Report on Solid Waste Management in the
Urban Local Bodies in Odisha
in pursuance of orders of Honourable National Green
Tribunal (NGT) dated 15/01/2015
Submitted by Commissioner cum Secretary, H&UD
Department, Government of Odisha
Government of Odisha
Housing and Urban Development Department
2 Act ion Plan fo r SW M in ULBs of Odisha
Contents
1 Current status ......................................................................................................... 7
1.1 Background ......................................................................................................... 7
1.2 Current Status ..................................................................................................... 8
1.3 Site Authorisation for SWM Projects ................................................................... 8
2 Initiatives for SWM Implementation in Odisha ......................................................... 9
2.1 State Government initiative ................................................................................. 9
2.1.1 Octroi Grant & Budgetary Support ................................................................. 9
2.1.2 State Plan for MSW ...................................................................................... 9
2.1.3 12th Finance Commission Grant ................................................................... 9
2.2 PPP initiatives ................................................................................................... 10
2.3 Integrated Coastal Zone Management Project (ICZMP) Initiatives .................... 11
2.4 Odisha Urban Infrastructure Development Fund (OUIDF) initiatives ................. 11
2.5 Initiative for Puri ................................................................................................ 13
2.6 On-going Initiatives by some ULBs ................................................................... 13
2.6.1 Composting Plant-NALCO and Jindal Townships ....................................... 13
2.6.2 TSU- Bhubaneswar Municipal Corporation ....................................................... 13
2.7 Potential ULBs for CSR initiatives ..................................................................... 13
2.8 Other Initiatives ................................................................................................. 14
2.8.1 Technical Assistance -DFID ........................................................................ 14
2.8.2 Project e-Municipality Programme ............................................................... 14
2.9 Swachh Bharat Initiative .................................................................................... 14
3. Proposed Strategic Intervention ............................................................................ 17
3.1. Door to door collection of MSW and segregation at source ............................... 17
3.2. Transportation of MSW to the processing site in a scientific manner ................. 20
3.3. Processing of MSW in a scientific manner ........................................................ 20
3.4. Disposal through common Sanitary Landfill Sites (SLF) .................................... 20
3.5. Reclamation of old dumps ................................................................................. 21
3.6. Provision of safety equipment ........................................................................... 21
3.7. Involvement of rag pickers and Khabadiwallahs ................................................ 21
3.8. Involvement of NGOs, Self Help Groups and Community Participation ............. 22
3.9. Enforcement of MSW Rules 2000 ..................................................................... 22
4. Investment Plan and cost recovery ....................................................................... 23
3 Act ion Plan fo r SW M in ULBs of Odisha
4.1. Project Cost and Means of Finance .................................................................. 23
4.2. Proposed Capital Expenditure-Year Wise ......................................................... 23
4.3. User charges and O&M costs ........................................................................... 23
4.4. Proposed Consolidated Cost-Year Wise ........................................................... 24
4 Act ion Plan fo r SW M in ULBs of Odisha
Annexures
1. Urban Map of Odisha
2. Details of the ULBs Cluster Wise
3. Details of the ULBs Standalone
4. Proposed user charges for SWM services by Bhubaneswar Municipal Corporation
5. Concept Note on State Urban Sanitation Strategy for the State of Odisha – Part A, Part B,
Part C
Annexure 2- List of Clusters
1 JHARSUGUDA, BRAJRAJNAGAR, BELPAHAR
2 JAJPUR, VYASANAGAR
3 BARBIL, JODA
4 DHENKANAL, ATHAGARH
5 ATABIRA, BARGARH & BARAPALI
6 JEYPORE, SUNABEDA, KORAPUT
7 KHURDA, JATNI, CUTTACK &BHUBANESHWAR
8 BERHAMPUR, GOPALPUR, CHATRAPUR, CHIKITI, DIGAPAHANDI
9 ASKA, KABI SURYA NAGAR, PURUSOTAMPUR & HINJLICUT
10 PARALAKHEMENDI, KASINAGAR
11 SAMBALPUR, HIRAKUD & BURLA
12 SORO, BASUDEVPUR
13 SONEPUR &TARBHA
Annexure 3- List of ULBs
1 ANANDAPUR MUNICIPALITY, DIST-KEOJHARGARH, ODISHA
2 ANGUL MUNICIPALITY, DIST-ANGUL, ORISSA
3 ATHAMALLIK NAC, DIST- ANGUL, ORISSA
4 BALIMELA NAC, DIST-MALKANGIRI, ORISSA
5 BALUGAON NAC, DIST-KHURDA, ORISSA
6 BANKI NAC, DIST-CUTTACK, ORISSA
7 BANAPUR NAC, DIST-KHURDA, ORISSA
8 BELAGUNTHA NAC, DIST-GANJAM, ORISSA
9 BHANJANAGAR NAC, DIST-GANJAM, ORISSA
10 BHUBAN NAC, DIST-DHENKANAL, ORISSA
11 BINIKA NAC, DIST-SUBARNAPUR, ORISSA
12 BOUDHGARH NAC, DIST-BOUDH, ORISSA
13 BUGUDA NAC, DIST GANJAM-, ORISSA
14 BALASORE MUNICIPALITY, DIST-BALASORE, ORISSA
15 BARIPADA MUNICIPALITY, DIST-MAYURBHANJ, ORISSA
16 BHADRAK MUNICIPALITY, DIST-BHADRAK, ORISSA
17 BHAWANIPATNA MUNICIPALITY, DIST-KALAHANDI, ORISSA
5 Act ion Plan fo r SW M in ULBs of Odisha
18 BIRAMITRAPUR MUNICIPALITY, DIST-SUNDERGARH, ORISSA
19 BOLANGIR MUNICIPALITY, DIST-BOLANGIR, ORISSA
20 CHOUDWAR MUNICIPALITY, DIST-CUTTACK, ORISSA
21 DEOGARH MUNICIPALITY, DIST- DEOGARH, ORISSA
22 G.UDAYAGIRI NAC, DIST-PHULBANI, ORISSA
23 GANJAM NAC, DIST-GANJAM, ORISSA
24 GUDARI NAC, DIST-RAYAGADA, ORISSA
25 GUNPUR NAC, DIST-RAYAGADA, ORISSA
26 JAGATSINGHPUR MUNICIPALITY, DIST- JAGATSINGHPUR, ORISSA
27 JALESWAR NAC, DIST-BALASORE, ORISSA
28 JUNAGARH NAC, DIST-KALAHANDI, ORISSA
29 KEONJHARGARH MUNICIPALITY, DIST-KEONJHAR, ORISSA
30 KAMAKSHYANAGAR NAC, DIST-DHENKANAL, ORISSA
31 KANTABANJI NAC, DIST-BALANGIR, ORISSA
32 KARANJIA NAC, DIST-MAYURBHANJA, ORISSA
33 KESINGA NAC, DIST-KALAHANDI, ORISSA
34 KHALLIKOTE NAC, DIST-GANJAM, ORISSA
35 KHANDAPARA NAC, DIST-NAYAGARH, ORISSA
36 KHARIAR ROAD NAC, DIST-NUAPADA, ORISSA
37 KHARIAR NAC, DIST- NUAPADA, ORISSA
38 KODALA NAC, DIST-GANJAM, ORISSA
39 KONARK NAC, DIST-PURI, ORISSA
40 KOTPAD NAC, DIST-KORAPUT, ORISSA
41 KUCHINDA NAC, DIST-SAMBALPUR, ORISSA
42 KENDRAPARA MUNICIPALITY, DIST-KENDRAPARA, ORISSA
43 MALKANAGIRI NAC, DIST-MALKANAGIRI, ORISSA
44 NAWARANGPUR MUNICIPALITY, DIST-NAWARANGPUR, ORISSA
45 NAYGARH NAC, DIST-NAYAGARH, ORISSA
46 NILAGIRI NAC, DIST-BALASORE, ORISSA
47 NIMAPARA NAC, DIST-PURI , ORISSA
48 PARADEEP MUNICIPALITY, DIST-JAGATSINGHPUR, ORISSA
49 PHULBANI MUNICIPALITY, DIST-PHULBANI, ORISSA
50 PURI MUNICIPALITY, DIST-PURI, ORISSA
51 PADAMPUR NAC, DIST-BARGARH, ORISSA
52 PATNAGARH NAC, DIST-BALANGIR, ORISSA
53 PATTAMUNDAI NAC, DIST-KENDRAPARA, ORISSA
54 PIPILI NAC, DIST-PURI , ORISSA
55 POLASARA NAC, DIST-GANJAM, ORISSA
56 RAJGANGPUR MUNICIPALITY, DIST-SUNDERGARH, ORISSA
57 RAYAGADA MUNICIPALITY, DIST-RAYAGADA, ORISSA
58 ROURKELA MUNICIPAL CORPORATION, DIST-SUNDERGARH, ORISSA
59 RAIRANGAPUR NAC, DIST-MAYURBHANJA, ORISSA
60 RAMBHA NAC, DIST-GANJAM, ORISSA
61 REDHAKHOL NAC, DIST-SAMBALPUR, ORISSA
62 SUNDERGARH MUNICIPALITY, DIST-SUNDERGARH, ORISSA
63 SURUDA NAC, DIST-GANJAM, ORISSA
6 Act ion Plan fo r SW M in ULBs of Odisha
64 TALCHER MUNICIPALITY, DIST-ANGUL, ORISSA
65 TITLAGARH NAC, DIST-BOLANGIR, ORISSA
66 UDALA NAC, DIST-MAYURBHANJA, ORISSA
67 UMERKOTE NAC, DIST-NAWRANGPUR, ORISSA
68 RECENTLY FORMED NACS – NUAPADA, ATABIRA, HINDOL, TUSURA, DHARMGARH, DASPALA, RANPUR
Abbreviations
DPR Detailed Project Report
CPHEEO Central Public Health and Environmental Engineering Organisation
ECI Empowered Committee on Infrastructure
GoI Government of India
GoO Government of Odisha
HPEC High Powered Expert Committee
H&UD Housing and Urban Development
ICZMP Integrated Coastal Zone Management Project
IEC Information, Education and Communication
IFC International Finance Corporation
MoUD Ministry of Urban Development
MSW Municipal Solid Waste
MT Metric Tonne
NAC Notified Area Council
NARC National Advisory Review Committee
NGO Non-Governmental Organisation
OUIDF Odisha Urban Infrastructure Development Fund
PPP Public Private Partnership
RDF Refuse Derived Fuel
SBM Swachh Bharat Mission
SHG Self Help Group
SLF Sanitary Land Fill
SWM Solid Waste Management
TPD Tonnes Per Day
ULB Urban Local Body
7 Act ion Plan fo r SW M in ULBs of Odisha
1 Current status
1.1 Background
Solid waste is the unwanted or useless solid materials generated from combined residential,
industrial and commercial activities in a given area. It may be categorized according to its origin
(domestic, industrial, commercial, construction or institutional); according to its contents (organic
material, glass, metal, plastic paper etc.); or according to hazard potential (toxic, non-toxin,
flammable, radioactive, infectious etc.).
Management of solid waste reduces or eliminates adverse impacts on the environment and human
health and supports economic development and improved quality of life. A number of processes
are involved in effectively managing waste for a municipality. These include source-segregation,
door-to-door collection, collection from community bins, transportation, processing, recycling and
disposal.
Solid Waste Management is one of the key functions of the ULBs. The management and disposal
of MSW is not satisfactory across towns and cities in India. The HPEC Report on Indian Urban
Infrastructure and Services prepared under guidance of Dr. Isher Judge Ahluwalia, Chairperson,
Indian Council for Research on International Economic Relations presents the status on
compliance with MSW Rules 2000 in India as given below.
Solid Waste Management Report Card %
Primary collection 38
Segregation of recyclables 72
Transportation 52
Processing 09
Disposal 01
Across towns and cities in India, neither the households nor the municipal authorities practice
segregation of biodegradable waste from the rest, and public awareness on the benefits of
segregation is low. The collection of the garbage from dump-sites is infrequent, processing is not
done in most cases, and disposal rules are not followed more in the breach. According to MoUD,
GoI scientific disposal of waste is almost never practiced.
The scenario in Odisha is no different from the rest of the country. Odisha has a total population of
4.2 Crore, as per Census 2011. There are 111 Urban Local Bodies in Odisha comprising of 5
Municipal Corporations, 45Municipalities and 61 Notified Area Councils in the state with a total
population of 59.8 lakhs accounting for about 14%of the total population of the State. The urban
map of Odisha is given in Annexure-1 & details of ULBs are given in Annexure –2& 3).These
ULBs generate approximately 1800 TPD of municipal waste. The MSW generated in these ULBs
are not managed properly resulting in degradation of the environment.
Efficient MSW management is essential in maintaining hygienic conditions leading to:
Lesser health issues of the inhabitants
Better living environment
Improved economic prosperity
Cleaner surroundings with cleaner drains for storm water flow
Cleaner water sources and safer neighborhoods
8 Act ion Plan fo r SW M in ULBs of Odisha
1.2 Current Status
In most of the ULBs in Odisha, until very recently, collection of MSW from market places and
community bins, street sweeping, bush cutting and drain cleaning, transportation and disposal at
the dump yard had been carried out by ULBs on their own. However, started with the
Bhubaneswar Municipal Corporation and being replicated in many other towns of the state for
about last five years door to door collection of waste and all aforesaid activities are carried out
more efficiently by involving SHGs, NGOs and by engaging private operators. It has been a
gradual transition from fully ULB-operated sanitation to mix of ULB and Public-Private-Community
Participation model. However, scientific disposal is yet to occur and the waste is dumped at the
dump yard without any processing or treatment. This has led to environmental degradation, air
pollution, ground water table pollution and poses grave health hazards.
MSW Rules 2000 designates the Urban Local Bodies as solely responsible to manage solid waste
in their area and dictates that “within the territorial area of the municipality, be responsible for the
implementation of the provisions of these rules, and for any infrastructure development for
collection, storage, segregation, transportation, processing and disposal of municipal solid
wastes”. However, the ULBs of Odisha are yet to fully comply with MSW Rules 2000.
Among all the ULBs of the state, Puri is the first town to have arrangements since 1998 for
scientist disposal and mechanized processing of solid waste in to bio-fertilizer in a scientific
manner. Under the Indo-Norwegian Development Corporation support and with the active
participation of Govt. of Odisha, a 100 TPD bio-compost plant has been operational in Puri. This
initiative assumes importance since Puri is the District headquarters and prime pilgrimage and
tourist centre of Odisha. A private firm is engaged to manage the plant. But this plant is facing
difficulty for lack of source segregation of the MSW.
1.3 Site Authorisation for SWM Projects
State Government has initiated various steps for implementation of integrated Solid Waste
Management projects in various ULBs as per MSW Rules 2000. As a first step towards it, land
was allotted to ULBs to gradually implement the SWM project involving processing of bio-
degradable and scientific disposal of processed and inert non-recyclable waste. Most of the ULBs
have provided approach road to the sites and have secured the site with a compound wall.
However, processing facility has not been set up in any of the ULBs. The waste is dumped in the
site without processing and scientific land fill. At present, 100% of the sanitation budget is utilized
only for collection and transportation.
Many of the ULBs have obtained site authorization from Pollution Control Board for setting up
processing plant and sanitary land fill. At present, waste is directly dumped in these sites without
processing. The summary of status of site authorization is given below.
Site Authorization No. of ULBs
No. of ULBs to whom authorization granted No. of ULBs having valid authorization
No. of ULBs who have applied for renewal of authorization No. of ULBs not applied for renewal
70 38 13 19
No. of ULBs whose applications are under consideration for grant of
authorization (new) 12
No. of ULBs to whom authorization refused 1
No. of ULBs not applied for authorization 25
Total 108
Total no. of ULBs (Dhamnagar NAC, Champua NAC and Baliguda NAC have been constituted recently)
111
9 Act ion Plan fo r SW M in ULBs of Odisha
2 Initiatives for SWM Implementation in Odisha
2.1 State Government initiative
2.1.1 Octroi Grant & Budgetary Support
In Odisha, Octroi Compensation Grant is the main stay for the ULBs to meet expenditure on
salary personnel, contribution to CPF, repayment of loan, electricity and water charges and
sanitation including solid waste management. In practice, the ULBs spend about 40% of the octroi
grant on O&M cost of SWM services. The octroi grant disbursed to ULBs in the last 8 years is
given below.
Year
2006-0
7
2007-0
8
2008-0
9
2009-1
0
2010-1
1
2011-1
2
2012-1
3
2013-1
4
2014-1
5*
Octroi Grant (Rs. Cr.) 143 171 206 233 259 279 307 338 500
Approx. amount of Octroi Grant spent on SWM services (Rs. Cr.)
57 69 82 93 103 112 123 135 200
*Budgeted amount
As mentioned earlier, collection and transportation of MSW is carried out by ULB on its own or by
engaging private operators or a combination of both. About 60% of the wards are outsourced and
balance managed by ULBs. ULBs employ over 4500 sanitary workers for SWM services.
2.1.2 State Plan for MSW
Year Fund disbursement under State Plan
2010 - 11 1.00 Cr.
2011 - 12 0.88 Cr.
2012 – 13 1.00 Cr.
2013 – 14 3.00 Cr.
2014 – 15 1.33 Cr.
2.1.3 12th Finance Commission Grant
A detailed study on the collection and transportation infrastructure requirement of 103 ULBs in the
State was carried out in 2004 by Orissa Renewable Energy Development Agency (OREDA).
Further, the report also suggested appropriate technologies for treatment and disposal of MSW by
ULBs. The report covered tools and equipment requirement of each ULB such as –
Auto tipper, tricycle, push cart
Long handle broom, shovel, gloves, gun boot, metal trays, small brooms
Road side bins, additional bins
Dumper bin of various sizes
Tractor with attachment, tipper lorry
The details of the above equipment and vehicles ULB-wise are given in Annexure 2 & 3
10 Act ion Plan fo r SW M in ULBs of Odisha
Based on the report, Rs. 98.59 Cr. was disbursed to ULBs during the period 2005-06 to 2009-10
under the 12th Finance Commission Grant.
Year 2005-06 2006-07 2007-08 2008-09 2009-10 Total
Disbursement
(Rs. in Cr.) 19.76 19.76 19.72 19.14 20.20 98.59
The ULB wise disbursement is given in Annexure 2 & 3.
2.2 PPP initiatives
The State Government had undertaken various initiatives to implement SWM projects in various
ULBs. In the following four Municipal Corporations viz. Bhubaneswar& Cuttack, Berhampur and
Sambalpur, SWM projects are proposed to be implemented on PPP basis. Concession
Agreements have already been signed with PPP partner by Bhubaneswar & Cuttack Municipal
Corporations and Berhampur Municipal Corporation.
Corporations Bhubaneswar & Cuttack Berhampur Sambalpur
Population Bhubaneswar – 886000
Cuttack - 606000 355000
Sambalpur –
183147
Burla – 42625
Hirakud - 30177
Estimated
waste
generation
(TPD)
550 138 100
Estimated
project cost
(Rs. Cr.)
58.47 40.60 28.75
Status of PPP
partner
selection
PPP Partner Selected
(Essel Infrastructure Projects
Ltd.)
PPP Partner
Selected (UPL
Environmental
Engineers Ltd.)
Under process
Concession
period
20 years + 2 years
(construction period) 20 years 20 years
Model Regional landfill + waste to
energy Integrated Integrated
Technology
for processing Waste To Energy Composting Composting
Current status
SPV formed.
In process of obtaining
various approvals and
clearances
SPV formed.
In process of
obtaining various
approvals and
clearances
RFP for selection
of PPP partner
has been floated
The Municipalities adjacent to these Municipal Corporations may avail the processing and land fill
facility set up by the PPP partner through a separate agreement.
11 Act ion Plan fo r SW M in ULBs of Odisha
2.3 Integrated Coastal Zone Management Project (ICZMP) Initiatives
Under ICZMP, it is proposed to implement integrated SWM project under ICZMP in Paradeep
Municipality on PPP mode. The estimated project cost is Rs. 29 Cr. The concession period for the
project is 25 years. Paradeep Municipality is in discussion with Paradeep Port Trust for land
acquisition. Selection of private partner for the project is in progress.
In addition, it is proposed to prepare DPR for SWM projects for implementation in the following
coastal towns viz. Bhadrak, Jagatsingpur, Konark, Gopalpur and Balugaon. The scope of work for
all these projects includes full cycle SWM - source segregation, collection, transportation and
scientific disposal. All the projects are proposed to be done through public private partnership
(PPP) under the direct supervision of the respective ULBs and overall supervision of the
Integrated Coastal Zone Management Project (ICZMP) authorities. The population and estimated
waste generation in these ULBs are given below.
ULB Population Estimated waste
generation (TPD)
Bhadrak 121247 36
Jagatsingpur 33639 10
Konark 21347 6
Gopalpur 7221 2
Balugaon 17635 5
The above does not include the floating population.
2.4 Odisha Urban Infrastructure Development Fund (OUIDF) initiatives
OUIDF is a dedicated fund for financing urban infrastructure projects in the State of Odisha.
OUIDF extends support to ULBs in the form of loan and grant for urban infrastructure project
financing besides offering project development assistance such as preparation of DPR, capacity
building etc.
OUIDF is extending concessional loan assistance and grant to private developers selected for
implementation of SWM projects at Bhubaneswar & Cuttack and Berhampur. OUIDF shall also
extend concessional loan assistance to PPP partner who will be selected for integrated SWM
project for Sambalpur.
OUIDF also intends to assist ULBs to undertake SWM projects in their towns. OUIDF conducted
workshop to create awareness amongst the ULBs regarding the need to implement SWM projects
in compliance with MSW Rules 2000 in their respective towns.
OUIDF has identified about 37 towns for implementation of SWM projects between 2015-16 and
2016-17.
Proposed SWM Clusters
Cluster No. of ULBs
Population
Estimated waste generation (TPD) @
300 gms/day per capita
Possible Regional Landfill Site
Cluster 1 - Jharsuguda, Brajrajnagar, Belpahar
3 217126 65 Brajrajnagar/ Jharsuguda
Cluster 2 -Jajpur, Vyasanagar,
2 86369 26 Vyasnagar
Cluster 3 -Barbil, Joda 2 113171 34 Joda
Cluster 4 -Dhenkanal, Athagarh
2 84718 25 Dhenkanal
12 Act ion Plan fo r SW M in ULBs of Odisha
The density of population is very low in Odisha at 269/ Sq.Km. This makes it
difficult to develop common facilities for processing and landfill encompassing
more number of municipalities per cluster.
Proposed SWM Clusters
Cluster No. of ULBs
Population
Estimated waste generation (TPD) @
300 gms/day per capita
Possible Regional Landfill Site
Cluster 5 -Atabira, Bargarh, Barapali
3 117874 35 Bargarh
Cluster 6 – Jeypore, Sunabeda, Koraput
3 182692 55 Koraput
Cluster 7 –Khurda, Jatni, Cuttack, & Bhubaneshwar
4 1553153 466 Bhubaneswar
Cluster 8-Berhampur, Gopalpur, Chatrapur, Chikiti, Digapahandi
5 410681 123 Berhampur
Cluster 9 -Aska, Kabi Surya Nagar, Purusotampur & Hinjlicut
4 88895 27 Aska
Cluster 10 -Paralakhemendi, Kasinagar
2 54153 16 Paralakhemendi
Cluster 11 - Sambalpur, Hirakud & Burla
3 260905 78 Sambalpur
Cluster 12 -Soro, Basudevpur
2 66221 20 Soro
Cluster 13 –Sonepur & Tarbha
2 29104 9 Sonepur
Total 37 32,65,062 980
The ULBs have been grouped into various clusters such that the distance between ULBs within a
cluster does not exceed 50 Km. In most of the ULBs in the cluster, the distance is between 25 and
35 Km.
It is proposed to upgrade the collection and transportation infrastructure of each of the ULBs.
Further, where the waste generation is more than 10 TPD standalone processing facility will be
set up in each of the ULBs. If the waste generation is less than 10 TPD, processing facility
proposed to be set up in nearest neighbouring ULB shall be utilized. Landfill will be common for all
the ULBs within a cluster.
For processing of bio-degradable waste mechanical composting is proposed. RDF facility will be
set up wherever commercially feasible on a standalone basis. Recyclables will be segregated and
by engaging SHGs, rag pickers and Khabadiwallas. Balance waste from the composting plant,
inert and other waste will be sent to landfill.
13 Act ion Plan fo r SW M in ULBs of Odisha
In addition to the above clusters, OUIDF will also initiate SWM projects at following ULBs on
stand-alone basis.
ULB Population Estimated Waste Generation (TPD)
Bolangir 98211 29
Balasore 118162 35
Keonjhar 60690 18
Rayagada 71208 21
Total 348271 104
2.5 Initiative for Puri
IFC has undertaken site identification for setting up processing plant and landfill site at Puri
Municipality as the previously identified sites were found unsuitable owing to opposition by local
people/ because of their location in the sweet-water zone.
Collector cum District Magistrate, Puri has identified an alternative location in Mouza Bangar
under Ramchandi Police Station. ECI has advised IFC to undertake site visit to assess the
suitability of the site.
2.6 On-going Initiatives by some ULBs
2.6.1 Composting Plant-NALCO and Jindal Townships
Mechanical composting plants of 15 TPD each are operational at NALCO Township at Damanjodi
and Jindal Township at Angul. This clearly shows that smaller capacity plants can be set up in
various ULBs for processing of biodegradable waste.
2.6.2 TSU- Bhubaneswar Municipal Corporation
Bhubaneswar Municipal Corporation has taken the initiative to set up a Technical Support Unit for
smooth management of Solid Waste Management in Bhubaneswar Municipal Corporation. The
proposed team comprises of Solid Waste Management Expert, Procurement Expert, MIS Expert,
Communication, Grievance Redressal Officer, Documentation Executive, Social Mobilization
Expert, Environmental Engineers. The recruitment procedure is in process and the team shall be
mobilized shortly. Such initiatives shall be replicated elsewhere in the State for capacity building of
the Municipalities.
2.7 Potential ULBs for CSR initiatives
Odisha is rich in mineral deposits such as bauxite, chromite, iron ore and coal. Many large scale
industries dependent on these mineral resources have been set up in the State. Some of these
industrial units have been supporting the local ULBs in their area through their CSR funds by
procuring vehicles, bins etc. for SWM services.
The District Collectors will be requested to approach these PSUs and private corporates for
channelizing a portion of their CSR funds for SWM capital expenditure and operating expenditure.
An indicative list of large industrial units located near various towns is given below.
ULBs PSUs Private Corporates
Rourkela Rourkela Steel Plant Indian Detonators Ltd.
Rajgangpur - Orissa Cements Ltd., L&T
14 Act ion Plan fo r SW M in ULBs of Odisha
ULBs PSUs Private Corporates
Jharsuguda - Bhushan Steel, Vedanta,
Lafarge
Sambalpur Mahanadi Coalfields Ltd.
(MCL) Bhushan Steel, Hindalco
Brajrajnagar - Orient Paper Mills
Belpahar - Tata Refractories Ltd.
Bargarh - ACC
Sunabeda HAL, NALCO -
Angul, Talcher MCL, NALCO, NTPC Jindal Steel & Power
Rayagada - JK Paper
Paradeep
Paradeep Phosphates Ltd.,
Indian Oil Ltd., Paradeep
Port Trust
POSCO
Gopalpur/ Chatrapur Indian Rare Earth Orissa Stevedores Ltd.,
Jayashree Chemicals
Joda, Barbil Odisha Mining Corporation Tata Steel
Barmitrapur - Tata Steel
Bhubaneswar, Cuttack Indian Oil Ltd. -
2.8 Other Initiatives
2.8.1 Technical Assistance -DFID
The Department for International Development (DFID), United Kingdom has agreed in-principle to
provide £5 million (Rs 48.327 crore) as technical assistance for the ‘Orissa Support to Urban
Infrastructure Development Programme’ project.
The DFID assistance would enable creation of a municipal reforms implementation cell in the
Directorate of Municipal Administration (DMA), capacity building of ULBs in an overall project
management cycle and overall municipal financial management and creating a Regional Institute
for Urban Management and governance for policy support design.
2.8.2 Project e-Municipality Programme Initiative on smart way of cleaning the city through solid waste management module via e-
Municipality Project is operational in 45 ULBs of the State since July 2009. The Broad objective
of the programme is the application of electronic means to improve the efficiency and
effectiveness in the interaction between local Government and its citizens as well as other interest
groups like NGOs, CBOs, RWAs, private sector, etc. It also aims at boosting internal Government
operations to support and stimulate good governance.
2.9 Swachh Bharat Initiative
Under the Swachh Bharat Mission (SBM) of the Central Government, ULBs can avail funding for
project development and implementation of SWM projects. The process for availing grant under
SBM is given below.
15 Act ion Plan fo r SW M in ULBs of Odisha
ULB’s are to prepare DPR for solid waste management of their city in consultation with state
governments. Smaller cities can form clusters to become viable entities to attract private
investment. 100% cost reimbursement for preparing the DPR shall be done by GoI as per
unit cost and norms set up by National Advisory Review Committee (NARC).
State governments may handhold ULB’s in quickly preparing DPR’s for SWM by empanelling
/shortlisting /identifying private or government agencies for the same.
The DPR’s should be bankable, having a viable financial model. These will be prepared
emanating from the needs identified in the City Sanitation Plan. DPRs should be aligned with
Govt. of India’s goals outlined in the NUSP 2008, SWM rules, advisories, CPHEEO manuals
(including cost-recovery mechanisms), O&M practices and Service-level Benchmark
advisories released by MoUD from time to time. Street Sweeping and litter control
interventions will be part of DPR which is essential for a clean city.
The State High Powered Committee (HPC) will authorize institutes of national repute for
appraisal of DPRs for the technical and economic appraisal of DPRs for projects
recommended by ULBs. No appraisal will be done by MoUD. The cost of DPR appraisal by
these institutes shall be an admissible component under administrative costs, subject to
norms as approved by MoUD.
The performance and quality of appraisal by these identified and authorized institutes will be
evaluated and monitored by HPEC as well as NARC and corrective actions taken wherever
necessary.
The State Level high power committee will approve the DPR as well as the financial model of
solid waste management.
The implementation of SWM projects will be as per directions of State Level High Power
Committee.
Central government incentive for the SWM projects will be in the form of a maximum of 20%
Grant / VGF for each project. The remaining funds have to be generated through –
o Private Sector Participation
o Additional Resources from State Government/ULB
o Beneficiary Share
o User Charges
o Land Leveraging
o Innovative revenue streams
o Swachh Bharat Kosh
o Corporate Social Responsibility
o Market Borrowing
o External Assistance
While considering projects under MSWM it will be ensured that there isno duplication in terms
of funding under any other scheme or programme.
Detailed technical and financial appraisal of the DPRs will be carried out. O&M arrangements
for the project shall necessarily be an integral part of the project in the DPR.
SWM projects will be sanctioned by the State level HPC which shall include a representative
of the MoUD. In the entire project approval and procurement process, all provisions and
procedures as prescribed by respective State Governments must be followed in their entirety.
16 Act ion Plan fo r SW M in ULBs of Odisha
The entire approval procedure for MSW projects except for release of Central funds will end
at the State Level.
The States shall be free to choose the technology for SWM projects, toilets and street
sweeping. The Ministry of Urban Development shall, from time to time, bring to the notice of
the States, through advisories and manuals, and other consultative mechanisms, various
options available in these fields.
States will contribute a minimum of 25% funds for SWM projects to match 75% Central
Share.
The State Government will initiate DPR preparation for the ULBs not covered under other
initiatives of the Government and will pursue implementation of SWM projects in various ULBs in
the next 3 years.
The State Government has set up SBM Directorate for implementation of the program and
appointed a Mission Director. OWSSB has been declared as the State Level Nodal Agency for the
Mission. A High Powered Committee is being set up under the Chairmanship of Chief Secretary.
A Program Management Unit is being set up at the State Level. A concept paper based on the
SBM guidelines to be submitted to GoI is given in Annexure 5.
17 Act ion Plan fo r SW M in ULBs of Odisha
3. Proposed Strategic Intervention
At present most of the ULBs in Odisha lack the financial strength and institutional capacity to
manage municipal solid waste in compliance with MSW Rules 2000 and implement and manage
SWM projects. Hence State Government intervention is necessary to tackle the sanitation issue
arising due to MSW in a systematic, coordinated and time bound manner.
The State Government has drawn up an action plan for ensuring compliance of MSW Rules 2000
by the ULBs in a time bound manner. The MSW projects will be implemented across various
ULBs between 2015-16 and 2019-20.
3.1. Door to door collection of MSW and segregation at source
Organizing door-to-door collection of waste to be the irreversible strategic approach to
prevent residents from dumping their garbage out. The waste collected from door-to-door
should be source segregated and collected separately in wet and dry waste from all sources.
Two bin system to be strictly followed and each household shall be given 2 bins by the ULB.
Door to door collection in Bhubaneswar
18 Act ion Plan fo r SW M in ULBs of Odisha
Community level large and unsightly garbage bins to be withdrawn from streets and ‘ Litter
Bins’ to be limited to busy commercial areas and public places.Bulk generators such as
vegetable/ fruit markets, shall be provided with closed large size containers with lid for easy
collection of waste. These bulk waste generators shall not dispose waste other than in the
bins provided.
Municipal Solid Waste to be segregated at source into groups of organic, inorganic,
recyclables and hazardous waste. MSW constituents like metal, plastics, glass and paper
wastes are to be segregated and recycled at the collection point through involvement of rag
pickers, social entrepreneurs, NGOs and Self Help Groups.
Route mapping of door to door collection activities on city wide scale for improved coverage.
Primary vehicles to be used to collect and transport waste from lanes and by- lanes to the
main roads synchronizing with bulk transportation vehicles. Entire town to be divided into
zones and further sub-divided into beats staffed with adequate sanitary workers for proper
door to door collection.
Daily collection of waste from slums and open squatter areas, hotels/restaurants/office
complexes and commercial areas
Collection of waste from community bins in Denkanal
19 Act ion Plan fo r SW M in ULBs of Odisha
ULBs shall target daily door to door collection and 100% segregation at
source in a period of next 3 years. State Government shall constitute
awards for ULBs which successfully implement source segregation in their
towns. Competitions shall be organized at schools and awareness created
amongst school children so that households gradually adopt source
segregation.
Collection of waste from community bins in Bhubaneswar
Construction/demolition wastes/debris to be separately collected and disposed off
following proper norms
Road sweeping and drain cleaning periodically
Road cleaning in Bhubaneswar
Though, ULBs have been carrying out door to door collection either on their own or by engaging
private operators, the performance is far from satisfactory in most of the ULBs and strict
enforcement is needed.
20 Act ion Plan fo r SW M in ULBs of Odisha
Waste to Energy is not suitable for the ULBs in Odisha except Bhubaneswar
3.2. Transportation of MSW to the processing site in a scientific manner
The waste should be transported in a segregated form (wet and dry) by vehicles, at the
primary collection and secondary/ bulk collection systems.
Waste to be handled mechanically across the MSW value chain with minimum human contact
with waste. Modernize fleet management services with covered transportation system to be
adopted for transportation of the waste.
3.3. Processing of MSW in a scientific manner
Waste received at the processing site shall be segregated mechanically as far as possible depending
on the quantum of waste generated. Suitable technology option for processing shall be adopted.
Common technology options for processing of MSW are given below.
Composting: Composting process is quite commonly used in MSW management in India and
results in production of a stable bio-fertilizer product known as bio-compost. This bio-compost,
depending upon its quality can be used as a useful manure and soil conditioner element.
Compost can be produced by either of the two processes viz. vermi-composting and mechanical
composting. Mechanical composting has been found to be suitable in most of the ULBs due to the
ease in handling and management of mechanical composting plant. Mechanical composting is
most suitable and is proposed to be adopted across ULBs in the State with MSW generation of 5
TPD and above.
Waste to Energy: It is the process of direct burning of wastes in the presence of excess air
(oxygen) to produce power. These plants require MSW of 300 TPD and above.
Anaerobic Bio-Methanisation facility: Bio-Methanation technology can also be used for
treatment of garbage as decentralized plants for treating limited quantity of municipal garbage.
The process involves biological decomposition of organic wastes in the absence of air to produce
bio-gas (methane) which can be directly used by the consumer or can be used to generate
electricity. This technology is most suitable in de-centralised locations like canteens, large
restaurants and large housing colonies. The State Government will promote this technology in
universities and colleges in the State.
Refuse Derived Fuel (RDF): In RDF plant, the combustible waste is shredded into a smaller,
more uniform particle size for burning. It involves the process of conversion of garbage into fuel
pellets involves primarily drying, separation of combustibles from garbage, size reduction and
pelletisation after mixing with binder and/or additives as required. RDF plant will be set up in
ULBs/ cluster of ULBs depending on commercial viability and market for RDF in the vicinity of the
ULB.
3.4. Disposal through common Sanitary Landfill Sites (SLF)
The final inert material will be disposed in the common sanitary landfill facility. Landfill sites shall be
used sparingly and only as a last resort in waste management hierarchy and shall not exceed
20% of the total municipal solid waste generated.
Common landfill sites shall be developed by adopting a cluster approach for ULBs within a distance of
less than 50 Km between each other. Land filling of mixed waste must be avoided, unless the waste is
found unsuitable for waste processing. Under unavoidable circumstances or till installation of alternate
facilities, land-filling shall be done following proper norms.
The major components of the MSW landfill site are-
A liner system at the base and sides of the landfill, which prevents migration of leachate or gas to
the surrounding soil.
21 Act ion Plan fo r SW M in ULBs of Odisha
A leachate collection facility to collect and extract leachate from within and from the base of the
landfill and then treats the leachate
A gas collection facility to collect and extract gas from within and from the top of the landfill and
then treat it and use it for energy recovery
A final cover system at the top of the landfill, which enhances the surface drainage, prevents
infiltration of water and supports surface vegetation.
A surface water drainage system to collect and remove all surface runoff from the landfill site.
An environmental monitoring system to periodically collect and analyses air, surface water, soil
gas and ground water samples around the landfill site.
A closure and post-closure plant close and secure a landfill site once the filling operation has
been completed and the activities for long term monitoring, operation and maintenance of the
completed landfill.
3.5. Reclamation of old dumps
The MSW is being dumped at the dump yard without any processing over many years by the ULBs.
Hence, apart from setting up of processing plant and scientific landfill facility, the ULBs shall reclaim
the dump yard in a time bound manner. The SWM project also includes reclamation of dump yard as
a key component. Reclamation process is given below.
Compacted old waste is loosened and scraped off in layers by a tractor-harrow. Composting bio-
culture is sprayed from a tanker-truck with high-pressure pump. It is formed into windrows & turned
weekly by JCB.At each turning, hired rag-pickers retrieve buried recyclables, which partly cover their
labour cost. After 3-4 weekly turnings, the waste is dry, volume-reduced & ready to sieve by either
manual or motorized simple portable sieves.
The reclamation process shall be completed within one year from setting up of processing plant and
scientific land fill facility.
3.6. Provision of safety equipment
The MSW project shall also include provision of necessary tools and tackles, adequate protective
clothing and safety gears to sanitary workers. Further, ULBs to provide adequate protection and
health care facilities to its sanitation workers.
3.7. Involvement of rag pickers and Khabadiwallahs
The rag picker plays a very important part in the segregation of waste. In India, only 30-60% waste is
collected by the ULBs, whereas waste collection by the rag pickers is estimated at 15-25%. About 1
million urban poor are engaged in informal waste management sector. However, MSW Rules 2000 &
majority SWM initiatives in the country somehow side-line the informal sector in solid waste
management. This is in spite of the fact that this sector, if integrated in to the mainstream SWM
system of cities and towns can lead to a win-win situation of providing secured livelihoods to the
urban poor and reducing expenditure on setting-up high cost energy intensive processing plants.
Moreover, in states like Odisha where large numbers of small sized ULBs are dispersed across the
state and density of urban population is very low and, neither cluster approach nor setting-up
processing plants is a viable option. It is precisely here, there is a need to go for decentralized
composting of bio-degradable waste and recycling of the non-biodegradable waste through the
network of rag pickers. Thus networking Rag Pickers and Kabadiwalas in to the municipal solid waste
management system in the states becomes imperative, especially in case of smaller ULBs of Odisha.
The H & UD Department in the State Govt. will take steps to integrate the informal sector in to the
mainstream SWM system of the ULBs through network building process.
22 Act ion Plan fo r SW M in ULBs of Odisha
3.8. Involvement of NGOs, Self Help Groups and Community Participation
Solid Waste management, after the passage of the Municipal Solid Waste Rules occupies primary
focus in ULBs, but suffers from lack of adequate community involvement and constraints with respect
to safe disposal.
Existing Municipal laws provide for punitive action against house/building owner in case of letting out
waste impacting local environment. However, punitive action recommended is not a major deterrent
and seldom enforced. Also, clarity on provisions to be made in places frequented by public (eating
places, shopping areas) need to be detailed in the bye-laws of the ULBs. Even with the necessary
legal provisions, city managers find enforceability a problem.
The successful implementation and management of MSW is dependent on community participation
involving the local residents of town.
Through effective IEC programs awareness need to be created regarding sanitation amongst
households, industries, elected body representatives and various other stakeholders. State
Government shall roll out such IEC programs across ULBs in a phased manner in the next one year.
State Government shall insist on deployment of a dedicated technical staff for SWM for each ULB.
Encourage sound contracting practice begins with setting operational goals, defining performance or
service benchmark standards and specifications and producing a document that communicates these
to private, semi-private, NGO, CBO or other economic actors who would like to participate as service
providers.
Through NGOs and SHGs, segregation shall be strengthened. Further revenue generation through
segregation of recyclables and sale of same thereby providing livelihood for rag pickers shall be
encouraged.
3.9. Enforcement of MSW Rules 2000
The non-compliance of MSW Rules 2000 by the ULBs has been due to the lack of financial strength,
institutional capacity of the ULBs and also lack of enforcement. ULBs are expected to submit reports
periodically regarding their SWM practice and compliance with MSW Rules 2000. This include -
Submission of Annual Report in Form II to Urban Development Department with a copy to
Pollution Control Board on or before 30th June every year.
Compliance with the guidelines, standards and specifications provided in Schedule II, III and IV of
State Pollution Control Board
Submit within 3 months from the date of site authorisation order proposal for waste processing
and landfill.
However, most of the ULBs have not followed the above compliance requirements. The State
Government shall enforce compliance by holding the Executive Officers of the ULBs accountable.
The State Government shall also extend all technical, institutional and financial support for assisting
the ULBs in SWM in compliance with MSW Rules 2000.
23 Act ion Plan fo r SW M in ULBs of Odisha
4. Investment Plan and cost recovery
As discussed in Chapter 2, various initiatives have been undertaken by the State Government for
implementation of SWM projects in compliance with MSW Rules 2000.
4.1. Project Cost and Means of Finance
The estimated project cost and means of finance is given below.
Source of Funding No.s Estimated project cost (Rs. Cr.)
Loan/ grant from Institutions (Rs. Cr.)
Central Govt. contribution (Rs. Cr.)
State Govt. Contribution (Rs. in Cr.)
Pvt. Sector investment (Rs. Cr.)
PPP projects in Municipal Corporations
3 99.07 14 85.07
Proposed under ICZMP
5 19.12 19.12
SBM/OUIDF initiative*
103 624.33 468.25 156.08
Total 111 742.52 33.12 468.25 156.08 85.07
*ULB contribution (Rs. Cr.) shall be @10% of the Estimated Project Cost for OUIDF Funding.
4.2. Proposed Capital Expenditure-Year Wise
Capital Expenditure Amount (Rs. in Cr.)
2015-16 194.73
2016-17 235.64
2017-18 252.13
2018-19 60.03
Total 742.52
4.3. User charges and O&M costs
Currently user charges are not levied by ULBs for SWM. The State Government is in the process of
approving user charges for SWM for Bhubaneswar Municipal Corporation (BMC). BMC has proposed
Rs. 50, Rs.100, Rs.200 per month respectively for Slum/EWS/LIG, MIG and HIG respectively. The
detailed user charges table is given as Annexure 4.
For other ULBs, average user fee of Rs. 50/month per household and Rs. 150/month for commercial
units for SWM services can be levied. It is proposed to include user fee for SWM in the holding tax
bill for ease of collection.
The O&M costs for management of municipal solid waste is ~Rs. 2000-2600/MT with collection and
transportation cost varying between Rs. 1500 and Rs. 1800/ MT (including road sweeping and drain
cleaning) and processing and landfill costs between Rs. 500 and Rs. 800/MT.
Currently due to absence of processing and scientific landfill facility the ULBs incur expenditure only
towards collection and transportation of municipal solid waste. To meet the additional cost associated
24 Act ion Plan fo r SW M in ULBs of Odisha
with processing and scientific disposal of waste user charges need to be levied for full cost recovery
for sanitation services.
On an average assuming a tipping fee of Rs. 2300/MT, the O&M costs shall be approximately Rs.
157 Cr. per annum. The O&M costs and cost recovery for services over a 10 year period is given
below.
Rs. in Cr.
SWM services revenue & cost recovery
2015-
16
2016-
17
2017-
18
2018-
19
2019-
20
2020-
21
2021-
22
2022-
23
2023-
24
2024-
25
Revenue 43 57 77 99 128 152 186 201 217 235
O&M / Tipping fee
157 167 178 189 201 214 227 242 257 274
Deficit -114 -110 -101 -90 -73 -62 -41 -41 -40 -38
Cost recovery for services
28% 34% 43% 53% 64% 71% 82% 83% 85% 86%
From the above table it can be seen that cost recovery for services gradually improves to 86%
over the next 10 years. The assumptions underlying the projections are given below:
No. of households to increase at 3% per annum in line with population growth
Tipping fee Rs.2300/MT with 5% escalation per annum; Additional revenue for operator from
compost
Per capita SWM generation @ 300 gm/day with increase of 1.3% per annum as per HPEC
Report on Indian Urban Infrastructure and Services;
Commercial units assumed at 15% of the households
Average collection efficiency assumed at 40% and 25% for BMC and rest of ULBs in the first
year respectively which will increase to 90% by seventh year in all the ULBs
Average user fee of Rs.90/month and Rs. 250/month assumed for residential and commercial
units respectively in BMC area and Rs.50/month and Rs. 150/month assumed for residential
and commercial units respectively in rest of the ULBs; User charges to increase at 5% per
annum.
4.4. Proposed Consolidated Cost-Year Wise
Rs. Cr.
Particulars
2015-
16
2016-
17
2017-
18
2018-
19
2019-
20
2020-
21
2021-
22
2022-
23
2023-
24
Capital Expenditure 195 236 252 60 - - - - -
O&M / Tipping fee 157 167 178 189 201 214 227 242 257
Total Expenditure 352 403 430 249 201 214 227 242 257
Total consolidated outlay including both capital and operating expenditure for the next five years ending
2019-20 is estimated to be Rs. 1635 Cr.
25 Act ion Plan fo r SW M in ULBs of Odisha
Assumptions
The capital outlay and the implementation schedule of SWM in various ULBs are based on the following
assumptions:
Per capita waste generation of 300 grams/day
Rs. 1500 per capita for arriving at capital cost as per SBM guidelines; Actual project cost may
vary depending on the technology, site conditions etc.
The clusters have been identified based on distances between towns and will vary during
implementation based on availability of suitable land
o The location of regional landfill sites may vary depending on availability of suitable land
The implementation plan is assuming that the Swachh Bharat Action Plan will be approved by the
Central Government and that State Budget shall be made available for implementation of SWM
projects
o It is assumed that all the ULBs shall apply for site allotment and shall obtain site
authorization prior to implementation
The projects have been assumed to be financed out of SBM funds; ULBs may tap alternate
source of funds.
26 Act ion Plan fo r SW M in ULBs of Odisha
27 Act ion Plan fo r SW M in ULBs of Odisha
Annexure 2 – SWM implementation on cluster basis
Name of the Cluster JHARSUGUDA, BRAJRAJNAGAR, BELPAHAR
Population 217126
Estimated MSW
Generation(TPD)* 65.54
Landfill Site Authorization
Status
Jharsuguda:- Authorization granted and Valid up to 31.03.2019.
Brajrajnagar:- Valid up to 31-03-2013. Renewal applied and is under process.
Belpahar:- Authorization granted and Valid up to 31-03-2018.
12th Finance Commission
Grantfor equipment and
vehicles procurement (Rs. in
Lakhs)
Jharsuguda:- 134.70
Brajrajnagar:- 108.10
Belpahar:- 88.60
Current Position
Door
to
Door
Colle
ction
Bins
Provid
ed
Whether collection spots
are attended daily
Segregation of waste
Transporta
tion facility
Qty Processe
d
Sanitar
y
Landfill
Jharsuguda Yes 126 Yes No
Truck-01, Truck
Tipper-03, Tractor
Trailer-01, Dumper
Placer-01, Tricycle-21
Nil No
Brajrajnagar Yes 211 Yes No
Tempo Tipper-04,
Tractor Trailer-03, Tractor-04,
Wheel barrow-128
Nil No
Belpahar Yes 183 - No
Truck Tipper-02,
Tractor Trailer-05, Dumper
Placer-02, Tricycle-13
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
28 Act ion Plan fo r SW M in ULBs of Odisha
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at
Brajrajnagar/ Jharsuguda
Estimated Project Cost (PC)
(Rs. in Crore)**
32.569
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant(@75% of
PC) 24.42
State Assistance/Grant (@25% of
PC) 8.142
Total 32.569
Period of implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
29 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
JAJPUR, VYASANAGAR
Population 86369
Estimated
MSW
Generation
(TPD)*
25.91
Landfill Site
Authorization
Status
Jajpur: Authorization granted was valid up to 31-03-2013. Applied for renewal.
Vyasanagar: Authorization granted was valid up to 31-03-2014. Renewal applied and
is under process.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Jajpur: 49.40
Vyasanagar: 73.20
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Jajpur Yes 107 Yes No
Auto Tipper-02, Tractor Trailer-
03,Dumper Placer-02,
Tricyc;e-15, Push Cart-13
Nil No
Vyasanagar No 92 Yes No
Truck Tipper-02,Tractor Trailer-03,
Tricycle-02, Tricycle-03,
JCB-01
Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Jajpur, Vyasanagar,
30 Act ion Plan fo r SW M in ULBs of Odisha
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
12.95
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 9.71
State Assistance/Grant (@25% of PC) 3.24
Total 12.95
Period of
implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
31 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
BARBIL, JODA
Population 113171
Estimated MSW generation (TPD)
34
Landfill Site
Authorization
Status
Barbil: Authorization granted was valid up to 31-03-2013. Renewal applied and is under
process.
Joda: Authorization granted and valid up to 31-03-2018.
12th Finance
Commission
Grant for
equipment and
vehicles
procurement
(Rs. in Lakhs)
Barbil: 71.20
Joda: 64.90
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Barbil Yes 68 Yes No
TractorTrailer-03,Tricycle-
18,AutoTipper-02,Hook
Loader-01
Nil No
Joda Yes 138 Yes No Tractor Trailer-03,Auto Tipper-
02 Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Barbil, Joda
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
16.98
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 12.73
State Assistance/Grant (@25% of PC) 4.24
32 Act ion Plan fo r SW M in ULBs of Odisha
Total 16.98
Period of
implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
33 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
DHENKANAL, ATHAGARH
Population 84718
Estimated MSW generation (TPD)
25
Landfill Site
Authorization
Status
Dhenkanal: Authorization granted and Valid up to 31-03-2018.
Athagarh: Not applied.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Dhenkanal: 77.90
Athagarh: 29.50
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Dhenkanal Yes 238 Yes No
Tractor Trailer-04, Dumper Placer-01,
Tricycle-48, Auto Tipper-05
Nil No
Athagarh No 20 No No Tractor Trailer-
02, Wheel Barrow-20
Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Dhenkanal, Athagarh
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
12.70
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 9.53
34 Act ion Plan fo r SW M in ULBs of Odisha
State Assistance/Grant (@25% of PC) 3.17
Total 12.70
Period of
implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
35 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster***
ATABIRA, BARGARH & BARAPALI
Population 117874
Estimated MSW generation (TPD)
35
Landfill Site
Authorization
Status
Atabira: Not applied.
Bargarh: Authorization granted was valid up to 31-03-2015.
Barapali Authorization granted was valid up to 31-03-2014. Not Applied for Renewal
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Atabira: NA
Bargarh: 91.70
Barapali:37.50
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Atabira NA NA NA NA NA NA NA
Bargarh - 72 Yes Yes
Tractor Trailer-05, Auto
tipperr-03, Tricycle-10
Nil No
Barapali Yes 91 - No
Tractor Trailer-02, Dumper Placer-01, Tricycle-13
Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Bargarh
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
17.68
36 Act ion Plan fo r SW M in ULBs of Odisha
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 13.26
State Assistance/Grant (@25% of PC) 4.42
Total 17.68
Period of
implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
***(Data Not available for Atabira&Barapali)
37 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
JEYPORE, SUNABEDA, KORAPUT
Population 182692
Estimated MSW generation (TPD)
55
Landfill Site
Authorization
Status
Jeypore: Authorization granted and Valid up to 31-03-2015.
Sunabeda: Authorization granted and Valid up to 31-03-2015.
Koraput: Authorization granted was valid up to 31-03-2014. Applied for Renewal.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Jeypore: 91.20
Sunabeda:128.50
Koraput: 99.50
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Jeypore Yes 44 Yes No
Tricycle-36, Tractor Trailer-05, Push Cart-
31, Wheel Barrow-60
Nil No
Sunabeda Yes 391 Yes No
Dumper Placer-02, Tractor Trailer-04,
Tricycle-27, Wheel Barrow-03, Push Cart-
23
Nil No
Koraput Yes 53 Yes No
Auto Tipper-02, Tractor Trailer-
03, Dumper Placer-02,
Tricycle-18, Wheel Barrow-30, Push Cart-
16
Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
38 Act ion Plan fo r SW M in ULBs of Odisha
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Koraput
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
27.40
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 20.55
State Assistance/Grant (@25% of PC) 6.85
Total 27.40
Period of
implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
39 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
KHURDA, JATNI, CUTTACK, &BHUBANESHWAR
Population 1553153
Estimated MSW generation (TPD)
466
Landfill Site
Authorization
Status
Khurda: Authorization granted and valid up to 31.03.2017.
Jatni: Authorization granted and valid up to 31-03-2015
Cuttack: Authorization was valid up to 31-03-2013. Case filed. Not applied for Renewal.
Bhubaneshwar: Authorization granted and valid up to 31-03-2018
12th Finance
Commission
Grant for
equipment and
vehicles
procurement
(Rs. in Lakhs)
Khurda: 65.60
Jatni: 64.20
Cuttack: 1299.90
Bhubaneshwar:1355.40
Current
Position (SLB
Data) & Target
for 2019-20
Service / Indicator National
Benchmark
Current
Status
Target
for FY
2018-19
HH level Coverage (%) 100 51 58.75
Efficiency of Collection (%) 100 54.25 67.5
Extent of Segregation (%) 100 10 16.25
Extend of MSW recovered (%) 80 27.5 35.25
Extent of Scientific Disposal (%) 100 0 2.5
Efficiency in Redressal of Complaints (%) 80 73.5 78.75
Extent of Cost Recovery (%) 100 2.5 11.25
Efficiency in Collection of SWM Charges (%) 90 17.5 48.75
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Khurda No 60 - No
Tractor Trailer-06, Auto Tipper-02,Wheel Barror-51, Tricycle-18
Nil No
Jatni Yes 157 Yes No Tractor Trailer-03, Auto Tipper-
03 Nil No
Cuttack Yes 2500 Yes Yes
Truck-02,Truck Tipper-10,Auto
Tipper-20,Tractor Trailer-
68,Tricycle-
Nil No
40 Act ion Plan fo r SW M in ULBs of Odisha
1500,Bob Cats-02
Bhubaneshwar Yes 922 Yes Yes
Primary Collection is done
by required of nos. of
Tractors/Tippers for Privatized 40 nos. of wards to the temporary transfer station
and primary collection for
BMC managed 20 nos of wards
is done by tractors (engaged by private agency
and 6 nos. of hook loader lorry and 22 nos of 9 cum capacity
containers(owned by BMC).
Secondary Collection from
Temporary Transfer station to Landfill site is done trough the
private agency by engaging
required nos. of Tippers/Haiwas
Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Bhubaneswar
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
232.97; project proposed to be implemented on PPP basis for Bhubaneswar and Cuttack
41 Act ion Plan fo r SW M in ULBs of Odisha
Period of
implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
42 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
BERHAMPUR, GOPALPUR, CHATRAPUR, CHIKITI, DIGAPAHANDI
Population 410681
Estimated MSW generation (TPD)
123
Landfill Site
Authorization
Status
Berhampur: Authorization Granted and valid upto 31.03.2018
Gopalpur: Not applied.
Chatrapur: Not applied.
Chikiti: Not applied.
Digapahandi: Applied and is under process.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Berhampur: 740.60
Gopalpur: 13.70
Chatrapur:26.30
Chikiti: 21.30
Digapahandi:24.80
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Berhampur Yes 651 Yes No
Tractor Trailler-16, Refuse
Collector-01, Dumper Placer-
06,Tricycle-134, Auto Tipper-11,
MiniTruck-02, Front end Loader-02 Nil No
Gopalpur Yes 04 Yes No
Tractor Trailer-01, Refuse
Collector-01, Tricycle-03 Nil No
Chatrapur Yes 130 Yes No
Tractor Trailer-03, Dumper
Placer-01,Tricycle-14, Wheel Barrow-40, Cesspool-
01 Nil No
Chikiti No 12 Yes No Tractor Trailer-
02 Nil No
Digapahandi - - - - -
- -
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
43 Act ion Plan fo r SW M in ULBs of Odisha
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Berhampur
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
61.60; (Project awarded on PPP basis to a private developer for Berhampur town at
estimated project cost of Rs. 40.60 Cr.)
Period of
implementation 2015-16
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
44 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
ASKA, KABI SURYA NAGAR, PURUSOTAMPUR & HINJLICUT
Population 88895
Estimated MSW generation (TPD)
27
Landfill Site
Authorization
Status
Aska: Authorization granted and valid up to 31.03.2018.
Kabi Surya Nagar : Authorization granted and valid up to 31.03.2018
Purusotampur: Authorization granted and valid up to 31.03.2018
Hinjlicut: Authorization granted was valid up to 31.03.2013. Not applied for renewal.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Aska: 27
Kabi Surya Nagar : 35.90
Purusotampur: 52.10
Hinjlicut:33.30
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Aska No 61 Yes No
Tractor Trailer-02, Tricycle-10, Wheel Barrow-
15 Nil No
Kabi Surya
Nagar Yes 119 Yes No
Tractor Trailer-02, Refuse
Collector-05, Tricycle-13 Nil No
Purusotampur No 50 Yes No
Tractor-02,Tricycle-09, Wheel Barrow-
50, Auto Tipper-02 Nil No
Hinjlicut No 11 Yes No Tractor-
02,Tricycle-23 Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Aska
45 Act ion Plan fo r SW M in ULBs of Odisha
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
11.83
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 8.87
State Assistance/Grant (@25% of PC) 2.95
Total 11.83
Period of
implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
46 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
PARALAKHEMENDI, KASINAGAR
Population 54153
Estimated MSW generation (TPD)
16
Landfill Site
Authorization
Status
Paralakhemendi: Not applied.
Kasinagar: Not applied.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Paralakhemendi: 44.90
Kasinagar: 22.40
Current Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Paralakhemendi No 21 Yes No
Tractor-02,Tricycle-20,
Refuse Collector-02,Wheel Barrow-30 Nil No
Kasinagar - - - - -
- -
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Paralakhemundi
Estimated
Project Cost
(PC)
(Rs. in Crore)**
8.12
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 6.09
47 Act ion Plan fo r SW M in ULBs of Odisha
State Assistance/Grant (@25% of PC) 2.03
Total 8.12
Period of
implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
48 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
SAMBALPUR, HIRAKUD & BURLA
Population 260905
*Estimated MSW generation TPD)
78
Landfill Site
Authorization
Status
Sambalpur: Valid up to 31.03.2013. Not Applied for Renewal Case filed.
Hirakud: Authorization granted was valid up to 31-03-2013. Not applied for Renewal.
Burla: Authorization granted and valid up to 31.03.2018.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Sambalpur:433.90
Hirakud:41.60
Burla: 53.50
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Sambalpur No 260 Yes No
Dumper Placer-02, Truck Tipper-01,
Tractor Trailer-02, Tricycle-63,
Hydraulic Loader-01,
Truck-03, Back whole Loader-
01 Nil No
Hirakud No 03 No No Tractor Trailer-04,Tricycle-14
Nil No
Burla No 66 No No Tractor Trailer-
02 Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Sambalpur
49 Act ion Plan fo r SW M in ULBs of Odisha
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
50.36; proposed to be funded on PPP basis
Period of
implementation 2016-17
50 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
SORO, BASUDEVPUR
Population 66221
Estimated MSW generation (TPD)
20
Landfill Site
Authorization
Status
Soro: Authorization granted and valid up to 31.03.2017
Basudevpur: Authorization granted was valid up to 31-03-2014. Not Applied for renewal
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Soro: 54.10
Basudevpur: 76
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Soro Yes 56 Yes No Tricycle-15,
Wheel Barrow-18 Nil No
Basudevpur Yes 16 No No
Tractor Trailer-01, Wheel Barrow-07,
Dumper Placer-01 Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material at Soro
Estimated
Project Cost
(PC)
(Rs. in
Crore)**
9.93
51 Act ion Plan fo r SW M in ULBs of Odisha
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 7.45
State Assistance/Grant (@25% of PC) 2.48
Total 9.93
Period of
implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
52 Act ion Plan fo r SW M in ULBs of Odisha
Name of the Cluster
SONEPUR&TARBHA
Population 29104
Estimated MSW generation (TPD)
9
Landfill Site
Authorization
Status
Tarbha: Authorization granted was valid up to 31-03-2013. Applied for renewal and
is under process.
12th Finance
Commission
Grantfor
equipment and
vehicles
procurement
(Rs. in Lakhs)
Sonepur: 31.23
Tarbha:23.20
Current
Position
Door to
Door
Collection
Bins
Provided
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
Sonepur Yes 112 Yes No Tractor trailer -03, Tricycle -12
Nil No
Tarbha No 38 Yes No
Tricycle-05, Wheel Barrow-
05, Tractor Trailer-02 Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Regional Land fill of non bio-degradable and inert material.Regional landfill at Sonepur
Estimated
Project Cost
(Rs. in
Crore)**
4.36
Means of
finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.27
State Assistance/Grant (@25% of PC) 1.09
53 Act ion Plan fo r SW M in ULBs of Odisha
Total 4.36
Period of
implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
54 Act ion Plan fo r SW M in ULBs of Odisha
Annexure 3–SWM implementation in various ULBs on standalone basis
Name of the ULB ANANDAPUR MUNICIPALITY, DIST-KEOJHARGARH, ODISHA
Population 39,585
Estimated MSW
Generation (TPD)* 11.88 MT
Landfill Site
Authorization Status Authorization granted and valid up to 31-03-2018.
12th Finance
Commission Grant for
equipment &vehicles
(Rs. in Lakhs)
111.90
Current Position
Door
to
Door
Colle
ction
Bins
Provid
ed
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processe
d
Sanitary
Landfill
Yes 95 Yes No
Truck tipper-
02, Tractor
Trailer-02,
Dumper
Placer-02,
Tricycle-16,
Wheel
Barrow-45
Nil No
Proposed Strategy
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material.
Estimated Project Cost** 5.94 Crore
Means of finance
Source Amount
Central Assistance/Grant (@75% of PC) 4.45 Crore
State Assistance/Grant (@25% of PC) 1.49 Crore
Total 5.94 Crore
Period of
implementation 2017-18
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
55 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB ANGUL MUNICIPALITY, DIST-ANGUL, ORISSA
Population 43,795
Estimated MSW
Generation (TPD)* 13.14 MT
Landfill Site
Authorization Status Authorization granted was valid up to 31-03-2014. Applied for renewal.
12th Finance
Commission Grant
for equipment and
vehicles procurement
(Rs. in Lakhs)
59.50
Current Position
Door to
Door
Collection
Bins
Provid
ed
Whether collection spots are attended
daily
Segregation of wast
e
Transportation
facility
Qty Process
ed
Sanitary
Landfill
Yes 184 Yes No
Truck-01,
Tractor
Trailer-
04,Tricycle-30
Nil No
Proposed
intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material.
Estimated Project
Cost (PC)
(Rs. in Crore)**
6.57 Cr
Means of finance
(through Swachha
Bharat Mission)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 4.93 Cr
State Assistance/Grant (@25% of PC) 1.64 Cr
Total 6.57 Cr
Period of
implementation 2016-17
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
56 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB ATHAMALLIK NAC, DIST- ANGUL, ORISSA
Population 12,298 Cr
Estimated MSW Generation
(TPD)* 3.69 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2014. Applied for renewal
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
36.40
Current Position
Door
to
Door
Colle
ction
Bins
Provid
ed
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitar
y
Landfill
No 41 Yes No
Tractor-02,
Push Cart-
05,Tricycle-08
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.84 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.38 Cr
State Assistance/Grant (@25% of PC) 0.46 CR
Total 1.84 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
57 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BALIMELA NAC, DIST-MALKANGIRI, ORISSA
Population 11,796
Estimated MSW Generation
(TPD)* 3.54 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
18.30
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
Yes 10 Yes No
Tractor Trailer-
01, Wheel
Barrow-04
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.78 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.34 Cr
State Assistance/Grant (@25% of PC) 0.44 Cr
Total 1.78 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
58 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BALUGAON NAC, DIST-KHURDA, ORISSA
Population 17,645
Estimated MSW Generation
(TPD)* 5.29 MT
Landfill Site Authorization
Status Authorization applied for and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
26.10
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether
collection
spots are
attended
daily
Segregation
of waste
Transportatio
n facility
Qty Processe
d
Sanitary
Landfill
Yes 10 Yes No Tractor
Trailer-02 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.9 Cr.; proposed under ICZMP
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
59 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BANKI NAC, DIST-CUTTACK, ORISSA
Population 17,521
Estimated MSW Generation
(TPD)* 5.26 MT
Landfill Site Authorization
Status Authorization Refused
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
25
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation
of waste
Transportatio
n facility
Qty Processed
Sanitar
y
Landfill
No 60 No No Tractor
Trailer-03 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.63 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.97 Cr
State Assistance/Grant (@25% of PC) 0.66 Cr
Total 2.63 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
60 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BANAPUR NAC, DIST-KHURDA, ORISSA
Population 17,278
Estimated MSW Generation
(TPD)* 5.18 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2014. Not applied for renewal.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
27.30
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
Yes 68 Yes No
Tractor Trailer-
01, Wheel
Barrow-07
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.59 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.94 Cr
State Assistance/Grant (@25% of PC) 0.65 Cr
Total 2.59 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
61 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BELAGUNTHA NAC, DIST-GANJAM, ORISSA
Population 11,297
Estimated MSW Generation
(TPD)* 3.39 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
17.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transpor
tation
facility
Qty Processed
San
itar
y
Lan
dfill
Yes 12 Yes No
Tractor
Trailer-
01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.69 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.27 Cr
State Assistance/Grant (@25% of PC) 0.42 Cr
Total 1.69 cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
62 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BHANJANAGAR NAC, DIST-GANJAM, ORISSA
Population 20,482
Estimated MSW Generation
(TPD)* 6.14 MT
Landfill Site Authorization
Status Not Applied
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
26.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation of waste
Transportation
facility
Qty Processed
San
itar
y
Lan
dfill
No 41 Yes No
Tractor Trailer-
01, Wheel
Barrow-08
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.07 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.30 Cr
State Assistance/Grant (@25% of PC) 0.77 Cr
Total 3.07 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
63 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BHUBAN NAC, DIST-DHENKANAL, ORISSA
Population 22,200
Estimated MSW Generation
(TPD)* 6.66 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
38.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
San
itar
y
Lan
dfill
Yes 50 Yes No
Tractor Trailer-01,
Dumper Placer-
01, Tricycle-16,
Auto Tipper-
01,Wheel Barrow-
20
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.33 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.50 Cr
State Assistance/Grant (@25% of PC) 0.83 Cr
Total 3.33 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
64 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BINIKA NAC, DIST-SUBARNAPUR, ORISSA
Population 15,765
Estimated MSW
Generation (TPD)* 4.73 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs.
in Lakhs)
37.70
Current Position
Door
to
Door
Collec
tion
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processe
d
Sanit
ary
Landfi
ll
No 21 No No
Tractor Trailer-
01, Power
Tiller-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost
(PC)
(Rs. in Crore)**
2.36 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.77 Cr
State Assistance/Grant (@25% of PC) 0.59 Cr
Total 2.36 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
65 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BOUDHGARH NAC, DIST-BOUDH, ORISSA
Population 20,424
Estimated MSW Generation
(TPD)* 6.13 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2016
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
40.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportati
on facility
Qty Processed
Sanit
ary
Landfi
ll
No 42 Yes No Tractor-02 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.07 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.30 Cr
State Assistance/Grant (@25% of PC) 0.77 Cr
Total 2.37 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
66 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BUGUDA NAC, DIST GANJAM-, ORISSA
Population 15,176
Estimated MSW Generation
(TPD)* 4.55 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
21.90
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation of waste
Transportation
facility
Qty Processe
d
Sanit
ary
Landfi
ll
Yes 68 Yes No
Tractor
Trailer-02,
Tricycle-09,
Wheel
Barrow-25
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.28 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.71 Cr
State Assistance/Grant (@25% of PC) 0.57 Cr
Total 2.28 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
67 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BALASORE MUNICIPALITY, DIST-BALASORE, ORISSA
Population 1,18,162
Estimated MSW
Generation (TPD)* 35.45
Landfill Site
Authorization Status Authorization valid up to 31.03.2014. Not applied for renewal
12th Finance
Commission Grant for
equipment &vehicles
procurement (Rs. lakhs)
278.30
Current Position
Door to
Door
Collectio
n
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Proces
sed
Sanitar
y
Landfill
Yes 328 No No
Mini Truck -02,
Tractor Tipper -
03, Tricycle-49,
Wheel barrow-
141,Push Cart-
42, Refuse
collector-01
Tricycle-65
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers and
kabadiwalas
C. Transportation
Transportation from Transfer Stations through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material.
Estimated Project Cost** Rs. 17.72 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 13.29 Cr
State Assistance/Grant (@25% of PC) 4.43 Cr
Total 17.72 Cr
Period of
implementation 2016-17
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
68 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BARIPADA MUNICIPALITY, DIST-MAYURBHANJ, ORISSA
Population 1,09,743
Estimated MSW Generation
(TPD)* 32.92 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2013. Not applied for renewal.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
112.20
Current Position
Door
to
Door
Colle
ction
Bins
Prov
ided
Whether collection spots
are attended daily
Segregation of wast
e
Transportation
facility
Qty Processed
Sanitary
Landfill
Yes 398 Yes No
Hydraulic Tractor-
02, Auto Tipper-04,
Tractor Trailer-02,
Dumper Placcer-
02,Tricycle-44,
Push Cart-38,Road
Roller-01, Cess
Pool Evacuation-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material.
Estimated Project Cost (PC)
(Rs. in Crore)** Rs. 16.46 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 12.35 Cr
State Assistance/Grant (@25% of PC) 4.11 Cr
Total 16.46 Cr
Period of implementation 2016-17
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
69 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BHADRAK MUNICIPALITY, DIST-BHADRAK, ORISSA
Population 1,07,463
Estimated MSW Generation
(TPD)* 32.24 MT
Landfill Site Authorization
Status Not applied
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
107.30
Current Position
Door
to
Door
Colle
ction
Bin
s
Pro
vid
ed
Whether
collection
spots are
attended daily
Segregation
of waste
Transportation
facility
Qty Processe
d
Sanitary
Landfill
No 254 Yes No
, Tractor Trailer-
03, Dumper
Placers-02,
Tricycle-43,
Auto Tipper-04,
Double Wheel
Barrow-50
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material.
Estimated Project Cost (PC)
(Rs. in Crore)** Rs. 16.12 Cr; proposed to be funded under ICZMP
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
70 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BHAWANIPATNA MUNICIPALITY, DIST-KALAHANDI, ORISSA
Population 69,045
Estimated MSW Generation
(TPD)* 20.71 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2012. Applied for renewal
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
67.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportation
facility
Qty Process
ed
Sanitary
Landfill
- 137 Yes No
Tricycle-
28,Tractor-05,
Tractor Trailer-
03, Auto
Tipper-03
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 10.36 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 7.77 Cr
State Assistance/Grant (@25% of PC) 2.59 Cr
Total 10.36 Cr
Period of implementation 2016-17
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
71 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BIRAMITRAPUR MUNICIPALITY, DIST-SUNDERGARH, ORISSA
Population 33,442
Estimated MSW Generation
(TPD)* 10.03
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
52.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportation
facility
Qty Processed
Sanit
ary
Landfi
ll
Yes 78 Yes No
Tractor Trailer-02,
Wheel Barrow-35,
Refuse Collector-
16,Tricycle-14,
AutoTipper-02,
AttachmentBin-02
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 5.02 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.76 Cr
State Assistance/Grant (@25% of PC) 1.26 Cr
Total 5.02 Cr
Period of implementation 2017-18
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
72 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB BOLANGIR MUNICIPALITY, DIST-BOLANGIR, ORISSA
Population 98,238
Estimated MSW Generation
(TPD)* 29.47
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2015.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
102.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Process
ed
San
itar
y
Lan
dfill
No 75 No No
Mini Truck -01,
Tractor-05,
Excavator-01,
Auto Tipper-04,
Hook Loader
Lorry-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 14.73 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 11.05 Cr
State Assistance/Grant (@25% of PC) 3.68 Cr
Total 14.73 Cr
Period of implementation 2016-17
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
73 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB CHOUDWAR MUNICIPALITY, DIST-CUTTACK, ORISSA
Population 42,784
Estimated MSW Generation
(TPD)* 12.84
Landfill Site Authorization
Status Authorization granted was valid up to 31-03-2014. Applied for renewal
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
67.32
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Process
ed
Sanitary
Landfill
No 22 Yes No
Tractor
Trailer-02,
Wheel
Barrow-70
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 6.42 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 4.82 Cr
State Assistance/Grant (@25% of PC) 1.60
Total 6.42 Cr
Period of implementation 2017-18
*Based on the calculation of the state average per capita per day MSW generation @300 gram
**Based on per capita cost of Rs 1500 in accordance with the “Swachh Bharat Mission” Guidelines
74 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB DEOGARH MUNICIPALITY, DIST- DEOGARH, ORISSA
Population 22,390
Estimated MSW Generation
(TPD)* 6.72 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2015
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
49.90
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of
waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
Yes 61 Yes No
Mini Truck-01,
Tractor
Trailer-
03,Tricycle-13
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.36 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.52 Cr
State Assistance/Grant (@25% of PC) 0.84 Cr
Total 3.36 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
75 Act ion Plan fo r SW M in ULBs of Odisha
Name of theULB G.UDAYAGIRI NAC, DIST-PHULBANI, ORISSA
Population 11,302
Estimated MSW Generation
(TPD)* 3.39 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
26.70
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transporta
tion facility
Qty Processed
Sanitar
y
Landfill
Yes 02 Yes No
Tractor
Trailer-02,
Tricycle-07
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.69 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.27 Cr
State Assistance/Grant (@25% of PC) 0.42 Cr
Total 1.69 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
76 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB GANJAM NAC, DIST-GANJAM, ORISSA
Population 11,474
Estimated MSW Generation
(TPD)* 3.52 MT
Landfill Site Authorization
Status Not Applied
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
23.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportati
on facility
Qty Process
ed
Sanitar
y
Landfill
Yes 30 Yes No
Tricycle-06,
Wheel
Barrow-08,
Tractor-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.76 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.52 Cr
State Assistance/Grant (@25% of PC) 1.32 Cr
Total 1.76 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
77 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB GUDARI NAC, DIST-RAYAGADA, ORISSA
Population 6,931
Estimated MSW Generation
(TPD)* 2.08 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
12.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanitar
y
Landfill
No 51 Yes No
Tractor
Trailer-02,
Dumper
Placer-
01,Animal
Cart-04
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.04 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 0.78 Cr
State Assistance/Grant (@25% of PC) 0.26 Cr
Total 1.04 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
78 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB GUNPUR NAC, DIST-RAYAGADA, ORISSA
Population 24,162
Estimated MSW Generation
(TPD)* 7.25 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31-03-2017.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
35.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transportati
on facility
Qty Processed
Sanit
ary
Land
fill
Yes 117 Yes No
Tractor
Trailer-
02,Dumper
Placer-
01,Tricycle-
14, Wheel
Barrow-20
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.62 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.71 Cr
State Assistance/Grant (@25% of PC) 0.91 Cr
Total 3.62 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
79 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB JAGATSINGHPUR MUNICIPALITY, DIST- JAGATSINGHPUR, ORISSA
Population 33,631
Estimated MSW Generation
(TPD)* 10.09 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
45.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportatio
n facility
Qty Processe
d
Sanit
ary
Landfi
ll
No 70 No No
Truck-01,
Tractor
Trailer-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.88 Cr. proposed under ICZMP
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
80 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB JALESWAR NAC, DIST-BALASORE, ORISSA
Population 25,747
Estimated MSW Generation
(TPD)* 7.72 MT
Landfill Site Authorization
Status Not Applied
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
39.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transporta
tion facility
Qty Proces
sed
Sanit
ary
Landfi
ll
No 15 Yes No
Truck
Tipper-01,
Animal
Cart-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.86 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.90 Cr
State Assistance/Grant (@25% of PC) 0.96 Cr
Total 3.86 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
81 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB JUNAGARH NAC, DIST-KALAHANDI, ORISSA
Population 19,656
Estimated MSW Generation
(TPD)* 5.90 MT
Landfill Site Authorization
Status
Authorization granted was valid up to 31.03.2013. Not Applied for Renewal
Case filed.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
34.90
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportati
on facility
Qty Processe
d
Sanitar
y
Landfill
No 131 No No
Tractor
Trailer-01,
Wheel
Barrow-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.95 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.21 Cr
State Assistance/Grant (@25% of PC) 0.74 Cr
Total 2.95 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
82 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KEONJHARGARH MUNICIPALITY, DIST-KEONJHAR, ORISSA
Population 60,590
Estimated MSW Generation
(TPD)* 18.18 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2019.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
71.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
Yes 325 Yes No
Tractor Trailer-
03, Dumper
Placer-
02,Tricycle-22,
Wheel Barrow-
35
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 9.09 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 6.82 Cr
State Assistance/Grant (@25% of PC) 2.27 Cr
Total 9.09 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
83 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KAMAKSHYANAGAR NAC, DIST-DHENKANAL, ORISSA
Population 16,810
Estimated MSW Generation
(TPD)* 5.04 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2019
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
30.10
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportation
facility
Qty Process
ed
Sanit
ary
Landfi
ll
Yes 62 No No
Tractor
Trailer-01,
Wheel
Barrow-04,
Power Trailer-
01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.52 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.89 Cr
State Assistance/Grant (@25% of PC) 0.63 Cr
Total 2.52 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
84 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KANTABANJI NAC, DIST-BALANGIR, ORISSA
Population 21,819
Estimated MSW Generation
(TPD)* 6.55 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2015
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
29.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Processed
Sanit
ary
Land
fill
Yes 06 Yes No
Tractor
Trailer-02,
Tricycle-13
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.27 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.45 Cr
State Assistance/Grant (@25% of PC) 0.82 Cr
Total 3.27 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
85 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KARANJIA NAC, DIST-MAYURBHANJA, ORISSA
Population 22,865
Estimated MSW Generation
(TPD)* 6.86 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2015
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
42.70
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of wast
e
Transportati
on facility
Qty Proces
sed
Sanit
ary
Landfi
ll
Yes 85 Yes No
Tractor
Trailer-02,
Tricycle-
14,Push
Cart-09
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.43 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.57 Cr
State Assistance/Grant (@25% of PC) 0.85 Cr
Total 3.42 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
86 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KESINGA NAC, DIST-KALAHANDI, ORISSA
Population 19,239
Estimated MSW Generation
(TPD)* 5.77 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
34.70
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processe
d
San
itar
y
Lan
dfill
Yes 385 Yes No
Tractor Trailer-02,
Wheel Barrow-30,
Dumper Placer-
01, Push Cart-07,
Tricycle-11, Auto
Tipper-01, Two
wheeler-06
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.88 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.16 Cr
State Assistance/Grant (@25% of PC) 0.72 Cr
Total 2.88 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
87 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KHALLIKOTE NAC, DIST-GANJAM, ORISSA
Population 13,022
Estimated MSW Generation
(TPD)* 3.91 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
43.70
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Process
ed
Sanit
ary
Landfi
ll
No 51 Yes No
Tractor
Trailer-01,
Tricycle-03
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.95 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.46 Cr
State Assistance/Grant (@25% of PC) 0.49 Cr
Total 1.95 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
88 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KHANDAPARA NAC, DIST-NAYAGARH, ORISSA
Population 9,038
Estimated MSW Generation
(TPD)* 2.71 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2014. Renewal not applied.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
27.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transporta
tion facility
Qty Processe
d
Sanit
ary
Landfi
ll
Yes 70 - No
Tractor
Trailler-
02,Tricycle
-06
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.36 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.02 Cr
State Assistance/Grant (@25% of PC) 0.34 Cr
Total 1.36 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
89 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KHARIAR ROAD NAC, DIST-NUAPADA, ORISSA
Population 18,967
Estimated MSW Generation
(TPD)* 5.69 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
39.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation
of waste
Transport
ation
facility
Qty Process
ed
Sanit
ary
Landfi
ll
Yes 34 - No Tractor
Trailer-02 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.84 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.13 Cr
State Assistance/Grant (@25% of PC) 0.71 Cr
Total 2.84 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
90 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KHARIAR NAC, DIST- NUAPADA, ORISSA
Population 15,087
Estimated MSW Generation
(TPD)* 4.53 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
32.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transportatio
n facility
Qty Processed
San
itar
y
Lan
dfill
Yes 43 Yes No
Tractor
Trailer-02,
Dumper
Placers(Bins)
-11, Tricycle-
09
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.26 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.70 Cr
State Assistance/Grant (@25% of PC) 0.56 Cr
Total 2.26 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
91 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KODALA NAC, DIST-GANJAM, ORISSA
Population 13,965
Estimated MSW Generation
(TPD)* 4.19 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
35.20
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Processe
d
San
itar
y
Lan
dfill
No 8 Yes No
Tricycle-08,
Tractor
Trailer-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.09 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.57 Cr
State Assistance/Grant (@25% of PC) 0.52 Cr
Total 2.09 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
92 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KONARK NAC, DIST-PURI, ORISSA
Population 16,779
Estimated MSW Generation
(TPD)* 5.03 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
52.20
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether
collection
spots are
attended
daily
Segregation
of waste
Transportatio
n facility
Qty Processe
d
Sanitary
Landfill
No 20 Yes No
Tractor-
01,Wheel
Barrow-10
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore) 2.88 Cr. proposed under ICZMP
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
93 Act ion Plan fo r SW M in ULBs of Odisha
Name of theULB KOTPAD NAC, DIST-KORAPUT, ORISSA
Population 16,326
Estimated MSW Generation
(TPD)* 4.90 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2014. Renewal not applied
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
31
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportati
on facility
Qty Processe
d
Sanitary
Landfill
Yes 04 No No
Tractor
Trailer-02,
Tricycle-02
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.45 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.84 Cr
State Assistance/Grant (@25% of PC) 0.61 Cr
Total 2.45 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
94 Act ion Plan fo r SW M in ULBs of Odisha
Name of theULB KUCHINDA NAC, DIST-SAMBALPUR, ORISSA
Population 15,576
Estimated MSW Generation
(TPD)* 4.67 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
33.20
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
No 17 Yes No Tractor
Trailer-01 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.34 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.75 Cr
State Assistance/Grant (@25% of PC) 0.59 Cr
Total 2.34 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
95 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB KENDRAPARA MUNICIPALITY, DIST-KENDRAPARA, ORISSA
Population 47,006
Estimated MSW Generation
(TPD)* 14.10 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31-03-2019.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
50.20
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transport
ation
facility
Qty Processed
San
itar
y
Lan
dfill
Yes - Yes No
Tractor
Trailer-
04,Tricycl
e-10,Auto
Tipper-
02,Wheel
Barrow-50
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 7.05 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 5.29 Cr
State Assistance/Grant (@25% of PC) 1.76 Cr
Total 7.05 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
96 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB MALKANAGIRI NAC, DIST-MALKANAGIRI, ORISSA
Population 31,007
Estimated MSW Generation
(TPD)* 9.30 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2019
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
40.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Process
ed
Sanit
ary
Landfi
ll
No 121 Yes No
Tractor-02,
Wheel
Barrow-50
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 4.65 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.49 Cr
State Assistance/Grant (@25% of PC) 1.16 Cr
Total 4.65 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
97 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB NAWARANGPUR MUNICIPALITY, DIST-NAWARANGPUR, ORISSA
Population 29,960
Estimated MSW Generation
(TPD)* 8.99 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2013. Renewal not applied.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
37.00
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of wast
e
Transportati
on facility
Qty Processed
San
itar
y
Lan
dfill
No 54 Yes No
Tractor-
04,Tractor
Trailer-02,
Tricycle-
07,Wheel
Barrow-20
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 4.49 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.37 Cr
State Assistance/Grant (@25% of PC) 1.12 Cr
Total 4.49 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
98 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB NAYGARH NAC, DIST-NAYAGARH, ORISSA
Population 17,030
Estimated MSW Generation
(TPD)* 5.11 MT
Landfill Site Authorization
Status Authorization granted was valid up to 31-03-2012. Not applied for Renewal.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
34.80
Current Position
Door
to
Door
Colle
ction
Bins
Provid
ed
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Proces
sed
Sanit
ary
Landfi
ll
No 70 Yes No
Tractor
Trailer-
03,Tricycle-
10, Wheel
Barrow-19
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.55 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.91 Cr
State Assistance/Grant (@25% of PC) 0.64 Cr
Total 2.55 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
99 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB NILAGIRI NAC, DIST-BALASORE, ORISSA
Population 17,264
Estimated MSW Generation
(TPD)* 5.18 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2015
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
35.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transporta
tion facility
Qty Process
ed
Sanitar
y
Landfill
No 10 Yes No
Tractor
Trailer-01,
Wheel
Barrow-06
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.59 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.94 Cr
State Assistance/Grant (@25% of PC) 0.65 Cr
Total 2.59 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
100 Act ion Plan fo r SW M in ULBs of Odisha
Name of theULB NIMAPARA NAC, DIST-PURI , ORISSA
Population 19,289
Estimated MSW Generation
(TPD)* 5.79 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2012. Renewal applied and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
34.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportati
on facility
Qty Process
ed
Sanit
ary
Land
fill
No 31 No No
Tractor
Trailer-
01,Tricycle-
10,Trolley
Rickshaw-
01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.89 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.17 Cr
State Assistance/Grant (@25% of PC) 0.72 Cr
Total 2.89 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
101 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PARADEEP MUNICIPALITY, DIST-JAGATSINGHPUR, ORISSA
Population 68,585
Estimated MSW Generation
(TPD)* 20.58 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
94.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation
of waste
Transportatio
n facility
Qty Process
ed
Sanit
ary
Land
fill
Yes 44 No No
Wheel
Barrow-50,
Tipper-01,
Tractor-05,
Mini Truck-
01,
Dallatempo-
01, Dumper-
01,
Cesspool-01,
Jeep-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore) 29.05 Cr. under ICZMP proposed to be implemented on PPP
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
102 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PHULBANI MUNICIPALITY, DIST-PHULBANI, ORISSA
Population 37,371
Estimated MSW Generation
(TPD)* 11.21 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
49.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Process
ed
Sanitar
y
Landfill
No 87 Yes No
Truck-01,
Tractor
Trailer-02
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 5.61 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 4.21 Cr
State Assistance/Grant (@25% of PC) 1.40 Cr
Total 5.61 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
103 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PURI MUNICIPALITY, DIST-PURI, ORISSA
Population 2,00,564
Estimated MSW Generation
(TPD)* 60.17 MT
Landfill Site Authorization
Status
Authorization granted was valid up to 31.03.2013.
Applied for renewalCase filed.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
307.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation
of waste
Transportation
facility
Qty Proces
sed
Sanit
ary
Landfi
ll
No 61 Yes No
Mini Truck-01,
Truck Tipper-
01, Tractor
Trailer-10,
Tricycle-275
30 No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 30.08 Cr.
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 22.56 Cr
State Assistance/Grant (@25% of PC) 7.52 Cr
Total 30.08 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
104 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PADAMPUR NAC, DIST-BARGARH, ORISSA
Population 17,625
Estimated MSW Generation
(TPD)* 5.29 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
29.68
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of
waste
Transportation
facility
Qty Processe
d
Sanitar
y
Landfill
No 21 Yes No
Tractor
Trailer-
02,Tricycle-10
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.64 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.98 Cr
State Assistance/Grant (@25% of PC) 0.66 Cr
Total 2.64 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
105 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PATNAGARH NAC, DIST-BALANGIR, ORISSA
Population 21,024
Estimated MSW Generation
(TPD)* 6.31 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2014. Not applied for renewal
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
38.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportatio
n facility
Qty Processe
d
Sanit
ary
Landfi
ll
Yes 25 Yes No
Tractor
Trailer-02,
Dumper
Placer-
02,Tricycle-
06
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.15 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.36 Cr
State Assistance/Grant (@25% of PC) 0.79 Cr
Total 3.15 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
106 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PATTAMUNDAI NAC, DIST-KENDRAPARA, ORISSA
Population 36,528
Estimated MSW Generation
(TPD)* 10.96 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
37
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation
of waste
Transportatio
n facility
Qty Processed
Sanit
ary
Land
fill
No 15 Yes No
Tractor
Trailer-01,
Wheel
Barrow-20
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 5.48 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 4.11 Cr
State Assistance/Grant (@25% of PC) 1.37 Cr
Total 5.48 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
107 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB PIPILI NAC, DIST-PURI , ORISSA
Population 17,623
Estimated MSW Generation
(TPD)* 5.29 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2014. Renewal not applied
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
27.10
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportati
on facility
Qty Processed
Sanit
ary
Landfi
ll
Yes 55 Yes No Tricycle-15 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.64 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.98 Cr
State Assistance/Grant (@25% of PC) 0.66 Cr
Total 2.64 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
108 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB POLASARA NAC, DIST-GANJAM, ORISSA
Population 23,119
Estimated MSW Generation
(TPD)* 6.94 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
32
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transportatio
n facility
Qty Processed
Sanit
ary
Landfi
ll
No 36 Yes No
Tractor
Trailer-
01,Tricycle-
01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.47 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.60 Cr
State Assistance/Grant (@25% of PC) 0.87 Cr
Total 3.47 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
109 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB RAJGANGPUR MUNICIPALITY, DIST-SUNDERGARH, ORISSA
Population 51,362
Estimated MSW Generation
(TPD)* 15.41 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
66.80
Current Position
Door
to
Door
Colle
ction
Bin
s
Pro
vid
ed
Whether
collection
spots are
attended daily
Segregation
of waste
Transportation
facility
Qty Processed
Sanitary
Landfill
No - Yes No
Tractor Trailer-
02, Tricycle-20,
Wheel Barrow-
100, Auto
Tipper-02
Nil No
Proposed intervention
A. CScope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 7.70 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 5.78 Cr
State Assistance/Grant (@25% of PC) 1.92 Cr
Total 7.70 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
110 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB RAYAGADA MUNICIPALITY, DIST-RAYAGADA, ORISSA
Population 71,208
Estimated MSW Generation
(TPD)* 21.36 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
72.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transporta
tion facility
Qty Processe
d
Sanitar
y
Landfill
Yes 58 Yes No
Tractor
Trailer-
06,Tricycle
-27, Hook
loader
Lorry-01
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 10.68 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 8.01 Cr
State Assistance/Grant (@25% of PC) 2.67 Cr
Total 10.68 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
111 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB ROURKELA MUNICIPAL CORPORATION, DIST-SUNDERGARH, ORISSA
Population 3,10,976
Estimated MSW Generation
(TPD)* 93.29 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
784.40
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Landfi
ll
Yes 282 Yes Yes
Truck Tipper-
05, Tractor
Trailer-04,
Tractor
Attachment-02,
Refuse
collector-02,
Tricycle-65
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 46.65 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 34.99 Cr
State Assistance/Grant (@25% of PC) 11.66 Cr
Total 46.65 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
112 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB RAIRANGAPUR NAC, DIST-MAYURBHANJA, ORISSA
Population 25,516
Estimated MSW Generation
(TPD)* 7.65 MT
Landfill Site Authorization
Status Authorization granted and valid up to 31.03.2018
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
20.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
Yes 168 Yes No
Tractor
Trailer-
02,Tricycle-
20,Auto
Tipper-
03,Wheeel
Barrow-
07,Push Cart-
18
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 3.83 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 2.87 Cr
State Assistance/Grant (@25% of PC) 0.96 Cr
Total 3.83 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
113 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB RAMBHA NAC, DIST-GANJAM, ORISSA
Population 12,111
Estimated MSW Generation
(TPD)* 3.63 MT
Landfill Site Authorization
Status Applied for Authorization and is under process
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
52.60
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
Yes 104 Yes No
Tractor Trailer-01,
Tricycle-04, Wheel
Barrow-10, Trolley-
04
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.82 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.37 Cr
State Assistance/Grant (@25% of PC) 0.45 Cr
Total 1.82 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
114 Act ion Plan fo r SW M in ULBs of Odisha
Name of theULB REDHAKHOL NAC, DIST-SAMBALPUR, ORISSA
Population 15,379
Estimated MSW Generation
(TPD)* 4.61 MT
Landfill Site Authorization
Status Authorization granted was valid up to 31-03-2014. Not applied for renewal.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
40.30
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation of wast
e
Transportation
facility
Qty Proces
sed
Sanit
ary
Land
fill
Yes 15 Yes No
Tractor Trailer-
01, Tractor-
02,Tricycle-09
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.31 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.73 Cr
State Assistance/Grant (@25% of PC) 0.58 Cr
Total 2.31 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
115 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB SUNDERGARH MUNICIPALITY, DIST-SUNDERGARH, ORISSA
Population 45,036
Estimated MSW Generation
(TPD)* 13.51 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2013. Not applied for renewal
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
59.50
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transporta
tion facility
Qty Processed
Sanit
ary
Land
fill
No 30 No No
Tractor
Trailer-02,
Tricycle-02
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 6.76 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 5.07 Cr
State Assistance/Grant (@25% of PC) 1.69 Cr
Total 6.76 Cr
Period of implementation 2016-17
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
116 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB SURUDA NAC, DIST-GANJAM, ORISSA
Population 14,867
Estimated MSW Generation
(TPD)* 4.46 MT
Landfill Site Authorization
Status Not applied.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
19.90
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transp
ortatio
n
facility
Qty Processed
San
itar
y
Lan
dfill
No - - - Tractor
-01 Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 2.23 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.67 Cr
State Assistance/Grant (@25% of PC) 0.56 Cr
Total 2.23 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
117 Act ion Plan fo r SW M in ULBs of Odisha
Name of theULB TALCHER MUNICIPALITY, DIST-ANGUL, ORISSA
Population 40,841
Estimated MSW Generation
(TPD)* 12.25 MT
Landfill Site Authorization
Status Applied for authoriation and is under process.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
61.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots
are attended daily
Segregation of waste
Transportation
facility
Qty Processed
Sanit
ary
Land
fill
No 133 No No
Truck-01,
Auto Tipper-
02, Tractor
Trailer-
04,Tricycle-21
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 6.13 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 4.60 Cr
State Assistance/Grant (@25% of PC) 1.53 Cr
Total 6.13 Cr
Period of implementation 2017-18
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
118 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB TITLAGARH NAC, DIST-BOLANGIR, ORISSA
Population 31,258
Estimated MSW Generation
(TPD)* 9.38 MT
Landfill Site Authorization
Status Authorization granted was valid up to 31-03-2014. Not applied for renewal.
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
34.70
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are
attended daily
Segregation of waste
Transportati
on facility
Qty Processed
Sanitar
y
Landfill
Yes 06 Yes No
Tractor
Trailer-03,
Refuse
Collector-
44,Dumper
Placer-02,
Tricycle-13
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 4.69 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.52 Cr
State Assistance/Grant (@25% of PC) 1.17 Cr
Total 4.69 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
119 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB UDALA NAC, DIST-MAYURBHANJA, ORISSA
Population 13,152
Estimated MSW Generation
(TPD)* 3.95 MT
Landfill Site Authorization
Status Not applied for Authorization
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
21.80
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of
waste
Transportation
facility
Qty Process
ed
Sanit
ary
Land
fill
Yes 40 Yes No
Tractor Trailer-01,
Refuse Collector-
49,Dumper
Placer-01, Wheel
Barrow-08
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Bacterial Composting with Sieve Arrangement (Manual) /Bio
Methanization
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 1.97 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 1.48 Cr
State Assistance/Grant (@25% of PC) 0.49 Cr
Total 1.97 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
120 Act ion Plan fo r SW M in ULBs of Odisha
Name of the ULB UMERKOTE NAC, DIST-NAWRANGPUR, ORISSA
Population 28,993
Estimated MSW Generation
(TPD)* 8.70 MT
Landfill Site Authorization
Status Authorization valid up to 31.03.2013. Applied for renewal
12th Finance Commission
Grant for equipment and
vehicles procurement (Rs. in
Lakhs)
51.20
Current Position
Door
to
Door
Colle
ction
Bins
Provi
ded
Whether collection spots are attended
daily
Segregation of waste
Transportation
facility
Qty Processed
Sa
nit
ary
La
ndf
ill
No 175 Yes No
Tractor-03,Truck
Tipper-
02,Tricycle-12
Nil No
Proposed intervention
A. Scope:
Collection, Transportation, Processing and Disposal
Road Sweeping 100%
Bush Cutting 100%
Drain Cleaning 100%
B. Collection:
Source segregation in phases by FY 2019-20
Door to door collection with Tippers/ Tricycles in phasesby FY 2019-
20
Collection from Community Bins until 100% door to door collection
Segregation of Recyclable materials through networks of rag-pickers
and kabadiwalas
C. Transportation
Transportation from Transfer Station s through Tractors/ Dumper placers
D. Processing:
Mechanical Composting
E. Disposal:
Sanitary Land fill of non bio-degradable and inert material
Estimated Project Cost (PC)
(Rs. in Crore)** 4.35 Cr
Means of finance (Rs. In
Lakhs)
Source Amount Rs. In Crore
Central Assistance/Grant (@75% of PC) 3.26 Cr
State Assistance/Grant (@25% of PC) 1.09 Cr
Total 4.35 Cr
Period of implementation 2018-19
*Based on per capita generation @300 gram per day
**Based on per capita cost of Rs 1500 in accordance with Swach Bharat Mission Programme
121 Act ion Plan fo r SW M in ULBs of Odisha
New NACs recently formed
ULBs Population Estimated waste generation TPD
Project cost (Rs. Cr.)
Central Govt. contribution (Rs. Cr.)
State Govt. Contribution (Rs. Cr.)
Nuapada 16708 5.0 2.5 1.9 0.6
Atabira 16399 4.9 2.5 1.8 0.6
Hindol 17387 5.2 2.6 2.0 0.7
Tusura 10638 3.2 1.6 1.2 0.4
Dharmgarh 16585 5.0 2.5 1.9 0.6
Daspala 18470 5.5 2.8 2.1 0.7
Ranpur 14715 4.4 2.2 1.7 0.6
122 Act ion Plan fo r SW M in ULBs of Odisha
Annexure 4 – Proposed user charges for SWM services by Bhubaneswar Municipal Corporation
Sr. No. Category User charges
Schedule C – Stacking of materials on public street side
Per truck load Rs. 200/- per day
Per tractor/ mini truck load Rs. 100/- per day
Schedule D – Stacking of construction/ demolition
debris materials on public street side
Stacking of construction/ demolition debris Rs. 1500/- per tractor trip
Rs. 3000/- per truck trip
Schedule E – User charge for littering/ dumping etc. of
solid waste management
1 Residential Households
EWS/LIG Rs. 50/- Per Month
MIG Rs. 100/- Per Month
HIG Rs. 200/- Per Month
2 Shops/Shops in Shopping Malls
Up to 200 sft Rs. 100/- Per Month
201 sft to 500 sft Rs. 200/- Per Month
501 sft to 1000 sft Rs. 500/- Per Month
Any extra sft Rs. 5/- Per Sqm Per Month
3 Hat
Shop > 500 sft Rs. 500/- Per Month
Shop (200 sft to 500 sft) Rs. 200/- Per Month
Shop (Up to 200 sft) Rs. 100/- Per Month
4 Road Side Vendors (including vending zone) Rs. 10/- Per Day
5 Godowns& Warehouse
Up to 1000 sft Rs. 100/- Per Month
1000 sft to 5000 sft Rs. 200/- Per Month
More than 5000 sft Rs. 1000/- Per Month
6 Hotels, Restaurants & Open Enclosure
Restaurants & Hotels without accommodation Rs. 10/- Per Sqm Per Month
Hotel & Lodging with accommodation Rs. 5/- Per Sqm Per Month
Other places of public congregation like Marriage Halls, Rs. 8/- Per Sqm Per Month
123 Act ion Plan fo r SW M in ULBs of Odisha
Sr. No. Category User charges
Restaurants, Bars, Convention Centers etc.
7 Dhabas on Highway
Up to 1000 sft Rs. 500/- Per Month
More than 1000 sft Rs. 5/- Per Sqm Per Month
8 Wine Shops Rs. 750/- Per Month
9 Big Fast Food chains like KFC, Dominos, Pizza Huts,
Café Coffee Day etc.
Rs. 5000/- Per Month
10 Educational Institutions
Play Schools Rs. 200/- Per Month
Coaching Center Rs. 500/- Per Month
Non-Residential School & Colleges
Up to 100 Students Rs. 500/- Per Month
From 100-500 Students Rs. 1000/- Per Month
More than 500 Students Rs. 3000/- Per Month
Residential School & colleges
Up to 100 Students Rs. 1000/- Per Month
From 100-500 Students Rs. 3000/- Per Month
More than 500 Students Rs. 5000/- Per Month
11 Health Care Unit
Medical Laboratory/Diagnostic Centers/Pathological
Centers/Doctors Clinic(Without beds)
Rs. 1000/- Per Month
Hospitals/Nursing Homes(With beds) Rs. 5/- Per Sqm Per Month
12 Cinema Halls & Multiplex Rs. 5/- Per Sqm Per Month
13 Beauty Parlour, Saloon & Spa
Beauty Parlour, Saloon Rs. 500/- Per Month
Spa Rs. 5/- Per Sqm Per Month
14 Showrooms, Service Centers & Garages
Small Garages Rs. 500/- Per Month
Service Centers Rs. 10/- Per Sqm Per Month
Showrooms Rs. 5/- Per Sqm Per Month
15 KalyanMandaps/Marriage Hall Rs. 10/- Per Sqm Per Month
16 Exhibition Grounds Rs. 5/- Per Sqm Per Month
17 Hostel & Paying Guest Hostels Rs. 5/- Per Sqm Per Month
18 Industries
124 Act ion Plan fo r SW M in ULBs of Odisha
Sr. No. Category User charges
Small Industry up to 1000 sft Rs. 3000/- Per Month
Industries >1000 sft Rs. 3/- Per Sqm Per Month
19 Printing Press
Up to 500 sft Rs. 300/- Per Month
More than 500 sft Rs. 3/- Per Sqm Per Month
20 Govt. &Pvt Offices
Up to 1000 sft Rs. 200/- Per Month
More than 1000 sft Rs. 2/- Per Sqm Per Month
21 Petrol Pump
Up to 500 sft Rs. 200/- Per Month
More than 500 sft Rs. 5/- Per Sqm Per Month
Schedule F – Slum houses listed under RAY Rs. 50/- month
125 Act ion Plan fo r SW M in ULBs of Odisha
Annexure 5 - Concept Note on State Urban Sanitation Strategy for the State of Odisha
PARTA: Parameters determining the existing urban sanitation situation
1 State Profile
1.1 Name of the state Odisha
1.2 Total Urban Population as per 2011Census 7003656
1.3 NumberofStatutorytowns1asperCensus2011 107
1.4 NumberofCensustowns2asperCensus2011 114
1.5 Population of statutory towns (as per
Census2011)
5969842
1.6 Population of census towns (as per Census2011) 1033814
1.7 Total number of urban households 1517073
2
StatusofSanitationSituationasperCensus2011[FORSTATUTORYTOWNSONLY]
Totalnos.as perAnnexure1 (State)*
2.1 Number of urban households resorting to open defecation(not in premises–open)
409398
2.2 Number of urban households having pit latrines 55453
2.3 Number of urban households having insanitary latrines 24810
3
Solid waste management(tentative quantity based on per capita waste generation)[FORSTATUTORYTOWNSONLY] Total(State)*
3.1 Total Solid waste generated(in MT) 1,791
3.2 Total Waste collected(in MT) 1,254
3.3 Total Waste Transported(in MT) 1,191
3.4 No. of cities with SWM Disposal Facility -
3.5 Total Waste treated(in MT) -
*City-wise information may also be added wherever available.
126 Act ion Plan fo r SW M in ULBs of Odisha
Part B : Institutional Mechanism for Swachh Bharat Mission (SBM) - Urban
Provide Details
Name of the Nodal Agency for SBM
[Provide name of Nodal Agency; elseifnotdesignated,providedetailsofprocessbywhichnodalagencywillbeappointed]
Name and Designation of Nodal Officer with contact no.
[Provide name of Nodal Officer; else if not designated, provide details of process by which nodal officer will be appointed]
Institutional Mechanism Start date (Month / Year)
End date(Month/ Year)
a. Constitution of the State‐level High Powered Committee(S‐ HPC)
[Provide details of S‐ HPC; else if not constituted, provide details of process by which S‐ HPC will be constituted; timeline should be max. within 1 month of submission of concept note]
b. Setting up of State Mission Directorate
[Provide details of Mission Directorate; Else if not constituted, provide details of process by which Mission Directorate will Be constituted; timeline should be max.within1 month of submission of concept note]
c. Setting up of PMU at the state‐level under SBM
[Provide details of PMU set‐up; else if not set‐up, provide details of process by which PMU will be put in place; timeline should be max. within 3 months of submission of concept note]
Submission of State Sanitation Strategy as per the National Urban Sanitation Policy, 2008 (please refer Ministry’s website www.moud.gov.in)
Start date (Month / Year)
Date of submission(Month/ Year)
127 Act ion Plan fo r SW M in ULBs of Odisha
Part C :Component wise action plan for Swachh Bharat Mission (SBM) - Urban
PhysicalTargets
1
Targets
Baseline 2014
Cumulative Estimated Projection upto2019
Target 2014-15
Target 2015-16
Target 2016-17
Target 2017-18
Target 2018-19
(up toOct, 2019)
Cumulative Target
(2014‐19) Remark
A*
a
Construction of new individual household latrines(IHL)
327518 327518 98255
(30%)
163759
(50%)
65504
(20%)
327518
b
Conversion of pit latrines into sanitary latrines
55453 33272 1664
(5%)
9982
(30%)
16636
(50%)
4991
(15%)
33273 Projected estimate is 60% of baseline
c
Conversion of insanitary latrines into sanitary latrines
24810 24810 1241
(5%)
7443
(30%)
12405
(50%)
3721
(15%)
24810
B* Construction of Community toilets[NORM: 1 seat/25 womenand1 seat/35men]
368458 12558 251
(2%)
3767
(30%)
6279
(50%)
2260
(18%) 12557
1. The figures indicate the
number of toilet seats
2. As per census data
a. HH size = 4.5
b. Sex ratio is 51.7:48.3
C* Construction of Public Toilets [NORM:1seat /50women and1 seat/ 100menup to specified numbers**]
7003656 5191 105
(2%)
519
(10%)
1557
(30%)
2076
(40%)
934
(18%) 5191
D Solid waste Management
107 104 21
(20%)
31
(30%)
42
(40%)
10
(10%)
104
Ongoing projects in 3 cities
E Capacity Building 107 107 107 107 107 107 107 107 Concurrent implementation in all cities
F Public Awareness & IEC
107 107 107 107 107 107 107 107 Concurrent implementation in all cities *Efforts shall be made to construct the toilets within two years i.e.upto2016-17.
**Please also refer Manual on Sewerage & Sewerage Systems, Part A form for details
128 Act ion Plan fo r SW M in ULBs of Odisha
Financial Targets
(RsinCrores) 2 Funding[Asper the funding pattern in the
SBM Urban Guidelines] 2014‐
2019(TOTAL) 2014‐15 2015‐16 2016‐17 2017‐18 2018‐
19(uptoOct.’19) Tentative/ estimate
Central Share
Tentative/ estimated
Central Share
Tentative/ estimated
Central Share
Tentative/ estimated
Central Share
Tentative/ estimated
Central Share
Tentative/ estimated
Central Share
A
a. Construction of new individual household latrines (IHL) (Based on the cost per Household toilet) 982.55 131.01 - - 294.77 39.30 491.28 65.50 196.51
26.20 - -
b. Conversion of pit latrines into sanitary latrines(based on thecost per household toilets)
66.55 13.31 3.33 0.67 19.96 3.99 33.27 6.65 9.98
2.00
- -
c. Conversion of insanitary latrines into sanitary latrines(based on the cost per household toilets)
37.22 9.92 1.86 0.50 11.16 2.98 18.61 4.96 5.58 1.49 - -
B Construction of Community toilets [NORM:1seat /25 women and1seat/35 men] (based on cost per seat)
81.62 61.22 1.63 1.22
24.49
18.36 40.81 30.61 14.69 11.02 - -
C Construction of Public Toilets[NORM:1seat/50womenand1seat/100 men upto specified numbers] (Based on cost per seat)
38.93 - 0.79 - 3.89 - 11.68 - 15.57 - 7.01 -
D Solid Waste Management (based on per capita cost ofRs.1500/ capita may be considered lessor more with proper justification in a separate sheet)
624.33 468.25 - - 126.07 94.55 186.10 139.57 252.13 189.10 60.03 45.02
E Capacity Building & A&OE (5%on Central share)
27.35 20.51 0.10 0.07 6.37 4.78 9.89 7.42 9.19 6.89 1.80 1.35
F Public Awareness & IEC (15% on Central share)
109.39 82.04 0.38 0.29 25.47 19.10 39.57 29.68 36.77 27.58 7.20 5.40
Total 1,967.94 786.26 8.09 2.74 512.18 183.06 831.21 284.40 540.43 264.28 76.04 51.78
Status of access to toilet in 107 Statutory Towns of Odisha (2011 Census)
Area Name
Total
number
of
househo
ld
Pit latrine Insanitary latrine
With
slab/
ventilate
d
improved
pit
Without
slab/
open pit
Night soil
disposed
into open
drain
Night
soil
removed
by
human
Night
soil
service
d by
animal
Open
Defecati
on
1 2 3 4 5 6 7 8
Padmapur
(NAC)
3,797
79
15
17
-
-
1,684
Barapali
(NAC)
4,734
343
82
12
-
7
2,460
Bargarh (M)
17,985
347
40
153
146
168
6,322
Belpahar (M)
8,667
125
70
25
-
3
4,313
Brajarajnagar
(M)
17,536
324
23
236
45
6
8,031
Jharsuguda
(M)
21,424
173
35
91
16
34
9,831
Kochinda
(NAC)
3,950
93
48
6
-
17
2,134
Hirakud
(NAC)
7,067
150
12
236
-
48
3,043
Burla (NAC)
10,367
122
37
54
11
28
4,430
Redhakhol
(NAC)
3,705
110
34
4
-
-
2,442
Sambalpur
(M + OG)
42,292
470
218
283
47
73
12,794
Debagarh (M)
5,431
280
32
12
-
10
2,454
Sundargarh
(M)
9,979
311
19
19
-
-
2,769
Rajagangapu
r (M)
10,830
86
90
39
-
11
3,444
Biramitrapur
(M)
7,115
34
14
18
-
4
4,148
Raurkela (M
+ OG)
70,810
613
399
330
200
606
19,286
Raurkela
(ITS + OG)
47,010
885
250
337
249
170
14,816
Barbil (M)
15,465
103
13
26
-
105
8,493
Balagoda
(Bolani) (CT)
2,704
52
-
4
-
-
1,229
130 Act ion Plan fo r SW M in ULBs of Odisha
Area Name
Total
number
of
househo
ld
Pit latrine Insanitary latrine
With
slab/
ventilate
d
improved
pit
Without
slab/
open pit
Night soil
disposed
into open
drain
Night
soil
removed
by
human
Night
soil
service
d by
animal
Open
Defecati
on
Joda (M )
10,742
536
58
19
42
22
5,819
Kendujhar
(M)
13,316
390
105
25
87
142
4,086
Anandpur (M)
8,518
404
255
18
186
3
4,741
Rairangpur
(NAC + OG)
7,580
128
28
7
-
15
4,223
Karanjia
(NAC)
5,055
145
35
5
-
12
2,286
Udala (NAC)
3,014
327
188
4
27
-
751
Baripada (M
+ OG)
25,990
2,072
445
34
158
16
6,793
Jaleshwar
(NAC)
5,548
653
331
34
-
2
2,201
Remuna
(NAC)
7,568
766
435
40
192
29
3,667
Nilagiri (NAC)
3,908
293
35
23
29
3
2,467
Soro (NAC)
6,747
399
763
8
57
2
3,147
Baleshwar (M
+ OG)
32,124
1,576
722
178
133
50
5,522
Dhamanagar
(NAC)
4,182
63
92
3
-
5
3,077
Bhadrak (M +
OG)
23,098
846
620
166
615
59
8,258
Basudebpur
(NAC)
6,581
241
445
142
51
18
4,429
Pattamundai
(NAC)
7,276
161
85
8
26
-
4,303
Kendrapara
(M)
8,664
252
58
22
43
13
2,160
Paradip (M)
18,235
58
87
127
49
14
9,275
Jagatsinghap
ur (M)
6,516
250
25
5
-
17
2,509
Banki (NAC)
3,595
139
16
1
-
1
1,969
Athagad
(NAC)
3,119
121
23
4
10
1
1,257
131 Act ion Plan fo r SW M in ULBs of Odisha
Area Name
Total
number
of
househo
ld
Pit latrine Insanitary latrine
With
slab/
ventilate
d
improved
pit
Without
slab/
open pit
Night soil
disposed
into open
drain
Night
soil
removed
by
human
Night
soil
service
d by
animal
Open
Defecati
on
Choudwar (M
+ OG)
11,018
313
96
276
105
9
4,697
Cuttack (MC)
116,820
2,724
349
842
653
763
13,390
Byasanagar
(M + OG)
12,546
511
44
12
147
56
4,241
Jajapur (M)
8,177
294
229
11
50
4
2,037
Kamakshyan
agar (NAC)
3,915
390
38
2
-
-
1,839
Bhuban
(NAC)
4,822
103
92
2
124
4
3,108
Dhenkanal
(M)
14,353
719
81
4
172
255
3,396
Talcher (M)
9,054
84
17
17
-
3
3,492
Anugul (M)
8,674
356
69
12
11
55
1,781
Athmallik
(NAC)
2,895
135
50
1
13
1
1,918
Khandapada
(NAC)
1,882
95
101
28
-
-
897
Nayagarh
(NAC)
4,056
166
40
9
-
7
744
Khordha (M)
8,950
181
50
24
-
49
2,705
Jatani (M +
OG)
13,531
177
98
96
31
5
3,661
Balugaon
(NAC)
3,719
24
13
2
35
11
1,542
Banapur
(NAC)
3,397
63
37
8
-
3
1,654
Bhubaneswar
(MC + OG)
201,873
9,110
2,278
2,176
1,621
716
34,808
Pipili (NAC)
3,570
294
123
5
-
10
1,497
Nimapada
(NAC)
3,907
127
46
3
-
3
1,291
Konark
(NAC)
3,298
64
7
3
27
10
2,483
Puri (M)
39,607
2,231
472
275
122
71
5,996
132 Act ion Plan fo r SW M in ULBs of Odisha
Area Name
Total
number
of
househo
ld
Pit latrine Insanitary latrine
With
slab/
ventilate
d
improved
pit
Without
slab/
open pit
Night soil
disposed
into open
drain
Night
soil
removed
by
human
Night
soil
service
d by
animal
Open
Defecati
on
Buguda
(NAC)
3,180
39
35
7
-
-
1,466
Bhanjanagar
(NAC)
4,719
194
65
126
11
44
1,301
Bellaguntha
(NAC)
2,415
144
27
9
-
-
1,197
Surada
(NAC)
3,160
59
52
6
-
1
1,560
Asika (NAC)
4,547
109
19
11
65
1
1,423
Kabisurjyana
gar (NAC)
3,548
118
71
1
-
-
1,591
Polasara
(NAC)
4,853
109
50
13
23
27
2,535
Kodala (NAC)
2,835
45
27
15
-
1
2,055
Khalikote
(NAC)
2,774
97
20
25
-
2
1,529
Rambha
(NAC)
2,434
110
29
7
12
-
1,688
Chhatrapur
(NAC)
4,875
34
32
10
33
77
709
Ganjam
(NAC)
2,541
53
12
5
-
8
1,247
Purusottamp
ur (NAC)
3,246
205
24
27
47
65
1,621
Hinjilicut
(NAC)
5,155
260
104
26
-
66
2,303
Gopalpur
(NAC)
1,441
130
22
229
-
1
740
Digapahandi
(NAC)
2,931
66
34
4
-
-
1,189
Chikiti (NAC)
2,446
203
13
35
-
-
1,103
Brahmapur
(MC)
67,397
1,135
392
4,231
129
333
7,861
Kashinagar
(NAC)
2,523
20
14
2
-
4
1,891
Paralakhemu
ndi (M + OG)
10,390
533
96
17
17
9
2,940
Phulabani
(M)
8,629
403
173
27
29
6
2,955
133 Act ion Plan fo r SW M in ULBs of Odisha
Area Name
Total
number
of
househo
ld
Pit latrine Insanitary latrine
With
slab/
ventilate
d
improved
pit
Without
slab/
open pit
Night soil
disposed
into open
drain
Night
soil
removed
by
human
Night
soil
service
d by
animal
Open
Defecati
on
G. Udayagiri
(NAC)
2,676
145
126
1
-
-
1,259
Baudhgarh
(NAC)
4,488
107
38
38
72
114
2,044
Binika (NAC)
3,800
19
1
3
-
1
2,918
Sonapur (M)
4,751
68
34
7
-
37
1,977
Tarbha
(NAC)
1,949
15
2
5
-
53
1,065
Balangir (M)
22,164
488
250
91
63
157
7,046
Patnagarh
(NAC)
5,238
84
49
13
-
24
2,440
Kantabanji
(NAC)
4,924
31
41
24
-
7
2,205
Titlagarh
(NAC + OG)
8,246
112
73
7
48
88
3,542
Khariar Road
(NAC)
4,423
3
6
10
-
69
2,517
Khariar
(NAC)
3,603
52
25
3
-
1
1,579
Kesinga
(NAC)
4,248
73
69
4
49
11
2,503
Bhawanipatn
a (M)
15,364
1,493
438
195
197
255
4,720
Junagarh
(NAC)
4,631
280
176
39
15
12
2,640
Rayagada
(M)
16,244
136
33
22
-
157
4,999
Gunupur
(NAC + OG)
6,592
154
96
19
-
81
2,872
Gudari (NAC)
1,728
22
139
15
53
3
853
Umarkote
(NAC)
6,550
255
258
17
29
25
2,866
Nabarangapu
r (M + OG)
8,738
115
60
51
-
89
3,456
Kotpad
(NAC)
3,878
17
27
4
-
3
1,890
Koraput
(NAC)
11,332
220
26
312
45
3
4,388
134 Act ion Plan fo r SW M in ULBs of Odisha
Area Name
Total
number
of
househo
ld
Pit latrine Insanitary latrine
With
slab/
ventilate
d
improved
pit
Without
slab/
open pit
Night soil
disposed
into open
drain
Night
soil
removed
by
human
Night
soil
service
d by
animal
Open
Defecati
on
Jeypur (M)
19,880
581
58
31
44
239
5,529
Sunabeda
(NAC).
12,383
46
5
17
-
107
4,025
Malkangiri
(NAC)
6,944
169
58
9
-
6
3,534
Balimela
(NAC)
2,767
4
6
8
-
2
1,387
Total 1335888 41436 14017 12361 6511 5938 409398