review fhc 14 031

Upload: triadi-bagus-gumilar

Post on 07-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Review FHC 14 031

    1/7

     

    REVIEW FORM

    No. Registrasi FHC-14-031

    Nama Tim ABHIPRAYA

    Perguruan Tinggi Politeknik Negeri Bandung

    Dami House

    No. Content

    1.

    2.

    3.

    4.

    Analisa elemen struktur (balok, kolom, dinding,sambungan dan pondasi)

    Analisa RAB direvisi sesuai dengan standard yang dikeluarkan panitia (file terlampir)

    Lengkapi konsep design

    Perhatikan rasio biaya struktural dan arsitektural

    STR-Fabricated House Competition, First Screening

    Jakarta, 13 Agustus 2014 Juries

    1. Ir. Sumargo, M.Sc., Ph.D

    2. Prof. Tavio, Ph.D

    3. Prof. Ir. Bhakti Setiawan, M.A., Ph.D.

    4. Dr.Ir. Arief Sabaruddin, CES.

    5. Tjetjep Hartono, Dipl. Ing.

    6. Agus Erfien

  • 8/18/2019 Review FHC 14 031

    2/7

     ANALISA HARGA PEKERJAAN

    No Pekerjaan Indek Satuan Harga Jum lah Harga Harga Total  

    PEKERJAAN PEMBERSIHAN LAPANGAN / M2 5,300.00 

    Mandor 0.005  org/hr 60,000.00  300.00 

    Pekerja 0.100  org/hr 50,000.00  5,000.00 

    PEKERJAAN PENGUKURAN DAN BOUWPLANK / M' 16,263.80 

    kaso 5/7 0.012  m3 400,000.00  4,800.00 paku 5 - 7 cm 0.020  kg 19,000.00  380.00 

    papan 2/20 0.007  m3 1,583,400.00  11,083.80 

    Mandor 0.005  org/hr 60,000.00  300.00  11,460.00 

    Pekerja 0.100  org/hr 50,000.00  5,000.00 

    Kepala Tukang 0.010  org/hr 66,000.00  660.00 

    Tukang Kayu 0.100  org/hr 55,000.00  5,500.00 

    PEKERJAAN GALIAN TANAH / M3 -  21,200.00 

    Kepala tukang 0.040  org/hr 50,000.00  2,000.00 

    Pekerja 0.400  org/hr 48,000.00  19,200.00 

    PEK PONDASI BATU KALI /M3, CAMP: 1PC:5PSR -  112,500.00 

    Mandor 0.075  org/hr 60,000.00  4,500.00 

    Pekerja 1.500  org/hr 50,000.00  75,000.00 

    Kepala Tukang 0.060  org/hr 50,000.00  3,000.00 

    Tukang batu 0.600  org/hr 50,000.00  30,000.00 

    Batu belah 15/20 1.100  m3 171,465.00  188,611.50  449,731.50 

    Semen portland 136.000  kg 1,320.00  179,520.00 pasir pasang 0.544  m3 150,000.00  81,600.00 

    Sloof beton bertulang 15/20/m3 - 

    a. upah 120,900.00 

    Mandor 0.010  org/hr 60,000.00  600.00 

    Pekerja 1.500  org/hr 50,000.00  75,000.00 

    Kepala Tukang 0.050  org/hr 66,000.00  3,300.00 

    Tukang batu 0.500  org/hr 54,000.00  27,000.00 

     Alat bantu 0.070  lot 15,000.00 

    b. Bahan beton/m3 695,400.00 

    Semen PC (50 kg) 6.800  zak 66,000.00  448,800.00 

    Split pecah 2/3 0.830  m3 180,000.00  149,400.00 

    Pasir beton 0.540  m3 180,000.00  97,200.00 

    c. 1 kg pembesian 33,115.65 

    Besi beton 1.050  kg 8,049.24  8,451.70 

    kawat beton 1.010  kg 20,895.00  21,103.95 

    alat bantu 0.020  lot 20,000.00  400.00 

    mandor 0.005  org/hr 60,000.00  300.00 

    kepala tukang 0.010  org/hr 66,000.00  660.00 

    tukang besi 1/2 trampil 0.025  org/hr 55,000.00  1,375.00 

    tukang besi trampil 0.015  org/hr 55,000.00  825.00 

    d. Pekerjaan bekisting / m2 78,618.00 

    Kaso 5/7 0.017  m3 400,000.00  6,800.00 

    papan 2/20 0.020  m3 1,583,400.00  31,668.00 

    paku 7 cm 0.400  kg 17,500.00  7,000.00 

    Pekerja 0.120  org/hr 50,000.00  6,000.00 

    Tukang kayu 0.150  org/hr 55,000.00  8,250.00 

    Kepala tukang kayu 0.150  org/hr 66,000.00  9,900.00 

    Mandor 0.050  org/hr 60,000.00  3,000.00 

    Tukang kayu 1/2 trampil 0.120  org/hr 50,000.00  6,000.00 

    e. Rekapitulasi 1m' pek.beton kolom dan balok 144,870.84 

    1. beton 0.023  m3 695,400.00  15,646.50 

    2. Besi 3.190  kg 33,115.65  105,638.94 3. bekisting 0.300  m2 78,618.00  23,585.40 

    4. upah cor per m' kolom 0.020  m3 120,900.00  2,418.00  2,418.00 

    Pekerjaan beton tumbuk 1pc:5psr, tebal 5 cm 35,520.00 

    Semen PC 16.000  kg 1,320.00  21,120.00 

    Pasir pasang 0.080  m3 180,000.00  14,400.00 

    koral beton -  m3 180,000.00  - 

    Pekerja 0.200  org/hr 50,000.00  10,000.00  15,100.00 

    tukang batu 0.150  org/hr 25,000.00  3,750.00 

    Kepala tukang 0.015  org/hr 66,000.00  990.00 

    5

    6

    3

    2

    1

    4

    halaman 1 dari 4

  • 8/18/2019 Review FHC 14 031

    3/7

     ANALISA HARGA PEKERJAAN

    Mandor 0.006  org/hr 60,000.00  360.00 

    Pekerjaan pasangan conblok HB 10, 1pc:5psr / m2 42,746.00 

    conblok 12.500  bh 1,400.00  17,500.00 

    Semen portland 14.050  kg 1,320.00  18,546.00 

    Pasir pasang 0.042  m3 150,000.00  6,300.00 

    kayu kelas III 0.001  m3 400,000.00  400.00 

    Pekerja 0.370  org/hr 50,000.00  18,500.00  29,170.40 

    Tukang batu 0.157  org/hr 54,000.00  8,478.00 Kepala tukang 0.016  org/hr 66,000.00  1,082.40 

    Mandor 0.019  org/hr 60,000.00  1,110.00 

    Pekerjaan kusen pintu dan jendela / m3 (kayu kelas II) 3,597,390.00 

    Kayu kelas II 1.100  m3 3,195,100.00  3,514,610.00 

    Paku 2.500  kg 19,000.00  47,500.00 

    lem kayu 1.000  kg 35,280.00  35,280.00 

    Pekerja trampil 4.000  org/hr 50,000.00  200,000.00  1,260,700.00 

    Tukang kayu trampil 15.500  org/hr 55,000.00  852,500.00 

    Kepala tukang 2.700  org/hr 66,000.00  178,200.00 

    Mandor 0.500  org/hr 60,000.00  30,000.00 

    Pekerjaan daun pintu kayu doble triplexs DP1/ unit 211,902.90 

    Rangka kayu 0.015  m3 3,195,100.00  47,926.50 

    triplexs 4 mm 2.000  lbr 80,000.00  160,000.00 

    lem kayu 0.005  kg 35,280.00  176.40 

    Paku triplex 0.200  kg 19,000.00  3,800.00 

    Pekerja trampil 0.300  org/hr 50,000.00  15,000.00  111,900.00 Tk.kayu 1/2 trampil 1.500  org/hr 55,000.00  82,500.00 

    Kepala tukang kayu 0.200  org/hr 66,000.00  13,200.00 

    Mandor 0.020  org/hr 60,000.00  1,200.00 

    Pekerjaan daun jendela kaca / m2 200,280.70 

    Rangka kayu 0.017  m3 3,195,100.00  54,316.70 

    lem kayu 0.300  kg 35,280.00  10,584.00 

    Lis kayu 4.000  m' 27,720.00  110,880.00 

    kaca 3 mm 0.350  m2 70,000.00  24,500.00 

    Pekerja 1/2 trampil 0.300  org/hr 50,000.00  15,000.00  90,120.00 

    Tukang kayu trampil 1.200  org/hr 55,000.00  66,000.00 

    Kepala tukang kayu 0.120  org/hr 66,000.00  7,920.00 

    Mandor 0.020  org/hr 60,000.00  1,200.00 

    Pekerjaan Kuda-kuda kayu 5/10/m3 3,616,110.00 

    Balok 5/10 1.100  m3 3,195,100.00  3,514,610.00 

    paku 8 - 12 cm 5.800  kg 17,500.00  101,500.00 

    Pekerja 1/2 trampil 3.000  org/hr 50,000.00  150,000.00  557,000.00 Tukang kayu 1/2 trampil 5.000  org/hr 55,000.00  275,000.00 

    Kepala tukang kayu 2.000  org/hr 66,000.00  132,000.00 

    Pekerjaan gording 5/10 kayu kelas III / m3 3,637,110.00 

    Kayu balok 5/10 1.100  m3 3,195,100.00  3,514,610.00 

    Paku 7.000  kg 17,500.00  122,500.00 

    Tukang kayu 1/2 trampil 5.000  org/hr 55,000.00  275,000.00  419,000.00 

    Kepala tukang kayu 2.000  org/hr 66,000.00  132,000.00 

    Mandor 0.200  org/hr 60,000.00  12,000.00 

    Pekerjaan Penutup atap asbes gelombang / m2 41,200.00 

     Asbes gelombang 0.460  lbr 85,000.00  39,100.00 

    Paku pancing 60 x 230 0.120  kg 17,500.00  2,100.00 

    Pekerja 0.140  org/hr 50,000.00  7,000.00  11,500.00 

    tukang batu 0.067  org/hr 54,000.00  3,618.00 

    Kepala tukang 0.007  org/hr 66,000.00  462.00 

    Mandor 0.007  org/hr 60,000.00  420.00 

    Pekerjaan bubungan asbes / m' 20,525.00 

    Bubungan asbes 1.000  lbr 20,000.00  20,000.00 

    Paku pancing 60 x 230 0.030  kg 17,500.00  525.00 

    Pekerja 0.100  org/hr 50,000.00  5,000.00  8,440.00 

    Tukang kayu 0.050  org/hr 55,000.00  2,750.00 

    Kepala tukang 0.005  org/hr 66,000.00  330.00 

    Mandor 0.006  org/hr 60,000.00  360.00 

    Pekerjaan rangka plafond /m2 60,094.25 

    Kaso 5/7 0.014  m3 3,195,100.00  44,731.40 

    Kayu 5/10 0.004  m3 3,195,100.00  11,182.85 

    paku 0.220  kg 19,000.00  4,180.00 

    11

    12

    13

    14

    15

    7

    8

    9

    10

    halaman 2 dari 4

  • 8/18/2019 Review FHC 14 031

    4/7

     ANALISA HARGA PEKERJAAN

    Pekerja 1/2 trampil 0.188  org/hr 50,000.00  9,375.00  17,980.00 

    tukang kayu terampil 0.100  org/hr 55,000.00  5,500.00 

    Kepala tukang kayu 0.038  org/hr 66,000.00  2,475.00 

    Mandor 0.011  org/hr 60,000.00  630.00 

    Pekerjaan list plank 3/20 per m' 12,983.80 

    Papan 3/20 0.007  m3 1,583,400.00  11,083.80 

    Paku 0.100  kg 19,000.00  1,900.00 

    Pekerja terampil 0.070  org/hr 50,000.00  3,500.00  16,060.00 Tukang kayu 1/2 terampil 0.200  org/hr 55,000.00  11,000.00 

    Kepala Tukang kayu 0.020  org/hr 66,000.00  1,320.00 

    Mandor 0.004  org/hr 60,000.00  240.00 

    Pekerjaan penutup Plafon eternit 4 mm, per m2 54,318.50 

    Eternit 4mm 1.100  m2 49,035.00  53,938.50 

    paku 0.020  kg 19,000.00  380.00 

    pekerja 1/2 terampil 0.047  org/hr 55,000.00  2,601.50  10,853.30 

    Tukang kayu terampil 0.113  org/hr 66,000.00  7,425.00 

    Kepala tukang kayu 0.010  org/hr 66,000.00  646.80 

    Mandor 0.003  org/hr 60,000.00  180.00 

    Pekerjaan pasang bak mandi teraso / 1 bh 254,910.00 

    Bak teraso 1.000  bh 245,490.00  245,490.00 

    Semen PC 6.000  kg 1,320.00  7,920.00 

    Pasir pasang 0.010  m3 150,000.00  1,500.00 

    Pekerja 2.100  org/hr 28,000.00  58,800.00  92,520.00 

    Tukang batu 0.750  org/hr 30,000.00  22,500.00 Kepala tukang 0.070  org/hr 66,000.00  4,620.00 

    Mandor 0.110  org/hr 60,000.00  6,600.00 

    Pekerjaan pasang kloset jongkok teraso / 1 bh 240,920.00 

    Kloset jongkok terso 1.000  bh 230,000.00  230,000.00 

    Bata merah 6.000  bh 250.00  1,500.00 

    Semen PC 6.000  kg 1,320.00  7,920.00 

    Pasir pasang 0.010  m3 150,000.00  1,500.00 

    Pekerja 1.000  org/hr 28,000.00  28,000.00  99,400.00 

    Tukang batu 1.500  org/hr 30,000.00  45,000.00 

    Kepala tukang 0.300  org/hr 66,000.00  19,800.00 

    Mandor 0.110  org/hr 60,000.00  6,600.00 

    Floor drain 40,000.00 

    Floor drain 1.000  bh 40,000.00  40,000.00 

    Tukang batu 0.100  org/hr 30,000.00  3,000.00  3,660.00 

    Kepala tukang 0.010  org/hr 66,000.00  660.00 

    pekerjaan Sumur pantek / 1 unit 270,500.00 

    Kompa tangan 1.000  unit 220,500.00  220,500.00 

    Pipa 1" 2.000  l t 25,000.00  50,000.00 

    Ongkos bor kedalaman 15 m' 1.000  ls 350,000.00  350,000.00  350,000.00 

    Pekerjaan 1 unit tangki septik 2,533,791.25 

    Galian tanah 4.500  m3 21,200.00  95,400.00 

    Pasir urug 0.214  m3 150,000.00  32,130.00 

    Lantai kerja 2.250  m2 35,520.00  79,920.00 

    Buis beton diameter 1mx 1,5m 4.000  bh 428,295.00  1,713,180.00 

    Plat penutup beton bertulang 0.300  m3 144,870.84  43,461.25 

    Pipa PVC 4" + sambungan 5.400  m' 16,750.00  90,450.00 

    Pipa GIP 1.5" 1.200  btg 3,000.00  3,600.00 

    Galian tanah utk rembesan 3.375  m3 21,200.00  71,550.00 

    Pasangan injuk 5.400  kg 7,500.00  40,500.00 

    Urugan kerikil 2/3 1.050  m3 180,000.00  189,000.00 

    Pipa PVC 4" berlubang 9.000  m' 16,750.00  150,750.00 

    Urugan kembali perataan tanah 1.125  m3 21,200.00  23,850.00 

    Upah pengerjaan 1.000  ls 365,000.00  365,000.00  365,000.00 

    Pek. Pipa Air Bersih PVC 3/4" / m' 4,455.00 

    Pipa PVC 3/4" 1.200  m' 2,750.00  3,300.00 

    Perlengkapan 35% harga pipa 1.000  ls 1,155.00  1,155.00 

    Pembantu tukang 0.081  org/hr 55,000.00  4,455.00  20,901.00 

    Tukang batu 0.135  org/hr 54,000.00  7,290.00 

    Kepala tukang 0.135  org/hr 66,000.00  8,910.00 

    Mandor 0.004  org/hr 60,000.00  246.00 

    Pek. Pipa Air Bersih PVC 4" / m' 27,135.00 

    Pipa PVC 4" 1.200  m' 16,750.00  20,100.00 

    23

    24

    17

    18

    19

    20

    21

    22

    16

    halaman 3 dari 4

  • 8/18/2019 Review FHC 14 031

    5/7

     ANALISA HARGA PEKERJAAN

    Perlengkapan 35% harga pipa 1.000  ls 7,035.00  7,035.00 

    Pembantu tukang 0.081  org/hr 55,000.00  4,455.00  20,901.00 

    Tukang batu 0.135  org/hr 54,000.00  7,290.00 

    Kepala tukang 0.135  org/hr 66,000.00  8,910.00 

    Mandor 0.004  org/hr 60,000.00  246.00 

    PEKERJAAN pasir urug / M3 150,000.00 

    pasir urug 1.500  m3 100,000.00  150,000.00 

    Kepala tukang 0.040  org/hr 55,000.00  2,200.00  21,400.00 Pekerja 0.400  org/hr 48,000.00  19,200.00 

    Urugan kembali tanah/m3 21,400.00 

    Kepala tukang 0.040  org/hr 55,000.00  2,200.00 

    Pekerja 0.400  org/hr 48,000.00  19,200.00 

    Pekerjaan siar 1 pc ; 2 psr / m2 8,076.00 

    Semen PC 4.300  kg 1,320.00  5,676.00 

    pasir pasang 0.016  m3 150,000.00  2,400.00 

    Pembantu tukang 0.150  org/hr 50,000.00  7,500.00  12,222.00 

    Tukang batu 0.070  org/hr 54,000.00  3,780.00 

    Kepala tukang 0.007  org/hr 66,000.00  462.00 

    Mandor 0.008  org/hr 60,000.00  480.00 

    Pekerjaa pasang dinding papan / m2 65,802.00 

    papan 2/20 0.020  m3 3,195,100.00  63,902.00 

    paku 7 cm 0.100  kg 19,000.00  1,900.00 

    Pekerja 0.060  org/hr 50,000.00  3,000.00  14,268.00 Tukang kayu 0.180  org/hr 55,000.00  9,900.00 

    Kepala tukang 0.018  org/hr 66,000.00  1,188.00 

    Mandor 0.003  org/hr 60,000.00  180.00 

    Pekerjaan pasang rangka dinding papan / m2 62,606.90 

    balok 0.019  m3 3,195,100.00  60,706.90 

    paku 7 cm 0.100  kg 19,000.00  1,900.00 

    Pekerja 0.060  org/hr 50,000.00  3,000.00  14,268.00 

    Tukang kayu 0.180  org/hr 55,000.00  9,900.00 

    Kepala tukang 0.018  org/hr 66,000.00  1,188.00 

    Mandor 0.003  org/hr 60,000.00  180.00 

    1 titik Pekerjaan tiang pondasi dari kayu ulin 147,803.25 

    Kayu ulin 10/10, 2.5 m 0.025  m3 4,431,000.00  110,775.00 

    Sunduk 3/5, 50 cm 0.001  m3 4,431,000.00  3,323.25 

    dolken diameter 10 cm 1.500  btg 22,470.00  33,705.00 

    upah pekerja ( 40% bahan ) 1.000  ls 56,830.00  56,830.00  56,830.00 

    Pekerjaan pasang lantai papan / m2 102,544.60 

    papan 2/20 (kayu kamper) 0.020  m3 5,032,230.00  100,644.60 

    paku 7 cm 0.100  kg 19,000.00  1,900.00 

    Pekerja 0.120  org/hr 50,000.00  6,000.00  28,800.00 

    Tukang kayu 0.360  org/hr 55,000.00  19,800.00 

    Kepala tukang 0.040  org/hr 66,000.00  2,640.00 

    Mandor 0.006  org/hr 60,000.00  360.00 

    Pekerjaan balok induk dan balok lantai kayu 6/12 kelas II / m3 5,657,953.00 

    Kayu balok 6/12 dan 5/10 1.100  m3 5,032,230.00  5,535,453.00 

    Paku 7.000  kg 17,500.00  122,500.00 

    Tukang kayu 1/2 trampil 2.500  org/hr 55,000.00  137,500.00  209,500.00 

    Kepala tukang kayu 1.000  org/hr 66,000.00  66,000.00 

    Mandor 0.100  org/hr 60,000.00  6,000.00 

    28

    29

    30

    31

    25

    25

    26

    27

    halaman 4 dari 4

  • 8/18/2019 Review FHC 14 031

    6/7

    DAFTAR HARGA UPAH

    No Tukang Satuan Harga

    1 Mandor hr 60,000.00 

    2 Tukang Gali hr 48,000.00 

    3 Kepala tukang besi hr 66,000.00 

    4 Kepala tukang kayu hr 66,000.00 

    5 Tukang batu hr 54,000.00 6 Tukang kayu hr 55,000.00 

    7 Tukang besi hr 55,000.00 

    8 Tukang listrik hr 55,000.00 

    9 Tukang ledeng hr 55,000.00 

    10 Pekerja hr 50,000.00 

  • 8/18/2019 Review FHC 14 031

    7/7

    DAFTAR HARGA BAHAN BANGUNAN

    No B ah an Sat Harg a  

    1 Batu pondasi m3 171,465 

    2 Batu pecah/kerikil m3 180,000 

    3 Pasir beton m3 180,000 

    4 Pasir pasang m3 150,000 

    5 Pasir urug m3 100,000 6 Conblok bh 1,400 

    7 Semen (50 kg) zak 66,000 

    8 Asbes gelombang lbr 85,000 

    9 bubungan asbes lbr 20,000 

    10 Kayu kelas III m3 3,195,100 

    11 buis beton, tinggi 0.5 m' bh 428,295 

    12 Besi beton diameter 6 mm kg 9,470 

    Besi beton diameter 10 mm kg 9,290 

    13 Besi beton diameter 12 mm kg 8,049 

    14 Kawat beton kg 20,895 

    15 Eternit lbr 49,035 

    16 Triplex 4 mm lbr 80,000 

    17 PVC 1" btg 25,000 

    18 PVC 2" btg 90,000 

    19 PVC 3" btg 100,000 

    20 PVC 4 " btg 120,000 

    21 Kaca 3 mm m2 70,000 22 Kunci tanam union 2 stag bh 200,000 

    23 Kunci tanam union 1 stag bh 100,000 

    24 Gerendel bh 770 

    25 Engsel kupu-kupu bh 20,000 

    26 Engsel nylon bh 7,245 

    27 Hak angin bh 11,070 

    28 Kloset jongkok bh 230,000 

    29 Bak mandi fibre bh 245,490 

    30 Pompa tangan bh 220,500 

    31 papan 2/20 m3 1,583,400 

    32 Paku beton/ kotak kg 36,855 

    33 Paku list kg 19,000 

    34 Paku reng kg 13,320 

    35 paku seng kg 17,500 

    36 lem kayu kg 35,280 

    37 Kayu list m' 27,720 

    38 Floor Drain bh 40,000 

    39 Kayu kelas I ( merbau ) m3 4,431,000 

    40 dolken - 4 m btg 22,470 

    41 Kayu kelas III papan m3 5,032,230 

    42 Kayu kelas III balok m3 5,032,230 

    43 Kayu Bekisting m3 400,000