resettlement action plan - world bank...surp will lead to the involuntary displacement of 134...
TRANSCRIPT
-
SOMALI URBAN RESILIENCE PROJECT
P163857
Resettlement Action Plan
Mogadishu Contract B: 19 Community Roads
Date: 3rd January 2019
Authors: Dr. Yahya Y. Omar & Mrs. Desta Solomon
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
-
ii
PROJECT DETAILS
Project Name Somali Urban Resilience Project
Grant Number TF-A8112
Project Number P163857
Grant Recipient Federal Government of Somalia
Project Implementing
Entity
Benadir Regional Administration/Municipality of
Mogadishu
Project TTL Zishan Karim
Project Co-TTL Makiko Watanabe
Social Safeguards
Specialist
Desta Solomon
Project Coordinator Omar Hussein
Project Focal Point Mohamed Hassan
Data Assistant Nabil Abdulkadir Awale
-
iii
TABLE OF CONTENTS
LIST OF FIGURES ...................................................................................... iv
LIST OF TABLES ........................................................................................ v
LIST OF ABBREVIATIONS ....................................................................... v
DEFINITIONS ............................................................................................. vi
EXECUTIVE SUMMARY .......................................................................... ix
1 INTRODUCTION ............................................................................... 12
1.1 Project Background ................................................................................................ 12
1.2 Project Context ....................................................................................................... 12
1.3 Project Description ................................................................................................. 13
1.4 Project Components that Give Rise to Resettlement ............................................. 24
2 RAP OBJECTIVES AND METHODOLOGY .................................. 26
2.1 Objectives ............................................................................................................... 26
2.2 Methodology .......................................................................................................... 27
3 POTENTIAL PROJECT IMPACTS .................................................. 28
4 SOCIO-ECONOMIC BASELINE CONDITIONS ............................ 30
4.1 Demographic Profile of PAP Household Heads .................................................... 31
4.1.1 Gender........................................................................................................... 31
4.1.2 Age ................................................................................................................ 32
4.1.3 Education Level ............................................................................................ 33
4.1.4 Main Income Source and Average Monthly Income .................................... 33
5 LEGAL AND INSTITUTIONAL FRAMEWORK ........................... 35
5.1 Somali National Laws ............................................................................................ 35
5.2 Municipality of Mogadishu Laws .......................................................................... 35
5.3 World Bank Policies .............................................................................................. 36
5.4 Gaps between Legal and Institutional Frameworks and Bank Policies ................. 38
6 ELIGIBILITY AND ENTITLEMENT ............................................... 43
6.1 Loss of Access........................................................................................................ 44
6.2 Loss of Structure .................................................................................................... 45
6.3 Loss of Trees .......................................................................................................... 46
6.4 Vulnerable Groups ................................................................................................. 46
7 CONSULTATION AND PARTICIPATION ..................................... 47
7.1 Consultations with BRA Leadership ...................................................................... 47
7.2 Consultations with the District Administration...................................................... 48
7.3 Consultations with Community Groups ................................................................. 48
7.4 Consultations with Resettlement and Grievance Committees ............................... 50
-
iv
7.5 Individual Interviews ............................................................................................. 51
8 IMPLEMENTATION PROCESS AND RESPONSIBILITIES ........ 54
8.1 Project Implementation Arrangement .................................................................... 54
8.2 Implementation Process ......................................................................................... 54
8.3 RAP Implementation Responsibilities ................................................................... 55
9 BUDGET AND RAP IMPLEMENTATION SCHEDULE ............... 57
10 GRIEVANCE REDRESS MECHANISM ......................................... 60
11 MONITORING AND EVALUATION .............................................. 62
11.1 Internal Monitoring ....................................................................................... 62
11.2 External Monitoring...................................................................................... 63
12 ANNEXES .......................................................................................... 64
Annex 1: List of PAPs and Types of Loss .................................................................... 64
Annex 2: Affected Assets and Compensation Calculations ......................................... 69
Annex 3: Attendance Sheets ......................................................................................... 70
Annex 4: Official List of Grievance Redress Committee Members ............................. 75
Annex 5: Educational Achievement of Household Heads ......................................... 76
Annex 6: Main Source of Income and Average Monthly Income ................................ 78
LIST OF FIGURES Figure 1: Mogadishu Districts Map ................................................................................. 13
Figure 2: Contract B Districts and Community Roads .................................................... 14
Figure 3: Educational Achievements of PAP Household Heads ..................................... 33
Figure 4: Main Source of Income for PAP Household Heads ........................................ 34
Figure 5: Consultations with BRA Leadership ............................................................... 47
Figure 6: Consultations with District Administration ..................................................... 48
Figure 7: Consultations with Community Groups ........................................................... 49
Figure 8: Grievance Committee Members Meeting ....................................................... 51
Figure 9: Enumerators Conducting Census ..................................................................... 52
Figure 10: Grievance Redress Process ............................................................................ 60
-
v
LIST OF TABLES
Table 1: Right of Way and Road Width .......................................................................... 25
Table 2: Types and Numbers of Affected Structures ...................................................... 29
Table 3: Gender Disaggregation of Household Heads .................................................... 31
Table 4: Age Groups of PAP Household Heads ............................................................. 32
Table 5: Gap Between Somali Laws and Bank Policy .................................................... 38
Table 6: Composition of Grievance Redress and Resettlement Committees .................. 50
Table 7: RAP Implementation Components .................................................................... 55
Table 8: RAP Implementation Responsibilities .............................................................. 56
Table 9: Breakdown of Compensation Budget................................................................ 57
Table 10: RAP Implementation Schedule ....................................................................... 58
LIST OF ABBREVIATIONS BRA: Benadir Regional Administration
FGS: Federal Government of Somalia
GRM: Grievance Redress Mechanism
IDP: Internally Displaced Person
IFC: International Finance Corporation
MOM: Municipality of Mogadishu
OP: Operational Policy
PAP: Project Affected Person
PCIP: Precast Concrete Interlocking Paving
PIM: Project Implementation Manual
PIU: Project Implementation Unit
RAP: Resettlement Action Plan
RPF: Resettlement Policy Framework
ROW: Right of Way
SUIPP: Somalia Urban Investment Planning Project
SURP: Somali Urban Resilience Project
TOR: Terms of Reference
USD: United States Dollar
WB: World Bank
-
vi
DEFINITIONS
Census A complete and accurate count of the population that will be
affected by land acquisition and related impacts. When properly
conducted, the population census provides the basic information
necessary for determining eligibility for compensation and for
preparing and implementing Abbreviated or full Resettlement
Action Plan (A/RAP).
Compensation Payment in cash or in kind for an asset or a resource that is
acquired or affected by a project at the time the asset needs to be
replaced1.
Cut-off Date The date the census and assets inventory of persons affected by
the project begins. Persons encroaching on the project area
after the cut- off date are not eligible for compensation and/or
any other type of resettlement assistance.2
Displaced Persons The people or entities directly affected by a project through the
loss of land and the resulting loss of residences, other
structures, businesses, or other assets3.
Eligibility The criteria for qualification to receive benefits under a
resettlement programme4.
Grievance Redress
Mechanism
Complaint mechanism is a locally based formalized way
through which project affected people and communities may
raise their concern directly with the project when they believe
the project has caused or may cause them harm. The Grievance
Redress Mechanism ensures that complaints are being promptly
received, assessed and resolved by those the responsible for the
project.
Host Community A host community is any community of people living in or
around areas to which people physically displaced by a project
will be resettled.
Household The term household refers to a group of people who reside
together and share in the functions of production and
consumption. It is also the smallest unit of consumption, and
sometimes production.
Household Head For purposes of a census, the household head is considered to
be that person among the household members who is
1 IFC Handbook for Preparing a Resettlement Action Plan, Undated
2 World Bank Operational Policies (OP 4.12)
3 Ibid
4 Ibid
-
vii
acknowledged by other members of the household as the head
and who is often the one who makes most decisions concerning
the welfare of the members of the household.
Involuntary
Resettlement
Direct economic and social impacts that both result from
investment projects, and are caused by:
(a) The involuntary taking of land resulting in
(i) relocation or loss of shelter;
(ii) loss of assets or access to assets; or
(iii) loss of income sources or means of livelihood, whether or
not the affected persons must move to another location; or
(b) The involuntary restriction of access to legally designated
parks and protected areas resulting in adverse impacts on the
livelihoods of the displaced persons5.
Involuntary Means actions that may be taken without the displaced person’s
informed consent or power of choice6.
Land Acquisition The process of acquiring land under the legally mandated
procedures of eminent domain.
Livelihood
Restoration
Livelihood Restoration means the measures required to ensure
that Project Affected Persons (PAPs) have the resources to at
least restore, if not improve, their livelihoods. It requires that
people are given the means and assistance necessary for them to
improve, or at least restore, their livelihood and living conditions
to pre-project levels. Inventory of Losses means the pre-
appraisal inventory of assets as a preliminary record of affected
or lost assets.
Project Affected
Person (PAP)
Project Affected Persons are persons on whom the project has a
direct economic and social impact. The impact may be caused
by the involuntary taking of land resulting in;
a) relocation or loss of shelter;
b) loss of assets or access to assets;
c) loss of income sources or means of livelihood whether or not
the person should move to another location; or
d) by the involuntary restriction of access to legally designated
parks and protected areas resulting in adverse impacts on the
livelihoods of the displaced persons7.
5Involuntary Resettlement Sourcebook, Planning and Implementing in Development Projects, 2004 World Bank
6 Ibid
7Ibid.
-
viii
Replacement Cost Full market value for replacing lost assets, plus transaction costs.
For agricultural land, it is the pre-project or pre-displacement,
whichever is higher, market value of land of equal productive
potential or use located in the vicinity of the affected land, plus
the cost of preparing the land to levels similar to those of the
affected land, plus the cost of any registration and transfer taxes.
For land in urban areas, it is the pre-displacement market value
of land of equal size and use, with similar or improved public
infrastructure facilities and services and located in the vicinity
of the affected land, plus the cost of any registration and transfer
taxes. For houses and other structures, it is the market cost of the
materials to build a replacement structure with an area and
quality similar to or better than those of the affected structure,
or to repair a partially affected structure, plus the cost of
transporting building materials to the construction site, plus the
cost of any labor and contractors’ fees, plus the cost of any
registration and transfer taxes. In determining replacement cost,
depreciation of the asset and the value of salvage materials are
not taken into account, nor is the value of benefits to be derived
from the project deducted from the valuation of an affected
asset. Where Somali law does not meet the standard of
compensation at full replacement cost, compensation under
domestic law is supplemented by additional measures so as to
meet the replacement cost standard.8
Resettlement Resettlement covers all direct economic and social losses
resulting from land taking and restriction of access, together
with the consequent compensatory and remedial measures9.
Resettlement
Action Plan
A resettlement action plan is the planning document that
describes what will be done to address the direct social and
economic impacts associated with involuntary displacement.
Resettlement
Entitlements
Resettlement entitlements with respect to a particular eligibility
category are the sum total of compensation and other forms of
assistance provided to displaced persons in the respective
eligibility category.
8 Ibid
9Ibid.
-
ix
EXECUTIVE SUMMARY
After more than two decades of conflict, Somalia’s capital city Mogadishu is on a path of
rapid recovery seeing considerable investments in its infrastructure. One of these
infrastructure investments is through the Somali Urban Resilience Project (SURP) funded
through the country’s Multi-Partner Fund (MPF) that is managed by the World Bank
(WB). SURP is currently being implemented by the Municipal governments of
Mogadishu and Garowe. It is envisioned that the project will eventually be rolled out to
other parts of the country such as Baidoa and Kismayo. In Mogadishu the SURP entails
the rehabilitation of 19 existing community roads in 7 of the city’s 17 districts covering
a total of 7 Kilometers (KM). Some of the roads are situated in populated areas and have
been partly encroached upon. SURP will lead to the involuntary displacement of 134
persons, who have encroached into the right of way (RoW). This has triggered WB
Safeguards Policy OP 4.12 designed to mitigate social and economic impacts that may
result from involuntary taking of land or involuntary restriction of access to property
whether legal or illegal. This policy requires the preparation of a resettlement action plan
(RAP) that includes compensation mechanism and entitlements. The Benadir Regional
Administration has budgeted USD 39,851.86 to cover compensation costs. The project
affected persons (PAPs) and potential losses were identified during a census and
registration of assets announced on the 5th of July 2018 and carried out between August
6, 2018 and October 29, 2018. The cut-off date was announced in the local district
headquarters and posters highlighting the date were put-up in each of the 19 roads.74
temporary standalone iron sheet structures comprising of 48 kiosks, 15 homes, one kiosk
cum home, 8 IDP latrines and 2 Islamic schools will be removed from the RoW. 3 papaya
trees that have also encroached upon the RoW will also be removed. In addition to this,
67 street vendors will suffer temporary loss of access. Compensation levels for all the
structures are full replacement cost derived from actual current market value of the
property as well as labor, and transport costs. The PAPs are also provided with the right
to salvage materials without deduction from their compensation. The 67 street vendors
and 48 Kiosk owners will be provided with cash compensation for their loss of income.
Kiosk owners will lose income hence will be provided with cash compensation equivalent
to one month of their lost income. The street vendors will suffer temporary loss of income
thus receiving cash compensation worth 50% of their estimated monthly income. In
-
x
addition, the kiosk owner and vendors will be offered employment opportunities to do
PCIP installation and repair training from the contractors to supplement their income.
This arrangement is based on an MoU to be signed between the BRA and the contractor.
In addition to this, the street vendors will be provided with alternative temporary space to
operate from in adjacent streets. The provision of these spaces has been agreed upon with
both the district commissioners and the municipal services. The kiosk owners will also
have similar opportunity as long as they use tables like the vendors. The BRA is currently
considering options for a more sustainable solution for housing the PAPS and vulnerable
persons losing their residential households. The construction of these two roads will only
begin after a more permanent alternative housing is made available for the PAPs. The
social and environmental safeguards in the PIU will follow up closely with the BRA and
inform the Bank on the resolution of the problem. Vulnerable families comprising six
orphan children, 4 disabled persons, three severely ill and one-person past retirement age
will receive additional assistance to cover 6 months of rent. Out of the 19 roads, the two
roads where vulnerable people need to be relocated are Madbacada Road and Sharif
Abow Road in Shangani district.
For the community facilities, madrasas will receive cash compensation at full replacement
cost for the entire structure. In addition to this, it has been agreed with the local elders
that learning will continue to take place at two nearby mosques thus eliminating the need
to commute for the learners. The IDP latrines will be moved to adjacent space, identified
by the IDPs, outside the RoW. In order to allow continued use, the municipal contractors
will be instructed to move two latrines at a time. In addition to replacing the currently
eroded iron sheets, a hand wash facility will also be built for the IDPs. A grievance redress
committee and a resettlement committee has been set up in each of the 7 districts to give
the residents and the PAPs a proper channel through which their concerns can be
addressed. During the implementation of this RAP regular monitoring will be carried out
through both internal and external monitors. This RAP is divided into 10 sections. Chapter
1 provides an overview of project context, description of the project and describes the
project components that give rise to resettlement. Chapter 2 outlines the objectives of the
RAP and the methodology used in its preparation while chapter 3 describes the potential
project impacts. Chapter 4 provides the socio-economic baseline condition and Chapter
5 analyzes applicable laws and policy framework. Chapter 6 offers a description of the
-
xi
eligibility and entitlement to compensation whereas Chapter 7 elaborates on the process
for consultation, participation, and disclosure. Chapter 8 provides an overview of the
Project implementation arrangements and process, and the different roles and
responsibilities in the implementation of the RAP. Chapter 9 describes the grievance
redress mechanism while Chapter 10 presents the RAP budget and implementation
schedule. Finally, Chapter 11 describes the arrangements that have been put into place
for the monitoring and evaluation of the RAP implementation.
-
12
1 INTRODUCTION
1.1 Project Background
The Somali Urban Resilience Project (SURP) is an infrastructure and governance development
project aimed at improving access to socio-economic infrastructure and strengthening
municipal governance in Somalia. The Project also aims to strengthen inter-governmental
relationships between the federal government, regional states and municipalities. It is intended
that the SURP will also strengthen the state-citizen relationship and the government’s
legitimacy in the eyes of its people by providing visible and tangible benefits. The Project is
thus as much about urban resilience as it is about peace building and institution building. SURP
builds on the preparation work carried out under World Bank’s ongoing Somalia Urban
Investment Planning Project (SUIPP). SUIPP financed institutional assessments, feasibility
studies and engineering design work for urban investments in Mogadishu, Hargeisa and
Garowe municipalities; institutional assessment of Hargeisa Water Agency and the Ministry of
Public Works at the federal level; and helped to set up Project Implementation Units (PIUs)
and build fiduciary, safeguards, project management, and monitoring and evaluation capacity
of the PIU staff based at these municipalities. The SUIPP carried out feasibility studies and
preliminary engineering designs for 4 primary urban roads (17km in length) and 47 secondary
roads (34km in length) across Mogadishu’s 17 districts; 30 km of secondary roads and 2 bridges
in Garowe; and a solid waste management facility and an anaerobic pond liquid waste
management system in Hargeisa. Due to funding limitations the initial interventions will begin
in Mogadishu and Garowe. However, the Federal Government of Somalia has made it explicit
that it wants this project to be of national scale. In Mogadishu SURP begins with the
construction of 19 community roads in 7 districts taking up to 12 months. There is a possibility
of extending SURP to include the rehabilitation of the other community roads studied during
SUIPP subject to the availability of funding.
1.2 Project Context
Mogadishu is the capital and most populous city in Somalia with an estimated population of
nearly 2 million inhabitants. Located in the Benadir region, this port city is among the oldest
cities along the Indian Ocean cost of Africa. The city is comprised of 17 districts (Figure 1)
whereby the old port districts of Hamarweyne, Hamarjajab, and Shangani are the earliest
settlements. After being mired in more than 2 decades of conflict the city has recovered and is
-
13
undergoing through rapid reconstruction. Each of the districts has a district headquarters and
a police station; however, the provision of public services such as education and health are
limited and mostly dominated by the private sector.
Figure 1: Mogadishu Districts Map
1.3 Project Description
The 47 community roads studied under SUIPP have been grouped into three different packages,
A, B, and C to allow for a systematic approach in their rehabilitation (Figure 2). During this
phase of SURP only 19 community roads will be rehabilitated.
-
14
Figure 2: Contract B Districts and Community Roads
The 19 roads in package B are located across 7 districts. The layout of these districts does
considerably vary, most notably Hamarweyne district, considered to be the oldest part of
Mogadishu, is mainly comprised of old concrete buildings and characterized by its narrow
roads and alleys. Most of the district’s residents are descendants of merchants from Arabia,
Portugal and Persia who settled in the area. Hamarweyne is home to many small businesses
and Suuqa Xamar Weyne, one of the largest markets in the city. Three roads will be
rehabilitated in Hamarweyne district: Iskool Xamar Weyne, Cadeyga, and Ex-Post Road.
-
15
Iskool Hamarweyne road is located in a populated commercial cum residential area.
The road starts from an intersection with an asphalted road, Via Roma, and ends at
an asphalted road (Philippine road). The road provides access to the main market,
Suuqa Hamarweyne, and Hamarweyne Secondary School. The buildings are a
mixture of old single and multistory made of concrete.
Cadeyga road is located in a populated residential area passing along the center of
the old city. Cadeyga road starts from an intersection with Ex-Post Road and ends
at an asphalted road that leads to Martini Hospital. There is an unused old sewage
network infrastructure installed on the road.
Ex-Post road is located in a populated residential area opposite old ruins. The road starts
from an intersection with an asphalted road (Ministry of Finance road) and ends at an
unpaved road. Most of the buildings are old stones and concrete or blocks and concrete
with the presence of a few modern buildings. Majority of buildings are multistory. An
electricity network is installed with electricity poles alongside the road. There are old
-
16
sewage and water supply networks infrastructure installed on the road. This road is
home to 800 years old, Masjid Jamee.. OP4.11 requirement will be followed during the
road construction for this section.
Unlike Hamarweyne, Abdiaziz district is much younger, less densely populated and is mostly
residential in nature. This district is home to the city’s beach facilities, particularly the famous
Lido beach. Two roads being constructed in Abdiaziz are Agoonta and UNDP roads.
Agoonta Road is located in a populated residential area and ends at an unpaved road
near a stadium gate. The road is connected with a road leading to Beach Road. It leads
directly to the gate of the stadium and passes by a police department and the district
office. Furthermore, it is used as an alternative road in case the main road is blocked.
Houses are made of concrete blocks. Moreover, there are walls which are also made
of concrete blocks.
UNDP Road is located in a scarcely populated residential area and starts from an
intersection with an unpaved road in Benaadir neighborhood and ends at a paved road
(Bandar Qasim Road) near Salaly Hospital. Most buildings are modern style buildings
including villas and buildings built with concrete blocks.
-
17
Shangani district is located between Hamarweyne
and Abdiaziz Districts and is characteristically a
mélange of the two districts in terms of its layout and
social composition. The district has five roads being
rehabilitated: Madbacada, Degmada, Ceymiska,
Sharif Abow and Todobatan iyo Talo.
Madbacada road is located in a sparsely populated area but contains the former
national printing press building which is home to nearly 90 IDP families. Along the
road there are some iron sheet structures that are used as homes. The road starts from
an intersection with an asphalted road (Todobatan iyoTalo Road) nearby the former
national press building and ends at an asphalted road (Fiisho Trafiko Road).
Degmada road is located in a populated
residential area and ends at the door of
the Shangani district headquarters. In
addition, the road intersects with four
unpaved footpaths. Most of the
buildings are old made of stones or
blocks.
-
18
Sharif Abow Road is located in a populated residential area. It starts from an
intersection with an asphalted road (Todobatan iyoTalo road) in front of the former
national printing press building and ends at an asphalted road. Many old building
destroyed during the war are located on this road.
.
Located in a populated residential area, Ceymiska starts from an intersection with an
asphalted road (Fiisho Trafiko Road). The road serves the neighborhood buildings
and there is a public square at the middle of its first section
-
19
Todobatan Iyo Talo road is located in a populated residential area. The road starts
from an intersection with an asphalted road nearby the building of district office and
ends at an asphalted road (Todobatan road) nearby the National Press building. In
addition, the road intersects with 12 unpaved roads. Most of the buildings are old
made from stone.
The other district along the coast is HamarJajab, home to the port and is also one of the oldest
districts in the city. This district is mostly comprised of low-income households who make
their living through manual labor. It is also home to the famous, Iskool Bolisio, Somalia’s
police academy. The houses in Hamar Jabjab are old but not as old as Hamarweyne. In Hamar
Jajab three roads will be renovated: Wikiyo/Simad, Iskool Hamar Jajab, and Fartaag Road.
Wiikiyo/Simad is located in a poor populated residential area and starts from an
intersection with an asphalted road (Uganda road) nearby SIMAD University and ends
at another asphalted road (Cairo road). The road is a zigzag type road and intersects
with many unpaved small roads. The road is considered part of the old city and passes
through one of the oldest neighborhoods in Mogadishu. The road serves many of the
public facilities such as a mother and child health center, a mosque and a madrasa. The
road also passes through a local once a week market.
-
20
Iskool Hamar Jabjaba Road is located in a populated poor residential area and has a T-
shape; the first part extends from east to west. The first road part starts from an
intersection with an asphalted road (Uganda road) near HamarJajab School. The road
is directly linked to the network of the main roads in the city. The road serves the
neighborhood and homes surrounding it and directly connects to the largest school in
the district, HammarJajab Secondary School. Most of the buildings are old and made
from concrete block with tin roofs.
Fartaag is an L shaped road located in a populated poor neighborhood passing through
old buildings. The road serves many public buildings such as SIMAD University, old
mosque, Hamar Jajab Schools, and health centers. Many of the buildings are old,
made from concrete block andiron sheet roofs.
The three remaining districts, Warta Nabada (previously, Wardigley), Bondheere, and
Hawlwadaag have varying levels of similarities and differences. Bondheere is adjacent to the
country’s statehouse and it is the poorest district in the city. This district is very susceptible to
flooding. During the rainy season many homes are vacated in fear of drowning. During every
-
21
rainy season life is lost due to flooding. The houses in the district have also been severely
affected by soil erosion and it is common to see high levels of soil deposits in some areas of
the district reaching up to the window level of other houses.
Binti Foodey Road is located in a populated poor residential area. Most of the buildings
are made of iron sheet and there a few old houses built from concrete block. There is
Om Al-Qura school compound at the beginning of the road. There are also remnants
of buildings along both sides of the road as well as many trees. Rainwater collects at
two locations and drains through very narrow corridors between the houses which
leaves the area prone to flooding.
.
-
22
Daaf Aleeley is located in a populated residential cum commercial area mostly
inhabited by the poor with a few of them in middle-class. Most of the houses are made
of iron sheet with a few modern buildings. The road starts from an intersection with
an asphalted road and ends at security barriers that completely block the road next to
a Minister’s residence. The road is characterized by a severe decline and there are
many encroachments from courtyards, built with iron sheet and block, on both sides
of the road. There is also significant drainage overflow from the houses onto the road.
Warta Nabada District is home to middle class residents who are mostly involved in business.
Compared to the other six districts, Warta Nabada is the longest extending from the middle
part of the city to the industrial area at the city perimeter. This district is also home to the
country’s largest stadium and most of the factories in Somalia. Warta Nabada has two roads
being renovated: Mire Ali Buubal and Garoonka Minishibiyo.
.
Garonka Minishibiyo Road is located in a populated residential near the municipal ground
and starts from an intersection with an asphalted road (Wadnaha road) and ends at an
unpaved road (Mahamud Harbi road). The road serves the neighborhood buildings, which
are a mixture of old concrete blocks and a few of modern houses
-
23
Mire Ali Buubaal Road is located in a populated residential area. The road starts from an
intersection with an unpaved road in front of the District Office and ends at an asphalted
road (Wadnaha road). In addition, the road intersects with many unpaved roads. The road
serves many public buildings such as district office, central market of the district, a
mosque and two schools. There is a mixture of old and new buildings located on road.
Hawlwaadag is home to one of the largest markets in East Africa, Suuqa Bakaaraha. The
district is properly laid out and most of its roads are broad. Outside of the market area, the
community is mostly of middle income. Only one road, Ceel Garweyne, will be rehabilitated
in Hawlwadaag District.
Ceel Garweyne is located in a populated middle-income residential area. The road
starts from an intersection with an asphalted road (Wadnaha Road) and ends at an
unpaved road, which links Dabka and Bar Bulsho divisions of the district. Most of the
buildings are modern, made from concrete blocks with reinforced concrete roofs. The
eastward side has empty areas some of them fenced with walls.
-
24
All roads in this component will be constructed using precast concrete interlocking paving
blocks with properly compacted sub-base and base materials. Such roads have two key
advantages: (i) it is labor intensive and will provide short term income generation opportunities
for communities; and (ii) it would allow communities to maintain and repair the roads with
minimal training and support. The construction of the 19 roads will be phased in and is expected
to take 245 working days. All roads have inverted block concrete open side drainage catered
for in the detailed engineering designs.
1.4 Project Components that Give Rise to Resettlement
This RAP is prepared for the resettlement resulting from the rehabilitation of these 19 existing
roads with a combined length of 7 KMs. These 19 roads along with all the other roads studied
under SUIPP were chosen by community members in 2016 during the planning phase of the
project. The roads were prioritized by the community based on aspects such as connectivity
and proximity to service facilities. Roads that would lead to high numbers of displacement
were dropped from the list and alternatives identified by the community. One of the main
challenges being faced in the rehabilitation of these roads is the lack of properly defined
carriage way and the absence of drainage. The width of the existing roads varies from 2m to
20m and only up to 6m would be renovated for each road (Table 1). The existing road width
would be considered as the right of way. Although this has helped minimize the impact, there
are some structures within the narrowly defined right of way that will be impacted by the
rehabilitation of the roads. Small kiosks and street vendors will also be affected.
-
25
Table 1: Right of Way and Road Width
District
Name No. Road Name
Exis
ting W
idth
Pro
pose
d W
idth
Abdia
ziz 1 1- Agoonta Road 20 6
2 2- UNDP Road 16 6
Bondher
e
3 1- Binti Foodey Road 8-10 6
4 2- Isbitaalka Jarmalka Road 7-10 6
5 3- DaafAlleeley Road 8-10 6
Ham
mar
Jaja
b
6 1- Wiikiyo (Simad) 4-16 4-6
7 2- Xamarjajab Street 7-10 6
8 3-Fartaag 5-7 5-6
Ham
arW
eyn
e
9 1- Ex-post Road 7.5-10 2.5-7.5
10 2- HamarWeyne School Road 2-10 2-6
11 3- Cadeyga Road 3.5-9.5 2-6
Haw
lWa
daa
g 12 1- CeelGarweyne 14-16 6
Shan
gan
i
13 1- Madbacada Road 16 6
14 2- Sharif Abow Road 3-15 3-6
15 3- Ceymiska Road 3-15 3-6
16 4- W. Degmada Road 3-5 3-5
17 5- TodobataniyoTalo Road 3-5 3-5
War
ta
Nab
ada
18 1- GaroonkaMinishibiyo 20 6
19 2- Mire Ali Bubal 20 6
Given the scale of the project and the small width of some of the roads camp sites will be
established in the less populous roads that have large empty spaces. Currently identified
locations are in UNDP road in Abdiaziz district near the district headquarters. The construction
materials will be sourced from currently existing licensed quarry sites in Kaaraan district.
-
26
2 RAP OBJECTIVES AND METHODOLOGY
2.1 Objectives
The key objective of this RAP for SURP Mogadishu Contract B is to provide an agreed plan
for the resettlement and compensation of Project Affected Persons (PAPs). This will ensure
that the Project has net positive impact on the PAPs’ socio-economic conditions and livelihood,
and that PAPs been affected by loss of residential and business structures, and loss of income
are able to improve or at least restore their income, livelihood and standards of living after
resettlement. The plan provides a road map for resettlement and compensation issues in line
with the national laws and the WB policy on involuntary resettlement OP 4.12. The specific
objectives of the RAP are to:
a) Identify project affected persons, eligibility for compensation, and entitlements;
b) Establish valuation method and rates for compensation on losses;
c) Develop a plan for compensation process and establish a grievance redress
mechanism;
d) Implement resettlements measures that in compliance with WB OP 4.12 and Somali
legislations;
e) Provide timely notice and fair compensation, with the ultimate goal that all project-
affected persons would be compensated at least to restore their pre- project living
standard levels;
f) Develop mitigation measures to ensure that the affected people are not worse off as a
result of the project and at least their livelihoods are restored to that of before the
project;
g) Engage PAPs and communities to gain understanding of project objectives and
impacts;
h) Involve PAPs and other stakeholders in developing a plan for compensation for lost
assets;
i) Provide information that will be used to implement the resettlement plan; and
j) Outline institutional arrangements for the implementation of the RAP
-
27
2.2 Methodology
The following methodology was employed to develop the RAP:
1. Review of project documents and secondary sources regarding the project area;
2. Public consultation with communities living around the project areas and consultation
with PAPs to communicate the purpose of the project, explain the process for the
preparation of the RAP and for identifying the main concerns and proposed mitigation
measures. Stakeholders identified by the project were also informed about the project
and their respective roles and responsibilities were clarified; and
3. Focus groups discussions and individual interviews were conducted to generate
qualitative and quantitative data used in the preparation of this report.
-
28
3 POTENTIAL PROJECT IMPACTS
The rehabilitation of the 19 community roads will have more beneficial impacts than negative
impacts both during and after SURP implementation. Poor and marginalized members of the
community and IDPs will benefit from short-term employment opportunities. It is estimated
that approximately 22,000-person days of labor would be generated from employment of
approximately 330 people in the rehabilitation of the targeted community roads. It is also
envisaged that the prospects of local procurement will improve local businesses and further
enhance the local economy. Moreover, the project will support the formation of maintenance
committees within each district to supervise and mobilize the community for necessary
maintenance and repairs. The inclusion of women in the different committees set up for the
implementation of this project will increase their status, empower them and make them part of
the decision makers. Other potential positive impacts include:
• Improved connectivity between and within Mogadishu’s districts and
betterment in access to services;
• Minimization of the likelihood of localized flooding and removal of breeding
grounds for mosquitoes due to installation of roadside drainage;
• Improved safety and security resulting from the installation of solar street lights
and speed calming measures; and
• Curbing of topsoil erosion by both wind and water.
The Project also has potential adverse impacts. Three categories of loses were identified during
the census and asset registration: loss of 74 standalone iron sheet structures that have
encroached upon the right of way, loss of income; and loss of 3 papaya trees. The 74 standalone
iron sheet structures that have encroached upon the RoW comprises of: 48 kiosks, 15 homes,
one kiosk cum home, 8 IDP latrines and 2 madrasas ( Table 2). Loss of income will be
experienced by the 49 kiosks owners and 67 street vendors with portable wooden tables, selling
mixed items including snacks, cigarettes and fizzy drinks. Overall income loss ranges from an
average monthly income of USD 70 to USD 300.
-
29
Table 2: Types and Numbers of Affected Structures
Structure Size
(meters)
Residential Kiosk Mixed Community Total
1.5X1.5 0 0 0 8 8
2 X 2 4 46 0 0 50
2X3 1 0 0 0 1
3X3 4 1 1 0 6
4X2 1 0 0 0 1
4X5 4 1 2 7
4X6 1 0 0 0 1
Total 15 48 1 10 74
Other potential adverse impacts include:
• Temporary restriction of access to the road during construction period;
• Labor influx; and potential security risk due to presence of machinery;
• Flooding during construction;
• Health and safety risk to residents and road users resulting from use of
machinery, waste piles, dust and noise during construction
-
30
4 SOCIO-ECONOMIC BASELINE CONDITIONS
Mogadishu is one of the main economic hubs along the East African coast of the Indian
Ocean. The city’s economy is driven by trade, mostly imports, with Asia. The list of
imports that is supplied to the hinterland of Somalia and in some cases to Ethiopia and
Kenya includes food items, textile and clothing, and spices. The main source of income
for majority of Mogadishu residents is small scale business involving the sale of food
items. Employment in the public sector continues to increase as working conditions and
salary levels become more acceptable to the city’s residents. The construction industry
is booming and there are many new multi-storey commercial buildings and apartments
being built in the city. In Mogadishu women are mostly employed as maids or household
help. However, there continues to be growth in the number of women working in the
public sector. The telecommunication sector along with financial services is also part of
the main drivers of the city’s economy. Traditional public services such as education and
health are dominated by the private sector who have been filling the gaps since the
collapse of Siad Barre’s government more than a quarter of a century ago.
As described in section 1.4 the existing road width is considered as the right of way and
any person with an asset or undertaking economic activities in the right of way is
considered as a PAP. Specifically, any individual who risks losing land, property or
investments made on land or property, livelihoods and/or access to natural and/or
economic resources as a result of a SURP subproject is considered as a PAP. This could
be persons with residential structures, small kiosks/businesses and street vendors. Any
household with an affected individual is categorized as project affected household. Also
considered as project affected are community assets and facilities that are impacted upon
by SURP.
The total number of persons to be affected by SURP is 134 These 134 persons comprise
of 49 kiosks owners, 67 street vendors, 16 temporary home owners, one papaya tree
owner and 2 care takers of a madrasas and IDP latrines. In establishing the demographic
profiles of PAP household heads, an asset inventory and census were carried out in all the
-
31
community roads between August 6, 2018 and October 29, 2018. The cut-off date was
agreed with PAPs to be the date of the census.
4.1 Demographic Profile of PAP Household Heads
4.1.1 Gender
Most of the household heads were identified as being female. Out of the total 134
surveyed, 53 were identified as being male and 81 as being female (Table 3).
Table 3: Gender Disaggregation of Household Heads
Road
Male Female
Head of Household Head of Household
Abdiaziz District
Agoonta 1 2
UNDP 0 0
Bondheere District
Binti Fodey 5 9
Isbitaalka Jarmalka 3 3
Daf Aleeley 5 1
Shangani District
Madbacada 10 3
Sharif Abow 3 9
Ceymiska 0 0
wadada Degmada 2 1
Todobatan Iyo Talo 0 0
Hawlwadaag District
Ceel Garweyne 1 13
Warta Nabada District
Mire Ali Buubal 3 9
Garoonka Minishibiyo 4 8
Hamar Jabjab District
Simad/Simad 5 8
Fartaag 0 3
Hamarjabjab 0 3
Hamar Weyne District
Iskoolka XamarWeyne 2 2
Cadeyga 6 3
EX-Post 3 4
-
32
The highest number of households identified as being female headed were on Ceel
Garweyne Road in Hawlwadaag District where only one out of 14 households were
identified as being headed by a male. One explanation for this is the sub-culture within
the district where women are more empowered and consider themselves to be household
heads. On the contrary, on Madbacada Road in Shangani district, 10 out of 13 households
were identified as being headed by a male. It has been suggested that this is attributable
to the fact that most of the household heads on this road are IDP families in which the
role of a male protector is very clear. Overall within the Somali culture it is considered
the norm to have households as being headed by a male but at the same time women as
having overall responsibility of managing the household.
4.1.2 Age
Based on findings of the census, 35% of the PAP household heads were between the ages
of 29 to 38 years (Table 4). The second largest age group at 28% was between 39 and 48
years. Only three households, 2 located in Warta Nabada district and one in Hamarweyne,
are headed by an under 18 years old and 2 household heads are older than 67 years old.
Table 4: Age Groups of PAP Household Heads
District Name Road Name Under
18
19-28 29-38 39-48 49-58 59-68 Above
68
Abdiaziz
Agoonta 0 0 1 2 0 0 0
UNDP 0 0 0 0 0 0 0
Boondheere Binti Foodey 0 3 8 1 2 0 0
Isbitaalka Jarmalka 0 0 3 3 0 0 0
DaafAlleeley 0 0 4 2 0 0 0
HammarJajab Wiikiyo/Simad 0 0 2 2 7 2 0
IskoolXamarjajab 0 0 0 2 1 0 0
Fartaag 0 0 2 0 1 0 0
HamarWeyne Ex-Post 0 0 2 2 1 2 0
IskoolHamarWeyne 0 0 1 1 1 0 1
Cadeyga 1 1 2 2 3 0 0
HawlWadaag CeelGarweyne 0 4 4 3 2 1 0
Shangani Madbacada 0 1 2 6 2 1 1
Sharif Abow 0 2 6 3 1 0 0
Ceymiska 0 0 0 0 0 0 0
-
33
Degmada 0 1 2 0 0 0 0
TodobataniyoTalo 0 0 0 0 0 0 0
Warta Nabada Garoonka
Minishibiyo
2 0 3 5 1 1 0
Mire Ali Bubal 0 1 5 4 2 0 0
Total 3 13 47 38 24 7 2
4.1.3 Education Level
Nearly 40% of the surveyed households’ heads have no formal education and none has
university education (Figure 3). Compared to the other districts, Bondheere had the
highest number of household heads with no formal education (Annex 5). This reflects on
the districts’ poverty level considered to be the highest in Mogadishu.
Figure 3: Educational Achievements of PAP Household Heads
The numbers of respondent household heads with primary and secondary level of
education were 34 % and 23% respectively. On the overall, the high numbers of
individual household heads with no formal education can be linked to the collapse of the
government and the end of free formal education.
4.1.4 Main Income Source and Average Monthly Income
Educational Level
Non
Primary
secondary
College
-
34
Small business is the main source of income for 90 household heads. Nearly 78% were
street vendors selling mixed items such as snacks, cigarettes, vegetables, and soap. The
second highest source of income declared was manual labor reported by 36 household
heads (Figure 4). 8 household heads mentioned employment by the government as their
main source of income.
Figure 4: Main Source of Income for PAP Household
Heads
The average monthly income of the households’ heads ranges from USD 70-300. The
highest earners are kiosk owners selling mixed items with an average monthly income
of USD 120. The highest average monthly income, USD 300, is declared by members
of an established business community located nearby the vibrant market of Suuqa
Xamar Weyne. A breakdown of main income source and average monthly income for
each road is provided in annex 6.
Small Buisness
Civil Service
Laborers
0 20 40 60 80 100
Main Source of Income
-
35
5 LEGAL AND INSTITUTIONAL FRAMEWORK
The Somali national laws are still being developed and at the moment there are many
parts, including land related matters such as expropriation, which are going through the
parliamentary processes. Notwithstanding this, in the current federal state system the
different levels of government have developed laws that address land issues or reverted
to laws that existed prior to the collapse of the Somali Democratic Republic.
5.1 Somali National Laws
The current supreme law in Somalia is the Provisional Constitution of 2012. The right to
own property and the right to compensation is addressed in Sections 1 and 2 of Article
26 which state:
• Every person has the right to own, use, enjoy, sell, and transfer property;
• The state may compulsorily acquire property only if doing so is in the public
interest;
• Any person whose property has been acquired in the name of public interest has
the right to just compensation from the State as agreed by the parties or decided
by a court.
5.2 Municipality of Mogadishu Laws
Law Number 10 of the Municipality of Mogadishu passed on 17/12/1980 deals with
compensation related issues. Article 15 states any building constructed without following
the municipal due processes will be considered to be illegal. Section 1 of Article16
indicates in the fulfillment of community standards, the Mogadishu Municipality can
order the demolition of illegally constructed structures, whether single structures or whole
estates, once such a decision is reached by the District Councils’ Permanent Committees.
According to Section 2of Article 16the demolition of illegally constructed structures can
take place in the case of one or both of the following reasons:
• In order to vacate the occupied land for purposes other than residential use; and/or
• Standardization of illegally constructed estate in compliance with urban planning
-
36
Section 3, Article 16 states that: Illegally constructed structures cannot be used for the
purpose of acquiring land and its eviction will not lead to compensation. But the
municipal government can compensate the affected persons with residential land once the
following conditions are met: the affected persons resided in the said structure for a period
of not less than eight years; and the property was not constructed for the purpose of
acquiring land.
Section 4, Article 16 states that any compensation resulting from eviction or demolition
of any structure or estates will be provided to the initial residents, and according to
Section 5 the Municipal Government cannot allocate any such land to other parties as
long as the affected persons are present.
Article 17, Section 1 indicates the Mayor of Mogadishu has the authority to order the
eviction of legally occupied land for the purpose of communal use. According to Section
2 of Article 17 any party evicted as a result of section 1 of this Article is entitled to
compensation of value similar to the property, and the same size of land shall be granted
to the affected person. Section 3 of Article 17 indicates that when compensation is
offered, the following will be taken into account: whether the structure is in compliance
with the law concerning land used for permanent or temporary purposes and if it is not
built in accordance with the above law the structure will be considered illegal and the
owner not qualified for compensation. Section 4 of Article 17 states that the process to
be followed in the acquiring of private property for communal purpose shall be in
accordance with Section 12 of law number 28 of the Democratic Republic of Somalia
passed on the 28th of May 1955. Section 5 of Article 17 indicates the expropriation of
property for the purpose of communal use, while taking Section 4 of Article 17 into
account, can only be used for communal purpose and not for private use.
5.3 World Bank Policies
World Bank Policy OP 4.12 - Involuntary Resettlement is designed to mitigate social
and economic impacts that may result from involuntary taking of land or involuntary
-
37
restriction of access to property10. This Policy demands that a resettlement plan be
developed to ensure that displaced persons are:
• Informed about their options and rights;
• Provided with technically and economically feasible resettlement alternatives; and
• Provided with prompt and effective compensation at full replacement costs
This Policy requires that particular attention be paid to the needs of vulnerable groups
such as those below the poverty line, landless, elderly; women and children, indigenous
peoples and ethnic minorities. The following general principles of this Policy are entirely
adopted as principles of this RAP:
• Involuntary resettlement should be avoided where feasible, or minimized while
exploring all viable alternative project designs;
• Where it is not feasible to avoid resettlement, resettlement activities should be
conceived and executed as sustainable development programs that provide
sufficient investment resources to enable the persons displaced by the project to
share in project benefits;
• Displaced persons should be meaningfully consulted and should have
opportunities to participate in planning and implementing resettlement programs;
and
• Displaced persons should be assisted in their efforts to improve their livelihoods
and standards of living or at least to restore them, in real terms, to pre-
displacement levels or to levels prevailing prior to the beginning of the
implementation, whichever is higher.
Under OP/BP 4.12 all PAPs are due for compensation to the extent that they have been
affected by the project.11
10 Policy document are available at https://policies.worldbank.org
11 More details provided in Section 4
-
38
5.4 Gaps between Legal and Institutional Frameworks and Bank
Policies
This section compares the different national laws of Somalia, the Municipality of
Mogadishu with the World Bank’s Policy on Involuntary Resettlement. Specifically
addressed are consultation requirements, eligibility for compensation, valuation method,
grievance redress mechanism, disclosure of information and the timing of compensation
payments (Table 5). For the SURP, the Bank's OP 4.12 will take precedence over any of
these other laws.
Table 5: Gap Between Somali Laws and Bank Policy
Item Somali Law/Policy World Bank
Requirements
Gaps Gap filling
measures
Consultation Mogadishu
Municipality: law
indicates demolition
of illegally
constructed
structures can only
take place once such
a decision is reached
by the District
Councils’ Permanent
Committees.
Puntland’s Laws
make consultation
obligatory and
requires that
meaningful
consultation take
place throughout the
different phases of
the Project.
Somaliland Laws call
Project affected
persons (PAPs)
facing physical or
economic
displacement
persons must be
meaningfully
consulted to
express their
concerns and
discuss ways to
minimize impacts
on affected
communities.
PAPs also should
have opportunities
to participate in
planning and
implementing
resettlement
programs
Somali
consultation
mechanisms
appear to
prioritize
government
agencies, and
may not
adequately
involve project
affected
individuals,
households,
businesses, or
communities
World Bank
OP/BP 4.12
and RAP
guidelines to
be followed
-
39
Item Somali Law/Policy World Bank
Requirements
Gaps Gap filling
measures
for consultation
between the Mayor
and the Permanent
National Planning
Committee prior to
the expropriation of
private land.
Compensation
Eligibility
Somalia’s Provisional
Constitution states
legally owned property
can be acquired for
public interest and that
the property owner will
be due for
compensation. Also,
the case for
Somaliland, Puntland,
and the Mogadishu
Municipality.
Compensation
eligibility by persons
with no formal legal
rights, although with
some variances, is
provided for by
Puntland, Somaliland,
and Mogadishu
Municipality.
Mogadishu: While
wording makes it
discretionary,
Mogadishu’s Municipal
law calls for the
offering of
compensation for
illegally situated
World Bank
recognizes three
classes of PAPs
eligible for
compensation:
1. Those with
formal legal rights
to land (including
customary and
traditional rights
recognized under
the laws of the
country)
2. Those who do not
have formal legal
rights to land at the
time of census, but
have a claim that is
recognizable under
the laws of the
country
3. Those who have
no recognizable
legal right or claim
to the land they are
occupying (e.g.
Those without
legal title to
land, including
squatters and
encroachers,
face less
protection under
Somali laws and
policies
World Bank
OP/BP 4.12
and RAP
guidelines to be
followed
-
40
Item Somali Law/Policy World Bank
Requirements
Gaps Gap filling
measures
property. Any
compensation is also
limited to persons who
have lived in the
location for a period of
not less than 8 years.
Nonetheless, the law
also clearly states that
evicted parties will be
settled in a suitable
land and their eviction
and settlement costs
will be covered by the
local government.
Somaliland:
compensation is only
provided for occupants
of temporary structures.
Affected persons are to
be settled in suitable
land and their eviction
and settlement costs be
paid for by the local
government.
Puntland: no
differentiation between
temporary and
permanent structures
and in both cases the
affected persons are to
be relocated to a
suitable location and
the cost are to be borne
by the local
government.
squatters,
encroachers).
Types of losses to
be compensated
include physical
and economic
displacement and
cover land,
residential or
commercial
structures, and lost
income caused by
temporary or
permanent
economic
displacement
-
41
Item Somali Law/Policy World Bank
Requirements
Gaps Gap filling
measures
Valuation
Method
According to all
reviewed Somali laws
eligible PAPs have a
right to be compensated
with the same value of
the affected property.
Unclear how this value
is set or determined by
government agencies.
Bank requires full
replacement cost for
all lost assets
Government
methods may
not ensure full
replacement
value.
World Bank
OP/BP 4.12
and RAP
guidelines to
be followed
Grievance
Redress
Mechanism
Somali laws mention
the right of the PAP to
file their grievances
with law courts,
however, there is no
clear redress
mechanism
World Bank policy
calls for project-
level grievance
redress mechanism
to cover
resettlement and
related
compensation
matters,
construction phase
grievances and
operations phase
grievances.
Records
Law courts may
be cumbersome,
costly or
intimidating
remedy,
especially for
those with no
formal land
titles, IDPs,
refugees, those
unable to read
or write, etc.
Ideally, should
be used only as
last resort.
World Bank
OP/BP 4.12
and RAP
guidelines to
be followed.
Information
Disclosure
No specific
requirement for
disclosure of
information
World Bank
requires disclosure
by Bank at Info
Shop, and
simultaneous public
disclosure in-
country disclosure
by clients
(Mogadishu and
Garowe
municipalities)
websites or other
Somali
law/policy
provides
insufficient
measures to
protect PAPs
World Bank
OP/BP 4.12
and guidelines
to be followed
-
42
Item Somali Law/Policy World Bank
Requirements
Gaps Gap filling
measures
readily accessible
public disclosure
means available in
their jurisdiction.
Information
disclosed in
language(s)
understood by the
PAPs and other
stakeholders.
Compensation
Payment
Schedule and
Cut-off date
Not addressed in
Somali laws or policies
Cutoff date to be
established at time
of census and asset
survey
Compensation to be
agreed upon with
PAPs and provided
prior to taking over
of assets or
relocation.
Somali
law/policy
provides
insufficient
measures to
protect PAPs
World Bank
OP/BP 4.12
and guidelines
to be followed
-
43
6 ELIGIBILITY AND ENTITLEMENT
As per the RPF the following are eligible for compensation and/assistance regardless of
their legal status:
• Those who have formal legal rights to land and property including renters and
lease holders;
• Those who do not have formal legal rights to land and property including
squatter sand IDPs;
• PAPs in buildings or structures constructed without permits on someone else’s
land or state-owned land, and property;
• Businesses that have legal rights to operate; and
• Businesses that do not have legal rights to operate including roadside vendors
and kiosks.
In compliance with the WB OP4.12 PAPs will be provided with prompt and effective
compensation for losses attributable to the Project. Details from the inventory of loses
along with the different entitlements are provided below.
3 papaya trees that have also encroached upon the RoW will also be removed. In addition
to this, 67 street vendors will suffer temporary loss of access. Compensation levels for all
the structures are full replacement cost derived from actual current market value of the
property as well as labor, and transport costs. The PAPs are also provided with the right
to salvage materials without deduction from their compensation. The 67 street vendors
and 48 Kiosk owners will be provided with cash compensation for their loss of income.
Kiosk owners will suffer permanent loss of income hence will be provided with cash
compensation equivalent to one month of their lost income. The street vendors will suffer
temporary loss of income thus receiving cash compensation worth 50% of their estimated
monthly income. For the restoration of their income both the vendors and kiosk owners
will be offered employment opportunities and PCIP installation and repair training from
the contractors. This arrangement is based on an MoU to be signed between the BRA
and the contractor. In addition to this, the street vendors will be provided with alternative
temporary space to operate from in adjacent streets. The provision of these spaces has
been agreed upon with both the district commissioners and the municipal services. The
-
44
kiosk owners will also have similar opportunity as long as they use tables like the vendors.
Those losing their residential property will be provided with cash to cover 1 month of
rent and transportation to rental residencies. Locations for residential rentals have been
identified in Kaaraan, Yaqshid, and Medina districts. The choice of these 3 locations,
done in consultation with the PAPs, is based on local clan dynamics and availability of
low-cost rental properties. Out of the 19 roads, the two roads where vulnerable people
need to be relocated are Madbacada Road and Sharif Abow Road in Shangani district.
The BRA is currently considering options for a more sustainable solution for housing
these vulnerable households. The construction of these two roads will only begin after a
more permanent alternative housing is made available for the PAPs. The social and
environmental safeguards in the PIU will follow up closely with the BRA and inform the
Bank on the resolution of the problem.
Vulnerable families comprising six orphan children, 4 disabled persons, three severely ill
and one-person past retirement age will receive additional assistance to cover 6 months
of rent. For the community facilities, madrasas will receive cash compensation at full
replacement cost for the entire structure. In addition to this, it has been agreed with the
local elders that learning will continue to take place at two nearby mosques thus
eliminating the need to commute for the learners. The IDP latrines will be moved to
adjacent space, identified by the IDPs, outside the RoW. In order to allow continued use,
the municipal contractors will be instructed to move two latrines at a time. In addition to
replacing the currently eroded iron sheets, a hand wash facility will also be built for the
IDPs. A grievance redress committee and a resettlement committee has been set up in
each of the 7 districts to give the residents and the PAPs a proper channel through which
their concerns can be addressed. During the implementation of this RAP regular
monitoring will be carried out through both internal and external monitors
6.1 Loss of Income
Compensation for income loss resulting from loss of access was calculated based on the
average monthly income declared by the PAP, and where no such declarations were made
average incomes from similar business was used. Compensation to be paid was
determined by considering the number of days it would take to complete the works, in
this case it would take less than a month to complete the works in each road. 67 street
-
45
vendors and 48 Kiosk owners will be provided with cash compensation for their loss of
income in line with the RPF. Kiosk owners will suffer permanent loss of income hence
will be provided with cash compensation equivalent to one month of their lost income.
The street vendors will suffer temporary loss of income thus receiving cash compensation
worth 50% of their estimated monthly income. For the restoration of their income both
the vendors and kiosk owners will be offered employment opportunities and PCIP
installation and repair training from the contractors. This arrangement is based on an
MoU to be signed between the BRA and the contractor. In addition to this, the street
vendors will be provided with alternative temporary space to operate from in adjacent
streets. The provision of these spaces has been agreed upon with both the district
commissioners and the municipal services. The kiosk owners will also have similar
opportunity on condition that they use tables like the vendors. All cash payment will be
made through mobile phones money transfer based on information collected from the
PAPs during census. This is an effective, verifiable, and secure way of cash payment that
is widely used in Mogadishu.
6.2 Loss of Structure
74 temporary standalone iron sheet structures comprised of 48 kiosks, 15 homes, one
kiosk cum home, 8 IDP latrines and 2 Islamic schools will be removed from the RoW.
Compensation levels for these structures were derived from the actual current market
value of the property. The current cost of materials used to construct the property was
established through a survey of nearby hardware stores and labor costs for construction
through a market survey. The PAPs are also provided with the right to salvage materials
without deduction from compensation and relocation assistance to cover moving cost.
The BRA is currently considering options for a more sustainable solution for housing the
PAPS and vulnerable persons losing their residential households. Two types of
community facilities to be affected are 2 Madrasas and 8 IDP toilets. For the Madrasas
cash compensation at full replacement cost for the entire structure. Right to salvage
materials without deduction from the compensation will also be provided. In addition to
this it has been that learning will continue to take place at two nearby mosques that will
not involve commuting for the learners. Compensation for the madras will be provided
to the religious leaders who currently manage their activities. For the IDP latrines, they
-
46
will be reconstructed in adjacent space outside the RoW. In addition to replacing the
currently eroded iron sheet, a hand wash facility will also be built for the IDPs. Two
structure owners that operated as kiosks were not available, compensation amount for
their structure will remain in the compensation account till they make the claim or for a
period of up to one year after which the money will be donated to a community group in
the district. Compensation calculations are provided in annex 2.
6.3 Loss of Trees
The household having its 3 papaya trees removed from the RoW will be provided with
compensation covering 2 years of yield at current market values.
6.4 Vulnerable Groups
Vulnerable families such as orphans and the disabled will be provided with additional
assistance to cover 6 months of rent. Members of these families include six orphan
children, 4 disabled persons, three severely ill and 3 persons past retirement age. Also
included are 28 IDP families and two under 18 household heads. Members of this group
who will be losing access to their sources of income will be provided with a full one
month’s compensation of income instead of the 50% prescribed in the RPF.
-
47
7 CONSULTATION AND PARTICIPATION
Consultations have been an integral part of this Project from the initial phase where the
communities were engaged to identify roads they needed to be renovated in their districts.
These consultations have continued to inform the process till the preparation of this RAP
and will continue to be central in the implementation and monitoring of the Project.
During the preparation of this RAP report multiple consultations were held with the
potential PAPs, community groups, district administration members, and the leadership
of the BRA, attendance sheets are provided in annex 3. Consultation included
communication on the RAP preparation conducted between the 9th and 13th of June 2018.
The PAPs and potential losses were identified during a census and registration of assets
announced on the 5th of July 2018 and carried out between August 6, 2018 and October
29, 2018. The following summarizes key consultation milestones.
7.1 Consultations with BRA Leadership
7 consultations were undertaken with the BRA leadership (Figure 5). The purpose of
these consultations was to inform the leadership on the purpose of the RAP, the process
involved, and the legal requirements as per the Bank’s policies. Discussions during these
consultations mainly focused on the issue of compensation.
Figure 5: Consultations with BRA Leadership
-
48
Initially it was difficult for the leadership to be positive with compensating illegal
potential PAPs, however, after the consultations the leadership pledged its support and
provided its commitment in following the different policies captured in the RAP,
particularly the compensation.
7.2 Consultations with the District Administration
All the district commissioners of the 7 districts were consulted and informed about the
RAP and what its implementation entails (Figure 6). The strict requirement of not
disrupting people’s lives and where it is unavoidable the requirement of compensating
them was explained to the district commissioners.
Figure 6: Consultations with District Administration
Some of the district commissioners felt the RAP implementation would be complicating
the project implementation, nonetheless, they were made aware of the significance of the
RAP implementation and the consequences of not implementing it could lead to halting
of the project.
7.3 Consultations with Community Groups
Representatives from women groups, IDPs, business and religious organizations, elders
and youth representatives from the districts were informed of the RAP process (Figure
7). Nearly all of these community members were involved in the project from the initial
phase of choosing and ranking of roads to be constructed. Their main concern was why
only a half of the roads they had chosen would be constructed and not the entire 2
-
49
kilometers identified during the initial consultations. They also indicated there were too
many consultations that have been taking place since 2016 while there is little progress
in actual commencement of the works.
Figure 7: Consultations with Community Groups
They asked for honesty and wanted to know if the consultation process was being dragged
till all the money designated for the construction would be misappropriated. The
community representatives were informed that consulting them was vital for the
successful implementation of the Project. It was indicated to them the available funding
would only cover construction of one kilometer road length for now and that out of the
17 districts initially studied the works would be starting in 7 districts. They were
informed that the different consultations were being undertaken for different purposes
such as to identify roads to be constructed, to inform the different policy frameworks, to
prepare the RAP and that the consultations would continue throughout the project to
ensure they were informed and took part in the decision-making process.
-
50
7.4 Consultations with Resettlement and Grievance Committees
Mogadishu is a city that has recovered from conflict and many of the wounds are
continuing to heal. Particular attention had to be paid to giving the community a voice in
the implementation of the project. During the community consultations it was agreed that
a resettlement and a grievance redress committee with different ToRs would be
established for each of the 7 districts. During their establishment, members of these
committees, except for the potential PAP representatives, were chosen from groups that
were actively involved in the community (Table 6). The PAP members of these
committees were identified during the potential PAPs consultations considering their
ability to voice PAP’s concerns and gender balance. In order to get full cooperation from
the district offices, the BRA leadership wrote official letters to the district commissioners
asking for their cooperation in the formation of these committees. Establishing the choice
of the PAPs representatives and their specific roles was very crucial. A list of all the GRC
members is provided in annex 4.
Table 6: Composition of Grievance Redress and
Resettlement Committees
Grievance Redress Committee Resettlement Committee
Deputy District Commissioner for Social
Services
District Secretary General
Chairlady women Group Deputy Chairlady women group
District youth representative District youth representative
2 PAP representatives 2 PAP representatives
Religious leader Religious leader
Community elder Community elder
Following the formation of these committees and meetings at each of the districts, all
committee members were invited to the BRA headquarters where they were informed of
their specific roles (Figure 8).
-
51
Figure 8: Grievance Committee Members Meeting
The committee members, particularly the PAP representatives, indicated they viewed the
formation of these committees as being very positive and wished a similar process was
available in the implementation of other development projects especially infrastructure
projects which tended to have high impacts on people’s lives.
7.5 Individual Interviews
Individual PAPs were interviewed to collect socio-economic data. For the purpose of this
study any individual who risked losing land, property or investments made on the right
of way was considered as a PAP. Also included were persons who risked losing their
livelihoods and/or access to natural and/or economic resources. During the gathering of
census data on household heads including their names, contact details, gender, age,
educational level and main source of income was collected and affected assets were also
registered (Figure 9).
-
52
Figure 9: Enumerators Conducting Census
During this process pictures were also taken, and GPS locations of their assets recorded.
A list of the names of household heads, their contact details and type of loss is provided
in Annex 1. Prior to the commencement of the census the community was informed of
the upcoming census and its purpose. These announcements were done at the local
district headquarters and through the community organizations. Posters showing the cut-
off date placed in all of the district’s headquarters. A pilot census was conducted in Expost
Road, Hamarweyne district. This road was chosen because of its characteristics identified
during the scoping study which included safety and presence of different PAP categories.
During the pilot census four key items emerged: 1) the questionnaire was very long, and
it had to be shortened without omitting any important questions; 2) All the PAPs would
not be present at the same time, some of the kiosks and vendors operated in the morning
and others in the evening. This meant it would be necessary to conduct the census at both
times to ensure all potential PAPs were included; 3) In some cases it would not be possible
-
53
to conduct the census because the PAP was engaged in other activities or was not present
at the time. In this situation it was decided that another attempt would be made to have a
face to face interview with the PAP and if it was not possible the census would be
conducted over the phone. In such cases, the identification of the PAP and ownership of
the assets was confirmed through the local community representatives and through the
neighbors. This approach was also utilized during periods of heightened security
concerns in some of the districts such as Hawlwadaag and