report ports of auckland - protecting our way of …...report ports of auckland assessment of...

230
REPORT Ports of Auckland Assessment of Sediment Quality and Biosecurity for Dumping of Dredged Sediment from the Port of Auckland at the Cuvier Dump Site Submitted to: Ports of Auckland Limited PO Box 1281, Auckland 1140 Submitted by: Golder Associates (NZ) Limited PO Box 33-849, Takapuna 0740, Auckland +64 9 486 8068 1779496-002-R-Rev0 November 2018 Part 1 of 4 Report Appendices A to C

Upload: others

Post on 29-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

  • REPORT

    Ports of Auckland Assessment of Sediment Quality and Biosecurity for Dumping of Dredged

    Sediment from the Port of Auckland at the Cuvier Dump Site

    Submitted to:

    Ports of Auckland Limited PO Box 1281, Auckland 1140

    Submitted by:

    Golder Associates (NZ) Limited

    PO Box 33-849, Takapuna 0740, Auckland

    +64 9 486 8068

    1779496-002-R-Rev0

    November 2018

    Part 1 of 4

    Report

    Appendices A to C

  • November 2018 1779496-002-R-Rev0

    Record of Issue

    Company Client Contact Version Date Issued Review

    Status/Comments

    Ports of Auckland

    Limited

    Nigel Ironside RevA 15 November 2018 Draft

    Ports of Auckland

    Limited

    Nigel Ironside Rev0 23 November 2018 Final

  • November 2018 1779496-002-R-Rev0

    Record of Issue

    Company Client Contact Version Date Issued Review

    Status/Comments

    Ports of Auckland

    Limited

    Nigel Ironside RevA 15 November 2018 Draft

    Ports of Auckland

    Limited

    Nigel Ironside Rev0 23 November 2018 Final

  • November 2018 1779496-002-R-Rev0

    i

    Table of Contents

    NO TABLE OF CONTENTS ENTRIES FOUND.

    TABLES

    No table of figures entries found.

    FIGURES

    No table of figures entries found.

    APPENDICES

    APPENDIX A Previous disposal Permits Granted for the Cuvier Disposal Site

    APPENDIX B Bio-security Assessment

    APPENDIX C Ministry of Primary Industries Bio-security Communications to Stakeholders

    APPENDIX D Sediment Quality in the Port of Auckland

    APPENDIX E Review of Alternatives to Disposal at Sea

    APPENDIX F MacDiarmid et al. (2017) Review of Environmental Information within the Exclusive Economic Zone Near the Cuvier Disposal site

    APPENDIX G Near-field Sediment Modelling Using STFATE (Beca 2018a)

    APPENDIX H Far-field sediment modelling using Regional Ocean Modelling System (Macdonald & Rickard 2018)

    APPENDIX I Dredging Management Plan (Beca 2018b)

    APPENDIX J Disposal Management Plan (Beca 2018c)

    APPENDIX K Limitations

  • November 2018 1779496-002-R-Rev0

    ii

    Abbreviations and Units

    oC Degrees Celsius

    µg Microgram

    AC Auckland Council

    ADCP Acoustic doppler current profiler

    AHB Auckland Harbour Board

    ANZECC Australian and New Zealand Environment and Conservation Council

    ARC Auckland Regional Council

    ARWB Auckland Regional Water Board

    BCF Bio-concentration factor

    BOMEC Broad benthic optimised marine environment classification

    BSAF Bio-accumulation to sediment accumulation factor

    bsl Below sea level

    BT Bio-accumulation trigger

    BWE Bledisloe Wharf east

    BWW Bledisloe Wharf west

    CCC Criterion continuous concentration

    CCREM Canadian Council of Resource and Environment Ministers

    CD Chart datum

    CDS Cuvier Disposal site

    CMA Coastal Marine Area

    CTD Conductivity, temperature and density

    d Day

    DDT Dichlorodiphenyltrichloroethane

    DGV Default guideline values for sediment quality (ANZECC 2018)

    DiMP Disposal Management Plan

    DMMO Dredged Material Management Office

    DMMU Dredging material management unit

    DMP Dredging Management Plan

    DOAG Disposal Options Advisory Group

  • November 2018 1779496-002-R-Rev0

    iii

    DoC Department of Conservation

    dw Dry weight

    EAUC East Auckland Current

    EEZ Exclusive Economic Zone

    EIA Environmental Impact Assessment

    EMP S Environmental Management Plan: Stormwater

    EPA Environmental Protection Authority

    ER-L Effects range low

    ER-M Effects range median

    ERDC U.S. Army Engineer Research and Development Center

    FWE Freyberg Wharf east

    FWW Freyberg Wharf west

    FTU Formazin turbidity unit

    g Gram

    gamma-BHC Gamma-hexachlorocyclohexane

    Golder Golder Associates (NZ) Limited

    GV-high Upper guideline values for sediment quality (ANZECC 2018)

    ha Hectare

    hr Hour

    Hs Wave height (significant)

    JWE Jellicoe Wharf east

    JWW Jellicoe Wharf west

    kg Kilogram

    km Kilometre

    km2 Square kilometre

    kn knot, nautical mile per hour

    Kow Octanol-water partition coefficient

    L Litre

    m Metre

    M million

    m2 Square metre

  • November 2018 1779496-002-R-Rev0

    iv

    m3 Cubic metre

    MD Maintenance dredging

    MHRSS Marine High-Risk Site Surveillance

    mg milligram

    mg Sn/m3 milligrams (expressed as tin) per cubic metre (of water)

    mm millimetre

    MoT Ministry of Transport

    MPI Ministry of Primary Industries

    MSA Maritime Safety Authority (New Zealand)

    NABIS National Aquatic Biodiversity Information System

    NDA Northern Disposal Area

    ng nanogram

    NHMRC National Health Medical Research Council

    NIS Non-indigenous species

    NIWA National Institute of Water and Atmospheric Research

    NP Navigation Precinct

    NRDS North Rangitoto Disposal site

    NTU Nephelometric turbidity unit

    OCP Organochlorine pesticides

    PAH Polyaromatic hydrocarbon

    Panuku Panuku Developments Auckland

    PCB Polychlorinated biphenyl

    POAL Ports of Auckland Limited

    POP Persistent organic compound

    PSU Practical salinity unit

    PWE princes Wharf east

    PWW Princes Wharf west

    QWE Queens Wharf east

    QWW Queens Wharf west

    ROMS Regional Ocean Modelling System

    s Second

  • November 2018 1779496-002-R-Rev0

    v

    Sn Tin

    SOP Standard operating procedure

    STFATE Short-term FATE

    t Ton

    TBT Tributyltin

    TEU Twenty-foot equivalent

    TN Total nitrogen

    TNC Threatened, nationally critical

    TOC Total organic carbon

    TPH Total petroleum hydrocarbons

    TSS Total suspended solids

    µg/kg milligrams per kilogram (sediment)

    µg Sn/kg micrograms (expressed as tin) per kilogram

    USEPA United States Environmental Protection Agency

    WWE Wynyard Wharf east

    y Year

    yd3 Cubic yard

  • November 2018 1779496-002-R-Rev0

    6

  • November 2018 1779496-002-R-Rev0

    7

    Signature Page

    Golder Associates (NZ) Limited

    Golder and the G logo are trademarks of Golder Associates Corporation

    \\akl2-v-file02\akl-dun-files\projects-dynamics\2017\7410\1779496_poal_longterm_disposal_permit\deliverables\002-r_aee\rev0\parts\1779496-002-r-rev0-poal dredged material

    disposal_eia part headers only.docx

  • November 2018 1779496-002-R-Rev0

    APPENDIX A

    Previous disposal Permits Granted for

    the Cuvier Disposal Site

  • November 2018 1779496-002-R-Rev0

    APPENDIX B

    Bio-security Assessment

  • November 2018 1779496-002-R-Rev0

    APPENDIX C

    Ministry of Primary Industries Bio-security

    Communications to Stakeholders

  • November 2018 1779496-002-R-Rev0

    APPENDIX D

    Sediment Quality in the Port of Auckland

  • November 2018 1779496-002-R-Rev0

    APPENDIX E

    Review of Alternatives to Disposal at Sea

  • November 2018 1779496-002-R-Rev0

    APPENDIX F

    MacDiarmid et al. (2017) Review of Environmental

    Information within the Exclusive Economic Zone

    Near the Cuvier Disposal site

  • November 2018 1779496-002-R-Rev0

    APPENDIX G

    Near-field Sediment Modelling Using STFATE

    (Beca 2018a)

  • November 2018 1779496-002-R-Rev0

    APPENDIX H

    Far-field sediment modelling

    using Regional Ocean Modelling

    System (Macdonald & Rickard

    2018)

  • November 2018 1779496-002-R-Rev0

    APPENDIX I

    Dredging Management Plan (Beca 2018b)

  • November 2018 1779496-002-R-Rev0

    APPENDIX J

    Disposal Management Plan (Beca 2018c)

  • November 2018 1779496-002-R-Rev0

    APPENDIX K

    Limitations

  • November 2018 1779496-002-R-Rev0

  • golder.com

  • November 2018 1779496-002-R-Rev0

    i

    Table of Contents

    1.0 INTRODUCTION ......................................................................................................................................... 1

    1.1 Purpose ............................................................................................................................................. 1

    1.2 Dredging in the Port of Auckland ...................................................................................................... 1

    1.3 Dredging Areas Covered by this Assessment .................................................................................. 3

    1.4 Assessment Contents ....................................................................................................................... 4

    2.0 DREDGED MATERIAL DUMPING REGULATIONS ................................................................................. 5

    2.1 Overview ........................................................................................................................................... 5

    2.2 Exclusive Economic Zone and Continental Shelf (Environmental Effects – Discharge and

    Dumping) Regulations 2015 .............................................................................................................. 5

    2.3 Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012 ....................... 6

    2.4 Dumping Location ............................................................................................................................. 7

    2.5 Past Disposal at the CDS .................................................................................................................. 8

    3.0 PORTS OF AUCKLAND FACILITIES, ACTIVITIES AND DREDGING ..................................................... 9

    3.1 The Port of Auckland ......................................................................................................................... 9

    3.2 Port Wharfs and Facilities ............................................................................................................... 10

    3.3 Stormwater ...................................................................................................................................... 11

    3.4 Port Dredging .................................................................................................................................. 14

    3.4.1 Introduction ................................................................................................................................. 14

    3.4.2 Maintenance dredging ................................................................................................................ 14

    3.4.3 Capital dredging .......................................................................................................................... 15

    4.0 PORT BIOSECURITY OVERVIEW .......................................................................................................... 15

    4.1 Introduction ...................................................................................................................................... 15

    4.2 Port Biosecurity Surveys ................................................................................................................. 15

    4.3 Target Pest Species Identified in the Port ....................................................................................... 17

    4.4 Non-indigenous Biota ...................................................................................................................... 17

    4.5 Biosecurity Summary ...................................................................................................................... 18

    5.0 PORT OF AUCKLAND SEDIMENT QUALITY ........................................................................................ 18

    5.1 Introduction ...................................................................................................................................... 18

    5.2 Assessment Framework .................................................................................................................. 18

  • November 2018 1779496-002-R-Rev0

    ii

    5.2.1 Overview of the assessment framework ..................................................................................... 18

    5.2.2 Level 1 assessment .................................................................................................................... 19

    5.2.3 Levels 2, 3 and 4 assessments ................................................................................................... 20

    5.3 Dredged Material Sampling in the Port (Maintenance Dredging) ................................................... 20

    5.3.1 Sampling methods ...................................................................................................................... 20

    5.3.2 Sample locations ......................................................................................................................... 21

    5.3.3 Sampling sites ............................................................................................................................. 21

    5.3.4 Sampling and sub-sampling of cores .......................................................................................... 23

    5.3.5 Number of samples collected ...................................................................................................... 23

    5.3.6 Recency ...................................................................................................................................... 24

    5.4 Port Maintenance Dredging Sediment Characteristics ................................................................... 25

    5.4.1 Sediment characterisation .......................................................................................................... 25

    5.4.2 Physical characteristics ............................................................................................................... 25

    5.4.2.1 Sediment textures ....................................................................................................................... 25

    5.4.2.2 Sediment colour .......................................................................................................................... 26

    5.4.2.3 Man-made debris ........................................................................................................................ 26

    5.4.3 Organic carbon ............................................................................................................................ 26

    5.4.4 Nitrogen and phosphorus ............................................................................................................ 27

    5.4.5 Trace elements ........................................................................................................................... 27

    5.4.6 Total petroleum hydrocarbons .................................................................................................... 29

    5.4.7 Polyaromatic hydrocarbons ........................................................................................................ 29

    5.4.8 Polychlorinated biphenyls ........................................................................................................... 29

    5.4.9 Organochlorine compounds ........................................................................................................ 29

    5.4.10 Antifoulants ................................................................................................................................. 30

    5.4.11 Other organic compounds ........................................................................................................... 31

    5.4.12 Elutriate testing ........................................................................................................................... 32

    5.4.13 Maintenance dredging sediment quality summary ..................................................................... 35

    5.5 Navigation Precinct Maintenance Dredging Characteristics ........................................................... 35

    5.5.1 Introduction ................................................................................................................................. 35

    5.5.2 Physical characteristics ............................................................................................................... 35

    5.5.3 Trace elements ........................................................................................................................... 36

  • November 2018 1779496-002-R-Rev0

    iii

    5.5.4 Organic compounds .................................................................................................................... 36

    5.5.5 Antifoulants ................................................................................................................................. 36

    5.5.6 Future sampling for channel maintenance dredging ................................................................... 36

    5.5.7 Summary ..................................................................................................................................... 36

    5.6 Capital Dredging Characteristics..................................................................................................... 37

    5.6.1 Introduction ................................................................................................................................. 37

    5.6.2 Navigation Channel deepening ................................................................................................... 37

    5.6.3 Berth deepening .......................................................................................................................... 37

    5.6.4 Summary ..................................................................................................................................... 37

    6.0 ALTERNATIVES TO MARINE DUMPING................................................................................................ 38

    6.1 Introduction ...................................................................................................................................... 38

    6.2 Harbour Edge Disposal ................................................................................................................... 38

    6.3 Land Disposal.................................................................................................................................. 39

    6.4 Marine Dumping .............................................................................................................................. 39

    6.5 Overview ......................................................................................................................................... 39

    7.0 DUMPING SITE ......................................................................................................................................... 40

    7.1 Introduction ...................................................................................................................................... 40

    7.2 Site Physical Environments ............................................................................................................. 40

    7.2.1 Bathymetry and seabed topography ........................................................................................... 40

    7.2.2 Sediments ................................................................................................................................... 41

    7.2.3 Sediment geology and mineralogy .............................................................................................. 43

    7.2.4 Summary ..................................................................................................................................... 43

    7.3 Site Oceanography ......................................................................................................................... 43

    7.3.1 Waves ......................................................................................................................................... 43

    7.3.2 Currents ...................................................................................................................................... 45

    7.3.3 Summary ..................................................................................................................................... 48

    7.4 Water Quality Characteristics .......................................................................................................... 48

    7.4.1 Introduction ................................................................................................................................. 48

    7.4.2 Temperature and salinity ............................................................................................................ 49

    7.4.3 Water clarity and suspended sediment ....................................................................................... 51

    7.4.4 Sediment deposition.................................................................................................................... 52

  • November 2018 1779496-002-R-Rev0

    iv

    7.4.5 Trace elements ........................................................................................................................... 53

    7.5 Site and Wider Environment Sediment Quality ............................................................................... 53

    7.5.1 Introduction ................................................................................................................................. 53

    7.5.2 Organic carbon and nitrogen ...................................................................................................... 54

    7.5.3 Trace elements ........................................................................................................................... 54

    7.6 Site Ecological Environment ........................................................................................................... 56

    7.6.1 Habitat ......................................................................................................................................... 56

    7.6.2 Vulnerable ecosystems ............................................................................................................... 57

    7.6.3 Local knowledge of vulnerable ecosystems ............................................................................... 58

    7.6.4 Benthic ecology ........................................................................................................................... 59

    7.6.5 Fish and fisheries ........................................................................................................................ 61

    7.6.6 Crayfish ....................................................................................................................................... 66

    7.6.7 Seabirds ...................................................................................................................................... 66

    7.6.8 Marine mammals ......................................................................................................................... 69

    7.6.9 Areas of conservation significance ............................................................................................. 70

    7.6.10 Summary ..................................................................................................................................... 70

    8.0 ENVIRONMENTAL EFFECTS OF DUMPING ......................................................................................... 71

    8.1 Introduction ...................................................................................................................................... 71

    8.2 Dumping Volumes ........................................................................................................................... 71

    8.2.1 Maintenance dredging ................................................................................................................ 71

    8.2.2 Capital dredging .......................................................................................................................... 72

    8.2.3 Disposal summary ....................................................................................................................... 72

    8.3 Method of Dredged Material Disposal ............................................................................................. 73

    8.4 Sediment Fate Modelling ................................................................................................................ 73

    8.4.1 Short-term modelling immediately following dumping ................................................................ 73

    8.4.2 Longer-term fate following dumping............................................................................................ 74

    8.5 Effects on Water Quality ................................................................................................................. 75

    8.5.1 Short-term near-field physical changes modelled using STFATE .............................................. 75

    8.5.2 Short-term near-field physical changes during disposal observed at the NDA .......................... 77

    8.5.3 Water quality changes adjacent to the descending plume at CDS ............................................. 78

    8.6 Longer-term Far-field Water Quality Effects (Total Suspended Solids) .......................................... 80

  • November 2018 1779496-002-R-Rev0

    v

    8.6.1 Introduction ................................................................................................................................. 80

    8.6.2 TSS during maintenance dredging material disposal ................................................................. 80

    8.6.3 TSS during capital dredging disposal ......................................................................................... 82

    8.6.4 Cumulative effects....................................................................................................................... 83

    8.6.5 Summary of disposal effects on TSS concentrations ................................................................. 85

    8.7 Effects of Suspended Solids on Ecological Resources .................................................................. 85

    8.7.1 Types of effects ........................................................................................................................... 85

    8.7.2 Effects on phytoplankton ............................................................................................................. 85

    8.7.3 Effects on fish .............................................................................................................................. 86

    8.7.4 Effects on Crayfish ...................................................................................................................... 87

    8.7.5 Effects on filter feeding and other benthic biota .......................................................................... 87

    8.7.6 Plume TSS and observable effects data .................................................................................... 88

    8.8 Effects on Sedimentation ................................................................................................................ 88

    8.8.1 Within the CDS as modelled using STFATE .............................................................................. 88

    8.8.2 Within and outside the CDS as modelled using ROMS for maintenance dredging disposal ..... 90

    8.8.3 Within and outside the CDS as modelled using ROMS for disposal of capital dredging material

    .................................................................................................................................................... 91

    8.8.4 Cumulative effects....................................................................................................................... 92

    8.8.5 Summary of capital and maintenance dredging disposal sedimentation .................................... 93

    8.9 Effects of Sediment Deposition on Ecological Resources .............................................................. 94

    8.9.1 Types of effects ........................................................................................................................... 94

    8.9.2 Sensitivity of biota ....................................................................................................................... 94

    8.9.3 Plume sedimentation and observable effects data ..................................................................... 95

    8.10 Effects of Sediment Quality on Benthic Biota ................................................................................. 96

    8.10.1 Introduction ................................................................................................................................. 96

    8.10.2 Effects inside the CDS ................................................................................................................ 96

    8.10.3 Effects outside the CDS .............................................................................................................. 97

    8.11 Effects on Seabirds and Marine Mammals ..................................................................................... 98

    8.11.1 Effects on seabirds...................................................................................................................... 98

    8.11.2 Effects on marine mammals ....................................................................................................... 98

    8.12 Sediment Resuspension ............................................................................................................... 101

  • November 2018 1779496-002-R-Rev0

    vi

    8.13 Biosecurity Risk ............................................................................................................................. 101

    8.14 Human Health ............................................................................................................................... 102

    8.14.1 Introduction ............................................................................................................................... 102

    8.14.2 Effects on water quality ............................................................................................................. 103

    8.14.3 Bio-uptake – transfer to fish etc. ............................................................................................... 104

    8.14.3.1 Bio-uptake Process ................................................................................................................ 104

    8.14.3.2 Trace Elements ...................................................................................................................... 104

    8.14.3.3 Organic Compounds .............................................................................................................. 106

    8.14.3.4 Implications changes in contaminant flux .............................................................................. 108

    8.15 Effects on Recreational Activities .................................................................................................. 108

    8.16 Effects on Commercial Fishing Activity ......................................................................................... 109

    9.0 DREDGING AND DISPOSAL MANAGEMENT ..................................................................................... 109

    9.1 Suitability of Dredged Material for disposal at CDS ...................................................................... 109

    9.1.1 Introduction ............................................................................................................................... 109

    9.1.2 Navigation Channel dredging .................................................................................................... 110

    9.1.3 Port maintenance dredging ....................................................................................................... 110

    9.2 Dredging Management .................................................................................................................. 111

    9.2.1 Introduction ............................................................................................................................... 111

    9.2.2 Exclusion areas ......................................................................................................................... 112

    9.2.3 Recency .................................................................................................................................... 112

    9.2.4 Further sediment quality characterisation ................................................................................. 113

    9.3 Dumping Management .................................................................................................................. 113

    9.4 Sampling and Assessment Plans.................................................................................................. 115

    9.4.1 Port maintenance dredging (port Precincts) ............................................................................. 115

    9.4.2 New areas of maintenance dredging within the port precincts ................................................. 115

    9.4.3 Navigation channel maintenance dredging ............................................................................... 115

    9.4.4 Areas of capital works ............................................................................................................... 115

    10.0 SUMMARY AND CONCLUSIONS ......................................................................................................... 116

    11.0 LIMITATIONS .......................................................................................................................................... 119

    12.0 REFERENCES ........................................................................................................................................ 119

  • November 2018 1779496-002-R-Rev0

    vii

    TABLES

    Table 1: Part 5 and Part 6 requirements. ............................................................................................................. 5

    Table 2: Section 39 requirements and relevant section of this Impact Assessment. ........................................... 6

    Table 3: Summary of recent dumping activity at the CDS since 2000. ................................................................ 9

    Table 4: Port of Auckland wharf activity and product handling contamination risks summary. .......................... 12

    Table 5: Major Auckland Council stormwater outfalls within Port of Auckland. .................................................. 14

    Table 6: List of marine species targeted during the biosecurity surveys and their known status in the Port of Auckland. ............................................................................................................................................................ 16

    Table 7: Summary of sampling in the Port of Auckland. .................................................................................... 20

    Table 8: Comparison of trace element concentrations with ANZECC (2018) guidelines. .................................. 27

    Table 9: Summary of GV-high exceedance in Port sediments.......................................................................... 28

    Table 10: Comparison of DDT and other organochlorine compound concentrations with the ANZECC (2018) sediment quality guidelines. ............................................................................................................................... 30

    Table 11: TBT and degradation products in sediment samples collected in the 2016-2017 and 2018 surveys. ............................................................................................................................................................................ 31

    Table 12: Comparison of port ammoniacal-nitrogen and trace elements elutriate concentrations with ANZECC (2018) marine water quality default guideline values. ........................................................................................ 33

    Table 13: TSS and turbidity in Hauraki Gulf waters. .......................................................................................... 52

    Table 14: Trace element concentrations in New Zealand offshore waters. ....................................................... 53

    Table 15: Major and trace element concentrations in regional sediment. .......................................................... 54

    Table 16: Regional bird species breeding on Islands within the area of interest*. ............................................. 67

    Table 17: Conservation status of key marine mammals identified near the CDS (refer also to table 3-4 in Appendix F for information about other species). ............................................................................................... 69

    Table 18: Indicative Maintenance and Capital Dredging Timeline. .................................................................... 73

    Table 19: Amount of sediment stripped from sediment plume. ......................................................................... 74

    Table 20: Summary of estimated dilution available within the plume as plume descends (source: Beca 2018a). ............................................................................................................................................................................ 76

    Table 21: Comparison of maximum concentration of trace elements in elutriate with USEPA acute criteria. ... 79

    Table 22: Concentrations of TSS at which adverse effects have been identified in New Zealand marine biota (source: James 2016). ....................................................................................................................................... 87

    Table 23: Sediment quality changes due to sediment deposition inside the CDS. ............................................ 97

    Table 24: Key marine mammals identified near the CDS (refer also to Table 3-4 in Appendix F for information about other species). .......................................................................................................................................... 99

    Table 25: Comparison of maximum elutriate concentrations with ANZECC contact recreation water quality guidance. .......................................................................................................................................................... 103

    Table 26: Mercury in snapper caught at the NRDS (source: POAL 1989). ...................................................... 105

    Table 27: Organic compounds in snapper caught at the Waitemata Harbour and Hauraki Gulf (source: POAL 1990). ................................................................................................................................................................ 107

  • November 2018 1779496-002-R-Rev0

    viii

    FIGURES

    Figure 1: Location of Ports of Auckland in the Waitemata Harbour (upper image from Auckland City Masterplan). .......................................................................................................................................................... 2

    Figure 2: Location of the areas of Port maintenance dredging. ........................................................................... 2

    Figure 3: Location of the Navigation Precinct. ...................................................................................................... 3

    Figure 4: Location of the CDS. ............................................................................................................................. 8

    Figure 5: Port of Auckland Fergusson Container Terminal reclamation works. ................................................. 10

    Figure 6: Assessment process from the New Zealand Guidelines for the Sea Disposal of Waste (source: MSA 1999). .................................................................................................................................................................. 19

    Figure 7: Core sample locations colour coded in groups of three at Jellicoe Wharf east and Freyberg Wharf west in 2011. ....................................................................................................................................................... 22

    Figure 8: Bathymetry and broad topography of the seabed at the dumping site and in the Bay of Plenty. ....... 42

    Figure 9: Seabed characteristics of the outer Hauraki Gulf (screen capture from Seasketch). ......................... 43

    Figure 10: Forty-four year (1958-2001) mean (a) annual maxima significant wave height; (b) mean wave period associated with annual maxima significant wave height (source: Godoi et al. 2017). ........................... 44

    Figure 11: Wave rose at the NDA location (source: Beca 2018d). ................................................................... 45

    Figure 12: Schematic surface circulation around New Zealand based on drifter and hydrographic data (EAUC) (source: Chiswell et al. 2015). ........................................................................................................................... 46

    Figure 13: Current roses from a mooring north of the CDS on 1,000 m depth contour. Upper roses are for actual and modelled currents at 340 m depth. Lower roses are for actual and modelled currents at near-bottom (source: Macdonald & Rickard 2018). ................................................................................................... 47

    Figure 14: Modelled surface and bottom current roses at the CDS (source: Macdonald & Rickard 2018). ..... 48

    Figure 15: Derived seasonal temperature profiles from within the CDS (source: NIWA). ................................ 49

    Figure 16: CTD surveys conducted in 1994-95 off the northeast coast of New Zealand. The figure (source: Stanton et al. 1997) shows CTD stations and line numbers, the current meter moorings deployed on Survey 1 (El, E2, E3, E4 and E6) and the 200 and 1,000 m depth contours. ................................................................... 50

    Figure 17: Temperature, density and salinity profiles at site I2 on April 10, 21 and 25 (Surveys 1, 3 and 4). Data collected using a “SeaBird” CTD (source: Flaim & de Lange 2011). ......................................................... 51

    Figure 18: Sediment sampling locations off the northeast coast of New Zealand (from Glasby et al. 1997). ... 55

    Figure 19: Left: Predicted hotspots for habitat forming bryozoans (sum of all species examined) within the EEZ (from Woods et al. 2013). Right: Predicted distribution of Scleratinia corals (source: Anderson et al. 2014). . 58

    Figure 20: Location of “Local environmental knowledge” areas from Coromandel north around the CDS (source: Jones 2016). ........................................................................................................................................ 59

    Figure 21: Benthic sampling stations in the Bay of Plenty (source: Rosli et al. 2018). ..................................... 61

    Figure 22: Location of fish sampling sites at 50, 100, 300, 500, 700, 900 and 1,200 m depth within the area of interest (Great Barrier Island (left) and White Island (right) locations from Zintzen et al. 2017). ....................... 62

    Figure 23: Most abundant fish species in “Great Barrier” transects in Figure 22 (source - Zintzen et al. 2012). ............................................................................................................................................................................ 62

    Figure 24: From top to bottom: Total fishing effort, bottom trawling, bottom long-line, Danish seining (source: MacDiarmid et al. 2017)...................................................................................................................................... 64

  • November 2018 1779496-002-R-Rev0

    ix

    Figure 25: From top to bottom: Total catch and fishing effort for hoki, gemfish, ling and scampi (source: MacDiarmid et al. 2017)...................................................................................................................................... 65

    Figure 26: Distribution of black petrel during incubation (upper graphic) and during migration east 2008 (lower graphic) (source: Bell et al. 2014). ...................................................................................................................... 68

    Figure 27: The ROMS model domains. A: Outer grid, with every 10th grid line shown. The thick black rectangle indicates the position of the inner grid shown in more detail in right figure. The two red points immediately north of the inner model indicate the position of the moorings described in Section 7.3.2. B: Inner grid, with every 10th grid line shown, red circle is CDS, black star within circle is release point, black square is region shown in Figure 30 onwards (source: Macdonald & Rickard 2018). ...................................................... 75

    Figure 28: Key components of sediment disposal from a hopper barge (figure 3.28 from Flaim & de Lange 2011) (note, that the extent of the dispersed component shown in the figure is for illustration purposes only). 76

    Figure 29: Transect 6 from a survey of light transmission % through the water column following a disposal event at the NDA (figure 3.76 from Flaim & de Lange 2011) (ADCP backscatter data is superimposed within the diagram, side graphic shows relative location of the survey tracks). ........................................................... 77

    Figure 30: Near-surface (level 29) maximum TSS concentrations (mg/L) for key particle size classes (note that the scale is log-based such that -1 = 0.1 mg/L, -2 = 0.01 mg/L, -3 = 0.001 mg/L etc.) for 50th and 80th percentile (source: Macdonald & Rickard 2018). The red contour in both figures = 0.01 mg/L. ...................... 81

    Figure 31: Maximum TSS concentrations (mg/L) for key particle size classes at about ~200 m depth (layer 14) (note that the scale is log-based such that -1 = 0.1 mg/L, -2 = 0.01 mg/L, -3 = 0.001 mg/L etc.) (source: Macdonald & Rickard 2018). The red contour in both figures = 0.01 mg/L. ...................................................... 81

    Figure 32: Near-seabed maximum TSS concentrations (mg/L) for key particle size classes (note that the scale is log-based such that -1 = 0.1 mg/L, -2 = 0.01 mg/L, -3 = 0.001 mg/L etc.) (source: Macdonald & Rickard 2018). The red contour in both figures = 0.01 mg/L. No areas have concentrations of 0.1 mg/L........ 82

    Figure 33: Near-surface maximum TSS concentrations (mg/L) for key particle size classes during 365 days of capital dredging disposal (note that the scale is log-based such that -1 = 0.1 mg/L, -2 = 0.01 mg/L, -3 = 0.001 mg/L etc.) (source: Macdonald & Rickard 2018). Black contour = 0.1 mg/L and red contour in both figures = 0.01 mg/L. ........................................................................................................................................................... 83

    Figure 34: Maximum TSS concentrations (mg/L) at ~200 m depth for key particle size classes during 365 days of capital dredging disposal (note that the scale is log-based such that -1 = 0.1 mg/L, -2 = 0.01 mg/L, -3 = 0.001 mg/L etc.) (source: Macdonald & Richard 2018). The black contour at the dumping point = 0.1 mg/L and red contour in both figures = 0.01 mg/L. ...................................................................................................... 84

    Figure 35: Near-seabed maximum TSS concentrations (mg/L) for key particle size classes during 365 days of capital dredging disposal (note that the scale is log-based such that -1 = 0.1 mg/L, -2 = 0.01 mg/L, -3 = 0.001 mg/L etc.) (source: Macdonald & Richard 2018). The red contour in both figures = 0.01 mg/L. There is no area with 0.1 mg/L. ............................................................................................................................................. 84

    Figure 36: Summary of STFATE model assessments of dump site disposal under different cross-currents (source: Beca 2018a). ....................................................................................................................................... 89

    Figure 37: Average bottom layer thickness (mm) for 50th and 80th percentile sediment class for inner model CDS domain arising from 86 days of maintenance dredging disposal. White contours are model bathymetry (metres). Black circle locates CDS perimeter. Distances X and Y (km) are relative to the CDS centre. Note that the colour bar scale is a logarithm to the base 10 scale, such that values of -1 and -2 equate to thicknesses of 0.1 and 0.01 mm and black and red contours are the 0.1 mm and 0.01 contours, respectively (source: Macdonald & Rickard 2018). ................................................................................................................ 90

    Figure 38: Average bottom layer thickness (mm) for 50th and 80th percentile sediment class for INNER model CDS domain. White contours are model bathymetry (metres). Black circle locates CDS perimeter. Distances X and Y (km) are relative to the CDS centre. Note that the colour bar scale is a logarithm to the base 10 scale, such that values of -1 and -2 equate to thicknesses of 0.1 and 0.01 mm and black and red contours are the 0.1 mm and 0.01 contours, respectively (source: Macdonald & Rickard 2018). .......................................... 91

  • November 2018 1779496-002-R-Rev0

    x

    Figure 41: Vessel tracks to and from the Hauraki Gulf over the period October 2011 to January 2012 (source: AC 2014). ............................................................................................................................................................ 99

    APPENDICES

    APPENDIX A Previous disposal Permits Granted for the Cuvier Disposal Site

    APPENDIX B Bio-security Assessment

    APPENDIX C Ministry of Primary Industries Bio-security Communications to Stakeholders

    APPENDIX D Sediment Quality in the Port of Auckland

    APPENDIX E Review of Alternatives to Disposal at Sea

    APPENDIX F MacDiarmid et al. (2017) Review of Environmental Information within the Exclusive Economic Zone Near the Cuvier Disposal site

    APPENDIX G Near-field Sediment Modelling Using STFATE (Beca 2018a)

    APPENDIX H Far-field sediment modelling using Regional Ocean Modelling System (Macdonald & Rickard 2018)

    APPENDIX I Dredging Management Plan (Beca 2018b)

    APPENDIX J Disposal Management Plan (Beca 2018c)

    APPENDIX K Limitations

  • November 2018 1779496-002-R-Rev0

    xi

    Abbreviations and Units

    oC Degrees Celsius

    µg Microgram

    AC Auckland Council

    ADCP Acoustic doppler current profiler

    AHB Auckland Harbour Board

    ANZECC Australian and New Zealand Environment and Conservation Council

    ARC Auckland Regional Council

    ARWB Auckland Regional Water Board

    BCF Bio-concentration factor

    BOMEC Broad benthic optimised marine environment classification

    BSAF Bio-accumulation to sediment accumulation factor

    bsl Below sea level

    BT Bio-accumulation trigger

    BWE Bledisloe Wharf east

    BWW Bledisloe Wharf west

    CCC Criterion continuous concentration

    CCREM Canadian Council of Resource and Environment Ministers

    CD Chart datum

    CDS Cuvier Disposal site

    CMA Coastal Marine Area

    CTD Conductivity, temperature and density

    d Day

    DDT Dichlorodiphenyltrichloroethane

    DGV Default guideline values for sediment quality (ANZECC 2018)

    DiMP Disposal Management Plan

    DMMO Dredged Material Management Office

    DMMU Dredging material management unit

    DMP Dredging Management Plan

    DOAG Disposal Options Advisory Group

  • November 2018 1779496-002-R-Rev0

    xii

    DoC Department of Conservation

    dw Dry weight

    EAUC East Auckland Current

    EEZ Exclusive Economic Zone

    EIA Environmental Impact Assessment

    EMP S Environmental Management Plan: Stormwater

    EPA Environmental Protection Authority

    ER-L Effects range low

    ER-M Effects range median

    ERDC U.S. Army Engineer Research and Development Center

    FWE Freyberg Wharf east

    FWW Freyberg Wharf west

    FTU Formazin turbidity unit

    g Gram

    gamma-BHC Gamma-hexachlorocyclohexane

    Golder Golder Associates (NZ) Limited

    GV-high Upper guideline values for sediment quality (ANZECC 2018)

    ha Hectare

    hr Hour

    Hs Wave height (significant)

    JWE Jellicoe Wharf east

    JWW Jellicoe Wharf west

    kg Kilogram

    km Kilometre

    km2 Square kilometre

    kn knot, nautical mile per hour

    Kow Octanol-water partition coefficient

    L Litre

    m Metre

    M million

    m2 Square metre

  • November 2018 1779496-002-R-Rev0

    xiii

    m3 Cubic metre

    MD Maintenance dredging

    MHRSS Marine High-Risk Site Surveillance

    mg milligram

    mg Sn/m3 milligrams (expressed as tin) per cubic metre (of water)

    mm millimetre

    MoT Ministry of Transport

    MPI Ministry of Primary Industries

    MSA Maritime Safety Authority (New Zealand)

    NABIS National Aquatic Biodiversity Information System

    NDA Northern Disposal Area

    ng nanogram

    NHMRC National Health Medical Research Council

    NIS Non-indigenous species

    NIWA National Institute of Water and Atmospheric Research

    NP Navigation Precinct

    NRDS North Rangitoto Disposal site

    NTU Nephelometric turbidity unit

    OCP Organochlorine pesticides

    PAH Polyaromatic hydrocarbon

    Panuku Panuku Developments Auckland

    PCB Polychlorinated biphenyl

    POAL Ports of Auckland Limited

    POP Persistent organic compound

    PSU Practical salinity unit

    PWE princes Wharf east

    PWW Princes Wharf west

    QWE Queens Wharf east

    QWW Queens Wharf west

    ROMS Regional Ocean Modelling System

    s Second

  • November 2018 1779496-002-R-Rev0

    xiv

    Sn Tin

    SOP Standard operating procedure

    STFATE Short-term FATE

    t Ton

    TBT Tributyltin

    TEU Twenty-foot equivalent

    TN Total nitrogen

    TNC Threatened, nationally critical

    TOC Total organic carbon

    TPH Total petroleum hydrocarbons

    TSS Total suspended solids

    µg/kg milligrams per kilogram (sediment)

    µg Sn/kg micrograms (expressed as tin) per kilogram

    USEPA United States Environmental Protection Agency

    WWE Wynyard Wharf east

    y Year

    yd3 Cubic yard

  • November 2018 1779496-002-R-Rev0

    1

    1.0 INTRODUCTION

    1.1 Purpose

    Ports of Auckland Limited (POAL) is applying to the Environmental Protection Agency (EPA) for a permit

    authorising the dumping of dredged material from the Port of Auckland (the Port). The dredged material

    proposed to be dumped would consist of maintenance and capital dredging material. POAL is applying for a

    permit to dump the dredged material to the designated offshore disposal site located east of Cuvier Island.

    POAL engaged Golder Associates (NZ) Limited (Golder) to prepare this Environmental Impact Assessment

    (EIA) to support the Application. This EIA provides an overview of the project description including the source

    of the dredged sediment to be disposed, an assessment of the biosecurity risks and sediment quality within

    the Port, outlines the alternatives to marine dumping, an assessment of the effects of the sediment dumping at

    the Cuvier Disposal Site (CDS), and outlines the dredging and disposal management practices to be

    implemented during the disposal activities.

    Section 1.2 presents the context of dredging in the Port. Section 1.3 presents the dredging areas covered by

    this assessment. Section 1.4 sets out the assessment contents and the structure of this document.

    1.2 Dredging in the Port of Auckland

    POAL operates the Port. To operate the port effectively, POAL needs to maintain the notified water depths

    within the port.

    The port is located in the lower Waitemata Harbour adjacent to the Auckland City central business district

    (Figure 1). It was established in 1840. The port has 12 wharfs and received 1,572 ship visits in 2017. The

    notified depths (typically 10 to 13 metres (m) at berth) allow vessels visiting the Port to berth safely. As the

    port basins are sheltered from the main channel and tidal currents of the Waitemata Harbour, they act as

    settling basins and accumulate fine sediment (mostly mud) over time. Sediment accumulation varies

    throughout the Port, ranging from 30 millimetres (mm) to 200 mm a year. In order to maintain the required

    water depths in each basin, the accumulated sediment requires dredging on a regular basis.

    Maintenance dredging is currently undertaken in accordance with two resource consent granted by Auckland

    Council (AC). These are:

    Permit 34673 to dredge a maximum of 175,000 m3 of sediment every five years and an average of 35,000 m3 of sediment annually from the seabed [within the Auckland Port Management Area] (Figure 2).

    The permit was granted on 15 August 2007 and expired 31 August 2027

    R/REG/2016/3946 to undertake maintenance dredging within the Waitemata Navigation Channel Precinct, Auckland (Figure 3). The permit was granted on 20 November 2016 and expired on 20

    November 2036.

  • November 2018 1779496-002-R-Rev0

    2

    Figure 1: Location of Ports of Auckland in the Waitemata Harbour (upper image from Auckland City Masterplan).

    Figure 2: Location of the areas of Port maintenance dredging.

  • November 2018 1779496-002-R-Rev0

    3

    1.3 Dredging Areas Covered by this Assessment

    This document provides supporting information for the Application by Ports of Auckland to Environment

    Protection Authority for disposal of dredged material at the designated Cuvier Disposal Site from:

    The areas of the Port Precincts of the Unitary Plan covered by Permit 34673 to undertake maintenance dredging (Figure 2), excluding specified area identified in the DMP which are identified as unlikely to

    meet contamination requirements for marine disposal (these areas are described further in Section

    5.3.16 and the DMP). At the time of this application this includes:

    the west side of Jellicoe Wharf;

    the west side of the Western Reclamation;

    the Inner Viaduct Harbour; and

    areas within 20 m of designated stormwater outfalls within the port.

    The area in the Navigation Precinct in the Unitary Plan covered by Permit 16/3946 to undertake maintenance dredging (Figure 3).

    Figure 3: Location of the Navigation Precinct.

  • November 2018 1779496-002-R-Rev0

    4

    This document also sets the framework for the disposal of capital dredging which is not covered by the two

    current AC permits to undertake dredging. A separate resource consent will be sought from AC for specific

    capital dredging works. As described in the POAL 30-year Masterplan1 , POAL considers it will need to

    deepen the navigation channel by between one to two metres within the next 10 years to cater for the

    increased size of vessels servicing New Zealand. In total POAL expects to dispose around 2 M m3 to 2.2 M

    m3 of capital dredging material within the life of the consent to dump being applied for. Deepening would

    involve removing high points from the channel and possibly widening some corners. Currently, the channel is

    12.5 m deep at low-tide and around 15.5 m at high-tide.

    1.4 Assessment Contents

    This assessment has been prepared by Golder Associates (NZ) Limited for Ports of Auckland Limited. It

    presents supporting information in relation to the dumping of maintenance and capital dredging material to the

    designated offshore dredged material disposal site east of Cuvier Island. The structure of this assessment is

    as follows:

    Section 2.0 provides an overview of key elements of New Zealand dredged material dumping regulations.

    Section 3.0 provides information on the proposed dredging at the Port and a summary of the methods used to undertake the required work.

    Section 4.0 provides an overview of the biosecurity assessment undertaken to meet the requirements of the Permit.

    Section 5.0 sets out information on the physical and chemical characteristics of sediment to be dredged.

    Section 6.0 provides an overview of alternatives to disposal at sea.

    Section 7.0 describes the physical and natural environment at the disposal site and within the adjacent Exclusive Economic Zone (EEZ).

    Section 8.0 steps through the environmental assessment process utilizing the sediment quality information provided in Section 5.

    Section 9.0 provides a summary of stakeholder engagement undertaken.

    Section 10.0 provides an overview of dredging and disposal management.

    Section 11.0 presents a summary and conclusions.

    Supporting information is provided in the following appendices:

    Appendix A – Previous disposal permits granted for the Cuvier Disposal site.

    Appendix B – Biosecurity assessment.

    Appendix C – Ministry of Primary Industries biosecurity communications to stakeholders.

    Appendix D – Sediment quality in the Port.

    Appendix E – Review of alternatives to disposal at sea.

    1 http://www.masterplan.poal.co.nz/

  • November 2018 1779496-002-R-Rev0

    5

    Appendix F – MacDiarmid et al. (2017) review of environmental information within the Exclusive Economic Zone near the Cuvier Disposal site.

    Appendix G – Near field sediment modelling using short-term fate (Beca 2018a).

    Appendix H – Far-field sediment modelling using Regional Ocean Modelling System (Macdonald & Rickard 2018).

    Appendix I – Dredging Management Plan (Beca 2018b).

    Appendix J– Disposal Management Plan (Beca 2018c).

    2.0 DREDGED MATERIAL DUMPING REGULATIONS

    2.1 Overview

    The dumping of waste in New Zealand’s Exclusive Economic Zone (EEZ) is managed by the Environmental

    Protection Authority (EPA) under the Exclusive Economic Zone and Continental Shelf Act (EEZ Act) and the

    Discharge and Dumping Regulations. New Zealand is a signatory to the 1996 London Protocol to the

    Convention on the Prevention of Marine Pollution by Dumping of Wastes and Other Matter 1972.

    2.2 Exclusive Economic Zone and Continental Shelf (Environmental Effects – Discharge and Dumping) Regulations 2015

    Under section 10 of the Regulations, the discharge of sediments, other than a discharge that is permitted by

    Regulation 7, 8 or 9 or prohibited by regulation, is classified as a discretionary activity under the EEZ Act.

    Table 1 summarises the requirements under Part 5 and Part 6 relating to the dumping of dredged material.

    Table 1: Part 5 and Part 6 requirements.

    Clause Regulations text

    Part 5 Provisions relating to dumping

    32 - Dumping in authorised

    location classified as non-

    notified activity

    Dumping in an authorised location of any of the following is classified as a

    non-notified activity under the Act:

    (a) dredged material.

    33 - Dumping classified as

    discretionary activity

    Dumping of any of the following is classified as a discretionary activity

    under the Act:

    (a) dredged material, unless the activity is classified under regulation 32

    as a non-notified activity under the Act.

    Part 6 Miscellaneous provisions: Impact assessments

    35 - Matters that must be

    included in impact assessment

    for marine discharge consent

    In addition to the matters required under section 39 of the Act, an impact

    assessment included in an application for a marine discharge consent

    must describe the effects on human health of the activity.

    http://www.legislation.govt.nz/regulation/public/2015/0228/latest/link.aspx?search=qs_act%40bill%40regulation%40deemedreg_discharge+and+dumping+regulations_resel_25_h&p=1&id=DLM6593985#DLM6593985http://www.legislation.govt.nz/regulation/public/2015/0228/latest/link.aspx?search=qs_act%40bill%40regulation%40deemedreg_discharge+and+dumping+regulations_resel_25_h&p=1&id=DLM3956190#DLM3956190

  • November 2018 1779496-002-R-Rev0

    6

    Clause Regulations text

    36 - Matters that must be

    included in impact assessment

    for marine dumping consent

    In addition to the matters required under section 39 of the Act, an impact

    assessment included in an application for a marine dumping consent

    must—

    (a) describe the effects on human health of the activity; and

    (b) describe any alternative method of disposal that could be used; and

    (c) specify any practical opportunities to re-use, recycle, or treat the

    waste.

    2.3 Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012

    Under Section 38 of the EEZ Act, any application to EPA for a marine consent, a marine discharge consent, or

    a marine dumping consent to undertake a discretionary activity, must include an impact assessment prepared

    in accordance with section 39 and any requirements prescribed in regulations. Table 2 sets out the

    requirements identified in Section 39 of the Act and identifies the relevant section within this impact

    assessment that the material is provided.

    Table 2: Section 39 requirements and relevant section of this Impact Assessment.

    Section 39 requirements text EIA

    section

    (1) An impact assessment must—

    (a) describe the activity (or activities) for which consent is sought; and 1.0

    (b) describe the current state of the area where it is proposed that the activity will be

    undertaken and the environment surrounding the area; and 7.0

    (c) identify persons whose existing interests are likely to be adversely affected by the

    activity; and Application*

    (d) identify the effects of the activity on the environment and existing interests

    (including cumulative effects and effects that may occur in New Zealand or in the

    sea above or beyond the continental shelf beyond the outer limits of the exclusive

    economic zone); and

    8.15, 8.16

    Application

    (e) identify the effects of the activity on the biological diversity and integrity of marine

    species, ecosystems, and processes; and 8.0

    (f) identify the effects of the activity on rare and vulnerable ecosystems and habitats of

    threatened species; and 8.0

    (g) describe any consultation undertaken with persons described in paragraph (c) and

    specify those persons who have given written approval to the activity; and

    Application*

    9.0

    (h) include copies of any written approvals to the activity; and NA

    (i) specify any possible alternative locations for, or methods for undertaking, the

    activity that may avoid, remedy, or mitigate any adverse effects; and 6.0

    http://www.legislation.govt.nz/regulation/public/2015/0228/latest/link.aspx?search=qs_act%40bill%40regulation%40deemedreg_discharge+and+dumping+regulations_resel_25_h&p=1&id=DLM3956190#DLM3956190

  • November 2018 1779496-002-R-Rev0

    7

    Section 39 requirements text EIA

    section

    (j) specify the measures that could be taken to avoid, remedy, or mitigate the adverse

    effects identified (including measures that the applicant intends to take). 6.0

    (2) An impact assessment must also

    (a) if it relates to an application for a marine discharge consent, describe the effects of

    the activity on human health.

    NA

    (b) if it relates to an application for a marine dumping consent,—

    (i) describe the effects of the activity on human health; and 8.14

    (ii) specify any practical opportunities to re-use, recycle, or treat the waste or other

    matter: 6.0

    (c) if it relates to any other application, describe the effects on human health that may

    arise from the effects of the activity on the environment. 8.0

    (3) An impact assessment must contain the information required under subsections (1) and

    (2) in

    (a) such detail as corresponds to the scale and significance of the effects that the

    activity may have on the environment and existing interests; and

    8.0

    (b) sufficient detail to enable the Environmental Protection Authority and persons

    whose existing interests are or may be affected to understand the nature of the

    activity and its effects on the environment and existing interests.

    8.0

    (4) The impact assessment complies with subsections (1)(c) to (f) and (2) if the

    Environmental Protection Authority is satisfied that the applicant has made a reasonable

    effort to identify the matters described in those provisions.

    -

    (5) The measures that must be specified under subsection (1)(j) include any measures

    required by another marine management regime and any measures required by or

    under the Health and Safety at Work Act 2015 that may have the effect of avoiding,

    remedying, or mitigating the adverse effects of the activity on the environment or existing

    interests.

    -

    Notes: * Stakeholder engagement information is provided in the Application document.

    2.4 Dumping Location

    Dumping of material at sea is allowed if authorised by a marine consent. There are five existing dumping

    grounds in the EEZ and these are the preferred locations for dumping of waste (dredged sediment is classified

    as waste under the EEZ Act). Dumping in the EEZ outside of these areas is possible, but any such proposal

    requires a greater level of impact assessment and justification as to why existing sites cannot be used. The

    Auckland site (referred to as the Cuvier Disposal site – CDS) is a circle of four nautical miles radius (7.4

    kilometres (km)) centred on position 36° 28’ S 176° 20’ E (27 nautical miles east of Cuvier Island) (Figure 4).

  • November 2018 1779496-002-R-Rev0

    8

    Figure 4: Location of the CDS.

    2.5 Past Disposal at the CDS

    No published information has been identified describing the history and use of the CDS for the dumping of

    munitions and other waste. During the period following the second world war and up to 1958, Wilkes (1993)

    reported that a total of 19,500 tons (t) of ammunition were dumped at explosives sites around New Zealand.

    A proportion of that total, from stockpiles in Auckland and Ngaruawahia, were dumped in the Hauraki Gulf

    (presumed to be the CDS) although shallow dumping did occur, as noted below.

    The current ammunition dumping sites within the EEZ were regulated in 1955. Prior to that, explosives

    dumping in the Auckland region had occurred in shallower waters within the Hauraki Gulf (between Tiritiri

    Matangi Island and The Noises in position 36° 38’S., 174° 57’E).

    Information is available for permits granted by Maritime New Zealand (up to 2000) and for consents granted

    by EPA since 2000. No documented information for dumping activity prior to 2000, including information on

    munitions disposal at the CDS, has been located.

    The CDS was also used for the dumping of 250,000 m3 of dredged material (mainly sandstone) during the

    development of the inner Viaduct Basin for the Americas Cup over the period 1997 to 1999.

    Appendix A provides a summary of all permits granted for dumping at the CDS since 2000. The dumping

    activity since 2000 has included three permits for vessel disposal (two barges and a steel pontoon used in

    military exercises) and three permits for the dumping of mortal remains. All other permits have been for the

    disposal of sediment. Nearly all have been for the dumping of dredged sediment with most of that being

    maintenance dredging from marinas located in the Auckland area. As summarised in Table 3, dredged

    sediment from Westpark Marina and Pine Harbour Marina has been disposed at this site in most years since

    2000.

  • November 2018 1779496-002-R-Rev0

    9

    Table 3: Summary of recent dumping activity at the CDS since 2000.

    Year Westpark Marina* Pine Harbour Marina Other dumping activity

    2000 x North Shore City Council (Rosedale outfall dredging)

    2002 x x Matiatia wharf

    2003 x x Sensation Yachts

    2004 x

    2005 x

    2006 x x Orakei Marina

    2007 x x

    2008 x x Bayswater Marina

    2009 x x

    2010 x x Maraetai Boating Club

    2011 x x

    2012 x x

    2013 x

    2014 x Bayswater Marina (2014-2015)

    2015 x x

    2016 x

    Notes: Information provided by EPA. * Now called Hobsonville Marina.

    3.0 PORTS OF AUCKLAND FACILITIES, ACTIVITIES AND DREDGING

    3.1 The Port of Auckland

    The Port of Auckland was ‘established’ with the construction of Wynyard Pier in 1851 followed by the first

    Queens Street wharf in 1852 (Barr 1926). The Auckland Harbour Board (AHB) was established in 1871 and

    POAL took over from the AHB in 1989. The Port of Auckland is 100 % owned by AC through Auckland

    Council Investments Limited.

    Dredging undertaken by AHB was disposed at the North Rangitoto Spoil ground. Prior to 1988, consent to

    dispose was required through Ministry of Transport (MoT) dumping permit application. From 1987 to 1988,

    following discussions with the Auckland Regional Water Board (ARWB) the AHB applied for water rights to

    dispose of dredged sediment at the North Rangitoto site. The ARWB special tribunal approved dumping to

    the North Rangitoto site in December 1988. MoT then granted dumping permits under the Marine Pollution

    Act for 1 January 1989 to 31 December 1989.

    POAL applied for, and was granted, a consent by Auckland Regional Council (ARC) to dispose of dredged

    sediment from the port at a new dumping site in the Hauraki Gulf in 1990. Following the dumping, an

    independent review of disposal alternatives was undertaken (Parliamentary Commissioner for the

    Environment (PCE) 1995). Following that review, POAL commenced disposal of maintenance dredging from

    throughout the Port into the Fergusson Container Terminal reclamation in 2004 (as mudcrete). Disposal has

    continued into the reclamation as of August 2018 (Figure 5).

  • November 2018 1779496-002-R-Rev0

    10

    Figure 5: Port of Auckland Fergusson Container Terminal reclamation works.

    3.2 Port Wharfs and Facilities

    Port of Auckland wharfs (from west to east) are:

    Wynyard Wharf on the west side of Viaduct Basin has historically been used for the handling of bulk liquids, including chemicals and liquids storage. The commissioning of the Marsden Point to Wiri

    pipeline in 1985 eliminated (80 % reduction) the import of bulk diesel and ‘motor spirits’ across the wharf.

    The southern end of Wynyard Wharf has also been used for the movement of cement, sand and shingle.

    Ferry cargo for the Hauraki Gulf is also handled in this area. It is intended that the southern section of

    Wynyard Wharf is to be redeveloped into a marina as part of proposed AC36 developments (application

    has been lodged with AC). The land behind the wharf is currently used for bulk petroleum, and related

    liquids and storage. These industries are being decommissioned as part of land-side developments for

    AC36 and the longer-term development of Wynyard Point Park by Panuku Development Auckland

    (Panuku).

    Hobson Wharf and the Viaduct Basin have multi-purpose berthing uses including recreational, large vessel and commercial tourism berthing. This area has been used for the Americas Cup and Round the

    World Race fleets.

  • November 2018 1779496-002-R-Rev0

    11

    Princes Wharf which is used for residential apartments and as a cruise ship terminal. An easement around the edge wharf provides for emergency services and ship berthing (such as when cruise ships

    visit). Passenger vessels berth on the east side of the wharf.

    Princes-Queens basin below the old ferry building is utilised by a variety of passenger ferry services, charter and tourism operators.

    Queens Wharf which is now owned and administered by Panuku and is utilised for cruise ship berthing.

    Captain Cook Wharf is used for roll-on roll-off vehicle carriers and Marsden Wharf is too small for modern ships and is in the process of being removed.

    Bledisloe Terminal is used principally for roll-on roll-off vehicle carriers.

    Jellicoe Wharf has historically been used for the fruit trade and vehicle imports but is now used for the Pacific Island container trade, cement and bulk (steel and timber etc). In the past this included

    phosphate rock.

    Freyberg Wharf has two berths and handles a variety of cargo including bulk cargo such as gypsum.

    Fergusson Terminal which is currently a container terminal developed in stages from the 1960s and handles the larger container ships.

    3.3 Stormwater

    POAL manages stormwater generated within the Port via the Environmental Management Plan: Stormwater

    (EMP-S) (POAL 2018). The focus of the Port’s EMP-S is on source control and operational and management

    practices, supported by structural measures for specific activities and/or high-risk activities which together

    reduce the potential for stormwater-borne contaminants to be discharged into the harbour. The EMP-S is a

    requirement of the resource consent (Consent 25179) issued (by AC in February 2010) for stormwater

    discharges from the Port east of Captain Cook Wharf. The plan is a living document, which is reviewed

    annually to ensure ongoing relevance.

    The Port areas draining into the harbour equates to approximately 90 hectares (ha). Stormwater falling on the

    Port will enter the Waitemata Harbour Coastal Marine Area (CMA) in one of two ways, namely:

    1) Collected and discharged through POAL’s stormwater system, which comprises of slot drains, channels,

    catch pits and underground pipework and outfalls, or into a stormwater pipe owned and operated by AC.

    2) The stormwater falls through the wharf structure and runs off directly into the CMA.

    Table 4 provides a summary of the activities undertaken at the port wharfs and the cargo/material handled at

    them along with the environmental controls that put in place for each activity.

  • November 2018 1779496-002-R-Rev0

    12

    Table 4: Port of Auckland wharf activity and product handling contamination risks summary.

    Product/Material Controls Procedures

    Dry bulk and breakbulk cargo

    Discharge of dry cargo.

    Organic material

    (e.g., timber).

    Inorganic material

    (e.g., cement).

    Wide variety of ship to

    shore conveyance

    protection, sweeper

    truck, filter socks at

    catchpits etc.

    Includes wind restrictions,

    checks and wharf cleaning,

    spill procedures.

    Wharf stockpiled

    materials include

    gypsum, silica

    sand, iron sand

    (export), calcite and

    shredded scrap

    steel.

    Dust control equipment.

    Specific controls (standard

    operating procedures (SOPs))

    in place for handling of all bulk

    products including iron sand

    and scrap steel.

    Container handling and equipment

    Discharge of shipping

    containers (Fergusson

    and, Multi Cargo).

    Containers

    transport/contain a

    variety of products.

    Containers are not

    unpacked within

    port.

    In the event of a

    container being

    damaged, a variety of

    controls and equipment

    are in place to manage

    any material lost from

    container.

    SOPs for specific activities.

    Crane washing

    Greases, oils,

    hydrocarbons,

    hydraulic fluid, and

    organics

    (biodegradable

    detergents).

    Temporary bunds

    Waste disposal containers

    SOP 10 – Plant and Equipment Washing

    Waste management and disposal

    Waste generated from

    workshops, facilities and

    office.

    Oils, metals,

    solvents, organic

    waste, litter

    Permanent stormwater

    treatment devices -

    workshop / refuel

    areas

    Discharges to Tradewaste from

    wash pads / wash

    facilities

    Waste recycling bins – scrap steel,

    waste oil, batteries,

    Waste segregation

    Used battery segregation and disposal

    Waste management contract including

    collection and disposal of

    skips and recycling

    materials. Sweeping and

    litter collection contract –

    includes manual

    collection of litter /

    dunnage and routine

  • November 2018 1779496-002-R-Rev0

    13

    Product/Material Controls Procedures

    paper, cardboard,

    organic material

    Spill kits

    vehicle sweeping of

    berths and roadways

    Workshop activities

    Discharge to stormwater

    system from workshop.

    Organic, inorganic

    (hydrocarbons,

    minerals).

    Workshop Stormceptor

    treatment device, spill

    kits, tray bunds, sealed

    containers.

    Container cleaning

    Discharge from shipping

    container cleaning to

    trade waste system.

    Organics and

    inorganics, oily

    wastes, greases,

    debris, detergents

    etc.

    Cleaning undertaken at

    dedicated wash. Wash

    water treated and

    discharged as trade

    waste.

    General port use

    Discharge from port

    pavements and wharfs

    to stormwater system or

    harbour.

    Dust, sediment,

    litter, contaminants.

    Sand filters on

    Fergusson Extension,

    sweeper truck, general

    waste skip bins,

    cardboard waste skip

    bins, scrap metal skip

    bins.

    SOP 5 – Waste Handling and

    Disposal.

    SOP 14 – Sweeping and Gross

    Litter Collection.

    The Port also accommodates several discrete activities with greater potential for discharge of contaminant-

    affected stormwater, these include:

    Engineering workshop where Port plant is maintained.

    Refuelling areas for Port plant and vehicles.

    Bulk materials handling.

    Container and vehicle cleaning areas.

    POAL operates a range of on-site treatment systems to improve water quality of runoff from a high-risk area

    prior to discharge to the Waitemata Harbour. Table 4 identifies Port activities and their potential for discharge

    of contaminant-affected stormwater. Holcim commenced operation of a cement facility at the Port in 2016.

    Holcim has obtained a separate Industrial Trade Activity / stormwater discharge consents for the facility. The

    Holcim facility is not covered by POAL’s stormwater discharge consent (No. 25179).

    POAL (2018) provides an inventory of all outfalls discharging to the Waitemata Harbour that drain impervious

    areas within the Port. There are also a series of major stormwater outfalls that discharge stormwater drainage

    from the Auckland central business district catchments behind the Port (Table 5). The location of these

    outfalls is shown in the DMP (Beca 2018b)

  • November 2018 1779496-002-R-Rev0

    14

    Table 5: Major Auckland Council stormwater outfalls within Port of Auckland.

    Pipe ref. Diameter (mm) Location

    75 225 Princes Wharf.

    77 Multiple 1,000 Ferry pontoons.

    78 1,200 Queens Wharf.

    79 1,800 x 1200 Captain Cook Wharf.

    79a 3,000 x 2650 Between Captain Cook and Marsden Wharfs.

    80 1,600 West side of Bledisloe Terminal.

    85 375 Base of Bledisloe Terminal B1.

    86 375 Between Bledisloe Terminal and Jellicoe Wharf.

    87 1,600 Base of Jellicoe Wharf.

    88 300 Base of Jellicoe Wharf.

    89 225 Immediately west of Freyberg Wharf.

    93 1050 West side, base of Fergusson Terminal.

    Note: Pipe numbers refer to stormwater outfall designations in POAL (2018).

    POAL has trade waste permits from Watercare Services Limited (Watercare) for a range of operations that

    discharge to sewer (trade waste). This includes straddle carrier wash facility, Fergusson Container wash

    facility, Ministry of Primary Industries (MPI) wash facility, Fryberg Wharf wash facility and the engineering

    wash facility.

    3.4 Port Dredging

    3.4.1 Introduction

    A summary of dredging undertaken in the Port prior to 1989 and future dredging needed at that time was

    presented in POAL (1989). Early dredging in the Port in the 1800s and early 1900s was utilised for the

    construction of various reclamations within the city.

    3.4.2 Maintenance dredging

    Maintenance dredging is required within the Port to ensure that notified depths are provided for visiting

    vessels. In the 1970s and 1980s, maintenance dredging was irregular but as shown below in more recent

    years has been carried out on a regular basis resulting in more consistent volumes of sedime