revised program on 30 apr 14

54
ID Task Name Duration Start Finish 0 MULTI STOREYED BUILDING, COLOMBO 747.2 days 22-10-2013 25-01-2017 1 PROJECT SUMMARY 747.2 days 22-10-2013 25-01-2017 2 Start of the Project 1 day 22-10-2013 22-10-2013 3 Final Handing Over 0 days 25-01-2017 25-01-2017 4 MOBILIZATION 203.2 days 28-10-2013 16-09-2014 5 Mobilization - Site Office 80 days 28-10-2013 15-01-2014 6 Mobilization - Staff & Workmen 96 days 28-10-2013 31-01-2014 7 Mobilization-Plant & Equipment 109 days 28-10-2013 13-02-2014 8 Erection of Tower Crane 45 days 09-07-2014 16-09-2014 9 PROCUREMENT (Major S/c only Shown) 611 days 10-02-2014 24-10-2016 10 DOMESTIC S/C 518 days 10-02-2014 04-06-2016 11 SHORING 12.8 days 10-02-2014 28-02-2014 12 Award of Workpackage 1 day 10-02-2014 10-02-2014 13 Design Submission & Approval 14 days 15-02-2014 28-02-2014 14 Mobilise at site 1 day 28-02-2014 28-02-2014 15 DEWATERING 11.2 days 12-02-2014 28-02-2014 16 Award of Workpackage 1 day 12-02-2014 12-02-2014 17 Design Submission & Approval 16 days 13-02-2014 28-02-2014 18 Mobilise at site 12 days 13-02-2014 24-02-2014 19 THERMAL & MOISTURE PROTECTION 50 days 19-05-2014 02-08-2014 20 Award of Workpackage 0 days 19-05-2014 19-05-2014 21 Shop Drawing Submission 5 days 27-06-2014 04-07-2014 22 Shop Drawing Approval 11 days 05-07-2014 23-07-2014 23 Material Sample Submission 10 days 27-06-2014 11-07-2014 24 Material Sample Approval 4 days 16-07-2014 21-07-2014 25 Procurement lead time 8 days 22-07-2014 02-08-2014 26 Delivery of Materials 0 days 02-08-2014 02-08-2014 27 FINISHES 339 days 17-09-2014 12-03-2016 28 WALL FINISHES 123 days 20-02-2015 14-09-2015 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 2014 2015 2016 Task Critical Progress Update Summary Milestone Client : Commissioner General ofLabour Department Consultant : Design Consortium ltd PMC : Department of Buildings MULTI STOREYED BUILDING, COLOMBO, SRI LANKA REVISED PROGRAM PS : 22-10-2013 PF : 25-01-2017 MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14 Page 1 of 54 Project: MULTI STOREYED BUILDING Date: 30-04-2014

Upload: lakshen-ktg

Post on 08-Sep-2015

4 views

Category:

Documents


0 download

DESCRIPTION

Site program

TRANSCRIPT

  • ID Task Name Duration Start Finish

    0 MULTI STOREYED BUILDING, COLOMBO 747.2 days 22-10-2013 25-01-2017

    1 PROJECT SUMMARY 747.2 days 22-10-2013 25-01-2017

    2 Start of the Project 1 day 22-10-2013 22-10-2013

    3 Final Handing Over 0 days 25-01-2017 25-01-2017

    4 MOBILIZATION 203.2 days 28-10-2013 16-09-2014

    5 Mobilization - Site Office 80 days 28-10-2013 15-01-2014

    6 Mobilization - Staff & Workmen 96 days 28-10-2013 31-01-2014

    7 Mobilization-Plant & Equipment 109 days 28-10-2013 13-02-2014

    8 Erection of Tower Crane 45 days 09-07-2014 16-09-2014

    9 PROCUREMENT (Major S/c only Shown) 611 days 10-02-2014 24-10-2016

    10 DOMESTIC S/C 518 days 10-02-2014 04-06-2016

    11 SHORING 12.8 days 10-02-2014 28-02-2014

    12 Award of Workpackage 1 day 10-02-2014 10-02-2014

    13 Design Submission & Approval 14 days 15-02-2014 28-02-2014

    14 Mobilise at site 1 day 28-02-2014 28-02-2014

    15 DEWATERING 11.2 days 12-02-2014 28-02-2014

    16 Award of Workpackage 1 day 12-02-2014 12-02-2014

    17 Design Submission & Approval 16 days 13-02-2014 28-02-2014

    18 Mobilise at site 12 days 13-02-2014 24-02-2014

    19 THERMAL & MOISTURE PROTECTION 50 days 19-05-2014 02-08-2014

    20 Award of Workpackage 0 days 19-05-2014 19-05-2014

    21 Shop Drawing Submission 5 days 27-06-2014 04-07-2014

    22 Shop Drawing Approval 11 days 05-07-2014 23-07-2014

    23 Material Sample Submission 10 days 27-06-2014 11-07-2014

    24 Material Sample Approval 4 days 16-07-2014 21-07-2014

    25 Procurement lead time 8 days 22-07-2014 02-08-2014

    26 Delivery of Materials 0 days 02-08-2014 02-08-2014

    27 FINISHES 339 days 17-09-2014 12-03-2016

    28 WALL FINISHES 123 days 20-02-2015 14-09-2015

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    100%

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 1 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    29 Award of Workpackage 0 days 20-02-2015 20-02-2015

    30 Shop Drawing Submission 28 days 14-03-2015 13-05-2015

    31 Shop Drawing Approval 28 days 14-05-2015 24-06-2015

    32 Material Sample Submission 28 days 14-03-2015 13-05-2015

    33 Material Sample Approval 28 days 14-05-2015 24-06-2015

    34 Procurement lead time 52 days 25-06-2015 11-09-2015

    35 Delivery of Materials 0 days 14-09-2015 14-09-2015

    36 CEILING FINISHES 85 days 24-10-2015 07-03-2016

    37 Award of Workpackage 0 days 24-10-2015 24-10-2015

    38 Shop Drawing Submission 11 days 16-11-2015 03-12-2015

    39 Shop Drawing Approval 11 days 17-02-2016 04-03-2016

    40 Material Sample Submission 11 days 16-11-2015 03-12-2015

    41 Material Sample Approval 11 days 03-12-2015 18-12-2015

    42 Procurement lead time 48 days 19-12-2015 04-03-2016

    43 Delivery of Materials 0 days 07-03-2016 07-03-2016

    44 FLOOR FINISHES 89 days 24-10-2015 12-03-2016

    45 Award of Workpackage 0 days 24-10-2015 24-10-2015

    46 Shop Drawing Submission 11 days 16-11-2015 03-12-2015

    47 Shop Drawing Approval 11 days 03-12-2015 18-12-2015

    48 Material Sample Submission 11 days 16-11-2015 03-12-2015

    49 Material Sample Approval 11 days 03-12-2015 18-12-2015

    50 Procurement lead time 52 days 19-12-2015 10-03-2016

    51 Delivery of Materials 0 days 12-03-2016 12-03-2016

    52 IRONMONGERIES 84 days 17-09-2014 26-01-2015

    53 Award of Workpackage 0 days 17-09-2014 17-09-2014

    54 Shop Drawing Submission 11 days 09-10-2014 25-10-2014

    55 Shop Drawing Approval 11 days 25-10-2014 12-11-2014

    56 Material Sample Submission 11 days 09-10-2014 25-10-2014

    57 Material Sample Approval 11 days 25-10-2014 12-11-2014

    58 Procurement lead time 48 days 12-11-2014 26-01-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 2 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    59 Delivery of Materials 0 days 26-01-2015 26-01-2015

    60 EQUIPMENT 108 days 25-05-2015 06-11-2015

    61 GARBAGE CHUTE 108 days 25-05-2015 06-11-2015

    62 Award of Workpackage 0 days 25-05-2015 25-05-2015

    63 Shop Drawing Submission 11 days 16-06-2015 03-07-2015

    64 Shop Drawing Approval 22 days 03-07-2015 05-08-2015

    65 Material Sample Submission 11 days 16-06-2015 03-07-2015

    66 Material Sample Approval 22 days 03-07-2015 05-08-2015

    67 Procurement lead time 60 days 05-08-2015 05-11-2015

    68 Delivery of Materials 0 days 06-11-2015 06-11-2015

    69 INTERNAL & EXTERNAL SIGNAGES 234 days 25-05-2015 04-06-2016

    70 Award of Workpackage 0 days 25-05-2015 25-05-2015

    71 Shop Drawing Submission 28 days 16-06-2015 28-07-2015

    72 Shop Drawing Approval 28 days 28-07-2015 09-09-2015

    73 Material Sample Submission 28 days 16-06-2015 28-07-2015

    74 Material Sample Approval 28 days 28-07-2015 09-09-2015

    75 Procurement lead time 104 days 09-09-2015 18-02-2016

    76 Delivery of Materials 0 days 04-06-2016 04-06-2016

    77 SANITARY WARES 193 days 02-07-2014 15-05-2015

    78 Award of Workpackage 0 days 02-07-2014 02-07-2014

    79 Material Sample Submission 28 days 28-07-2014 06-09-2014

    80 Material Sample Approval 15 days 02-09-2014 24-09-2014

    81 Procurement lead time 18 days 30-03-2015 15-05-2015

    82 Delivery of Materials 0 days 15-05-2015 15-05-2015

    83 Shop Drawing Submission 28 days 10-10-2014 22-11-2014

    84 Shop Drawing Approval 28 days 29-11-2014 13-01-2015

    85 NOMINATED SUBCONTRACTORS 598.2 days 01-03-2014 24-10-2016

    86 MEP WORKS 63.2 days 01-03-2014 20-06-2014

    87 MEP WORKS S/C 53.6 days 01-03-2014 05-06-2014

    88 Award of Workpackage 1 day 01-03-2014 01-03-2014 100%

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 3 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    89 Raft - Shop Drawing Submission 7 days 07-05-2014 17-05-2014

    90 Raft - Shop Drawing Approval 7 days 27-05-2014 05-06-2014

    91 S/c Mobilise at site 0 days 05-06-2014 05-06-2014

    92 CCTV, SMATV 27 days 03-05-2014 13-06-2014

    93 Nominate CCTV, MATV S/c 1 day 03-05-2014 05-05-2014

    94 Agreement with Nominated S/c 11 days 05-05-2014 21-05-2014

    95 S/C mobilise at site 11 days 28-05-2014 13-06-2014

    96 Air Conditioning & Mechanical Ventilation System 27 days 10-05-2014 20-06-2014

    97 Nominate Air Conditioning & Mechanical Ventilation System Contrcator

    1 day 10-05-2014 12-05-2014

    98 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014

    99 S/C mobilise at site 11 days 04-06-2014 20-06-2014

    100 Fire Protection and detection system 27 days 10-05-2014 20-06-2014

    101 Nominate Fire Protection and detection contractor 1 day 10-05-2014 12-05-2014

    102 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014

    103 S/C mobilise at site 11 days 04-06-2014 20-06-2014

    104 Installation of Generators 27 days 10-05-2014 20-06-2014

    105 Nominate Generators Contractor 1 day 10-05-2014 12-05-2014

    106 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014

    107 S/C mobilise at site 11 days 04-06-2014 20-06-2014

    108 PA, PABX SYSTEM 27 days 10-05-2014 20-06-2014

    109 Nominate PA, PABX S/c 1 day 10-05-2014 12-05-2014

    110 Agreement with Nominated S/c 11 days 12-05-2014 29-05-2014

    111 S/C mobilise at site 11 days 04-06-2014 20-06-2014

    112 ACCESS CONTROL SYSTEM 25 days 10-05-2014 18-06-2014

    113 Nominate Access Control System 1 day 10-05-2014 12-05-2014

    114 Agreement with Nominated S/c 9 days 12-05-2014 26-05-2014

    115 S/C mobilise at site 9 days 04-06-2014 18-06-2014

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 4 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    116 LIFTS 243 days 10-05-2014 06-06-2015

    117 Award of Workpackage 0 days 10-05-2014 10-05-2014

    118 Shop Drawing Submission 28 days 05-06-2014 18-07-2014

    119 Shop Drawing Approval 28 days 25-07-2014 05-09-2014

    120 Material Sample Submission 28 days 05-06-2014 18-07-2014

    121 Material Sample Approval 28 days 25-07-2014 05-09-2014

    122 Procurement lead time 160 days 12-09-2014 05-06-2015

    123 Delivery of Materials 1 day 05-06-2015 06-06-2015

    124 ALUMINIUM GLAZING & METAL WORKS 177 days 11-01-2016 24-10-2016

    125 Shop Drawing Submission 28 days 11-01-2016 24-02-2016

    126 Shop Drawing Approval 28 days 02-03-2016 29-04-2016

    127 Material Sample Submission 28 days 11-01-2016 24-02-2016

    128 Material Sample Approval 28 days 02-03-2016 29-04-2016

    129 Delivery of Materials 16 days 29-09-2016 24-10-2016

    130 Award of Workpackage 0 days 28-03-2016 28-03-2016

    131 EARTHWORK FOR LANDSCAPING WORKS 121 days 25-10-2014 19-05-2015

    132 Award of Workpackage 0 days 25-10-2014 25-10-2014

    133 Shop Drawing Submission 14 days 19-11-2014 11-12-2014

    134 Shop Drawing Approval 14 days 13-12-2014 06-01-2015

    135 Material Sample Submission 14 days 19-11-2014 11-12-2014

    136 Material Sample Approval 14 days 13-12-2014 06-01-2015

    137 Delivery of Materials 0 days 19-05-2015 19-05-2015

    138 Co-Ordination Drawings and Identification of provision to keep with structure

    22 days 29-05-2014 01-07-2014

    139 Co-Ordination Drawings 20 days 29-05-2014 28-06-2014

    140 Identification of MEP provisions to keep with structure 20 days 31-05-2014 01-07-2014

    141 CONSTRUCTION 725.2 days 22-11-2013 25-01-2017

    142 Ground Breaking Ceromony 1 day 22-11-2013 23-11-2013

    143 SHORING, DEWATERING & EXCAVATION 176.8 days 05-12-2013 16-09-2014

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 5 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    144 Excavation, Dewatering and shoring work (ref Method Statement)

    176.8 days 05-12-2013 16-09-2014

    145 Excavation up to -6m level grid between (C-K) (1-6) ref: Method Statement & Dra SPS/SD/EX/001

    83.2 days 05-12-2013 09-04-2014

    146 Grouting Work for Contiguous piles 40 days 01-03-2014 16-05-2014

    147 Capping Beam 20 days 07-05-2014 06-06-2014

    148 Monitoring of defection of earth retaining system, Building monitoring

    75 days 01-03-2014 08-07-2014

    149 Supporting to Contingeous Piles , Erection of Whaler and King Post ref: Method Statement & Dra SPS/SD/EX/001

    45 days 10-03-2014 02-06-2014

    150 12 m permanent Sheet Pilling alog grid 6 between (A-G) and provide whealer

    35 days 20-03-2014 28-05-2014

    151 Step 1 :Excavation -3m to -6m between grid (C-K)/(1-6) ref: Method Statement & Dra SPS/SD/EX/002

    14 days 01-04-2014 08-05-2014

    152 Sheet piles -6m to -18 m in lift core area ref: Method Statement & Dra SPS/SD/EX/003

    10 days 08-05-2014 23-05-2014

    153 Supporting arrangement with using sheer walls 3 days 02-09-2014 06-09-2014

    154 Removal of King posts 2 days 05-09-2014 09-09-2014

    155 Step 2 :Balance Excavation up to -6m 5 days 09-09-2014 16-09-2014

    156 Sheet Pilling Work alog grid A in betn ( 1-6) and along 1 in betn (A-C) with keeping provision to earth moving

    35 days 11-03-2014 19-05-2014

    157 FOUNDATION/ SUBSTRUCTURE 173.6 days 04-04-2014 12-01-2015

    158 Level -12000 to -5975 Lift Core/ Sheer Walls 46 days 24-05-2014 02-08-2014

    159 Excavation in lift core area 8 days 24-05-2014 04-06-2014

    160 Pile Hacking 8 days 30-05-2014 10-06-2014

    161 Pile Testing 3 days 07-06-2014 13-06-2014

    162 High Strength Concrete Grouting on top of pile caps 4 days 07-06-2014 14-06-2014

    100%

    25%

    70%

    10%

    10%

    20%

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 6 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    163 Leveling and Compaction of bottom of basement slab/pile caps

    2 days 13-06-2014 16-06-2014

    164 Screed Concrete 2 days 16-06-2014 19-06-2014

    165 200x 200 Tie Beam 6 days 19-06-2014 27-06-2014

    166 200tk Hollow Block Work 10 days 21-06-2014 07-07-2014

    167 Waterproofing for Side walls 8 days 01-07-2014 14-07-2014

    168 Pile Cap PC05 Fm/wk, R/f, Concrete works 10 days 05-07-2014 21-07-2014

    169 Strom water tank walls/ Lift well 4 days 21-07-2014 26-07-2014

    170 Waterproofing and Testing 4 days 26-07-2014 02-08-2014

    171 Basement 2 Level -5975 to Basement 1 Level -2750 169.6 days 04-04-2014 06-01-2015

    172 Lift Core/ Sheer Walls 21 days 02-08-2014 02-09-2014

    173 Slab Fm wk, r/f, Concrete @ -5975 7 days 02-08-2014 13-08-2014

    174 Lift Core sheer walls up to -2750 7 days 13-08-2014 22-08-2014

    175 Staircases - Structural Works 7 days 23-08-2014 02-09-2014

    176 Grid (G-K)/ (1-6) 169.6 days 04-04-2014 06-01-2015

    177 (G-K)/(2-5) 83 days 04-04-2014 25-08-2014

    178 Pile Hacking 45 days 04-04-2014 28-06-2014

    179 Pile Testing 25 days 09-04-2014 30-06-2014

    180 High Strength Concrete Grouting on top of pile caps

    20 days 03-06-2014 02-07-2014

    181 Leveling and Compaction of bottom of basement slab/pile caps

    20 days 05-06-2014 05-07-2014

    182 Screed Concrete 15 days 21-06-2014 14-07-2014

    183 Pile Caps and Basement 2 Form work, R/f Concrete

    40 days 25-06-2014 25-08-2014

    184 (G-K)/(1-3)//(G-K)/(4-6) 31 days 06-08-2014 20-09-2014

    185 Pile Hacking 30 days 06-08-2014 19-09-2014

    186 Pile Testing 14 days 30-08-2014 20-09-2014

    20%

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 7 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    187 High Strength Concrete Grouting on top of pile caps 14 days 01-09-2014 22-09-2014

    188 Leveling and Compaction of bottom of basement slab/pile caps

    4 days 19-09-2014 25-09-2014

    189 Screed Concrete 10 days 13-09-2014 27-09-2014

    190 Pile Caps Form work, R/f Concrete 20 days 17-09-2014 16-10-2014

    191 Basement 2 Slab Fm Wk, R/F wk, Concrete Wk 25 days 24-09-2014 01-11-2014

    192 Columns up to -2750 beam bottom 6 days 01-11-2014 11-11-2014

    193 Ramps and Landing up to -5.375 14 days 01-11-2014 22-11-2014

    194 Ramps and Landing up to -3.375 14 days 15-12-2014 06-01-2015

    195 Retaining Walls 25 days 21-10-2014 28-11-2014

    196 Grid (A-G (1-6) 62 days 04-09-2014 09-12-2014

    197 Excavation & Dewatering associated Works 8 days 06-09-2014 19-09-2014

    198 Pile Hacking 15 days 04-09-2014 26-09-2014

    199 Pile Testing 15 days 06-09-2014 30-09-2014

    200 High Strength Concrete Grouting on top of pile caps 10 days 18-09-2014 02-10-2014

    201 Leveling and Compaction of bottom of basement slab/pile caps

    10 days 20-09-2014 06-10-2014

    202 Screed Concrete 10 days 29-09-2014 14-10-2014

    203 Pile Caps Form work, R/f Concrete 20 days 01-10-2014 01-11-2014

    204 Basement 2 Slab Fm Wk, R/F wk, Concrete Wk 20 days 17-10-2014 17-11-2014

    205 Columns up tp -2750 beam bottom level 14 days 18-11-2014 09-12-2014

    206 Retaining Walls 14 days 18-11-2014 09-12-2014

    207 Basement 1 Level -2750 to +Ground Floor +0.45 92 days 23-08-2014 12-01-2015

    208 Lift Core/ Sheer Walls 21 days 23-08-2014 24-09-2014

    209 Slab @ -2750 7 days 23-08-2014 02-09-2014

    210 Lift Core sheer walls up to +0.45 7 days 02-09-2014 13-09-2014

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 8 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    211 Staircases - Structural Works 7 days 13-09-2014 24-09-2014

    212 Grid (G-K)/ (1-6) 28 days 29-11-2014 12-01-2015

    213 Basement 1 Slab 10 days 29-11-2014 15-12-2014

    214 Columns 8 days 15-12-2014 27-12-2014

    215 Ramps and Landing up to -2.175 18 days 15-12-2014 12-01-2015

    216 Ramps and Landing up to +0.45 18 days 15-12-2014 12-01-2015

    217 Retaining Walls 10 days 15-12-2014 30-12-2014

    218 Grid (A-G (1-6) 20 days 05-12-2014 06-01-2015

    219 Basement 1 Slab 10 days 05-12-2014 20-12-2014

    220 Columns up to +0.45 beam bottom level 8 days 20-12-2014 02-01-2015

    221 Retaining Walls 10 days 20-12-2014 06-01-2015

    222 SUPERSTRUCTURE (Ground Floor to Roof) 435 days 13-09-2014 18-08-2016

    223 Ground Level +0.45 to Level 1 +3.675 114 days 13-09-2014 10-03-2015

    224 Lift Core/ Sheer Walls 25 days 13-09-2014 21-10-2014

    225 Slab @ +0.45 7 days 13-09-2014 24-09-2014

    226 Lift Core sheer walls up to +3.675 10 days 24-09-2014 09-10-2014

    227 Staircases - Structural Works 10 days 06-10-2014 21-10-2014

    228 Grid (G-K)/ (1-6) 44 days 31-12-2014 10-03-2015

    229 Ground Floor Slab at +0.45 8 days 31-12-2014 12-01-2015

    230 Columns up to Level 1 +3.675 Beam Bottom Level 6 days 13-01-2015 22-01-2015

    231 Ramps and Landing up to -2.175 18 days 13-01-2015 11-02-2015

    232 Ramps and Landing up to +0.45 18 days 11-02-2015 10-03-2015

    233 Retaining Walls 15 days 13-01-2015 06-02-2015

    234 Grid (A-G (1-6) 24 days 07-01-2015 13-02-2015

    235 Ground Floor Slab at +0.45 9 days 07-01-2015 21-01-2015

    236 Columns up to Level 1 +5.60 Beam Bottom Level 6 days 21-01-2015 29-01-2015

    237 Retaining Walls 15 days 21-01-2015 13-02-2015

    238 Level 1 +3.675 to Level 2 +7.20 101 days 09-10-2014 16-03-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 9 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    239 Lift Core/ Sheer Walls 32 days 09-10-2014 27-11-2014

    240 Slab at Level 1 +3.675 8 days 09-10-2014 21-10-2014

    241 Lift Core sheer walls up to Level +5.60 8 days 21-10-2014 03-11-2014

    242 Slab at Level 1 +5.60 8 days 03-11-2014 15-11-2014

    243 Staircase up to Level 1 +5.60 8 days 03-11-2014 15-11-2014

    244 Lift Core sheer walls up to Level +7.20 8 days 15-11-2014 27-11-2014

    245 Grid (F-K)/ (1-6) 11 days 22-01-2015 10-02-2015

    246 Level 1 Slab at +3.675 6 days 22-01-2015 30-01-2015

    247 Columns up to Level 2 +7.2 Beam Bottom Level 5 days 31-01-2015 10-02-2015

    248 Grid (A-D (1-6) 10 days 29-01-2015 16-02-2015

    249 Level 1 Slab at +5.60 6 days 29-01-2015 10-02-2015

    250 Columns up to Level 2 +8.80 Beam Bottom Level 4 days 10-02-2015 16-02-2015

    251 Ramp (F-D) /(4-5) 14 days 31-01-2015 23-02-2015

    252 Ramp +3.675 to +5.60 14 days 31-01-2015 23-02-2015

    253 Ramp (D-G) /(2-3) 14 days 23-02-2015 16-03-2015

    254 Ramp +5.60 to +7.20 14 days 23-02-2015 16-03-2015

    255 Level 2 +7.2 to Level 3 +10.40 80 days 27-11-2014 01-04-2015

    256 Lift Core/ Sheer Walls 32 days 27-11-2014 17-01-2015

    257 Slab at Level 2 +7.2 8 days 27-11-2014 10-12-2014

    258 Lift Core sheer walls up to Level +8.80 8 days 10-12-2014 22-12-2014

    259 Slab at Level 2 +8.80 8 days 22-12-2014 03-01-2015

    260 Staircase up to Level 2 +8.80 8 days 22-12-2014 03-01-2015

    261 Lift Core sheer walls up to Level +10.40 8 days 03-01-2015 17-01-2015

    262 Grid (F-K)/ (1-6) 11 days 10-02-2015 25-02-2015

    263 Level 2 Slab at +7.2 6 days 10-02-2015 18-02-2015

    264 Columns up to Level 3 +10.40 beam bottom 5 days 18-02-2015 25-02-2015

    265 Grid (A-D (1-6) 10 days 16-02-2015 02-03-2015

    266 Level 2 Slab at +8.80 6 days 16-02-2015 24-02-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 10 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    267 Columns up to Level 3 +12.00 beam bottom 4 days 24-02-2015 02-03-2015

    268 Ramp (F-D) /(4-5) 14 days 18-02-2015 12-03-2015

    269 Ramp +7.20 to +8.80 14 days 18-02-2015 12-03-2015

    270 Ramp (D-G) /(2-3) 14 days 12-03-2015 01-04-2015

    271 Ramp +8.80 to + 10.40 14 days 12-03-2015 01-04-2015

    272 Level 3 10.40 to Level 3 Mezzanine Floor at +13.15 45 days 17-01-2015 27-03-2015

    273 Lift Core/ Sheer Walls 32 days 17-01-2015 09-03-2015

    274 Slab at Level 3 at +10.40 8 days 17-01-2015 29-01-2015

    275 Lift Core sheer walls up to Level +12.00 8 days 29-01-2015 12-02-2015

    276 Slab at Level 3 +12.00 8 days 12-02-2015 24-02-2015

    277 Staircase up to Level 3 +12.00 8 days 12-02-2015 24-02-2015

    278 Lift Core sheer walls up to Level +13.15 8 days 24-02-2015 09-03-2015

    279 Grid (F-K)/ (1-6) 11 days 26-02-2015 14-03-2015

    280 Level 3 Floor Slab at +10.40 6 days 26-02-2015 07-03-2015

    281 Columns up to Level 3 Mezzanine Floor +13.15 beambottom

    5 days 07-03-2015 14-03-2015

    282 Grid (A-D (1-6) 15 days 02-03-2015 25-03-2015

    283 Level 2 Slab at +12.00 9 days 02-03-2015 16-03-2015

    284 Columns up to Level 4 +16.50 beam bottom 6 days 17-03-2015 25-03-2015

    285 Ramp (F-D) /(4-5) 14 days 07-03-2015 27-03-2015

    286 Ramp +7.20 to +8.80 14 days 07-03-2015 27-03-2015

    287 Level 3 Mezzanine Floor at +13.15 to Level 4 16 days 09-03-2015 01-04-2015

    288 Lift Core/ Sheer Walls 16 days 09-03-2015 01-04-2015

    289 Slab at Level 3 at +13.15 8 days 09-03-2015 20-03-2015

    290 Lift Core sheer walls up to Level 4 8 days 20-03-2015 01-04-2015

    291 Staircase up to Level 4 8 days 20-03-2015 01-04-2015

    292 Grid (F-K)/ (1-6) 11 days 14-03-2015 31-03-2015

    293 Level 3 Mezzanine Floor Slab at +13.15 6 days 14-03-2015 24-03-2015

    294 Columns up to Level 3 +10.40 beam bottom 5 days 24-03-2015 31-03-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 11 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    295 Level 04 Office Floor +20.4 16 days 30-03-2015 12-05-2015

    296 Slab Form work 6 days 30-03-2015 08-04-2015

    297 Slab Reinforcement work 6 days 04-04-2015 29-04-2015

    298 Slab M& E Works 4 days 08-04-2015 30-04-2015

    299 Slab Concrete -1 st Pour 1 day 28-04-2015 29-04-2015

    300 Slab Concrete- Final Pour 1 day 30-04-2015 04-05-2015

    301 Core Walls R/F Work 8 days 01-04-2015 30-04-2015

    302 Core Walls Formwork 6 days 07-04-2015 04-05-2015

    303 Core Wall Conctete 4 days 28-04-2015 06-05-2015

    304 Columns F/W, R/F Concrete and associated Works 6 days 30-04-2015 12-05-2015

    305 Level 05 Office Floor +24.3 17 days 06-05-2015 30-05-2015

    306 Slab Form work 6 days 08-05-2015 18-05-2015

    307 Slab Reinforcement work 6 days 11-05-2015 19-05-2015

    308 Slab M& E Works 4 days 14-05-2015 20-05-2015

    309 Slab Concrete -1 st Pour 1 day 18-05-2015 19-05-2015

    310 Slab Concrete- Final Pour 1 day 20-05-2015 21-05-2015

    311 Core Walls R/F Work 8 days 06-05-2015 18-05-2015

    312 Core Walls Formwork 6 days 11-05-2015 19-05-2015

    313 Core Wall Conctete 4 days 14-05-2015 20-05-2015

    314 Columns F/W, R/F Concrete and associated Works 6 days 22-05-2015 30-05-2015

    315 Level 06 Office Floor +28.2 17 days 20-05-2015 15-06-2015

    316 Slab Form work 6 days 26-05-2015 05-06-2015

    317 Slab Reinforcement work 6 days 28-05-2015 06-06-2015

    318 Slab M& E Works 4 days 01-06-2015 08-06-2015

    319 Slab Concrete -1 st Pour 1 day 05-06-2015 06-06-2015

    320 Slab Concrete- Final Pour 1 day 08-06-2015 09-06-2015

    321 Core Walls R/F Work 8 days 20-05-2015 01-06-2015

    322 Core Walls Formwork 6 days 25-05-2015 03-06-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 12 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    323 Core Wall Conctete 4 days 29-05-2015 05-06-2015

    324 Columns F/W, R/F Concrete and associated Works 6 days 06-06-2015 15-06-2015

    325 Level 07 Office Floor +32.1 17 days 05-06-2015 30-06-2015

    326 Slab Form work 6 days 11-06-2015 19-06-2015

    327 Slab Reinforcement work 6 days 12-06-2015 20-06-2015

    328 Slab M& E Works 4 days 17-06-2015 23-06-2015

    329 Slab Concrete -1 st Pour 1 day 19-06-2015 20-06-2015

    330 Slab Concrete- Final Pour 1 day 23-06-2015 24-06-2015

    331 Core Walls R/F Work 8 days 05-06-2015 17-06-2015

    332 Core Walls Formwork 6 days 10-06-2015 18-06-2015

    333 Core Wall Conctete 4 days 13-06-2015 19-06-2015

    334 Columns F/W, R/F Concrete and associated Works 6 days 22-06-2015 30-06-2015

    335 Level 08 Office Floor +36 17 days 19-06-2015 15-07-2015

    336 Slab Form work 6 days 25-06-2015 06-07-2015

    337 Slab Reinforcement work 6 days 27-06-2015 07-07-2015

    338 Slab M& E Works 4 days 01-07-2015 08-07-2015

    339 Slab Concrete -1 st Pour 1 day 06-07-2015 07-07-2015

    340 Slab Concrete- Final Pour 1 day 08-07-2015 09-07-2015

    341 Core Walls R/F Work 8 days 19-06-2015 01-07-2015

    342 Core Walls Formwork 6 days 24-06-2015 03-07-2015

    343 Core Wall Conctete 4 days 29-06-2015 06-07-2015

    344 Columns F/W, R/F Concrete and associated Works 6 days 07-07-2015 15-07-2015

    345 Level 09 Office Floor +39.9 17 days 06-07-2015 31-07-2015

    346 Slab Form work 6 days 11-07-2015 20-07-2015

    347 Slab Reinforcement work 6 days 13-07-2015 21-07-2015

    348 Slab M& E Works 4 days 17-07-2015 23-07-2015

    349 Slab Concrete -1 st Pour 1 day 20-07-2015 21-07-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 13 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    350 Slab Concrete- Final Pour 1 day 23-07-2015 24-07-2015

    351 Core Walls R/F Work 8 days 06-07-2015 17-07-2015

    352 Core Walls Formwork 6 days 10-07-2015 18-07-2015

    353 Core Wall Conctete 4 days 14-07-2015 20-07-2015

    354 Columns F/W, R/F Concrete and associated Works 6 days 22-07-2015 31-07-2015

    355 Level 10 Office Floor +43.8 17 days 20-07-2015 14-08-2015

    356 Slab Form work 6 days 25-07-2015 05-08-2015

    357 Slab Reinforcement work 6 days 28-07-2015 06-08-2015

    358 Slab M& E Works 4 days 01-08-2015 07-08-2015

    359 Slab Concrete -1 st Pour 1 day 05-08-2015 06-08-2015

    360 Slab Concrete- Final Pour 1 day 07-08-2015 08-08-2015

    361 Core Walls R/F Work 8 days 20-07-2015 01-08-2015

    362 Core Walls Formwork 6 days 24-07-2015 03-08-2015

    363 Core Wall Conctete 4 days 30-07-2015 05-08-2015

    364 Columns F/W, R/F Concrete and associated Works 6 days 06-08-2015 14-08-2015

    365 Level 11 Office Floor +47.7 17 days 05-08-2015 29-08-2015

    366 Slab Form work 6 days 11-08-2015 19-08-2015

    367 Slab Reinforcement work 6 days 12-08-2015 20-08-2015

    368 Slab M& E Works 4 days 17-08-2015 22-08-2015

    369 Slab Concrete -1 st Pour 1 day 19-08-2015 20-08-2015

    370 Slab Concrete- Final Pour 1 day 22-08-2015 24-08-2015

    371 Core Walls R/F Work 8 days 05-08-2015 17-08-2015

    372 Core Walls Formwork 6 days 10-08-2015 18-08-2015

    373 Core Wall Conctete 4 days 13-08-2015 19-08-2015

    374 Columns F/W, R/F Concrete and associated Works 6 days 21-08-2015 29-08-2015

    375 Level 12 Office Floor +51.6 17 days 19-08-2015 14-09-2015

    376 Slab Form work 6 days 25-08-2015 04-09-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 14 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    377 Slab Reinforcement work 6 days 27-08-2015 05-09-2015

    378 Slab M& E Works 4 days 31-08-2015 07-09-2015

    379 Slab Concrete -1 st Pour 1 day 04-09-2015 05-09-2015

    380 Slab Concrete- Final Pour 1 day 07-09-2015 08-09-2015

    381 Core Walls R/F Work 8 days 19-08-2015 31-08-2015

    382 Core Walls Formwork 6 days 24-08-2015 01-09-2015

    383 Core Wall Conctete 4 days 28-08-2015 04-09-2015

    384 Columns F/W, R/F Concrete and associated Works 6 days 05-09-2015 14-09-2015

    385 Level 13 Office Floor +55.53 17 days 04-09-2015 29-09-2015

    386 Slab Form work 6 days 10-09-2015 18-09-2015

    387 Slab Reinforcement work 6 days 11-09-2015 19-09-2015

    388 Slab M& E Works 4 days 16-09-2015 22-09-2015

    389 Slab Concrete -1 st Pour 1 day 18-09-2015 19-09-2015

    390 Slab Concrete- Final Pour 1 day 22-09-2015 23-09-2015

    391 Core Walls R/F Work 8 days 04-09-2015 16-09-2015

    392 Core Walls Formwork 6 days 09-09-2015 17-09-2015

    393 Core Wall Conctete 4 days 12-09-2015 18-09-2015

    394 Columns F/W, R/F Concrete and associated Works 6 days 21-09-2015 29-09-2015

    395 Level 14 Office Floor +59.4 17 days 18-09-2015 14-10-2015

    396 Slab Form work 6 days 24-09-2015 05-10-2015

    397 Slab Reinforcement work 6 days 26-09-2015 06-10-2015

    398 Slab M& E Works 4 days 30-09-2015 07-10-2015

    399 Slab Concrete -1 st Pour 1 day 05-10-2015 06-10-2015

    400 Slab Concrete- Final Pour 1 day 07-10-2015 08-10-2015

    401 Core Walls R/F Work 8 days 18-09-2015 30-09-2015

    402 Core Walls Formwork 6 days 23-09-2015 01-10-2015

    403 Core Wall Conctete 4 days 28-09-2015 05-10-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 15 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    404 Columns F/W, R/F Concrete and associated Works 6 days 06-10-2015 14-10-2015

    405 Level 15 Office Floor +63.3 17 days 05-10-2015 30-10-2015

    406 Slab Form work 6 days 10-10-2015 19-10-2015

    407 Slab Reinforcement work 6 days 12-10-2015 20-10-2015

    408 Slab M& E Works 4 days 16-10-2015 23-10-2015

    409 Slab Concrete -1 st Pour 1 day 19-10-2015 20-10-2015

    410 Slab Concrete- Final Pour 1 day 23-10-2015 24-10-2015

    411 Core Walls R/F Work 8 days 05-10-2015 16-10-2015

    412 Core Walls Formwork 6 days 09-10-2015 17-10-2015

    413 Core Wall Conctete 4 days 13-10-2015 19-10-2015

    414 Columns F/W, R/F Concrete and associated Works 6 days 21-10-2015 30-10-2015

    415 Level 16 Office Floor +67.2 17 days 19-10-2015 14-11-2015

    416 Slab Form work 6 days 26-10-2015 05-11-2015

    417 Slab Reinforcement work 6 days 28-10-2015 06-11-2015

    418 Slab M& E Works 4 days 31-10-2015 07-11-2015

    419 Slab Concrete -1 st Pour 1 day 05-11-2015 06-11-2015

    420 Slab Concrete- Final Pour 1 day 07-11-2015 09-11-2015

    421 Core Walls R/F Work 8 days 19-10-2015 31-10-2015

    422 Core Walls Formwork 6 days 26-10-2015 05-11-2015

    423 Core Wall Conctete 4 days 30-10-2015 06-11-2015

    424 Columns F/W, R/F Concrete and associated Works 6 days 06-11-2015 14-11-2015

    425 Level 17 Office Floor +71.1 16 days 06-11-2015 30-11-2015

    426 Slab Form work 6 days 11-11-2015 19-11-2015

    427 Slab Reinforcement work 6 days 12-11-2015 20-11-2015

    428 Slab M& E Works 4 days 17-11-2015 23-11-2015

    429 Slab Concrete -1 st Pour 1 day 19-11-2015 20-11-2015

    430 Slab Concrete- Final Pour 1 day 23-11-2015 24-11-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 16 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    431 Core Walls R/F Work 8 days 06-11-2015 18-11-2015

    432 Core Walls Formwork 6 days 11-11-2015 19-11-2015

    433 Core Wall Conctete 4 days 16-11-2015 20-11-2015

    434 Columns F/W, R/F Concrete and associated Works 6 days 21-11-2015 30-11-2015

    435 Level 18 Office Floor +75 16 days 21-11-2015 15-12-2015

    436 Slab Form work 6 days 25-11-2015 05-12-2015

    437 Slab Reinforcement work 6 days 27-11-2015 07-12-2015

    438 Slab M& E Works 4 days 01-12-2015 08-12-2015

    439 Slab Concrete -1 st Pour 1 day 05-12-2015 07-12-2015

    440 Slab Concrete- Final Pour 1 day 08-12-2015 09-12-2015

    441 Core Walls R/F Work 8 days 21-11-2015 03-12-2015

    442 Core Walls Formwork 6 days 25-11-2015 05-12-2015

    443 Core Wall Conctete 4 days 30-11-2015 07-12-2015

    444 Columns F/W, R/F Concrete and associated Works 6 days 07-12-2015 15-12-2015

    445 Level 19 Office Floor +78.9 16 days 07-12-2015 31-12-2015

    446 Slab Form work 6 days 11-12-2015 19-12-2015

    447 Slab Reinforcement work 6 days 12-12-2015 21-12-2015

    448 Slab M& E Works 4 days 17-12-2015 23-12-2015

    449 Slab Concrete -1 st Pour 1 day 19-12-2015 21-12-2015

    450 Slab Concrete- Final Pour 1 day 23-12-2015 24-12-2015

    451 Core Walls R/F Work 8 days 07-12-2015 18-12-2015

    452 Core Walls Formwork 6 days 11-12-2015 19-12-2015

    453 Core Wall Conctete 4 days 16-12-2015 21-12-2015

    454 Columns F/W, R/F Concrete and associated Works 6 days 22-12-2015 31-12-2015

    455 Level 20 Office Floor +82.8 18 days 22-12-2015 20-01-2016

    456 Slab Form work 6 days 26-12-2015 06-01-2016

    457 Slab Reinforcement work 6 days 31-12-2015 09-01-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 17 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    458 Slab M & E Works 4 days 06-01-2016 12-01-2016

    459 Slab Concrete -1 st Pour 1 day 08-01-2016 09-01-2016

    460 Slab Concrete- Final Pour 1 day 12-01-2016 13-01-2016

    461 Core Walls R/F Work 8 days 22-12-2015 02-01-2016

    462 Core Walls Formwork 6 days 26-12-2015 06-01-2016

    463 Core Wall Conctete 4 days 31-12-2015 07-01-2016

    464 Columns F/W, R/F Concrete and associated Works 6 days 11-01-2016 20-01-2016

    465 Level 21 Office Floor +86.7 18 days 07-01-2016 05-02-2016

    466 Slab Form work 6 days 15-01-2016 25-01-2016

    467 Slab Reinforcement work 6 days 18-01-2016 26-01-2016

    468 Slab M& E Works 4 days 21-01-2016 27-01-2016

    469 Slab Concrete -1 st Pour 1 day 25-01-2016 26-01-2016

    470 Slab Concrete- Final Pour 1 day 27-01-2016 28-01-2016

    471 Core Walls R/F Work 8 days 07-01-2016 20-01-2016

    472 Core Walls Formwork 6 days 12-01-2016 21-01-2016

    473 Core Wall Conctete 4 days 18-01-2016 22-01-2016

    474 Columns F/W, R/F Concrete and associated Works 6 days 26-01-2016 05-02-2016

    475 Level 22 Office Floor +90.6 18 days 23-01-2016 20-02-2016

    476 Slab Form work 6 days 30-01-2016 10-02-2016

    477 Slab Reinforcement work 6 days 01-02-2016 11-02-2016

    478 Slab M& E Works 4 days 08-02-2016 13-02-2016

    479 Slab Concrete -1 st Pour 1 day 10-02-2016 11-02-2016

    480 Slab Concrete- Final Pour 1 day 13-02-2016 15-02-2016

    481 Core Walls R/F Work 8 days 23-01-2016 05-02-2016

    482 Core Walls Formwork 6 days 27-01-2016 08-02-2016

    483 Core Wall Conctete 4 days 01-02-2016 09-02-2016

    484 Columns F/W, R/F Concrete and associated Works 6 days 12-02-2016 20-02-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 18 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    485 Level 23 Office Floor +94.5 18 days 09-02-2016 07-03-2016

    486 Slab Form work 6 days 16-02-2016 25-02-2016

    487 Slab Reinforcement work 6 days 18-02-2016 26-02-2016

    488 Slab M& E Works 4 days 22-02-2016 27-02-2016

    489 Slab Concrete -1 st Pour 1 day 25-02-2016 26-02-2016

    490 Slab Concrete- Final Pour 1 day 27-02-2016 29-02-2016

    491 Core Walls R/F Work 8 days 09-02-2016 20-02-2016

    492 Core Walls Formwork 6 days 13-02-2016 22-02-2016

    493 Core Wall Conctete 4 days 18-02-2016 23-02-2016

    494 Columns F/W, R/F Concrete and associated Works 6 days 26-02-2016 07-03-2016

    495 Level 24 Office Floor +98.4 18 days 24-02-2016 22-03-2016

    496 Slab Form work 6 days 02-03-2016 11-03-2016

    497 Slab Reinforcement work 6 days 04-03-2016 12-03-2016

    498 Slab M& E Works 4 days 09-03-2016 15-03-2016

    499 Slab Concrete -1 st Pour 1 day 11-03-2016 12-03-2016

    500 Slab Concrete- Final Pour 1 day 15-03-2016 16-03-2016

    501 Core Walls R/F Work 8 days 24-02-2016 07-03-2016

    502 Core Walls Formwork 6 days 27-02-2016 09-03-2016

    503 Core Wall Conctete 4 days 04-03-2016 10-03-2016

    504 Columns F/W, R/F Concrete and associated Works 6 days 14-03-2016 22-03-2016

    505 Level 25 Office Floor +102.3 18 days 10-03-2016 06-04-2016

    506 Slab Form work 6 days 17-03-2016 26-03-2016

    507 Slab Reinforcement work 6 days 19-03-2016 28-03-2016

    508 Slab M& E Works 4 days 23-03-2016 29-03-2016

    509 Slab Concrete -1 st Pour 1 day 26-03-2016 28-03-2016

    510 Slab Concrete- Final Pour 1 day 29-03-2016 30-03-2016

    511 Core Walls R/F Work 8 days 10-03-2016 22-03-2016

    512 Core Walls Formwork 6 days 15-03-2016 23-03-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 19 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    513 Core Wall Conctete 4 days 19-03-2016 24-03-2016

    514 Columns F/W, R/F Concrete and associated Works 6 days 28-03-2016 06-04-2016

    515 Level 26 Office Floor +106.2 18 days 25-03-2016 07-05-2016

    516 Slab Form work 6 days 01-04-2016 26-04-2016

    517 Slab Reinforcement work 6 days 04-04-2016 27-04-2016

    518 Slab M& E Works 4 days 08-04-2016 29-04-2016

    519 Slab Concrete -1 st Pour 1 day 26-04-2016 27-04-2016

    520 Slab Concrete- Final Pour 1 day 29-04-2016 30-04-2016

    521 Core Walls R/F Work 8 days 25-03-2016 06-04-2016

    522 Core Walls Formwork 6 days 29-03-2016 08-04-2016

    523 Core Wall Conctete 4 days 04-04-2016 09-04-2016

    524 Columns F/W, R/F Concrete and associated Works 6 days 28-04-2016 07-05-2016

    525 Level 27 Office Floor +110.1 18 days 09-04-2016 21-05-2016

    526 Slab Form work 6 days 03-05-2016 12-05-2016

    527 Slab Reinforcement work 6 days 05-05-2016 13-05-2016

    528 Slab M& E Works 4 days 09-05-2016 14-05-2016

    529 Slab Concrete -1 st Pour 1 day 12-05-2016 13-05-2016

    530 Slab Concrete- Final Pour 1 day 14-05-2016 16-05-2016

    531 Core Walls R/F Work 8 days 09-04-2016 07-05-2016

    532 Core Walls Formwork 6 days 29-04-2016 09-05-2016

    533 Core Wall Conctete 4 days 05-05-2016 10-05-2016

    534 Columns F/W, R/F Concrete and associated Works 6 days 13-05-2016 21-05-2016

    535 Level 28 Auditorium level 1 +114 17 days 11-05-2016 06-06-2016

    536 Slab Form work 8 days 14-05-2016 26-05-2016

    537 Slab Reinforcement work 7 days 18-05-2016 27-05-2016

    538 Slab M& E Works 5 days 23-05-2016 30-05-2016

    539 Slab Concrete -1 st Pour 1 day 25-05-2016 26-05-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 20 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    540 Slab Concrete- Final Pour 1 day 30-05-2016 31-05-2016

    541 Core Walls R/F Work 8 days 11-05-2016 21-05-2016

    542 Core Walls Formwork 6 days 14-05-2016 24-05-2016

    543 Core Wall Conctete 4 days 19-05-2016 25-05-2016

    544 Columns F/W, R/F Concrete and associated Works 6 days 26-05-2016 06-06-2016

    545 Level 29 Auditorium level 2 +117.9 17 days 25-05-2016 20-06-2016

    546 Slab Form work 9 days 28-05-2016 11-06-2016

    547 Slab Reinforcement work 7 days 01-06-2016 13-06-2016

    548 Slab M& E Works 5 days 07-06-2016 14-06-2016

    549 Slab Concrete -1 st Pour 1 day 10-06-2016 11-06-2016

    550 Slab Concrete- Final Pour 1 day 14-06-2016 15-06-2016

    551 Core Walls R/F Work 8 days 25-05-2016 07-06-2016

    552 Core Walls Formwork 6 days 30-05-2016 08-06-2016

    553 Core Wall Conctete 4 days 04-06-2016 09-06-2016

    554 Columns F/W, R/F Concrete and associated Works 6 days 11-06-2016 20-06-2016

    555 Level 30 (Double Height) Auditorium level 3 +123.425 16 days 10-06-2016 04-07-2016

    556 Slab Form work 9 days 11-06-2016 24-06-2016

    557 Slab Reinforcement work 8 days 14-06-2016 25-06-2016

    558 Slab M& E Works 5 days 20-06-2016 27-06-2016

    559 Slab Concrete -1 st Pour 1 day 23-06-2016 24-06-2016

    560 Slab Concrete- Final Pour 1 day 28-06-2016 29-06-2016

    561 Core Walls R/F Work 8 days 10-06-2016 21-06-2016

    562 Core Walls Formwork 6 days 14-06-2016 23-06-2016

    563 Core Wall Conctete 4 days 18-06-2016 24-06-2016

    564 Columns F/W, R/F Concrete and associated Works 6 days 24-06-2016 04-07-2016

    565 Level 31 Recreational level +126.675 16 days 23-06-2016 18-07-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 21 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    566 Slab Form work 10 days 23-06-2016 08-07-2016

    567 Slab Reinforcement work 9 days 25-06-2016 09-07-2016

    568 Slab M& E Works 5 days 05-07-2016 12-07-2016

    569 Slab Concrete -1 st Pour 1 day 07-07-2016 08-07-2016

    570 Slab Concrete- Final Pour 1 day 12-07-2016 13-07-2016

    571 Core Walls R/F Work 8 days 24-06-2016 07-07-2016

    572 Core Walls Formwork 6 days 29-06-2016 08-07-2016

    573 Core Wall Conctete 4 days 05-07-2016 09-07-2016

    574 Columns F/W, R/F Concrete and associated Works 6 days 08-07-2016 18-07-2016

    575 Level 32 Pump Room Level +129.975 15 days 11-07-2016 03-08-2016

    576 Slab Form work 6 days 13-07-2016 21-07-2016

    577 Slab Reinforcement work 6 days 14-07-2016 23-07-2016

    578 Slab M& E Works 4 days 19-07-2016 25-07-2016

    579 Slab Concrete -1 st Pour 1 day 22-07-2016 23-07-2016

    580 Slab Concrete- Final Pour 1 day 25-07-2016 26-07-2016

    581 Core Walls R/F Work 8 days 11-07-2016 21-07-2016

    582 Core Walls Formwork 6 days 14-07-2016 23-07-2016

    583 Core Wall Conctete 4 days 19-07-2016 25-07-2016

    584 Columns F/W, R/F Concrete and associated Works 6 days 23-07-2016 03-08-2016

    585 Level R2 Water Tank level +133.175 15 days 25-07-2016 18-08-2016

    586 Slab Form work 6 days 28-07-2016 08-08-2016

    587 Slab Reinforcement work 6 days 30-07-2016 09-08-2016

    588 Slab M& E Works 4 days 05-08-2016 10-08-2016

    589 Slab Concrete -1 st Pour 1 day 08-08-2016 09-08-2016

    590 Slab Concrete- Final Pour 1 day 11-08-2016 12-08-2016

    591 Core Walls R/F Work 7 days 25-07-2016 06-08-2016

    592 Core Walls Formwork 6 days 28-07-2016 08-08-2016

    593 Core Wall Conctete 4 days 03-08-2016 09-08-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 22 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    594 Water Tank Top Slab 6 days 09-08-2016 18-08-2016

    595 Internal Finishes & MEP works 402.8 days 06-05-2015 25-01-2017

    596 Basement 2 199.2 days 06-05-2015 07-03-2016

    597 Masonry Works 48.8 days 06-05-2015 17-07-2015

    598 Blockwork 21 days 06-05-2015 29-05-2015

    599 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    21 days 30-05-2015 23-06-2015

    600 Internal Plaster 21 days 24-06-2015 17-07-2015

    601 Wet Areas 150.4 days 18-07-2015 07-03-2016

    602 Dry Areas 150.4 days 18-07-2015 07-03-2016

    603 MEP 2nd Fix (Under Ceiling Slab Works, Electricalrooms etc.)

    52 days 18-07-2015 18-09-2015

    604 Kerbstones 26 days 19-09-2015 19-10-2015

    605 Interlock Pavings 26 days 20-10-2015 18-11-2015

    606 Install Doors & False Ceiling 13 days 19-11-2015 03-12-2015

    607 Painting 26 days 04-12-2015 05-01-2016

    608 Traffic Marking 26 days 06-01-2016 05-02-2016

    609 MEP Plant rooms - Equipment install & test 52 days 06-01-2016 07-03-2016

    610 Basement 1 256.2 days 12-05-2015 23-06-2016

    611 Masonry Works 48.8 days 12-05-2015 23-07-2015

    612 Blockwork 21 days 12-05-2015 04-06-2015

    613 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    21 days 05-06-2015 29-06-2015

    614 Internal Plaster 21 days 30-06-2015 23-07-2015

    615 Wet Areas 207.4 days 24-07-2015 23-06-2016

    616 Dry Areas 207.4 days 24-07-2015 23-06-2016

    617 MEP 2nd Fix (Under Ceiling Slab Works, Electricalrooms etc.)

    52 days 24-07-2015 24-09-2015

    618 Kerbstones 26 days 25-09-2015 24-10-2015

    619 Interlock Pavings 26 days 26-10-2015 24-11-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 23 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    620 Install Doors & False Ceiling 13 days 07-03-2016 22-03-2016

    621 Painting 26 days 22-03-2016 22-04-2016

    622 Traffic Marking 26 days 22-04-2016 24-05-2016

    623 MEP Plant rooms - Equipment install & test 52 days 22-04-2016 23-06-2016

    624 Ground Floor 249.8 days 12-05-2015 14-06-2016

    625 Masonry Works 60.8 days 12-05-2015 11-08-2015

    626 Blockwork 26 days 12-05-2015 10-06-2015

    627 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    26 days 11-06-2015 10-07-2015

    628 Internal Plaster 26 days 11-07-2015 11-08-2015

    629 Wet Areas 189 days 12-08-2015 14-06-2016

    630 Wet Area Waterproofing 18 days 12-08-2015 01-09-2015

    631 MEP 2nd fix High level 45 days 02-09-2015 24-10-2015

    632 Wall Tiling 21 days 08-10-2015 31-10-2015

    633 Floor Tiling 26 days 12-03-2016 12-04-2016

    634 Install Doors & False Ceiling 16 days 12-04-2016 02-05-2016

    635 Paint 28 days 12-04-2016 17-05-2016

    636 MEP Final Fixes 21 days 28-04-2016 24-05-2016

    637 Civil Final Fixes 18 days 24-05-2016 14-06-2016

    638 Dry Areas 160.8 days 12-08-2015 02-05-2016

    639 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    52 days 12-08-2015 12-10-2015

    640 False Ceiling Suspension 26 days 19-09-2015 19-10-2015

    641 MEP Dropworks to Ceilings 26 days 03-10-2015 02-11-2015

    642 Install Doors & Windows 21 days 03-11-2015 26-11-2015

    643 Fase Celing Boarding 26 days 27-11-2015 28-12-2015

    644 Painting 26 days 29-12-2015 28-01-2016

    645 Civil - Final Finishes 26 days 29-01-2016 29-02-2016

    646 MEP Plant Rooms - Equipment Install & test 78 days 29-01-2016 30-04-2016

    647 Final Paint, Clean & Snags 1 day 02-05-2016 02-05-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 24 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    648 Level 01 - Parking 242.6 days 23-05-2015 15-06-2016

    649 Masonry Works 56.8 days 23-05-2015 17-08-2015

    650 Blockwork 21 days 23-05-2015 16-06-2015

    651 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    21 days 23-06-2015 16-07-2015

    652 Internal Plaster 21 days 23-07-2015 17-08-2015

    653 Wet Areas 181.8 days 24-08-2015 15-06-2016

    654 Wet Area Waterproofing 13 days 24-08-2015 08-09-2015

    655 MEP 2nd fix High level 39 days 09-09-2015 23-10-2015

    656 Wall Tiling 18 days 17-10-2015 06-11-2015

    657 Floor Tiling 21 days 24-03-2016 19-04-2016

    658 Install Doors & False Ceiling 16 days 19-04-2016 09-05-2016

    659 Paint 26 days 19-04-2016 20-05-2016

    660 MEP Final Fixes 18 days 06-05-2016 27-05-2016

    661 Civil Final Fixes 13 days 31-05-2016 15-06-2016

    662 Dry Areas 104 days 18-08-2015 25-01-2016

    663 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    52 days 18-08-2015 17-10-2015

    664 Kerbstones 26 days 25-09-2015 24-10-2015

    665 Interlock Pavings 26 days 09-10-2015 07-11-2015

    666 Install Doors 13 days 09-11-2015 23-11-2015

    667 Painting 26 days 24-11-2015 23-12-2015

    668 Traffic Marking 26 days 24-12-2015 25-01-2016

    669 MEP Plant rooms - Equipment install & test 78 days 24-09-2015 23-12-2015

    670 Level 02 - Parking 240.2 days 29-05-2015 17-06-2016

    671 Masonry Works 56.8 days 29-05-2015 22-08-2015

    672 Blockwork 21 days 29-05-2015 22-06-2015

    673 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    21 days 29-06-2015 22-07-2015

    674 Internal Plaster 21 days 30-07-2015 22-08-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 25 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    675 Wet Areas 179.4 days 29-08-2015 17-06-2016

    676 Wet Area Waterproofing 13 days 29-08-2015 14-09-2015

    677 MEP 2nd fix High level 39 days 15-09-2015 29-10-2015

    678 Wall Tiling 18 days 23-10-2015 12-11-2015

    679 Floor Tiling 21 days 30-03-2016 25-04-2016

    680 Install Doors & False Ceiling 16 days 25-04-2016 14-05-2016

    681 Paint 26 days 25-04-2016 26-05-2016

    682 MEP Final Fixes 18 days 12-05-2016 02-06-2016

    683 Civil Final Fixes 13 days 02-06-2016 17-06-2016

    684 Dry Areas 104 days 24-08-2015 30-01-2016

    685 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    52 days 24-08-2015 23-10-2015

    686 Kerbstones 26 days 01-10-2015 30-10-2015

    687 Interlock Pavings 26 days 15-10-2015 13-11-2015

    688 Install Doors 13 days 14-11-2015 28-11-2015

    689 Painting 26 days 30-11-2015 30-12-2015

    690 Traffic Marking 26 days 31-12-2015 30-01-2016

    691 MEP Plant rooms - Equipment install & test 78 days 30-09-2015 30-12-2015

    692 Level 03 - Parking 241 days 04-06-2015 23-06-2016

    693 Masonry Works 57.6 days 04-06-2015 28-08-2015

    694 Blockwork 21 days 04-06-2015 27-06-2015

    695 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    21 days 04-07-2015 28-07-2015

    696 Internal Plaster 21 days 05-08-2015 28-08-2015

    697 Wet Areas 179.4 days 05-09-2015 23-06-2016

    698 Wet Area Waterproofing 13 days 05-09-2015 19-09-2015

    699 MEP 2nd fix High level 39 days 21-09-2015 04-11-2015

    700 Wall Tiling 18 days 29-10-2015 18-11-2015

    701 Floor Tiling 21 days 05-04-2016 30-04-2016

    702 Install Doors & False Ceiling 16 days 30-04-2016 20-05-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 26 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    703 Paint 26 days 30-04-2016 01-06-2016

    704 MEP Final Fixes 18 days 18-05-2016 08-06-2016

    705 Civil Final Fixes 13 days 08-06-2016 23-06-2016

    706 Dry Areas 103.2 days 29-08-2015 06-02-2016

    707 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    52 days 29-08-2015 29-10-2015

    708 Kerbstones 26 days 07-10-2015 05-11-2015

    709 Interlock Pavings 26 days 21-10-2015 19-11-2015

    710 Install Doors 13 days 20-11-2015 04-12-2015

    711 Painting 26 days 05-12-2015 06-01-2016

    712 Traffic Marking 26 days 07-01-2016 06-02-2016

    713 MEP Plant rooms - Equipment install & test 78 days 06-10-2015 06-01-2016

    714 Level 04 - Office 234.6 days 16-06-2015 25-06-2016

    715 Masonry Works 52.8 days 16-06-2015 03-09-2015

    716 Blockwork 18 days 16-06-2015 06-07-2015

    717 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 14-07-2015 04-08-2015

    718 Internal Plaster 18 days 14-08-2015 03-09-2015

    719 Wet Areas 172.2 days 17-09-2015 24-06-2016

    720 Wet Area Waterproofing 8 days 17-09-2015 25-09-2015

    721 MEP 2nd fix High level 39 days 26-09-2015 10-11-2015

    722 Wall Tiling 21 days 31-10-2015 24-11-2015

    723 Floor Tiling 26 days 05-04-2016 07-05-2016

    724 Install Doors & False Ceiling 16 days 07-05-2016 26-05-2016

    725 Paint 18 days 07-05-2016 28-05-2016

    726 MEP Final Fixes 18 days 14-05-2016 04-06-2016

    727 Civil Final Fixes 13 days 09-06-2016 24-06-2016

    728 Dry Areas 181 days 05-09-2015 25-06-2016

    729 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 05-09-2015 27-10-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 27 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    730 False Ceiling Suspension 26 days 05-10-2015 03-11-2015

    731 MEP Dropworks to Ceilings 26 days 19-10-2015 17-11-2015

    732 Install Doors & Windows 21 days 09-11-2015 02-12-2015

    733 Fase Celing Boarding 26 days 03-12-2015 04-01-2016

    734 Painting 26 days 05-01-2016 03-02-2016

    735 Civil - Final Finishes 21 days 05-02-2016 29-02-2016

    736 MEP Service Rooms - MEP works 21 days 05-02-2016 29-02-2016

    737 Final Paint, Clean & Snags 1 day 24-06-2016 25-06-2016

    738 MEP Final Finishes 13 days 05-02-2016 19-02-2016

    739 Level 05 - Office 223.4 days 04-07-2015 27-06-2016

    740 Masonry Works 45.6 days 04-07-2015 10-09-2015

    741 Blockwork 18 days 04-07-2015 24-07-2015

    742 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 25-07-2015 15-08-2015

    743 Internal Plaster 18 days 20-08-2015 10-09-2015

    744 Wet Areas 169 days 23-09-2015 25-06-2016

    745 Wet Area Waterproofing 8 days 23-09-2015 01-10-2015

    746 MEP 2nd fix High level 39 days 02-10-2015 16-11-2015

    747 Wall Tiling 21 days 06-11-2015 30-11-2015

    748 Floor Tiling 26 days 11-04-2016 13-05-2016

    749 Install Doors & False Ceiling 16 days 13-05-2016 01-06-2016

    750 Paint 18 days 13-05-2016 03-06-2016

    751 MEP Final Fixes 18 days 20-05-2016 10-06-2016

    752 Civil Final Fixes 13 days 10-06-2016 25-06-2016

    753 Dry Areas 177.8 days 11-09-2015 27-06-2016

    754 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 11-09-2015 02-11-2015

    755 False Ceiling Suspension 26 days 10-10-2015 09-11-2015

    756 MEP Dropworks to Ceilings 26 days 24-10-2015 23-11-2015

    757 Install Doors & Windows 21 days 14-11-2015 08-12-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 28 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    758 Fase Celing Boarding 26 days 09-12-2015 09-01-2016

    759 Painting 26 days 11-01-2016 10-02-2016

    760 Civil - Final Finishes 21 days 11-02-2016 05-03-2016

    761 MEP Service Rooms - MEP works 21 days 11-02-2016 05-03-2016

    762 Final Paint, Clean & Snags 1 day 25-06-2016 27-06-2016

    763 MEP Final Finishes 13 days 11-02-2016 25-02-2016

    764 Level 06 - Office 217.2 days 18-07-2015 02-07-2016

    765 Masonry Works 43.2 days 18-07-2015 22-09-2015

    766 Blockwork 18 days 18-07-2015 10-08-2015

    767 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 10-08-2015 31-08-2015

    768 Internal Plaster 18 days 31-08-2015 22-09-2015

    769 Wet Areas 169 days 29-09-2015 01-07-2016

    770 Wet Area Waterproofing 8 days 29-09-2015 07-10-2015

    771 MEP 2nd fix High level 39 days 08-10-2015 21-11-2015

    772 Wall Tiling 21 days 12-11-2015 05-12-2015

    773 Floor Tiling 26 days 16-04-2016 19-05-2016

    774 Install Doors & False Ceiling 16 days 19-05-2016 07-06-2016

    775 Paint 18 days 19-05-2016 09-06-2016

    776 MEP Final Fixes 18 days 26-05-2016 16-06-2016

    777 Civil Final Fixes 13 days 16-06-2016 01-07-2016

    778 Dry Areas 174 days 22-09-2015 02-07-2016

    779 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 22-09-2015 13-11-2015

    780 False Ceiling Suspension 26 days 21-10-2015 20-11-2015

    781 MEP Dropworks to Ceilings 26 days 04-11-2015 04-12-2015

    782 Install Doors & Windows 21 days 25-11-2015 19-12-2015

    783 Fase Celing Boarding 26 days 15-12-2015 15-01-2016

    784 Painting 26 days 16-01-2016 16-02-2016

    785 Civil - Final Finishes 21 days 17-02-2016 11-03-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 29 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    786 MEP Service Rooms - MEP works 21 days 17-02-2016 11-03-2016

    787 Final Paint, Clean & Snags 1 day 01-07-2016 02-07-2016

    788 MEP Final Finishes 13 days 17-02-2016 02-03-2016

    789 Level 07 - Office 209.8 days 05-08-2015 08-07-2016

    790 Masonry Works 42.4 days 05-08-2015 07-10-2015

    791 Blockwork 18 days 05-08-2015 25-08-2015

    792 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 26-08-2015 16-09-2015

    793 Internal Plaster 18 days 17-09-2015 07-10-2015

    794 Wet Areas 166.6 days 08-10-2015 07-07-2016

    795 Wet Area Waterproofing 8 days 08-10-2015 16-10-2015

    796 MEP 2nd fix High level 39 days 17-10-2015 01-12-2015

    797 Wall Tiling 21 days 19-11-2015 12-12-2015

    798 Floor Tiling 26 days 23-04-2016 25-05-2016

    799 Install Doors & False Ceiling 16 days 25-05-2016 13-06-2016

    800 Paint 18 days 25-05-2016 15-06-2016

    801 MEP Final Fixes 18 days 01-06-2016 22-06-2016

    802 Civil Final Fixes 13 days 22-06-2016 07-07-2016

    803 Dry Areas 167.4 days 08-10-2015 08-07-2016

    804 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 08-10-2015 28-11-2015

    805 False Ceiling Suspension 26 days 06-11-2015 05-12-2015

    806 MEP Dropworks to Ceilings 26 days 20-11-2015 19-12-2015

    807 Install Doors & Windows 21 days 11-12-2015 06-01-2016

    808 Fase Celing Boarding 26 days 21-12-2015 21-01-2016

    809 Painting 26 days 22-01-2016 22-02-2016

    810 Civil - Final Finishes 21 days 23-02-2016 17-03-2016

    811 MEP Service Rooms - MEP works 21 days 23-02-2016 17-03-2016

    812 Final Paint, Clean & Snags 1 day 07-07-2016 08-07-2016

    813 MEP Final Finishes 13 days 23-02-2016 08-03-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 30 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    814 Level 08 - Office 203.8 days 19-08-2015 14-07-2016

    815 Masonry Works 42 days 19-08-2015 22-10-2015

    816 Blockwork 18 days 19-08-2015 10-09-2015

    817 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 10-09-2015 01-10-2015

    818 Internal Plaster 18 days 01-10-2015 22-10-2015

    819 Wet Areas 161 days 22-10-2015 13-07-2016

    820 Wet Area Waterproofing 8 days 22-10-2015 31-10-2015

    821 MEP 2nd fix High level 39 days 31-10-2015 16-12-2015

    822 Wall Tiling 21 days 03-12-2015 29-12-2015

    823 Floor Tiling 26 days 29-04-2016 31-05-2016

    824 Install Doors & False Ceiling 16 days 31-05-2016 18-06-2016

    825 Paint 18 days 31-05-2016 21-06-2016

    826 MEP Final Fixes 18 days 07-06-2016 28-06-2016

    827 Civil Final Fixes 13 days 28-06-2016 13-07-2016

    828 Dry Areas 161.8 days 22-10-2015 14-07-2016

    829 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 22-10-2015 14-12-2015

    830 False Ceiling Suspension 26 days 20-11-2015 21-12-2015

    831 MEP Dropworks to Ceilings 26 days 04-12-2015 06-01-2016

    832 Install Doors & Windows 21 days 26-12-2015 21-01-2016

    833 Fase Celing Boarding 26 days 06-01-2016 06-02-2016

    834 Painting 26 days 06-02-2016 08-03-2016

    835 Civil - Final Finishes 21 days 08-03-2016 01-04-2016

    836 MEP Service Rooms - MEP works 21 days 08-03-2016 01-04-2016

    837 Final Paint, Clean & Snags 1 day 13-07-2016 14-07-2016

    838 MEP Final Finishes 13 days 08-03-2016 23-03-2016

    839 Level 09 - Office 198.6 days 03-09-2015 20-07-2016

    840 Masonry Works 41.6 days 03-09-2015 05-11-2015

    841 Blockwork 18 days 03-09-2015 24-09-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 31 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    842 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 25-09-2015 15-10-2015

    843 Internal Plaster 18 days 16-10-2015 05-11-2015

    844 Wet Areas 156.2 days 06-11-2015 19-07-2016

    845 Wet Area Waterproofing 8 days 06-11-2015 14-11-2015

    846 MEP 2nd fix High level 39 days 16-11-2015 31-12-2015

    847 Wall Tiling 21 days 18-12-2015 13-01-2016

    848 Floor Tiling 26 days 06-05-2016 06-06-2016

    849 Install Doors & False Ceiling 16 days 06-06-2016 24-06-2016

    850 Paint 18 days 06-06-2016 27-06-2016

    851 MEP Final Fixes 18 days 13-06-2016 04-07-2016

    852 Civil Final Fixes 13 days 04-07-2016 19-07-2016

    853 Dry Areas 157 days 06-11-2015 20-07-2016

    854 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 06-11-2015 29-12-2015

    855 False Ceiling Suspension 26 days 05-12-2015 06-01-2016

    856 MEP Dropworks to Ceilings 26 days 19-12-2015 20-01-2016

    857 Install Doors & Windows 21 days 12-01-2016 05-02-2016

    858 Fase Celing Boarding 26 days 21-01-2016 20-02-2016

    859 Painting 26 days 22-02-2016 22-03-2016

    860 Civil - Final Finishes 21 days 23-03-2016 15-04-2016

    861 MEP Service Rooms - MEP works 21 days 23-03-2016 15-04-2016

    862 Final Paint, Clean & Snags 1 day 19-07-2016 20-07-2016

    863 MEP Final Finishes 13 days 23-03-2016 06-04-2016

    864 Level 10 - Office 191.8 days 18-09-2015 26-07-2016

    865 Masonry Works 40.8 days 18-09-2015 20-11-2015

    866 Blockwork 18 days 18-09-2015 09-10-2015

    867 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 09-10-2015 30-10-2015

    868 Internal Plaster 18 days 30-10-2015 20-11-2015

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 32 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    869 Wet Areas 150.2 days 20-11-2015 25-07-2016

    870 Wet Area Waterproofing 8 days 20-11-2015 30-11-2015

    871 MEP 2nd fix High level 39 days 30-11-2015 16-01-2016

    872 Wall Tiling 21 days 04-01-2016 28-01-2016

    873 Floor Tiling 26 days 12-05-2016 11-06-2016

    874 Install Doors & False Ceiling 16 days 11-06-2016 30-06-2016

    875 Paint 18 days 11-06-2016 02-07-2016

    876 MEP Final Fixes 18 days 18-06-2016 09-07-2016

    877 Civil Final Fixes 13 days 09-07-2016 25-07-2016

    878 Dry Areas 151 days 20-11-2015 26-07-2016

    879 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 20-11-2015 14-01-2016

    880 False Ceiling Suspension 26 days 19-12-2015 21-01-2016

    881 MEP Dropworks to Ceilings 26 days 05-01-2016 05-02-2016

    882 Install Doors & Windows 21 days 26-01-2016 20-02-2016

    883 Fase Celing Boarding 26 days 05-02-2016 07-03-2016

    884 Painting 26 days 07-03-2016 06-04-2016

    885 Civil - Final Finishes 21 days 06-04-2016 02-05-2016

    886 MEP Service Rooms - MEP works 21 days 06-04-2016 02-05-2016

    887 Final Paint, Clean & Snags 1 day 25-07-2016 26-07-2016

    888 MEP Final Finishes 13 days 06-04-2016 22-04-2016

    889 Level 11 - Office 186.4 days 03-10-2015 02-08-2016

    890 Masonry Works 40.8 days 03-10-2015 04-12-2015

    891 Blockwork 18 days 03-10-2015 23-10-2015

    892 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 24-10-2015 13-11-2015

    893 Internal Plaster 18 days 14-11-2015 04-12-2015

    894 Wet Areas 145 days 05-12-2015 01-08-2016

    895 Wet Area Waterproofing 8 days 05-12-2015 14-12-2015

    896 MEP 2nd fix High level 39 days 15-12-2015 30-01-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 33 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    897 Wall Tiling 21 days 19-01-2016 12-02-2016

    898 Floor Tiling 26 days 18-05-2016 17-06-2016

    899 Install Doors & False Ceiling 16 days 17-06-2016 06-07-2016

    900 Paint 18 days 17-06-2016 08-07-2016

    901 MEP Final Fixes 18 days 24-06-2016 15-07-2016

    902 Civil Final Fixes 13 days 15-07-2016 01-08-2016

    903 Dry Areas 145.6 days 05-12-2015 02-08-2016

    904 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 05-12-2015 28-01-2016

    905 False Ceiling Suspension 26 days 06-01-2016 05-02-2016

    906 MEP Dropworks to Ceilings 26 days 20-01-2016 19-02-2016

    907 Install Doors & Windows 21 days 11-02-2016 05-03-2016

    908 Fase Celing Boarding 26 days 20-02-2016 21-03-2016

    909 Painting 26 days 22-03-2016 21-04-2016

    910 Civil - Final Finishes 21 days 22-04-2016 17-05-2016

    911 MEP Service Rooms - MEP works 21 days 22-04-2016 17-05-2016

    912 Final Paint, Clean & Snags 1 day 01-08-2016 02-08-2016

    913 MEP Final Finishes 13 days 22-04-2016 07-05-2016

    914 Level 12 - Office 179.8 days 17-10-2015 08-08-2016

    915 Masonry Works 40.8 days 17-10-2015 19-12-2015

    916 Blockwork 18 days 17-10-2015 07-11-2015

    917 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 07-11-2015 28-11-2015

    918 Internal Plaster 18 days 28-11-2015 19-12-2015

    919 Wet Areas 138.2 days 19-12-2015 06-08-2016

    920 Wet Area Waterproofing 8 days 19-12-2015 30-12-2015

    921 MEP 2nd fix High level 39 days 30-12-2015 16-02-2016

    922 Wall Tiling 21 days 02-02-2016 27-02-2016

    923 Floor Tiling 26 days 24-05-2016 23-06-2016

    924 Install Doors & False Ceiling 16 days 23-06-2016 12-07-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 34 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    925 Paint 18 days 23-06-2016 14-07-2016

    926 MEP Final Fixes 18 days 30-06-2016 21-07-2016

    927 Civil Final Fixes 13 days 21-07-2016 06-08-2016

    928 Dry Areas 139 days 19-12-2015 08-08-2016

    929 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 19-12-2015 13-02-2016

    930 False Ceiling Suspension 26 days 20-01-2016 20-02-2016

    931 MEP Dropworks to Ceilings 26 days 03-02-2016 05-03-2016

    932 Install Doors & Windows 21 days 25-02-2016 21-03-2016

    933 Fase Celing Boarding 26 days 05-03-2016 05-04-2016

    934 Painting 26 days 05-04-2016 07-05-2016

    935 Civil - Final Finishes 21 days 07-05-2016 01-06-2016

    936 MEP Service Rooms - MEP works 21 days 07-05-2016 01-06-2016

    937 Final Paint, Clean & Snags 1 day 06-08-2016 08-08-2016

    938 MEP Final Finishes 13 days 07-05-2016 23-05-2016

    939 Level 13 - Office 174.6 days 03-11-2015 13-08-2016

    940 Masonry Works 42.4 days 03-11-2015 06-01-2016

    941 Blockwork 18 days 03-11-2015 23-11-2015

    942 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 24-11-2015 14-12-2015

    943 Internal Plaster 18 days 15-12-2015 06-01-2016

    944 Wet Areas 131.4 days 07-01-2016 12-08-2016

    945 Wet Area Waterproofing 8 days 07-01-2016 15-01-2016

    946 MEP 2nd fix High level 39 days 16-01-2016 02-03-2016

    947 Wall Tiling 21 days 19-02-2016 14-03-2016

    948 Floor Tiling 26 days 30-05-2016 29-06-2016

    949 Install Doors & False Ceiling 16 days 29-06-2016 18-07-2016

    950 Paint 18 days 29-06-2016 20-07-2016

    951 MEP Final Fixes 18 days 06-07-2016 27-07-2016

    952 Civil Final Fixes 13 days 27-07-2016 12-08-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 35 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    953 Dry Areas 132.2 days 07-01-2016 13-08-2016

    954 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 07-01-2016 29-02-2016

    955 False Ceiling Suspension 26 days 06-02-2016 07-03-2016

    956 MEP Dropworks to Ceilings 26 days 20-02-2016 21-03-2016

    957 Install Doors & Windows 21 days 12-03-2016 05-04-2016

    958 Fase Celing Boarding 26 days 22-03-2016 21-04-2016

    959 Painting 26 days 22-04-2016 23-05-2016

    960 Civil - Final Finishes 21 days 24-05-2016 16-06-2016

    961 MEP Service Rooms - MEP works 21 days 24-05-2016 16-06-2016

    962 Final Paint, Clean & Snags 1 day 12-08-2016 13-08-2016

    963 MEP Final Finishes 13 days 24-05-2016 07-06-2016

    964 Level 14 - Office 167.8 days 18-11-2015 19-08-2016

    965 Masonry Works 41.6 days 18-11-2015 22-01-2016

    966 Blockwork 18 days 18-11-2015 09-12-2015

    967 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 09-12-2015 31-12-2015

    968 Internal Plaster 18 days 31-12-2015 22-01-2016

    969 Wet Areas 125.4 days 22-01-2016 18-08-2016

    970 Wet Area Waterproofing 8 days 22-01-2016 01-02-2016

    971 MEP 2nd fix High level 39 days 01-02-2016 18-03-2016

    972 Wall Tiling 21 days 05-03-2016 30-03-2016

    973 Floor Tiling 26 days 04-06-2016 05-07-2016

    974 Install Doors & False Ceiling 16 days 05-07-2016 23-07-2016

    975 Paint 18 days 05-07-2016 26-07-2016

    976 MEP Final Fixes 18 days 12-07-2016 03-08-2016

    977 Civil Final Fixes 13 days 03-08-2016 18-08-2016

    978 Dry Areas 126.2 days 22-01-2016 19-08-2016

    979 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 22-01-2016 16-03-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 36 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    980 False Ceiling Suspension 26 days 22-02-2016 23-03-2016

    981 MEP Dropworks to Ceilings 26 days 07-03-2016 06-04-2016

    982 Install Doors & Windows 21 days 28-03-2016 22-04-2016

    983 Fase Celing Boarding 26 days 06-04-2016 09-05-2016

    984 Painting 26 days 09-05-2016 08-06-2016

    985 Civil - Final Finishes 21 days 08-06-2016 02-07-2016

    986 MEP Service Rooms - MEP works 21 days 08-06-2016 02-07-2016

    987 Final Paint, Clean & Snags 1 day 18-08-2016 19-08-2016

    988 MEP Final Finishes 13 days 08-06-2016 23-06-2016

    989 Level 15 - Office 161.8 days 04-12-2015 25-08-2016

    990 Masonry Works 41.6 days 04-12-2015 08-02-2016

    991 Blockwork 18 days 04-12-2015 24-12-2015

    992 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 26-12-2015 16-01-2016

    993 Internal Plaster 18 days 18-01-2016 08-02-2016

    994 Wet Areas 119.4 days 09-02-2016 24-08-2016

    995 Wet Area Waterproofing 8 days 09-02-2016 17-02-2016

    996 MEP 2nd fix High level 39 days 18-02-2016 02-04-2016

    997 Wall Tiling 21 days 22-03-2016 14-04-2016

    998 Floor Tiling 26 days 10-06-2016 11-07-2016

    999 Install Doors & False Ceiling 16 days 11-07-2016 30-07-2016

    1000 Paint 18 days 11-07-2016 02-08-2016

    1001 MEP Final Fixes 18 days 18-07-2016 09-08-2016

    1002 Civil Final Fixes 13 days 09-08-2016 24-08-2016

    1003 Dry Areas 120.2 days 09-02-2016 25-08-2016

    1004 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 09-02-2016 31-03-2016

    1005 False Ceiling Suspension 26 days 09-03-2016 07-04-2016

    1006 MEP Dropworks to Ceilings 26 days 23-03-2016 22-04-2016

    1007 Install Doors & Windows 21 days 13-04-2016 09-05-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 37 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    1008 Fase Celing Boarding 26 days 23-04-2016 24-05-2016

    1009 Painting 26 days 25-05-2016 23-06-2016

    1010 Civil - Final Finishes 21 days 24-06-2016 18-07-2016

    1011 MEP Service Rooms - MEP works 21 days 24-06-2016 18-07-2016

    1012 Final Paint, Clean & Snags 1 day 24-08-2016 25-08-2016

    1013 MEP Final Finishes 13 days 24-06-2016 08-07-2016

    1014 Level 16 - Office 155.8 days 18-12-2015 31-08-2016

    1015 Masonry Works 41.6 days 18-12-2015 23-02-2016

    1016 Blockwork 18 days 18-12-2015 11-01-2016

    1017 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 11-01-2016 01-02-2016

    1018 Internal Plaster 18 days 01-02-2016 23-02-2016

    1019 Wet Areas 113.4 days 23-02-2016 30-08-2016

    1020 Wet Area Waterproofing 8 days 23-02-2016 03-03-2016

    1021 MEP 2nd fix High level 39 days 03-03-2016 19-04-2016

    1022 Wall Tiling 21 days 05-04-2016 30-04-2016

    1023 Floor Tiling 26 days 16-06-2016 16-07-2016

    1024 Install Doors & False Ceiling 16 days 16-07-2016 05-08-2016

    1025 Paint 18 days 16-07-2016 08-08-2016

    1026 MEP Final Fixes 18 days 23-07-2016 15-08-2016

    1027 Civil Final Fixes 13 days 15-08-2016 30-08-2016

    1028 Dry Areas 114.2 days 23-02-2016 31-08-2016

    1029 MEP 2nd Fix (Under Ceiling Slab Works, Electrical rooms etc.)

    45 days 23-02-2016 15-04-2016

    1030 False Ceiling Suspension 26 days 23-03-2016 23-04-2016

    1031 MEP Dropworks to Ceilings 26 days 06-04-2016 09-05-2016

    1032 Install Doors & Windows 21 days 28-04-2016 24-05-2016

    1033 Fase Celing Boarding 26 days 09-05-2016 08-06-2016

    1034 Painting 26 days 08-06-2016 08-07-2016

    1035 Civil - Final Finishes 21 days 08-07-2016 03-08-2016

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2014 2015 2016

    Task Critical Progress Update Summary Milestone

    Client : Commissioner General ofLabour DepartmentConsultant : Design Consortium ltdPMC : Department of Buildings

    MULTI STOREYED BUILDING, COLOMBO, SRI LANKAREVISED PROGRAM

    PS : 22-10-2013PF : 25-01-2017

    MULTI STOREYED BUILDING, COLOMBO Revision : Rev 3, dtd 28-Apr-14

    Page 38 of 54

    Project: MULTI STOREYED BUILDINGDate: 30-04-2014

  • ID Task Name Duration Start Finish

    1036 MEP Service Rooms - MEP works 21 days 08-07-2016 03-08-2016

    1037 Final Paint, Clean & Snags 1 day 30-08-2016 31-08-2016

    1038 MEP Final Finishes 13 days 08-07-2016 23-07-2016

    1039 Level 17 - Office 148.2 days 06-01-2016 06-09-2016

    1040 Masonry Works 34.8 days 06-01-2016 29-02-2016

    1041 Blockwork 18 days 06-01-2016 26-01-2016

    1042 MEP 1st Fix (Conduits, Concealed Pipes, Backboxes etc)

    18 days 18-01-2016 08-02-2016

    1043 Internal Plaster 18 days 08-02-2016 29-02-2016

    1044 Wet Areas 112.6 days 29-02-2016 05-09-2016

    1045 Wet Area Waterproofing 8 days 29-02-2016 09-03-2016

    1046 MEP 2nd fix High level 26 days 09-03-2016 08-04-2016

    1047 Wall Tiling 18 days 14-04-2016 07-05-2016

    1048 Floor Tiling 26 days 22-06-2016 22-07-2016

    1049 Install Doors & False Ceiling 16 days 22-07-2016 11-08-2016

    1050 Paint 18 days 22-07-2016 13-08-2016

    1051 MEP Final Fixes 18 days 30-07-2016 20-08-2016

    1052 Civil Final Fixes 13 days 20-08-2016 05-09-2016

    1053 Dry Areas 123.8 days 13-02-2016 06-09-2016

    1054 MEP 2nd Fix (Under Ceil