rfp offeror’s section refernced question response … for information/general... · ip rfp...
TRANSCRIPT
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 1 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
1. Section 8 Resource
Requirements
119 Offeror shall propose a staffing model
that demonstrates how they will provide
all of the required expertise (stated or
implied) over the project life, how a
sufficient number of skilled staff will be
deployed on the project, and how the
project team will be structured to
effectively deliver the required work.
Page 119, Section 9, Integration
Platform Resource Requirements,
subsection A. Organization Structure
states: The IP Contractor shall design an
organization structure for the IP team
that enables efficient, high quality
performance and effective management
of all resources to successfully deliver
work under the IP contract.
However, RFP pages 120-126, Section
11, Key Personnel is very prescriptive
requiring 13 Named Staff, 11 of whom
must work 100% onsite in Santa Fe
throughout the life of the project. This
requirement as stated appears to
contradict the approach listed in Section
8 and 9 and significantly limits
Offerors’ ability to present bids that will
enable the most efficient, cost effective
and highest quality solutions for
Vendors must bid as required in the RFP.
Vendors may submit an alternative staffing
proposal, the proposals will be scored on
the staffing model required by the RFP.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 2 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
delivery.
Will HSD modify Section 11, Key
Personnel to allow Offerors the
opportunity to bid the number of Key
Personnel and an onsite/offsite
blended delivery model that best fits
with each Offerors bid solution?
2. Appendix G, 1.c Complete
Solution
9 With respect to the evaluation of re-use,
please confirm that the State does not
want vendors to assume re-use of any
components and that pricing should be
provided for all necessary hardware and
software.
CMS requires maximum reuse; it is the
State’s position that vendors who reuse
components also will be expected to factor
in additional costs.
3. Section II - B.
MMISR
Approach
MMISR
Approach
Will HSD consider releasing answers to
questions on a rolling basis prior to
September 22, 2016?
No
4. Will HSD kindly publish the Bidder’s
Conference attendee list that identifies
all HSD SME staff and Vendor
attendees?
Will be posted to
http://www.hsd.state.nm.us/LookingForInf
ormation/open-rfps.aspx
5. Section II - B.
MMISR
Approach
MMISR
Approach
18 The RFP states that that HSD must
complete implementation of the entire
MMISR solution not later than
November 30, 2018. The
implementation timelines for future
models will be dependent on the
implementation timeline for the
Integrated Platform. Will the State be
Yes.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 3 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
communicating the timelines and
systems availability of the IP to assure
the other modules can consider the IP
Vendor’s availability in order to meet
the needs?
6. Section II - B.
MMISR
Approach
MMISR
Approach
18 The overall MMISR implementation
timeline will be shaped by the ability for
multiple Vendors to meet inter-
dependencies. Will the State consider
other timelines for this, or other
modules which are contemplated to be
shorter than the IP due to end date for
the entire Enterprise, that may address
the situation where vendors do not feel
the timeline is adequate to meet the
requirements and timing of each
module?
The State will consider other timelines
within the overall MMISR framework, but
RFP responses should be framed in the
context of the timelines presented in the
RFP.
7. Appendix G – 3.
Database
Database 85 The IP Module Contractor will have
responsibility for the planning, design,
implementation, operation and
maintenance of an EDW that will be the
master repository for reporting, ad hoc
queries and analytics for the MMISR
solution and for HHS 2020. While the
Data Services Module Contractor will
identify and provide the specific tools,
techniques and approaches used to
deliver these services, HSD wants to
ensure that the core infrastructure
Section 3 of the Requirements addresses
Hosting. These requirements to not require
or limit the IP vendor on hosting
subsequent modules. The Vendor should
describe its hosting solution and outline
any assumptions used for the solution.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 4 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
supporting DS is consistent with and is
hosted by the IP Contractor.
HSD has stated that the IP contractor
will provide, not just the database, but
also the infrastructure and hosting for
the Data Services Module; what is the
expectation of HSD for hosting the
remaining modules as those future
modules are described as "black box".
Will HSD confirm the future module
vendors will be hosting their own
solutions?
8. Appendix G
- b.
Operational
Data store
101 In some instances the ODS is described
as a Data Warehouse and in some
instances it may be described to be the
“system of record” for all modules data,
including that data which goes beyond
reporting needs. For example, all data
will be converted from the legacy
MMIS to the ODS and all modules will
exchange data with the ODS. Please
confirm the full intent of the Operational
Data Store identified in the RFP. Is it to
be only an analytic database/data store
or is also a more transaction focused
database where modules will get the
info they need to operate and process
transactions (e.g. such that if the claims
module needs provider data will it go to
The IP is comprised of three major
components: the ESB, the ODS and the
EDW. The ODS is intended to be used for
system migration and data conversion
activities only. As each legacy system gets
replaced, the ODS will serve as the
repository of those source systems’ data.
As is typical for traditional ODS
implementations, it will likely mimic the
source systems’ physical schemas.
The EDW can more accurately be thought
of as the IP’s System of Record, where
message content may be stored in an HSD-
compliant format and vernacular, for use
by the DS system.
All message requests, responses, inquiries,
broadcasts, subscriptions, etc. will be made
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 5 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
the ODS or is that data acquired via a
service call through the IP to the
Provider module)?
through/via the ESB, which may source
some of the data from the EDW, but likely
not the ODS, since it is a data conversion
artifact only. Any data required to support
ongoing business activities will flow
through the ESB portion of the IP, and
some or all of those data may end up in the
EDW/System of Record.
9. Section 4,
Section 5,
Appendix G, 100, 112 As per our understanding from the RFP,
we assume that the IP contractor will be
responsible for performing the following
testing activities throughout the
engagement: Please confirm.
1. During the IP Implementation phase:
a. Quality Assurance Testing (QAT)
b. System Integration Testing (SIT)
c. Automated Regression testing
d. Performance (Load) Testing -
Benchmarking
c. User Acceptance Testing (UAT)
Support
2. During the Maintenance and support
phase:
a. Production defect fixes testing
b. End to end testing for any Change
Request/Enhancement planned as part of
a production release
c. Integration Testing for integration
1) Confirmed
2) Confirmed
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 6 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
of IP solution with other MMISR
modules
d. Automated regression and
performance (load) testing to ensure
there is no impact on the production
system due to other MMISR module
integration (or) IP production release
10. Section 4 Appendix G 106 We understand that the State expects the
vendor to perform QAT (Quality
assurance testing) as part of IP
implementation phase. Please elaborate
on the testing activities and tasks
expected as part of QAT.
The State expects the IP vendor to oversee
QAT testing to ensure integration. Vendor
to provide testing plan. Each vendor is
expected to perform QAT testing. The
activities will be outlined in a testing plan
submitted to the State for approval by the
selected Vendor.
11. Section 13 Append
ix G
131 Appendix G, Section 13, point 6
mentions that "HSD will provide staff to
participate in IP solution and MMISR
solution testing in accordance with
agreed-upon test plans". Please confirm
if all the resources required for testing
will be provided by HSD (or) is the
vendor expected to provide the testing
resources.
Vendor is expected to provide testing
resources.
12. Section 5 Appendix G 114 RFP mentions " Report regularly upon
QM/QA activities, including but not
limited to: work performed, detailed
analyses of QA/QM findings, statistics
related to the findings, corrective action
Regular reporting will include weekly, bi-
weekly, monthly, quarterly, and annually
frequencies.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 7 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
plans and status". What is the
recommended frequency of QM/QA
report submitted to the State (Weekly,
Bi-Weekly, Monthly, Quarterly, etc.)
13. Section 5 Appendix G 112 a)Are there any Non-functional
requirements or SLA's which the IP
solution is expected to meet from
performance standpoint (Ex: Response
time, Concurrent user load, etc.)
b) Could you please confirm if there are
any test cases already available with the
State .
a) Expectation is for State and Vendor to
work together to establish reasonable
SLA’s. Please see 9 - HHS 2020 MMIS
Activity Data in the procurement library.
Vendor is expected to specify assumptions.
b) No. Current test cases do not apply to
the MMISR solution.
14. Privacy and
Security
h. REQUIRED
PROTOCOLS
AND
STANDARDS,
We are assuming that the NM DoIT
Simms Data Center in Santa Fe, NM,
and HSD’s non-production data center
in Albuquerque, NM are FISMA and
FedRamp compliant. Please confirm.
We are compliant with Federal and State
audit partners. We are NOT certified
FISMA or FedRamp compliant.
15. 2.b Enterprise
Technology
Service
Components
82 a) In this section, we could see the
following EDI transactions : 27X, 837,
834, 835.If any EDI tool is being used,
please share the landscape showcasing
presence of EDI applications and end to
end flows of these transactions.
b) If EDI tool is not being used
currently, please let us know if the State
has any preference ?
Vendor to provide/propose tool
16. 2.b Enterprise
Technology
Service
82 What are the kind of data
transformations occurring in the present
system (App-App/App-EDI/EDI-
Vendor’s solution must provide the
appropriate adaptors and transformation
tools to process all standard data formats.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 8 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Components App/App-xml/xml-app/xml-xml,etc)?
17. 2.b Enterprise
Technology
Service
Components
82 Are 837, 835, 834, 27X
transactions processed in real-time or
batch?
The current transactions are batched.
18. 2.b Enterprise
Technology
Service
Components
82 Are we processing both 4010 and 5010
versions of Enrollments.
5010
19. 2.b Enterprise
Technology
Service
Components
82 Are there any specific processing
requirements for the documents received
(For example: encryption, decryption,
adding a prefix or suffix, etc.)
Yes, as needed per individual document.
20. 2.b Enterprise
Technology
Service
Components
82 Please provide the details of the tracking
and exception handling mechanism in
the current system
Vendor to propose a solution.
21. 2.b Enterprise
Technology
Service
Components
82 Please provide the details of any
customer specific EDI data validations
enabled in the current system
Please refer to the Xerox System
Documentation in the Procurement
Library. Vendor should note that the State
is seeking an entire Enterprise solution
which is broader than the MMIS alone.
22. 2.b Enterprise
Technology
Service
Components
82 How do we receive files from
TPA/Employer in current system, please
specify the current file transfer method
The State does not understand the reference
to TPA/Employer files. The IP vendor will
define the file transfer method standards
subject to State approval.
23. 2.b Enterprise
Technology
82 a) Do you have any archival process in
current system, if yes please provide the
a) The current MMIS has a retention period
of 10 years.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 9 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Service
Components
retention period.
b)What data is critical? Any special care
to be taken for the same?
b) From a security perspective – PHI, IRS,
SSA, Master Data. All audit requirements
must be met for confidential data.
24. 2.b Enterprise
Technology
Service
Components
82 Are the mapping requirement
specification documents available for
the existing EDI maps?
System Documentation is being posted to
Procurement Library
25. 2.b Enterprise
Technology
Service
Components
82 What is the number of transactions /
documents received by the system in a
day/week/month/quarter/year?
These numbers are not known for the
future Enterprise solution. Please see
Procurement Library 9 - HHS 2020 MMIS
Activity Data for current Medicaid
information only.
26. 2.b Enterprise
Technology
Service
Components
82 a) What is the frequency of the inbound
and outbound document flow?
b) How much time do you take in
processing the received inbound and
outbound documents (Real time / Batch
processing)?
a) Refer to Addendum 12 - HHS 2020
Legacy Interfaces (2) in the procurement
library.
b) The State currently receives both real
time and batch documents and expects the
same with the IP vendor.
27. 2.b Enterprise
Technology
Service
Components
82 What is the number of trading partners
currently supported on the system?
This is an Enterprise solution and there are
currently 167 Medicaid only trading
partners. This number will be higher for
the Enterprise solution but a specific
number is not known at this time
28. 2.b Enterprise
Technology
Service
Components
82 Is server redundancy / load balancing
required for the IP solution ?
Yes.
29. 2.b Enterprise
Technology
82 a) What is the minimum uptime
SLA/requirement?
a) See requirement 7.56
b) Vendor to propose scheduled
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 10 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Service
Components
b) What can be the acceptable downtime
of the application for scheduled
maintenance?
maintenance windows, which the State
expects will not result in limitation of end
point systems to conduct business
transactions.
30. 2.b Enterprise
Technology
Service
Components
82 a) What kind of reporting system exists?
What kind of reconciliation is required
for production support
(manual/automatic reconciliation, etc.)
and how many reports in scope?
b) What is the expected file format for
these reports? Do we need to log report
generation activity? Do we require any
separate database for off line reports?
a) The State does not currently have an IP.
b) The Vendor’s proposed solution is
expected to include reconciliation
proposals, file format
recommendations, and its plans for
report generation. The proposal should
specify the tools the Vendor proposes
to use.
31. 2.b Enterprise
Technology
Service
Components
82 a) Does the application need support for
multiple languages? What are the
languages it should support?
b) Do we need to provide the support for
the entire application or should it be
limited to certain modules of the
application.
c) Integration Platform (IP) should
support Internationalization. IP should
be developed with products and tools
that can support international character
sets (Unicode).
d) IP vendor is responsible for supporting
the IP module and for ensuring the
readiness of subsequent modules to
connect using the transmission and
security standards established by the IP
Contractor.
32. 2.b Enterprise
Technology
Service
82 Is a Disaster Recovery site present for
the business critical applications or will
it be needed to be built by the vendor?
A Disaster Recovery solution must be built
by the Vendor. The frequency is no less
than annually.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 11 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Components What is the frequency of performing the
Disaster Recovering Exercise?
33. 2.b Enterprise
Technology
Service
Components
82 Is sufficient Disaster recovery
documentation available for the critical
flows / server
configurations/transformations .
The existing DR document is not relevant
to the MMISR Enterprise solution. Vendor
should propose a solution and provide
documentation.
34. Addendum 12 HHS 2020
Legacy
Interfaces
document,
MMIS
Interface List
3,4 a) What is the number of Interfaces in
scope? We see 128+ interfaces with
some indicated as TBD.
b) What are the different types of back
end Systems / Legacy System to be
integrated as part of IP solution. ?
a) There is no definitive number. We
have provided information on known
interfaces. As this is an Enterprise
solution we anticipate this number will
increase.
12 - HHS 2020 Legacy Interfaces (2)
in the Procurement Library
35. General Could you please share the architecture
roadmap for HHS 2020 vision
Please see the amendment for the updated
diagram.
36. 2c Table 8 76 a) No middleware/ESB tools are listed
in the tools list in Page 76 of the RFP
document. Is the State already
evaluating any tools for ESB?
b) Could you please let us know if there
is any preference for open source stack
or commercial vendors such as IBM?
c) Does the State already have any tools
for SOA governance.
d) What is current ETL tool that is being
used.
a) No
b) No preference
c) No
d) There is no ETL tool for the Enterprise
envisioned by this and subsequent
modular procurements.
The State expects the Vendor to provide
design/development tools such as
Individual Development Environment
(IDE), Automated Code Review (ACR),
Continuous Integration (CI), Source Code
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 12 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Editor (SCE), and Graphic User Interface
Development/Builder (GUID/B). State
expects any tools that are used to view or
access code will not be proprietary or will
be licensed to the State at no additional
cost.
37. Appendix H
Is customer evaluating any off-the-shelf
products for the member enrollment and
claims adjudication workflows? If not,
can we propose BPM tools like Pega
etc.
Member enrollment occurs in ASPEN and
claims adjudication will be in the financial
services module provided by BPO. It is
expected that each module will have its
own workflow; IP is responsible for
“moving” task between modules.
38. Appendix H
What is the State's mobile technology
roadmap? Is customer looking to expose
and monetize the APIs to external world
for building mobile applications?
No roadmap yet, but the goal is to utilize
mobile technology. State is looking for
vendor to provide recommendations and a
roadmap for solution. The State is not
asking Vendors to monetize APIs.
39. Appendix H
Is there any requirement to view how
the entire business process is performing
and see if there is any SLA breach and
improve the process performance .?
Yes. See Appendix G and Appendix H.
Specific SLAs are agreed upon during
contract negotiations.
40. Appendix H
What are the different channel /
different data formats through which
enrollments /claims will be submitted to
IP Platform for processing?
Vendor’s proposed solution must
demonstrate the capability to integrate all
formats.
41. Section 4 100 How many source tables/files are The legacy MMIS system has 405
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 13 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
present in the legacy MMIS system?
Production DB2 Tables (which includes 7
years of Claims History information).
These numbers are based on the current
MMIS and not the anticipated Enterprise.
42. Section 4 100 What are the modules that are currently
present in the legacy MMIS application
that need migration?
The current MMIS is not a modular
solution. All MMIS capabilities will need
migration, though not all functional areas
will be the responsibility of the IP Vendor.
43. IV B 26 How many source tables/files are
present in the legacy CSES system
maintained by Xerox?
None. CSES Source tables/files are not
maintained by Xerox.
44. b. Operational
Data Store
227 a) What is the current data volume (in
GB) of the ODS source
b) What are the different data file
formats going to flow into ODS
a) The current data volume is not relevant
for what is anticipated in the Enterprise
solution.
b) Standardized file formats.
45. i. define model-
to-model
relationships of
repository
objects
230 Is this requirement similar to 'Abinitio
MDR' tool representation
Yes
46. Section C 3 What is the expected volume of files/DB
Size (both History & ongoing) for the
following?
1. Conversion of data from the Legacy
MMIS to the IP ODS
2. Import Legacy data from the
Omnicaid DB into ODS
3. ETL Process to load the data into
Refer to addendum 15- Conversion in the
procurement library.
T O T A L S I Z E: TRACKS===>
6985060
CYLINDERS===>
465670.667
Or 500 GB which includes 7 years-worth
of claims history. Including 10 years of
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 14 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
MMISR DW or DS Contractor from
ODS
4. What are the number of files that will
be exported by Xerox for loading to
ODS.
claims history, we are looking at 1000 GB
or 1 Terabyte worth of data.
1&2. See question #41. Omnicaid is a
DB2 system.
These numbers are based on the current
MMIS and not the entire Enterprise.
3. Vendor to propose a process. As a DB2
system, Xerox would leverage the DB2
unload function to unload the data from the
DB2 tables.
4. This would depend on the non-DB2
files the State would like to export. For
DB2 unloads, we would break the 7 years
of claims data into extract files by paid date
ranges to facilitate timely extracting, file
exchange and loading of smaller files as
needed. The number of files will be
dependent on the size and will be
determined during conversion.
47. Section C 3 A)What is the expected YoY growth of
data? This would be helpful for
appropriate infrastructure identification
b) How many years of historical data
will have to be loaded and maintained?
a) The State declines to provide estimates
for these parameters as these numbers
are not known. The known data for the
MMIS is in the Procurement Library.
The State will add to the Procurement
Library 9 - HHS 2020 MMIS Activity
Data.
SFYE17 Enrollment is projected to be
at 927,547 the projected growth is for
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 15 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Medicaid only members. Vendor
should note that Medicaid is just one
component of the Enterprise.
b) The current MMIS has a retention
period of 10 years.
Vendor should provide assumptions used
in their proposal.
48. Appendix H
How many extracts are expected to be
provided to external systems?
The known interfaces are included in the
Procurement Library 12 - HHS 2020
Legacy Interfaces (2)
49. Appendix H
Do we have Reporting requirement as
part of this scope? If so,
a. What is the estimated number of
Standard, Dashboards and Scorecards
looking at as part of the proposal? ?
b. What are the standard report output
formats (like PDF, Xls, etc.) or
Reporting tool expected as part of this
scope?
c. Do we have analytic Reports
expected as part of this RFP?
a) Reporting requirements for IP are for
system performance, not data analytics.
b) Propose the format in which you
produce reports. The IP Vendor is to
bring the reporting and analytic tools
for system monitoring and performance
etc.
c) Only as they relate to IP module
performance.
50. Appendix H
What is the technology platform of
databases in the source systems.
Varied Relational Data Base, Varied Flat
Files and Varied Proprietary sources. We
expect the Vendor to have adaptors
(including JSON) to handle a variety of
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 16 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
source data.
51. Section 4.b (b) 102 What will be the total number of data
sources ? How many inbound and
outbound files are expected as part of
this engagement ?
See the interface list in the procurement
library. Vendor is expected to understand
that there will be sources other than the
MMIS.
52. Section 4.b.c.1 102 As mentioned Xerox will be responsible
to extract comma-separated files to load
data for IP ODS and MMIS Data
warehouse (other requirements)
Would it be possible XEROX to send
the information in a defined (Common)
format across all submitters? Will all the
(Claim, MCO E&M, etc.) details come
in a one single master file or individual
separate files for each data sets?
See Addendum 15 in the Procurement
Library related to Turnover.
53. Section 4.b.e 102 We are assuming that the State will
provide the existing Data model
document to incorporate new /
additional fields as part of the data
movement into IP ODS and MMIS
DW/DS tables. Please confirm.
No
54. Section 4.b.c.2 102 How frequently does the inaccurate
exception report needs to be sent to
HSD ? Is the expectation to schedule
this report or execute on-demand?
Both - Scheduled and On-Demand,
dependent upon the exception.
55. 2.c Enterprise 82 For each of the master indexes - MCI, a) This is an Enterprise system with
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 17 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Technology
Service
Components -
Master Index
MPI, MAI, MEI, explain the sources in
terms of the following:
a) What are the sources?
b) What are the functional areas covered
by these sources?
c) What is the nature of each of these
sources (type of database, files etc.)?
d) Are there any external sources? If
Yes, what is the integration mechanism
for such sources?
e) In what frequency will the sources
send data to MDM?
multiple sources for each.
b) All functional areas.
c) All types of sources and the expectation
is the Vendor will have the adapters
needed.
d) Vendor is expected to recommend an
integration mechanism.
e) varies
56. 2.c Enterprise
Technology
Service
Components -
Master Index
83 Do you have licenses for any of the
following -
a) Data Quality Tool
b) Metadata Management Tool
c) Master Data Management Tool
If not, what is choice of tool for these
components?
a) Data Quality Tools are part of ASPEN
b) No
c) No; see table 8 in the RFP – Reuse.
Vendor’s proposed solution should
outline the tools.
57. 2.c Enterprise
Technology
Service
Components -
Master Index
83 For each of the master indexes - MCI,
MPI, MAI, MEI, explain the
downstreams in terms of the following:
a) What are the downstreams?
b) What are the functional areas covered
by these downstreams?
d) What are the requirements /
expectations of these downstreams?
e) What is the mode of interaction
(including frequency) for each of these
See response to Question 55.
The expectation is that the Vendor will
create the master indices within the MDM
and will use the MDM functionality to
manage the indices.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 18 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
downstreams?
58. 2.c Enterprise
Technology
Service
Components -
Master Index
83 a)Is there any requirement for Business
Glossary? Please provide the details if
applicable .
b) Is there any requirement for
requirement for Data Lineage to be
established? Please provide the details
if applicable .
c) Is there any requirement to link the
different master indexes? Please provide
the details if applicable.
a) Yes.
b) Yes.
c) Yes.
Defining details would be part of the JAD
process for the selected Vendor.
59. 2.c Enterprise
Technology
Service
Components -
Master Index
85 a) What is the current state of Data
Governance?
b) We understand that the DS contractor
will be responsible for designing and
implementing the Data Governance.
What is the scope of Data Governance
from IP Contractor perspective.
a) In development
b) The State expects the IP Contractor to
participate in and contribute to
discussions and decisions related to
Data Governance with the State and the
selected DS module Vendor. The State
also expects the IP Contractor to
enforce the established Data
Governance processes.
60. 2.c Enterprise
Technology
Service
Components -
Master Index
86 Has any data profiling activity been
done for the sources of Master Data
Management?
No
61. 2.c Enterprise
Technology
87 Is there any existing implementation of
any of the following -
No
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 19 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Service
Components -
Master Index
Data Quality
Metadata Management
Master Data Management
If YES, please provide the details of the
transitions
62. section b Operational
Data Source
101 Do we have "Data Dictionary", "Data
Model" and other documentation for
understanding of legacy MMIS and
Omnicaid systems
Yes. See procurement library
63. Appendix H 140 What is the approximate amount of
storage that you will be replicating
between sites (ex: 30TB)?
Not sure what is meant by “between sites.”
Depends upon Vendor’s proposed
deployment strategy.
64. Appendix H 140 What is the expected rate of data change
at the primary site(s) (GB/day)?
State does not have an estimate available.
65. Appendix H 140 Will any new applications be accepted
when we are in DR
No
66. Appendix H 140 In the event of a disaster, should the site
failover be initiated manually or
automatically?
Automatically preferred
67. Appendix H 140 Will the vendor be expected to setup a
DR for the primary datacenter? If so
please mention the DR requirements
(Hot/Warm/Cold with recovery time
expectations) ?
Refer to Requirements 6.01, 6.02 and 6.03
for DR. Vendor should include their
recommendation for Hot/Warm/Cold
recovery time.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 20 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
68. Appendix H 140 What are the RPO / RTO requirement
for the solution in scope?
Vendor to propose solution.
69. Appendix H 140 Are there any external application
dependencies for the DR scope which
needs to be factored in .
Vendor to describe their solution for
dependencies. See the Interface List in the
Procurement Library.
70. Appendix H 140 Are there any encryption requirements
for the replicated data?
Yes. Please see 14 14 - HHS 2020
Security Privacy and Standard in the
Procurement Library
71. Appendix H 140 Is the requirement for replication 1-way,
bi-directional or multi-site?
Vendor to submit recommended solution.
72. Appendix H 140 What are the number and frequency of
application bookmarks (checkpoints)
required and what is the associated
retention period?
Vendor to submit recommended solution
73. Appendix H 140 List any replication technology
requirements if any
Network/SAN/Hosted)?
Dependent upon Vendor’s proposed DR
solution. See Table 8 in the RFP – Reuse.
74. Appendix H 140 List the network requirements for
replication between the facilities
(MPLS, HOSTING PARTNER
Backbone, …. ).
Dependent upon Vendor’s proposed DR
solution. Please see Table 8 RFP - Reuse
75. Appendix H 140 Is there a current Disaster recovery
system in place? If so, please provide
Yes, see table 8 RFP – Reuse
The existing DR recovery system is
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 21 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
more details.
irrelevant and Vendor should propose a
solution and provide the documentation.
State has a disaster recovery site located in
Albuquerque that hosts non-Omnicaid
systems.
76. Appendix H 140 How many Disaster recovery sites do
you have?
State has a disaster recovery site located in
Albuquerque that hosts non-Omnicaid
systems.
77. Appendix H 140 Is an external vendor currently being
used for DR activities?
Yes, all of the State’s current external
vendors, such as Xerox, are required to
have their own DR plans and activities.
78. Appendix H 140 What is the current Storage architecture
for the state which is expected to be
used for this engagement
Vendor to propose a solution.
79. Appendix H 140 We see that the existing application is
using Corticon Business rules engine
5.3.4.6 and planned for upgrade to 5.5.
Could you please let us know if you are
open for evaluating other BRMS tools
apart from Corticon for this RFP (either
Open source tools like Drools /
Proprietary products like IBM ODM,
FICO Blaze)?
Yes
80. Appendix H 140 Could you please provide the following
additional details to help us better
understand the processing of Business
rules in the current system?
a) 15200
b) 5 million transactions from the ASPEN
eligibility system
c) both
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 22 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
a) Approximate number of Business
rules configured in the Corticon rules
engine
b) Approximate number of rules engine
hits/ transactions daily
c) Is the processing of business rules
batch processing / real time processing /
mix of both ?
Corticon is used for ASPEN Eligibility
system only.
Vendor’s proposed IP solution must
address the entire Enterprise’s data
integration requirements.
81. Appendix H 140 Could you please provide the sample
Business rules for major categories in
the existing application to understand
the level of complexity of the Business
Rules?
We assume bidder is asking about the
MMIS. See the Xerox system
documentation in the procurement library.
Bidder should note that this documentation
is not reflective of the complexity of
business rules that may be required for the
Enterprise.
82. Appendix H 140 Could you please let us know the scope
of work with respect to Business Rules?
Is there a need to completely revamp the
existing Business rules?
Scope of Work is defined in Appendix G.
Revamp is not needed for IP. The State
does not have a BRE that can be used for
the IP module.
83. Appendix H 140 Could you please let us know if the
Rules engine needs to interact with any
Database / external systems for
retrieving any relevant data during
processing other than the data that is
being sent by the Calling Application ?
If so, please provide the details.
Vendor to propose a recommended
solution.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 23 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
84. Appendix H 140 Could you please share the complexity
details of the Interfaces, possibly along
with the complexity definition.
Vendors familiar with Medicaid and
Healthcare should understand the
complexity of the interfaces listed in the
Procurement Library.
85. Appendix H 140 Could you please let us know the level
of configurability of Business rules by
Business users in the current system.
Will business users be able to configure
the rules directly?
The current system is not indicative of the
intended Enterprise.
86. Appendix H 140 Could you please let us know the
number of applications that are
triggering Corticon business rules in the
current system?
The current system is not indicative of the
intended Enterprise.
87. Appendix H 140 For which service/Use Cases will the
Business Rule engine be used for? Is it
confined to claim adjudication alone?
The IP rules engine is related to performing
services for the ESB. IP Vendor is not
responsible for claims adjudication.
88. Appendix H 140 Are Standard NFR's defined for the
Rules application? Example Response
time, production peak and average
service load, growth of users in
production, Throughput TPS, etc.?
No
89. VII Response
Specifications,
B. Other
Requirements,
51 Section 3. Financial Stability
Documents requests that Offerors
submit most recent audited financial
statements and 10K, for the preceding
The State requires hard copies of all
documents submitted.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 24 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
3. Financial
Stability
Documents
three years.
Given these documents are hundreds of
pages in volume and in order to remain
environmentally conscience, would the
State please accept these items via
electronic submission only?
90. Appendix H Response to
Specifications
142, 143 Within "System" Requirements, there's
a jump from Requirement 7.23 to 7.26.
Please clarify if there should be two
additional requirements, 7.24 and 7.25,
included.
The following requirements are to be
considered part of RFP and addressed in
Vendor’s response. These requirements
are also included in the RFP amendment.
7.24 Vendor shall propose required
tooling for Data Conversion/ODS and
EDW/IP System of Record such as
ETL/ELT, data profiling, metadata
management; for ESB, an administrative
dashboard and tuning tools; and for
MDM/Master Index, tools for
administration and tuning. Vendor shall
also propose roles and responsibilities for
State participants to interact with these
tools.
7.25 Vendor shall employ best practice
Software Quality Management tools such
as IDEs, Automated Code Review and
Continuous Integration tools, as well as
best practices for eliminating defects
before code goes to test. Vendor shall state
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 25 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
its understanding that all architecture and
design artifacts shall be approved by State
architects before being finalized and
submitted for development, configuration
and implementation.
91. VIII Evaluation, 1.
Mandatory
Specifications,
Required
Sample
Documents
53,54 The item "Required Sample
Documents" is listed under evaluation
and Mandatory Specifications, however,
there does not appear to be specific
guidance as to what sample documents
the Offeror is required to submit. Will
the State please provide clarification?
No. Vendor should use its own judgement
as to which sample documents best reflects
an understanding of the IP module.
92. VIII Evaluation,
Cost Points at
Sub-Factor
Level .v. Total
Evaluated Price
Receiving Total
Cost Points
54,55 The current approach to scoring Cost
Proposals may encourage companies to
shift their proposed costs into lower
point categories. Will the State please
consider scoring and awarding points
related to Cost based on Total Cost and
the Total Points attributed to Cost? If
not, will the State please clarify how
Cost Points will be scored in a way that
eliminates the potential for inappropriate
cost submissions?
Please see Amendment.
93. B. MMISR
Approach
1. The MMISR
Modular
Procurements -
b. Data
Services
15,16 RFP states that IP contractor is
responsible for providing Infrastructure
for Data Services procurement and Data
Services contractor will be responsible
for designing, implementing, operating
The IP Vendor is responsible for providing
the integration infrastructure for all
modules. All Module Vendors must
comply with the IP standards and
specification for service integration, data
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 26 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
and continually improving the
structures, processes and data needed to
support HSD.
As IP contractor will not know the
proposed solution, tools, and
performance needs of the Data Services
contractor at the time of submission,
will the State please provide guidance
on expected storage and growth or
entertain an option that would allow for
capacity to be increased/decreased as
needs change over time?
transmission, security, etc. as outlined in
this RFP. The State expects the Vendor to
provide a scalable solution which has
capacity that can be increased or decreased
over time without disruption to the
solution.
94. G. MMISR
Procurement
Library
Program-
related
Documents
33,35 RFP identifies 12 documents that are
contained within the Procurement
library, however, one seems to be
missing -"1. HHS 2020 Roles and
Responsibilities." Will the State please
upload this document to the
Procurement library?
Posted.
95. D. Contractor
Period of
Performance and
Scope
30 To create a level playing for all offerors
and reduce variation in sizing of HW
and SW Licenses, we request NM HSD
to publish input sizing parameter for all
key components including:
a) ESB
b) ODS
c) Data warehouse
The State declines to provide estimates for
these parameters as these numbers are not
known. The known data for the MMIS is
in the Procurement Library.
Vendor should note that Medicaid is just
one component of the Enterprise.
Vendor should provide assumptions used
in its proposal.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 27 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
The parameters may include the
following:
a) No. of transactions per hour on the
ESB
b) No. of Transactions during peak
hours
c) Size of Payload on the Messages
going through the ESB ODS
d) Total no of transactions per day
e) Total No of Transactions during peak
hours
f) Expected no of tables in the Data
warehouse
96. Appendix G -
Integration
Platform Detailed
Statement of
Work
1. IP Contractor
Role, c.
Complete
Solution
73,74 RFP states that IP Contractor will be
responsible for setting standards that
apply across the whole MMISR
solution; for facilitating problem
diagnosis and resolution across the
integrated solution; and for providing
guidance, review, testing, coordination
and troubleshooting as additional
MMISR contracts are awarded and
modules are implemented.
Our understanding is that NM has an
existing investment for Ticket and
Problem Management. Would the State
please provide additional information on
the product, version, and current
The State currently utilizes the Cherwell
ITSM version 8.1 for incident and request
ticket management across the Enterprise.
The State’s choice of a ticketing
management system may change over the
life of the IP contract. The State requires
the awarded Contractor to utilize the same
ticketing management system as the State.
The State will be responsible for building
in needed categories in the Service Catalog
as for the IP solution. Customization
beyond building necessary categories or
custom interfaces to the ticking
management system will need to be agreed
upon and may be at the Contractor’s
expense.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 28 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
utilization?
97. Appendix G -
Integration
Platform Detailed
Statement of
Work
2. IP
Technology
Requirements,
b. IP Tools
75 Will the State please let us know if there
is any Application Performance
Monitoring tools that are currently
utilized at DoIT State data centers?
There are no such tools at the data centers.
98. Appendix G -
Integration
Platform Detailed
Statement of
Work
3. Database, a.
Operational
Data Store
(ODS)
84,85 RFP states that the ODS must "Have
sufficient capacity to support known
workload requirements and be readily
expandable to accommodate increasing
or changing workloads."
Will the State consider publishing the
expected workload with a YOY growth
target in order to minimize variation?
See response to Question 95.
99. Appendix G -
Integration
Platform Detailed
Statement of
Work
3. Database, b.
Data
Warehouse
Infrastructure
85 The IP Module Contractor will have
responsibility for the planning, design,
implementation, operation and
maintenance of an EDW that will be the
master repository for reporting, ad hoc
queries and analytics for the MMISR
solution and for HHS 2020. While the
Data Services Module Contractor will
identify and provide the specific tools,
techniques and approaches used to
deliver these services, HSD wants to
ensure that the core infrastructure
supporting DS is
consistent with and is hosted by the IP
The IP Vendor is responsible for the
Enterprise Data Warehouse. We believe
this is outlined clearly in this RFP.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 29 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
Contractor.
Our Understanding is that IP contractor
will be responsible for providing
Infrastructure for Data Services
procurement scope on EDW and data
services contractor will be responsible
for implementation and operations of
EDW. Please clarify.
100. Appendix G -
Integration
Platform Detailed
Statement of
Work
4. Tools, g.
Hosting
87 In the option where NM hosts in the
DoIT Simms Data Center, should we
assume that NM will operate (monitor
and manage) the HW, Network,
Security, Hypervisor, and VMs up
through the Operating System as part of
DoIT standard infrastructure operations?
This should not be assumed. Vendor is
required to provide staffing for operations
of the IP solution.
The Security requirements include the
Vendor providing Authentication,
Authorization and Auditing (AAA).
101. Appendix D Reference
Questionnaire
Form
Appendix D states that the procurement
office must receive the Reference
Questionnaire Form no later than
September 7. Will the State please
clarify if this should be October 14, the
submission date of the proposal
response?
The Reference Questionnaire Forms are
due with the Proposal no later than October
14, 2016, 3PM.
102. Q&A Process Will the State consider allowing
potential Offerors the opportunity to
submit a second round of questions,
specifically for further clarification to
the answers posted on 9/22, if deemed
necessary?
No
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 30 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
103.
Appendix G
90 3. IP Project Management, Item a, bullet
f, refers to “Appendix G, Section IV,
D”. Could you please clarify the
reference to wherein the RFP details
may be found?
The RFP details for IP project management
are found in APPENDIX G, Section 3,
APPENDIX G, Section 6. and in the
Requirements listed in Appendix H.
104 Can you please clarify or provide a list
of what should be included as “Required
Sample Documents” which is cited as
25 points under the Evaluation Point
system? Also, please confirm that these
documents do not conform to the 300
page limit
See response to Question 91.
Sample documents are not considered as
part of the 300 page limit.
105. Within the Proposal Format instructions
on page 48, can you please clarify that
tables and/or figures may use other fonts
and sizes different from the Times
Roman 12 pt. font required.
Vendors may use other fonts and sizes in
Tables and Figures provided they are
readable. Vendor should note that all
submitted materials should be spellchecked
prior to submission.
106. I.A. Purpose Of
This Request
For Proposals
8 Please confirm that this requirement
applies only to an Offeror who is
bidding as the Prime Contractor, and
does not preclude vendors participating
as subcontractors on more than 2
modules.
As part of the HSD commitment to
maximizing the benefits of a modular
MMISR solution, which includes no
longer being dependent on a single
That is correct.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 31 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE
MMIS vendor, each Offeror may win no
more than two MMISR module
procurements. The selected IP
Contractor may not compete for or win
the Data Services (DS) module
procurement which will occur after this
release.
107. II.B.1.b 14 Please clarify whether the QA vendor
will use a CMS-compliant platform
provided by the IP vendor (or another
module vendor) or will be expected to
propose a QA module.
d. Quality Assurance (QA) –
Through a BPO contract, HSD will
contract with a vendor to obtain and
perform the following services for the
QA module using a CMS-compliant
platform and processes:
All modules must comply with CMS and
HSD requirements. Each module will be
procured independently. The IP Vendor is
not expected to propose a solution for any
other module.
108 Appendix H 8.02 Clarify the IP RFP requirements section
to help define the boundaries of work
between the IP vendor and future BPO
vendors for data conversion efforts - to
the effect that the IP vendor provides
future BPO vendors with data in formats
required to support BPO vendors’ data
conversion/migration activities.
The IP vendor is expected to provide future
BPO Vendors with data in standard
formats which the BPO Vendors may need
for conversion/migration/testing activities.
NM Human Services Department, Information Technology Division IP RFP #17-630-4000-1001
RESPONSES TO QUESTIONS
Page 32 of 32
RFP
SECTION
SECTION
TITLE
REFERNCED
PAGE
OFFEROR’S
QUESTION
HSD’S
RESPONSE