REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES (220 kV & ABOVE) VIS-A-VIS PROGRAMME DURING 2015-2016 As on 30-NOV-2015 Schedule 1. 2. 5. 6. 7. 8. 9. 10. 12. 3. Revised/ Anticipate d 11. Construction progress Status Target Date Remark (Status of all statutory clearences particularly forest clearence and ROW problem, if any needs to be mentioned here.) Towers TL (Nos) STC (Nos) TE (Nos) STG (cKM) Voltage Level 4. Sl No Name of Transmission Lines Total Lengt h CKM Ckts (S/C) & (D/C) DAMODAR VALLEY CORPORATION (DVC) Railway Crossing:SER, Ranchi approved in principle for 3 no.rail crossing on 24.11.2014. Demand note raised by SER has been paid. SER being persued for agreement in this respect.PTCC: proposal submitted to concerned authority on 27.8.14. Matter is being persued with H'bag, BSNL & Ranchi, BSNL. Forest Clearance: Working Clearance issued on 22.5.2015. Progress affected due to non-availability of tower materials. In order to solve fund crisis faced by Contractor (M/s ECI-SEW), approval has been arranged for payment to the sub-vendor directly & subsequently 234 MT of tower materials has been delivered at site. NOV-14 112 Gola - Ranchi (PG) 216 149 96 0 1 D/C MAR-16 220 Commissioned 08/15. FEB-10 212 Kodarma-Giridih 324 324 324 212 2 D/C AUG-15 220 Severe ROW problem in 17 no locations. SE Railway has given in principle clearance of crossing. Around 24 no. locations outside the ISP premises are being diverted again due to severe ROW problem. Contractual issues cropped up due to repeated route diversion. Presently work is held up. 37 LILO of Mejia-Kalyaneswari at Burnpur S/S 79 55 0 0 3 D/C MAR-16 220 Forest: Working clearance obtained on 6.3.2013 from GOJ. Contractual issues cropped up due to delay in obtaining forest clearance as well as theft of materials (100 Ckm.) from erected line. Rectification work of the theft portion of the line has been completed. 54 km (i.e 108 ckm) of line charged at 220 KV from MTPS end on 09.9.15. DEC-08 342 Mejia TPS - Gola 552 541 509 148 4 D/C MAR-16 220 Forest: Working clearance obtained in January 2013.PTCC clearance:issued on 18.2.14. Aviation clearance: Obtained. Slow progress due to non-availability of working gang due to fund crunch of Contractor (M/s Jyoti Structures). Approval has been arranged for payment to the sub-vendor directly to solve above fund crisis of M/s JSL which has subsequently resumed work in Sep 2015 for the balance portion. AUG-10 311 Raghunathpur TPS -Ranchi (PG) 439 439 436 274 5 D/C MAR-16 400

Upload: hoangdan

Post on 26-Mar-2018

277 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES (220 kV & ABOVE) VIS-A-VISPROGRAMME DURING 2015-2016

As on 30-NOV-2015

Schedule

1. 2. 5. 6. 7. 8. 9. 10. 12.3.

Revised/Anticipate

d

11.

Construction progress StatusTarget Date Remark

(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)

Towers

TL(Nos)

STC(Nos)

TE(Nos)

STG(cKM)

VoltageLevel

4.

SlNo

Name ofTransmission

Lines

TotalLengt

hCKM

Ckts(S/C)

&(D/C)

DAMODAR VALLEY CORPORATION (DVC)

Railway Crossing:SER, Ranchi approved in principle for 3 no.rail crossing on24.11.2014. Demand note raised by SER has been paid. SER being persued foragreement in this respect.PTCC: proposal submitted to concerned authority on27.8.14. Matter is being persued with H'bag, BSNL & Ranchi, BSNL. ForestClearance: Working Clearance issued on 22.5.2015.Progress affected due to non-availability of tower materials. In order to solvefund crisis faced by Contractor (M/s ECI-SEW), approval has been arranged forpayment to the sub-vendor directly & subsequently 234 MT of tower materialshas been delivered at site.

NOV-14112Gola - Ranchi (PG) 216 149 96 01 D/C MAR-16220

Commissioned 08/15.FEB-10212Kodarma-Giridih 324 324 324 2122 D/C AUG-15220

Severe ROW problem in 17 no locations. SE Railway has given in principleclearance of crossing.Around 24 no. locations outside the ISP premises are being diverted again dueto severe ROW problem. Contractual issues cropped up due to repeated routediversion. Presently work is held up.

37LILO of Mejia-Kalyaneswari at Burnpur S/S 79 55 0 03 D/C MAR-16220

Forest: Working clearance obtained on 6.3.2013 from GOJ. Contractual issuescropped up due to delay in obtaining forest clearance as well as theft of materials(100 Ckm.) from erected line. Rectification work of the theft portion of the linehas been completed. 54 km (i.e 108 ckm) of line charged at 220 KV from MTPSend on 09.9.15.

DEC-08342Mejia TPS - Gola 552 541 509 1484 D/C MAR-16220

Forest: Working clearance obtained in January 2013.PTCC clearance:issued on18.2.14. Aviation clearance: Obtained.Slow progress due to non-availability of working gang due to fund crunch ofContractor (M/s Jyoti Structures). Approval has been arranged for payment tothe sub-vendor directly to solve above fund crisis of M/s JSL which hassubsequently resumed work in Sep 2015 for the balance portion.

AUG-10311Raghunathpur TPS -Ranchi (PG) 439 439 436 2745 D/C MAR-16400

Page 2: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

POWER GRID CORPORATION OF INDIA LIMITED (PGCIL)

Ready for commissioning 09/15.AUG-133506+/- 800KV HVDC Biswanath Chariyali - Agra Bi-poleline

4369 4369 4369 35061 BIPOLE

SEP-15±800

Commissioned 04/15.APR-1520400 kV D/C trans. Line for swapping of Kahalgaon #1bay with Sasaram# 1 bay at Biharshariff S/Stn.

38 38 38 202 D/C APR-15400

Work under progress.APR-17114Ajmer (New) - Ajmer (RVPN) (Quad) 163 54 10 03 D/C APR-17400

Stringing commenced from Nov'15. Work under progress.JUN-16486Allahabad - Kanpur line 629 506 245 34 D/C JUN-16400

JAN-17334Alusteng - Drass - Kargil - Khalsti-Leh 1072 319 108 05 D/C MAY-17220

ROW being faced. Hug forest involvement clearance awaited. CriticalDEC-15570Angul - Jharsauguda line 790 667 285 446 D/C DEC-16765

Forest clearance received in May'14. Severe ROW in 32Loc/50Km at Angul end.Work being executed with police protection.

MAR-13270Angul Pooling Station - Jharsuguda Pooling Stationline-II

510 510 510 2707 S/C JAN-16765

Forest clearance awaited.CriticalAUG-14570Aurangabad (PG) - Padghe (PG) 772 638 612 1758 D/C SEP-16765

Stage-I Forest clearance (138ha.) received in Aug'15. Severe ROW problem(involvement grape garden).

JUL-14654Aurangabad - Boisar line 896 674 589 3149 D/C JUN-16400

Aurangabad - III - Aurangabad (PG)10 2xS/C 765

Commissioned 09/15.MAR-16556Aurangabad - Solapur line 760 760 760 55611 D/C SEP-15765

Work yet to stared.80Bairasuil HEP - Sarna12 D/C 220

Completion matching with varansai S/stn.AUG-14165Balia - Varanasi 463 463 463 16413 S/C JAN-16765

Commissioned 09/15.AUG-13114Balipara - Biswanath Chariyali 165 165 165 11414 D/C SEP-15400

Award pleced in Jul'15. Engg. & survey under progress.APR-18570Banaskanta - Chittorgarh line 836 0 0 015 D/C APR-18765

Award placed in Jul'15. Engg. in progress.APR-1852Banaskanta - Sankhari line 130 0 0 016 D/C APR-18400

Commissioned 04/15.APR-13202Bareilly - Kashipur line (Quad) 282 282 282 20217 D/C APR-15400

Barethi - Etawah18 D/C 765

Commissioned 05/15.AUG-14698Barh-II - Gorakhpur 944 944 944 69819 D/C MAY-15400

Work under progress.MAY-16338Betul - Khandwa (Quad) line 434 293 225 4020 D/C MAY-16400

Commissioned 10/15.MAR-16113Bhiwani - Hissar line 159 159 159 11321 D/C OCT-15400

Award under progress.JUL-18618Bhuj Pool - Banaskanta line 0 0 0 022 D/C JUL-18765

Completion matching with Champa HVDC Station. Efforts being made for Pole-Iin Mar'16. Stage-I forest clearance for WR-II portion obtain in Jun'15. Permissionto work obtained in Sep'15.

JUN-152573Champa Pooling Station - Kurukshetra (HVDC) 3474 3438 2250 85023 BIPOLE

JUN-16±800

Work under progress.APR-1750Chittorgarh (New) - Chittorgarh (RVPN) (Quad) line 71 62 8 024 D/C APR-17400

Work under progress.APR-18398Chittorgarh - Ajmer line 625 171 10 025 D/C APR-18765

Severe ROW problem in Uttrakhand.NOV-14144Dehradun - Abdullapur 247 218 205 5126 D/C JUN-16400

Severe ROW problem in western UP.NOV-11249Dehradun - Bagpat 443 421 397 12527 D/C JUN-16400

Ready for Commissioning 09/15.MAR-13848Dharamjaygarh - Jabalpur Pooling Station line 1138 1138 1138 84828 D/C SEP-15765

Severe ROW problem faced in Karnataka. CriticalAUG-14244Dharmapuri (Salem New) - Somanahalli 336 311 265 17129 D/C FEB-16400

Implementation affecetd due to delay in forest clearance(received in Feb'15).NOV-14242Dulhasti - Kishenpur 340 307 272 6530 D/C JUN-16400

Page 3: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Aportion of line (279 Ckm) commissioned in April'12. balance portion under holddue to ECL.

314Durgapur-Jamshedpur (Balance Portion) 434 434 434 31431 D/C JUL-13400

G.O issued by govt. of Kerela dated on 19.08.14 recommanding additionalcompensation by land owner. Work to start after assessment of compensation &payment by state Govt./KSEB. Revised G.O. issued on Jan'15. Recently GOissued on 30.07.15 in which compensation is to be done on land value, to befinalised by concerned DC. DC yet to initiate action.

NOV-08297Edamon (KSEB) - Muvattupuzha (PG) 438 159 105 2932 D/C DEC-16400

Severe ROW problem being encountered.09 fdn. 10 TE & 3.5 Km stringing holddue to non-finalisation of gantry by Essar Power.

FEB-14450Essar Gujarat TPS - Bachau 605 596 593 42433 D/C DEC-15400

Completion matching with Varansai S/stn.MAY-15251Ext. of one ckt Biharshariff - Sasaram at Varanasi (Q) 344 344 337 17134 D/C JAN-16400

Re-conductoring work under progress. Efforts being made to complete earlier.NOV-1686Farakka - Malda 035 D/C NOV-16400

Award under progress.NOV-17203Gadarwara - Jabalpor Pool line36 D/C 765

Award under progress.NOV-17640Gadarwara - Warora Pooling Station37 D/C NOV-17765

Completion matching with S/stn. Varansi sub station critical due to delay in landacquisation.Severe ROW )Naxalite)problem faced.

AUG-14246Gaya - Varanasi 738 730 716 22538 S/C FEB-16765

112Gola - Ranchi line39 D/C 220

Commissioned 11/15.JUN-14418Gooty - Madhugiri 575 572 572 41840 D/C NOV-15400

Commissioned 08/15.MAR-14305Gwalior - Jaipur (Ckt 1) 834 834 834 30541 S/C AUG-15765

Commissioned 08/15.MAR-14311Gwalior - Jaipur line (Ckt 2) 656 656 656 31142 S/C AUG-15765

Work under progress.APR-18838Jabalpur PS - Orai 2095 318 7543 D/C APR-18765

ROW problem on 8 nos. fdn.& 20 nos TE at Bhiwani end.MAR-16277Jaipur (RVPNL) - Bhiwani (IInd Ckt) line 749 740 345 8644 S/C MAR-16765

Commissioned 08/15.MAR-16272Jaipur - Bhiwani line 741 741 741 27245 S/C AUG-15765

Stage-I forest clearance received in Dec'14 & permission to work received inMay'15.

NOV-13372Jharkhand Pool - Gaya (Quad) line 332 307 246 2046 D/C FEB-16400

Huge forest involvement.CriticaDEC-15312Jharsuguda - Dharamjaygarh line 296 252 133 1147 D/C DEC-16765

work under progress.OCT-1676Kakrapar APP - Navsari line 108 87 5848 D/C OCT-16400

Stringing commenced from Nov'15. Work under progress.OCT-16208Kakrapar APP - Vapi line 326 316 195 149 D/C OCT-16400

ATS slowed-down to the extent possible to match with Gen. of Kameng. Gen.proj. delayed. (expected in 2016-17).

AUG-13110Kameng - Balipara 149 136 102 050 D/C DEC-16400

Matching with Kanpur 765KV GIS.OCT-1441Kanpur (new) - Kanpur (exit) 62 62 62 3851 D/C MAR-16400

Efforts being made to complete earlier.OCT-14483Kanpur - Jhatikara 1265 1268 956 36652 S/C JUN-16765

Severe ROW problem in Roorkee end.APR-13302Kashipur - Roorkee line 420 420 418 29653 S/C DEC-15400

work under progress.AUG-16292Khamam - Nagarjunasagar line (Vzag TCL) 388 377 354 16454 D/C DEC-15400

Work under progress.MAY-16360Khandwa - Indore line 490 432 330 21555 D/C MAY-16400

Khargone TPP-Indore56 D/C DEC-15400

Award for tower pkgs. placed in march 2015. Engg. & survey under progress.MAR-18206Kishanganga - Amargarh 132 757 D/C JUL-17220

Works under progress.MAR-1878Kishanganga - Wagoora 336 1758 D/C MAR-18220

Page 4: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Completion matching with Kishanganj s/stn. Land acquired in Aug'13.NOV-13692Kishanganj - Patna line (Quad) 915 915 914 68759 D/C DEC-15400

Final forest clearance to be issue after cabinit meeting. Limited working perioddue to snow-bound area & flood affecting implementation. Critical

JUL-13278Kishenpur - New Wanpoh line (132 KM D/C + 7 KMMulti Ckt)

394 390 366 18260 MC+D/C

JUN-16400

Kishenpur - Ratle, (Dulhasti- Kishenpur Second Cktstringing extending up to Ratle HP)

61 S/C JUN-16400

Award placed in Aug'15. Engg. in progress.NOV-17360Kota - Jaipur (South) 52962 D/C NOV-17400

400KV D/C Nellor-Gooty line commissioned in Mar'13. (early K'patnam UMPP -Gooty line)

632Krishnapatnam UMPP - Gooty line (Quad) 788 788 788 57863 D/C MAR-13400

Work under progress.AUG-16119Kurnool (New) - Raichur line 319 318 280 9564 D/C DEC-15765

Ready for Commissioned 11/15.JUN-15266Kurukshetra - Jallandhar (Ckt-I) 728 728 728 26665 D/C NOV-15400

265Kurukshetra - Jallandhar (Ckt-II)66 D/C 400

Work under progress.MAR-18190Kurukshetra - Jind line (Q) 270 62 0 067 D/C MAR-18400

Severe ROW problem. Critical.OCT-1497LILO of Aurangabad - Pune at Pune 67 62 51 2368 D/C DEC-15400

Award placed in May'15.Work under progress.JUL-1717LILO of One Ckt Parbati Pooling Station - Amritsar atJalandhar

42 1369 D/C JUL-17400

Commissioned 07/15.NOV-1232LILO of One Ckt of Baripada - Mendhasal line at Dubri(OPTCL)

48 48 48 3270 D/C JUL-15400

Ready for Commissioning 08/15.JUL-1546LILO of 2nd ckt of Neyveli - Trichy at Nagapattnam 65 65 65 4671 D/C AUG-15400

Award under progress.JUL-172LILO of Abdullapur - Karchan wangtoo at Kala Amb72 D/C JUL-17400

Ready for Commissioning 11/15.JUN-1530LILO of Abdullapur - Sonepat at Kurukshetra (Tripal) 45 45 45 3073 D/C NOV-15400

Award placed in Mar'15.JUL-17120LILO of Agra - Bharatpur at Agra 30074 S/C JUL-17220

Award placed in Mar'15.Engg. & survey under progress.APR-18LILO of Agra - Meerut at Aligarh 9975 D/C APR-18765

Package under re-tendering.DEC-1230LILO of Aizwol (PG) - Zemabawk at Melriat (PG) 45 0 0 076 D/C JUN-16132

Completion matching with Sub station. Severe ROW problem being faced.54LILO of Baripada - Mendhasal at Pindiabil 106 96 72 877 D/C DEC-15400

Gen. Project delayed (ant. in 2016-17).Work under progress. In order to commissioning of Alipurduar Terminalalongwith Pole-II of NEA-Agra completion is planned to be preponed.

JAN-1524LILO of Bishwanath Chariali - Agra at Alipurduar 63 30 1178 HVDC MAR-16±800

Work under progress.JAN-1513LILO of Bongaigaon - Siliguri at Alipurduar 23 11 779 D/C MAR-16400

Award under progress.MAY-17LILO of Both Ckt of Bawana - Mandola at Rajgarh80 D/C MAY-17400

Award under progress.JUL-1770LILO of Both Ckt of Bmanauli - Samaypur atTughlakabad

15081 D/C JUL-17400

Severe ROW problem in western UP.Line proposed for deletion as advised byState Govt. (reffered to CEA). Completion Uncertain

NOV-1258LILO of Both Ckt of Dehradun - Bagpat line (QUAD) atSaharanpur

78 35 0 082 D/C MAR-16400

Work under progress.JUN-1650LILO of Dadri - Malerkotla at Kaithal 67 1783 D/C JUN-16400

Commissioned 07/15.AUG-1429LILO of Dehar - Bhiwani at Rajpura (PSTCL) 43 43 43 2984 S/C JUL-15400

19LILO of Gangtok - Melli at Rangpo85 S/C 132

Commissioned 11/14.NOV-147LILO of Gangtok - Rangit at Rangpo 21 21 21 786 S/C NOV-14132

Commissioning matching with S/stn.MAY-157LILO of Gaya - Fatehpur at Varanasi line 9 9 9 687 S/C DEC-15765

Work under progress.JUN-1438LILO of Gazuwaka - Vijayawada at Vemagiri 85 488 D/C NOV-17400

Page 5: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Award placed in Mar'15.Engg. & survey in progress.MAR-187LILO of Hyderabad - Kurnool at Maheshwaram 1589 D/C MAR-18400

LILO of Jiribam - Aizawl at Turial90 D/C 132

Work under progress.MAY-1621LILO of Kadapa (Cuddapah) - Kolar at Kunta PoolingStation

30 2491 D/C MAY-16400

Award placed in Mar'15.Engg. & survey under progress.APR-1835LILO of Kanpur - Jhatikara at Aligarh 9992 D/C APR-18765

Commissioned 03/13.DEC-121LILO of Loktak - Imphal at Imphal (New) line 5 5 5 193 D/C MAR-13132

Balance protion of line using under ground cable. Award placed in Sep'13.ROWproblem for laying of cable continue. Critical

SEP-1018LILO of Lonikhand (MSETCL)- Kalwa at Navi Mumbai 25 25 24 1594 D/C FEB-16400

Completion matching with Bagpat S/Stn. (delay in land acquisation). SevereROW problem.

FEB-12124LILO of Meerut - Kaithal at Bagpat 177 177 174 10695 D/C DEC-15400

Commissioned 06/15.MAR-164LILO of Moga - Bhiwani at Hissar line 4 4 4 496 D/C JUN-15400

Completion uncertain.ROW problem. Critical.Petition filed in Karnataka High Court for now resolved on31.07.13. Work commenced in Jan'14. However work again stopped due toagitation.

JUL-1234LILO of Neelamangla - Hoddy line and LILO ofSomanhally - Hoddy at Yelahanka

25 25 25 2597 D/C DEC-15400

Award under progress.MAY-1745LILO of One Ckt of Bamnauli - Jhattikara at Dwarka-I98 D/C MAY-17400

work under progress.APR-16906LILO of Rajarhat - Purnea at Gokarana 1341 773 332 6099 D/C APR-16400

Commissioned 10/15.AUG-13114LILO of Ranganadi - Balipara 400KV D/C line atBiswanath Chariyali (Pooling Point)

77 77 77 114100 D/C OCT-15400

Work under progress. Efforts being made to complete earlier.JUL-1734LILO of Sarna - Hiranagar at Samba 57 18101 S/C JUL-17220

Completion matching with Varansai S/stn.OCT-14237LILO of Sasaram - Allabhadad at Varanasi (Q) 342 342 337 100102 D/C MAR-16400

Completion matching with kishenganj S/S.JAN-138LILO of Siliguri (Existing) - Purnea at Kishanganj 25 25 25 6103 D/C DEC-15400

Completion matching with Kishenganj S/S.JAN-1336LILO of Siliguri - Dalkhola line at New Pooling StationKishanganj

69 69 68 35104 D/C DEC-15220

ROW problem. Critical.State Govt. help required for resolution of compensationissue.

DEC-1525LILO of Somanhally - Hoddy line at Yelahanka 25 25 25 25105 D/C JUN-16400

Work under progress. Stringing commenced from Nov'15.APR-168LILO of Subhashgram - Jeerat at Rajarhat 16 11 10 2106 S/C APR-16400

Works was held up. Severe ROW problem issue.Now started. Construction of 01LILO deferred.

NOV-1341LILO of Teesta-III - Kishanganj 400 KV D/C (Q) atRangpo (21 D/C+1.5 M/C)

84 26 14 5107 MC+D/C

JAN-16400

LILO of Tilaiya - Balia line at Gaya108 D/C DEC-16765

Investment approval pending.LILO of Vishnu Prayag - Muzaffarnagar at TapovanVishnugarh HEP

109 D/C MAR-15400

NOV-17180LILO of Wardha - Parli at Warora PS (Q)110 2xD/C 400

Award placed in May'14 LILO only one ckt is to be carried out scheme has beenrevised.

JUN-1648LILO of boht ckt RAPP - Kankroli at Chittorgarh 54111 D/C JUN-16400

Commissioned 11/15.APR-1590LILO of both ckt of Kolhapur - Mapusa at Kolhapur(new)

120 120 120 90112 D/C NOV-15400

.LILO of one circuit of Dulhasti - Kishenpur at RatleHEP.

113 D/C 400

Work under progress.APR-18160LILO of one ckt of Satna - Gwalior at Orai 222 22 0 0114 D/C APR-18765

Work under progress.APR-17224Lara STPS - Champa pooling Station line (Q) 307 16 10115 D/C APR-17400

Work under progress.APR-1736Lara STPS - Raigarh (Kotra) line 50 22 22116 D/C JUN-16400

Route alignment completed, check survey copleted.17Leh-Kharu (And LILO of Leh-Nimmo) 0 0 0 0117 D/C MAY-1766

Page 6: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Completion uncertain. Works stand still on a/c of localm disturbance /agitationagainst big dam. Generation uncertain.

AUG-13334Lower Subhansiri - Biswanath Chariyali line -I 444 329 228 64118 D/C MAR-15400

Completion uncertaion.Works stand still on a/c of local disturbancec /agitationagainst big dam. Gen. schedule uncertain.

AUG-13340Lower Subhansiri - Biswanath Chariyali line -II 465 327 196 35119 D/C MAR-16400

Work under progress.JUN-16320Lucknow - Kanpur 454 110 5120 D/C JUN-16400

Completion uncertain due to severe ROW problem in Karnataka.Critical.

JUN-14122Madhugiri - Yelhanka 177 131 103121 D/C JUN-16400

Ready for Commissioning 06/15.DEC-1297Mariani (New) - Mokikchung (PG) 163 163 163 97122 D/C JUN-15220

Work under progress.MAY-16386Mauda-II - Betul (Quad) line 537 419 280 72123 D/C MAY-16400

Commissioned 05/15.MAR-15337Meerut - Moga line 922 922 922 337124 S/C MAY-15765

Work slowed down to the extent feasible matching with Generation project.JUL-1556Meja - Allahabad line 81 79 59 5125 D/C JUN-16400

Stage-I forest clearance awaited.package under re-tendering.DEC-1212Melriat (New) - Sihmui line 30 0 0 0126 D/C JUN-16132

Line commissioned in Jul'15.DEC-122Mokokchung (PG) - Mokokchung (Nagaland) line 11 11 11 2127 D/C JUL-15132

Ready for Commissioning 09/15.DEC-07420Mysore - Kozhikode 614 614 614 420128 D/C SEP-15400

Work under progress.FEB-1733NCC gen Sw Yd. - Nellore PS line (Q) 101 101 96 25129 D/C MAR-16400

Work under progress.MAR-15534Nagapattinam Pooling Station - Salem (NMTCL) 543 428 302 63130 D/C DEC-15765

Ready for Commissioned 11/15.APR-15374Narendra (New, Kudgi) - Kolhapur (new) 489 489 489 374131 D/C NOV-15765

Ready for Commissioning 11/15.APR-15354Narendra (New, Kudgi) - Narendra (Existing) 464 464 462 354132 D/C NOV-15400

Contigrncy arrangement to connect Navsari-Boisar with Vapi-Navi Mumbai lineby passing forest area to form Vapi-Navsari line (212 Ckm) commissioned inMar'13.For balance portion, forest clearance awaited. Critical. Severe ROWproblem being faced.

OCT-12432Navsari - Boisor 599 483 452 290133 D/C JUN-16400

Commissioned 11/15.JUL-1514Neyveli TS-II - Neyveli TS-I134 D/C NOV-15400

Award placed in Mar'15. Engg. & survey under progress.MAY-1822Nizamabad - Dichpali 55135 D/C MAY-18400

Award Placed in Mar'15.Engg. & survey under progress.APR-18600Orai - Aligarh 892136 D/C APR-18765

Award placed in Mar'15.Engg. in progress.APR-1876Orai - Orai (Q) 100137 D/C APR-18400

Commissioning of Kuddus S/S by MSETCL critical. Completion matching withAurangabad-Padghe line.

AUG-1434Padghe (PG) - Kudus line 46 45 44 27138 D/C JUN-16400

Completion of Kudus S/S by MSETCL critical.Completion matching Aurangabad- Padghe line.

AUG-1450Padghe (PG) - Padhe (PG) 46 45 44 27139 D/C SEP-16400

Work under progress.JUN-16131Panchkula - Patiala 183 163 86 10140 D/C JUN-16400

Award under progress.JAN-1840Parli - Parli (Q)141 D/C JAN-18400

Award under progress.NOV-17294Parli - Solapur142 D/C 765

Readiness of up stream & down stream system being implementated byArunachal Pradesh Govt. Critical for commissioning of line.

DEC-1270Pasighat - Roing line. 345 345 344 101143 S/C onD/C

FEB-16132

Pipalkoti HEP - Pipalkoti (THDC) (Kuwari Pass)144 D/C 400

Gen. expected beyound 2017-18. Wild life sanctuary involved. Case underprocess at NBWL.

JAN-15128Punatsangchu-I - Alipurduar 174 152 135 24145 D/C DEC-16400

Forest clearance for Bundi & Kota Div. are awaited.77nos. location are inMAR-15104RAPP - Kota line 130 40 16146 D/C DEC-16400

Page 7: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

forest. Critical

Commissioned 05/15.MAY-1496Raigarh Pooling Station (Near Kotra) - ChampaPooling Station line

247 247 247 96147 S/C MAY-15765

Stage-I Forest clearance (295 Ha)received in Jun'15. Permission to workobtained in July 15.

JAN-15713Raipur Pooling station - Wardha line -II 961 741 595 202148 D/C JUN-16765

Permission to work in forest received in May'15.AUG-14341Ranchi (New) - Dharamjaygarh /Near Korba 921 921 920 340149 S/C JAN-16765

Testing under progress. Completion matching with Jharkhand Pool & JharkhandPool bey at line.

NOV-13136Ranchi - Jharkhand Pool line (Quad) 195 195 195 138150 D/C FEB-16400

Commissioned 05/15.NOV-1354Rangpo - New Melli line (Twin Moose) (20.5 D/C & 1.5M/C)

115 115 115 54151 MC+D/C

MAY-15220

Ready for Commissioning in 08/15.NOV-1231Rihand - Vindhyachal Pooling Station (2nd Ckt) 91 91 91 31152 D/C AUG-15765

Progress affected due to severe ROW problem.CriticalAPR-1260Roing - Tezu line 244 212 180 31153 S/C onD/C

MAR-16132

ROW problem in western UP.APR-1376Roorkee - Saharanpur line (Quad) 100 98 98 66154 D/C JAN-16400

Work under progress.DEC-15217Salem - Madhugiri 574 245 114155 D/C MAR-16765

Severe ROW being faced in Karnataka. Critical.SEP-14244Salem Pooling Station - Madhugiri Pooling Station line 645 605 564 97156 S/C MAR-16765

Ready for commissioning 08/15.SEP-14120Salem Pooling Station - Salem 165 165 165 120157 D/C AUG-15400

Commissioned 04/15.APR-156Sasan - Vindhyachal (PS) 18 18 18 6158 S/C APR-15765

MAY-154Sasaram - Allahabad line 11 11 10 5159 D/C JAN-16400

Completion matching with Daltanganj S/S delayed due to non-availibility of S/Sland (land acquired in May'15).

NOV-12392Sasaram - Deltonganj line 523 512 475 295160 D/C DEC-16400

Foundation commenced from Nov'15.MAR-1722Sholapur STPP - Sholapur line - II 35 8161 D/C MAR-17400

Ready for commissioning 04/15.OCT-1522Sholapur STPP - Sholapur line-I 35 35 35 22162 D/C APR-15400

Contract reviewed through assignement to JV partner.AUG-12336Sikar - Jaipur line 480 470 438 205163 D/C MAR-16400

Line test charged in Jun'12.50Silchar - Hailakandi (Contingency arrangement) 65 65 65 39164 D/C JUN-12132

Major portion of line in forest. severe ROW in vicinity of Aizwl town due to stiffresistance from influential local owner. package under re-tendering.

DEC-12286Silchar - Melriat (New) line (charged at 132KV) 436 366 211 101165 D/C JUN-16400

Commissioned 07/15.DEC-12254Silchar - Purba Kanchan Bari line (charged at 132KV) 373 373 373 254166 D/C JUL-15400

SEP-13Siliguri - Purnea167 D/C SEP-15400

Work under progress.JUN-16170Singrauli - Allahabad line 422 150 65168 D/C JUN-16400

Work under progress.AUG-16668Srikakulam PP - Vemagiri - II Pooling Station (VizagTCL)

877 719 470 87169 D/C AUG-16765

Stage - I forest clearance awaited (99 Ha.).1 package under re-tended &awarded in Jun'15. Completion matching with Srikakulam - Vimagiri beingexecuted under TBCB route (sch. Aug'16).

JUN-15552Srikakulam Pooling Station - Angul line 726 594 447 131170 D/C AUG-16765

Efforts being made to complete by Dec'15.46Suraj mani nagar - North Comilla (Indian portion) 63 57 42 14171 D/C DEC-15400

Investment approval pending.Tapovan Vishnugadh - Kunwari Pass172 D/C MAR-17400

Award placed in Feb'15.Engg. & survey under progress.NOV-1714Tehri Gen. - Tehri Pooling Station (Q) 50173 D/C OCT-17400

Award placed in Feb'15. Engg in progress.NOV-174Tehri Pooling Station - Meerut 10174 D/C OCT-15765

Page 8: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Progress affecetd due to severe ROW problem.DEC-1290Tezu - Namsai line. 332 213 153 32175 S/C onD/C

JUN-16132

Work under progress.APR-17116Tirunelveli PS - Tuitcorin PS (Quad) line-1 232 23 0 0176 D/C APR-17400

Award placed in Apr'15. Engg. & survey under progress.APR-17114Tirunelveli PS - Tuitcorin PS (Quad) line-2 228 0 0 0177 D/C APR-17400

Contractual issue.SEP-14739Tuticorin Pooling Station - Salem Pooling Station 1000 995 675 145178 D/C JUN-16765

Work under progress.SEP-1660Unchahar - Fatehpur 145 126 79 0179 D/C JUN-16400

Due to severe ROW problem at Novi Mumbai end, line was decided to beterminatedat Kudus S/stn.of MSETCL.Forest clearancereceived on Aug'15Contingency arrangement to connect Vapi-Navi Mumbai with Navsari-Boiser linebypassing ROW area to form Vapi-Navsari line(24 ckm) comm. in Mar'13.400 kV D/C Vapi-Kala portion comm. in Mar'14 (61 ckm)Balance to complete by Mar'16.Kudus s/s being implemeted by MSETCL. CRITICAL

236Vapi (PG) - Kala - Kudus 346 205 185 90180 D/C JUN-16400

Due to severe ROW portion at Navi-Mumbai end,Line now decided to theterminated at Kudus S/stn. of MSETCL. Forest clearance (Stage-I) received inAug'14.Contigency arrangement to connect Vapi-Navi Mumbai with Navsari-Boisar lineby passing ROW area to form Vapi-Navsari line (24 Ckm) commissioned inMar'13.40KV D/C Vapi-Kala portion (61 Ckm0 commissioned in Mar'14. Balancematching with readiness of Kudus S/S by MSETCL.

SEP-10258Vapi (PG) - Navi Mumbai 346 205 185 90181 D/C JUN-16400

258Vapi-Boisar 0 0 0 0182 D/C 400

Completion matching with Varansai sub station critical. Balance land for varansaiGIS acquired in Jun'14.

OCT-14652Varanasi - Kanpur 885 882 876 414183 D/C MAR-16765

Commissioned 07/15.NOV-14661Vijayawada - Nellore line 887 887 887 661184 D/C JUL-15400

Award under progress.JUN-181520Vindhyachal - Jabalpur185 D/C JUN-18765

Commissioned 08/15.271Vindhyachal Pooling Station - Satna Ckt-II 586 586 586 271186 S/C AUG-15765

Contract terminated 01 out of 02 nos due to unsatisfactory performanc and freshtender being taken up.The pkg. has been bifurcated into two pkgs.. 01 pkg.award in Dec'14 & 2nd pkg. awarded in Feb'15.Remaning 01 pkg. alsoterminated in Aug'15 due to poor performance & fresh tender is being taken up.

OCT-12700Wardha - Aurangabad (on 1200 kV) 961 875 678 196187 D/C DEC-161200

Work under progress.MAY-181032Wardha - Hyderabad line 1474 378 56188 D/C MAY-18765

Award under progress.NOV-17640Warora Pooling Station - Parli189 D/C JAN-18765

Page 9: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

ASSAM ELECTRICITY GRID CORP. LIMITED (AEGCL)

completed/ Ready to be charged.NOV-1323Agia - Matia (Dudhnoi) line 87 87 87 231 S/C onD/C

MAY-15132

Frequent Bandhs in BTAD area, forest clearance received, RoW at Loc 21,22 inforest area etc. are making the project slipped.

DEC-1310BTPS - Kokrajhar line 39 37 28 52 S/C onD/C

JAN-16132

1. Delay due to re alignment of line such as proposed airport at BTAD area, 800kV line of PGCIL, ROW, Local Problem etc. are attributing to the delay. Nowthere is almost settlement of RoW and compensation related issues, the Erectionwork is going on smoothly. How ever in Mushalpur areas (Baksa) District therehas been serious law and order issues and construction work is carried out bydeploying Security personnel.

JAN-13327Bongaigaon TPS - Rangia (Salakati) 517 494 452 773 D/C JUN-16220

Work in progress. Clearance and RoWSEP-1363Kokrajhar - Bilashipara - Gauripur 203 199 121 224 S/C onD/C

FEB-16132

Check survey done. Profile drawing approved.DEC-115Kukurmara - Azara line 24 0 05 S/C onD/C

MAR-16132

Project has been abandoned25Kukurmara - Boko line 162 0 0 06 S/C onD/C

DEC-14132

Commissioned 08/15.JAN-132LILO of One Ckt Langpi - Sarusajai at Sonapur 1 1 1 27 D/C AUG-15220

Completed on 06.07.2015.NOV-1310LILO of Jorhat - Bokakhat at Jorhat (West) S/S 9 9 9 38 D/C AUG-15132

completed 13.07.2015.NOV-134LILO of Namrup - Tinsukia at Bordubi S/S 9 9 8 59 D/C MAY-15132

in progress.DEC-1314LILO of both ckt of Balipara (PG) Samaguri at Sonabil 6 6 5 210 2xD/C JUN-16220

in progress.NOV-135LILO of both ckt of Depota - Gohapur at Sonabil S/S 6 6 6 111 2xD/C JUN-16132

RoW & Water logging problems adversely affected erection work.DEC-1355LILO of one ckt Samaguri - Sarusajai line at SonapurS/S

41 31 0 012 D/C JUN-16220

commissioned on July 2015.JAN-1359LILO of one ckt of Tinsukia - Margherita at Rupai(Doomdooma) S/S

109 109 109 5913 D/C JUN-16132

Railway Crossing & Gantry is not ready at Namrup GSS.DEC-13145Namrup - Mariani 448 448 448 14514 S/C onD/C

JAN-16220

completed.34Nazira - Mariani (Garmur) line 237 237 137 6915 S/C APR-13132

Completed/ Charged on 04.12.2015.NOV-1361Samaguri - Lanka line (2nd Ckt) 205 205 205 6116 S/C JUN-16132

completed in Dec' 2013.JAN-1342Samaguri - Nagaon line 142 142 142 4217 S/C onD/C

DEC-13132

In progress Railway crossing/ ROW/ compensation issue..NOV-1328Sonapur - Chandrapur line 51 39 11 018 D/C JUN-16132

In progress (compensation issue)..NOV-1352Sonapur - Jagirod line 86 40 25 019 D/C JUN-16132

Page 10: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

BEAS VALLEY POWER CORPORATION LIMITED (BVPCL)

.Uhl-III - Hamir Pur1 S/C onD/C

132

Page 11: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

BIHAR STATE ELECTRICITY BOARD (BSEB)

Work yet to start.JUN-16200Barauni TPS Exte. - Hazipur 350 0 0 01 D/C JUN-16220

SEP-03366Begusarai-Purnea 564 551 172 162 D/C DEC-14220

No Progress.JUL-1534Bihta (New) - Bihta3 D/C 220

108Bihta - Sipara4 D/C SEP-15220

MAR-1620Darbhanga - Darbhanga 16 3 0 05 D/C MAR-16220

DEC-15200Darbhanga - Motipur 397 230 86 06 D/C DEC-15220

MAR-1650Darbhanga - Samastipur (New) 178 4 0 07 D/C MAR-16220

JUN-16190Darbhanga - Supaul/Lokhi 326 0 0 08 D/C JUN-16220

118Gaurichak - Bihta (New) 207 89 81 119 D/C 220

JAN-16200Gaya (PG) - Sonenagar (New) 299 252 188 010 D/C JAN-16220

Severe ROW issues.101Kanti - Gopalganj (2nd Ckt.)11 S/C MAR-16220

Detailed survey of APO to AP 18 done, rest under progress.JUN-16250Kishanganj (New) - Madhepura12 D/C JUN-15220

FEB-1516Kishanganj (PG) - Kishanganj (New) 29 0 0 013 D/C FEB-16220

Likely to start soon.MAY-154LILO of 2nd ckt Pusouli (PG) - Ara (PG) at Pusouli(New).

14 D/C 220

JAN-1660LILO of Begusarai - Kanti at Samastipur 53 6 0 015 D/C JAN-16220

work yet to be awardedLILO of Both Ckt of Purnea - Begusarai at BTPS Extn16 D/C 220

4LILO of Both ckt of Biharsharif - Begusarai at BTPSExtn.

9 5 2 017 D/C AUG-15220

DEC-15140LILO of Darbhanga - Kanti at Motipur 251 197 142 018 D/C DEC-15220

MAR-1684LILO of Darbhanga - Kanti at Musahari 166 7 0 019 D/C JUN-16220

Ready for Commissioning 08/15.MAY-155LILO of Pusouli (PG) - Ara (PG) at Pusouli (New) 19 19 19 520 D/C AUG-15220

Detailed survey of APO to AP 14 done, rest under progress.150Madhepura - Lokhi21 D/C AUG-16220

Not yet decided due to incorporation of Multi-Ckt. Towers in the scope of work.1Patna (PG) - Gourichak22 D/C AUG-15220

MAY-1562Pusouli (New) - Dehri 199 125 23 523 D/C 220

Page 12: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. (CSPTCL)

Ready for Commissioning 11/15.FEB-11189Chhuri - Mopka (Bilaspur) 345 345 345 1891 D/C NOV-15220

Work is under progress.JUN-15155Korba (E) - Vishrampur (2nd Ckt.) 482 D/C MAR-16220

Commissioned 05/15.MAR-13116LILO of One ckt of Korba (W) - Khedamara at Marwa 161 161 161 1163 D/C MAY-15400

Commissioned 04/15.JUL-1430LILO of Korba - Vishrampur at Churri 30 30 30 304 D/C APR-15220

Commissioned 08/15.FEB-1418LILO of Raigarh - Budipadar line at Raigarh (PG) 46 46 46 185 D/C AUG-15220

Work is under progress. 2nd Phase forest clearance obtained. Compliance ofAvifauna as per forest office letter no. 1085 dtd. 01.05.2015 is under process.Work in forest is under progress.

MAY-14658Raita - Jagadalpur 901 848 810 4046 D/C MAR-16400

Page 13: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

DELHI TRANSCO LIMITED (DTL)

¿Case for extension of time upto 28.02.15 was processed and approval of sameis awaited.

12Bawana-Rohini -II (Sec -29) 38 30 19 01 D/C MAR-15220

180Harsh Vihar - Patparganj line2 D/C 220

Commissioned 07/15.11LILO of Kanjhawala - Najafgarh at Mundka 400 kV S/S 35 35 35 113 D/C JUL-15220

Commissioned 04/15.MAY-1126Mundka -Peeragarhi U/G 200 mm, 250 MW 264 D/C APR-15220

.Cable laid in 13 Sections out of 19 Sections. 42 Joints made out of 108 Joints.

.Delay in RBI permission to M/s TBEA to open INR account in India received inNov,13..¿ROW charges amounting to Rs. 7.6 Crore deposited to Railways . Thepermission is expected within a week.¿Work has been stopped by TBEA and their sub-contractor for approx. last 4months on account of pending INR payments. Finance deptt. is not releasingpayments amounting to Rs. 2.7 Crore citing WCT/Taxation issues.

17Peeragarhi-Wazirpur U/G 1000 mm, 200 MW5 D/C MAR-15220

Page 14: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

DEPARTMENT OF POWER ARUNACHAL PRADESH ()

.LILO of Ranganadi - Nirjuli at Pare HEP1 D/C 132

Page 15: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

GOA ELECTRICITY DEPARTMENT (ED- GOA)

Under planning Stage.30Colvale-Cuncolim1 D/C APR-17220

Administration and expenditure approval has been accorded and placing ofaward likely by March 2015.

90Ponda - Verna 0 0 02 D/C APR-17220

Page 16: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

GUJARAT ENERGY TRANSMISSION CORP. LIMITED (GETCO)

Line dropped as scheme changed110Amerli-Jasdan 0 0 01 D/C MAR-16220

W I P / Severe RoW problems470Amreli - Kasor line 676 584 471 02 D/C MAR-16400

Commissioned 10/15.80Amreli - Sukhpar line 126 126 126 803 D/C OCT-15220

WIP188BECL (Padva) - Botad line 292 138 87 04 D/C MAR-16220

Yet to award.340Bhachau - Radhanpur 0 0 05 D/C JUN-15220

Commissioned 11/15.104Bhadreshwar - Varsana line 1046 D/C NOV-15220

W I P / Severe RoW problems238Bhatiya-Kalwad line 373 101 59 07 D/C APR-14220

Yet to award240Bhogat-Kalavad 0 0 08 D/C MAR-16400

199Chanranka - Veloda 275 217 192 539 D/C MAR-16400

Ready for Commissioning 06/15.193Charanka - Jangral 302 302 302 19310 D/C JUN-15220

Line test charged on 01.06.2015 from Jangral to AP-13.191Charanka - Langral 302 302 302 19311 D/C JUN-15220

Yet to award200Chhara -Keshod 0 0 012 D/C MAR-17400

Commissioned 10/15.OCT-1538Chharodi - Ford line 33 33 33 3813 D/C OCT-15220

Yet to award40Chhatral - Dhanaj 0 0 014 D/C MAR-16220

Yet to award170Chikhli - Bhilad 0 0 015 D/C MAR-17220

WIP160Chorania - Botad 196 36 0 016 D/C OCT-15220

Yet to award71Choraniya - Viramgam 0 0 017 D/C MAR-15220

Yet to award120Fedra - Botad 0 0 018 D/C MAR-15220

Severe ROW Problem.MAR-1294GPPC (Pipavav)- Dhokadva 152 152 152 7019 D/C OCT-15220

wip194Gavasad - Salejada line 313 245 96 020 D/C MAR-16220

Yet to award50Hadala - Rajkot-II 0 0 021 D/C MAR-15220

Yet to award60Halvad - Charadva 0 0 022 D/C MAR-17220

W I P / Severe RoW problems76Halvad-Sadla 124 97 87 3123 D/C DEC-15220

W I P/Row problems111Hazaira (GSEC) - Mota 182 107 94 2024 D/C MAR-16220

Yet to award100Jasdan - Gondal 0 0 025 D/C MAR-17220

W I P / Severe RoW problems112Kalawad-Kangasiyali 191 154 129 5626 D/C DEC-15220

WIP37Kasor - Herang 73 71 71 3827 D/C OCT-15400

Yet to award10Keshod - Keshod 0 0 028 D/C MAR-15220

Yet to award140Keshod - Timbdi 0 0 029 D/C MAR-16220

Yet toaward120Keshod - Visavadar 0 0 030 D/C MAR-15220

Yet to award140Kosamba- Achhalia 0 0 031 D/C MAR-17400

Yet to award80LILO of SSP- Asoj & SSP -Kasor lines at Achhalia 0 0 032 D/C MAR-16400

Page 17: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

S/S

Commissioned 04/15.15LILO of Asoj - Karamsad at Mogar S/S 1533 D/C APR-15220

Yet to award40LILO of Bhatia - Kalav ad - Kangasiyali at Khambhalia 0 0 034 D/C MAR-15220

Yet to award50LILO of Chorania - Gondal at Rajkot-II 0 0 035 D/C MAR-15220

Yet to award40LILO of Chorania - Gondal at Shapar 0 0 036 D/C MAR-17220

WIP100LILO of Essar-Hadala line at Kalavad S/S 695 26 1 037 D/C MAR-16400

5LILO of Godhra -Kadana line at Lunawada38 D/C MAR-15220

Yet to award50LILO of Hadala - Sartanpar - Halvad at Tankara 0 0 039 D/C MAR-17220

Yet to award2LILO of Jambuva - Karamsad at Asodar 0 0 040 D/C MAR-17220

Yet to be awarded.116LILO of Jamnagar - Jetpur line-I at Sikka 178 0 0 041 D/C APR-15220

WIP. Case of 6 locations is pending in district court120LILO of Jamnagar - Jetpur line-II at Sikka 187 170 162 4342 D/C MAR-16220

yet to award10LILO of Jetpur - Rajkot at Metoda 0 0 043 D/C MAR-15220

Commissioned 08/15.33LILO of Kangasiyali - Nyara at Hadala 69 69 69 3344 D/C AUG-15220

AT given on 10.07.1520LILO of Karamsad - Vartej at Fedra 33 0 0 045 D/C MAR-16220

Work in Progress.60LILO of Karmsad -Vartej at Dhuvaran 152 143 94 1846 D/C DEC-15220

AT given on 10.07.201520LILO of Kasor - Vertej at Fedra 33 0 0 047 D/C MAR-16220

80LILO of Kasor-Amerli line at Fedra48 D/C MAR-16400

WIP82LILO of Kasor-Boated at Dhuvaran CCPP-III 148 145 144 5849 D/C DEC-15220

Yet to award24LILO of Morbi - Hadala at Tankara 0 0 050 D/C MAR-16220

WIP200LILO of Mundra (Adani)- Zerda line at Sankhari 45 0 0 051 D/C MAR-16400

W I P / Severe RoW problems89LILO of Mundra - Hadala at Halvad. 126 124 67 052 D/C APR-16400

17LILO of Navsari - Vav at Popada53 D/C 220

Yet to awardLILO of Navsari-Talangpore line at Utran 0 0 054 D/C APR-15220

Yet to award50LILO of Radhanpur - Mehsana at Sankhari 0 0 055 D/C MAR-15220

Yet to award1LILO of Ranasan - Karamsad at Gatrad 0 0 056 D/C MAR-16220

Yet to award10LILO of Salejada - Bhat at Kerala 0 0 057 D/C MAR-16220

WIP50LILO of Sankhari - Jangral at Sankhar 53 42 2 058 D/C MAR-16220

Yet to award50LILO of Savarkundla - Visavadar at Bagasara 0 0 059 D/C MAR-15220

Sever ROW problem. Tender reinvited for remaining portionAPR-0934LILO of Shivalkha - Nanikhakhar at Kukma 54 40 40 1860 D/C APR-15220

Commissioned 04/15.56LILO of Shivlakha - Deodhar line at PS-2 5661 D/C APR-15220

Yet to award10LILO of Tappar - Hadala at Navlakhi 0 0 062 D/C MAR-17220

Yet to award20LILO of Ukat (Th) - Achhalia at Achhalia 0 0 063 D/C MAR-15220

WIP100LILO of Vadavi-Zerda at Sankhari 45 464 D/C DEC-15400

Yet to award28LILO of Wanakbori -Soja line at Dehgam (PG) S/S 0 0 065 D/C MAR-16400

Page 18: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Ready for Commissioning 08/15.2LILO of one ckt Halvad - Morbi line to Bhimasar (PG)at Charadava S/S

5 5 5 266 D/C AUG-15220

Yet to award80LILO of one ckt Kosamba-Chorania line at Fedra 0 0 067 D/C MAR-16400

Yet to award80LILO of one ckt Wanakbori -Soja line at Prantji S/S 0 0 068 D/C MAR-17400

28LILO of one ckt of Wanakbori - Asoj at Vyankatpura(Jarod)

69 D/C 220

Commissioned 10/15.10LILO on one ckt of Jamanwada - Varsana line atUkheda S/s

18 18 18 1070 D/C OCT-15220

WIP/Severe RoW Issue664Mundra (Adani) - Zerda line 1 997 453 275 071 D/C JUN-16400

WLine terminated at 400kV Varsana S/s (2x80.26kM) on 31.03.2015 under stopgap arrangement. W I P (Severe RoW problems)

664Mundra (Adani) - Zerda line 2 956 956 950 59572 D/C DEC-15400

Yet to award290Nanikhakhar - Varsana - Chitrod 0 0 073 D/C MAR-16220

yet to award90Palitana - Talaja 0 0 074 D/C MAR-15220

Yet to award150Pipavav-Amreli 0 0 075 D/C MAR-17400

Yet to award50Pirana (PG) - Gatrad 0 0 076 D/C MAR-17220

WIP218Pooling station -Sankhari 275 217 192 5377 D/C MAR-16400

Yet to award60Prantij - Agiyol 0 0 078 D/C MAR-16220

Yet to award70Prantij - Dhansura 0 0 079 D/C MAR-16220

Commissioned 06/15.JUL-1322SSNNL PS-I - PS-2 (ACSR Zebra conductor) 38 38 38 2280 D/C JUN-15220

Will be in line with generation project which is delayed350Salaya (EPGCL generating station )-Halvad 0 0 081 D/C MAR-18400

Yet to award200Sankhari-Prantij 0 0 082 D/C MAR-17400

Generation project is delayed so this evacuation line will be in line with thegeneration project

220Shapoorji Pallonji generating station 0 0 083 D/C MAR-16400

Commissioned 08/15.157Sikka - Moti Paneli line 259 259 259 15784 D/C AUG-15220

Yet to award280Soja-Zerda 0 0 085 D/C MAR-16400

Yet to award140Suva - Achhalia 0 0 086 D/C MAR-15220

Yet to award90Termination of GPEC - Haldarva at Achhalia 0 0 087 D/C MAR-16220

WIP60Termination of one Achhalia- Jambuva line at Jarod 125 88 7088 D/C MAR-16220

DEC-0986Utran - Kosamba Line-II89 D/C 220

WIP13Vadavi - Chhatral 88 39 32 090 D/C MAR-16220

Yet to award38Vadavi - Dhanaj 0 0 091 D/C MAR-16220

Yet to award53Vadavi - Viramgam 0 0 092 D/C MAR-14220

WIP240Vadavi-Halvad 394 127 87 093 D/C DEC-15400

W I PNOV-09239Vadinar(Essar)- Amreli (Balance) 365 309 256 11394 D/C JUN-15400

Commissioned 10/15.348Varsana - Jamanwada line 565 565 565 34895 D/C OCT-15220

Commissioned 11/15.109Varsana - Mokha 230 230 230 10996 D/C NOV-15220

Yet to award60Varsana-Bhachau 0 0 097 D/C APR-16220

Page 19: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

WIP220Varsana-halvad 378 110 38 098 D/C MAY-16400

WIP120Visavadar - Timbdi 295 268 251 6499 D/C MAR-16220

Yet to award2Wanakbori S/y -Wanakbori S/y (existing) 0 0 0100 D/C APR-16400

Yet to award200Wanakbori TPS-Soja 0 0 0 0101 D/C JUN-15400

Page 20: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

HARYANA VIDYUT PRASARAN NIGAM LIMITED (HVPNL)

Line almost completed.Only stringing pending between tower location no. 46 to48 as the matter pending in Lok Adalat, Faridabad.

15A5(Faridabad) - A4(Faridabad) 33 33 33 151 D/C DEC-15220

Work awarded to Inabensa Bharat Ltd. Contractual problem.Court case.15Bhiwani - Bhiwani 0 0 0 02 D/C 220

Work awarded to Inabensa Bharat Ltd. Contractual problem.Court case.65Bhiwani - Isharwal 218 61 0 03 D/C MAR-16220

Work under progress.5Deepalpur - Sonepat 27 15 8 04 D/C DEC-15220

Due to dismal progress of contractor the firm has been blacklisted. The work wasre-awarded in January 2015 with schedule completion period of one year. Workin progress.

MAY-1342Deepalpur-Sonepat HSIIDC Rai 113 101 28 05 M/C JAN-16220

Commissioned 04/15.1Gurgaon Sector 72 (PGCIL) - Gurgaon Sector 72(HVPNL)

16 D/C APR-15220

Commissioned 04/15.7Gurgaon Sector 72 (PGCIL) - Gurgaon Sector 33(HVPNL)

19 19 19 77 D/C APR-15220

Commissioned 09/15.APR-11146Gurgaon Sector 72 - Nuh - Rangla Raipur (Ckt-I & II) 318 318 318 1468 D/C SEP-15220

Commissioned 04/15.3LILO of Badshahpur - Bhiwadi - Mau line atPanchgaon

39 D/C APR-15220

Due to dismal progress of contractor the firm was blacklisted. Contract forbalance work has been re-awarded. Work under progress.Work under progress.Firm has been requested to expedite the progress of work.

JUL-1384LILO of Chormar - Fathebad line at Hukmawali 165 132 22 010 D/C MAR-16220

Work is to be re-awarded as the contractor to whom the work was awarded hasbeen blacklisted

5LILO of Madnpur - Kunihar line at Panchkula sector-3211 D/C JUN-16220

Ready for Commissioning 08/15.JAN-112LILO of Moga-Hisar line at RGTPS Khedar 212 D/C AUG-15400

Work awarded to Inabensa Bharat Ltd. Contractual problem.Court case.44LILO of Narwana - Mund at Khatkar (Jind) 0 0 0 013 2xD/C MAR-16220

work under progressJUL-1380LILO of both Ckt of Cheeka - Durala at Sonta 128 102 70 014 D/C NOV-15220

Work yet to be award.1LILO of gurgaon Sec -72 - Sector 52 (A) at Sector 5715 D/C SEP-15220

Commissioned 05/15.91Masudpur-Samain line 182 182 182 9116 D/C MAY-15220

Commissioned 07/15.37Mau - Balwal 64 64 64 3717 D/C JUL-15220

RoW on account of Railway crossing and NHAI crossing. Approval of railwayauthorities for crossing between TL No. 47 & 48 has been accorded. Highwaycrossing is involved between TL No. 44, 45 and the matter is being pursued withthe NHAI and same will be resolved shortly.

52Palwal (Meghpur) - Meerpur Kurali 106 106 106 5318 D/C DEC-15220

The contractor has been blacklisted. Work is yet to be re-awarded.15Panchkula (PGCIL)- Panchkula Sector 3219 D/C AUG-16220

Page 21: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. (HPPTCL)

Delay FAC approval.MAR-17100Barsaini -Banala1 D/C MAR-17220

MAR-18110Dehan-Hamirpur2 D/C MAR-17220

Delay FAC approval.MAR-1754Hatkoti-Pragati Nagar3 D/C MAR-16220

OCT-154Kairan-Chamera II (PG) 20 11 7 04 D/C DEC-15220

out of 2 ckt, one ckt completed and charged on 7/2011.3 gangs working

OCT-1578Kashang - Bhaba 100 100 100 625 D/C DEC-15220

Jhangi Pooling Station yet to be awarded.Kashang - Jangi Pooling Station6 D/C 220

Delay FCA approval.35Koti-Karian7 S/C MAR-17220

.6LILO Jhakri A/Pur8 D/C MAR-14400

8LILO of Nalagarh-Baddi at Mandhala S/S9 D/C SEP-14220

Commissioned 07/15.13LILO of AD Hydro-Nalagarh at Fozal 24 24 24 1310 D/C JUL-15220

Work yet to startLILO of Kasang - Bhbaba at Tidong-I11 D/C DEC-16220

Yet to award.LILO of Parbati III - Parbati Pooling station at Sainj12 D/C APR-14400

Delay FAC approval pending for the lest three year. Stage -I clearance in July2015.

MAR-17LILO of one ckt of Nathpa Jhakri - Abdullapur at SwaraKuddu

13 D/C JUL-16400

Delay FCA approval. (Work awarded ).OCT-163Lahal -Budhil HEP14 D/C SEP-16220

Delay FCA approval.OCT-1872Lahal-Chamera15 D/C MAR-17400

.33Nalagarh -Kunihar16 S/C APR-14400

28Rauri-Kunihar17 D/C APR-14220

18Shongtong Karcham HEP - Wangtoo (Quad)18 D/C 400

MAR-1724Snail -Hatkoti (Swara Kudu)19 D/C MAR-16220

Delay FCA approval.MAR-1754Sunda-Hatkoti20 D/C DEC-16220

Page 22: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

J&K POWER DEVELOPMENT DEPARTMENT (JKPDD)

Commissioned.31Alachi - Khalsi S/S 140 140 140 311 S/C JUN-1466

Commissioned.5Chutak HEP-Gramthong -II 29 29 29 52 S/C SEP-1266

Commissioned.10Chutak HEP-Kargil-I 55 55 55 103 S/C OCT-1266

Fund yet to be tied up.80Delina - Wahipora-Kishanganga4 D/C 220

Rerouting of line and ganglas s/s droped. Leh Army S/S shall be connected withLeh S/S.

9Ganglas - Leh Army base 46 22 0 05 S/C SEP-1566

Commissioned.27Gramthong -II - Sankoo 154 154 154 276 S/C SEP-1466

Commissioned23Khangral - Mulbek -II 117 117 117 237 S/C SEP-1466

Slow progress.51Kharu S/S - Himya S/S 242 239 204 368 S/C SEP-1466

Fund yet to be tied up.12LILO of Wagoora - Mirbazar at Lassipora9 D/C 220

Progress at 2 locations have been affected due to severe RoW issue and matterin court for one location.

12LILO of one ckt of Kishanpur - New wanpoh atBaglihar HEP

17 4 1 010 D/C JAN-16400

Commissioned.25Leh (C.P.) - Kharu S/S 107 107 107 2511 S/C SEP-1466

Rerouting of line and ganglas s/s droped. Leh Army S/S shall be connected withLeh S/S.

10Leh III - Ganglas 53 29 8 212 S/C SEP-1566

Commissioned.28Mulbek-II - Kargil -I 124 124 124 2813 S/C SEP-1466

Stringing completed.The line could not be charged due to dipute betweenPSTCL and JKPDD on sharing of cost of bay at Shahpur Khadi.

MAR-0840Thein (RSD)-Hiranagar (2nd ckt) 117 117 117 4014 S/C SEP-14220

Severe RoW and Court case.APR-0848Udhampur- Gladni 165 165 165 4815 S/C SEP-14220

ROW issue at Dangarpora.Original Project provision exhausted.MAR-0960Wagoora-Budgam- Zainkote 118 103 82 1716 D/C SEP-14220

ROW issues and slow pace of execution of work by contractor due to paddycultivation.

104Wagoora-Mirbazar 177 175 170 4917 D/C SEP-14220

Slow pace of execution of work in Zainkote-Alusteng section. Original Projectcost provision exhausted, For Alusteng - Miarbazar section contract case sent toGovt for approval.

MAR-10254Zainkote-Alusteng-Mirbazar 441 410 68 018 D/C SEP-14220

Page 23: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

JHARKHAND STATE ELECTRICITY BOARD (JSEB)

Due to poor progress of working agency, the work order is cancelled.APR-0980Chaibasa -Ramchandrapur 130 109 88 181 D/C MAR-16220

Delay due to Forest Clearance, Coal Block of TUBED coal mines undertransmission corridor, ROW, non-availability of fund.

208Chatra - Latehar 320 187 82 02 D/C AUG-15220

Delay due to Forest Clearance, ROW, non- availability of fund.114Chatra - PBCMP (Barkagaon) 171 34 10 03 D/C AUG-15220

Delay due to Coal Block of Usha Martin under transmission corridor, ROW, non -availability of fund.

66Daltonganj - Garhwa 111 24 0 04 D/C MAR-15220

160Dumka - Jasidih5 D/C SEP-16220

Ready for commissioning 06/15.147Dumka - Rupnarayanpur 242 242 242 1476 D/C JUN-15220

82Essar (Latehar) - Latehar 114 98 79 217 D/C DEC-15400

ROW problems.204Govindpur - Dumka 330 266 192 08 D/C APR-16220

Critical ROW.66Hatia - Namkum (PGCIL) 125 51 39 09 D/C MAR-16220

180Jasidih - Giridih10 D/C SEP-16220

70LILO of one ckt TTPS - Govindpur at Phase-III11 D/C SEP-16220

Latehar & PTPS end S/S not finalized and forest clearance in process.218Latehar (JSEB) - PTPS 305 251 216 5412 D/C DEC-15400

PTPS end S/S not finalized and forest clearance in process.100PTPS - Bero (New Ranchi) 139 129 125 7013 D/C APR-15400

180TTPS - Govindpur 282 117 69 014 D/C MAR-16120

Page 24: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

KARNATAKA POWER TRANSMISSION CORP. LIMITED (KPTCL)

Work under progress.JUL-15186Bagalkot - Gadag 380 380 380 1011 D/C NOV-15220

Check survey approved. 5 location excavated. Work under progress.AUG-0741Beerenahalli - Thallak (Chitradurga) (Balance portion) 73 50 26 02 D/C FEB-16220

Tender invited on 7.3.2015. Detailed survey under progress.Bellary (PS) - C.N. Hally3 D/C MAR-17400

Work under progress.437Bellary (PS) - New Madhugiri (near Tumakur) 498 347 311 754 D/C DEC-16400

LOI issued on 25-Aug-15.5Bellary (TPS) - Bellary (PS)5 D/C AUG-16400

Work short closed.For balance works LOI issued to M/s Shivakumar & Co.,Belagavi on 19-11-2015.

SEP-0670Chikkodi-Kudachi 120 120 90 406 D/C DEC-15220

21/21 sections laid, 20/20 joints completed. Cable testing to be taken up by theagency for which opening of link boxes is required. BBMP permission awaited.Satisfactory restoration certificate to be obtained from BBMP /BDA/Nimhans.Balance works :1. OFC cable to be laid in 11th section (approx 510Mtrs).2. Jointing and termination of OFC cable.3. Fixing of balance Link box at JB-1.4. Testing and commissioning of cable.

11HSR Layout - Nimhans S/S 0 0 0 97 UGCable

DEC-15220

Work under progress.65Ittagi - Kudligi line 119 60 51 08 D/C DEC-15220

Tender invited on 28.4.2015.20JSW TPS - Bellary (PS)9 D/C MAR-16400

Work under progress.JAN-16106Kapnoor - Humnabad line 191 175 154 610 D/C JAN-16220

Work completed and to be commissioned.8LILO of Arasikere -Kanthenahalli at Arasikere S/S 21 21 21 1011 D/C DEC-15220

Detailed survey under progress.LILO of Both ckt of Nelamangala - Talaguppa at CNHalli

12 D/C DEC-16400

Work short closed vide O.M No. CEE/TZ/GLB/SEE(O)/AEE-3/2014-15/3830.37dtd 12.09.2014 of Chief Engineer, Elec, Transmission zone, Gulbarga . To beretendered.

1LILO of Gadag - Lingapur at Koppal 2 113 D/C MAR-15220

Work under progress.(1) ROW problems at corridor between 4 & 5 pending inJMFC, Hoskote, Additional Civil Judge(Junior division) since 9.12.10.(2)Loc 4 & 5: Case filed by party at High court vide Writ Petition: 46532-533/2012 dtd: 19.11.2012 seeking injunction.(3) Loc 4 : The petitioner has obtained stay order vide WP 32606-32607/2013from the Hon'ble High Court against the proceedings in the OS No: 253/2010 on02.09.13.(4) Loc 36 : Case No: MAG(CR)/1/13-14 at DC Court, B'lore Rural.Reserved forOrders.Being pursued.

SEP-0726LILO of Hoody-Kolar at Hoskote 55 35 31 014 D/C MAR-16220

Work under progress.JUL-1516LILO of Hubli - Lingapur 2nd Ckt at Gadag15 D/C onM/C

NOV-15220

Commissioned 06/15.33LILO of RTPS - Btps at YTPS 43 43 43 3316 D/C JUN-15400

Work under progress.6LILO of RTPS - Lingasugur S/C line at Mallat (Manvi) 13 12 10 017 D/C DEC-15220

Page 25: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Forest clearance required for 3.836 hectares in locations 25,34 &35. Stage-Iapproval received on 20.04.11.NPV & compensatory afforestation charges of Rs.28,01,923/- paid on June-2011.Additional NPV & compensatory afforestation charges of Rs.4,04,973/-paid on 01.10.2011.Demarkation of the line corridor in the forest land done on01.04.2013.Letter addressed on 01.04.2013 to forest authorities to process forstage-II. Payment of Rs.7,61,404 made on 06.11.2014 to KFDC, Chikkamagalurfor stage-II clearance. The file was forwarded to DCF, Hassan on 14.11.2014and from there to CCF, Hassan on 08.12.2014 and then to APCCF , AranyaBhavan, Bengaluru on 23.12.2014.Intimation received from the Principal Chief Conservator of forest, Hassan toaccord Stage-II clearance in view of clearing the required payments by KPTCLon 20.04.2015.Stage-II clearance approval awaited.

FEB-0835LILO of Shimoga - Mysore at Dandiganahally 70 62 61 2218 D/C FEB-16220

Work under progress. (1) Local ROW problems atlocations: (i)9,10,14A,16,- being pursued.(2) DC COURT:For corridor 8-9 & 10-11: Case filed in DC court on 27.05.2013. Being pursued.(ii) Loc 16: Case filed at DC Court on 26.11.2014. Being pursued.

JUN-119LILO of Somanahalli - Malur at Vikas Tech Park 32 27 23 019 D/C DEC-15220

Work under progress.

Railway crossing :There is a Tumkur -Rayadurga railway corridor problem.Correspondence made with the railway authorities. A meeting was held byDeputy Commissioner, Tumkur with Railway authorities and KPTCL and directedto shift the line from the railway track. (loc No 2 to 5, Loc No 30 to 37, Loc No 62to 81). Total 9 towers to be deviated (Loc 63,64,65,75,76,77,78,80 erected to bedeviated and Loc 79 concreted to be deviated). Revised survey submitted byagency on 23.08.14. Cost implication and revised detailed survey is underapproval.

120Madhugiri - Pavagada 214 155 140 1820 D/C MAR-16220

Work under progress.SEP-0915Shanthigrama - B4 line ( near Hedanahalli limits) 34 34 32 921 D/C OCT-15220

Malur-Kolar line charged (42 Ckm). The line from Malur end upto Loc 137charged (68.98 Ckm).The line from Somanahalli end upto Loc 55 charged (23.64Ckm). Total line charged 134.62 Ckm. Balance work under progress.Casepending in High Court: (i) At Loc 59 (for stub concreting) : Case disposed.(ii)Loc 84,85,86,88 & 89: Case filed by KPTCL in DC Court on 27.01.2014. Beingpursued.(iii) Loc 84,85,86,88 & 89 : Case filed by party in Court of Junior Civil Judge ,Bangalore Rural district on 11.02.2014. Being pursued.(iv) Loc 135,135A,135B, 135C & 136 : case filed in High Court by party (IndiaInternational School) on 19.06.2013. Being pursued.

MAR-08180Somanahalli - Malur - Kolar 272 267 267 14022 D/C MAR-16220

Line work short closed vide OM No CEE/TZB/SEE(O)/AE-3/15-16/925-31 dated:12.08.2015

23Somananahalli Malur I & II lines - Jigani 34 6 4 023 D/C MAR-16220

Page 26: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Due to severe ROW problems for the earlier awarded line routes, new proposalof converting SC Singarpet line to MC line from crossing point of Somanahalli-Malur line to Yerandanahalli S/s & DC line from Bommasandra I/A to Jigani s/sin the KIADB road median has been submitted. Estimate for MC line submitted toP&C on 25.10.2014 and for UG cable on 08.01.2015. DPR approved for 220kVMC line on 01.06.2015.

Detailed survey under progress.Termination of Nelamangala - Talaguppa at CN Halli24 D/C DEC-16400

220 kV DC line from 220 kV Tubinakere S/s to Kothipura S/s :(1) (i) ROWproblems pending in JMFC Ramanagara for- (a) Loc 81 since 2009(2)ROW problems pending in DC Court Ramanagar for (a) Loc 133: Case filedon 24-08-2011.Reserved for orders on 09.02.2016.(3)ROW problems at locations 208: being pursued locally.

220-66 kV MC line from 220 kV Kothipura to Bidadi S/s:(1) ROW problems pending in DC Court Ramanagar for Loc 15 : Case filed on19-07-2012.(2) ROW problems to be solved locally at 8 locations 2,3,4,4A,5,6,33 & 77

JUN-09137Tubinakere- Kothipura 278 278 257 8725 D/C MAR-16220

Work under progress.39Vajamangala - Kadakola 55 49 45 026 D/C MAR-16220

Varahi-Khemar 150 Ckm (75 km route length) charged on 22.07.2010. Work of220 kV line completed. Inspection report with observations received from CEIG,B'lore vide Lr.No: CEIG/ACEI/EI-2/AEI-4/24043/15-16 Dtd: 18.11.2015

ROW problem pending at Civil court :(i) For Corridor between 2-3A-2A, case filed in Civil Judge ( Jr. Division)Mangalore, Interim order received against KPTCL on 24.01.2014. Miscellaneousappeal filed at the Court of Civi Judge (Sr. Division), Mangalore, MA no. 11/2014.Being pursued.

JUL-08245Varahi -Khemar- Kavoor in the existing 110 kVcorridor(balance portion)

420 420 420 24527 D/C onM/C

MAR-16220

Work under progress.JAN-1638Vasanthanarasapura - Antharasanahally 97 43 1 028 D/C JUL-16220

Work under progress.JUL-1689Vasanthanarasapura - Madhugiri 209 0 0 029 D/C JUL-16220

Work under progress.JUL-1525Yelahanka - Chikkabettahalli 42 41 36 230 M/C DEC-15220

LOI issued on 19-Oct-15. Work to be taken up.284Yermarus TPS - Bellary Pooling Station31 D/C 400

Estimate under preparation.Yermarus TPS - Gulbarga32 D/C DEC-15400

Page 27: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

KERALA STATE ELECTRICITY BOARD (KSEB)

ATS of Pallivasal Extension HEP. Work is yet to start.LILO of Idukki-Udumalpet at Pallivasal HEP 5 0 0 01 D/C MAR-16220

ATS of Thottiar HEP.May be deleted, as the work is not targeted in the Annual Plan of 2015-16.

LILO of Ldukki - Kozikode at Kodakpara2 D/C 220

Re-tendering in Dec,1557Pothencode - Kattakkada 108 103 72 03 D/C MAR-16220

ATS of Thottiar HEP. May be deleted, as the work is not targeted in the AnnualPlan of 2015-16.

Thottiyar - Kodakpara4 D/C MAR-17220

Page 28: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

M.P. POWER TRANSMISSION CORPORATION LIMITED (MPPTCL)

Work under progress.About 12% work completed.95Ashta - Shajapur 72 17 13 321 D/C MAR-16220

80Dada Dhuniwale TPP - Moondi Pooling Point2 D/C 400

Commissioned 06/15.158Damoh - Tikamgarh (2nd Ckt) 1583 D/C JUN-15220

180Handia - Ashta(2nd stage)4 D/C 400

160Julwania - Kukshi5 D/C 220

220Katni - Damoh6 D/C 220

Work under progress.8LILO of Bina - Guna at Ashoknagar 14 14 13 07 D/C DEC-15220

30LILO of Bhilai - Seoni at Balaghat / Kirnapur8 D/C 400

Commissioned 04/15.2LILO of Bina - Gwalior at Datia 29 D/C APR-15220

40LILO of Both ckt of Badod - Ujjain at Ujjain10 D/C 220

40LILO of Damoh - Bhopal at Sagar11 D/C 400

40LILO of Handia - Barwaha at Handia12 D/C 220

40LILO of Indira Sagar - Satpura at Handia13 D/C 400

40LILO of Indore - Itarsi at Handia14 D/C 400

20LILO of Indore-II - Ashta at Shankargarh15 D/C 220

4LILO of Jabalpur - Amarkantak at Gorabazar16 D/C 220

.20LILO of Khandwa (PGCIL) - Rajgarh at Chhegaon17 D/C 400

40LILO of Nagda - Rajgarh at Badnawar18 D/C 400

40LILO of Ratlam - Badnagar at Badnawar19 D/C 220

Ready for Commissioning 06/15.10LILO of Rewa - Ton at Sirmour 20 20 20 1020 D/C JUN-15220

8LILO of both ckt Indore - Pithampur at Indore21 D/C 220

40LILO of both ckt Nagda - Ujjain at Ujjain22 D/C 220

40LILO of both ckt of Ratlam - Badnagar at Badnawar23 D/C 220

Work under progress.About 45% work completed.10LILO of one ckt of Bina - Gwalior at Datia 7 6 5 024 D/C MAR-16220

40LILO of one ckt Bhopal - Ashta at Mugalia Chhap.25 D/C 220

2LILO of one ckt of Bansagar (Tons) - Satna at Sirmour26 D/C 220

10LILO of one ckt of Bina - Sagar at Bina27 D/C 220

13LILO of one ckt of Indore - Barwaha at Simrol28 D/C 220

20LILO of one ckt of Khandwa (PGCIL) - Rajgarh(PGCIL) at Chhegaon

29 D/C 400

4LILO of one ckt of Pithampur - Rajgarh (PGCIL) atDhar

30 D/C 220

.LILO of one ckt of Vindhychal - Satna at Nigrie31 D/C 400

6LILO of second ckt of Auraiya - Malanpur at Mehgaon32 D/C 220

Page 29: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

10LILO of second ckt of Damoh - Tikamgarh at Damoh 0 0 0 033 D/C 220

Double entrypreviously as Maheshwar - Rajgarh

230Maheshwar (HEP) - Rajgarh (Dhar)34 D/C 220

240Moondi Pooling Point - Handia35 D/C 400

80Morena - Malapur36 D/C 220

Double entrypreviously as Nagda - Ujjain

150Nagda - Ujjain line37 D/C 400

Nigri TPP - Satna38 D/C 400

150Pithampur - Badnawar DCDS39 D/C 400

60Pithampur - Gandhinagar40 D/C 220

280Pithampur - Moondi Pooling Point41 D/C 400

70REVA TPP - Moondi Pooling Point42 D/C 400

160Satna - Chhatarpur (2nd ckt) 1543 S/C MAR-16220

.40Shri Singaji TPP - Moondi Pooling Point44 D/C 400

90Ujjain - Dewas45 D/C 220

Page 30: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. (MSETCL)

Commissioned 04/15.53Ahmednagar - Jeur (Kaudgaon) 531 S/C APR-15220

Agency is not ready to carry out the work.Order awaited for U/G cable (3.7 KM)

44Ambazari - Mankapur 37 0 0 02 M/C MAR-16220

line is to be deleted. As line is not possible due to major ROW problem as linepasseing through N.A. and defence land only.

184Ambazari - New Buttibori-II 0 0 0 03 M/C APR-16220

Arbitral award- Group C. Tender being processed for balance work.104Apatapa - Anjangaon 172 77 65 04 D/C MAR-16220

Commissioned 05/15.5Aurangabad (Ektuni - III) - Aurangabad -II(Thaptitanda) Ckt-II

55 S/C MAY-15400

Commissioned 04/15.87Babhaleshwar - Jeur (Kaudgaon) 876 S/C APR-15220

Forest Involved: Nashik Zone - 32 Hec (27 locations)Vashi Zone - 116 hec (60 locations) Forest Proposal pending at CCF, Nashik,Pune & Thane.ROW: (Nasik Zone) For 39 locations: Cases filed. Hon. Collector Pune delegatedthe powers to SDO Revenue Manchar.Loc. No. 33 - Due to GMRT issue and intervene of MLA Junnar, SDO RevenueManchar has instructed that unless this issue is resolved, orders will not beissued.(Vashi Zone) ROW cases for 27 locations pending at Collector, Thane office.Rly Crossing: 100KV Railway crossing involved for total 4 Nos. Loc(Mumbai-Nashik central railway near Vashind, Tadavali):-On 12.08.2015 reminder letter given to Sr. DEN, CST w/r to track crossingapproval on dtd. 12.08.2015.PTCC: Proposal forwarded to BSNL, Mumbai. Telecom details awaited.

447Babhaleshwar - Kudus 708 547 481 1737 D/C MAR-16400

Work stopped due to severe ROW problems.MAR-0753Boisar (PG)-Wada 211 173 165 288 S/C onD/C

MAR-16220

Forest permission received on 14.01.2013 for SGNP(81.42 Hec) and on17.09.2012 for teritorial forest(117.28 Hec).ROW at Loc. No. 9/0: Case pending at Collector Palghar.

DEC-11329Boisar II-Borivali 261 260 253 3239 M/C MAR-16220

Work in Progress.24Bridgestone-II - Chakan-II 27 25 15 010 M/C MAR-16220

Work in progress.40Chandrapur II - MIDC - Ballarshah 66 66 60 311 D/C MAR-16220

ROW cases to be filed for 19 locations.For 16 locations. Order passed and police protection is needed.

40Chandrapur II - Tadali 89 65 48 1612 D/C MAR-16220

Commissioned 06/15.30Chinchwad - Apta 3013 M/C JUN-15220

Collector order received for balance foundations. Police Protection can be madeavailable, agency is not deploying the sufficient required manpower.

87Eklahare - Pimpalgaon 158 135 119 1214 D/C MAR-16220

Commissioned 10/15.MAR-1186Ghatodi - Hingoli line 269 269 269 8615 S/C OCT-15220

Forest: 1] Combined proposal for both (Package I, Pacage II) submitted byEHVCD-2. Compliance yet to be submitted .2] Forest proposal initiated as per Ltr. No. EE/EHV/Constn /Dn-II/PN/1183 dt.25/6/13. Final forest proposal submitted online in lock mode on dt 19.03.15 tonodal officer Nagpur. Hard copies are submitted to forest authority vide T.O.Lr.No. 562 dt 13.04.15

93Jejuri - Hinjewadi - I 146 105 94 3016 D/C MAR-16400

Page 31: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Highway Crossing:Involved however, Loc No. are not identified as survey ispending due to ROW.Forest1] Combined proposal for both (Package I, Pacage II) submitted byEHVCD-2. Compliance yet to be submitted .2] Forest proposal initiated as per Ltr. No. EE/EHV/Constn /Dn-II/PN/1183 dt.25/6/13. Final forest proposal submitted online in lock mode on dt 19.03.15 tonodal officer Nagpur. Hard copies are submitted to forest authority vide T.O.Lr.No. 562 dt 13.04.15ROW: 4 Nos of location order received, police protection needed.

114Jejuri - Hinjewadi -II 127 88 76 1617 D/C MAR-16400

ROW: For 18 locations, Cases filed at Collector office, Nagpur. Hearing underprocess.

170Kalmeshwar - Warud 277 159 72 018 D/C MAR-16220

Forest permission received on 14.01.2013 for SGNP(81.42 Hec) and on17.09.2012 for teritorial forest(117.28 Hec).

68Kalwa-Borivali 52 52 20 1619 M/C MAR-16220

Commissioned 10/1547Khanapur length tap to Vita - Lamboti line 4720 D/C OCT-15220

L.No. 2133 dt. 13.11.13 has given to agency to start the work. But agency hasgiven a letter for cancellation of work on 13.11.13.

42Koradi II - Ambazari 27 0 0 021 D/C onM/C

MAR-16220

Forest Involved: 10.36 Ha Received FRA certificate.After compliances proposal along with FRA again submitted from Nodal to GoMon dt: 05.05.2015.ROW: Cases filed for 17 locations at Collector office, Nagpur.13 no. of cases closed for orders on Dt: 01.10.15. Orders yet to be received.Agency stopped work since 24.01.2014.National Highway (NH-69) crossing: Reminder letter given to NHAI regardingapproval of long pending cases vide no:3162 Dt:26.08.15.

MAR-11106Koradi II - Butibori 189 133 117 2222 D/C onM/C

MAR-16220

Forest: 16.9392 Ha (Wardha :3.85 & Nagpur:13.0892 )In-Principal approval received on dt: 04.03.14. Permission for tree cutting andwork commencement letter received from CCF, Nagpur vide letter no: 3831 Dt:09.10.15Compliance for Stage-I submitted and final approval awaited.ROW: 2 locations (Loc. No. 30/0, 16/0) Closed for order on Dt:01.10.15. Orderyet to be received.National Highway (NH-69) crossing: Reminder letter given to NHAI regardingapproval of long pending cases vide no:3162 Dt:26.08.15.

APR-11239Koradi TPS - Wardha 336 336 336 23123 D/C MAR-16400

Forest area involved 4.122 Ha.In-principal approval received on Dt: 11.09.15.Permission for tree falling and work commencement letter awaited from CCF,Nagpur.ROW: Work stopped. Police protection required.

DEC-1329Koradi TPS-New Khaparhkeda 72 71 70 2224 D/C MAR-16220

Forest: Area involved 0.5523 Ha Proposal Submitted to DCF Nagpur vide ltr no.1159 dt: 06.05.2015.Approved on dt.30.10.15ROW: (Total 15 locations) 06 no. cases closed for orders on Dt:15.10.15. Ordersyet to be received.PTCC:Proposal submitted vide l.no:1284 Dt: 10.07.15 and forwarded byCorporate Office, Mumbai to PTCC Office vide Ltr No. 10038 Dtd 29.07.2015.

239Koradi-II - Koradi-III 111 81 63 225 D/C MAR-16400

Page 32: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Telecom & railway details awaited.Highway: In principle approval received on dt. 13.10.15.Commissioned 06/15.5LILO (Tapping) of Dhule - Malegaon at Sayne 18 18 18 526 S/C JUN-15220

Work in progress.ROW at total 03 locations (Loc. No. 79, 67-68). Cases filed at collector office on06.07.2015.

62LILO of Amravati - Badnera line at Nandgaon Peth. 99 99 99 4927 D/C MAR-16220

ROW: For total 13 locations order is awaited.PTCC: Order awaited.

14LILO of Bhugaon - Pusad at Wardha (PG) 33 14 13 028 D/C MAR-16220

ROW: Nil at present.50LILO of Bhugaon - Warora-I at Warora 42 22 12 229 D/C MAR-16220

Ready for Commissioning 08/15.1LILO of Chinchwad - Phursungi at Kondhwa 130 D/C AUG-15220

Commissioned 07/15.8LILO of Kandalgaon - Lonand at Lonand MIDC 11 11 11 831 D/C JUL-15220

Work in progress.ROW: order passed for Loc. No. 2, 42.Continuous persuance with District Collector, S. P. Kolhapur, SDM, Tahasildar,Kagal & Murgud police station.Very poor response / follow up from agency M/s Jyoti.

26LILO of Kolhapur - Sawantwadi at Mudhaltitta 44 42 39 832 D/C MAR-16220

Commissioned 08/15.20LILO of Mhaisal - Jath at Mendhegiri S/S (Ckt-I) 2033 D/C AUG-15220

Commissioned 11/15.11LILO of Sawangi - Bhokardan at Phulambri 20 20 20 1134 D/C NOV-15220

Forest land involved in the route at Loc. No. 16A, proposal yet to be approved.The proposal is returned by Nodal Officer, Nagpur to Dahanu forest dn. forcompliances of Dwellers Act. Obtaining of NOC under Dwellers Act is in processfrom concerned Grampanchayats.WOrk stopped due to severe ROW problem.

MAR-0716LILO of Tarapur-Borivli at Boisar II 15 15 12 1135 D/C MAR-16220

Commissioned 04/15.26LILO of Waluj Bahaleshwar - Deogaon Rangari S/S 2636 D/C APR-15220

ROW: Nil at Present.50LILO of Warora - Wardha at Warora 42 22 12 237 D/C MAR-16220

MAY-12154LILO of both ckt Bhusawal II - Aurangabad I atAurangabad-II (Ckt-II)

38 D/C NOV-15400

.LILO of both ckt Parli (GCR) - Beed at Parli39 D/C 220

Commissioned 05/15.97LILO point of IEPL to LILO point of Warora-Wardhaline

9740 D/C MAY-15400

Work in progress.97Malegaon - Kalwan 171 156 128 041 D/C MAR-16220

Work is carried out by M/s JSW under ORC. Fresh tenderisation is held up dueto non receipt of assurance payment from ISPAT.

30Nagothane - Wadkhal 93 56 44 042 D/C MAR-16220

Slow work by agency. Forest NOC received.73Nanded - Bhokar 122 122 115 6943 D/C MAR-16220

Arbitral award- Group C. Tender for balance work to be refloated136Nanded - Krishnoor 51 28 0 044 M/C MAR-16220

Arbitral award- Group C. Tender for balance work to be refloated.32Nanded - Narsi 50 22 0 045 D/C MAR-16220

Ready for Commissioning 08/15.30Nanded - Waghala 52 51 51 3046 D/C AUG-15220

Work yet to be started by MSETCL.Nasik TPP - Nasik (MSETCL)47 D/C MAR-15400

Commissioned 11/15.MAR-11258New Bhusawal - Chalisgaon 431 431 431 25848 D/C NOV-15220

ROW: Cases filed for 8 locations at Add. collector Jawhar office.Forest land confirmation is awaited from DCF Dahanu, Forest department.PTCC:Proposal forwarded to BSNL, Mumbai. Telecom details awaited.

30Padghe - Tarapur 12 3 0 049 D/C MAR-16400

Page 33: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Commissioned 09/15.134Sawangi - Bhokardhan 224 224 224 13450 D/C SEP-15220

Commissioned 06/15.37Shedyal - Jath line 3751 D/C JUN-15220

Commissioned 06/15.114Shivajinagar - Malegaon 11452 S/C JUN-15220

Commissioned 06/15.96Shivajinagar - Satana 9653 S/C JUN-15220

Commissioned 04/15.1Tapping on Lonand Kandalgaon for Lonand MIDC 154 S/C APR-15220

ROW at total 15 locations. Cases filed at Collector office on dt. 01.10.2015.32Uppalwadi - Mankapur 28 1 0 055 M/C MAR-16220

Work not started by agency.RAILWAY-Loc. no. 3&4& Loc. no. 21 & 22Proposal yet to be prepared by Agency. Regular follow up being done.

54Uppalwadi - New Pardi 45 0 0 056 M/C MAR-16220

Work in progress.ROW: Cases to be filed for 6 locations.For 28 locations, Cases filed at Collector office. Order is awaited.

322Wardha (PGCIL) - Ghatodi 547 345 204 057 D/C MAR-16220

ROW: Total 9 locations - Order is awaited.165Warora - Wardha 289 260 250 9858 D/C MAR-16220

Page 34: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

MEGHALAYA ENERGY CORP. LTD. (MeECL)

No issues of forest clearance and no court cases. Work is under progress.17Killing (Byrnihat)-EPIP-I 19 19 19 91 M/C DEC-15132

Work completed and line charged on 28.01.2014.5LILO of Agia - Nangal at Mendipathar 9 9 9 52 D/C JAN-14132

No issue on forest clearance and no court cases.Work held up due to ROWproblem. The PHED,GOMe has complained and filed and FIR against Loc No. 3to 8. Overall status is 90% completed.

10LILO of Mawlai - Cherra at Mawngap. 16 15 15 53 D/C MAR-16132

Work completed & commissioned on 20.11.2015.1LILO of NEHU - Khliehriat line at Mustem 4 4 4 14 D/C NOV-15132

No issues on forest clearance. Materials procurement is in process.6LILO of NEIGRIHMS - Khliehriat at Lad Nongkrem 9 0 0 05 D/C JUL-16132

Land for the substation has been identified and procurement of the same is inprogress.

20LILO of Rongkhon - Ampati at Praharinagar 34 0 0 06 D/C DEC-16132

Commissioned 05/15.4LILO of one ckt Palatana - Bongaigaon at Byrnihat line 10 10 10 47 D/C MAY-15400

Work completed and line charged on 21.12.2011.66Mawngap - Sumer 102 102 102 668 D/C DEC-11132

Work Completed and line charged on 06.08.2013.92Nangalbibra - Agia 316 316 316 929 S/C AUG-13132

No issues of forest clearance. Survey works completed. Re-survey done due toconstruction of a new building in the corridor of the approved profile survey &due to crossing of the 132kV D/C Killing-EPIP-II line. Material procurement isunder process. Inspection of column & beams done on 31.03.2015.

New Umtru - Umtru HEP10 S/C MAR-16132

No issues of forest clearance. Survey works completed. Re-survey done due toconstruction of a new building in the corridor of the approved profile survey &due to crossing of the 132kV D/C Killing-EPIP-II line. Material procurement isunder process. Inspection of column & beams done on 31.03.2015.

6New Umtru HEP - Norbong (EPIP-II) 9 0 0 011 D/C MAR-16132

No issues on forest clearance and no court cases. ROW problem resolved. Workdelayed presently due to fund constraint.

33Rongkhon S/S - Ampati 102 97 86 1212 D/C MAR-16132

Page 35: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

ORISSA POWER TRANSMISSION CORPORATION LTD. (OPTCL)

Commissioned 06/15. (By passing Pandiabil S/S)APR-1545Atri - Pandiabil 88 88 88 451 D/C JUN-15220

Work for river bed piling was held up due to flood in the river.However work hasalready resumed

DEC-0920Bidanasi -Cuttack 38 31 31 52 D/C MAR-16220

Forest clearance pending with DFO Bolangir & Kalahandi North for Demarcationof forest land and enumeration of trees coming in the corridor of 220 kV Kesinga-Bolangir D/C line.

JAN-15160Bolangir - Kesinga 315 189 0 03 D/C SEP-16220

Re-routing required due to acute ROW proble. Survey completed. Locationdetails is being worked out

64Cuttack (OPTCL) - Pratapsasan4 D/C MAR-16220

One circuit from lapanga to Meramundali(Part of Ib-Meramundali line) wascharged in the month of October 2014. But immediately after charging theft ofconductot taken place for which th e line is again under restoration and theportion from Lapanga to Meramundali is expected to be charged in the month ofDecember 2015.After charging of this portion the balace portion from Lapanga toIb will be taken up through other mode of execution

470Ib-Meramundali 625 625 625 4705 D/C DEC-15220

Repeated. already at sl. 6. This may be deleted.17Jayanagar (OPTCL) - Jayanagar (PGCIL) 37 0 0 06 D/C MAR-16220

16LILO of (Existing) Budhipadar-Burla at Lapanga 19 19 19 67 D/C DEC-15220

The survey work is in progress8LILO of (Existing) Bhanjanagar - Meramundali atNarasinghpur

8 D/C SEP-16220

Work offloaded from Contractors scope.SEP-1529LILO of (Existing) Budhipadar - Tarkera atKuanrmunda.

9 D/C OCT-15220

Survey in progress. Location details is being worked out. It is decided to deferthe project right now.

DEC-1679LILO of Duburi - Balasore at Dhamara10 D/C DEC-16220

The line work will be taken through other modalities. Survey in progress.However S/s order already placed on M/s Alsthom

JUN-1311LILO of IB- Thermal-Meramandali at Lapanga11 D/C FEB-16400

Work order just placed for S/s. The line work tendering not done. The completionschedule mentioned is for S/s.

AUG-164LILO of Indravati - Theruvali at Kasipur12 D/C AUG-16220

Work order just placed for S/s. The line work tendering not done. The completionschedule mentioned is for S/s.

MAR-1710LILO of Katapalli - Bolangir at Bargarh (New)13 D/C MAR-17220

The project is likely to be taken up on a later date. Tendering not doneMAR-1710LILO of Meramundali - Duburi at Dhenkanal (New)14 D/C MAR-17220

Work in progress.7LILO of Narendrapur - Mendhasal at Attri (OldKaradagadia)

8 8 7 015 D/C DEC-15220

Work is deffered. May be deleted for now.36LILO of Rengali - TTPS at Chendipada16 D/C MAR-16220

All foundation work completed. Since the balance work of S/s is re-tenderedeven though line is completed total project can not be completed.However linework is taken up through OPTCL empanelled contractor

6LILO of Rengali - Tarkera at Bonai 17 17 0 017 D/C MAR-16220

Work order just placed for S/s. The line work tendering not done. The completionschedule mentioned is for S/s.

DEC-1728LILO of one ckt of Indravati - Thervali line at Jaypatna18 D/C DEC-17220

The project is likely to be taken up on a later date. Tendering not doneJUN-1360LILO of one ckt of Rengali - Tarkera at Deogarh19 D/C MAR-17220

The project is not taken up right now.May be deleted.44Lapanga (PGCIL) - Sundergarh.20 D/C MAR-15400

There is no such project under OPTCL. May be deleted62Malibrahmani - Angul 108 100 80 2021 D/C MAR-16400

Ready for Commissioning 08/15.192Meramundali-Duburi (1st Ckt) 279 279 279 19222 D/C AUG-15400

Page 36: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Commissioned 07/15. (By passing Pandiabil S/S ).92Puri (Samangra) - Pandiabil 155 155 155 9223 D/C JUL-15220

Page 37: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

POWER AND ELECTRICITY DEPARTMENT, MIZORAM (P&ED Mizo)

5LILO of Zemabawk - W.Phaileng at Sihhmui 0 0 01 S/C DEC-13132

Turial HEP - Aizawl2 S/C MAR-14132

Page 38: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. (PTCUL)

DPR prepared. DPR submission to funding agency is in progress.146Almora-Pithoragarh 0 0 0 01 D/C JUN-16220

Construction of line as per Connectivity Schedule of Generators in YamunaValley.

94Arakot -Mori and LILO of Arakot -Mori at Hanol Tuni 0 0 0 02 D/C MAR-18220

Construction of line as per Connectivity Schedule of Generatiors in YamunaValley.

52Devsari-Karanprayag 0 0 0 03 D/C NOV-17220

Construction of line as per Connectivity Schedule of Generators in YamunaValley.

76Jakhol -Sankri -Mori and LILO of Jakhol -Sankri -Moriat Natwar Mori

0 0 0 04 D/C MAR-18220

Contract has been awarded on 06.05.11 to M/s TATA Project Ltd., contracteffective date is 14.10.11 and GMVN has not given the permission to cross theAuli Ropeway, hence crossing by underground cable is proposed at Joshimath.Land sliding zone being encountered at village Malli Tangri and Talli Tangri thesurvey and forest case yet to be completed. Forest Case of 51.3 Hect. is underpreparation. Total Progress 6%.

40Joshimath - Kunwari Pass (Pipalkoti)5 D/C JUN-18220

Retendering is under Process.184Kuwari Pass (Pipalkoti)-Karanprayag -Srinagar 0 0 0 06 D/C JUN-16400

Contract has been awarded on 06.05.11 to M/s TATA Project Ltd. contracteffective date is 03.09.11 and will be taken after award of 400 KV Pipalkoti S/s.Total Progress 11%.

2LILO of Muzaffarnagar - Vishnu Prayag at KuwariPass (Pipalkoti)

6 0 0 07 D/C DEC-15400

Construction of line as per Schedule of construction of Singoli HEP and to beconstructed by L&T.

5LILO of Baramwari - Srinagar at Singoli Bhatwari 0 0 0 08 D/C OCT-16220

Tendering is under process.12LILO of Kashipur - Pantnagar line at Jaffarpur9 D/C JUN-15220

The work at Pala Maneri HEP stopped as per GOI order.10LILO of Loharinagpala - Koteshwar at Pala - Maneri 0 0 0 010 D/C 400

Construction of line as per connectivity schedule of generatiors in Yamuna Valley10LILO of Mori - Dehradun line at Nogaon11 D/C MAR-18220

Construction of line as per Schedule of construction of Langrasu.16LILO of Nandprayag -Karanprayag at Langrasu 0 0 0 012 D/C NOV-17220

Tendering is under process.1LILO of Rishikesh-Dehradun at Harrawala 0 0 0 013 D/C MAR-15220

10LILO of Roshanabad - Puhana line at Imlekhera(Pirankaliyar)

14 D/C MAR-16220

LoA is to be issued.10LILO of Roshnabad -Puhana at Pirankaliyar S/S 0 0 0 015 D/C DEC-16220

Tender has been floated.70LILO of Vyasi HEP - Dehradun at Dehradun (PG) S/S 0 0 0 016 D/C APR-16220

Regarding Forest land Transfer proposal nodal officer Dehradun raised queriesvide letter no 3042 dated 01-06-2013. Reply of the same is being done. Totalprogress 13%

24Lata Tapovan- Joshimath 36 0 0 017 D/C DEC-15220

The work at Loharinagpala HEP stopped as per GOI order.180Loharinagpala-Koteshwar line 0 0 0 018 D/C 400

Construction of line as per Connectivity Schedule of Generators in YamunaValley.

200Mori -Dehradun 0 0 0 019 D/C MAR-18220

Forest approval granted on 02.04.2013.Tender scrapped retendering is underprogress

182Rudrapur(Brahmwani) - Ghansali-Srinagar line 248 0 0 020 D/C DEC-16220

28Srinagar HEP - Sringar 400 kV S/S. 39 9 0 021 D/C DEC-15400

Survey work is in progress in the alternative route proposed by M//s304Sringar - Kashipur 0 0 0 022 D/C DEC-18400

Page 39: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

cobra.The go ahead was issued through this alternate route on dated24/12/2014.detailed surey of 189 Km completed.Forest case preparation inprogress and profile potting in progress

Tower foundation-1/21 and Tower erection-0/21.Total progress-11%12Twin Zebra - Dehradun (PGCIL) 21 1 023 D/C MAR-16220

Contract has been awarded on 06.05.11 to M/s TATA Project Ltd. contracteffective date is 03.09.11 Forest case prepared for 43.694 Hect. and submittedto DFO Joshimath/ DM Chamoli. NOC from 04 Nos. village panchyat NaurakhAgthalla, Tangri Talli and Tangri Malli is pending. Matter is being pursuedGOU/District Administration.

40Vishnugad - Kuwari Pass (Pipalkoti) 62 0 0 024 D/C DEC-15400

Page 40: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

PUNJAB STATE TRANSMISSION CORPORATION LIMITED (PSTCL)

Work is in progress.71Bajakhana - Bagha Purana 103 103 103 641 D/C JAN-16220

1. Work is in progress.2. Forest and railway case approved.

33Balchak - Naraingranth 58 58 56 182 D/C JAN-16220

Commissioned 05/15.23Bhatinda - Mukatsar (2nd CKt) 233 D/C MAY-15220

Work is in progress.80Goindwal Sahib - Bottianwala 201 152 123 04 D/C JUN-16220

Work in progress.55Goindwal Sahib - Chola Sahib 92 92 92 555 D/C JAN-16220

Work is in progress. Forest case cleared. Railway case pending.ROW problem at PTU Jalandhar.

29Kanjali - Jalandhar 54 53 326 D/C MAR-16220

Commissioned 04/15.12LILO of Both Ckt Malerkotla - Barnala at Sandhaur 25 25 25 127 D/C APR-15220

Commissioned 04/15.13LILO of Both Ckt Malerkotla - Pakhowal at Sandhaur 25 25 25 138 D/C APR-15220

Commissioned 07/15.29LILO of Dhuri - Bangan at Chhajali (Loop in) 299 D/C JUL-15220

Work is in progress.Shifting of PSPCL 11 KV lines involved.48LILO of Ferozepur - Talwandi Bhai line at Sadiq 80 80 79 4810 D/C JAN-16220

Work is in progress. Forest case sent to sector-31 for approval21LILO of GGSSTP - Jsmsher at Jadla 41 21 19 611 D/C MAR-16220

Work is in progress.21LILO of Ganguwal - Mohali at Majra 40 40 35 1512 D/C JAN-16220

Work is in progress. Forest case approved by DFO Bhatinda and DFOMukutasar, case submitted to MOEF, sector-32, Chandigarh.

50LILO of Malout - GNDTP Bhatinda at Badal 82 78 52 313 D/C MAY-16220

Loop out work completed.Further work is in progress.68LILO of Patial - Mondi Gobindgarh at Rajpura 109 109 109 6714 D/C FEB-16220

Work is in progress.In principle approval for forest case given by PCCF, Sector-68, Chandigarh.Railway clearance not required.

12LILO of one ckt of Ganguwal - Gobindgarh-II at Bhari 13 13 9 115 D/C MAR-16220

Work is in progress.28Ludhiana - Doraha 95 95 78 1316 D/C MAR-16220

Work is in progress. Forest & Railway cases pending101Makhu - Algaon 159 47 42 017 D/C JUN-16220

Work is in progress.Work also exist at sr. no 7.92Makhu - Rashiana 146 121 73 2618 D/C MAR-16220

Also exist at Sr.no.28. Work is in progress.60Makhu - Taran |Tarn 146 121 73 2619 D/C MAR-16220

Work is in progress. Forest and Railway cases pending.30Malout - Abohar 95 40 1120 D/C JUN-16220

Work is in progress. forest case pending.105Moga - Mehal Kalan 170 120 7221 D/C JUN-16220

Commissioned 08/15.87Mukatsar - Abohar 134 134 134 8722 D/C AUG-15220

Forest and railway cases pending.76Mukatsar - Kotkapura 129 66 52 023 D/C JUN-16220

Work is in progress. Forest case pending.Railway case not involved.47Mukatsar - Malout 83 72 3824 D/C JUL-16220

Work is in progress.84Nabha -Bhawanigarh 80 44 11 1025 S/C onD/C

JUN-16220

Work is in Progress.Forest & Railway cases pending.134Nakodar - Ladhowal 122 102 88 026 D/C JUN-16220

Work is in progress.71Nakodar - Rehana 121 121 92 1227 D/C JAN-16220

Work in progress. Forest case pending.37Rajpura - Devigarh 114 101 31 028 D/C MAR-16220

Work is in progress.59Rajpura - Lalru 98 98 87 4629 D/C FEB-16220

Work deferred for the time being62Sarana- Kotli Surat Malli line 185 70 0 030 S/C MAY-16220

Page 41: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

on D/C

Commissioned 06/15.63Talwandi - Dharamkot 113 113 113 6331 D/C JUN-15220

Page 42: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED (RVPNL)

80Ajmer (400 kV) - Bherunda (TK)1 D/C 220

50Akal (1)- Jaisalmer -22 D/C MAR-15400

480Akal -Jodhpur (New) 650 230 1483 D/C MAR-17400

W.O. earlier placed to M/s Trans- Era has been cancelled45Anta -Kota (PG) (Extension) 141 414 D/C MAR-16400

100Badisid-Aau 196 196 160 545 D/C MAR-16220

30Badisid-Bap6 D/C MAR-15220

W.O. to M/s Hythro Power on turnkey has been cancelled , further order yet tobe placed.

160Banswara (Switching Station) - Pratapgarh 3137 D/C MAR-16220

SEP-0920Banswara TPS - Banswara8 D/C 220

360Banswara TPS- Chittorgarh9 D/C MAR-17400

320Banswara TPS- Udaipur10 D/C MAR-17400

280Barmer-Bhinmal (PG)11 D/C MAR-16400

1. Forest Clearance required at 22 locations at Indira Gandhi Canal crossings inthree districts.Distt. Jodhpur- Loc 4 nos, Area 3.204 ha. Distt. Jaisalmer- Loc 2 nos, Area 1.631ha. Distt. Bikaner- Loc 16 nos, Area 17.58 ha2. Clearance taken from DFO(Bikaner,Jaisalmer,Jodhpur) and CCF. Nowpending at APCCF(FCA),Jaipur.3. Severe ROW issues- There is a court case by land owner at 2 nos location inDistt. Bikaner, sought for diverson of line route.

379Bhadla-Bikaner 512 492 476 23012 D/C MAR-16400

50Bhadla-Kanasar 83 41 2513 D/C MAR-16220

APR-14320Bhilwara TPS -Ajmer 432 432 415 5614 D/C MAR-16400

Work held up due to court stay. 2 No bays at 400 kV GSS Bhinmal are to beprovided by PGCIL.

JAN-12100Bhinmal - Sayla line 132 131 131 7415 D/C OCT-15220

420Bikaner -Sikar (PG)16 D/C MAR-17400

Commissioned 11/15.MAR-14172Bikaner- Merta 465 465 465 17217 S/C NOV-15400

120Chatrail-Ramgarh 146 145 140 4018 D/C MAR-16220

53Chittorgarh - Sawa 91 90 88 4219 D/C 220

W.O. issued to SPML Infra Ltd., work progress slow.99Chittorgarh-Bhilwara 134 134 127 1220 D/C DEC-15400

.Dahanu - Degchu GSS21 D/C 132

Commissioned 09/15.DEC-1364Debari - Salumber (2nd Ckt) 5 5 5 6422 D/C SEP-15220

ROW problem at Loc. no. 9-10 & 12 to 63.31Dhod-Danta Ramgarh 101 4423 S/C MAR-16220

Stringing completed.APR-093Extension of Bikaner- Barsinghsar at Barsinghsar TPS 10 10 10 324 S/C APR-14220

30Gajner -Kolayat25 D/C MAR-16220

14Heerapura -Chambal (Cable)26 D/C MAR-16220

Commissioned 11/15.72Hindaun -Chonkarwada 122 122 122 7227 D/C NOV-15220

AUG-1312Indira Gandhi Nagar - Jawahar Nagar28 S/C 220

Shifting work of 11 KV feeder by JVVNL com pleted on dt. 29.9.15.16Indira Gandhi Nagar -Sitapur (Upgradation) 29 29 19 029 D/C NOV-15220

Page 43: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Balance work under progress.

JAN-1362Jaipur North (400 kV GSS) - Manoharpur (Turnkey) 141 137 126 330 D/C MAR-16220

260Jaisalmer -2 -Barmer31 D/C MAR-16400

Commissioned 10/15.JAN-1254Jalore - Sayla 177 177 177 5432 S/C OCT-15220

Actual line length is 119.652 CkmDEC-12120Jethana - Ajmer line 203 201 188 9233 D/C JAN-16220

OCT-1221Jodhpur (400 kV GSS) - Banar 35 33 2534 D/C 220

APR-1090Jodhpur (New) - Barli (TK) 142 140 125 2335 D/C 220

APR-1040Jodhpur (New) - Jhalamand (TK) 65 61 60 3436 D/C 220

12Jodhpur - NPH Jodhpur37 D/C 220

22Jodhpur -Bhadwasia 0 0 0 038 D/C MAR-16220

M/s Classic Coal, work stopped due to ROW problem.16Jodhpur CHB - Soorsagar 31 19 0 039 D/C MAR-16220

Ready for Commissioning 08/15.84Kotputli (PG) - Bansur 141 141 141 8440 D/C AUG-15220

14Kunda ki dhani-Purana Ghat (upgradation)41 D/C MAR-15220

20LILO of Kolayat -Bajju at Kolayat42 D/C MAR-16220

6LILO of 2nd Ckt Sikar (RVPN), Ratnagarh at Sikar43 D/C MAR-14220

10LILO of Aau -Phalodi at Aau44 D/C MAR-16220

Ready for commissioning 06/15.MAR-1411LILO of Ajmer -Kishangarh line at Ajmer 15 15 15 1145 D/C JUN-15220

Commissioned 11/15.2LILO of Alwar -Kotputli at Bansur 5 5 5 246 D/C NOV-15220

10LILO of Amberi - Debari at Udaipur47 D/C 220

W.O order earlier placed to M/s Trans- Era has been cancelled1LILO of Chabra TPS -Dahra at Anta (2nd ckt) 4 4 348 D/C MAR-16400

20LILO of Chandan- Pokaran at Pokaran49 D/C MAR-16220

10LILO of Chittorgarh - Debari at Udaipur50 D/C 220

Work under progress.JUL-131LILO of Heerapura - Babai at Niwana 4 4 4 151 D/C 220

work held up due to court stay on 132kV line6LILO of Jodhpur (GSS) - Jodhpur at Barli 6 6 3 252 D/C MAR-16220

W.O. to M/s R.S. Infra Projects.AUG-0999LILO of Jodhpur - Merta line at Jodhpur (New) 140 140 139 7653 D/C NOV-15400

2LILO of Jodhpur -Jodhpur interconnectorl atJhalamand

54 D/C MAR-16220

.320LILO of Jodhpur -Merta at Pooling station Badla 608 139 5255 D/C MAR-16400

Ready for Commissioning 08/15.11LILO of KTPS - Sanganer line at Vatika 21 21 21 1156 D/C AUG-15220

Court stay for stringing at Loc. No. 22-23 and next hearing on 3.11.1530LILO of Kankroli (PG) -Debari at Amberi 60 60 60 2957 D/C FEB-16220

Ready for Commissoioning 06/15.5LILO of Khetri - Heerapura line at Babai 13 13 13 558 D/C JUN-15220

Line work completed except gantry work.36LILO of Kota (PG) -Bhilwara at Mandalgarh 76 76 76 3959 D/C DEC-15220

Commissioned 06/15.88LILO of Kuchamancity -Dhod at Deedwana 146 146 146 8860 D/C JUN-15220

Commissioned 07/15.5LILO of Mandawar -Nadbai- Bharatpur atChonkarwada

10 10 10 561 D/C JUL-15220

Gantry & bay work pending.24LILO of Nagaur -Merta at Kuchera 36 28 28 1762 D/C DEC-15220

Page 44: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

20LILO of PS 1- Bajju at PS 1/Bajju63 D/C MAR-16220

LILO of VKIA - Kukas at Jaipur (North) (Turnkey)64 D/C 220

1LILO of both ckts Ramgarh GTPS -Dechu at Ramgarh 1 1 1 165 D/C APR-15220

20LILO of both ckts Ramgarh GTPP -Dechu line atPokaran

66 D/C MAR-16220

16LILO of existing Jodhpur GSS - Pali at Jodhpur (New) 18 18 1767 D/C 220

56LILO of one ckt Jaipur (South) to Chaksu at Goner 101 101 70 068 D/C MAR-16220

Commissioned 05/15.12LILO of one ckt Kotputli -Manoharpur at Kotputli (PG) 26 26 26 1269 D/C MAY-15220

Commissioned 05/15.31LILO of one ckt Neemrana -Kotputli at Behror 53 53 53 3170 D/C MAY-15220

W.O. to M/s Megha Hyderabad.103LILO of one ckt Raj west -Jodhpur at Jodhpur (New) 138 138 138 10271 D/C MAR-17400

33LILO of one ckt of Ramgarh GTPS - Dechu atAmarasagar

59 58 46 072 D/C 220

5Mansarovar - Chambal (Cable System)73 D/C 220

AUG-1311Mansarovar - Jawahar Nagar74 S/C 220

Ready for Commissioning 10/15.MAR-1554Neemrana-(PG)-Behror 100 100 100 5475 D/C OCT-15220

40PS 1 /Bajju -Bhadla 107 105 98 2476 D/C MAR-16220

(i)Work order withdrawn from M/s. GET and placed to M/s Varsana Ispat on02.02.15.(ii) One no. NHAI crossing approval awaited.

SEP-1286Phagi GSS (Jaipur) - Heerpura 128 124 115 4777 D/C MAR-16400

(i)Work order withdrawn from M/s. GET and placed to M/s Varsana Ispat on02.02.15.(ii)Two nos. NHAI crossing & one no. railway crossung approval awaited.

SEP-12210Phagi(Jaipur south-765 kV)-Ajmer line 283 257 184 078 D/C MAR-16400

240Pratapgarh- Chittorgarh 407 183 4679 D/C JAN-16220

200Ramgarh (Jaisalmer)-Akal (Jaisalmer ) 293 132 9580 D/C MAR-16400

360Ramgarh -Bhadla 440 368 181 2381 D/C MAR-16400

33Renwal -Danta Ramgarh 113 111 10182 S/C MAR-16220

Commissioned 04/15.MAR-1411Sanganer- Sitapura (Upgradation) Ckt-II 40 40 40 1183 D/C APR-15220

Commissioned 11/15.OCT-1266Sanganer-Chaksu (Upgradation) 144 144 144 6684 D/C NOV-15220

25Sirohi-Pindwara 106 6485 S/C MAR-16220

Line work completed / commissioned on 132kV voltage level on 24.07.15.1Sitapura- Sitapura (Existing) (Upgradation) 3 3 3 186 D/C JUN-15220

AUG-1111Soorpora - Banar line 35 33 27 1287 D/C MAR-16220

W.O. to M/s SPIC- SMO, case for diverting route due to air force is underprocess.

480Suratgarh TPS - Babai ( Jhunjhunu) 640 555 521 12588 D/C MAR-16400

340Suratgarh TPS- Bikaner89 D/C MAR-17400

Commissioned 10/15.32Tehandesar(proposed)-Bandnu 111 111 111 3290 S/C OCT-15220

140Undoo - Pokaran91 D/C 220

Page 45: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

SIKKIM POWER DEVELOPMENT CORPORATION LTD. (SIKKIM)

.Dikchu - Gangtok1 D/C 132

Dikchu - Mangan2 D/C 132

Page 46: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TAMILNADU TRANSMISSION CORPORATION LTD. (TANTRANSCO)

Koladi - PH Road: OH Line work under progress. Stub: 47/76, TE:46/76completed. Stringing: 15/23.For cable laying from PH road to Koyambedu,Onecircuit to be terminated at Koyembedu (CMRL) for which work awarded and to betaken up and another one circuit to be terminated at Alandur(CMRL) for whichrevised administrative approval is accorded and tender is under process.

Alamathy - Koyembedu1 D/C MAR-16400

Commissioned 06/15.JUN-1239Arasur 400 kV S/S - Karamadai 230 kV S/S 169 169 169 392 S/C JUN-15220

Cable energised on 01.09.153Avadi-Ayappakkam line 0 0 0 03 S/C SEP-15220

Tender is to be floated23Basin Bridge - TNEB HQ (UG Cable) 0 0 0 04 S/C DEC-15220

Commissioned 04/15.14Kadapperi - Guindy (UG Cable) 145 S/C APR-15220

Issues involved and is being followed up.(i) 2 locations : severe ROW issue. Work will be taken up under DCW basis.(ii) 12 Locations: Case at National Green tirubunal. Case cleared and work isbeing taken up. Subsequently stay obtained by the villagers and hearing on14.07.15 postponed and next hearing date is awaited. (iii) 4 locations:Court case. Status quo maintained.

52Kalivanthapattu - Sholinganallur 88 72 67 276 S/C DEC-15400

Works are under progress. ROW issues at 3 locations. Work held up by thecontrator.

24Kanarpatty - Kayathar 39 36 33 177 D/C DEC-15400

Issues involved at 3 locations : (i) Sincethe land owner has objected for erecting the tower at loc.No.137, representationhas been sent to the District Collector/Madurai and enter upon permission isawaited.(ii) Due to severe objections/threatening by the land owners, tower foundationwork at loc.No.215 & loc.No.249 are pending. Representation sent to localPolice for protection and they assured to give police protection at the time oftaking up the work.Further,the contractor M/s.GET has not turned up for work. Hence one monthnotice issued to contractor for termination. Balance work will be carried out byGCC for which tender is to be floated.

DEC-11140Karaikudi - Sembatty 554 548 491 848 S/C SEP-15220

Commissioned 06/15.320Karaikudi-Pugalur 460 460 460 3209 D/C JUN-15400

work under progress for 2 reaches and work awarded and to be taken up for 3rdreach.

23Koladi - PH Road 76 65 61 2210 D/C DEC-15220

Commissioned 10/15.9LILO of Alamathy - CMRL Koyembedu atThiruverkkadu

911 D/C OCT-15220

Commissioned 07/15.2LILO of Alamathy - Koyembedut Thiruverkkadu 1 1 1 212 D/C JUL-15220

Work awarded and is being commenced6LILO of Arasur (PG) - Karamadai at Karuvalur13 D/C 220

Tender finalised and work is being awarded.12LILO of Chekkanurani - Kayather at Kinnimangalam14 D/C 220

Tender finalised and work is being awarded.8LILO of Chekkanurani - TTPS-I at Kinnimangalam15 D/C MAR-16220

Not related to TANTRANSCOLILO of Chilakallu - Narketpally at Huzumnagar.16 D/C DEC-15220

Works are under progress. Objections cleraed at Loc 41. Meanwhile, the landowner got injunction order from High court chennai and work stopped. Lasthearing on 27.10.15 and posted to next week. It is being followed up.

32LILO of K.R. Thoppur - Ingur at Thingalur 99 99 98 2117 D/C FEB-16220

Page 47: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Commissioned 07/15.39LILO of Kalivanthapattu - Veerapuram at OMEGA 75 75 75 3918 D/C JUL-15220

Work under progress.20LILO of Kalpakkam - Arani at Purisai 49 2019 D/C APR-16220

Commissioned 08/15.6LILO of Korattur - Koyambedu at Alamathy 620 D/C AUG-15220

Commissioned 09/15.23LILO of Korattur - Koyambedu at Alamathy (BalancePortion)

2321 D/C SEP-15220

Works are under progress.6LILO of Korattur - Koyembedu at Ambattur (3rd MainRoad)

5 4 222 D/C DEC-15220

Ready for Commissioning 08/15.1LILO of Manali - Basin Bridge (BBGTP) at Vyasarpadi 6 6 6 123 D/C AUG-15220

Work under progress. Objection encounted from loc.1 to 119. Action is beingtaken for getting entry permission from District Collector/Tiruppur and DC/Karur.Objection involved at entire line work vide WP No:23265/2015 and is beingfollowed up. Enquiry conducted on 10.09.15 and orders awaited.

62LILO of Myvady - Pugalur at Kurukathi 124 81 56 524 D/C FEB-16220

Commissioned 07/15.52LILO of Neyveli Zero unit - Neyveli - TS-II atUlundurpet

90 90 90 5225 S/C JUL-15220

Commissioned 07/15.2LILO of Shoolagiri - Singarapet at Gurabarapally 3 3 3 226 D/C JUL-15220

Work under progress.2LILO of Siruseri - Tharamani at Sholinganallur 14 14 13 227 D/C NOV-15220

Due to long penging Court case, revised route is under study.DEC-1012LILO of Sriperumbadur- Arni at Sunguvarchatram 28 10 3 028 D/C MAR-16220

Work awarded and to be commenced.Road cut advice received from High waysand HR submitted.

18LILO of Sriperumbudur - Koyambedu at Guindy (UGCable)

0 0 0 029 D/C MAR-16220

Work awarded on 03.09.1520LILO of Thatchankurichi - Eachangadu at Poiyur30 D/C 220

Tender finalised and work is being awarded.40LILO of Thiruvarur - Kadalangudi at Kumbakkonam31 D/C MAR-16220

Cable already laid.1LILO of Tonidapet - Mylapore at TNEB HQ (UG Cable) 0 0 0 032 D/C DEC-15220

Commissioned 07/15.68LILO of Ulundurpet - STCMS at Ulundurpet 153 153 153 6833 D/C JUL-15220

Dharmapuri 400 KV SS has been sanctioned. Hence, work will be taken upaccording to that BP.

200MTPS St.III - Singarpet 0 0 0 034 D/C JUN-16400

Commissioned 05/15.338MTPS Stage-III - Thiruvalam (Ckt-II) (Balance) 33835 D/C MAY-15400

Work completed.39MTPS-Malco 50th tower-New common point towardsThingalur

0 0 0 3836 D/C SEP-14220

Work under progress. Cable laying work completed in 21/26 sections.25Mylapore - Tharamani (UG Cable) 0 0 0 037 D/C DEC-15220

At present,SC line works are under progress.70Ottiyambakkam - Omega 153 141 131 2638 D/C MAR-16220

One circuit to be terminated at Koyembedu (CMRL) for which work awarded andcommenced and another one circuit to be terminated at Alandur(CMRL) forwhich revised administrative approval is accorded and tender opened on17.07.15. Evaluation is under process.

6PH Road - Koyambedu (UG Cable) 0 0 0 039 D/C MAR-16220

Work under progress. Objection by land owners involved atlocations 160 to 190.Isuues are being followed up. Multi circuit tower involved atloc.236 to 249. Loc 94: ROW issue involved and enter upon permission awaitedfrom District Collector. Location :187court case. Last hearing on 20.08.15. Issuesare being followed up.

62Palladam - Ingur 249 236 20840 S/C onD/C

MAR-16220

Line work completed. Will be energised along with the commissioning of86Rasipalayam - Anaikadavu 115 115 115 7741 D/C SEP-15400

Page 48: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

the SS.

Works are under progress. ROW issues involved at 14 locations. Distictcollectors Tiruppur, Erode and Dharmapuri approached for solving the issues.

390Rasipalayam - Salem 556 544 543 33742 D/C MAR-16765

Stub setting and tower erection is under progress.1Sholinganallur - KITS 50 39 30 443 D/C DEC-15220

Line work is under modification. Revised administrative approval is underprocess.

SEP-0620Sriperumbudur -Korattur (Changing of conductor) 70 0 0 1244 S/C MAY-13220

works are under progress.Court case and Railway crossing involved and issuesare being followed up.

358Thappakundu - Anaikadavu 501 499 499 33945 D/C MAR-16400

Line work completed.17Thingalur Common point - MTPS & MALCO line 39 39 39 946 D/C NOV-14220

Work completed40Thingalur Common Point-Gobi47 S/C MAR-14220

Ready for Commissioning 08/15.143Thiruvalam - Almathy 198 198 198 14348 D/C AUG-15400

Work under progress. ROW issue at one location. Enter upon permissionawaited from District collector/Tirunelveli. 7 nos. Locations are under waterlogging area.

16Tirunelveli (Abishekapatty) - Kanarpatty 56 46 37 1449 S/C MAR-16400

Due to poor progress by the contractor, termination notice issued for terminationof the contract.

55Villupuram - Ulundurpet 183 164 8 050 S/C DEC-15220

Page 49: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED. (APTRANSCO)

Commissioned 11/15.84Appannadorapalem - Bobbili (Ckt-I) 269 269 269 841 D/C NOV-15220

130Chittoor 400 kV SS-Mananapalli2 D/C MAR-15220

Works under progressDEC-109Gaddamvaripalli- Goddumari 31 31 29 43 D/C DEC-15220

70Garividi - Garividi4 D/C 220

100Garividi - Pydibhimavaram5 D/C 220

Tenders called and LOI issued on 01.10.2015 with the completion period of 12months

75Garividi-Bobbili 125 86 0 06 D/C OCT-16220

136Jammalamadugu - Betamacherla7 D/C 220

Line works are under progress and expected to be completed by Jan,2016.JAN-15172Jammalamadugu - Chakrayapet 296 283 281 1648 D/C JAN-16220

Works under progress.JUL-15202Jammalamadugu - Narnur Kurnool Dist 282 281 279 1829 D/C DEC-15400

Works are under progress. 10 Nos tower foundations and 2.8 km stringing inForest reach are pending for want of forest clearance.

JAN-15198Jammalamadugu - Porumamilla 338 320 314 17310 D/C DEC-15220

works are under progress.JUL-1454Jammalamadugu - Tirumalayapalli 88 72 4711 D/C MAR-16220

Works under progress.JUL-15264Jammalamadugu - Uravakonda 347 280 221 7712 D/C DEC-15400

Works under progress.300Kalpaka - Proposed Garividi S/S 358 135 24 013 D/C MAR-16400

61Kalyandurg-Anantapur14 S/C MAR-14220

30Kamavarapukota - Kamavarapukota15 D/C 220

90Kamavarapukota - Nuziveedu16 D/C 220

Due to standing crops and people are demanding hug compensation than thecompenasation fixed up by Revenue authories and not allowing the works to becarried out in their locations. The frequent rains are also the reason for dlealy totake up the line works.

SEP-15212Kamavarrapukota - Surypet (Kamavarrapukota -Chinnakorukondi)

248 142 111 3517 D/C MAR-16400

Commissioned 07/15.180Krishnapatnam TPS- Chittoor(Balance) 18018 D/C JUL-15400

The Check survey is in progress.60Kurnool (Narnoor) - Gani S/S 5019 D/C 400

Works are under progress.DEC-14200LILO of Both ckt Pulivendula - Hindupur at Gollapuram 93 35 0 020 D/C SEP-16220

140LILO of Pendurthy - Garividi at Garividi21 D/C 220

80LILO of Podili - Nellore at Atmakur22 D/C 220

Shadnagar - Yeddumailaram line commissioned on 07.03.201412LILO of Shadnagar - Yeddumailaram atYeddumailaram

19 19 19 1223 D/C MAR-14220

22LILO of Uravakonda - Kalyandurga at Borampalli24 D/C 220

200Muddanur (RTPP) - Dharmavaram25 D/C 220

100Muddanur-Anantapur (3rd line)26 S/C onD/C

MAR-14220

60Narketpally_Suryapet27 S/C onD/C

MAR-14220

15Narsapur-Doultabad28 S/C MAR-15220

Page 50: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

15Narsapur-Manoharabad29 S/C MAR-15220

20Nirmal-Nandipeta30 S/C MAR-15220

10Nizamabad-Janakampeta31 S/C MAR-15220

112Numa - Juyarni 166 165 162 7032 D/C SEP-15400

20Oddugudem-Koyagudem33 D/C MAR-15220

36Oglapur(Warangal 400 kV SS)-Warangal 220 kV SS34 D/C MAR-15220

All foundation works completed. 4 Nos tower erection and 8 ckm of Strining isunder progress

JUN-11250Pulivendula-Hindupur 393 393 389 24235 D/C DEC-15220

Commissioned 10/15.DEC-15112Purushottapatnam (Nunna) - Jujjuru 11236 D/C OCT-15400

Commissioned 3/13.17Rentachintala - Macherla S/S 58 58 58 1537 S/C MAR-13132

Commissioned 08/14.16Rentachintala - Nagarjuna Sagar Plant 34 34 34 1638 S/C AUG-14132

110Sattenapalli - Guntur39 D/C 220

20Somayajulapalli - Gani/Panyam S/S40 D/C 220

Charged on 09/15. ( Reported late).NOV-108Thimmapuram- Yellanur 27 27 27 841 D/C SEP-15220

Works under progress.JUL-1543Tungabhadra river - Yemmiganur 58 54 54 3342 D/C OCT-15400

Works are under progress.MAR-1572Uravakonda - Borampalli 111 22 0 043 D/C SEP-16220

Works are under progress.NOV-14100Uravakonda - Kalyanduring 160 123 98 044 D/C MAR-16220

ROW problem resolved. Works under progress.DEC-1432Uravakonda - Vajrakarur 57 44 33 045 D/C DEC-15220

LOI issued on 04.09.2015.Vemagiri - Kamavarapukota46 D/C 400

The works are getting delayed due to severe resistance from farmers and landOwners through their lands. These people are demanding huge compensationthat the compenasation fixed up by Revenue authories and not allowing theworks to be carried out. Water logged areas, collasable soil, existing crops andfrequent rains are also the reasons for delay to take up the line works. However,construction activity is being continued with the help of Revenue and otherconerned authorites.

NOV-15712Vizag TPP - KamavarapukotaKota 964 380 138 1047 D/C MAR-16400

Commissioned 07/15.14Vizag TPP - Kalpaka 1448 D/C JUL-15400

Ready for Commissioning 10/15.JUL-15205Yemmiganur - Uravakonda 271 271 271 20549 D/C OCT-15400

84ppannadorapalem - Bobbili (Ckt-II)50 D/C 220

Page 51: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TRANSMISSIPN CORPORATION OF TELANGANA (TSTRANSCO)

14Budidampadu - Bhongiri (2nd Ckt) 24 24 24 141 D/C DEC-14220

25Chilakallu - Narketpally 42 41 41 152 D/C DEC-15220

170Chinnakorukondi - Suryapet 234 233 197 483 D/C DEC-15400

Preliminary survey completed. Detailed survey to be awarded.Estimates under scrutiny.

200Gajwel - Narsapur 0 0 0 04 D/C MAR-15400

Works are under progress36Ghanapur - Marripally 72 71 67 105 D/C OCT-15220

work under progress145Jagityal - Nirmal 210 24 6 06 D/C MAR-17400

work under progress.144Jaipuram - Jagityal 201 10 0 07 D/C MAR-17400

24Kalwakurthy-Dindi 3rd line8 S/C MAR-14220

15Kamareddy-Bhumpally9 S/C MAR-15220

SEP-15212Kamavarrapukota - Surypet ( Chinnakorukondi -Suryapet)

234 223 197 4810 D/C DEC-15400

Stringing under progress8LILO of VTS - Malkaram (Ckt-I) at Suryapet 12 12 12 711 D/C NOV-15400

Commissioned 04/15.2LILO of 1st ckt of Shapurnagar - Gachibowlly line atMiyapur

212 D/C APR-15220

2LILO of Bhoothpur - Kalwakurthy at Thimmajipet 4 4 0 013 D/C SEP-15220

2LILO of Bhoothpur - Kalwakurthy at Thimmajipet (Ckt-II)

4 4 0 014 D/C SEP-15220

DEC-1314LILO of Budidampadu - Bhongiri at Waddekothapally15 D/C 220

Cable laying and jointing completed. OFC cable works in progress.18LILO of Ghanapur - Malkaram at Moulali16 D/C 220

Commissioned 10/15.34LILO of Kalpaka - Khammam at Asupaka 49 49 49 3417 D/C OCT-15400

60LILO of RSS - Warangal at Manthani18 D/C 220

Commissioned 05/15.19LILO of Shapur Nagar - Gachilbowli feeder at GISErragadda SS

1919 DC UGcable

MAY-15220

Commissioned 11/15.OCT-14158LILO of Srisailam - Hyderabad (Ckt-I)atYeddumailaram (Shankarapally)

221 221 221 15820 D/C NOV-15400

P.O.issued on 18.05.2013.Work completed.Substation works yet to becompleted.

34LILO of Vizag - Khammam (Ckt-I) at Asupaka 49 49 49 3421 D/C JAN-16400

Works are under progress.11LILO of Wanaparthy - Ragimanagadda at Singotam XRoad SS

17 15 1422 D/C OCT-14220

Commissioned 07/15.2LILO of both ckt Dindi - Chandrayangutta at Bonguloor 223 D/C JUL-15220

Erection of 2 towers for Krishna river crossing are balance and casting of pilefoundation is under progress.

22Lower Jurala HEP - Upper Jurala 36 34 34 2124 D/C OCT-15220

Commissioned 04/15.6Mamidipally - Fab city 625 D/C APR-15220

All works completed and line commissioned on 03.11.201411Mamidipally S/S M/s K.S.K. Photo Voltaic near FabcityRavirala (V)

37 37 37 1126 D/C JUL-14220

Works are under progress.13/14 Nos Cable joints completed and remainingworks are under progress

14Marripally common point- Hayatnagar S/S XLPE cable 827 DC UGcable

MAR-15220

Works are under progress.Cable laying work completed. Joint works completed.cable along with substation is expeced to be charged by October-2015

18Moulali - Osmania University (Chilakalaguda) SS 1828 DC UGcable

AUG-14220

Page 52: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

36Nagole - Ghanapur29 M/C OCT-15220

Severe R.O. W Problem222Nandiwanaparthi - Shankarpalli 315 291 223 830 D/C MAR-16400

Terminated at 220 kV Sitapuram S/S for power evacuation from PulichintalaHEP.

74Pulichintala - Huzumnagar 130 117 102 1631 D/C DEC-15220

Work awarded to L&T/KEC in 9/2015 with completion period of 15 months.298Singareni - Nirmal 17432 D/C JUN-17400

Commissioned 11/15.325Singareni TPS (Jaipur TPP) - Gajwel 459 459 459 32533 D/C NOV-15400

240Suryapet - Nandiwanaparthi 343 342 341 23634 D/C DEC-15400

462Suryapet - Shankarpalli 656 626 553 24035 D/C NOV-15400

240Vadarevu - Amangal 0 0 0 036 S/C AUG-16765

R.O.W problem.147Veltoor - Thungabhadra 200 189 175 1237 D/C MAR-16400

84Veltur-Thimmajipet 129 52 0 038 S/C MAY-15220

Works are in progress135Yeddumailram - Pargi 137 137 137 9039 D/C 220

Page 53: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TRIPURA STATE ELECTRICITY CORPORATION LIMITED (TSECL)

AGTP - Agartala line1 D/C 132

AGTP - Kumarghat line2 S/C 132

ROW problems affected the work31Gamai Tilla - Dhalabil 107 101 78 173 S/C SEP-13132

20LILO of Rokia - Udaipur at Melaghat for connection toMonoarchak

40 0 0 04 D/C JUN-15132

Work in progress.42Monarchak - Surajmani Nagar 150 49 38 65 D/C MAR-15132

All works completed in non forest land. Stage- I clearance received andcompliance for conditions completed.

47P.K. Bari - Kanchanpur 113 109 99 176 S/C MAR-15132

Completed 9/1318Surajmani Nagar - Agartala 79 Tilla Grid S/S 71 71 71 187 D/C SEP-13132

Fund proposed in World Bank.6Surajmani Nagar - Badarghat 0 0 08 D/C MAR-15132

Completed 9/133Surajmani Nagar - Rabindra nagar 13 13 13 39 D/C SEP-13132

3.598 KM line in forest land for which TSECL will apply for forest clearance. LOAissued

20Surajmani Nagar - Rokhia 80 32 5 010 D/C DEC-14132

Proposed under NEC.50Surajmani Nagar - Udaipur 50 0 0 011 D/C JUN-15132

Fund not yet tied up. Proposed under World Bank Financing /SPA/NEC.260Surajmani nagar-P.K.Bari 0 0 0 012 D/C MAR-15400

Page 54: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

U.P. POWER TRANSMISSION CORPORATION LTD. (UPPTCL)

Commissioned 09/15.20220 kV LOC 49 of Roza-Hardoi to 220 Shahjehanpur 201 D/C SEP-15220

WIP.AUG-16142Agra (UP) - Mathura line 388 265 195 02 S/C MAR-16400

WIP.AUG-16142Agra(UP) - Agra (South) 190 164 105 03 D/C MAY-16400

Tower material reached at site.MAR-1669Aligarh - Atrauli 125 73 68 24 D/C JAN-16220

Seperate Agency finalized for DFCC diversion work. 2. 09 no.tower had collapsed and 04 no. tower foundation to be cast at Sikandarabadend. Expected date of completion is 31.01.2016.

190Aligarh - Sikandarabad 258 254 254 1665 D/C DEC-15400

Work yet to be awarded.Allahabad (PG) - Rewa Road (Allahabad)6 D/C 400

1.Forest Clearancea. Kamoor wild lifeb. Reserved forest area2. Railway xing3. Power line xing4. Foundation

274Anpara - jhusi 542 367 318 737 S/C JUN-16765

Contract of the firm M/s Maharashtra Power Transmission Structures Ltd. hasbeen terminated on 20.05.2014 and LOI issued on 30.12.14 by SE, Mirzapur forthe balance work. Work in progress.

10Anpara B-Anpara D 23 23 21 68 D/C OCT-15400

1.Apnara D - Jhusi section.(a) Forest clearanceb. Reserved forest area2 Railway xing3. Power line xing4. Foundationb. Jhunsi - Unnao section1. forest clearance2. Railway xing3. Power line xing

JAN-12416Anpara D - Unnao 1215 1039 989 3009 S/C DEC-15765

1.Termination point at 400KV S/s Aurai not yet decided.2. River crossing work to be taken up.3.Severe ROW at 15 locations being persued.

43Aurai - Mizapur 147 129 82 010 S/C MAR-16220

1. Termination point at 400kV s/s Aurai(PPP) not yet decided. Last 2 Sectionswork held up due to this. 2. ROW at loc.2/1,3/0,4/0,5/0,12/0,12/1,12/2,17/5,39/3,53/0,53/1,53/3 being pursued.Expected date of completion is 31.01.2016.

71Aurai - Phoolpur 216 210 195 4811 S/C JAN-16220

Commissioned 11/15.86Badaun - Sambhal 250 250 250 8612 S/C NOV-15220

Letter written from MD, UPPTCL to DM baghpat regarding ROW, being pursuedlocally.

13Baghpat - Baghpat 49 45 32 013 S/C DEC-15220

Charged on 31.10.1119Balrampur - Utraula 56 56 56 1814 S/C 132

New firm started the fdn work in banda- allahabad line.350Banda - Allahabad (Rewa Road) DCQ 484 446 184 015 D/C MAR-16400

Work is in progress of check survey by the new agency. The physical verificationof previous firm is held up on the level of reconciliation field.

216Banda - Orai DCQ 295 211 130 016 D/C OCT-16400

Line energized on 26.05.14. Barkhera-pilibhit Section,I ckt. Energisedon10.02.12.II ckt. On 14.2.12

Barkhera (Bajaj) - Dohna 203 203 203 12917 D/C MAR-15132

Page 55: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Bayas - Dohna18 D/C 132

Bayas - Pilibhit19 D/C 132

.Bhognipur - Gatampur20 S/C 765

Bhognipur - Jawarharpur21 S/C 765

Bhognipur - Moradabad/Rampur22 S/C 765

.Bhognipur - Orai (PG)23 2xS/C 765

Bilhaur - Sandila24 S/C 765

Bilhaur - Kanpur (PG)25 D/C 400

work stopped in diwali to be started with in 3 days.60Chhatta - Mathura 114 11 0 026 D/C MAR-16220

Route Alignment submitted. Approval awaited to submit Detail Profile.40Dasna (400) - Faridnagar 0 0 0 027 S/C DEC-15220

WIP.83Deoria - Rasra 253 253 252 8228 S/C DEC-15220

1. Payment of pending crop compensation cases to be done by Div. on priority.2. Approval of 1 nos. Rly xing being pursued, PTCC clearance ir required by Rly.3. Balance work to be taken up after completion of 220kV Shajahanpur-Nighasanline. Expected date of completion is 30.12.2015.

48Dohna - C.B. Ganj 92 92 83 2929 S/C DEC-15220

.Dopaha - Anpara30 D/C 765

Dopaha - Ghazipur31 D/C 765

Dopaha - Varanasi / Jaunpur32 D/C 765

Fdn WIP, Fdn ROW at loc. No. 32,under court case, next hearing on 01.12.15.Dumariaganj- - Utraula 114 109 107 3233 S/C DEC-15132

work on Railway xing span remaining, letter written from MD, UPPTCL to DRM,NR.

AUG-0937Gajokhar-Jaunpur 132 132 132 3734 S/C onD/C

DEC-15220

.Ghatampur - Moradabad / Rampur35 2xS/C 765

Ghatampur - Kanpur (PG)36 D/C 400

Ghazipur - Varanasi / Jaunpur37 S/C 400

41Gokul-Mitai(Hathras) 135 135 129 1538 S/C DEC-15220

.460Gonda - Shahjehanpur (PG)39 D/C 400

23Gr. Noida - JPSK 0 0 0 040 S/C 220

Fdn row in loc. 125-146(Gr. noida authority) & loc no. 70-75, 82,84,86,87,88,89(by local farmer)

88Gr. Noida - Noida (Quad) 140 93 66 141 D/C DEC-15400

Land of 220 kV S/s Pratap vihar not finalized.16Indirapuram - Pratap Vihar 0 0 0 042 D/C 220

Jawaharpur - G Noida43 D/C 765

Jawaharpur - Agra (UP)44 D/C 765

Jawarpur - Mainpuri45 D/C 765

1.Forest Clearance2. Railway xing3. Power line xing

239Jhusi - Unnao 673 672 671 22746 D/C DEC-15765

Khurja - Hapur47 S/C 765

Page 56: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

LILO Mainpuri (PG) - Harduaganj at Jwrpur48 D/C 220

1. 01 no. Fdn gang, 01 no. Erec. Gang & 02 no. Str gangs are working. 2.Another Er gang to be deployed by 21.11.15.3. Tower Parts delievered. Theproposed date of complition 15.01.16

67LILO of 1st Ckt Bhogaon-Mainpuri at Sirsaganj 111 107 50 1049 D/C DEC-15400

WIP.AUG-1664LILO of Agra - Muradnagar at Mathura 88 60 9 050 D/C MAR-16400

LILO of Agra - Muradnagar at Kurja51 D/C 4.4

1.The remaining work is held up due to DFCC work and the restoration work isprogress on 09 no. tower.

LILO of Aligarh - Sikandarabad 258 254 254 16652 D/C DEC-15400

LILO of Anpara - Mau at Ghazipur53 D/C 400

Work not Started.120LILO of Azamgarh - Sultanpur at Tanda54 D/C 400

FDN WIP.90LILO of Bhauti - Orai at Sikandara 105 42 0 055 D/C DEC-15220

LILO of Bhognipur - Mbd at Bilhaur56 D/C 765

LILO of Ghatampur - Mbd at Sandila57 D/C 765

Only 01 fdn gang working at site although firm asured total 03 no. fdn gangs tobe deployed by 26.11.15.. The proposed date of completion is 31.03.16.

40LILO of Gorakhpur - Basti at Bansi 155 58 12 058 S/C DEC-15220

WIP.43LILO of Harduagani - Hathras at Aligarh 71 71 69 3959 D/C DEC-15220

Commissioned 09/15.6LILO of Harduaganj- Khair (Aligarh) line at Boner 660 D/C SEP-15220

Survey under progress.30LILO of Hathras - Gokul at Mathura 22161 D/C DEC-15220

LILO of Mainpur (765) Aligarh (400) at Jwrpur62 D/C 400

LILO of Mainpur - Etah at Jwrpur63 D/C 220

LILO of Mainpuri - Gr Noida at Khurja64 D/C 765

Foundation WIP.60LILO of Meza - Rewa Road at Masuli (Allahabad) 90 22 0 065 D/C JUL-16400

.104LILO of Mohanpur - Behat line66 S/C 220

30LILO of Muradnagar - Loni at Ataur 91 9 0 067 S/C DEC-15220

Letter written from MD, UPPTCL to DM Baghpat regarding ROW, being pursuedlocally.

9LILO of Muradnagar - Shamli at Baghpat 20 15 12 068 S/C DEC-15220

Commissioned 04/15.20LILO of Muzaffarnagar - Nara II at Jansath Ckt-II 2069 D/C APR-15220

Rly Xing Case at Loc. 17-18 Submitted to DRM Jhansi.Work stopped fromseveral Months. Proposal for withdrawal of line moved.

6LILO of Orai - Bhauti at Orai 15 13 8 070 S/C NOV-15220

Line charged on 14.02.14100LILO of Orai - Mainpuri at Bah 258 258 258 15471 S/C MAY-14220

.LILO of Panki - Muradnagar at Jwrpur72 D/C 400

2nd Rly block availed on 26.11.15. and Rly xing completed , 02 no stringinggangs are working at site, Stringing at loc.57-61.

42LILO of Sarnath (400) - Azamgarh at Harhua 75 75 74 3573 S/C DEC-15220

Work not Started.LILO of Sarnath - Azamgarh at Varanasi / Jaunpur74 D/C 400

Line charged on 11.09.2015 at 20.55 Hrs.MAR-1118LILO of Shajahanpur - Hardoi line at Rosa 52 52 52 1875 S/C SEP-15220

Stringing at ROW Loc no. 76-78 is being pursued.48LILO of Sultanpur - Phoolpur at Pratapgarh 80 80 80 4676 D/C DEC-15220

12LILO of Unnao - Bareilly at Shahjahanpur77 D/C 400

.LILO of Unnao - Mainpur at Bilhaur78 D/C 765

Page 57: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

WIP.AUG-1668LILO of existing Agra (UP) - Agra (PG) at Agra (UP) 100 58 27 079 D/C MAY-16400

WIP.AUG-16158LILO of existing Agra (UP) - Muradnagar at Agra (UP) 212 116 60 080 D/C MAY-16400

Commissioned 09/15.1LILO of khurja-NAPP-I line at Debai 181 D/C SEP-15220

Commissioned 04/15.19Lalitpur - Lalitpur TPS (Ckt-II) 1982 D/C APR-15220

Foundation, Erection & Stringing WIP.AUG-16332Lalitpur TPS - Agra (UP) Ckt-I 955 763 518 1983 S/C MAR-16765

FDN, Ere, Stringing work in progress.AUG-16334Lalitpur TPS - Agra (UP) Ckt-II 889 737 588 684 S/C MAR-16765

1.01 no. erection gang is working2. IInd Erec. gang was to be deployed by 25.11.15

50Lucknow PG (400) - Kursi Road 66 66 20 085 D/C DEC-15220

220Mathura - Jawaharpuram86 D/C 400

Meja - Bargarh87 D/C 765

Land of 220 kV S/s Pratap vihar not finalized.36Morti - Pratap Vihar 0 0 0 088 D/C 220

Charged on 30/09/15.0Muradnagar-Agra line 089 D/C SEP-15400

Commissioned 04/15.12Muzaffarnagar - Nara Ckt-II 1290 D/C APR-15220

Line completed OPGW stringing work held up due ROW at loc. 326, Tree cuttingis also required.

216Rosa - Dohna 340 340 340 21691 D/C DEC-15220

104Saharanpur (PG)-Behat92 D/C NOV-15220

Agency not taking interest in work.18Sahupuri-Bhelupur 39 39 38 1593 D/C DEC-15220

Sandila - Farrukhabad94 S/C 400

Sandila - Lucknow Hardoi Road95 S/C 400

Stringing of river xing completed. 2 nos. Erection/ Stringing gang working at site.121Shahjahanpur - Nighasan 369 369 365 10496 S/C DEC-15220

1. ROW at Loc no.-84, tree cutting is to be done with the help of police force,which shall available after Panchayat election.2. Balance work to be taken up after completion of 220 KV Shajahanpur-Nighasan line. Expected date of completion is 31.12.2015.

110Sitapur - Nighasan 336 335 318 8597 S/C DEC-15220

Fdn ROW at 09 locs loc no-11,12,23,29,183,190,248,249 & 250, Er ROW at locno-145, Str ROW at loc no-92, as per joint inspection of OPGW between M/sPNC, M/s Sterlite and field unit, in the m/o June 15 there is no any issue ofOPGW & H/ws, .Stringing of OPGW is in the scope of M/s PNC.

185Sohawal - Tanda 348 338 253 2498 D/C DEC-15220

200Tanda - Gonda99 D/C 400

Varanasi / Jaunpur - Gorakhpur100 D/C 400

Varanasi/Jaunpur - Aurai101 D/C 400

Varanasi/Jaunpur - Azamgarh102 D/C 400

Varanasi/Jaunpur - Meja103 D/C 765

Page 58: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED (WBSETCL)

MAY-1713Alipurduar - Alipurduar (PG) 0 0 0 01 D/C MAR-16220

Commissioned 11/15.JUN-14210Gokarna - Krishnanagar 389 389 389 2102 D/C NOV-15220

JAN-17340Gokarna - N. Chanditala 514 167 0 03 D/C FEB-16400

APR-16107Kharagpur - Egra 205 152 135 204 D/C APR-16220

SEP-16277Kharagpur - N. Chanditala 405 357 232 145 D/C FEB-16400

Ready for Commissioning 10/15.APR-1492Kharagpur - Vidyasagar Park 133 133 133 926 D/C OCT-15220

Server RoW issue rerouting line is proposed.AUG-0820LILO of Arambagh -Rishra at Singur 37 10 2 07 D/C MAR-16220

SEP-1613LILO of Bakreswar - Gokarna at Sadaipur 27 1 0 08 D/C MAR-16220

9LILO of Jeerat - Rishra at Dharampur 21 0 0 09 D/C FEB-16220

JUL-1589Sagardighi - Gokarna 154 130 52 010 D/C FEB-16400

PGCIL is executing the work as a deposit work of WBPDCL.The work is stalled due to repeated theft. WBPDCL asked PGCIL to take up withthe present vendor for resumption of work or deploy a new vendor by cancellingthe existing contract.

OCT-08224Santaldhi TPS-Bishnupur 347 347 325 19311 D/C 220

Line commissioned on 02/12/2014.MAR-1025Sushasgram- Saintala 51 51 51 2512 D/C NOV-14220

SEP-0821Teest LDP -III - Teesta LDP-IV 94 83 67 613 S/C DEC-15220

SEP-08145Teesta LDP - IV - New Jalpaiguri (NJP) 250 250 250 13814 D/C SEP-15220

Page 59: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

XYZ ()

.Bhavanapaddu TPP - Sri Kakulam1 D/C 400

Bilaspur (PS) - Dhanwahi (PS)2 D/C 765

.CSPL TPS - Raigarh Pooling Station (Near Kotra)3 D/C 400

Champa (Pool) - Dharamjaigarh 2nd Ckt4 S/C 765

.Chitrangi TPS - Vindhyachal Pooling Station5 D/C 765

Dwarkesh Energy TPP - Indore6 D/C 765

Ellora TPP - Seoni7 D/C 765

Gadarwara STPS - Jabalpur Pool8 D/C 765

Gadarwara STPS - Warora9 D/C 765

Gwalior - Morena10 D/C 765

110HEGCL TPP - Pune (AIS) (PG)11 D/C 400

Karchanna - Rewa Road Allahabad12 D/C 400

LILO of Both ckt Jabalpur - Orai at Dhanwahi (PS)13 2xD/C 765

LILO of Both ckt Wardha - Parli (PG) at Warora14 D/C 400

LILO of Gazuwaka - Behrampure at BhavanapadduTPP

15 D/C 400

LILO of Lonikhand - Kalwa at HEGCL TPP16 D/C 400

LILO of Raipur/Bhilai - Bhadrawati at Rajnandgaon17 D/C 400

.LILO of Tuticorin - Madurai at Ind Barath TPP(madras)

18 D/C 400

LILO of Vindhyachal - Jabalpur at Dhanwahi (PS)19 2xD/C 400

LILO of one ckt of Aurangabad - Padghe at Pune20 D/C 765

Maheshwaram (PG) - Mahboob Nagar21 D/C 400

Mohindergarh - Bhiwani22 D/C 400

.NCC Power TPP - Nellore Pooling Station (PG)23 D/C 400

NNTPS - Villupuram (Ginjee)24 D/C 400

Nizamabad - Yeddumailaram (Shankarapalli)25 D/C 400

.Orrisa UMPP - Jharsuguda Pooling Station26 D/C 765

.PLNGL TPP - Vadodra27 D/C 400

Parli (New) - Parli (PG)28 D/C 400

Parli (New) - Solapur29 D/C 765

Raigarh (Kotra) - Champa (Pool) 2nd Ckt30 S/C 765

.Raigarh TPS - Raigarh Pooling Station (Near Tamnar)31 D/C 400

Raipur (Pool) - Rajnandgaon32 D/C 765

Rajnadgaon - Warora33 D/C 765

Page 60: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

.Reliable TPP - Vindhyachal Pooling Station34 D/C 765

.107SJK TPS - Jabalpur Pooling Station 339 330 292 5935 D/C 400

Sasan UMPP - Vindhyachal (PS)36 S/C 765

Sipat - Bilaspur (3rd PS)37 S/C 765

.Suzlon wind farm - Bhachau (PG)38 D/C 220

Line under construction.30TRN TPP - Raighar (near Tamnar) Pooling Station39 D/C JUN-15400

Vindhyachal (PS) - Jabalpur (PS)40 D/C 765

Vindhyachal STPP - Vindhyachal (2nd Quad)41 D/C 400

Warora (PS) - Parli (New)42 D/C 765

Welspun Anuppur TPS - Vindhyachal Pooling Station43 D/C 400

Page 61: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

ADANI POWER LTD. (APL)

CommissionedLILO of Korba-Mopka at Swastic TPP 1321 D/C 132

Page 62: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

ATHENA CHHATTISGARH POWER LIMITED ()

50Athena Singhitarai - Raigarh Pooling Station (nearKotra)

75 75 73 401 D/C SEP-15400

.LILO of one ckt of MSCTL - Chandrapur at Singhitrai2 D/C 400

Page 63: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

BAJAJ ENERGY PVT. LTD. (BEPL)

Existing line.Balrampur-Utraula line1 D/C 132

Page 64: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

BHARAT ALUMINIUM CO. LTD. (BALCO)

Stage-I Clearance is awaited.46Balco - Dharamjaygar Pooling Station 72 72 70 421 D/C OCT-15400

Page 65: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

CORPORATE POWER LTD. (CPL)

6Corporate TPP - Jharkhand Pooling Station 111 D/C DEC-12400

.216Latehar - Namkum 320 293 274 1322 D/C DEC-12400

Page 66: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Costal Energen Private Limted (CEPL)

The total length of line is 38 KM and line will be extended from 22 ckm iscompleted of Mudrai - Tuticorin LILO line.

76Mutiara TPP - Tuticorin Pooling Station 32 32 32 221 D/C DEC-15400

Page 67: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

D.B.POWER CORP. LTD. (DBPCL)

Line completed. (Interim)30LILO of Raigarh - Raipur (3rd Ckt) at Baradhara TPP (Interim arrangement)

44 44 44 301 D/C MAY-13400

Page 68: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

DANS ENERGY PVT. LTD. (DEPL)

220 kv line from Jorethang switchyard to interconnection point has beencompleted as in interim arrangement.

20Jorethang HEP - New Melli 35 35 35 201 S/C AUG-15220

Page 69: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

DIRANG ENERGY PVT. LTD. (DEPL)

Gongri - Dinchang Pooling Station1 D/C 220

Page 70: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Darbhanga Motihari Transmission Company Limited ()

1) As per RFP, there was no forest in the route of transmission line. Involvementof forest is a deviation from RFP Documents.

2) Line has approx. 9 Km. of river bed. The unexpected increase in water levelhas affected the site work.

3) The no of power line crossings increased from 8 Nos. to 14 nos. w.r t RFPdocument.

4) ED increased to 12.5% from 12.36% and service tax to 14% from 12.36%.

5) Due to ongoing Assembly elections, material and manpower movement atlocations was severely affected leading to slow progress in Nov'15.6) Swachh Bharat cess @ 0.5 % is imposed on service tax.

JUL-16152LILO of both ckt Barh - Gorakhpur at Motihar 209 138 68 61 D/C AUG-16400

1) As per RFP, there was no forest in the route of transmission line. Involvementof forest is a deviation from RFP Documents.

2) There is change in co-ordinates at Muzaffarpur S/S end.

3) The no of power line crossings increased from 2 Nos. to 8 nos. w.r t RFPdocument.

4) ED increased to 12.5% from 12.36% and service tax to 14% from 12.36%.

5)Due to ongoing Assembly elections,material and manpower movement atlocations was severely affected, leading to slow progress in Nov'15.

6)Swachh Bharat cess @ 0.5% is imposed on service tax.7) Very high no. of fruit bearing trees in the route of transmission line severelyaffecting the site progress.

JUL-16129Muzaffarpur - Darbhanga line 173 128 125 402 D/C JUN-16400

Page 71: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

ESSAR POWER TRANSMISSION CO. LTD. (EPTCL)

Contractor is remobilising and work is getting started.670Mahan -Sipat 942 938 909 3941 D/C JUN-15400

.Navbharat TPP - Angul P.S. (PG)2 D/C 400

.Tori - Jhharkhand Pooling Station3 D/C 400

Page 72: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

GATI INFRASTRUCTURE LTD. (GATI)

Line commissioned.Chujachen HEP - Rangpo PS1 D/C 132

Commissioned 04/13. (Interim arrangement)47LILO of Melli - Gantok at Chuzachen (LILO point atnamthang)

91 91 91 472 D/C APR-13132

.LILO of one circuit of Rongnichu - Randpo at Bhasmay3 S/C APR-13220

Page 73: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

GMR ENERGY LIMITED (GMR ENERG)

.Alaknanda HEP - Joshimath1 D/C 220

For start up power,work completed 5/12.1LILO of Talchar -Meramundli at Kamalanga TPP 3 3 3 12 D/C MAY-12400

Commissioned in February 2014. Reported in July 2015.131Raikheda (GMR) - Raipur Pooling Station 181 181 181 1313 D/C JUL-15400

Page 74: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

GUPTA ENERGY PVT. LTD. (GEPL)

.LILO of one ckt of Bhadrawati -Parli at GEPL TPS1 D/C 400

Page 75: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

HIMACHAL SORANG POWERGEN PVT. LIMITED (HSPPL)

Commissioned 10/15.7LILO of one ckt Karcham wangto - Abdullapur atSorang HEP

11 11 11 71 D/C OCT-15400

Page 76: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

HIMGIRI HYDRO ENERGY PVT LTD (HHEPL)

Panan HEP - Mangan1 2xD/C 220

Page 77: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

IDEAL ENERGY PROJECTS LTD. (IEPL)

The progress of Koradi-Wardha line is slow . Forest clearence awaited.50LILO of Koradi II- Wardh(PG) at Bela TPP 75 75 75 501 D/C DEC-15400

Completed (Interim)0LILO of Mouda - Wardha at Bela 2 2 2 02 D/C NOV-12400

Page 78: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

IND BHARATH POWER INFRA LIMITED (IBPIL)

Progress of line has been affected due to severe ROW issue as land owner aredemanding hefty amount for crop/land compensation.

84Ind Barath - Jharsuguda pooling Station 125 120 117 601 D/C NOV-15400

47LILO of Rouekila - Raigarh at Ind Barath 72 72 72 472 D/C JUN-15400

Page 79: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

INDIABULLS POWER LTD. (IBPL)

Ready for commissioning 08/15.57Nasik - Bobleshwar (2nd Ckt) 152 152 152 571 D/C AUG-15400

Page 80: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

JAIN ENERGY TRADING LTD (JAIN ETL)

.Jain Energy TPS - Dharamjaygarh Korba Poolingstation

1 D/C 400

Page 81: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

JAL POWER CORP. LTD. (JPCL)

Rangit IV - New Melli line1 D/C 220

Page 82: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

JHABUA POWER LTD. (JHAPL)

Commissioned 05/15.131Jhabua Power TPS - Jabalpur Pooling Station. 207 207 207 1311 D/C MAY-15400

Page 83: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

KORBA WEST POWER COMPANY LIMITED (KWPCL)

There are RoW issues involved at 8 locations.42Avantha Bhandar TPS (Korba West) - Raigarh (Kotra) 64 64 60 221 D/C NOV-15400

Interim arrangement.10LILO of on Ckt of Raigarh - Raipur at AvanthaBhandar (Korba west ) TPS

22 22 22 102 D/C DEC-13400

Page 84: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

KSK ENERGY VENTURE LTD. (KSK LTD.)

Ready for Commissioning 06/15.105KSK Mahanadi (Warda Power) - Champa PoolingStation

164 164 164 1051 2xD/C JUN-15400

Commissioned 04/15. (Interim)71LILO of both ckt, of Raigarh - Raipur at Akaltara TPP 118 118 118 712 2xD/C APR-15400

Page 85: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

KVK ENERGY PVT. LTD. (KVK)

Work yet to Start.16LILO of Mendasal - Baripada at Nilanchal TPP 0 0 0 01 D/C JUN-16400

Page 86: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Kudgi Transmission Company Limited (KTCL)

Ready for Commissioning 08/15.FEB-1536Kudgi STPS - Narendra 46 46 46 361 2xD/C AUG-15400

The villagers are not allowing for any construction work at the respectivelocations and asking for huge compensation.Matter is brought to the notice of District Administration. These locations arenearer to 400/220 kV POWERGRID Bidadi substation. Being terminating point,no alternatives available for re-routing the line.

DEC-15186Madhugiri - Bidadi 256 229 216 502 D/C DEC-15400

DEC-15758Narendra (New) - Madhugiri 870 800 789 4703 D/C DEC-15765

Page 87: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

LANCO ENERGY (P) LTD,. (LEPP)

Work yet to start.48Babandh TPP - Angul Pooling Station 72 0 0 01 D/C DEC-16400

15LILO of Seoni - Wardha at Lanco Vidarbha TPS 162 D/C DEC-13765

.95Lanco Amarkantak - Champa Pooling Station 158 96 12 03 D/C APR-16400

8Phata HEP-Baramwari (Rudrpur) 20 0 0 04 D/C DEC-16220

.Routing of one circuit of Jorthong - New Melli viaRangit - IV

5 D/C DEC-13220

Detail survey completed section 164 approval received. Work yet to started.25Teesta VI HEP - Rangpo Pooling Station6 D/C 220

Page 88: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

MADHYA BHARAT POWER CORPORATION LIMITED (MBPCL)

Rongnichu - Rangpo Pooling Station1 D/C 220

Page 89: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

MALANA POWER COMPANY (MPCL)

Chango Yangthang - Ka Dogri Pooling Station1 D/C 220

.Ka Dogri - Jangi Pooling Station2 D/C 400

Page 90: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

NORTH EAST TRANSMISSION CO. LTD. (NETC)

Stringing Completed but cannot be commissioned since loop out arrangement byMeghalaya State Electricity Board is not ready at Byrnihat 400 kV S/S.

42Byrnihat - Azara (1st ckt) 124 124 124 421 D/C JUL-14400

Page 91: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

NORTH KARANPURA TRANSMISSION CO. LTD. (NKTCL)

NOV-13220Agra - Gurgaon1 D/C SEP-15400

NOV-13240Bareilly - Meerut2 S/C SEP-15765

NOV-1320Gurgaon - Gurgaon (PG)3 D/C SEP-15400

NOV-13220Lucknow - Bareilly4 S/C SEP-15765

NOV-13334Seoni - Sipat / Korba (Pooling).5 S/C SEP-15765

Page 92: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

NRSS XXXI (B) Transmission Limited (NRSSXXXI(B))

1)Due to change in co-ordinates at Malerkotla S/S end, the line length isincreased by 1.5 Km.2)Double level Gantry to be considered at Malerkotla end for termination ofKurukshetra & Amritsar lines. The same was not specified in the RFP. This leadsto use of Multi Circuit towers.3)As per RFP Documents, there is no involvement of forest in the route of line.However during survey, forest was found in the route of the line. Also, additionalexpenditure towards 'Greening Punjab Mission' is being incurred.4)The no. of power line crossings increased to 19 nos. from 15 nos. w.r.t RFPDocument.5)Court case at Location No. 35/0 & 13/2.6)Severe RoW at Malerkotla end.7)ED increased to 12.5% from 12.36% and service tax to 14% from 12.36%.8)Swachh Bharat cess @0.5% is imposed extra on service tax.9)NH Proposal is required to be endorsed by CEA.The same is required by NHofficials.10)Power line approval is taking capital time to be cleared by HVPNL.

SEP-16278Kurukshetra - Malerkotla line 375 257 160 271 D/C SEP-16400

1)Double level Gantry to be considered at Malerkotla end for termination ofKurukshetra & Amritsar lines. The same was not specified in the RFP. This leadsto use of Multi Circuit towers.2)As per RFP Documents, there is no involvement of forest in the route of line.However during survey, forest was found in the route of the line. Also, additionalexpenditure towards 'Greening Punjab Mission' is being incurred.3)Severe ROW at Malerkotla end.4)Increase in water level in Beas River has affected the pile work progress inSep & Oct 2015.5)ED increased to 12.5% from 12.36% and service tax to 14% from 12.36%.6)Swachh Bharat cess @0.5% is imposed extra on service tax.7)NH Proposal is required to be endorsed by CEA.The same is required by NHofficials.

SEP-16298Malerkotal - Amritsar line 412 235 185 152 D/C SEP-16400

Page 93: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

NSL NAGAPATNAM POWER PVT. LTD. (NSLNPPL)

Project Authority intimated that PGCIL yet to award construction of work.46NSL TPP - Angul 0 0 0 01 D/C 400

Page 94: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

PATRAN TRANSMISSION COMPANY LIMITED (PATRANTCL)

LILO of both ckt of Patiala - Kaithal at Patran1 D/C MAR-16400

Page 95: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

RELIANCE POWER TRANSMISSION LTD. (RPTL)

.Moti Khavdi TPP - Jam Nagar1 D/C 400

Progress stalled due to non-availability of MP state Forest Clearance (Stage-II) &Wildife Clearance.

JUN-11486Rajgarh (PG) - Karamsad (GETCO) 654 651 651 4822 D/C MAR-16400

Commissioned in March 2012. reported in july 2015.(Line Charged by passingShahjehanpur S/S).

16Rosa - Shahjehanpur (PG) 163 D/C JUL-15400

Page 96: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

RKM POWERGEN PVT. LIMITED (RKMPPL)

Commissioned (Interim Arrangement)LILO of Raigarh (Kotra) - Raipur at Uchpinda (InterimArrangement)

1 D/C 400

D/C portion of line is complete but the multi ckt portion of line is balance.57Uchpinda - Raigarh line 88 88 87 412 D/C JAN-16400

Page 97: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

SHIGA ENERGY PVT. LTD. ()

20Legship - New Malli 33 0 0 01 D/C MAR-16220

Detailed survey along the selected transmission line route has been completed.Actions for land acquisition and obtaining various clearances as well as finalizingthe design consultant are in progress. Prior approval from CEA for installation ofoverhead transmission line has also been received.Land acquisition for the first 7towers is completed and Tower foundation work was started during the month on4 tower locations.

14Tashiding - Legship 21 0 0 02 D/C 220

Page 98: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

SIKKIM HYDRO POWER LIMITED (SHPL)

LILO of one ckt of Legship - New Melli at Rangit-II1 D/C 220

Page 99: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

SKS POWER GENERATION LTD. (SKS)

Commissioned 05/15.55Binjkote - Raigarh (Kotra) Pooling Station 93 93 93 551 D/C MAY-15400

Interim arrangement removed.LILO of one ckt of Raigarh - Raipur at Binjkote TPP2 D/C 400

Page 100: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

STERLITE ENERGY LIMITED (SEL)

Construction of line yet to be started from LILO Point to Jhasugda S/S.Sterlite TPP - Jharsuguda1 2xD/C 400

Page 101: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

STERLITE GRID LTD. (SGL)

Commissioned 09/15.MAR-14758Dhramjaygarh - Jabalpur (JTCL) 992 992 992 7581 D/C SEP-15765

Commissioned 06/15.MAR-14274Jabalpur - Bhopal (BDTCL) 665 665 665 2742 S/C JUN-15765

Commissioned 06/15.MAR-14245Jabalpur - Bina (JTCL) 610 610 610 2453 S/C JUN-15765

Transmission licensee granted by CERC.Tariff adoption done by CERC.Forcemejure events flood,Border Ceasefire violation, unseasonal heavy snow fall,rainfall and land slides notices sent to all LTTC's.Change in Law:i.As per notificationSRO-105 by Dept.of Finance,Govt.of J&K GST has been changed from 10% to12 % w.e.f 01.04.2015.ii.Central Excise duty has been increased 12.36% to 12.5% w.e.f 01.03.2015. iii.Service tax has been increased 12.36% to 14% w.e.f01.06.2015.iv.Custom duty has been changed due to Finance Act.v.NewGuidelines by MoP No.3/7/2015-Trans dated 15.10.2015 for payment ofadditional Row compensation for Tower Base Area and corridor in addition toCrop Compensation,same has been intimated to all LTTCs.Force Majeureevent:Delayed in approval of Sec.164 under EA2003.

AUG-18270Jullandhar - Samba line 356 283 245 484 D/C FEB-16400

Force Majeure event: Delay in forest clearance.Transmission licensee grantedby CERC. Tariff adoption done by CERC.Project execution plan submitted to CEA & lead LTTC.Kharagpur S/s &Chaibasa S/s bays orientation has been shifted & project has been delayed dueto shifting of bays.Resurvey has to be done for route & forestidentification.Change in Law: i.Central Excise duty has been increased 12.36%to 12.5 % w.e.f 01.03.2015. ii.Service tax has been increased 12.36% to 14%w.e.f 01.06.2015.iii.Custom duty has been changed due to Finance Act. iv.NewGuidelines by MoP No.3/7/2015-Trans dated:15.10.2015 for payment ofadditional RoW compensation for Tower Base Area and corridor in addition tocrop compensation.The same has been intimated to all LTTCs.

MAR-16Kharagpur (WBSETCL) - Chaibasa (PG) 421 356 325 1045 D/C FEB-16400

Trans.licensee granted by CERC. Tariff adoption done by CERC.Force mejureevents flood,Border Ceasefire violation, unseasonal heavy snow fall,rain fall andland slides notices sent to all LTTC's.Change in Law:i.As per notification SRO-105 by Dept. of Finance,Govt. of J&K GST has been changed from 10% to 12 %w.e.f 01.04.2015.ii.Central Excise duty has been increased 12.36% to 12.5 %w.e.f 01.03.2015. iii.Service tax has been increased 12.36% to 14% w.e.f01.06.2015.iv.Custom duty has been changed due to Finance Act.v.NewGuidelines by MoP No.3/7/2015-Trans dated15.10.2015for payment of additionalRoW compensation for Tower Base Area and corridor in addition to CropCompensation,same has been intimated to all LTTCs.Force Majeureevent:Delayed in approval of Sec.164 under EA2003.

AUG-186LILO of Both ckt Uri - Wagoora at Amargarh6 D/C AUG-17400

Force Majeure event: Delay in forest clearance. Transmission licensee grantedby CERC. Tariff adoption done by CERC. Project execution plan submitted toCEA & lead LTTC. Bays at Purulia S/s & Ranchi S/s has been shifted by therespective Utilities due to which project has been delayed as resurvey has to bedone again for route & forest identification.In this regard Notice has been servedto LTTC's.Multiple changes in substation gantry coordinates and Issues ispending with WBSETCL.Change in Law: i.Central Excise duty has beenincreased 12.36% to 12.5 % w.e.f

MAR-16370Purulia PSP (WB) - Ranchi (PG) 302 96 61 07 D/C APR-16400

Page 102: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

01.03.2015. ii.Service tax has been increased 12.36% to 14% w.e.f 01.06.2015.iii. Custom duty has been changed due to Finance Act. iv.New Guidelines byMoP no.3/7/2015-Trans dated:15.10.2015 for payment of additional RoWcompensation for Tower Base Area and Corridor in addition to Cropcompensation. The same has been intimated to all LTTCs.

Force Majeure event: Delay in forest clearance. Transmission licensee grantedby CERC. Tariff adoption done by CERC.CERC has granted Liberty forextension of COD and additional tariff.TSP has started the work. Projectexecution plan submitted to CEA & lead LTTC. Critical RoW Issues Dist. Kota &Jhalawar in Rajasthanand Dist. Agar Malwa & Rajgarh in MadhyaPradesh.Change in Law: i.Central Excise duty has been increased 12.36% to12.5 % w.e.f 1st March 2015. ii.Service tax has been increased 12.36% to 14%w.e.f 1st June 2015. iii.Custom duty has been changed due to Finance Act. iv.New Guidelines by MoP no.3/7/2015-Trans dated:15.10.2015 for payment ofadditional Row compensation for tower base area and corridor in addition to cropcompensation. The same has been intimated to all LTTCs. v. Increase inChareges by West Central Railway for Plan & Drawings,departmentalsupervision and Site Survey Charges and Power,Traffic Blockage Charges to betaken from Power Supply Company & Concern.

FEB-16310RAPP - Shujalpur 521 521 521 4028 D/C DEC-15400

Transmission licensee granted by CERC. Tariff adoption done by CERC. ForestDiversion &Wild Life Clearance Proposals submitted.Force mejure eventsflood,Border,Ceasefire violation, unseasonal heavy snow fall,rain fall and landslides notices sent to all LTTC's.Wild Life proposal is pending withNBWL.Change in Law:i.As per notification SRO-105 by Dept. of Finance, Govt.of J&K GST has been changed from 10% to 12 % w.e.f 01.04.2015.ii.CentralExcise duty has been increased 12.36% to 12.5 % w.e.f 01.03.2015.iii.Servicetax has been increased 12.36% to 14% w.e.f 01.06.2015.iv.Custom duty hasbeen changed due to Finance Act.v.New Guidelines by MoP No. 3/7/2015-Transdated 15.10.2015for payment of additional RoW compensation for Tower basearea and corridor in addition to crop compensation,same has been intimated toall LTTCs.Force Majeure event:Delayed in approval of Section 164 underEA2003.

AUG-18574Samba - Amargarh line 783 72 0 09 D/C AUG-17400

Page 103: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

Shekhawati Transmission Service Company Limited (SKHWTTSCL)

court case pending, severe ROW problem, Railway crossing pending.FEB-1532Jhunjhunu - Nawalgarh line 108 77 68 01 S/C DEC-15220

court case pending, severe ROW problem, Railway crossing pending.FEB-1522Sikar - Nawalgarh line 76 55 40 02 S/C DEC-15220

Page 104: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

South East UP Power Transmission Company Limited (SEUPPTCL)

Karchana gantry not finalised80Bara - Karchana 124 0 0 01 D/C FEB-16400

442Gonda - Shahjanpur 542 279 140 02 D/C FEB-16400

2/0 ¿ 2A/0 stringing under hold due to construction of engineering college in theline corridor. Matter is pending with DM Mainpuri.

92LILO 400 Orai - Mainpur at Bah 135 133 131 513 D/C FEB-16400

1LILO of Obra - Sultanpur at Aurai 5 0 0 04 S/C FEB-16400

Completed.1LILO of Panki - Obra at Rewa Road 2 2 2 15 S/C FEB-16400

14LILO of Sarojini Nagar - Kursi RD at Sultanpur RD 186 D/C FEB-16400

186Mainpuri - Aligarh 219 215 204 247 D/C FEB-16400

3 locations are under hold since long due to land allocated for women PAC campin line corridor at Mainpuri. Matter has been taken up with DM Mainpuri.Approx 3.8 km route of each line passing through proposed refinery of BPCLnear Bara. Matter is pending with High Power committee as per directives ofHigh Courte Allahabad.

375Mainpuri - Bara Ckt-I 889 609 318 08 S/C FEB-16765

3 locations are under hold since long due to land allocated for women PAC campin line corridor at Mainpuri. Matter has been taken up with DM Mainpuri.Approx 3.8 km route of each line passing through proposed refinery of BPCLnear Bara. Matter is pending with High Power committee as per directives ofHigh Courte Allahabad.

750Mainpuri - Bara Ckt-II 899 830 721 1259 S/C FEB-16765

3 locations are under hold since long due to land allocated for women PAC campin line corridor at Mainpuri. Matter has been taken up with DM Mainpuri.

188Mainpuri - Unnao (Quad) 449 380 254 010 S/C FEB-16765

Completed.64Meja - Bara 83 83 83 6411 D/C FEB-16400

Karchana gantry not defined.58Rewa Road - Karchana 10212 D/C FEB-16400

Completed68Rewa Road - Meza 91 91 91 6813 D/C FEB-16400

188Tanda - Gonda line 241 92 54 014 D/C FEB-16400

Page 105: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TALCHER TRANSMISSION CO. LTD. (TTCL)

OCT-12290Behrampur - Gazuwaka1 D/C SEP-13400

OCT-12220Talcher II - Behrampur2 D/C SEP-13400

OCT-12161Talcher II - Rourkela3 D/C SEP-13400

Page 106: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TEESTA URJA LTD. (TUL)

GOKE Territorial Forest, MANJHA UCC Reserve Forest, GHUM SIMANAReserve Forest (Darjeeling & Kurseong division) - " In principle Approval (Stage-I)" has been accorded by MoEF, New Delhi on 28.05.2013. (30 Towers, TotalArea 47.4932 Ha.)Stage-II clearance for WB portion is pending. Kishanganj S/S of PGCIL isexpected to commission by Dec.15.

424Teesta III - Kishanganj 571 393 371 1601 D/C MAR-16400

Work in progress.72Teesta III - Rangpo line 98 94 91 262 D/C DEC-15400

Page 107: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

TORRENT POWER LTD (TOR. POW. (UNOSUGEN))

Work awarded to M/s Instalaciones. Inabemsa. Spian on May 2014. Routechanged after survey observations.

DGEN - Vadodara1 D/C 400

.DGEN TPS - Bharuch/Dahej Pooling Station2 D/C 400

Work awarded to M/s Instalaciones. Inabemsa. Spian on May 2014. Routechanged after survey observations.

Navseri - Bhasten3 D/C 220

Sandila TPP - ATS not defind4 D/C 400

Page 108: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

VANDANA VIDYUT LTD. (VVL)

Yet to start construction of 400 kV D/C line from Salora TPS - Dhranjaygarh (70KM). Interim arrangement available. LOI has been issued to M/s EBPL VenturesPvt. Ltd. , Bhilai. The line is expected to be completed by March, 2017.

60Salora TPS - Dharamjaigarh (Korba) (PGCIL) PoolingStation

841 D/C MAR-17400

Page 109: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

VEMAGIRI TRANSMISSION SYSTEM LIMITED (VTSL)

Bidding process to be taken upAPR-15410Khammam - Hyderabad line -I1 D/C 765

Bidding process to be taken upAPR-15455Vemagiri Pooling Station - Khammam line -I2 D/C 765

Page 110: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

VISA POWER LTD (VISA)

Work is under Construction.26Visa Power TPP - Raigarh Pooling Station 37 33 26 01 D/C JUN-15400

Page 111: REPORT INDICATING STATUS OF CONSTRUCTION OF …cea.nic.in/reports/monthly/transmission/2015/construction_tx-11.pdf · REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES

WESTERN U.P. POWER TRANSMISSION CO. LTD. (WUPPTCL)

Approval u/s 164 received16Ataur-Indirapuram 54 8 2 01 D/C DEC-15400

Approval u/s 164 received46Greater Noida-Noida (Sec -148) 130 66 16 02 D/C DEC-15400

Approval u/s 164 received17Greater Noida-Sikandrabad 53 53 53 173 D/C NOV-15400

Approval u/s 164 received53Hapur-Ataur 154 127 97 24 D/C DEC-15400

66Hapur-Greater Noida 187 168 103 05 S/C DEC-15765

Approval u/s 164 received14Hapur-dasna 44 28 14 06 D/C DEC-15400

11LILO of Meerut -Agra at Greater Noida 35 35 35 117 S/C NOV-15765

Approval u/s 164 received2LILO of Moradabad-Muradnagar at Hapur 7 7 2 08 D/C DEC-15400

Approval u/s 164 received15LILO of Muradnagar -Muzzafarnagar at Ataur 48 17 0 09 D/C DEC-15400

Approval u/s 164 yet received15LILO of Rishikesh -Kashipur at Nehtaur (Bijnor) 44 0 0 010 D/C DEC-15400

180Mainpuri-Greater Noida 494 494 494 18011 S/C NOV-15765

217Mainpuri-Hapur 602 590 546 8912 S/C DEC-15765

Trasmission Lines: Page 111 of 111

Legends

TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed