risk and return 2009

Upload: rajkumar35

Post on 06-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Risk and Return 2009

    1/10

    Risk and Return

    Rajan B. Paudel

    Course outline

    Risk and return - review of concepts and their measurement: return, risk, the expectedreturn on a portfolio, variance and standard deviation of a portfolio, portfolio opportunitysets, efficient set.

    Risk and return - theory: risk preference and mean-variance indifference curve, Marketequilibrium the capital market line, the capital assets pricing model (CAPM) and thesecurity market line (SML), applications of the CAPM, Empirical evidence on theCAPM, The Arbitrage Pricing Theory.

    Empirical evidences on risk and return

    Consider the following table

    Table 1: Rates of Return for the Projects

    Economic

    conditionProbability Project A Project B

    Combined

    (50%each)

    Very bad .2 -5% 35% 15%

    Bad .2 5 25 15

    Average .2 10 15 12.5

    Good .2 15 5 10

    Very good .2 20 -15 2.5

    Which project provides the firm more return?

    Which project is riskier?

    In which project should the firm invest?

    Return

    Return is what an investor earns in his investment.

    The expected rate of return is the weighted average of all possible returns where the returns areweighted by the probability that each will occur. Symbolically,

    E(R) = Pi Ri (1)

    where,E(R) = the expected rate of returnPi = probability of occurring each rate of returnRi = rate of return in ith state

    Accordingly, the expected return for Project A (given in Table 1) isE(RA) = 0.2(-5%) + 0.2(5%) + 0.2(10%) + 0.2(15%) + 0.2(20%)

    1

  • 8/3/2019 Risk and Return 2009

    2/10

    = 9%Similarly, the expected return for Project B is

    E(RB) = 0.2(35%) + 0.2(25%) + 0.2(15%) + 0.2(5%) + 0.2(-15%)= 13%

    Looking at the expected return, Project B is better

    What about the other measures of return like mode (most frequent item) and median (outcome in themiddle, 50th percentile)?

    Mode is not often used because security returns are real number (i. e. they can take on any decimalvalue)

    Median is better only when security returns are skewed

    Riskis defined as variability in returns.

    Related terms

    Uncertainty it is imprecise knowledge about potential future events, whereas risk is uncertainty thatcan be systematically assessed that is measured, priced and most importantly shared.

    Werner Heisenberg the noble laureate in Physic in 1932 explained the principle of uncertainty as: youcannot simultaneously assess the location as well as the future movement of an atomic particle; to doso you have to hit it with another atomic particle and that act changes both the position andmomentum of the target particle.

    Peril cause of loss, fire is the cause of loss it ones house burns

    Hazard - condition that create or increase the chances of loss, e.g. mountain terrain for air crash

    As we see in our example graphed in Figure 1, the return for project A varies between 5 percent to20 percent while that for Project B, it varies between 15 percent to 35 percent.

    Figure 1: The range of returns

    The range of the return as well as the deviation of the returns from the expected mean for Project B ishigher; hence, it is more risky than Project A.

    How can we possibly view variations above the expected return as risk? Should we not beconcerned only with the negative deviations? Some would agree and view risk as only thenegative variability in returns from a predetermined minimum acceptable rate of return. However,as long as the distribution of returns is symmetrical, the same conclusions will be reached.

    2

    - 50 - 40 - 30 - 20 - 10 0 10 20 30 40 50

    Project A with 9% expected return

    Project B with 13% expected return

    Project return (%)

    - 15 35- 5 139

  • 8/3/2019 Risk and Return 2009

    3/10

    Variance

    The variance of return, given that we have subjective probability distribution, is defined as averageof the mean squared error terms.

    A mean squared error is simply the square of the difference between a given return, Ri, and the

    average of all returns, E(R).

    Variance, (2) = [Ri - E(R)]2 Pi (2)

    Note, in case of sample data, the sum of the mean squared error is divided by (N -1) to arrive atthe variance.

    The variance of returns for Project A is

    2 (RA) = 0.2(- 5% - 9%)2 + 0.2(5% - 9%)2+ 0.2(10% - 9%)2+ 0.2(15% - 9%)2 +0.2(20% -9%)2 = 74

    The variance for Project B is2 (RB) = 0.2(35% - 14%)2 + 0.2(25% - 14%)2 + 0.2(15% - 14%)2+ 0.2(5% - 14%)2 +

    0.2(- 15% -14%)2 = 296

    Standard deviation

    It is the square root of variance.

    Standard deviation, () = (3)

    For Project A, the standard deviation is (RA) = = (74)1/2 = .086 = 8.6%

    For Project B, it is (RB) = = (296)1/2 = .172 = 17.2%

    Looking at the risk alone (either variance or standard deviation) Project A is better because it has lessrisk than Project B.

    Significance of standard deviation

    Tells which project is riskier and by how much

    Assists to predict the likelihood that earning is more or less than the desired rate

    Example

    Determine the probability that the rate of return from Project A will be zero or less.

    Steps

    Calculate the difference between zero and the mean of probability distribution of returns fromProject A

    Standardize this difference by dividing it by the standard deviation of the probabilitydistribution of possible returns.

    S = (4)

    3

  • 8/3/2019 Risk and Return 2009

    4/10

    Where, X is the outcome in which we are interested, E(R) is the mean of the probability distributionof return, and is the standard deviation. For Project A

    S = % = - 1.047

    This figure (-1.047) tells us that a zero expected rate of return lies 1.047 standard deviation to the leftof the mean of the probability distribution of possible rate of returns.

    To determine the probability that the expected rate of return will be zero or less, consult the normalprobability distribution table

    Going through the column representing number of standard deviations from mean (X) andinterpolating we find that there is a 0.1465 probability that an observation will be less than 1.047standard deviations from the mean of that distribution. Thus, there is 0.1465 probability that theexpected rate of return will be zero or less.

    Coefficient of variation

    Table 2: Return and Risk of Project A and Project B

    Project A Project B

    Expected return 9% 13%

    Variance 74 296

    Standard deviation 8.6% 17.2%

    Which Project will be chosen if both risk and return are considered simultaneously?

    To consider both return and risk we calculate the coefficient of variation, which is a relative measureof risk.

    Coefficient of variation relates risk to return and measures risk in terms of per unit of return.

    Coefficient of variation (CV) = (5)

    The coefficient of variation for Project A is 0.956 = (8.6%/ 9%), while for Project B, it is 1.1323 =(17.2%/ 13%).

    It indicates that the risk per unit of return is higher for Project B than for Project A.

    Note, investors would not solely base their decision even on coefficient of variation. They need toincorporate their preference towards risk in the final selection.

    The Expected Return on a Portfolio of Assets

    If we combine Project A and Project B, we call the combination a portfolio

    Formation of portfolio stabilizes the combined return, hence reduces the risk. The only conditionrequired is that the returns from the assets should not be perfectly positively correlated

    The effect of combining assets on the return of portfolio is illustrated in Figure 2.

    4

    Good Very bad Very good Bad Average

    - 20

    - 10

    0

    10

    20

    30

    40

    Project A

    Project A and B combined

    Project B

  • 8/3/2019 Risk and Return 2009

    5/10

    Figure 2: The Return from Project A, Project B and Combination of A and B

    The expected return for a portfolio is a weighted average of expected returns for securities makingup that portfolio,

    E(RP) = Rj wj (6)

    Where,E(Rp) = the expected return on the portfolio

    Rj = the expected return on the jth

    securitywj = the proportion of total funds invested in securityj N = total number of securities in the portfolio

    The expected rate of return on the portfolio consisting of equal investment in Project A and Project Bis

    E(Rp) = 0.5(9%) + (0.5)(13%) = 11%

    Figure 3: Rates of Return on a Two-asset Portfolio

    The expected return of a two-asset portfolio is a linear combination of the two assets expected return.

    The Variance and Standard Deviation of the Portfolio

    The variance of the portfolio is influenced by not only the variance of return of each asset but also by

    the covariance of the returns. The variance of a portfolio is calculated as(RP) = (7)

    where m is the total number of assets in the portfolio, wj is the proportion of the total funds investedin asset j, wk is the proportion invested in asset k, and jk is the covariance between possible returnsfor assets j and k.

    The simplified version of the general model for two-asset case is

    2(RP) = wA2 2(RA) + 2wAwB Cov(RA,RB) + wB

    2 2(RB) (8)

    5

    100% inProject A

    50% in ProjectA and B each

    100% inProject B

    E(R)

    13%

    11%

    9%

    B

    A

  • 8/3/2019 Risk and Return 2009

    6/10

    For three-asset case it is

    2(Rp) = w12 2(R1) + w2

    2 2(R2) + w32 2(R3) + 2w1w2 Cov(R1,R2) + 2w1w3 Cov(R1,R3) +2w2w3 Cov

    (R2,R3) (9)

    The variance of the return of portfolio, 2(Rp), consisting 50 percent investment in each project is

    2(Rp) = (0.5)2(74) + 2(0.5)(0.5) (-142) + (0.5)2 (296)

    = 21.5

    The standard deviation of the return of the portfolio is simply the under root of the variance of theportfolio.

    (Rp) = [2(Rp)]

    1/2 (10)

    The standard deviation of the portfolio consisting of 50 percent investment in each project is

    (Rp) = (21.5)1/2 = 4.64 percent

    Covariance and Correlation

    The covariance of the possible returns of two assets is a measure of the extent to which they are

    expected to vary together rather than independently of each other

    Cov(RA,RB) = Pi[RA E(RA)] [RB E(RB)] (11)

    The covariance between the return of Project A and the return of Project B is calculated below

    Table 3: Calculation of Covariance

    State of

    the

    economy

    Probability,

    Pi

    RA- E(RA) RB- E(RB)[RA-E(RA)][RB-

    E(RB)]Pi

    Very good 0.2 (-5 9) =-14

    (35 13) =22

    (-14)(22)(.2) =-61.60

    Good 0.2 (5 9) =-4

    (25 13) =12

    (-4)(12)(.2) = -48

    Average 0.2 (10 9) =1

    (15 13) = 2 (1)(2) (.2) = 2

    Bad 0.2 (15 9) =6

    (5 13) = -8 (6)(-8) (.2) = -48

    Very bad 0.2 (20 9) =11

    (-15 13) =-28

    (11)(-28)(.2) =-61.60

    Pi[RA E(RA)][RB E(RB)] = -142

    The negative covariance indicates that the return of two projects vary inversely, i. e. there is negativecorrelation between the returns of two projects.

    The relationship between covariance and correlation is as shown in Equation 12.

    Cov(RA, RB) = (RA,RB)(RA) (RB) (12)OR

    (RA, RB)= (13)The correlation coefficient between the return of Project A and Project B is - 0.96

    6

  • 8/3/2019 Risk and Return 2009

    7/10

    We can replace the covariance term, Cov(RA,RB), in Equation 8 with its equivalent, (RA,RB) ( RA)(RB), and rewrite the equation as

    2(Rp) = wA2 2(RA) + 2wAwB (RA,RB)( RA)(RB) + wB2 2(RB) (14)

    Equation 14 shows that the risk of the portfolio is influenced by

    the proportion (w) variance of each asset (2) included in the portfolio,

    the degree of relationship ( ) between the returns of assets included in the portfolio.

    Example: Mean return and standard deviation under different proportions and correlations

    In our earlier example, the expected return and standard deviation of Project A were 9 percent and8.6 percent respectively. Similarly, they were 13 percent and 17.2 percent respectively for ProjectB. The expected return and the standard deviation of the portfolios consisting various proportions

    of each asset under three different degree of relationship [ (AB) = +1, (AB) = 0, and (AB)= 1] are presented in Table 4.

    T A B L E 4

    Portfoli

    o

    Proportion

    in A,

    (wA)

    Proportion

    in B,

    (wB)

    (AB) = +1 (AB) = 0 (AB) = -1

    E(RP) RP E(RP) RP E(RP) RP

    1 (2) (3) (4) (5) (6) (7) (8) (9)

    M 125% - 25% 8% 6.6%4 8% 11.58% 8% 15.05%

    N 100 0 9 8.6 9 8.6 9 8.6

    O 75 25 10 10.75 10 7.75 10 2.15

    P 66.67 33.33 10.33 11.47 10.33 8.11 10.33 0Q 50 50 11 12.9 11 9.62 11 4.3

    R 25 75 12 15.05 12 13.08 12 10.75

    S 0 100 13 17.2 13 17.2 13 17.2

    T - 25 125 14 19.36 14 21.62 14 23.66

    Calculation of the expected return and standard deviation of a portfolio consisting of 75 percent of Aand 25 percent of B, with correlation coefficient 1, are

    E(Rp) = 0.75(9%) + (0.25) (13%) = 10%2(Rp) = (.75)2(74) + 2(.75) (.25) (-142) + (.25)2 (296) = 2.15%

    In two-assets case, the risk minimizing weights of assets in the portfolio are calculated as follows:wA =

    and wB = 1 - wA

    7

  • 8/3/2019 Risk and Return 2009

    8/10

    First, consider the expected returns

    The expected return for each portfolio is same irrespective of the value of the correlationcoefficient.

    They change with the change in proportion of assets in the portfolio.

    The expected return, E(Rp), and proportion, (w), is linear. It is evident from Figure 4.

    Case I:XY = 1 Case II:XY = 0 Case III:XY = - 1

    Figure 4: Expected Returns under Varying Degree of Correlation

    Next, consider the portfolio standard deviation

    When the correlation between assets is perfectly positive, (AB) = +1, the portfolio risk isthe weighted average of the risk of the assets in the portfolio, and the portfolios plot along astraight line (Figure 5, Case I).

    When the correlation between assets is perfectly negative, (AB) = -1, it is possible toeliminate all risk. (Figure 5, Case III)

    When the correlation coefficient is less than 1, it is possible to reduce the portfolio risk, but itwould not be eliminated, (Fig 5, Case II).

    When more than one asset is held in the portfolio, the lower the correlation between theassets, the lower the risk of the portfolio for any given set of asset weights

    When a portfolio contains only one asset (i. e. wx = 100 percent, or wy = 100 percent), the riskof the portfolio is the standard deviation of the return of the asset

    8

    A

    100% inProject A

    50% in Aand B each

    100% inproject B

    E(R)

    B

    A

    100% inProject A

    50% in Aand B each

    100% inproject B

    E(R)

    B

    A

    13%

    11%

    9%

    13%

    11%

    9%

    13%

    11%

    9%

  • 8/3/2019 Risk and Return 2009

    9/10

    Case I:XY = 1 Case II:XY = 0 Case III:XY = - 1

    Figure 5: Standard deviation under varying degree of correlation

    The Portfolio Opportunity Set and the Efficient Set

    When we plot the expected return and risk calculated for each portfolio under different degree ofrelationship in risk-return space, they appear as shown in Figure 6.

    Figure 6:The General Shape of the Portfolio Opportunity Set

    Figure 6 puts together the risk and returns of the portfolios under three states of relationship.

    The straight line connecting X and Y represents the upper and lower limits of risk for

    portfolios consisting of X and Y having highest degree of correlation, (XY) = +1

    The line XZY represents the risk for portfolios having lowest degree of correlation, (XY) =

    -1. In this state of relationship it is possible to eliminate all risk.

    These two states of relationship ( (XY) = +1 and (XY) = -1) limit the upper and lowerboundaries for investment opportunities

    Any relationship between these two extremes, such as curve XMY with (XY) = +0, will lie

    inside these boundaries

    The curved line will have the same general shape regardless of the number of assets under

    consideration since the correlation coefficients between the assets range between +1 and 1

    9

    Y

    XY

    = - 1

    XY

    = 1

    E(Rp)

    X

    Z

    (Rp)

    M

    100% in B

    E (R) %

    13%

    8.6 17.2

    100% inA

    100%in B

    Q

    E (R) %

    100% inA

    100%in B

    8.6 17.2

    Q

    12.9 9.62

    50% inA and B

    each

    50% inA and B

    each

    11%

    9%

    13%

    11%

    9%

    E (R) %

    100% in A

    Optimal P

    8.6 17.2

    A

    4.3

    50% in Aand B each

    13%

    11%

    9%

  • 8/3/2019 Risk and Return 2009

    10/10

    N-assets in the portfolio

    If we considern assets instead of two, the number of potential portfolios is innumerable. If potential

    portfolios are plotted in risk-return space, it appears as shown in Fig. 7.

    Figure 7: The Opportunity Set and the Efficient Frontier

    Figure 7 shows risk and return relationship for portfolios that can be formed from n assets

    Each point in the curve and dots inside the curve represents possible combination of assets

    (portfolios) that are available for investment. These possible portfolios are called attainable sets

    An efficient set is one that has the highest return for a given level of risk or lowest risk for given

    level of return. Therefore, a rational investor always chooses portfolios from the efficient sets.

    The efficient frontier represents the locus of all portfolios that has the highest return for a given levelof risk.

    10

    D

    E(Rp)

    A (R

    p)

    Z

    Y

    X

    P

    O

    BW

    C