ID Task Name Duration Start Finish
0 MULTI STOREYED BUILDING, COLOMBO 747.2 days 22-10-2013 25-01-2017
1 PROJECT SUMMARY 747.2 days 22-10-2013 25-01-2017
2 Start of the Project 1 day 22-10-2013 22-10-2013
3 Final Handing Over 0 days 25-01-2017 25-01-2017
4 MOBILIZATION 203.2 days 28-10-2013 16-09-2014
5 Mobilization - Site Office 80 days 28-10-2013 15-01-2014
6 Mobilization - Staff & Workmen 96 days 28-10-2013 31-01-2014
7 Mobilization-Plant & Equipment 109 days 28-10-2013 13-02-2014
8 Erection of Tower Crane 45 days 09-07-2014 16-09-2014
9 PROCUREMENT (Major S/c only Shown) 611 days 10-02-2014 24-10-2016
10 DOMESTIC S/C 518 days 10-02-2014 04-06-2016
11 SHORING 12.8 days 10-02-2014 28-02-2014
12 Award of Workpackage 1 day 10-02-2014 10-02-2014
13 Design Submission & Approval 14 days 15-02-2014 28-02-2014
14 Mobilise at site 1 day 28-02-2014 28-02-2014
15 DEWATERING 11.2 days 12-02-2014 28-02-2014
16 Award of Workpackage 1 day 12-02-2014 12-02-2014
17 Design Submission & Approval 16 days 13-02-2014 28-02-2014
18 Mobilise at site 12 days 13-02-2014 24-02-2014
19 THERMAL & MOISTURE PROTECTION 50 days 19-05-2014 02-08-2014
20 Award of Workpackage 0 days 19-05-2014 19-05-2014
21 Shop Drawing Submission 5 days 27-06-2014 04-07-2014
22 Shop Drawing Approval 11 days 05-07-2014 23-07-2014
23 Material Sample Submission 10 days 27-06-2014 11-07-2014
24 Material Sample Approval 4 days 16-07-2014 21-07-2014
25 Procurement lead time 8 days 22-07-2014 02-08-2014
26 Delivery of Materials 0 days 02-08-2014 02-08-2014
27 FINISHES 339 days 17-09-2014 12-03-2016
28 WALL FINISHES 123 days 20-02-2015 14-09-2015
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 1 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
29 Award of Workpackage 0 days 20-02-2015 20-02-2015
30 Shop Drawing Submission 28 days 14-03-2015 13-05-2015
31 Shop Drawing Approval 28 days 14-05-2015 24-06-2015
32 Material Sample Submission 28 days 14-03-2015 13-05-2015
33 Material Sample Approval 28 days 14-05-2015 24-06-2015
34 Procurement lead time 52 days 25-06-2015 11-09-2015
35 Delivery of Materials 0 days 14-09-2015 14-09-2015
36 CEILING FINISHES 85 days 24-10-2015 07-03-2016
37 Award of Workpackage 0 days 24-10-2015 24-10-2015
38 Shop Drawing Submission 11 days 16-11-2015 03-12-2015
39 Shop Drawing Approval 11 days 17-02-2016 04-03-2016
40 Material Sample Submission 11 days 16-11-2015 03-12-2015
41 Material Sample Approval 11 days 03-12-2015 18-12-2015
42 Procurement lead time 48 days 19-12-2015 04-03-2016
43 Delivery of Materials 0 days 07-03-2016 07-03-2016
44 FLOOR FINISHES 89 days 24-10-2015 12-03-2016
45 Award of Workpackage 0 days 24-10-2015 24-10-2015
46 Shop Drawing Submission 11 days 16-11-2015 03-12-2015
47 Shop Drawing Approval 11 days 03-12-2015 18-12-2015
48 Material Sample Submission 11 days 16-11-2015 03-12-2015
49 Material Sample Approval 11 days 03-12-2015 18-12-2015
50 Procurement lead time 52 days 19-12-2015 10-03-2016
51 Delivery of Materials 0 days 12-03-2016 12-03-2016
52 IRONMONGERIES 84 days 17-09-2014 26-01-2015
53 Award of Workpackage 0 days 17-09-2014 17-09-2014
54 Shop Drawing Submission 11 days 09-10-2014 25-10-2014
55 Shop Drawing Approval 11 days 25-10-2014 12-11-2014
56 Material Sample Submission 11 days 09-10-2014 25-10-2014
57 Material Sample Approval 11 days 25-10-2014 12-11-2014
58 Procurement lead time 48 days 12-11-2014 26-01-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 2 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
59 Delivery of Materials 0 days 26-01-2015 26-01-2015
60 EQUIPMENT 108 days 25-05-2015 06-11-2015
61 GARBAGE CHUTE 108 days 25-05-2015 06-11-2015
62 Award of Workpackage 0 days 25-05-2015 25-05-2015
63 Shop Drawing Submission 11 days 16-06-2015 03-07-2015
64 Shop Drawing Approval 22 days 03-07-2015 05-08-2015
65 Material Sample Submission 11 days 16-06-2015 03-07-2015
66 Material Sample Approval 22 days 03-07-2015 05-08-2015
67 Procurement lead time 60 days 05-08-2015 05-11-2015
68 Delivery of Materials 0 days 06-11-2015 06-11-2015
69 INTERNAL & EXTERNAL SIGNAGES 234 days 25-05-2015 04-06-2016
70 Award of Workpackage 0 days 25-05-2015 25-05-2015
71 Shop Drawing Submission 28 days 16-06-2015 28-07-2015
72 Shop Drawing Approval 28 days 28-07-2015 09-09-2015
73 Material Sample Submission 28 days 16-06-2015 28-07-2015
74 Material Sample Approval 28 days 28-07-2015 09-09-2015
75 Procurement lead time 104 days 09-09-2015 18-02-2016
76 Delivery of Materials 0 days 04-06-2016 04-06-2016
77 SANITARY WARES 193 days 02-07-2014 15-05-2015
78 Award of Workpackage 0 days 02-07-2014 02-07-2014
79 Material Sample Submission 28 days 28-07-2014 06-09-2014
80 Material Sample Approval 15 days 02-09-2014 24-09-2014
81 Procurement lead time 18 days 30-03-2015 15-05-2015
82 Delivery of Materials 0 days 15-05-2015 15-05-2015
83 Shop Drawing Submission 28 days 10-10-2014 22-11-2014
84 Shop Drawing Approval 28 days 29-11-2014 13-01-2015
85 NOMINATED SUBCONTRACTORS 598.2 days 01-03-2014 24-10-2016
86 MEP WORKS 63.2 days 01-03-2014 20-06-2014
87 MEP WORKS S/C 53.6 days 01-03-2014 05-06-2014
88 Award of Workpackage 1 day 01-03-2014 01-03-2014 100%
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 3 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
89 Raft - Shop Drawing Submission 7 days 07-05-2014 17-05-2014
90 Raft - Shop Drawing Approval 7 days 27-05-2014 05-06-2014
91 S/c Mobilise at site 0 days 05-06-2014 05-06-2014
92 CCTV, SMATV 27 days 03-05-2014 13-06-2014
93 Nominate CCTV, MATV S/c 1 day 03-05-2014 05-05-2014
94 Agreement with Nominated S/c 11 days 05-05-2014 21-05-2014
95 S/C mobilise at site 11 days 28-05-2014 13-06-2014
96 Air Conditioning & Mechanical Ventilation System 27 days 10-05-2014 20-06-2014
97 Nominate Air Conditioning & Mechanical Ventilation System Contrcator
1 day 10-05-2014 12-05-2014
98 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014
99 S/C mobilise at site 11 days 04-06-2014 20-06-2014
100 Fire Protection and detection system 27 days 10-05-2014 20-06-2014
101 Nominate Fire Protection and detection contractor 1 day 10-05-2014 12-05-2014
102 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014
103 S/C mobilise at site 11 days 04-06-2014 20-06-2014
104 Installation of Generators 27 days 10-05-2014 20-06-2014
105 Nominate Generators Contractor 1 day 10-05-2014 12-05-2014
106 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014
107 S/C mobilise at site 11 days 04-06-2014 20-06-2014
108 PA, PABX SYSTEM 27 days 10-05-2014 20-06-2014
109 Nominate PA, PABX S/c 1 day 10-05-2014 12-05-2014
110 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014
111 S/C mobilise at site 11 days 04-06-2014 20-06-2014
112 ACCESS CONTROL SYSTEM 25 days 10-05-2014 18-06-2014
113 Nominate Access Control System 1 day 10-05-2014 12-05-2014
114 Agreement with Nominated S/c 9 days 12-05-2014 26-05-2014
115 S/C mobilise at site 9 days 04-06-2014 18-06-2014
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 4 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
116 LIFTS 243 days 10-05-2014 06-06-2015
117 Award of Workpackage 0 days 10-05-2014 10-05-2014
118 Shop Drawing Submission 28 days 05-06-2014 18-07-2014
119 Shop Drawing Approval 28 days 25-07-2014 05-09-2014
120 Material Sample Submission 28 days 05-06-2014 18-07-2014
121 Material Sample Approval 28 days 25-07-2014 05-09-2014
122 Procurement lead time 160 days 12-09-2014 05-06-2015
123 Delivery of Materials 1 day 05-06-2015 06-06-2015
124 ALUMINIUM GLAZING & METAL WORKS 177 days 11-01-2016 24-10-2016
125 Shop Drawing Submission 28 days 11-01-2016 24-02-2016
126 Shop Drawing Approval 28 days 02-03-2016 29-04-2016
127 Material Sample Submission 28 days 11-01-2016 24-02-2016
128 Material Sample Approval 28 days 02-03-2016 29-04-2016
129 Delivery of Materials 16 days 29-09-2016 24-10-2016
130 Award of Workpackage 0 days 28-03-2016 28-03-2016
131 EARTHWORK FOR LANDSCAPING WORKS 121 days 25-10-2014 19-05-2015
132 Award of Workpackage 0 days 25-10-2014 25-10-2014
133 Shop Drawing Submission 14 days 19-11-2014 11-12-2014
134 Shop Drawing Approval 14 days 13-12-2014 06-01-2015
135 Material Sample Submission 14 days 19-11-2014 11-12-2014
136 Material Sample Approval 14 days 13-12-2014 06-01-2015
137 Delivery of Materials 0 days 19-05-2015 19-05-2015
138 Co-Ordination Drawings and Identification of provision to keep with structure
22 days 29-05-2014 01-07-2014
139 Co-Ordination Drawings 20 days 29-05-2014 28-06-2014
140 Identification of MEP provisions to keep with structure 20 days 31-05-2014 01-07-2014
141 CONSTRUCTION 725.2 days 22-11-2013 25-01-2017
142 Ground Breaking Ceromony 1 day 22-11-2013 23-11-2013
143 SHORING, DEWATERING & EXCAVATION 176.8 days 05-12-2013 16-09-2014
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 5 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
144 Excavation, Dewatering and shoring work (ref Method Statement)
176.8 days 05-12-2013 16-09-2014
145 Excavation up to -6m level grid between (C-K) (1-6) ref: Method Statement & Dra SPS/SD/EX/001
83.2 days 05-12-2013 09-04-2014
146 Grouting Work for Contiguous piles 40 days 01-03-2014 16-05-2014
147 Capping Beam 20 days 07-05-2014 06-06-2014
148 Monitoring of defection of earth retaining system, Building monitoring
75 days 01-03-2014 08-07-2014
149 Supporting to Contingeous Piles , Erection of Whaler and King Post ref: Method Statement & Dra SPS/SD/EX/001
45 days 10-03-2014 02-06-2014
150 12 m permanent Sheet Pilling alog grid 6 between (A-G) and provide whealer
35 days 20-03-2014 28-05-2014
151 Step 1 :Excavation -3m to -6m between grid (C-K)/(1-6) ref: Method Statement & Dra SPS/SD/EX/002
14 days 01-04-2014 08-05-2014
152 Sheet piles -6m to -18 m in lift core area ref: Method Statement & Dra SPS/SD/EX/003
10 days 08-05-2014 23-05-2014
153 Supporting arrangement with using sheer walls 3 days 02-09-2014 06-09-2014
154 Removal of King posts 2 days 05-09-2014 09-09-2014
155 Step 2 :Balance Excavation up to -6m 5 days 09-09-2014 16-09-2014
156 Sheet Pilling Work alog grid A in betn ( 1-6) and along 1 in betn (A-C) with keeping provision to earth moving
35 days 11-03-2014 19-05-2014
157 FOUNDATION/ SUBSTRUCTURE 173.6 days 04-04-2014 12-01-2015
158 Level -12000 to -5975 Lift Core/ Sheer Walls 46 days 24-05-2014 02-08-2014
159 Excavation in lift core area 8 days 24-05-2014 04-06-2014
160 Pile Hacking 8 days 30-05-2014 10-06-2014
161 Pile Testing 3 days 07-06-2014 13-06-2014
162 High Strength Concrete Grouting on top of pile caps 4 days 07-06-2014 14-06-2014
100%
25%
70%
10%
10%
20%
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 6 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
163 Leveling and Compaction of bottom of basement slab/pile caps
2 days 13-06-2014 16-06-2014
164 Screed Concrete 2 days 16-06-2014 19-06-2014
165 200x 200 Tie Beam 6 days 19-06-2014 27-06-2014
166 200tk Hollow Block Work 10 days 21-06-2014 07-07-2014
167 Waterproofing for Side walls 8 days 01-07-2014 14-07-2014
168 Pile Cap PC05 Fm/wk, R/f, Concrete works 10 days 05-07-2014 21-07-2014
169 Strom water tank walls/ Lift well 4 days 21-07-2014 26-07-2014
170 Waterproofing and Testing 4 days 26-07-2014 02-08-2014
171 Basement 2 Level -5975 to Basement 1 Level -2750 169.6 days 04-04-2014 06-01-2015
172 Lift Core/ Sheer Walls 21 days 02-08-2014 02-09-2014
173 Slab Fm wk, r/f, Concrete @ -5975 7 days 02-08-2014 13-08-2014
174 Lift Core sheer walls up to -2750 7 days 13-08-2014 22-08-2014
175 Staircases - Structural Works 7 days 23-08-2014 02-09-2014
176 Grid (G-K)/ (1-6) 169.6 days 04-04-2014 06-01-2015
177 (G-K)/(2-5) 83 days 04-04-2014 25-08-2014
178 Pile Hacking 45 days 04-04-2014 28-06-2014
179 Pile Testing 25 days 09-04-2014 30-06-2014
180 High Strength Concrete Grouting on top of pile caps
20 days 03-06-2014 02-07-2014
181 Leveling and Compaction of bottom of basement slab/pile caps
20 days 05-06-2014 05-07-2014
182 Screed Concrete 15 days 21-06-2014 14-07-2014
183 Pile Caps and Basement 2 Form work, R/f Concrete
40 days 25-06-2014 25-08-2014
184 (G-K)/(1-3)//(G-K)/(4-6) 31 days 06-08-2014 20-09-2014
185 Pile Hacking 30 days 06-08-2014 19-09-2014
186 Pile Testing 14 days 30-08-2014 20-09-2014
20%
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 7 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
187 High Strength Concrete Grouting on top of pile caps 14 days 01-09-2014 22-09-2014
188 Leveling and Compaction of bottom of basement slab/pile caps
4 days 19-09-2014 25-09-2014
189 Screed Concrete 10 days 13-09-2014 27-09-2014
190 Pile Caps Form work, R/f Concrete 20 days 17-09-2014 16-10-2014
191 Basement 2 Slab Fm Wk, R/F wk, Concrete Wk 25 days 24-09-2014 01-11-2014
192 Columns up to -2750 beam bottom 6 days 01-11-2014 11-11-2014
193 Ramps and Landing up to -5.375 14 days 01-11-2014 22-11-2014
194 Ramps and Landing up to -3.375 14 days 15-12-2014 06-01-2015
195 Retaining Walls 25 days 21-10-2014 28-11-2014
196 Grid (A-G (1-6) 62 days 04-09-2014 09-12-2014
197 Excavation & Dewatering associated Works 8 days 06-09-2014 19-09-2014
198 Pile Hacking 15 days 04-09-2014 26-09-2014
199 Pile Testing 15 days 06-09-2014 30-09-2014
200 High Strength Concrete Grouting on top of pile caps 10 days 18-09-2014 02-10-2014
201 Leveling and Compaction of bottom of basement slab/pile caps
10 days 20-09-2014 06-10-2014
202 Screed Concrete 10 days 29-09-2014 14-10-2014
203 Pile Caps Form work, R/f Concrete 20 days 01-10-2014 01-11-2014
204 Basement 2 Slab Fm Wk, R/F wk, Concrete Wk 20 days 17-10-2014 17-11-2014
205 Columns up tp -2750 beam bottom level 14 days 18-11-2014 09-12-2014
206 Retaining Walls 14 days 18-11-2014 09-12-2014
207 Basement 1 Level -2750 to +Ground Floor +0.45 92 days 23-08-2014 12-01-2015
208 Lift Core/ Sheer Walls 21 days 23-08-2014 24-09-2014
209 Slab @ -2750 7 days 23-08-2014 02-09-2014
210 Lift Core sheer walls up to +0.45 7 days 02-09-2014 13-09-2014
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 8 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
211 Staircases - Structural Works 7 days 13-09-2014 24-09-2014
212 Grid (G-K)/ (1-6) 28 days 29-11-2014 12-01-2015
213 Basement 1 Slab 10 days 29-11-2014 15-12-2014
214 Columns 8 days 15-12-2014 27-12-2014
215 Ramps and Landing up to -2.175 18 days 15-12-2014 12-01-2015
216 Ramps and Landing up to +0.45 18 days 15-12-2014 12-01-2015
217 Retaining Walls 10 days 15-12-2014 30-12-2014
218 Grid (A-G (1-6) 20 days 05-12-2014 06-01-2015
219 Basement 1 Slab 10 days 05-12-2014 20-12-2014
220 Columns up to +0.45 beam bottom level 8 days 20-12-2014 02-01-2015
221 Retaining Walls 10 days 20-12-2014 06-01-2015
222 SUPERSTRUCTURE (Ground Floor to Roof) 435 days 13-09-2014 18-08-2016
223 Ground Level +0.45 to Level 1 +3.675 114 days 13-09-2014 10-03-2015
224 Lift Core/ Sheer Walls 25 days 13-09-2014 21-10-2014
225 Slab @ +0.45 7 days 13-09-2014 24-09-2014
226 Lift Core sheer walls up to +3.675 10 days 24-09-2014 09-10-2014
227 Staircases - Structural Works 10 days 06-10-2014 21-10-2014
228 Grid (G-K)/ (1-6) 44 days 31-12-2014 10-03-2015
229 Ground Floor Slab at +0.45 8 days 31-12-2014 12-01-2015
230 Columns up to Level 1 +3.675 Beam Bottom Level 6 days 13-01-2015 22-01-2015
231 Ramps and Landing up to -2.175 18 days 13-01-2015 11-02-2015
232 Ramps and Landing up to +0.45 18 days 11-02-2015 10-03-2015
233 Retaining Walls 15 days 13-01-2015 06-02-2015
234 Grid (A-G (1-6) 24 days 07-01-2015 13-02-2015
235 Ground Floor Slab at +0.45 9 days 07-01-2015 21-01-2015
236 Columns up to Level 1 +5.60 Beam Bottom Level 6 days 21-01-2015 29-01-2015
237 Retaining Walls 15 days 21-01-2015 13-02-2015
238 Level 1 +3.675 to Level 2 +7.20 101 days 09-10-2014 16-03-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 9 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
239 Lift Core/ Sheer Walls 32 days 09-10-2014 27-11-2014
240 Slab at Level 1 +3.675 8 days 09-10-2014 21-10-2014
241 Lift Core sheer walls up to Level +5.60 8 days 21-10-2014 03-11-2014
242 Slab at Level 1 +5.60 8 days 03-11-2014 15-11-2014
243 Staircase up to Level 1 +5.60 8 days 03-11-2014 15-11-2014
244 Lift Core sheer walls up to Level +7.20 8 days 15-11-2014 27-11-2014
245 Grid (F-K)/ (1-6) 11 days 22-01-2015 10-02-2015
246 Level 1 Slab at +3.675 6 days 22-01-2015 30-01-2015
247 Columns up to Level 2 +7.2 Beam Bottom Level 5 days 31-01-2015 10-02-2015
248 Grid (A-D (1-6) 10 days 29-01-2015 16-02-2015
249 Level 1 Slab at +5.60 6 days 29-01-2015 10-02-2015
250 Columns up to Level 2 +8.80 Beam Bottom Level 4 days 10-02-2015 16-02-2015
251 Ramp (F-D) /(4-5) 14 days 31-01-2015 23-02-2015
252 Ramp +3.675 to +5.60 14 days 31-01-2015 23-02-2015
253 Ramp (D-G) /(2-3) 14 days 23-02-2015 16-03-2015
254 Ramp +5.60 to +7.20 14 days 23-02-2015 16-03-2015
255 Level 2 +7.2 to Level 3 +10.40 80 days 27-11-2014 01-04-2015
256 Lift Core/ Sheer Walls 32 days 27-11-2014 17-01-2015
257 Slab at Level 2 +7.2 8 days 27-11-2014 10-12-2014
258 Lift Core sheer walls up to Level +8.80 8 days 10-12-2014 22-12-2014
259 Slab at Level 2 +8.80 8 days 22-12-2014 03-01-2015
260 Staircase up to Level 2 +8.80 8 days 22-12-2014 03-01-2015
261 Lift Core sheer walls up to Level +10.40 8 days 03-01-2015 17-01-2015
262 Grid (F-K)/ (1-6) 11 days 10-02-2015 25-02-2015
263 Level 2 Slab at +7.2 6 days 10-02-2015 18-02-2015
264 Columns up to Level 3 +10.40 beam bottom 5 days 18-02-2015 25-02-2015
265 Grid (A-D (1-6) 10 days 16-02-2015 02-03-2015
266 Level 2 Slab at +8.80 6 days 16-02-2015 24-02-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 10 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
267 Columns up to Level 3 +12.00 beam bottom 4 days 24-02-2015 02-03-2015
268 Ramp (F-D) /(4-5) 14 days 18-02-2015 12-03-2015
269 Ramp +7.20 to +8.80 14 days 18-02-2015 12-03-2015
270 Ramp (D-G) /(2-3) 14 days 12-03-2015 01-04-2015
271 Ramp +8.80 to + 10.40 14 days 12-03-2015 01-04-2015
272 Level 3 10.40 to Level 3 Mezzanine Floor at +13.15 45 days 17-01-2015 27-03-2015
273 Lift Core/ Sheer Walls 32 days 17-01-2015 09-03-2015
274 Slab at Level 3 at +10.40 8 days 17-01-2015 29-01-2015
275 Lift Core sheer walls up to Level +12.00 8 days 29-01-2015 12-02-2015
276 Slab at Level 3 +12.00 8 days 12-02-2015 24-02-2015
277 Staircase up to Level 3 +12.00 8 days 12-02-2015 24-02-2015
278 Lift Core sheer walls up to Level +13.15 8 days 24-02-2015 09-03-2015
279 Grid (F-K)/ (1-6) 11 days 26-02-2015 14-03-2015
280 Level 3 Floor Slab at +10.40 6 days 26-02-2015 07-03-2015
281 Columns up to Level 3 Mezzanine Floor +13.15 beambottom
5 days 07-03-2015 14-03-2015
282 Grid (A-D (1-6) 15 days 02-03-2015 25-03-2015
283 Level 2 Slab at +12.00 9 days 02-03-2015 16-03-2015
284 Columns up to Level 4 +16.50 beam bottom 6 days 17-03-2015 25-03-2015
285 Ramp (F-D) /(4-5) 14 days 07-03-2015 27-03-2015
286 Ramp +7.20 to +8.80 14 days 07-03-2015 27-03-2015
287 Level 3 Mezzanine Floor at +13.15 to Level 4 16 days 09-03-2015 01-04-2015
288 Lift Core/ Sheer Walls 16 days 09-03-2015 01-04-2015
289 Slab at Level 3 at +13.15 8 days 09-03-2015 20-03-2015
290 Lift Core sheer walls up to Level 4 8 days 20-03-2015 01-04-2015
291 Staircase up to Level 4 8 days 20-03-2015 01-04-2015
292 Grid (F-K)/ (1-6) 11 days 14-03-2015 31-03-2015
293 Level 3 Mezzanine Floor Slab at +13.15 6 days 14-03-2015 24-03-2015
294 Columns up to Level 3 +10.40 beam bottom 5 days 24-03-2015 31-03-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 11 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
295 Level 04 Office Floor +20.4 16 days 30-03-2015 12-05-2015
296 Slab Form work 6 days 30-03-2015 08-04-2015
297 Slab Reinforcement work 6 days 04-04-2015 29-04-2015
298 Slab M& E Works 4 days 08-04-2015 30-04-2015
299 Slab Concrete -1 st Pour 1 day 28-04-2015 29-04-2015
300 Slab Concrete- Final Pour 1 day 30-04-2015 04-05-2015
301 Core Walls R/F Work 8 days 01-04-2015 30-04-2015
302 Core Walls Formwork 6 days 07-04-2015 04-05-2015
303 Core Wall Conctete 4 days 28-04-2015 06-05-2015
304 Columns F/W, R/F Concrete and associated Works 6 days 30-04-2015 12-05-2015
305 Level 05 Office Floor +24.3 17 days 06-05-2015 30-05-2015
306 Slab Form work 6 days 08-05-2015 18-05-2015
307 Slab Reinforcement work 6 days 11-05-2015 19-05-2015
308 Slab M& E Works 4 days 14-05-2015 20-05-2015
309 Slab Concrete -1 st Pour 1 day 18-05-2015 19-05-2015
310 Slab Concrete- Final Pour 1 day 20-05-2015 21-05-2015
311 Core Walls R/F Work 8 days 06-05-2015 18-05-2015
312 Core Walls Formwork 6 days 11-05-2015 19-05-2015
313 Core Wall Conctete 4 days 14-05-2015 20-05-2015
314 Columns F/W, R/F Concrete and associated Works 6 days 22-05-2015 30-05-2015
315 Level 06 Office Floor +28.2 17 days 20-05-2015 15-06-2015
316 Slab Form work 6 days 26-05-2015 05-06-2015
317 Slab Reinforcement work 6 days 28-05-2015 06-06-2015
318 Slab M& E Works 4 days 01-06-2015 08-06-2015
319 Slab Concrete -1 st Pour 1 day 05-06-2015 06-06-2015
320 Slab Concrete- Final Pour 1 day 08-06-2015 09-06-2015
321 Core Walls R/F Work 8 days 20-05-2015 01-06-2015
322 Core Walls Formwork 6 days 25-05-2015 03-06-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 12 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
323 Core Wall Conctete 4 days 29-05-2015 05-06-2015
324 Columns F/W, R/F Concrete and associated Works 6 days 06-06-2015 15-06-2015
325 Level 07 Office Floor +32.1 17 days 05-06-2015 30-06-2015
326 Slab Form work 6 days 11-06-2015 19-06-2015
327 Slab Reinforcement work 6 days 12-06-2015 20-06-2015
328 Slab M& E Works 4 days 17-06-2015 23-06-2015
329 Slab Concrete -1 st Pour 1 day 19-06-2015 20-06-2015
330 Slab Concrete- Final Pour 1 day 23-06-2015 24-06-2015
331 Core Walls R/F Work 8 days 05-06-2015 17-06-2015
332 Core Walls Formwork 6 days 10-06-2015 18-06-2015
333 Core Wall Conctete 4 days 13-06-2015 19-06-2015
334 Columns F/W, R/F Concrete and associated Works 6 days 22-06-2015 30-06-2015
335 Level 08 Office Floor +36 17 days 19-06-2015 15-07-2015
336 Slab Form work 6 days 25-06-2015 06-07-2015
337 Slab Reinforcement work 6 days 27-06-2015 07-07-2015
338 Slab M& E Works 4 days 01-07-2015 08-07-2015
339 Slab Concrete -1 st Pour 1 day 06-07-2015 07-07-2015
340 Slab Concrete- Final Pour 1 day 08-07-2015 09-07-2015
341 Core Walls R/F Work 8 days 19-06-2015 01-07-2015
342 Core Walls Formwork 6 days 24-06-2015 03-07-2015
343 Core Wall Conctete 4 days 29-06-2015 06-07-2015
344 Columns F/W, R/F Concrete and associated Works 6 days 07-07-2015 15-07-2015
345 Level 09 Office Floor +39.9 17 days 06-07-2015 31-07-2015
346 Slab Form work 6 days 11-07-2015 20-07-2015
347 Slab Reinforcement work 6 days 13-07-2015 21-07-2015
348 Slab M& E Works 4 days 17-07-2015 23-07-2015
349 Slab Concrete -1 st Pour 1 day 20-07-2015 21-07-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 13 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
350 Slab Concrete- Final Pour 1 day 23-07-2015 24-07-2015
351 Core Walls R/F Work 8 days 06-07-2015 17-07-2015
352 Core Walls Formwork 6 days 10-07-2015 18-07-2015
353 Core Wall Conctete 4 days 14-07-2015 20-07-2015
354 Columns F/W, R/F Concrete and associated Works 6 days 22-07-2015 31-07-2015
355 Level 10 Office Floor +43.8 17 days 20-07-2015 14-08-2015
356 Slab Form work 6 days 25-07-2015 05-08-2015
357 Slab Reinforcement work 6 days 28-07-2015 06-08-2015
358 Slab M& E Works 4 days 01-08-2015 07-08-2015
359 Slab Concrete -1 st Pour 1 day 05-08-2015 06-08-2015
360 Slab Concrete- Final Pour 1 day 07-08-2015 08-08-2015
361 Core Walls R/F Work 8 days 20-07-2015 01-08-2015
362 Core Walls Formwork 6 days 24-07-2015 03-08-2015
363 Core Wall Conctete 4 days 30-07-2015 05-08-2015
364 Columns F/W, R/F Concrete and associated Works 6 days 06-08-2015 14-08-2015
365 Level 11 Office Floor +47.7 17 days 05-08-2015 29-08-2015
366 Slab Form work 6 days 11-08-2015 19-08-2015
367 Slab Reinforcement work 6 days 12-08-2015 20-08-2015
368 Slab M& E Works 4 days 17-08-2015 22-08-2015
369 Slab Concrete -1 st Pour 1 day 19-08-2015 20-08-2015
370 Slab Concrete- Final Pour 1 day 22-08-2015 24-08-2015
371 Core Walls R/F Work 8 days 05-08-2015 17-08-2015
372 Core Walls Formwork 6 days 10-08-2015 18-08-2015
373 Core Wall Conctete 4 days 13-08-2015 19-08-2015
374 Columns F/W, R/F Concrete and associated Works 6 days 21-08-2015 29-08-2015
375 Level 12 Office Floor +51.6 17 days 19-08-2015 14-09-2015
376 Slab Form work 6 days 25-08-2015 04-09-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 14 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
377 Slab Reinforcement work 6 days 27-08-2015 05-09-2015
378 Slab M& E Works 4 days 31-08-2015 07-09-2015
379 Slab Concrete -1 st Pour 1 day 04-09-2015 05-09-2015
380 Slab Concrete- Final Pour 1 day 07-09-2015 08-09-2015
381 Core Walls R/F Work 8 days 19-08-2015 31-08-2015
382 Core Walls Formwork 6 days 24-08-2015 01-09-2015
383 Core Wall Conctete 4 days 28-08-2015 04-09-2015
384 Columns F/W, R/F Concrete and associated Works 6 days 05-09-2015 14-09-2015
385 Level 13 Office Floor +55.53 17 days 04-09-2015 29-09-2015
386 Slab Form work 6 days 10-09-2015 18-09-2015
387 Slab Reinforcement work 6 days 11-09-2015 19-09-2015
388 Slab M& E Works 4 days 16-09-2015 22-09-2015
389 Slab Concrete -1 st Pour 1 day 18-09-2015 19-09-2015
390 Slab Concrete- Final Pour 1 day 22-09-2015 23-09-2015
391 Core Walls R/F Work 8 days 04-09-2015 16-09-2015
392 Core Walls Formwork 6 days 09-09-2015 17-09-2015
393 Core Wall Conctete 4 days 12-09-2015 18-09-2015
394 Columns F/W, R/F Concrete and associated Works 6 days 21-09-2015 29-09-2015
395 Level 14 Office Floor +59.4 17 days 18-09-2015 14-10-2015
396 Slab Form work 6 days 24-09-2015 05-10-2015
397 Slab Reinforcement work 6 days 26-09-2015 06-10-2015
398 Slab M& E Works 4 days 30-09-2015 07-10-2015
399 Slab Concrete -1 st Pour 1 day 05-10-2015 06-10-2015
400 Slab Concrete- Final Pour 1 day 07-10-2015 08-10-2015
401 Core Walls R/F Work 8 days 18-09-2015 30-09-2015
402 Core Walls Formwork 6 days 23-09-2015 01-10-2015
403 Core Wall Conctete 4 days 28-09-2015 05-10-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 15 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
404 Columns F/W, R/F Concrete and associated Works 6 days 06-10-2015 14-10-2015
405 Level 15 Office Floor +63.3 17 days 05-10-2015 30-10-2015
406 Slab Form work 6 days 10-10-2015 19-10-2015
407 Slab Reinforcement work 6 days 12-10-2015 20-10-2015
408 Slab M& E Works 4 days 16-10-2015 23-10-2015
409 Slab Concrete -1 st Pour 1 day 19-10-2015 20-10-2015
410 Slab Concrete- Final Pour 1 day 23-10-2015 24-10-2015
411 Core Walls R/F Work 8 days 05-10-2015 16-10-2015
412 Core Walls Formwork 6 days 09-10-2015 17-10-2015
413 Core Wall Conctete 4 days 13-10-2015 19-10-2015
414 Columns F/W, R/F Concrete and associated Works 6 days 21-10-2015 30-10-2015
415 Level 16 Office Floor +67.2 17 days 19-10-2015 14-11-2015
416 Slab Form work 6 days 26-10-2015 05-11-2015
417 Slab Reinforcement work 6 days 28-10-2015 06-11-2015
418 Slab M& E Works 4 days 31-10-2015 07-11-2015
419 Slab Concrete -1 st Pour 1 day 05-11-2015 06-11-2015
420 Slab Concrete- Final Pour 1 day 07-11-2015 09-11-2015
421 Core Walls R/F Work 8 days 19-10-2015 31-10-2015
422 Core Walls Formwork 6 days 26-10-2015 05-11-2015
423 Core Wall Conctete 4 days 30-10-2015 06-11-2015
424 Columns F/W, R/F Concrete and associated Works 6 days 06-11-2015 14-11-2015
425 Level 17 Office Floor +71.1 16 days 06-11-2015 30-11-2015
426 Slab Form work 6 days 11-11-2015 19-11-2015
427 Slab Reinforcement work 6 days 12-11-2015 20-11-2015
428 Slab M& E Works 4 days 17-11-2015 23-11-2015
429 Slab Concrete -1 st Pour 1 day 19-11-2015 20-11-2015
430 Slab Concrete- Final Pour 1 day 23-11-2015 24-11-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 16 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
431 Core Walls R/F Work 8 days 06-11-2015 18-11-2015
432 Core Walls Formwork 6 days 11-11-2015 19-11-2015
433 Core Wall Conctete 4 days 16-11-2015 20-11-2015
434 Columns F/W, R/F Concrete and associated Works 6 days 21-11-2015 30-11-2015
435 Level 18 Office Floor +75 16 days 21-11-2015 15-12-2015
436 Slab Form work 6 days 25-11-2015 05-12-2015
437 Slab Reinforcement work 6 days 27-11-2015 07-12-2015
438 Slab M& E Works 4 days 01-12-2015 08-12-2015
439 Slab Concrete -1 st Pour 1 day 05-12-2015 07-12-2015
440 Slab Concrete- Final Pour 1 day 08-12-2015 09-12-2015
441 Core Walls R/F Work 8 days 21-11-2015 03-12-2015
442 Core Walls Formwork 6 days 25-11-2015 05-12-2015
443 Core Wall Conctete 4 days 30-11-2015 07-12-2015
444 Columns F/W, R/F Concrete and associated Works 6 days 07-12-2015 15-12-2015
445 Level 19 Office Floor +78.9 16 days 07-12-2015 31-12-2015
446 Slab Form work 6 days 11-12-2015 19-12-2015
447 Slab Reinforcement work 6 days 12-12-2015 21-12-2015
448 Slab M& E Works 4 days 17-12-2015 23-12-2015
449 Slab Concrete -1 st Pour 1 day 19-12-2015 21-12-2015
450 Slab Concrete- Final Pour 1 day 23-12-2015 24-12-2015
451 Core Walls R/F Work 8 days 07-12-2015 18-12-2015
452 Core Walls Formwork 6 days 11-12-2015 19-12-2015
453 Core Wall Conctete 4 days 16-12-2015 21-12-2015
454 Columns F/W, R/F Concrete and associated Works 6 days 22-12-2015 31-12-2015
455 Level 20 Office Floor +82.8 18 days 22-12-2015 20-01-2016
456 Slab Form work 6 days 26-12-2015 06-01-2016
457 Slab Reinforcement work 6 days 31-12-2015 09-01-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 17 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
458 Slab M & E Works 4 days 06-01-2016 12-01-2016
459 Slab Concrete -1 st Pour 1 day 08-01-2016 09-01-2016
460 Slab Concrete- Final Pour 1 day 12-01-2016 13-01-2016
461 Core Walls R/F Work 8 days 22-12-2015 02-01-2016
462 Core Walls Formwork 6 days 26-12-2015 06-01-2016
463 Core Wall Conctete 4 days 31-12-2015 07-01-2016
464 Columns F/W, R/F Concrete and associated Works 6 days 11-01-2016 20-01-2016
465 Level 21 Office Floor +86.7 18 days 07-01-2016 05-02-2016
466 Slab Form work 6 days 15-01-2016 25-01-2016
467 Slab Reinforcement work 6 days 18-01-2016 26-01-2016
468 Slab M& E Works 4 days 21-01-2016 27-01-2016
469 Slab Concrete -1 st Pour 1 day 25-01-2016 26-01-2016
470 Slab Concrete- Final Pour 1 day 27-01-2016 28-01-2016
471 Core Walls R/F Work 8 days 07-01-2016 20-01-2016
472 Core Walls Formwork 6 days 12-01-2016 21-01-2016
473 Core Wall Conctete 4 days 18-01-2016 22-01-2016
474 Columns F/W, R/F Concrete and associated Works 6 days 26-01-2016 05-02-2016
475 Level 22 Office Floor +90.6 18 days 23-01-2016 20-02-2016
476 Slab Form work 6 days 30-01-2016 10-02-2016
477 Slab Reinforcement work 6 days 01-02-2016 11-02-2016
478 Slab M& E Works 4 days 08-02-2016 13-02-2016
479 Slab Concrete -1 st Pour 1 day 10-02-2016 11-02-2016
480 Slab Concrete- Final Pour 1 day 13-02-2016 15-02-2016
481 Core Walls R/F Work 8 days 23-01-2016 05-02-2016
482 Core Walls Formwork 6 days 27-01-2016 08-02-2016
483 Core Wall Conctete 4 days 01-02-2016 09-02-2016
484 Columns F/W, R/F Concrete and associated Works 6 days 12-02-2016 20-02-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 18 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
485 Level 23 Office Floor +94.5 18 days 09-02-2016 07-03-2016
486 Slab Form work 6 days 16-02-2016 25-02-2016
487 Slab Reinforcement work 6 days 18-02-2016 26-02-2016
488 Slab M& E Works 4 days 22-02-2016 27-02-2016
489 Slab Concrete -1 st Pour 1 day 25-02-2016 26-02-2016
490 Slab Concrete- Final Pour 1 day 27-02-2016 29-02-2016
491 Core Walls R/F Work 8 days 09-02-2016 20-02-2016
492 Core Walls Formwork 6 days 13-02-2016 22-02-2016
493 Core Wall Conctete 4 days 18-02-2016 23-02-2016
494 Columns F/W, R/F Concrete and associated Works 6 days 26-02-2016 07-03-2016
495 Level 24 Office Floor +98.4 18 days 24-02-2016 22-03-2016
496 Slab Form work 6 days 02-03-2016 11-03-2016
497 Slab Reinforcement work 6 days 04-03-2016 12-03-2016
498 Slab M& E Works 4 days 09-03-2016 15-03-2016
499 Slab Concrete -1 st Pour 1 day 11-03-2016 12-03-2016
500 Slab Concrete- Final Pour 1 day 15-03-2016 16-03-2016
501 Core Walls R/F Work 8 days 24-02-2016 07-03-2016
502 Core Walls Formwork 6 days 27-02-2016 09-03-2016
503 Core Wall Conctete 4 days 04-03-2016 10-03-2016
504 Columns F/W, R/F Concrete and associated Works 6 days 14-03-2016 22-03-2016
505 Level 25 Office Floor +102.3 18 days 10-03-2016 06-04-2016
506 Slab Form work 6 days 17-03-2016 26-03-2016
507 Slab Reinforcement work 6 days 19-03-2016 28-03-2016
508 Slab M& E Works 4 days 23-03-2016 29-03-2016
509 Slab Concrete -1 st Pour 1 day 26-03-2016 28-03-2016
510 Slab Concrete- Final Pour 1 day 29-03-2016 30-03-2016
511 Core Walls R/F Work 8 days 10-03-2016 22-03-2016
512 Core Walls Formwork 6 days 15-03-2016 23-03-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 19 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
513 Core Wall Conctete 4 days 19-03-2016 24-03-2016
514 Columns F/W, R/F Concrete and associated Works 6 days 28-03-2016 06-04-2016
515 Level 26 Office Floor +106.2 18 days 25-03-2016 07-05-2016
516 Slab Form work 6 days 01-04-2016 26-04-2016
517 Slab Reinforcement work 6 days 04-04-2016 27-04-2016
518 Slab M& E Works 4 days 08-04-2016 29-04-2016
519 Slab Concrete -1 st Pour 1 day 26-04-2016 27-04-2016
520 Slab Concrete- Final Pour 1 day 29-04-2016 30-04-2016
521 Core Walls R/F Work 8 days 25-03-2016 06-04-2016
522 Core Walls Formwork 6 days 29-03-2016 08-04-2016
523 Core Wall Conctete 4 days 04-04-2016 09-04-2016
524 Columns F/W, R/F Concrete and associated Works 6 days 28-04-2016 07-05-2016
525 Level 27 Office Floor +110.1 18 days 09-04-2016 21-05-2016
526 Slab Form work 6 days 03-05-2016 12-05-2016
527 Slab Reinforcement work 6 days 05-05-2016 13-05-2016
528 Slab M& E Works 4 days 09-05-2016 14-05-2016
529 Slab Concrete -1 st Pour 1 day 12-05-2016 13-05-2016
530 Slab Concrete- Final Pour 1 day 14-05-2016 16-05-2016
531 Core Walls R/F Work 8 days 09-04-2016 07-05-2016
532 Core Walls Formwork 6 days 29-04-2016 09-05-2016
533 Core Wall Conctete 4 days 05-05-2016 10-05-2016
534 Columns F/W, R/F Concrete and associated Works 6 days 13-05-2016 21-05-2016
535 Level 28 Auditorium level 1 +114 17 days 11-05-2016 06-06-2016
536 Slab Form work 8 days 14-05-2016 26-05-2016
537 Slab Reinforcement work 7 days 18-05-2016 27-05-2016
538 Slab M& E Works 5 days 23-05-2016 30-05-2016
539 Slab Concrete -1 st Pour 1 day 25-05-2016 26-05-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 20 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
540 Slab Concrete- Final Pour 1 day 30-05-2016 31-05-2016
541 Core Walls R/F Work 8 days 11-05-2016 21-05-2016
542 Core Walls Formwork 6 days 14-05-2016 24-05-2016
543 Core Wall Conctete 4 days 19-05-2016 25-05-2016
544 Columns F/W, R/F Concrete and associated Works 6 days 26-05-2016 06-06-2016
545 Level 29 Auditorium level 2 +117.9 17 days 25-05-2016 20-06-2016
546 Slab Form work 9 days 28-05-2016 11-06-2016
547 Slab Reinforcement work 7 days 01-06-2016 13-06-2016
548 Slab M& E Works 5 days 07-06-2016 14-06-2016
549 Slab Concrete -1 st Pour 1 day 10-06-2016 11-06-2016
550 Slab Concrete- Final Pour 1 day 14-06-2016 15-06-2016
551 Core Walls R/F Work 8 days 25-05-2016 07-06-2016
552 Core Walls Formwork 6 days 30-05-2016 08-06-2016
553 Core Wall Conctete 4 days 04-06-2016 09-06-2016
554 Columns F/W, R/F Concrete and associated Works 6 days 11-06-2016 20-06-2016
555 Level 30 (Double Height) Auditorium level 3 +123.425 16 days 10-06-2016 04-07-2016
556 Slab Form work 9 days 11-06-2016 24-06-2016
557 Slab Reinforcement work 8 days 14-06-2016 25-06-2016
558 Slab M& E Works 5 days 20-06-2016 27-06-2016
559 Slab Concrete -1 st Pour 1 day 23-06-2016 24-06-2016
560 Slab Concrete- Final Pour 1 day 28-06-2016 29-06-2016
561 Core Walls R/F Work 8 days 10-06-2016 21-06-2016
562 Core Walls Formwork 6 days 14-06-2016 23-06-2016
563 Core Wall Conctete 4 days 18-06-2016 24-06-2016
564 Columns F/W, R/F Concrete and associated Works 6 days 24-06-2016 04-07-2016
565 Level 31 Recreational level +126.675 16 days 23-06-2016 18-07-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 21 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
566 Slab Form work 10 days 23-06-2016 08-07-2016
567 Slab Reinforcement work 9 days 25-06-2016 09-07-2016
568 Slab M& E Works 5 days 05-07-2016 12-07-2016
569 Slab Concrete -1 st Pour 1 day 07-07-2016 08-07-2016
570 Slab Concrete- Final Pour 1 day 12-07-2016 13-07-2016
571 Core Walls R/F Work 8 days 24-06-2016 07-07-2016
572 Core Walls Formwork 6 days 29-06-2016 08-07-2016
573 Core Wall Conctete 4 days 05-07-2016 09-07-2016
574 Columns F/W, R/F Concrete and associated Works 6 days 08-07-2016 18-07-2016
575 Level 32 Pump Room Level +129.975 15 days 11-07-2016 03-08-2016
576 Slab Form work 6 days 13-07-2016 21-07-2016
577 Slab Reinforcement work 6 days 14-07-2016 23-07-2016
578 Slab M& E Works 4 days 19-07-2016 25-07-2016
579 Slab Concrete -1 st Pour 1 day 22-07-2016 23-07-2016
580 Slab Concrete- Final Pour 1 day 25-07-2016 26-07-2016
581 Core Walls R/F Work 8 days 11-07-2016 21-07-2016
582 Core Walls Formwork 6 days 14-07-2016 23-07-2016
583 Core Wall Conctete 4 days 19-07-2016 25-07-2016
584 Columns F/W, R/F Concrete and associated Works 6 days 23-07-2016 03-08-2016
585 Level R2 Water Tank level +133.175 15 days 25-07-2016 18-08-2016
586 Slab Form work 6 days 28-07-2016 08-08-2016
587 Slab Reinforcement work 6 days 30-07-2016 09-08-2016
588 Slab M& E Works 4 days 05-08-2016 10-08-2016
589 Slab Concrete -1 st Pour 1 day 08-08-2016 09-08-2016
590 Slab Concrete- Final Pour 1 day 11-08-2016 12-08-2016
591 Core Walls R/F Work 7 days 25-07-2016 06-08-2016
592 Core Walls Formwork 6 days 28-07-2016 08-08-2016
593 Core Wall Conctete 4 days 03-08-2016 09-08-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 22 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
594 Water Tank Top Slab 6 days 09-08-2016 18-08-2016
595 Internal Finishes & MEP works 402.8 days 06-05-2015 25-01-2017
596 Basement 2 199.2 days 06-05-2015 07-03-2016
597 Masonry Works 48.8 days 06-05-2015 17-07-2015
598 Blockwork 21 days 06-05-2015 29-05-2015
599 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
21 days 30-05-2015 23-06-2015
600 Internal Plaster 21 days 24-06-2015 17-07-2015
601 Wet Areas 150.4 days 18-07-2015 07-03-2016
602 Dry Areas 150.4 days 18-07-2015 07-03-2016
603 MEP 2nd Fix (Under Ceiling Slab Works, Electricalrooms etc.)
52 days 18-07-2015 18-09-2015
604 Kerbstones 26 days 19-09-2015 19-10-2015
605 Interlock Pavings 26 days 20-10-2015 18-11-2015
606 Install Doors & False Ceiling 13 days 19-11-2015 03-12-2015
607 Painting 26 days 04-12-2015 05-01-2016
608 Traffic Marking 26 days 06-01-2016 05-02-2016
609 MEP Plant rooms - Equipment install & test 52 days 06-01-2016 07-03-2016
610 Basement 1 256.2 days 12-05-2015 23-06-2016
611 Masonry Works 48.8 days 12-05-2015 23-07-2015
612 Blockwork 21 days 12-05-2015 04-06-2015
613 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
21 days 05-06-2015 29-06-2015
614 Internal Plaster 21 days 30-06-2015 23-07-2015
615 Wet Areas 207.4 days 24-07-2015 23-06-2016
616 Dry Areas 207.4 days 24-07-2015 23-06-2016
617 MEP 2nd Fix (Under Ceiling Slab Works, Electricalrooms etc.)
52 days 24-07-2015 24-09-2015
618 Kerbstones 26 days 25-09-2015 24-10-2015
619 Interlock Pavings 26 days 26-10-2015 24-11-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 23 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
620 Install Doors & False Ceiling 13 days 07-03-2016 22-03-2016
621 Painting 26 days 22-03-2016 22-04-2016
622 Traffic Marking 26 days 22-04-2016 24-05-2016
623 MEP Plant rooms - Equipment install & test 52 days 22-04-2016 23-06-2016
624 Ground Floor 249.8 days 12-05-2015 14-06-2016
625 Masonry Works 60.8 days 12-05-2015 11-08-2015
626 Blockwork 26 days 12-05-2015 10-06-2015
627 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
26 days 11-06-2015 10-07-2015
628 Internal Plaster 26 days 11-07-2015 11-08-2015
629 Wet Areas 189 days 12-08-2015 14-06-2016
630 Wet Area Waterproofing 18 days 12-08-2015 01-09-2015
631 MEP 2nd fix High level 45 days 02-09-2015 24-10-2015
632 Wall Tiling 21 days 08-10-2015 31-10-2015
633 Floor Tiling 26 days 12-03-2016 12-04-2016
634 Install Doors & False Ceiling 16 days 12-04-2016 02-05-2016
635 Paint 28 days 12-04-2016 17-05-2016
636 MEP Final Fixes 21 days 28-04-2016 24-05-2016
637 Civil Final Fixes 18 days 24-05-2016 14-06-2016
638 Dry Areas 160.8 days 12-08-2015 02-05-2016
639 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
52 days 12-08-2015 12-10-2015
640 False Ceiling Suspension 26 days 19-09-2015 19-10-2015
641 MEP Dropworks to Ceilings 26 days 03-10-2015 02-11-2015
642 Install Doors & Windows 21 days 03-11-2015 26-11-2015
643 Fase Celing Boarding 26 days 27-11-2015 28-12-2015
644 Painting 26 days 29-12-2015 28-01-2016
645 Civil - Final Finishes 26 days 29-01-2016 29-02-2016
646 MEP Plant Rooms - Equipment Install & test 78 days 29-01-2016 30-04-2016
647 Final Paint, Clean & Snags 1 day 02-05-2016 02-05-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 24 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
648 Level 01 - Parking 242.6 days 23-05-2015 15-06-2016
649 Masonry Works 56.8 days 23-05-2015 17-08-2015
650 Blockwork 21 days 23-05-2015 16-06-2015
651 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
21 days 23-06-2015 16-07-2015
652 Internal Plaster 21 days 23-07-2015 17-08-2015
653 Wet Areas 181.8 days 24-08-2015 15-06-2016
654 Wet Area Waterproofing 13 days 24-08-2015 08-09-2015
655 MEP 2nd fix High level 39 days 09-09-2015 23-10-2015
656 Wall Tiling 18 days 17-10-2015 06-11-2015
657 Floor Tiling 21 days 24-03-2016 19-04-2016
658 Install Doors & False Ceiling 16 days 19-04-2016 09-05-2016
659 Paint 26 days 19-04-2016 20-05-2016
660 MEP Final Fixes 18 days 06-05-2016 27-05-2016
661 Civil Final Fixes 13 days 31-05-2016 15-06-2016
662 Dry Areas 104 days 18-08-2015 25-01-2016
663 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
52 days 18-08-2015 17-10-2015
664 Kerbstones 26 days 25-09-2015 24-10-2015
665 Interlock Pavings 26 days 09-10-2015 07-11-2015
666 Install Doors 13 days 09-11-2015 23-11-2015
667 Painting 26 days 24-11-2015 23-12-2015
668 Traffic Marking 26 days 24-12-2015 25-01-2016
669 MEP Plant rooms - Equipment install & test 78 days 24-09-2015 23-12-2015
670 Level 02 - Parking 240.2 days 29-05-2015 17-06-2016
671 Masonry Works 56.8 days 29-05-2015 22-08-2015
672 Blockwork 21 days 29-05-2015 22-06-2015
673 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
21 days 29-06-2015 22-07-2015
674 Internal Plaster 21 days 30-07-2015 22-08-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 25 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
675 Wet Areas 179.4 days 29-08-2015 17-06-2016
676 Wet Area Waterproofing 13 days 29-08-2015 14-09-2015
677 MEP 2nd fix High level 39 days 15-09-2015 29-10-2015
678 Wall Tiling 18 days 23-10-2015 12-11-2015
679 Floor Tiling 21 days 30-03-2016 25-04-2016
680 Install Doors & False Ceiling 16 days 25-04-2016 14-05-2016
681 Paint 26 days 25-04-2016 26-05-2016
682 MEP Final Fixes 18 days 12-05-2016 02-06-2016
683 Civil Final Fixes 13 days 02-06-2016 17-06-2016
684 Dry Areas 104 days 24-08-2015 30-01-2016
685 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
52 days 24-08-2015 23-10-2015
686 Kerbstones 26 days 01-10-2015 30-10-2015
687 Interlock Pavings 26 days 15-10-2015 13-11-2015
688 Install Doors 13 days 14-11-2015 28-11-2015
689 Painting 26 days 30-11-2015 30-12-2015
690 Traffic Marking 26 days 31-12-2015 30-01-2016
691 MEP Plant rooms - Equipment install & test 78 days 30-09-2015 30-12-2015
692 Level 03 - Parking 241 days 04-06-2015 23-06-2016
693 Masonry Works 57.6 days 04-06-2015 28-08-2015
694 Blockwork 21 days 04-06-2015 27-06-2015
695 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
21 days 04-07-2015 28-07-2015
696 Internal Plaster 21 days 05-08-2015 28-08-2015
697 Wet Areas 179.4 days 05-09-2015 23-06-2016
698 Wet Area Waterproofing 13 days 05-09-2015 19-09-2015
699 MEP 2nd fix High level 39 days 21-09-2015 04-11-2015
700 Wall Tiling 18 days 29-10-2015 18-11-2015
701 Floor Tiling 21 days 05-04-2016 30-04-2016
702 Install Doors & False Ceiling 16 days 30-04-2016 20-05-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 26 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
703 Paint 26 days 30-04-2016 01-06-2016
704 MEP Final Fixes 18 days 18-05-2016 08-06-2016
705 Civil Final Fixes 13 days 08-06-2016 23-06-2016
706 Dry Areas 103.2 days 29-08-2015 06-02-2016
707 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
52 days 29-08-2015 29-10-2015
708 Kerbstones 26 days 07-10-2015 05-11-2015
709 Interlock Pavings 26 days 21-10-2015 19-11-2015
710 Install Doors 13 days 20-11-2015 04-12-2015
711 Painting 26 days 05-12-2015 06-01-2016
712 Traffic Marking 26 days 07-01-2016 06-02-2016
713 MEP Plant rooms - Equipment install & test 78 days 06-10-2015 06-01-2016
714 Level 04 - Office 234.6 days 16-06-2015 25-06-2016
715 Masonry Works 52.8 days 16-06-2015 03-09-2015
716 Blockwork 18 days 16-06-2015 06-07-2015
717 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 14-07-2015 04-08-2015
718 Internal Plaster 18 days 14-08-2015 03-09-2015
719 Wet Areas 172.2 days 17-09-2015 24-06-2016
720 Wet Area Waterproofing 8 days 17-09-2015 25-09-2015
721 MEP 2nd fix High level 39 days 26-09-2015 10-11-2015
722 Wall Tiling 21 days 31-10-2015 24-11-2015
723 Floor Tiling 26 days 05-04-2016 07-05-2016
724 Install Doors & False Ceiling 16 days 07-05-2016 26-05-2016
725 Paint 18 days 07-05-2016 28-05-2016
726 MEP Final Fixes 18 days 14-05-2016 04-06-2016
727 Civil Final Fixes 13 days 09-06-2016 24-06-2016
728 Dry Areas 181 days 05-09-2015 25-06-2016
729 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 05-09-2015 27-10-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 27 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
730 False Ceiling Suspension 26 days 05-10-2015 03-11-2015
731 MEP Dropworks to Ceilings 26 days 19-10-2015 17-11-2015
732 Install Doors & Windows 21 days 09-11-2015 02-12-2015
733 Fase Celing Boarding 26 days 03-12-2015 04-01-2016
734 Painting 26 days 05-01-2016 03-02-2016
735 Civil - Final Finishes 21 days 05-02-2016 29-02-2016
736 MEP Service Rooms - MEP works 21 days 05-02-2016 29-02-2016
737 Final Paint, Clean & Snags 1 day 24-06-2016 25-06-2016
738 MEP Final Finishes 13 days 05-02-2016 19-02-2016
739 Level 05 - Office 223.4 days 04-07-2015 27-06-2016
740 Masonry Works 45.6 days 04-07-2015 10-09-2015
741 Blockwork 18 days 04-07-2015 24-07-2015
742 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 25-07-2015 15-08-2015
743 Internal Plaster 18 days 20-08-2015 10-09-2015
744 Wet Areas 169 days 23-09-2015 25-06-2016
745 Wet Area Waterproofing 8 days 23-09-2015 01-10-2015
746 MEP 2nd fix High level 39 days 02-10-2015 16-11-2015
747 Wall Tiling 21 days 06-11-2015 30-11-2015
748 Floor Tiling 26 days 11-04-2016 13-05-2016
749 Install Doors & False Ceiling 16 days 13-05-2016 01-06-2016
750 Paint 18 days 13-05-2016 03-06-2016
751 MEP Final Fixes 18 days 20-05-2016 10-06-2016
752 Civil Final Fixes 13 days 10-06-2016 25-06-2016
753 Dry Areas 177.8 days 11-09-2015 27-06-2016
754 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 11-09-2015 02-11-2015
755 False Ceiling Suspension 26 days 10-10-2015 09-11-2015
756 MEP Dropworks to Ceilings 26 days 24-10-2015 23-11-2015
757 Install Doors & Windows 21 days 14-11-2015 08-12-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 28 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
758 Fase Celing Boarding 26 days 09-12-2015 09-01-2016
759 Painting 26 days 11-01-2016 10-02-2016
760 Civil - Final Finishes 21 days 11-02-2016 05-03-2016
761 MEP Service Rooms - MEP works 21 days 11-02-2016 05-03-2016
762 Final Paint, Clean & Snags 1 day 25-06-2016 27-06-2016
763 MEP Final Finishes 13 days 11-02-2016 25-02-2016
764 Level 06 - Office 217.2 days 18-07-2015 02-07-2016
765 Masonry Works 43.2 days 18-07-2015 22-09-2015
766 Blockwork 18 days 18-07-2015 10-08-2015
767 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 10-08-2015 31-08-2015
768 Internal Plaster 18 days 31-08-2015 22-09-2015
769 Wet Areas 169 days 29-09-2015 01-07-2016
770 Wet Area Waterproofing 8 days 29-09-2015 07-10-2015
771 MEP 2nd fix High level 39 days 08-10-2015 21-11-2015
772 Wall Tiling 21 days 12-11-2015 05-12-2015
773 Floor Tiling 26 days 16-04-2016 19-05-2016
774 Install Doors & False Ceiling 16 days 19-05-2016 07-06-2016
775 Paint 18 days 19-05-2016 09-06-2016
776 MEP Final Fixes 18 days 26-05-2016 16-06-2016
777 Civil Final Fixes 13 days 16-06-2016 01-07-2016
778 Dry Areas 174 days 22-09-2015 02-07-2016
779 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 22-09-2015 13-11-2015
780 False Ceiling Suspension 26 days 21-10-2015 20-11-2015
781 MEP Dropworks to Ceilings 26 days 04-11-2015 04-12-2015
782 Install Doors & Windows 21 days 25-11-2015 19-12-2015
783 Fase Celing Boarding 26 days 15-12-2015 15-01-2016
784 Painting 26 days 16-01-2016 16-02-2016
785 Civil - Final Finishes 21 days 17-02-2016 11-03-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 29 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
786 MEP Service Rooms - MEP works 21 days 17-02-2016 11-03-2016
787 Final Paint, Clean & Snags 1 day 01-07-2016 02-07-2016
788 MEP Final Finishes 13 days 17-02-2016 02-03-2016
789 Level 07 - Office 209.8 days 05-08-2015 08-07-2016
790 Masonry Works 42.4 days 05-08-2015 07-10-2015
791 Blockwork 18 days 05-08-2015 25-08-2015
792 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 26-08-2015 16-09-2015
793 Internal Plaster 18 days 17-09-2015 07-10-2015
794 Wet Areas 166.6 days 08-10-2015 07-07-2016
795 Wet Area Waterproofing 8 days 08-10-2015 16-10-2015
796 MEP 2nd fix High level 39 days 17-10-2015 01-12-2015
797 Wall Tiling 21 days 19-11-2015 12-12-2015
798 Floor Tiling 26 days 23-04-2016 25-05-2016
799 Install Doors & False Ceiling 16 days 25-05-2016 13-06-2016
800 Paint 18 days 25-05-2016 15-06-2016
801 MEP Final Fixes 18 days 01-06-2016 22-06-2016
802 Civil Final Fixes 13 days 22-06-2016 07-07-2016
803 Dry Areas 167.4 days 08-10-2015 08-07-2016
804 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 08-10-2015 28-11-2015
805 False Ceiling Suspension 26 days 06-11-2015 05-12-2015
806 MEP Dropworks to Ceilings 26 days 20-11-2015 19-12-2015
807 Install Doors & Windows 21 days 11-12-2015 06-01-2016
808 Fase Celing Boarding 26 days 21-12-2015 21-01-2016
809 Painting 26 days 22-01-2016 22-02-2016
810 Civil - Final Finishes 21 days 23-02-2016 17-03-2016
811 MEP Service Rooms - MEP works 21 days 23-02-2016 17-03-2016
812 Final Paint, Clean & Snags 1 day 07-07-2016 08-07-2016
813 MEP Final Finishes 13 days 23-02-2016 08-03-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 30 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
814 Level 08 - Office 203.8 days 19-08-2015 14-07-2016
815 Masonry Works 42 days 19-08-2015 22-10-2015
816 Blockwork 18 days 19-08-2015 10-09-2015
817 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 10-09-2015 01-10-2015
818 Internal Plaster 18 days 01-10-2015 22-10-2015
819 Wet Areas 161 days 22-10-2015 13-07-2016
820 Wet Area Waterproofing 8 days 22-10-2015 31-10-2015
821 MEP 2nd fix High level 39 days 31-10-2015 16-12-2015
822 Wall Tiling 21 days 03-12-2015 29-12-2015
823 Floor Tiling 26 days 29-04-2016 31-05-2016
824 Install Doors & False Ceiling 16 days 31-05-2016 18-06-2016
825 Paint 18 days 31-05-2016 21-06-2016
826 MEP Final Fixes 18 days 07-06-2016 28-06-2016
827 Civil Final Fixes 13 days 28-06-2016 13-07-2016
828 Dry Areas 161.8 days 22-10-2015 14-07-2016
829 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 22-10-2015 14-12-2015
830 False Ceiling Suspension 26 days 20-11-2015 21-12-2015
831 MEP Dropworks to Ceilings 26 days 04-12-2015 06-01-2016
832 Install Doors & Windows 21 days 26-12-2015 21-01-2016
833 Fase Celing Boarding 26 days 06-01-2016 06-02-2016
834 Painting 26 days 06-02-2016 08-03-2016
835 Civil - Final Finishes 21 days 08-03-2016 01-04-2016
836 MEP Service Rooms - MEP works 21 days 08-03-2016 01-04-2016
837 Final Paint, Clean & Snags 1 day 13-07-2016 14-07-2016
838 MEP Final Finishes 13 days 08-03-2016 23-03-2016
839 Level 09 - Office 198.6 days 03-09-2015 20-07-2016
840 Masonry Works 41.6 days 03-09-2015 05-11-2015
841 Blockwork 18 days 03-09-2015 24-09-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 31 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
842 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 25-09-2015 15-10-2015
843 Internal Plaster 18 days 16-10-2015 05-11-2015
844 Wet Areas 156.2 days 06-11-2015 19-07-2016
845 Wet Area Waterproofing 8 days 06-11-2015 14-11-2015
846 MEP 2nd fix High level 39 days 16-11-2015 31-12-2015
847 Wall Tiling 21 days 18-12-2015 13-01-2016
848 Floor Tiling 26 days 06-05-2016 06-06-2016
849 Install Doors & False Ceiling 16 days 06-06-2016 24-06-2016
850 Paint 18 days 06-06-2016 27-06-2016
851 MEP Final Fixes 18 days 13-06-2016 04-07-2016
852 Civil Final Fixes 13 days 04-07-2016 19-07-2016
853 Dry Areas 157 days 06-11-2015 20-07-2016
854 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 06-11-2015 29-12-2015
855 False Ceiling Suspension 26 days 05-12-2015 06-01-2016
856 MEP Dropworks to Ceilings 26 days 19-12-2015 20-01-2016
857 Install Doors & Windows 21 days 12-01-2016 05-02-2016
858 Fase Celing Boarding 26 days 21-01-2016 20-02-2016
859 Painting 26 days 22-02-2016 22-03-2016
860 Civil - Final Finishes 21 days 23-03-2016 15-04-2016
861 MEP Service Rooms - MEP works 21 days 23-03-2016 15-04-2016
862 Final Paint, Clean & Snags 1 day 19-07-2016 20-07-2016
863 MEP Final Finishes 13 days 23-03-2016 06-04-2016
864 Level 10 - Office 191.8 days 18-09-2015 26-07-2016
865 Masonry Works 40.8 days 18-09-2015 20-11-2015
866 Blockwork 18 days 18-09-2015 09-10-2015
867 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 09-10-2015 30-10-2015
868 Internal Plaster 18 days 30-10-2015 20-11-2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 32 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
869 Wet Areas 150.2 days 20-11-2015 25-07-2016
870 Wet Area Waterproofing 8 days 20-11-2015 30-11-2015
871 MEP 2nd fix High level 39 days 30-11-2015 16-01-2016
872 Wall Tiling 21 days 04-01-2016 28-01-2016
873 Floor Tiling 26 days 12-05-2016 11-06-2016
874 Install Doors & False Ceiling 16 days 11-06-2016 30-06-2016
875 Paint 18 days 11-06-2016 02-07-2016
876 MEP Final Fixes 18 days 18-06-2016 09-07-2016
877 Civil Final Fixes 13 days 09-07-2016 25-07-2016
878 Dry Areas 151 days 20-11-2015 26-07-2016
879 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 20-11-2015 14-01-2016
880 False Ceiling Suspension 26 days 19-12-2015 21-01-2016
881 MEP Dropworks to Ceilings 26 days 05-01-2016 05-02-2016
882 Install Doors & Windows 21 days 26-01-2016 20-02-2016
883 Fase Celing Boarding 26 days 05-02-2016 07-03-2016
884 Painting 26 days 07-03-2016 06-04-2016
885 Civil - Final Finishes 21 days 06-04-2016 02-05-2016
886 MEP Service Rooms - MEP works 21 days 06-04-2016 02-05-2016
887 Final Paint, Clean & Snags 1 day 25-07-2016 26-07-2016
888 MEP Final Finishes 13 days 06-04-2016 22-04-2016
889 Level 11 - Office 186.4 days 03-10-2015 02-08-2016
890 Masonry Works 40.8 days 03-10-2015 04-12-2015
891 Blockwork 18 days 03-10-2015 23-10-2015
892 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 24-10-2015 13-11-2015
893 Internal Plaster 18 days 14-11-2015 04-12-2015
894 Wet Areas 145 days 05-12-2015 01-08-2016
895 Wet Area Waterproofing 8 days 05-12-2015 14-12-2015
896 MEP 2nd fix High level 39 days 15-12-2015 30-01-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 33 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
897 Wall Tiling 21 days 19-01-2016 12-02-2016
898 Floor Tiling 26 days 18-05-2016 17-06-2016
899 Install Doors & False Ceiling 16 days 17-06-2016 06-07-2016
900 Paint 18 days 17-06-2016 08-07-2016
901 MEP Final Fixes 18 days 24-06-2016 15-07-2016
902 Civil Final Fixes 13 days 15-07-2016 01-08-2016
903 Dry Areas 145.6 days 05-12-2015 02-08-2016
904 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 05-12-2015 28-01-2016
905 False Ceiling Suspension 26 days 06-01-2016 05-02-2016
906 MEP Dropworks to Ceilings 26 days 20-01-2016 19-02-2016
907 Install Doors & Windows 21 days 11-02-2016 05-03-2016
908 Fase Celing Boarding 26 days 20-02-2016 21-03-2016
909 Painting 26 days 22-03-2016 21-04-2016
910 Civil - Final Finishes 21 days 22-04-2016 17-05-2016
911 MEP Service Rooms - MEP works 21 days 22-04-2016 17-05-2016
912 Final Paint, Clean & Snags 1 day 01-08-2016 02-08-2016
913 MEP Final Finishes 13 days 22-04-2016 07-05-2016
914 Level 12 - Office 179.8 days 17-10-2015 08-08-2016
915 Masonry Works 40.8 days 17-10-2015 19-12-2015
916 Blockwork 18 days 17-10-2015 07-11-2015
917 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 07-11-2015 28-11-2015
918 Internal Plaster 18 days 28-11-2015 19-12-2015
919 Wet Areas 138.2 days 19-12-2015 06-08-2016
920 Wet Area Waterproofing 8 days 19-12-2015 30-12-2015
921 MEP 2nd fix High level 39 days 30-12-2015 16-02-2016
922 Wall Tiling 21 days 02-02-2016 27-02-2016
923 Floor Tiling 26 days 24-05-2016 23-06-2016
924 Install Doors & False Ceiling 16 days 23-06-2016 12-07-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 34 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
925 Paint 18 days 23-06-2016 14-07-2016
926 MEP Final Fixes 18 days 30-06-2016 21-07-2016
927 Civil Final Fixes 13 days 21-07-2016 06-08-2016
928 Dry Areas 139 days 19-12-2015 08-08-2016
929 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 19-12-2015 13-02-2016
930 False Ceiling Suspension 26 days 20-01-2016 20-02-2016
931 MEP Dropworks to Ceilings 26 days 03-02-2016 05-03-2016
932 Install Doors & Windows 21 days 25-02-2016 21-03-2016
933 Fase Celing Boarding 26 days 05-03-2016 05-04-2016
934 Painting 26 days 05-04-2016 07-05-2016
935 Civil - Final Finishes 21 days 07-05-2016 01-06-2016
936 MEP Service Rooms - MEP works 21 days 07-05-2016 01-06-2016
937 Final Paint, Clean & Snags 1 day 06-08-2016 08-08-2016
938 MEP Final Finishes 13 days 07-05-2016 23-05-2016
939 Level 13 - Office 174.6 days 03-11-2015 13-08-2016
940 Masonry Works 42.4 days 03-11-2015 06-01-2016
941 Blockwork 18 days 03-11-2015 23-11-2015
942 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 24-11-2015 14-12-2015
943 Internal Plaster 18 days 15-12-2015 06-01-2016
944 Wet Areas 131.4 days 07-01-2016 12-08-2016
945 Wet Area Waterproofing 8 days 07-01-2016 15-01-2016
946 MEP 2nd fix High level 39 days 16-01-2016 02-03-2016
947 Wall Tiling 21 days 19-02-2016 14-03-2016
948 Floor Tiling 26 days 30-05-2016 29-06-2016
949 Install Doors & False Ceiling 16 days 29-06-2016 18-07-2016
950 Paint 18 days 29-06-2016 20-07-2016
951 MEP Final Fixes 18 days 06-07-2016 27-07-2016
952 Civil Final Fixes 13 days 27-07-2016 12-08-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 35 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
953 Dry Areas 132.2 days 07-01-2016 13-08-2016
954 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 07-01-2016 29-02-2016
955 False Ceiling Suspension 26 days 06-02-2016 07-03-2016
956 MEP Dropworks to Ceilings 26 days 20-02-2016 21-03-2016
957 Install Doors & Windows 21 days 12-03-2016 05-04-2016
958 Fase Celing Boarding 26 days 22-03-2016 21-04-2016
959 Painting 26 days 22-04-2016 23-05-2016
960 Civil - Final Finishes 21 days 24-05-2016 16-06-2016
961 MEP Service Rooms - MEP works 21 days 24-05-2016 16-06-2016
962 Final Paint, Clean & Snags 1 day 12-08-2016 13-08-2016
963 MEP Final Finishes 13 days 24-05-2016 07-06-2016
964 Level 14 - Office 167.8 days 18-11-2015 19-08-2016
965 Masonry Works 41.6 days 18-11-2015 22-01-2016
966 Blockwork 18 days 18-11-2015 09-12-2015
967 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 09-12-2015 31-12-2015
968 Internal Plaster 18 days 31-12-2015 22-01-2016
969 Wet Areas 125.4 days 22-01-2016 18-08-2016
970 Wet Area Waterproofing 8 days 22-01-2016 01-02-2016
971 MEP 2nd fix High level 39 days 01-02-2016 18-03-2016
972 Wall Tiling 21 days 05-03-2016 30-03-2016
973 Floor Tiling 26 days 04-06-2016 05-07-2016
974 Install Doors & False Ceiling 16 days 05-07-2016 23-07-2016
975 Paint 18 days 05-07-2016 26-07-2016
976 MEP Final Fixes 18 days 12-07-2016 03-08-2016
977 Civil Final Fixes 13 days 03-08-2016 18-08-2016
978 Dry Areas 126.2 days 22-01-2016 19-08-2016
979 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 22-01-2016 16-03-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 36 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
980 False Ceiling Suspension 26 days 22-02-2016 23-03-2016
981 MEP Dropworks to Ceilings 26 days 07-03-2016 06-04-2016
982 Install Doors & Windows 21 days 28-03-2016 22-04-2016
983 Fase Celing Boarding 26 days 06-04-2016 09-05-2016
984 Painting 26 days 09-05-2016 08-06-2016
985 Civil - Final Finishes 21 days 08-06-2016 02-07-2016
986 MEP Service Rooms - MEP works 21 days 08-06-2016 02-07-2016
987 Final Paint, Clean & Snags 1 day 18-08-2016 19-08-2016
988 MEP Final Finishes 13 days 08-06-2016 23-06-2016
989 Level 15 - Office 161.8 days 04-12-2015 25-08-2016
990 Masonry Works 41.6 days 04-12-2015 08-02-2016
991 Blockwork 18 days 04-12-2015 24-12-2015
992 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 26-12-2015 16-01-2016
993 Internal Plaster 18 days 18-01-2016 08-02-2016
994 Wet Areas 119.4 days 09-02-2016 24-08-2016
995 Wet Area Waterproofing 8 days 09-02-2016 17-02-2016
996 MEP 2nd fix High level 39 days 18-02-2016 02-04-2016
997 Wall Tiling 21 days 22-03-2016 14-04-2016
998 Floor Tiling 26 days 10-06-2016 11-07-2016
999 Install Doors & False Ceiling 16 days 11-07-2016 30-07-2016
1000 Paint 18 days 11-07-2016 02-08-2016
1001 MEP Final Fixes 18 days 18-07-2016 09-08-2016
1002 Civil Final Fixes 13 days 09-08-2016 24-08-2016
1003 Dry Areas 120.2 days 09-02-2016 25-08-2016
1004 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 09-02-2016 31-03-2016
1005 False Ceiling Suspension 26 days 09-03-2016 07-04-2016
1006 MEP Dropworks to Ceilings 26 days 23-03-2016 22-04-2016
1007 Install Doors & Windows 21 days 13-04-2016 09-05-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 37 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
1008 Fase Celing Boarding 26 days 23-04-2016 24-05-2016
1009 Painting 26 days 25-05-2016 23-06-2016
1010 Civil - Final Finishes 21 days 24-06-2016 18-07-2016
1011 MEP Service Rooms - MEP works 21 days 24-06-2016 18-07-2016
1012 Final Paint, Clean & Snags 1 day 24-08-2016 25-08-2016
1013 MEP Final Finishes 13 days 24-06-2016 08-07-2016
1014 Level 16 - Office 155.8 days 18-12-2015 31-08-2016
1015 Masonry Works 41.6 days 18-12-2015 23-02-2016
1016 Blockwork 18 days 18-12-2015 11-01-2016
1017 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 11-01-2016 01-02-2016
1018 Internal Plaster 18 days 01-02-2016 23-02-2016
1019 Wet Areas 113.4 days 23-02-2016 30-08-2016
1020 Wet Area Waterproofing 8 days 23-02-2016 03-03-2016
1021 MEP 2nd fix High level 39 days 03-03-2016 19-04-2016
1022 Wall Tiling 21 days 05-04-2016 30-04-2016
1023 Floor Tiling 26 days 16-06-2016 16-07-2016
1024 Install Doors & False Ceiling 16 days 16-07-2016 05-08-2016
1025 Paint 18 days 16-07-2016 08-08-2016
1026 MEP Final Fixes 18 days 23-07-2016 15-08-2016
1027 Civil Final Fixes 13 days 15-08-2016 30-08-2016
1028 Dry Areas 114.2 days 23-02-2016 31-08-2016
1029 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)
45 days 23-02-2016 15-04-2016
1030 False Ceiling Suspension 26 days 23-03-2016 23-04-2016
1031 MEP Dropworks to Ceilings 26 days 06-04-2016 09-05-2016
1032 Install Doors & Windows 21 days 28-04-2016 24-05-2016
1033 Fase Celing Boarding 26 days 09-05-2016 08-06-2016
1034 Painting 26 days 08-06-2016 08-07-2016
1035 Civil - Final Finishes 21 days 08-07-2016 03-08-2016
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016
Task Critical Progress Update Summary Milestone
Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings
MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM
PS : 22-10-2013PF : 25-01-2017
MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14
Page 38 of 54
Project: MULTI STOREYED BUILDINGDate: 30-04-2014
-
ID Task Name Duration Start Finish
1036 MEP Service Rooms - MEP works 21 days 08-07-2016 03-08-2016
1037 Final Paint, Clean & Snags 1 day 30-08-2016 31-08-2016
1038 MEP Final Finishes 13 days 08-07-2016 23-07-2016
1039 Level 17 - Office 148.2 days 06-01-2016 06-09-2016
1040 Masonry Works 34.8 days 06-01-2016 29-02-2016
1041 Blockwork 18 days 06-01-2016 26-01-2016
1042 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)
18 days 18-01-2016 08-02-2016
1043 Internal Plaster 18 days 08-02-2016 29-02-2016
1044 Wet Areas 112.6 days 29-02-2016 05-09-2016
1045 Wet Area Waterproofing 8 days 29-02-2016 09-03-2016
1046 MEP 2nd fix High level 26 days 09-03-2016 08-04-2016
1047 Wall Tiling 18 days 14-04-2016 07-05-2016
1048 Floor Tiling 26 days 22-06-2016 22-07-2016
1049 Install Doors & False Ceiling 16 days 22-07-2016 11-08-2016
1050 Paint 18 days 22-07-2016 13-08-2016
1051 MEP Final Fixes 18 days 30-07-2016 20-08-2016
1052 Civil Final Fixes 13 days 20-08-2016 05-09-2016
1053 Dry Areas 123.8 days 13-02-2016 06-09-2016
1054 MEP 2nd Fix (Under Ceil