RHIC Heavy Ion Run-11
Status Meeting Updates
Heavy Ion Run Final Update 6/24-27
● Physics running, 41 stores
– Tandem intensity issues
– Access controls failure
– Access for RF trip
Outstanding items
Next 48 hours 6/27-29
● Physics ends 2200 Tuesday 6/28
● APEX and Power Supply tests until 0600
Wednesday 6/29
Heavy Ion Run Update 6/22-6/24● Physics running, 28 stores
– No failed ramps
– 4 aborted stores
● ODH HW failure
● Node card failure
● Abort kicker trip
● Power dip
● Blue injection retuned
● Reduced store length to 1
hour
● Conducted vernier scans
Outstanding items
● Yellow end-ramp
efficiency
– Better overnight
– Injection damper issues?
Weekend outlook 6/24-27
● Network recovery
● Continue Physics
● APEX and MD next week?
● Last meeting: Monday, noon
Heavy Ion Run Update 6/20-6/22● Setup started ~1730
Monday
● Physics started ~1730
Tuesday
– 6 stores
● Injection & ramp
collimation implemented
● Correcting injection drift
● Tandem reverted to optimal
Au configuration
Outstanding items
● Blue injection efficiency
● Yellow ramp efficiency
● Injection damper issues?
Next 48 hours 6/22-24
● Continue Physics
– Store length? Optimal ~1 hour.
– Can detectors remain on?
● Status meetings M-W-F
Heavy Ion Run Update 6/17-6/20● Physics running, 12 stores
– 2 failed ramps
● Blue abort prefire
– 1 aborted store
● power dip, QLI
● Tandem foil work conducted
behind store Friday.
● One additional store for
AnDY (16081)
● 200 GeV Physics ended 0800
Monday.
Outstanding items
● Blue injection efficiency
● Storage cavity voltage
calibration
– Blue cavities
– Requires working Blue
longitudinal Schottky
27 GeV startup 6/20-22
● Starts Monday 1600– IR access during hysteresis– Beam development follows
● Re-establish injected beam● Ramp with feedback● Store setup
● Status meetings M-W-F
Heavy Ion Run Update 6/15-6/17● Physics running, 6 stores
– 1 failed ramp
● LLRF test ramp
– 1 aborted store
● False BLM trip, 7W
● IP2 crossing angle removed after
maintenance
– Corrected with feedbacks
● Machine Development: 9 hours
– 7 hours LLRF
● Punctuated with 2 HLRF
failures/accesses and Blue injection
kicker failure
● Second ramp needed
– 2 hours AnDY collision setup
Outstanding items
● Tandem low on stripping foils
● Blue injection efficiency
● Blue transition
– Landau problem again, fill
16071
● Storage cavity voltage
calibration
– Blue cavities
– Requires working Blue
longitudinal Schottky
ZDC Accidental correction
● Number of buckets: Blue filled bunches
● STAR
– ZDC Singles East, ch 1
– ZDC Singles West, ch 2
– ZDC, ch 3
Corrected=ZDC-{East*West/[(Blue-Blue/14)*78000]}
● PHENIX
– ZDC Singles North, ch 1.1
– ZDC Singles South, ch 1.2
– ZDC, ch 16
Corrected=ZDC-[North*South/(Blue*78000)]
Final 200 GeV weekend 6/17-20
● Continue Physics– One more store with AnDY– One more set of vernier scans– One more test of β* squeeze
● Tandem foil work behind store● APEX Monday 0800-1600● √SNN = 27 GeV beam development starts Monday
1600● Status meetings M-W-F
Heavy Ion Run Update 6/13-6/15● Physics running, 10 stores
– 3 failed ramps
● Yellow feedback target tunes too
close?
● Yellow debunching before accramp
● Blue abort kicker prefire + quench
– 4 aborted stores
● Yo1-sxf1 trip
● Yellow abort kicker prefire + quench
● Wrong Chrom values left from MD
● Cryo lead flow interlock
● Beta squeeze, DX ramp test for
AnDY work
– Partially behind Booster RF failure
● Some Tandem intensity issues
Outstanding items
● Blue injection efficiency
● Storage cavity voltage
calibration
– Blue cavities
– Requires working Blue
longitudinal Schottky
Next 48 hours 6/13-15
● LLRF firmware upgrade
– Dump at 0900 tomorrow to begin
● AnDY ZDC calibration
– 2 stores following LLRF work
● Continue Physics● √SNN = 27 GeV beam development next Monday
● Status meetings M-W-F
Heavy Ion Run Update 6/10-6/13● Physics running, 14 stores
– 2 failed ramps
● Network switch failure,
11A
● BBQ lock windows not set
for ramp
– 1 early dump
● Rebucketing failure, HLRF
misconfiguration after
access
Outstanding items
● Blue longitudinal problems
on ramp
● Blue injection efficiency
● Storage cavity voltage
calibration
– Blue cavities
● LLRF firmware upgrade
– 4 hrs, week of 6/13
● AnDY ZDC calibration
27 GeV medium energy run notes
● Ramp name Au11v6 (work in progress)
– 13.5 GeV beam energy
– 3m β* at IP6 and IP8
– Below transition
● No rebucketing
● No longitudinal cooling
● AP shifts start 0800 Monday 6/20
Next 48 hours 6/13-15
● End of store MD: β* squeeze at IP6– Slow ramp to try and eliminate rise in beam decay
● Continue Physics– Continue fine tuning cooling for best performance.
● √SNN = 27 GeV beam development next
Monday● Status meetings M-W-F
Heavy Ion Run Update 6/8-6/10● Physics running, 4 stores
– no failed ramps
– 2 early dumps
● Sextupole temperature
problems in 1003B
● APEX, 16 hours
– Lost 4 hours to weather
and related issues.
Outstanding items
● Blue longitudinal problems on
ramp
– Although, none on the last few
ramps
● Blue injection efficiency
● Storage cavity voltage calibration
– Blue cavities
● LLRF firmware upgrade
– 4 hrs, week of 6/13
● AnDY ZDC calibration
Weekend outlook 6/10-13
● Access for PHENIX RPC issues.● Continue Physics
– Continue fine tuning cooling for best
performance.
● NOTE plan to run at √SNN = 27 GeV
● Status meetings M-W-F
Heavy Ion Run Update 6/6-6/8● Physics running, 9 stores
– 1 failed ramp
● Early ramp loss, LLRF problem
– 2 aborted stores
● Yellow abort kicker
● Yellow RF permit failure
● Machine development
– Beta* squeeze test, “MAD-X
knob”
– Some complications to
measured results, will try again
Outstanding items
● Blue longitudinal
problems on ramp
● Blue injection efficiency
● Storage cavity voltage
calibration
– Blue cavities
● LLRF firmware upgrade
– 4 hrs, week of 6/13
Cooling on vs. off
Next 48 hours 6/6-8
● Continue Physics– Continue fine tuning cooling for best
performance.● Test β* squeeze at end of store.● APEX Thursday
– Note NSRL/Tandem Si beam conflict● Status meetings M-W-F
Heavy Ion Run Update 6/3-6/6● Physics running, 14 stores
– 3 failed ramps
● Sextupole trip late in ramp
● Early Blue loss, RF or node
card?
– 1 aborted store, QD problem
– Landau cavity issues at
transition
● Machine development
– Beta* squeeze test, “MAD-
X knob”
Outstanding items
● Blue injection efficiency
● Storage cavity voltage
calibration
– Blue cavities
● LLRF firmware upgrade
– 4 hrs, week of 6/13
● Stochastic cooling issues
– BL kicker drive
Next 48 hours 6/6-8
● Continue Physics– Continue fine tuning cooling for best
performance.● APEX Wednesday
– Note NSRL/Tandem Si beam conflict● Status meetings M-W-F
Heavy Ion Run Update 5/27-6/1● Maintenance, vacuum pump down
complete Thursday 0330.
– STAR, PHENIX polarity reversal
● Physics running, 5 stores
– 1 early dump
● Low rates, Blue vacuum
– 3 aborted stores
● Yellow quench after rebucketing, YS5
cavity problem
● Yellow abort late in store, related to
activate?
● Cryo lead flow
● Machine development
– Beta* squeeze test, all planes both IRs
– Working point scan
– Yellow RF cavity voltage calibration
Outstanding items
● Blue injection efficiency
● Storage cavity voltage
calibration
– Blue cavities
● LLRF firmware upgrade
– 4 hrs, week of 6/13
● Stochastic cooling issues
– BL kicker drive repair
– BV not yet operational
New RF voltage calibrations
Present Yellow working point
Run-10 Yellow working point
Weekend outlook 6/3-6
● Restore stochastic cooling systems– Requires additional access– PHENIX access concurrently
● Continue Physics– Vernier scans Friday: early in store
● Status meetings M-W-F
Heavy Ion Run Update 5/27-6/1● Physics running, 19 stores
– 5 failed ramps
● Early loss attributed to y-qtrim?
● Yellow RF trip on ramp
● Fast Blue loss ~10 sec after γt (2x)
● Unexplained fast Blue loss late in ramp
– 5 aborted stores
● PASS failure
● Blue abort kicker
● STAR magnet ramping/chiller problems
● Early dump, YS3 trip/bad rebucketing
● QLI at dump, Yellow debunched beam
– 1 extended store
● Insufficient Tandem beam
● Some YL cooling issues, off for last 3 stores
Outstanding items
● Yellow, Blue store conditions
● Blue injection efficiency
● Storage cavity voltage calibration
– 1 test ramp
● BV cooling pickup
– Maintenance day item
● LLRF firmware upgrade
– 4 hrs, week of 6/13
● AGS ag17-qgt magnet failure
– Deferred to shutdown
Next 48 hours 6/1-3
● Complete maintenance– BV cooling pickup– YL cooling kicker motion control– YS2, YS3 RF– Yellow collimator pindiodes
● Resume Physics– STAR, PHENIX polarity switches– Vernier scans Thursday or Friday: early in store
● Machine Development Thursday:– End of store: test beta* squeeze, 2 IRs 4 planes– Starts between daytime stores– Store conditions
● Working point scans (dedicated ramp)● Storage voltage calibration
● Status meetings M-W-F
Heavy Ion Run Update 5/23-25● APEX completed Wednesday
– Attempt at fixing post-γt ramp loss
● Physics running, 4 stores
– 3 failed ramps
● Early loss attributed to y-qtrim?
● FEC reboot and subsequent steering error
● Fast loss ~10 sec after γt
– 1 aborted store
● Unexplained permit drop 6a to 7a
– AGS vacuum failure+Blue injection kicker
● Other work completed concurrently
– Machine Development deferred
– Some YV cooling issues(limit switch
fixed)
Outstanding items
● AGS ag17-qgt magnet failure
– Long maintenance day or shutdown
repair
● Yellow, Blue store conditions
● Blue injection efficiency
● Storage cavity voltage calibration
– 1 test ramp
● BV cooling pickup
– Maintenance day item
● LLRF firmware upgrade
– 4 hrs, week of 6/13
Holiday weekend 5/27-31
● Continue Physics● Machine Development items:
– Store conditions● Working point scans (dedicated ramp)● Yellow negative chromaticity? Blue?● Beta* squeeze – prepare for automation.
– More beam– Ramp Efficiency
● Ramp quicker after fill
● Status meetings M-W-F● Run Coordinator will be off-island but on cell...● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/23-25● Physics running, 7 stores
– No aborted stores (2 early dumps, 1 late
dump).
– 5 failed ramps
● Sextupole ramp rate (2x)
● Post-transition loss (3x)
– Accesses for repairs: YA1 cavity, stochastic
cooling amplifiers, sextupole feedthrough
ground current, collimator pin diodes…
– QD controls problems (2x)
● 3rd test of beta squeeze at store
– 4 planes successfully squeezed at once
– Requires more beam time to measure optics,
interpret resulting rate changes.
● Vernier scans conducted
● Outstanding items
– Blue, Yellow store conditions
● MD Thursday
– Storage cavity voltage calibration
● Requires test ramp
– Blue injection efficiency
● Fine tuning
● Offline evaluation
– AGS: ag17-qgt, tune quad
– ATR synchro errors
– BV cooling pickup
● Open vacuum to repair
– LLRF firmware upgrade
● 4 hrs week of 6/13
Next 48 hours 5/25-27
● APEX completes 2359 tonight ● Continue Physics● Machine Development Thursday
– Store conditions● Working point scans (dedicated ramp)● Yellow negative chromaticity? Blue?● Beta* squeeze – prepare for automation.
– More beam– Ramp Efficiency
● Ramp quicker after fill
● Status meetings M-W-F ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/20-23
● Physics running, 14 stores
– Only 2 failed ramps (Yellow abort
prefire)
– No aborted stores.
● All stochastic cooling systems on
– Still some kicker insertion issues
● Additional test of beta squeeze at
store (successful)
– Requires more beam time to
measure optics, interpret resulting
rate changes.
● Outstanding items– YA1 cavity problem
– Source/injector intensity
– Blue, Yellow store conditions● Ready for more beam?
– Storage cavity voltage
calibration● Requires test ramp
– Blue injection efficiency
● Fine tuning
● Offline evaluation
Next 48 hours 5/23-25
● Continue Physics– AGS access behind store for RF?– Store length with cooling?
– Continue stochastic cooling development● Machine Development items for improved luminosity
– More beam– Store conditions
● Working point scans (dedicated ramp)● Yellow negative chromaticity? Blue?● Beta* squeeze – prepare for automation.
– Ramp Efficiency● Ramp quicker after fill
● Status meetings M-W-F ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/18-20● Maintenance completed
– YS5, BS5 in operation
– Booster B3 RF modified
● Physics running, 8 stores
– Storage cavity trip at rebucketing
– Loss at rebucketing
– AGS extraction issue, early dump
– Power dip
– Loss at transition
● All stochastic cooling systems on but…
– YL slip detection issue
– BV broken switch
● Beta squeeze at store tested
● Outstanding items– Source/injector intensity
– Tenuous Yellow store
conditions
– Storage cavity voltage
calibration
– Blue injection efficiency
● Fine tuning
● Offline evaluation
YL, BL
YL, VL, YV, BV
YL, BL, YV, BV
YL, BL, YV
Measured tune shift at rebucketing
Weekend outlook 5/20-23
● Continue Physics– Store length with cooling?
● Stochastic cooling– Goal: all 4 operational this weekend
● Machine Development items for improved luminosity– Store conditions
● Yellow negative chromaticity? Blue?● Check y5-lm3.2 loss, collimation setup
– Ramp Efficiency● Ramp quicker after fill
– More beam
● Status meetings M-W-F ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/16-18
● Physics running, 7 stores
– Yellow losses after rebucketing (5x)
– bo3-sxd1 trip, loss after rebucketing
– ATR cogging problem during/after
MD
– Other LLRF issue?
● “Cured” by hysteresis
● Machine Development
– Corrected Blue injection
● Yellow vertical cooling
operational, but losses at kicker
exceed limits
● Outstanding items– Blue injection efficiency
● Fine tuning
● Offline evaluation
– Booster B3 RF, deferred
troubleshooting
– YS5, BS5 cavity conditioning● Maintenance item
– Storage cavity voltage
calibration
Injection efficiencies
5-May
6-May
7-May
8-May
9-May
10-May
11-May
12-May
13-May
14-May
15-May
16-May
17-May
18-May
19-May
0
100
200
300
400
500
600
700
Run11 RHIC AuAu Integrated Luminosity for Physics (200 GeV)
STAR PHENIX
Lmax Lmin
Phenix Run10
date
Inte
gra
ted
Lu
min
osi
ty [
mb
^-1
]
thru store 15877 Tuesay 17 May
Lumi data error corrected(still Run-10 cross section)
Next 48 hours 5/18-20
● Finish Maintenance● Continue Physics
– Store length with partial cooling?
● Stochastic cooling setup, Blue vertical– Every possible store
● Machine Development items for improved luminosity– Store conditions
● Yellow negative chromaticity? Blue?● Have we drifted from optimal working point?
– Ramp Efficiency● Ramp quicker after fill
– More beam
● Status meetings M-W-F ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update weekend
5/13-16● Physics running, 12 stores
– Landau cavity
configuration issue
– Controls server failure
+ restoration issue
– Transition abort
– Yellow store collimation
● Blue & Yellow longitudinal
cooling operational
● Outstanding items
– Blue injection efficiency
– Booster B3 RF, deferred
troubleshooting
– YS5, BS5 cavity
conditioning
This week’s outlook 5/16-?
● Continue Physics– Store length w/o cooling should be 4 hours.
● Stochastic cooling setup, vertical– Every possible store
● Machine Development items for improved luminosity– Ramp Efficiency
● Blue injection efficiency● Ramp quicker after fill● Yellow beam decay spikes at rebucketing.● Longitudinal growth after transition – gap volts? Low intensity bunch?
– More beam
● Next meetings M-W-F ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/12-13
● Physics running, 5 stores
– Peak luminosities
approaching best stores
from last run
● Yellow longitudinal
cooling operational
● Blue longitudinal tested,
not yet operational
● Outstanding items
– BS2 cavity trip
– Blue injection efficiency
● Better, but still variable
– Booster B3 RF, deferred
troubleshooting
– YS5, BS5 cavity
conditioning
● More conditioning for YS4,
BS4?
Longitudinal cooling on/off
Weekend 5/13-16
● Continue Physics– Store length w/o cooling should be 4 hours.
● Stochastic cooling setup– Every possible store
● Machine Development items for improved luminosity– Ramp Efficiency
● Ramp quicker after fill● Blue injection efficiency● Transition efficiency – chromaticity? Yellow dipole feedback?● Yellow beam decay spikes at rebucketing.
– More beam
● Next meeting Monday noon in LCR. ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/10-12
● Physics running, 4 stores
● Stochastic cooling setup
continues
● APEX
● Maintenance
– YA2 opened, repaired
– YS4, BS4 cavities in operation
– LLRF failure post-
maintenance
● Outstanding items
– Blue injection efficiency
● Better, but still variable
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
– YS5, BS5 cavity
conditioning
● More conditioning for YS4,
BS4?
Stores since Tuesday
Injection efficiency
IR4 Vacuum
Next 24 hours 5/11-12
● Continue Physics– Store length w/o cooling should be 4 hours.
● Stochastic cooling setup– Every possible store
● Machine Development items for improved luminosity– Ramp Efficiency
● Ramp quicker after fill
● Transition efficiency – chromaticity? Yellow dipole feedback?
● More vernier scans?
● Meeting tomorrow noon in LCR. ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/9-10
● Access for RF
troubleshooting, experiments
● Physics running, more long
stores
– PS problems
● Main magnet
– Abort kicker prefire
– Stochastic cooling trip
● Stochastic cooling setup
continues
● Outstanding items
– YA2 cavity
– AGS extraction efficiency
– Blue injection efficiency
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
– YS4, YS5, BS4, BS5
cavity conditioning
5-May
6-May
7-May
8-May
9-May
10-May
11-May
12-May
13-May
14-May
15-May
16-May
17-May
18-May
19-May
0
100
200
300
400
500
Run11 RHIC AuAu Integrated Luminosity for Physics (200 GeV)
STAR PHENIX
Lmax Lmin
Phenix Run10
date
Inte
gra
ted
Lu
min
osi
ty [
mb
^-1
]
thru store 15818 Monday 09 May
Next 24 hours 5/10-11● Continue Physics
– Reduce store length w/o cooling?
● Stochastic cooling setup– Every possible store
● Machine Development items for improved luminosity– AGS extraction efficiency work (parasitic)
● Still ~7% low?
– Ramp Efficiency● Ramp quicker after fill
● Transition efficiency – chromaticity?
● Schedule vernier scans
● APEX 0001-0800● Maintenance 0800-1600● NO MEETING TOMORROW ● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update
weekend 5/6-9● Physics running but with few
normal dumps
– PS problems
● Sextupole trip
● Main magnet
● UPS
– Periodic orbit correction/lead flow
– Abort kicker prefire
– Stochastic cooling trip
– YA2 RF problems
● Stochastic cooling setup
continues
● Outstanding items
– YA2 cavity
– AGS extraction efficiency
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
– YS4, YS5, BS4, BS5
cavity conditioning
– WCM calibration?
Weekend stores
Rates and backgrounds
WCM and DCCT
Next 24 hours 5/9-10
● Troubleshoot YA2● Continue Physics
– Reduce store length w/o cooling?
● Stochastic cooling setup– Every possible store
● Machine Development items for improved luminosity– AGS extraction efficiency work (parasitic)– Ramp Efficiency
● Ramp quicker after fill
● Transition efficiency – chromaticity?
● Schedule vernier scans● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 5/5-6● Rebucketing
operational
● 2 stores overnight
● Outstanding items
– Ramp efficiency
● 5-6% snapback loss
● 3-8% transition loss
– Storage cavity conditioning
● New cavities not yet up to
voltage
– Booster B3 RF cavity
● May limit our highest
injector intensities
– BS3 cavity
● investigating
Weekend 5/6-9● Ramp tuning
– Transition losses – chromaticity?– Orbit after transition– Injection debunching – check cavity phasing?– Continue ramp collimation setup
● Physics– Store length 4 hours?
● Store setup– Stochastic cooling setup, longitudinal first– Check & adjust store chromaticity– Increase bunch intensity/number up to 1.3/111
● Other items– Check injection drift correction – Optics measurements, Blue– Ramp chromaticity with Booster off?
● WEEKEND MEETINGS -- cancelled
Heavy Ion Run Update 5/4-5● Beam resumed ~2000 after
maintenance – Bunch intensities approaching 1.3e9
● YA1 cavity operational
● Landau cavities on
● Rebucketing setup started– Storage cavity phasing
● Yellow store chromaticity measured– Suggests negative horizontal
● Yellow tune scan at store– Best Yellow: (.2319, .2071)
– Blue: (.2310, .2147)
● b2-dhx, sector 5 qgt problems
● Outstanding items
– Ramp efficiency
● 5-6% snapback loss
● 3-8% transition loss
– Storage cavity
conditioning
● New cavities not yet up to
voltage
– WCM rebucket error
– Booster B3 RF cavity
● May limit our highest
injector intensities
Ramp Efficiency
Present working point
Next 24 hours 5/5-6
● Store setup– Rebucket setup has highest priority– Stochastic cooling setup, longitudinal first– Check & adjust chromaticity– Increase bunch intensity/number up to 1.3/111
● Overnight stores for experiments– Pending rebucket work
● Other items– Continue ramp collimation setup– Check injection drift correction – Optics measurements– Ramp chromaticity with Booster off?
Heavy Ion Run Update 5/3-4
● Collisions established
– 79x79, 1e11
● Initial collimation
complete
● 10 Hz feedback running
● Gap cleaning operational
● Outstanding items
– YA1 cavity
● Repair made, opened
vacuum during maintenance
today
– Misc elog issues
● Ramp efficiency entry
● RatView scales
– Booster B3 RF cavity
Store tunes
IPM Emittance
Next 24 hours 5/4-5
● Finish maintenance, restore beam– Evaluate YA1 repair
● Store setup– Rebucket setup– Stochastic cooling setup, longitudinal first– Increase bunch intensity/number up to 1.3/111
● Other items– Landau cavities– Check injection drift correction – Continue ramp collimation setup– Store chromaticity, Yellow– Optics measurements– Ramp chromaticity with Booster off?
Heavy Ion Run Update 5/2-3
● Beam to store on first ramp
● Ramp development finishes
major work in ~3 hours
● Completed items:
– Gamma jump, yellow dipole
feedback
– BPM timing @ injection, store
– Tune/coupling/orbit feedback
employed
– Tune/coupling replay exercised
– Ramp chromaticity measurement
● Outstanding items
– YA1 cavity
● Presently focusing on external
issues
– Note change in global beam sync
timing
● 26 ns Blue
● 24 ns Yellow
– WCM transition
– Misc elog issues
● Ramp efficiency entry
● Injection statistics?
● RatView scales
First ramp attempt
Blue ramp chromaticity
Yellow ramp chromaticity
Next 24 hours 5/3-4
● Ramp development, store setup until 0700 Wednesday– Investigate YA1 issue (access if necessary)– Increase bunch intensity/number up to 56 – Ramp collimation– RhicInjection orbit feedback test– RF cogging on ramp– Separation bump removal on ramp– Steer for collisions– Rebucket? Stochastic cooling?– Ramp chromaticity with Booster off?
Heavy Ion Run Update 4/29-5/2
● Low energy run
completed at 0800 this
morning
● Weekend troubles:
– Lead flow interlock
– AGS L10 RF cavity
● Outstanding items
– Injection efficiency
● Lower than normal injection
● Limits injected intensity
– Booster B3 RF, deferred
troubleshooting
Next 24 hours 5/2-3
● Injection beam development 1100-1300● PS ramp testing, Booster B3 RF troubleshooting ~1300-
1500 Monday.● Setup with beam resumes 1500 today.● AP shifts resume
– Re-establish injection– Instrumentation check– Ramp Development
Heavy Ion Run Update 4/28-29/11
● PHENIX zero field run
completed, settings
reverted.
● Second set of vernier
scans conducted.
● Power dip 1550-0030
– Booster, AGS ring accesses
required
● Outstanding items
– Injection efficiency
● Lower than normal injection
● Limits injected intensity
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
Weekend 4/29-5/2
● Continue Physics– Store length = 30 min
● Last vernier scans● APEX 0800-1400 Monday● √sNN=200 GeV setup begins 1400 Monday
– Ramp Au11v3::injection→Au11v1::injection with beam, feedback
● PS ramp testing, Booster B3 RF troubleshooting ~1600
Monday.● AP shifts resume Monday evening
Heavy Ion Run Update 4/27-28/11
● PHENIX zero field run
under way.
● Outstanding items
– Injection efficiency
● Lower than normal injection
● Limits injected intensity
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
Run-10 Au-Au
Run-11 Au-Au
Next 24 hours 4/28-29
● Resume normal stores● Continue Physics
– Store length = 30 min
● More vernier scans● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update 4/26-27/11
● Initial vernier scans
completed
– Optimized PHENIX,
repositioned STAR
● Booster beamstop failure
2130-0600
– Replaced bo6-qs3, yi6-sx3
– Repaired bi8-qf3
– Sublimated sector 4 vacuum
● Outstanding items
– Injection efficiency
● Limits injected intensity
– Orbit control
● High RMS since hysteresis
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
Next 24 hours 4/27-28
● Examine closed orbit, injection efficiency● Continue Physics
– Store length = 30 min
● More vernier scans● PHENIX zero field run
– Prior to tour access
● AP shifts: on call – ...but be prepared to log in remotely or come in if necessary.
● NO MEETING TOMORROW
Heavy Ion Run Update 4/25-26/11
● MD for Yellow
– Delayed by Booster failure
– Yellow orbit work: 1 hour
● Injection efficiency up > 10%
● No BLM issues since
– Initial collimation work: 1 hour
But…
● Blue orbit shifted
– Why? No evidence found yet
– Corrected blue steering for collisions
– Re-collimated.
– Eventually, corrected closed orbit
again and resteered, collimated.
● Outstanding items
– Injection efficiency
● Limits injected intensity
– Orbit control
● Can we correct orbit drift?
Should we?
● BPM issues?
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
– bo6-qs3 failure
Next 24 hours 4/26-27
● Continue Physics– Store length = 30 min
● Schedule vernier scans● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update Weekend
4/22-25/11● Mostly continuous running
– Over 80 stores since Friday
afternoon
– Store length reduced to 30 min
● Optimal ~15-20 min
● Scanned RF voltages
● PHENIX “vertex shift”
– Determined to be collimator
backsplash from opposite ring
● Outstanding items
– Beam lifetime
– Injection efficiency
● Limits injected intensity
– Orbit control
– Booster B3 RF, deferred
troubleshooting
– Vernier scans
– bo6-qs3 failure
– Instrumentation setup
● IPM, WCM
Next 24 hours 4/25-26
● Continue Physics– Store length = 30 min
● Machine Development items for improved luminosity– Work on orbit feedback management
● Yellow bend trim adjustment
– Injection efficiency work– Beam lifetime work
● Change working point● Better RF voltage choice (parasitic)?● Octupoles (parasitic)?
– 10 Hz GOFB (parasitic)● Schedule vernier scans● AP shifts: on call
– ...but be prepared to log in remotely or come in if necessary.
Heavy Ion Run Update Fri 4/22/11
● Booster B3 RF cavity running,
issues unresolved
– Will be of concern when we
start to push for maximum
injector performance
● Beam restored, captured in
both rings
● Tuned up to nominal intensities
● Initial collision steering and
collimation successful
● Outstanding items
– Bunched beam lifetime
– Booster B3 RF, deferred
troubleshooting
– Store automation
Weekend 4/22-24
● Start Physics– Store length = 1 hour?
● Improve store conditions, store turnaround times.– Store automation
– Optimize rates, minimize backgrounds
– Increase intensities
● AP shifts: Friday in MCR, Saturday/Sunday on call – ...but be prepared to log in remotely or come in if necessary.
● NO meeting Sunday. Saturday?
Heavy Ion Run Update Thu 4/21/11
● 28 MHz RF repairs, q7
polarity reversal complete
Wed ~2300
● Beam restored to both rings
● Intensities too low for RF
capture
● Beam from injectors unstable
● Node card/UPS failure,
1007C
● Outstanding items
– Tunes far from design
– Corrector strength/avg
offset too high?
– Booster B3 RF, AGS
bunch merge
RHIC operations
Injector performance
ATR transport
Next 24 hours 4/21-22
● Repair Booster B3 RF cavity● PHENIX access for tour● Resume RHIC injection setup
– Circulating beam● Check set/measured tunes vs. Au104/6/7
● Revert orbits to pp or med/hi Au ramps?
– RF capture
– Lifetime/intensity tuning
Heavy Ion Run Update Wed 4/20/11● 28 MHz RF acceleration cavity mechanical tuner problem
– fRF at 9 GeV: 27.9996 MHz
– fRF at 9.8 GeV normal injection: 28.0232 MHz
– Cavity lower limit: 28.070 MHz
● Setup items completed:– AGS-RHIC synchro
– AGS extraction, ATR transport (twice)
– 9.8 GeV lattice loaded
– RHIC first turn
– Injection kicker setup, circulating beam Blue and Yellow
– Blue RF capture
Next 24 hours 4/20-21
● Access to repair RF cavity tuners● Reverse q7 polarities, switch to IBS lattice.● Address other maintenance items
– AGS main magnet motor maintenance
● Resume RHIC injection setup– 9.8 GeV, Au11v3– First turn
– Circulating beam
– RF capture
– Lifetime/intensity tuning