response-audit report on jalayagnam-vol.2

Upload: nmsusarla999

Post on 02-Apr-2018

266 views

Category:

Documents


7 download

TRANSCRIPT

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    1/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    194

    Response ofIrrigation & Command Area

    Development Department

    to the Draft Performance Audit

    Report on

    Jalayagnam

    Vol. 2

    Irrigation & CAD Department.

    Government of Andhra Pradesh

    July 2012

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    2/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    3/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    196

    27

    Devadula Lift Irrigation Scheme (J.

    Chokka Rao Godavari Lift Irrigation

    Scheme)

    5.10

    28

    Chitravathi Balancing Reservoir (CBR)

    Right Canal (Lingala Canal) and Lift

    Irrigation Scheme

    5.11

    29 Gandikota - CBR Lift Irrigation Scheme 5.12

    30Modernization and Micro Irrigation of

    Pulivendula Branch Canal5.13

    31 Somasila Project 5.14

    32 Somasila Swarnamukhi Link Canal 5.15

    33Telugu Ganga Project (N.T. Rama Rao

    Telugu Ganga Project) 5.16

    34Jyothirao Phule Dummugudem

    Nagarjunasagar Tail Pond5.17

    35Veligonda Project

    (Poola Subbaiah Veligonda Project)5.18

    36Yellampally Project (Sirpadasagar

    Yellampally Project)5.19

    37 Bhupathipalem Reservoir Project 5.20

    38

    Kanthanapally Sujala Sravanthi (P.V.

    Narasimha Rao Kanthapally SujalaSravanthi)

    5.21

    39 Sri Komaram Bheem Project 5.22

    40 Sriramsagar Project - Stage II 5.23

    41Thotapally Barrage Project and

    Gajapathinagaram Branch Canal 5.24

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    4/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    197

    42Vamsadhara Project - Stage-II (Bdooepalli

    Rajagopala Rao Vamsadhara Project)5.25

    43

    Uttarandhra Sujala Sravanthi (Dr. Babu

    Jagajjivan Ram Uttarandhra Sujala

    Sravanthi

    5.26

    44 Venkatanagaram Pumping Scheme 5.27

    45 Project Completion 6

    46 Creation of Irrigation Potential 6.1

    47 Completion of Projects 6.2

    48 Completion of Packages 6.3

    49 Quality Assurance 7

    50 Monitoring 8

    51 Project Monitoring System 8.1

    52 Financial Management 9

    53 Budgeting 9.1

    54Funding under Accelerated Irrigation

    Benefit Programme (AIBP) of GOI9.2

    55 Allocative Pririties 9.3

    56 Impact on State finances 9.4

    57 Conclusion 10

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    5/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    198

    5. PROJECT EXECUTION:

    5.1 Status of the projects

    In the year 2004, the Government of A.P. has given toppriority for irrigation and identified 26 projects to be taken up

    as Prioritized Projects and subsequently the number of

    projects proposed under Jalayagnam increased to 86 Nos

    including 12 Nos Flood Banks & Modernization works at an

    outlay of Rs.185609.35 Crores. Four projects are yet to be

    taken up viz., Uttarandhra Sujala Sravanti, Kanthanapally

    LIS, Modernization of Yeleru System and Modernization of

    Nagavali System.

    The details of 74 Irrigation projects (excluding Flood

    Banks & Modernization works) are as follows:

    REGION

    No. of Irrigation

    projects proposed

    under Jalayagnam

    Estimated cost

    (Rs in crores)

    Coastal 21 30356.11

    Telangana 30 105433.96

    Rayalaseema 23 32656.69

    Total 74 168446.76

    So far 82 projects are grounded. Of these, 13 projects (including

    one more project i.e Ralivagu Project during 2011-12) have been

    completed i.e 6 Nos in Andhra Region, 3 Nos in Rayalaseema

    Region and 4 Nos in Telangana Region. Out of the remaining 69

    ongoing projects, partial IP is created in 22 projects and they are

    at various stages of construction as below.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    6/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    199

    RegionNo. of

    projects

    Financial Progress

    Above 50% Below 50%

    Coastal 20 9 11

    Telangana 27 20 7

    Rayalaseema 22 13 9

    Total 69 42 27

    5.1.1 Non-receipt of clearances

    ISRLIS: There are no railway lines National Highways and Gas

    Pipelines crossing in these schemes.

    RDLIS: There are no National Highways and Gas Pipelines

    crossings. Proposal of 9 railway crossings were submitted to the

    railway authorities for according permission and for balance 3

    Nos, proposals are awaited from the agency.

    JRPDNSS: Proposals for 4 Nos. Railway crossing and One

    National Highway crossing are awaited from the agencies.

    Jawahar Nettempadu:The required amount payable to the South Central Railway

    authorities have since been deposited and the bridges are in

    tender stage.

    Sripada Yellampally Project: In Sripada Yellampally Project,

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    7/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    200

    non receipt of clearances have not affected the project

    completion time. Permissions were obtained from the authorities

    concerned for the electrical poles, Power lines, shifting of towers

    and the same are being shifted simultaneously during the

    execution of the work. The works are under progress without any

    obstruction.

    Pulichintala Project:

    No pending clearances in respect of Pulichintala Project.

    Polavaram Project:

    The audit pointed out that clearances were received,

    involved change in scope of work in Indira Sagar Polavaram

    Project, which resulted in disputes with the contractors and pre-

    closure of works mid way. This is not correct. The reasons for the

    pre-closure are due to slow progress, lack of co-ordination etc.,

    partly attributable to the contractors.

    In respect of ISPP canals, the Irrigation Department is

    constantly pursuing the clearances from HPCL/GAIL authorities.

    However the same are delayed due to the nature of the crossings

    i.e. inflammables are involved and the HPCL/GAIL authorities areconsidering all the safety precautions in designing such a huge

    crossings and hence the delay and there is no laxity on the part

    of the Irrigation Department. Moreover the delay is not at all a

    hindrance to overall progress of the work as the length involved

    in such crossings is very small when compared to the total length

    of the canal.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    8/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    201

    Similarly, the canal is also crossing N.H-5/16 at 10

    locations. Number of permissions is required for National high

    way crossings from the Government of Andhra Pradesh and

    Government of India which is a lengthy process. Action was taken

    to deposit the amount requisitioned by NHAI and the authorities

    have been frequently pursued.

    In addition, there are two railway crossings in package-8 of

    ISLMC for which necessary amounts have been deposited as per

    the requisition of the Railways and the authorities are being

    pursued to expedite the work.

    B.R.R Vamsadhara Project Phase-II of Stage II :

    1). In principle consent of CWC clearance: As per IS Agt of 1962

    AP is entitled to utilize 50% share of Vamsadhara waters.

    Accordingly the proposals for In-Principle Consent from theCentral Water Commission were submitted to Chief Engineer,

    PAO(s), Central Water Commission, New Delhi vide letter dated

    25.8.2005. The replies for remarks communicated by the Central

    Water Commission in this regard were submitted during 02/2006.

    Subsequently, in compliance to the decisions taken during the

    interstate meeting held on 24.04.2006, the Detailed Project

    Report for Vamsadhara Project Phase-II of Stage-II was prepared

    and submitted to the Central Water Commission and Government

    of Orissa in anticipation of In-Principle Consent of CWC on the

    proposals of Vamsadhara Project Phase-II of Stage-II . The

    remarks of CWC on DPR are being attended to .

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    9/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    202

    2). R&R Clearance :

    The proposals for obtaining clearance from Ministry of

    Tribal Affairs regarding the implementation of R&R were

    submitted to the Government. However, the Government have

    remarked to revise the R&R cost proposals in the light of

    G.O.Ms. No. 76, dated 13.4.2006. Since the R&R is being taken

    up phase-wise, the Project authorities have requested the

    Government to recommend the R&R proposals to MOTA. The

    clearance from MOTA is being pursued.

    3).Investment Clearance:

    In respect of Vamsadhara Project Phase-II of Stage-II, the

    clearances involved at various ministries are being pursued.

    Certain clearances like Environmental clearance, Forest

    clearance were obtained from concerned ministries (MOEF).

    Meanwhile , the cost of the project is being met from the state

    Plan funds . On receipt of necessary / balance clearances from

    ministries, investment clearance will be obtained from planning

    commission.

    The main contention of the I&CAD Department, expressed

    in discussions, was that the Department could not afford to wait

    for fulfillment of these pre-requisites, since this would take an

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    10/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    203

    unduly long time. Hence, advance action for tendering ,

    contracting and project execution was initiated, alongside action

    for obtaining of clearances / land acquisition.

    THOTAPALLI BARRAGE PROJECT EPC PACKAGE No-II

    The works of the canal system is likely to have several

    crossings for National Highway, State Highway, Other Roads,

    Railway Lines, HPCL Oil pipelines, GAIL gas pipelines, Water

    pipelines etc., and as such necessary letter to grant the

    permission for crossing those premises shall be issued to the

    respective authorities by the Engineer-in-Charge. However the

    Contractors will have to keep the follow-up and obtain timely

    clearance from the concerned authorities costs of those crossing

    are included in the Bid except the crossings pertaining to railway

    lines.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    11/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    204

    The Government in Memo. No.17873/Major.Irr.1(2)/2006-15,

    Dt:26.06.2007 has issued instructions as Deletion of execution

    of bridge across canal system on National Highway Authority of

    India from the purview of EPC contract. Further it was stated

    that the quantum of work to be deleted from the scope of the

    EPC contract is to be assessed by the State Level Standing

    Committee Constituted vide G.O.Ms.No.144, I&CAD (Reforms)

    Department, Dt: 13.06.2007 and submitted the proposals to the

    Government for approval of effecting the deletion from the EPCAgency and it should be ensured that the contracting agency

    also give their concurrence for the deletion without giving scope

    for raising further disputes. In Package-II there are two NHAI

    Crossings. One on Srikakulam Branch Canal and another on

    Vizianagaram Branch Canal. It is further ensured that the

    contracting agencies also give their concurrence for deletion

    without giving scope for raising further disputes.

    1) The construction of all bridges across the canals falling

    with in the Jurisdiction of National Highway Authority of India

    shall be deleted from the purview of the EPC contracting

    agency.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    12/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    205

    2) The construction of these deleted portion of bridges will

    be taken up by the NHAI and the necessary amounts will be

    deposited by the I & CAD Department in favour of NHAI. As per

    the Government Memo the process of deletion of construction of

    all bridges across canals falling in the jurisdiction of NHAI

    Authority from the purview of contracting agency is in progress.

    After approval of the above proposal, the amount towards NHAI

    crossings will be deducted from the agreement value of the

    agency.

    NHAI policy is to investigate, design, execute, and maintain

    them for specified period including concessionaire profit and

    overhead charges. Further, they are insisting to provide

    additional lanes keeping in view the future needs resulting in

    extra cost, which are not binding on agencies. Thus the cost of

    bridges taken up by NHAI are costing more.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    13/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    206

    5.1.2 Land Acquisition

    Land Acquisition is a major activity and also a major hurdlein construction of Irrigation Projects and in particular when so

    many Irrigation Projects are taken up simultaneously.

    For speeding up the Land Acquisition, the EPC agency will

    prepare Land Plan Schedules and submits to the Department for

    further processing with Revenue authorities. Land Acquisition

    involves Government lands, Patta lands, Endowment lands,

    Forest lands, Court cases etc., and considering all these points,

    the Government for speedy completion of Land Acquisition in

    various projects, 5 posts of Special Collectors, and 44 posts of

    Special Deputy Collectors were created and persons appointed to

    work under Irrigation Department. District and State Level

    Negotiating Committees under the Chairmanship of District

    Collectors and Chief Commissioner of Land Administration (CCLA)

    respectively are also constituted with suitable delegation of

    powers to acquire litigation free land from land owners facilitating

    Consent Awards. The Consent Awards are passed after

    discussions with the land owners, duly paying higher amounts

    than Registration value and the farmers are generally satisfied

    with the compensation given to them. A land bank is also created

    towards compensatory afforestation lands for acquiring Forest

    land expeditiously.

    The Land acquisition process gets delayed due to various

    Court cases. There was also delay due to shortage of sufficient

    staff in the cadre of Deputy Tahsildars, Special Surveyors and

    Officer cadre staff in L.A. Units. To overcome shortage of Field

    Surveyors and other staff, Field staff are being pooled up from

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    14/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    207

    different Units to attend the pending Land Acquisition work

    identified by Project authorities. Special Collectors, LA were

    permitted by the Govt for engaging retired Surveyors on out

    sourcing basis to expedite the L.A. survey. Inspite of above

    delays, the arrangements / efforts made by the Government has

    so far enabled to achieve remarkable land acquisition of about 6

    Lakh acres (upto 03/2012) in a short period of time.

    TABLE-5.4 (in acres)

    REGION

    REQUIRED REQUISITIONED ACQUIRED BALANCE

    COASTAL 253089 204528 142677 110412

    RAYALASEEMA 295891 294591 255465 40426

    TELANGANA 370431 276603 198960 171471

    TOTAL 919411 775722 597102 322309

    Hence the audit remark that the Government failed to fulfill

    its obligations relating to acquisition and handing over of land to

    the contracting agencies in time for speedy execution of work is

    not correct.

    ISRLIS: 5716.97 acres of Non-forest is land required for entire

    Project in which 937.26 acres land already acquired. Balance

    land acquisition is well in advance stage.

    RDLIS: 6192.57 acres of Non-forest is land required for entire

    Project in which 730.35 acres land already acquired. Balance

    land acquisition is well in advance stage.

    The Superintending Engineer, Executive Engineers, Deputy

    Executive Engineers and Section Officers are constantly pursuing

    with the District Collector, Special Collector (LA) and Special

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    15/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    208

    Deputy Collector (LA) for early completion of land acquisition.

    Jawahar Nettempadu: The land acquisition authorities are

    being pursued constantly by the Superintending Engineer and the

    field Engineers for early land acquisition. 85% of the required

    land is acquired and the balance 15% is in differenct stages of

    acquisition.

    Projects in Kadapa:

    The Audit made a comment that the I & CAD Department failed

    to acquire adequate land required for the Projects under

    Jalayagnam on time.

    Various factors influence the process of Land Acquisition. The

    predominant factors affecting the speedy acquisition are as

    under.

    1)As many projects are taken up at a time, large extents of

    land were required for construction of these Projects. The

    sequential activities in L.A process like survey, DN & DD

    etc., cannot be taken up at a time for all these Projects

    with the available Revenue Staff especially experienced

    Surveyors and has to be done simultaneously Project wise.

    2)The land owners in some areas are creating hurdles

    demanding for higher compensation.

    3)In some areas, the land owners are unwilling to part their

    costly gardens and are not even co-operating for peg

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    16/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    209

    marking.

    4)Paucity of funds.

    This Department is constantly bestowing its best efforts in

    co-ordination with Revenue authorities in overcoming the

    hurdles encountered in Land Acquisition.

    Projects in Kurnool:

    I & CAD department have sent the LA proposals to LAO

    immediately after receipt of EPC agencies. The lands were to be

    acquired by LAO after following the procedures of their

    department. Land acquisition generally gets delayed when there

    is dispute between land owners and LAO on quantum of

    compensation. Sometimes, the land owners approach the courts

    for higher compensation. These are unavoidable instances and

    beyond the control of this department. If the works are taken upafter the completion of land acquisition as suggested by Audit,

    the department have to wait up to the completion of land

    acquisition and resolution of court cases and after that the works

    are to be tendered and grounded with rates as on that date. Even

    in this procedure gets delayed and higher rates are inevitable.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    17/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    210

    Table- 5.4

    Sripada Yellampally project - Status of Land Acquisition

    Name of the Project

    Total

    Land

    Required

    (in Acres)

    Land

    Requisitio

    ned

    (in Acres)

    Land

    Acquired

    (in Acres)

    Land to

    be

    acquired

    (in Acres)

    Rema

    rks

    Sripada Yellampally

    Project - Stage I Phase I

    - Barrage

    16085 16085 12592 3493

    Sripada Yellampally

    Project - Gates- - - -

    LA

    Not

    requi

    red

    NTPC LIS (8.50 TMC) 56-03 56-03 56-03 NIL

    Manthini LIS (2.00 TMC) 581 581 133 448

    SYP- Stage II Phase 5430 5430 2732 2698

    1 Ha

    of

    Fores

    t

    Land

    to be

    acqui

    red

    Kaddem LIS (3.00 TMC) 85-24 85 54 31

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    18/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    211

    Canal Network Package

    No I1500 354 35 1465

    Canal Network Package

    No III1646 1646 699 947

    Total: 25383 24237 16301 9082

    As shown above, In Sripada Yellampally Project, total land is

    acquired in the NTPC Lift Scheme and nearly 80 % of the Lands

    are acquired in submergence area of barrage. In rest of the

    Packages nearly 40 % of the land is acquired and the progress

    of work is Proportional.

    In I & CAD Department, earlier to adoption of EPC System, the

    Major Irrigation projects like SriramSagar and Jurala were

    executed under Lump sum Contract system where the Designs

    and Land Acquisition are completed before entrusting the work

    to the Agency. It can be observed that the time taken and cashoverruns are more than that of EPC System in creation of

    Ayacut for the Public.

    Pulichintala Project:

    As against 24,605.83 Acres, 23,350.57 Acres is already

    acquired. Acquisition of balance land is under process. R & Rworks are programmed to be completed by the end of July

    2012.

    Projects in North Coast:

    With regard to the observation of the PAG that the I & CAD

    Department failed to acquire adequate land required for any of

    the projects under Jalayagnam on time and the apprehension

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    19/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    212

    of the PAG that the provision towards land compensation

    already made by the department is likely to increase in light of

    new national land compensation policy to be enacted, the reply

    is as follows:

    The Government of Andhra Pradesh in order to expedite the

    land acquisition process speedily have established several

    Special Deputy Collector units in projects depending upon thesize of the project and the land involved. However the land

    acquisition process is bound to have problems from public in

    any irrigation projects which have to be sorted out amicably.

    Further the land acquisition would also involve disposing off

    court cases related to Land Acquisition which would invariably

    delay the land acquisition process. These hindrances are

    unavoidable and every effort is being made by coordinatingwith the revenue authorities for acquiring the land required for

    the projects.

    Details of Land Acquisition Particulars as of April 2012

    in respect of each Project is submitted as separate

    Statement 5.1.2.

    The total extent of land required for all the above projects

    under the control of this unit is 37,765.55 Acres, the extent of

    land requisitioned is 35,800.18 Acres out of which 31,227.64

    Acres has been acquired and the balance extent of land to be

    acquired is 6,537.91 Acres.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    20/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    213

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    21/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    22/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    215

    response. The Government in 06/2011 had accorded permission

    to go for fresh Tender call for a combined work Spillway, Dam

    and Excavation of foundation of 960 MW Hydro Power House.

    The tenders are floated during 06/2011 and moderate response

    was received. But due to various implications involved in the

    offers received, the Government took a decision to cancel the

    Tenders and to go for fresh Tenders again. The Tenders are

    invited and last date for receipt of tenders is 5.07.2012. There is

    no lapse on the part of Department in selecting a new agency.

    The project is found to be economically viable and technically

    feasible even after considering the revised cost based on SSR

    2010-11.

    5.2.3 Benefit Cost Ratio

    The project is found to be economically viable and technicallyfeasible even after considering the Revised cost based on SSR

    2010-11.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    23/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    216

    5.2.4 Project Approvals & 5.2.5 Environmental clearance

    Polavaram Project:

    (5.2.4 & 5.2.5) The Tenders for the works in Indira Sagar

    Polavaram Project were invited in anticipation of approvals on

    pre-requisite clearances so as to gain time in completion of

    Project. But, unfortunately, unlike other projects, this project has

    faced some unprecedented circumstances after grounding the

    works. To alleviate such hurdles and in accordance with the

    suggestions of Central Empowered Committee, the Government

    took a decision to stop the works from May, 2006 to April 2007

    with an intention to obtain the pre-requisite clearances in a

    smooth atmosphere. In fact, there are so many other constraints

    came across even after allowing to proceed with the works by

    Government in 04/2007. All these impediments are certain, even

    if all these works start only after obtaining all statutory

    clearances. However, the Government is planning to complete

    the project in a time bound manner.

    5.2.6 Clearance from Central Water Commission

    Polavaram Project:

    The Detailed project report has been submitted to Central Water

    Commission (CWC) during 1983 and remarks to the comments

    were attended by the project authorities from time to time at

    CWC. The scrutiny at CWC for most of the important components

    like Hydrology Directorates, FE &SA Directorates, Interstate

    issues are at advance stage and expecting clearance from

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    24/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    25/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    218

    Further the fact that the CWC and planning commission

    accorded the clearances and extended central financial assistance

    under AIBP to this project show that the CWC/MoWR after being

    satisfied that all interstate issues in respect of this project had

    been resolved,accorded Techno-economic clearance. Accordingly

    the planning commission accorded investment clearance to the

    project.

    Godavari Water Disputes Tribunal was formed by

    Government of India to resolve the interstate issues regarding

    construction of Polavaram Project during 1969. After a lot of

    deliberations, between the riparian states an Interstate

    agreement has been entered between the states of Andhra

    Pradesh, Chattisgarh and Orissa on 2.4.1980 paving the way for

    the construction of Polavaram Project with FRL/MWL +150Ft,.

    The Godavari Water Disputes Tribunal gave its final award on

    7.4.1980 called GWDT Award 1980 in which the interstate

    agreement 2.4.1980 made a part. The GWDT in its final order

    stated as follows: The Polavaram Project shall be cleared by the

    CWC as expeditiously as possible for FRL / MWL + 150Ft. The

    design of the dam and its operation schedule shall be left to the

    Central Water Commission, which they shall decide keeping in

    view all the Agreements between the parties, including the

    Agreement of 2nd April, 1980. If there is to be any change in the

    operation schedule as indicated in the agreement of 2nd April,

    1980 it shall be made only after consultation with the States of

    Andhra Pradesh, Madhya Pradesh and Orissa. The design aspects

    shall, however, be left entirely to the Central Water Commission.

    Thus, in accordance to GWDT Award, 1980, all the

    Interstate issues related to the construction of Polavaram Project

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    26/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    27/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    220

    structures on Head works are now in progress and will be

    completed in a time bound manner.

    The Agency has concluded the Agreement in respect of

    ECRF Dam vide Agrt. No.1/2006-07, Dt.11.08.2006 Work

    Order was issued on 07.07.2007 by the SE/ISHW Circle,

    Dowlaiswaram. The decision of preclosing the contract is

    not due to change in designed discharge as stated in Audit.

    The contracting agency started the execution of work in

    07/2007. The contractor has carried out the work upto

    05/2009 and stopped the work suddenly. Department has

    issued several notices for resuming the work and to improve

    the progress of work. In reply the contracting agency, has

    attributed the reasons for slow progress of work i.e., (1) Delay

    in L.A. & R&R (2) Delay in Approval of Designs by CWC etc.,

    showing the above reasons the agency has not resumed the

    work. Hence the Department has taken steps to terminate the

    contract duly issuing notice under clause 61 of APDSS. The

    Government has taken up the issue and had detailed

    discussions with Department as well as with the executing

    agency and finally decided to pre-close the contract and to

    settle their claims amicably and reasonably to avoid legal and

    contractual obligations. Accordingly the Agreement was pre-

    closed vide Superintending Engineer Letter No.DB/ATO.3/W/48

    EPC, Dt.28.08.2009 and the same is ratified by the

    Government vide Govt., Memo. No.22241/2009, Dt.27.08.2009

    & 24676/2009, Dt.23.09.2009 (Minutes of Meeting chaired by

    Honble Chief Minister, Dt.23.09.2009)

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    28/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    221

    In respect of Spillway work the PMF is not main criteria to

    close the work. It is true that the CWC has recommended

    the PMF of 50 lakh cusecs for the design of Spillway during

    2006. The reasons for the pre-closure were partly

    attributable to the agencies. The contention of the audit is

    not correct.

    As stated in performance audit report not even a single

    structure was completed in any of the connectivity works

    even after six years is not correct. In Right side

    connectivities, under package 62 two main structures i.e.,

    OT regulator and P-head regulator and depletion sluice of F-

    saddle dam are in progress. While the OT-regulator and

    depletion sluice are nearing completion. The work on P-head

    regulator is completed to an amount of more than 50%.

    Similarly on left side connectivities under package-67 four

    structures i.e., lock-I, II, III and syphon work taken up.

    While the syphon work is completed the civil works on the

    remaining three locks are nearing completion. Further the

    tunnel work inrespect of Package-63, 64 & 66 are in good

    progress. So the contention of audit that only earth work

    and no structure was done even after six years is not

    correct and hence denied.

    The work of Earth work excavation for foundations of

    ISPHEP is included in the present tenders called for ECRF

    Dam and Spillway of Indira Sagar Polavaram Project vide

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    29/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    222

    Tender notice No. 1/2012-13, Dt. 16.04.2012. The tender is

    under process. The action for commencing of HE project will

    be taken up after commencing the work in ECRF and

    spillway of ISPP.

    Indira Sagar Left Main canal

    Government have accorded administrative approval for

    Rs. 1954.74 Crores vide G.O.Ms.No. 104, Dt: 30.05.2008 forexecution of Left Main Canal works. The Canal runs for a length

    of 181.50 Kms in East Godavari and Visakhapatnam Districts. For

    execution purpose, the Canal is divided into 8 Packages. All the

    works are grounded and works are in progress.Out of 445

    structures, 67 are completed and 83 are in progress. The

    percentage of work done is 52%. The total extent of land

    required is 10540.92 Acres under the Left Main Canal. The extent

    of land so far acquired is 10251.84 Acres (97%).

    Indira Sagar Right Main canal

    Government have accorded administrative approval for Rs.

    2240.688 Crores vide G.O.Ms No.150, Dt: 23.07.2008 for

    execution of Right Main Canal. The Canal runs for a length

    of 174 Kms in West Godavari and Krishna Districts. For

    execution purpose, the canal is divided into 7 Packages. All

    the works are grounded and the works are in progress. Out

    of 248 structures 93 are completed and 22 are in

    progress.The percentage of work done is 64%. The total

    extent of land required for Right Main Canal in 12687.70

    Acres. The extent of land so far acquired is 10749.80 Acres

    (85%). The handing over of Forest land to Department is in

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    30/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    31/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    32/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    225

    attributable to the agencies as well as the reasons not attributable

    to the agencies. The contention of audit that the Government

    hastily awarded Spillway and ECRF works is not at all correct. All

    the required design parameters have been fixed before award of

    contract and incorporated in Bid documents itself. Under EPC

    contract system, the designs after detail survey and investigation

    are to be furnished by the EPC contractor and after thorough

    scrutiny by department the same will be transmitted to CWC for

    scrutiny and approval. The execution of work will be taken up asper approved drawings only. Accordingly the construction

    drawings have been submitted to the Government for PMF of 50

    Lakh cusecs. As already stated, the contracts were preclosed on

    account of slow progress of works due to the reasons attributable

    to the agency as well as other reasons not attributable to the

    agency. After preclosure of the contracts tenders have been called

    for and the tenders received are under process.

    The observation of the audit that the state of Andhra

    Pradesh was deprived of 35 TMC of water out of river

    Krishna to upper states of Karnataka and Maharashtra from

    the date of clearance of Indira Sagar Polavaram Project is

    not correct. As on today the upper states of Karnataka and

    Maharashtra are not utilizing the additional 35 TMC of water

    out of Krishna river from the date of clearances of ISPP.

    Indira Sagar Polavaram Project is a major multi-purpose

    project taken up across river Godavari to utilize water which

    otherwise will go as waste to sea and is very important for

    overall development of the State and during the

    construction of such major projects several unexpected

    hurdles will come in the way. The Government is

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    33/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    34/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    227

    The audit has observed on account of pre- closure of

    contracts of ECRF & Spillway the Government had to admit

    a claim of contracts for Rs.19.39 Crores for the reasons

    outside the ambit of the agreements. Most of the claims of

    the contractors admitted by the Government are pertaining

    to the infrastructure works like approach roads,

    procurement of dumping areas, deposits paid by the

    contractors to AP Transco authorities etc., which can be

    made use of by the new executing agencies to be fixed.These available infrastructure works are specifically

    mentioned in the bid document and the prospective bidders

    are requested to quote their bid prices keeping availability

    of these infrastructure facilities also in view. Hence, the

    contention of audit is not correct.

    The provisions of the agreement under clause 16 & 17 of

    G.C.C and Clause 50 of APSS stipulates the contractingagencies for taking Insurance policies to cover all types of

    risks including natural calamities. This will safe guard the

    exchequer against any type of risk. So, the contracting

    agencies have taken the Insurance policies in terms of

    provisions of agreement, from the start date to safe guard

    the works, plants and materials, equipment, property,

    personnel against possible risks like the act of God or

    natural calamities or accidents.

    The respective firms have paid the Insurance premiums as

    given below.

    1. Spillway : Rs.2,77,80,330

    2. ECRF Dam: Rs.5,11,83,412

    Total Rs.7,89,14,742

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    35/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    228

    As this is a major project involving lot of critical operations viz.,

    exploration of foundations, blasting operation, usage of heavy

    earth moving equipment in the hilly terrain, river surveys,

    soundings, Geo-physical surveys, Hydrographic survey even

    during floods which involves lot of risk to men, material,

    equipment etc., insurance policy is necessary.

    The contracting agencies also faced several difficulties

    due to natural calamities like floods, cyclones, manmade

    disturbances through local agitations and also accidents caused

    during operation of heavy machinery. Thus the insurance has

    covered several risks uncovered during execution of work.

    As the subsisting contract of both Spillway and Earth

    cum Rock fill Dam was pre closed, both the firms have claimed for

    the reimbursement of insurance paid. However the State Level

    Standing Committee admitted the claim to a tune of Rs. 4.0Crores and Rs. 2.39 Crores for Earth cum Rock fill Dam and

    Spillway respectively duly deducting proportionate amount

    towards work done.

    Survey and Investigation 6.98 Crores: There is a

    Provision of Rs. 10.00 Crores towards Survey Preparation

    of L.P. Schedules, Investigation and designs etc., After

    concluding the Agreement the contracting agency has

    attended to the investigation, alignment proposals,

    submission of L.P. Schedules and design proposals for

    GapI,II,&III. Based on the proposals submitted by the

    Agency (1) Land acquisition was taken up & completed (2)

    Alignment proposals in gap gb, gg & gb were finalized (3)

    The detailed designs for Gap I,(gd) Gap (gg), Gap III (gb)

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    36/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    37/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    230

    Agreement, 2004 initiated in hastiness was poorly sequenced is

    not correct. Generally execution of projects and obtaining

    clearances will go on simultaneously, as the Government is very

    keen in completing the pending irrigation projects on top priority

    under Jalayagnam. Government of several such projects, court

    intervention were encountered in respect of this project only.

    The contention of the audit, that the project works are

    to be taken up only after getting all clearances, completing all

    investigation and designs for construction/ working drawings;completion of L.A. process; completion of R&R etc., is not at all

    correct. Even by such arrangement, the escalation of the project

    cost on account of time taken for completion all the formalities

    like clearances, L.A, R&R, Designs etc., will be much more than

    the present system where delays are in respect of certain portion

    of works only where problems are encountered.

    Generally the canal & distributory system works arescattered and takes more time for completion than the head

    works which are located at one place. In respect of canals, even

    though substantial portion of works are completed, it will take

    quite a long time to complete balance works especially

    problematic. Stretches held up due to local problem, ryots

    objections, court cases etc., The works pertaining to balance

    distributory system are to be taken up. If the canal works which

    are scattered are not taken up early as there works will take more

    time for completion in the light of real time problems like L.A

    issues, Ryots objections, court case etc., which cannot be avoided

    unlike head works which are concentrated works. When large

    projects like Indira Sagar Polavaram Project are taken up, it is not

    possible to take up all the components of the projects in such a

    way that are all completed on the same day in whatever way one

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    38/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    231

    plans as the problem which were encountered during execution

    cannot anticipated. Further, while taking up such large projects,

    the works shall be taken up such that the funds requirement such

    as with Budget provision that can be made available.

    All the project components were taken up almost

    simultaneously with an intention to complete them simultaneously

    to reap the early benefits. But on account of certain unexpected

    problems, there are certain delays in execution of some

    components and every effort shall be made to complete theprojects at the earliest by sorting out the problems.

    5.2.11 Compromise / Reduction in specifications

    Polavaram Project:

    As per clause 2.5 of Section-2, general specifications of

    Agreement the contractor have to submit the designs duly

    carrying out investigations and it shall be as per relevant I.S.

    Codes, since the drawings enclosed in the bid documents are only

    tentative. Accordingly the contracting agency has carried out the

    investigations and submitted designs as per the relevant I.S.

    Codes. The designs submitted by the contracting Agency verified

    with reference to the I.S. Codes and approved by the Chief

    Engineer, Central Designs Organization, Hyderabad. Hence

    question of lowering of specifications does not arise. Regarding

    cost adjustment as per clause 38 and 39 of G.C.C. the contractor

    bound to execute all the supplemental works that are found

    essential, incidental and inevitable during execution of main work

    at no extra cost to the employer. This being a EPC contract

    system the contracting agency has to carry out the investigation,

    soil exploration works etc., based on this prepare and submit the

    drawings for approval. Hence, variations in the quantities

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    39/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    232

    excess/less may take place. Therefore one can not see only one

    side of the coin i.e. decrease in quantities. The other side of the

    coin is some items such as shotcreting, construction of portals,

    temporary and permanent supports etc are increased beyond the

    provisions made in the estimate. The resultant savings on account

    of lowering of specifications of any item of work in deviation from

    the basic parameters will be assessed by referring to the State

    Level Standing Committee constituted by the Government and

    approval of the Government will be obtained. Such savings asapproved by Government will accrue to the Government. Hence

    the observations of audit that the lowering of specification without

    cost adjustment resulted in undue benefit of Rs 45.53 Crores to

    the construction agency is not correct and hence denied. When

    supplemental works are being executed without any cost to the

    employer on single source responsibility, the other work in which

    there is some saving in it have to be considered as costadjustment is not correct.

    5.2.12 Land acquisition

    Polavaram Project:

    Total land required for working areas of ISP Project was almost

    acquired.. The total land under submission of the ISP project in

    three Districts 1) KHAMMAM, 2) WEST GODAVARI & 3)

    EASTGODAVARI IS 88366.84 Acres out of it 45150.35 Acres of

    land which is more than 50% total land required has been

    acquired. Therefore, there is no shortfall in acquiring the land

    required. The balance Land acquisition will be done as per

    programme of the project .The total estimated cost towards Land

    acquisition is Rs 3405.98 Crores only but not Rs. 8724.81 Crores

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    40/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    233

    as reported. Out of it Rs 441.941 Crores were spent, on Forest

    Land only 43216.49 Acres of Non Forest Land is yet to be

    acquired. The Forest Land affected due to submergence of ISP

    project is 8961.04 Acres and the process of handing forest land is

    in progress. Total Land required for land to land Compensation

    under R& R is 40,330.54Acres out of it 2,800.93Acres has been

    acquired and balance land 37,529.61 Acres will be acquired as per

    Scheduled programme.

    5.2.13 Rehabilitation and resettlement

    Polavaram Project:

    R & R for Project Affected Families is under progress as per

    construction programme of ISP Project. The draft action plan

    for all the 29 habitations in West Godavari district, 43 habitations

    in East Godavari District has been submitted and approved. In

    respect of Khammam District, the draft action plan for about 60villages has been prepared and for remaining villages, it is under

    preparation. All the villages in Khammam District are categorized

    under phase 3 and 4 R&R in these villages will be completed One

    year before actual submersion takes place.

    West Godavari District:- Out of 478.12 acres of land

    required for house sites, 280.29 acres of land has already

    been acquired and the remaining extent has to be acquired

    for the villages which are categorized under phase 2 and 3

    and which are not urgent. Out of 3582.50 Acres of land

    required for land to land, 1208.37 acres of land was already

    acquired and the remaining extent is falling in the villages

    which are categorized under phase 2 and 3 only. Total No.

    of Housing Units to be constructed is 4139 Nos. out of which

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    41/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    234

    352 Housing Units were completed and 1259 Units are

    under Progress. Out of total PAFs of 4363., 490 were

    Rehabilitated.

    The infrastructure works for all the 7 villages falling in 1st phase

    have been completed already and the remaining villages fall under

    2nd and 3rd phase. The Socio Economic survey for all the

    prioritized 1st phase villages has already been completed.

    Rs.106.560 Crores has been spent so far on R&R in West Godavari

    District

    East Godavari District:- The infrastructure facilities for the

    1st phase villages has been completed and the same for

    remaining villages which are in 2nd, 3rd phases is under

    progress. The land for 4 prioritized villages has already been

    acquired. The Below Poverty Line housing units to a tune of

    498 nos in 1st phase have been completed and remaining

    units which are categorized under phase 2 and 3 are under

    various stages. Total No. of Housing Units to be constructed

    is 4409 Nos. out of which 498 Housing Units are completed

    and 119 Units are under Progress. Out of total PAFs of

    4643, 481 PAFs were rehabilitated. Rs. 25.763 Crores has

    been spent so far on R&R.

    Khammam District:- All the villages are categorized under

    phases 3 and 4 which are affected under submersion only.

    The R&R in this district will be completed 1 year before

    actual inundation takes place. Total No. of Housing Units to

    be constructed is 33708 Nos. As the process of Land

    Acquisition is still under progress these housing units were

    not yet completed. Total PAFs are 33708. Rs. 6.178 Crores

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    42/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    235

    has been spent so far in Khammam District. Therefore the

    R&R implementation is as per programmed action plan.

    The draft plan for most of the villages pertaining to ISPP

    was prepared. Every effort is being made to complete the R&R for

    all the affected villages as per action plan. In respect of

    Chattisgarh and Orissa, there will not be any submersion of lands

    and villages due to proposed construction of protective

    embankments in the territories of Orissa and Chattisgarh, The

    submergence issue of ISPP in Chattisgarh and Odisha was settledlong back in terms of Interstate agreement Dt 2-4-1980 and

    GWDT award. The contention of audit that the submergence issue

    with Chattisgarh and Odisha were not sorted out and led to

    prolonged litigation is not at all correct. The observation of audit

    that there have been consistent lethargy towards R&R is not at all

    correct. As implementation of R&R involves coordination and

    carrying out works from different departments duly consultingaffected people. The R&R work will be completed as per the

    action plan. The implementation of R&R for Gandikota has been

    recommended as this particular village Gandikota was a

    rehabilitation village which is again affecting under PLIS sub lifts.

    5.2.14 Coordination with Statutory organizations:

    Polavaram Project:

    In respect of ISLMC, as per clause 27 @ page No.110 of the

    agreement, the E.P.C. agency has to follow up with the

    Department for obtaining clearance and take-up the

    construction.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    43/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    236

    However as per the policy decision taken by the NHAI, the

    grant of permission for way leave facility (Canal crossings) will be

    accorded by NHAI provided the Government of Andhra Pradesh

    foot the bill for the entire scope of work involved and to be carried

    out as deposit work.

    After protracted correspondence and obtaining information

    from NHAI, Government vide G.O.Rt.No.103, dated 13.02.2012

    accorded permission for payment of Planning and estimatecharges and amount has been paid to NHAI in 03/2012.

    Permission is awaited.

    Planning and estimate charges have been paid to NHAI in

    03/2012. Permission is awaited.

    In respect of ISRMC Package II

    1) HPCL & GAIL Crossing in between Km 19.200 and km 19.750 ofRMC

    The laying of new pipe lines of HPCL/ GAIL at the point of

    crossing of RMC is the most suitable option, among the various

    studies made, as suggested by HPCL / GAIL authorities. Further it

    is submitted that as per agreement condition 27 of Special

    conditions of contract, it is the responsibility of the contractor to

    obtain clearance for HPCL oil pipe lines and GAIL gas pipe lines

    from the concerned authorities and cost of the crossing of pipe

    lines are included in the bid. As per agreement condition 24 of

    other special conditions (Appendix OS), if the canal system is

    crossing HPCL oil pipe lines, GAIL pipe lines or any other pipe lines

    the contractor shall provide suitable crossing in consultation with

    the authorities concerned after obtaining the approval either by

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    44/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    237

    himself or getting them executed by the concerned authorities as

    a deposit work duly depositing the requisite amount to HPCL/

    GAIL authorities. The Engineer-in-Charge will help in processing

    the proposals to the authorities concerned to obtain their

    permission. The cost of such crossings shall be deemed to be

    included in the contract price.

    In view of the above facts it is submitted that the

    department have taken necessary action from time to time to

    obtain the permission from GAIL & HPCL authorities. Several

    times the Prl.Secretary to the Govt., (Projects), I&CAD dept,

    Hyderabad and the Engineer-in- Chief, ISPP, Dowlaiswaram

    reviewed the status of permission. Because of technical difficulties

    only, as per site conditions, new pipe lines are inevitable and

    because of the efforts made by the department with proper

    coordination with GAIL& HPCL authorities present status of

    permission could be obtained. The agency is requested to deposit

    the amount and as soon as the amount paid by the agency work

    will be completed .There is no financial burden on the Govt., since

    the cost of crossings has to be paid by the agency within the

    contract price.

    2) Electrical lines in RMC Package-II

    As per agreement conditions electrical lines coming in the

    alignment of canal shall be shifted by the EPC agency at their own

    cost within the contract price. At many places the EPC agency

    shifted the electrical lines at their own cost duly paying requisite

    charges to APEPDCL.

    From KM 35.000 to Km 37.000 of RMC, 33 KV and 11 KV

    lines are existing in the canal alignment. The Department pursued

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    45/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    238

    the matter with APEPDCL. The APEPDCL authorities informed to

    pay an amount of Rs.20.47 lakhs towards shifting of 11 KV and 33

    KV lines. The agency was requested to deposit the amount. The

    department have taken necessary action from time to time for

    shifting of electrical lines. Now action is being taken by the

    Department to shift the electrical lines in between Km 35.000 to

    37.000 within the contract price only.

    ISRMC Package No.IV :-

    GAIL pipe line is crossing ISRMC at Km 103.700. After pursuing

    the matter with the GAIL authorities, an amount of Rs.1.05 lakhs

    was deposited to the GAIL authorities for preparation of estimate.

    At the time of preparing detailed estimate, certain field

    information was sought for by the GAIL authorities. While

    gathering the required information at field, ryoths of Pedavegi (V)

    were objected the survey works and not allowed into the fields

    duly arguing that the area is covered under stay orders of the

    Honble High Court, Hyderabad in W.P.No.27352/2007. Hence, it

    is not possible to furnish the required information to the GAIL

    authorities.

    5.2.15 Unforeseen ground conditions

    uncertainties involved in bidding:

    Polavaram Project:

    Polavaram Project canals works are still under progress.

    Only 50 to 60% works are completed and the lining works

    under these excavated canals are under progress. The

    original alignment of these canals is going through Black

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    46/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    239

    Cotton soils in some reaches. In these reaches CNS

    (Cohesive Non Swelling) treatment below the lining course

    was provided in IBM estimates to reduce the effect of

    swelling and shrinkage of the soils. After entrusting the

    works to the EPC contractors and after detailed survey by

    the agency, it was decided to take the alignment in cutting

    only rather than partial cutting or embankment and the

    revised alignment was approved in place of original

    alignment proposed in IBM estimates to safeguard the canalsystem. Because of these reasons there were some

    changes in the alignments of canals proposed earlier. As

    the alignment of canals were changed, the length of the

    canal, quantity of earth work excavation and structures on

    the canal in each package work are increased heavily. It is

    well known that the above changes caused heavy

    expenditure and the contractors represented Governmentfor additional payments and these proposals were rejected

    by the Government. In as much as 52% of the lining works

    are completed the reaches where CNS treatment is required

    is not fully identified. As the above fact is very clear, it is

    not rational to say that the amount provided in IBM

    estimate towards CNS treatment is fully paid to the

    contractor.

    In respect of Packages 63 & 64, the tunnels were provided

    with concrete lining thickness for 900 mm in the estimate as

    per approved drawings by the CE/CDO/Hyderabad based on

    detailed soil exploration/ bore hole data. Lining thickness of

    900 mm was provided due to lack of data on investigations

    is not correct. Now as per detailed design calculation based

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    47/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    240

    on IS Codes and rock strata available in the field, concrete

    lining thickness of 800 mm was finalized and approved by

    the CE/CDO, Hyderabad. The agency proposals to provide

    concrete lining thickness of 500 mm is insufficient, hence

    not accepted. However, the savings due to reduction of

    lining thickness in Package 63&64 have been worked out

    and recovery proposals to this effect have been submitted

    to the Government. Hence the contention of audit is not

    correct.

    In respect of ISRMC Package-3, the work Earth Work

    Excavation, formation of embankment and construction of CM

    & CD works including investigation, designing and estimation of

    ISRMC from Km 38.199 to Km 71.500 was awarded on EPC

    basis to M/s. Hindustan Construction Company Ltd., Mumbai

    vide Agreement No. 11 SE /2004-2005 Dt:23-10-2004 for anagreed value of Rs.321.30 crores at 3% excess over ECV of

    Rs.311.94 Crores. The work was scheduled to be completed

    within 24 months i.e 22.10.2006. EOT was sanctioned up to

    30.062012.

    The Right main canal is carrying huge discharge of 391 Cumecs

    the alignment running in full cutting in higher contour is

    considered instead of those having embankment reaches to avoid

    formation of breaches and R4 alignment is approved . Infact the

    ryots have filed a W.P.in the Hon`ble High court vide

    W.P.No.452/06 which was dismissed on 07/4/2006 uphelding the

    decision of the CE, CDO for approving the R4 alignment. The only

    alignment approved by the dept, was R4 alignment keeping in

    view to minimize embankment and to avoid risk of breaching. As

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    48/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    241

    per EPC norms agency has to execute the work as per approved

    alignment only. Hence the agencys claim for Rs.58.49 Crores is

    not untenable and hence rejected. The contention of audit all

    these issues have cropped up only because of lack of detailed

    survey and investigation and unforeseen soil condition is not

    correct. Under EPC contract all the items of works from

    investigation, designs, execution and completion of works

    including O&M falls under single source responsibility of the EPC

    contractor.

    5.2.16 Approval of designs:

    Polavaram Project:

    Status on approval of Designs as on 31.05.2012.

    Total No.of structures : 717

    No.of Designs submitted by the Agency : 558

    No.of Designs approved : 414

    No.of Designs under scrutiny at O/o

    CE/CDO & CE/ISPP: 15

    No.of Designs returned at different stages

    of scrutiny i.e, from O/o ENC/ISPP and O/oCE/CDO with major remarks and for want

    of further field data etc., and still pending

    with Agency for re submission

    : 129

    No.of Designs yet to be submitted by the

    agency: 159

    From the above status report it is clear that out of 303 Designs

    yet to be approved, only 15 Designs are under scrutiny with

    Department i.e., at O/o ENC/ISPP and O/o CE/CDO, and the rest

    i.e., 288 Designs are pending with Agency, of which 129 Designs

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    49/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    242

    are pending for resubmission after attending the remarks and

    supplementing further data called for, and 159 Designs are

    pending for first submission itself till to date.

    5.2.17 Third Party Supervisions:

    Polavaram Project:

    The TPQC package 17 consists of Head works 62 to 67

    packages. The QMP for package 62, 63 & 64 are with the

    department and the same will be transmitted to the TPQC

    Agency. For the remaining Packages the department isconstantly pursuing with the Agencies. As soon as received from

    the Agencies it will be transmitted to the TPQC Agency for

    review.

    At present no works are in progress in Package No.5, 6 &

    7 of ISRMC which comes under the purview of Package No.20 of

    3rd Party Quality Control. The works are held up for want of land

    due to delay in land acquisition due to Ryoths objections and the

    stay orders of Honble High Court. In spite of constant

    persuasion through Advocate General of Andhra Pradesh, the

    matter in the court is still pending.

    The civil works in Packages 5 & 6 are stopped since

    06/2009 and continuing as on date except two months in

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    50/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    243

    Package No.5, where as the works of Package No.7 are

    continued up to March 2010. Even though the works are idle in

    Package No.5&6, the agency carried out the Q.C/Q.A operations

    in Package No.7 where the works are continued up to March. At

    the same time, the agency carried out non destructive tests in

    the completed reaches in Package No.5 & 6 in the idle period. As

    Package No.7 is one of the component of Package No.20, an

    amount of Rs.1.17 Crs was paid to the agency towards

    supervision charges at Rs.12,98,573 per month for 9 Months i.e,from July 2009 to March 2010. Beyond March 2010, the services

    of agency are continued expecting the land is being handed over

    and the court cases are cleared. However, the payments were

    paid by the concerned Quality Control Authorities.

    The Government have accorded permission vide

    G.O.Ms.No.29 dt:04.06.2011 to continue the services of the 3rd

    Party Quality Control agency with selection staff duly paying the

    remuneration of Rs.1.57 Lakhs Month to M/s Engineering Staff

    College of India, Hyderabad for Package No.20 of ISRMC till the

    package works are resumed.

    Accordingly the supervision charges are being paid to the

    agency from 01.07.2010 onwards for selection staff only.

    5.2.18 Stoppage of works midway:

    Polavaram Project:

    There is a provision of Rs.10.00 Crores towards Survey,

    preparation of L.P. Schedules, Investigation and designs etc.,

    After concluding the Agreement the contracting agency has

    attended to the Investigation alignment proposals & L.A.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    51/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    244

    proposals including submission of L.P. schedules and designs of

    proposals Gap I, II & III Based on the proposals submitted by

    the Agency (1) Land Acquisition was taken up & completed (2)

    Alignment proposals were finalized (3) Based on the data

    furnished by the agency the Central Water Commission has

    issued working drawings (estimate purpose) for the Earth-Cum-

    Rock Fill Dam for Gap I&II. Based on the work done by the

    agency an amount of Rs.4.11 Crores paid to the agency against

    Rs.10.00 Crores claimed by the agency. However in the balanceestimate a provision of Rs.5.00 Crores was made available

    towards balance Investigation & Designs etc, to the second

    agency. Hence there will not be any extra payment to the

    second agency.

    5.2.19

    Unwarranted owning of contracting agencies burden:

    Polavaram Project:

    The audit has observed that one of the objectives of EPC

    turnkey system of contracting was to eliminate the need for

    revision of project cost. It also observed that the department

    owned the burden of the contracting agencies in several aspects

    and listed two packages (Package-67 & 62) of ISPP out of 12

    cases reported.

    The above observation of the audit are not correct. The

    objective of the EPC system of contracting is not to have cost

    over run pertaining to the works coming with in the scope of the

    contract. Any works which are not contingent and fall out side of

    the scope of the contract are to be treated as extra item and

    payment is to be made to this extra item as per clause 39.3.1 of

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    52/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    245

    GCC of agreement. The audit is calling out the extra items which

    fall out side the scope of the contract as the burden of

    contracting agencies and pointing out that the department is

    owing such burden of contracting agencies is not correct. The

    details of additional item which fall out side the scope of

    contract in respect of 62 & 67 of ISPP are furnished below.

    Package: 62: As stated in performance Audit report i.e., the

    action of Government was unwarranted and resulted inunavoidable burden to the Government and undue benefit to the

    contractor is not correct. Essentiality of providing depletion

    sluices to saddle dam E & F was finalized only after Design

    experts decision during field visit to Polavaram Project in

    December-2007. It is a unforeseen item and out side the scope

    of original contract. As per agreement conditions 39.3.1

    whenever additional item not contingent to main work and outside the scope of original contract are to be entrusted to the

    original contractor, on entrustment of such items and price to be

    paid shall be referred to a committee constituted by

    Government for final decision. Accordingly, the depletion sluices

    item was referred to state level standing Committee for

    decision. After elaborate discussions only, additional item was

    recommended to the Government, by the State Level Standing

    Committee. Hence as per agreement condition 39.3.1 it is

    genuine to consider as an additional item. The observation of

    audit that even such additional item which fall out side the

    scope of the contract clearly as burden of agencies is not at all

    correct and amounts to violation of agreement condition.

    Package: 67: The construction of flood gate was not included

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    53/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    246

    in the original scope of work, basic parameters and also in the

    agreement. Only after detailed investigation, the necessity of

    the flood gate structure was identified and recommended to the

    State Level Standing Committee to take up the work as an

    additional item of work not contingent to original work under

    clause 39.3.1 of the GCC of contract. As per the state level

    standing committee recommendations, the Government

    accepted and accorded permission to construct the flood gate

    structure. The financial aspect is still under examination.Hence the contention of the audit that this item of work is

    burden of agency is baseless incorrect and denied.

    5.2.20 Payment Schedules Preparation and Revisions:

    Polavaram Project:

    The observation of the audit that in Indira Sagar Polavaram

    Project, the payment schedules are improperly fixed and the

    revision was not based on the detailed estimates is not correct.

    The details are furnished below:

    The work ISRMC Package No.VI i.e., Earth work

    excavation, formation embankment and construction of

    CM&CD works including investigation, designing and

    estimation of ISRMC from KM133.800 to KM 156.500

    was entrusted to M/S Progressive constructions ltd,

    Hyderabad vide Agreement No.8SE/2004-2005 dated

    20-10-2004 on EPC turnkey system.

    Out of total length 24.078KMs, the land handed over to

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    54/322

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    55/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    248

    sanctioned by the Engineer-in-Chief Vide ref.

    No.2/2004-05, Dt.7-10-2004 for Rs.248.44 Crores. The

    work was awarded to M/s Patel-Soma J.V, Mumbai Vide

    Agt. No. 9 SE/04-05, Dt.21-10-2004 for Rs.241.50

    Crores.

    Out of the total length of 14.80 kms.(from km.0.000 to

    km14.800 of ISRMC), 12.80 Kms length of Earth work

    excavation and 11.725 kms length of CC lining and 22Nos of

    CM & CD structures were almost completed out of 25 Nos and3 Nos (2 OTs and 1 Surplus escape) yet to be started and the

    balance 2.00 kms work was held up due to Forest Area and

    R&R problem.

    The detailed estimates submitted by the agency as per

    the approval Hydraulic particulars, the payment schedule

    works out to 41.80% for Earth Work Excavation, 31.50% for

    CC Lining, and 26.70% for CM & CD Works against thepercentages made in the payment schedules in original

    agreement. The Physical percentage of work done, so far is

    87.85% EWE, 78.30% CC Lining, 84.60% CM & CD Works.

    The Land required for the work has been handed over to

    the agency in stages as and when the land acquisition

    authorities hand over the land to the irrigation department.

    The agency commenced the Earth work, CC lining,

    Construction of CM & CD Works simultaneously in the reaches

    where the land is available. So, the contention of the audit that

    the items like Earth work Excavation was taken up as front

    items and the construction of CM & CD works as backend items

    is not correct. Hence the contention of the audit that huge

    front loading for the items taken up in the beginning is not

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    56/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    249

    correct about 90% of work is already completed.

    Even though the original payment schedule was fixed

    erroneously, the contractor executed all the three components

    simultaneously and there by there is no front loading

    payments made to the contractor.

    There is no excess amount made to the agency. Further,

    the payment schedule is being revised for the balance work tobe done by the agency as per the actual quantities.

    The work "Earth Work Excavation, formation of

    embankment and construction of CM & CD works

    including investigation, designing and estimation of

    ISRMC from Km 38.199 to Km 71.500 " was awarded on

    EPC Turnkey basis to M/s. Hindustan Construction

    Company Ltd., Mumbai. vide Agreement No. 11 SE /2004-2005 Dt.: 23-10-2004 for an agreed value of Rs.

    321.30 crore..

    As per the agreement conditions 41.2.1 of cost

    control in the agreement the total work specified under EPC

    turn Key contract is divided into several components of work to

    facilitate payments component wise. The work of the each of

    the components are specified as percentage of the total bid

    price under Annexure-II, Schedule of payments. In EPC

    contract system there is no change in total amount to be paid

    to the contractor. The payment schedule was fixed based on

    the approximate quantities in the IBM. After conducting

    detailed investigation the agency has submitted details for

    earth work quantities only.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    57/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    250

    Originally the canal Earth Work Quantities was arrived

    based on tentatively alignment in which canal is running in

    balance depth of cutting. The present alignment approved by

    Department duly keeping the FSL almost below ground level.

    Due to this the Earth work Excavation in cutting has been

    increased abnormally due to deep cuts in alignment. Further

    due to reduction in length of canal (2.589Kms.) the quantity of

    lining work is decreased. Hence the main components such as

    Earth work, lining have been changed and the firm hassubmitted the revised payment schedule.

    As per the approved HPs the earth work quantity is increased

    to from 1.14 Crores cum. To 2.40 Crores cum. Hence the

    revision of payment schedule is necessitated. Hence the

    Government have approved the revised payment schedule to

    regulate the payment as per the agreement clause 41.2.1

    Vol.I, Part-A, conditions of contract.

    Even the alignment is running in higher contour

    (deep cut portions) the lining quantity is not increased as the

    perimeter of lining proposed is constant throughout reach. The

    logic of the audit that the lining quantity shall increase if

    earthwork quantity increases is not correct as the length of

    canal is decreased and depth of cutting is only increased.

    The payment schedule contemplated in Agreement and revised

    payment schedule submitted by the agency and revised

    payment schedule approved by the Govt. is as follows.

    Sl

    NoDescription

    Earth work

    excavationLining

    CM&CD

    worksTotal

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    58/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    251

    1Percentage as per

    agreement20.91 41.61 37.48 100

    2

    Amount as per

    agreement

    (Rs Crores)

    67.18 133.69 120.43 321.30

    3Restriction to

    agreement value

    97.39

    (30.31)

    101.20

    (31.50)

    122.71

    (38.19)

    321.30

    (100%)

    4

    Percentage as per

    revised payment

    schedule asapproved by Govt.

    30.31 31.50 38.19 100%

    The payment schedules are revised considering the quantities

    of earth work, Lining and structures and approved by the Govt

    memo no.6818/Maj.Irrgn.1(2)/2006.. Hence the contention of

    the audit that the corresponding lining work is not increased is

    not correct as the values of the components Earth work and

    Structures are infact increases as per actuals and restricted to

    the agreement value . as shown in the above table. The lining

    amount as per the agreement of Rs 131.587Crores has been

    decreased to Rs 101.20Crores due to decrease in length. But

    due to proportionate restriction to agreement value, the

    percentage lining component is reduced from 41.61% to

    38.19%.There is nothing absurd in the calculations. Thus thecontention of the audit that the revision of payment schedule

    resulted in advance/ premature payment on front end items of

    Rs 30.21Cr is not correct.

    The work "Earth Work Excavation, formation

    embankment and construction of CM & CD works includi

    investigation, designing and estimation of ISRMC from Km 71.5

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    59/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    252

    to Km 105.100" was awarded on EPC basis to M/s. Jayaprakas

    Gayati JV, Hyderabad vide Agreement No. 10 SE / 2004-20

    Dt.: 23-10-2004 for an agreed value of Rs. 301.30 crore at

    tender discount of 5.71% of ECV of Rs. 319.53 Crore. The wo

    was scheduled to be completed within 24 months i.e 22.10.200

    EOT was sanctioned up to 30.06.2012.

    Due to change in the alignment of canal from balance dep

    of cutting to FSL cutting & deep cutting, the length of the canalincreased from 33.600 Kms to 36.065 Kms. Due to increase

    length of canal, and running the canal in full cutting there

    increase in Earth work, lining and CM&CD Works.

    The revised payment schedule is as follows considering

    detailed quantities for Earth work , Lining. The cost of CM and

    CD works, is arrived based on the cost as per sanctionedestimate.

    Sl

    No

    Description Earth work

    excavation

    Lining CM&CD

    works

    Total

    1 Percentage as per

    agreement17.079 36.99 45.931 100

    2 Amount as per

    agreement(Rs Lakhs)

    5145.90 11145.09 13839.01 30130

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    60/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    253

    3 Amount as per Revised

    payment schedule of

    approved alignment for36.065km in lakhs with

    estimate rates

    10677 11183 14100 35960

    4 Proportionate restriction

    to agreement value8946 9370 11814 30130

    5 Percentage as per revised

    payment schedule29.69% 31.10% 39.21% 100%

    The payment schedules are revised considering the

    quantities of earth work, Lining and structures and approved

    by the Government in Govt.Memo No.6818/Maj.Irrig.I

    (2)/2006-1 dt 22-3-2006. Hence the contention of the audit

    that the corresponding lining work is not increased is not

    correct as the values of the components are infact increased as

    per actuals and restricted to the agreement value on prorata

    basis, as shown in the above table. The lining amount as per

    the agreement of Rs 11145.09 lakhs has been increased to Rs

    11183.00 lakhs due to increase in length. But due to

    proportionate restriction to agreement value, the percentage

    lining component is reduced from 36.99% to 31.10%.There is

    nothing absurd in the calculations. Thus the contention of the

    audit that the revision of payment schedule resulted inadvance/ premature payment on front end items of Rs 38.00

    Cr is not correct.

    In respect of package 66 of ISPP, initially the agency

    has started the work to a small extent in the non forest

    area where the land was made available to work since

    the major part of the work was involved in the Forest

    area. The IBM values were arrived as per the

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    61/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    254

    preliminary investigation only.

    The total earth work quantity provided in the IBM

    estimate as 1,88,598 Cum (i.e, soil quantity as1,05,533 Cum

    and Hard Rock quantity as 83,065 cum)

    During actual execution, the total quantity arrived

    at 3,06,425 Cum (i.e, soil quantity as 7765 cum and Hard

    Rock as 2,98,660 Cum) based on the approved H.Ps and

    detailed estimate prepared and thus the value of the

    component is also increased. The payment of Rs.3.33 croreswas made as per the payment schedule provided in the

    original agreement. Out of which an amount of Rs.3.06 crores

    was made towards earth work excavation and the remaining of

    Rs.0.27 crores was made towards investigation work.

    Considering the actual quantities of work involved,

    there was no excess or front load payment made to the

    contractor. Considering the actual quantities as per designs,the Revised payment schedule was prepared and the same

    was approved by the competent authority. The forest land was

    also handed over to the agency recently and the execution of

    Tunnel work is in progress. Now the payment is being allowed

    as per the approved revised payment schedule only.

    Therefore the contention in the audit report that the contractor

    benefited is not correct.

    In Indira Sagar Polavaram Project, the payment

    schedules of all the packages will be revised duly

    including the O&M component and the payments will be

    regulated.

    The agreements were concluded for package 63 & 64

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    62/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    255

    vide Agreement No.64/2004-05, Dt.09.03.2005 and

    Agreement No.65/2004-05, D5.11.03.2005. Accordingly

    works were grounded. As it is the first time for

    grounding of works on EPC System the bills were made

    as per the payment schedule appended in the

    agreement. Due to stoppage of works by the

    Government from dated 04.05.2006 to 11.05.2007 and

    for want of forest clearance till 10/2010 the payments

    which were made based on the payment schedule in theagreement of Package 63 & 64 could not be regularized.

    However, soon after resumption of the works by

    1/2011(package63) &12/2010(package64) the Revised

    Payment Schedule was prepared and got approved

    based on the approved drawings and payments were

    regularized in the running account bills of the package

    63 and Package 64 by 7/2011. The payments wouldhave regularized, if the work had been under progress.

    Because stoppage of works by the Government and non-

    receipt forest clearance from the MoEF the regularization

    of payment have delayed. Hence interest forgone by

    the Department and unduly benefited the contracting

    agency for a period of 5 years was Rs.7.45 crores is not

    correct.

    The procedure adopted by the audit in assessing

    Rs.32.93 Crores as premature excess payment is not

    rational and incorrect. When actual quantities as per

    execution are to be considered in finding out the

    entitlement of the contractor for payment, it is

    obligatory to consider the relevant revised payment

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    63/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    256

    schedule based on actual quantities of execution to

    ascertain the correctness of payments made. The audit

    while considering the actual quantities of execution

    taken it for granted the payment schedule in the

    agreement as granted and assessed the premature

    excess payment as Rs. 32.93 Crores in correctly. Also

    structures quantity was considered as 150000 cum as

    against the probable quantities of 98000 cum.

    Further, in the IBM estimate provisions for earthwork,

    lining, and CM& CD works are 52.14%, 21.36%, and

    26.50% respectively. As per schedule II of agreement

    percentage of earthwork, lining and CM& CD works are

    33.51%, 44.49% and 22%. The percentages components

    approved are much lower than the IBM provisions and

    payments were made at lesser percentages than theeligible percentage (as per IBM). As the payments for

    earthwork were being made at lower percentages and it

    was considered to revise the payment schedule after

    finalisation of actual quantities based on detail designs and

    estimates.

    As per the detailed estimate quantities the %

    components of earth work, lining and structures are

    worked out as 55.55%, 25.79% and 18.66% respectively.

    Even from the actual quantities view, percentage

    component approved in respect of the earthwork and

    lining are advantageous to the department.

    Had the payments were made with reference to

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    64/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    257

    quantities, more component would have been paid in respect

    of earthwork and in case of lining premature excess payment

    does not arise since lining is to be done after the earthwork is

    completed and lining was completed to the extent of earthwork

    completed.

    However, it is submitted that required component schedule

    was approved as per hydraulic particulars but at present the

    matter is Sub judice. Necessary action will be taken toimplement the revised payment schedule with detail

    quantities.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    65/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    258

    5.2.21 Payments for price variations

    Polavaram Project:

    Inrespect of ISLMC package 2, as per Clause 37.2:37.3 and

    38.1 of E.P.C, the work awarded on a lump sum contract on

    EPC Turnkey basis, the contractor will be paid a firm contract

    price for completion of all works as specified under the scope

    of the work.

    CNS soil treatment is one of the operations involved in the

    finished item of work of lining, it can not be treated separately for

    inclusion or deletion of the work.

    However, the percentage of fuel factor was worked out as

    per IBM is 12.003% and percentage of fuel factor worked out as

    per actual quantities of value of work is 12.554% (copy enclosed).The percentage of fuel factor considered for payment is in

    accordance with the IBM is less than the actual percentage of fuel

    factor to be paid to the contractor. Hence, the remarks of the

    performance audit stating that an amount of Rs. 68.10 Lakhs

    excess paid to the contractor is not correct

    Inrespect of ISRMC package 2, the fuel component in the

    work was worked out based on the state level standing

    committee recommendation and IBM estimate quantities.

    The percentage of fuel component as per IBM estimate

    worked out to 12.20%

    For assessing the fuel component, if the actual execution

    quantities were considered i.e., quantities as per approved H.Ps

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.2

    66/322

    Go To ContentsPerformance Audit Report on Jalayagnam

    259

    the percentage of fuel component works out to 14.12 %, which is

    higher than approved value of 12.20%. In order to assess the fuel

    component, either IBM estimate (as being done in all other works

    across the State) or revised estimate with actual quantities shall

    be considered. If the provision of gravel backing was not to be

    considered as it was not executed, then the increased quantities of

    earth work, concrete and other items as per approved drawings

    and as per actual execution should be considered.

    As the % component with reference to IBM es