resettlement planning document - adb.org...total length of integration - 3.00 km total length of...
TRANSCRIPT
Resettlement Planning Document
This involuntary resettlement due diligence report has been submitted to ADB by the Karnataka Urban Infrastructure Development & Finance Corporation, Bangalore and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.
This involuntary resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 38254-043 March 2016
IND: MFF - North Karnataka Urban Sector Investment Program - Tranche 2 Subproject: Package No-02 HUB 02A
Submitted by
Karnataka Urban Infrastructure Development & Finance Corporation, Bangalore
DUE DILIGENCE REPORT
Document Stage: Due Diligence report ADB Loan No 2638-IND, ADB Assisted KUIDFC-NKUSIP
Package No-02 HUB 02A
Sub-project – Construction of Wet well for SBR Type STP in Hubballi.
March 2016
IND: North Karnataka Urban Sector Investment
Program Package I, Tranche-II
Prepared by
M/s. CDM Smith Pvt. Ltd.
1st floor, IT Park, Hubballi.
The Due Diligence Report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be
preliminary in nature
KARNATAKA URBAN INFRASTRUCTURE DEVELOPMENT AND FINANCE
CORPORATION, LTD. (KUIDFC)
NORTH KARNATAKA URBAN SECTOR INVESTMENT PROGRAM,
Package No-02 HUB 02A (ADB Loan No. IND -2638)
(SITE CONDITION DURING CIVIL WORKS
AT BHAIRIDEVARAKOPPA)
Due Diligence Report for Wet well in Hubballi
Mar 2016
M/s. CDM Smith Pvt. Ltd.
1st floor, IT Park, Hubballi.
( PHOTOS OF WET WELL, AT BHAIRIDEVARAKOPPA VILLAGE,)
Wet well TC at Bhairidevarkoppa, Hubballi
Wet well DG Room at Bhairidevarkoppa, Hubballi
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
ABBREVIATIONS
ADB – Asian Development Bank
APs – Affected Persons
BPL – Below Poverty Line
CBO Community Based Organization
CDP Community Development Plan
CMC City Municipal Corporation
DC Deputy Commissioner
GRC Grievance Redress Committee
HH House Holds
IA Implementing Agency
KUIDFC Karnataka Urban Infrastructure Development and Finance
Corporation
KUWSDB Karnataka Urban Water Supply and Drainage Board
LA Land Acquisition
M&E Monitoring and Evaluation
NGO Non-Government Organization
NOC No Objection Certificate
NKUSIP North Karnataka Urban Sector Investment Program
RF Resettlement Framework
RP Resettlement Plan
WTP Water Treatment Plant
TMC Town Municipal Council
ULB Urban Local Body
WTP Water treatment plant
OHT Over Head tank
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
Table of Contents
Project Background:.................................................................................................................... 1
Need of the Subproject: .............................................................................................................. 1
Location of the project site: ........................................................................................................ 2
Objectives of the Project ............................................................................................................. 2
Scope of the Sub-project ............................................................................................................. 2
Requirement of Due-Diligence Report ....................................................................................... 3
Scope of Land Acquisition and Resettlement ............................................................................. 4
Project Impact and Out come ...................................................................................................... 4
Extent of Impact .......................................................................................................................... 5
Findings....................................................................................................................................... 5
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
Page 1 of 5
Introduction
Project Background:
The Government of Karnataka (GoK) through the Karnataka Urban Infrastructure
Development and Finance Corporation (KUIDFC) has envisaged the North Karnataka Urban
Sector Investment Programme (NKUSIP) under the Asian Development Bank (ADB)
assistance. The goal of the programme is to improve the level, quality and sustainability of
basic urban services in selected Urban Local Bodies (ULB), contributing to improved quality
of life among the urban poor. The objectives of NKUSIP is consistent with Government of
India (GoI) urban reform objectives for the Tenth Plan period, which entails a reform agenda
to initiate the process of
Enhancing the capacity of urban local bodies to assume their functions in accordance
with the 74th constitutional Amendment, with greater sustainability and
accountability.
Strengthening local finances through rationalization and improvement of property tax,
and levy of sufficient user charges.
Ensuring improved maintenance of existing assets; and
Introducing better accounting and Financial Management practices.
KUIDFC was set up as an agency for the speedy planning and implementation of its urban
development programs. The program would comprise the works in Environmental sanitation,
water supply, storm water drainage, poverty alleviation programmes, and non municipal
infrastructure.
Hubballi sub-projects include Sewerage Treatment plant, UGD Sewage network and wet-
wells. The Investment Program is designed to minimize land acquisition and resettlement
impacts.
Need of the Sub-project:
Hubli-Dharwad has an underground drainage system (UGD) since 1950, which covers 35
percent of total road length in Hubli area and 27 percent in Dharwad area. Karnataka Urban
Water Supply and Drainage Board (KUWSDB) have taken up the responsibility of providing
sewerage and sanitation services in these twin cities. Survey results indicate that all
households have access to safe disposal systems (40 percent of households with individual
toilets are connected to UGD while the remaining 60 percent are connected to septic tanks).
Forty eight percent of sample households that do not have access to UGD dispose their
kitchen waste into roadside drains. In absence of a centralized sewage disposal system in the
entire area, the toilets in the individual houses are connected to septic tanks with soak pits.
The public toilets are connected to existing sewerage system if available nearby or to septic
tanks with soak pits. As soak pits are not effective in dispersion of the effluent to subsurface,
wastewater overflow from septic tanks into storm water drains and nallas are common
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
Page 2 of 5
phenomenon. The public conveniences existing in the city are not adequate to serve the slum
dwellers and the economically weaker section of the society.
Sewerage facility will have to be designed to take care of the city municipal council in the
following aspects.
• Providing the sewer network to carry anticipated flows in year 2041.
• Providing sewage treatment plant to take care of year 2041 demand and Located at
` suitable location so that entire sewage can be drained into this plant by gravity
possibly.
Location of the project site:
1) Wet Well site is situated in Byiridevarakoppa Village in Tq Hubballi, Dist- Dharwad.
The site ares is 6320 sq mtr, The site is easily accessible from the Hubballi-Dharwad
City and the distance to Byiridevarakoppa Village is around 01 km .
Objectives of the Project
The main objectives of the project are as follows:
Wet wells are the holding sump for gravity-flow sewer systems. As sewage enters the
wet well and the water level rises, pumps are engaged to pump out the sewage to a
forced main, or the sewage is lifted to a higher grade to continue the gravity flow to
the outlet point. Solid material will accumulate in the bottom of the wet well and
incoming sewage lines.
Lift stations are low points in a gravity-flow sewer system where incoming sewage is
pumped from a well to a higher grade to continue the gravity flow to the treatment
plant. As solid material, such as rags, enters the lift station, buildup will occur on the
bottom of the well and in other components within the station. Solid materials can
often plug or damage pump impellers, so periodic cleaning is required to remove the
solid material from the lift station.
Sewage lift/pump stations are used for pumping wastewater or sewage from a lower
to higher elevation, particularly where the elevation of the source is not sufficient for
gravity flow and/or when the use of gravity conveyance will result in excessive
excavation and higher construction costs.
Sewage lift stations/pump stations may be used as a matter of economics or to
overcome inadequate hydraulic head when it is obvious that no other solution is
practical. For instance, it may be more economical to utilize a sewage pump station to
pump or lift the sewage over a ridge and let it flow by gravity to a sewage treatment
plant, or to elevate sewage to pass through a sewage treatment system by gravity.
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
Page 3 of 5
Key elements of lift/pump stations include a wastewater treatment receiving well
(wet-well), equipped with lift pumps and piping with valves, a junction box, and an
equipment control panel with alarm system.
A properly designed wet well is essential for efficient and trouble-free operation of
the lift/pump station. The purpose of a wet well is to provide a means of allowing
automatic operation of the lift station with a simple control. Use of the wet well for
any other purpose, such as a storage reservoir for sewage, is not recommended. The
wet well should be as small as possible in order to minimize detention time of the
sewage. Should the wastewater remain too long in the wet well, septic action may
occur. Although, the wet well should be large enough so excessive starting and
stopping of the lift station pump will not take place. Lift/pump stations do not usually
include large above ground structures and tend to blend in with their surrounding
environment.
Scope of the Sub-project
The salient features of the subproject are as below:
Pipes laying of UGD Networks
Construction of Wet well
Total Length of Sub main Proposed - 37.31 Km
Total Length of Trunk main - 4.375 Km
Total Length of Integration - 3.00 Km
Total Length of Additional lines - 15.25 Km
Requirement of Due-Diligence Report
Government land has been used for the purpose of construction of Wet well. In this project
there is no involuntary resettlement involved and hence the preparation of RP for this project
is not required. The objective of this Due diligence report (DDR) is to review the Sub project
Land acquisition and resettlement (LAR) impacts if any, based on the detailed design and
propose mitigation measures if, necessary in accordance with ADB’s Involuntary
Resettlement Policy, (IR)1995.
Prior to detailed design, the cadastral maps were examined to understand the ownership of
land. Verification of the cadastral maps was done in the field based on the survey and
measurement.
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
Page 4 of 5
For the construction of wet-well , 6320 Sq mtrs of land was required. Vacant land
measuring 6320 Sq mtrs which was under the ownership of HDMC was earmarked for the
subproject .
The subproject will not entail any permanent land acquisition and resettlement. Site
assessment of the entire proposed areas, where works will be undertaken was taken up.
Based on it: there will be no expected impacts on private/public land, private properties like
housing, shops, commercial buildings, religious and community infrastructure. No negative
impacts on livelihood are envisaged. The proposed area is completely vacant and in
possession of HDMC . There are no Non-Titled Holders in the earmarked land.
Scope of Land Acquisition and Resettlement
As mentioned earlier, the total land requirement for the sub project was 6320 Sq mtrs , for
which Government land was utilized.
Project Impact and Outcome: The expected outcomes of the project are:
Promote sustainable measures to increase potable sewerage line supply to the
population
Improve the environmental Quality of Urban areas through better urban
infrastructure facilities.
Increase the No of Manholes and easy to supply Sewerage water
Improving living conditions of the urban people.
Increase sewerage supply system for future sustainable source developments
Supply and laying of New gravity system sewerage Networks in the city of
Hubballi
Development of sewerage network to maintain the clean city
Development of an appropriate system of indicators for the evaluation of the
performance of sewerage supply systems, also enhancing monitoring of clean city
Development of a Decision Support System tool for the selection of appropriate
measures for tackling the problem of waste water, sewerage with particular
emphasis on regional characteristics and conditions prevailing in certain areas.
UGD Pipe laying and Construction of FAL STP is contribute towards a
sustainable regional development
To improve the current state of the waste water and sewerage system cycle of
Hubballi through improvements in the separate components of the UGD and STP
in the investment program.
North Karnataka Urban Sector Investment Program, Package -I Due Diligence Report for Wet Well site at Hubballi for SBR Type STP.
Page 5 of 5
To reduce the costs of operation and maintenance of the UGD system.
Extent of Impact:
Since the construction of Wet well is being undertaken in Government land ,there is no
negative impact on the community
Findings:
The Subproject will not cause any permanent and/or temporary impacts as government land
is proposed to be used for construction of Wet well. The land earmarked is vacant, no
common property resources are affected.