FUEL BASKET AND CONTAINER COSTS
2 Stainless steel baskets
Carbon steel container3 m of 0.3 m (12") Schedule 40 pipe2 end platesWelding and testing, plus allowance forremote welding and testing of the topend plate
Hot cell operation at reactor siteCapital charges and operating costsfor hot cell
Asbestos cement liner, shielding plug and baseLiner - material
installationoverheads and contingencies
Shield plug and base- installed costs0.37 m3 @ $l96/m3
TOTAL
Cost per Container
(Dollars)
336
7836
370
484
436
1123232
176
72
1504
$/kg u
0.40
0.58
0.51
1.09
0.21
0.09
1.79
TABLE 7
ANNUAL COST FOR 50-YEAR SURVEILLANCE PERIOD
Labour
Utilities and supplies
Taxes
Insurance
Maintenance
15% Contingency
TOTAL
Dollars
100 000
20 000
65 000
65 000
50 000
300 000
50 000
350 000
![Page 169: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/169.jpg)
H-18
TABLE 8
SALT MINE CASH FLOWS (1972 DOLLARS)
YEAR
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
TOTALS
Mining CostsCapital (i)Expenditures
5870
1663
308
584
158
425
836
584
885
11313
- 103 Dollars jOperating (ii)Expenditures
90
1736
382
405
433
459
502
473
525
593
659
739
821
2128
1006
1098
1209
2535
1339
1514
1605
2729
1779
1868
1979
28606
Waste Disposal Costs: 103
Capital(iii)Expenditures
3101
410
375
63
375
375
375
63
375
375
375
375
375
375
375
375
8137
Spent Fuel(iv)Baskets andContainers
1307
1449
1628
1789
2058
1880
2201
2631
3043
3544
4063
4618
5227
5799
6497
7178
7733
8413
8986
9522
10077
10632
11331
121606
DollarsOperating(v)Expenditures
90
Perpetual(vi)Care Costs:103 Dollars
130
562
562
572
572
572
572
572
572
809
810
810
819
820
820
878
978
1035
1035
1036
1207
1208
1208
1208
19457
19200
19200
![Page 170: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/170.jpg)
H-19
CASH FLOW FOOTNOTESMINING
Ci) Capital Expenditures
In the first two years O980-1981), expenses are due to miningmachinery, shafts, hoists, salt handling equipment, etc. Lateron, these costs indicate money spent in replacing existingequipment.
(ii) Operating Expenditures
These costs include all salt mining and handling costsexclusive of machinery, which is a capital expenditure.Mining Costs $1.731/Mg of saltSurface Handling $1.225/Mg of salt
TOTAL $2.956/Mg of salt
Other costs included are heating, insurance, and taxes.
WASTE DISPOSAL
(iii) Capital Expenditures
Capital expenditures in the first two years (1980-1981) are dueto construction of two hot cells.
1980 - Surface Hot Cell1981 - Nine Level Hot Cell
All other expenditures are due to purchases of transportersand hole drillers.
(iv) Spent Fuel Baskets and Containers (Figure 10)
The cost per container is $1504. A breakdown of this cost isgiven in Table 6.
Annual costs are arrived at by multiplying the number ofcontainers required per year by the individual container costs.
(v) Operating Expenditures
Wages, salaries, overhead, and contingencies were taken fromreference 4 and were adjusted to suit our requirements. Checkswere made in which the people required for all jobs were listedand a 15% contingency added. Agreement with the adjusted 0KNLvalues for the years 1982 and 2004 was good. On this basis,the adjusted ORNL values were accepted. Other items includedin these costs are:a) transporter maintenanceb) transporter fuelc) taxesd) insurance
(vi) Perpetual Care Costs
These costs are described in section 3.4.
![Page 171: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/171.jpg)
H-20
TABLE 9
LEVELIZED COST FOR MINING, FUEL HANDLING, AND PERPETUAL CARE
Mining
Capital per cash flow chartInterest charges on borrowed moneyTotal
Cost: 106 Dollars
11.34.8
Total
Perpetual Care
Total value of funds in year 2000Interest earnings to year 2000Deposits to sinking funds during
filling
Total Cost for Mining, Fuel Handlingand Perpetual Care
152.6
19.2- 3.6
15.6
212.9
Levelized Cost$/kg U
0.170.07
Operating
Total
Waste Handling
Capital
General facilities as per cashflow chart
Interest chargesTotal
Baskets and spent fuel containers
Operating
28.6
8.13.4
121.6
19.5
44.7
0.42
0.120.05
1.79
0.29
0.66
2.25
0.23
3.14
![Page 172: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/172.jpg)
H-21
TABLE 10
SUMMARY OF COSTS FOR MANAGEMENT OF SPENT FUEL IN SALT MINES
Development, site selection and public
Penalty for four extra years of storage
Shipping
Capital and operating costs during site
Mining costsWaste handling and emplacement
Total
Perpetual care
Total
relations
at reactor site
filling period
0.662.25
$/kg U
0.38
0.47
2.20
2.91
0.23
6.19
![Page 173: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/173.jpg)
H-22
CENTRAL AREA(HOT CELL)(76 cm dia. FUEL HANDLING SHAFT)(2.4 m dia. FUEL HANDLING VENTILATION SHAFT)(4.9 m dia. MINING & MINE VENTILATION SHAFT) .-.-
'•'/ •••
CROSS-OVER TUNNELFUEL HANDLING TUNNEL (OUTER)SALT MINING TUNNEL (INNER)STORAGE ROOMPILLAR, 16.7 m
HEIGHT 4.6 mWIDTH 7.6m
-807.7 nv
PLAN VIEWAT
MINE LEVEL FIGURE 1
SALT MINE QUADRANT
809.2 m
![Page 174: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/174.jpg)
DRILL WITHJUMBO RIGS
UNDERCUT WITHGOODMAN SHORT WALLUNDERCUTTER
LOAD POWDER USINGWAGNER MOBILEWITH CHERRYPICKERATTACHED
*HAUL TO GRIZZLEYAND CRUSHER WITHDIESEL SHUTTLE
CARS
HAUL SALT FROMCRUSHER TOSHAFT BOTTOM
HAUL TOSURFACE ANDLOAD ON TRUCK
BLAST(3m /BLAST)*
HAUL SALT TOBURIAL SITE
LOAD SALT INTOVEHICLE WITHJOY LOADERS
EXCAVATE BURIALSITE
COVER BURIALSITE BOTTOMWITH PLASTIC
LINER
SPREAD ATHIN LAYER OFSALT ON THELINER AND SPRAYSALT WITH OIL
BUILD PILE TODESIRED SHAPEWITH MORE SALT,PACKING WITHPACKER AS REQUIRED
!J
SPRAY SURFACEWITH ASPHALTAND COVERWITH PLASTIC
COVER PILEWITH THREEFEET OFEARTH FILL
COVER FILLWITH SOD
**
NOTES: *MINING RATE 3m /SHIFT
** SALT WOULD BE REPLACED IN THE MINE BY REVERSING THE PROCESS.
FIGURE 2SALT HANDLING OPERATIONS
![Page 175: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/175.jpg)
GRASS
ceho
FIGURE 3 SALT DISPOSAL SCHEME
![Page 176: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/176.jpg)
34.7 m
RAILWAY TRACK B ff^
\_^DOOR^.
SERVICES
91 \
t_'••:i*#
OPERATING!AREA
30.5 m
REPAIRHOT CELL
DOOR(!^ri-ISOLATION
CELL
CHANGE | HOT-CELLROOM v SERVICE
L AREA
.SHIELDDOOR
! I
HATCH
RECEPTION AREA
31IM
35.6 cm SCH.10 S PIPE
MAIN ENTRANCE
-FLOOR PLAN- ELEV 30.5 m
FIGURE 4 SALT MINE STORAGE- GROUND LEVEL HOT-CELL
![Page 177: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/177.jpg)
Y+- 36.6 m-
VENTILATIONAND OTHERSERVICES
25.9 m
STAIRS OFF.
ooL.WR.
IM.WR.
OFF. OFF.
HOT CELLSERVICEAREA
TRANSFER HOT CELLFER HOT CE
OPERATING AREA
OFF. CHANGEROOM
HALLWAY
OFF. OFF. I OFF.I
OFF.
RECEPTIONAREA
FIGURE 5FLOOR PLAN OF HOT CELLS
ELEV. 37.2 m
•••*•*
OOOO8888OOOO
_ I
7.9 mto
![Page 178: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/178.jpg)
(4.5 m *
15.85 m
VENTILATIONAND
OTHERSERVICES
'S/////////,
7.92 m
WASTEOPERATING
AREA
//////////,
32.0 m
»•••: .->«V-. ~
-T-P'-—1>»
-•
. TRAVELLING.CRANE
WASTEMANAGEMENTAREA
Ï-JT
J^^TrTi?
ELEV. 46.33 m
ELEV. 37.9 m
GROUND LEVEL
RAIL CARS
ELEV. 22.55 m
.48CANISTERTRAILER
\ ///////y£i;,y-,"FUEL-CAN STORAGE CELL
FIGURE 6
CROSS SECTIONAL ELEVATION A-AOF HOT CELLS
xi
![Page 179: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/179.jpg)
OPERATINGAREA
-*,ACTIVE HOLD-UPTANKS & PUMPS
POT. r-i
MED. ACTIVEHOLD-UP TANKS& PUMPS I,'
EVAPORATORROOM
-FLOOR PLAN-ELEV. 22.55 m
VENTILATIONAND OTHERSERVICES
SERVICES
s//// //y/s// /s/7.
61
FUELTRANSFERHOT CELL
ELEV. 46.33 m
OPERATINGAREA
OFF,
REPAIRHOT CELL
ISOLATIONCELL
LSI \WASTE MANAGEMENT v
U AREA
OFF.
HOT-CELL SERVICEAREA
S/ST. COVERS/ST. LINER
ELEV. 30.48 m91 m dia. HATCH2.44 m2 HATCHS/ST. LINER
ELEV. 22.55 m
is
00
-CROSS SECTIONAL ELEVATION B-BOF HOT CELL
FIGURE 7
![Page 180: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/180.jpg)
H-29
91 cm
RAMP
ir 18.3 m
///.
i
i>li
— -0- 0 0 ©
© 0 © 0
0 0 0 0
i i iU PLUG e£t
OPERATINGAREA
-FLOOR PLAN-
9.1 m
6.1 m
FUEL HANDLING SHAFT
UNDERGROUNDTRANSPORTER 11.0 m
TEMPORARY STORAGE
CROSS SECTIONAL ELEV. A-A
FIGURE 8 SALT MINE STORAGE- MINE LEVEL HOT CELL
![Page 181: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/181.jpg)
H-30
CENTERING GUIDE
^ SHIELD
FIGURE 9 -MINE LEVEL TRANSPORTER-
15 cm "CONCRETEPLUG
4.75 m
15 cm ; •
TRANSIENT PIPE, CLASS 200(42.1 cm o/dia. x 34.5 cm i/dia.)
0.44" air gap
MILD STEEL CAN SCH. 40 PIPE(SPENT FUEL CONTAINER)
FIGURE 10 SPENT FUEL CONTAINER
![Page 182: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/182.jpg)
FLASKSSTART
FLASKS ARRIVEON RAILWAY CARFROM REACTOR
CARS AND FLASKSARE CHECKED FORCONTAMINATION
CARS ARE PUSHEDINTO POSITIONUNDER SHIELD COLLAF
FLASKS AREOPENED, CANS LIFTEDINTO HOT CELL ANDINSPECTED FOR LEAKSETC.
FUEL
NORMAL
SHIELD PLUGINSTALLEDANDCONTAMINATIONCHECK MADE
TRANSPORTERPOSITIONED OVERHOLE AND OPENED,CAN INSERTED INSLEEVE
TRANSPORTERDRIVEN TOSTORAGE HOLE
CANS ARE PLACED INTRANSPORTER WITHTRAVELLING CRANE
PERIODICLEAK CHECKSMADE
END
SALT HOLE DRILLED,SLEEVE INSERTED,BOTTOM PLUGPORED
ANNULUS AROUNDHOLE FILLED WITHFINE CRUSHED SALT
J
CANS*ARE LOWEREDDOWN MINE SHAFTINTO MINE LEVELHOT CELL
CONTAMINATED
CONTAMINATED AND/ORDEFECTIVE CANS AREREPAIRED AND/ORCLEANED .
U
TRANSPORTER TRANSPORTER
TRANSPORTERCHECKED FORCONTAMINATION
NORMAL>•—
CONTAMINATED
IF CONTAMINATEDTRANSPORTER IS CLEANED
TRANSPORTER ISDRIVEN UNDERHOT CELL
* CAN = FUEL CONTAINER
CARS ARE RETURNEDTO REACTOR FOR ANOTHERLOAD
FLASKSARE CHECKEDAND COVERS REPLACED
FIGURE 11FUEL HANDLING OPERATIONS
![Page 183: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/183.jpg)
PHASES
SiteSurvei1 lance
H-32
YEAR
©O
OPERATIONS
J2054
MineSurvei1 lance
2004
Fuel loaded into mine.Mining done as required.
Mine backfilled withsalt, shafts sealed,surface facilitiesdismantled.
Mine filled with spiritfuel
1
Fuel Five yearcooled atreactor site.
1982
1981
1980
1979
1978
Insertion of firstfuel
Construction of minelevel cell, mineperiferal tunnels;and initial storagerooms.
Construction of shafts,surface hot cells etc.
-1— First fuel arisings.
FIGURE 12
GEOLOGIC STORAGE SCHEDULE
![Page 184: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/184.jpg)
H-33
1.0
0.9
08
0.7
0 6
0.5
0.4
0.3
0.2
0.1
8 0
70
6 0
5 0
40
30
2 0
10
I 1 1 1
SALT MINED -YEARLY AMOUNTS
-
-
- i
-
SALT MINED -CUMULATIVE AMOUNT
—
—
—
— — ——^""^
1 I
A A» A A\J* ^ PEAKS ARE DUE
TO EXCAVATIONOF PERIPHERALTUNNELS AROUNDQUADRANTS
/
i i
1984 1988 1992
YEAR
FIGURE 13SALT MINING SCHEDULE
1996 2000
![Page 185: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/185.jpg)
APPENDIX I
TRANSPORTATION
1. INTRODUCTION
Transportation is a vital aspect of any fuel storage scheme.
The committee has not examined transportation in detail but has discussed
the logistics problem and aspects related to siting. In the following
sections, estimates have been made based on what appear to be reasonable
.-sumptions at the present time.
DISTRIBUTION OF CANADIAN SPENT FUEL ARISINGS IN THE YEAR 2000
It is necessary to examine the transportation requirements in
the year 2000 in order to determine mature costs and practices. The
distribution of arisings was obtained from Foster's data on installed
capacity . This was fitted to the CAFS arisings, as shown in Appendix B.
The results are shown in Table 1.
3. SHIPPING SYSTEM
Fuel can be shipped by road, rail, barge, or possibly air.
CAFS did not examine all shipping modes, but instead assumed that rail
![Page 186: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/186.jpg)
1-2
transport was the most likely. In addition, it was assumed that only
unit trains would be used. It was felt that shipping by standard freight
would unnecessarily increase shipping time.
3.1 GENERAL ASSUMPTIONS
Various assumptions were made regarding flask weight, number
of cars per unit train, number of flasks per car, average travel distance,
and so on. These are summarized in Table 2.
3.2 FLASK AND UNIT TRAIN REQUIREMENTS
From the preceding data, flask requirements and numbers of
unit train trips can be calculated. These data are shown in Tables 3 and
4. For the weighted average shipping distance of 1358 km (one way), 48
flasks and 6 unit train systems are required in the year 2000.
4. COSTS
4.1 CAPITAL COSTS
The major nuclear industry capital requirement for shipping
will be for flasks. Capital is also required for unit trains and although
the railway will probably provide this investment, the sums are of interest.
These costs were calculated from the data in Table 4. It was assumed that
an 8-car unit train would cost $1.5 million and the flask cost is $4.40/kg .
The results are shown in Table 5. These data apply to a single site in
Canada located north of Lake Huron.
4.2 UNIT SHIPPING COSTS
Unit freight costs, (see Figure 1) were derived from freight rates
for radioactive shipments obtained from a Canadian railway company. These data
![Page 187: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/187.jpg)
1-3
applied to the use of regular trains. However, comparison with limited
data for unit trains indicated that rates would not be significantly
different. The best line was drawn through the data ignoring the two
points which appear to be anomalous.
To obtain total costs, flask capitalization and insurance
must be added to the freight costs, and these in turn will both depend
upon the shipping distance. These data have been calculated as a function
of distance and are shown in Table 6. The assumptions used are as follows:
1. flask cost = $0,203 x 106 ($4.40/kg weight),
2. insurance cost = 1/2 capitalization cost,
3. flask write-off is at 8% over 10 years.
The total shipping cost is also shown and is plotted in Figure 1.
Based on the distances and fractional arisings quoted in Table
1, the weighted average shipping cost to a single storage site located
north of Lake Huron, is $2.20/kg U. This value was taken as the shipping
cost in all other sections of this report.
4.3 WEIGHTED AVERAGE SHIPPING COSTS FOR MORE THAN ONE SITE
It is obvious that if more than one storage site is established,
the weighted average shipping cost will be reduced. Assuming sites are
chosen in lower mainland B.C., Ontario north of Lake Huron, and central
New Brunswick, the weighted average shipping cost will reduce to $1.40/kg U.
Obviously, however, the cost of establishing and maintaining three sites
will be greater than the cost of one. On the other hand, shipping safety
will be improved, and fuel will spend less time on the road. These items
must all be considered in a study to optimize freight costs and safety.
However, they were beyond the scope of this work.
![Page 188: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/188.jpg)
1-4
5. SUMMARY
A power and spent fuel distribution has been calculated by-
applying Foster's power distribution to CAFS fuel arisings. The distance
and turnaround tiires indicate 6 unit trains carrying eight 192-bundle
flasks per train would be adequate to handle spent fuel in the year 2000.
The cost of transporting fuel to a single central site is $2.20/kg U.
The cost using three specific sites is $1.40/kg U.
6. RECOMMENDATIONS
A study of the shipping problems should be undertaken in all
future studies of waste storage methods. This study should include the
following:
1. Methods for integration of all spent fuel handling operationsfrom the reactor site to the storage site should be investigated.
2. Alternatives to conventional flasks lor moving spent fuelshould be considered.
3. Flask design criteria should be reviewed. For example, presentregulations set the radiation field at a maximum of 10 mR/hat 2 metres from the edge of the transport vehicle. This mayresult in unacceptably high doses to flask handlers at acentral site, whops sole job is flask unloading.
4. Some nethod of rating the risk of shipping as a function ofdistance and as a function of the age of fuel for comparisonwith risks at the reactor and storage site is desirable.
5. The logistics of shipping the fuel across the country by road,rail, unit trains, etc., from the potential reactor sitesshould be examined.
6. The advantages of storing spent fuel at the reactor site toavoid shipping should be considered. The advantages thatmay arise if fuel shipment is postponed until after the reactorhas been shut down and the fuel has undergone 25' to 30 yearsof decay should also be assessed.
7. The cost of shipping should be estimated as accurately aspossible. This will require collaboration with the shippingindustry.
![Page 189: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/189.jpg)
1-5
REFERENCES
Cl) J.S. Foster, "Financial Resources Required for Future NuclearPower Program", Canadian Nuclear Association, CNA 73-502, June 1973.
(2) A.G. Trudeau, D.E. lïaagensen, "An economic and engineeringanalysis of a unit train concept for the transportation ofspent fuel assemblies from commercial Nuclear Power Plants",Bartelle-Northwest, Pacific Northwest Laboratory Report,BNWL-SA-3906, August 1971.
![Page 190: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/190.jpg)
1-6
TABLE 1
ANNUAL SPENT FUEL ARISINGS IN THE YEAR 2 0 0 0 ^
Area
Atlantic ProvincesNew BrunswickNova Scotia
QuebecSt. Lawrence Area 1St. Lawrence Area 2St. Lawrence Area 3
OntarioSudbury DistrictNiagara PeninsulaBruce PeninsulaLake. Ontario Region
Prairie ProvincesSaskatchewanManitoba
British ColumbiaLower MainlandVancouver Island
TOTAL
Distance FromCentral Site,
(km)
1 6832 118
6531 030869
225869740451
2 7041 979
5 1825 375
MW(e)Installed
21
926
4589
11
42
58
400200
400400200
600600000600
000000
800400
600
Mg SpentFuel per Year
266133
1 017260671
492600856
1 027
114114
525263
6 338
% of TotalSpent Fuel
4.22.1
16.14.110.6
7.89.513.516.2
1.81.8
8.34.2
100.
(i) Foster's data indicate about twice this quantity of power and fuelarisings.
The data used to derive these values were:
1. Burnup = 9000 MWd/Mg U2. Availability = 80%3. Conversion, thermal to electric « 30%4. Fuel arisings in the year 2000 = 6330 Mg
![Page 191: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/191.jpg)
1-7
TABLE 2
ASSUMPTIONS USED IN SHIPPING CALCULATIONS
(i)
(iii)
Fuel shipment size
Flask weight
Flasks per flat car
Cars per unit train
Flask shipments in year 2000(iv)
,(iv)Unit train shipments in 2000
Weighted average shipping distance
Flask loading time
Flask unloading time
(v)
3
46
1
8
1648
206
1358
5
5
.84 Mg U
Mg
km
hours
hours
(i) A 192-bundle package was chosen. For higher loadings, the fueltemperature may be too high. This point should be checked insubsequent studies.
(ii) Assumes a flask/fuel ratio of 12. This may be slightly conservative.
(iii) Ontario Hydro information suggests road bed loads as low as 73 Mg.Thus, only one flask per car is possible.
(iv) Calculated from Table 1 and note (iii) above.
(v) Calculated from Table 1; assumes only one site in Canada locatednorth of Lake Huron.
(vi) Estimated time, also checked with some experience and consideredto be reasonable.
TABLE 3
FLASK TURNAROUND TIME IN 2000 VERSUS SHIPPING DISTANCE
Distance(km)
402
804
1287
1609
3219
4828
Travel toReactor(days)
0.95
1.90
3.00
3.75
7.50
11.30
Loading
(days)
1.75
1.75
1.75
1.75
1.75
1.75
Travel toStorage Site
(days)
0.95
1.90
3.00
3.75
7.50
11.30
Unloading
(days)
1.75
1.75
1.75
1.75
1.75
1.75
TotalTurnaround Time
(days)
5.30
7.30
9.50
11.00
18.50
26.00
![Page 192: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/192.jpg)
1-8
TABLE 4
FLASK AND UNIT TRAIN REQUIREMENTS IN 2000 VERSUS SHIPPING DISTANCE
One WayDistance
(km)
402
804
1287
1609
3219
4828
Train TripsRequired Per Year
61
46
35
30
18
13
TrainsRequired
3.37
4.47
5.89
6.£7
11.44
15.84
Total Fl,Requir
27
36
47
55
92
127
TABLE 5
CAPITAL REQUIREMENTS FOR SHIPPING IN THE YEAR 2000
One Way Distance(km)
402
804
Ï287
1609
3219
4828
Unit(1972
Train Cost$, Millions)
5.0
6.7
8.S
10.3
17.2
23.8
Flask Cost(1972 $, millions)
5.5
7.3
9.5
11.2
18.6
25.7
Total(1972 $, will
10.5
14.0
18.3
21.5
35.8
49.5
TABLE 6
TOTAL SHIPPING COST AS A FUNCTION OF ONE WAY SHIPPING DISTANCE
One WayDistance
(km)
402
804
1287
1609
3219
4828
FlasksRequired
27
36
47
55
92
127
CapitalizationCharges($/kg U)
0.13
0.17
0.23
0.26
0.44
0.61
InsuranceCost
($/kg U)
0.07
0.09
0.12
0.13
0.22
0.32
Freight
($/kg U)
1.35
1.95
2.70
3.20
5.60
8.05
Total
($/kg U)
1.55
2.21
2.95
3.59
6.26
8.98
![Page 193: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/193.jpg)
5.0 -
i i rA SHIPPING BY RAIL (Jan. 16. 1974)
B SHIPPING & FLASK AMORTIZATION
1 1 11000 2000 3000
ONE WAY DISTANCE (km)
SHIPPING COSTSFIGURE I
4000 5000
![Page 194: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/194.jpg)
J-l
APPENDIX J
RETRIEVABILITY
by
John Coady
1. INTRODUCTION
The potential toxicity of spent CANDU fuel requires that it
be contained for hundreds of thousands of years. It is unlikely that
current generations will be prepared to leave to future generations a
legacy of continual rebuilding of surface storage facilities and rehandling
of spent fuel wastes. However, until methods suitable for the long term
have been selected and evaluated, there will be a need for interim retrie-
vable storage facilities on the surface; retrievability being defined as
the ability to recover fuel from storage using substantially no more energy
than was required to place it in storage.
The length of time for which spent fuel could continue to be
stored in this manner is difficult to define. The question is often raised,
however, and although it has been the subject of much debate, opinions
differ widely on just when it might become a problem to maintain an ongoing
system of rebuilding, rehandling, and supervision. One of the reasons for
the lack, of agreement is that there has also been a lack of useful data
from which to draw conclusions.
![Page 195: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/195.jpg)
J-2
The aim of this appendix is to outline, in terms of projected
arisings for the CANDU fuel cycle, what the probable dimensions of such
a system would he, and in so doing provide a quantitative basis for further
discussion. It must Be emphasized that this is not meant to be an exhaus-
tive examination of retrievability since this would require, among other
things, a detailed safety analysis of each scheme.
In going through the calculations, using both pools and
canisters as examples, the costing ground rule of 50 years was used as
the lifetime of each facility. This somewhat conservative assumption is
offset, however, by the choice of the lower set of values for projected
CANDU arisings. It should be noted that the assumption of a short life-
time really only influences the rate at which fuel must be rehandled and
therefore has no effect on other observations drawn from the results of
the calculations.
No attempt has been made to draw hard and fast conclusions
from this exercise and it is probable that more questions have been raised
than can be answered at this time. However, it was possible to identify
certain problem areas, mainly logistical in nature, that might arise if
surface storage facilities were to be in use for a prolonged period of time.
2. PROJECTED ARISINGS OF SPENT CANDU FUEL
Two sets of calculations were carried out. Both provide
predictions of arisings to the year 2120, assuming the continuous use of
natural uranium reactors over this period (approximately 150 years of
nuclear energy). The values and the assumptions on which they are based
are given in Table 1.
Figure 1 shows the cumulative production for each prediction
and includes for comparison the values derived from the estimates of
energy consumption to the year 2050, given in "An Energy Policy for Canada".
![Page 196: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/196.jpg)
J-3
It can be seen that the latter values coincide with the higher of the two
CAFS predictions.
According to the "high" estimate, the uranium needs of a
"throwaway" fuel cycle would be about 30 million tonnes over the next 150
years. This is about 1% of the uranium probably contained in the sea.
All calculations in the remainder of the appendix are based
only on the "low" prediction. It should be noted that although the values
up to the year 2000 are very close to those used in the rest of this report,
they were derived in a different way than, and are not intended to be the
same as, the standard CAFS projection.
3. STORAGE REQUIREMENTS
Tables 2 and 3 show what the predictions mean in terms of the
number of pools and canisters required to store the fuel. Pools increase
from one per year in 2000 to an equilibrium requirement of four per year
after 2035. In the same period, the number of canisters for storing five-
year-cooled fuel increases from about 1100 per year to just over 6000 per
year. In the 150 years covered by the predictions, the total number of
facilities increases from 8 to 366 in the case of pools and from 9 000 to
680 000 for canisters.
These values represent minimum requirements for the set of
predictions used. Ideally, in a mature fuel handling economy there will
always be standby capacity. In addition, as time passes, there will be
an increasingly significant group of vaults or pools in process of being
decommissioned, and sites being reclaimed.
![Page 197: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/197.jpg)
J-4
4. CONSEQUENCES OF REHANDLING
One of the consequences of adopting a policy of retrievable
storage is that as each building reaches the end of its useful life its
contents must be removed and placed in a new building. Presumably, old
facilities will be demolished and their sites reclaimed for further building.
In addition to cost and logistical burdens, this technique
could impose an undesirable radiation burden on future generations. Under
normal conditions, the maintenance of handling facilities, the loading and
unloading of flasks, and the trasport of active material all give rise to
the accumulation of man-rem. Being forced to retrieve the fuel, in itself,
increases the amount of handling and will, therefore, lead to increases
in dose. In addition to this, the damage incurred by the fuel during each
movement will increase the possibility of the spread of contamination.
Table 4 and Figures 2 and 3 illustrate the extent of the
rehandling requirements. In 2035, the first year in vxhich rehandling takes
place, the total handling rate is 5% higher than the rate at which fuel is
committed to storage in that year. By 2060, the rate at which fuel is being
rehandled reaches 50% of the rate at which new fuel is being put into
permanent storage. The two rates become equal in about 2085. From that
time on, the amount of fuel in process of relocation in any one year will
be greater than the fuel production in that year. This is based on a 50
year lifetime for each facility and would be different if another value
were used.
5. EMERGENCY RETRIEVAL
One of the arguments made in favour of retrievable storage is
that in an emergency there would be ready access to the fuel so that it
![Page 198: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/198.jpg)
3-5
could be moved to a new location. Apart irom the possibility that any
eventuality requiring the evacuation of a fuel storage site might also
affect the mechanism for retrieval, this gives rise to two important
considerations. If it p.ver becomes necessary to move all or part of the
fuel at a particular site, where would it go and how lor.? would this take?
5.1 STANDBY STORAGE
True retrievability can only be said to exist if there also
exists sufficient standby storage capacity to absorb the fuel which must
be relocated. Little consideration has been given to the question of
whether such standby facilities should be available at all times or
whether in a properly managed system there would be sufficient time in
which to build new facilities.
5.2 RELOCATION TIME
At some time in the future, it may become necessary to move all
or part of the fuel in storage. For instance, the whole inventory may have
to be shifted if a more suitable form of management is adopted or if a
decision is made that the fuel should be reprocessed. The need to move a
part of the fuel could result from an accident or from the deterioration
of some of the facilities. In the case of an emergency relocation,
presumably it would be desirable to move the fuel out of the impaired
repository as quickly as possible. It is therefore worthwhile examining
the time required to completely relocate the existing inventory. These
times are shown in Table 6.
The assumption here is that the equipment available to move
the fuel is equal in capacity to the equipment in existence for handling
the arisings of the current year Csee Appendix I). This could be available
in two ways. Either all existing equipment could be directed completely
to the relocation operation or there could be a backup of 100% of existing
equipment. The first of these is probably impossible to do and it is
extremely unlikely that the second procedure would ever be adopted. Yet
any smaller availability of equipment will increase the moving time.
![Page 199: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/199.jpg)
J-6
6. OBSERVATIONS
1. There is no doubt that a continuing system of retrievablestorage will be viable for many decades. It is also evidentthat such a system will eventually assume massive proportionsdue mainly to inherent rehandling requirements.
2. If it is assumed that each facility has a lifetime of 50 yearsthen, around 2060, the rate at which fuel is being rehandledreaches 50% of the rate at which new fuel is being put intopermanent storage. The two rates become equal in about 2085,just over 100 years from now. From that time on the amountof fuel in the process of relocation in any one year will begreater than the fuel production in that year. For facilitieswith longer lifetimes the crossover point will occur at a laterdate.
3. A consequence of the use of engineered surface facilities toachieve retrievability is that the structures themselves wearout making continued retrieval and relocation a necessity.Because of the additional risks involved, the adoption of acourse of action requiring continual rehandling may place anunreasonable burden on future generations.
4. In an accident situation the damage incurred by a storagefacility could impair or even prevent retrieval. The proba-bility of this occurring and the effects that it might haveis a subject which requires further consideration.
5.. The time required to retrieve and relocate whole inventoriesbecomes so large that it is questionable whether, in an emer-gency, a truly effective retrieval operation could be carriedout. It may be necessary, for example, to restore coolingwithin a few weeks or days after an incident, but to moveeven one hundredth of the inventory in 2000 could take aslong as one month. This is another aspect of retrievabilitywhich needs to be further evaluated.
6. This study raises serious questions concerning the logisticsof retrievable storage for the long term. No commitment tosuch a system should be made without concurrent investigationand development of alternative methods for disposal.
![Page 200: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/200.jpg)
J-7
TABLE 1
PROJECTED ARISINGS OF SPENT CANDU FUEL
2000
2035
2070
2100
2120
LOW PREDICTION
RATE OF FUELPRODUCTIONCMg/a x 10"3)
7.1
26.3
29.2
29.2
29.2
CUMULATIVEPRODUCTION(Mg x 10"6)
0.071
0.68
1.68
2.55
3.43
HIGH PREDICTION
RATE OF FUELPRODUCTION(Mg/a x 10"3)
9.9
106.3
305.6
405.6
405.6
CUMULATIVEPRODUCTION(Mg x 10"6)
0.088
1.72
8.94
19.9
27.9
The assumptions used to compile these projections are as follows:
LOW Population
Power Consumption
HIGH Population
Power Consumption
i) growth rate drops to 0 over 50years from 1970
ii) Equilibrium population 36 million
i) rate of increase of consumptiondrops to 0 over 50 years from 1970
ii) equilibrium consumption 20 kW(t)/capita
i) present growth rate to 2060ii) rate drops to 0 over next 40 yearsiii) equilibrium 200 million
i) present rate of increase to 2000ii) rate drops to 0 over next 50 years
iit) equilibrium 50 kW(t)/capita
In both cases, nuclear power was assumed to supply ^ 100% of all energyrequirements by 2060.
![Page 201: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/201.jpg)
J-8
TABLE 2
RATE OF STORAGE OF SPENT CANDU FUEL
YEAR
2000
2035
2070
2100
2120
ONE-YEAR-r.vCOOLED F U E L W
CMg/a x 10"3)
6.0
25.8
29.2
29.2
29.2
POOLSREQUIREDPER YEAR
1
3
4
4
4
FIVE-YEAR-,.MCOOLED FUEL^ '(Mg/a x 10"3)
4.9
23.9
29.2
29.2
29.2
CANISTERSREQUIREDPER YEAR
1115
5441
6637
6637
6637
(i) Rate at which one year old fuel is moved from reactor site to storagein pools at a central site.
(ii) Rate at which five year old fuel is moved from reactor site to storagein canisters at a central site.
TABLE 3
CUMULATIVE STORAGE REQUIREMENTS FOR SPENT CANDU FUEL
YEAR
2000
2035
2070
2100
2120
ONE-YEAR-, vCOOLED F U E L W
(Mg x 10"6)
0.06
0.65
1.65
2.52
3.11
POOLSREQUIRED
8
77
194
297
366
FIVE-YEAR-/..vCOOLED FUELV11''(Mg x 10"6)
0.04
0.06
1.53
2.40
2.99
CANISTERSREQUIRED
9016
12502
348182
547273
680000
(i) Fuel which was placed in storage when one year old.
(ii) Fuel which was placed in storage when five years old.
![Page 202: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/202.jpg)
J-9
TABLE 4
REHANDLING REQUIREMENTS IN A SYSTEM OF RETRIEVABLE STORAGE
2000
2035
2070
2100
2120
FUEL PLACEP
IN STORAGE
(Mg/a x 10"3)
6.7
25.8
29.2
29.2
29.2
TOTAL HANDLING
RATE(l)
(Mg/a x 10"3)
6.7
27.0
47.3
64.4
76.J
REHANDLED
FUEL
(%)
0
5
62
120
162
(i) First rehandling assumed to occur in 2035, i.e. 50 yearsafter filling of first pool at central site. Subsequentrehandlings assumed to commence as each pool becomes 50years old.
![Page 203: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/203.jpg)
J-10
TABLE 5
STANDBY REQUIREMENTS FOR EMERGENCY RELOCATION OF 10% STORE FUEL
YEAR
2000
2035
2070
2100
2120
FUEL INSTORAGE
(Mg x 10~6)
0.064
0.65
1.65
2.52
3.11
POOLSREQUIRED
8
77
194
297
366
STANDBYPOOLSREQUIRED
1
8
20
30
37
AREA FORSTANDBYPOOLS(tan2)
0.3
0.8
2
3
3.7
AREA FORSTANDBYCANISTERS
(km2)
0.4
0.9
2.1
3.2
3.8
TABLE 6
TIME REQUIRED TO RELOCATE FUEL IN STORAGE
YEAR
2000
2035
2070
2100
2120
FUEL IN STORAGE
(Mg x 10"6)
0.064
0.65
1.65
2.52
3.11
TIME TO MOVE FUEL
(years)
9.6
25.3
56.5
86.5
106.5
![Page 204: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/204.jpg)
31VC10212 0113 0602 010Z 0502 0Ê02 0102 0661
MM
1
1
1
1
Mil
l 1
1
1 1
-
-
-
-
mi
» —
.——
3 aod ^nod
N0ii3ia3yd
— —
. — • —
.. — .
NVi. 0
'
NOU 3IQ3bd H9IH
Mil
l 1
1
1
II I
II 1
1
1
1
-
—
-
•rnr
—
0Z6I
,01
= eOl
gOI'
- «01
![Page 205: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/205.jpg)
,0 8
"£ I05
io4t
10
|l 11 1 1 1 1
lllll
Mi
l
=
-
-
-
z.
- f/
IIII Mi
l Illlll 1 1
1
- 'FUEL
•PROD
PRODU(
jcTior
;TION',** 0 YEAR COOLED) .
/
/
! + RE
— -y*
HANDL
- —
^
ING
<
—»=
REHAI\
i———
DLING
— •
—
REQUIRED
-
-
•a
—
nil.
-
-
1970
C-i
h-'S3
1990 2010 2030 2 0 5 0 2070
DATE
FIGURE 2: HANDLING OF SPENT CANDU FUEL (216
2090
J.h/kg)
2110 2130
![Page 206: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/206.jpg)
10
107 -
10° z
S io4
10
Illl 1 1 1 1
Illll 1 1 1 1
TTTT
-
z /Z J
/
*y
PROC
(1
UCTIO
^ ^FUEL
YEAR
/
N + R
PRODU
COOLf
y
/
EHANDL
CTION
I NG ~^ — •. —
^ —
^ - —
---RERE
—. —
. *
HANDL1QUIREE
..
.
NG)
—
^
—
-
-
-
-=
2090 21101970 1990 2010 2030 2050 2070
DATE
FIGURE 3 : CUMULATIVE HANDLING OF SPENT CANDU FUEL ( 2 1 6 MW.h/kg)
2 1 3 0
![Page 207: REPORT BY THE COMMinEE ASSESSING FUEL STORAGE PART 2 ... · appendix j retrievability j-1 1 introduction j-1 2 projected arisings of spent candu fuel j- 2 3 storage requirements j-3](https://reader036.vdocument.in/reader036/viewer/2022081607/5edb3e94ad6a402d66655a98/html5/thumbnails/207.jpg)
The International Standard Serial Number
ISSN 0067-0367
has been assigned to this series of reports.
To identify individual documents in the serieswe have assigned an AECL-number.
Please refer to the AECL-number whenrequesting additional copies of this document
from
Scientific Document Distribution OfficeAtomic Energy of Canada Limited
Chalk River, Ontario, CanadaKOJ1J0
PRICE-$9.00 per copy