revised resettlement action plan - world bank resettlement action plan for ampara district of...
Embed Size (px)
TRANSCRIPT

i
Government of the Democratic Socialist
Republic of Sri Lanka
Provincial Roads Department
Provincial Roads Project
Revised Resettlement Action Plan
for
Ampara District of Eastern Province‘s 11
Roads
July 2011
The Resettlement Plan is a document of the borrower. The views expressed herein do not necessarily
represent those of the Bank‘s Board of Directors, Management or staff and may be preliminary in
nature
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized

i
Summary
1. The Project.
The Provincial Roads Improvement Project aims at improving approximately 350 km length of
roads as about 150 Km in Uva and about 100 Kms each in Ampara and Jaffna. This RAP
prepared to cover only the 11 priority roads in Ampara district of Eastern Province (see table 1.1
of chapter 1), for which the bidding documents are being completed.
Feasibility studies were carried out along the Social Impact Management Framework (SMIF)
which was disclosed in-country on May 5, 2009 and a revised SIMF was prepared and disclosed
in October 2009 (to account for inclusion of the roads in Jaffna in the Project). Road specific
Social Impact Assessments have carried out for Ampara district in Eastern Province and will be
carried out for the remaining provinces. An Entitlement Matrix has been prepared to define
categories of PAPs and types of mitigation measures.
The Resettlement Action Plan is prepared in compliance with the Government‘s National Policy
on Involuntary Resettlement and World Bank‘s Policies in particular, Operational Policy (OP)
4.12.
2. Scope of Land Acquisition and Resettlement.
The study of the revised RAP was carried out based on each proposed road cross section width
(Including carriageway, shoulders and drains) (Annex-3.) Presently, only about 494 PAPs have
been impacted. Since the roads involve improvement and rehabilitation with limited widening
(within the existing RoW), the negative impacts are also limited. Land acquisition is not
envisaged nor is there any resettlement or relocation in this project. The project will only work
with land voluntarily donated by individuals/communities. For any donated land the project will
ensure that a participatory and transparent process has been followed and an agreement/MOU
signed between the donor and the recipient that will among other, ensures i) the ownership of the
land and voluntary nature of the donation, ii) that the land is appropriate for the intended purpose
iii) that the land does not belong to any donor who is below the poverty line or whose holding
would be reduced below the minimum size as stipulated to be economically viable ( 2.5 acres), iv)
that there are no encumbrances on the land, v) that it does not negatively impact on the livelihood
of any vulnerable group, and if so, that community developed mitigation measures are acceptable
to the affectees, vi) that no compensation will be paid for the land, and vii) that the owner gives
up all claims on the land and the title will be transferred to the recipient through the notary public
or a registered deed or any other procedure prescribed by the law of the state.

ii
Table 1 – Details on persons and Property affected
Table 1 Affectees & Losses by types in 11 priority roads of Ampara District
Number of PAP families 109
Number of affectees 494
Land
15
Boundary walls, gates and toilet pits 03
Boundary walls, gates 49
Boundary walls 21
Boundary walls, Roof and pillars 01
Fences 07
Shop/house wall 02
Water supply line 1
Trees
Fruit-0
Timber – 46
46
Electric poles 311
Telephone poles 247
Pre cast drainages 17414
Source – Resettlement survey and SIA for Ampara District – 2010
Most affectees have more than one type of loss. See annex 2 for details.
3. Socio-Economic Profile and Vulnerability of PAPs
The PAPs belong to 109 households. About 20 percent of affected persons are reported as
women. Majority of PAPs are Muslim followed by Sinhala and Tamils. These roads serve all the
3 communities who live in close proximity to these 11 roads.

iii
Agriculture is the main source of income but prices of agricultural goods are impacted by
middlemen who fix prices arbitrarily due to lack of access of farmers to markets as a result of
poor roads This also prevents other wholesale buyers from coming to these areas to buy the
agricultural produce.
Ampara district is one of the poorest area of the country and most the families of PAPs can be
categorized as families close to the poverty line of the country. Underemployment is common in
this area and some PAPs are involved in small business activities such as shops/boutiques.
Ampara district is comprised with flat and or undulate terrain. Besides being a poor region,
Ampara also lies in to the conflict areas and thus is impacted economically.
The project has developed a conflict filter that will be monitored during implementation.
4. Resettlement Policy and Entitlements
The policy and entitlements in this project have been built upon the requirements of the
Government of Sri Lanka, principally the Land Acquisition Act (1950 and revised in 1979) and
the National Involuntary Resettlement Policy (2001) and also World Bank‘s Policy on
Involuntary Resettlement (O.P. 4. 12). Provisions and principles adopted in this RAP will
supersede the provisions of relevant acts or laws currently in force in Sri Lanka wherever a gap
exists or a waiver is required to meet the standards established in the National Involuntary
Resettlement Policy and World Bank‘s policy.
The Project entitlements have been designed to provide compensation, resettlement and
rehabilitation for lost assets and restore or enhance the livelihoods of all categories (directly and
indirectly affected, title holders and non-title holders) of affected people. Detail project
entitlement matrix is discussed in chapter 4.
5. Implementation Arrangements and Budget
The Project Director with support from the PIU along with the Provincial Directors will be
responsible to implement the project. Most of the issues related to resettlement have been
identified and mitigation provided in the RAP. The existing implementation arrangements for
implementing the RAP and the budgets are provided in chapter 7. Under the Entitlement matrix
all affected assets/infrastructure/livelihood etc. affected will be replaced/restored. The roles and
responsibilities of the different players are also identified in the RAP.
6. Participation and Grievance Redress Mechanism
The RAP follows the SIMF in the procedures for redressal and mitigation of the negative impacts.
The public will be informed about the grievances redressal mechanism and the PRDD will
continue informing the new development of the project to the public through the identified
communication and public awareness mechanism. Details are provided in chapter 6.

iv
The Grievances Redress mechanism is a multi-tiered one and aims to respond to the requirements
of the project over its life cycle. For minor matters the GN and the social staff of the project will
be responsible to respond to them. At the next level, complaints can be registered in the office of
the SE/DE through entering it in the complaint register. Complaints can be in verbal or written
forms but must be entered in the register. The complaints and their resolution status will be
closely monitored. At the next level the Grievance Redressal Committee can be called upon to
provide resolutions to complaints. Its composition and functions have been laid out in the RAP.
The RAP also provides a role to the Samatha Mandala (peace committee) established by the
Department of Justice.
7. Information Disclosure
Information disclosure is a very important aspect of the RAP and the project will ensure that all
relevant information is available to all stakeholders over the life of the project. Key information
on resettlement issues will be provided to the affected persons as well as the other stakeholders,
and agency staff in each sub project (road) area.
All Project documents including the SIMF were disclosed in May 2009 while the addendum/
revised SIMF were disclosed in October 2009. This will also be disclosed to the PAPs and other
stakeholder agencies through the existing mechanisms of communication. The executive
summary will be translated into the local languages and disclosed to all affectees, communities
and stakeholders. The PRDD will use its web-site also to disseminate the information of the RP.
8. Monitoring and Evaluation
A monitoring and reporting system has been provided in the RAP.
However, the project will improve the process of monitoring. The improved monitoring
mechanism will help to achieve following specific objectives.
(i) to ensure that the livelihood systems/ activities of the public are not disturbed by the
project
(ii) to monitor whether the time lines are being met;
(iii) to assess if compensation, rehabilitation measures are sufficient;
(iv) to identify problems or potential problems; and
(v) to identify methods for responding immediately to mitigate problems.
9 Total Cost of the Plan.
The impacted infrastructure and costs have been revisited with the new information and the
total cost of mitigation is SL Rs. 77057800/-

v
Acronyms
ADB Asian Development Bank
BP Bank Policies
CBOs Community Based Organizations
CV Chief Valuer
DCE District Chief Engineers
DE Divisional Engineer
DS Divisional Secretary
EP Eastern Provinces
FGDs Focused Group Discussions
GN Grama Niladari
GOSL Government of Sri Lanka
GRM Grievance Redress Mechanism
HIV/AIDS Human Immunodeficiency Virus/Acquired Immunodeficiency Syndrome
IEE Initial Environment Examination
IRP Involuntary Resettlement Policy
KIIs Key-Informants Interviews
LAA Land Acquisition Act
LARC Land Acquisition and Resettlement Committee
MC Municipal Councils
MLGPC Ministry of Local Government and Provincial Council
MOH Medical Officer of Health
NEA National Environmental Act
NGOs Non-Governmental Organizations
NIRP National Involuntary Resettlement Policy
OP Operation Procedures
PAP Project Affected Person
PC Provincial Council
PD Project Director
PD Provincial Director
PEA Project Executing Agency
PIU Project Implementation Unit
PRDD Provincial Road Development Department
PS Pradeshiya Saba
RP Resettlement Plan
RDA Road Development Authority
SE Senior Engineer
SIA Social Impact Assessment
SIMF Social Impact Management Framework
SM Samatha Mandala
STDP Southern Transport Development Project
TOs Technical Officers
UC Urban Councils
UP Uva Province
WB World Bank

vi
Table of Contents 1 Project Background .................................................................................................................. 1
1.1 Scope of the Resettlement Plan 2
1.2 Summary of Key Issues ................................................................................................... 3
1.3 Methodology .................................................................................................................... 4
1.3.1 Study 1: Type of information collected by feasibility study (2008) ........................ 4
1.3.2 Study 2: The information collected for the Social Impact Management Framework and the
revised SIMF (February and October 2009) 4
Study 3: Information collected for the Social Impact Assessment and the RP (October 2009 and
August 2010) ..................................................................... 4
1.4 The consultations for the SIMF: ...................................................................................... 4
1.5 Organization of this report ............................................................................................... 5
2 Baseline Information of the country and the Project area ........................................................ 7
2.1 Profile of Sri Lanka .......................................................................................................... 7
2.1.1 Economy ..................................................................... 7
2.1.2 Important social indicators of Sri Lanka .................................................................. 8
2.1.3 Poverty and conflict: ..................................................................... 8
2.1.4 Provincial Road network. ..................................................................... 8
2.2 Socio-economic context in the project area. .................................................................... 9
3 Legal Frame work: National Policies and Social Safeguards Policies of the Bank ............... 11
3.1 Land Acquisition Act ..................................................................................................... 11
3.1.1 National Policy on Involuntary Resettlement ........................................................ 12
3.1.2 Other Laws and Regulations of the Country .......................................................... 13
3.1.3 Social Safeguards Relating to Project ................................................................... 13
3.2 Operational Policy-4.01-Environmental Assessment .................................................... 14
3.2.1 Operational Policy-4.04 –Natural Habitat .............................................................. 14
3.2.2 Operational Policy-4.10-Indigenous Peoples ......................................................... 14
3.2.3 Operational Policy-4.11-Cultural Property ............................................................ 15
3.2.4 Operational Policy-4.12 -Involuntary Resettlement .............................................. 16
3.2.5 Operational Policy 7.60- Projects in Disputed Areas ............................................. 17
3.2.6 Operational Policy 7.50-Projects in International Waterways ............................... 17
3.2.7 Operational Policy 17.50-Disclosure Policy .......................................................... 18
4 Mitigation Measures .............................................................................................................. 19
4.1 Project Resettlement Principles and Scope of Mitigation .............................................. 19

vii
4.2 The RP provides for the following good practices......................................................... 20
4.3 Impact Mitigation Modalities ......................................................................................... 21
4.4 Other principles to be followed by PRDD ..................................................................... 21
4.5 Voluntary land donation: ............................................................................................... 23
4.6 Mitigation of Impact on Houses: ................................................................................... 24
4.7 Mitigation of Impact on Commercial Center: ................................................................ 24
4.8 Mitigation of impact on Walls, Gates and Fences: ........................................................ 24
4.9 Provision of pre-cast drainage slabs: ............................................................................. 24
4.10 Mitigation of the Impact on Public Institutes, Religious and Cultural Places: .............. 24
4.11 Mitigation of Project Induced Economic Impacts: ........................................................ 24
4.12 Impact on Trees: ............................................................................................................ 24
4.13 The Entitlement Matrix: ................................................................................................. 25
5 Stakeholder Consultation ....................................................................................................... 27
5.1 Direct and Indirect Stakeholders .................................................................................... 27
5.2 Expectations and likely benefits .................................................................................... 27
5.3 Issues and concerns of stakeholders ............................................................................... 28
5.4 Consultation Strategy ..................................................................................................... 31
5.5 Disclosure of Information .............................................................................................. 32
6 Grievances Redressal Mechanism ......................................................................................... 33
6.1 Mechanism. .................................................................................................................... 33
6.2 Establishment of grievance redresses committee (GRC) for each project ..................... 34
6.3 Creation of Awareness of the Grievance Redressal Mechanism ................................... 35
6.4 Receiving Application for Redressal. ............................................................................ 35
6.5 Redressal Committee Meetings, Hearings, Proceedings and Recommendations. ......... 35
6.6 Implementation of Compensation. ................................................................................. 35
6.7 Public Awareness. .......................................................................................................... 35
7 Institutional Mechanism ......................................................................................................... 36
7.1 Roles and responsibilities............................................................................................... 36
7.2 The Divisional Secretary. ............................................................................................... 36
7.3 Monitoring and Evaluation Mechanism. ........................................................................ 36
7.4 Reporting........................................................................................................................ 37
7.5 Capacity Building Program ............................................................................................ 37
7.6 Resettlement Budget: ..................................................................................................... 37
Annexure

1
1 Project Background
1. The Government of Sri Lanka (GOSL) has requested financing from the World Bank (WB) to
undertake a Provincial Roads Improvement Project to upgrade and rehabilitate dilapidated provincial road
infrastructure. Provincial roads are the key connectors between the rural and the national networks. The
proposed project is aimed at improving the reliability and efficiency of management of provincial roads
that facilitate the access to provincial productive markets by (a) rehabilitating provincial roads
infrastructure in selected prioritized areas, and (b) supporting development of technical capacity at the
provincial level to improve their ability to manage their assets.
2. The proposed project is for the improvement of provincial roads in the Uva Province (UP), Ampara
district of Eastern Provinces (EP) and Jaffna from the Northern Province (NP), of Sri Lanka, and is being
prepared to provide beneficiaries with improved sustainable road transport by enhancing quality, durability,
efficiency, and economic benefits from the provincial road network. Furthermore, the project will enhance
the accessibility to the national road network in the UP the EP and the NP
3. The project plans to improve roads totalling 350 km in UP, EP and NP districts. This Resettlement
Action Plan only covers the 11 roads identified as priority roads in Ampara district of Eastern. Table
1.1 provides details of the roads covered in this RAP. The roads selected for Ampara have been
reconfirmed through consultations in the field while a similar exercise will be followed for selecting the
roads in Jaffna in the NP.
4.
Table 1.1: Roads selected in Ampara for this RAP
Table 01: List of Selected Roads
S. No. Road Code E.E. Division Road Name
Length of
Road
(km)
01 EPAMC016 Kalmunai Sainthamaruthu Kalmunaikudy Boundary Road. 1.10
02 EPAMC006 Kalmunai Natpaddimunai Pandiruppu Boundary Road. 2.50
03 EPAMC071 Kalmunai Akkarratpattu Neethai Ambalanoya 8.3
04 EPAMC007 Kalmunai Thirupothi Ammankovil Road. 1.20
05 EPAMC053 Kalmunai Central Road Ninthavur 1.30
06 EPAMC040 Kalmunai Karaipthivu Village Road. 2.10
07 EPAMC037 Kalmunai Viliniyadi Road 3.60
08 EPAMD059 Kalmunai Arasadi Field Road. 5.00
09 EPAMC039 Kalmunai Malwatta Suruipodai Road. 5.00
10 EPAMC091 Kalmunai Manal (Hijra) Road 1.80
11 EPAMC130 Ampara Damana Ambalanoya Pannalgama Road. 22.60
Total 54.5

2
5. The Resettlement Action Plan benefited from the work conducted under the SIMF and the Social
Impact Assessment that resulted in the:
Development and implementation of the social criteria for screening the roads
Identification of likely social impacts both positive and negative
Assessment of social safeguards triggered and
Development of mitigation measures
6. As a part of project preparation the roads were selected through a series of studies and consultation
exercises including the feasibility study conducted in 2008 where the selection criteria included among
other, poverty of the area, condition of the roads, access to services, connectivity, inclusion (access to all
ethnic groups) etc. This was strengthened through consultations held during March to June 2008 and
reconfirmed during the preparation of the Social Impact Management Framework and the Social Impact
Assessment in May 2009 and October 2009.
1.1 Scope of the Resettlement Action Plan:
7. The Bank‘s Policy on Involuntary Resettlement requires the preparation of a Resettlement Action
Plan if more than 200 persons are impacted negatively by any intervention funded by the World Bank.
Land acquisition is the trigger for this Operational Policy. The Resettlement Action Plan needs to be a
time-bound action plan with appropriate budget provisions and should be incorporated as an integral part of
the project design. Project Affected Persons (PAPs) are people of any age, skill level, or socio-economic
circumstance who may be losing land or assets/infrastructure/livelihood etc. Thus OP 4.12 requires that a
Plan be prepared that sets out all the compensation and rehabilitation support to be provided to any person,
family or household who on account of the execution of the project would have his/her or their standard of
living adversely affected. It focuses on those who may lose residential house, land including agricultural
and grazing land, commercial properties, tenancy, right in annual or perennial crops and trees or any other
fixed or moveable assets, income earning opportunities, business, occupation etc. These losses are
identified during the process of developing the resettlement plan.
8. Keeping in view the above, the objectives of this Resettlement Action Plan include the following
for the priority roads of Ampara:
Identification of affected persons, in order to determine the persons likely to be adversely impacted
by project works and the severity and extent of the respective impacts. This also includes as
assessment of impact on their assets, infrastructure, livelihood etc. located in the Right of Way
(RoW) or in the Corridor of Impact (CoI) of the selected project roads (along with an income and
asset survey).
Identify poor and vulnerable groups with strategies to ensure that such groups benefit from the
project
Ensure adequate stakeholder consultation and participation
Review of the legal and other management framework.
Develop mitigation measures in consultation with affectees/stakeholders
A detailed implementation plan
M&E and reporting system for the RAP
A resettlement budget.

3
1.2 Summary of Key Issues
9. The review of the existing land acquisition law and compensation process as well as discussion
with project affectees, stakeholders, PRDD staff and team members implementing other road projects has
led to a number of key conclusions being made in the resettlement plan. These are as follows:
a. Issues Relating to Compensation
The existing compensation process is unnecessarily complex and time consuming. APs can receive
up to four different payments with payments for each being made at different times. Further, there
is a provision in Sri Lanka‘s law for the compensation payment to be made in instalments that
further delays the receipt of full compensation by APs.
This prolongs the land acquisition process, effectively preventing APs from being able to make an
immediate start on restoration of their livelihoods. However, land acquisitions are not envisaged in
this Project and land requirements will be met through land donated voluntarily by individuals/
communities for the project. Therefore, compensation for land is not an issue.
b. Issues Relating to Grievance Redress
A grievance redress process will be established for the project. This along with the existing
mechanisms for conflict resolution will be implemented in a transparent manner.
c. Issues Relating to Consultation & Provision of Information
Prior to any investigation or commencement of surveys the project must establish a relationship
with the Provincial Directors, Divisional Engineers, Grama Niladaris, and also the Divisional
Secretaries along the subproject routes. Engaging in dialogues from the outset with affected people
and stakeholders through the existing communication structure will provide transparency and allow
for a consistent and clear message to be sent out regarding their rights and entitlements. Provision
of project information to affected communities and APs in a timely manner is critical.

4
1.3 Methodology
10. The data and information for the analysis of socio economic condition of the project area were
obtained from primary and secondary sources, The primary sources include feasibility studies carried by
ADB in 2008, consultations held with stakeholders including beneficiaries/affectees residing contagious to
the some of the selected roads, by the preparation missions, as well as information collected through field
visits, census of project affectees, surveys and consultations/focus group discussion undertaken for the
preparation of the SIMF, SIA and RAP. Secondary data included information of the Census and Statistics
Department, the PRSP Report and other publications of the World Bank.
1.3.1 Study 1: Type of information collected by feasibility study (2008)
11. Apart from data obtained from secondary sources, the consultants collected socio economic data
along with information through field surveys on road corridors and ROWs. The feasibility studies
undertook social feasibility of the proposed roads to assess the degree of social significance of improving
the roads; identified general issues; road specific issues (both positive and negative) proposals for
enhancing the positive impacts and mitigating the negative impacts etc. The study also undertook Initial
Poverty and Social Analyses. The identified properties that might be impacted positively or negatively
during the project implementation period include houses, commercial establishments, fences, boundary
walls, and road specific information such as dangerous road bends and sections that need expansion etc. of
the roads. They also undertook a review of all Bank‘s Operational Policies to determine if any were
triggered and if so, to provide mitigation measures.
1.3.2 Study 2: The information collected for the Social Impact Management Framework
(SIMF) (February 2009).
12. The consultations for the SIMF was carried out on all the roads screened out of the in the feasibility
study and selected to be a part of this project. These roads were reconfirmed by the communities through
consultations. In addition, information leading to the preparation of the stakeholders consultation strategy,
the grievance redressal mechanism, the entitlement framework, the implementation framework etc. were
collected, collated and the report prepared. The triggers for the social safeguards were also identified. The
Report thus provided the guidelines and procedures for the preparation of the Resettlement Plan.
1.3.3 Study 3: Information collected for the Social Impact Assessment and the RAP (May and
October 2009)
13. The Social Impact Assessment was launched for Ampara in October 2009 with the aim of
determining the magnitude of social impact on affectees and communities in terms of exact losses. This
included a census of all affected persons along with affected assets, infrastructure, livelihood, utilities to be
impacted, any land to be donated, any loss of access to houses or economic /income earning sources ( that
will need to be replaced) etc. Other information included an income/asset survey, a socio economic study
of the project area (macro information). An assessment of the social safeguards triggered and a revalidation
of information collected for the SIMF to enable the development of the social mitigation plans such as the
Resettlement Plan.

5
14. Thus the data collected for preparation of this Resettlement Action Plan of the Project include the
following:
Land required through voluntary donation
Houses affected
Commercial establishments impacted
Parapet walls, fences and gates to be demolished
Other structures such as wells, latrines etc.
Public institutions and religious/ cultural centres impacted
Public utilities impacted (including telephone, electricity etc.)
Privately owned trees to be removed
Any loss to income earning sources/loss of livelihood
Any squatters/encroachers that need to be removed temporarily
Loss of community owned assets/infrastructure etc.
15. The 100% household survey was carried out with owners of affected properties/assets/livelihood
etc., for the 11 roads.
The secondary data: Secondary data for preparation of this Resettlement Action Plan (RAP) was
collected mainly from documents of department of census and statistics and other similar studies
carried out in the country, along with use of World Bank publications.
Consultations: Stakeholder consultations were undertaken at all stages of the project, for
preparation of feasibility, the SIMF the SIA and RAP. The groups of people consulted include all
stakeholders. Special attention was paid to include women and all ethnic groups including Tamils,
Singhala and Muslims in the consultation process (For details please see chapter 5).
1.4 Organization of this report
The information of the (RAP is presented below and the chapters of the report are organized in the
following manner:
Chapter 1 - Introduction, Background and the Methodology
Chapter 2 - Descriptions of the Baseline Information and Socio Economic Impact of the project
(Resettlement Impact).
Chapter 3 - Review of Legal Framework and method of Disclosure of Information
Chapter 4 -. Mitigation Measures
Chapter 5 -The Stakeholder Consultation carried out in different stages of the project.
Chapter 6 - Grievances Redressal Mechanism
Chapter 7 - Institutional arrangements & cost for implementing the Resettlement Plan, M&E systems,
Awareness Raising of project stakeholders/training program and the Resettlement Budget

6
Annex
Annex1 - Socio Economic Data
Annex 2 - Detailed PAP list.
Annex 3- Details of Land Donors
Annex 4 - List of stakeholders
Annex 5 - Land donation forms
Annex 6 - Budget for Capacity Building

7
2 Baseline Information of the country and the Project area
2.1 Profile of Sri Lanka
16. The Democratic Socialist Republic of Sri Lanka (formerly known as Ceylon) is an island in the
Indian Ocean about 28 kilometres (18 miles) off the south-eastern coast of India with a population of about
19 million. Density is highest in the southwest where Colombo, the country's capital, main port and
industrial centre, is located. The net population growth is about 1.3%. Sri Lanka is ethnically,
linguistically, and religiously diverse1 .
17. Sinhalese make up 74% of the population and are concentrated in the densely populated southwest.
Ceylon Tamils, whose south Indian ancestors have lived on the island for a long time, total about 12% and
live predominantly in the north and east. Indian Tamils, represent about 5% of the population. Other
minorities include Muslims (Moors and Malays), at about 7% of the population, Burghers, (who are
descendants of European colonists, principally from the Netherlands and the United Kingdom (U.K.) and
the aboriginal Veddahs. Most Sinhalese are Buddhist; most Tamils are Hindu. The majority of Sri Lanka's
Muslims practice Sunni Islam. Sizable minorities of both Sinhalese and Tamils are Christians, most of
whom are Roman Catholic2.
2.1.1 Economy
18. Sri Lanka is a lower-middle income developing nation with a Gross Domestic Product of about
$23.5 billion. This translates into a per capita income of $1,200. Sri Lanka‘s 90 percent literacy rate in
local languages and life expectancy of 72 years rank well above those of India, Bangladesh and Pakistan.
English language is spoken by a large number of people.
19. Sri Lanka‘s income inequality is severe, with striking differences between rural and urban areas.
About a quarter of the country‘s population of 19.7 million remains impoverished.
20. Despite a brutal civil war that raged from 1983, economic growth averaged around 4.5% in the last
ten years. In 2001, however, GDP growth was negative (-1.4%), the only contraction since independence.
Growth recovered to 4.0% in 2002. Following the 2002 ceasefire and subsequent economic reforms, the
economy grew more rapidly, recording growth rates of 6.0% in 2003 and 5.4% in 2004. The economic
situation in Sri Lanka in 2005 was remarkably stable, despite the December 2004 Indian Ocean tsunami,
which killed 32,000 people, displaced 443,000, and caused an estimated $1 billion in damages. In 2007 the
growth was 6.8 percent.
21. The service sector is the largest component of GDP at 55.8%. In 2005-6, the service sector
continued its strong expansion, fuelled primarily by strong growth in telecom, trading and financial
1 Department of Census and Statistics, Government of Sri Lanka
2 ibid

8
services. The tourism sector suffered in 2005 following the tsunami. While beach resorts have been rebuilt,
tourism remains well below its potential.
22. Manufacturing accounts for about 16% of GDP. The textile, apparel, and leather products sector is
the largest, accounting for 39.5% of the total industrial output. The second-largest group in the industrial
sector at 22.4% of total manufacturing output is food, beverages, and tobacco. The third-largest group is
chemical, petroleum, rubber, and plastic products. The construction sector accounts for 7.2% of GDP and
has posted strong growth rates in 2005-6, Mining and quarrying accounts for 1.9%.
23. Agriculture has lost its relative importance to the Sri Lankan economy in the recent past. It employs
33% of the working population, but accounts for only 17.2% of GDP. Rice, the staple cereal, is cultivated
extensively. The plantation sector consists of tea, rubber, and coconut. In the recent years, tea has made
significant contributions to export earnings3 .
2.1.2 Important social indicators of Sri Lanka
24. According to studies by Centre for Economic and Policy Research, Sri Lanka has made significant
progress in the realm of social development over the last few decades, while also achieving impressive
economic growth. Sri Lanka‘s human Development index4 reflects this progress, improving over the years
from 0.616 in 1975, to 0.697 in 1990 and to 0.741 in 2000.
25. Sri Lanka's health and demographic indicators are comparable with those of far wealthier Asian
nations due to a wide range of pro-poor policies and programs including subsidized health and education,
targeted food subsidies, subsidized transport, and broad-based family planning services, which have been
in existence for several decades5 .
26. In 1960 Sri Lanka‘s life expectancy at birth was 60.1 years, in 1980 it was 67.6 years, and in 2000 it
had increased to 73.1 years.
2.1.3 Poverty and conflict:
27. The Eastern and Northern Provinces have been most severely affected by the decade-long fighting
and subsequent displacements. Many of the displaced people who returned to Eastern Province face a
challenging environment with restricted access to fields and fishing waters because of security reasons, and
difficulty in the restoration of civilian life due to the presence of paramilitary groups. Inadequate and
restricted transport services, poor quality roads, and access to credit remain the main impediments to
growth and poverty reduction. Before the conflict, the agriculture and fishing sector contributed a
substantial share to national GDP, but now, due to transportation difficulties and the trade embargo,
commercial agriculture in the East has transformed into subsistence agriculture.
2.1.4 Provincial Road Network.
28. The provincial road network, estimated at about 15,700 km6, constitutes about 14 percent of the
country‘s total road network. It provides the key connection between the rural and the national networks.
3 World Bank, Bureau of South and Central Asian Affairs October 2006 4 World Bank, Center for Economic and Policy Research
5 Government of Sri Lanka, Connecting to Growth: Sri Lanka‘s Poverty Reduction Strategy, June 2002. pp 89
6 Public Expenditure Review of Provincial Roads in Eastern, North Central and Uva Provinces.

9
Due to the long-running conflict and a lack of consistent funding for provincial roads over the past 20
years, little maintenance or rehabilitation of the network has taken place. The roads in the provincial
network are mostly in an advanced state of deterioration, with extensive pot holing, breakup of bitumen
surfacing, broken and inadequate culverts and pavement failure. Only 9 percent of the provincial roads
(total 1098 km) in Eastern Province and 21 percent in Uva Province (total 1741 km) are in good condition.
These roads were recently rehabilitated under the Asian Development Bank (ADB)-Financed Road Sector
Development Project. The mountainous topography of Uva contributes to the poor quality of the road
network, through increasing the rate of road deterioration, and by increasing road maintenance and
construction costs.
29. The road net work as a whole play a significant role in providing inputs for economic development.
Improved roads net work opens the rural areas to the urban centres. Similarly roads are also instrumental in
connecting urban centres to the international markets. Thus road improvement projects contribute to a
country by opening its economy to the international markets and at the local level, they contribute to
regional economic development and help reduce poverty.
2.2 Socio-economic Context in the Project Area.
30. The project covers the Uva Province (UP) a section of the Eastern province (EP) and Northern
Province (NP) that have distinct geographical and socio-economic characters. The district of Ampara has a
flat terrain and is mostly covered with paddy fields and forest reservations while many areas of the UP are
covered by steep range of mountains
31. Ampara District is Eastern Province‘s highest populated district, with 589344 persons. Agriculture
to be the main occupation in the project areas and there are some small and medium scale industries such as
garment factories, mining and tourism industries, trade, etc.
32. Agriculture and fisheries are the main sources of income of the people in the area. But the income
generated through agriculture is seasonal and fluctuates according to the market trend, and the prices of
agricultural products tend to get fixed by a few middlemen who have links with urban centres. Farmers are
unable to sell their products to the urban buyers due to lack of proper transportation in the area and are thus
dependent on middlemen who have a monopoly of the farmer‘s products and can exploit them. As a result
farmers are unable to improve their income. It is hopes that improved roads will help improved the farmers
income and bargaining position.( see annex for details)
33. Of the 3 districts Badulla has the highest urban population while, Monaragala and Ampara are
typically rural with small urban population. This project is expected to focus on upgrading, rehabilitating
and maintaining the priority provincial roads in UP and Ampara District of EP where provincial roads are
considered to be the key connectors between the rural and the national networks. In the long run, the
project will help improve the livelihood of people in these districts, ushering in many positive social
impacts
34. The Uva Province comprises two districts namely, Badulla and Monaragala. Badulla has the
somewhat urban and Moneragala is predominantly rural. Agriculture is the main occupation. Some few
areas of the province suffered considerably from ethnic conflict. Badulla is a multi-ethnic district, with the

10
majority being Sinhala (558,218). The second largest ethnic group in the district is Indian Tamil (141087).
Ethnic composition of Ampara differs from Badulla and Monaragala. (See details in table 2). The largest
Sri Lankan Moor population (245,089) is found in the Ampara.
35. Gender has been a focus of the RP and about15 percent of the affectees are women, all of whom
have been consulted and their opinion used to inform the RP.
Table 2.1: Ethnic Representation of Ampara District and Uva in Project Area – Year 2001
District Sinhala SL Tamil Indian Tamil SL Moor Burgher Malay SL Chetty Bharatha Other
Ampara 231,771 110,180 410 245,089 1,008 169 6 1 710
Badulla 558,218 32,230 141,087 40,455 606 1,390 112 21 436
Monaragala 374,553 5,579 7,660 8,047 113 83 19 1 118
Source: Census of Population and Housing 2001, Department of Census and Statistics
Administrative Units:
36. There are two administrative systems in all districts, namely, the central government/state
administration and the provincial council (PC) administration7. The portfolio of tasks is defined in the
constitution and the Provincial Council Act. Public roads are divided into 4 categories, where category A
and B are administered by the central government and its ministries, departments, authorities, institutions,
etc, while category C and D roads are administered by the respective PCs. Other rural and municipal roads
are managed by Pradeshiya Saba (PS) and Municipal Councils (MC) or Urban Councils8 (UC).
7 The provincial council administration was introduced in 1987 after the 13th amendment to the constitution. 8 Municipal Councils, Urban Councils, and Pradeshiya Sabas are constituted by local level politicians and their administration of respective areas.

11
3 Legal Frame work: National Policies and Social Safeguards Policies of the Bank
37. The mitigation measures will be implemented under the national laws and policies of Sri Lanka as
well as the World Bank. The relevant polices and laws are described in this chapter.
Sri Lanka’s Laws and policies
Land Acquisition Act
The law governing acquisition of land for public purposes is the Land Acquisition Act (LAA), enacted in
1950 and which has been the subject of several amendments and revisions, the latest being 1979. The LAA
sets out the procedures for acquiring land and for payment of compensation for acquired land.
A notice is issued specifying that land is potentially required for a public purpose, and this permits
authorized personnel to undertake investigations (surveys, boreholes, and setting out of boundaries etc) to
determine suitability. If the land is deemed suitable for the public purpose a written declaration to that
effect is made, and notices are issued describing the land, the intention to acquire the land, and requiring
that persons with an interest in the land notify (in writing) the acquiring officer of their claim (including the
expected amount of compensation).
The acquiring officer then holds an inquiry into the market value of the land, the claims for compensation,
and the respective interests of the claimants, as well as any other related matters. At the conclusion of the
inquiry the acquiring officer either makes a decision on the claims or refers the claims to the District Court
or Primary Court.
Following the decision (either by the acquiring officer or the courts), the acquiring officer makes an award
determining the persons who are entitled to compensation, the total amount of compensation deemed to be
allowed for the acquisition, and the apportionment of the compensation between the persons with interest
in the land. In the event of a dispute over the determination, it may be appealed to either the compensation
Review Board or Court of Appeal (on questions of law following a decision by the Compensation Review
Board), provided that the appeal is lodged within 21 days of receipt of notification of the award.
Provided that there are no appeals, the compensation is paid (the LAA allows for an initial payment and the
remainder to be paid in instalments). If the person with an interest in the land has agreed to a land exchange
in lieu of cash, the transfer is put into effect at this time. After the awards are made the Minister publishes
or gazettes a ―vesting order‖ for the possession of the land, after which time occupants of any buildings
located on the land to be vested are given notice to vacate.
One of the inadequacies of the LAA is that the onus to prove ownership or interest in, demonstrate clear
title to, gather all information and submit a compensation claim in respect of land to be acquired, is on the
AP. Often APs are not aware of their rights or timeframes to be observed under the LAA, or they are aware
but are ill-equipped to deal with the procedures required and are also not experienced in dealing with
various officials and documentation.

12
38. APs often face serious delays in the land acquisition process due to inquiries that can go on for
several days, and the fact that they are conducted by Divisional Secretaries who often do not have
experience or are unable to interpret legal documents or decide complicated.
39. As noted earlier the LAA provides for an initial payment (Rs25,000) and then the balance of
compensation which is to be paid ―…in not more than ten equal instalments, so that the entire balance
compensation is paid before the lapse of ten years from the date of payment of the said sum of Rs 25,000‖
[Section 29 (ii)]. Clearly, so as to permit APs to restore their livelihoods within a short a period as possible
after the time of land acquisition, payment of compensation and allowances (and initiation of livelihood
restoration and support measures) must be effected in a lump sum.
40. It is clear that the compensation process as set out in the LAA is inherently flawed, APs can receive
up to four different payments at different times (the statutory compensation (Section 17 of the LAA), the
―top-up‖ compensation referred to as the LARC payment, the ex-gratia payment, and then interest on any
compensation amount not paid) and the statutory payment can be paid in instalments therefore, further
delaying the receipt of full compensation. This prolongs the land acquisition process, effectively prevents
APs from being able to immediately restore their livelihoods.
3.1.1 National Policy on Involuntary Resettlement
The objectives of the NIRP:
Avoid, minimize and mitigate negative impacts of involuntary resettlement by facilitating the re-
establishment of the affected people on a productive and self sustaining basis. The policy should
also facilitate the development of the APs and the project;
Ensure that APs are fully and promptly compensated and successfully resettled.
The livelihoods of any and all displaced persons should be re-established and their standard of
living improved;
Ensure that no impoverishment of people shall result as a consequence of compulsory land
acquisition for development purposes by the state;
Assist APs in dealing with the psychological, cultural, social and other stresses caused by
compulsory land acquisition;
Make all APs aware of processes available for the redress of grievances that are easily accessible
and immediately responsive; and
Have in place a consultative, transparent and accountable involuntary resettlement process with a
time frame agreed to by the project executing agency and APs.

13
41. Adhering to the foregoing objectives, the scope of the NIRP includes all development induced land
acquisition, or recovery of possession, by the State. The NIRP requires that a comprehensive resettlement
action plan be prepared where twenty or more families are affected. In cases where less than twenty
families are affected the NIRP still requires a plan but states that this can be prepared to a lesser level of
detail. The NIRP applies to all projects regardless of source of funding.
42. The Ministry of Lands (MOL) has the overall institutional responsibility for implementing the
NIRP, and has established a Resettlement Division to coordinate implementation. A number of technical
guidelines are provided to assist the MOL and project executing agencies in planning, implementing,
monitoring and evaluating all involuntary resettlement impacts.
43. Four sets of guidelines have so far been prepared. Copies of the guidelines are available from
MOL. Sinhalese and Tamil translations of the documents are currently being prepared. With support from
ADB, over 130 persons from Government, NGOs, universities, district and divisional administrations, and
local authorities have been trained in involuntary resettlement.
3.1.2 Other Laws and Regulations of the Country
44. Sri Lanka has various laws established to ensure fair and equitable decisions taken on various issues
related to people of the country. These laws are not explained in detailed in this section but they are
referred here to substantiate the availability of the required legal provisions of the country. The key laws
available for the social safety system in the country are mentioned below.
Provincial Council Act
Act for labour conflict resolution- Act number 43 of 1950
Industrial regulation act of Sri Lanka
The employee compensation act
Act of labour unions
The act of employment of women, teenagers and children
Special act of discontinuation of employments.
Maternity assistance act (provisions for maternity leave, Maternity assistance, payments of salaries
of mothers etc are covered under this act- This is exclusively focused on Women)
Act of employees provident fund
Act for payment of bonuses to the employees
Act for employment of women in mining industry (exclusively focused on women)
National Child Protection act
National Thoroughfares Act
Rent Act no 7 of 1972 and the Ceiling on House Property Law No.1 of 1973
3.1.3 Social Safeguards Relating to Project
45. The environmental and resettlement related regulations and guidelines of the World Bank have been
spelled out in the World Bank Operational Manual comprising documents relating to Operational Policies

14
(OP) and Bank Procedures (BP). For the purpose of this report references have been made to Operational
Policies. The applicable safeguard policies of the Bank in case of rehabilitation project are:
Operational Policy 4.01 Environmental Assessment
Operational Policy 4.04 Natural Habitats
Operational Policy 4.10 Indigenous People
Operational Policy 4.11 Management of Cultural Property
Operational Policy 4.12 Involuntary Resettlement
Operational Policy 4.36 Forests
Operational Policy 7.60 Projects in Disputed Areas
Operational Policy 17.50 Disclosure of Operational Information
Provisions of Bank’s Safeguards Policies
46. The World Bank‘s Safeguards Polices are described in the section below with indication on OPs
that are triggered in the Project, based on the field investigations/consultations/surveys undertaken.
3.2 Operational Policy-4.01-Environmental Assessment
47. Operational Policy 4.01 identifies the general policy of the World Bank about the EIA, lays down
the procedures and guidelines for conducting EIA of the projects including the aspects to be considered in
EIA, public consultation and information disclosure procedures. This policy requirement has already been
investigated by the project in the initial stage. The essential actions to be taken in response to this policy
have been addressed in the environmental management plan already prepared (EMP).
3.2.1 Operational Policy-4.04 –Natural Habitat
48. Operational Policy 4.04 deals with the conservation of natural habitats. Similar to OP 4.01 the
requirements of the OP 4.04 have been addressed in the EMP prepared for the project.
3.2.2 Operational Policy-4.10-Indigenous Peoples
49. Definition of Indigenous People: The Provincial Roads will use the World Bank‘s guidelines to
identify IPs in particular geographic areas by examining the following characteristics:
Close attachment to ancestral territories and natural resources therein;
Self-identification by the IPs themselves and identification by others as members of distinct
cultural groups;
Use of an indigenous language often different than the predominant language (even if they use
other languages in dealing with the non-indigenous peoples);
Presence of customary social and political institutions; and
Presence of a primarily subsistence production system.

15
50. In fostering full respect for their dignity, human rights and cultural uniqueness, a Bank-financed
project has to ensure that indigenous peoples do not suffer adverse impacts in the development process, and
that they receive culturally compatible social and economic benefits. The Bank policy (OP 4.10 on
Indigenous Peoples) requires that the sub-projects be carefully screened to identify whether there are
indigenous peoples living in the project areas, and that informed participation of the IPs themselves must
be undertaken to identify local concerns and preferences through direct consultations with the IPs and
incorporation of indigenous knowledge into project planning approaches. This policy contributes to the
Bank‘s mission of poverty reduction and sustainable development by ensuring that the development
process fully respects the dignity, human rights, economies, and cultures of Indigenous Peoples. For all
projects that are proposed for Bank financing and affect Indigenous Peoples, the Bank requires the
borrower to engage in a process of free, prior, and informed consultation. The Bank provides project
financing only where free, prior, and informed consultation results in broad community support to the
project by the affected Indigenous Peoples. Such Bank-financed projects include measures to (a) avoid
potentially adverse effects on the Indigenous Peoples‘ communities; or (b) when avoidance is not feasible,
minimize, mitigate, or compensate for such effects. Bank-financed projects are also designed to ensure that
the Indigenous Peoples receive social and economic benefits that are culturally appropriate and gender and
inter-generation inclusive. As proposed in the project , the roads require only rehabilitation, paving and
some widening ( but within the ROW) and the consultations held under the Social Impact management
Framework and the Social Impact Assessments did not identify any indigenous people as defined by OP
4.10 in the project area. Hence this Policy is not triggered. However, during implementation, should any
such group get identified the Project will prepare an Indigenous Peoples Development Plan (IPDP) in
conformity with OP 4.10, get it cleared by the Bank and implement it.
3.2.3 Operational Policy-4.11-Cultural Property
51. This policy addresses physical cultural resources, which are defined as movable or immovable
objects, sites, structures, groups of structures, and natural features and landscapes that have archaeological,
pale-ontological, historical, architectural, religious, aesthetic, or other cultural significance. Physical
cultural resources may be located in urban or rural settings, and may be above or below ground, or under
water. Their cultural interest may be at the local, provincial or national level, or within the international
community.
52. The Bank assists countries to avoid or mitigate adverse impacts on physical cultural resources from
development projects that it finances. The impacts on physical cultural resources resulting from project
activities, including mitigating measures, may not contravene either the borrowers‘ national legislation, or
its obligations under relevant international environmental treaties and agreements. The Bank adheres to the
following project financing policies:
The Bank finances only those projects that are sited and designed so as to prevent significant
damages to non-replicable cultural property. This policy pertains to any project where the Bank is
involved, irrespective of whether the Bank is itself financing the part of the project that may affect
cultural property.
Deviation from this policy may be justified only where expected project benefits are great, and the
loss of or damage to cultural property is judged by competent authorities to be unavoidable, minor,
or otherwise acceptable. The Bank also requires a discussion with specific details for their
justification in the documents.
The Social Impact Assessment did not identify any cultural property in the project site,
however, should any such site get identified, the Project will do the following: Whenever chance
finds are made during the construction of the roads, the contractor will immediately inform the project

16
execution agency which will, in turn, inform the government department concerned with cultural
property.
The project execution agency will be responsible for securing the artefacts from theft, pilferage and
damage until the responsibility is taken over by the relevant authorities.
Failure to report a chance find immediately by the contractor will result in cancellation of the
contract and punishment according to the relevant laws.
These conditions and procedures regarding chance finds will be included as standard provisions in
the construction document in details and made available for IDA review and other interested
persons and entities.
3.2.4 Operational Policy-4.12 -Involuntary Resettlement
53. This policy deals with the issues and concerns related to land acquisition, their compensation for all
categories of affectees and affected assets, relocation, resettlement, loss of livelihood, access and related
issues.
54. If involuntary resettlement is not properly mitigated it creates severe economic, social and
environmental problems, people face impoverishment when their productive sources are lost, people are
relocated to such environment where productive skills are not properly utilized, the competition for
resources is increased, the community institutions and local networks are weakened.
55. Where it is not feasible to avoid resettlement, these activities should be conceived and executed as a
sustainable development program. Displaced persons should be properly consulted and should have
opportunities to participate in planning and implementing resettlement programs.
56. The Bank policy covers direct economic and social impacts that result from Bank assisted
investment projects and are caused by the involuntary resettlement. The following are the main objectives
of Bank‘s policies:
Involuntary resettlement should be avoided up to the possible limit or minimized by exploring
other viable alternatives;
Where it is not feasible to avoid, resettlement, resettlement activities should be conceived and
executed as sustainable development program, providing sufficient investment resources to
enable the persons displaced by the project to share in project benefits;
Displaced persons should be assisted in their efforts to improve their livelihoods and standards
of living or at least restore to the extent of pre-displacement levels.
57. Displaced persons may be classified into: i) those with formal legal rights to land (including
customary and traditional rights recognized under the law of the country) ii) those who do not have formal
legal rights to land at the time the census begins but have a claim to such land or assets—provided that
such claims are recognized under the law or become recognized through a process identified in the
resettlement plan. iii) Those who have no recognizable legal right or claim to the land they are occupying.
Although there is no land acquisition envisaged nor is there any resettlement or relocation, but OP
4.12 has been triggered to deal with all types of negative social impacts that need to be compensated/
replaced/restored. The prescribed responses to adverse impacts are presented in the form of an
Entitlement Matrix which is a part of the Resettlement Plan.

17
58. In addition, for all cases of voluntarily donated land the project requires a participatory and
transparent process to be followed and an agreement/MOU to be signed between the donor and the
recipient that will among other ensure i) the ownership of the land and voluntary nature of the donation,
ii) that the land is appropriate for the intended purpose iii) that the land does not belong to any donor who
is below the poverty line or whose holding would be reduced below the minimum size as stipulated to be
economically viable ( 2.5 acres) iv) that there are no encumbrances on the land, v) that it does not
negatively impact on the livelihood of any vulnerable group, and if so, that community developed
mitigation measures are acceptable to the affectees, vi) that no compensation will be paid for the land, and
vii) that the owner gives up all claims on the land and the title will be transferred to the recipient through
the notary public or a registered deed or any other procedure prescribed by the law of the state. ( See annex
4 for the form)
3.2.5 Operational Policy 7.60- Projects in Disputed Areas
59. Projects in disputed areas may raise a number of delicate problems affecting relations not only
between the Bank and its member countries, but also between the country in which the project is carried
out and one or more neighbouring countries. In order not to prejudice the position of either the Bank or the
countries concerned, any dispute over an area in which a proposed project is located is dealt with at the
earliest possible stage.
The Bank may support a project in a disputed area if the governments concerned agree that, pending the
settlement of the dispute, the project proposed for country A should go forward without prejudice to the
claims of country B. This policy is not triggered.
3.2.6 Operational Policy 7.50-Projects in International Waterways
60. This policy applies to the following types of international waterways:
(a) any river, canal, lake, or similar body of water that forms a boundary between, or any river or body
of surface water that flows through, two or more states, whether Bank members or not;
(b) Any tributary or other body of surface water that is a component of any waterway described in (a)
above; and
(c) any bay, gulf, strait, or channel bounded by two or more states or, if within one state, recognized as
a necessary channel of communication between the open sea and other states—and any river flowing
into such waters
Projects on international waterways may affect relations between the Bank and its borrowers and
between states (whether members of the Bank or not). The Bank recognizes that the cooperation and
goodwill of riparian is essential for the efficient use and protection of the waterway. Therefore, it
attaches great importance to riparian‘s' making appropriate agreements or arrangements for these
purposes for the entire waterway or any part thereof. The Bank stands ready to assist riparian in
achieving this end. In cases where differences remain unresolved between the state proposing the
project (beneficiary state) and the other riparian, prior to financing the project the Bank normally urges

18
the beneficiary state to offer to negotiate in good faith with the other riparian to reach appropriate
agreements or arrangements. This policy is not triggered.
3.2.7 Operational Policy 17.50-Disclosure Policy
61. ―The Bank reaffirms its recognition and endorsement to the fundamental importance of
transparency and accountability of the development process. Accordingly, it is the Bank‘s policy to be
open about its activities and to welcome and seek out opportunities to explain its work to the widest
possible audience.‖ 9 Thus all Bank funded documents are to be widely disseminated and accessible to all
affectees and stakeholders. This Policy is triggered: Thus in accordance with the Disclosure Policy of the
World Bank, the Social Impact Management Framework (SIMF) has been disclosed at the info shop and
the Project sites, viz., Project Offices and Public Libraries. The Executive Summaries of all the documents
will be translated into local languages (both Tamil and Sinhalese) will also be disclosed at the Project site
where it will be accessible to affectees. The revised Resettlement Plan (RP) too will be disclosed in the
project sites and in other appropriate locations such as Grama Niladharies‘ offices in the local area. The
executive summary will be translated into the local languages and disseminated in a similar manner. In
addition the web site of the provincial Roads department will be used for wider dissemination of the RP.
9 The World Bank Policy on Disclosure of Information (2002)

19
4 Mitigation Measures
62. This and the following chapters discuss the mitigation measures proposed in the Resettlement Plan.
4.1 Project Resettlement Principles and Scope of Mitigation
63. The basic resettlement principles of the RAP are as follows:
The affected persons (APs) are defined as those who stand to lose land, houses, structures, trees,
crops, businesses, income and other assets as a consequence of improvements to/or improvement
of the project‘s roads.
Cut-off dates will be established to determine compensation eligibility of persons and their assets.
These are the dates on which census of the affected persons and their assets will be taken. Any
claim for compensation by affected people after the cut-off date will be ineligible for compensation.
For the roads in table 1 the cut-off date was May 7, 2009
All APs are equally eligible for cash compensation and rehabilitation assistance, irrespective of
their land ownership status, to ensure that those affected by the Project shall be at least as well off,
if not better off, than they would have been without the Project. Absence of a title will not be a bar
to receiving compensation and livelihood assistance, (except for land where a title is required).
All losses will be compensated at replacement cost, at market prices without deducting depreciation
and salvage value for all losses (such as lands, crops, trees, structures, businesses, etc.).
Alternatively structures/assets etc. will be rebuilt by the project at replacement cost.
In case cash/cheques compensation, Provincial Project Director -PRDD of Eastern Province- shall take a
valuation (estimate) report for affected structures from Chief Valuer of Valuation Department. Estimation for
crop/tree has to be taken from officer of relevant institutes (eg. for agriculture crops has to be taken from
Agriculture Instructor of Department of Agriculture). Based on the valuation, after the recommendation by
The Resident Engineer, the payment will be made by the Provincial Project Director.
Encroachers in this context are defined as people occupying legal or customarily recognized
properties on public space in the ROW.
Squatters are defined as those that occupy space that is legally or customarily someone else‘s, in
this case the ROW.
It is not the usual practice to get the ―No objection‖ certificate from the Government before award the
contract. The normal practice is, start the compensation events after awarding the civil contracts through
Contractors.
Accordingly, structures demolition, relocation and other related compensation events have been included in
the civil work contracts as BOQ items. Therefore it is the responsibility of the Contractors to carry out these
activities. The Engineer of the Contract is responsible to get this work done through the Contractor.
Therefore, execution of the Contract means the completion of the entire physical targets including social
events listed in the Contract.
APs will be systematically informed and consulted about the project, and the RP will be made
available in both English and local languages to the affected persons and communities.
The consultative process shall include not only those affected, but also the adjacent communities,
representatives of the local governments of the areas where the project is located, community
leaders, local government, and community-based organizations (CBOs). Vulnerable groups
(households below the recognized poverty line; disabled, elderly persons or female headed
households) should be identified and included in the consultation process. The Project will not

20
acquire land but depend on donated land where an Agreement will be signed laying out the terms
and conditions
Contractors will also follow the same principles (i.e. payment of compensation for all losses
incurred etc.)
The Contract shall prepare a traffic management and diversion plan and submit to the Consultant and take a
clearance/approval from the Engineer. Social Specialist of the Consultancy is responsible to carry out
awareness among the general public and road users and to get the clearance for approved traffic management
and diversion plan.
The proposed RAP will apply to all Project Affected Persons who may be impacted through
impacts on private/community land or other assets due to minor realignments.
Where community owned facilities or restricting access to common property resources etc., result
from project related interventions, the project will rebuild such facilities and provide alternative
access.
There will be no land acquisition in the project. Any land that is required will be voluntarily
donated or the project will use land owned by the government. For any voluntarily donated land, a
participatory and transparent process will be followed and an agreement/MOU will be signed
between the donor and the recipient that will among other, ensure ) the ownership of the land and
voluntary nature of the donation, ii) that the land is appropriate for the intended purpose iii) that
the land does not belong to any donor who is below the poverty line or whose holding would be
reduced below the minimum size as stipulated to be economically viable ( 2.5 acres) iv) that there
are no encumbrances on the land, v) that it does not negatively impact on the livelihood of any
vulnerable group, and if so, that community developed mitigation measures are acceptable to the
affectees, vi) that no compensation will be paid for the land, and vii) that the owner gives up all
claims on the land and the title will be transferred to the recipient through the notary public or a
registered deed or any other procedure prescribed by the law of the state. The agreement will be
signed in presence of the DS and his/her signature will be placed as a third party.
Any land (land with structures/land without structures) to be required for road construction will be obtained
only based on land donation agreement signed between relevant parties. All the terms and conditions will
apply to the same.
In case any person will not meet land donation conditions such as donors include below poverty line, it
negatively impact on the livelihood of any vulnerable group and etc. mentioned under the 4.1, PIU shall
identify person /persons and offer training and provide necessary financial support to initiate suitable income
generation activity to rebuild/improve the livelihoods.
The Project executing agency will bear the costs of implementing this Resettlement Action Plan.
4.2 The revised RAP provides for the following good practices
Place all sign boards where it is necessary indicating maximum speed limits.
Place pedestrian crossing lines (zebra crossing) where it is necessary, particularly near the schools,
religious places, government establishments, hospitals, town sections, etc.
Make aware all contractors and supervisors on the importance of villagers‘ privacy and their
freedom to engage in their customary duties and tasks.
The Contractor is responsible to create awareness of preventing HIV/AIDS among the migrated
workers in all project sites.

21
4.3 Impact Mitigation Modalities
64. The following types of losses are expected to result from Project intervention and will be mitigated.
Temporary displacement of mobile vendors and other vulnerable encroachers. The project will
ensure that their livelihood is not affected by helping to relocate them during the construction phase
and they may return to their original place subsequently.
Encroacher owners of the affected businesses will be compensated for temporary loss of income
based on net income, or an one-time lump sum grant
Where physical assets of affectees (walls, gardens, gates, etc.) located in the ROW come in the
project‘s area of construction, the facility will be rebuilt or the owners will be compensated at
replacement cost.
The project will identify and implement policies to mitigate any adverse impacts that may appear
during implementation of the project.
4.4 Other principles to be followed by PRDD
Provide opportunities for all affected persons to interact with the PRDD
Opportunities will be provided to the affected persons to discuss the design of the structures to be
rehabilitated or reconstructed. They will also be given opportunities to know about the construction
material to be used, and the timeframe required to complete the construction work
Throughout the reconstruction period of the affected structures the relevant PAPs will be given
opportunities to act as informal supervisors to get a good structure constructed to replace their
affected properties.
The project will consider the option of keeping the communities involved in the maintenance of the
roads
65. In response to the requests from the affected communities, PRDD has agreed to the following:
Since the roads are narrow to ensure that construction work is completed on time
Provide alternate routes to traffic and ensure safety of road users
Proper direction to Contractors to maintain high quality/ standards in construction activities.
Providing retaining walls where there may be landslides and serious erosions as a result of
construction activities.

22
Table 4.1 Affected families, Affectees Amount properties & Losses by types in 11 roads of
Ampara
Types of Properties Affected
families
Number of
Affectees ( Family
members)
Amount of
Properties/land lost
Lands
15 71 19
Boundary walls gates and
toilet pits
03 17 03
Boundary walls and gate 49 243 53
Boundary walls 21 71 21
Boundary wall, Roof and
pillars
01 04 01
Fences 06 32 06
Shop/house wall 02 04 01
Water supply line - - 01
Trees
Fruit-0
Timber – 46
12 52 46
Electric poles - - 311
Telephone poles - - 247
Pre cast drainages - - 17414
Total 109 494

23
Table.- 4.2 Severity of the impact
Types of Properties Severity of the Impact
Land
Moderate- It has been recorded 3675m2
from 15 families with 71 affectees.
Boundary walls Moderate- 74 boundary walls to be
demolished.
Roof and pillars Minor- there is 01 roof and pillar will be
affected.
Fences Minor- Only 06 wire fence to be shifted for
maintaining the road width.
Gates Moderate- There are 52 gates to be shifted
Toilet pits Minor- Only 03 toilet pits
Front of shop/house Minor- Only 02front of shop house to be
demolished.
Water supply line Minor- 1 water supply unit to be shifted.
Trees
Fruit-0
Timber – 46
Minor/moderate- 46 timber trees to be
removed from 12 families
Electric poles -
Telephone poles -
Pre cast drainages -
Most affected families have more than one type of loss. See annex 2 for details
Source: SIA/RP survey -2009/2011
4.5 Voluntary land donation:
Small lands stretches approximately 3675m2 are required from 15 PAP families to maintain the
proposed road width in some of the roads. Since the project is not envisaged land acquisition, the
required lands will be donated voluntarily.

24
4.6 Mitigation of Impact on Houses/shops:
The only impact on houses is damaged to the front of shops/huts/houses that extends into the
proposed road width for rehabilitation, all of which will be replaced (at the same or better quality)
or compensated at replacement cost.
4.7 Mitigation of Impact on Commercial Centre:
There is no impact on any commercial or business centre on the 11 roads in this RAP
4.8 Mitigation of impact on Walls, Gates, Fences and Pavements:
This is the major impact of these roads. The contractors will rehabilitate/replace all these affected
structure. Many of the fences (made of bushes/Wooden) will be replaced with retaining way due
to the mountainous nature of the roads that may cause erosion with removal of these high bushes.
The contractors will replace the assets prior to completion of work on the particular stretch of
road where the affected asset is located
4.9 Provision of pre-cast drainage slabs:
Road side landscape and house access have to be destroyed due to road improvements. Therefore, it has
been proposed to provide pre cast drainage slabs to all residents who live either side of the road. This
provision has been included in to the contract.
4.10 Mitigation of the Impact on Public Institutes, Religious and Cultural Places:
There are no shrine will be impacted.
4.11 Mitigation of Project Induced Economic Impacts:
There are no encroachers located in the proposed road width for rehabilitation as such. However,
there is economic impact through loss of tree timber that will need to be removed.
4.12 Impact on Trees:
For timber, the method will be to take the total life span, present age, and price over its life for
determining compensation.
4.13 Impact on Paddy field:
Small land stretches amounting 0.3675 ha out of 33.6 ha of paddy lands are required to maintain the
proposed road width. As the extent of the paddy land to be donated is very small, there will not be a
remarkable impact on farming income.

25
The Entitlement Matrix:
The Entitlement matrix has been developed to address impacts/losses, entitlement of entitled persons.
The Project does not envision any land acquisition, relocation or resettlement the potential impacts are
limited. Hence the entitlement matrix is reflective of this issue. However, should any land be required
the project will depend on voluntary land donation and sign an Agreement/MOU ensuring a
participatory and transparent process has been followed and an agreement/MOU signed between the
donor and the recipient that will among other, ensures ) the ownership of the land and voluntary nature
of the donation, ii) that the land is appropriate for the intended purpose iii) that the land does not
belong to any donor who is below the poverty line or whose holding would be reduced below the
minimum size as stipulated to be economically viable ( 2.5 acres) iv) that there are no encumbrances
on the land, v) that it does not negatively impact on the livelihood of any vulnerable group, and if so,
that community developed mitigation measures are acceptable to the affectees, vi) that no
compensation will be paid for the land, and vii) that the owner gives up all claims on the land and the
title will be transferred to the recipient through the notary public or a registered deed or any other
procedure prescribed by the law of the state.
Entitlement Matrix
Type of Impacts Compensation
recommended
eligibility responsibility
Loss of land, of any kind
All land required will be
donated voluntarily by their
present owners. If owner is
unwilling to donate land,
design of road will be altered
Individual or
community
owning land to
donate. No
compensation
Social staff/ Senior
Engineer/Divisional
Secretary
Lost assets ( parts of
houses/shops/huts, other
structures, walls, fences
etc.)
Built by project or pay
replacement cost at
prevailing market value.
All affectees
losing assets
irrespective of
ownership of
title to land
Social
staff/Contractor/DE/SE
Loss income / livelihoods
due to lost assets
The project will pay
compensation to rebuild the
assets used for livelihood or
pay a lump sum (2 months
earning).
All affectees
losing livelihood
due to project
implementation
Social staff/DE/SE
Loss of agricultural
income
Compensation for value of
lost yields. If perennial crops
are involved, cost for re-
establishment of crops
All owners of
crops
irrespective of
title to land
Social staff/DE/SE

26
elsewhere and compensation
for lost yields up to one year
at market price.
Owners of front of roof
extending into RoW
Money for rebuilding of the
demolished structures at the
market price/replacement
cost, or rebuild by the
project.
All affectees
losing this asset
Social
staff/Contractor/SE/DE
Value of fruit and timber
trees
Timber and fruit trees lost
will be valued at present age,
overall life expected and lost
income/output from the tree
and compensated without
deducting the salvage value.
All owners of
trees irrespective
of owner of title
to land
Social staff/SE/DE
Compensation for tenants
This is not expected to be
triggered. However, if during
implementation it is
triggered, moving cost and
rent for 3 months, assistance
for finding alternative place
if house on rent is involved.
If agricultural or any other
livelihood involved,
compensation for lost income
and lost assets by the tenant
on tenanted property.
Tenants
impacted
Social staff/DE/SE
Loss of Access to
houses/shops/communities
Access to be
provided/rebuilt.
All affectees
losing access
Contractor/Social
staff/DE/SE
Pre cast drainage Slabs to be provided All affectees
losing access.
Contractor/Social
staff/DE/SE

27
5 Stakeholder Consultation
66. Stakeholders are defined as individuals or agencies that are either impacted by and /or can impact
the project. The stakeholders at national, district, divisional, project and village levels representing
different geographical areas as well as different management systems are mapped out in this section.
5.1 Direct and Indirect Stakeholders
67. The most significant stakeholder is the Project Affected Person who is negatively/positively
impacted by the Project. The most significant and direct beneficiary groups at the local level include all
kinds of road users. The groups that frequently benefit from the roads are school children, school teachers,
drivers, farmers, traders and all other type of road users. The regional economies as well as household
economies will get positively affected due to improved road network.
68. At the institutional level, the major direct stakeholder is the Provincial Roads Department. This
organization is responsible for improving the provincial road network of the country while officers
attached to PRDD at the local level are middle level direct stakeholders because complaints about the
problems of dilapidated road systems are frequently brought up by the communities. The GN and Samatha
Mandala are also important stakeholders who have a role to play in resolving grievances.
69. Water supply & drainage board, tea estates are also stakeholders because these organizations will
benefit from the project. This is equally applicable to the public and private transport providers.
70. In the process of consultation special attention was paid to consult all ethnic groups, women,
youths and other vulnerable groups. The details of the road users consulted are shown in Annex 3.
71. Provincial Council members, local level community based organizations and others are in the
indirect group of stakeholders. The contractors, material suppliers can benefit from the construction work.
The local communities can also benefit because of employment generated in their local areas in the
construction sites.
5.2 Expectations and likely benefits
72. Different stakeholders expect different benefits from the Project. The information gathered on this
aspect during the different studies conducted for the preparation of the project are briefly discussed below:
Transportation will get enhance and busses that do not travel the entire length of the roads due to its
poor conditions will do so. Thus improved ability to travel to desired destination on time, and
expectation of increase of public and private buses etc.
Reduced transport cost and better regulation of public transport.
Improved road will provide effective transportation of tea and agricultural goods to markets,
centres, factories and other economic institutions.
The maintenance cost of the vehicles will significantly go down.
The various public service delivery programs such as education, health will get significantly
improved with improvement in children regular attendance and fall in dropout rates etc.
Poverty reduction with better prices to farmers, increased competition in commercial sector where
previously there was monopoly and price setting by a few middle men.
Enhanced links with urban centres
Increase in land value particularly of land contagious to the improved roads.

28
Anticipate better collaboration between different ethnic communities living on the roads
particularly for maintaining roads ( if project envisages such activities)
5.3 Issues and concerns of stakeholders
73. While expecting significant benefits from the proposed project, the stakeholders expressed their
concerns on certain issues also. These are:
The roads should be improved with required widths and safety measures. A program should
be implemented in parallel to road improvement project to enhance the public transportation
system on improved roads.
The construction work should be completed on time and be of good quality. There may be
lack of access during construction period particularly since roads are narrow.
Shops and other livelihood activities of the communities residing close to the candidate roads
will get disturbed during construction period.
Building structures, privately owned assets located within the ROW may get damaged during
road improvement.
Potential construction related disputes among workers and villagers
Dust and pollution during construction
Increase in accidents with better roads and higher speed of travels
Loss of land that will be donated
Table 5.1 – views of the stakeholders on the project as whole
The
stakeholder
Positive impacts
Negative impacts
Mitigation measures
General
Public
The transportation problems due
to dilapidated roads will get
solved. The improved roads will
significantly contribute to
Improve the conditions of the
public transportation and also the
local people will be able to find
income generation opportunities
in the nearby markets /centres.
During construction period
construction related problems
will be created (lack of access,
congestions and other
disturbances). More accidents
due to higher speed
Provide the detours/by passes
and advice to work side by side
or section wise the road. Limit
the construction work during
the heavy traffic time. Erect the
necessary road signs (sign
boards and road markings).
The project
affected
persons
There will be opportunity to have
new structures instead of affected
old ones (those negatively
impacted and replaced by
project). Local economy will
benefit from job creation in the
area, the property value will get
Construction related problems
such as dust; noise will be
created by the construction
sites. Short term problems due
to demolition of structures.
Some structures, such as houses
and parapet walls become un-
Water application is done
periodically for dust
controlling. Introduce noise
barriers for noise sensitive
places and advice to use good
silencers for vehicles and limits
night works

29
increased and also the business
activities in the area will be
developed.
protected due to earth cuts of
the roads in front of the
structures.
Farming
community
Better income from better prices
and business activities as a whole
will get enhanced. Perishable
goods will get sold on time
The routine business activities
will get disturbed during
construction period; there will
be increased competition
among business people due to
emergence of new business
centres.
Provide the temporary places
for non-permanent businessmen
(lottery, make shift boutiques)
and provide the temporary
access for permanent business
centres during the construction
period.
Engineers
and other
staff
Roads maintenance cost will get
reduced
But higher speed may require
more maintenance and
additional safety measures.-
Erect safety sign boards and
speed limits boards at specific
locations such as schools,
hospitals, town areas and etc.
Department
of Provincial
Roads
Able to get priority roads
rehabilitated, routine maintenance
cost of the department will get
reduced.
In the short-run the officers will
be extremely busy due to
increased projects on
rehabilitation.
PRD will recruit additional
officers the contract basis for
short period.
School
community
Able to reach the school on time.
In general the performance in
education of children will go up.
Education officers will have
effective access to schools for
frequent supervisions; there may
be opportunities to motivate good
teachers to remain in the rural
schools.
Disturbances during
construction period, accidents
might go up due to physically
improved roads
Introduce the detours/by passes
and advice constructing side by
side or section wise. Limit the
construction work during the
heavy traffic time. Erect the
necessary road signs (sign
boards and road markings).
Introduce the Noise barriers as
required
Religious
groups
The religious centres will have
increased visitors.
During construction period
there will be disturbances due
to dust and noise, the visitors
also may have access problems
during the construction phase,
Water application is done
periodically for dust
controlling. Introduction of
noise barriers for noise
sensitive places and advice to
use good silencers for vehicles
and limit the night work.
Introduction of detours/by
passes advice to construct side
by side or section wise. Limit
the construction work during
heavy traffic time.
General
Time saving, able to make desired
Disturbances to the
Introduce the detours/by passes,

30
commuters number of trips to the desired
destinations
transportation during
construction phase
advice to construct side by side
or section wise. Limit the
construction work during the
heavy traffic time.
Drivers
Opportunity to handle vehicles
comfortably, time saving,
decreased break-downs
Vehicle
owners
Decreased cost of vehicle
maintenance, decreased vehicle
operation cost (fuel cost), durable
use of vehicles
Tendency for increased
accidents, increased
competition among private bus
drivers.
Erect of road signs (safety,
speed limits sign boards and
road markings).

31
5.4 Consultation Strategy
74. The project anticipates a high level of stakeholder‘s participation throughout the project cycle.
Therefore, it is essential to identify the type of stakeholders to be consulted and the required stage when
consultation would be necessary.
75. As identified in the field exercise almost all stakeholders expressed an overt intention to support
the project. The stages of the project cycle and the required stakeholder participation are shown in the
following table.
76. It is not necessary to consult all stakeholders at every stage of the project. However, the Social
Safeguard Officer that will be recruited for the project should maintain all records of all stakeholder
consultations.
5.2: Stages of Stakeholder Participation
Stakeholder Stage 1:
Feasibility
Level
Stage 2: Social
Assessment
Level
Stage 3: Land
Donation Level
Stage 4: GRM
Level
Stage 5: Road
Construction
Level
Stage 6:
Evaluation of
Benefits
Primary
affectees (all
categories) + + + + +- +
Road users (all
categories) + + - - + +
Owners of
common properties + + + + - +
Wage earners - + - - + + Vulnerable groups + + - + - + Others (if any) + + + + + +
Secondary Divisional
Secretary - + + + - +
Grama Niladaries + + + + - + Owners of
business
establishments
+ + - + + +
Land officers + + - - - - Property
developers + - + - - -
CBOs/NGOs
leaders - + + + + +
MOH/Midwife - - - - + + Others (if any) + + + + + +

32
5.5 Disclosure of Information
As highlighted in WB policies all information should be disclosed to all the stakeholders concerned.
Therefore, it is suggested to follow the same policy in this project. Along with disclosure of all project
documents as discussed earlier, the following methods would be employed to disseminate and disclose
relevant information. They are:
Conduct FGDs and KIIs with all stakeholders.
Establish grievances redress mechanism for each subproject.
Consult all affectees and inform them on the nature of impact on their property/assets, and their
livelihood.
Inform all relevant Grama Niladharies, Smamtha Mandala, and Divisional Secretaries about
affectees and summon a meeting in which DEs, TOs, and Social Safeguard Officer are represented.
Make available and disclose all hard copies of detailed designs of subprojects, SIMF, SIAs,
resettlement plans , and other documents at PC, DE offices, and all sub offices related to
subprojects. In addition, these documents should be pasted in relevance Web Sites of PC, MLGPC,
and WB.
All public disclosure documents should be translated into Sinhala and Tamil languages in addition
to the English version.

33
6 Grievances Redressal Mechanism
6.1 Mechanism
77. The grievance mechanism has been established to prevent grievances at the outset rather than react
to problems. Grievances can be minimized through careful subproject design and implementation by
ensuring active participation and consultation with affectees establishing rapport between the community
and the PRDD and the PIU through frequent interactions, transparency and monitoring.
78. A Grievance Redress Mechanism (GRM) will be established by both UPC and EPC that will be
transparent, accessible to all, inclusive, participative and unbiased. Affectees will be made fully aware of
their rights and the procedures for making a grievance – whether verbally or in writing – during
consultation. The structure of GRM is shown in table 6.1. It will be a multi- tiered approach. At the sub
project level minor issues may be informally settled at the village or GN level through consultation and
involvement of the project Social Safeguard Officer/Specialists and local implementing officer/Senior
Engineer. For complaints related to project related impacts of any kind a complaint register will be
maintained at the sub project office. This will state the type of complaint, the name of the complainant, date
of the complaint and person responsible to resolve it. At the next level the GRM will be headed by the
Provincial Project Director with the members as shown in the chart 6.2. If the complaint cannot be
resolved by the PD it will seek assistance from the Samatha Mandala.
79. The Samatha Mandala (Peace Council) is the conflict resolution committee appointed by the
Ministry of Justice in all Judicial Districts, as part of the grievance redress process. The members of this
committee are well respected as they are educated and citizens drawn from towns and villages. The
Samatha Mandala attempts to resolve conflicts prior to complaints being referred to the courts. If a conflict
cannot be resolved by the committee, it can still be pursued through the court system. Furthermore since
the Samatha Mandala is not involved in the decision-making process associated with project related land
issues and properties, it can therefore provide adjudication unencumbered by any specific interest in the
project.
80. The grievance mechanism established under the Project enables the Affected Person to appeal any
issue / decision or practice arising from compensations or to settle any general project-related disputes. APs
will be made fully aware of their rights and the procedures for making a grievance - whether verbally or in
writing through the disclosure and public awareness mechanism of the project.
81. Under the Project, there is potential for different types of grievances: i)grievances related to land
donation ii) grievances related to reestablishment of affected structures/livelihood restoration etc. iii) those
related to loss of access, safety measures and iv) construction related problems.
82. Along with the role of the PD to seek assistance from the Samatha Mandala, an affectees can also
place their appeals in the complaint register and if dissatisfied can request for meeting of the GRM or
Samatha Mandala.

34
6.2 Establishment of grievance redresses committee (GRC) for each project
Proposed structure of GRM
83. Under the Resettlement Plan the PRD will form grievance redressal committees in each Division or
other appropriate project location. The members of the GRC and their key functions are briefly described
below:
Table 6.1
Member Key functions
Provincial director PRD He is the convener of the GRC meetings he
is also responsible for chairing the GRC
and sending recommendation to the
relevant parties for action.
Divisional Secretary He will represent the Division
Senior engineer or his representative He will act as secretary of GRC, and
maintain the minutes and other
correspondence
Member of Local community /NGO He will represent the community in the
area.
Representative of concerned PAP /
Stakeholder
He is a member representing concerns of
PAPs
Social Development Officer He will deal with the local complaints and
provide feed to the Committee regarding
local issues.

35
6.3 Creation of Awareness of the Grievance Redressal Mechanism
84. The PRD/PIU will inform the APs/Communities and local officials such as GNs and Samatha
Mandala about the availability of GRC and also its role and functions.
Existence of the grievance redress mechanism
Procedures for registering a complaint
Categories of persons, institutions and property/assets affected and can claim compensation
Explanation of those who would not be considered as an affected person, property etc.
The address of the authority to receive and register the application with the name of the officer in-
charge, address, and telephone/fax numbers for contact.
6.4 Receiving Application for Redressal.
The applications on grievances for redressal can be submitted to Senior engineer (SE) on week days during
office hours. These applications are registered in the SE‘s office with all details such as names of the
person, type of grievances etc. The SE along with the social safeguards staff will be responsible for the
resolution of the grievance at the local level and if required will request a meeting of the GRC and inform
the other committee members regarding the grievance registered and actions taken so far.
6.5 Redressal Committee Meetings, Hearings, Proceedings andRecommendations.
Depending on the applications to be considered, the Redressal Committee‘s meetings are held in the PD
office on Thursday of every second week of each month at 2.00pm unless called by the PD on a specific
issue. If this day falls on a holiday, the meeting will be held on the following day at 2.00pm. Additional
meetings can be called.
6.6 Implementation of Compensation.
The minutes of the GRC signed by the GRC members are maintained at the office of the Provincial
Director of PRD. The recommendations for compensation including cost and other details along with other
issues will be sent to the Project Director within a week after the GRC meeting. The same information will
also be sent to the relevant applicants for his information. The recommendations will be implemented
before the construction work is started in the sections of the road where affected persons have claimed for
compensation.
6.7 Public Awareness.
The Project will undertake public awareness campaigns to inform citizens about the project related
activities, including the rights and entitlements of the affectees, the timings of the project construction
activities, any safety measures required to be followed by communities etc. In addition, once the GRM is
established in each subproject, it will be disclosed to the project affected people with its structure, official
address (most suitably DE‘s/SEs office), members of GRM, and role of GRM.

36
7 Institutional Mechanism
7.1 Roles and responsibilities.
85. The roles and responsibilities of the major actors in the RP are the following: The Project Director
and the Provincial Director. They together, have the overall responsibility for implementing the project and
the RP. They will allocate tasks to the Divisional Secretary, Senior Engineer and the social staff.
86. The social staff with oversight from the senior and division engineer will be responsible for the
following:
Carry out stakeholder consultation on project objectives, scope, and potential adverse/positive
impacts of project intervention; and process the stakeholder feedback for consideration to the
project.
Explain the mitigation policies and measures of the project. Identify PAPs (who are informal users
of public land in the ROW) and process the entitlements stipulated in the RP.
Explain to the PAPs the grievance redressal mechanism and its scope, functions and the procedure
to bring grievances to the Grievance Redressal Committees (GRCs).
Plan, design and conduct census of the project affected persons and households listed by the
surveyors; and collect all information required to identify the losses; and determine the
entitlements, application guidelines and implementation issues as suggested in the
‗compensation/entitlement matrix‘.
7.2 The Divisional Secretary.
He will facilitate the signing of the MOU for voluntary land donations.
87. The GRM Committee headed by the Provincial Director will responsible for resolution of
grievances and can delegate responsibility to the Samatha Mandala if required.
7.3 Monitoring and Evaluation Mechanism.
Monitoring and evaluation are vital activities of the project. The project has the responsibility to implement
all activities identified and on time. The objectives of monitoring of the RP are to: 1) ensure that the
standard of living of affectees is restored or improve 2) monitor whether the time lines are being met, 3)
assess whether mitigation efforts are sufficient, 4) identify construction related problems or potential
problems, and 5) identify methods of responding immediately to mitigate hardships.

37
88. Internal monitoring will be conducted by project staff of each PC, and external monitoring which
will be conducted by an independent body.
89. The monitoring indicators will be for activities as laid out in the entitlement matrix to ensure that
the affected persons identified in the RP receive the compensation on time and for those that they are
eligible for. While the outcome indicators will monitor the objectives of the RP as laid out above.
90. In addition the GRM will be closely monitored to ensure that all complaints are resolved on time
and in an adequate manner. The conflict filter that is a part of the project will also be monitored.
7.4 Reporting
91. This will include quarterly updates of progress in preparation and implementation of social and
safeguards concerns (disaggregated by sub project). Reports will be prepared for formal supervision
mission with details of progress and identification of any social and safeguards issues that may impede
progress.
7.5 Capacity Building Program
92. For successful project implementation, a capacity building program will be conducted for all staff
of the project. It should cover the following areas:
National Involuntary Resettlement Policy
World Bank Policies on Involuntary Resettlement, Indigenous People, Women Participation in
Development, Information Disclosure
The Resettlement Plan of the Project
Grievances Redress Mechanism
HIV/AIDS: The Project will need to ensure that awareness raising/training is provided by all
contractors to their staff.
93. The training/workshops should be organised at the level of the PC. Such workshops should be
attended by all Chief/Senior Engineers, DEs, TOs and Project staff who deal with social and environmental
issues. It may be worthwhile to have two workshops for each PC to address a). Conceptual framework and
b). Its applications in this project.
94. The budget for the workshops should be borne by the project (a tentative budget for these
workshops is attached in Annex 5).
7.6 Resettlement Budget:
95. The budgets below are based on the methodology provided in the chapter on mitigation. In addition
all infrastructures are valued at replacement cost, present market prices.

38
Roads code Losses of Assets and Infrastructure( in SLRs)
EPAMC016 14,13,000
EPAMC006 14,38,000
EPAMC071 3,12,000
EPAMC007 99,60,000
EPAMC053 30,94,000
EPAMC040 58,63,000
EPAMC037 -
EPAMD059 -
EPAMC039 -
EPAMC091 2,10,500
EPAMC130 360,000
Table 2 Total Budget (in SL Rs)
Assets/Infrastructure etc Cost (in LRS)
Infrastructure 20,420,000
Trees-timber 920,000
Training 701,000
Monitoring 500,000
Utilities 10,398,000
Pre cast drainage 44,558,800
Total 77,497,800
For details see Annex 2.

39
Annexures
Annex 1-Socioeconomic Data
Table 02: Basic Information of Uva and Eastern Provinces
Province Capital Districts Area in Km2
Eastern Trincomalee Trincomalee, Batticaloa, and Ampara 9,951
Uva Badulla Badulla and Monaragala 8,488
Source: Population and Housing Census 2001, Department of Census and Statistics, Sri Lanka
Table 03: Size of Land Holding in Uva and Eastern Provinces
District
Small Holding Sector Estate Sector
All Sectors Less than or equal to 1/4 acre 1/4 acre and above 20 Acres and above (less than 0.10 ha) * (0.10 Ha and above) ** (8.09 Ha and above)
# of Holdings Extent # of Holdings Extent # of Holdings Extent # of Holdings Extent Batticaloa 78,897 - - - - - - -
Ampara 67,778 - - - - - - -
Trincomalee 33,333 4,690 18,920 50,797 - - 52,253 55,487
Badulla 38,733 5,789 91,004 156,800 186 101,017 129,923 263,606
Monaragala 8,603 1,584 81,723 225,219 23 11,288 90,349 238,091
Sri Lanka 1,462,904 202,182 1,783,473 3,643,875 6,577 384,843 3,252,954 4,797,004 * Holdings reporting extent less than or equal to 40 Perches (0.10hectares) of land with agricultural output mainly for home consumption
** Holdings reporting extent more than 40 Perches (0.10hectares) of land or producing agricultural output mainly for sale purposes Source: Census of Agriculture 2002, Department of Census and Statistics, Sri Lanka
Table 04: Ethnic Representation of Project Influenced Area – Year 2001 District Sinhala SL Tamil Indian Tamil SL Moor Burgher Malay SL Chetty Bharatha Other
Ampara 231,771 110,180 410 245,089 1,008 169 6 1 710
Badulla 558,218 32,230 141,087 40,455 606 1,390 112 21 436
Monaragala 374,553 5,579 7,660 8,047 113 83 19 1 118
Source: Census of Population and Housing 2001, Department of Census and Statistics
Table 05: Male and Female Representations
District Male Female Total Sex Ratio
Ampara 295,319 294,025 589,344 100.4
Badulla 383,067 391,488 774,555 97.9
Monaragala 200,558 195,615 396,173 102.5
Source: Census of Population and Housing 2001, Department of Census and Statistics

40
Table 06: Population Growth by District in Identified Years (in ‘000s)
District 1981 1997 2000 2003 2006
Amapara 389 540 565 605 627
Badulla 641 770 826 831 837
Monaragala 274 384 399 405 420
Source: Annual Report 2006, Central Bank of Sri Lanka
Table 07: Number of Administrative Units Coming under State and
Local Government Administration by 2002
District DSD PS MC UC Electorate GND Village
Badulla 15 14 1 2 9 567 2229
Monaragala 11 10 - - 3 319 1198
Ampara 19 14 - 2 4 504 876
Sri Lanka 319 257 17 38 160 14,009 38,259 Source: Population and Housing Census 2001, Department of Census and Statistics, Sri Lanka
Table 08: Poverty by Province
Province Unit Year 2002
Western % of poor HH 9.2
Central % of poor HH 20.8
Southern % of poor HH 23.6
North Western % of poor HH 22.3
North Central % of poor HH 18.1
Uva % of poor HH 31.8
Sabaragamuwa % of poor HH 28.9
Eastern - - Source: Household Income and Expenditure Survey, 2002, Department of Census and Statistics

41
Table 09: Monthly Income level of the PAP
Road Code No. Affected
Families
Monthly
Income
Rs. <5000
Monthly
Income
Rs. 5000-
10000
Monthly
Income
Rs. 10000-
15000
Monthly
Income
Rs. 15000-
20000
Monthly
Income
Rs. >20000
EPAMC016 10 08 02
EPAMC006 06 04 02
EPAMC071 13 08 4 01
EPAMC007 24 01 01 16 06
EPAMC053 10 02 06 02
EPAMC040 25 01 01 12 11
EPAMC037 -
EPAMD059 03 - 03
EPAMC039 07 01 04 02
EPAMC091 07 02 02 03
EPAMC130 04 04
Total 109 02 05 59 47 05
% 1.8 3.7 48.6 41.3 4.6

42
Table 10. Name, Gender, Age Education and Primary Occupation of PAP
There are no affectees in roads, EPAMC037
Road Name :- Central Road Nithavur Code :- EPAMC 053
Name of Affectee
Gender Age Education Primary Occupation
School - - - -
Y.M. Yehiya Male 40 Post graduate Banker
M. Mohideen Male 54 NTD Engineer
Naheem Male 45 Graduate Engineer
I. Sulaiman Male 55 OlL Business
A.B.L.Gany Male 68 O/L Retired Driver
A.M.M.Navas Male 42 O/L Business
P.Majeed Male 35 O/L Business
P. Makar Male 50 O/L Business
A.Sadeek Male 40 O/L Labourer
B.Hairulla Male 50 Grade 10 Business
Owner is in abroad Male - - -
Road Name :- Santhamaruthu kalmunaikudy Boundary Road Code :- EPAMC 016
Name of Affectee Gender Age Education Primary Occupation
Vellathambi Male 45 Grade 8 Driver
Mrs. M.H.U. Rinufa Female 42 Graduate Teacher
M.I.Safeena Female 40 Grade 10 House wife
M.J.Ansar Male 36 A/L Business
A.L.Sulaiman Lebbei Male 52 Grade 10 Business
M.Nawzard Male 31 Grade 09 Business
M.C.M.Arafath Male - A/L Formal job
M.Zahirthurai Male 31 A/L Company agent
M.Thahaumma Female 55 Grade 10 House wife
M.S.Ajmir Male 48 O/L Business
Road Name :- Natpaddiminai Pandiruppu Boundary Road Code :- EPAMC 006
Name of Affectee
Gender Age Education Primary Occupation
A.M.Ali Male 41 O/L Driver
M.Abdul Hameed Male 60 Grade 8 Farmer
Y.L.M.Hussain 45 O/L Business
J.Jayaraj Male 30 Grade 10 Business
M.Kuthoos Male 45 Grade 10 Mechanic
N.Johenthiran Male 46 O/L House wife

43
Road Name :- Thirupothi Ammankovil Road Code :- EPAMC 007
Name of Affectee
Gender Age Education Primary Occupation
N.Nathan Male 52 Grade 10 Business
S.Palanthan Male 84 Grade 9 Business
J.Nagarathnam Male 64 Grade 10 Business
S.Visunathansan Male 55 A/L MLT
S.Naharathnam Male 45 Grade 8 Business
I.Kanthan Male 42 A/L Business
N.Chanthanalaasumi Female 65 O/L House wife
S.Rasamanikam Female 72 Grade8 House wife
K.Balachanthiran Male 35 Grade 10 Business
T.Rajakopal Male 31 O/L Business
S.Maheswari Female 78 Grade 5 House wife
J.Vallipuram Male 65 Graduate Teacher
P.Pakiyanathan Female 52 O/L House wife
K.Rajakumar Male 34 Grade 8 Farmer
E.Amarasooriya Female 35 Grade 10 House wife
K.Kanchamma Female 52 Grade 10 Farmer
K.Sanmugam Female 78 Grade 8 House wife
T.Thangeswaran Female 36 O/L House wife
K.Wikneswaran Female 30 Grade 10 House wife
S.Velupillai Male 78 Grade 5 Farmer
M.Nathan Male 42 Grade 8 Farmer
S.Tharmagulasinga Male 55 A/L Business
K.Kavitheeswaran Male 30 Grade 10 Business
S.Raviharan Male 46 A/L PHI

44
Road Name :- Karaipthivu Village Road Code :- EPAMC 040
Name of Affectee Gender Age Education Primary Occupation
Mrs. Thangarajah Female 68 O/L House wife
Mrs. M. Pathmanathen Male 62 O/L Retired Teacher
P. Kupenthirarajah Male 39 Graduate Teacher
S.Mathathevan Male 55 O/L Business
S. Nagarajah Male 49 A/L Secretary PS
Mrs. S. Sotheswaran Female 40 O/L House wife
K.Maheshwaran Male 50 A/L Technical Officer
S. Rasaiah Female 58 A/L Technical Officer
S. Ganeshan Male 39 Graduate Supervisor
Mrs. T. Saravanamuthiu Female 55 A/L Teacher
C.Thirunavarash Male 60 A/L AMP Doctor
S.Maheshan Male 38 A/L Govt. officer
K.Sivappirakasam Male 52 O/l Govt. officer
M.Vithiyananthan Male 43 O/L Security Guards
M.Rasamanikam Male 50 A/L Teacher
P.Sundaralingam Male 58 A/L Technical officer
Vinayahamoorthi Male 65 O/L Former Chairman (PS)
T.Varothyan Male 37 Graduate Engineer
K.Thadchinanthan Male 45 A/L Teacher
Mrs.T.Thangarasa Female 38 A/L Nurse
P.Balasubramuniyam Male 60 A/L Teacher
T.Baskaran Male 54 A/L Teacher
A.Chanthirakantha Male 38 Grade 10 Farmer
S.Siveligam Male 60 Grade 10 Security Guard
K.Srikantharaja Male 35 O/L Govt. Officer

45
Road Name :- Manal (Hijra) Road Code :- EPAMC091
Name of Affectee
Gender Age Education Primary Occupation
M.I.Sehumuhaideen Male 30 O/L Farmer
Mrs. Ameena Umma Female 48 Grade 05 House wife
Mrs K.M.Zakeena Female 45 Grade 08 House wife
K.M. Lafeer Male 36 Grade 09 Farmer
K. Nawoorthabi Male 45 Grade 10 Farmer
A.M. Farook Male 35 Grade 09 Farmer
Road Name :- Malwaththa Suripodai Road Code :- EPAMC039
Name of Affectee
Gender Age Education Primary Occupation
Mrs. Thankaswari Female 52 A/L Farmer
M.Ummer farook Male 47 O/L Farmer
M.S.Maharoof Male 46 O/L Farmer
M.S.Jasmine Male 52 Grade 10 Farmer
M.Athampodai Male 60 O/L Farmer
Road Name :- Arasady Field Road Road Code :- EPAMC 071
Name of Affectee
Gender Age Education Primary Occupation
A.Aboobakar Male 67 Grade 5 Farmer
A.B.Abdul Rahuman Male 35 O/L Farmer
K.L.Sinnathambi Male 41 O/L Farmer

46
Road Name :- Akkaraipattu Neethai Ambalanoya Code :- EPAMC 0059
Name of Affectee
Gender Age Education Primary Occupation
S.M.M.Musthafa Male 52 Grade 8 Business
A.Uppqlihajiyar Male 55 Grade 5 Farmer
A.L.M.Ummer Lebbai Male 45 Grade 8 Farmer
Abdul Kafoor Male 50 Grade 10 Farmer
A.Jabbar Male 45 Grade 8 Farmer
M.Meera Lebbai Male 48 Grade 5 Farmer
A.Abdull Male 49 Grade 9 Farmer
M.Ismail Male 52 Grade 6 Farmer

47
Annex 2
Potential Affected house head and types of loss on Selected Roads with Costs
Table 1. EPAMC 053 Central Road Nithavur - Affected Area and Nature of Project Support
Chainage Name of Affectee
(Household Head)
Affected Property Nature of Project
Support
Linear
Length (m)
Estimated
Cost (Rs)
0+100(LHS) School Boundary wall Reconstructing of
Boundary wall
30 3,30,000
0+200(LHS) Y.M. Yehiya Boundary wall Reconstructing of
Boundary wall
15 1,10,000
0+200(RHS) M. Mohideen Boundary wall Reconstructing of
Boundary wall
15 1,10,000
0+215(LHS) Naheem Boundary wall,
Toilet pit Reconstructing of
Boundary wall, Toilet
pit
10 1,10,000
0+215(RHS) S.Naheem Boundary wall Reconstructing of
Boundary wall 10 1,10,000
0+225(LHS) I. Sulaiman Boundary wall Reconstructing of
Boundary wall 45 4,95,000
0+225(RHS) A.B.L.Gany Boundary wall, gate Reconstructing of
Boundary wall 45 4,97,000
0+550(LHS) A.M.M.Navas Boundary wall, gate
and toilet pit Reconstructing of
Boundary wall toilet
and relocating of gate
25 3,22,000
0+550(RHS) P.Majeed Boundary wall Reconstructing of
Boundary wall
25 1,54,000
0+575(LHS) P. Makar Boundary wall , gate Reconstructing of
Boundary wall,
relocating of gate
10 2,82,000
0+575(RHS) A.Sadeek Boundary wall and
roof with pillars
Reconstructing of
Boundary wall and
Roof with pillars
10 110,000
0+585(LHS) B.Hairulla Boundary wall, gate
and toilet pit
Reconstructing of
Boundary wall,
relocating of gate
15 2,97,000
0+585(LHS) Owner is in abroad Boundary wall, gate Reconstructing of
Boundary wall,
relocating of gate
15 1,67,000
Total 30,94,000

48
Table 3. EPAMC 016 Sainthamaruthu Kalmunaikudy Boundary Road - Affected Area and Nature of
Project Support
Chainage Name of Affectee
(Household Head)
Affected Property Nature of Project
Support
Linear
Length
(m)
Estimated
Cost (Rs)
0+525(LHS) Vellathambi Boundary wall Reconstructing of
Roof and wall
2 22,000
0+610(LHS) M.H.U. Rinufa Boundary wall, gate Reconstructing of
Boundary wall, gate
relocate
15 167,000
0+615(LHS) M.I.Safeena Boundary wall Reconstructing of
Roof and pillars
2 22,000
0+625(LHS) M.J.Ansar Boundary wall Reconstructing of
Boundary wall
10 1,10,000
0+700(LHS) A.L.Sulaiman Lebbei Boundary wall Reconstructing of
Boundary wall
25 2,75,000
0+775(LHS) M.M.Nawzard Shop wall Reconstructing of
Shop wall
5 55,000
0+740(LHS) M.C.M.Arafath Boundary wall, gate
and Toilet Pit
Reconstructing of
Boundary wall, Toilet
Pit and relocating of
gate
25 3,22,000
0+800(LHS) Zaleem Thurai Boundary wall Reconstructing of
Boundary wall
15 1,65,000
0+825(LHS) Thahaumma Boundary wall Reconstructing of
Boundary wall
15 1,65,000
0+860(LHS) Ajmai Boundary wall Reconstructing of
Boundary wall
10 1,10,000
Total 14,13,000

49
Table 4. EPAMC 007 Thirupothi Ammankovil Road -Affected Area and Nature of Project Support
Chainage Name of Affectee (Household
Head)
Affected Property Nature of Project
Support
Linear
Length(m)
Estimated
Cost (Rs)
0+020(LHS) N.Nathan Boundary wall and
Gate Reconstructing of
Boundary wall
80 882000
0+020(RHS) S.Palanthan Boundary wall,
Gate
Reconstructing of
Boundary wall, toilet
pit and relocating of
gate
80 882000
0+200(LHS) J.Nagarathnam Boundary wall and
Gate Reconstructing of
Boundary wall
10 112000
0+200(RHS) S.Visunathasam Boundary wall and
Gate Reconstructing of
Boundary wall 10 112000
0+210(LHS) S.Naharathnam Boundary wall and
Gate Reconstructing of
Boundary wall 20 222000
0+210(RHS) I.Kanthan Boundary wall and
Gate Reconstructing of
Boundary wall and
relocating of gate
20 222000
0+230(LHS) N.Chanthanalaasumi Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+230(LHS) S.Rasamanikam Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+270(LHS) K.Balachanthiran Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+270(RHS) T.Rajakopal Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+300(LHS) S.Maheswari Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
30 332000
0+300(RHS) J.Vallipuram Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
30 332000
0+330(LHS) P.Pakiyanathan Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
20 222000
0+330(RHS) K.Rajakumar Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
20 222000
0+350(LHS) E.Amarasooriya Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
50 552000
0+420(LHS) K.Kanchamma Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
80 882000
0+420(RHS) K.Sanmugam Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
80 882000

50
Chainage Name of Affectee (Household
Head)
Affected Property Nature of Project
Support
Linear
Length(m)
Estimated
Cost (Rs)
0+510(LHS) T.Thangeswaran Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+510(RHS) K.Wiknewaran Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+520(LHS) S.Velupillai Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+520(RHS) M.Nathan Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+530(LHS) S.Tharmagulasiga Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
10 112000
0+540(LHS) K.Kavitheeswaran Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
60 662000
0+540(RHS) S.Raviharan Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
60 662000
Total 81,88,000
Table 5. EPAMC 006 Natpaddimuni Pandiruppu Boundary Road- Affected Area and Nature of Project
Support
Chainage Name of Affectee (Household
Head)
Affected Property Nature of Project
Support
Linear
Length(m)
Estimated
Cost (Rs)
0+390(LHS) A.M.Ali Boundary wall Reconstructing of
Boundary wall
10 1,12,000
0+390(RHS) M.Abdul Hameed Boundary wall,
Gate
Reconstructing of
Boundary wall,
relocating of gate
10 1,12,000
0+400(LHS) Y.L.M.Hussain Boundary wall Reconstructing of
Boundary wall
10 1,12,000
0+400(RHS) J. Jayaraj Boundary wall Reconstructing of
Boundary wall
10 1,12,000
0+500(LHS) Kuthoos Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
20 2,22,000
0+500(RHS) Johenthiran Boundary wall and
Gate
Reconstructing of
Boundary wall and
relocating of gate
20 2,22,000
Total 8,92,000

51
Table 6 EPAMC 040 Karaipthivu Village Road - Affected Area and Nature of Project Support
Chainage Name of Affectee (Household
Head)
Affected Property Nature of Project
Support
Linear
Length(m)
Estimated
Cost (Rs.)
0+210(LHS) Mrs. Thangarajah Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
30 3,50,000
0+220(LHS) Mrs. M. Pathmanathen Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
40 4,60,000
0+230(LHS) P. Kupenthirarajah Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
45 4,89,000
0+240(LHS) S.Mathathevan Boundary wall Reconstructing of
Boundary wall 35 3,85,000
0+250(LHS) S. Nagarajah Boundary wall Reconstructing of
Boundary wall 35 3,85,000
0+260(LHS) Mrs. S. Sotheswaran Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
25 2,77,000
0+270(LHS) K.Maheshwaran Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
35 3,87,000
0+300(LHS) S. Rasaiah Boundary wall Reconstructing of
Boundary wall
03 33,000
0+320(LHS) S. Ganeshan Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
04 46,000
0+330(LHS) Mrs. T. Saravanamuthiu Boundary wall Reconstructing of
Boundary wall
04 46,000
0+350(LHS) C.Thirunavarash Boundary wall Reconstructing of
Boundary wall
25 2,75,000
0+400(LHS) S.Maheshan Boundary wall Reconstructing of
Boundary wall
30 3,30,000
0+420(LHS) K.Sivappirakasam Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
30 3,32,000
0+430(LHS) M.Vithiyananthan Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
20 2,22,000
0+460(LHS) M.Rasamanikam Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
30 3,32,000
0+470(LHS) P.Sundaralingam Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
10 1,12,000
0+480(LHS) Vinayahamoorthi Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
20 2,22,000

52
Chainage Name of Affectee (Household
Head)
Affected Property Nature of Project
Support
Linear
Length(m)
Estimated
Cost (Rs.)
0+500(LHS) Varothyan Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
16 1,78,000
0+600(LHS) K.Thadacinanthan Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
40 4,42,000
0+700(LHS) T.Thangarasa Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
25 2,77,000
0+800(LHS) P.Balasubramuniyam Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
20 2,22,000
0+820(LHS) T.Baskaran Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
10 1,12,000
0+830(LHS) A.Chanthirakantha Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
10 1,12,000
0+880(LHS) S.Sivelingam Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
10 1,12,000
0+900(LHS) K.Srikantharaja Boundary wall and
gate
Reconstructing of
Boundary wall and
Relocating of gate
10 1,12,000
Total 62,50,000
Table 7. EPAMC 091. Manal (Hijra) Road -Affected Area and Nature of Project Support
Chainage Name of Affectee (Household
Head)
Affected Property Nature of Project
Support
Linear
Length(m)
Estimated
Cost (Rs)
0+725(RHS) M.I.Sehumuhaideen Wire fence Replacing with
improved fence
35 17,500
1+300(LHS) Mrs K.M.Zakeena Wire fence Replacing with
improved fence
45 22,500
1+400(RHS) Mrs. Ameena Umma Wire fence Replacing with
improved fence
50 25,000
1+500(RHS) K.M. Lafeer Wire fence Replacing with
improved fence
15 7,500
1+550(LHS) A..M. Farook Wire fence and
house wall
Replacing with
improved fence and
reconstructing of
house wall
18 and 4 53,000
1+550(RHS) K.Nawoorthambi Wire fence Replacing with
improved fence
10 5,000
Total 1,30,500

53
Table 8. EPAMC 039. Malwaththa Suripodai Road -Affected Area and Nature of Project Support
Chainage Name of Affectee
(Household Head)
Affected
Property
Nature of Project Support Extend m
2
2+700(LHS) S.Thangeswaran Paddy land If required, safety precautions
will be provided by the project
180
3+200 (RHS) M.Ummar Farook Paddy land If required, safety precautions
will be provided by the project
70
3+200(LHS) M.S.Maharoof Paddy land If required, safety precautions
will be provided by the project
70
3+400(RHS) M.Ummar Farook Paddy land If required, safety precautions
will be provided by the project
30
3+400(LHS) M.S.Jasmin Paddy land If required, safety precautions
will be provided by the project
30
3+500(RHS) M. Ummar Farook Paddy land If required, safety precautions
will be provided by the project
150
3+500(LHS) M.Athampodal Paddy land If required, safety precautions
will be provided by the project
150
Table 9. EPAMC 059. Arssady Field Road -Affected Area and Nature of Project Support
Chainage Name of Affectee
(Household Head)
Affected
Property
Nature of Project Support Extend/linear
length
m
5+550(LHS) A.Aboobakar Paddy land If required, safety precautions
will be provided by the project
45
5+625(LHS) A.B.Abdul Rahuman Paddy land If required, safety precautions
will be provided by the project
100
5+750(LHS) K.L.Sinnathambi Paddy land If required, safety precautions
will be provided by the project
150

54
Table 10. EPAMC 071. Akkaraipattu Neethai Ambalanoya Road -Affected Area and Nature of Project
Support
Chainage Name of Affectee
(Household Head)
Affected
Property
Nature of Project
Support
Linear
Length(m)
Cost (Rs.)
0+075(LHS) S.M.M.Musthapha Fence Replacing with improved
fence
24 12,500
7+800(LHS) A.Upplihajiyar Paddy land If required, safety
precautions will be
provided by the project
340 -
8+000(RHS) A.Upplihajiyar Paddy land If required, safety
precautions will be
provided by the project
650 -
8+500(RHS) A.L.M.Ummer Lebbai Paddy land If required, safety
precautions will be
provided by the project
340 -
8+700(LHS) Abdul Kafoor Paddy land If required, safety
precautions will be
provided by the project
480 -
9+000(RHS) A.Jabbar Paddy land If required, safety
precautions will be
provided by the project
330 -
9+300(LHS) Meera Lebbai Paddy land If required, safety
precautions will be
provided by the project
260 -
9+500(RHS) A.Abdull Paddy land If required, safety
precautions will be
provided by the project
240 -
9+700(LHS) M.Ismail Paddy land If required, safety
precautions will be
provided by the project
260 -
Total 12,500

55
Table 12. The Number Electricity and Telephone Posts Required to be Shifted
S.
N. Road Code
Number of
Electricity Posts
Estimated Cost Number
Telephone Posts
Estimated Cost
1. EPAMD059 - 2. EPAMD130
10 220,000
15 210,000 3. EPAMD053
47 1,034000
51 714,000 4. EPAMD037
06 132,000
12 168,000 5. EPAMD016
61 1,342,000
39 546,000
6. EPAMD006 41
902,000 31 434,000
7. EPAMD007 34
748,000 35 490,000
8. EPAMD040 93
2,046,000 61 854,000
9. EPAMD091 13
286,000 10 140,000
10. EPAMD039 -
- - -
11. EPAMD071 06
132,000 - -
Total
311
6842000 247 3,556,000
Source: Census, August 2010
Many of these rural roads have several electricity and telephone posts which need to be shifted (Shifting
cost are approximately 22000SLR per EP and 14000SLR per TP). The project office and respective
engineers have already informed relevant government institutions (Ceylon Electricity Board and Sri Lanka
Telecom are the responsible government departments and they run provincial units) to undertake necessary
shifting activities. Each road has been examined and several roads have been identified where it is
necessary to shift or change posts. Details are given in table 6 above.

56
Table 13: Estimate Cost for Providing House access slabs
S. N. Road Code Road Name Required
No. of Slabs
Estimated Cost
1. EPAMD059 Arasadi Field Road. 25
75,000
2. EPAMC130 Damana Ambalanoya Pannalgama Road. 6215
18,645,000
3. EPAMC053 Central Road Ninthavur 1140
3,420,000
4. EPAMC037 Viliniyadi Road 2422
7,266,000
5. EPAMC016 Sainthamaruthu Kalmunaikudy Boundary
Road. 1156
3,468,000
6. EPAMC006 Natpaddimunai Pandiruppu Boundary
Road. 1545
4,635,000
7. EPAMC007 Thirupothi Ammankovil Road. 705
2,115,000
8. EPAMC040 Karaipthivu Village Road. 1443
4,329,000
9. EPAMC091 Manal (Hijra) Road. 1298
3,894,000
10. EPAMC039 Malwatta Suruipodai Road. 70
210000
11. EPAMC071 Akkarratpattu Neethai Ambalanoya road 1395
4,185,000
Total 17414 44,558,800
Source: Census, August 2010
The estimated cost for developing drainage system and replacing pre-cast drainage units are given
in table7.The amounts related to replacement of structures figured out on the basis of on- the- spot
investigations with DEs and TOs measuring the length and height of the structures and calculating
the number of square feet. In addition, they have examined the existing condition and determined
the best way to replace or renovate these structures during the construction period. The DEs and
TOs have indicated the cost of a pre-cast drainage unit (SLR 3000) and finally that amount is
calculated with the number of required units for each road.

57
Annex-3
A. Table 1. General Details of Land donors
Serial
No.
Chainage Name of land donor Amount land
lost by each
(m2)
Total land
holding by
each (m2)
Percentage of
land lost by
each
EPAMC 039. Malwaththa Suripodai Road
01 2+700(LHS) S.Thangeswaran 180 16000 1.13
02 3+200(RHS)
3+400(RHS)
3+500(RHS)
M.Ummar Farook 250 32000 0.78
03 3+200(LSH) M.S.Maharoof 70 28000 0.25
04 3+400(LSH) M.S.Jasmin 30 24000 0.13
05 3+500(LHS) M.Athampodal 150 16000 0.94
EPAMC 059. Arssady Field Road
06 5+550(LHS) A.Aboobakar 45 24000 0.19
07 5+625(LHS) A.B.Abdul Rahuman 100 24000 0.42
08 5+750(LHS) K.L.Sinnathambi 150 16000 0.94
EPAMC 071. Akkaraipattu Neethai Ambalanoya Road
09 7+800(LHS)
8+000(LHS)
A.Upplihajiyar 790 32000 2.46
10 8+500(LHS) A.L.M.Ummer Lebbai 340 24000 1.42
11 8+700(LSH) Abdul Kafoor 480 24000 2.00
12 9+000(LHS) A.Jabbar 330 20000 1.65
13 9+300(LHS) Meera Lebbai 260 16000 1.63
14 9+500(LHS) A.Abdull 240 16000 1.50
15 9+700(LHS) M.Ismail 260 24000 1.08
Total 3675m2
(0.3675 ha)
336000m2
(33.6 ha)
1.09

58
B. Details of the Road Widths and Willingness of Land Donors
Table 1. EPAMC 053 Central Road Ninthavur
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
Concern taken Remarks
L R Y No
0+000
0+100
0+130
0+160
0+200
0+215
0+225
0+275
0+300
0+325
0+350
0+400
0+500
0+550
0+575
0+585
0+600
0+650
0+700
0+800
0+900
1+000
1+100
1+200
1+300
1+400
0+000-0+130
0+130-0+800
0+800-1+000
1+000-1+150
1+150-1+350
1+350-1+450
7.7
7.7
7.7
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
5.1
8.7
8.7
8.7
8.7
9.5
9.5
10.1
5.9
7.9
5.2
4.9
4.8
4.8
5.3
5.1
5.3
5.6
5.6
5.6
4.7
4.9
4.4
5.6
5.7
6.0
8.0
8.7
8.8
8.7
8.8
9.6
8.7
1.1
0.1
0.15
0.15
0.2
0.1
0.35
0.2
0.1
0.35
Y
Y
Y
Y
Y
Y
Y

59
Table 2. EPAMC 037 Vilaniayadi Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
Concern
taken
Remarks
L R Y N
0+000
0+100
0+200
0+400
0+600
0+800
1+000
1+200
1+400
1+600
1+800
2+000
2+200
2+400
2+600
2+800
3+000
3+200
3+400
3+600
0+000-0+300
0+300-0+400
0+400-0+500
0+500-1+200
1+200-1+300
1+300-1+550
1+550-2+980
2+980-3+100
3+100-3+600
7.7
7.7
7.7
7.7
7.2
7.2
7.2
7.2
7.7
7.7
7.7
7.7
7.7
7.7
7.7
7.7
7.0
7.0
7.0
7.0
8.2
7.9
8.2
8.2
9.1
8.6
10.1
7.9
7.8
7.9
9.5
10.1
9.5
9.2
8.1
7.0
7.2
7.3
9.2
Additional
lands are not
required for
road
construction
due to
spaces are
available

60
Table 3. EPAMC 016 Sainthamaruthu Kalmunaikudy Boundary Road
Chainage Cross section
chainage
Required width
as per cross
section for
respective
chainage (m)
Existing
available
width (m)
Additional
width
Concern
taken
Remarks
L R Y No
0+000
0+100
0+200
0+300
0+400
0+500
0+525
0+600
0+610
0+615
0+625
0+700
0+725
0+740
0+800
0+860
0+900
1+000
1+250
0+000-0+300
0+300-0+500
0+500-0+700
0+700-1+000
1+000-1+250
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
7
6.9
7.8
6.7
7.0
6.7
6.2
5.9
6.2
5.5
5.5
5.5
5.7
5.3
4.7
5.2
5.8
6.1
7.2
7.3
0.1
0.5
0.5
0.5
0.3
0.7
1.3
0.8
0.2
Y
Y
Y
Y
Y
Y
Y
Y
Y

61
Table 4. EPAMC 006 Natpaddimunai Pandiruppu Boundary Road
Chainage Cross section
chainage
Required width
as per cross
section for
respective
chainage (m)
Existing
available
width
Additional
width
Concern
taken
Remarks
L R Y No
0+000
0+100
0+200
0+230
0+300
0+390
0+400
0+410
0+500
0+600
0+700
0+800
0+900
1+000
1+200
1+300
1+400
1+500
1+600
1+700
1+800
1+900
2+000
2+100
0+000-0+150
0+150-0+230
0+230-0+280
0+280-0+410
0+410-0+480
0+480-0+850
0+850-0+950
0+950-1+730
1+730-1+900
1+900-2+100
6
6
6.3
7
6.6
6.6
6.6
7.7
7.7
7.7
7.7
7.7
6.2
6.2
6.2
6.2
6.2
6.2
6.2
6
6
5.5
5.5
7.6
8.3
7.5
7.7
8.5
6.2
6
5.8
6.3
7.7
10.4
10.2
9.6
9.5
9.3
9.2
9.4
8.3
6.8
7.8
6.3
5.7
6.0
0.2
0.3
0.4
0.7
0.2
0.3
0.4
0.7
Y
Y
Y
Y

62
Table 5. EPAMD 007 Thirupothi Ammankovil Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
Concern
taken
Remarks
L R Y No
0+000
0+020
0+100
0+200
0+210
0+230
0+240
0+270
0+280
0+300
0+330
0+350
0+400
0+420
0+500
0+510
0+520
0+530
0+540
0+600
0+700
0+800
0+900
1+000
1+100
1+200
0+000-0+200
0+200-0+540
0+540-0+700
0+700-0+760
0+760-1+200
6.0
5.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
5.6
5.6
5.6
5.6
5.6
6.7
5.1
6.3
5.2
5.0
3.8
3.8
4.9
4.8
4.4
4.4
4.0
7.0
5.8
6.0
5.4
5.6
5.6
5.5
6.0
6.2
6.4
6.2
6.5
6.4
6.2
0.45
0.4
0.5
1.1
1.1
0.55
0.6
0.8
0.8
1.0
0.1
0.3
0.2
0.2
0.25
0.45
0.4
0.5
1.1
1.1
0.55
0.6
0.8
0.8
1.0
0.1
0.3
0.2
0.2
0.25
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
N
(0+200)
RHS- person
does not like
to donate and
all others like
to donate the
lands

63
Table 06. EPAMC 040 Karaipthivu Village Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
required
Concern
taken
Remarks
L R Y No
0+000
0+100
0+200
0+210
0+220
0+250
0+270
0+300
0+320
0+340
0+350
0+370
0+400
0+430
0+460
0+480
0+500
0+600
0+700
0+750
0+800
0+820
0+830
0+840
0+850
0+860
0+880
0+900
1+000
1+100
1+200
1+300
1+400
1+500
1+600
1+700
1+800
1+900
2+000
2+100
0+000-0+060
0+060-0+500
0+500-1+300
1+300-1+900
1+900-2+100
9.0
6.0
6.0
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
5.75
9.2
9.2
9.2
9.2
7.65
8.45
9.5
6.5
6.1
5.2
5.4
5.1
5.2
5.3
5.1
5.2
5.2
5.3
5.4
5.3
5.2
5.4
5.4
5.8
5.9
5.5
5.4
5.3
5.2
5.4
5.3
5.2
5.4
5.3
5.8
5.8
5.9
6.2
6.2
10.2
10.1
9.3
9.2
10.0
8.8
10.5
0.55
0.35
0.65
0.55
0.45
0.45
0.65
0.55
0.45
0.35
0.45
0.55
0.35
0.35
0.25
0.35
0.45
0.55
0.35
0.45
0.55
0.35
0.45
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
As additional
width required
is a small land
strip, lands take
from one side
(LHS) only.

64
Table 07. EPAMC 091 Manal (Hijra) Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width (m)
Additional
width (m)
Concern
taken
Remarks
L R Y No
0+000
0+010
0+075
0+100
0+140
0+200
0+300
0+400
0+500
0+600
0+700
0+725
0+800
0+900
1+000
1+100
1+200
1+300
1+400
1+500
1+600
1+700
1+800
0+000-0+140
0+140-0+275
0+275-1+200
1+200-1+300
1+300-1+375
1+375-1+800
5.0
5.0
5.0
5.0
5.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.5
6.5
6.5
6.5
6.5
6.5
5.2
5.0
5.2
6.1
5.2
9.8
8.1
8.0
6.4
6.2
6.2
5.7
6.4
6.6
6.6
6.5
6.2
5.6
5.3
6.9
7.2
7.1
7.2
0.5
0.6
0.3
0.5
0.6
Y
Y
Y
All persons
like to donate
the lands

65
Table 08. EPAMC 039 Malaththa Suripodai Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
Concern
taken
Remarks
L R Y No
0+000
0+250
0+500
0+750
1+000
1+250
1+500
1+750
2+000
2+250
2+500
2+750
3+000
3+250
3+500
3+750
4+000
4+250
4+500
4+750
5+000
5+200
0+000-0+100
0+100-0+400
0+400-1+700
1+700-3+100
3+100-3+200
3+200-4+200
4+200-5+200
6.5
6.5
6.5
6.5
6.5
6.5
6.5
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.5
6.5
6.5
6.5
6.5
6.5
6.5
6.5
6.5
6.5
10.0
7.0
7.0
7.1
6.9
6.5
6.3
6.6
6.1
6.3
5.6
4.8
5.2
4.8
4.5
4.6
4.6
4.5
5.5
0.25
0.25
0.25
0.4
0.5
0.9
0.7
0.9
1.0
1.0
1.0
1.0
0.5
0.25
0.25
0.25
0.3
0.4
0.8
0.6
0.8
1.0
0.9
0.9
1.0
0.5
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
All persons
like to donate
the lands

66
Table -9 EPAMCD 059 Arasadi Fied Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width (m)
Additional
width
Concern
taken
Remarks
L R Y No
0+250
0+500
0+750
1+000
1+250
1+500
1+750
2+000
2+250
2+500
2+750
3+000
3+250
3+500
3+750
4+000
4+250
4+500
4+750
5+000
5+250
5+500
5+550
5+750
6+000
0+250
0+950-1+000
1+000-1+500
1+500-2+500
2+500-3+000
3+000-3+600
3+600-5+500
5+550-6+000
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.6
8.5
8.5
8.3
9.5
9.3
10.2
7.9
8.1
8.2
9.0
9.4
8.7
9.6
7.8
8.6
7.8
9.3
9.6
8.2
9.1
8.9
6.9
6.7
6.9
0.6
0.8
0.6
Y
Y
Y
Reservation land
available for
reconstruction
of the box
culvert.
Lands can not
be taken from
RHS due to
irrigation
channel is
located on RSH
from 5+500.

67
Table 10. EPAMC 071 Akkaraipattu Neethai Ambalanoya Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
Concern
taken
Remarks
L R Y No
0+000
0+075
0+500
1+000
1+500
2+000
2+500
3+000
3+500
4+000
4+500
5+000
5+500
5+750
6+000
6+500
7+000
7+500
7+800
8+000
8+500
8+700
9+000
9+300
9+500
9+700
10+000
10+500
3+950-7+840
7+840-7+950
7+950-9+000
9+000-10+500
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
8.4
6.3
8.3
8.6
8.5
8.4
8.5
8.3
7.8
8.1
8.2
8.1
7.9
7.8
7.6
7.6
7.5
7.5
5.8
6.2
5.8
6.1
6.4
6.2
6.3
6.2
7.8
7.8
1.7
1.3
1.7
1.6
1.1
1.3
1.2
1.3
1.2
Y
Y
Y
Y
Y
Y
Y
Y
Y
Road traverse
though the
paddy lands

68
Table 11. EPAMC 130 Damana Ambalanoya Pannalgama Road
Chainage Cross section
chainage
Required
width as per
cross section
for respective
chainage (m)
Existing
available
width
Additional
width
Concern taken Remarks
L R Y No
0+000
0+250
0+500
0+750
1+000
1+250
1+500
1+750
2+000
2+250
2+500
2+750
3+000
3+250
3+500
3+750
4+000
4+250
4+500
4+750
5+000
5+250
5+500
5+700
6+000
6+250
6+500
6+750
7+000
7+250
7+500
7+750
8+000
8+250
8+500
8+750
9+000
9+250
9+500
9+750
10+000
10+250
0+000-0+100
0+100-0+500
0+500-1+500
1+500-2+500
2+500-3+300
3+300-3+400
3+400-4+000
4+000-5+700
5+700-6+000
6+000-6+600
6+600-7+000
7+100-10+100
10+100-10+400
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
7.5
9.0
8.0
8.1
8.0
8.0
8.2
8.0
8.0
8.3
8.0
8.1
8.0
8.2
8.2
8.0
9.0
8.1
8.1
8.1
8.0
8.2
8.0
8.2
8.0
8.1
8.0
8.1
8.1
8.0
8.1
4.5
4.5
4.5
4.5
5.0
4.5
4.5
4.5
5.0
4.5
4.5
4.5
4.5
8.0
Existing width of
the road is
adequate therefore
no land required
for road
construction from
0+100 to 23+000
Tank bund is
located 7+100 to
10+100

69
10+500
10+750
11+000
11+250
11+500
11+750
12+000
12+250
12+500
12+750
13+000
13+250
13+500
13+750
14+000
14+250
14+500
14+750
15+000
15+250
15+500
15+750
16+000
16+250
16+500
16+750
17+000
17+250
17+500
18+000
18+250
18+500
18+750
19+000
19+250
19+500
19+750
20+000
20+250
20+500
20+750
21+000
21+250
21+500
21+750
22+000
22+250
22+500
10+400-10+550
10+550-10+900
10+900-14+600
14+600-16+000
16+000-19+900
19+900-20+050
20+050-22+000
22+000-22+500
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.5
7.
8.9
8.0
8.1
8.1
8.0
8.2
8.0
8.1
8.0
8.0
8.2
8.2
8.0
8.1
8.0
8.1
8.0
8.2
8.1
8.1
8.0
7.9
8.0
8.0
8.0
8.0
7.9
8.0
8.0
8.1
8.0
8.0
8.1
8.0
8.2
8.0
8.3
8.3
9.5
8.2
8.0
8.0
8.1
8.1
8.0
7.8
8.0
8.2

70
Annex 4
List of Stakeholders Consulted
Group or Individual
Consulted
Total FGD KII Date of
Consultation
Place of Consultation
1. Three Wheel Drivers
4 03.11.2009 Kalmune Bus Stand
7 03.11.2009 Karthive Junction
5 03.11.2009 Kalmune Beach Road
4 05.11.2009 Natpatmune Junction
6 05.11.2009 Ninthaur Town
87 4 05.11.2009 Ninthaur Beach Road
4 05.11.2009 Akkarapattu Town
8 06.11.2009 Pothuvil Town
5 06.11.2009 Arugambe Junction
5 07.11.2009 Lahugala Town
4 08.11.2009 Thottama Junction
6 08.11.2009 Damana Junction
5 08.11.2009 Malwatta Junction
8 09.11.2009 Vilaniyadi Junction
6 09.11.2009 Samanthure Town
2. Lorry Drivers
2 08.11.2009 Thottama Junction
2 09.11.2009 Vilaniyadi Junction
9 1 08.11.2009 Damana Junction
1 08.11.2009 Malwatta Junction
1 06.11.2009 Pothuvil Town
3. Bus Drivers 1 06.11.2009 Pothuvil Town
2 03.11.2009 Kalmune Bus Stand
7 1 09.11.2009 Samanthure Town
1 05.11.2009 Ninthaur Town

71
1 08.11.2009 Bakmitiyava Junction
4. Bus Conductor
1 06.11.2009 Pothuvil Town
2 03.11.2009 Kalmune Bus Stand
7 1 09.11.2009 Samanthure Town
1 05.11.2009 Ninthaur Town
1 08.11.2009 Bakmitiyava Junction
5. Businessmen
2 04.11.2009 Natpatmune Road
11 4 04.11.2009 Vilaniyadi Road
3 10.11.2009 Arugambe Town
1 10.11.2009 Nindaur Road
6. School Principals
1 23.11.2009 Saindamarudu Girls
College
1 23.11.2009 Saindamarudu Boys
College
4 1 24.11.2009 Akkarapattu National
School
7. Teachers
2 23.11.2009 Saindamarudu Girls
College
9 2 23.11.2009 Saindamarudu Boys
College
3 24.11.2009 Akkarapattu National
School
4 24.11.2009 Lahugala
Vidyalaya
Saindamarudu Girls
College
14 4 23.11.2009 Saindamarudu Boys
College
3 24.11.2009 Akkarapattu National
School
9. Farmers 3 25.11.2009 Vilaniyadi Road
Samanthure
22 4 25.11.2009 Karthivu Village

72
4 26.11.2009 Manal Hijra Village
6 26.11.2009 Pothuvil
10. Women
4 25.11.2009 Vilaniyadi Road
Samanthure
3 25.11.2009 Karthivu Village
16 4 26.11.2009 Manal Hijra Village
2 26.11.2009 Nindavur
11. Labourers
4 25.11.2009 Vilaniyadi Road
Samanthure
4 25.11.2009 Karthivu Village
14 6 27.11.2009 Market Kalmune
12. Armed Forces
1 27.11.2009 Karthivu STF Post
1 27.11.2009 Malwatta Army Post
9 2 27.11.2009 Neetta Army Post
2 28.11.2009 Natpatmune Police Post
3 28.11.2009 Samanthure Police Post
13. Grama Niladhari
1 05.12.2009 Kachcheri Ampara
6 1 05.12.2009 Kachcheri Ampara
1 05.12.2009 Kalmune North GN
Office
1 28.11.2009 Natpatmune GN Office
1 29.11.2009 Vilaniyadi GN Office
1 29.11.2009 Malwatta Suripoda GN
Office
14. Divisional Secretaries
and
Assistant Divisional
Secretaries
1 08.12.2009 DS Nindavur
1 08.12.2009 DS Samanthure
3 1 07.12.2009 DS Karthivu
15. Other Government
Officers
3 06.12.2009 Base Hospital
Akkarapattu
2 06.12.2009 Base Hospital Nindavur
7 1 06.12.2009 Post Office Thirukkovil
1 06.12.2009 Co-oparative
Natpatmune
16. Pradeshiya Saba
Chairman
1 08.12.2009 PS Nindaur
3 1 08.12.2009 PS Samanthure
1 07.12.2009 PS Karthivu
17. EPC Officials
1 13.12.2009 EPC Office Ampara
2 1 13.12.2009 EPC Office Ampara
18. MLGPC
1 14.12.2009 Kachchery Ampara
2 1 14.12.2009 Kachchery Ampara
19. DEs and TOs
2 1 12.12.2009 RDD Office Ampara
2 1 12.12.2009 RDD Office Ampara
10 2 15.12.2009 RDD Office Kalmune
2 15.12.2009 RDD Office Kalmune
Total 242 201 41 - -

73
Annex 5
Land Donation Agreement
AGREEMENT
Demolishing of the Constructions to acquire the land to improve / rehabilitate the
………………………………………………. Road. This agreement is made and entered into
on this …….. day of …... Two Thousand ………… at ……… in Democratic Socialist Republic
of Sri Lanka.
BY AND BETWEEN Provincial Road Development Department (PRDD), a governmental
authority created by Provincial Council Act No. 42 of 1987 of Sri Lanka and having its‘
principal office at Second Floor, Office Complex, R. H. Gunawardena Mawatha, Badulla herein
after called and referred to as the PRDD and which term of expression shall mean and included
the said PRDD or its‘ successors and Divisional Secretary, ………… permitted assigns of the
one part.
AND ………………………………………………………… (name of owner of the land) of
…………………………………………………………………... (address) which term in
expression shall where the context so admits or requires, mean and include the said
……………………………………. of his successors and permitted assigns of the other part.
NOW THIS AGREEMENT WITNESSETH THAT THE PRDD AND
……………………………………………………….. has mutually agreed as follows.
Considering the Social & Economical impact of the rehabilitation of the above mentioned road
I/We …………………………………. The owner / owners of the land called
………………………………………… (morefully described in the schedule hereto) donate and
will be transferred in the name of the Director of the Provincial Road Development Department.
The land is being given of my / our own free will and is an entirely voluntary donation. I / We
……………………………… do hereby assure that I / We relinquish all Claim and title to the
donated land & that land is free of all encumbrances. The relinquished & donated land does not
affect any person‘s livelihood. I / We ……………………………… agree on demolishing
……………........ Which has been recognized to be demolished to rehabilitate the road, on the
condition of a new construction to be consigned.

74
THE SCHEDULE ABOVE REFERRED
Detail about the land ………………………………………………………………
Size of the Land ………………………………………………………………
Details about the Constructions, Properties & Cultivations
To North ……………………………………………………………....
………………………………………………………………
To South ………………………………………………………………
………………………………………………………………
To East ………………………………………………………………
………………………………………………………………
To West ………………………………………………………………
………………………………………………………………
Here by we grant & acknowledge the acceptance of the land more fully described in the
schedule hereto on ………………………. Date.
…………………………………. …………………………….
Signature of the 1st party Signature of the 2nd party
01. Director, RDD. ……………….
02. Divisional Secretary…………………
03. Independent Witness (Name and Signature)………………………………..

75
Annex 6
Budget for the Two Workshops on Social Safeguard Issues
S.N. Description Unit Cost Estimated Budget SLR
1. Charges for the venue
(Provincial Training Centre
– Ampara) for two days
25,000x2 50,000.00
2. Accommodation expenses
for 50 persons
2,000x40x3 240,000.00
3. Meals expenses for 40
persons for 7 meals in three
days
500x40x7 140,000.00
4. Water and other
refreshments for the
participants
100x40x2 8,000.00
5. Transport expenses for
resource persons - 2
vehicles
8,000x3x2 48,000.00
6. Resource persons
remunerations – 4 persons
5,000x4x2 40,000.00
7. Stationeries 25,000 25,000.00
8. Printing cost for workshop
materials
25,000 25,000.00
9. Remuneration for the
participants – 40 persons
1,000x40x2 80,000.00
10. Equipments hired – two
computers and two
projectors
2,500x4x2 20,000.00
11. Contingent 25,000 25,000.00
Estimated Total Budget 701,000.00