requirements = scope, ba world bengaluru 2011
Post on 18-Oct-2014
3.359 views
DESCRIPTION
In May 2011 I presented this discussion of why project scope is driven by requirements, how requirements change is inevitable, and how that makes good project estimates very difficult. I then present one useful technique for managing this challenge.TRANSCRIPT
![Page 1: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/1.jpg)
Requirements = Project Scope Managing Requirements to Achieve Project Success
Craig Brown www.BetterProjects.net
www.BusAnalysts.com.au
Business Analyst World Conference Bangalore May 26 2010
![Page 2: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/2.jpg)
LEARNING GOALS
1. Lean how requirements drive project scope
2. And how project requirements change can be anticipated
3. So that project budgets and schedules can properly managed!
![Page 3: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/3.jpg)
![Page 4: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/4.jpg)
![Page 5: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/5.jpg)
REQUIREMENTS = SCOPE
![Page 6: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/6.jpg)
IIBA/BABOK • When reading the BABOK Guide it is vital that
‘requirements’ be understood in the broadest possible sense.
• Requirements include but are not limited to past, present and future conditions or capabilities in an enterprise and descriptions of organisational structures, roles, processes, policies, rules and information systems.
IEEE • A condition or capability needed by a user to
solve a problem or achieve an objective • A condition or capability that must be met or
possessed by a system or system component to satisfy a contract, standard, specification, or other formally imposed document
• A documented representation of a condition or capability as in (1) or (2)
Req
uir
emen
ts
![Page 7: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/7.jpg)
Scope: The sum of the products, services, an results to be provided as a project.
Project scope: The work that must be performed to deliver a product, service or result with the specified features and functions Product scope: The features and functions that characterise the product, service or result. Scope creep: Adding features and functionality (project scope) without addressing the effects of time, costs and resources, or without customer approval
Sco
pe
![Page 8: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/8.jpg)
Requirements = Scope
Project Scope
Work to be Done
Product Scope
Product/Service Capabilities
Requirements Budget and Schedule
Drives
![Page 9: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/9.jpg)
REQUIREMENTS AND SCOPE
CHANGE
Incomplete
Inconsistent
Poor quality
Changing needs
Don’t forget poor estimating ability
![Page 10: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/10.jpg)
STORY
Deadlocked!
![Page 11: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/11.jpg)
REQUIREMENTS AND SCOPE
CHANGE
Incomplete
Inconsistent
Poor Quality
Changing
poor estimating ability
![Page 12: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/12.jpg)
GAME
Estimate this!
![Page 13: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/13.jpg)
![Page 14: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/14.jpg)
![Page 15: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/15.jpg)
![Page 16: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/16.jpg)
![Page 17: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/17.jpg)
How did you go?
![Page 18: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/18.jpg)
Budget compliance
Scope compliance
Schedule compliance
Quality compliance
Value generated
People learning from the process
Simply getting it finished
![Page 19: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/19.jpg)
EXPECTATION MANAGEMENT
Success =
Expectation
Perceived Experience
![Page 20: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/20.jpg)
• Image: trusted advisor
![Page 21: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/21.jpg)
• Image: con man
![Page 22: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/22.jpg)
HOW TO MANAGE PROJECT SCOPE
A description of a method
In a context
With some caveats
![Page 23: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/23.jpg)
![Page 24: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/24.jpg)
-
20
40
60
80
100
120
140
160
180
200
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Work done Work remaining
![Page 25: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/25.jpg)
![Page 26: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/26.jpg)
2% per month
![Page 27: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/27.jpg)
200
250
300
350
400
450
500
Jan Feb Mar Apr May Jun JulAug
SepOct
NovDec
249 308
380
466
2% 4% 6% 8%
200
![Page 28: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/28.jpg)
200
250
300
350
400
450
500
Jan Feb Mar Apr May Jun JulAug
SepOct
NovDec
249 308
380
466
2% 4% 6% 8%
200
25% 54% 90% 133%
![Page 29: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/29.jpg)
-
20
40
60
80
100
120
140
160
180
200
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Work done Work remaining
8%
6%
4%
2%
![Page 30: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/30.jpg)
![Page 31: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/31.jpg)
0
500
1000
1500
2000
16-Jan 16-Feb16-Mar 16-Apr 16-May 16-Jun 16-Jul 16-Aug 16-Sep 16-Oct 16-Nov 16-Dec 16-Jan 16-Feb 16-Mar 16-Apr 16-May 16-Jun
Work to do Work remaining Work done
![Page 32: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/32.jpg)
0
500
1000
1500
2000
16-Jan 16-Feb16-Mar 16-Apr 16-May 16-Jun 16-Jul 16-Aug 16-Sep 16-Oct 16-Nov 16-Dec 16-Jan 16-Feb 16-Mar 16-Apr 16-May 16-Jun
Work to do Work remaining Work done
![Page 33: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/33.jpg)
0
500
1000
1500
2000
16-Jan 16-Feb16-Mar 16-Apr 16-May 16-Jun 16-Jul 16-Aug 16-Sep 16-Oct 16-Nov 16-Dec 16-Jan 16-Feb 16-Mar 16-Apr 16-May 16-Jun
Work to do Work remaining Work done
![Page 34: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/34.jpg)
0
500
1000
1500
2000
16-Jan 16-Feb16-Mar 16-Apr 16-May 16-Jun 16-Jul 16-Aug 16-Sep 16-Oct 16-Nov 16-Dec 16-Jan 16-Feb 16-Mar 16-Apr 16-May 16-Jun
Work to do Work remaining Work done
![Page 35: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/35.jpg)
0
500
1000
1500
2000
16-Jan 16-Feb16-Mar 16-Apr 16-May 16-Jun 16-Jul 16-Aug 16-Sep 16-Oct 16-Nov 16-Dec 16-Jan 16-Feb 16-Mar 16-Apr 16-May 16-Jun
Work to do Work remaining Work done
![Page 36: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/36.jpg)
2% per month We got >>>
After measuring, monitoring and proactively managing the stakeholders and requirements
![Page 37: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/37.jpg)
0
500
1000
1500
2000
Requirements Growth v Delivery
![Page 38: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/38.jpg)
-
50
100
150
200
250
Work to do Work done Work remaining
![Page 39: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/39.jpg)
-
50
100
150
200
250
Work to do Work done Work remaining
0
500
1000
1500
2000
Work to do Work remaining Work done
~ 250 Stories
~ 2000 Story Points
![Page 40: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/40.jpg)
May June July….
Number of requirements
Number Completed this month
Number remaining
Requirements by size
Small
Medium
Large
![Page 41: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/41.jpg)
![Page 42: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/42.jpg)
Concluding
Requirements = Scope
You drive Scope
You need to manage expectations
You need information
Here is a simple technique
![Page 43: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/43.jpg)
Go collect your data and report back to me
Better Projects Blog
www.betterprojects.net
/Measuring Requirements/
http://www.betterprojects.net/p/measuring-
requirements.html
![Page 44: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/44.jpg)
LEARNING GOALS
1. Lean how requirements drive project scope
2. And how project requirements change can be anticipated
3. So that project budgets and schedules can properly managed!
![Page 45: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/45.jpg)
May June July….
Number of requirements
Number Completed this month
Number remaining
Requirements by size
Small
Medium
Large
![Page 46: Requirements = Scope, BA World Bengaluru 2011](https://reader034.vdocument.in/reader034/viewer/2022051816/54422365afaf9fe3098b4578/html5/thumbnails/46.jpg)
Picture Credits
Pic CC @ http://www.flickr.com/photos/subspace-eddy/2038095329/sizes/l/in/photostream/