rhode island department of environmental management office of waste management (owm) cynthia...
Post on 19-Dec-2015
217 views
TRANSCRIPT
Rhode Island Department of Environmental Management
Office of Waste Management (OWM)
Cynthia Gianfrancesco222-4700 X7126Terry Gray X2405
Overview of Tonight’s Topics Site Investigation Process Charbert Overburden Site Investigation Charbert Overburden Remediation Charbert Bedrock Aquifer Investigation Production Well Shutdown Oversight and Enforcement Site Security Communications Upcoming meetings
RIDEM Site Investigation and Remediation Program All Site Investigations must be conducted in accordance
with RIDEM regulations.
Investigation must include• Soil• Groundwater
• Overburden • Bedrock – if necessary
• Sediment - if necessary• Surface water - if necessary
Frequently includes a phased approach, especially where complex geology exists
Exceedances of RIDEM criteria must be identified and remediated
RIDEM Site Investigation and Remediation Program
Remediation Criteria Include: Soil:
• Direct Exposure Criteria for• Residential properties• Industrial/Commercial properties (Charbert site)
• GA or GB Leachability Criteria
Groundwater Criteria• GA criteria – suitable for drinking (Richmond & rural
areas)• GB criteria – not suitable for drinking (urban areas)
Site Investigation Pertaining to the Charbert Site
Site Investigation at the Charbert site was divided into 2 phases due to the presence of Chlorinated Solvents:
Overburden Site Investigation Report was submitted in June 2005 Supplemental Reports 1-9-06, 4-28-06
and 8-7-06
Bedrock Investigation is on going
Example of Aquifer
Shallow overburden aquifer ~ 50’ – 80’ thick
Confining layer ~ 10’ – 20’ thick
Deep overburden aquifer ~ 10 – 20’ thick
Bedrock aquifer ` 40’ – 120’ deep
Overburden Site Investigation
Over 40 monitoring wells installed 70 groundwater analysis 6 wells sampled quarterly around lagoons 14 wells sampled quarterly around SVE/AS
Over 70 soil analysis Over 40 private well analysis
Quarterly analysis of 14, 16 & 18 River St. since February 2005.
8 Diffusion Bag sample location in Wood River - samples groundwater under river
Overburden Site Investigation
Identified Areas of Concern (AOCs) requiring action:
Chlorinated solvent (drycleaning) spill area Residential Wells at 14, 16 & 18 River Street Solid Waste Disposal Areas Old Lagoon 5 Channel sediments Petroleum Product Recovery Trench Oil Line Rupture Environmental Land Use Restriction
Overburden Remedial Action Work Plan
October 2007 – ongoing source removal Chlorinated solvent spill area Soil Vapor Extraction/Air Sparge System Order of
Approval issued by RIDEM December 19, 2007 Air Sparge System – injects air into ground, enhances
bioremediation and strips vapors from groundwater
Soil Vapor Extraction System – enhances bioremediation and vacuums vapors from soil
Sparge Curtain – prevents migration of contaminants in groundwater to Wood River
All treated through Granular Activated Carbon prior to discharge to air
System fully operational on January 18, 2008
Extensive monitoring of system, groundwater and river to determine system performance
Water table
groundwater
soil
Air
vacuum
Treatment
16 SVE and 16 AS wells under building9 Horizontal SVE and 9 AS wells between building and river5 Horizontal SVE and 5 AS wells as Sparge Curtain along river
GZML-1
Overburden Remedial Action Work Plan October 2007 - ongoing
Residential Wells at 14, 16 and 18 River Street
These wells were identified as needing treatment due to trace levels of chlorinated solvents and bacteria.
Possible source: former septic system
Whole House Treatment Systems were installed in January 2005 by Charbert and have been operational since.
Charbert will continue to monitor quarterly and maintain as long as is necessary.
Overburden Remedial Action Work Plan
October 2007 Remaining RAWP Action Items for
approval Solid Waste Disposal Areas
• Four areas identified during site investigation• Solid waste removed in 2006 and areas
subsequently restored• Limited soil excavation required in one area
for elevated arsenic
Overburden Remedial Action Work Plan October 2007
Remaining RAWP Action Items for RIDEM approval (con’t) Old Lagoon 5 Channel sediments removal Petroleum Product Recovery Trench Oil Line Rupture removal Long Term Monitoring Environmental Land Use Restriction
All Activities expected to be on-going or completed by December 2008
Bedrock Aquifer Investigation – completed to date
Bedrock Aquifer Evaluation Work Plan–March 2006 Geophysical Investigation (ground penetrating radar) for
Bedrock Aquifer Evaluation, and Recommended Bedrock Well Locations July 2006
Bedrock Wells Installed & Borehole Geophysics conducted August – December 2006
Recommended Monitoring Well Packer Installation Zones for Bedrock Boreholes, February 2007
Bedrock Aquifer Evaluation Progress Report #2, Sept. 2007
Phase II Bedrock Aquifer Evaluation Work Plan, January 29, 2008 (under review)
3 bedrock wells installed 2006GZML-1 ( 205 feet deep) = trace levels of VOCsGZML-2 (206 feet deep) = cleanGZML-3 (160 feet deep) = high levels of VOCs
GZML-1
Bedrock Aquifer Investigation Geophysical report indicates bedrock fractures
are tilted away from Alton neighborhood, towards Wood River
September 2007 report confirmed bedrock contamination and zones (June and August sample results)
November 2007 DEM assisted Charbert in sampling 4 wells west of Wood River - no VOC contamination detected
RIDEM unable to confirm use of bedrock wells in Alton neighborhood.
Bedrock Aquifer Investigation Schedule
Additional data collection, evaluation and well location proposal: February - August 2008
Bedrock well installation :September 2008 – March 2009
Bedrock well sampling: March – April 2009
Bedrock Aquifer Site Investigation Report: April - June 2009.
Production Wells Shutdown Production wells are still being used to a limited extend
during plant shutdown
Groundwater monitoring began Feb. 18, 2008 and will continue until equilibrium has been reached to determine changes in groundwater flow, then quarterly thereafter
The groundwater depression associated with the production wells will revert to a natural state – this is not expected to adversely effect groundwater quality on the site
The groundwater mound associated with the lagoons will revert to a natural state – it is expected that this will improve groundwater quality on the site
DEM Oversight and Enforcement of Investigation and Remediation
Charbert’s parent company, NFA Corporation, is the responsible party
They are held to conducting all required work through the Consent Agreement and state law
In the event that they fail, DEM enforce through Superior Court
Site Security
According to Charbert:
Property Manager on site 40 hrs/week indefinately
Security System installed in building
Communications Documents at Clark Memorial
Library
DEM web site - with major documents and milestones
Upcoming Meetings April 2nd – Site Investigation and
Remediation 2nd meeting – Lagoons, Wetlands
and Plant Closure 3rd meeting – drinking water 4th meeting – tentative – if necessary