review group 221: option 3 – security provided after allocation
TRANSCRIPT
Review Group 221: Option 3 – security provided after allocation
2
Security Provision Timing Options Discussed by RG221
Sept
Option 1 -Security Provided
pre auction
Aug
QSECAuction
held
Allocation processstarts - after last
bid window
Option 3 - Securityprovided after
allocation
Max 18 days
Allocation processfinalised
Max 60 days
Oct Nov Dec
30 days?
Jan
Min 30 days
Option 2. Securityprovided prior to
allocationAdditional 15days requiredfor allocation
proccess
Variations
Option 4 - (hybrid of option 1 + 2) - minimum level of security or bid bond provided pre auction and security topped up prior to allocation
Option 5 - (hybrid of 1 + 3) minimum level of security or bid bond provided pre auction and security topped up after allocation has been finalised
3
Option 3 – security provided after provisional allocation
Option 3 Security is provided within one month of the provisional allocation taking place.
User provides their security within [30] days of the provisional allocation
Pros Cons
This option has the benefit of the User knowing
exactly what security is required.
User may fail to provide the security and the
auction may need to be re-run..
Allows for sufficient time for the security to be put
in place.
Re-running an auction would affect other QSEC
auction participants, incur costs, impact on
investment lead times and may impact on the
timing of other capacity auctions/processes.
The existence of the “defaulting User” may effect
the bids or allocations of other Users in the
auction.
•RG Meeting 26 Feb •Option 3 identified as preferred option but in the event of a User failing to provide security NG would not look to re-run auction allocations or assess impact on other auction participants
4
Amendments to QSEC auction process to accommodate option 3
SeptAug
QSECAuction
held
Allocationprocess
starts - afterlast bidwindow
User informed ofprovisional
allocation andgiven 28 days toprovide security
Max 18days
Allocationprocessfinalised90 days (previously 60 days)
Oct Nov Dec Jan
28 days
Network DesignEvaluation
28 days to veto
Application toOfgem
28 days
Securityprovided?
Allocation removed and where anapplication had been sent to
Ofgem, NG will write to informOfgem that the allocation has
been removed and that therevenue driver will not apply
Yes
No
42 Month Investment lead time starts 1/10
5
Does this process work?
Scenario 1 – One User bidding for baseline capacity at an existing ASEP
User fails to provide Security
Provisional allocation removed
Unsold baseline capacity considered as part of substitution and/or offered for sale again at next relevant auction
Process Works? – Yes
6
Does this process work?
Scenario 2 – One User bidding for Incremental capacity at a new ASEP
User fails to provide Security
Provisional allocation removed
NG will write to Ofgem to inform them that the allocation has been removed and that the revenue driver will not apply
Process works? – Yes*
* Process has potential impacts on investment lead time if User does put credit in place
7
Does this process work?
Scenario 3 – Multiple Users bidding for Incremental capacity at a new ASEP – for example Milford Haven
Provisional allocations: User A = 100 units, User B = 180 units & User C = 30 units
User A fails to provide Security
Provisional allocation for User A removed
Remaining bids for Users B and C no longer pass Economic Test (300 units required)
Provisional allocation for User B and User C also removed
NG will write to Ofgem to inform them that the allocations have been removed and that the revenue driver will not apply
Users B and C would need to discuss with NG, the prospect of holding an adhoc auction at a later date - investment process delayed pending new auction
Process works? – Yes?
8
Does this process work?
Scenario 4 – Multiple Users bidding for Incremental capacity and baseline at an existing ASEP
Provisional allocations: User A = 100 units, User B = 180 units & User C = 30 units
User A bids for both baseline and incremental but fails to provide Security
Provisional allocation (baseline and incremental) for User A removed
Remaining bids for Users B and C no longer pass Economic Test (300 units required)
Provisional allocation for capacity for User B and User C removed
NG will write to Ofgem to inform them that the allocations have been removed and that the revenue driver will not apply
Baseline is available for substitution
Users B and C would need to discuss prospect of holding an adhoc auction with NG
Process works? –No
9
Scenario 4 – Multiple Users bidding for Incremental capacity and baseline at an existing ASEP
Easington – 2006 QSEC Auction
19 Users buying baseline capacity & 12 Users buying incremental capacity and baseline capacity
Baseline capacity value - £153m & Incremental capacity value - £14m~
Easington
0
5000000
10000000
15000000
20000000
25000000
30000000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Baseline Incremental