rev 3 to 'inservice insp for pumps & valves.' · 2017. 9. 18. · the testing methods...
TRANSCRIPT
Page 2 of 113
SUSQUEHANNA STEAM ELECTRIC STATION UNIT 1
PUMP AND VALVE INSERVICE INSPECTIONTESTING PROGRAM
The pump and valve ISI testing program at the Susquehanna SES Unit 1 will beconducted in accordance with the 1980 Edition of Section XI of the ASME Boilerand Pressure Vessel Code incorporating through the Winter 1980 Addenda.Specific exceptions from these requirements are included here as ReliefRequests. The inservice portion of the program commences at the receipt ofthe Operating License.„ Requirements for specific components commenceconcurrent with Technical Specification operability requirements.
For valves so equipped, remote position indicators will be utilized todemonstrate valve operability. Proper functioning of these positionindicators will be demonstrated at least once every 24 months. Pressurerelief valve testing will be conducted using test procedures which incorporatethe testing methods of Section 4.09 of ANSI/ASME PTC 25.3-1976. Theprovisions of Paragraph IWV-3511 shall begin at the receipt of the operatinglicense. Thermal relief devices are excluded from the program. With theexception of valves providing a high pressure to low pressure boundary(pressure isolation function), valve leakage rate testing and acceptancecriteria will be based on 10CFR50 Appendix J requirements as discussed in FSARSubsection 6.2.6 and Susquehanna SES Technical Specification 3/4.6.1.2.Pressure isolation function testing is discussed below.
Excess flow check valves are installed on instrument lines penetratingcontainment in accordance with Regulatory Guide 1.11. As such, the lines aresized and/or orificed such that off-site doses will be substantially below10CFR100 limits in the event of a rupture. Therefore, individual leak ratetesting of these valves is not required for conformance with 10CFR50,Appendix J requirements. Functional testing of valves to verify closure canbe accomplished by the process of venting the instrument side of the valvewhile the process side is under pressure. Such testing is required byTechnical Specification 4.6.3.4 at least once per 18 months. Testing on amore frequent basis is not feasible for several reasons. Instruments servicedby these valves frequently have interlock or actuation functions that would beinterfered with should testing be performed during plant operation. Also,process liquid will be contaminated to some degree, requiring special measuresto collect flow from the vented instrument side. Functional testing withverification that flow is checked will be performed at least once per 18months per Technical Specification 4.6.3 via SI-199-205. A listing of excessflow check valves can be found in Technical Specification Table 3.6.3-1.
Check valves whose safety function is to open will be full-stroke tested.Since disc position is not always observable, verification of the safetyanalysis design flowrate through the valve is considered an adequatedemonstration of the full-stroke requirement.
~>o>ozoigpPDR ggDCg ~412g16 a5000387
PDR Revision 311/84
I1
~ ~
1I 11 1'
t
I
K
h
'llrt
PI
4 4 I
~ P
I,S
PM ~ I
Pth
l f P
4
MM
1 ~ rtrh
P
'
P M 11) P
4 1
Page 3 of 113
Valve stroke times listed herein reflect current values. In the event of arepair, replacement, or system redesign; stroke times may be changed inaccordance with IWV-3413. In addition, changes in FSAR or TechnicalSpecification stroke times may require program plan changes. Any changes tovalve stroke times will be documented in the Valve Record and incorporated inthe next program plan revision.
J
Where devices monitoring appropriate parameters exist, permanently installedinstrumentation will be used during pump performance testing. Both permanentplant instrumentation and measuring and test equipment will be maintained bythe Instrumentation and Controls Section in accordance with theiradministrative procedures.
Revision 311/84
rrl) ~I ) I N N ~I
I*
I )
)
N I Nil
I 'I
)I'
IN r
* ff'll) IN~ )
Page 4 of 113
LEGEND FOR VALVE TABLES
Valve Number: Unique system designated valve identificationHV — hand switch-operated valveSV — solenoid-operated valvePSV — pressure safety/relief valveXV- excess flow check valveFV — flow control valvePSE — rupture disks
ASME Class: ASME Code Classes 1, 2, and 3S - non-code valve which performs a safety-related function
PGID Coordinates: Location of valve on PAID drawing
Section XI Valve Category: A — valves with specified maximum leakage rate
B — valves with no specified maximum leakagerate
C — self-actuating (check, relief valves)
0 D — actuated by energy source capable of onlyone operation (rupture disks, explosivevalves)
Active: Valves required to change position to accomplish specified safetyfunction
Passive: Valves not required to change position to accomplish specified safetyfunction
Size: Nominal valve size in inches
Valve Type: C-B—G-
GL—RV-
XFC-RD-BA—X-
SC—
Check valveButterfly valveGate valveGlobe valvePressure relief valveExcess Flow Check valveRupture DiskBall valveShear (explosive valve)Stop Check valve
Actuator Type: M —MotorA — AirS — SolenoidH — Hand (manual)
Revision 311/84
h
Ph
yr
I'
IP
PI, I
I PP I
IIIP
I'
P
I II h
h I I P I 1
Page 5 of 113
—— None (self-actuated)E/H — Electro-hydraulic
Remote Position Indicator:(RPI)
X — valve is equipped with an RPI- — valve is not equipped with an RPI
Stroke Time: Time required for valve movement (in seconds)
Normal Position: C — closed0 - open
Test Requirements:MT
LTCV
SRV
DT-
quarterly exercise teststroke time measurement concurrent with quarterlyexercise testleakage rate test once per 24 monthsquarterly check valve exercise testsafety/relief valve lift setpoint test in accordancewith ASME PTC 25.3-1976, Section 409 (testingschedule per Table IWV-3510-1)category D test requirement
Relief Request: Yes/No and number(s) of applicable relief request(s)
CS — Testing shall commence no later than 48 hoursafter the plant enters Cold Shutdown (OperationalCondition 4) from Power Operation. Valves inthis category are subject to testing if they havenot been tested in the previous 92 days. Testingshall continue until all subject valves aretested or the plant begins startup. Testing at
, 'ubsequent cold shutdowns will'ommence withthose valves having the longest interval (ifgreater than 92 days) since previous tests. Thisdefinition applies to all relief requests withcold shutdown alternative testing.
RR — every 18 or 24 months as specified in reliefrequest
See relief request — specific guidance inindividual relief request
Remarks: Notes on any special methods of testing. If identified as apressure isolation valve, additional leak rate testing will beperformed (water as test medium) at 1000 +10 psig with an acceptancecriterion of 1 gpm. Valve testing configurations will be similar tothat utilized for containment local leak rate testing.
Revision 311/84
l
r
0II[,
l
II
LEGEND FOR PUMP TABLE
Page 6 of 113
Pump Number: Unique designated pump identification number
Pump Name:
ASME Class:
Commonly recognized pump name
ASME Code Classes 1, 2, and 3S - non-code pump which performs a safety-related
function
Parameters Measured: Required test measurements in accordance withSection XI, Subsection IWP
X — Parameter will be required to be measuredSpecific code exemptions listed
Test Frequency: Scheduled test implementation frequency
Relief Request Number: Reference to individual relief requests from coderequirements
Remarks: Notes on methods of testing.
Revision 311/84
c y 't 4 t I, ~4 ~4 ~ ~
4
Page 7 of 113
VALVE TABLES
Revision 311/84
SERVICE WATER H~109
ValveNum.bar
C
CIIM & 0A CP De CP
MOC
C'0
~u cl CO) CI0 M uCI a IOIII ) CP
B C
00)
~u cou Io
D
0C
~uCl
Cl )II~u aIII'
0 Cl0 CO
00 u
ClIO B0
00 uu CI 0 Cl0 u 0
0 A 0n '0
0 OI 0 uOC M CO
C0
~AIO
~A uOI C
Deg'4
80 Cl CIZ P
IO'eliefRequestReqld
Testing,Alternative Renarks
HV-10943A2 3 E-5
HV-10943B2 3 C-5 X
X 4 B A X 60 0 Q HT
4 B A X 60 0 QINT
No
No
SERVICE MATER M-110
ValveNumber
4lIJCJ
C
MO ~OCPP H >CP 0WCJ CP4 CJ
PC:
0JJCP
CP
CPP
>40'0 CO) CPJJ
C>) O
A B C D
CP ))~8 CO
CJ >PCP CP
C>4
C~ >4
Cl.CP )
>C~~ CJ
Cll
00
0 CJ
>Po
C>4 00 CJCJ CPP
CP CJ 00Q '0
0 0 mCP >4
CJJC0CJ
CPP
00JJ Ol>4 Cl
C0 Cl
CP 8
CJ
8O 0 Cl& CC:
ReliefRequest
RcqcdTesting
Alternative Remarks
1-10-109
1-10-112
3 F-5
3 E-5
HV-.11024Al 3 F-5
HV-11024B1 3 E-5
HV-11024A2 3 F-5
HV-11024B2 3 E-5
X
X
X
X
X
X
X
X
X
X
1 C
1 C
10 B
10 B
10 B
10 B
A X
A X
A ~ X
0 CV
0 CV
60 C Q>MT
60 C Q>MT
60 C Q,MT
A X 60 C Q>MT
Ycs
Ycs
No
No
No
No
24 See Relief Request.
24 See Relief Request.
ap
Oo r.c ep
PJ ~
0
EMERGENCY SERVICE WATER M-111 Sheet 1
ValveNumber
lJec
A I40
v5 0Cl O
B-6
0-11-002
0-1 L-003
0-11-004
0-11-033
0-11-034
3 B-5
B-3
3 B-3
D-7
D-7
0-11-035
0-11-036
D-5
D-5
0-11-037
0-11-038
D-3
D-3
0-11-039 3 D-2
0-11-040 3 D-1
0-11-001 3
-M
c0 0
~A 0 COll ) 0VM ll0 0 0Cll) O
A B C
X
X
X
X
X
D
X
X
X
a
X
18 C ~
18 C
18 C
18 C
8 C
8 C
8 C
8 C
8 C
8 C
8 C
8 C
JJ0ll0llV
c0ll0 '4
0ll
C4 M
eJC0~JCO
c0lJ ll
~ r4 lJco c0 CP
0J 8
0 v 0& C4
C CV
C CV
C CV
C CV
C CV
C CV
C CV
C CV
C CV
C CV
C CV
C CV
ReliefRequest
Req'd
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
TestingAlternative
51 See Relief Request.
51 See Relief Request.
51 See Relief Request.
51 See Relief Request.
27
27
27
27
27
27
27
27
Remarks
Open check only
Open check only
Open check only
Open check only
(D
(0W Vl
0
7
EMERGENCY SERVICE WATER (Continued)
ValveNumber
CI '0ccc A
cfl M ca 0eo 0cJ A
MX40 0
Cc CO0OM IJ444
CJJ 0
B C D
ClCl) pc
O0
40
Cl cC
0 IJ~ cc
0Oc 0
0 IJu Cl 4cC IJ Oun 84O CJ C
$4 M
oCl 4cc 0
IJ
g Cll0
Oc
4ou 0CJI Z
IJ4
~AIJCC
0'l
CP~ gg
ReliefRequest Testing
Req'd f Altcrnativc Remarks
HV-01101 A 3 B-6
'V-01101 B 3 B-3
HV-01101 C 3. B-5
HV-01101 D 3 B-3
HV-01110 A 3 D-7
HV-01110 B 3 D-3
HV-01110 C 3 D-5
HV-01110 D 3 D-2
HV-01112 A 3 D-7
HV-01112 B 3 D-3
HV-01112 C 3 D-5
HV-01112 D 3 D-2
HV-01120 A 3 D-6
HV-01120 B 3 D-3
HV-01120 C 3 E-4
HV-01120 D 3 E-1
HV-01122 A 3 E-7
HV-01122 B 3 E-3
C ibHV-01122,C 3 E-5
Cot c
~ co'V-01122 D 3 . E-l0
X
X
X
X
X
X
X
18 B M- X 39 C Q,MT No
18 B M X 37 C Q.MT
18 B H X 41 C QIHT
8 B M X 37 C Q,MT
No
No
No
8 B H X 37 C Q,HT No
8 B M X 36 C Q,MT
8 B M X 38 C
8 B M X 39 C Q,MT
8 B M X 36 C Q,HT
8 B M X 37 C Q,HT
8 B M X. 37 C QIHT
8 B M X 37 C Q,HT
8 B M .X 34 C Q,HT
8 B H. X 36 C Q,MT
8 B H X 38 C Q,MT
No
No
No
No
No
No
No
No
No
No
8 B
8 B
8 B
M X 38
M X 36
M X 37
C Q,MT
C Q,MT
C Q,MT
No
No
No
8 B M X 38 C Q,MT No
18 B M X 37 C Q,MT No
* Eor a diesel generator,for that diesel.
onc 'switch controls operation of both supply and both return valves, placing either ESW loop A or loop B in service
FAERGENCY SERVICE WATER M-111 Sheet 2
ValveNumber
ch w<o ).OJ A
M
C0 0
0 OOlJ ) OIV&lJOI OI IOIh ) Cl
B C
OIOI )) t4
0 4 c"
C~ A
OIOl )IJ
~A 0Ih
C0
0 llIO0
OJ DI 00 JJlJ OI 00 JJ V
0 rilJ S '0V OI
OIJO0OJ
Ih
C0lJ IO~4 JJIO C0 OI
$4 8
PlJ
0 OI OIR OO
ReliefRequest
Req'dTesting
Alternative Remarks
HV-1114I3A
HV-11143B
3 '53 G-2 4 B A X'0 C Q,MT No
4 B A X 60 C Q,MT No
(D
00CO
0
RHR SERVICE WATER M-112
ValveNumber
cCcC, Cc
CPP ~ 44» 0,040
»4PC
c0 0
~»4 0 CC) CP0CP CC CP
CPP ) CP
A B C D
0C
~ »4
CP )PC
~ H 0CPP
C0
cC0 14
PP4 00 4»4» CP cCCP 44 CP0»444 n '00 cP C
CC»4
CPJC04»
0
0cpc
44c
CP CP
ReliefRequest
Req'dTesting
Alternative Remarks
1-12-001 3 D-3 X X 20 C C CV No Open check only, verifyoperation during pumptest.
1-12-003 3 B-3
.1-12-009 3 E-j
1-12-010 3 B-7
X X
X X
X X
20 C - - - C CV
20 C — - — C CV
20 C — — - C CV
No
No
No
Open check only, verifyoperation during pump test.
Open check only, verifyoperation during pumptest.
Open check only, verifyoperation during pumptest,
HV-11210 A
HV-11210 B
3 E-6 X
3 B-6 X
X 20B M X 40 C Q,MT No
20 B M X 40 C Q»MT No
~ psap ~
CPO )P.W CPP
0
C»l
PSV-11212 A 3 E-7
PSV-11212 B 3 B-7
HV-11215 A 3 E-7 X
HV-11215 B 3 B-7 X
HV-01222 A 3 G-2 X
HV-01222 'B 3 G-0 X
HV-01224 A1 3 0-3 X
HV-01224 A2 3 G-3 X
HV-01224 B1 3 C-1 X
X
X
X
4 RV C SRV No
4 RV
20B M X
20B M X
36B M X
36B M X
C SRV No
40 C Q,MT No
40 C Q MT No
40 C Q,MT No
40 C Q,MT No
24B H X
30B M X
40 C Q,MT No
40 C Q,MT No
30 B M X'0 C Q,MT No
0
0
RHR SERVICE HATER (Continued)
Valve-Number
CPJlCP
A PC
M 0cPP 0SPc CP
MPc:
C0rl CPV )V MV
CPP )0CD
CP
O
A B C D
V0
~I~ A CD
CP CD
V CPClc
)0CP~P
C0
0Clc 0
~PCP CP
V0s '0CP C
CP'
0JC0CP
V0~ACP CD
CCP C0 CP
0 s
O CP Cl
ReliefRequest
Req'dTesting
Alternative Remarks
HV-01224 M2 3 G-0 X 24 B M X 40 C Q,MT No
HV-IF073 A 3
HV-IF073 B 3
HV-IF074 A S
HV-IF074 B S
HV-IF075 A 2
.D-6
F-6 X
D-6
G-6 X
X
X
X
6 G M X
6 G M X
I GL M
I GL M
40 C Q,'tlT No
40 C Q,MT
20 0 Q,MT
20 0 Q,MT
No
No
No
No6 G M X 40 C Q,MT
HV-IF075 B 2 F-6 X X 6 G M X 40 C Q,MT No
IP078 A 2
IP078 B 2
G-5
D-5
X
X X,
6 C
6 C
C CV
C CV
No
No
Open check only.
Open check only.
I ap
Oo p~ COr.0
REACTOR BUILDING CLOSED COOLING MATER M-113
ValveNumber
CJ M 0VJM aO 0CO C4O
MOC
C0 0Cl OO
OJ P 0VM JJCl lO cO
Cll W O
A B C D
Cl )JJ EO
V OlaJ
m~H
~4 Clth
0JJCl
JJ
m0
0Oc 0
JJCl CC
~J V0 IJ8 '0cl 0
C4 M
B
JC0JJ
m0
~rtCOOJ
lO0 Cl
Oe 8
0 Cl ClZ ROC*
ReliefRequest
Req'dTesting
Alternative Remarks
HV-11313
HV-11314
HV-11345
HV-11346
2 E-7 X
2 E-5 X
2 E-7 X
2 E-5 X X
4 G M X
4 G M X
4 G M X
4 G M X
30 0 Q,MT,LT Yes 1
30 0 Q,MT,LT Yes 1
30 0 Q,MI',LT Yes 1
30 0 Q,MT,I.T Yes 1
CS
CS
CS
CS
DIESEL OIL STORAGE AND TRANSFER M-120
ValveNumber
» «CCJuCJ
a»«
QCJ J4CJ
MJC
cCJ CC«
Cl«JMua a a
«JJ ) CP
B C
Cl )JJ «C
0 aD a «4
0a
~~CJ
CJ )N
~w a«JJ
a0a
«4 uP» P«
»««
0'4 «4 0
08 '0
«J CJ C
«a M
CP
JC0$»JJ«JJ
a0JJ Cl
~6, JJcl a0 CI
C4 8
JJ
O Cl CJ
Relief.Request
Req«dTesting
Alternative Remarks
0-20-007
0-20-009
0-20-012
0-20-015
S E-7
S D-7
S C-7
S B-7
X
X
X
X
X
2 C
2 C
2 C
2 C
C CV
C CV-
C CV
C CV
Yes
Yes
Yes
Yes
47 See Relief Request
47 See Relief Request
47 See Relief Request
47 See Relief Request
Q
co r.4 m
r»0
CONTAINMENT INSTRUMENT GAS M-126
ValveNumber QV oc Cl A
OC
m0 0
~ a ccc cocc>o& c>
cp ccc ccc
c>> m cp
B C D
cc> cl >>0 c>
ci>
m0
cc>
o
0l4 0
o c>cl cc> >0>> i> o
0JJ n 'uo ccp m
OC H
OOPco o
Q co~ r4 o
l4ccl
c>
8 8>J oVl
c>m
>Jco
o'eliefRequest Testing
Req'd 8 Alternative Remarks
1-26-070
1-26-072
2 8-2 XI
c
2 D-2 X
X
X
1 C
C
C CV,LT
C CV,LT
Yes 2 RR
Yes 2 RR
Closure test only,verify operation duringleak test.
Closure test only,verify operation duringleak test.
1-26-074 2 E-2 X X X
1-26-152 2 F-2 X X X
1-26-154 2 F-2 X X X
1-26-164 2 B-2 X X X
3 C - - - C CV,LT Yes 2 RR
1 C - - - C CV,LT Ycs 2 RR
1 C — — — C CV,LT Yes 2 RR
1 C - - - C CV,LT Yes 2 RR
Closure test only,verify operation duringleak test.
Verify operation duringleak test.
Verify operation duringleak test.
Closure test only,verify operation duringleak test.
HV-12603 2 D-2 ~ X 2 GL M X 20 0 Q,MT,LT .No
.PSV-12643 2 F-6
SV-12605 2 D-2 X
X
2 GL S X
I RV
3 0 Q,MT,LT
SRV
Yes
No
38 See Relief Request. Rapid acting valve.
SV-12644 2
PSV-12648 3
F-5 X
E-3
SV-12643 3 F-6 X
X
1 GL 8 X
1 GL S X
1 RV
3 C Q>MT
3 0 QMT
SRV
Ycs
No
38 See Relief Request.
38 Scc Relief Request.
Rapid acting valve.
Rapid acting valve.
SV-12649 2
~N SV-12651 2
0
F-2 X
E-2 X
SV-12648 3 E-3 X 1 GL S X 3 C Q>MT
1 GL S X 3 0 Q,MT
Yes 38 See Relief Request.
Yes 38 Scc Relief Request.
3 GL S X 3 0 Q,MT,LT Yes 3,38 CS
Rapid acting valve.
Rapid acting valve.
Rapid acting valve.
CONTAINHFST INSTRlJHENT GAS H-126 (Continued)
ValveNumber
C~4'4
AM 0~4 0De CJ
IC
40 0
CI COll ) 4va v4 ij ijIII)O
A B C
CJ )rill 4
o".
CI
4~ A
CICIIj
~ 8 ijIII
40
40Ii OJ 00 iJ
lJ CI 44 li V
0 'H8 '0
V Cl CR M
CIJC0llClj
0ll IC~I lJCI m0 CI
Oc BIi
PIJ
0 CI CIZ
ReliefRequest . Testing
Req'd f= Alternative Remarks
SV-12654 A 2 F-2 X
F-2 X
SV-12661
SV-12671
~ D-2 X
2 B-2 X
SV-12654 B 2
X
1 GL S X 3 0 Q,HT,LT Yes
1 GL S X
1 Gl S X
3 0 Q,HT,LT Yes
3 C Q,HT,LT Yes
1 GL S X ~ 3 0 Q,HT,LT Yes
4,38 CS
4,38 CS
38 See Relief Request.
38 See Relief Request.
Rapid acting valve.
Rapid acting valve.
Rapid acting valve.
Rapid acting valve.
~ GI
00 jJ''4 OIjJ ~
0
MSIV LINEAGE CONTROL SYSTEM M-139
Valve i cl
Number 0 o
'0AM 0
0o u A
4C
C0 0
~ e4 Cl C4II ) ClVM IIIC IC
444) O
B C
Cl
IJ CIV Cl
D e o.
V0
m~H
ClCl )44
~A ClIII
00 rI0 44
fE 44OII C4 00V ICu V0
44 8'0V Cl C
44 M
ClJC0'4IJIfl
m044~4 IIIC CO Cl
C4 844
CC
8 44II CI 0'
VZ BCC
ReliefRequest Testing
Req'd 0 Althrnative Remarks
HV-IFOOI B I E-6 X
HV-IF001 F I 8-6 X
HV-IF001 K I B-6 X
HV-IF001 P I B-6 X
X
X
2 G M X 13 C Q,MT,LT Yes 5 CS
2 G M X 13 C Q,MT,LT Yes 5 CS
2 G M X 13 C Q,MT,LT Yes 5 CS
2 G M X 13 C Q,MT,LT Yes 5 CS
Reduced Pressure LeakTest.
Reduced Pressure LeakTest.
Reduced Pressure LeakTest.
Reduced Pressure LeakTest
HV-IF006
HV-IF007
HV-IF008
HV-IF009
2 D-3 . X
2 D-3 X
2 E-3 X
2 E-3
HV-IF002-B 2 D-6 X
HV-IF002 F 2 B-6 X
HV-IF002 K 2 B-6 X
HV-IF002 P 2 B-6 X
HV-IF003 B 2 D-5 X
HV-IF003 F 2 B-5 X
HV-IF003 K 2 B-5 X
HV-IF003 P 2 B-5 X
X 2 G M X
2 G M X
2 G M X
2 G M X
2 G M X
2 G M X
2 G M X
2 G M X
2 G M X
2 G'
X
2 G M X
2 G M X
13 C Q MT
13 C Q,MT
13 C Q,MT
13 CQ,MI'3
C Q,MT
13 C QIMT
13 C Q>MT
13 C Q,MT
Yes
Yes
Yes
Yes
No
No
No
25 C
25 C Q MT
25 C Q,MT
Yes
Yes
Yes
25 C Q,MT Yes
5 CS
5 CS
5 CS
5 CS
6 CS
6, CS
6 CS
6 CS
ib
Co I(or.0
NUCLEAR BOILER M-141
ValveNumber
ci. JJ0o
A
M
c Le0 0
O dd)OM JJdl Ctl C5
CO) CP
B C
Q )JJ m0 co
D K o
0JJcJJV
c0
0 0JJ
dl mJJ o0 rcn 'oCl Ct4 M
dl
0JJth
c0
0Oe
o
JJc
~4JJm
o'l
dlR dd
Relief'equest
ReqldTesting
Alternative Remarks
nl
COOd
I0
1-41-017 2
1-41-018 2
HV-14107 B
PSV-14137 A 3
PSV-14137 B 3
PSV-14137 C 3
PSV-14137 D = 3
PSV-14137 E 3
PSV-14137 F 3
PSV-14137 G 3
PSV-14137 H 3
PSV-14137 J 3
PSV-14137 K 3
PSV-14137 L 3
PSV-14137 M -3
PSV-14137 N 3
PSV-14137 P 3
PSV-14137 R . 3
PSV-14137 S 3
1F010 A 1
1F010 B 1
B-7 X
B-7 X
B-7
B-4
B-4
B-4
B-4
B-4
8-4
B-4
B-4
B-4
8-4
8-4
B-4
B-4
B-4
B-4
B-4
D-6 X
C-6 X
X
X
X
X X
X
X X
X
X
X
X
X X
X X
X
X X
X X
X
X X
'X 1 GL H
24 C
.6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
24 C
24 C
1 GL H
C LT
C LT
0 CV
C 8RV
C SRV
C SRV
C SRV
C 'SRV
C SRV
C SRV
C SRV
No
No
No
Ycs
Ycs
Ycs
Ycs
Ycs
Yes
. Yes
Yes .
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
0 CV,LT
0 CV,LT
Yes
Ycs
Ycs
Yes
Ycs
Yes
Yes
C SRV Yes . 8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
8 Sce Relief Request.
8 Sce
8 Scc
Relief Request
Relief Request.
8 See Relief Request.
8 Sce Relief Request.
7 See Relief Request.
7 See Relief Request.
8 See Relief Request.
8 See Relief Request.—
8 Sce Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Reques't.
8 See Relief Request.
8 See Relief Request.
Open cheek only.
Closure check only.
I
h
NUCI.EAR BOlLER (Continued)
Val'veNumber
v) w >4> 0K CJ OI CJ
4C
00 0
'>I C> DOIJ ) 0VWIJ0 >4 CC
(J>) O4>0
D
0Cl0 IJ
I>0 >I
4> OI 00 4J4> C> CC
IC IJ 00
IJ n '00 C>
>u w
A04>
0IJ I>
C> CO C>
OI 8
8CO O'C> C>
Relief„ RequestReq'd
TestingAlternative Remarks
PSV IF013 A I E-5
PSV-IFOI3 B I E-5
PSV-IF013 C I E-5
PSV-IF013 D I E-5
PSV-IF013 E I E-5
PSV-IF013 F I E-5
PSV-IF013 G I E-5
PSV-IF013 H I E-5
PSV-IF013 J I E-5
PSV-IF013 K I E-5
PSV-IF013 L 'I E-5
PSV-IF013 M I E-5
PSV-IF013 N I E-5
PSV-IF013 P I E-5
PSV-IF013 R I E-5
PSV-IF013 S I E-5
X
X
X X
X X
X X
X X
X X
X
X
X
X
X
X
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
.6 RV
6 RV
6 RV
6 RV
6 RV
A
A
A
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
N/A C SRV>Q
C SRV
No
No
No
No
No
No
Yes
No
N/A C SRV >Q
N/A C SRV Q
Yes
Yes
N/A C SRV,Q Yes
N/A C SRV,Q Yes
C SRV
C SRV
C SRV
No
No
No
N/A C SRV,Q 'es
10 RR
10 RR
10 RR
10 RR
10 RR
10 RR
ADS Valve.
ADS Valve.
ADS Valve.
ADS Valve.
ADS Valve.
ADS Valve.
~ nJ
oo r.o>r.0
HV-IF016
HV-IF019
HV-IF020
I D-3 X
I D-3 X
2 D-2
X
3 G M X
3 G M X
3 GL M X 30 0 Q>MT No
10 0 Q,MT,LT No
10 0 Q,MT,LT No
0
NUCLFJK BOILER (Continued)
Valve,Nucber
AM 0aO 0Oc O
M'
L0 0
~ e4 0 OQVVM IJ
0CO) Cl
B C
c0
04 $4 00 V
0 00 IJ V
0 'HS 'U
V 0 C~C g4
0 Ca) 0
~IV
g CO~6 0
C4
0U
4 80 0CO
0C
nV$ 1
'r40Ol U'
& C4
ReliefRequest
Req'dTesting
Alternative Remarks
HV-IF022 A I E-3 X 26 GL A X >3 0Z5
Q,MT,LT Yes 11 See Relief Request. Reduced pressure leaktest in reversedirection.
HV-IF022 B I C-3 X
HV-IF022 C I C-3 X
26 GL A X
26 GL A X
>3 0<5
>3 0<5
Q,MT,LT Yes
Q,MT,LT Yes
11 See Relief
11 See Relief
Request.
Request.
Reduced prcssure leaktest in reversedirection.
Reduced pressure leaktest in reversedirection.
HV-IF022 D — I C-3 X
HV-IF028 A I E-2 X
HV-IF028 B I C-2 X.
26 GL A X
26 GL A X
26 GL A X
>3 0<5
>3 0<5
>3 0<5
Q,MT,LT Ycs
Q,MT,LT Yes
Q,MT,LT Yes
11 See Relief Request.
11 Sce Relief Request.
11 See Rclicf Request.
Reduced pressure leaktest in reversedirection.
Reduced pressure leaktest.
Reduced pressure leaktest.
HV-IF028 C I C-2 X 26 GL A X >3 0<5
Q>MT,LT Yes 11 See Relief Request Reduced prcssure leaktest.
HV-IF028 D I C-2 X X 26GL A X >3 0<5
Q,MT,LT Ycs 11 Sce,Relief Request. Reduced pressure leaktest.
HV-IF032 A 2 D-8 X
HV-IF032 B 2 C-8 X X X 24 SC M X 120. 0 QiCV.MT,LT
Ycs
24 SC M X 120 0 Q,MT,LT Ycs 12 CS
12 CS
Closure test only.
Closure test only.
PSV-IF037I (D
PSV-IF037oo r
r PSV-IF037
0'SV-IF03740
B 3 B4
C 3 ~ B-4
D 3 B-4
E 3 B-4
PSV-IF037 A 3 B-4 X X
X ~ X
X X
X ~ X
X X
6 RV
6 RV
6. RV
6 RV
6 RV
SRV
SRV
C SRV
C SRV
C SRV
Ycs
Ycs
Yes
Yes
Yes
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
0
NUCLEAR BOILER (Continued)
ValveNunbcr
clcl
ccl ~
C$
n
AH 0s4 044m A
C0 0
~ cc Cl 44) Cl0 W 44Cl 4$ 4$444) O
B C
~ Cc44
D
uIQ)Cl .ri
C4 ccl
04445
440
0
0444 0
44Cl C$44 00 rln 'clcl n
ClA04444
044 ccl
~A 44Co C0 Cl
$44 844
8 e~O 0 Cl
& 44
ReliefRequest
Req'dTesting
Alternative Renarks
PSV-1F037 F 3
PSV-1F037 0 3
PSV-1F037 H . 3
PSV-1F037 J 3
. PSV-1F037 K 3
8-4
8-4
B-4
B-4
B-4
PSV-IF037 M 3
PSV-1F037 N 3
PSV-1F037 P 3
. PSV-1F037 R . 3
PSV-1F037 S 3
B-4
B-4
B-4
B-4
B-4
PSV-'1F037 L 3 B-4
X
X
X
X
X
X
X
X
X
X
X
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
6 RV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
C SRV
Yes
Yes
Ycs
Yes
Yes
Ycs
Ycs
Yes
Yes
Yes
Yes
8 See Relief Request.
8 Sec Relief Request.
8 See Relief Request.
8 See
8 See
Relief Request.
Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
8 See Relief Request.
CO )colr.0
REACTOR RECIRCULATION M-143
ValveNumber
4l«C
m
«C M 0«JI M ««J 0W CJ SJ«CJ
00 0
~H Cl COClVM 4J
Cl CJ «C«JJ m O
A B C D
0
m w 4«~rl & 0
JJ«C
CI«4 M JJ~4 «C V
«II
0~AJl
0 4«$4«0
4JCl Cl~J V08 MCl C
4«'
Cl
0JJ«JI
m04I ~4«4 4Icl 00 ClJJ«n
P,0 Cl Cl
ReliefRequest
Req'dTesting
if Alternative Remarks
IF013 A
IF013 B
2 B-6 X X
2 A-6 X X
HV-IF019 I 0-4 X
HV-IF020 I G-3 X
HV-IF031 A I B-4
HV-IF031 B I A-4
HV-IF032 A I B-4
HV-IF032 B I A-4
XV-IF017 A 2 B-7 X'
XV-IFO)7 B 2 A-7 . X X
X
X
X
I C 0 CV,LT Yes
I C 0 CV,LT . Yes
I XFC - X
I XFC - X
3/4 GL . A X
I GL A X
28G M X
0 CV ILT
0 CVJLT Yes
2 C QIMT,LT Yes
2 C Q,MT,LT Yes
33 0 Q,MT
Yes
No
4 G M .X 30 0 Q,MT No
28 G M X 33 0 QIMT
4 G M X '30 0 Q MT
15 RR
15 RR
14 RR
14 RR
38 See Relief Request.
38 See Relief Request.
16 CS
16 CS
Closure test. only.
Closure test only.
Closure test only.
Closure test only.
Rapid acting valve.
Rapid acting valve.
ps)D
Cool
0'
RECTOR 'WATER CLEANUP M-144
ValveNumber
oCCC&, 4 040 CCc0
OC
0 ~
0 0~rl 0 Docc ) 0VW CJCP cC CCC
ccc m'p
B C
00
CC CO
0 CC
9 e,o
~6
tl 0co
CC
0JJCC
CC
0
00
0CCc 0
CJ0 ccc
CC 008 '00 C
C4 M
00CC
0CCc
0z
CC
CC
8
CO
47 0& cu
ReliefRequest
Reqcd gTesting
Alternative Remarks
HV-I'FOOI I F-7 X X 6 G M X 30 0 Q,MT>LT No
HV-IF004
HV-IF04c2
H'V-IFI04
F-7 X
2 F-2 X
2 F-3 X
X 4 GL M X
4 GL M X
80 0 Q,MT,LT No
80 C Q,MT,LT No
6 G M X 30 0 Q,MT,LT No
CONTROL ROD DRIVE M-147
ValveNumber
'jm
AoM M ~ o
l4 D
C0 0t4 JJ Cg
mVH JJm m JJCO) CP
A B C
m) r4~IJJ m
a"
mo
C~ H
oo )JJ
mJJJ
m
'40JJaJJo
mo
o $4c4 0
JJmJJ 008 Mm C
JJ M
m0
~A
0Ov
8 8JJ oCll
JJm
~ e4JJm o'
m&
JJ'eliefRequest=Req'd
TestingAlternative Remarks
114*
115*
2 D-5
2 B-4
XV-127* 2 D-5
138" 2 B-6
XV-IFOIO
XV-1F011
S G-2
S D-4
XV-126* 2 B-5
~ X
X
X
X
X
X
X
X
3/4 C
I/2 C
1/2 GL A
1/2 GL A
1/2 C
1 GL A X
C CV
C CV
N/A C
N/A C
0 CV
30 0 Q.MT
2 GL A X 30 0 Q,MT
Ycs
Yes
Yes
No
No
17 See Relief Request.
17 See Relief Request.
17 See Relief Request.
17 See Relief Request.
17 See Relief Request.
Open test only.
Closure test only.
Open test only.
Open test only.
Closure test only.
*There are a total of 185 sets of these valves, one for each of the 185 CRD Hydraulic Control Units.
Oo(h
0
STANDBY LIQUID CONTROL M-148
Valve.Nucber
1F004 A
1F004 5,
lOlo Cl
V)M 40Wo CJCJ
2 D-7
2 D-7
M
C0 0~rl OJ COJJ 0 OJOM JJOl C COJ) CJ
B C D
OJ rlOP) v4
~8 0 OJJJ OJ OJO C
OJ OO
C0
~O
0OJ 0
o JJJJ OJ IOC JJ O
0 t4JJ n 'oo oJ C
JC M
S~A
Ol
oJJ
CoJJ CO
JJCO
0 OlCJ 6
O Ol& lC
X X 1$ X C DT
X X 1$ X - - — C DT
ReliefRequest Testing
Req'd f Alternative
No
No
Recarks
Explosive Valve.
Explosive Valve.
HV-IF006 1 D-7 X X 1$ SC M X 34 C Q,MT,LT,CV
Yes 18 RR Closure test vith aotoroperator, open test durihgreactor vessel infection test.
1F007 1 D-8 X X 11' C CV,LT Ycs 19 RR Closure test duringleak test, open test duringreactor vessel in)ection test.
PSV-1F029 A 2 D-5
PSV-1F029 B 2 C-5
IF033 A 2 B-5
X
X
11'V — - — C SRV No
1$ RV - - - C SRV No
14 C - - — C CV No Verify operation duringpucp test.
1F033 B 2 C-5 X IQ C - - - C CV No Verify operation duringpunp test.
REACTOR CORE ISOLATION COOLING M-149
ValveNunber
1-49-020
HV-1F007
4lou
EO
CO
ch ~ ab o~c cp Qecp
2 C-4 X
1 D-5 X
c0 0~I Q DQ
oQW jlo c cCO) CD
A B C
o )) pl
D e o
C~rl
~ e4 cCO
1 GL
4 G
c0
Clon F4 00 Jlll o c
C5 IJ oun 84v o CC M
A04
CO
oDe
lJC
8Se
R c4
C LT
ReliefRequest
Req'd
No
M X 20 0 Q,MP,LT Yes
TestingAlternative Renarks
20 See Relief Request. Leak test in reversedirection.
HV-1P008 2 D-5 X
HV-IF013 2 C-4 X
FV-1F019 2 C-5 X
1F021 2 C-3 X X X
IF028 2 B-4 X X X
HV-1P031 2 B-6 X
4 G M X 20 0 Q,MT,LT No
6 G M X 15 C g,MT,LT No
2 GL M X 20 0 g,MP,LT No
2 C - - - C CV,LT Yes
2 C - — - C CV,LT Ycs
6 0 M X 35 C Q,MT,LT Yes
21 RR
21 RR
20 See Relief Request.
Leak test in reversedirection.
Closure test only.
Closure test only.
Leak test in reversedirection.
1P040 2 C-4 X X
HV-1F059 2 C-5 X
HV-1F060 2 B-5 X
10 C
10G M X
2 GL M X
C CV,LT Yes
60 0 Q,MT,LT Yes
25 0 Q,MF,LT No
21 RR
20 Sec Relief Request.
Closure test only.
Leak test in reversedirection.
Leak test in reversedirection.
HV-IP062
HV-IF084
2 C-4 X
2 C-5 X
2 G M X 10 0 Q,MT,LT No
2 G M X 10 0 Q,MT,LT Yes 20 See Relief Request. Leak test in reversedirection.
HV-1F088 1 D-5 X 1 GL 'A X 3 C Q,MT,LT No Leak test in reversedirection.
1F063
co ) 1F064~ CO
0
C-5
2 C-5
C - - - C CV
C CV
Ycs 22 RR
22 RR
Open check only.
Open check only.
RESIDUAL HEAT REMOVAL M-151 Sheet I
ValveNumber
ej>ec
~A'oA»00
0> CP
XC»'0
~I o >o>> ) CPow >>e >> eCO) CP
A B C
0
D e o"
C~ et
e>>
cO ~ W
o
»o~ >cj
>>
0
o>» o
>>>> e>J o0n 'ue
C>'
O>I>>
co
oo>
0
ReliefRequest
Req'dTesting
Alternative Reaarks
HV-IF003 A 2 D-6
HV-IF004 A 2 C-3 X
20 G M X 110 0 Q>MT No
24 G M X 120 0 Q,MI',LT Yes 20 See Relief Request. Leak test in reversedirection.
HV-IF004 C 2 C-2 24 G M X 120 0 Q,MT,LT Yes 20 See Relief Request. Leak test in reversedirection.
lD
co r.~lO
Qo0
HV-IF006 A 2 C-3 X
HV-IF006 C 2 C-2 X
HV-IF007 A 2 D-3 X
HV-IF011 A 2 C-8 X
HV-IF015 A I E-3 X
HV-IF016 A 2 G-4 X
HV-IF017 A 2 E-5
HV-IF021 A 2 G-3
HV-IF022 I G-3 X
HV-IF023 I G-3 X
HV-IF024 A 2 D-3 X
HV-IF027 A 2 D-3 X
HV-IF028 A 2 D-5 X
4 G M X 14 C Q MT LT No
24 G M X, 24 C Q,MT,LT Yes 26 CS.
12 GL M X 90 C Q,MT,LT No
24 GL M X
120 M X
6 G M X
30 0 Q,MT No
75 C Q,MT No
30 C Q,MT,LT Yes 20,26 CS
.6 G M X 20 C Q,MT,LT Yes 26 CS
18 GL M X 194 C Q,MT No
6 GL M X 46 C . Q,MT No
18 G M X 90 C Q,Ã1'>LT No
20 G M X 120 C Q,MT No
20 G M X 120 C Q,MT No
6 G M X 32.5 0 Q,MT,LT Yes 20 See Relief Request. Leak test in reversedirection.
Pressure isolationvalve.
Leak test in reversedirection.
RESIDUAL NFL REMOVAL (Continued)
Valve 0 >c
Number 2 u
M
C $40 0~4 0 C>>l> ) C>OW lJCl 4$ Cj
C>> W CJO >4M 00 o A B C D
C>
N.Cl
>>4
0C
~A
C>C> )>l
CO
00 c>0 CC
C! 440 ll
'4> 4Pe n0>4 C4 00 lJlJ C> C$ C>
>C lJ 00 44 08 '0 >4
>J ci mc IL H CO
00
0>>4
0R
~J
>C0'>
C>
ReliefRequest Testing
Rcq'd f Alternative Remarks
IF031 A 2
IF031 C 2
IF046 A 2
IF046 C 2
A-4
C-4
B-4
C-4
20 C
20 C
4 C
4 C
C CV
C CV
CV
C CV
No
No
No
No
Open test only.
Open test. only.
HV-IF047 A 2 C-5 X
HV-IF048 A 2 D-5 X
HV-IF050 A I E-3 X X
PV-IF051 A 2 C-8 X
HV-IF053 A 2 C-7 X
PSV-IF055 A 2 C-5 X X
SV-IF079 A 2 B-6 *X
HV-IF103 A 2 C-4 X ~
X
X
No
No
24 C C CV>LT Yes4
6 GL A X N/A C Q>MT
4 GL A X N/A C Q>MT
Ycs
8 RV C LT,SRV No
I GL S X
I GL M X
3 C QMT
N/A C LT
Yes
No
20 G M X 110 0 Q>MT
24 GL M X 147 0 Q,MT
26 CS
25 CS
25 CS
38 See Relief Request.
Pressure isolationvalve.
Rapid acting valve.
Leak test in reversedirection.
PSV-15106 A 2 B-5 X X X I RV - - - C LT No
HV-IF122 A I E-3 X I GL A X 3 C Q>MT>LT Ycs 26,38 CS Prcssure isolationvalve. Rapid actingvalve.
IF090 A 2 F-5 X 2 C - - - .0 CV Ycs 24 See Relief Request. Closure test only.
> n>
CX) P~co
0
-RESIDUAL HEAT REMOVAL M-151 Sheet 2
ValveNumber
I>uC'0
CIH 0ad 00> &
MOC
C I>000) I(>u M 00 0I>) C
C>> O
A B C
0 ))D e 0
0C ClO >>
I>0 u
0» . 80
I> l4 00 uI> 0 0 I>co u 0 A
0 r4 0u nm0 0 CI>' I>>
C0u >>
~A I>»
Oeg
>> rl8O 0 >>
ReliefRequest
Req'dTesting
Alternative Remarks~
HV-IF003 B 2 D-3 X
HV-IF004 B- 2 C-7 X
HV-IF004 D 2 C-6 X
HV-IF006 B 2 C-7 X
HV-IF006 D 2 C-7 X
HV-IF007 B 2 D-6 X
20 G M X 104 0 Q>MT No
24 G M X 120 0 Q,MT,LT Yes
20 G M X 115 C Q,MT No
20 G M X 120 C Q,MT No
6 G M X 32.5 0 Q,MT,LT Yes
24 G M X 120 0 Q>MT>LT Yes 20 See Relief Request.
20 See Relief Request.
20 See Relief Request.
Leak «est in reversedirection.
Leak test in reversedirection.
Leak test in reversedirection.
HV-IF008 I E-6 X 20G M X 52 C Q>MT,LT Yes 23 CS Pressure isolationvalve.
HV-IF009 I E-7 X X 20G M X 52 C Q,MT,LT Yes 23 CS Pressure isolationvalve.
HV-IFOII B 2 D-5 X
HV-IF015 B f F-6 X
HV-IFOI6 B 2 G-6 X
HV-IF017 B 2 E-5 X
X
12GL M X 90 C Q,MT,LT No
24 GL M X 30 0 Q,MT No
4 G M X 14 C Q,MT,LT No
24 G M X 24 C Q,MT,LT Yes 26 CS Pressure isolationvalve.
HV-IF021 B 2 G-7 X X 12 G M X 73 C Q,MT No
Q
CoCO
0
HV-IF024 B 2 D-6 X
HV-IF027 B 2 D-6„ X
HV-IF028 B 2 E-5 X
No
6 GL M X
18 G M X
41 C Q,MT," No
90 C Q>MT>LT No
18 GL M X 188 C Q,MT
RFBIDUAL HEAT REMOVAL (Continued)
ValveNumber
>>J C>
C O
uCj0'0
A0
~J> 0>» CJ
M
C0 0
~» Cl 00>J ) ClVA JJ0 >C >C
V>) O
A B C D
Cl)»JJ oV Cl
0>
u0
CI »0 JJ
Cl0» 0> 0
0 0 >JV
0u 6%V Cl C
>4 ~
ClJC0>JVl
00
0>J>
a80
JJ
uC>
0'l
CJ&l>'eliefRequest Testing
Req'd 8 - Alternative Renarks
IF031 B B-6 20 C C CV . No
IF046 B
IF046 D
. HV-IF047 B 2
HV-IF048 B 2
C-6
B-6
C-4
E-4
IF031 D 2 A-5
X
X
X
X
20 C
4 C
4 C
C CV
C CV
C CV
24 GL M X 147 0
20 G M X 115 0 Q>MT
No
No
No
No
No
Open test only.
Open test only.
HV-IF050 B I E-7 X X 24. C C CV,LT Yes 26 CS Pressure isolationvalve.
PV-IF051 B 2 C-5 6 GL A X N/A C Q>MT Yes 25 CS
HV-IF053 B 2 D-4
PSV-IF055 B 2 D-4 X
SV-IF079 B 2 C-2
HV-IF103'B 2 C 3 X
X
X
X
X
X
4 GL A X = N/A C Q>MT
8 RV C LT>SRV
I GL S X 3 C Q>ÃI'
GL M X N/A C LT
Yes
No
Yes
No
25 CS
38 See Relief Request. Rapid acting valve.
Leak test in reversedirection.
PSV-15106 B 2 C-3 X I RV - — - C LT No
PSV-IF097 2 A-5 X X X 4 RV C LT,SRV No
HV-IF122 B I E-7 X I GL A X 3 C Q,MT,LT Yes 26,38 CS Pressure isolationvalve. Rapid actingvalve.
PSV-IF126 I E-7 X X I RV C LT No
G>
COL ~
C Clr.0
IF090 B 2 F-5 X 2 C 0 CV Yes 24 See Relief Request. Closure test only.
CORE SPRAY M-152
ValveNumber
llaCs4'0
A IiM 0>e 0
A
)'u
0 0~ t4 0 IOI> ) 00 MIp >I CjI>I) O
B C
Cl)ll lO0 0
D
0C
~A
0Cl )>I
~ 8C>I
c00 rl
0, l>
c>0
I> )i 00 llu 0>ICI l> 0
0l> n0 Ol C
p4 M
c0
00>
uc
uC>> 0
ReliefRequest
Req'dTesting
Alternative Remarks
HV-IF001 A 2 B-6 X 16 G M X 80 0 Q,MT>LT Ycs 20 See Relief Request. Leak test in rcvcrsedirection.
HV-IF001 B 2 B-7 X 16 G M X 80 0 Q,MT,LT Yes 20 See Relief Request. Leak test in reversedirection.
IF003 A
IF003 B
IF003 C
IF003 D
2 D-4
2 D-2
2 D-4
2 D-2
HV-IF004 A 2 E-5 X
HV-IF004 B 2 E-5 X
HV-IF005 A I E-5 X
12 C
12 C
12 C
12 C
12 G M X
12 G M X
12G M X
C CV No
C CV No
C CV
C CV
12 0 Q,MT
12 0 Q,MT
No
No
No
No
12 C Q,MT,LT Yes 45 CS Pressure isolationvalve.
HV-IF005 B I E-5 X
HV-IF006 A I E-6 X
HV-IF006 B I E-6 X
PSV-IF012 A 2 D-3
PSV-IF012 B 2 E-3
HV-IF015 A 2 C-5 X
HV-IF015 B 2 C-5 X
IF029 A 2 F"4
CI IF029 B 2 F-4
X X
X X
12 G M X 12 C Q>MT>LT Ycs 45 CS
12 C - X - C CV,LT Yes 45 CS
12 C - X - C CV,I.T Ycs 45 CS
Iiq RV - - - C SRV No
Ig RV
10 GL M X
C SRV No
60 C Q,MT>LT No
10 GL M X 60 C Q,MT,LT No
2 C " - - 0 CV Yes 24 See Relief Request.
2 C - - - 0 CV Yes 24 See Relief Request.
Pressure isolationvalve.
Pressure isolationvalve.
Pressure isolationvalve.
Leak test in reversedirection.
Leak test in reversedirection.
CORE SPRAY (Continued)
ValveNumber
Q>O
>JJ MCO
0l>
C
C> 00
C4 O
M,):C0lJV
00 CO) 0llp p) O
A B C
)~»lJV
0
p$4
0C
~A
00
~wlh
0lJp
V
C0
00> 0
>JV PIJ V0B m>>> C
CC M
8~ H
00lJ>JJ
C0ll
~ A
0C>
ReliefRequest ~
Req'dTesting
Alternative Remarks
IF030 A
IF030 B
HV-IF031 A 2 C-5 X
X 2 C
2 C
3 G M X 19
0 CV Yes
0 CV Yes
0 Q,MT,LT Yes
24 Sec Relief Request.
24 See Relief Request.
20 See Relief Request. Leak test in reversedirection.
HV-IF031 B 2 C-5 X 3 G M X 19 0 Q,MT,LT Yes 20 See Relief Request. Leak test in reversedirection.
PSV-IF032 A 2 A-5
IF036 B 2
IF036 C 2
D-2
C-4
IF036 D 2
HV-IF037 A I
D-2
E-6 X
PSV-IF032 B 2 A-2
IF036 A 2. C-4
X X
X X
X X
X
X
I RV
I RV
3 C
3 C
3 C
3 C
I GL A X
C SRV No
C SRV No
C CV No
C CV No
C CV No
C CV No
3 C Q>MT>LT Yes 45>38 CS
Check during pump test.
Check during pump test.
Check during pump test.
Check during pump test.
'rcssure isolationvalve. Rapid actingvalve.
HV-IF039 B I E-6 X I GL A X 3 C Q,MT>LT Yes 45,38 CS Pressure isolationvalve. Rapid actingvalve.
lb
'll
~ V
FUBL POOI, COOLING & CLFANUP M-153
ValveNumber e cJ
1-53-071 A S
1-53-071 B S
~ r4IJ
D
F-2 X X
X
00 0
4 CO
QH IJCI 0 Cd
CII 0 OA0
A B C
8 C
8 C
000 e40 IJ
m0
S4 00 IJIJ 4I CJCC IJ CJ
0 rl~J n'00 CC C
C4 H
JC0~J
0IJ~I IJm C0 IV
ac 8
0 Cl CJ
& CIt'
CV
C CV
ReliefRequest
Reqcd g
Yes 13
Ycs 13
TestingAlternative Remarks
Open check only.
Open check only.
c ac
Co P.rn
0
HIGH PRESSURE COOLANT INJECTION M-155
ValveNumber
CO
CO
CPP ~ clj 0eO j>u A
00 0
~A OP COP'P CIP
CPA CJOP >j Cj
CPP V CJ
B C D
CP
CP) pl~8 IO
OP
jj>
0~ et
00>l
~ W OjCPP
C0
CP
0 CJ~Im0 ji
CP> 00 CJlJ CP OjOj CJ CJ
0 elu sM0 CP C
CC'
00JJ m
CJ~O C0 CP
Dc 8ji
Ojn JJ
CO 0'CO CP
ReliefRequest
Req'dTesting
Alternative Remarks
1-55-012
1-55-038
HV-1F001
HV-1F002
2 C-5
2 C-5 X
2 D-2
1 E 6 X
X
X
X
X
2 C
X 1 GL H
100 M X
100 M X
0 CV
C LT
20 C Q,MT
Yes
No
No
50 0 Q>MT,LT Yes
24 Sec Relief Request.
20 See Relief Request. Leak test in reversedirection.
HV-1F003 1
HV-IF004 2
E-5 X
E-3
IF005 2, C-4
X
X . X
X X
10 G M X 50 0 Q>MT>LT No
16 G M X ~ 81 0 ',MT No
14 C - - - C CV No Open check only duringpump test.
HV-IF006 2 C-5 X
HV-1F007 2 C-4 X
HV«1F008 2 D-5 X,
HV-1F012 2 C-5 X
1F019 2 E-3
HV-IF042 2 B-7 X
X
14 G M X 20 C Q,MT Yes
14 G M X 20 0 Q,MT No
10 GL M X 58 C Q,MT No
16 C C CV Ycs
16 G M X 90 C Q,MT,LT Ycs
4 G M X 10 C Q,MT,LT Yes
29 CS
20 See Relief Request.
32 RR
20 See Relief Request.
Leak test in reversedirection. Verify strokeduring pump test.
Closure test only.
Leak test in reversedirection.
1F045
1F046
2 B-6 X X
2 C-4 X X X
16 C
4 C
C CV Yes
C CV,LT Yes
31 See Rclicf Request.
28 See Relief Request
Open test only.
Open test only duringpump test.
np
Oo r.cp
CP
1F049 2 B-4 X X . X 20 C - - — C CV,LT Yes 28 See Relief Request Open test only duringpump test.
HIGH PRESSURE COOLANT INJECTION (Continued)
ValveNumber
4
4 4gl
tn~ woCO AO
MX40 o
Cl 60iJ P Clorl U4 4 4
CA W C7
A B C
4CP )
4ll 4
4o4 '44, lJ
v4OlO k
c4 oo JJ
4 4Cl ll O
O '8lJ n'4O Cl 4
C4 &
4o
th
4o4
I IJ4 40
Oe 8
clg JJ$4 4 4'
4
ReliefRequest
Req'dTesting
Alternative Remarks
HV-1F066 2 B-5 X 20 G M X 100 0 Q,MT,LT Yes 20 See Relief Request. Leak test in reversedirection.
1F076
1F077
HV-1F075
HV-IF079
2 C-5
2 C-5
2 C-4 X
2 C-5 X
X X
X X
X
3 C
3 C
3 G M X
3 G M X
C CV Yes
CV Ycs
15 0 Q,MT,LT No
15 0 Q,MT LT Yes
34 RR
34 RR
Open test only.
Open test only.
20 See Relief Request. Leak test in reversedirection.
HV-1F100 1 E-6 X X 1 GL A X 3 C Q MT LT No
l nl
oo t"(0l0
HPCI TURBINE — PUMP M-156
ValveNumber
CO
'cC
0O CcO A
00 0
~ W CC OOO'J0& lJCC cO CO
CCJ 0 O
B C
0)~6 CO
CO
D 4 0
CO
0~ 8
~ 8 CO
CCJ
m0
~4CO
0Slc '0
0 CJu CJ CJCO lJ 0
840 cc m
CC'
CJA0JJCCJ
m0
~4 lJco m0 CJ
CCC 8
0 CC CC
ReliefRequest
Req'dTesting
Alternative Remarks
1-56-012 2 B-2 11c! C C CV No Test during HPCI pumptest, open check only.
FV-15612 2 E-2 X 10 GL E/H X - C QJMT Yes 53 See Relief Request Test during HPCI pumptest.
1F048
1F052
1F057
'2 B-4
2 B-3
2 B-3
X X
X X
2 C - - - C CV
2 C - - - C CV
2 C - - - C CV
No
No
No
Test during HPCI pumptest, open check only.-
Test during HPCI pumptest, open check only.
Test during HPCI pumptest, open check only.
HV-1F059 2 C-5 2 GL M X 35 C Q,MT No Test during HPCI pumptest.
PSE-1D003 2 E-3
PSE-1D004 S E-3
.X X
X X
16 RD
16 RD
C DT
C DT
No
No
No testing required.
No testing required:
V gw accod
0
0
CONTAINMENT ATMOSPHERE CONTROL M-157 Sbeet I
ValveNumber
0CC
CCI
CCC CCI CicC M 0
CII M cCC 0eO oo A
M
Cc0 0
'cc 0 ce11 ) 4I0M 110 CC
CCI ) O
B . C
0CI )
~4
11 CC
0 CC
D e 0
00
~ e4
00 )Cl
0$Co
00
0 Ccoc 0
011 0 CC
CC 11 00 r4
cc 8 '00 Cl mM
A011
CCC
m0
~A11 CCI
~I 11
Coc
gReliefRequest Testing
Req'd 8 Alternative Remarks
HV-15703 2 C-6 X 18 B A X 19 C Q,MT,LT Yes 37 CS Leak test in reversedirection.
HV-15704 2 C-7 X 18 B A X 19 C Q,MT,LT Yes 37 CS
PSV-15704AI S B-5
PSV-15704A2 S B-5
PSV-15704BI S B-5
PSV-15704B2 S B-5
PSV-15704CI S B-5
PSV-15704C2 S B-5
PSV-15704DI S B-5
PSV-15704D2 S B-5
ESV-15704EI S B-5
PSV-15704E2 S B-5
HV-15705 2 C-6 X
HV-15713 2 E-5 X
HV-15711 2 E-6 X
X
X
24 RV . A X
24 RV A X
24 RV A X
24 RV A X
24 RV A X
24 RV A X
24 RV A X
24 RV A X
24 RV A X
24 RV A X
2 GL A 'X
2 GL A X
C SRV
C SRV
No
No
C SRV 'oC SRV
C SRV
No
No
C SRV No
C SRV
C SRV
C SRV
C SRV
No
No
No
No
C Q,MT,LT Ycs
Q,MT,LT Yes
24 B A X 30 C Q,MT,LT Yes
37 CS
37 CS
37 CS Leak test in reversedirection.
HV-15722 2. D-4 X
1D
co r HV-15723C cor
0
2 D-2 X
HV-15714 2 E-7 X
HV-15721 2 D-3 X
X
X
24 B A X 30 C Q,MT,LT Yes 37 CS
6 B A X 6 C Q,MT,LT Yes 37 CS
24 B A X 30 C Q,MT,LT Yes 37 CS
24 B h X 30 C Q,MT,LT Yes 37 CS
Leak test in reversedirection.
CONTAINHENT ATMOSPHERE CONTROL (Continued)
ValveNumber
CO
CJ
m
Cl '0Cd l5 Cm
CC M 0CCJ M dJ 0
OC O
MX.m0 0
Cl DOlJ ) CJOM CJ0 CC CC
CJJ) O
A B C D
mCl
0 )) eE CP~ 8 Cl CJ )ll Cl CJ0 CS A CC
000 u
lOo u
lc oc 0O CJu 0 CCCC lJ 0
0 rIll S'00 cl m
Cd M
JC0CJ
0~AlJ CC
CJCl ~
0 ClClc 8
8O C7'l
ReliefRequest
Req'dTesting
Alternative Remarks
HV-15724
HV-15725
2 C-2 X
2 C-4 X
18 B h X 19 C Q,MT,LT Yes
18 B A X 19 C Q,MP,LT Yes
37 CS
37 CS Leak test in reversedirection.
SV-15734 A 2 B-3 X
SV-15734 B 2 B-6 X
SV-15736 A 2 8-4 X
SV-15736 B 2 B-6 X
X
X
X
I GL S X 3
I,GL S X 3
I .GL S X 3
I GL S X 3
0 Q,LT,MT Yes
C Q,LT,MT Yes
0 Q,LT,MT Yes
C Q,LT,HT Yes
38 Sec Reliefi Request.
38 See Relief Request.
38 See Relief Request.
38 See Relief Request.
Rapid acting valve.
Rapid acting valve.
Leak test in reversedirection. Rapid actingvalve.
Leak test in reversedirection. Rapid actingvalve.
SV-15737 2 B-4 X
SV-15740 A 2 D-4 X I GL S X 3 0 Q,LT,HT Yes
I GL S X 3- C Q,LT>MT Yes 38 See Relief Request...
38 Sce Relief Request.
Rapid acting valve.
Leak test in reversedirection. Rapid actingvalve.
SV-15740 B 2 D-5 X
SV-15742 A 2 D-4 X
SV-15742 B 2 D-6 X
SV-15750 A 2 D-4 X.
X
I GL S X 3
I GL S X 3
I GL S X 3
I GL S X 3
C Q,LT,MT Yes
0 Q;LT,HT Yes
C Q,LT,MT Yes
0 Q,LT,MT Yes
38 Scc Relief ReqIccst.
38 See Relief Request.
38 See Relief Request.
38 Sce Relief Request.
Leak test in reversedirection. Rapid actingvalve.
Rapid acting valve.
Rapid acting valve.
Leak test in reversedirection. Rapid actingvalve.
SV-15750 B
c ac
CoSV-15752 A
0
2 D-6 X
2 D-4 X
X I GL S X 3
I GL S X 3
C Q,LT,MT Ycs
0 Q,LT,MT Ycs
38 Sce Relief Request.
38 Sec Relief Rcqucst.
Leak test in reversedirection. Rapid actingvalve.
Rapid acting valve.
I
I1
0CONTAINMENT ATMOSPHERE CONTROL (Continued)
ValveNumber
CJIC0
'e4'0
AM 00
C4 CJ
M
C0 0~rl CI CC) 00M JJ
CJ CJ ICCIJ W CJ
A B C
~ 0~w
0IC
~ W 0CC
00 JJ
0 CI'4 0I 00 JJCJ CJ CC
IC JJ 0840 CJ
CJ: M
Pl
A0JJIJJ
00
~JC) 00 00I n
CC
E0 0 CP
Z BCC
ReliefRequest
Req'dTesting
f Alternative Remarks
HV-15766 2 A-4* X
'SV-15752 B 2 D-6 X X
6 G M 'XI GL S X 3 C Q,LT,MT Yes
30 C QJMT,LT Ycs
38 See Relief Request.
20 See Relief Request.
Rapid. acting valve
Leak test in reversedirection.
SV-15767
HV-15768
2 C-4 X
2 A 4 X
I GL S X
6 G M X
3 C Q,LT,MT Yes
30 C Q,MT,LT No
38 Sec Relief Request. Rapid acting valve.
SV-15774 A 2 C-4 X
SV-15774 B 2 D-6 X
SV-15776 A 2 B-6 X
I GL S X 3 0 Q,LT,MT Ycs
I GL S X 3 C Q,LT,MT Yes
I GL S X 3 0 Q LT MT Ycs
38 Sce Relief Request.
38 Scc Relief Request.
38 Scc Relief Request.
Rapid acting valve.
Rapid acting valve.
Leak test in reverse'irection.Rapid acting
valve.
SV.-15776 B 2 C-4 X
SV-15780 A 2 B-4 X
X I GL S X
I GL S X
3 C Q,LT,MT Yes
3 0 Q LT MT Yes
38 See.Relief Request.
38 See Relief Request.
Leak test in reversedirection. Rapid actingvalve.
Leak test in reversedirection. Rapid actingvalve.
SV.-15780 B 2 B-6 X X I GL S X 3 C Q,LT,MT Yes 38 Sce Relief Request. Leak test in reversedirection. Rapid actingvalve.
SV-15782 A ' B-4 X
SV-15782 B 2 B-6 X
I GL S X 3 0 Q,LT,MT Ycs 38 Sce Relief Request.
I GL S X 3 C Q,LT,MT Ycs 38 See Relief Request.
Rapid acting valve.
Rapid acting valve.
M 000 P.
0)Qo0
LIQUID RADWASTE COLLECTION M-161 Sheet 1
ValveNumber
OCPl
C0 0CP CPP
IJ ) CPVA IJCl Cl Cl
IPP ) CP
IJCP
0
A B C D
Cl
~A
0J
m0
CP0 Il
0 PIPI $4 00 IJ
Cl CP
Cl IJ V0 '<
IJ 0 '0V CP C
JC', M
VClCC 0
IJCP
n ppp
0g4
0A c$0
PIJ 0IPP
Ilm
~AIJm
0'l
Cl~ I4
ReliefRequest
Req'dTesting
Alternative Remarks
HV-16108 Al 2 F-6 X
HV-16108 A2 2 F-9 X
HV-16116 Al 2 B-5 X
3 G
3 G
3 G
A X
A X
A X
15 C Q,MT,LT No
15 C Q,MT,LT No
15 C Q,MT,LT No
HV-16116 A2 2 A-5 X 3 G A . X 15 C QJMTLT No
CONTROL STRUCTURE CHILLED HATER M-186
ValveNunber
JJcI
o>h ~ >h 0
h> 4)
o0
~» Cl~ > )oe a
Ch W
0CO
>>eO
A B C D
oo
>> >>V
0>
Qo
C~»
ClCJ>>
~» C$th
CO
»>o
» h> 0o >J>> 4I e>> 1> >>oJ> s'u0 c> c4 >>'H
JCo»>>
- Ch
u0~AJ>
0h>
>JC
J>eo'elief
RequestRcq>d
TestingAlternative Res>arks
0-86-018
0-86-118
0-86-039
0-86-139
3 E-5
3 A-7
3 C-5
3 A-7
HV-08613 A 3 F-5
HV-08613
SV-08621
B 3 A-7
A S D-6
X
X
SV-08621 B S A-7
HV-08601 A 3 A-5
HV-08601 B 3 A-7
HV-08602 A . 3 A-4
X
X
HV-08603 A 3 A-5
HV-08603 B 3 A-7 ,X
HV-08602 B 3 A-7 X
X
X
X
X
X
6 C
6 C
6 C
6 C
C CV . Yes
C CV Ycs
CV Yes
C CV
6 B
6 B
1 GL
1 GL
2 G
S
M X
N/A C Q
N/A C Q
N/A 0 Q
N/A C Q
13 C Q,MT
Yes
Yes
Ycs
Yes
No
No
2 G
2 G
M X
M X
2 G M X
2 G M X
13 0 Q>MT
14 0 Q>MT
14 C Q MT
12 C Q,MT
No
No
No
No
2 G M X ., 13 C Q MT
40 See Relief Request.
40 See Relief Request.
40 Sce Relief Request.
40 Sce Relief Request.
40 See Relief Request.
40'See Relief Request.
40 See Relief Request.
40 Sce Relief Request.
pstb
Oom
-0
REACTOR BUILDING CHILLED WATER M-187 Sheet 2
ValveNumber
Cl .CJclm
CO
«OM 0
O> M cc> O<o o«o
M
0 0Cl OO
CJ P ClCJM 1>Cl CC CC
CJ>) O
A B C
Cl0
~A CO
CO
D o cl
0
0JJCO
CJCJ
m0
0CC«0
JJ
CC; M
8~ A
00>1JJ
CJ>
0CO
P« 1>co m0 Clo 8
CJ
CO
g CJ>1 IO O'
Cl ClZ
ReliefRequest
ReqcdTesting
Alternative Remarks
HV-18781 Al
HV-18781 A2
2 C-2 X
2 D-2 X X
8 G
8 G A X
A X 40 0 .Q,MT,LT
40 0 Q,MT,LT
No
No
HV-18781 B1 2 E-2 X
HV-18781 B2 2 F-2 X
HV-18782 Al 2 E-3 X
HV-18782 A2 2 F-3 X
-X
X
8 G A X
8 G A X
40 0 Q,MT,LT No
40 0 Q>MT>LT No
8 B A X 6 0 Q,MT,LT No
8 B A X ' 0 Q,MT,LT No
HV-18782 Bi 2 C-3
HV-18791 B1
HV-18791 B2
2 D-2 X
2 E 2 X
HV-18782 B2 2 D-3 X
HV-18791 A1 - 2 F-2 X
HV-18791 A2 2 G-2 X
X
X
8 B X
3 G
3 G
3 G
A X
A X
A X
8 B A X
3 G A X.
6 0 Q,MT,LT No
6 0 Q,MT,LT No
15 0 Q,MT,LT Yes 39 CS
15 0 Q,MT,LTc
15 0 Q>MT,LT
Yes 39 CS
Yes 39 CS
15 0 Q,MT>LT Yes . 39 CS
HV-18792 B2I
2 G-3 X
HV-18792 Al 2 D-3 X
HV-18792 A2 2 E-3 X
HV-18792 B1 2 F-3 X
X
X
X
3 B A X
3 B A X
3 B A X
3 B A X
4 0 Q,MT,LT . Yes
4 0 Q,MT,LT Yes
4 0 Q,MT,LT Yes
4 0 Q,MT,LT Yes 39 CS
39 CS
39 CS
39 CS
l Gl
oor.C CO
Pc0
Ir
TRAVERSING INCORE PROBE (TIP)
ValveNumber
~JCP
0m
AVP M s4 0W CJ P4 CJ
MPC
00 0
CP 00CPVM lJ
cp cp 0VP0'
A B CV
CP)~A
CP CJCP m0l4 VP
CP
0CP
0j-c 0
JJCP a
llC$ V
r0ll0 PJ
P4 0lJCP 0~J V0 v48 WCP C
P4 M
CiCP 0
ll CPCP lJg CP
0 CP
l4 8CP
CP IJ
8 8ll 0 CP CP
VP Z B CC
ReliefRequest
ReqldTesting
Alternative Remarks
TIP Chan A Man Valve*
TIP Chan A Squib Valve++
TIP Chan B Man Valve
2 N/A
2 N/A
2 N/A X
X
X X
X
3/8
3/8
BA S X
3/8 BA S X
0 DT No
5 C Q,MT,LT No
5 C Q,MT,LT No
TIP Chan B Squib Valve 2 N/A X X 3/8 0 DT No
TIP Chan C Man Valve 2 N/A X 3/8 BA S X 5 C Q,MT,LT No
TIP Chan C Squib Valve 2 N/A X X 3/8 X 0 DT No
TIP Chan D Man Valve 2 N/A X 3/8 BA 8 X 5 C Q,MT,LT No
TIP Chan D Squib Valve 2 N/A X X 3/8 X 0 DT No
TIP Chan E Man Valve 2 N/A X 3/8 BA S X 5 C Q,MTJ LT No
TIP Chan E Squib Valve 2 N/A X X 3/8 X 0 DT No
* TIP Channel manual (ball) isolation valve.
** TIP Channel Squib (explosive/shear) isolation valve.
P OP
00 Iopr.0
Page 46 of 113
PUMP TABLE
Revision 311/84
PumpNumber
PumpName
ASMEClass Speed
Parameter Measured
Inlet Pump Flow BearingPressure A P Rate Vibration Temp.
LubricantLevel orPrcssure
TestFrequency
ReliefRequestNumbers Remarks
1P202A Residual HeatRemoval-A
2 ExemptIWP-4400
X X X X kA Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
)
1P202B Residual HeatRemoval-B
1P202C Residual HeatRemoval-C
)P202D Residual HeatRemoval-D
1P204A,B )ligh PressureCoolant Injection
~ Main & Booster
1P206A Core Spray-A
1P206B Core Spray-B
2 ExemptIWP-4400
2 ExemptIWP-4400
2 ExemptIWP-4400
2 ExemptIWP-4400
2 Exempt XIWP-4400
X X
X X X
X X X
X X X
X X X
X X X
Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
44 Bypass loop, main andbooster pumps operate intandem - measurementstaken as one pump.
Bypass, loop, bearings inmain flow path lubricatedby pumped liquid.
Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
1P206C Core Spray-C
1P206D Core Spray-D
2 ExemptIWP-4400
2 ExemptIWP-4400
X X X X
X X X X
Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
Bypass loop, bearings inmain flow path lubricatedby pumped liquid.
1P208A Standby LiquidControl-A
1P208B Standby LiquidControl-B
2 Exempt . See Relief XIWP-4400 Request 43.
2 Exempt Sec Relief XIWP-4400 Request 43.
43 Bypass loop.
43 Bypass loop.
OoC co
0
+See Relief Request 48.+>Sec Relief Request 54.
~~~See Relief Request 49.
PumpNumber
PumpName
ASMEClass Speed
Parameter Neasurcd
Inlet Pump Flow BearingPressure h P Rate Vibration Temp.
Lubricant ReliefLevel or Test RequestPressure Frequency Numbers Remarks
OP504A Emergency ServiceWater-A
3 Exempt X X X XIWP-4400
Bearings in main flowpath lubricated by pumpedliquid inlet pressurederived from spray pondlevel.
OP504B Emergency ScrviccWater-B
3 Exempt X X X XIWP-4400
Bearings in main flowpath lubricated by pumpedliquid inlet pressurederived from spray pondlevel.
OP504C Emergency ServiceWater-C
OP504D Eaergency ServiceMater-D
3 Exempt X X X XIWP-4400
3 Exempt X X X XIMP-4400
Bearings in main flowpath lubricated by pumpedliquid inlet pressurederived from spray pondlevel.
Bearings in main flowpath lubricated by pumpedliquid inlet pressurederived from spray pondlevel.
IP506A RHR ServiceWater-A (Unit 1)
3 ExemptIWP-4400
X X X Bearings in main flowpath lubricated by pumpedliquid inlet pressurederived from spray pondlevel.
1P506B RHR ServiceWater-B (Unit 1)
3 ExemptIMP-4400
X X X Bearings in main flowpath lubricated by pumpedliquid inlet pressurederived from spray pondlevel.
OP162A
OP162B
C. ST Chilled WaterLoop Circ. Pump-A
C. S. Chilled WaterLoop Circ. Pump-B
S Exempt See Relief Request Number 50.IMP-4400
S Exempt See Relief Request Nunber 50.IMP-4400
50
50
*See Relief Request 54.
PumpNumber
PumpName
ASMEClass Speed
InletPressure
Parameter Measured
Pump Flow BearingA P Rate Vibration Temp.
LubricantLevel orPressure
ReliefTest Request
Frequency Numbers Remarks
OP171A
OP171B
OP514A
OP514B
OP514C
Emergency CondenserWater Cir. Pump-A
Emergency CondenserWater Cir. Pump-B
Diesel Oil TransferPump A
Diesel Oil TransferPump B
Diesel Oil TransferPump C
3 ExemptIWP-4400
3 ExempfIWP-4400
S ExemptIWP-4400
S ExemptIWP-4400
ExemptIWP-4400
See Relief Request Number 50.
See Relief Request Number 50.
See Relief Request Number 47.
See Relief Request Number 47.
See Relief Request Number 47.
50
50
47
47
47
OP514D Diesel Oil TransferPump D
S , Exempt See Relief Request Number 47.IWP-4400
47
Monthly test per Tech. Specs.
Page 50 of 113
RELIEF REQUESTS
Revision 311/84
Page 51 of 113
RELIEF RE UEST NUMBER 1
System:
P&ID:
Reactor Building Closed Cooling Water
M-113
Valves: HV-11313HV-11314HV-11345HV-11346
Category: A
Class:
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These valves are in the'ooling water supply and returnlines for the reactor recirculation pump bearing and sealcoolers. Cycling of these valves during po~er operationwould interrupt this cooling water flow, possibly causingpump bearing damage or seal failure.
Alternative Testing: Exercise valves during Cold Shutdowns (no morefrequently than once per 92 days).
Revision 311/84
Ptl tl 'IW
*
1I
~ 1 *o
'I
R «I l
~~
~ ~ )I'
rP
XC<'>~ f
I ,t ll 's r
4I g ~1 ~ ~ -e ~~'if
P
1.
RELIEF RE VEST NUMBER 2
Page 52 of 113
System:P&ID'ontainment Instrument Gas
M-126
Valves: 1-26-0701-26-0721-26-0741-26-1521-26-1541-26-164
Category:
Class:,
A, 'C
, Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These check valves serve the containment isolation functioninside containment and are not equipped with remoteposition indicators. Downstream of the valves (insidecontainment) there are no pressure measurement devices orother means of remotely verifying valve position. The onlypractical method of closure testing involves pressurizingthe downstream side and measuring pressures with temporaryinstrumentation. With the inerted containment, suchtesting can only be performed during a major outage whichrequires containment purging. This testing, which requiressignificant effort in the installation and removal oftemporary equipment in the high radiation area of thecontainment drywell, is already performed during Category Aleak rate testing.
Two valves, 1-26-152 and 1-26-154, serve a safety functionon opening as well as their containment isolation function.The open test cannot be performed as there would be nopositive indication (flow measurements) of function.Operation of the equipment serviced by these valves (ADSfunction of the safety/relief valves) will not verifytheir proper opening since the accumulators at the SRVoperators provide capacity for several lifts.
Revision 311/84
qphf
H
P
r
I '
"N
~ b
Page 53 of 113
RELIEF RE VEST NUMBER 2 (Cont'd)
Performing continued lifts in an attempt to verify checkvalve opening will increase the potential for SRV leakageor failure to reseat, will impact proper maintenance'freactor pressure control, and has the potential fordegradation of the ADS function.
Alternative Testing: Valve closure is demonstrated by completion of leakrate testing performed once per 24 months. Commencingwith the first refueling outage, verification of theopening capability of valves 1-26-152 and 1-26-154will also be performed at that time with an airpressure applied through the outboard test valves(1-26-021, 1-26-031), opening'he inboard test valves(1-26-155, 1-26-153), and observing essentiallyunrestricted flow.
Revision 311/84
r
f
t
f
Page 54 of 113
RELIEF RE UEST NUMBER 3
System:
P&ID:
Valves:
Containment Instrument Gas
M-126
SV-12651
Category: A
Class: 2
Function: Containment Isolation
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: Closing this,valve interrupts instrument gas supply toseveral important valves inside containment such as theSafety/Relief Valves (non-ADS function) and the MSIVs.This could compromise the ability of the SRV's to operatein the relief mode which, while not an ECCS function, isimportant to safety. Loss of instrument gas could alsocause the MSIVs to close, resulting in a severe reactortransient.
Alternative Testing: Exercise valve during cold shutdowns (no morefrequently than once per 92 days).
Revision 311/84
»
I Q Il
PF)P ~(
'l,l „PPg'
»I
*
'»IP'»»Ptl
»»[Pled
JPP"
N P
~,P»
f
»r'
P PP
~ ~ »
pl, P
»I ~
P
Page 55 of 113
RELIEF RE UEST NUMBER 4
System:
PAID:
Valves:
Containment Instrument Gas
M-126
SV-12654ASV-12654B
Category: A
Class:
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: Closing these valves will interrupt instrument gas supplyto the ADS solenoids of the Safety/Relief Valves,compromising their ability to provide the opening motiveforce for the ADS valves in support of the long-termcooling ECCS function.
Alternative Testing: Exercise valves during cold shutdown (no morefrequently than once per 92 days).
Revision 311/84
F
I
P'
0
Page 56 of 113
RELIEF RE UEST NUMBER 5
System:
P&ID:
MSIV-Leakage Control
M-139
Valves ~Cate ot Class
HV-1F001 B,F,K,PHV-1F002 B,F,K,P
AB
Function: Containment Isolation; System Initiation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: The MSIV-LCS inboard bleed lines are directly connected tothe main steam lines at the outboard MSIV. During poweroperations, these lines are pressurized with main steam upto the first isolation valve (HV-1F001 B,F,K,P). Doublevalve isolation is provided by HV-1F002 B,F,K,P. Openingany of these valves during power operations will leave onlyone barrier against the release of main steam to occupiedplant areas through the system piping. Maintenance ofdouble valve isolation is desired for personnel safetyconsiderations and for prevention of inadvertent leakagepaths from the main steam lines.
Alternative Testing: Exercise during cold shutdowns (no more frequentlythan once per 92 days).
Revision 311/84
RELIEF RE VEST NUMBER 6
Page 57 of 113
System:
P&ID:
MSIV-Leakage Control
M-139
Valves: HV-1F006HV-1F007,HV-1F008HV-1F009
Category:
Class:
Function: System Initiation
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: The MSIV-LCS outboard bleed and blowdown lines are directlyconnected to the main steam system at the steam line drain.During power operations these lines are pressurized withmain steam up to the first isolation valve (HV-lF006,HV-1F008). Double valve isolation is provided by HV-1F007and HV-1F009. Opening any of these valves will leave onlyone barrier against the release of main steam to occupiedplant areas through system piping. Maintenance of doublevalve isolation is desired for personnel safetyconsiderations and for prevention of inadvertent leakagepaths from the main steam lines.
Alternative Testing: Exercise during cold shutdowns (no more frequentlythan once per 92 days).
Revision 311/84
C
'44
P I ~ 4CW
~tht "
II
I ~ W
!
I
Wt
W
„.' 4 f
]'I "4 W
4'
"."P" I'W"p
I* fh '4'
I'py
"I - I l~h't" 4- 4 ~ I
,'t-4
WT
~ ~
~ ~
Page 58 of 113
RELIEF RE UEST NUMBER 7
System:
P6 ID:
Valves:
Nuclear Boiler
M-141
1F010 A,B
Category:
Class:
AJ C
Function: Containment Isolation
Impractical Test Requirement: , Exercise valves closed once per 92 days.
Basis for Relief: These check valves remain open maintaining the flowpath tothe vessel whenever the feedwater/condensate, HPCI or RCICsystems are providing makeup to the vessel or when ReactorWater Cleanup is returning flow to the vessel. Due to thenecessity of maintaining this flowpath in virtually allmodes of operation, closure testing is only practicalduring extended outages such as refuelings during whichthese systems are shutdown. Also, plant design does notprovide a practical means of demonstrating closure otherthan by upstream pressurization performed during leak ratetesting. This testing involves significant effort forinstallation of temporary equipment, and requires completepurging of the inerted reactor containment.
Alternative Testing: Proper valve closure will be verified in by completionof leak rate testing performed once per 24 months.
Revision 311/84
fP
~ P h ~
~ P
P
P I
4 I F
~h
Page 59 of 113
RELIEF RE VEST NUMBER 8
System:
P&ID:
Nuclear Boiler
M-141
Valves: PSV 14137 A~B~CpD~E~FpGiH~J~K~L~M~N~P~R~S
Category: C
Class: 3
Function: SRV Discharge Pipe Vacuum Breaker
Impractical Test Requirement: Setpoint test per PTC 25.3-1976.
Basis for Relief: The ASME performance test code does not provide the mostpractical method for testing these vacuum relief devices.
Alternative Testing: Commencing with the first refueling outage, thesetpoint will be checked once per refueling outage bypouring water into the valve inlet and measuring theheight of water column necessary to activate thevalve.
Revision 311/84
, 4)
'
~,, ~r yah
4
r \O')~ > y Plw >'I >, h * '4 g)'g
4'l
l.
44
~ ) ~ 4 '
ggr» >,4 rp
~, > ~ '4 4 i»g» ~ >
4
' *
4
'4
* ~
4 l> l > I I ')4 ( 'h h )
4 h 5 4,, 4 ~ $ 4 I>,)
~''I'< "I
4
~ ~ I ) W ll
4'4F \ ~
h >I) ~
p
Page 60 of 113
RELIEF RE VEST NUMBER 9
System:
P&ID:
General
General
Valves: General
Category: General
Class: General
Function: As applicable to specific valves.
Impractical Test Requirement: Paragraphs IWV-3417(b) and IWV-3523 ofSection XI require that when correctiveaction is required as a result of tests madeduring cold shutdown, the condition shall becorrected before startup.
Basis for Relief: For those valves specified 'therein, the Limiting Conditionsfor Operation presently contained within the SusquehannaSteam Electric Station Technical Specifications provide thecontrol by which valves and/or systems are declaredinoperable. They also control entry into the variousoperational conditions. Further controls are not necessaryfor these valves. Valves which are not under the controlof the Technical Specifications will be declared inoperableshould they fail ISI testing.
Alternative Testing: The requirements contained within Susquehanna SESTechnical Specifications will control plant operationsand testing with regard to out-of-service valves. Forvalves which are not addressed in the TechnicalSpecifications, any failures will cause the affectedvalve(s) to be declared inoperable and correctiveaction to be initiated as appropriate.
Revision 311/84
I t
V
H
I
4,
RELIEF RE UEST NUMBER 10
Page 61 of 113
System:
P&ID:
Valves:
Nuclear Boiler
M-141
PSV-1F013 G>J,K,L,M,N
Category: B, C
Class: 1
Function: ADS Valve, Code Safety/Relief Valve
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: The six safety relief valves assigned to the ADS systemperform an essential safety function when operated by thepneumatic actuator with gas supplied through the ADSsolenoid valves. Operation of these valves is notpractical during power operations because this action willvent main steam to the suppression pool, inducing atransient condition and increasing the potentiality for anopen failure of a safety relief valve. Also, no stroketiming is practical as these are pneumatic assisted SRVs.Since "position indication" of the SRVs is provided byacoustic monitors attached to the valve discharge piping,exercising during cold shutdown cannot be accomplishedbecause of lack of steam flow (and attendant noise).
Alternative Testing: The ADS valves will be exercised once per 18 months inaccordance with Technical Specification 4.5.l.d.2.b,which provides manual opening of each ADS valve withreactor dome pressure greater than or equal to 100psig and observing either control valve or bypassvalve response or corresponding change in measuredsteam flow. No stroke timing will be done.
Revision 311/84
II - I
II
~ '
'i
n
)1 I
r
Page 62 of 113
RELIEF RE VEST NUMBER ll
System:
P&ID:
Nuclear Boiler
M-141
Valves: HV-1F022 A,BIC,DHV-1F028 A,B,C,D
Category: A
Class: 1
Function: Containment Isolation
Impractical Test Requirement: Exercise valves'once per 92 days.
Basis for Relief: During full power operation, it is impractical to fullstroke cycle these valves, since the interruption in steamflow would induce a reactor pressure transient withincreased probability of reactor scram, main steam lineisolation and SRV actuation. Trending of valve stroketimes is not necessary due to Technical Specificationlimits on minimum as well as maximum allowable stroke timeswith a tolerance of 2 seconds.
Alternative Testing: Full stroke testing will be performed in OperationalCondition 1, 2, or 3 when power level is low enough toprevent the above mentioned transients (no morefrequently than once per 92 days). No reduction fromhigh power levels will be made specifically toaccomplish this testing. No trending of valve stroketimes will be done.
Revision 311/84
II
Pl 4
'Ih
r ~
I'/
rtH
ff
I
Page 63 of 113
RELIEF RE VEST NUMBER 12
System:
P&ID:
Valves:
Nuclear Boiler
M-141
HV-1F032 A,B
Category: A, C (HV-1F032B only)
Class: 2
Function: Containment isolation; HPCI flowpath (HV-1F032B only).
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: a. These check valves remain open maintaining theflowpath to the vessel whenever the feedwater/condensate systems are providing makeup to the vessel.Interruption of the feedwater flowpath by motoroperator closure of these valves can only bepractically accomplished during cold shutdowns.
b. No practical means other than upstream pressurizationsimilar to leak rate testing is available todemonstrate valve closure of HV-1F032B as a checkvalve.
Alternative Testing: a ~ Cycle valves shut using stop-check motoroperators during cold shutdowns (no more frequentthan once per 92 days).
b. Closure testing of HV-1F032B as a check valvewill be demonstrated by completion of leak ratetesting to be performed once per 24 months.
Revision 311/84'
ri
I 'I
Ft t
t
*I I
t4 ~
4 )I I . I
4
t
II'
~ )4
<)il
„„C.tf
I tl' )
F
I 4
'I
IhI' I 4
C
4
Page 64 of 113
RELIEF RE VEST NUMBER 13
System: Fuel Pool Cooling and Clean-Up
P&ID: M-153
Valves: 1-53-071 A,B
Category: C
Class: Non-Code safety function
Function: Prevent backflow from fuel storage pool.
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: In an alternative, flowpath to the fuel storage pool,exercising of these valves utilizing flow can only beaccomplished utilizing ESW or RHR water. Use of ESW wouldintroduce "raw" water from the ESSW spray pond, undesirablefor chemistry and fuel integrity considerations. While useof the RHR flowpath is possible, the difficulty ofoperating the RHR system in an abnormal lineup forsupplying the fuel pool creates a dynamic "control situationthat is best minimized.
Alternative Testing: Verify valve operability by inspection upondisassembly. Commencing with the first refuelingoutage, one valve will be disassembled every refuelingoutage.
Revision 311/84
~ I ~
~ - *j
c C Acre
j ~ c II
RELIEF RE UEST NOSER 14
Page 65 of 113
System:
PAID:
Valves:
Reactor Recirculation
M-143
XV-1F017 A,B
Category:
Class:
A, C
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: Closure testing of these excess flow check valves involvesdepressurization of the CRD system side of the valves andverification that the valve will close and stop excessflow. Such actions require interruption of seal water tothe recirculation pumps, which creates a potential for pumpseal damage; disruption of CRD Hydraulic System flow; andinstallation of temporary equipment.
Alternative Testing: Closure testing will be demonstrated by completion ofleak rate testing to be performed once per 24 months.
I
Revision 311/84
I I
Ph
~ I
t 'I 4
I J i'l I ~ )
f 'If I ~y
~(
fI
A "Ig
IV
I ~
J
) 1 I I,TI
g ~ / I I lF,
PI PII I > I',I
Ipl J
~ 'll 't " P" 4 ~4 I
, 4
RELIEF RE UEST NUMBER 15
Page 66 of 113
System:
P&ID:
Reactor Recirculation
M-143
Valves: 1F013 A,B
Category: A, C
Class: 2
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These simple check valves serve as containment isolationvalves inside containment. The valves are not equippedwith remote indication and there is no pressure indicationdownstream of the valves. For these valves, closuretesting is only practical through pressurization downstreamof the valve with the upstream piping vented, andverification of the absence of flow upstream. Interruptionof the CRD flow (seal purge) during Reactor RecirculationPump operation to perform this testing could result in sealdamage. This type of testing can only be performed duringa period when the containment is accessible. Thedeinerting of the containment will only be performed duringma)or outages and the testing will be performed duringCategory A leak rate testing.
Alternative Testing: Valve closure is demonstrated by completion of leakrate testing performed once per 24 months.
Revision 311/84
*
i UI
f ~
I
pl~ I~ ~
!lt)
h UPI, lf 'qf
l ~I Ul
~ < !I
Ul
RELIEF RE VEST NUMBER 16
Page 67 of 113
System:
PAID:
Reactor Recirculation
M-143
Valves: HV-1F031 A,B
Category: B
Class: 1
Function: Reactor Recirculation Pump Discharge Isolation, LPCI flowpath.
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: The recirculation pump discharge isolation valves are inthe main flowpath of the reactor recirculation system whichis necessary to maintain reactivity control of the reactor.Cycling of these valves during power operations wouldinterrupt the driving core flow, possibly resulting insevere changes in core power level.
Alternative Testing: Technical Specification 4.4.1.1.1 provides for andcontrols the exercising of these valves prior toexceeding 25% power during each startup.
Revision 311/84
4 P
k
1
P
'h N
Et 4
tP
0
Page 68 of 113
RELIEF RE UEST NUMBER 17
System:
P&ID:
Control Rod Drive
M-147
Valves ~Cate or
114-001 through 114-185115-001 through 115-185XV-126-001 through XV-126-185XV-127-001 through XV-127-185138-001 through 138-185
Class:
Function:
2
Control Rod Scram
Impractical Test Requirement:, Exercise valves once per 92 days and measurestroke times.
Basis for Relief: These valves, located on the hydraulic control units forthe 185 control rod drives, function on a reactor scramsignal from the reactor protection system to insert thecontrol rods rapidly into the reactor core. Their properfunctioning is most practically verified by an actual scramtest.
Alternative Testing: Scram testing and rod insertion timing will beperformed in accordance with Technical SpecificationsSection 4.1.3.2 (at reactor coolant pressure 950 psigfor:
a. All control rods prior to THERMAL POWER exceeding40% or after a shutdown longer than 120 days.
b. Following maintenance or modification.
c. 10% on a rotating basis at least once per 120days).
This will verify proper functioning of valves 114,115, XV-126, XV-127 and 138. Additionally, closure ofcheck valves 115 is assured for each accumulator bydemonstration of the ability to maintain requiredpressure in the accumulator for',> 1'0 minutes with theCRD Pumps secured.
Revision 311/84
CH, il Hh " ' "'W
~ ~ D
PS I
DS
HI h" I HDh
h
'I
I, I,
~"r, II P ~
Ih
P
H
I'I I D, 'I
~ D
I P
~ r
e
I IhDl
h
~ Pr
Page 69 of 113
RELIEF RE VEST NUMBER 17 (Cont'd)
This testing is performed once per 18 months inaccordance with Technical Specification 4.1.3.5.b.2.Closure of check valve 138 will be assured by ventingof the cooling water header during Integrated LeakageTesting per 10CFR50, Appendix J.
Revision 311/84
Page 70 of 113
RELIEF RE VEST NUMBER 18
System:
P&ID:
Standby Liquid Control
M-148
Valves: HV-1F006
Category: A, C
Class:
Function: Containment Isolation
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: To verify proper opening of this stop-check valve, it isnecessary to pass fluid through the valve. This actionwould result in an injection into the reactor vessel andwould require actuation of an explosive valve. Bothactions are undesirable during power operations. Closuretesting as a motor-operated stop-check valve during poweroperations presents the danger of having the disc stick inthe closed position, blocking the only SLC injectionflowpath, with no means of detecting the failure.
Alternative Testing: The proper functioning of the Standby Liquid ControlSystem injection flowpath, including opening ofHV-lF006, will be demonstrated once per 18 months inaccordance with Technical Specification Section4.1.5.d (includes meeting minimum flow, actuation ofexplosive valve, pump relief valve setpoint, andverification of free flow to show proper operation ofheat tracing). Closure testing of the valve by motoroperator will be performed just prior to the injectiontesting once per 18 months.
Revision 311/84
nt
I 'I I 4 f,}t 1
'1 ~ 4 W}7
f II 1
41
~ ~ 4
r CH
I 4
.} < H'J
,tf'
4
1 f}lf
4 ~"4
nn V}n
4
~ 4
tr ' ' }tt'-2'"'}
~ 4
~4 HO 4 nr
"O 4 I,1
'~
4
~ t P, H III
I 4'1 fp 1}
"4 C"
4 4
RELIEF RE VEST NUMBER 19
Page 71 of 113
System:
PAID:
Valves:
Standby Liquid Control
M-148l
1F007
Category: A, C
Class:
Function: Containment Isolation
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: To verify proper opening of this check valve, it isnecessary to pass fluid through the valve. This actionwould result in an injection into the vessel and wouldrequire actuation of an explosive valve, both undesirableduring power operations. Closure testing is only practicalby pressurizing downstream of the valve (the upstream sidebeing vented) and verifying absence of flow in the upstreamside. This requires installation of temporary equipmentand access to the containment which is inerted during poweroperation.
Alternative Testing: The proper functioning of the Standby Liquid ControlSystem injection flowpath, including opening of 1F007,will be demonstrated once per 18 months in accordancewith Technical Specification Section 4.1.5.d. Valveclosure is demonstrated by completion of leak ratetesting performed once per 24 months. See ReliefRequest Number 18 for explanation of TechnicalSpecification 4.1.5.d.
Revision 311/84
I T:
1, ~
a K
'1 .I
l f
~ u'
'I
Page 72 of 113
RELIEF RE UEST NUMBER 20
~see em
RCIC
RCIC
RCIC
RCIC
RHR
Core Spray
Core Spray
HPCI
HPCI
HPCI
HPCI
HPCI
ContainmentAtmosphere Control
P&ID
M-149
M-149
M-149
M-149
M-151
M-151
M-151
M-152
M-152
M-155
M-155
M-155
M-155
M-155
M-157
Valve
HV-1F007
HV-1F031
HV-1F059
HV-1F084
HV-lF004A,B,CiD
HV-1F007A,B
HV-1F022
HV-1F001A,B
HV-lF031A,B
HV-1F002
HV-1F012
HV-1F042
HV-1F066
HV-1F079
HV-15766
Class
Category: A
Function: Containment Isolation
Impractical Test Requirement: Leak test gate valve with pressuredifferential in same direction as safetyfunction.
Basis for Relief: These valves are configured such that there is no practicalmeans of pressurizing in the direction of safety function(lack of proper isolation valves, test connections, etc.).
Revision 311/84
»
I~
'f
tfI
4tl t t t
III t
~
*»I I'tl 3 II
&Igb t
I'
RELIEF RE UEST NUMBER 20 '(Cont'd)
Page 73 of 113
Pressurization in the direction of safety function wouldrequire actions such as pressurizing the containment(equivalent to an ILRT) or precisely controlling the entireRCS at the valve test pressure.
Alternative Testing: Leak test each valve in the reverse direction.Penetration will be subjected to test pressures in thecorrect direction during containment integrated leakrate tests.
0Revision 311/84
ci" 4 v~ ~ l"
a
I
"'x( I'
0
Page 74 of 113
RELIEF RE UEST NUMBER 21
System:
P &ID
Valves:
Reactor Core Isolation Cooling
M-149
1F028, 1F040, 1F021
Category:
Class:
A$ C
Function: Containment Isolation
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: These check valves are not equipped with positionindication and system design does not provide any practicalmethod of verifying closure other than pressurizationsimilar to leak rate testing. Such testing requiresinstallation of temporary equipment which is impractical ona quarterly basis, and it would render the RCIC systeminoperable during the testing period. While RCIC is not anECCS system, it is important to safety and can provide anadditional margin for prevention or mitigation of reactortransients. Normally, testing of this type is accomplishedby required containment local leak rate testing inaccordance with 10CFR50, Appendix J. More frequentperformance represents an unnecessary burden on thelicensee.
Alternative Testing: Demonstrate closure by completion of leak rate testingperformed once per 24 months.
Revision 311/84
0
II ~ M
F I'
,I ~ 0~
I'
P, ~M
IF
) ~0
'I 0 'FM 'I I 'f~ r, ' 0 1 ...MM
F *r
I,,II
0
V0
lt
II'
Page 75 of 113
RELIEF RE UEST NUMBER 22
System:
P&ID:
Valves:
Reactor Core Isolation Cooling
M-149
1F063, 1F064
Category:
Class:
Function: Vacuum Breaker
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: These vacuum breakers installed on the RCIC turbine exhaustline are not provided with position indication equipmentnor is there pressure indication installed that wouldprovide positive verification of valve operation. Apractical method of testing involves supplying low pressureair upstream of the valve and verifying that flow can bedetected downstream of the valve. This test methodinvolves installation of temporary equipment and is notpractical except during major outages, and it would renderthe RCIC system inoperable during the testing period.While RCIC is not an ECCS system, it is important to safetyand can provide an additional margin for prevention ormitigation of reactor tranients. Normally, testing of thistype is accomplished by"required containment local leakrate testing in accordance with 10CFR50, Appendix J. Morefrequent performance represents an unnecessary burden onthe licensee.
Alternative Testing: Commencing with the first refueling outage, verifyopening once per 24 months in con)unction with leakrate testing.
Revision 311/84
t h
P ~
s
) i
II
Page 76 of 113
RELIEF RE VEST NUMBER 23
System:
P&ID:
Valves:
Residual Heat Removal
M-151 S}1. 2
HV-1F008, HV-1F009
Category: A
Class: 1
Function: Containment Isolation (Shutdown Cooling)
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These normally closed isolation valves are only required toopen when bringing the unit to a cold shutdown condition,providing the flowpath for the shutdown cooling mode ofRHR. In accordance with guidance presented in IEInformation Notice 84-74, draft R.G. 901-4, and previousNRC concerns regarding intersystem LOCAs, cycling thesevalves every 92 days during power operation increases theprobability of exposing the downstream low pressure pipingto,reactor coolant pressure (since only one valve wouldhave to be ruptured or failed open to'xpose the lowpressure system to reactor coolant pressure). Duringreactor operations above aproximately 100 psig, interlocksinhibit'cycling of these valves for the express purpose ofprotecting low pressure piping.
Alternative Testing: Exercise valves during cold shutdown (no morefrequently than once per 92 days).
Revision 311/84
t
~ C i 1
IV 1 f
Page 77 of 113
RELIEF RE VEST NOSER 24
~Re
tern
ESW (on ServiceWater P&ID)
ESW (on ServiceWater P&ID)
Core Spray
Core Spray
Core Spray
Core Spray
HPCI
RHR
RHR
P&ID
M-110
M-110
M-152
M-152
M-152
M-152
M-155
M-151
M-151
Valve
1-10-109
1-10-112
1F029A
1F029B
1F030A
1F030B
1-55-012
1F090A
1F090B
Class
Category:
Function: Prevent backflow dovn "keep fill"line.
Impractical Test Requirement: Exercise valves closed once per 92 days.
Revision 311/84
~ ~ 4
ft
Page 78 of 113
RELIEF RE VEST NUMBER 24 (Cont'd)
Basis for Relief: 1) HPCI, RHR, & ESW
The check valves, located in "keep fill"lines for theHPCI, RHR, & ESW systems, serve an identical functionas those associated with Core Spray. The differentfeature in these systems is that there are testconnections between the two check valves in each line.Using these test connections in HPCI & RHR to monitoressentially restricted flow will involve collectingpotentially contaminated seepage while performing a"full flow" test of the systems. This creates thepotential for spillage and further contamination.
The increased water hammer potential in ESW & HPCI andthe burden on the licensee of handling contaminated
" seepage dictates that testing be performed lessfrequently. ,The fact that two che'ck valves are inseries lessens the probability of failure to retardbackflow. The small line size involved minimizes theimpact of such a failure. These circumstances warranttesting on the frequency requested.
2) Core Spray
These check valves, located in keep filllines for theCore Spray System, permit Condensate Storage andTransfer water flow into the respective headers whilepreventing process flow in the reverse directionduring CS system operation. The two check valves ineach line are located in series within several inchesof each other. There are no vent, drain or testvalves located between or upstream of the checkvalves. Therefore, no practical method exists toverify closure of either valve upon cessation orreversal of flow., A relief valve located upstream ofthe check valves is set to actuate at approximately150 psig, while Core Spray System pressure is greaterthan 250 psig.
Revision 311/84
)
)
It1
~" 't t'
~ '"
'
Page 79 of 113
RELIEF RE VEST NUMBER 24 (Cont'd)
Alternative Testing: 1) Commencing with the first refueling outage, testthe RHR, HPCI, & ESW "keep fill"line checkvalves by monitoring essentially restricted flowthrough the test connections once per refuelingoutage during a "full flow" test of therespective system.
2) During refueling outage full flow tests of theCore Spray System, closure of at least one of thetwo check valves in each pair will bedemonstrated by manual lifting of the upstreamrelief valve to provide a more positive means ofvalve seating and to preclude the possibility ofthe check valve not properly reseating duringPlant Conditions 1, 2, or 3. This test will beperformed when in modes 4 or 5.
Revision 311/84
I 4 tlI',
4 4~I ~
4
tlt, I fg
MM
hMI pt,
M
~ ~ I
II
5 fI
11 ~ I IM,
4 ~
II "I~
'IM
RELIEF RE VEST NUMBER 25
Page 80 of 113
System:
P&ID:
Residual Heat Removal
M-151 Sh. 1 and Sh. 2
Valves: a) PV-lF051A,Bb) HV-1F053A,B
Category: B
Class: 2
Function: a) Steam Condensing Mode Pressure Controlb) Isolation from RCIC suction
Impractical Test Requirement: Exercise valves once per 92 days and measurestroke times.
Basis for Relief: PV-1F051A(B), HV-lF053A(B), and PV-1F052A(B) are allcontrolled through the same handswitch (HS-15151A(B)).Attempting to cycle either PV-1F051A(B) or HV-1F053A(B)would result in a cycling of all three valves. This wouldcause steam to be introduced into the RHR heat exchangerthereby degrading the functions of suppression pool coolingand spray. It is also possible, if this line isoverpressurized, to actuate relief valve PSV-1F055A(B)which will deposit heat in the suppression pool with thepossible result of exceeding the limit of 90'F required byTechnical Specification 3.6.2.1. These valves, whenperforming their function, are set at some variableintermediate position. It is not practical to monitorstroke timei of such,,a valve as it will change dependentupon the set position.
Alternative Testing: Exercise valves during cold shutdowns (no morefrequently than once per 92 days) with no stroke timemeasurement, only, verification of proper movement toits "fail-safe" position.
Revision 311/84
k
k
k >7 1
I
~ ~
I"'I ~ *,
e „, klh
\f I
I*> 1 h
I1
e
~ \ >I >j'
Page 81 of 113
RELIEF RE UEST NUMBER 26
System:
P&ID:
Residual Heat Removal
M-151 Sh. 1 and Sh. 2
Valve ~Cate ~~orp
HV-1F015AHV-1F015BHV-1F022HV-1F023HV-1F050AHV-1F050BHV-1F122AHV-1F122B
AAAA
A,CA,C
AA
Class: 1
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These normally closed isolation valves serve as thepressure isolation between RHR system piping and reactorcoolant pressure. In accordance with guidance presented inIE Information Notice 84-74, draft R.G. 901-4, and previousNRC concerns regarding intersystem LOCAs, cycling thesevalves every 92 days during power operation increases theprobability of exposing the downstream low pressure pipingto reactor coolant pressure (since only one valve wouldhave to be ruptured or stuck open to expose the lowpressure system to reactor coolant pressure). Maintenancehistory on these valves has shown that excessive cycling atpressure will reduce the leak tightness of the valves. Inaddition, failure of these valves during testing topositively re-seat could cause loss of RHR system function.
Alternative Testing: Exercise valves during cold shutdowns (no morefrequently than once per 92 days).
Revision 3. 11/84
»
I I I ',t ht
h
)„,» h
r ~,
hÃ"
h
h It
hh ItIt» lt t
I» lt / h t t
'»IIt ' th
II 1» ~
rt»r
hd ';I ~
II
tt
I'
P
f It
ttt I'h ti I 11
I ~ ''
tt , trTqh'(
Page 82 of 113
RELIEF RE UEST NUMBER 27
System:
PAID:
Emergency Service Water
M-111 Sheet 1
Valves: 0-11-0330-11-0340»11-0350-11-036
0-11-0370-11-0380-11-0390-11-040
Category:
Class:
Function: Diesel generator cooling flowpath alignment.
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: Individual pressure or flow indication is not provided onESW cooling lines to the diesel generators, nor is positionindication installed. This configuration provides nodirect evidence of valve position during system operation.A level of assurance of proper valve operation is providedby observation of appropriate system flows during ESW pumptesting and adequate cooling during diesel generatoroperation.
Due to the sharing of diesel generators between two units,removal of a diesel generator from service to accomplishthe alternative inspections will normally occur with oneunit in operation. Minimization of these inspections isindicated.
Alternative Testing: Verify proper valve functioning by valve disassembly.Commencing with the first refueling outage, fourvalves will be inspected every other refueling outageof Unit 1.
Revision 311/84
f
4
R
0
Page 83 of 113
RELIEF RE UEST NUMBER 28
System:
P&ID
Valves:
Category:
Class:
High Pressure Coolant Infection
M-155
1F049, 1F046
A, C
Function: Containment Isolation
Impractical Test Requirement: Exercise valve closed once per 92 days.
Basis for Relief:
a
Alternative Testing: Demonstrate closure once per 24 months by completionof leak rate testing.
This valve is not equipped with position indication. Itsconfiguration with an open discharge into the suppressionpool prevents usage of reverse flow to demonstrate closure.No practical method exists to perform closure testing otherthan the downstream pressurization of leak rate testing.Such testing requires installation of temporary equipment
nd closure of valves which renders the system inoperable.
Revision 311/84
'llr ' 4 ~ (I'If 4 4 ', "" g''4,
4 rh
~) I~
l -h l)C
4
4 ~
«thP
4
t-h
hah ) ) 'Ia 4
'4
g,h n
Page 84 of 113
RELIEF RE VEST NUMBER 29
System:
P&ID:
Valve:
High Pressure Coolant Injection
M-155
HV-1F006
Category:
Class:
Function: Containment Isolation, HPCI Injection
Impractical Test Requirement: Exercise valve once per 92 days.
Alternative Testing:
Basis for Relief: This valve is in the HPCI injection flowpath. Theinterlocks on this valve prevent its being open unless theSteam Admission and Turbine Stop Valves are open. This isonly possible during pump flow testing. Cycling this valveduring, normal plant operation or HPCI testing may lead toHPCI injection into the vessel. This would affect reactoroperations and introduce a thermal transient in the vesselnozzle.
Exercise valve during cold„shutdowns (no morefrequently than once per 92 days).
Revision 311/84
»
h,
»'
lh
h
h
cv
»
'- »
Page 85 of 113
RELIEF RE UEST NUMBER 30
System:
P&ID:
General
General
Valves: All valves specified as tested on a cold shutdown or refuelingfrequency.
Category: As applicable
Class: As applicable
Function: As applicable
Impractical Test Requirement: Paragraph IWV-3417(a) of Section XI requiresthat should an unacceptable increase instroke time be observed, the valve testfrequency shall be increased to once permonth until corrective action is taken.
Basis for Relief: Valves are tested on a cold shutdown or refueling frequencybecause there is a defined basis for exemption fromquarterly testing frequency during power operation (e.g.,the plant is put into an unsafe condition, system designdoes not permit testing). This same reasoning would,therefore, provide the basis for exemption from the monthlytesting as well.
Alternative Testing: The testing frequency will remain unchanged. Therequirements contained in the Susquehanna SteamElectric Station Technical Specifications will controlplant operations with regard to out-of-service valves.
Revision 311/84
II'1 0
f',Hh
,I A,g ~4'I'
4
q ~
l' llC'
I 'I $
a
8 III 5 II
/ f, W
1
h
S E', I f t
1
1I „f
'I
l I
i
I ~ ~}" A
l'
Page 86 of 113
RELIEF RE VEST NUMBER 31
System:
PAID:
High Pressure Coolant Injection
M-155
Valves: 1F045
Category:
Class:
Function: Backflow Prevention
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: To verify proper opening of this valve, it is necessary toinitiate HPCI flow while taking suction from thesuppression pool. Since the water quality in thesuppression pool is not maintained at reactor coolantstandards, it is not advisable to initiate this flow at anytime during normal operations. The resulting contaminationof the HPCI system from such flow testing would affect thecondensate storage tank purity and ultimately affect thechemistry control of the reactor coolant system. Thereexists no other practical method of verifying proper valveoperation.
Alternative Testing: Verify operability by inspection during valvedisassembly. Commencing with the second refuelingoutage, the valve will be disassembled at least onceevery other refueling outage on an alternating basis.
Revision 311/84
~ ~
III~ P 4
pal
~ I~; nr,."ri »" I ~
)i ,I ~
Page 87 of 113
RELIEF RE UEST NUMBER 32
System:
P&ID:
High Pressure Coolant Injection
M-155
Valves: 1F019
Category: C
Class: 2 1I
Function: Backflow Prevention
Impractical Test Requirement: Exercise valve closed once per 92 days.I
0
Basis for Relief: This check valve in the HPCI pump suction line is notinstalled in a configuration permitting positiveverification of valve closure. As stated in Relief RequestNumber 31, alignment of the HPCI pump to the suppressionpool is not desirable. Attempting to verify closure duringleak rate testing of 1F045 will not provide positiveverification, since there is no appropriate pressureinstrumentation provided on the CST side of 1F019, andlevel changes in the CST would not be readily detected dueto the large tank volume.
Alternative Testing: Verify operability by inspection during valvedisassembly. Commencing with the second refuelingoutage, the valve will be disassembled at least onceevery other refueling outage on an alternating basis.
Revision 311/84
,e
.' l J l) ' 'l 'i ~ ~ei~
thill
«< f
0
T"
Page 88 of 113
RELIEF RE UEST NUMBER 33
Relief Request Deleted.
This Page Intentionally Left Blank.
Revision 311/84
~ tQ V
I''
'I
Vk
Page 89 of 113
RELIEF RE VEST NUMBER 33 (Cont'd)
Relief Request Deleted.
This Page Intentionally Left Blank.
Revision 311/84
h 0
S
'I
I
Page 90 of 113
RELIEF RE VEST NUMBER 33 (Cont'd)
Relief Request Deleted.
This Page Intentionally Left Blank.
Revision 311/84
Page 91 of 113
RELIEF RE VEST ',NUMBER 33 (Cont!d)
Relief Request Deleted.
This Page Intentionally Left Blank.
Revision 311/84
C 1, f ) II
~.} ~ f'
'ff
Page 92 of 113
RELIEF RE UEST NUMBER 34
System:
P&ID
Valves:
High Pressure Coolant Injection
M-155
1F076, 1F077
Category:
Class:
Function: Vacuum Breaker
Impractical Test'equirement: Exercise valve once per 92 days.
Basis for Relief: These vacuum breakers installed on the HPCI turbine exhaustline are not provided with position indication equipmentnor is there pressure indication installed that wouldprovide positive verification of valve operation. Apractical method of testing involves supplying low pressureair upstream of the valves and verifying that flow can bedetected downstream of the valve. This test methodinvolves installation of temporary equipment and is notpractical except during major outages. Its implementationwould also require temporary removal of the HPCI Systemfrom service.
Alternative Testing: Commencing with the first refueling outage, verifyopening once per 24 months in conjunction with leakrate testing.
Revision 311/84
4
4 '1
I i1 II
4
fl
I I
"'ll j 4F
'.' 1I. I
,, I II
lI4
~ ~ E I
4
I fff4 I
I KI
4 " I II4
0 k 41
4
~~ C
4'
I1
I ~)II I 'I 4
4
"y" I)4( ti pgtw Ip* 4
„)I)r, S-
4,, I 1' a.4
14, "44,. I
RELIEF RE UEST NUMBER 35
Page 93 of 113
System:
P&ID:
Valves:
General
General
All containment isolation valves.
Category: A
Class: As applicable to specific valves.
Function: Containment Isolation
Impractical Test Requirement: Category A valves shall be tested inaccordance with Section XI, ParagraphIWV-3420.
Basis for Relief: Containment leakage rate testing is governed by 10CFR50Appendix J and Susquehanna SES Technical Specification3/4.6.1.2. Compliance with these requirements is describedin FSAR Section 6.2.6 and in FSAR Tables 6.2-19 through6.2-22. Leak rates for individual valves are not specifiedbut rather leak rate criteria are determined in SusquehannaSteam Electric Station Technical Specifications. Thistesting adequately assures the isolation capabilities ofthese valves.
Alternative Testing: Containment isolation valve leak testing (with theexception of identified pressure isolation) will beperformed in accordance with FSAR Section 6.2.6 andFSAR Tables 6.2-19 through 6.2-22.
Revision 311/84
~ It FP tt
hh(
~ ~
~ ~ r ~
~ Ft
h~ 'P
) „'e'lr)
tt PP
"II ~ II 'PP'I
7,.a'
r
e 'h F
Page 94 of 113
RELIEF RE UEST NUMBER 36
This Page Intentionally Left Blank.
Revision 311/84
RELIEF RE VEST NUMBER 37
Page 95 of 113
System:
PAID:
Containment Atmosphere Control
M-157 Sht. 1
Valves: HV-15703HV-15704HV-15705HV-15711
HV-15713HV-15714HV-15721HV-15722
HV-15723HV-15724HV-15725
Category: A
Class: 2
Function: Containment Isolation
Impractical Test Requirement: Exercise valve once per 92 days.
Basis for Relief: These normally closed containment isolation valves on thecontainment purge inlet and exhaust lines are not openedduring power operations except during startup for inertingpurposes and during shutdown procedure to de-inert. It isnot good practice to cycle a normally closed containmentisolation valve, as this increases the possibility offailure in the open position. Technical Specification3.6.1.8 controls and limits the amount of time these valvescan be open in a one-year period.
Alternative Testing: Exercise valves at cold shutdown (no more frequentlythan once per 92 days).
Revision 311/84
4II
J~
C
P
I0
0 RELIEF RE VEST NUMBER 38
Page 96 of 113
System: Various
P&ID: Various
Valves: Those designated "Rapid-Acting" in the REMARKS column.
Category: A or B
Class: 1 or 2
Function: Various (sample, containment isolation, etc.)
Impractical Test Requirement: Trend valve stroke times per IWV-3417(a).
0
Basis for Relief: The listed valves, designated as "rapid acting valves,"have stroke times of such short duration that comparison ofmeasurements with previous data for specified percentageincreases is not indicative of degrading valve performance.With measurement of stroke times to the nearest second perIWV-3413(b), a very small increase in stroke time willresult in an extremely large percentage change.Verification that valves meet a specified maximum stroketime of short duration provides adequate assurance ofoperability.
Alternative Testing: The maximum stroke time will be verified for all thesevalves when tested.
Revision 311/84
h Pl
Pangs ~ PI'I ll '
~hff h P/)Pl ll ~ ~
P'll ~ P P
$ $1I I "1
Page 97 of 113
RELIEF RE UEST NUMBER 39
System:
P&ID:
Valves: HV-18791A1'HV-18791A2HV-18791B1HV-18791B2
HV-18792A1HV-18792A2HV-18792B1HV-18792B2
Reactor Building Chilled Water
M-187 Sh. 2
Category: A
Class: 2
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Exercise valves during cold shutdowns (no morefrequently than once per 92 days).
Basis for Relief: These containment isolation valves are located in theReactor Building Chilled Water supply and return linesserving the Reactor Recirculation pump motor coolers. Theclosure of these valves during power operation willinterrupt cooling water flow to the Reactor Recirculationmotor coolers, which creates the possibility of overheatingand damage.
Alternative Testing:
Revision 311/84
w
t,> ~
~F. t
P
Page 98 of 113
RELIEF RE VEST NUMBER 40
System:
P&ID
Control Structure Chilled Water
M-186
Valves ~Cata ot Class
0-86-018
0-86-118
0-86-039
0-86-139
HV-08613A
HV-08613B
SV-08621A
SV-08621B
Non-Code; Safety Function
Non-Code; Safety Function
Non-Code; Safety Function
Non-Code; Safety Function
Function: Condenser and Chilled Water Flowpath
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: The ultimate function of these valves is providing chilledwater to the cooling coils of the Control Structure HVACsystem. Rather than individually testing each valve forproper functioning, operation of the chilled water loopwith cooling supplied by the emergency condenser loopprovides a functional system test which is indicative ofproper operation of all system components. As this is anauxiliary support system rather than a water-supply system,this testing provides more meaningful results thanindividual valve testing.
Individual stroke testing (including stroke timemeasurement) of power operated valves in these subsystemsis not feasible. System interlocks require initiation andstartup of circulating pumps and/or chiller, after whichthe valves automatically actuate. Time delays andequipment actuation times render any attempts at stroketime measurement meaningless. No provision is made for
Revision 311/84
I Vh
Page 99 of 113
RELIEF RE VEST NUMBER 40 (Cont'd)
individual stroking of power operated valves in thecircuitry.
Alternative Testing: In conjunction with the chiller pump tests, monitorthe chilled water loop chiller discharge temperatureand verify that the specified discharge temperaturesare maintained.
4
Revision 311/84
k
W~
0
Page 100 of 113
RELIEF RE UEST NUMBER 41
System:
P&ID:
General
General
Valves: All Fail-Safe Valves
Category: As applicable
Class: As applicable
Function: As applicable
Impractical Test Requirement: Paragraph IWV-3415, Section XI
Basis for Relief: Valves which have a "fail-safe" requirement at SusquehannaSteam Electric Station will normally be cycled once every92 days, unless otherwise relieved. This test willaccomplish the intent of the "fail-safe" test becausenormal valve movement is achieved by means of interruptingmotive force to the valve.
Alternative Testing: No additional testing of "fail-safe" provisions willbe done because normal valve testing will achieve thesame results.
Revision 311/84
«F'
'IIQ P « II ' ,g '« I
I
,«5 I « F' !
F'F jI «
«
~«. $ ~~ '
«F
I'I«F
~
\~
FI
Page 101 of 113
RELIEF RE UEST NUMBER 42
System: General
P6ID: General
Valves: All pressure relief valves.
Category: As applicable
Class: As applicable
Function: System Overpressure Protection
Impractical Test Requirement: Paragraph IWV-3100, all valves shall bepressure tested after installation and priorto seivice.
Basis for Relief: Pressure relief valves used at Susquehanna SES have beenpurchased in accordance with specifications which requireperformance testing at the manufacturer's shop. Records ofthese tests are part of the Quality Assurance records. Inaddition, a technical procedure requires inspection of thesealing mechanism as part of the preoperational/acceptancetest program.
Alternative Testing: No additional testing beyond that which was performedas part of the purchase and installation will beperformed. The records will remain part of either thepurchase or preoperational records and not part of theISI files.
Revision 311/84
c CCI 1' C
)
CCl, "1
'l"II
~,
l
f 1'
1 II ~
gC' ~ g 'J II ll f I f)
I
J k" I r
~ I ~II
1,1 C' 'IC, CC III
'l
II 1
II I I
SI
r ltI
"1
41
Page 102 of 113
RELIEF RE VEST NUMBER 43
System:
PAID:
Standby Liquid Control
M-148
Pumps: 1P208 A,B
Class: 2
Function: Standby Liquid Control Pumps
Impractical Test Requirement: Measure inlet pressure prior to and duringpump test and measure pump delta-p duringpump test.
Basis for Relief: System configuration does not provide a pressure indicatoron the pump,suctions. It is possible to determine suctionpressure by calculation from tank level (elevationdifference) when the pumps are in normal alignment to theSLC Storage Tank. However, when pump testing is beingperformed, the tank is valved out and the suctions arealigned to a demineralized water header. While someestimation of the pressure in this alignment is availableby the setting of the pressure control valve on thedemineralized water header, no direct pressure indicationis available. Since the SLC pumps are positivedisplacement type pumps, suction pressure will not affectdeveloped discharge pressure.
Alternative Testing: Do not measure inlet pressure prior to or during pumptests. Utilize pump discharge pressure reading inlieu of Pump delta-p reading.
Revision 311/84
,f P'lR
n
Page 103 of 113
RELIEF RE VEST NUMBER 44
System:
P&ID:
High Pressure Coolant Injection
M-156
Pumps: 1P204 A,B
Class: 2
Function: HPCI Main and Booster Pumps
Impractical Test Requirement: If not tested during plant shutdown, thepump shall be tested within one week afterthe plant is returned to normal operation.
Basis for Relief: The required steam supply pressure for HPCI surveillanceflow verification testing is specified in the TechnicalSpecification's. This pressure may not be attained withinthe above prescribed time interval.
Alternative Testing: Perform HPCI flow verification test in accordance withquarterly schedule. After a shutdown which hasexceeded the quarterly limit, recommence quarterlyschedule in accordance with Technical Specification4.5.1.b.3.
Revision 311/84
I
g
4~
lr y,
e* ~' ~
tII
C
'
CI h
I I'-n P
IP
k
',cf,»I
$
4.y ~ 't sf
I g 0'gFy
P
1-
"s, i pe
0 ~ ~ ~
Page 104 of 113
RELIEF RE UEST NUMBER 45
System:
P &ID:
Core Spray
M-152
Valves ~Cate ot
HV-1F005AHV-1F005B
'V-1F006AHV-1F006BHV-1F037AHV-1F037B
AA
A,CA$ C
AA
Class: 1
Function: Containment Isolation
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These normally closed Isolation valves serve as thepressure isolation between CS system piping and reactorvessel pressure. In accordance with guidance presented inIE Information Notice 84-74, draft R.G. 901-4, and previousNRC concerns regarding intersystem LOCAs, cycling thesevalves every 92 days during power operation increases theprobability of exposing the downstream low pressure pipingto reactor coolant pressure (since only one valve wouldhave to be ruptured or failed open to expose the lowpressure system to reactor coolant pressure). In addition,failure of these valves after, testing to positively reseatcould cause loss of Core Spray system function.
Alternative Testing: Exercise valves during cold shutdown (no morefrequently than once per 92 days).
Revision 311/84
P0
«
~ «»
».
Ig«
PP
-„P
«
Page 105 of 113
RELIEF RE VEST NUMBER 46
System: General
PAID: General
Valves/Pumps: General
Category: As applicable
Class: As applicable
Function: As applicable
Impractical Test Requirement: Test equipment in accordance with Section XIfrequency requirements.
E
Alternative Testing: Testing will be suspended on equipment in operableloop when there is a redundant loop out-of-service.
Basis for Relief: With one loop out-of-service in a system, it is notdesirable to test the redundant loop per ISI requirementsas such testing may increase the chance of failure in acondition where backup equipment is not available. Also,these situations will be governed by the Susquehanna Steamlectric Station Technical Specifications.
Revision 311/84
'I
'1 ~ —1
IIg
*
Page 106 of 113
RELIEF RE VEST NUMBER 47
System:
PAID:
Diesel Fuel Oil Transfer
M-120
Pumps: OP514 A thru D
Valves: 0-20-007/009/012/015
Class: Non-Code; Safety Function
Function: Fuel Oil Transfer from Storage Tank to Day Tank
Impractical Test Requirement: Test in accordance with IWP/IWV.
Basis for Relief: These pumps are a sealed-unit submersible type with theentire unit submerged in the Diesel Oil Storage Tanks. TheSusquehanna Steam Electric Station Technical Specificationspresently require at least a monthly functional test ofthese pumps. This test verifies fuel oil flow from thestorage tank to each diesels skid-mounted day tank.Similarly, the diesel oil firing pumps are tested duringthe diesel functional tests. These pumps take suction fromthe day tank and supply the diesel cylinders. SSESconsiders all these pumps an extension of the diesel engineequipment skid, and therefore all are adequately tested perTechnical Specifications along with the diesel itself. Inaddition the actual flowrate for the diesel fuel oiltransfer pumps is over five times the required dieselengine fuel usage at rated conditions. Thus, even a largereduction in pump flow will not affect system operability.The pump discharge check valves are similarly testedmonthly via plant Technical Specifications.
Alternative Testing: Each pump will continue to be functionally tested atleast monthly via Technical Specification 4.8.1.1.2.No other testing need be performed.
Revision 311/84
Ih
I
RELIEF RE VEST NUMBER 48
Page 107 of 113
System:
P&ID
High Pressure Coolant In)ection
M-156
Pumps: 1P204 A,B
Class: 2
Function: HPCI main and booster pumps
Impractical Test Requirement: Paragraph IWP-4310, Bearing TemperatureMeasurement.
Basis for Relief: These pumps are driven by a steam turbine which exhaustssteam into the suppression pool. Extended run timesnecessary to achieve stabilized bearing temperatures couldheat the suppression pool water to a temperature exceedingthe Technical Specification limit of 105'F.
Alternative Testing: Eliminate bearing temperature measurement. Vibrationmeasurements will give adequate information concerningpotential bearing temperature problems.
Revision 311/84
)0) l 0) ggr 0 *000
0
~ "0 fj
~ 'g'Pk hl Ir
0 'llh 1''
, Ilg
I
, ~
0
CP I
IP
P
pl>0th('
~ ~ r
~ I* 0I " 'I I
rr ~ 0 'I
rll Ill 0 'h 0
f0 0 0
y II
Page 108 of 113
RELIEF RE UEST NUMBER 49
System:
PAID:
Pumps:
Class:
S tandby Liquid Control
M-148
1P208 A,B
Function: Injection of sodium pentaborate into Rx vessel.
Impractical Test Requirement: a) IWP-3500(b), bearing temperaturestabilization.
b) IWP-3500(a), five minute minimumrun time.
Basis for Relief: One characteristic of positive displacement pumps is thatthere is essentially no lag time between starting the pumpsand reaching equilibrium conditions. To measure pump flowrate, the measured rate of drainage from the test tank(IT-203) is measured. No installed instrumentation isavailable to measure flow rate. This testing configurationprevents recirculation of the pump discharge flow throughthe test tank during the test. Since the capacity of thetest tank is 210 gallons and the pumps rated flow is 43gpm, the tank will overflow before bearing temperature isstabilized. The pump bearings are located in a motorgearbox and no direct measurement of gearbox oiltemperature is possible. The gearbox casing is not areproducible measurement point. In addition, the test tankwould be very close to overflow if a five minute run timetest is performed.
Alternative Testing: Vibration measurements will give informationconcerning potential bearing problems. The pump flowrate will be measured and changes in pump flow rateprovide an early indication of degradation in pumpperformance. The pumps will be run for a period oftime which will not cause the capacity of the testtank to be exceeded.
Revision 311/84
~''f
I ~,II
I )
l
i'f
RELIEF RE VEST NUMBER 50
Page 109 of 113
System:
P&ID:
Control Structure Chilled Water
M-186
~Pum Class Function
OP162AOP162BOP171AOP171B
Chilled water loop circulating pumpChilled water loop circulating pumpEmergency condenser water circulating pumpEmergency condenser water circulating pump
Impractical Test Requirement: Test pumps once per 92 days per requirementsof Section XI, Subsection IWP.
Basis for Relief: The ultimate function of these pumps is to provide chilledwater to the cooling coils of the Control Structure HVACsystem. Rather than individually testing each pump forproper functioning based on the prescribed measurementsrequired by IWP, operation of the chilled water loop withcooling supplied by the emergency condenser loop provides afunctional system test which is indicative of properoperation of all system components. This testing is morepractical and provides a method of pump testing which doesnot require the removal of this safety system fromoperation. See Relief Request Number 40.
Alternative Testing: Monitor the chilled water loop chiller dischargetemperature and verify that the specified dischargetemperature is maintained.
Revision 311/84
h
I „
I
„'I
I
~ y
II
I F
I ~ J
I
,, E
AI
If I~ 'I
F III h
0
Page 110 of 113
RELIEF RE UEST NUMBER 51
System:
P&ID:
Valves:
Emergency Service Water
M-ill, Sheet 1
0-11-001, 0-11-002, 0-11-003, 0-11-004
Category: C
Class: 3
Function: Pump Discharge Check
Impractical Test Requirement: Exercise valves once per 92 days.
Basis for Relief: These check valves, located in the pump discharge, arerequired to open during system operation to permit coolingwater flow to system loads. Due to the presence ofautomatic motor-operated valves in series with the checkvalves, closure is not a safety function. During quarterlypump tests, the valves are in fact cycled open and designflow passed through, indicating operability. However, asdiscussed in IE Bulletin 83-03, such testing in raw watercooling systems may be inadequate to ensure valvemechanical integrity.
Alternative Testing: In addition to quarterly exercising in con)unctionwith pump tests, verify valve mechanical integrity byvisual inspection during disassembly. Commencing withthe first refueling outage, 1 valve from each loopwill be disassembled at least once per 18 months suchthat all valves are inspected at least once per 36months.
'Revision 311/84
I
I It
u
ii"
II
Page ill of 113
RELIEF RE UEST NUMBER 52
System:
P&ID:
Pumps:
Class:
RHR, Core Spray, ESW, RHRSW, HPCI, SBLC
Various
All in above systems
Various
Function: Process flow for above systems
Impractical Test Requirement: Section XI, Paragraph IWP-3210, AllowableRanges of Inservice Test Quantities
Basis for Relief: Ranges of acceptable instrument accuracies, as establishedby ASME Section XI paragraph IWP-4110 and Table IWP-4110-1allow up to 6% error in pump pressure and flow readings dueto acceptable instrument accuracy of 6% (2% of full scalerange times full scale range <3 times reference value).
In contrast, the acceptable pump pressure and flow valuesrequired to result from pump tests, as established by ASMESection XI paragraph IWP-3100 and Table IWP-3100-2, arelimited to a range extending only 2% above thecorresponding reference value and only 6% flow or 7%
pressure below the reference value.
Alternative Testing: Actual instrument accuracies shall be applied toindicated values of pump flow and pressure. Thevalues of pump flow and pressure, so corrected for theeffects of instrument accuracy, shall be compared tothe allowable ranges for the corresponding testquantities, from Table IWP-3100-2, for determinationof acceptability.
Instrument accuracies for use in these correctionsshall be determined, as needed, by calibration of theflow, and/or pressure instruments utilized for the pumptest.
Actual instrument accuracies for use in thesecorrections shall conform to the ac'ceptable instrumentaccuracies established for flow instruments and forpressure instruments by Table IWP-4110-1.
Revision 311/84
~ II
FII
tM
V T
P
P
~ < " r
t
RELIEF RE UEST NUMBER 53
Page 112 of 113
System: HPCI
P&ID
Valves:
M-156
FV-15612
Category: B
Class: 2
Function: Opens to admit steam to HPCI turbine, closes to isolate steam inthe event of a turbine trip.
Impractical Test Requirements: Stroke time valves when exercised, once per92 days.
Basis for Relief: The HPCI Turbine Stop Valve, FV-15612, has a design stroketime of 0.5 seconds. In keeping with current philosophyregarding other rapid-acting valves, this valve cannot betimed accurately and thus cannot be trended from test-to-test. Minor variations in each test could cause needlessadditional testing, which would require rendering the HPCIsystem inoperable.
Alternative Testing: Valve will be tested functionally each time the HPCIturbine is tested (quarterly). No stroke timing or
, trending will be performed. In addition, responsetime testing for the HPCI system will be performed inaccordance with Technical Specifications once per 18months.
Revision 311/84
a
„ I ~ 1*
I
I
1 b I
~ 'I
~ 1
I ~ ay
II I 'I
I ~ ''a1 '
I pa
I
'I I
I " Ia"'
1
1I' a
I'
I
a) "
I
1a11'll all ~
1 C-)I
a <11
a
I
I
I
~ la ''
I 1L
RELIEF RE VEST NUMBER 54
Page 113 of 113
System:
PAID:
RHR, Core Spray, ESW, RHRSW
Various
Pumps: All in above systems
Class: Various
Function: Process flow for above systems
Impractical Test Requirement: Measure bearing temperature and lubricantlevel or pressure during test.
Basis for Relief: The bearings for the pumps listed above are lubricated bythe flowing fluid and therefoxe require no verification ofadequate lubrication. Similarly, the bearing temperaturescannot be accurately measuxed due to the flowing fluid.
Alternative Testing: None; component vibration readings will serve asindications of pump mechanical condition.
eRevision 311/84
« ~K
'* V 'I »4«
~" ~ ~ 't 4'='" ~ t;,>
~ 44
~ . '
'4
~ I »4 .
I I »I'
I™
,'.f ~ «4 ~ I"fl,'4 'I
ll» «It~
~ 4, «,;II
«