response-audit report on jalayagnam-vol.2
TRANSCRIPT
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
1/322
Go To ContentsPerformance Audit Report on Jalayagnam
194
Response ofIrrigation & Command Area
Development Department
to the Draft Performance Audit
Report on
Jalayagnam
Vol. 2
Irrigation & CAD Department.
Government of Andhra Pradesh
July 2012
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
2/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
3/322
Go To ContentsPerformance Audit Report on Jalayagnam
196
27
Devadula Lift Irrigation Scheme (J.
Chokka Rao Godavari Lift Irrigation
Scheme)
5.10
28
Chitravathi Balancing Reservoir (CBR)
Right Canal (Lingala Canal) and Lift
Irrigation Scheme
5.11
29 Gandikota - CBR Lift Irrigation Scheme 5.12
30Modernization and Micro Irrigation of
Pulivendula Branch Canal5.13
31 Somasila Project 5.14
32 Somasila Swarnamukhi Link Canal 5.15
33Telugu Ganga Project (N.T. Rama Rao
Telugu Ganga Project) 5.16
34Jyothirao Phule Dummugudem
Nagarjunasagar Tail Pond5.17
35Veligonda Project
(Poola Subbaiah Veligonda Project)5.18
36Yellampally Project (Sirpadasagar
Yellampally Project)5.19
37 Bhupathipalem Reservoir Project 5.20
38
Kanthanapally Sujala Sravanthi (P.V.
Narasimha Rao Kanthapally SujalaSravanthi)
5.21
39 Sri Komaram Bheem Project 5.22
40 Sriramsagar Project - Stage II 5.23
41Thotapally Barrage Project and
Gajapathinagaram Branch Canal 5.24
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
4/322
Go To ContentsPerformance Audit Report on Jalayagnam
197
42Vamsadhara Project - Stage-II (Bdooepalli
Rajagopala Rao Vamsadhara Project)5.25
43
Uttarandhra Sujala Sravanthi (Dr. Babu
Jagajjivan Ram Uttarandhra Sujala
Sravanthi
5.26
44 Venkatanagaram Pumping Scheme 5.27
45 Project Completion 6
46 Creation of Irrigation Potential 6.1
47 Completion of Projects 6.2
48 Completion of Packages 6.3
49 Quality Assurance 7
50 Monitoring 8
51 Project Monitoring System 8.1
52 Financial Management 9
53 Budgeting 9.1
54Funding under Accelerated Irrigation
Benefit Programme (AIBP) of GOI9.2
55 Allocative Pririties 9.3
56 Impact on State finances 9.4
57 Conclusion 10
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
5/322
Go To ContentsPerformance Audit Report on Jalayagnam
198
5. PROJECT EXECUTION:
5.1 Status of the projects
In the year 2004, the Government of A.P. has given toppriority for irrigation and identified 26 projects to be taken up
as Prioritized Projects and subsequently the number of
projects proposed under Jalayagnam increased to 86 Nos
including 12 Nos Flood Banks & Modernization works at an
outlay of Rs.185609.35 Crores. Four projects are yet to be
taken up viz., Uttarandhra Sujala Sravanti, Kanthanapally
LIS, Modernization of Yeleru System and Modernization of
Nagavali System.
The details of 74 Irrigation projects (excluding Flood
Banks & Modernization works) are as follows:
REGION
No. of Irrigation
projects proposed
under Jalayagnam
Estimated cost
(Rs in crores)
Coastal 21 30356.11
Telangana 30 105433.96
Rayalaseema 23 32656.69
Total 74 168446.76
So far 82 projects are grounded. Of these, 13 projects (including
one more project i.e Ralivagu Project during 2011-12) have been
completed i.e 6 Nos in Andhra Region, 3 Nos in Rayalaseema
Region and 4 Nos in Telangana Region. Out of the remaining 69
ongoing projects, partial IP is created in 22 projects and they are
at various stages of construction as below.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
6/322
Go To ContentsPerformance Audit Report on Jalayagnam
199
RegionNo. of
projects
Financial Progress
Above 50% Below 50%
Coastal 20 9 11
Telangana 27 20 7
Rayalaseema 22 13 9
Total 69 42 27
5.1.1 Non-receipt of clearances
ISRLIS: There are no railway lines National Highways and Gas
Pipelines crossing in these schemes.
RDLIS: There are no National Highways and Gas Pipelines
crossings. Proposal of 9 railway crossings were submitted to the
railway authorities for according permission and for balance 3
Nos, proposals are awaited from the agency.
JRPDNSS: Proposals for 4 Nos. Railway crossing and One
National Highway crossing are awaited from the agencies.
Jawahar Nettempadu:The required amount payable to the South Central Railway
authorities have since been deposited and the bridges are in
tender stage.
Sripada Yellampally Project: In Sripada Yellampally Project,
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
7/322
Go To ContentsPerformance Audit Report on Jalayagnam
200
non receipt of clearances have not affected the project
completion time. Permissions were obtained from the authorities
concerned for the electrical poles, Power lines, shifting of towers
and the same are being shifted simultaneously during the
execution of the work. The works are under progress without any
obstruction.
Pulichintala Project:
No pending clearances in respect of Pulichintala Project.
Polavaram Project:
The audit pointed out that clearances were received,
involved change in scope of work in Indira Sagar Polavaram
Project, which resulted in disputes with the contractors and pre-
closure of works mid way. This is not correct. The reasons for the
pre-closure are due to slow progress, lack of co-ordination etc.,
partly attributable to the contractors.
In respect of ISPP canals, the Irrigation Department is
constantly pursuing the clearances from HPCL/GAIL authorities.
However the same are delayed due to the nature of the crossings
i.e. inflammables are involved and the HPCL/GAIL authorities areconsidering all the safety precautions in designing such a huge
crossings and hence the delay and there is no laxity on the part
of the Irrigation Department. Moreover the delay is not at all a
hindrance to overall progress of the work as the length involved
in such crossings is very small when compared to the total length
of the canal.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
8/322
Go To ContentsPerformance Audit Report on Jalayagnam
201
Similarly, the canal is also crossing N.H-5/16 at 10
locations. Number of permissions is required for National high
way crossings from the Government of Andhra Pradesh and
Government of India which is a lengthy process. Action was taken
to deposit the amount requisitioned by NHAI and the authorities
have been frequently pursued.
In addition, there are two railway crossings in package-8 of
ISLMC for which necessary amounts have been deposited as per
the requisition of the Railways and the authorities are being
pursued to expedite the work.
B.R.R Vamsadhara Project Phase-II of Stage II :
1). In principle consent of CWC clearance: As per IS Agt of 1962
AP is entitled to utilize 50% share of Vamsadhara waters.
Accordingly the proposals for In-Principle Consent from theCentral Water Commission were submitted to Chief Engineer,
PAO(s), Central Water Commission, New Delhi vide letter dated
25.8.2005. The replies for remarks communicated by the Central
Water Commission in this regard were submitted during 02/2006.
Subsequently, in compliance to the decisions taken during the
interstate meeting held on 24.04.2006, the Detailed Project
Report for Vamsadhara Project Phase-II of Stage-II was prepared
and submitted to the Central Water Commission and Government
of Orissa in anticipation of In-Principle Consent of CWC on the
proposals of Vamsadhara Project Phase-II of Stage-II . The
remarks of CWC on DPR are being attended to .
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
9/322
Go To ContentsPerformance Audit Report on Jalayagnam
202
2). R&R Clearance :
The proposals for obtaining clearance from Ministry of
Tribal Affairs regarding the implementation of R&R were
submitted to the Government. However, the Government have
remarked to revise the R&R cost proposals in the light of
G.O.Ms. No. 76, dated 13.4.2006. Since the R&R is being taken
up phase-wise, the Project authorities have requested the
Government to recommend the R&R proposals to MOTA. The
clearance from MOTA is being pursued.
3).Investment Clearance:
In respect of Vamsadhara Project Phase-II of Stage-II, the
clearances involved at various ministries are being pursued.
Certain clearances like Environmental clearance, Forest
clearance were obtained from concerned ministries (MOEF).
Meanwhile , the cost of the project is being met from the state
Plan funds . On receipt of necessary / balance clearances from
ministries, investment clearance will be obtained from planning
commission.
The main contention of the I&CAD Department, expressed
in discussions, was that the Department could not afford to wait
for fulfillment of these pre-requisites, since this would take an
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
10/322
Go To ContentsPerformance Audit Report on Jalayagnam
203
unduly long time. Hence, advance action for tendering ,
contracting and project execution was initiated, alongside action
for obtaining of clearances / land acquisition.
THOTAPALLI BARRAGE PROJECT EPC PACKAGE No-II
The works of the canal system is likely to have several
crossings for National Highway, State Highway, Other Roads,
Railway Lines, HPCL Oil pipelines, GAIL gas pipelines, Water
pipelines etc., and as such necessary letter to grant the
permission for crossing those premises shall be issued to the
respective authorities by the Engineer-in-Charge. However the
Contractors will have to keep the follow-up and obtain timely
clearance from the concerned authorities costs of those crossing
are included in the Bid except the crossings pertaining to railway
lines.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
11/322
Go To ContentsPerformance Audit Report on Jalayagnam
204
The Government in Memo. No.17873/Major.Irr.1(2)/2006-15,
Dt:26.06.2007 has issued instructions as Deletion of execution
of bridge across canal system on National Highway Authority of
India from the purview of EPC contract. Further it was stated
that the quantum of work to be deleted from the scope of the
EPC contract is to be assessed by the State Level Standing
Committee Constituted vide G.O.Ms.No.144, I&CAD (Reforms)
Department, Dt: 13.06.2007 and submitted the proposals to the
Government for approval of effecting the deletion from the EPCAgency and it should be ensured that the contracting agency
also give their concurrence for the deletion without giving scope
for raising further disputes. In Package-II there are two NHAI
Crossings. One on Srikakulam Branch Canal and another on
Vizianagaram Branch Canal. It is further ensured that the
contracting agencies also give their concurrence for deletion
without giving scope for raising further disputes.
1) The construction of all bridges across the canals falling
with in the Jurisdiction of National Highway Authority of India
shall be deleted from the purview of the EPC contracting
agency.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
12/322
Go To ContentsPerformance Audit Report on Jalayagnam
205
2) The construction of these deleted portion of bridges will
be taken up by the NHAI and the necessary amounts will be
deposited by the I & CAD Department in favour of NHAI. As per
the Government Memo the process of deletion of construction of
all bridges across canals falling in the jurisdiction of NHAI
Authority from the purview of contracting agency is in progress.
After approval of the above proposal, the amount towards NHAI
crossings will be deducted from the agreement value of the
agency.
NHAI policy is to investigate, design, execute, and maintain
them for specified period including concessionaire profit and
overhead charges. Further, they are insisting to provide
additional lanes keeping in view the future needs resulting in
extra cost, which are not binding on agencies. Thus the cost of
bridges taken up by NHAI are costing more.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
13/322
Go To ContentsPerformance Audit Report on Jalayagnam
206
5.1.2 Land Acquisition
Land Acquisition is a major activity and also a major hurdlein construction of Irrigation Projects and in particular when so
many Irrigation Projects are taken up simultaneously.
For speeding up the Land Acquisition, the EPC agency will
prepare Land Plan Schedules and submits to the Department for
further processing with Revenue authorities. Land Acquisition
involves Government lands, Patta lands, Endowment lands,
Forest lands, Court cases etc., and considering all these points,
the Government for speedy completion of Land Acquisition in
various projects, 5 posts of Special Collectors, and 44 posts of
Special Deputy Collectors were created and persons appointed to
work under Irrigation Department. District and State Level
Negotiating Committees under the Chairmanship of District
Collectors and Chief Commissioner of Land Administration (CCLA)
respectively are also constituted with suitable delegation of
powers to acquire litigation free land from land owners facilitating
Consent Awards. The Consent Awards are passed after
discussions with the land owners, duly paying higher amounts
than Registration value and the farmers are generally satisfied
with the compensation given to them. A land bank is also created
towards compensatory afforestation lands for acquiring Forest
land expeditiously.
The Land acquisition process gets delayed due to various
Court cases. There was also delay due to shortage of sufficient
staff in the cadre of Deputy Tahsildars, Special Surveyors and
Officer cadre staff in L.A. Units. To overcome shortage of Field
Surveyors and other staff, Field staff are being pooled up from
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
14/322
Go To ContentsPerformance Audit Report on Jalayagnam
207
different Units to attend the pending Land Acquisition work
identified by Project authorities. Special Collectors, LA were
permitted by the Govt for engaging retired Surveyors on out
sourcing basis to expedite the L.A. survey. Inspite of above
delays, the arrangements / efforts made by the Government has
so far enabled to achieve remarkable land acquisition of about 6
Lakh acres (upto 03/2012) in a short period of time.
TABLE-5.4 (in acres)
REGION
REQUIRED REQUISITIONED ACQUIRED BALANCE
COASTAL 253089 204528 142677 110412
RAYALASEEMA 295891 294591 255465 40426
TELANGANA 370431 276603 198960 171471
TOTAL 919411 775722 597102 322309
Hence the audit remark that the Government failed to fulfill
its obligations relating to acquisition and handing over of land to
the contracting agencies in time for speedy execution of work is
not correct.
ISRLIS: 5716.97 acres of Non-forest is land required for entire
Project in which 937.26 acres land already acquired. Balance
land acquisition is well in advance stage.
RDLIS: 6192.57 acres of Non-forest is land required for entire
Project in which 730.35 acres land already acquired. Balance
land acquisition is well in advance stage.
The Superintending Engineer, Executive Engineers, Deputy
Executive Engineers and Section Officers are constantly pursuing
with the District Collector, Special Collector (LA) and Special
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
15/322
Go To ContentsPerformance Audit Report on Jalayagnam
208
Deputy Collector (LA) for early completion of land acquisition.
Jawahar Nettempadu: The land acquisition authorities are
being pursued constantly by the Superintending Engineer and the
field Engineers for early land acquisition. 85% of the required
land is acquired and the balance 15% is in differenct stages of
acquisition.
Projects in Kadapa:
The Audit made a comment that the I & CAD Department failed
to acquire adequate land required for the Projects under
Jalayagnam on time.
Various factors influence the process of Land Acquisition. The
predominant factors affecting the speedy acquisition are as
under.
1)As many projects are taken up at a time, large extents of
land were required for construction of these Projects. The
sequential activities in L.A process like survey, DN & DD
etc., cannot be taken up at a time for all these Projects
with the available Revenue Staff especially experienced
Surveyors and has to be done simultaneously Project wise.
2)The land owners in some areas are creating hurdles
demanding for higher compensation.
3)In some areas, the land owners are unwilling to part their
costly gardens and are not even co-operating for peg
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
16/322
Go To ContentsPerformance Audit Report on Jalayagnam
209
marking.
4)Paucity of funds.
This Department is constantly bestowing its best efforts in
co-ordination with Revenue authorities in overcoming the
hurdles encountered in Land Acquisition.
Projects in Kurnool:
I & CAD department have sent the LA proposals to LAO
immediately after receipt of EPC agencies. The lands were to be
acquired by LAO after following the procedures of their
department. Land acquisition generally gets delayed when there
is dispute between land owners and LAO on quantum of
compensation. Sometimes, the land owners approach the courts
for higher compensation. These are unavoidable instances and
beyond the control of this department. If the works are taken upafter the completion of land acquisition as suggested by Audit,
the department have to wait up to the completion of land
acquisition and resolution of court cases and after that the works
are to be tendered and grounded with rates as on that date. Even
in this procedure gets delayed and higher rates are inevitable.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
17/322
Go To ContentsPerformance Audit Report on Jalayagnam
210
Table- 5.4
Sripada Yellampally project - Status of Land Acquisition
Name of the Project
Total
Land
Required
(in Acres)
Land
Requisitio
ned
(in Acres)
Land
Acquired
(in Acres)
Land to
be
acquired
(in Acres)
Rema
rks
Sripada Yellampally
Project - Stage I Phase I
- Barrage
16085 16085 12592 3493
Sripada Yellampally
Project - Gates- - - -
LA
Not
requi
red
NTPC LIS (8.50 TMC) 56-03 56-03 56-03 NIL
Manthini LIS (2.00 TMC) 581 581 133 448
SYP- Stage II Phase 5430 5430 2732 2698
1 Ha
of
Fores
t
Land
to be
acqui
red
Kaddem LIS (3.00 TMC) 85-24 85 54 31
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
18/322
Go To ContentsPerformance Audit Report on Jalayagnam
211
Canal Network Package
No I1500 354 35 1465
Canal Network Package
No III1646 1646 699 947
Total: 25383 24237 16301 9082
As shown above, In Sripada Yellampally Project, total land is
acquired in the NTPC Lift Scheme and nearly 80 % of the Lands
are acquired in submergence area of barrage. In rest of the
Packages nearly 40 % of the land is acquired and the progress
of work is Proportional.
In I & CAD Department, earlier to adoption of EPC System, the
Major Irrigation projects like SriramSagar and Jurala were
executed under Lump sum Contract system where the Designs
and Land Acquisition are completed before entrusting the work
to the Agency. It can be observed that the time taken and cashoverruns are more than that of EPC System in creation of
Ayacut for the Public.
Pulichintala Project:
As against 24,605.83 Acres, 23,350.57 Acres is already
acquired. Acquisition of balance land is under process. R & Rworks are programmed to be completed by the end of July
2012.
Projects in North Coast:
With regard to the observation of the PAG that the I & CAD
Department failed to acquire adequate land required for any of
the projects under Jalayagnam on time and the apprehension
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
19/322
Go To ContentsPerformance Audit Report on Jalayagnam
212
of the PAG that the provision towards land compensation
already made by the department is likely to increase in light of
new national land compensation policy to be enacted, the reply
is as follows:
The Government of Andhra Pradesh in order to expedite the
land acquisition process speedily have established several
Special Deputy Collector units in projects depending upon thesize of the project and the land involved. However the land
acquisition process is bound to have problems from public in
any irrigation projects which have to be sorted out amicably.
Further the land acquisition would also involve disposing off
court cases related to Land Acquisition which would invariably
delay the land acquisition process. These hindrances are
unavoidable and every effort is being made by coordinatingwith the revenue authorities for acquiring the land required for
the projects.
Details of Land Acquisition Particulars as of April 2012
in respect of each Project is submitted as separate
Statement 5.1.2.
The total extent of land required for all the above projects
under the control of this unit is 37,765.55 Acres, the extent of
land requisitioned is 35,800.18 Acres out of which 31,227.64
Acres has been acquired and the balance extent of land to be
acquired is 6,537.91 Acres.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
20/322
Go To ContentsPerformance Audit Report on Jalayagnam
213
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
21/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
22/322
Go To ContentsPerformance Audit Report on Jalayagnam
215
response. The Government in 06/2011 had accorded permission
to go for fresh Tender call for a combined work Spillway, Dam
and Excavation of foundation of 960 MW Hydro Power House.
The tenders are floated during 06/2011 and moderate response
was received. But due to various implications involved in the
offers received, the Government took a decision to cancel the
Tenders and to go for fresh Tenders again. The Tenders are
invited and last date for receipt of tenders is 5.07.2012. There is
no lapse on the part of Department in selecting a new agency.
The project is found to be economically viable and technically
feasible even after considering the revised cost based on SSR
2010-11.
5.2.3 Benefit Cost Ratio
The project is found to be economically viable and technicallyfeasible even after considering the Revised cost based on SSR
2010-11.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
23/322
Go To ContentsPerformance Audit Report on Jalayagnam
216
5.2.4 Project Approvals & 5.2.5 Environmental clearance
Polavaram Project:
(5.2.4 & 5.2.5) The Tenders for the works in Indira Sagar
Polavaram Project were invited in anticipation of approvals on
pre-requisite clearances so as to gain time in completion of
Project. But, unfortunately, unlike other projects, this project has
faced some unprecedented circumstances after grounding the
works. To alleviate such hurdles and in accordance with the
suggestions of Central Empowered Committee, the Government
took a decision to stop the works from May, 2006 to April 2007
with an intention to obtain the pre-requisite clearances in a
smooth atmosphere. In fact, there are so many other constraints
came across even after allowing to proceed with the works by
Government in 04/2007. All these impediments are certain, even
if all these works start only after obtaining all statutory
clearances. However, the Government is planning to complete
the project in a time bound manner.
5.2.6 Clearance from Central Water Commission
Polavaram Project:
The Detailed project report has been submitted to Central Water
Commission (CWC) during 1983 and remarks to the comments
were attended by the project authorities from time to time at
CWC. The scrutiny at CWC for most of the important components
like Hydrology Directorates, FE &SA Directorates, Interstate
issues are at advance stage and expecting clearance from
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
24/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
25/322
Go To ContentsPerformance Audit Report on Jalayagnam
218
Further the fact that the CWC and planning commission
accorded the clearances and extended central financial assistance
under AIBP to this project show that the CWC/MoWR after being
satisfied that all interstate issues in respect of this project had
been resolved,accorded Techno-economic clearance. Accordingly
the planning commission accorded investment clearance to the
project.
Godavari Water Disputes Tribunal was formed by
Government of India to resolve the interstate issues regarding
construction of Polavaram Project during 1969. After a lot of
deliberations, between the riparian states an Interstate
agreement has been entered between the states of Andhra
Pradesh, Chattisgarh and Orissa on 2.4.1980 paving the way for
the construction of Polavaram Project with FRL/MWL +150Ft,.
The Godavari Water Disputes Tribunal gave its final award on
7.4.1980 called GWDT Award 1980 in which the interstate
agreement 2.4.1980 made a part. The GWDT in its final order
stated as follows: The Polavaram Project shall be cleared by the
CWC as expeditiously as possible for FRL / MWL + 150Ft. The
design of the dam and its operation schedule shall be left to the
Central Water Commission, which they shall decide keeping in
view all the Agreements between the parties, including the
Agreement of 2nd April, 1980. If there is to be any change in the
operation schedule as indicated in the agreement of 2nd April,
1980 it shall be made only after consultation with the States of
Andhra Pradesh, Madhya Pradesh and Orissa. The design aspects
shall, however, be left entirely to the Central Water Commission.
Thus, in accordance to GWDT Award, 1980, all the
Interstate issues related to the construction of Polavaram Project
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
26/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
27/322
Go To ContentsPerformance Audit Report on Jalayagnam
220
structures on Head works are now in progress and will be
completed in a time bound manner.
The Agency has concluded the Agreement in respect of
ECRF Dam vide Agrt. No.1/2006-07, Dt.11.08.2006 Work
Order was issued on 07.07.2007 by the SE/ISHW Circle,
Dowlaiswaram. The decision of preclosing the contract is
not due to change in designed discharge as stated in Audit.
The contracting agency started the execution of work in
07/2007. The contractor has carried out the work upto
05/2009 and stopped the work suddenly. Department has
issued several notices for resuming the work and to improve
the progress of work. In reply the contracting agency, has
attributed the reasons for slow progress of work i.e., (1) Delay
in L.A. & R&R (2) Delay in Approval of Designs by CWC etc.,
showing the above reasons the agency has not resumed the
work. Hence the Department has taken steps to terminate the
contract duly issuing notice under clause 61 of APDSS. The
Government has taken up the issue and had detailed
discussions with Department as well as with the executing
agency and finally decided to pre-close the contract and to
settle their claims amicably and reasonably to avoid legal and
contractual obligations. Accordingly the Agreement was pre-
closed vide Superintending Engineer Letter No.DB/ATO.3/W/48
EPC, Dt.28.08.2009 and the same is ratified by the
Government vide Govt., Memo. No.22241/2009, Dt.27.08.2009
& 24676/2009, Dt.23.09.2009 (Minutes of Meeting chaired by
Honble Chief Minister, Dt.23.09.2009)
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
28/322
Go To ContentsPerformance Audit Report on Jalayagnam
221
In respect of Spillway work the PMF is not main criteria to
close the work. It is true that the CWC has recommended
the PMF of 50 lakh cusecs for the design of Spillway during
2006. The reasons for the pre-closure were partly
attributable to the agencies. The contention of the audit is
not correct.
As stated in performance audit report not even a single
structure was completed in any of the connectivity works
even after six years is not correct. In Right side
connectivities, under package 62 two main structures i.e.,
OT regulator and P-head regulator and depletion sluice of F-
saddle dam are in progress. While the OT-regulator and
depletion sluice are nearing completion. The work on P-head
regulator is completed to an amount of more than 50%.
Similarly on left side connectivities under package-67 four
structures i.e., lock-I, II, III and syphon work taken up.
While the syphon work is completed the civil works on the
remaining three locks are nearing completion. Further the
tunnel work inrespect of Package-63, 64 & 66 are in good
progress. So the contention of audit that only earth work
and no structure was done even after six years is not
correct and hence denied.
The work of Earth work excavation for foundations of
ISPHEP is included in the present tenders called for ECRF
Dam and Spillway of Indira Sagar Polavaram Project vide
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
29/322
Go To ContentsPerformance Audit Report on Jalayagnam
222
Tender notice No. 1/2012-13, Dt. 16.04.2012. The tender is
under process. The action for commencing of HE project will
be taken up after commencing the work in ECRF and
spillway of ISPP.
Indira Sagar Left Main canal
Government have accorded administrative approval for
Rs. 1954.74 Crores vide G.O.Ms.No. 104, Dt: 30.05.2008 forexecution of Left Main Canal works. The Canal runs for a length
of 181.50 Kms in East Godavari and Visakhapatnam Districts. For
execution purpose, the Canal is divided into 8 Packages. All the
works are grounded and works are in progress.Out of 445
structures, 67 are completed and 83 are in progress. The
percentage of work done is 52%. The total extent of land
required is 10540.92 Acres under the Left Main Canal. The extent
of land so far acquired is 10251.84 Acres (97%).
Indira Sagar Right Main canal
Government have accorded administrative approval for Rs.
2240.688 Crores vide G.O.Ms No.150, Dt: 23.07.2008 for
execution of Right Main Canal. The Canal runs for a length
of 174 Kms in West Godavari and Krishna Districts. For
execution purpose, the canal is divided into 7 Packages. All
the works are grounded and the works are in progress. Out
of 248 structures 93 are completed and 22 are in
progress.The percentage of work done is 64%. The total
extent of land required for Right Main Canal in 12687.70
Acres. The extent of land so far acquired is 10749.80 Acres
(85%). The handing over of Forest land to Department is in
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
30/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
31/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
32/322
Go To ContentsPerformance Audit Report on Jalayagnam
225
attributable to the agencies as well as the reasons not attributable
to the agencies. The contention of audit that the Government
hastily awarded Spillway and ECRF works is not at all correct. All
the required design parameters have been fixed before award of
contract and incorporated in Bid documents itself. Under EPC
contract system, the designs after detail survey and investigation
are to be furnished by the EPC contractor and after thorough
scrutiny by department the same will be transmitted to CWC for
scrutiny and approval. The execution of work will be taken up asper approved drawings only. Accordingly the construction
drawings have been submitted to the Government for PMF of 50
Lakh cusecs. As already stated, the contracts were preclosed on
account of slow progress of works due to the reasons attributable
to the agency as well as other reasons not attributable to the
agency. After preclosure of the contracts tenders have been called
for and the tenders received are under process.
The observation of the audit that the state of Andhra
Pradesh was deprived of 35 TMC of water out of river
Krishna to upper states of Karnataka and Maharashtra from
the date of clearance of Indira Sagar Polavaram Project is
not correct. As on today the upper states of Karnataka and
Maharashtra are not utilizing the additional 35 TMC of water
out of Krishna river from the date of clearances of ISPP.
Indira Sagar Polavaram Project is a major multi-purpose
project taken up across river Godavari to utilize water which
otherwise will go as waste to sea and is very important for
overall development of the State and during the
construction of such major projects several unexpected
hurdles will come in the way. The Government is
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
33/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
34/322
Go To ContentsPerformance Audit Report on Jalayagnam
227
The audit has observed on account of pre- closure of
contracts of ECRF & Spillway the Government had to admit
a claim of contracts for Rs.19.39 Crores for the reasons
outside the ambit of the agreements. Most of the claims of
the contractors admitted by the Government are pertaining
to the infrastructure works like approach roads,
procurement of dumping areas, deposits paid by the
contractors to AP Transco authorities etc., which can be
made use of by the new executing agencies to be fixed.These available infrastructure works are specifically
mentioned in the bid document and the prospective bidders
are requested to quote their bid prices keeping availability
of these infrastructure facilities also in view. Hence, the
contention of audit is not correct.
The provisions of the agreement under clause 16 & 17 of
G.C.C and Clause 50 of APSS stipulates the contractingagencies for taking Insurance policies to cover all types of
risks including natural calamities. This will safe guard the
exchequer against any type of risk. So, the contracting
agencies have taken the Insurance policies in terms of
provisions of agreement, from the start date to safe guard
the works, plants and materials, equipment, property,
personnel against possible risks like the act of God or
natural calamities or accidents.
The respective firms have paid the Insurance premiums as
given below.
1. Spillway : Rs.2,77,80,330
2. ECRF Dam: Rs.5,11,83,412
Total Rs.7,89,14,742
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
35/322
Go To ContentsPerformance Audit Report on Jalayagnam
228
As this is a major project involving lot of critical operations viz.,
exploration of foundations, blasting operation, usage of heavy
earth moving equipment in the hilly terrain, river surveys,
soundings, Geo-physical surveys, Hydrographic survey even
during floods which involves lot of risk to men, material,
equipment etc., insurance policy is necessary.
The contracting agencies also faced several difficulties
due to natural calamities like floods, cyclones, manmade
disturbances through local agitations and also accidents caused
during operation of heavy machinery. Thus the insurance has
covered several risks uncovered during execution of work.
As the subsisting contract of both Spillway and Earth
cum Rock fill Dam was pre closed, both the firms have claimed for
the reimbursement of insurance paid. However the State Level
Standing Committee admitted the claim to a tune of Rs. 4.0Crores and Rs. 2.39 Crores for Earth cum Rock fill Dam and
Spillway respectively duly deducting proportionate amount
towards work done.
Survey and Investigation 6.98 Crores: There is a
Provision of Rs. 10.00 Crores towards Survey Preparation
of L.P. Schedules, Investigation and designs etc., After
concluding the Agreement the contracting agency has
attended to the investigation, alignment proposals,
submission of L.P. Schedules and design proposals for
GapI,II,&III. Based on the proposals submitted by the
Agency (1) Land acquisition was taken up & completed (2)
Alignment proposals in gap gb, gg & gb were finalized (3)
The detailed designs for Gap I,(gd) Gap (gg), Gap III (gb)
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
36/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
37/322
Go To ContentsPerformance Audit Report on Jalayagnam
230
Agreement, 2004 initiated in hastiness was poorly sequenced is
not correct. Generally execution of projects and obtaining
clearances will go on simultaneously, as the Government is very
keen in completing the pending irrigation projects on top priority
under Jalayagnam. Government of several such projects, court
intervention were encountered in respect of this project only.
The contention of the audit, that the project works are
to be taken up only after getting all clearances, completing all
investigation and designs for construction/ working drawings;completion of L.A. process; completion of R&R etc., is not at all
correct. Even by such arrangement, the escalation of the project
cost on account of time taken for completion all the formalities
like clearances, L.A, R&R, Designs etc., will be much more than
the present system where delays are in respect of certain portion
of works only where problems are encountered.
Generally the canal & distributory system works arescattered and takes more time for completion than the head
works which are located at one place. In respect of canals, even
though substantial portion of works are completed, it will take
quite a long time to complete balance works especially
problematic. Stretches held up due to local problem, ryots
objections, court cases etc., The works pertaining to balance
distributory system are to be taken up. If the canal works which
are scattered are not taken up early as there works will take more
time for completion in the light of real time problems like L.A
issues, Ryots objections, court case etc., which cannot be avoided
unlike head works which are concentrated works. When large
projects like Indira Sagar Polavaram Project are taken up, it is not
possible to take up all the components of the projects in such a
way that are all completed on the same day in whatever way one
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
38/322
Go To ContentsPerformance Audit Report on Jalayagnam
231
plans as the problem which were encountered during execution
cannot anticipated. Further, while taking up such large projects,
the works shall be taken up such that the funds requirement such
as with Budget provision that can be made available.
All the project components were taken up almost
simultaneously with an intention to complete them simultaneously
to reap the early benefits. But on account of certain unexpected
problems, there are certain delays in execution of some
components and every effort shall be made to complete theprojects at the earliest by sorting out the problems.
5.2.11 Compromise / Reduction in specifications
Polavaram Project:
As per clause 2.5 of Section-2, general specifications of
Agreement the contractor have to submit the designs duly
carrying out investigations and it shall be as per relevant I.S.
Codes, since the drawings enclosed in the bid documents are only
tentative. Accordingly the contracting agency has carried out the
investigations and submitted designs as per the relevant I.S.
Codes. The designs submitted by the contracting Agency verified
with reference to the I.S. Codes and approved by the Chief
Engineer, Central Designs Organization, Hyderabad. Hence
question of lowering of specifications does not arise. Regarding
cost adjustment as per clause 38 and 39 of G.C.C. the contractor
bound to execute all the supplemental works that are found
essential, incidental and inevitable during execution of main work
at no extra cost to the employer. This being a EPC contract
system the contracting agency has to carry out the investigation,
soil exploration works etc., based on this prepare and submit the
drawings for approval. Hence, variations in the quantities
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
39/322
Go To ContentsPerformance Audit Report on Jalayagnam
232
excess/less may take place. Therefore one can not see only one
side of the coin i.e. decrease in quantities. The other side of the
coin is some items such as shotcreting, construction of portals,
temporary and permanent supports etc are increased beyond the
provisions made in the estimate. The resultant savings on account
of lowering of specifications of any item of work in deviation from
the basic parameters will be assessed by referring to the State
Level Standing Committee constituted by the Government and
approval of the Government will be obtained. Such savings asapproved by Government will accrue to the Government. Hence
the observations of audit that the lowering of specification without
cost adjustment resulted in undue benefit of Rs 45.53 Crores to
the construction agency is not correct and hence denied. When
supplemental works are being executed without any cost to the
employer on single source responsibility, the other work in which
there is some saving in it have to be considered as costadjustment is not correct.
5.2.12 Land acquisition
Polavaram Project:
Total land required for working areas of ISP Project was almost
acquired.. The total land under submission of the ISP project in
three Districts 1) KHAMMAM, 2) WEST GODAVARI & 3)
EASTGODAVARI IS 88366.84 Acres out of it 45150.35 Acres of
land which is more than 50% total land required has been
acquired. Therefore, there is no shortfall in acquiring the land
required. The balance Land acquisition will be done as per
programme of the project .The total estimated cost towards Land
acquisition is Rs 3405.98 Crores only but not Rs. 8724.81 Crores
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
40/322
Go To ContentsPerformance Audit Report on Jalayagnam
233
as reported. Out of it Rs 441.941 Crores were spent, on Forest
Land only 43216.49 Acres of Non Forest Land is yet to be
acquired. The Forest Land affected due to submergence of ISP
project is 8961.04 Acres and the process of handing forest land is
in progress. Total Land required for land to land Compensation
under R& R is 40,330.54Acres out of it 2,800.93Acres has been
acquired and balance land 37,529.61 Acres will be acquired as per
Scheduled programme.
5.2.13 Rehabilitation and resettlement
Polavaram Project:
R & R for Project Affected Families is under progress as per
construction programme of ISP Project. The draft action plan
for all the 29 habitations in West Godavari district, 43 habitations
in East Godavari District has been submitted and approved. In
respect of Khammam District, the draft action plan for about 60villages has been prepared and for remaining villages, it is under
preparation. All the villages in Khammam District are categorized
under phase 3 and 4 R&R in these villages will be completed One
year before actual submersion takes place.
West Godavari District:- Out of 478.12 acres of land
required for house sites, 280.29 acres of land has already
been acquired and the remaining extent has to be acquired
for the villages which are categorized under phase 2 and 3
and which are not urgent. Out of 3582.50 Acres of land
required for land to land, 1208.37 acres of land was already
acquired and the remaining extent is falling in the villages
which are categorized under phase 2 and 3 only. Total No.
of Housing Units to be constructed is 4139 Nos. out of which
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
41/322
Go To ContentsPerformance Audit Report on Jalayagnam
234
352 Housing Units were completed and 1259 Units are
under Progress. Out of total PAFs of 4363., 490 were
Rehabilitated.
The infrastructure works for all the 7 villages falling in 1st phase
have been completed already and the remaining villages fall under
2nd and 3rd phase. The Socio Economic survey for all the
prioritized 1st phase villages has already been completed.
Rs.106.560 Crores has been spent so far on R&R in West Godavari
District
East Godavari District:- The infrastructure facilities for the
1st phase villages has been completed and the same for
remaining villages which are in 2nd, 3rd phases is under
progress. The land for 4 prioritized villages has already been
acquired. The Below Poverty Line housing units to a tune of
498 nos in 1st phase have been completed and remaining
units which are categorized under phase 2 and 3 are under
various stages. Total No. of Housing Units to be constructed
is 4409 Nos. out of which 498 Housing Units are completed
and 119 Units are under Progress. Out of total PAFs of
4643, 481 PAFs were rehabilitated. Rs. 25.763 Crores has
been spent so far on R&R.
Khammam District:- All the villages are categorized under
phases 3 and 4 which are affected under submersion only.
The R&R in this district will be completed 1 year before
actual inundation takes place. Total No. of Housing Units to
be constructed is 33708 Nos. As the process of Land
Acquisition is still under progress these housing units were
not yet completed. Total PAFs are 33708. Rs. 6.178 Crores
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
42/322
Go To ContentsPerformance Audit Report on Jalayagnam
235
has been spent so far in Khammam District. Therefore the
R&R implementation is as per programmed action plan.
The draft plan for most of the villages pertaining to ISPP
was prepared. Every effort is being made to complete the R&R for
all the affected villages as per action plan. In respect of
Chattisgarh and Orissa, there will not be any submersion of lands
and villages due to proposed construction of protective
embankments in the territories of Orissa and Chattisgarh, The
submergence issue of ISPP in Chattisgarh and Odisha was settledlong back in terms of Interstate agreement Dt 2-4-1980 and
GWDT award. The contention of audit that the submergence issue
with Chattisgarh and Odisha were not sorted out and led to
prolonged litigation is not at all correct. The observation of audit
that there have been consistent lethargy towards R&R is not at all
correct. As implementation of R&R involves coordination and
carrying out works from different departments duly consultingaffected people. The R&R work will be completed as per the
action plan. The implementation of R&R for Gandikota has been
recommended as this particular village Gandikota was a
rehabilitation village which is again affecting under PLIS sub lifts.
5.2.14 Coordination with Statutory organizations:
Polavaram Project:
In respect of ISLMC, as per clause 27 @ page No.110 of the
agreement, the E.P.C. agency has to follow up with the
Department for obtaining clearance and take-up the
construction.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
43/322
Go To ContentsPerformance Audit Report on Jalayagnam
236
However as per the policy decision taken by the NHAI, the
grant of permission for way leave facility (Canal crossings) will be
accorded by NHAI provided the Government of Andhra Pradesh
foot the bill for the entire scope of work involved and to be carried
out as deposit work.
After protracted correspondence and obtaining information
from NHAI, Government vide G.O.Rt.No.103, dated 13.02.2012
accorded permission for payment of Planning and estimatecharges and amount has been paid to NHAI in 03/2012.
Permission is awaited.
Planning and estimate charges have been paid to NHAI in
03/2012. Permission is awaited.
In respect of ISRMC Package II
1) HPCL & GAIL Crossing in between Km 19.200 and km 19.750 ofRMC
The laying of new pipe lines of HPCL/ GAIL at the point of
crossing of RMC is the most suitable option, among the various
studies made, as suggested by HPCL / GAIL authorities. Further it
is submitted that as per agreement condition 27 of Special
conditions of contract, it is the responsibility of the contractor to
obtain clearance for HPCL oil pipe lines and GAIL gas pipe lines
from the concerned authorities and cost of the crossing of pipe
lines are included in the bid. As per agreement condition 24 of
other special conditions (Appendix OS), if the canal system is
crossing HPCL oil pipe lines, GAIL pipe lines or any other pipe lines
the contractor shall provide suitable crossing in consultation with
the authorities concerned after obtaining the approval either by
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
44/322
Go To ContentsPerformance Audit Report on Jalayagnam
237
himself or getting them executed by the concerned authorities as
a deposit work duly depositing the requisite amount to HPCL/
GAIL authorities. The Engineer-in-Charge will help in processing
the proposals to the authorities concerned to obtain their
permission. The cost of such crossings shall be deemed to be
included in the contract price.
In view of the above facts it is submitted that the
department have taken necessary action from time to time to
obtain the permission from GAIL & HPCL authorities. Several
times the Prl.Secretary to the Govt., (Projects), I&CAD dept,
Hyderabad and the Engineer-in- Chief, ISPP, Dowlaiswaram
reviewed the status of permission. Because of technical difficulties
only, as per site conditions, new pipe lines are inevitable and
because of the efforts made by the department with proper
coordination with GAIL& HPCL authorities present status of
permission could be obtained. The agency is requested to deposit
the amount and as soon as the amount paid by the agency work
will be completed .There is no financial burden on the Govt., since
the cost of crossings has to be paid by the agency within the
contract price.
2) Electrical lines in RMC Package-II
As per agreement conditions electrical lines coming in the
alignment of canal shall be shifted by the EPC agency at their own
cost within the contract price. At many places the EPC agency
shifted the electrical lines at their own cost duly paying requisite
charges to APEPDCL.
From KM 35.000 to Km 37.000 of RMC, 33 KV and 11 KV
lines are existing in the canal alignment. The Department pursued
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
45/322
Go To ContentsPerformance Audit Report on Jalayagnam
238
the matter with APEPDCL. The APEPDCL authorities informed to
pay an amount of Rs.20.47 lakhs towards shifting of 11 KV and 33
KV lines. The agency was requested to deposit the amount. The
department have taken necessary action from time to time for
shifting of electrical lines. Now action is being taken by the
Department to shift the electrical lines in between Km 35.000 to
37.000 within the contract price only.
ISRMC Package No.IV :-
GAIL pipe line is crossing ISRMC at Km 103.700. After pursuing
the matter with the GAIL authorities, an amount of Rs.1.05 lakhs
was deposited to the GAIL authorities for preparation of estimate.
At the time of preparing detailed estimate, certain field
information was sought for by the GAIL authorities. While
gathering the required information at field, ryoths of Pedavegi (V)
were objected the survey works and not allowed into the fields
duly arguing that the area is covered under stay orders of the
Honble High Court, Hyderabad in W.P.No.27352/2007. Hence, it
is not possible to furnish the required information to the GAIL
authorities.
5.2.15 Unforeseen ground conditions
uncertainties involved in bidding:
Polavaram Project:
Polavaram Project canals works are still under progress.
Only 50 to 60% works are completed and the lining works
under these excavated canals are under progress. The
original alignment of these canals is going through Black
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
46/322
Go To ContentsPerformance Audit Report on Jalayagnam
239
Cotton soils in some reaches. In these reaches CNS
(Cohesive Non Swelling) treatment below the lining course
was provided in IBM estimates to reduce the effect of
swelling and shrinkage of the soils. After entrusting the
works to the EPC contractors and after detailed survey by
the agency, it was decided to take the alignment in cutting
only rather than partial cutting or embankment and the
revised alignment was approved in place of original
alignment proposed in IBM estimates to safeguard the canalsystem. Because of these reasons there were some
changes in the alignments of canals proposed earlier. As
the alignment of canals were changed, the length of the
canal, quantity of earth work excavation and structures on
the canal in each package work are increased heavily. It is
well known that the above changes caused heavy
expenditure and the contractors represented Governmentfor additional payments and these proposals were rejected
by the Government. In as much as 52% of the lining works
are completed the reaches where CNS treatment is required
is not fully identified. As the above fact is very clear, it is
not rational to say that the amount provided in IBM
estimate towards CNS treatment is fully paid to the
contractor.
In respect of Packages 63 & 64, the tunnels were provided
with concrete lining thickness for 900 mm in the estimate as
per approved drawings by the CE/CDO/Hyderabad based on
detailed soil exploration/ bore hole data. Lining thickness of
900 mm was provided due to lack of data on investigations
is not correct. Now as per detailed design calculation based
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
47/322
Go To ContentsPerformance Audit Report on Jalayagnam
240
on IS Codes and rock strata available in the field, concrete
lining thickness of 800 mm was finalized and approved by
the CE/CDO, Hyderabad. The agency proposals to provide
concrete lining thickness of 500 mm is insufficient, hence
not accepted. However, the savings due to reduction of
lining thickness in Package 63&64 have been worked out
and recovery proposals to this effect have been submitted
to the Government. Hence the contention of audit is not
correct.
In respect of ISRMC Package-3, the work Earth Work
Excavation, formation of embankment and construction of CM
& CD works including investigation, designing and estimation of
ISRMC from Km 38.199 to Km 71.500 was awarded on EPC
basis to M/s. Hindustan Construction Company Ltd., Mumbai
vide Agreement No. 11 SE /2004-2005 Dt:23-10-2004 for anagreed value of Rs.321.30 crores at 3% excess over ECV of
Rs.311.94 Crores. The work was scheduled to be completed
within 24 months i.e 22.10.2006. EOT was sanctioned up to
30.062012.
The Right main canal is carrying huge discharge of 391 Cumecs
the alignment running in full cutting in higher contour is
considered instead of those having embankment reaches to avoid
formation of breaches and R4 alignment is approved . Infact the
ryots have filed a W.P.in the Hon`ble High court vide
W.P.No.452/06 which was dismissed on 07/4/2006 uphelding the
decision of the CE, CDO for approving the R4 alignment. The only
alignment approved by the dept, was R4 alignment keeping in
view to minimize embankment and to avoid risk of breaching. As
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
48/322
Go To ContentsPerformance Audit Report on Jalayagnam
241
per EPC norms agency has to execute the work as per approved
alignment only. Hence the agencys claim for Rs.58.49 Crores is
not untenable and hence rejected. The contention of audit all
these issues have cropped up only because of lack of detailed
survey and investigation and unforeseen soil condition is not
correct. Under EPC contract all the items of works from
investigation, designs, execution and completion of works
including O&M falls under single source responsibility of the EPC
contractor.
5.2.16 Approval of designs:
Polavaram Project:
Status on approval of Designs as on 31.05.2012.
Total No.of structures : 717
No.of Designs submitted by the Agency : 558
No.of Designs approved : 414
No.of Designs under scrutiny at O/o
CE/CDO & CE/ISPP: 15
No.of Designs returned at different stages
of scrutiny i.e, from O/o ENC/ISPP and O/oCE/CDO with major remarks and for want
of further field data etc., and still pending
with Agency for re submission
: 129
No.of Designs yet to be submitted by the
agency: 159
From the above status report it is clear that out of 303 Designs
yet to be approved, only 15 Designs are under scrutiny with
Department i.e., at O/o ENC/ISPP and O/o CE/CDO, and the rest
i.e., 288 Designs are pending with Agency, of which 129 Designs
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
49/322
Go To ContentsPerformance Audit Report on Jalayagnam
242
are pending for resubmission after attending the remarks and
supplementing further data called for, and 159 Designs are
pending for first submission itself till to date.
5.2.17 Third Party Supervisions:
Polavaram Project:
The TPQC package 17 consists of Head works 62 to 67
packages. The QMP for package 62, 63 & 64 are with the
department and the same will be transmitted to the TPQC
Agency. For the remaining Packages the department isconstantly pursuing with the Agencies. As soon as received from
the Agencies it will be transmitted to the TPQC Agency for
review.
At present no works are in progress in Package No.5, 6 &
7 of ISRMC which comes under the purview of Package No.20 of
3rd Party Quality Control. The works are held up for want of land
due to delay in land acquisition due to Ryoths objections and the
stay orders of Honble High Court. In spite of constant
persuasion through Advocate General of Andhra Pradesh, the
matter in the court is still pending.
The civil works in Packages 5 & 6 are stopped since
06/2009 and continuing as on date except two months in
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
50/322
Go To ContentsPerformance Audit Report on Jalayagnam
243
Package No.5, where as the works of Package No.7 are
continued up to March 2010. Even though the works are idle in
Package No.5&6, the agency carried out the Q.C/Q.A operations
in Package No.7 where the works are continued up to March. At
the same time, the agency carried out non destructive tests in
the completed reaches in Package No.5 & 6 in the idle period. As
Package No.7 is one of the component of Package No.20, an
amount of Rs.1.17 Crs was paid to the agency towards
supervision charges at Rs.12,98,573 per month for 9 Months i.e,from July 2009 to March 2010. Beyond March 2010, the services
of agency are continued expecting the land is being handed over
and the court cases are cleared. However, the payments were
paid by the concerned Quality Control Authorities.
The Government have accorded permission vide
G.O.Ms.No.29 dt:04.06.2011 to continue the services of the 3rd
Party Quality Control agency with selection staff duly paying the
remuneration of Rs.1.57 Lakhs Month to M/s Engineering Staff
College of India, Hyderabad for Package No.20 of ISRMC till the
package works are resumed.
Accordingly the supervision charges are being paid to the
agency from 01.07.2010 onwards for selection staff only.
5.2.18 Stoppage of works midway:
Polavaram Project:
There is a provision of Rs.10.00 Crores towards Survey,
preparation of L.P. Schedules, Investigation and designs etc.,
After concluding the Agreement the contracting agency has
attended to the Investigation alignment proposals & L.A.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
51/322
Go To ContentsPerformance Audit Report on Jalayagnam
244
proposals including submission of L.P. schedules and designs of
proposals Gap I, II & III Based on the proposals submitted by
the Agency (1) Land Acquisition was taken up & completed (2)
Alignment proposals were finalized (3) Based on the data
furnished by the agency the Central Water Commission has
issued working drawings (estimate purpose) for the Earth-Cum-
Rock Fill Dam for Gap I&II. Based on the work done by the
agency an amount of Rs.4.11 Crores paid to the agency against
Rs.10.00 Crores claimed by the agency. However in the balanceestimate a provision of Rs.5.00 Crores was made available
towards balance Investigation & Designs etc, to the second
agency. Hence there will not be any extra payment to the
second agency.
5.2.19
Unwarranted owning of contracting agencies burden:
Polavaram Project:
The audit has observed that one of the objectives of EPC
turnkey system of contracting was to eliminate the need for
revision of project cost. It also observed that the department
owned the burden of the contracting agencies in several aspects
and listed two packages (Package-67 & 62) of ISPP out of 12
cases reported.
The above observation of the audit are not correct. The
objective of the EPC system of contracting is not to have cost
over run pertaining to the works coming with in the scope of the
contract. Any works which are not contingent and fall out side of
the scope of the contract are to be treated as extra item and
payment is to be made to this extra item as per clause 39.3.1 of
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
52/322
Go To ContentsPerformance Audit Report on Jalayagnam
245
GCC of agreement. The audit is calling out the extra items which
fall out side the scope of the contract as the burden of
contracting agencies and pointing out that the department is
owing such burden of contracting agencies is not correct. The
details of additional item which fall out side the scope of
contract in respect of 62 & 67 of ISPP are furnished below.
Package: 62: As stated in performance Audit report i.e., the
action of Government was unwarranted and resulted inunavoidable burden to the Government and undue benefit to the
contractor is not correct. Essentiality of providing depletion
sluices to saddle dam E & F was finalized only after Design
experts decision during field visit to Polavaram Project in
December-2007. It is a unforeseen item and out side the scope
of original contract. As per agreement conditions 39.3.1
whenever additional item not contingent to main work and outside the scope of original contract are to be entrusted to the
original contractor, on entrustment of such items and price to be
paid shall be referred to a committee constituted by
Government for final decision. Accordingly, the depletion sluices
item was referred to state level standing Committee for
decision. After elaborate discussions only, additional item was
recommended to the Government, by the State Level Standing
Committee. Hence as per agreement condition 39.3.1 it is
genuine to consider as an additional item. The observation of
audit that even such additional item which fall out side the
scope of the contract clearly as burden of agencies is not at all
correct and amounts to violation of agreement condition.
Package: 67: The construction of flood gate was not included
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
53/322
Go To ContentsPerformance Audit Report on Jalayagnam
246
in the original scope of work, basic parameters and also in the
agreement. Only after detailed investigation, the necessity of
the flood gate structure was identified and recommended to the
State Level Standing Committee to take up the work as an
additional item of work not contingent to original work under
clause 39.3.1 of the GCC of contract. As per the state level
standing committee recommendations, the Government
accepted and accorded permission to construct the flood gate
structure. The financial aspect is still under examination.Hence the contention of the audit that this item of work is
burden of agency is baseless incorrect and denied.
5.2.20 Payment Schedules Preparation and Revisions:
Polavaram Project:
The observation of the audit that in Indira Sagar Polavaram
Project, the payment schedules are improperly fixed and the
revision was not based on the detailed estimates is not correct.
The details are furnished below:
The work ISRMC Package No.VI i.e., Earth work
excavation, formation embankment and construction of
CM&CD works including investigation, designing and
estimation of ISRMC from KM133.800 to KM 156.500
was entrusted to M/S Progressive constructions ltd,
Hyderabad vide Agreement No.8SE/2004-2005 dated
20-10-2004 on EPC turnkey system.
Out of total length 24.078KMs, the land handed over to
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
54/322
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
55/322
Go To ContentsPerformance Audit Report on Jalayagnam
248
sanctioned by the Engineer-in-Chief Vide ref.
No.2/2004-05, Dt.7-10-2004 for Rs.248.44 Crores. The
work was awarded to M/s Patel-Soma J.V, Mumbai Vide
Agt. No. 9 SE/04-05, Dt.21-10-2004 for Rs.241.50
Crores.
Out of the total length of 14.80 kms.(from km.0.000 to
km14.800 of ISRMC), 12.80 Kms length of Earth work
excavation and 11.725 kms length of CC lining and 22Nos of
CM & CD structures were almost completed out of 25 Nos and3 Nos (2 OTs and 1 Surplus escape) yet to be started and the
balance 2.00 kms work was held up due to Forest Area and
R&R problem.
The detailed estimates submitted by the agency as per
the approval Hydraulic particulars, the payment schedule
works out to 41.80% for Earth Work Excavation, 31.50% for
CC Lining, and 26.70% for CM & CD Works against thepercentages made in the payment schedules in original
agreement. The Physical percentage of work done, so far is
87.85% EWE, 78.30% CC Lining, 84.60% CM & CD Works.
The Land required for the work has been handed over to
the agency in stages as and when the land acquisition
authorities hand over the land to the irrigation department.
The agency commenced the Earth work, CC lining,
Construction of CM & CD Works simultaneously in the reaches
where the land is available. So, the contention of the audit that
the items like Earth work Excavation was taken up as front
items and the construction of CM & CD works as backend items
is not correct. Hence the contention of the audit that huge
front loading for the items taken up in the beginning is not
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
56/322
Go To ContentsPerformance Audit Report on Jalayagnam
249
correct about 90% of work is already completed.
Even though the original payment schedule was fixed
erroneously, the contractor executed all the three components
simultaneously and there by there is no front loading
payments made to the contractor.
There is no excess amount made to the agency. Further,
the payment schedule is being revised for the balance work tobe done by the agency as per the actual quantities.
The work "Earth Work Excavation, formation of
embankment and construction of CM & CD works
including investigation, designing and estimation of
ISRMC from Km 38.199 to Km 71.500 " was awarded on
EPC Turnkey basis to M/s. Hindustan Construction
Company Ltd., Mumbai. vide Agreement No. 11 SE /2004-2005 Dt.: 23-10-2004 for an agreed value of Rs.
321.30 crore..
As per the agreement conditions 41.2.1 of cost
control in the agreement the total work specified under EPC
turn Key contract is divided into several components of work to
facilitate payments component wise. The work of the each of
the components are specified as percentage of the total bid
price under Annexure-II, Schedule of payments. In EPC
contract system there is no change in total amount to be paid
to the contractor. The payment schedule was fixed based on
the approximate quantities in the IBM. After conducting
detailed investigation the agency has submitted details for
earth work quantities only.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
57/322
Go To ContentsPerformance Audit Report on Jalayagnam
250
Originally the canal Earth Work Quantities was arrived
based on tentatively alignment in which canal is running in
balance depth of cutting. The present alignment approved by
Department duly keeping the FSL almost below ground level.
Due to this the Earth work Excavation in cutting has been
increased abnormally due to deep cuts in alignment. Further
due to reduction in length of canal (2.589Kms.) the quantity of
lining work is decreased. Hence the main components such as
Earth work, lining have been changed and the firm hassubmitted the revised payment schedule.
As per the approved HPs the earth work quantity is increased
to from 1.14 Crores cum. To 2.40 Crores cum. Hence the
revision of payment schedule is necessitated. Hence the
Government have approved the revised payment schedule to
regulate the payment as per the agreement clause 41.2.1
Vol.I, Part-A, conditions of contract.
Even the alignment is running in higher contour
(deep cut portions) the lining quantity is not increased as the
perimeter of lining proposed is constant throughout reach. The
logic of the audit that the lining quantity shall increase if
earthwork quantity increases is not correct as the length of
canal is decreased and depth of cutting is only increased.
The payment schedule contemplated in Agreement and revised
payment schedule submitted by the agency and revised
payment schedule approved by the Govt. is as follows.
Sl
NoDescription
Earth work
excavationLining
CM&CD
worksTotal
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
58/322
Go To ContentsPerformance Audit Report on Jalayagnam
251
1Percentage as per
agreement20.91 41.61 37.48 100
2
Amount as per
agreement
(Rs Crores)
67.18 133.69 120.43 321.30
3Restriction to
agreement value
97.39
(30.31)
101.20
(31.50)
122.71
(38.19)
321.30
(100%)
4
Percentage as per
revised payment
schedule asapproved by Govt.
30.31 31.50 38.19 100%
The payment schedules are revised considering the quantities
of earth work, Lining and structures and approved by the Govt
memo no.6818/Maj.Irrgn.1(2)/2006.. Hence the contention of
the audit that the corresponding lining work is not increased is
not correct as the values of the components Earth work and
Structures are infact increases as per actuals and restricted to
the agreement value . as shown in the above table. The lining
amount as per the agreement of Rs 131.587Crores has been
decreased to Rs 101.20Crores due to decrease in length. But
due to proportionate restriction to agreement value, the
percentage lining component is reduced from 41.61% to
38.19%.There is nothing absurd in the calculations. Thus thecontention of the audit that the revision of payment schedule
resulted in advance/ premature payment on front end items of
Rs 30.21Cr is not correct.
The work "Earth Work Excavation, formation
embankment and construction of CM & CD works includi
investigation, designing and estimation of ISRMC from Km 71.5
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
59/322
Go To ContentsPerformance Audit Report on Jalayagnam
252
to Km 105.100" was awarded on EPC basis to M/s. Jayaprakas
Gayati JV, Hyderabad vide Agreement No. 10 SE / 2004-20
Dt.: 23-10-2004 for an agreed value of Rs. 301.30 crore at
tender discount of 5.71% of ECV of Rs. 319.53 Crore. The wo
was scheduled to be completed within 24 months i.e 22.10.200
EOT was sanctioned up to 30.06.2012.
Due to change in the alignment of canal from balance dep
of cutting to FSL cutting & deep cutting, the length of the canalincreased from 33.600 Kms to 36.065 Kms. Due to increase
length of canal, and running the canal in full cutting there
increase in Earth work, lining and CM&CD Works.
The revised payment schedule is as follows considering
detailed quantities for Earth work , Lining. The cost of CM and
CD works, is arrived based on the cost as per sanctionedestimate.
Sl
No
Description Earth work
excavation
Lining CM&CD
works
Total
1 Percentage as per
agreement17.079 36.99 45.931 100
2 Amount as per
agreement(Rs Lakhs)
5145.90 11145.09 13839.01 30130
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
60/322
Go To ContentsPerformance Audit Report on Jalayagnam
253
3 Amount as per Revised
payment schedule of
approved alignment for36.065km in lakhs with
estimate rates
10677 11183 14100 35960
4 Proportionate restriction
to agreement value8946 9370 11814 30130
5 Percentage as per revised
payment schedule29.69% 31.10% 39.21% 100%
The payment schedules are revised considering the
quantities of earth work, Lining and structures and approved
by the Government in Govt.Memo No.6818/Maj.Irrig.I
(2)/2006-1 dt 22-3-2006. Hence the contention of the audit
that the corresponding lining work is not increased is not
correct as the values of the components are infact increased as
per actuals and restricted to the agreement value on prorata
basis, as shown in the above table. The lining amount as per
the agreement of Rs 11145.09 lakhs has been increased to Rs
11183.00 lakhs due to increase in length. But due to
proportionate restriction to agreement value, the percentage
lining component is reduced from 36.99% to 31.10%.There is
nothing absurd in the calculations. Thus the contention of the
audit that the revision of payment schedule resulted inadvance/ premature payment on front end items of Rs 38.00
Cr is not correct.
In respect of package 66 of ISPP, initially the agency
has started the work to a small extent in the non forest
area where the land was made available to work since
the major part of the work was involved in the Forest
area. The IBM values were arrived as per the
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
61/322
Go To ContentsPerformance Audit Report on Jalayagnam
254
preliminary investigation only.
The total earth work quantity provided in the IBM
estimate as 1,88,598 Cum (i.e, soil quantity as1,05,533 Cum
and Hard Rock quantity as 83,065 cum)
During actual execution, the total quantity arrived
at 3,06,425 Cum (i.e, soil quantity as 7765 cum and Hard
Rock as 2,98,660 Cum) based on the approved H.Ps and
detailed estimate prepared and thus the value of the
component is also increased. The payment of Rs.3.33 croreswas made as per the payment schedule provided in the
original agreement. Out of which an amount of Rs.3.06 crores
was made towards earth work excavation and the remaining of
Rs.0.27 crores was made towards investigation work.
Considering the actual quantities of work involved,
there was no excess or front load payment made to the
contractor. Considering the actual quantities as per designs,the Revised payment schedule was prepared and the same
was approved by the competent authority. The forest land was
also handed over to the agency recently and the execution of
Tunnel work is in progress. Now the payment is being allowed
as per the approved revised payment schedule only.
Therefore the contention in the audit report that the contractor
benefited is not correct.
In Indira Sagar Polavaram Project, the payment
schedules of all the packages will be revised duly
including the O&M component and the payments will be
regulated.
The agreements were concluded for package 63 & 64
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
62/322
Go To ContentsPerformance Audit Report on Jalayagnam
255
vide Agreement No.64/2004-05, Dt.09.03.2005 and
Agreement No.65/2004-05, D5.11.03.2005. Accordingly
works were grounded. As it is the first time for
grounding of works on EPC System the bills were made
as per the payment schedule appended in the
agreement. Due to stoppage of works by the
Government from dated 04.05.2006 to 11.05.2007 and
for want of forest clearance till 10/2010 the payments
which were made based on the payment schedule in theagreement of Package 63 & 64 could not be regularized.
However, soon after resumption of the works by
1/2011(package63) &12/2010(package64) the Revised
Payment Schedule was prepared and got approved
based on the approved drawings and payments were
regularized in the running account bills of the package
63 and Package 64 by 7/2011. The payments wouldhave regularized, if the work had been under progress.
Because stoppage of works by the Government and non-
receipt forest clearance from the MoEF the regularization
of payment have delayed. Hence interest forgone by
the Department and unduly benefited the contracting
agency for a period of 5 years was Rs.7.45 crores is not
correct.
The procedure adopted by the audit in assessing
Rs.32.93 Crores as premature excess payment is not
rational and incorrect. When actual quantities as per
execution are to be considered in finding out the
entitlement of the contractor for payment, it is
obligatory to consider the relevant revised payment
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
63/322
Go To ContentsPerformance Audit Report on Jalayagnam
256
schedule based on actual quantities of execution to
ascertain the correctness of payments made. The audit
while considering the actual quantities of execution
taken it for granted the payment schedule in the
agreement as granted and assessed the premature
excess payment as Rs. 32.93 Crores in correctly. Also
structures quantity was considered as 150000 cum as
against the probable quantities of 98000 cum.
Further, in the IBM estimate provisions for earthwork,
lining, and CM& CD works are 52.14%, 21.36%, and
26.50% respectively. As per schedule II of agreement
percentage of earthwork, lining and CM& CD works are
33.51%, 44.49% and 22%. The percentages components
approved are much lower than the IBM provisions and
payments were made at lesser percentages than theeligible percentage (as per IBM). As the payments for
earthwork were being made at lower percentages and it
was considered to revise the payment schedule after
finalisation of actual quantities based on detail designs and
estimates.
As per the detailed estimate quantities the %
components of earth work, lining and structures are
worked out as 55.55%, 25.79% and 18.66% respectively.
Even from the actual quantities view, percentage
component approved in respect of the earthwork and
lining are advantageous to the department.
Had the payments were made with reference to
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
64/322
Go To ContentsPerformance Audit Report on Jalayagnam
257
quantities, more component would have been paid in respect
of earthwork and in case of lining premature excess payment
does not arise since lining is to be done after the earthwork is
completed and lining was completed to the extent of earthwork
completed.
However, it is submitted that required component schedule
was approved as per hydraulic particulars but at present the
matter is Sub judice. Necessary action will be taken toimplement the revised payment schedule with detail
quantities.
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
65/322
Go To ContentsPerformance Audit Report on Jalayagnam
258
5.2.21 Payments for price variations
Polavaram Project:
Inrespect of ISLMC package 2, as per Clause 37.2:37.3 and
38.1 of E.P.C, the work awarded on a lump sum contract on
EPC Turnkey basis, the contractor will be paid a firm contract
price for completion of all works as specified under the scope
of the work.
CNS soil treatment is one of the operations involved in the
finished item of work of lining, it can not be treated separately for
inclusion or deletion of the work.
However, the percentage of fuel factor was worked out as
per IBM is 12.003% and percentage of fuel factor worked out as
per actual quantities of value of work is 12.554% (copy enclosed).The percentage of fuel factor considered for payment is in
accordance with the IBM is less than the actual percentage of fuel
factor to be paid to the contractor. Hence, the remarks of the
performance audit stating that an amount of Rs. 68.10 Lakhs
excess paid to the contractor is not correct
Inrespect of ISRMC package 2, the fuel component in the
work was worked out based on the state level standing
committee recommendation and IBM estimate quantities.
The percentage of fuel component as per IBM estimate
worked out to 12.20%
For assessing the fuel component, if the actual execution
quantities were considered i.e., quantities as per approved H.Ps
-
7/27/2019 Response-Audit Report on Jalayagnam-Vol.2
66/322
Go To ContentsPerformance Audit Report on Jalayagnam
259
the percentage of fuel component works out to 14.12 %, which is
higher than approved value of 12.20%. In order to assess the fuel
component, either IBM estimate (as being done in all other works
across the State) or revised estimate with actual quantities shall
be considered. If the provision of gravel backing was not to be
considered as it was not executed, then the increased quantities of
earth work, concrete and other items as per approved drawings
and as per actual execution should be considered.
As the % component with reference to IBM es