report to api sc18, task group 6, welding api 2013 summer standardization conference © 2013...

10
Report to API SC18, Task Group 6, Welding API 2013 Summer Standardization Conference © 2013 Qualified Specialists, Intl. Chairman: Bud Weightman

Upload: norma-ray

Post on 24-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Report to API SC18,Task Group 6, Welding

API 2013 Summer Standardization Conference

© 2013 Qualified Specialists, Intl.

Chairman: Bud Weightman

Report to API SC18 on Task Group 6, Welding

© 2013Qualified Specialists, Intl. 2

SC18, TG 6 Charge

To review all API product specifications and Recommended Practices and to cross-functionally identify requirements for welding, brazing and soldering; the purpose is to identify criteria to be recommended for use where these processes are required.

Report to API SC18 on Task Group 6, Welding

© 2013Qualified Specialists, Intl. 3

Members / Interested Parties

Line Item Name Company

Chairman Bud Weightman Qualified Specialists, LLC

1 Bamidele Agbogun Self

2 Bob Prince ExxonMobil

3 Rick Noecker ExxonMobil

4 Stacey Hagan ExxonMobil

5 Jim McHaney ExxonMobil

6 Charlie Ribardo British Petroleum

7 David Alva Drillmec

8 Ed Baniak API

9 Eric Wehner NOV

10 Don McDowell Antelope Oil Tools

11 Gary Devlin Cameron

12 Jerry Longmire GE Oil & Gas Pressure Control

13 Jim Harris (alt) GE Oil & Gas Pressure Control

14 Jimmy Hashem Halliburton

Line Item Name Company

15 Jude Boudreaux Frank’s Casing

16 Timothy Burns Shell

17 William Blue Baker Hughes

18 Allen Bolyard Baker Hughes

19 Billy Croker IQAS

20 Ron Schlappy Unique Machine

21 Nels Wickander Wickander & Associates

22 Eric Berger Global Energy Service

23 Amos Ware National Oilwell Varco

24 Gil Hunter National Oilwell Varco

25 Randy Mariott National Oilwell Varco

26 Carlos Medina National Oilwell Varco

27 David Bartholomew Amega West

Report to API SC18 on Task Group 6, Welding

© 2013Qualified Specialists, Intl. 4

Members / Interested Parties

Line Item Name Company

28 Angus Lamont Weatherford

29 Mike Briggs Cameron

30 Alan Johnson Alan Johnson Associates

31 Raouf Naguib Woodco USA

32 Chris North NOV

33 Dave Dufresne Inserpetrol

34 David Harris Schlumberger

35 Carlo Iasella U.S. Steel Tubular Products

36 Mike Webber Hunting Energy Services, LP.

37 Andrea Romero Hunting Energy Services, LP.

38 James Fraysur Weatherford

39 William Howie Weatherford

40 Stan Jones Weatherford

41 Justin Grimes SCV

Line Item Name Company

42 Michael Teele Array Products

43 Mel Wright Shell

44 Philip Castle-Smith Shell

45 Chris Halbrook FMC

46 Bill Coble Cameron

47 Michael Wright Permian Tank & MFG.

48 Oscar Baker Permian Tank & MFG.

49 Gary Crisp Independence Contract Drilling

50 Garrett Schopper NOV

51 Teresa Comeaux T3

52 Scott Dillard T3

53 Jim Alban Cameron

54 Bryan Busser Aker Solutions

55 Jim McCabe GE Oil & Gas

Report to API SC18 on Task Group 6, Welding

© 2013 Qualified Specialists, Intl. 5

Purpose

Task Group work has been completed

Key Welding Criteria have been identified

A gap analysis template has been developed

Gap analyses have been performed on 23 API Product Specifications

Report to API SC18 on Task Group 6, Welding

© 2013Qualified Specialists, Intl. 6

Product Specifications Have Been Evaluated

2C

4F5CT5DP5L6A6D

6DSS7-17K8C14A14L16A16C

16D16F16RCD17D17F19G119G2

Report to API SC18 on Task Group 6, Welding

© 2013Qualified Specialists, Intl. 7

Results of TG6’s Work

The TG:

feels that its concept has been proven

requests SC18 members to review and comment on the TG’s work output

requests SC18 members to identify any areas that require clarification

© 2013Qualified Specialists, Intl. 8

Report to API SC18 on Task Group 6, Welding

If results are not accepted, the TG will rework as needed

When accepted by SC18, request TG6 work output be submitted to Product Specification SC Chairs for adoption

Additional work (if needed) to be performed through the creation of a Welding Quality Assurance Specification

Future Work Program

© 2013Qualified Specialists, Intl. 9

Report to API SC18 on Task Group 6, Welding

Future Meeting Dates / Resources

To be determined

Future Activities

Report to API SC18 on Task Group 6, Welding

© 2013Qualified Specialists, Intl. 10

Questions