revised prc 421 recommissioning project on state oil and gas lease no. prc 421 1 california state...

31
Revised PRC 421 Recommissioning Project on State Oil and Gas Lease No. PRC 421 1 California State Lands Commission December 17, 2014

Upload: garey-snow

Post on 13-Dec-2015

219 views

Category:

Documents


2 download

TRANSCRIPT

Revised PRC 421 Recommissioning Project on State Oil and Gas Lease No. PRC 421

1

California State Lands Commission

December 17, 2014

Final Environmental Impact Report (EIR) for Revised PRC 421 Recommissioning Project released – Jan 2014

California State Lands Commission (CLSC) meeting requested additional analysis – April 23, 2014

Recirculated Final EIR builds on previous EIR, providing additional analysis as directed by CSLC

Introduction

Vaqueros Reservoir Repressurization

Section 5.0, Project Alternatives Analysis No Project Alternative (redefined) No Production/ Quitclaim State Oil

and Gas Lease PRC 421 Alternative Processing PRC 421 Oil at LFC

Alternative

Information Added During Recirculation

Increasing pressure in the Vaqueros Formation documented in 1987 to 2000; no data available after 2000

Engineering analysis- repressurization is most likely from aquifer influx (natural groundwater movement)

Approximately 21 offshore wells in this formation were not properly abandoned (1930-1950’s) and could leak under pressure

PRC 421-1 and 421-2 only remaining wells for pressure measurements; measurements cannot be taken while shut-in

Repressurization of the Vaqueros Formation

Historical Overview (1929 to 1994)

1929First Oil & Gas

Lease at PRC 421 (by State Surveyor

General)

Oct 1949Lease extended

and renewed by CA State Lands Commission

May 1994Production

curtailed due to onshore spill from

a 6-inch line

PRC 421 was produced continuously from 1929 to 1994

PRC 421 key Infrastructure

EOF

PRC 421 generally shut in (no production) since 1994

2000-2001 Production – In order to repair methane leak, oil produced to reduce pressure in Vaqueros Reservoir

2001 Repairs – Caissons, casings, wellheads; production equipment removed; subsurface safety valves installed

2004 Repairs – New seaward facing caisson at Pier 421-1

2011 Repairs – Pier 421-2 seaward facing caisson repaired; older pilings removed from Piers 421-1 and 421-2

Historical Overview (1995 to present)

PRC 421 Current Conditions

Table 1. Active Oil and Gas Operations in California State Waters

Pier 421-1

Pier 421-2

Existing Piers and Caissons

Pier

421

-1Pi

er

421

-2

Throughout EIR Coordination with city of Goleta and CCC through a Joint Review Panel.

preparation 10+ public notices, news releases, or news articles published in the

Santa Barbara Independent, Santa Barbara News-Press, and Noozhawk.

2004 Application submitted.

2005 Notice of Preparation (NOP) (May 2004 application).Public scoping meetings (Goleta).

2006 -- 2007 Joint Review Panel Formed.Two Administrative Drafts Reviewed by JRP.Public Draft EIR / 60-day comment period.Draft EIR public meetings (Goleta).

2008 Two Administrative Draft Final EIRs Reviewed by JRP.

2008 - 2013 EIR suspended due to various Project delays.11

Chronology of Events

2013 CSLC staff and Venoco agree to restart the EIR process.Venoco submits application for revised project.NOP published (May 2004 application with 2013 amendment). Public scoping meetings (Goleta).Administrative Draft Reviewed by JRP. Public Revised Draft EIR / 60-day comment period. Public meetings (Goleta).

2014 Final EIR published.Meeting w/ Venoco, the City, and CSLC on MMP.Final EIR and CSLC Hearing (Directed to recirculate to address LFC).Administrative Draft Recirculated DEIR reviewed by JRP.Public Recirculated Draft EIR (Public meetings in Goleta).CSLC staff presents at City of Goleta City Council – Discussion of

Recirculated EIR Final EIR released.Commission Hearing. 12

Chronology of Events (Cont’d)

Recommission Pier 421-2 & Well 421-2

Repairs, new equipment and improvements at Pier/ Well 421-2, along access road and delivery pipeline

Limited improvements to Ellwood Onshore Facility (e.g., power equipment and monitoring and control system)

Pressurization monitoring

No new drilling, use of hydraulic fracturing, matrix acidization, or acid- fracking stimulation treatments – production resumption from well 421-2.

Summary of Proposed Project

Decommission and remove Pier 421-1 & Well 421-1

Following start up of PRC 421-2 (application within 90 days)

Remove pier, caisson, piping, and ancillary supporting facilities

Processing of produced oil/gas/water emulsion at the Ellwood Onshore Facility (EOF)

Commingled with production from Platform Holly

Processed using existing equipment

Within existing production limits for Platform Holly and permitted throughput of EOF

Would not extend the life of the EOF

Summary of Proposed Project (cont)

15

Aeri

al V

iew

of

the

Pro

ject

Impacts Associated with the Proposed Project

Resource Area

Potentially

Significant

Significant &

Unavoidable

Geological Resources 4 0

Safety 4 3

Hazardous Materials 2 0

Air Quality and Greenhouse Gasses 1 0

Hydrology, Water Resources and Water Quality 2 2

Marine Biological Resources 2 3

Terrestrial Biological Resources 1 2

Land Use, Planning, and Recreation 0 4

Public Services 1 1

Transportation and Circulation 1 0

Noise 0 0

Aesthetic and Visual Resources 1 1

Cultural, Historical, and Paleontological Resources 1 0

Energy Mineral Resources 0 0

TOTAL 20 16

Impact summary 20 Potentially Significant Impacts 16 Significant and Unavoidable Impacts

13 related to potential for an oil spill to occur (even though volumes/ potential for occurrences are low)

3 related to small addition of processing at the EOF and safety response

Primary concerns Use of the EOF for processing

Continued/expanded use of a legal non-conforming facility Compatibility with surrounding uses; potential safety

concerns

Summary of Potential Impacts

• Venoco’s rights to resume production at PRC 421

• Life of the Ellwood Onshore Facility (EOF) it’s status as a legal non-conforming use

• Project Duration

• Reservoir repressurization

• Processing PRC 421 oil at ExxonMobil’s Las Flores Canyon facility

18

Comments Raised Regarding the Final EIR

Project Alternativesand Potential Impacts

Commission agreement that Venoco has adequately repaired PRC 421 infrastructure

Venoco authorized to resume production as the current lease operator

Production and processing on Pier 421-2, wastewater and gas reinjection at Well 421-1

Includes new processing equipment on Pier 421-2

No ProjectAlternative

Impact summary 20 Potentially

Significant 15 Significant and

Unavoidable Primary concerns

Processing in shorezone

Continued use of 421-1 Greater impacts than

the proposed Project

Potential Impacts

State terminates PRC 421 – denies Venoco’s contractual right to produce

State likely required to pay Venoco for interest taken

Potentially no production or processing at PRC 421

No pressure testing of the Vaqueros Reservoir

No Production/ Quitclaim Lease 421 Alternative

Impact summary 0 Potentially

Significant 14 Significant and

Unavoidable Primary concerns

Cost to the State Vaqueros Reservoir

repressurization Greater impacts than

the proposed Project

Potential Impacts

Similar to No Project – oil processing on Pier 421-2

Wastewater and gas reinjection at Platform Holly

Use of existing utility pipeline to Platform Holly

Operational changes at Platform Holly (H2S scrubbers)

Decommissioning of PRC 421-1

Impact summary 20 Potentially

Significant 15 Significant and

Unavoidable Primary concerns

Processing in shore zone

Greater impacts than the proposed Project

Potential Impacts

Reinjection atPlatform Holly

PRC 421-2 production transported to LFC for processing

No processing at the EOF Decommissioning of PRC 421-1 Construction of 10.2 miles of

pipelines Additional equipment on Pier 421-2

Larger ESP, isokinetic sampler, check meter, 4 chemical tanks

New Venoco Receiving Station at LFC Oil dehydration plant, oil &water

storage tanks, injection well

Processing PRC 421 Oil at Las Flores Canyon (LFC) Alternative

NOTE Assumes pipeline

transport of oil/gas/water emulsion

If not possible, additional equipment at PRC 421-2 1,000 to 1,500-barrel

breakout tank, flare, and oil shipping pump

24

Bore Hole Segments along the New Pipeline

New Pipeline Route

25

New

Ven

oco R

eceiv

ing

S

tati

on

an

d P

ipelin

e

Rou

te a

t LFC

Impacts Associated with the LFC Alternative

Resource Area

Potentially

Significant

Significant &

Unavoidable

Geological Resources 11 0

Safety 5 3

Hazardous Materials 4 0

Air Quality and Greenhouse Gasses 4 0

Hydrology, Water Resources and Water Quality 5 5

Marine Biological Resources 4 6

Terrestrial Biological Resources 2 6

Land Use, Planning, and Recreation 2 7

Public Services 1 3

Transportation and Circulation 3 0

Noise 2 0

Aesthetic and Visual Resources 2 1

Cultural, Historical, and Paleontological Resources 6 0

Energy Mineral Resources 1 0

TOTAL 52 31

Impact summary 52 Potentially Significant 31 Significant and Unavoidable

Primary concerns Impacts from construction and operation of 10.2

miles of new pipelines and new 1.5 acre oil processing facility

New equipment at Pier 421-2, including 4 chemical tanks (55 to 350 gallons)

Reduced accuracy in the leak detection system (from 3-phase operation)

Greater impacts than the proposed Project

Summary of Potential Impacts

Proposed Project selected as the environmentally superior alternative

Benefits No processing in the surf zone Decommissioning of PRC 421-1 Minimal new equipment on Pier

421-2 Pressurization monitoring

Use of the EOF for processing Primarily uses existing

infrastructure No extension of the life of the EOF

Environmentally Superior Alternative

1) Certify the Environmental Impact Report, CSLC EIR No. 732, State Clearinghouse No. 2005061013.

2) Adopt the Mitigation Monitoring Program (Exhibit C).

3) Adopt the CEQA Findings & Statement of Overriding Considerations (Exhibit D).

4) Find that this activity is consistent with the use classification designated by the Commission for the land pursuant to Public Resources Code section 6370 et seq.

5) Find that adequate corrective measures have been taken to repair the infrastructure associated with PRC 421, as required under California Code of Regulations, Title 2, section 2121, and that, pursuant to the Lease, Venoco is obligated to resume production of oil and gas from PRC 421.

29

Recommended Commission Actions

6) Find that Venoco’s proposed Project, utilizing the EOF for processing oil from PRC 421, subject to the implementation of the MMP identified in Exhibit C1, is consistent with Lease PRC 421 and the Final EIR, pursuant to the following conditions:

i. Well 421-2 will not be stimulated, within the meaning of Public Resources Code section 3157, using hydraulic fracturing, matrix acidization or acid fracturing techniques, unless subsequently approved by the State Lands Commission.

ii. Venoco must comply with all other applicable laws and obtain all required DOGGR permits.

iii. Venoco shall be responsible for all costs associated with the execution of the adopted MMP, including staff/consultant monitoring.

30

Recommended Commission Actions (Cont’d)

7) Exercise the State’s option to require Venoco to remove, at Venoco’s sole expense, Well 421-1 and its associated facilities, including Pier 421-1, pursuant to the following conditions:

i. Venoco shall submit to the Executive Officer the information necessary to evaluate whether the decommissioning and abandonment plan of Well 421-1 and its associated facilities is consistent with the Commission’s regulations, Lease PRC 421, and the Final EIR within 90 days of receipt of all required permits.

ii. If the Executive Officer determines that the decommissioning and abandonment plan is consistent with the Commission’s regulations, Lease PRC 421, and the Final EIR, then the Executive Officer is authorized to allow the removal and decommissioning of Well 421-1 and its associated facilities to proceed.

31

Recommended Commission Actions (Cont’d)

Thank You