REPORT ON
Brainstorming Session for
Enhancing Performance in Drilling Surface
Activities
08th
June – 11th
June-2011
1
Oil India Limited
Brainstorming Session for
Drilling Surface Activities
TABLE OF CONTENTS
CONTENT PAGE NO
INTRODUCTION 2
PURPOSE 3
ESSENCE 3
MEMBERS INVOLVED 4
AREAS IDENTIFIED 5
IDEAS ON PREPARATOY SERVICE 10
IDEAS ON RIG DOWN-ILM-RIG UP
26
IDEAS ON OPERATION PHASE
IDEAS ON ENVIROMENTAL AND STATUTORY ISSUES
36
48
IDEAS ON PROJECTISATION 59
CONCLUSION & ACKNOWLEDGEMENT 66
2
OIL INDIA LIMITED
A report on the Brainstorming Session on Drilling Surface Activities held at Shillong
from 08th
June 2011 to 11th
June 2011
1.0 INTRODUCTION
The first brainstorming session on Exploration of Oil and Gas Field was held from 15th
to 18th
March, 2009 at Kaziranga, Assam. Subsequently, the second, third and fourth sessions were
held at Shillong, Guwahati and Kaziranga on “Development, Management and Monitoring of
oil and Gas field”, “Workover performance” and “Enhancing Performance in Down hole
Drilling Activities respectively during July 2009, February and May 2011. In line with these
earlier sessions, fifth Brainstorming session on Drilling Surface Activities was held from
08th
June 2011 to 11th
June 2011 at Shillong where a total of 21 participants from Drilling,
Production, Drilling-TS, G&R, Transport, Civil, Electrical, S&E, Administration, Security,
Chemical, Land, Field Engineering department were brought together in common platform to
deliberate on issues related to enhancing performance of Drilling Surface Activities.
Under guidance of B.P coaches, deliberation /discussion were held in various sessions with
the objective to find out practical solutions to enhance the drilling performance. All the
participants took active part in the discussion and came out with ideas in five different areas
and the same were presented to Director (Operation) and other senior officers on the final day
of the session i.e. on 11.06.2011.
The inaugural session was graced by ED (Operation), G.M (Drilling) and Head-FE.
Mr. K.K.Nath, ED (Operation) highlighted deteriorated performance of the drilling activities
and challenges faced by OIL. He expressed that the basic objective of conducting the session
at the outdoor location is to be free from all hassles of respective workplaces and focus on the
objective of the session. Strong support by the Corporate Management is the indicator of the
importance of the sessions. He said that being a Navaratna and Listed Company should not
make us complacent and the real challenge is sustainable growth. He called upon the
participants to focus and work-out what needs to be done to foster co-ordination between 37
odd departments of OIL to achieve drilling target. Maximizing Reserve Accretion and
Optimizing Production being the motto, he called-upon the participants to find out ways and
means to improve drilling performance.
Mr. Arpon Barbora, G.M (Drilling) said that of-late the drilling target of the company has not
been met which is an area of concern. The challenge for the group is to sit together and
analyse the reasons for failure and find out means to improve it. Saying that small things add-
up to great achievements, he said that time-saving in all surface operations is the essence and
asked the participants to work on it.
3
Mr. T. B. Chakraborty, Head–FE, called upon the participants to stress on root-cause analysis
of the breakdown for repetitive type of failures. He also called upon participants to advocate
for ETP in place of traditional age-old system of laying pit water disposal lines. He expressed
that at the time of raising P.R, specification of the critical items should be vetted by Field
Engineering Department. He said the need of the hour is not to do different things but to do
things differently. Stressing upon the concept of projectisation of jobs, he said that the start
and end dates of the jobs are to be fixed. He also called upon the participants to thrust upon
real teamwork and relationship management by sitting together and dialoguing to find out
what needs to be done. Calling the participants as the best resources, he wished them good
luck.
The brainstorming session concluded on 11th
evening and culminated after a presentation on
the ideas generated during these four days of brainstorming session to Director (Operations)
and other senior officers of OIL. All the ideas and views that emerged out of the discussions
during the four-day brainstorming session is complied and documented in this report.
2.0 PURPOSE
To identify areas and generate ideas proposing for enhanced performance in drilling Surface
Activities
3.0 ESSENCE
“Enhancing Surface Activities”
4
4.0 MEMBERS INVOLVED
The participants were executives from various departments viz. Drilling, Production, Drilling-
TS , G & R, Transport, Civil, Electrical, S&E, Admin, Security, Chemical, Land, Field
Engineering who are actively participating in the drilling support service activities. The
members are:
Sl. NO Name of the Participants Designation
1 B. Goswami C. E. – Drilling
2 A. K. Sarma C.E. – P. O.
3 Arabinda Das C. E. – Civil
4 D. M. Pradhan C.E-.Dilling
5 B. N. Sahoo C. E. (I/C) – S & E
6 M. K. Kotoki Dy. C. E. – Drilling
7 Anurag Gupta Dy. CE – FE
8 Rudrajit Brahma Dy. C. E. – Transport
9 Sahaja Nanda Das Dy. CED – TS
10 Poran Baruah Dy. C. E. – P. G.
11 Dilip Deori Manager – Land
12 Kankusubhan Gogoi S. E. - Elect
13 Jayanta Phookan S. E. – Civil
14 Dr. Jugal Hazarika Supdtg. Chemist
15 Lakhi Prasad Das S. E. – Transport
16 S. K. Pegu Dy. S. E. – Drilling
17 Nababrot Gogoi Dy. Supdtg – Geologist
18 Porag Gogoi Manager – Security
19 Jayanta Kr. Das Dy. Manager – Admin
20 Jaseng Langkhun Engineer – Drilling T. S.
21 Bijay Sharma Geologist
Mr. Arpon Barbora, G. M. – Drilling as Resource Person
Mr. Pranjit Deka, Head –P.R as Resource Person
The session was facilitated by B P Coaches Sri J.K.Sarma, Sri Prakash Deka and Sri Arindam
Bordoloi
5
5.0 AREAS IDENTIFIED
The participants identified five areas wherein the participants feel that they can contribute
ideas in these areas. The identified areas are
Area –I: Preparatory Services
Ideas
To carry out logistic survey during Pre-bid evaluation by a Team comprising of Civil,
Land, PR, S&E, Logistics, G&R, Geophysics, Drilling, Production
Video conferencing with approving authority & also visit of corresponding team to
corporate office for timely release of the proposed locations and clarification.
Field Head Quarter may be empowered to release Development location. Any
necessary policy change including DOP etc. may be looked into.
Detailed recee (demographic, logistics, staking) to be carried out in the released
location by a team (G&G, Land, Civil, PR, S&E) before carrying out detailed
topographical survey & issuing LAF-2. Opportunities for involving concerned NGOs
& academician for need analysis of the surroundings. Location co-ordinates may be
re-verified during plinth preparation.
To generate online tracking system of all LAFs with the help of IT
To extend rehabilitation/ welfare schemes to the land affected & nearby societies.
Regular compensation (annuity/pension) to affected land holder may be considered.
Advance land value payment along with surface compensation should be provided to
the land affected people through involvement of Circle Officer / Gao Burha / District
Authority before taking over possession.
To gear up additional infrastructure / facilities (GIS) with regards to Civil Survey,
Land Acquisition. To share facilities & infrastructure with Geophysics dept
Policy to be framed for acquiring Tea bearing land only after uprooting of tea bushes
by the TGA . Necessary compensation package may be thought about concerned tea
garden labours.
Liaison Officer on deputation from the Govt. Revenue Dept. in Land Dept.
6
Impress upon the Govt. Revenue Authority on top level (Principal Secretary of
Revenue etc.) for waiver of sale/ purchase permissions for land to be purchased by
OIL
To explore possibilities of engaging competent agencies to address land acquisition
bottle necks such frequent ownership change, vetting from District / State authorities
etc
To fix up and standardized ancillary specifications for CISF accommodation with their
top officials.
Use of pre fabricated structures for accommodation of CISF personnel instead of
present practice. Arrangement may be extended for OIL security also.
To take up with higher-ups of State PWD authorities for use of PMGSY roads for OIL
operations & maintenance etc.
Quality contractors: Mechanism to ensure that the resourceful first party contractors
are actually executing the work at site (instead of subcontracting that results in
delays)
Up gradation of Civil specifications & practices as regards to plinth preparation and
approach road in order to accommodate present day scenario & best practices.
Revisit benchmarks for lead time of contractual procedures after PR from present 4
months or more after introduction of e-tendering.
To explore possibilities of transporting construction materials from outside
Possibilities for acquiring land on lease basis instead of purchasing may be explored
7
Area –II: Rig down- ILM- Rig up
Ideas
Benchmarking of each phase of cycle time to be carried out.
Communicate Job assignment & Target dates to all concerned.
Minimise mud spillage on plinth.
There should be equipment maintenance /replacement policy in the company which
should be in line with the best maintenance practice.
A Multi-skilled manpower to be developed within the existing strength of employees
Improved coordination amongst concerned deptts /personnel.
Infrastructure facilities to be improved/standardized.
Custodian of Well Plinth to be assigned.
Grouping of rigs on the basis of zones.
Two shifts to be introduced instead of general shift duty.
Working Drawings to be reviewed for actual requirements at site for foundations and
mud drains as well as for storm waters and ETP.
Policy for prefabricated steel structures (sheds, canteens, camps etc.)
Introduction of a full time safety officer against each rigs as per best industry practice.
Manpower assigned against each rig not to be changed as far as practicable.
Area –III: Operation Phase
Ideas
Preparation of written standard Operating procedure for all drilling practices
pertaining to major drilling activities.
Introduction of the advanced technology, like top drive system, solid control system,
spinners for tubular, cementing unit , mud logging unit for all wells.
Improvement of the well site work culture.
8
Human resource development.
Upgradation of existing storage facility at the well site.
Important contractual services for certain specialized drilling operations should be
finalized on priority basis to minimize downtime of rigs.
Involvement of crane services during lowering of casing by picking up casing joint
from rack on to derrick floor.
Possibility of carrying out certain initial testing and completion operations beyond day
light.
Deployment of rig building crews during operation phase on shift basis.
Dedicated equipment for each drilling rig.
More officers should be available in the well site to assist the drilling engineer.
Study for Introduction of Slant rig concept for shallow deviated wells
Area –IV: Environmental and Statutory issues
Issues
Environmental clearance to be in place for all locations released till date.
Acoustic enclosure to be provided in generator /power pack engines
ETP (Effluent Treatment Plant) to be in place at all drilling wells.
HDPE Lining to be provided in all the wells before spudding.
Compulsory drill site restoration.
MVT (DGMS Issues)
PME (DGMS Issues)
Safety of Contractor personnel (DGMS Issues)
Implementation of Audit recommendations (OISD Issues)
9
Area –IV: Environmental and Statutory issues
Ideas
Land value payment should be made before ILM.
Consideration of appropriate representation from producing/future exploration areas in
direct and indirect employment.
Thrust in Pro - active CSR activities rather than reactive.
Reduction in implementation time of Projects under CSR.
All CSR activities/initiatives should be circulated/ informed to Installation managers
and Field going Executives.
Mass publicity of CSR activities with specific reference to Operational areas.
Minimizing Road traffic accidents involving OIL vehicles
Quick response team (QRT) to be introduced to reduce reaction time.
Introduction of Security Intelligence cell.
Area –V: Projectisation
Idea
Projectisation of in-house Drilling surface activities rig wise as a whole starting from
land acquisition to production testing.
Projectisation of in-house Drilling surface activities rig wise in parts:
Projectisation of in-house Drilling surface activities as a whole starting from land
acquisition to production testing.
Projectisation of in-house Drilling surface activities in parts area wise.
Projectisation of drilling surface activities outsourcing rig wise, as a whole starting
from land acquisition to production testing .
Projectisation of drilling surface activities outsourcing rig wise (in parts).
Projectisation of drilling surface activities outsourcing area wise as a whole starting
from land acquisition to production testing .
Projectisation of drilling surface activities outsourcing area wise (in parts).
10
AREA-I
PREPARATORY SERVICES
(Release of Location, Land acquisition,
Contract, Plinth approach & Study areas)
11
AREA-I: PREPARATORY SERVICES (Release of Location, Land acquisition, Contract,
Plinth approach & Study areas)
SUB AREAS:
1. Release of locations
2. Land acquisition
3. Contract
4. Plinth preparation
5. Study areas
SUB AREA- 1: RELEASE OF LOCATIONS
RECOMMENDATIONS – SHORT TERM
IMPLEMENTABLE IDEA-1: To carry out logistic survey during Pre-bid evaluation by
a Team comprising of Civil, Land, PR, S&E, Logistics, G&R, Geophysics, Drilling,
Production
WHY WE NEED
Presently not in place in OIL.
EXPECTED RESULTS
To map logistic challenges that may be encountered in order to prepare for future
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Formation of a Team (Civil, Land,
PR, S&E, Logistics, G&R,
Geophysics, Drilling, Production)
prior to each Pre-bid evaluation
D(E&D) 01.07.2011 CMD 01.10.2011
Study and to submit report on
communication facilities,
demography, logistics, topography of
the blocks being evaluated
Team
Within 15
days after
completion
of survey
D(E&D)
Within one
week of
submission
12
IMPLEMENTABLE IDEA-2: Video conferencing with approving authority & also visit of
corresponding team to corporate office for timely release of the proposed locations and
clarification.
WHY WE NEED
Early release of location.
EXPECTED RESULTS
To avoid possible delays in location release and timely proactive action initiation.
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Approval for adoption of methods GM(G&R) 01.08.2011 ED(O) 01.12.2011
To form corresponding G&G team GM (G&R)
Within One
week after
publishing
the final
proposal
report
D (E&D)
Within one
week after
video
conferencing
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA-1: Field Head Quarter may be empowered to release
Development location. Any necessary policy change including DOP etc. may be looked
into.
WHY WE NEED
To expedite location release and other follow on civil preparatory jobs
EXPECTED RESULTS
Faster location release and proactive civil preparatory jobs
13
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Put up proposal, incorporating two
tier check mechanism, for approval
in Field HQ itself
GM
(G&R)
01.07.2011 D (E&D) 01.09.2011
Once approved necessary correction
in DOP, other policies
RCE 01.10.2011 D (E&D) 01.12.2011
SUB AREA- 1: LAND ACQUISITION
RECOMMENDATIONS – SHORT TERM
IMPLEMENTABLE IDEA-1: Detailed recee (demographic, logistics, staking) to be
carried out in the released location by a team (G&G, Land, Civil, PR, S&E) before
carrying out detailed topographical survey & issuing LAF-2. Opportunities for involving
concerned NGOs & academician for need analysis of the surroundings. Location co-
ordinates may be re-verified during plinth preparation.
WHY WE NEED
Early acquisition of land for plinth preparation of location
Presently issue of revised LAF-2 for shifting surface position.
EXPECTED RESULTS
To avoid repetition of LAF-2 and other issues like effective CSR
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Formation of a Team (G&G,
Land, Civil, PR, S&E) for
detailed recee
GM (S)
Within one
week after
issue of
LAF-1
ED(O)/
RCE
15 days
from the
date of
formation
of the Team
Selection of NGOs &
academician (Local
Universities) for need
analysis of the surroundings..
GM
(PR&CC/A)/project
Head
Already
initiated for
Assam and
to be
initiated for
other areas.
RCE/
D(E&D) 31.09.2011
14
IMPLEMENTABLE IDEA-2: To generate online tracking system of all LAFs with the
help of IT
WHY WE NEED
Present traceable system is not adequate
Timely processing of LAF will help in acquisition of land and further work.
EXPECTED RESULTS
For effective monitoring
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Formation of group (G&R,
Land, Civil, ERP/IT) for
identifying traceability
structure
GM(G&R) 01/07/2011 ED(O) 01/09/2011
Finalisation of format &
preparation of report
Group/
Head-IT 01/10/2011 ED(O) 01/11/2011
IMPLEMENTABLE IDEA-3: To extend rehabilitation/ welfare schemes to the land
affected & nearby societies. Regular compensation (annuity/pension) to affected land
holder may be considered.
WHY WE NEED
Smooth operation throughout.
Example: Harryana State.
EXPECTED RESULTS
To earn goodwill during / after drilling.
To facilitate land acquisition.
15
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Formation of a team and
finalization of policy
GM(PR & CC/A) 01.08.2011 D(HR &
BD)
01.10.2011
To form team (PR, Finance,
Land & Civil) to asses
suitable scheme Vs.
identified target(s)
GM(PR&CC/A) 01/11/2011 ED(Ops) One week
after
submission
of report
To execute the scheme GM(PR&CC/A) Right after
issue of
LAF-2
RCE After 3
months
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA-1: Advance land value payment along with surface
compensation should be provided to the land affected people through involvement of
Circle Officer / Gao Burha / District Authority before taking over possession.
WHY WE NEED
To avert blockade by landowners during operations.
EXPECTED RESULTS
To carry out smooth preparatory services followed by other operations
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Put up proposal for approval Head-Land 01.09.2011 GM (S) 01.05.2012
To work out modalities &
execute after approval
Head-Land 01.08.2012 RCE 01.10.2012
IMPLEMENTABLE IDEA-2: To gear up additional infrastructure / facilities (GIS) with
regards to Civil Survey, Land Acquisition. To share facilities & infrastructure with
Geophysics dept.
16
WHY WE NEED
Presently not available with survey. It will help in accelerating in preparation of LAF-2
and land map.
EXPECTED RESULTS
To cope up with increased activities in the forthcoming 5 years plan (accelerated
drilling activities)
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Identify additional
infrastructures required & put
up proposal for purchase/hire.
Head-Civil 15.08.2011 GM (S) 01.06.2012
Liaison with Geophysics for
sharing the existing resources
(GIS)
CEC (P&D) 01.07.2011 Head-
Civil
15.07.2011
IMPLEMENTABLE IDEA-3: Policy to be framed for acquiring Tea bearing land only
after uprooting of tea bushes by the TGA. Necessary compensation package may be
thought about concerned tea garden labourers.
WHY WE NEED
To avert blockade by the tea garden labourers.
EXPECTED RESULTS
For smooth carrying out of civil preparatory jobs.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To form team for putting up
suitable proposal including
notes in place
Head-Land 01.07.2011 GM (S) 01.11.2011
If viable, action to be initiated
immediately
GM (S) 15.11.2011 RCE 15.04.2012
17
IMPLEMENTABLE IDEA-4: Liaison Officer on deputation from the Govt. Revenue
Dept. in Land Dept.
WHY WE NEED
To facilitate land acquisition at various stages of the revenue authorities.
EXPECTED RESULTS
Early release of land.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Proposal to be put up through
GM(HR) to competent
authority
Head-Land 01.07.2011 GM(S) 01.10.2011
IMPLEMENTABLE IDEA-5: Impress upon the Govt. Revenue Authority on top level
(Principal Secretary of Revenue etc.) for waiver of sale/ purchase permissions for land to
be purchased by OIL
WHY WE NEED
To cut lag time of 60 to 90 days
EXPECTED RESULTS
Early payment of land value.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To put up proposal to RCE in
this regard Head-Land 01.09.2011 D (O) 01.01.2012
If agreed, higher up
management to visit Revenue
dept, Govt of Assam for
waiver of sale-purchase
permission also to invite state
Revenue Officials for
interaction & guidance
RCE 15.01.2012 D(O) 01.05.2012
18
IMPLEMENTABLE IDEA-6: To explore possibilities of engaging competent agencies
to address land acquisition bottle necks such frequent ownership change, vetting from
District / State authorities etc
WHY WE NEED
Facilitate addressing land acquisition bottle necks such as frequent ownership change,
vetting from District / State authorities etc.
EXPECTED RESULTS
Quick acquisition of land
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To explore including visits to
other E&P companies &
frame policy and arrange for
deployment
Head-Land 01.09.2011 GM(S) 01.05.2012
SUB AREA- 1: PLINTH PREPARATION
RECOMMENDATIONS – SHORT TERM
IMPLEMENTABLE IDEA-1: To fix up and standardize ancillary specifications for
CISF accommodation with their top officials.
WHY WE NEED
To avoid last minute ambiguity
EXPECTED RESULTS
Timely deployment of CISF personnel
19
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To form team (Security, Civil,
CISF, Drilling) to fix up
standards & get vetted by
GM(HR)/DIG-CISF &
GM(OD&RS)
Head-Security 1/07/2011 GM (HR) 01.08.2011
After finalization of standards
the specifications to be passed
down suitably for preparation
of all forthcoming locations
Head-Civil 01.09.2011 GM (S) 01.10.2011
IMPLEMENTABLE IDEA-2: To take up with higher-ups of State PWD authorities for
use of PMGSY roads for OIL operations & maintenance etc.
WHY WE NEED
Presently there is confusion regarding use of PMGSY road by OIL
EXPECTED RESULTS
Availability of PMGSY roads for OIL operation
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
RCE accompanied by a team
GM(S), Head-Civil, Head-
Admn. to meet higher-ups of
State PWD authorities
(Dispur)
RCE 15.07.2011 D(O) 15.09.2011
20
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA-1: Use of pre fabricated structures for accommodation of
CISF personnel instead of present practice. Arrangement may be extended for OIL
security also.
WHY WE NEED
Safety hazard
Mobile accommodation
EXPECTED RESULTS
Time & money saving
To avoid last minute ambiguity
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Feasibility study by a team
(Civil, Security, CISF &
Drilling)
Head-Civil 01.08.2011 GM(S) 01.11.2011
If feasible, raise appropriate PR
for Services/infrastructure
Head-Civil 01.02.2012 GM(S) 01.05.2012
IMPLEMENTABLE IDEA-2: Quality contractors: Mechanism to ensure that the
resourceful first party contractors are actually executing the work at site (instead of
subcontracting that results in delays)
WHY WE NEED
Better and un-interrupted work.
EXPECTED RESULTS
Quality & timely work completion
21
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Explore for mechanism of
ensuring through processes
like vendor rating after
contract closure etc.
Head-Contract/
Civil
01.08.2011 GM(S) 01.12.2011
If suitable solution are found,
arrange for implementation
Head-Contract 01.03.2012 GM(S) 01.06.2012
IMPLEMENTABLE IDEA-3: Up gradation of Civil specifications & practices as
regards to plinth preparation and approach road in order to accommodate present day
scenario & best practices
WHY WE NEED
Present policy is being in force since inception
Reduction in Maintenance time & effort
Removal of time consuming bottlenecks during ILM & R/up as regards to Road & plinth
condition
EXPECTED RESULTS
Timely completion of rigging up work and subsequent better plinth maintenance
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To form team for finding out
industry best practices & their
relevance to OIL’s operations
(Civil, Drilling, Transport,
Finance)
Head-Civil 01.08.2011 GM (S) 01.12.2011
Viability report if suitable and
implement as policy
GM(S) 01.01.2012 RCE 01.05.2012
22
SUB AREA- 1: CONTRACT
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA-1: Revisit benchmarks for lead time of contractual
procedures after PR from present 4 months or more after introduction of e-tendering.
WHY WE NEED
Timely execution of civil work.
EXPECTED RESULTS
To reduce lead time
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Team for focused
benchmarking for reduction
of contract lead time
Head-Contract 01.08.2011 GM (S) 01.11.2011
Implement findings with
suitable appropriation &
revalidate
Head-Contract 01.02.2012 GM (S) 01.05.2012
PLEMENTABLE IDEA-2: Quality contractors: Mechanism to ensure that the
resourceful first party contractors are actually executing the work at site (instead of
subcontracting that results in delays)
WHY WE NEED
Better and un-interrupted work.
EXPECTED RESULTS
Quality & timely work completion
23
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
Explore for mechanism of
ensuring through processes
like vendor rating after
contract closure etc.
Head-Contract/
Civil
01.08.2011 GM(S) 01.12.2011
If suitable solution are found,
arrange for implementation
Head-Contract 01.03.2012 GM(S) 01.06.2012
IMPLEMENTABLE IDEA-3: Up gradation of Civil specifications & practices as
regards to plinth preparation and approach road in order to accommodate present day
scenario & best practices
WHY WE NEED
Present policy is being in force since inception
Reduction in Maintenance time & effort
Removal of time consuming bottlenecks during ILM & R/up as regards to Road & plinth
condition
EXPECTED RESULTS
Timely completion of rigging up work and subsequent better plinth maintenance
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To form team for finding out
industry best practices & their
relevance to OIL’s operations
(Civil, Drilling, Transport,
Finance)
Head-Civil 01.08.2011 GM (S) 01.12.2011
Viability report if suitable and
implement as policy
GM(S) 01.01.2012 RCE 01.05.2012
24
SUB AREA- 5: STUDY AREA
IMPLEMENTABLE IDEA-1: To explore possibilities of transporting construction
materials from outside
WHY WE NEED
Scarcity of quarry materials.
EXPECTED RESULTS
Timely completion of plinth.
To avoid Rig idling
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To carryout scarcity study,
involving experts, of
construction materials by a
team (Civil, Contract,
Finance)
Head-Civil 01.09.2011 GM(S) 01.12.2011
Scarcity study report if
feasible, implementation
policy to be framed
Head-Civil 01.01.2012 GM(S) 01.04.2012
IMPLEMENTABLE IDEA-2: Possibilities for acquiring land on lease basis instead of
purchasing may be explored
WHY WE NEED
To avoid procedural delays
EXPECTED RESULTS
Early release of land.
25
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To find out possibilities by a
team (Land, Finance, PR,
Legal Cell) including visit to
organizations who are already
following the method
Head-Land 01.08.2011 GM(S) 01.11.2011
To workout suitable
modalities if found feasible
GM (S) 01.12.2011 RCE 15.04.2012
IMPLEMENTABLE IDEA-2:
Improvement of working environment. i.e. office premises/ worksite
Enforcement of discipline & accountability
Due recognition to right person in right time.
Inculcate team spirit
HR policy to address competency profiling, mapping & succession planning.
System to assess skill-set requirement for each individual job/post and address the
gaps
WHY WE NEED
To facilitate better readdressal of key areas
EXPECTED RESULTS
Better relationships better understanding leading to better output
Better & timely work output
Motivate for better performance
Better understanding & higher output.
It will lead to transparency in career growth, highly motivated work force.
Right person in the right place. Better work out put.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW
BY WHEN
To study & execute where
ever appropriate. To take-up
bottom level fruits for
immediate action.
GM (OD&RS)/
GM (E)
01.08.2011 RCE 01.02.2012
26
AREA-II
RIG DOWN-ILM-RIG UP
27
AREA-II: RIG DOWN-ILM-RIG UP
The above activities involve all operations related to rig down after completion of production
testing, rig movement to the forward location and subsequent rig up.
RECOMMENDATIONS – SHORT TERM
IDEAS GENERATED:
IMPLEMENTABLE IDEA 1: Benchmarking of each phase of cycle time to be carried
out.
The basic philosophy of benchmarking of each phase is to ensure speedy and timely and
safe completion of all the operations related to a particular phase. In case of elapse of the
desired time frame, necessary corrective measure can be adopted accordingly.
WHY WE NEED: To fix a target and reduce cycle time.
EXPECTED RESULTS: Faster Rig-down, ILM & Rig-up.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN TO
INITIATEBY
REVIEW BY
WHOM REVIEW BY WHEN
• Copies of earlier
studies to be
provided.
• Discuss on the
earlier reports.
• Identify a pilot rig.
• Implement
recommendations
for the pilot rig.
HEAD-
DRILLING
(SERVICE) /
GM(ENGG)
GM
(OD&RS)
GM
(OD&RS)
01/07/2011
01/10/2011
15/11/2011
GM(OD&RS)
ED(O)
ED(O)
01/10/2011
(quarterly thereafter)
01/01/2011
(quarterly thereafter)
01/02/2012(quarterly
thereafter)
28
IMPLEMENTABLE IDEA 2: Communicate Job assignment & Target dates to all
concerned.
Concerned department (Civil, Electrical etc) are often not aware of the sequence of rig
materials movement. Communication of sequencing with assigned target date will enable
prompt support services.
WHY WE NEED: To avoid lack of co-ordination. Presently there is time loss because of
communication not in time.
EXPECTED RESULTS: The operation will be target driven. All concerned can take
proactive actions resulting in reduced rig cycle time.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• After rig-down has been
declared all concerned
department to be
communicated in the
fastest mode of
communication with the
target period of ILM
• Activities earmarked to all
concerned to also be
communicated
• Sequence of ILM to be
communicated in writing
to all concerned.
GM(ENGG) 01/07/2011 ED(O) 01/10/2011
(quarterly
thereafter)
IMPLEMENTABLE IDEA-3: Minimise mud spillage on plinth.
Draining of leftover mud on well plinth should be avoided.
WHY WE NEED: Spillage of mud to plinth hard standing areas causes slushy plinth
conditions & unsafe working environment during rig down.
EXPECTED RESULTS: This will minimize the spillage of mud to plinth hard standing
areas.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY WHOM
REVIEW BY
WHEN
• Draining of Mud
from Mud tanks
before rig-down
should be in a
planned manner.
HEAD-
CHEMICAL
01/07/2011 GM(OD&RS) 01/11/2011
(quarterly
thereafter)
29
IMPLEMENTABLE IDEA-4: There should be equipment maintenance /replacement
policy in the company which should be in line with the best maintenance practice.
Maintenance of the equipment plays a vital role in operation from it’s life & availability point
of view. Maintenance plan starts from the procurement stage of the equipment. Technology
induction, equipment specifications are also affected by the maintenance factor.
WHY WE NEED: As of now, OIL do not follow the equipment maintenance /replacement
policy.
For procurement of spares/services in case of emergency/breakdown, the procedure of
procurement is time consuming.
EXPECTED RESULTS: Reduce the equipment breakdown & increase the equipment life,
resulting in cost saving. Also it will save cycle time, avoiding untimely break downs.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• To study the best practice
followed by the industry.
• To implement the policy
• To carry out root cause
analysis of break down of
major equipment.
• HOD’s to be empowered
to procure
material/services for
critical items during
emergency through
imprest cash. The limit
may be fixed at rupees
one lakh.
GM (Engg)
GM (S)
01/07/2011
01/10/2011
01/07/2011
ED(O)
RCE
01/09/2011
(quarterly
thereafter)
01/03/2012
(quarterly
thereafter)
01/12/2011
(quarterly
thereafter)
30
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA 5: A Multi-skilled manpower to be developed within the
existing strength of employees
WHY WE NEED: To increase the skilled manpower availability and increase efficiency.
EXPECTED RESULTS: Reduce shutdown due to non availability of manpower thereby
reducing rig-cycle time.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• To train the manpower
for multiskilled jobs and
deploy accordingly.
GM
(OD&RS)/
GM(HR)
01/04/2012 ED(O) 01/04/2013
(quarterly
thereafter)
SHORT TERM MEASURES-ILM
IMPLEMENTABLE IDEA No. 6 : Improved coordination amongst concerned deptts
/personnels
WHY WE NEED: For better coordination & uninterrupted ILM
EXPECTED RESULTS: Reduced ILM time.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW BY WHOM REVIEW
BY WHEN
• A recce to be
organized to
finalize the rig
movement route
by a multi
disciplinary
team(including
compensation
committee).
HEAD-
TRANSPORT
15/07/2011 GM(ENGG)/GM(OD&RS) 01/10/2011
(quarterly
thereafter)
31
IMPLEMENTABLE IDEA No. 7: Infrastructure facilities to be improved/standardized.
WHY WE NEED: At present the food quality & hygiene of Canteen facilities is not up to the
mark. If proper control of food quality is carried out by concerned authority regularly the
quality can be improved.
During ILM period there is no canteen in well site, hence crew members tend to go outside
the well site for food, thereby causing manhour losses.this is a necessity to provide good and
same quality of food to employees and executives.
EXPECTED RESULTS: Faster ILM & good health to all personnel. Better housekeeping &
living standards.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY WHOM
REVIEW BY
WHEN
• Common Canteen
Facilities: There is no
quality control on food
quality & hygiene.
Regular inspections
from ER & introduction
of mineral water in
canteen. Canteen
facilities to start prior to
ILM.
• A policy to be
introduced to use
prefabricated steel
structures for all sheds,
canteens, camps etc.
HEAD-ER
HEAD-
CIVIL/GM(S)
01/07/2011
01/07/2011
GM(OD&RS)
GM(OD&RS)
01/10/2011
(quarterly
thereafter)
01/10/2011
(quarterly
thereafter)
32
IMPLEMENTABLE IDEA No. 8 : Custodian of Well Plinth to be assigned.
WHY WE NEED: At present in most cases after completion of civil construction of the
plinth, it is handed over to Drilling. However, in case the rig movement gets delayed the
plinth is damaged by miscreants because of non availability of custodian.
EXPECTED RESULTS: Ensure protection to well plinth from miscreants & encroachment.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
Formulation & issuance of
guidelines from the
management for custody of
the plinth at various stages
from land release to
production stage.
GM
(OD&RS)
01/07/2011 ED(O) 01/11/2011
(quarterly
thereafter)
IMPLEMENTABLE IDEA No. 9: Grouping of rigs on the basis of zones.
WHY WE NEED: To reduce the inter location distance.
EXPECTED RESULTS: Minimize ILM time.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• To identify the zones
operation wise.
• Identify rigs and group
them as per zones.
GM(OD&RS) 01/07/2011 ED(O) 01/05/2012
(quarterly
thereafter)
SHORT TERM MEASURES –RIG –UP
IMPLEMENTABLE IDEA No. 10 : Two shifts to be introduced instead of general shift
duty.
WHY WE NEED: To increase working hours & reduce cycle time.
EXPECTED RESULTS: Rig-up time will reduce. This will ultimately reduce rig cycle
time.
33
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• To select a well as pilot
project.
GM(OD&RS) 01/07/2011 ED(O) 01/11/2011
(quarterly
thereafter)
IMPLEMENTABLE IDEA No. 11: Working Drawings to be reviewed for actual
requirements at site for foundations and mud drains as well as for storm waters and
ETP.
WHY WE NEED: At present there is no standard drawing for the storm water drains & mud
drain on the plinth. Hence the drainage system is not effective, which causes water stagnation
on plinth.
EXPECTED RESULTS: This will minimize the spillage of mud to plinth hardstanding
areas. Minimise surface pollution & ensure better housekeeping, safety to all.
ACTION(S) TO
INITIATE
WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW BY
WHOM
REVIEW
BY WHEN
• To review all rig-
layout drawings
including ETP
HEAD-
CIVIL
01/07/2011 GM(S)/GM(OD&RS) 01/10/2011
(quarterly
thereafter)
LONG TERM MEASURES: Rig-Up
IMPLEMENTABLE IDEA No. 12 : Policy for prefabricated steel structures
(sheds, canteens, camps etc.)
WHY WE NEED: The existing practice of using bamboo structures is not safe and
causes discomfort to all.
EXPECTED RESULTS: Speedy construction & safe structures & better
accommodation at site.
34
ACTION(S) TO
INITIATE
WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• To form a team to
assess the
requirements,
Make the design
& drawings.
• Submission of
report
• Procurement &
implementation
GM
(S)/GM(OD&RS)
Team
Head-
Materials/Head-
Civil
01/07/2011
01/08/2011
01/12/2011
ED(O)
GM (S)
GM (S)
01/08/2011(quarterly
thereafter)
01/09/2011(quarterly
thereafter)
15/12/2011(quarterly
thereafter)
IMPLEMENTABLE IDEA No. 13: Introduction of a full time safety officer against each
rigs as per best industry practice.
WHY WE NEED: We do not have a full time Safety Officer at well site. Safety norms are
not appropriately followed in all rigs.
EXPECTED RESULTS: Ensure safety measures at all time. Relief to the IM & shift DE.
ACTION(S) TO
INITIATE
WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
• Appoint Safety officers
in all rigs
GM
(OD&RS)/HEAD
(S&E)
01/07/2011
ED(O)
01/05/2012
(quarterly
thereafter)
35
IMPLEMENTABLE IDEA No. 14: Manpower assigned against each rig not to be
changed as far as practicable.
WHY WE NEED: Manpower change in rig causes various maintenance problems, hampers
progress.
EXPECTED RESULTS: Belongingness to the rig
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY
WHOM
REVIEW BY
WHEN
To provide dedicated
manpower against each
rig
GM
(OD&RS)
15/07/2011
ED(O)
15/10/2011
(quarterly
thereafter)
WHAT TO STOP: 1. Stop transporting unnecessary extra materials during ILM
WHY WE NEED: Many materials/load are being moved along with the rig from location to
location without any use, such as scrap bunk houses, pipe cut pieces, empty spools, damaged
spare parts etc.
EXPECTED RESULTS: Save money and ILM time
ACTION(S) TO
INITIATE
WHO TO
INITIATE
WHEN TO
INITIATE
BY
REVIEW
BY WHOM
REVIEW BY
WHEN
• Identify unnecessary
materials & transfer it to
designated yard.
• GM(Drilling) to write to
all IM for identifying the
same.
IM
01/07/2011
GM(OD&RS)
01/09/2011
36
AREA-III
OPERATION PHASE
(STARTING FROM SPUD-IN)
37
AREA-III: OPERATION PHASE
IDEAS GENERATED:
1. Preparation of written standard Operating procedure for all drilling practices
pertaining to major drilling activities.
2. Introduction of the advanced technology, like top drive system, solid control system,
spinners for tubular, cementing unit , mud logging unit for all wells.
3. Improvement of the well site work culture.
4. Upgradation of existing storage facility at the well site.
5. Important contractual services for certain specialized drilling operations should be
finalized on priority basis to minimize downtime of rigs.
6. Involvement of crane services during lowering of casing by picking up casing joint
from rack on to derrick floor.
7. Possibility of carrying out certain initial testing and completion operations beyond day
light.
8. Deployment of rig building crews during operation phase on shift basis.
9. Dedicated equipment for each drilling rig.
10. More officers should be available in the well site to assist the drilling engineer.
11. Study for Introduction of Slant rig concept for shallow deviated wells.
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA - 1
Preparation of written standard Operating procedure for all drilling practices
pertaining to major drilling activities.
A standard Company specific operating procedure for each and every drilling related
activity is pre requisite for smooth executions of any operation. Although the same being
carried out now is based on work experience and expertise, it leaves space for
improvement and it involves certain safety hazards. Besides the present practice has
tendency to become person specific with varying level of output for the same activities.
In view of this it is felt that a written document in the form of a standard operating
procedure should help in the form of a guideline for cost effective trouble free
38
operations which will lead to enhancement of productivity. Initial guide line in the form
of written document can be liberating because it imbues a different kind of thinking to
start with. It gives people space to think about operations and making instant decisions
combining his own skills.
WHY WE NEED
Standard operating procedure helps to carry out all the operation smooth and in a
standardized manner.
For better well management during drilling.
For introduction of uniformity in operational practices.
Written standardized operating procedures will include:
o Operational steps for each drilling activities.
o Drilling processes and problems, their management and remedies.
o Information on risk & safety of each activity.
EXPECTED RESULTS
Smooth and trouble free operations.
Reduced commercial days.
Standardization of operation procedure.
Minimization of communication errors.
Minimizing Decision Making Time.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
1. Formation of team for preparation
of written Standard Operating
procedure.
2. Study to hire services of an
international expert for formulation of
the same
GM
(OD & RS)
Above team
01.09.2011
ED(O) 01.12.2011
(quarterly
thereafter)
39
IMPLEMENTABLE IDEA - 2
Introduction of the advanced technology, like top drive system, solid control system,
spinners for tubular, cementing unit , mud logging unit for all wells.
Advantages of Top Drive system are manifold and are of particular help while drilling
through extended shale. The point has been deliberated at other forums also. An experimental
service initially on hiring basis may be thought of as first step in a deeper well to actually
asses its numerous advantages. Similarly advantages of an advanced solid control system are
mandatory to drill a quality deep hole with minimum reservoir damage and minimal surface
environmental issues. Presently we are already using LMSS in selective wells. Same should
be a general practice for all wells. Concept of zero discharge system should be on the agenda
in a phased manner.
WHY WE NEED
• Advanced technology like TDS, solid control system will result in quality hole in
lesser time.
• A quality hole with quality cementation would result in better productivity.
•
EXPECTED RESULTS
• Quality hole in less time.
• Reduced pollution hazards
40
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
Hiring of TDS on an experimental
basis GM
(OD &
RS)
01.04.2012
ED(O)
30.09.2012
(quarterly
thereafter)
Introduction of advanced solid
control system in line with other
national oil companies HEAD
(D/PLG)
01.09.2011
GM
(OD & RS)
31.12.2011
(quarterly
thereafter)
Cementing unit with hired services
for oil string cementation. HEAD(D-
S)
01.09.2011
GM
(OD & RS)
31.12.2011
(quarterly
thereafter)
IMPLEMENTABLE IDEA – 3
Improvement of the well site work culture.
Although it must be conceded at the very beginning that our work culture still stand
among the very best of all public enterprises, it has been acutely felt that there is a scope for
further improvement. It is observed that disciplines in our organization are stagnating at best if
not improving at all. Furthermore due recognition in time for the right person as well as
assessment of skill and competency level for work persons are deficient from satisfactory
level. Accordingly a third party source may be thought of for skill and competency assessment
for all and recognition and development upon the same. A more accountable work
environment at well sites with specific assignment may be thought of.
41
WHY WE NEED
• Increase work efficiency.
• Revive sense of belongingness and interrelationship.
EXPECTED RESULTS
• Better relationship.
• Better team work.
• Enhanced productivity.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW BY
WHEN
1.Assigned responsibility
for specific task to work
person for the entire shift
duration and
accountability.
2.Strict maintenance of T
card by all work persons &
officers at well site.
3.Assessment of skill and
competency level of work
person and officers thereby
assignment , reward and
development accordingly
by third party source.
accordingly by third party
source.
Drilling
Engineer
&
Installation
Manager
Head ER
GM(OD&RS
)
01/08/2011
01/03/2012
Head D/O
GM(OD&
RS)
01/01/2012(quarterly
thereafter)
01/12/2012
(quarterly thereafter)
42
RECOMMENDATIONS – SHORT TERM
IMPLEMENTABLE IDEA– 4
Human resource developments.
WHY WE NEED
HR development is the backbone for success and growth of a company
Helps to increase competency level to carry out critical jobs.
EXPECTED RESULTS
Improvement of skill and competency.
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
1. To provide job specific training
for enhancing skill and
knowledge.
2. Frequent application Reward &
recognition system.
Departmental
Heads
Already
initiated
Concerned
GMs
Quarterly
.
IMPLEMENTABLE IDEA – 5
Important contractual services for certain specialized drilling operations should be
finalized on priority basis to minimize downtime of rigs.
.
WHY WE NEED
To prevent unnecessary idling of rigs, like idling of S-7 rig due to non availability of
specialized window cutting services.
EXPECTED RESULTS
To prevent unnecessary idling of rigs.
43
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW BY
WHEN
Finalization of
specialized drilling
operation related
contracts.
GM(G&R)/
GM(OD&RS)
Already
initiated
ED(O)
01.09.2011(quarterly
thereafter)
.
IMPLEMENTABLE IDEA – 6
Involvement of crane services during lowering of casing by picking up casing joint from
rack on to derrick floor
.
WHY WE NEED
Present oil practices of Lowering of bigger sized casing to deeper depth is laborious and time
consuming.
EXPECTED RESULTS
For quicker lowering of casings.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW BY
WHEN
Availability of cranes with
competent personnel to
assist casing lowering.
CET(F)
01.09.2011
HEAD(DO)
01.12.2011(quarterly
thereafter)
.
IMPLEMENTABLE IDEA –7
Possibility of carrying out certain initial testing and completion operations beyond day
light.
Certain production testing operations like packer setting, bridge plug setting etc. should be
considered for carrying out beyond daylight after considering all safety aspects.
44
WHY WE NEED
It will help to reduce production testing time.
EXPECTED RESULTS
To reduce cycle days.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW BY
WHEN
Carrying out operations like
packer setting beyond day
light. Other possible
operations may be
identified.
GM(P-O)
15.08.11 ED(O)
31.12.2011(quarterly
thereafter)
.
IMPLEMENTABLE IDEA – 8
Deployment of rig building crews during operation phase on shift basis.
Rig building crew should be considered for deployment on shift basis to attend breakdown
problems round the clock particularly at odd hours to minimize downtime.
WHY WE NEED
Helps to take immediate remedial action in case of failure of the equipment.
EXPECTED RESULTS
Reduced down time
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY WHOM
REVIEW BY
WHEN
Deployment of rig building
crews during operation
phase on shift basis.
HEAD(DS)
15.08.11
GM(OD&RS) 30.03.12(quarterly
thereafter)
45
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA –9
Dedicated equipment for each drilling rig.
Key drilling equipment/items like all tubular of non consumable nature, surface BOPs with
accessories, kill pumps, casing lowering gears etc should be available separately for each rig.
Surface BOPs are also required as per OISD RP.
WHY WE NEED
To prevent shortage of critical drilling items during operational phase.
EXPECTED RESULTS
• Better acquaintance and ownership feeling.
• Increased drilling efficiency
ACTION(S) TO INITIATE WHOTO
INITIATE
WHEN
TO
INITIATE
REVIE
W BY
WHOM
REVIEW BY
WHEN
1. Dedicated Casing gears for
each drilling rig.
2. Surface BOP for 20” casings
3. Other identified dedicated
equipment for each rig
GM(OD&RS)
HEAD(D-PLG)
HEAD(D-PLG)
Already
initiated
01.04.2012
01.04.2012
GM(OD
&RS)
30.09.13(quart
erly thereafter)
01.08.2012
01.08.2012
46
IMPLEMENTABLE IDEA – 10
More officers should be available in the well site to assist the drilling engineer.
It is a known fact that in all rigs of Drilling service providers, a number of competent persons
of officers rank present throughout the entire shift duration which translates to ease of
operation and shared responsibilities. In contrast SICs in our rigs are stressed to carry out the
operation in the absence of the same.
WHY WE NEED
To provide technical support and guidance to enhance overall operational efficiency.
EXPECTED RESULTS
For smoother operation and increase efficiency.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW BY
WHEN
1.A committee should be
formed to study and
initiate action in this
regard
2. As a pilot case 12
hours shift concept with
well site camp should be
introduced.
ED(O)
GM(OD&RS)
01.09.2011
01.09.2011
D(E&D)
ED(O)
01.12.2011(quarterly
thereafter)
01.12.2011(quarterly
thereafter)
47
RECOMMENDATIONS – SHORT TERM, after feasibility study and cost benefit
analysis.
IMPLEMENTABLE IDEA – 11
Study for Introduction of Slant rig concept for shallow deviated wells.
It is a easily movable rig with a capability drill a deviated hole with fix inclination
throughout entire course length. This alone will result a quality hole with lesser energy and
material consumption.
WHY WE NEED
Possibility of drilling a deviated hole with a fixed inclination from surface to target to obtain
desired horizontal displacement
EXPECTED RESULTS
• Fast rig moves - is easily disassembled for highway transportation and can be moved
fast.
• Fully automated, hence provides a highly safe working environment.
• Less manpower requirement.
.
ACTION(S) TO
INITIATE
WHOTO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY WHOM
REVIEW BY
WHEN
Study for introduction of
Slant rig concept for
shallow deviated wells.
HEAD
(D-PLG)
31.10.11 GM(OD&RS)
15.04.12(quarterly
thereafter)
48
AREA – IV
ENVIORMENTAL AND STATUTORY
ISSUES
49
Environmental and Statutory Issues.
HSE plays a vital role in the industry today. Failure to comply with statutory HSE
guidelines and beyond, many a times leads to closure of wells by statutory bodies and public.
As a result drilling activity is adversely affected.
Realizing this important function, a thorough discussion in this brainstorming session
was done in HSE and other related areas and a common understanding was arrived to address
key HSE , PR ,Security and related issues.
ISSUES:
The issues that were discussed in length during the session are as under:
Environmental clearance to be in place for all locations released till date.
1. Acoustic enclosure to be provided in generator /power pack engines
2. ETP (Effluent Treatment Plant) to be in place at all drilling wells.
3. HDPE Lining to be provided in all the wells before spudding.
4. Compulsory drill site restoration.
5. MVT (DGMS Issues)
6. PME (DGMS Issues)
7. Safety of Contractor personnel (DGMS Issues)
8. Implementation of Audit recommendations (OISD Issues)
IDEAS:
The ideas generated during the session are as under:
1. Land value payment should be made before ILM.
2. Consideration of appropriate representation from producing/future exploration areas in
direct and indirect employment.
3. Thrust in Pro - active CSR activities rather than reactive.
4. Reduction in implementation time of Projects under CSR.
5. All CSR activities/initiatives should be circulated/ informed to Installation managers
and Field going Executives.
6. Mass publicity of CSR activities with specific reference to Operational areas.
7. Minimizing Road traffic accidents involving OIL vehicles
8. Quick response team (QRT) to be introduced to reduce reaction time.
9. Introduction of Security Intelligence cell.
The following issues require further studies:
• Reclamation of abandoned wells.
• Land acquisition on Lease.
• Timely implementation of Field Development plan.
• Camp accommodation for far flung locations.
50
• Taking up with Govt. Of India for EC at the bidding stage itself.Modern security
equipment/Infrastructure and Skilled Supervisory staff of Security department.
ISSUE 1 - Environmental clearance to be in place for all locations released till
date.
Why
Statutory Compliance.
Expected Results:
• Statutory compliance.
• Better environment management.
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by when
Queries raised by
MOEF to be
replied
GM (OD&RS) 01/07/2011 ED (Ops) 01/08/2011,
thereafter every 15
days
Central EC cell to
be formed at FHQ
ED (Ops)/Head
(S&E)
01/08/2011 RCE 01/09/2011,
thereafter every
one month.
ISSUE 2 - Acoustic enclosure to be provided in generator /power pack engines
EXPECTED RESULTS:
• Minimize public complain.
• Statutory compliance.
• Better working environment
WHY WE NEED
Statutory Compliance
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by when
To provide Acoustic
enclosures in all
power pack engines
GM
(OD&RS)/GM(E)
01/07/2011 ED (Ops) 01/08/2011,
thereafter every 15
days
51
ISSUE 3 : - ETP (Effluent treatment plant) to be in place at all drilling wells.
EXPECTED RESULTS:
• Better effluent management at site.
• Conservation of natural resources.
• Eliminating laying of line.
• Minimize public complain.
WHY WE NEED:
Statutory Compliance
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by when
To provide ETP in
all drilling wells
GM (OD&RS) 01/07/2011 ED (Ops) 01/08/2011,
thereafter every 15
days
ISSUE 4: - HDPE lining to be provided in all the wells
EXPECTED RESULTS:
• Statutory compliance.
• Prevention of seepage/leaching.
• Minimize public complain
•
WHY WE NEED:
Statutory Compliance
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
To provide HDPE
lining in all drilling
effluent pits.
HEAD (Civil) 01/07/2011 GM (S)/GM
(OD&RS)
01/08/2011,
thereafter every 15
days
52
ISSUE 5: - Compulsory drill site restoration.
EXPECTED RESULTS:
• Aesthetics.
• Pollution free environment.
• Minimize Public complain.
WHY WE NEED:
Statutory Compliance
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
Restoration policy to
be finalized and
implemented in all
drilling wells
Head –Civil/
Head - S&E
01/07/2011 GM (OD&RS) 01/08/2011,
thereafter every 15
days
ISSUE 6 – Mines Vocational Training
EXPECTED RESULTS:
Trained manpower.
Reduction in accident potential.
Better understanding of the organizational function
WHY WE NEED:
Statutory Compliance.
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
MVT to all
employees including
contractor personnel.
GM (OD&RS) 01/07/2011 ED (Ops) 01/08/2011,
thereafter every 15
days
53
ISSUE 7 – PME
EXPECTED RESULTS:
Better health.
Reduction in accident potential.
Increase in work efficiency.
WHY WE NEED:
Statutory Compliance.
Action to initiate Who to initiate
When to initiate
Review by Whom
Review by when
Formulate PME policy for all
contractor personnel.
Complete PME of all employees
including contractor personnel.
GGM
(MS)
GM
(OD&RS)
01/07/2011 RCE 01/08/2011,
thereafter every
30 days.
ISSUE 8 – Safety of Contractor personnel as per the 10th
Conference on Mines Safety.
EXPECTED RESULTS:
Reduction in accident potential.
Better understanding of work responsibilities.
WHY WE NEED:
Statutory Compliance.
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
To ensure
compliance of the
stipulations by the
contractors.
GM (OD&RS) 01/08/2011 ED (Ops) 01/09/2011,
thereafter every 30
days.
ISSUE 9 : Implementation of Audit recommendations
EXPECTED RESULTS:
Ensure better safety standards.
Avoid queries from Ministry/ Litigation.
54
WHY WE NEED
Statutory requirement
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
Time bound action
plan for
implementation of
long pending
recommendation
GM (OD&RS) 01/07/2011 ED (Ops) 01/08/2011,
thereafter every 20
days.
• IMPLEMENTABLE IDEA 1 -Land value payment should be made before ILM.
EXPECTED RESULTS:
• Minimizing local problems.
WHY WE NEED:
To avoid any stoppage/delay in operations
Action to initiate Who to
initiate
When to initiate Review by
Whom
Review by when
Discussion with higher
Govt. Authority for
support and priority in
clearing land documents.
GM (S) 01/07/2011
RCE
1/08/2011
Outsourcing of the process
of getting updated
documents from Pattadars
and long pending payment
issues
Head - Land 1/8/2011 GM (S)
1/10/2011
IMPLEMENTABLE IDEA 2 - Consideration of appropriate representation from
producing/future exploration areas in direct and indirect employment.
EXPECTED RESULTS:
• Minimizing local problems.
• Enhancing goodwill.
55
WHY WE NEED
• To avoid agitations.
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
Review of different
policies
RCE 01/08/2011 Director
HR & BD
01/01/2002
IMPLEMENTABLE IDEA 3 - Thrust in Pro - active CSR activities rather than
reactive.
• EXPECTED RESULTS:
• Minimizing local problems.
• Enhancing goodwill.
WHY WE NEED:
To create goodwill and confidence amongst people.
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
Need assessment
survey for
assessment of
suitable CSR
activities.
GM (CC&PR) 1/8/2011 RCE 1/11/2011
IMPLEMENTABLE IDEA 4: Reduction in implementation time of Projects under CSR.
EXPECTED RESULTS:
• Faster implementation of area development projects.
WHY WE NEED:
To earn confidence and belief of people.
56
Action to initiate Who to initiate When to initiate Review by
Whom
Review by when
More financial
sanctioning power in
Field Headquarters
for CSR projects.
GM (CC&PR) 1/8/2011 RCE 1/10/2011
Review of CSR
policy as per DPE
Guideline & freezing
of Administrative
guideline.
Head –PR&CC 1/9/2011 GM (CC&PR) 1/11/2011
IMPLEMENTABLE IDEA 5: Mass publicity of CSR activities with specific reference to
Operational areas.
EXPECTED RESULTS:
• Better awareness of OIL activities.
• Image building.
WHY WE NEED:
To focus on OIL’S contribution to the society.
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by
when
Communicate through print
and electronic media as well
as other modes of publicity
such as Road Show, Street
Plays, hoardings etc.
GM (CC&PR) 1/9/2011 RCE 1/11/2011
57
IMPLEMENTABLE IDEA 6: Minimizing Road traffic accidents involving OIL vehicles
EXPECTED RESULTS:
• Minimize bandhs /blockades etc
WHY WE NEED:
To focus on OIL’S contribution to the society
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by
when
Optimise bowser
movement-through alternate
arrangements.
GM (P-Oil) 1/8/2011 ED (Ops) 1/10/2011
Training to the drivers at
regular intervals.
GM (T&D)
1/8/2011 RCE 1/10/2011
Penal action for errant
drivers/Contractors.
Head –P -Oil 1/8/2011 RCE 1/10/2011
IMPLEMENTABLE IDEA 7 : Quick response team (QRT) to be introduced to reduce
reaction time.
EXPECTED RESULTS:
• Reduction in reaction time
• Minimizing bandhs /blockades etc
• Enhancing co-ordination with District and Police administration
WHY WE NEED:
To facilitate uninterrupted field operations
.
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by
when
Formation of two QRTs with
guidelines (Dib-Sib, TSK)
comprising concerned officers
on rotation with adequate
decision making power,
infrastructure, empowerment.
GM (CC&PR) 1/7/2011 RCE WEEKLY
58
IMPLEMENTABLE IDEA 8 : All CSR activities/initiatives (area wise, organization
wise etc) should be circulated/informed to all Installation Managers.
EXPECTED RESULTS:
• Better awareness.
• Enhancing confidence to Installation Managers to act as a PR man.
WHY WE NEED:
Confidence building
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by
when
Special sessions must be
organized for IM’s.
CSR workshop for Field
going Executives and
Union councilors.
Formation & Updating
of CSR Data Bank
GM (CC&PR)
Head (PR&CC)
1/8/2011
1/9/2011
RCE
GM (CC&PR)
Quarterly
Quarterly
IDEA 9 : Introduction of Security Intelligence cell.
EXPECTED RESULTS:
• Pro-active action.
• Minimizing untoward incidents.
WHY WE NEED:
To cope up with present security scenario.
Action to initiate Who to initiate When to
initiate
Review by
Whom
Review by
when
Starting of the intelligence
cell with experienced
persons from I.B. and police
personnel.
GM (HR)
1/7/2011
RCE
MONTHLY
59
AREA-V
PROJECTISATION
60
AREA-5 : Projectisation of Drilling surface activities.
Projectisation means- Collaborative approach, careful planning, research & design to
achieve specific objective.
CONCEPT
1. The process starting from land acquisition to production testing can be carried out as
project with proper field development plan in place. The accountability and authority
should be fixed.
2. Projectisation may be carried out in parts as follows –
(a) Preparatory services: Land acquisition, contract preparation and execution.
(b) Rig-down, ILM and Rig-up.
(c) Drilling operation.
(d) Production testing
3. It may be executed by in-house resource or outsourced either Rig-wise or area wise.
IDEAS GENERATED:
The following ideas were generated for projectisation of Drilling surface activities:-
A. In-house : Rig wise (As a whole)
Rig wise (In parts)
Area wise (As a whole)
Area wise (In parts)
B. Outsourcing : Rig wise (As a whole)
Rig wise (In parts)
Area wise (As a whole)
Area wise (In parts)
61
WHY WE NEED
To establish the concept of projectisation and to initiate the feeling of belongingness.
To have better Collaboration.
Forward location not available in time.
Rig idling time is increasing.
Proper tracking of job progress is not in place.
EXPECTED RESULTS
Timely availability of forward locations.
Adherence to TDP.
Reduction in Rig idle time.
Increasing operational efficiency by proper planning & documentation.
Minimizing decision making time.
RECOMMENDATIONS – SHORT TERM
IMPLEMENTABLE IDEA-1: Projectisation of in-house Drilling surface activities rig
wise as a whole starting from land acquisition to production testing.
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(E&D)/RCE
01.09.11
Note:
1) May be experimented in one rig.
2) Core team may be comprised of Drilling, G&R, Land, Civil, Production.
62
IMPLEMENTABLE IDEA-2 : Projectisation of in-house Drilling surface activities rig wise
in parts:
(a) Preparatory services: Land acquisition, contract preparation and execution.
(b) Rig-down, ILM and Rig-up.
(c) Drilling operation.
(d) Production testing.
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
Note:
1. May be experimented in one rig.
2. Core team may be comprised of-
(a) Prepatory services - Drilling, G&R, Land, Civil.
(b) Rig-down, ILM and Rig up - Drilling, Transport & Electrical.
(c) Drilling operation- G&R, Drilling, and Chemical.
(d) Production testing- G&R, Production & Drilling.
IMPLEMENTABLE IDEA-3 : Projectisation of in-house Drilling surface activities as a
whole starting from land acquisition to production testing .
.
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
Note:
1) May be experimented in one area in MPA.
2) Core team may be comprised of - Drilling, G&R, Land, Production & Civil.
63
IMPLEMENTABLE IDEA- 4 : Projectisation of in-house Drilling surface activities in
parts area wise .
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
Note:
1).May be experimented in one area in MPA.
2).Core team may be comprised of- Drilling, G&R, Land, production & Civil.
RECOMMENDATIONS – LONG TERM
IMPLEMENTABLE IDEA-1 : Projectisation of drilling surface activities outsourcing
rig wise , as a whole starting from land acquisition to production testing .
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
Note:
1).May be experimented in one Rig.
2).Core team may be comprised of- Drilling, G&R, Land, production & Civil.
IMPLEMENTABLE IDEA-2 : Projectisation of drilling surface activities outsourcing
rig wise (in parts).
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
64
Note:
1).May be experimented in one Rig.
2).Core team may be comprised of- Drilling, G&R, Land, production & Civil.
IMPLEMENTABLE IDEA-3 : Projectisation of drilling surface activities outsourcing
area wise as a whole starting from land acquisition to production testing .
ACTION TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
Note:
1).May be experimented in one Rig.
2).Core team may be comprised of- Drilling, G&R, Land, production & Civil.
IMPLEMENTABLE IDEA-4 : Projectisation of drilling surface activities outsourcing
area wise (in parts).
ACTION(S) TO INITIATE WHO TO
INITIATE
WHEN
TO
INITIATE
REVIEW
BY
WHOM
REVIEW
BY WHEN
To create a core team ED(O) 01.07.2011 D(O)/RCE 01.09.11
Note:
1).May be experimented in one area MPA.
2).Core team may be comprised of - Drilling, G&R, Land, production & Civil.
65
SUGGESTED ISSUES:
A. The projects (in-house) which were found suitable/successful in short term may be
applied to rest of the Rigs or Areas in the long run subsequently.
B. Similarly, the projects (outsourcing) which were found suitable/successful may be
extended in the long run subsequently.
C. All activities right from release of location to production testing need to be
benchmarked
PRACTICES TO CONTINUE:
1. Outsourcing of drilling operation from Rig down, ILM, Rig up & Drilling
completion.
2. Present practices of drilling well outside MPA like Amguri etc. may be relooked
and continued.
66
6.0 CONCLUSION
“Sustainable growth” for any industry, how big it may be, is the need of the hour. For
achieving sustenance, three prime factors play a major role i.e. People, Profit and Planet. In
order to maintain sustainability, we need to be proactive, generate new ideas and think out of
box by brain storming and orienting various thoughts in a linear motion.
This brainstorming session was held for finding out practicable ideas for its implementation
with an objective of “Reduction in Surface related problems for reducing cycle time of
drilling operation”. Recent analysis of drilling performance indicated that the cycle time of
drilling operation has increased considerably due to various surface problems and
conventional way of working since years together. The team for brainstorming was selected
from a multidisciplinary group of people from various departments. The group was divided in
to five teams. Each team brainstormed on different related issues primarily focusing towards
practical solution and generating implementable ideas with action plan which can lead to
“Reduction of cycle time in drilling by solving surface problems”.
This document contains ideas generated, benefits which will accrue, why required and the
practicable action plans with time frame for five areas such as 1) Preparatory services 2) Rig
down–ILM–Rig Up 3) Operation Phase 4) Environmental and Statutory issues 5)
Projectisation. All these areas focus towards achieving the targeted goal as mentioned above.
Implementation of above ideas will definitely pave the way for achieving the real benefit of
the brainstorming session which will manifest in our drilling operation thus increasing
efficiency.
Further deliberations and discussions at higher level may be required in certain cases to
address the intricacies in a more effective and objective manner. The group strongly feels that
the thoughts and ideas generated in the session if implemented in its true spirit will definitely
go a long way for realising our committed & co-created vision of improving drilling cycle
time by reducing surface problems.
ACKNOWLEDGEMENT
The participants of the session are extremely grateful to Mr.B.N.Talukdar, Director (E & D)
for initiating the idea of the brainstorming session and providing a truly learning experience
for the participants. We would also like to place on record our sincere gratitude to the OIL
Management for providing us the opportunity to participate in this meaningful session.
We are grateful to Sri K.K.Nath, E.D (Operation), Sri A.Barbora, G.M (Drilling),
Sri T.B.Chakraborty, Head-FE for their encouraging presence and words during the beginning
of the session.
We are also thankful to Sri S. Rath, Director (O) and other senior Officials of OIL for their
valuable guidance during the presentation. The group is also overwhelmed by the excellent
planning and conduction of the session by the B.P coaches.
-------------------------------------------