Resource Offer Commitment Parameters

Structured Market Trials August 23, 2013

Gay AnthonySPP Market Design

Page 2: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters• What are the Parameters?

• How are they used in SMT?

• Parameter Relationships

• How the Parameters are used for Commitment

• Examples

2Gay Anthony

Page 3: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment ParametersWhat are the Parameters?•Time-Related Parameters for Resource Commitment

• Minimum Run Time

• Maximum Run Time

• Minimum Down Time

• Min-To-Off Time

• Sync-To-Min Time

• Hot-to-Cold Time

• Hot-to-Intermediate Time

3Gay Anthony

Page 4: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Commitment Reminders• DA Market, DA RUC, and ID RUC processes use the Current

Operating Plan (COP) for determining if a Resource has satisfied submitted “Commitment Parameters”

• Commit Times are communicated as “Start” or “Stop” notifications • Indicates when SPP expects the resource to be at minimum

• PLEASE NOTE: During SMT, the COP True-Up process is performed after DA RUC and run every two hours throughout an OD• DA Market will be affected by EIS Market commitments

• Example: Resource with Max Run Time of 24 hours but shows as online for a week due COP True Up

» DA Market will decommit the resource

4Gay Anthony

Page 5: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters

5

Markets User Interface

Gay Anthony

Page 6: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters

6

Parameter Relationships

Commit Time

De-Commit TimeMinimum

Run Time

Min-To-Off Time

Minimum Down Time

Commit Time

Sync-To Min Time

Start-up order issued by SPP

Hot-to-Cold Time

Hot-to-Intermediate Time

Commit Time

Commit Time Maximum

Run Time

Gay Anthony

Page 7: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters

7

Minimum Run Time• A Resource’s physical min run time begins when the resource is

synchronized and is the amount of time a resource must remain synchronized. (Sync to Off)

• The MP’s submitted Min Run Time used by the Market should be the physical min run time minus the Sync-to-Min time and Min-to-Off time

• SCUC does NOT consider Sync-to-Min and Min-to-Off when evaluating Min Run Time for commitment purposes

Gay Anthony

Page 8: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters

8

Maximum Run Time• A Resource’s physical max run time begins when the resource is

synchronized but has a limit for how long it can remain synchronized. (Sync to Off)

• The MP’s submitted Max Run Time used by the market should be the physical max run time minus the Sync-to-Min time and Min-to-Off time

• SCUC does NOT consider Sync-to-Min and Min-to-Off when evaluating Max Run Time for commitment purposes

Gay Anthony

Page 9: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters

9

Minimum Down Time• A resource’s physical min down time begins when the resource is

de-synchronized and ends when the resource is physically able to synchronize again. • The MP’s submitted Min Down Time used by the market should be the physical • min down time of the resource. (completely offline)

• SCUC automatically adds Sync-to-Min and Min-to-Off time to the value entered for Min Down Time• This sum represents the “effective” Min Down Time, which is

evaluated by SCUC for commitment purposes

Gay Anthony

Page 10: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Example

Resource Offer Commitment Parameters

10

Resource Aphysical min run time: 5 hoursphysical max run time: 10 hoursphysical min down time: 3 hoursSync-to-Min Time: 1 hourMin-to-Off Time: 15 minutes

Gay Anthony

Page 11: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Example

Resource Offer Commitment Parameters

11

Resource Aphysical min run time: 5 hoursphysical max run time: 10 hoursphysical min down time: 3 hoursSync-to-Min Time: 1 hourMin-to-Off Time: 15 minutes

Markets UI – Resource A (MP-submitted)

Min Run Time - 3:45Max Run Time - 8:45Min Down Time - 1:45Sync-to-Min Time - 1:00Min-to-Off Time - :15

Gay Anthony

Page 12: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment ParametersStart-Up Parameters

•In the Start-Up Offer, MPs submit a hot, intermediate and cold start-up price

•In the Resource Offer, MPs submit two time-related parameters:• Hot-to-Cold Time

• Hot-to-Intermediate Time

•These parameters are used to determine which start-up price is applied

12Gay Anthony

Page 13: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters• Hot-to-Cold Time

• A resource’s physical hot-to-cold Time begins when the resource is de-synchronized and represents the amount of time required before the next synchronization after which a cold start-up offer will apply.

• The MP-submitted Hot-to-Cold Time should be equal to the sum of the physical hot-to-cold time, the Sync-To-Min Time and the Min-To-Off Time

• No programmatic summing of parameters is performed in determining start-up times for applying start-up price

13

Gay Anthony

Page 14: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment Parameters• Hot-to-Intermediate Time

• A resource’s physical hot-to-intermediate Time begins when the resource is de-synchronized and represents the amount of time required before the next synchronization after which an intermediate start-up offer will apply.

• The MP-submitted Hot-to-Intermediate Time should be equal to the sum of the physical Hot-To-Intermediate time, the Sync-To-Min Time and the Min-To-Off Time

• No programmatic summing of parameters is performed in determining start-up times for applying start-up price

14

Gay Anthony

Page 15: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Hot-To-Cold Time Example

If the Resource’s De-Commit Time is 10:00 AM, the Cold Start-Up Offer price would apply for Resource commitments after 8:00 PM.

Resource Offer Commitment Parameters

15

Resource Aphysical hot-to-cold time: 8 hoursSync-to-Min Time: 1 hourMin-to-Off Time: 1 hour

Markets UI – Resource A (MP-submitted)Hot-to-Cold Start-Up Time: 10 hours

Gay Anthony

Page 16: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Hot-To-Intermediate Time Example

If the Resource’s De-Commit Time is 10:00 AM, the Intermediate Start-Up Offer price would apply for Resource commitments between 4:00 PM and 8:00 PM. The Hot Start-Up Offer price would apply for Resource commitments prior to 4:00PM.

Resource Offer Commitment Parameters

16

Resource Aphysical hot-to-intermediate time: 4 hoursSync-to-Min Time: 1 hourMin-to-Off Time: 1 hour

Markets UI – Resource A (MP-submitted)Hot-to-Intermediate Time: 6 hours

Gay Anthony

Page 17: Resource Offer Commitment Parameters Structured Market Trials August 23, 2013 Gay Anthony SPP Market Design

Resource Offer Commitment ParametersSummary•The MP’s submitted Min Run Time should be the Resource’s physical min run time minus the Sync-to-Min time and Min-to-Off time

•The MP’s submitted Max Run Time should be the Resource’s physical max run time minus the Sync-to-Min time and Min-to-Off time

•The MP’s submitted Min Down Time should be equal to the physical min down time.

•The MP’s submitted time-related start-up parameters should be equal to the physical start-up time plus Sync-to-Min and Min-to-Off Time.

• These parameters are used to determine which Start-Up price to use

17Gay Anthony