RFI FORM RFI NO. 176 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins Eastman CONSTRUCTION MANAGER: Rizzo Corporation DATE: 11/30/18 FROM: Mike Walton COMPANY NAME: Northeast Interior Systems SUBJECT: Door and Drawer pulls DISCIPLINE/TRADE: BP#5 Architectural Woodwork DWG./SPEC. REFERENCE: 2/A-551 QUESTION: Detail shows cabinet door and drawer pulls oriented horizontally and pulls and locks in specific locations. 1. Elevations show door pulls oriented vertically: which is correct? 2. Can our standard pull and lock locations be used to assure lock bolt operates correctly? (Distance from receiver/strike plate is critical). ANSWER: 1. Drawer pulls to be horizontal. Cabinet pulls to be vertical. 2. Yes RESPONSE BY: J. Culotta @ PE DATE: 12/06/2018

Upload: others

Post on 15-May-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 176

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Mike Walton

COMPANY NAME: Northeast Interior Systems

SUBJECT: Door and Drawer pulls

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE: 2/A-551

QUESTION:

Detail shows cabinet door and drawer pulls oriented horizontally and pulls and

locks in specific locations.

1. Elevations show door pulls oriented vertically: which is correct?

2. Can our standard pull and lock locations be used to assure lock bolt operates

correctly? (Distance from receiver/strike plate is critical).

ANSWER:

1. Drawer pulls to be horizontal. Cabinet pulls to be vertical.

2. Yes

RESPONSE BY: J. Culotta @ PE DATE: 12/06/2018

Page 2: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 177

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Mike Walton

COMPANY NAME: Northeast Interior Systems

SUBJECT: Mailbox

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE:

QUESTION:

Detail shows mailbox box as 2" thick panel and horizontal shelves as 1" thick. For

economy and consistency can mailbox components be made from 3/4" panel

material?

ANSWER:

Yes.

RESPONSE BY: J. Culotta@PE DATE: 12/06/2018

Page 3: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 178

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Mike Walton

COMPANY NAME: Northeast Interior Systems

SUBJECT: Shelf Supports

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE: 06 40 23 2.03D

QUESTION:

Specification calls for KV 331 shelf support, which is a metal pin inserted into a

hole bored in the cabinet side. This is consistent with all of the details on sheet A-

551 except for 7/A-551, which calls for recessed metal standard shelf supports.

Can the KV 331 shelf pin be used at all cabinet shelves including the full height

wardrobe shown in 7/A-551?

ANSWER:

Provide access to metal standard shelf support as shown in 7/A-551

RESPONSE BY: J. Culotta @ PE DATE: 12/06/2018

Page 4: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 179

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Mike Walton

COMPANY NAME: Northeast Interior Systems

SUBJECT: Wood Benches

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE: A-552

QUESTION:

2,4,6/A-552 various bench types are shown with metal support pedestals and wall-

mount angle support brackets. This is provided by BP#5 as indicated in RFI-096.

Please identify required make and model.

What does the rectangle with the circle at the intersection of the bench top and

front drop-edge represent?

ANSWER:

Refer to RFI 044.

Provide blocking for the front drop edge.

RESPONSE BY: A.Dobbertin@PE DATE: 12/06/2018

Page 5: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 180

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Joe Puglisi

COMPANY NAME: The NY-CONN Corp.

SUBJECT: Extent of Surface Mount Electrical/ Comm/ AV/ Security

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE: EP-101A, EP-102B

QUESTION:

The electrical power floor plans (EP-101A, EP-101B) dated 7/27/18, include a

"General Power Note" directing the electrical contractor to utilize surface mounted

raceways and devices where new outlets and devices are to be installed on existing

CMU walls. This general note does not appear on any of the other electrical

drawnings, nor does the note appear on the Technology or Security drawings.

Please clarify if all installations at existing CMU walls under the electrical scope of

work, including lighting controls, tele-comm outlets, AV outlets/boxes , and

security devices and pathways are to be surface mounted per the general note on

the power drawings, when located on an existing CMU wall.

If any installations at existing CMU walls are to be flush mounted, please indicate

which installations will require flush mounting and which contractor shall be

responsible for opening and channeling the existing block and then patching and

painting the same.

Page 6: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

ANSWER:

GENERAL POWER NOTE ON SHEET E-001 IS APPLICABLE TO ALL ELECTRICAL

DRAWINGS. ALL SYSTEMS WIRING (INCLUDING LIGHTING CONTROLS) ON

EXISTING

CMU WALLS TO UTILIZE SURFACE MOUNTED RACEWAY. INTENT IS NOT TO

CUT

EXISTING CMU WALLS, BUT TO RUN CIRCUIT IN SURFACE MOUNTED

RACEWAY. REFER

TO ARCHITECTURAL PLANS FOR EXISTING WALL TYPES AND LOCATIONS.

REFER TO

SPECIFICATION SECTION 260519.3.2.E FOR WIRING METHODS.

THIS IS APPLICABLE TO IT, AV, TELE/COM AND SECURITY RACEWAYS ON

EXISTING CMU WALLS.

RESPONSE BY: J. Culotta @ PE DATE: 12/06/2018

Page 7: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 181

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: John Legere

COMPANY NAME: Legere Group

SUBJECT: Plastic laminate

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE:

QUESTION:

According to RFI response #25, colors of plastic laminate and solid surface are “to

be selected from manufacturer’s full range of standard colors.” As it was

mentioned in RFI #25, the costs vary widely depending on color. Please specify

specific price groups for plastic laminate and solid surface materials.

Page 8: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

ANSWER:

For Plastic Laminate, provide High Pressure Laminate from one of the following

three manufacturer’s educational product lines:

1) Panolam/Nevamar

2) Wilsonart International; Div. of Premark International, Inc

3) Formica Corporation

For Solid Surface Material, Provide options from price group 3 from any of the

following manufacturers:

1) Wilsonart International; Div. of Premark International, Inc

2) Formica Corporation

3) Corian by du Pont Nemours and Company.

RESPONSE BY: A.Dobbertin@PE DATE: 12/06/2018

Page 9: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 182

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Doug BurdickCOMPANY NAME: J. Iapaluccio

SUBJECT: Site elevations

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:Re: Grease Trap: Drawings P 101C and C301.1 show the proposed invert elevation of the 6” PVC waste line from The building to the grease trap at 373.5 and 373.18. The issue is that these elevations are above the proposed finished grade of the new bus loop in that area. Please provide direction.

ANSWER:

Kitchen waste invert leaving the building has been adjusted to 369.2’. See revised civil drawing C-301.1 in Addendum #5.

RESPONSE BY: Jim Stenqvist DATE: 12/6/18

Page 10: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 183

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ava Faulkner

COMPANY NAME: Mulberry Signs

SUBJECT: Signage

DISCIPLINE/TRADE: BP#10 – Signage

DWG./SPEC. REFERENCE:

QUESTION:

The Sign Types listed on Drawing IG-001 has no sizes for the signs. Only the

letter heights. What are the dimensions of the signs?

ANSWER:

See Matrix below. Sizes given are minimum overall dimensions for the non-

decorative portion of the sign (see area dimensioned in red below). decorative

borders may vary in size.

Page 11: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

Sign Type Height Width

A1 3 1/2" 6"

A2 3 1/2" 6"

A3 3 1/2" 6"

A4 3 1/2" 6"

B1 8" 6"

B1* 8" 6"

B2 8 3/4" 6"

B3 8 3/4" 6"

C 8 3/4" 6"

D 8 1/2" 6"

E 8 1/2" 6"

E1 8 3/4" 6 1/2"

F 10 1/2" 11"

G 10 1/2" 10"

J 8" 6"

K 10 1/2" 6"

L 6" 6"

M 8" 6"

O 6" 6"

P 3" 6"

R 1'-1" 8 1/2"

RESPONSE BY: A. Dobbertin@PE DATE: 12/06/2018

Page 12: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 184

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ava Faulkner

COMPANY NAME: Mulberry Signs

SUBJECT: Signage

DISCIPLINE/TRADE: BP#10 – Signage

DWG./SPEC. REFERENCE:

QUESTION:

Is there a sign schedule list of the sign types for each room. It is impossible to

determine which belong to which room. Ex: Which get decorative borders, which

get employee names, which get Plain Room ID

ANSWER:

Refer to signage plans for locations of each sign type.

RESPONSE BY: A.Dobbertin@PE DATE: 12/06/2018

Page 13: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 185

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Retaining Wall at Dumpster

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE: C-301.1, C-600.2

QUESTION:

Utilities plan C301.1 calls for a cast in place concrete retaining wall to support the

dumpster pad. This wall is not shown on the materials plan, the grading plan, or

the dumpster pad details on C600.2. Please clarify what this retaining wall is and

provide details.

ANSWER: There is no longer a cast-in-place concrete retaining wall behind the dumpster. This note can be disregarded

RESPONSE BY: Dan Kroeber, MMI DATE: 12/06/2018

Page 14: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 186

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Dwight Ballard

COMPANY NAME: Robert Lord

SUBJECT: Wall Pads

DISCIPLINE/TRADE: BP#11B – Gymnasium Equipment

DWG./SPEC. REFERENCE:

QUESTION:

Are we to supply an alternate to place wall pads on the wall where the bleacher is

IF the bleacher isn’t purchased?

ANSWER:

Provide wall pads on west gym wall as part of the base bid.

RESPONSE BY: J. Culotta@PE DATE: 12/06/2018

Page 15: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 187

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Dwight Ballard

COMPANY NAME: Robert Lord

SUBJECT: Gym Divider

DISCIPLINE/TRADE: BP#11B – Gymnasium Equipment

DWG./SPEC. REFERENCE:

QUESTION:

Most drawings call for a roll-up divider curtain but the specification calls for a

center-roll divider curtain. These are two different styles of divider curtain. Which

is preferred?

ANSWER:

Provide Center-roll divider curtain as specified.

RESPONSE BY: A.Dobbertin@PE DATE: 12/06/2018

Page 16: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 188

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Renee Macklin

COMPANY NAME: OWI

SUBJECT: Wardrobe Cabinets

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE:

QUESTION:

Please clarify intent for the tops of the full-height wardrobe cabinets. Detail A-

551/7 shows what looks like a shop-made plastic laminate countertop on top of the

wardrobe instead of a standard finished cabinet top. There is also a note for PLAM

on moisture-resistant core (which is what we’d use for a shop-made laminate

countertop that had a sink in it). This is very unusual & also unnecessary for the

top of a 7-foot-tall cabinet. Is this correct or is it an error? Note that specs in 06 40

00 do not include plastic laminate countertops.

ANSWER:

Provide plastic laminate on standard substrate as indicated in specification section

06 40 23.

RESPONSE BY: J. Culotta@PE DATE: 12/06/2018

Page 17: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 189

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Renee Macklin

COMPANY NAME: OWI

SUBJECT: Semi -Exposed Interiors of Closed Cabinets

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE:

QUESTION:

Please clarify the intent for the semi-exposed interiors of the closed cabinets (i.e.

cabinets with doors/drawers).

1. Are standard white interiors acceptable at closed cabinets? Or should the

interiors match the exterior colour?

2. Details on A-551 include references to melamine at the interiors of closed

cabinets. Specs in 06 40 00 do not include melamine (see paragraph 2.05). Which

is correct? Note that melamine would be more cost effective than high pressure

laminate and would meet AWS standards for casework.

ANSWER:

1. Match exterior color.

2. Refer to RFI 41.

RESPONSE BY: A.Dobbertin@PE DATE: 12/06/2018

Page 18: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 190

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Linda McKimCOMPANY NAME: Ferguson

SUBJECT: Equipment Supports

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE:

QUESTION:On Drawing M502 Detail 2/M502 Note#8 says that RTU/DOAS Roof Curbs must be structurally self-supporting and must include all steel required to support units without structural steel beneath units. Note #8 on Detail 2 / M-502 does not apply to this project (accidental carry-over from another project).Drawing S-102A & S-102B indicate new W8 X 10S beams to support the RTU’s. Spec. Section 230548 Page 16 calls for Restrained Vibration Isolation Roof Curb Rails.Are the RTU’s & DOAS Units Curb mounted or on Dunnage above the roof with Vibration Rails? RTUs and DOAS units are all to be curb mounted.Detail on S-501 show both Options. If the RTU’s are Curb mounted Please Clarify if a self-supporting structural curb is required. Self-supporting structural curbs are not required (accidental carry-over from another project).

ANSWER:See responses underlined in red above.

RESPONSE BY: Jesse Vose, PE DATE: 12-04-2018

Page 19: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 191

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken Hunt

COMPANY NAME: Rizzo Corp.

SUBJECT: Hazmat Testing

DISCIPLINE/TRADE: BP#1 – Demolition & Abatement

DWG./SPEC. REFERENCE:

QUESTION:

Has existing CMU been tested for loose fill?

ANSWER: NO.

RESPONSE BY: J. Culotta @ PE DATE: 12/6/18

Page 20: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 192

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken Hunt

COMPANY NAME: Rizzo Corp.

SUBJECT: Wood Fiber Mulch

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

Is the wood fiber mulch part of FF&E with the playground and site furnishings

provided by others, or is it part of construction?

ANSWER:

Wood fiber mulch is part of construction.

RESPONSE BY: Colleen Fowler - MMI DATE: 12/6/18

Page 21: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 193

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken Hunt

COMPANY NAME: Rizzo Corp.

SUBJECT: Expansion Joints

DISCIPLINE/TRADE: BP#2 – Concrete, BP#3 – Masonry, BP#7 - Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Please clarify locations of all required expansion joints.

ANSWER:

Refer to S-103C for expansion joint at Gym Addition.

Provide 2” expansion joint at fire wall between column XM and Mat Classroom

addition at 2nd floor and roof levels. See image below. (S-102a and S-103a)

Page 22: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RESPONSE BY: JC@PE DATE: 12/6/18

Page 23: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

EPDM ROOF MEMBRANE

NOTES:1) NAILERS SHALL BE SECURELY ANCHORED TO THE DECK TO RESIST

A FORCE OF 300 POUNDS PER LINEAL FOOT IN ANY DIRECTION.2) VAPOR BARRIER SHALL BE SEALED AT EDGES.

FLASHING STRIPFOAM ROD TUBING (COMPATIBLE)SPECIFIED SECUREMENTFIRE RESISTANT WOOD NAILERSECURELY ANCHORED

INSULATION SECURELY FASTENED

STRUCTURAL DECK

MINERAL WOOL INSULATION

VAPOR BARRIER

COVER BOARD

422 Summer Street Stamford, CT 06901 T. +1 203 251 7400 F. +1 203 251 7474

PROJECT:

DRAWING TITLE:

DATE:

PROJECT NO.

SCALE:

DWG. NO.:

6" = 1'-0"

68962RALPH M. T. JOHNSON ELEMENTARY SCHOOL ADDITIONS & RENOVATIONS

BID RFI 193 ROOF EXPANSION JOINT DETAIL

DEC 6, 2018 SKA-002

6" = 1'-0"1 ROOF EXPANSION JOINT DETAIL

Page 24: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

SEALANT CONT.

COUNTER FLASHING AND HARDWARE

EPDM ELASTOMERIC BELLOWS, CLOSED CELL FOAM BACKER WITHINTEGRAL SPLICING KIT.

FASTENER @ 8" 0C

BONDING ADHESIVEFASTENING PLATEMAX 12" OC

ENCASED BATT INSULATION

TREATED WOOD CURB CONT.

6" WIDE PRESSURE SENSITIVE FLASHINGEPDM ROOFING MEMBRANECOVER BOARD INSULATION

EXTERIOR WALL

8" M

IN

SEALANT TAPE

422 Summer Street Stamford, CT 06901 T. +1 203 251 7400 F. +1 203 251 7474

PROJECT:

DRAWING TITLE:

DATE:

PROJECT NO.

SCALE:

DWG. NO.:

3" = 1'-0"

68962RALPH M. T. JOHNSON ELEMENTARY SCHOOL ADDITIONS & RENOVATIONS

BID RFI 193 ROOF TO WALL EXPANSION JOINT

DEC 6, 2018 SKA-003

3" = 1'-0"1 ROOF TO WALL EXPANSION JOINT DETAIL

Page 25: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 194

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken Hunt

COMPANY NAME: Rizzo Corp.

SUBJECT: Site Railings

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE:

QUESTION:

Please confirm that all site railings are stainless steel.

ANSWER:

All site railings are to be galvanized steel. See specification included in this

Addendum.

RESPONSE BY: Colleen Fowler - MMI DATE: 12/6/18

Page 26: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

Johnson Elementary School METAL RAILINGS

Additions and Renovations 05 52 00 - 1

PE Project 68962.00 Construction Document Submission – July 27, 2018

State Project No. 009-0059-RNV ADDENDUM 5 – December 6, 2018

SECTION 05 52 00

METAL RAILINGS

PART 1 - GENERAL

1.1 SUMMARY

A. Includes but Not Limited To:

1. Furnish and install galvanized steel pipe handrails as described in Contract Documents.

a. Exterior handrails.

B. Products Supplied but Not Installed Under This Section:

1. Anchoring sleeves in concrete.

C. Related Sections:

1. Section 32 13 16 – Cast-In-Place-Concrete

2. Section 32 13 13 – Concrete Paving and Curbing

1.2 REFERENCES

A. American Society for Testing And Materials:

1. ASTM A 36-00, 'Standard Specification for Carbon Structural Steel.'

2. ASTM A 53-01, 'Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and

Seamless.'

3. ASTM A 123-97a, 'Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and

Steel Products.'

4. ASTM A 501-01, 'Specification for Hot-Formed Welded and Seamless Carbon Steel Structural

Tubing.'

1.3 SUBMITTALS

A. Shop Drawings: Show fabrication and installation of handrails and railings including plan, elevations,

sections, details of components, and attachments to other elements of The Work.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Storage:

1. Store handrails and railing systems in clean, dry location, away from uncured concrete and masonry,

and protected against damage.

Page 27: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

Johnson Elementary School METAL RAILINGS

Additions and Renovations 05 52 00 - 2

PE Project 68962.00 Construction Document Submission – July 27, 2018

State Project No. 009-0059-RNV ADDENDUM 5 – December 6, 2018

2. Cover with waterproof paper, tarpaulin, or polyethylene sheeting. Allow for air circulation inside

covering.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Handrails, Railings, And Balusters: 1-1/2 inch outside diameter galvanized steel pipe, meeting

requirements of ASTM A 53 or galvanized steel tubing meeting requirements of ASTM A 501.

B. Rail Setting Grout:

1. Commercial nonshrink grout conforming to requirements of ASTM C 1107, Type B or Type C.

2. Approved Manufacturers:

a. Normal Construction Grout A by W R Bonsal, Charlotte, NC (800) 334-0784 or (704)

525-1621. www.bonsal.com

b. Advantage 1107 Grout by Dayton/Richmond, Miamisburg, OH (800) 745-3700 or

(937) 866-0711. www.daytonrichmond.com

c. NS Grout by Euclid Chemical Co, Cleveland, OH (800) 321-7628 or (216) 531-9222.

www.euclidchemical.com

d. 5 Star Special Grout 110 by Five Star Products Inc, Fairfield, CT (800) 243-2206 or

(203) 336-7900. www.fivestarproducts.com

e. Duragrout by L&M Construction Chemicals Inc, Omaha, NE (800) 362-3331 or (402)

453-6600. www.lmcc.com

f. Masterflow 713 Pre-mixed Grout by Master Builders, Cleveland, OH (800) 628-9990

or (216) 831-5500 www.masterbuilders.com

g. Sonogrout 10K by Sonneborn Building Products, Shakopee, MN (800) 496-6067 or

(612) 496-6000. www.chemrex.com

h. Tamms Grout 621 by TAMMS Industries, Mentor, OH (800) 218-2667 or (815) 522-

3394. www.tamms.com

i. CG-86 Grout by W R Meadows, Elgin, IL (800) 342-5979 or (847) 683-4500.

www.wrmeadows.com

2.2 FABRICATION

A. General:

1. Preassemble railing systems in shop to greatest extent possible to minimize field splicing and

assembly.

2. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for

reassembly and coordinated installation. Use connections that maintain structural value of joined

pieces.

3. Grind smooth welded joints and buff welds to same appearance as remainder of railing. Repair

galvanizing and cut pipe ends.

4. Return pipe ends of wall mounted handrails into wall.

5. Cap pipe ends of floor/ground mounted handrails and exterior handrails.

6. After fabrication, shop prime metal to be painted.

Page 28: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

Johnson Elementary School METAL RAILINGS

Additions and Renovations 05 52 00 - 3

PE Project 68962.00 Construction Document Submission – July 27, 2018

State Project No. 009-0059-RNV ADDENDUM 5 – December 6, 2018

B. Form curves by bending pipe in jigs to produce uniform curvature for each configuration required.

Maintain cylindrical cross-section of pipe throughout entire bend without buckling, twisting, cracking,

or otherwise deforming exposed surfaces of pipe.

C. Welded Connections:

1. Fabricate railing system and handrail connections by welding.

2. Weld corners and seams continuously to comply with following:

a. Use materials and methods that minimize distortion and develop strength and corrosion

resistance of base metals.

b. At tee and cross intersections, notch ends of intersecting members to fit contour of pipe to

which end is joined and weld all around.

c. At exposed connections, finish exposed welds and surfaces smooth and blended so no

roughness shows after finishing and so contours of welded surfaces match adjacent surfaces.

D. Brackets, Flanges, Fittings, And Anchors:

1. Provide standard wall brackets, flanges, miscellaneous fittings, and anchors for connection of

handrails and railings to other construction.

2. Provide inserts and other anchorage devices for connecting handrails and railing systems to concrete

or masonry work.

2.3 FACTORY APPLIED COLOGALV FINISH

A. Factory-Applied Architectural Finish Over Galvanized Steel: Provide factory-applied architectural

coating over hot-dip galvanized steel matching approved samples.

1. Basis-of-Design: Colorgalv by Duncan Galvanizing.

2. Color: to be selected by Architect.

B. Coating:

1. Primer coat shall be factory-applied polyamide epoxy primer. Apply primer within 12 hours

after galvanizing at the same galvanizer’s plant in a controlled environment meeting applicable

environmental regulations and as recommended by the primer coating manufacturer.

2. Finish coat shall be factory-applied color-pigmented architectural finish. Apply finish coating at

the galvanizer’s plant, in a controlled environment meeting applicable environmental

regulations and as recommended by the finish coating manufacturer.

3. Coatings shall be certified OTC/VOC compliant and conform to applicable regulations and EPA

standards.

4. Apply the galvanizing, primer, and coating within the same facility and provide single-source

responsibility for galvanizing, priming and finish coating.

5. Clean galvanized surface to create an acceptable profile for coatings. Galvanizer shall certify

that performance will be met without blast cleaning and coating will be applied within 12 hours

of galvanizing at the galvanizer’s plant. If blasted, galvanizer shall certify that rugosity

standards are met.

Page 29: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

Johnson Elementary School METAL RAILINGS

Additions and Renovations 05 52 00 - 4

PE Project 68962.00 Construction Document Submission – July 27, 2018

State Project No. 009-0059-RNV ADDENDUM 5 – December 6, 2018

PART 3 - EXECUTION

3.1 INSTALLATION

A. Touch up field welds to match pre-finished material.

END OF SECTION

1777-32-03-o3018-spec 055200 metal railings

Page 30: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 195

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken Hunt

COMPANY NAME: Rizzo Corp.

SUBJECT: Equipment Supports

DISCIPLINE/TRADE: BP#7 – Roofing, BP#15 - HVAC

DWG./SPEC. REFERENCE:

QUESTION:

Spec Section 07 72 00 2.03 Roof Curbs and 2.04 Equipment Supports. Why are

these in this spec section? Roof Curbs and Equipment Supports should be by the

HVAC Contractor?

ANSWER:

Delete section 07 72 00 2.03 roof curbs and 2.04 equipment supports. refer to 23

05 48 and 23 74 16.

RESPONSE BY: J. Culotta@PE DATE: 12/06/2018

Page 31: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 196

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken HuntCOMPANY NAME: Rizzo Corp.

SUBJECT: Warranties

DISCIPLINE/TRADE: BP#15 - HVAC

DWG./SPEC. REFERENCE:

QUESTION:Spec Section 23 51 23 1.4 There is a Special Warranty section but no warranty period

ANSWER:Warranty period added to 23 51 23 1.6

RESPONSE BY: Jesse Vose, PE DATE: 12-04-2018

Page 32: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 197

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ryan Davis

COMPANY NAME: Schenectady Steel

SUBJECT: Roof Screens

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE:

QUESTION:

Please reconsider the roof top equipment screens and exterior sound screens to be

part of BP6 or 7.

There is no structural support steel shown on the structural drawings or on 9 / A-

324.

ANSWER:

Roof screens and their connections to the structure are to be provided by the roof

screen manufacturer. Layout and structural steel requirements have been shown in

reissued sheet S-103a. Bid Packaging by Rizzo Corporation.

RESPONSE BY: Brian Skecher, DTC DATE: 12/6/2018

Page 33: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 198

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ryan Davis

COMPANY NAME: Schenectady Steel

SUBJECT: Anchor Bolt Survey

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE:

QUESTION:

Does BP#4 own an anchor bolt survey?

ANSWER:

Yes

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 34: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 199

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ryan Davis

COMPANY NAME: Schenectady Steel

SUBJECT: Anchor Bolt Survey

DISCIPLINE/TRADE: BP#4 – Structural Steel & Misc. Metals

DWG./SPEC. REFERENCE:

QUESTION:

All demolition, shoring, and abatement covered by BP#1?

ANSWER:

Demolition and Shoring by BP#1 – Demolition & Abatement. All contractors are

responsible for lead removal work and cost wherever they are attaching to existing

painted surfaces.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 35: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 200

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Joe Puglisi

COMPANY NAME: The NY-CONN Corp.

SUBJECT: Access Control Wiring

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE: 28 13 00

QUESTION:

Spec Section 28 13 00 - Access Control (3.2A & 3.2B), states to the access control

integrator that cabling has been provided and installed by others and is coiled up in

the respective MDF/IDF room at the junction box at each door. This leads us to

believe that composite cables called for on the symbol legend found on drawing Y-

001 dated 7/27/18, are to be furnished & installed under BP#16. See attached

drawing Y-001, dated 7/27/18. The description for "CR" (card reader) included on

the security symbol legend, provides direction for installing composite cables to

each card reader, however goes on to state that "conduits and back boxes" shall be

provided & installed by the contractor awarded this project and refers us to

drawing T-200. The description does not state that the contractor awarded this

project is to provide and install the access control cables, as it does for other

symbols on the legend such as cameras. Lastly, the access control details found on

drawing Y-200, as referenced on the symbol legend on drawing Y-001, do not

show any cables in the conduits to accessible ceilings as the details for items where

Page 36: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

cabling is clearly to be provided by BP#16 do (please see attached). Please clarify

if access control system cabling is to be furnished and installed under BP#16.

ANSWER:

Access control cabling, backboxes, and conduit are to be furnished and installed by

the contractor awarded this project per Y-001.

RESPONSE BY: DATE: 12/6/18

Page 37: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 201

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Joe Puglisi

COMPANY NAME: The NY-CONN Corp.

SUBJECT: CO Detection

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE:

QUESTION:

Item #36-E of BP#16 states that the Electrical Contractor shall furnish and install

the CO Detection system in the boiler room. Please note that beside the one fire

alarm system CO detector shown in the boiler room on drawing EP-101C, dated

7/27/18, we cannot find any information or requirements for any such CO

Detection System in the building or boiler room. Please advise.

ANSWER:

Only include what is on the bid documents

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 38: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 202

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Joe Puglisi

COMPANY NAME: The NY-CONN Corp.

SUBJECT: Heat Trace

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE:

QUESTION:

Item #36G, of BO#16, states that the Electrical Contractor shall furnish and install

Heat Trace on Site Utilities. We cannot locate any heat trace requirements for site

utilities on any of the bid documents. Please advise.

ANSWER:

Only include what is on the bid documents

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 39: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 203

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Joe PuglisiCOMPANY NAME: The NY-CONN Corp.

SUBJECT: Alternate for Curved Canopy

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE:

QUESTION:The scope sheet for BP#16, under Item #1 - Alternates - required alternate pricing for lighting on the extended curved canopy. The electrical drawings do not include any specifications for light fixtures at the curved canopy, nor do they include circuiting or controls for the same. It appears that the canopy is not shown on the electrical drawings at all. We have found indication on the light fixtures on the curved canopy on drawing A-111c, dated 7/27/18, however there is not enough information provided on this drawing to foster fair & level bidding of the alternate. Please advise.

ANSWER:

PROVIDE (8) “SR” FIXTURES AS SHOWN ON A-111C, (1) “RC1” SINGLE ZONE DIGITAL ROOM CONTROLLER, AND (1) “BC” DIGITAL NETWORK BRIDGE. LOCATE CONTROLS IN ELECTRICAL ROOM AND WIRE TO SPARE 20A/1P CIRCUIT BREAKER IN PANEL “LP2-L” WITH 2#12, #12G, 3/4”C.

Commented [SC1]:

Page 40: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

SR: SELUX- L60W-1B35-40-LW-X-04-X-277V-DIM

RESPONSE BY: Brian Poeltl DATE: 12/6/18

Page 41: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 204

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Jack Tibbetts

COMPANY NAME: Connecticut Carpentry Corp.

SUBJECT: Basketball hoops

DISCIPLINE/TRADE: BP#11B – Gym Equipment

DWG./SPEC. REFERENCE:

QUESTION:

We need clarification on the basketball equipment. The drawings say exiting hoops

to remain, but the spec is calling out ceiling suspended units. Please advise.

ANSWER:

Provide new retractable basketball backstops as indicated in construction

documents.

RESPONSE BY: A. Dobbertin@PE DATE: 12/06/2018

Page 42: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 205

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT: Piping Insulation

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE: 23 07 19

QUESTION:HVAC Piping Insulation Spec (23 07 19, page 26 #G), states to insulate the Engine Exhaust Piping and Silencer with Calcium Silicate: 4 inches thick? There is no engine exhaust piping, silencer or generator shown on the HVAC drawings? Please verify this spec section can be ignored for this project?

ANSWER:Engine exhaust / silencer insulation does not apply to this project.

RESPONSE BY: Jesse Vose, PE DATE: 12-05-2018

Page 43: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 206

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT: HVAC Equipment Insulation

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE: 23 07 16

QUESTION:"HVAC Equipment Insulation Spec (23 07 16, page 24 #J) states that the Piping system filter-housing insulation shall be one of the following:1. Cellular Glass: 3 inches thick.2. Mineral-Fiber Board: 2 inches thick and 3-lb/cu. ft. nominal density.3. Mineral-Fiber Pipe and Tank: 2 inches thick.Please provide a detail on the filter housings needed so the HVAC Insulation Contractors can account for this, if necessary?"

ANSWER:Piping system filter-housing insulation does not apply to this project.

RESPONSE BY: Jesse Vose, PE DATE: 12-05-2018

Page 44: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 207

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT: Heat Trace

DISCIPLINE/TRADE: BP#14 – Plumbing

DWG./SPEC. REFERENCE: P-300

QUESTION:Please verify that the Plumbing Contractor would only own furnishing and installing the heat tracing found on drawing P-300. The Heat Trace spec has extensive requirements including Gutters & Downspouts, Snow & Ice Melting on Roofs, etc., but none of these items are shown on the Plumbing drawings? Please advise on the scope of work to carry for Heat Tracing, if additional items are required, other than what is shown on the P-300 Plumbing drawing.ANSWER:

Construction Manager is responsible to advise on your scope of project.

RESPONSE BY: Jim Stenqvist DATE: 12/6/18

Page 45: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 208

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT:

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE: MP-101A

QUESTION:The 3" CHWS&R and HWS&R lines in the Lobby (C105) have symbols on the pipes that seems to be tees, however, no piping is coming off of them (See area near the center of the oval X-Ref background)? Is there perhaps some additional HVAC equipment and piping required in this area, or can those tees be disregarded? Or are those symbols meant to symbolize something else, as quite a few of them show up throughout the project?

ANSWER:Tees in Lobby C105 can be disregarded. When the piping connections were revised during design, the tees were accidentally left in the model.

RESPONSE BY: Jesse Vose, PE DATE: 12-06-2018

Page 46: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 209

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Richard MeloCOMPANY NAME: MJ Daly

SUBJECT:

DISCIPLINE/TRADE: BP#15 – HVAC

DWG./SPEC. REFERENCE: MP-101A

QUESTION:FCU-6 in 3rd Grade Classroom (109) and FCU-6 in 3rd Grade Classroom (111) on drawing MP-101A shows a shared 1" Condensate line tying into each unit, but a termination point to the plumbing system is not indicated on the drawing? Please indicate the "condensate indirect connect to sanitary" location for this condensate line?

ANSWER:Pipe has been extended to connect Classroom 109 & 111 condensate to the sanitary system. See sketch SKM-6.

RESPONSE BY: Jesse Vose, PE DATE: 12-06-2018

Page 47: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 210

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michele Shuler

COMPANY NAME: Tull Bros.

SUBJECT: Doors & Frames

DISCIPLINE/TRADE: BP#6 – General Trades; BP#8 – Aluminum Doors, Frames,

etc.

DWG./SPEC. REFERENCE: Door Schedule

QUESTION:

Opening ST-004A, Door schedule indicates HM Frame with Aluminum Doors. It

is very unusual to mix metals in this way. Please verify this is actual what is

desired, and if so who is supplying the hardware for this opening?

ANSWER:

Provide a wood door.

RESPONSE BY: JC@PE DATE: 12/5/18

Page 48: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 211

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michele Shuler

COMPANY NAME: Tull Bros.

SUBJECT: Hardware

DISCIPLINE/TRADE: BP#6 – General Trades

DWG./SPEC. REFERENCE: Door Schedule

QUESTION:

Opening 134.2 both door schedule and plan view indicate this opening to be a

single door – hardware set 35 indicated for this opening is for a pair of doors.

Please advise.

ANSWER:

Provide HW set #17.

RESPONSE BY: JC@PE DATE: 12/5/18

Page 49: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 212

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michele Shuler

COMPANY NAME: Tull Bros.

SUBJECT: Hardware

DISCIPLINE/TRADE: BP#6 – General Trades

DWG./SPEC. REFERENCE: Door Schedule

QUESTION:

Opening 126B is indicated to have hardware set 47, yet this opening is not

indicated to be STC rated. Please advise if this opening is to have and STC rating

(and if so what it is) or advise another hardware set for this opening.

ANSWER:

Provide STC-53 rated door.

RESPONSE BY: JC@PE DATE: 12/5/18

Page 50: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 213

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michele Shuler

COMPANY NAME: Tull Bros.

SUBJECT: Hardware

DISCIPLINE/TRADE: BP#6 – General Trades, BP#8 – Aluminum Doors, Frames,

etc.

DWG./SPEC. REFERENCE:

QUESTION:

Who is responsible for supplying the door hardware at openings C101a.1, C101a.2,

C101a.3, C101a.4 and 101.1 if it is similar to these?

ANSWER:

BP#8 – Aluminum Doors, Frames, etc. provides all hardware for aluminum doors.

BP#6 – General Trades provides all other door hardware.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 51: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 214

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michele Shuler

COMPANY NAME: Tull Bros.

SUBJECT: Hardware

DISCIPLINE/TRADE: BP#6 – General Trades

DWG./SPEC. REFERENCE: 08 11 13

QUESTION:

From Hollow Metal Spec 08 11 13-5, please advise opening numbers of which

exterior hollow metal doors are to be provided as 08 11 13-5 B. and which are to

be type 08 11 13-5 C.

ANSWER:

Provide extra heavy duty (08 11 13-5 B) at all egress doors and door 142.2.

RESPONSE BY: JC@PE DATE: 12/6/18

Page 52: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 215

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michele Shuler

COMPANY NAME: Tull Bros.

SUBJECT: Wall Type

DISCIPLINE/TRADE: BP#6 – General Trades

DWG./SPEC. REFERENCE:

QUESTION:

Verify wall type A03 has an overall width of 4-7/8”.

ANSWER:

Yes

RESPONSE BY: A. Dobbertin@PE DATE: 12/06/2018

Page 53: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 216

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken HuntCOMPANY NAME: Rizzo Corp.

SUBJECT: Missing power

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE:

QUESTION:EP-103C C-1 missing (near MAU-1) (refer to M-103C) Power for MAU-1 not shown.

ANSWER:

PROVIDE POWER TO CU-1 ON ROOF NEAR MAU-1. PROVIDE 2#10,#10G,3/4”C AND 25A/2P CIRCUIT BREAKER IN PANEL SB2-L. PROVIDE 25AT/30AF FUSED DISCONNECT SWITCH ON ROOF FOR EQUIPMENT.

RESPONSE BY: Brian Poeltl DATE: 12/6/18

Page 54: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 217

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Ken Hunt

COMPANY NAME: Rizzo Corp.

SUBJECT: Fill under slab on grade

DISCIPLINE/TRADE: BP#17 – Sitework

DWG./SPEC. REFERENCE:

QUESTION:

S-500 detail 24 typical slab on grade, shows 8” of 3/8” crushed stone under slab.

31 20 00 – 3.3F calls for 4” crushed stone and 8” structural fill. Which is correct?

ANSWER:

Provide 6-inches of subbase (as specified in Appendix F of the Geotech report)

over native glacial till or structural fill. Where shallow bedrock is present within

12-inches of the bottom of slab, provide 6-inches of subbase over, a minimum of

6-inches of structural fill, over bedrock.

RESPONSE BY: JC@PE DATE: 12/6/18

Page 55: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 218

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Michael Walton

COMPANY NAME: Northeast Interior Systems

SUBJECT: Cabinet Cores

DISCIPLINE/TRADE: BP#5 – Architectural Woodwork

DWG./SPEC. REFERENCE:

QUESTION:

RFI 040 was asked specifically about the doors and drawer fronts. My RFI applies

to all of the core material. We request FSC ULEF M2 particleboard be included as

an acceptable core material for the case body and doors of the plastic-laminate

cabinets on this project. (NU GREEN 2 Product Data attached).

ANSWER:

FSC ULEF M2 particle board is acceptable for use for the core material.

RESPONSE BY: JC@PE DATE: 12/06/2018

Page 56: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 219

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Top soil

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

Which bid package is responsible for screening and placing topsoil?

What about for the alternate for the field?

ANSWER:

BP#17B - Landscaping is responsible to place and amend as necessary all topsoil,

and all seeding.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 57: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 220

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Timber Rails

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

Please confirm that the site contractor shall furnish the timber rails even though

there is a separate bid package for site fencing.

ANSWER:

BP#17 Sitework shall furnish and install timber guard rails.

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 58: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 221

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Foundation Insulation

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

The wall sections on the structural drawings show the foundation insulation

extending down to the top of footing. The Architectural wall sections call out the

insulation extending down 2 feet below the slab. Please clarify which is correct.

ANSWER:

Provide minimum 2’-0” of insulation per architectural wall sections.

RESPONSE BY: A. Dobbertin@PE DATE: 12/06/2018

Page 59: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 222

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Peter Maddox

COMPANY NAME: Richards Corp.

SUBJECT: Footing Drains

DISCIPLINE/TRADE: BP#17 – Site Work

DWG./SPEC. REFERENCE:

QUESTION:

Drawing S-500 provides details for a footing drain and an underslab drain,

however no locations are shown on the drawings. Please identify where these are

to be installed.

ANSWER:

A footing drain should be installed at the edge of all exterior foundation wall

footings and tied into the site drainage.

Under slab drains are not mentioned in Geotechnical report.

RESPONSE BY: Brian Skelcher, DTC DATE: 12/6/2018

Page 60: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 223

PROJECT: Johnson Elementary SchoolRenovations and Additions500 Whittlesey DriveBethel, CT 06801

OWNER: Town of BethelARCHITECT: Perkins EastmanCONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Mark HaberCOMPANY NAME: Rizzo Corp.

SUBJECT: Feeders for LS Panels

DISCIPLINE/TRADE: BP#16 – Electrical

DWG./SPEC. REFERENCE:

QUESTION:Per E-401 it shows that the Feeders for the LS panels are to be run at a 2 Hour Fire rating. The rest of the cabling that runs out of this panel is not 2 hour rated. Because of this can Normal Conduit/Conductors be run in lieu of having the 2 hour fire rating on the main feeder only?If the 2 hour fire rating is to be maintain can 2 hour fire rated cable be used in lieu of conduit/conductors?

ANSWER:

ALL FEEDER CIRCUITS SHALL BE 2 HOUR RATED (HORIZONTAL AND VERTICAL), LISTED/LABELED, AND INSTALLED IN ACCORDANCE WITH UL 2196 (E.G. MINERAL INSULATED CABLES) AS INDICATED ON E-401. BRANCH WIRING DOES NOT HAVE TO BE 2 HOUR RATED.

RESPONSE BY: Brian Poeltl DATE: 12/6/18

Page 61: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 224

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Tom

COMPANY NAME: Imperial Roofing

SUBJECT: Existing Roof Insulation

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Is the Existing Roof insulation to remain in place? See Demo Note “F” on AD-

102A. Indicates Existing Roof Insulation to remain…..

ANSWER:

No. See updated note in Addendum #5.

RESPONSE BY: A. Dobbertin@PE DATE: 12/06/2018

Page 62: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 225

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukeski

COMPANY NAME: Barrett Roofing

SUBJECT: Canopy Plywood

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Please identify which contractor is to furnish and install the plywood sheathing for

the roof deck on the Canopy at the Bus Loop.

ANSWER:

BP#6 – General Trades

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 63: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 226

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Roof Finish

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Specification section 076200 references a 3-coat fluoropolymer finish which is an

expensive finish. Is a 2-coat finish acceptable?

ANSWER:

Maintain a 3-coat fluoropolymer finish.

RESPONSE BY: M. Convertito DATE: 12/06/2018

Page 64: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 227

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukesky

COMPANY NAME: Barrett Roofing

SUBJECT: Roof Color

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

There are details that call out White EPDM Membrane. The color of the membrane

in Spec Section 075323 is called out as black. What shall be the color of the

furnished EPDM membrane?

ANSWER:

Provide black as specified.

RESPONSE BY: A.Dobbertin@PE DATE: 12/06/2018

Page 65: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 228

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukeski

COMPANY NAME: Barrett Roofing

SUBJECT: Wood Blocking

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Please identify which contractor(s) are to furnish and install each piece of wood

blocking, plywood, and each insulation material at the roof edges for the following

details.

Details 3, 5, 7, 10, and 11 on Sheet A-321

Details 3, 8, and 11 on Sheet A-322

Details 1 and 2 on Sheet A323

ANSWER:

Sheet A-321 - BP#6 General Trades owns details 5, 7 & 11. BP#7 Roofing owns

details 3 & 10.

Sheet A 322 - BP#6 owns details 6 & 8, BP#7 - Roofing owns detail 3

Sheet A-323 - BP#7 Roofing owns details 1 & 2

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 66: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 229

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: David Lukeski

COMPANY NAME: Barrett Roofing

SUBJECT: Equipment Curbs & Rails

DISCIPLINE/TRADE: BP#7 – Roofing

DWG./SPEC. REFERENCE:

QUESTION:

Please confirm which contractor shall furnish and install the specified equipment

curbs and rails as specified in Spec Section 077200.

ANSWER:

See RFI-195

RESPONSE BY: Susan M. Chipouras DATE: 12/6/18

Page 67: RFI FORM - Connecticut · RFI FORM RFI NO.180 PROJECT: Johnson Elementary School Renovations and Additions 500 Whittlesey Drive Bethel, CT 06801 OWNER: Town of Bethel ARCHITECT: Perkins

RFI FORM

RFI NO. 230

PROJECT: Johnson Elementary School

Renovations and Additions

500 Whittlesey Drive

Bethel, CT 06801

OWNER: Town of Bethel

ARCHITECT: Perkins Eastman

CONSTRUCTION MANAGER: Rizzo Corporation

DATE: 11/30/18

FROM: Eric Rieve

COMPANY NAME: Firestop Incorporated

SUBJECT: Phasing of Sprinkler System

DISCIPLINE/TRADE: BP#13 – Fire Suppression

DWG./SPEC. REFERENCE:

QUESTION:

Various sections of the building will be completed at different times. It is expected

that the sprinkler system will be tested but not live in the earlier phases of the

project or are their plans for temporary removal of ceilings to create access from

the sprinkler riser room to the second floor during phase 2 to allow the system to

be live at the completion of phase 2. (There were no plans in the phasing to include

the ceiling removal work.) Since there are currently no sprinklers in the building,

will the Fire Marshall allow occupancy in areas with inactive sprinklers?

ANSWER:

The Fire Marshall and the Building Official will require that as sections are turned

over that the fire sprinkler systems be activated in those areas. This is based on the

Ct Fire & Building codes that stipulate fire sprinklers in "E" use buildings, as they

will fall under the CT Fire & Building Codes for alterations and new

construction/renovations.

RESPONSE BY: Thomas E. Galliford, Fire Marshall DATE: 12/5/18